Final Cost Reports Due in June

Final Cost Reports Due No Later than June 30, 201

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/18/12 at 10:55:16




COBLESKILL CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-04-01-06
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GILBOA CONESVILLE CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-08-01-04
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




JEFFERSON CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-09-01-04
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MIDDLEBURGH CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-10-01-04
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




RICHMONDVILLE CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-11-01-04
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




COBLESKILL-RICHMONDVILLE CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-11-02-06
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SCHOHARIE CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-12-01-04
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SHARON SPRINGS CSD FINAL COST REPORTS DUE JUNE 30, 2012 FOR CAPITAL PROJECTS
District No.: 54-14-01-04
last updated on 07/18/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO FCRs DUE THIS JUNE                     /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition