REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-1372 Reconstruction 0-003-010 12/01/10 2,4,8,9,10,155,15,16 0 85,625 / / / / / / / / DDJ
08-1338 Reconstruction 0-010-010 05/11/09 2,7,8 0 285,199 / / / / / / / / MGL
07-1701 Reconstruction 0-010-011 03/24/08 2,10,16 0 968,561 / / / / / / / / MGL
08-0882 Reconstruction 0-010-012 03/30/09 2,4,8,9,155,15,16 0 65,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
00-1456 Reconstruction 0-020-014 08/27/01 7 0 170,000 / / / / / / / / BJB
03-0102 Reconstruction 0-020-016 10/06/03 13 0 466,000 / / / / / / / / MGL
03-0103 Reconstruction 0-020-017 09/25/03 13 0 275,000 / / / / / / / / MGL
06-0353 Reconstruction 0-020-020 10/23/06 4,13 0 110,000 / / / / / / / / JOD
06-0354 Reconstruction 0-020-022 10/23/06 2,4,8,9,10,155,15,16 0 11,253,303 / / / / / / / / JOD
08-1497 Reconstruction 0-020-023 04/07/09 2,4,10 0 40,000 / / / / / / / / JOD
10-0041 Reconstruction 0-020-024 07/27/10 9,10 0 208,185 / / / / / / / / JOD
06-0566 Reconstruction 0-045-002 11/30/06 16 0 3,287 / / / / / / / / JOD
06-0567 Reconstruction 0-046-002 11/30/06 16 0 4,157 / / / / / / / / JOD
06-0569 Reconstruction 8-055-002 11/30/06 16 0 2,190 / / / / / / / / JOD
06-0570 Reconstruction 8-056-002 11/30/06 16 0 2,190 / / / / / / / / JOD
01-1504 Reconstruction 8-072-L01 07/17/02 0 685,652 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
02-2138 Reconstruction 0-001-025 05/18/04 16 0 151,356 / / / / / / / / DDJ
02-2139 Reconstruction 0-002-023 05/18/04 16 0 156,481 / / / / / / / / DDJ
98-0798 Reconstruction 0-004-018 05/07/99 2,7,8,9,155,15,16 0 609,500 / / / / / / / / MGL
00-1826 Reconstruction 0-004-030 07/30/01 14,16 0 50,869 / / / / / / / / MGL
02-2140 Reconstruction 0-004-032 05/18/04 16 0 485,610 / / / / / / / / DDJ
02-2141 Reconstruction 0-006-024 05/18/04 16 0 189,728 / / / / / / / / DDJ
98-1606 Reconstruction 0-007-022 07/21/99 2,16 0 376,423 / / / / / / / / MGL
02-2142 Reconstruction 0-007-034 05/18/04 16 0 438,109 / / / / / / / / DDJ
02-2143 Reconstruction 0-009-027 05/18/04 16 0 284,460 / / / / / / / / DDJ
02-2144 Reconstruction 0-011-020 05/18/04 16 0 214,045 / / / / / / / / DDJ
02-2145 Reconstruction 0-012-022 05/18/04 16 0 243,324 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
07-0299 Reconstruction 0-001-019 12/10/07 8,16 0 21,830 / / / / / / / / HCM
07-0300 Reconstruction 0-002-013 12/10/07 8,16 0 123,434 / / / / / / / / HCM
07-0301 Reconstruction 0-003-022 12/10/07 8,16 0 13,334 / / / / / / / / HCM
07-0302 Reconstruction 0-004-018 12/10/07 8,16 0 12,626 / / / / / / / / HCM
02-2182 Reconstruction 0-005-020 05/28/03 7 0 250,000 / / / / / / 07/26/04 HCM
07-0303 Reconstruction 0-005-024 12/10/07 8,16 0 39,530 / / / / / / / / HCM
08-0896 Reconstruction 0-005-027 03/31/09 16 0 250,000 / / / / / / / / HCM
01-0650 Reconstruction 0-006-012 07/22/02 2 0 202,895 / / / / / / 02/04/04 MGL
01-1120 Reconstruction 0-006-015 08/26/02 9,13,16 0 202,895 / / / / / / / / MGL
07-0304 Reconstruction 0-006-020 12/10/07 8,16 0 23,246 / / / / / / / / HCM
04-1379 New Construction 7-016-001 04/24/07 02 - 16 0 91,000 / / / / / / 07/07/07 HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
08-0315 Additions and Alterations 0-014-013 02/25/09 02 - 16 0 2,000,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
06-0338 Reconstruction 0-001-017 01/25/07 2,8,9,10,16 0 203,000 / / / / / / / / JOD
00-0832 New Construction 7-010-001 02/16/01 02 - 16 0 41,040 / / / / / / / / BJB
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
03-0411 Reconstruction 0-005-010 10/14/03 155 0 73,000 / / / / / / / / RDR
02-0912 Reconstruction 0-006-011 07/31/02 2 0 192,840 / / / / / / 09/05/02 MGL
- New Construction 7-034-001 12/30/10 02 - 16 0 0 / / / / / / / / HCM
04-0093 Reconstruction 7-999-002 08/11/02 2,4,8,9,155,15,16 0 987,202 / / / / / / / / RDR
04-0738 Reconstruction 7-999-003 08/11/02 4,9 0 723,662 / / / / / / / / MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-0524 Reconstruction 0-010-021 02/26/10 2,9,15 0 75,000 / / / / / / / / HCM
09-0577 New Construction 7-022-001 11/23/10 02 - 16 0 3,000 / / / / / / / / HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
01-0180 New Construction 7-032-001 06/04/03 02 - 16 0 50,000 / / / / / / 10/15/04 MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
05-0149 Reconstruction 0-001-010 12/07/05 10,15,16 0 50,000 / / / / / / / / DDJ
04-1308 Reconstruction 0-001-011 12/23/05 155,15,16 0 404,560 / / / / / / / / DDJ
07-2227 Reconstruction 0-001-016 09/05/08 2,9,155,15,16 0 100,000 / / / / / / / / DDJ
04-1309 Reconstruction 0-002-012 12/23/05 155,15,16 0 1,053,935 / / / / / / / / DDJ
04-1310 Reconstruction 0-003-008 12/22/05 155,15,16 0 637,060 / / / / / / / / DDJ
04-1311 Reconstruction 0-004-007 12/23/05 155,15,16 0 355,975 / / / / / / / / DDJ
04-1418 Reconstruction 7-999-003 08/12/05 16 0 100,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
01-1132 Reconstruction 0-001-017 06/28/02 8,10 0 16,200 / / / / / / 09/01/02 MGL
01-1133 Reconstruction 0-002-011 06/28/02 8,10 0 16,200 / / / / / / 09/01/02 MGL
01-1134 Reconstruction 0-003-013 06/28/02 8,10 0 16,200 / / / / / / 09/01/02 MGL
06-0098 Reconstruction 0-003-015 10/06/06 155 0 28,500 / / / / / / 12/15/06 JOD
01-1135 Reconstruction 0-004-009 06/28/02 8,10 0 16,200 / / / / / / 09/01/02 MGL
06-0099 Reconstruction 0-004-010 10/06/06 155 0 28,500 / / / / / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
00-1299 Additions and Alterations 0-002-009 06/28/01 02 - 16 0 225,970 / / / / / / / / RDR
03-0165 Reconstruction 0-006-010 08/11/03 2 0 0 / / / / / / / / RDR
04-1032 Reconstruction 0-006-018 05/23/05 15,16 0 397,285 / / / / / / / / RDR
00-1890 Reconstruction 0-007-004 04/12/02 8,155,15,16 0 143,130 / / / / / / / / RDR
04-1314 Reconstruction 0-007-005 07/27/05 15 0 7,665 / / / / / / / / RDR
06-1536SR Additions and Alterations 0-008-010 06/28/07 02 - 16 0 0 / / / / / / / / MGL
00-1984 New Construction 0-020-001 12/14/01 02 - 16 0 260,000 / / / / / / / / RDR
00-1985 New Construction 0-021-001 12/14/01 02 - 16 0 260,000 / / / / / / / / RDR
00-1986 New Construction 0-022-001 12/14/01 02 - 16 0 450,000 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
03-0750 Reconstruction 0-001-024 12/21/04 155,15,16 0 137,780 / / / / / / 03/15/06 HCM
08-1631 Reconstruction 0-002-027 08/21/09 2,4,7,155,15,16 0 2,194,196 / / / / / / / / HCM
09-0120 Reconstruction 0-004-026 12/08/09 2,4,7,155,15,16 0 1,781,124 / / / / / / / / HCM
09-0126 Reconstruction 0-007-038 12/10/09 8,9,10,155,15,16 0 1,114,163 / / / / / / / / HCM
08-1409 Reconstruction 0-008-037 05/22/09 2,4,8,9,10,155,15,16 0 5,605,200 / / / / / / / / HCM
09-0127 Reconstruction 0-008-038 12/10/09 8,9,10,155,15,16 0 1,413,190 / / / / / / / / HCM
99-0599 Reconstruction 7-999-003 12/23/99 16 0 1,220,700 / / / / / / / / MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-0033 Reconstruction 0-003-015 07/23/09 155,15,16 0 97,500 / / / / / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
99-1679 Reconstruction 0-001-003 07/10/01 155,16 0 93,868 / / / / / / 08/31/01 RDR
05-1185 Reconstruction 0-001-004 06/23/06 7 0 50,000 / / / / / / / / MGL
99-1678 Reconstruction 0-003-003 07/10/01 155,16 0 72,834 / / / / / / 08/31/01 RDR
98-0890 Reconstruction 0-004-002 04/12/99 2,9,155 0 620,845 / / / / / / / / RDR
03-0209 Reconstruction 0-004-007 02/19/04 2,15 0 200,000 / / / / / / 02/23/05 RDR
98-0889 Reconstruction 0-005-003 04/12/99 2,9,10,15,16 0 1,689,000 / / / / / / / / RDR
03-0210 Reconstruction 0-005-008 02/19/04 2,15 0 200,000 / / / / / / / / RDR
09-0889 Reconstruction 0-005-010 06/18/10 4,9,16 0 32,500 / / / / / / / / JOD
98-0891 Reconstruction 0-006-008 04/12/99 4,7 0 855,150 / / / / / / / / RDR
99-1681 Reconstruction 0-006-010 07/10/01 155,16 0 217,709 / / / / / / 08/31/01 RDR
05-0487 Reconstruction 0-006-012 05/18/06 8,9,13,15,16 0 250,000 / / / / / / / / RDR
05-1186 Reconstruction 0-006-013 06/23/06 7 0 523,000 / / / / / / / / MGL
09-1205SR Additions and Alterations 0-006-016 05/13/10 02 - 16 0 0 / / / / / / / / JOD
05-0488 Reconstruction 0-007-012 05/18/06 8,9,13,15,16 0 250,000 / / / / / / / / RDR
05-1187 Reconstruction 0-018-005 06/23/06 7 0 860,000 / / / / / / / / MGL
98-1502 Reconstruction 5-009-003 08/05/99 2,14,155 0 86,000 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
02-0127 Reconstruction 0-001-018 12/02/02 7,9 0 157,500 / / / / / / / / MAC
02-2130 Reconstruction 0-001-020 09/08/03 2,155 0 116,487 / / / / / / / / RDR
04-1159 Reconstruction 0-001-023 05/17/05 7 0 47,200 / / / / / / 01/15/07 DDJ
09-1517 Reconstruction 0-002-006 06/22/10 2,8 0 100,000 / / / / / / / / DDJ
02-2131 Reconstruction 0-003-011 06/04/03 7 0 95,001 / / / / / / / / RDR
00-0516 Reconstruction 7-999-001 03/02/01 16 0 2,639,326 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
02-0533 New Construction 7-021-001 01/30/03 02 - 16 0 342,000 / / / / / / 10/14/03 DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
00-1816 Reconstruction 0-001-013 06/04/01 7 0 138,183 / / / / / / / / MGL
02-1115 Reconstruction 0-001-014 01/31/03 4 0 50,000 / / / / / / / / MGL
02-1116 Reconstruction 0-002-014 01/31/03 4,8 0 30,000 / / / / / / / / MGL
01-0287 Reconstruction 0-004-015 09/26/01 155,15,16 0 90,000 / / / / / / / / MGL
99-1754 Reconstruction 0-005-013 08/17/00 8,9,155,16 0 81,000 / / / / / / / / MGL
99-1311 Reconstruction 0-005-015 05/09/00 9,10 0 14,825 / / / / / / / / MGL
00-0187 Reconstruction 0-005-016 10/04/00 9,10 0 66,850 / / / / / / / / MGL
01-1377 Reconstruction 0-005-017 10/16/02 9,16 0 109,522 / / / / / / / / MGL
06-1359 Reconstruction 0-005-023 03/12/08 9,10,155,15,16 0 877,940 / / / / / / / / JOD
08-1575 Reconstruction 0-007-017 05/13/09 8,9 0 28,310 / / / / / / 09/24/09 JOD
01-1400 Reconstruction 0-008-010 01/08/03 155,15,16 0 1,661,280 / / / / / / / / MGL
02-0716 Additions and Alterations 0-008-011 01/31/03 02 - 16 0 926,367 / / / / / / / / JOD
02-0046 New Construction 0-026-001 08/28/03 02 - 16 0 150,000 / / / / / / / / MGL
01-0253 New Construction 7-028-001 11/01/02 02 - 16 0 34,500 / / / / / / / / MGL
09-0348 Reconstruction 7-999-004 01/15/10 16 0 826,900 / / / / / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
05-1215 Reconstruction 0-001-022 11/16/06 16 0 130,699 / / / / / / / / HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
98-0477 Reconstruction 0-005-007 01/27/99 4 0 10,800 / / / / / / / / MEM
00-1874 New Construction 0-014-001 06/11/01 02 - 16 0 46,980 / / / / / / / / MAC
04-0260 New Construction 0-017-001 02/15/05 02 - 16 0 50,000 / / / / / / 02/27/08 MAC
06-1623 New Construction 7-018-001 09/17/07 02 - 16 0 80,000 / / / / / / / / MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
05-0230 Reconstruction 0-004-FP2 10/14/05 16 0 3,995 / / / / / / 08/31/05 JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-0001 Reconstruction 0-003-024 11/02/09 10 0 250,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
08-1272 Reconstruction 0-004-031 06/16/09 2,8,9 0 120,000 / / / / / / / / JOD
00-0517 Reconstruction 0-008-001 01/19/01 155 0 12,000 / / / / / / / / MGL
98-1688 Reconstruction 7-008-006 10/15/99 10,15 0 23,500 / / / / / / / / MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
98-1365 Reconstruction 0-005-016 05/13/99 4 0 241,905 / / / / / / / / MEM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
07-0061 Reconstruction 0-001-016 08/10/07 8 0 57,790 / / / / / / / / HCM
07-0062 Reconstruction 0-002-015 08/10/07 8 0 38,375 / / / / / / / / HCM
07-0063 Reconstruction 0-004-014 08/10/07 8 0 19,845 / / / / / / / / HCM
09-1395 Reconstruction 0-004-018 07/15/10 2,8 0 138,591 / / / / / / / / HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
03-1540 Reconstruction 0-001-007 05/28/04 2 0 278,500 / / / / / / / / MAC
00-1991 Reconstruction 0-002-006 08/03/01 2 0 37,000 / / / / / / 09/03/01 MAC
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
03-1555 New Construction 7-038-001 07/01/04 02 - 16 0 33,000 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-1508 Reconstruction 0-001-028 11/12/10 2,16 0 249,000 / / / / / / / / HCM
09-1509 Reconstruction 0-003-035 11/12/10 9,16 0 249,000 / / / / / / / / HCM
09-1510 Reconstruction 0-004-045 11/12/10 2,16 0 275,000 / / / / / / / / HCM
98-1255 Reconstruction 0-005-029 06/09/99 2,14 0 450,000 / / / / / / 06/07/00 RDR
09-1511 Reconstruction 0-005-044 11/12/10 2,16 0 777,000 / / / / / / / / HCM
09-1512 Reconstruction 0-006-021 11/12/10 16 0 249,000 / / / / / / / / HCM
09-1513 Reconstruction 0-007-034 11/12/10 16 0 275,000 / / / / / / / / HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
00-0482 Reconstruction 0-001-025 03/09/01 16 0 30,000 / / / / / / 10/31/01 RDR
10-0369 Reconstruction 0-001-036 12/01/10 2,4,7,155,15,16 0 2,852,400 / / / / / / / / DDJ
09-0048 Reconstruction 0-003-019 04/16/10 4,155,15,16 0 914,000 / / / / / / / / DDJ
09-0669 Additions and Alterations 0-003-020 07/09/10 02 - 16 0 1,246,182 / / / / / / / / DDJ
09-0049 Reconstruction 0-004-021 04/16/10 2,4,7,8,14,155,15,16 0 3,467,200 / / / / / / / / DDJ
99-1470 Reconstruction 0-005-020 06/19/00 10 0 28,000 / / / / / / / / RDR
08-1551 Reconstruction 0-005-024 06/09/09 4 0 8,223,825 / / / / / / / / DDJ
08-1466 Reconstruction 0-005-025 12/12/07 7,8,9,155,15,16 0 5,349,175 / / / / / / / / DDJ
09-0050 Reconstruction 0-005-026 04/16/10 155,15,16 0 313,000 / / / / / / / / DDJ
09-0670 Additions and Alterations 0-005-027 07/09/10 02 - 16 0 3,662,542 / / / / / / / / DDJ
09-0671 Reconstruction 0-005-028 01/29/10 2,4,7,8,9,155,15,16 0 900,000 / / / / / / / / DDJ
01-0116 Reconstruction 0-011-030 03/19/02 155 0 1,671,053 / / / / / / 05/08/03 RDR
05-1196 Reconstruction 0-011-033 06/19/07 2,10,16 0 110,000 / / / / / / / / MGL
06-0941 Reconstruction 0-011-034 05/16/07 16 0 355,000 / / / / / / / / MGL
09-1506 Reconstruction 0-011-042 09/15/10 10,15,16 0 550,000 / / / / / / / / DDJ
03-0166 Reconstruction 5-013-002 08/20/03 2 0 690,990 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
07-2275 Reconstruction 0-007-022 12/23/08 155,15,16 0 130,000 / / / / / / / / MGL
05-1102 New Construction 0-020-001 11/02/06 02 - 16 0 500,000 / / / / / / / / RDR
08-1675 New Construction 7-030-001 07/08/09 02 - 16 0 120,000 / / / / / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
00-1869 Additions and Alterations 0-001-016 06/14/01 02 - 16 0 6,435,997 / / / / / / 09/26/02 BJB
08-0570 Reconstruction 0-001-020 03/20/09 4,9,10,155,16 0 364,371 / / / / / / 12/08/09 HCM
09-1384 Reconstruction 0-001-023 06/02/10 2,16 0 210,000 / / / / / / / / HCM
08-0571 Reconstruction 0-002-018 03/20/09 2,4,10,16 0 130,200 / / / / / / / / HCM
09-1385 Reconstruction 0-002-020 06/02/10 2 0 230,000 / / / / / / / / HCM
00-1871 Additions and Alterations 0-003-011 06/14/01 02 - 16 0 6,513,589 / / / / / / 12/05/02 BJB
08-0572 Reconstruction 0-003-014 03/20/09 10,155,16 0 98,599 / / / / / / / / HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
06-1635 Reconstruction 0-002-027 06/19/07 2 0 750,000 / / / / / / 10/22/07 DDJ
03-1090 Reconstruction 0-006-017 03/24/04 7 0 298,820 / / / / / / / / MAC
08-0595 Reconstruction 0-006-026 01/07/09 2,9,10,16 0 1,811,149 / / / / / / / / DDJ
08-0144 Reconstruction 7-005-004 08/21/08 2,15 0 50,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
05-1272 Reconstruction 0-001-022 05/30/06 2 0 650,000 / / / / / / 06/20/06 HCM
08-0052 Reconstruction 0-001-026 12/22/08 2,10 0 1,175,753 / / / / / / / / HCM
99-1216 Reconstruction 0-005-019 04/29/00 7 0 46,000 / / / / / / / / MGL
98-0457 Reconstruction 0-006-021 01/26/99 16 0 247,310 / / / / / / / / RDR
99-1641 Reconstruction 0-006-024 06/12/00 2,8,9 0 23,000 / / / / / / / / MGL
00-0002 Reconstruction 0-006-025 07/27/00 8,9,15,16 0 68,400 / / / / / / / / MAC
99-1219 Reconstruction 0-010-020 04/29/00 9 0 72,300 / / / / / / / / MGL
00-1504 New Construction 0-041-001 05/07/01 02 - 16 0 375,000 / / / / / / 10/28/01 MGL
99-1180 Reconstruction 7-999-002 04/27/00 16 0 132,000 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
06-1304 Reconstruction 0-002-021 05/10/07 10,15 0 50,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
01-1098 Reconstruction 0-001-008 05/17/02 155,16 0 52,155 / / / / / / / / MAC
98-0846 Reconstruction 0-001-009 04/30/99 155 0 187,440 / / / / / / / / LSS
98-1282 Reconstruction 0-001-010 06/25/99 4 0 78,919 / / / / / / 12/01/99 LSS
98-1721 Reconstruction 0-001-011 03/13/00 8 0 27,944 / / / / / / / / LSS
98-1593 Reconstruction 0-001-012 09/27/99 15 0 196,170 / / / / / / / / LSS
00-1618 Reconstruction 0-001-014 05/11/01 16 0 209,333 / / / / / / / / MAC
01-1099 Reconstruction 0-004-016 05/17/02 155 0 421,909 / / / / / / / / MAC
98-0845 Reconstruction 0-004-017 04/30/99 155 0 186,375 / / / / / / / / LSS
98-1283 Reconstruction 0-004-018 06/25/99 4 0 153,359 / / / / / / / / LSS
98-1302 Reconstruction 0-004-019 07/08/99 8,9,10 0 425,599 / / / / / / / / LSS
99-1199 Reconstruction 0-004-020 05/05/00 8,9,15,16 0 60,225 / / / / / / / / RDR
98-1720 Reconstruction 0-004-021 03/13/00 8 0 97,805 / / / / / / / / LSS
98-1594 Reconstruction 0-004-022 09/27/99 15 0 700,499 / / / / / / / / LSS
00-0467 Reconstruction 0-004-025 01/10/01 16 0 250,000 / / / / / / / / MAC
00-1619 Reconstruction 0-004-026 05/11/01 16 0 329,100 / / / / / / / / MAC
04-1270 Reconstruction 0-004-027 09/02/05 2,16 0 300,000 / / / / / / / / RDR
09-0821 Additions and Alterations 0-004-037 05/11/10 02 - 16 0 3,295,386 / / / / / / / / JOD
01-1100 Reconstruction 0-005-009 05/17/02 155,16 0 59,950 / / / / / / / / MAC
98-0847 Reconstruction 0-005-011 04/30/99 155 0 254,535 / / / / / / / / LSS
98-1284 Reconstruction 0-005-012 06/25/99 4 0 57,122 / / / / / / / / LSS
98-1719 Reconstruction 0-005-013 03/13/00 8 0 121,926 / / / / / / / / LSS
99-1197 Reconstruction 0-005-014 05/04/00 2 0 91,542 / / / / / / / / LSS
07-1375 New Construction 7-029-001 02/05/08 02 - 16 0 200,000 / / / / / / 09/09/09 MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
01-0293 Reconstruction 0-012-010 03/09/04 16 0 275,000 / / / / / / / / MGL
00-1376 Reconstruction 0-014-010 06/22/01 2 0 15,000 / / / / / / / / MGL
03-1327 Reconstruction 0-015-015 08/09/04 8,9,10,13,155,15,16 0 175,000 / / / / / / / / HCM
98-0377 Reconstruction 0-017-007 02/01/99 7,9,15,16 0 149,000 / / / / / / / / RDR
01-0122 Reconstruction 0-018-012 08/22/01 2,16 0 480,000 / / / / / / / / MGL
01-0294 Reconstruction 0-019-016 03/09/04 16 0 410,000 / / / / / / / / MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-1039 Reconstruction 0-002-019 07/19/10 13,16 0 41,667 / / / / / / / / DDJ
09-1040 Reconstruction 0-003-017 07/19/10 10,16 0 41,666 / / / / / / / / DDJ
09-1041 Reconstruction 0-005-021 07/19/10 10,16 0 41,666 / / / / / / / / DDJ
00-1307 Reconstruction 0-008-025 06/06/01 4,8,9,155,15,16 0 147,960 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
01-0835 Reconstruction 0-004-012 03/27/02 16 0 60,000 / / / / / / 08/11/05 MGL
04-0084 Reconstruction 0-004-014 08/24/04 7 0 65,000 / / / / / / 08/11/05 HCM
07-2340 Reconstruction 7-999-001 10/03/08 10,13,16 0 143,000 / / / / / / / / HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
04-1234SR Additions and Alterations 0-003-014 05/17/05 02 - 16 0 0 / / / / / / 02/03/06 DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
99-1284 New Construction 0-025-001 03/30/00 02 - 16 0 500,000 / / / / / / / / RDR
07-0427 New Construction 0-038-001 03/03/08 02 - 16 0 200,000 / / / / / / / / MGL
09-0598 Reconstruction 5-040-002 03/08/10 2,10,15 0 35,000 / / / / / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
04-1143 Reconstruction 0-002-006 07/15/05 10,155 0 60,382 / / / / / / / / MGL
06-0977 Reconstruction 0-004-017 07/10/07 8 0 20,000 / / / / / / / / HCM
06-0978 Reconstruction 0-005-016 07/10/07 7 0 70,000 / / / / / / / / HCM
00-0796 Reconstruction 0-006-014 03/08/01 155 0 43,200 / / / / / / 09/01/01 MGL
02-1126 Additions and Alterations 0-010-026 09/11/03 02 - 16 0 5,616,265 / / / / / / / / MGL
06-0980 Reconstruction 0-010-033 07/11/07 2,155,15,16 0 227,000 / / / / / / / / HCM
06-0981 Reconstruction 0-012-020 07/11/07 4,7,9,10,155,15,16 0 210,000 / / / / / / / / HCM
03-1410 Additions and Alterations 0-013-014 07/01/04 02 - 16 0 767,782 / / / / / / / / HCM
03-0567 New Construction 0-040-001 02/20/04 02 - 16 0 32,400 / / / / / / 11/01/04 HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
98-0662 Reconstruction 0-002-007 02/22/99 14 0 162,000 / / / / / / / / RDR
07-1811 Reconstruction 0-002-011 02/19/09 2,15,16 0 310,673 / / / / / / / / MGL
09-1022 Reconstruction 0-002-013 07/30/10 2,8,9,155,15,16 0 891,770 / / / / / / / / JOD
07-1812 Reconstruction 0-003-014 02/19/09 2,16 0 242,098 / / / / / / / / MGL
07-1813 Reconstruction 0-009-009 02/19/09 2,8,16 0 178,950 / / / / / / / / MGL
09-1232 Reconstruction 0-009-010 05/20/10 2,9 0 110,588 / / / / / / / / JOD
07-1814 Reconstruction 0-010-011 02/19/09 2,16 0 157,438 / / / / / / / / MGL
09-0165 Reconstruction 0-010-012 10/07/09 2 0 179,866 / / / / / / / / JOD
09-1231 Reconstruction 0-010-013 05/20/10 9 0 224,911 / / / / / / / / JOD
99-0367 Reconstruction 0-012-018 01/28/00 155 0 150,000 / / / / / / 03/20/01 RDR
99-0655 Reconstruction 0-012-019 03/14/00 8 0 720,000 / / / / / / / / RDR
07-1679 Reconstruction 0-012-022 06/11/08 2,9,10,155,15,16 0 432,500 / / / / / / / / MGL
07-1815 Reconstruction 0-012-027 02/19/09 2,8,16 0 2,797,925 / / / / / / / / MGL
09-1103 Reconstruction 0-012-030 09/30/10 2,7,8,9,155,15,16 0 577,348 / / / / / / / / JOD
07-1817 Reconstruction 5-004-006 02/19/09 2,16 0 45,093 / / / / / / / / MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-1150 Reconstruction 0-012-029 07/06/10 2,4,7,8,9,10,14,155, 0 165,000 / / / / / / / / JOD
09-1151 Reconstruction 0-014-028 07/06/10 2,4,7,8,9,10,14,155, 0 165,000 / / / / / / / / JOD
09-1152 Reconstruction 0-015-040 07/06/10 2,4,7,8,9,10,14,155, 0 115,000 / / / / / / / / JOD
99-1291 Additions and Alterations 0-020-005 05/05/00 02 - 16 0 470,339 / / / / / / / / MGL
02-0098 New Construction 7-027-001 08/06/02 02 - 16 0 150,000 / / / / / / 04/14/03 MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
98-0573 Reconstruction 0-001-019 02/08/99 9,155,15,16 0 60,000 / / / / / / / / BJB
98-1090 Reconstruction 0-001-020 04/08/99 155,15 0 113,000 / / / / / / / / BJB
98-1681 Reconstruction 7-009-004 05/30/00 2,9,13 0 75,000 / / / / / / / / BJB
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
09-1282 Reconstruction 0-001-012 05/12/10 2,7 0 1,500,000 / / / / / / / / JOD
00-0113 Reconstruction 0-003-027 10/10/00 2,8,15,16 0 140,000 / / / / / / 05/14/01 MGL
00-1167 Reconstruction 0-003-030 04/05/01 2 0 70,000 / / / / / / / / MGL
04-0995 Reconstruction 0-003-031 04/04/05 8,9,10,155,16 0 50,000 / / / / / / / / JOD
02-0130 New Construction 0-020-001 08/20/02 02 - 16 0 150,000 / / / / / / 10/15/02 JOD
02-0131 New Construction 0-021-001 08/20/02 02 - 16 0 150,000 / / / / / / 10/15/02 JOD
99-1543 New Construction 7-018-001 03/27/00 02 - 16 0 20,000 / / / / / / 04/27/01 MGL
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
08-0917 Reconstruction 0-003-018 03/11/09 4,8 0 27,288 / / / / / / / / DDJ
08-0919 Reconstruction 0-005-019 03/11/09 4,8 0 59,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
01-1501 Reconstruction 5-023-L01 06/27/02 0 117,000 / / / / / / / / RDR
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
- NO LATE or OVERDUE FCRs / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
99-0155 Reconstruction 0-001-015 11/05/99 2,9,155,16 0 32,400 / / / / / / / / MGL
02-0251 Reconstruction 0-003-017 01/07/03 2,155,16 0 887,570 / / / / / / / / MGL
03-1568 Reconstruction 0-003-019 07/08/04 9,16 0 100,000 / / / / / / / / DDJ
06-0709 Reconstruction 0-003-023 03/07/07 155 0 972,300 / / / / / / / / DDJ
02-0088 Reconstruction 0-006-013 01/31/03 155,16 0 432,370 / / / / / / / / MGL
00-0278 Additions and Alterations 0-006-014 01/04/01 02 - 16 0 4,635,870 / / / / / / 08/15/01 MGL
03-1569 Reconstruction 0-006-018 07/08/04 9,16 0 100,000 / / / / / / / / DDJ
98-0672 Reconstruction 0-007-019 03/05/99 2,7,155 0 1,025,000 / / / / / / / / MGL
00-0235 Reconstruction 0-007-022 09/13/00 2,16 0 130,000 / / / / / / 03/25/03 MGL
08-1413 Reconstruction 0-007-039 04/02/09 8 0 800,000 / / / / / / 08/22/09 DDJ
09-1197 Reconstruction 0-007-040 05/26/10 8 0 4,582,200 / / / / / / / / DDJ
98-0673 Reconstruction 0-009-015 03/05/99 2,8,155,16 0 300,000 / / / / / / / / MGL
03-1570 Reconstruction 0-009-021 07/08/04 155 0 125,000 / / / / / / / / DDJ
03-1571 Reconstruction 7-999-009 07/08/04 16 0 150,000 / / / / / / / / DDJ
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
98-1058 Reconstruction 0-001-014 04/08/99 16 0 68,200 / / / / / / / / BJB
98-1059 Reconstruction 0-006-011 04/08/99 16 0 53,500 / / / / / / / / BJB
98-1060 Reconstruction 0-007-018 04/08/99 16 0 81,150 / / / / / / / / BJB
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
06-1147 Reconstruction 0-013-002 04/11/07 7 0 39,303 / / / / / / / / JOD
07-0085 Reconstruction 0-017-016 08/27/07 8 0 3,402,228 / / / / / / / / JOD
99-1736 New Construction 0-030-017 06/21/00 02 - 16 0 0 / / / / / / / / MGL
07-1980 Reconstruction 0-057-002 05/20/08 16 0 20,000 / / / / / / 03/12/09 JOD
02-1754 Reconstruction 0-131-002 04/03/02 2,4,7,8,9,155,15,16 0 0 / / / / / / 09/03/03 MAC
03-0241 New Construction 0-139-001 02/24/04 02 - 16 0 1,062,700 / / / / / / / / MAC
06-1089 Reconstruction 5-040-003 03/16/07 7 0 72,000 / / / / / / / / JOD
10-0081 Reconstruction 5-040-004 12/08/10 16 0 79,430 / / / / / / / / JOD
02-2377 Reconstruction 8-083-004 06/25/03 8 0 739,000 / / / / / / / / MAC
03-1284 Reconstruction 8-083-006 04/19/04 4,7,8 0 306,650 / / / / / / 09/03/04 MAC
- Reconstruction 8-095-002 06/07/07 2,15 0 20,000 / / / / / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition