ADDISON CENTRAL SCHOOL: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-01-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
04-0166    Reconstruction               0-006-008  05/05/05   16                             0       90,000     /  /                /  /       /  /      02/07/07  JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




AVOCA CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-02-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
99-1381    Reconstruction               5-011-005  10/15/00   2,7,155,16                     0      444,000     /  /                /  /       /  /        /  /    MEM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SAVONA CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-03-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BATH CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-03-02-06
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
08-1469    Reconstruction               5-009-002  12/23/09   2,7,155,16                     0       36,464     /  /                /  /       /  /        /  /    HCM
99-0196    New Construction             7-018-001  11/09/99   02 - 16                        0            0     /  /                /  /       /  /        /  /    MGL
02-0051    New Construction             7-019-001  11/07/02   02 - 16                        0       85,000     /  /                /  /       /  /      07/28/05  MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BRADFORD CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-04-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CAMPBELL CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-06-02-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CAMPBELL-SAVONA CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-06-03-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
00-1520    New Construction             7-007-001  11/07/01   02 - 16                        0       25,000     /  /                /  /       /  /      08/28/03  BJB
03-1051    New Construction             7-009-001  09/17/04   02 - 16                        0      130,000     /  /                /  /       /  /      12/22/05  DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CANISTEO CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-07-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
00-1181    Reconstruction               0-003-001  11/21/01   2                              0        2,000     /  /                /  /       /  /      09/01/03  MGL
99-1347    New Construction             7-015-001  06/29/00   02 - 16                        0       27,147     /  /                /  /       /  /      01/11/02  MGL
00-1183    New Construction             7-016-001  11/21/01   02 - 16                        0       10,000     /  /                /  /       /  /      09/01/03  MGL
00-1184    New Construction             7-017-001  11/21/01   02 - 16                        0       40,000     /  /                /  /       /  /      10/01/05  MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




COHOCTON CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-09-05-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CORNING-PAINTED POST SCHOOL DISTRICT: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-10-00-01
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GREENWOOD CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-15-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CANISTEO-GREENWOOD CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-15-02-06
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
09-0772    Reconstruction               5-004-002  06/09/10   10                             0       25,923     /  /                /  /       /  /        /  /    DDJ
10-0044    New Construction             7-026-001  08/31/10   02 - 16                        0        2,825     /  /                /  /       /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HORNELL CITY SCHOOL DISTRICT: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-18-00-01
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
09-1567    Reconstruction               0-013-010  12/09/10   2,4,7,8,9,16                   0    3,032,078     /  /                /  /       /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ARKPORT CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-19-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
98-1615    New Construction             7-006-001  06/25/99   02 - 16                        0      175,170     /  /                /  /       /  /        /  /    MEM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PRATTSBURGH CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-23-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




JASPER-TROUPSBURG CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-27-02-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HAMMONDSPORT CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-29-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
06-1000    Additions and Alterations    0-002-010  05/14/07   02 - 16                        0    1,197,600     /  /                /  /       /  /      03/21/08  MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WAYLAND CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-30-01-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WAYLAND-COHOCTON CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-30-02-04
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BOCES STEUBEN-ALLEGANY: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 57-90-00-00
last updated on 01/14/13
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition