WEST PARK UFSD(DISTRICT CLOSED): CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-02-02-02
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




KINGSTON CITY SCHOOL DISTRICT: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-06-00-01
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
06-0235    Alterations                  0-026-007  09/21/06   02 - 16                        0            0     /  /                /  /       /  /        /  /    JOD
08-0850    Reconstruction               0-026-010  05/19/09   2,8,155,16                     0    2,000,000     /  /                /  /       /  /        /  /    JOD
06-0236    Alterations                  0-028-009  09/21/06   02 - 16                        0            0     /  /                /  /       /  /        /  /    JOD
99-1274    Reconstruction               0-032-004  05/16/00   2,10                           0    1,300,000     /  /                /  /       /  /        /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HIGHLAND CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-08-03-04
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
07-1102    Reconstruction               0-001-003  01/11/08   7                              0      198,116     /  /                /  /       /  /        /  /    JOD
07-2019    Reconstruction               0-001-004  11/24/08   2,4,8,10,16                    0      299,635     /  /                /  /       /  /        /  /    JOD
07-1103    Reconstruction               0-009-007  01/11/08   7                              0      502,449     /  /                /  /       /  /        /  /    JOD
07-2020    Reconstruction               0-009-008  11/24/08   2,8,10,155,16                  0      797,317     /  /                /  /       /  /        /  /    JOD
07-1104    Reconstruction               0-010-007  01/11/08   7                              0      258,315     /  /                /  /       /  /        /  /    JOD
07-2021    Reconstruction               0-010-008  11/24/08   2,4,8,10,155,16                0      444,168     /  /                /  /       /  /        /  /    JOD
07-2022    Reconstruction               5-002-004  11/24/08   2,7,15                         0            0     /  /                /  /       /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




RONDOUT VALLEY CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-09-01-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
08-0593    Additions and Alterations    0-002-007  05/14/09   02 - 16                        0   25,736,500     /  /                /  /       /  /        /  /    JOD
08-0594    Reconstruction               0-007-010  05/14/09   2,8,9,10,15,16                 0    2,181,205     /  /                /  /       /  /        /  /    MGL
09-0908    Reconstruction               0-012-007  04/19/10   2,7                            0      271,919     /  /                /  /       /  /        /  /    JOD
09-0909    Reconstruction               5-008-003  06/02/10   2,7                            0       98,210     /  /                /  /       /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MARLBORO CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-10-01-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
07-1263    Additions and Alterations    0-007-005  09/26/08   02 - 16                        0   20,878,500     /  /                /  /       /  /        /  /    HCM
09-0311    Reconstruction               0-007-006  01/21/10   2,4,7,8,155,15,16              0    3,500,000     /  /                /  /       /  /        /  /    HCM
09-1472    Reconstruction               0-007-007  09/13/10   15,16                          0      360,000     /  /                /  /       /  /        /  /    HCM
09-0400    New Construction             7-021-001  04/26/10   02 - 16                        0            0     /  /                /  /       /  /        /  /    HCM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




NEW PALTZ CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-11-01-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
06-0004    Reconstruction               0-001-010  05/11/07   2,4,8,9,155,15,16              0      126,200     /  /                /  /       /  /        /  /    DDJ
06-0005    Reconstruction               0-004-008  05/11/07   2,4,7,8,9,155,15,16            0       12,400     /  /                /  /       /  /        /  /    DDJ
09-0985    Reconstruction               0-005-015  03/03/10   2,4,8,9,10,155,15,16           0       12,700     /  /                /  /       /  /        /  /    DDJ
02-0832    Reconstruction               0-008-006  01/30/03   7                              0      375,000     /  /                /  /       /  /        /  /    MGL
08-1610    Reconstruction               0-008-009  05/12/09   2,4,8,9,10,155,15,16           0       20,000     /  /                /  /       /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ONTEORA CENTRAL SCHOOL DISTRICT: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-12-01-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
00-0348    Reconstruction               0-001-014  11/27/00   2,4,8,9,10,155,15,16           0      523,532     /  /                /  /       /  /        /  /    MAC
02-0303    Reconstruction               7-014-002  11/01/02   15,16                          0    1,452,000     /  /                /  /       /  /        /  /    MAC


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SAUGERTIES CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-16-01-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
11-0228    Reconstruction               0-010-009  01/28/10   2,15                           0       65,000     /  /                /  /       /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WALLKILL CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-18-01-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ELLENVILLE CSD: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-20-02-06
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
  -        NO LATE or OVERDUE FCRs                   /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BOCES ULSTER: CAPITAL PROJECTS WITHOUT FINAL COST REPORTS
District No.: 62-90-00-00
last updated on 10/24/12
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________
98-1479    Reconstruction               0-014-010  08/23/99   8,155,15,16                    0      336,000     /  /                /  /       /  /        /  /    RDR
99-1741    Reconstruction               0-016-001  08/04/00   2                              0       47,500     /  /                /  /       /  /      01/23/01  MAC
99-1740    Reconstruction               8-023-002  08/04/00   2                              0       75,000     /  /                /  /       /  /      02/15/01  MAC


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition