REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Congers Elementary:
91-0774 Reconstruction 0-001-002 02/26/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1196 Reconstruction 0-001-003 05/03/93 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0416 Reconstruction 0-001-006 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1214 Reconstruction 0-001-007 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
3 43,525 01/16/07 / / Institutional Systems
04-0386 Reconstruction 0-001-009 12/17/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0036 Additions and Alterations 0-001-010 02/04/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0627 Reconstruction 0-001-011 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
GC-15 0 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-2 7,726 10/30/09 12/29/09 AARK CONTRACTORS INC
07-1363 Reconstruction 0-001-012 07/24/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0801 Reconstruction 0-001-014 10/23/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Birchwood School:
92-1227 Reconstruction 0-002-002 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0417 Reconstruction 0-002-007 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0469 Reconstruction 0-002-008 01/19/01 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0628 Reconstruction 0-002-009 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1074 Reconstruction 0-002-010 09/04/12 NO CHANGE ORDERS ON ELECTRONIC FILE
New City Elementary:
92-0768 Reconstruction 0-003-003 04/01/93 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0863 Reconstruction 0-003-005 11/27/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0418 Reconstruction 0-003-006 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0806 Reconstruction 0-003-007 06/07/02 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1215 Reconstruction 0-003-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institutional Systems
06-0625 Additions and Alterations 0-003-010 03/09/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0678 Reconstruction 0-003-011 05/23/06 *CO No.* Amount Disallowed Received Approved Contractor
003 1,053 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
004 2,812 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
005 -4,522 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
02 1,090 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
1 9,165 02/13/09 06/09/09 ALL BRIGHT ELECTRIC
1 123,878 05/22/09 02/02/11 PEARL RIVER PLUMBING HEATING & ELEC
07-0629 Reconstruction 0-003-012 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
ADT-3 731 05/12/10 12/22/10 ADT SECURITY SERVICES
GC-8 7,012 10/30/09 12/29/09 AARK CONTRACTORS INC
11-1041 Reconstruction 0-003-013 08/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1213FP Reconstruction 0-003-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Little Tor Elementary School:
91-0106 Reconstruction 0-004-002 08/12/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-1317 Reconstruction 0-004-004 06/01/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1630 Reconstruction 0-004-006 07/14/95 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0370 Reconstruction 0-004-007 10/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0419 Reconstruction 0-004-009 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1216 Reconstruction 0-004-010 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institutional Systems
05-0679 Reconstruction 0-004-011 05/23/06 *CO No.* Amount Disallowed Received Approved Contractor
002 1,090 05/22/09 06/05/09 BERTUSSI PLUMBING HEATING & COOLING
003 5,472 05/22/09 06/05/09 BERTUSSI PLUMBING HEATING & COOLING
1 1,551 02/13/09 06/09/09 ALL BRIGHT ELECTRIC
1 81,432 05/22/09 06/05/09 PEARL RIVER PLUMBING, HEATING & ELEC
4 -4,522 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
07-0630 Reconstruction 0-004-013 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1042 Reconstruction 0-004-014 08/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Chestnut Grove(Data Center):
91-1073 Reconstruction 0-005-003 04/20/92 NO CHANGE ORDERS ON ELECTRONIC FILE
91-1550 Reconstruction 0-005-004 07/08/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1561 Reconstruction 0-005-006 07/27/95 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0420 Reconstruction 0-005-009 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1043 Reconstruction 0-005-011 08/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-2340FP Reconstruction 0-005-FP1 08/26/03 NO CHANGE ORDERS ON ELECTRONIC FILE
West Nyack Elementary School:
92-0769 Reconstruction 0-006-003 04/01/93 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0864 Reconstruction 0-006-007 11/27/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0421 Reconstruction 0-006-008 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1217 Reconstruction 0-006-010 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institional systems
02-0196 Reconstruction 0-006-012 03/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0680 Reconstruction 0-006-014 05/23/06 *CO No.* Amount Disallowed Received Approved Contractor
003 3,719 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
004 -4,522 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
005 3,205 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
006 3,745 02/13/09 06/10/09 BERTUSSI PLUMBING HEATING & COOLING
1 65,736 02/13/09 06/10/09 PEARL RIVER PLUMBING HEATING & ELECT
1 15,116 02/13/09 06/10/09 ALL BRIGHT ELECTRIC
2 4,448 02/13/09 04/03/09 BERTUSSI PLUMBING HEATING & COOLING
7 10,000 02/13/09 06/10/09 BERTUSSI PLUMBING HEATING & COOLING
07-0631 Reconstruction 0-006-015 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0802 Reconstruction 0-006-017 10/23/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Bardonia Elementary School:
92-0284 Reconstruction 0-007-003 10/21/92 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0732 Reconstruction 0-007-005 01/27/98 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0422 Reconstruction 0-007-007 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1218 Reconstruction 0-007-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
2 2,959 2,959 01/16/07 12/28/07 Institutional Systems
3 43,525 01/16/07 12/28/07 Institional Systems
06-0564 Reconstruction 0-007-011 05/17/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0681 Reconstruction 0-007-012 05/23/06 *CO No.* Amount Disallowed Received Approved Contractor
003 10,131 02/13/09 04/03/09 BERTUSSI PLUMBING HEATING & COOLING
004 -4,522 02/13/09 04/03/09 BETRUSSI PLUMBING HEATING & COOLING
005 3,744 02/13/09 04/03/09 BETUSSI PLUMBING HEATING & COOLING
006 6,774 02/13/09 04/03/09 BERTUSSI PLUMBING HEATING & COOLING
1 75,771 02/13/09 04/03/09 PEARL RIVER PLUMBING
1 7,174 02/13/09 06/09/09 ALL BRIGHT ELECTRIC
2 7,390 02/13/09 / / BERTUSSI PLUMBING HEATING & COOLING
07-0632 Reconstruction 0-007-014 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 1,558 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
07-1364 Reconstruction 0-007-015 07/24/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1044 Reconstruction 0-007-017 08/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1212FP Reconstruction 0-007-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
High School North Annex:
00-1317 Reconstruction 0-009-003 05/29/01 *CO No.* Amount Disallowed Received Approved Contractor
01 3,542 04/12/02 04/26/02 Pearl River PH&E
04-0158 Reconstruction 0-009-004 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Senior High School North:
91-1074 Reconstruction 0-010-002 04/20/92 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0775 Reconstruction 0-010-003 02/26/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-0975 Reconstruction 0-010-005 05/10/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1255 Reconstruction 0-010-007 05/25/94 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1130 Reconstruction 0-010-011 04/29/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0756 Additions and Alterations 0-010-012 06/30/02 *CO No.* Amount Disallowed Received Approved Contractor
0001A 896,291 10/24/05 04/03/07 darlind Construction
003 5,132 04/06/09 / / VARDON, INC.
003 11,672 04/06/09 / / J.D. PARRELLA ELECTRIC, INC.
005 13,355 04/06/09 / / J.D. PARRELLA ELECTRIC, INC.
006 65,000 04/06/09 / / J.D. PARRELLA ELECTRIC, INC.
1 52,000 12/23/05 04/12/06 Vardon Inc
1 71,395 12/23/05 / / thomas Kempton
1 15,041 12/23/05 01/19/06 JD parrella electric
2 20,995 10/24/05 03/23/07 Darlind Construction
2 36,421 12/23/05 / / Vardon Inc
2A 46,776 10/24/05 04/03/07 darlind Construction
3 16,901 10/24/05 04/03/07 darlind Construction
4 2,216 10/24/05 12/07/05 darlind Construction
5 41,529 12/23/05 06/26/06 Darlind Construction
03-0423 Reconstruction 0-010-013 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1259 Reconstruction 0-010-014 12/11/12 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0626 Additions and Alterations 0-010-015 03/09/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0633 Reconstruction 0-010-017 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
GC-7 1,897 10/30/09 12/29/09 AARK CONTRACTORS INC
PC-2 8,050 08/07/09 09/18/09 JAC MECHANICAL SERVICES INC
07-0641 Reconstruction 0-010-018 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
SGC-1 -22,327 10/23/09 12/28/09 ETRE ASSOCIATES LTD
SGC-3 5,750 10/23/09 12/28/09 ETRE ASSOCIATES LTD
12-0065 Additions and Alterations 0-010-019 03/04/13 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1216FP Reconstruction 0-010-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Laurel Plains Elementary:
91-0107 Reconstruction 0-011-002 08/12/91 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1197 Reconstruction 0-011-003 05/03/93 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0896 Additions and Alterations 0-011-005 05/05/03 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0424 Reconstruction 0-011-006 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0682 Reconstruction 0-011-007 05/23/06 *CO No.* Amount Disallowed Received Approved Contractor
004 667 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
005 9,159 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
1 91,703 02/13/09 04/03/09 PEARL RIVER PLUMBING HEATING & ELEC
1 8,460 02/13/09 06/09/09 ALL BRIGHT ELECTRIC
2 544 02/13/09 04/03/09 BERTUSSI PLUMBING HEATING & COOLING
3 4,522 02/13/09 04/23/09 BERTUSSI PLUMBING HEATING & COOLING
07-0634 Reconstruction 0-011-008 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0266 Reconstruction 0-011-010 09/27/10 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0803 Reconstruction 0-011-011 10/23/12 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0934FP Reconstruction 0-011-FP1 02/02/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Felix Festa Junior High:
92-1228 Reconstruction 0-012-005 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1471 Reconstruction 0-012-006 06/21/95 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0211 Reconstruction 0-012-008 10/03/94 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0425 Reconstruction 0-012-014 10/08/04 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
002 59,016 07/25/06 12/27/06 Joe Lombardo Plumbing
005 65,000 07/25/06 / / Joe Lombardo Plumbing
007 69,429 07/25/06 / / JD Parella Electric
12 45,890 07/25/06 08/10/06 Morris Park Contracting
4 8,048 07/25/06 12/27/06 Joe Lombardo Plumging
6 32,535 07/25/06 / / JD Parella Electric
8 20,312 07/25/06 / / Jd Parella Electric
03-1440 Reconstruction 0-012-016 04/13/05 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1045 Reconstruction 0-012-018 08/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0287 Reconstruction 0-012-019 12/28/06 NO CHANGE ORDERS ON ELECTRONIC FILE
05-1419 Reconstruction 0-012-020 01/24/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0635 Reconstruction 0-012-021 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
ADT-1 18,833 05/12/10 12/22/10 ADT SECURITY SERVICES
EC-2 12,674 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
EC-3 1,823 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
EC-4 1,295 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
EC-6 5,170 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
EC-7 -8,500 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
GC-11 2,715 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-13 9,067 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-16 953 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-6 1,765 10/30/09 12/29/09 AARK CONTRACTORS INC
MC-1 15,000 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
MC-2 65,000 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
MC-3 14,000 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
MC-4 16,369 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
MC-5 8,864 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
MC-6 6,440 08/07/09 09/18/09 TM BRENNAN CONTRACTORS, INC
MC-7 -5,000 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
PC-1 -2,272 08/07/09 09/18/09 JAC MECHANICAL SERVICES INC
PC-3 9,926 08/07/09 09/18/09 JAC MECHANICAL SERVICES INC
PC-4 3,951 08/07/09 09/18/09 JAC MECHANICAL SERVICES INC
07-0642 Reconstruction 0-012-022 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
SGC-4 6,600 10/23/09 12/28/09 ETRE ASSOCIATES LTD
SGC-5 1,975 10/23/09 12/28/09 ETRE ASSOCIATES LTD
SGC-6 2,100 10/23/09 12/28/09 ETRE ASSOCIATES LTD
10-0187 Reconstruction 0-012-024 09/03/10 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1464 Reconstruction 0-012-025 09/03/10 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1263FP Reconstruction 0-012-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Dina Link Elementary:
92-1198 Reconstruction 0-013-002 05/03/93 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1205 Reconstruction 0-013-005 07/28/00 *CO No.* Amount Disallowed Received Approved Contractor
1 3,700 06/30/04 06/30/04 Parker Elec.
1 2,428 06/30/04 06/30/04 Pearl River Plumbing
1 12,600 06/30/04 06/30/04 Robert Runge Const.
2 830 06/30/04 06/30/04 Parker Elec.
2 5,083 06/30/04 06/30/04 Pearl River Plumbing
2 -18,268 06/30/04 06/30/04 Robert Runge Const.
3 4,000 06/30/04 06/30/04 Parker Elec.
3 575 06/30/04 06/30/04 Pearl River Plumbing
4 1,725 06/30/04 06/30/04 Pearl River Plumbing
03-0426 Reconstruction 0-013-006 10/08/04 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institutional Systems
01-1219 Reconstruction 0-013-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
1 11,116 01/16/07 / / Instituional Systems
02-1695 Additions and Alterations 0-013-009 03/16/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0636 Reconstruction 0-013-012 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1046 Reconstruction 0-013-013 08/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Wood Glen Elementary:
98-0900 Reconstruction 0-016-004 04/28/99 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0283 Alterations 0-016-005 11/29/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0427 Reconstruction 0-016-008 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0637 Reconstruction 0-016-010 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0804 Reconstruction 0-016-012 10/23/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1214FP Reconstruction 0-016-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Lakewood Elementary School:
91-0109 Reconstruction 0-017-002 08/12/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1443 Additions and Alterations 0-017-004 06/21/95 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0514 Additions and Alterations 0-017-005 02/12/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0428 Reconstruction 0-017-007 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1220 Reconstruction 0-017-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
1 11,116 11,116 01/16/07 12/28/07 Instituional Systems
3 43,525 43,525 01/16/07 Disapproved Ins6itutional Systems
07-0638 Reconstruction 0-017-009 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
GC-4 925 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-5 310 10/30/09 12/29/09 AARK CONTRACTORS INC
MC-6 6,440 08/07/09 / / TM BRENNAN CONTRACTORS INC
11-0805 Reconstruction 0-017-010 10/23/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1211FP Reconstruction 0-017-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Senior High School South:
92-0976 Reconstruction 0-018-003 05/10/93 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1039 Reconstruction 0-018-004 05/20/93 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1229 Reconstruction 0-018-005 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0017 Reconstruction 0-018-007 07/28/00 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0085 Reconstruction 0-018-008 08/28/95 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0845 Reconstruction 0-018-010 03/06/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1242 Additions and Alterations 0-018-011 06/30/02 *CO No.* Amount Disallowed Received Approved Contractor
1 68,875 08/08/05 08/15/05 Pearl River Plumbing
1 5,905 08/08/05 / / GTL Construction
1 3,531 08/08/05 08/15/05 Pearl River Plumbing Heating
2 9,403 08/08/05 / / GTL Construction
2 9,403 12/08/05 07/26/06 GTL CONSTRUCTION, LLC.
3 10,961 08/08/05 / / GTL Construction
00-0119 Reconstruction 0-018-012 10/17/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0429 Reconstruction 0-018-013 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1441 Reconstruction 0-018-014 04/13/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0389 Reconstruction 0-018-015 02/21/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0936 Reconstruction 0-018-016 05/04/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0639 Reconstruction 0-018-017 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
ADT-2 8,543 05/12/10 12/22/10 ADT SECURITY SERVICES
EC-5 2,559 10/23/09 12/28/09 FANSHAWE INC d/b/a ROCKLAND ELECTRIC
GC-1 0 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-14 -330 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-17 3,714 10/30/09 12/29/09 AARK CONTRACTORS INC
GC-3 17,895 10/30/09 12/29/09 AARK CONTRACTORS INC
MC-8 -5,000 08/07/09 09/18/09 TM BRENNAN CONTRACTORS INC
SMC-1 10,000 05/12/10 12/22/10 PEARL RIVER P/H/E dba BERTUSSI'S
07-0643 Reconstruction 0-018-018 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
SGC-2 6,750 10/23/09 12/28/09 ETRE ASSOCIASTES INC
11-0806 Reconstruction 0-018-019 10/23/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1215FP Reconstruction 0-018-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Strawtown Road Elementary:
92-1230 Reconstruction 0-019-002 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0809 Reconstruction 0-019-004 06/07/02 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0016 Reconstruction 0-019-007 08/24/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0430 Reconstruction 0-019-008 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0810 Reconstruction 0-019-009 06/07/02 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0470 Reconstruction 0-019-010 01/19/01 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0640 Reconstruction 0-019-011 04/15/08 *CO No.* Amount Disallowed Received Approved Contractor
GC-10 4,073 10/30/09 12/29/09 AARK CONTRACTORS INC
11-1075 Reconstruction 0-019-012 09/04/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Storage Shed:
03-1080 New Construction 2-027-001 03/16/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
10-1113 Reconstruction 5-005-003 06/08/11 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1546 Reconstruction 5-022-002 06/05/95 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0431 Reconstruction 5-022-004 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Press Box @ South High School:
06-0369 New Construction 7-030-001 10/19/07 NO CHANGE ORDERS ON ELECTRONIC FILE
Press Box @ NHS:
11-1455 New Construction 7-034-001 11/08/12 NO CHANGE ORDERS ON ELECTRONIC FILE
North HS Concession Stand:
12-0456 New Construction 7-035-001 03/26/13 NO CHANGE ORDERS ON ELECTRONIC FILE
NHS Guard Booth:
12-0929 New Construction 7-036-001 05/02/13 NO CHANGE ORDERS ON ELECTRONIC FILE
Districtwide-Elementary:
94-1506 Reconstruction 7-999-001 06/27/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-0849 Reconstruction 7-999-002 02/28/97 NO CHANGE ORDERS ON ELECTRONIC FILE
NANUET UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-01-08-03
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Miller Elementary:
96-1247 Additions and Alterations 0-001-004 04/30/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1362 Additions and Alterations 0-001-005 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0558 Reconstruction 0-001-006 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1388 Reconstruction 0-001-007 07/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1437 Reconstruction 0-001-008 07/23/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1077 Additions and Alterations 0-001-009 05/11/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0334 Reconstruction 0-001-010 10/15/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0447 Reconstruction 0-001-011 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1060 Reconstruction 0-001-012 02/12/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0065 Reconstruction 0-001-013 07/24/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0989 Reconstruction 0-001-014 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0974 Reconstruction 0-001-015 08/19/10 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0555 Reconstruction 0-001-016 02/19/10 *CO No.* Amount Disallowed Received Approved Contractor
GC-003 0 07/02/12 12/20/12 C&M DOOR CONTROLS
10-1387 Reconstruction 0-001-017 08/01/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0681FP Reconstruction 0-001-FP1 03/03/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Highview Elementary:
94-1337 Reconstruction 0-002-004 05/11/95 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1330 Reconstruction 0-002-005 07/06/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0559 Reconstruction 0-002-006 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1361 Reconstruction 0-002-007 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0064 Additions and Alterations 0-002-008 05/07/04 *CO No.* Amount Disallowed Received Approved Contractor
EL-3 -25,000 08/05/05 08/17/05 Habiterra Architecture and Landscape
03-0448 Reconstruction 0-002-009 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1061 Reconstruction 0-002-010 02/12/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0990 Reconstruction 0-002-011 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0975 Reconstruction 0-002-012 08/19/10 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0556 Reconstruction 0-002-013 02/19/10 *CO No.* Amount Disallowed Received Approved Contractor
GC-004 0 07/02/12 12/20/12 C&M DOOR CONTROLS
10-1388 Reconstruction 0-002-014 08/01/11 NO CHANGE ORDERS ON ELECTRONIC FILE
Nanuet Senior High:
98-1364 Reconstruction 0-003-006 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0560 Reconstruction 0-003-007 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1390 Reconstruction 0-003-008 07/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1436 Reconstruction 0-003-009 07/23/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1075 Reconstruction 0-003-010 03/21/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0335 Additions and Alterations 0-003-012 07/13/04 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0080 Reconstruction 0-003-013 03/26/03 *CO No.* Amount Disallowed Received Approved Contractor
01-001 6,128 03/04/04 03/15/04 Cali Brothers
03-001 -5,000 04/05/04 04/08/04 Pearl River Plumbing
04-001 395 03/04/04 03/25/04 Fanshawe Inc
03-0449 Reconstruction 0-003-014 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1062 Reconstruction 0-003-015 02/12/04 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1427 Reconstruction 0-003-016 07/19/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0991 Reconstruction 0-003-017 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0838 Reconstruction 0-003-018 04/16/09 *CO No.* Amount Disallowed Received Approved Contractor
001 4,351 01/19/10 05/27/10 JAC MECHANICAL SERVICES
001 -4,441 01/19/10 05/27/10 FANSHAWE INC
001 -5,000 05/03/10 08/17/10 PEARL RIVER PLUMBING & HEATING INC
002 -559 01/19/10 05/27/10 FANSHAWE INC
09-0976 Reconstruction 0-003-020 08/19/10 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0557 Reconstruction 0-003-021 02/19/10 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1389 Reconstruction 0-003-022 08/01/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0682FP Reconstruction 0-003-FP1 03/03/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Nanuet Middle:
98-1363 Reconstruction 0-004-003 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0561 Reconstruction 0-004-004 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1389 Reconstruction 0-004-005 07/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1438 Reconstruction 0-004-006 07/23/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1078 Additions and Alterations 0-004-007 06/06/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0065 Reconstruction 0-004-008 05/07/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0450 Reconstruction 0-004-009 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0992 Reconstruction 0-004-011 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0977 Reconstruction 0-004-012 08/19/10 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0558 Reconstruction 0-004-013 02/19/10 *CO No.* Amount Disallowed Received Approved Contractor
GC-002 0 07/02/12 12/20/12 C&M DOOR CONTROLS
10-1390 Reconstruction 0-004-014 08/01/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0680FP Reconstruction 0-004-FP1 12/19/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Maintenance Building:
98-1703 New Construction 7-007-001 10/22/99 NO CHANGE ORDERS ON ELECTRONIC FILE
New Press Box @ HS:
06-1677 New Construction 7-010-001 09/12/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Land Purchse w/23 Structures(See L):
06-0690 New Construction 7-011-001 03/21/07 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1215 Reconstruction 7-011-002 07/15/11 NO CHANGE ORDERS ON ELECTRONIC FILE
Children of Promise Equestrian Ring:
12-0535 New Construction 7-017-001 05/02/13 NO CHANGE ORDERS ON ELECTRONIC FILE
District Wide:
98-1165 Reconstruction 7-999-001 05/06/99 NO CHANGE ORDERS ON ELECTRONIC FILE
NORTH ROCKLAND/HAVERSTRAW-STONY PT STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-02-01-06
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Farley Middle School:
03-1549 Reconstruction 0-003-007 06/01/04 *CO No.* Amount Disallowed Received Approved Contractor
0 3 / / / /
0 / / / /
0 3 / / / /
01 -44,900 02/16/05 02/18/05 Milcon Construction
02 14,000 02/16/05 02/18/05 Milcon Construction
03 6,100 06/10/05 06/30/05 Milcon Construction Corp
RC-04 1,178,300 05/20/05 06/03/05 Milcon Construction Corp
RC-05 11,900 07/22/05 07/26/05 Milcon Construction
RC-06 15,000 02/06/06 12/18/06 Milcon Construction
RC-07 6,400 03/28/06 07/13/06 milcon Construction
RC-08 5,800 03/28/06 07/24/06 Milcon Construction
10-1357 Reconstruction 0-003-008 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0322FP Reconstruction 0-003-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
No. Garnerville Elem/Admin.:
93-1221 Additions and Alterations 0-007-005 06/16/94 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1368 Reconstruction 0-007-006 06/10/94 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1544 Reconstruction 0-007-008 01/23/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 2,936 01/28/03 02/05/03 NEI/Naber Elec.
GC-1 -15,000 12/23/02 01/10/03 Piazza Brothers
GC-2 -13,800 12/23/02 01/10/03 Piazza Brothers
PC-1 3,990 01/28/03 02/05/03 Thomas Kempton
PC-2 3,200 05/02/03 05/05/03 Thomas Kempton
01-0285 Reconstruction 0-007-010 02/08/02 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1358 Reconstruction 0-007-013 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0323FP Reconstruction 0-007-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Haverstraw Middle School:
97-0560 Reconstruction 0-009-008 12/29/97 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0713 Reconstruction 0-009-009 12/27/02 *CO No.* Amount Disallowed Received Approved Contractor
1 5,000 06/23/04 06/28/04 Pearl River Plumbing
2 4,850 06/23/04 06/28/04 Pearl River Plumbing
3 14,800 06/23/04 06/28/04 Pearl River Plumbing
4 5,929 06/23/04 06/28/04 Pearl River Plumbing
99-1139 Reconstruction 0-009-010 06/22/00 *CO No.* Amount Disallowed Received Approved Contractor
EC-11 1,309 12/12/02 01/07/03 Ray S. Pantel
EC-13 870 03/20/03 03/28/03 Ray S. Pantel
EC-14 -5,000 10/10/03 11/05/03 Ray S. Pantel
EC-3 1,007 11/29/02 01/02/03 Ray S. Pantel
EC-4 2,416 12/23/02 01/10/03 Ray S. Pantel
G-15 -7,000 12/17/03 12/29/03 Helmer Cronin
G-7 1,524 12/23/02 01/10/03 Helmer Cronin
HC-5 -1,250 07/28/03 08/04/03 Hauser Brothers
09-0074 Reconstruction 0-009-013 10/21/09 *CO No.* Amount Disallowed Received Approved Contractor
1 13,225 06/20/12 12/13/12 Fanshawe, Inc. - Rockland Electric
2 9,000 06/20/12 12/13/12 Fanshawe, Inc. - Rockland Electric
3 9,000 06/20/12 12/13/12 Fanshawe, Inc. - Rockland Electric
4 -2,074 06/21/12 / / Fanshawe, Inc. - Rockland Electric
5 7,633 06/21/12 12/13/12 Fanshawe, Inc. - Rockland Electric
6 -4,440 06/21/12 12/13/12 Fanshawe, Inc. - Rockland Electric
7 -1,080 06/21/12 12/13/12 Fanshawe, Inc. - Rockland Electric
8 -2,000 06/22/12 12/13/12 Fanshawe, Inc. - Rockland Electric
10-1359 Reconstruction 0-009-014 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Gerald F. Neary Elementary:
02-1498 Reconstruction 0-011-004 04/08/03 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1360 Reconstruction 0-011-006 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Railroad Avenue School (Alt. Ed. Bld:
03-0770 Reconstruction 0-013-001 02/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1389 Reconstruction 0-013-002 10/21/05 *CO No.* Amount Disallowed Received Approved Contractor
1 2,021 02/15/07 03/14/07 KG Construction Associates
10-1361 Reconstruction 0-013-003 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Stony Point Elementary:
92-0463 Additions and Alterations 0-014-005 01/27/93 NO CHANGE ORDERS ON ELECTRONIC FILE
08-1452 Reconstruction 0-014-006 07/24/09 *CO No.* Amount Disallowed Received Approved Contractor
1 1,613 06/18/10 08/06/10 VARDON INC
2 6,845 06/18/10 08/06/10 VARDON INC
10-1362 Reconstruction 0-014-007 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
North Rockland High School:
90-1498 Reconstruction 0-016-007 06/14/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-0073 Reconstruction 0-016-008 09/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-0235 Reconstruction 0-016-009 10/28/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1683 Additions and Alterations 0-016-010 06/16/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1090 Reconstruction 0-016-011 08/30/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1362 Reconstruction 0-016-013 05/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0175 Reconstruction 0-016-015 02/05/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 4,150 11/29/02 12/09/02 Ray Pantel Elec.
EC-10 2,236 12/23/02 01/02/03 Ray Pantel
EC-12 1,750 03/20/03 03/24/03 Ray Pantel
EC-2 4,174 11/29/02 12/09/02 Ray Pantel
EC-5 2,236 11/22/02 01/08/03 Ray Pantel
EC-6 280 11/22/02 01/08/03 Ray Pantel
EC-7 1,415 11/22/02 01/08/03 Ray Pantel
EC-8 2,830 11/22/02 01/08/03 Ray Pantel
EC-9 1,677 12/02/02 01/02/03 Ray Pantel
G-1 51,480 12/23/02 01/10/03 Helmer Cronin Const.
G-10 6,036 11/22/02 01/08/03 Helmer Cronin Const.
G-11 1,493 11/22/02 01/08/03 Helmer Cronin Const.
G-12 1,819 11/22/02 01/08/03 Helmer Cronin Const.
G-13 -1,000 12/17/03 12/26/03 Helmer Cronin Const.
G-14 -26,452 12/17/03 12/26/03 Helmer Cronin Const.
G-2 2,117 12/23/02 01/10/03 Helmer Cronin Const.
G-3 1,732 12/23/02 02/21/03 Helmer Cronin Const.
G-4 3,850 12/23/02 02/21/03 Helmer Cronin Const.
G-5 1,900 12/23/02 01/10/03 Helmer Cronin Const.
G-6 853 12/23/02 02/21/03 Helmer Cronin Const.
G-8 21,500 12/23/02 01/10/03 Helmer Cronin Const.
G-9 938 12/23/02 01/10/03 Helmer Cronin Const.
HB-3 4,995 02/03/04 02/03/04 Hauser Brothers
HC-1 1,250 12/23/02 01/07/03 Hauser Brothers
HC-2 4,700 12/23/02 01/07/03 Hauser Brothers
HC-4 7,171 07/28/03 07/29/03 Hauser Brothers
PC-1 5,064 01/28/03 02/05/03 Thomas Kempton
PC-2 -5,000 10/10/03 12/22/03 Thomas Kempton
PW-1 15,500 12/23/02 01/07/03 Urban-Suburban Recreation
PW-2 9,638 12/23/02 01/07/03 Urban-Suburban Recreation
PW-3 25,544 03/12/02 05/06/02 Urban-Suburban Recreation
SC-1 104,250 01/28/03 02/05/03 Mountain View Const.
SC-2 80,812 02/11/02 03/22/02 Mountain View Const.
SC-3 19,136 03/12/02 05/06/02 Mountain View Const.
SC-4 -1,654 12/22/03 12/26/03 Mountain View Const.
00-1868 Additions and Alterations 0-016-016 06/12/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1071 Reconstruction 0-016-017 05/24/04 *CO No.* Amount Disallowed Received Approved Contractor
04 1,600 06/10/05 07/20/05 Carjen Fence Co
05 -1,746 10/21/05 11/08/05 Carjen Fence Co
GC-01 5,000 06/10/05 07/20/05 carjen Fence Co
GC-02 6,600 06/10/05 07/20/05 Carjen Fence Co
GC-03 2,400 06/10/05 07/20/05 Carjen Fence Co
GW-06 -5,000 03/28/06 07/21/06 Carjen Fence Co
04-0319 Reconstruction 0-016-018 11/05/04 *CO No.* Amount Disallowed Received Approved Contractor
GW-04 200 02/06/06 / / Conserv Construction
GW-2 4,500 02/06/06 / / Conserv Corp
GW-3 14,212 10/21/05 11/07/05 Consery Corp
03-1550 Reconstruction 0-016-019 07/16/04 *CO No.* Amount Disallowed Received Approved Contractor
01 -6,611 06/10/05 01/11/06 Eagle Electric
02 5,400 06/10/05 08/18/05 Eagle electric
03 1,472 03/28/06 04/21/06 Eagle Electric
10-1363 Reconstruction 0-016-022 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0319FP Reconstruction 0-016-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0139 Visual Structural Inspection 0-016-SC1 08/07/06 NO CHANGE ORDERS ON ELECTRONIC FILE
West Haverstraw Elementary:
92-0629 Reconstruction 0-024-005 03/10/93 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1361 Reconstruction 0-024-006 05/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0284 Reconstruction 0-024-007 02/08/02 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1388 Reconstruction 0-024-008 10/21/05 *CO No.* Amount Disallowed Received Approved Contractor
1 14,400 11/15/06 01/09/07 Monpat Construction
2 6,400 02/13/07 03/14/07 Monpat Construction
08-1453 Reconstruction 0-024-009 07/24/09 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1364 Reconstruction 0-024-010 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0321FP Reconstruction 0-024-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Thiells Elementary School:
92-1134 Additions and Alterations 0-025-006 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0403 Reconstruction 0-025-008 11/07/97 *CO No.* Amount Disallowed Received Approved Contractor
1 88,920 01/28/03 02/11/03 Ed Coupart & Son
2 14,375 01/28/03 02/11/03 Ed Coupart & Son
99-0303 Reconstruction 0-025-009 10/07/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1192 Reconstruction 0-025-011 04/09/04 *CO No.* Amount Disallowed Received Approved Contractor
01 -109,600 02/16/05 02/18/05 Milcon Construction Corp
02 29,080 06/10/05 06/30/05 Milcon Construction
03 18,890 08/23/06 08/25/06 Milcon Construction
10-1365 Reconstruction 0-025-012 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0320FP Reconstruction 0-025-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
8/9th Grade Ctr. @ Letchworth:
01-1106SR New Construction 0-031-001 05/23/02 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
EC-01 19,631 05/19/08 / / All Bright Electric
EC-22 17,468 06/20/12 / / All Bright Electric
GC-67 16,804 05/19/08 / / Morris Park Contracting
GC-68 55,625 05/19/08 / / Morris Park Contracting
HC-01 975,000 05/19/08 / / David L. Kempton Inc.
PC-01 16,448 05/19/08 / / Davidson and Howard
SC-01 0 12/09/02 01/07/03 Pinnacle Environ.
02-0309 New Construction 0-031-001 12/11/02 *CO No.* Amount Disallowed Received Approved Contractor
CW-01 4,180 06/16/05 07/12/05 Longo Associates
EC-01 19,630 03/15/04 08/11/08 All Bright Electric
EC-02 56,780 10/12/04 10/18/04 All Bright Electric
EC-03 22,147 06/07/04 06/22/04 All Bright Electric
EC-04 3,512 06/07/04 06/22/04 All Bright Electric
EC-05 6,696 06/07/04 06/22/04 All Bright Electric
EC-06 122,910 122,910 06/17/04 09/27/04 All Bright Electric
EC-07 19,248 06/16/04 09/27/04 All Bright Electric
EC-08 11,454 09/29/04 12/24/04 All Bright Electric
EC-09 19,954 12/06/04 12/23/04 All Bright Electric
EC-10 7,323 09/29/04 12/24/04 All Bright Electric
EC-11 43,343 09/29/04 12/24/04 All Bright Electric
EC-12 10,005 09/29/04 12/24/04 All Bright Electric
EC-13 -5,391 09/29/04 12/24/04 All Bright Electric
EC-14 19,555 11/01/04 12/06/04 All Bright Electric
EC-15 14,297 11/01/04 12/21/04 All Bright Electric
EC-16 8,212 11/18/04 12/06/04 All Bright Electric
EC-17 18,772 01/18/05 03/17/05 All Bright Electric
EC-18 18,184 01/18/05 03/17/05 All Bright Electric
EC-19 16,830 01/18/05 03/17/05 All Bright Electric
EC-20 17,597 01/18/05 03/17/05 All Bright Electric
EC-21 14,735 01/18/05 03/17/05 All Bright Electric
EC-22 17,468 06/20/12 10/24/12 All Bright Electric
EC-23 16,860 06/20/12 10/24/12 All Bright Electric
EC-24 16,596 06/20/12 10/24/12 All Bright Electric
EC-25 67,810 06/13/05 07/12/05 All Bright Electric
EC-26 17,159 06/13/05 07/12/05 All Bright Electric
EC-27 2,433 06/20/12 10/24/12 All Bright Electric
EC-28 9,500 06/20/12 10/24/12 All Bright Electric
EC-29 5,890 09/18/06 10/19/06 All Bright Electric
EC-30 4,000 09/18/06 10/19/06 All Bright Electric
EQ-01 4,428 01/18/05 03/18/05 Nickerson Corp
EQ-02 3,575 10/24/05 11/08/05 Nickerson Corp
FS-01 3,100 10/24/05 11/08/05 E Friedman Associates
GC-01 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-02 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-03 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-04 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-05 17,603 07/28/03 07/29/03 Morris Park Contracting
GC-06 12,020 10/23/03 11/18/03 Morris Park Contracting
GC-07 16,283 10/23/03 11/18/03 Morris Park Contracting
GC-08 14,460 10/23/03 11/18/03 Morris Park Contracting
GC-09 4,062 10/23/03 11/18/03 Morris Park Contracting
GC-10 10,323 10/10/03 11/26/03 Morris Park Contracting
GC-11 12,032 10/10/03 11/26/03 Morris Park Contracting
GC-12 10,201 10/10/03 11/26/03 Morris Park Contracting
GC-13 6,771 10/10/03 11/26/03 Morris Park Contracting
GC-14 17,550 10/20/03 11/17/03 Morris Park Contracting
GC-15 19,643 11/13/03 12/26/03 Morris Park Contracting
GC-16 40,000 11/13/03 12/26/03 Morris Park Contracting
GC-17 10,809 11/13/03 11/24/03 Morris Park Contracting
GC-19 11,701 12/17/03 12/26/03 Morris Park Contracting
GC-20 19,620 01/23/04 03/08/04 Morris Park Contracting
GC-21 9,876 03/15/04 04/07/04 Morris Park Contracting
GC-22 13,333 03/15/04 04/07/04 Morris Park Contracting
GC-23 15,722 06/07/04 06/22/04 Morris Park Contracting
GC-24 14,247 06/07/04 06/22/04 Morris Park Contracting
GC-25 8,463 06/07/04 06/14/04 Morris Park Contracting
GC-26 23,926 06/07/04 06/22/04 Morris Park Contracting
GC-27 13,825 06/07/04 06/22/04 Morris Park Contracting
GC-28 11,591 06/07/04 06/22/04 Morris Park Contracting
GC-29 30,100 06/07/04 06/22/04 Morris Park Contracting
GC-30 12,730 06/07/04 06/22/04 Morris Park Contracting
GC-31 8,080 06/07/04 06/22/04 Morris Park Contracting
GC-32 14,830 06/07/04 06/22/04 Morris Park Contracting
GC-33 14,484 06/17/04 06/22/04 Morris Park Contracting
GC-34 2,633 09/29/04 12/24/04 Morris Park Contracting
GC-35 12,429 09/29/04 12/24/04 Morris Park Contracting
GC-36 18,259 09/29/04 12/24/04 Morris Park Contracting
GC-37 15,366 09/29/04 12/24/04 Morris Park Contracting
GC-38 19,795 09/29/04 12/24/04 Morris Park Contracting
GC-39 19,590 09/29/04 12/24/04 Morris Park Contracting
GC-40 18,449 09/29/04 12/24/04 Morris Park Contracting
GC-41 11,740 09/29/04 12/24/04 Morris Park Contracting
GC-42 19,132 09/29/04 12/24/04 Morris Park Contracting
GC-43 10,285 09/29/04 12/24/04 Morris Park Contracting
GC-44 -1,492 09/29/04 12/24/04 Morris Park Contracting
GC-45 16,109 11/01/04 12/21/04 Morris Park Contracting
GC-46 14,158 11/01/04 12/21/04 Morris Park Contracting
GC-47 13,462 11/01/04 12/21/04 Morris Park Contracting
GC-48 13,674 11/01/04 12/06/04 Morris Park Contracting
GC-49 9,471 11/01/04 12/06/04 Morris Park Contracting
GC-50 19,635 11/10/04 12/06/04 Morris Park Contracting
GC-51 -955 11/10/04 12/06/04 Morris Park Contracting
GC-52 16,025 11/10/04 12/06/04 Morris Park Contracting
GC-53 2,436 11/10/04 12/06/04 Morris Park Contracting
GC-54 11,567 11/10/04 12/06/04 Morris Park Contracting
GC-55 12,650 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-56 9,616 01/24/05 03/18/05 Morris Park Contracting Corp
GC-57 16,991 01/24/05 03/18/05 Morris park Contracting
GC-58 15,280 01/24/05 03/18/05 Morris Park Contracting
GC-59 19,604 01/18/05 / / Morris Park Contracting Corp
GC-59 19,604 01/18/05 03/17/05 Morris Park Contracting
GC-60 10,257 01/24/05 03/18/05 Morris Park Contracting Corp
GC-61 9,888 01/24/05 03/18/05 Morris Park Contracting
GC-62 33,558 01/24/05 03/18/05 Morris Park Contracting Corp
GC-63 13,597 01/24/05 03/18/05 Morris Park Contracting
GC-64 11,217 01/24/05 03/18/05 Morris Park Contracting Corp
GC-65 21,820 01/24/05 03/18/05 Morris Park Contracting
GC-66 7,136 04/08/05 04/24/06 Morris Park Contracting
GC-67 16,804 04/08/05 10/24/12 Morris Park Contracting
GC-68 55,625 04/08/05 08/11/08 Morris Park Contracting
GC-69 21,244 04/08/05 04/24/06 Morris Park Contracting
GC-70 17,179 04/08/05 06/15/05 Morris Park Contracting
GC-71 15,659 04/08/05 06/15/05 Morris Park Contracting
GC-72 10,221 04/08/05 06/15/05 Morris Park Contracting
GC-73 3,738 04/08/05 06/15/05 Morris Park Contracting
GC-74 49,140 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-75 12,382 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-76 14,052 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-77 18,690 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-78 16,002 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-79 13,379 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-80 15,979 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-81 19,727 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-82 18,052 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-83 15,029 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-84 8,145 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-85 16,211 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-86 14,957 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-87 11,674 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-88 1,987 06/20/12 10/24/12 Morris Park Contracting Corp.
HC-01 975,000 10/10/03 08/11/08 David Kempton
HC-02 17,735 10/24/05 10/26/05 David kempton Inc
HC-03 15,463 10/24/05 11/01/05 david kempton
HC-04 2,218 08/19/05 09/02/05 David kampton
HC-05 3,159 03/31/06 07/24/06 David kempton
HC-06 2,307 09/18/06 10/19/06 David Kempton
PC-01 16,448 03/15/04 08/11/08 Davidson and Howard
PC-02 6,804 04/07/04 06/22/04 Davidson and Howard
PC-03 4,575 09/29/04 12/24/04 Davidson and Howard
PC-04 14,284 11/10/04 12/06/04 Davidson and Howard
PC-05 19,858 01/18/05 03/22/05 Davidson and Howard Inc
PC-06 6,791 04/08/05 06/21/05 Davidson and Howard Inc
PC-07 -1,052 10/24/05 10/26/05 Davidson and Howard
SC-02 13,500 03/20/03 03/24/03 Pinnacle Environ.
SC-03 8,740 03/20/03 03/24/03 Pinnacle Environ.
SC-04 12,760 03/20/03 03/24/03 Pinnacle Environ.
SC-05 8,426 08/12/03 08/14/03 Pinnacle Environ.
SC-06 -94,886 06/07/04 06/22/04 Pinnacle Environ.
10-1366 Reconstruction 0-031-002 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0346SC Visual Structural Inspection 0-031-SC1 11/15/05 NO CHANGE ORDERS ON ELECTRONIC FILE
8/9 Grade Ctr-Mechanical Bldg.(#28):
02-0310 Reconstruction 0-042-001 12/11/02 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
GC-18 11,324 12/17/03 12/26/03 Morris Park Contracting
GC-89 2,723 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-90 15,198 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-91 -4,950 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-92 9,690 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-93 9,873 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-94 14,091 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-95 2,017 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-96 -8,434 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-97 -117,264 06/20/12 10/24/12 Morris Park Contracting Corp.
GC-97 -117,264 06/20/12 / / Morris Park Contracting Corp.
03-1651 Reconstruction 0-042-002 01/26/05 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1525 Reconstruction 0-042-003 06/05/07 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 29:
99-1202 Reconstruction 0-043-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
````````````` Bldg 31:
99-0665 Reconstruction 0-045-001 04/10/00 *CO No.* Amount Disallowed Received Approved Contractor
AC-1 -10,000 01/17/02 03/26/02 Netrix
CAT Letchworth Bldg 32:
99-0666 Reconstruction 0-046-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 33:
99-0667 Reconstruction 0-047-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 35:
99-0668 Reconstruction 0-049-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 36:
99-0669 Reconstruction 0-050-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 37:
99-0670 Reconstruction 0-051-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 38:
99-0671 Reconstruction 0-052-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
Railroad Ave Admin. Bldg.:
96-0255 Reconstruction 1-013-004 09/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1140 Reconstruction 1-013-005 06/22/00 NO CHANGE ORDERS ON ELECTRONIC FILE
Buckberg Warehouse:
10-1367 Reconstruction 2-015-002 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Maintenance Garage:
96-1363 Reconstruction 3-002-003 05/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
District Wide:
99-1647 Reconstruction 7-999-003 06/20/00 *CO No.* Amount Disallowed Received Approved Contractor
G-1 12,306 01/28/03 02/03/03 Tenavision
G-2 5,918 01/28/03 02/03/03 Tenavision
G-3 7,526 01/28/03 02/03/03 Tenavision
G-4 61,205 02/06/02 05/05/03 Tenavision
G-5 19,409 02/06/02 03/21/02 Tenavision
G-6 19,562 12/23/02 01/14/03 Tenavision
G-7 11,135 12/23/02 01/14/03 Tenavision
Willow Grove Middle School:
96-1023 Reconstruction 8-030-002 04/16/97 *CO No.* Amount Disallowed Received Approved Contractor
PC-01 -15,320 10/24/05 11/25/05 David kempton
97-0502 Additions and Alterations 8-030-003 12/18/97 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0124 Reconstruction 8-030-005 09/17/02 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0496 Reconstruction 8-030-006 03/12/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1541 Reconstruction 8-030-008 07/16/04 *CO No.* Amount Disallowed Received Approved Contractor
01 9,504 02/16/05 02/18/05 Nikko Construction Corp
02 11,695 02/16/05 02/18/05 Nikko Construction
03 4,604 02/16/05 02/18/05 Nikko Construction
04 13,981 02/16/05 02/18/05 Nikko Construction
03-1563 Reconstruction 8-030-009 07/23/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1769 Reconstruction 8-030-010 07/29/08 NO CHANGE ORDERS ON ELECTRONIC FILE
10-1368 Reconstruction 8-030-011 03/15/12 NO CHANGE ORDERS ON ELECTRONIC FILE
SOUTH ORANGETOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-01-06
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Tappan Zee High School:
90-1294 Reconstruction 0-006-009 05/02/91 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0521 Additions and Alterations 0-006-010 03/11/99 *CO No.* Amount Disallowed Received Approved Contractor
7 4,802 03/15/00 12/01/03 Rockland Elec.
97-0228 Reconstruction 0-006-011 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0775 Reconstruction 0-006-012 01/27/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1431 Reconstruction 0-006-014 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1478 Additions and Alterations 0-006-015 06/28/05 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
1C-SC133 -9,000 10/05/07 11/08/07 LANDTEK
1C-SC134 5,000 10/05/07 11/08/07 LANDTEK
1C-SC135 -6,000 10/05/07 11/08/07 LANDTEK
1C-SC136 1,000 10/05/07 12/11/12 LANDTEK
1CSC102 0 10/19/09 12/26/12 LandTek
1CSC119 -5,000 10/19/09 12/26/12 LandTek
1CSC124 -50,000 10/19/12 12/11/12 LandTek
EC-201 0 08/04/06 08/31/06 Perreca Electric
EC-207 1,645 11/07/06 01/30/07 Perreca electric
EC-208 886 11/07/06 01/30/07 Perreca Electric
EC-210 -1,719 11/07/06 01/30/07 Perreca Electric
EC202 2,201 08/04/06 08/31/06 Perreca Elecgtric
EC203 3,550 08/25/06 10/12/06 Perreca Electric
EC205 0 08/25/06 10/12/06 Perreca Electric
EC206 15,214 08/25/06 10/12/06 Perreca Electric
SC-110 0 08/25/06 10/13/06 Landtek
SC-115 0 08/25/06 10/13/06 Landtek
SC-122 0 07/05/07 07/17/07 Landtek
SC-123 13,175 07/05/07 07/17/07 Landtek
SC-125 7,000 07/05/06 07/17/07 Landtek
SC-126 -4,400 07/05/07 07/17/07 Landtek
SC-128 0 07/05/07 07/17/07 Landtek
SC-129 4,000 07/05/07 07/17/07 Landtek
SC-130 700 07/05/07 / / Landtek
SC-131 5,900 07/05/07 07/17/07 Landtek
SC132 1,720 07/05/07 07/17/07 Landtek
Sc127 7,265 07/05/07 07/17/07 Landtek
05-0523 Reconstruction 0-006-016 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2 EC220 0 03/06/07 04/03/07 Fanshawe Inc
2 PC402 0 03/06/07 03/13/07 Pearl River Plumbing
2-EC 235 5,234 02/28/08 04/15/08 FANSHAWE
2-EC 236 651 02/28/08 04/15/08 FANSHAWE
2-EC 237 835 02/28/08 04/15/08 FANSHAWE
2-EC 241 1,900 02/28/08 04/15/08 FANSHAWE
2-EC 242 7,900 02/28/08 04/15/08 FANSHAWE
2-EC 243 6,292 02/28/08 04/15/08 FANSHAWE
2-EC-244 3,414 03/17/08 08/06/08 FANSHAWE, INC.
2-GC-157 85,298 10/05/07 11/08/07 FOURMAN CONSTRUCTION INC.
2-GC-158 55,030 10/05/07 11/08/07 FOURMAN CONSTRUCTION INC.
2-GC-159 2,006 10/05/07 11/08/07 FOURMAN CONSTRUCTION INC.
2-GC-162 6,208 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-163 3,689 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-164 23,024 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-168 15,000 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-169 -2,023 03/17/08 03/31/08 FOURMEN CONSTRUCTION INC.
2-GC-170 -1,600 03/17/08 03/31/08 FOURMEN CONSTRUCTION INC.
2-GC-171 -4,793 03/17/08 03/31/08 FOURMEN CONSTRUCTION INC.
2-MC-315 -2,980 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-316 1,532 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-317 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-318 2,198 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-320 -436 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-322 3,085 02/28/08 04/15/08 PEARL RIVER PLUMBING & HEATING
2-MC-324 2,401 03/17/08 08/06/08 PEARL RIVER PLUMBING, HEATING & E
2-PC-406 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-408 41,224 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-409 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-410 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-411 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-414 1,926 06/02/08 09/29/08 Pearl River Plumbing
2-PC-415 0 06/02/08 02/12/09 Pearl River Plumbing Heating & Elec
2EC 204 0 03/06/07 04/03/07 Fanshawe Inc
2EC 205 0 03/06/07 04/03/07 Fanshawe Inc
2EC 206 0 03/06/07 04/03/07 Fanshawe Inc
2EC 207 0 03/06/07 04/03/07 Fanshawe Inc
2EC 208 0 03/06/07 04/03/07 Fanshawe Inc
2EC 209 0 03/06/07 04/03/07 Fanshawe Inc
2EC 210 0 03/06/07 04/03/07 Fanshawe Inc
2EC 211 -12,481 03/06/07 04/03/07 Fanshwe Inc
2EC 212 0 03/06/07 04/03/07 Fanshwe Inc
2EC 213 0 03/06/07 04/03/07 Fanshwe Inc
2EC 214 0 04/06/07 04/03/07 Fanshawe Inc
2EC 215 0 03/06/07 04/03/07 Fanshawe Inc
2EC 216 0 03/06/07 04/03/07 Fanshawe Inc
2EC 217 0 03/06/07 04/03/07 Fanshawe Inc
2EC 218 0 04/06/07 04/04/07 Fanshawe Inc
2EC 219 0 03/06/07 04/04/07 Fanshawe Inc
2EC 221 0 03/06/07 04/03/07 Fanshawe Inc
2EC-222 0 05/01/07 05/15/07 Fanshawe Inc
2EC-223 0 05/01/07 05/15/07 Fanshawe Inc
2EC-224 0 05/01/07 05/15/07 Fanshawe Inc
2EC-226 3,600 06/15/07 06/20/07 Fanshawe Inc
2EC-227 -4,565 06/15/07 06/20/07 Fanshawe Inc
2EC-228 7,471 06/15/07 06/20/07 Fanshawe Inc
2EC-229 85,825 06/15/07 06/20/07 Fanshawe Inc
2EC-230 -17,603 06/15/07 06/20/07 Fanshawe Inc
2EC-231 0 06/15/07 06/20/07 Fanshawe Inc
2EC-232 2,823 06/15/07 06/20/07 Fanshawe Inc
2GC-105 15,453 11/07/06 12/28/06 Fourmen Construction
2GC-106 6,171 11/07/06 12/28/06 Fourmen Construction
2GC-107 -111 05/29/07 06/20/07 Fourmen Construction
2GC-108 0 05/29/07 06/20/07 Fourmen Construction
2GC-109 0 05/29/07 06/20/07 Fourmen Construction
2GC-110 0 05/29/07 06/20/07 Fourmen Construction
2GC-111 -13,149 05/29/07 06/20/07 Fourmen Construction
2GC-112 0 05/29/07 06/20/07 Fourmen Construction
2GC-113 0 05/29/07 06/20/07 Fourmen Construction
2GC-114 0 05/29/07 06/20/07 Fourmen Construction
2GC-115 0 05/29/07 06/20/07 Fourmen Construction
2GC-116 0 05/29/07 06/20/07 Fourmen Construction
2GC-117 -47,593 05/29/07 06/20/07 Fourmen Construction
2GC-119 -2,473 05/29/07 06/20/07 Fourmen Construction
2GC-121 12,034 05/29/07 06/20/07 Fourmen Construction
2GC-122 -3,319 05/29/07 06/20/07 Fourmen Construction
2GC-123 0 05/29/07 06/20/07 Fourmen Construction
2GC-125 0 05/29/07 06/20/07 Fourmen Construction
2GC-126 0 05/29/07 06/20/07 Fourmen Construction
2GC-127 0 05/29/07 06/20/07 Fourmen Construction
2GC-128 0 05/29/07 06/20/07 Fourmen Construction
2GC-129 -16,656 05/29/07 06/20/07 Fourmen Construction
2GC-131 4,152 05/29/07 06/20/07 Fourmen Construction
2GC-132 0 05/29/07 06/20/07 Fourmen Construction
2GC-133 0 05/29/07 06/20/07 Fourmen Construction
2GC-134 0 05/29/07 06/20/07 Fourmen Construction
2GC-140 1,864 05/29/07 06/20/07 Fourmen Construction
2GC-141 1,425 05/29/07 06/20/07 Fourmen Construction
2GC-142 2,349 05/29/07 06/20/07 Fourmen Construction
2GC-143 6,991 05/29/07 06/20/07 Fourmen Construction
2GC-145 2,631 05/29/07 06/20/07 Fourmen Construction
2GC-148 34,536 05/29/07 06/20/07 Fourmen Construction
2GC-149 21,379 05/29/07 06/20/07 Fourmen Construction
2GC-151 5,482 05/29/07 06/20/07 Fourmen Construction
2GC-152 3,500 05/29/07 06/20/07 Fourmen Construction
2GC-153 2,429 05/29/07 06/20/07 Fourmen Construction
2GC-154 -5,000 06/15/07 06/20/07 Fourmen Construction
2GC-155 -9,900 06/15/07 06/20/07 Fourmen Construction
2GC-156 14,363 03/15/07 06/20/07 Fourmen Construction
2GC124 0 05/29/07 06/20/07 Fourmen Construction
2Gc-144 6,139 05/29/07 06/20/07 Fourmen Construction
2MC 305 0 03/06/07 03/13/07 Pearl River Plumbing
2MC 311 0 05/01/07 07/27/07 Pearl River Plumbing
2MC 312 0 05/01/07 07/27/07 Pearl River Plumbing
2MC306 0 03/06/07 03/13/07 Pearl River Plumbing
2MC307 0 03/06/07 03/13/07 Pearl River Plumbing
2MC308 0 04/06/07 03/13/07 Pearl River Plumbing
2MC313 0 05/01/07 07/27/07 Pearl River Plumbing
2PC 401 0 03/06/07 03/13/07 Pearl River Plumbing
2PC 403 0 03/06/07 03/13/07 Pearl River Plumbing
2PC 404 0 03/06/07 03/13/07 Pearl River Plumbing
07-0580 Reconstruction 0-006-017 10/18/07 *CO No.* Amount Disallowed Received Approved Contractor
GC X-001 8,139 03/17/08 03/31/08 TRITION CONSTRUCTION COMPANY
GC X-002 2,515 03/17/08 03/31/08 TRITION CONSTRUCTION COMPANY
08-0140 Reconstruction 0-006-018 08/19/08 NO CHANGE ORDERS ON ELECTRONIC FILE
09-0141 Reconstruction 0-006-019 11/20/09 NO CHANGE ORDERS ON ELECTRONIC FILE
09-1446 Reconstruction 0-006-020 06/14/10 *CO No.* Amount Disallowed Received Approved Contractor
001 7,630 08/25/11 09/14/11 AMB CONSTRUCTION
001-HS -13,475 07/08/11 09/15/11 AMB CONSTRUCTION INC
002 3,000 08/25/11 09/14/11 AMB CONSTRUCTION INC
003 15,180 08/25/11 09/14/11 AMB CONSTRUCTION INC
004 1,000 10/13/11 12/08/11 AMB CONSTRUCTION INC
005 7,600 10/13/11 12/08/11 AMB CONSTRUCTION INC
006 3,500 10/13/11 12/08/11 AMB CONSTRUCTION INC
007 4,920 01/20/12 04/17/12 AMB CONSTRUCTION INC
008 7,894 04/20/12 08/31/12 AMB CONSTRUCTION INC
02-2170FP Reconstruction 0-006-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Tappan Zee Elementary:
93-0802 Reconstruction 0-007-008 03/25/94 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0115 Additions and Alterations 0-007-009 10/30/98 *CO No.* Amount Disallowed Received Approved Contractor
2 16,100 11/19/99 01/16/03 Environcon LLC
97-0229 Reconstruction 0-007-010 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1432 Reconstruction 0-007-011 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0524 Additions and Alterations 0-007-012 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2-GC-130 -3,300 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-150 1,357 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-166 24,745 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-MC-310 14,804 05/01/07 07/27/07 Pearl River Plumbing, Heating& Ele.
2-MC-314 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-416 14,725 02/12/09 05/18/09 PEARL RIVER PLUMBING, HEATING & ELEC
09-0142 Reconstruction 0-007-014 11/20/09 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0808 Reconstruction 0-007-016 04/21/11 *CO No.* Amount Disallowed Received Approved Contractor
001 -14,071 04/20/12 10/19/12 WB CONTRACTING CORP
02-2166FP Reconstruction 0-007-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Palisades Elementary:
10-0809 Reconstruction 0-008-010 04/21/11 *CO No.* Amount Disallowed Received Approved Contractor
002 -16,113 04/20/12 10/19/12 WB CONTRACTING CORP
Cottage Lane Elementary:
98-0116 Additions and Alterations 0-010-008 10/30/98 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0230 Reconstruction 0-010-009 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1433 Reconstruction 0-010-010 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0525 Additions and Alterations 0-010-011 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2-EC 240 7,875 02/28/08 / / FANSHAWE
2-EC-233 -5,673 06/15/07 06/20/07 Fanshawe, Inc.
2-EC-234 2,151 06/15/07 06/20/07 Fanshawe, Inc.
2-EC-245 707 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-246 1,000 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-247 1,867 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-248 -2,500 03/17/08 08/06/08 FANSHAWE, INC.
2-GC-135 52,500 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-136 12,619 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-137 19,274 05/29/07 07/30/09 Fourmen Construction Inc.
2-GC-138 12,680 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-139 23,419 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-146 3,837 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-147 10,149 05/29/07 06/20/07 Fourmen Construction Inc.
2-GC-161 16,943 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-165 -4,824 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-167 27,984 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-MC 321 34,877 02/28/08 / / PEARL RIVER PLUMBING & HEATING
2-MC 323 45,888 02/28/08 / / PEARL RIVER PLUMBING & HEATING
2-MC-319 3,735 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-325 -2,988 03/17/08 08/06/08 PEARL RIVER PLUMBING, HEATING & E
2-MC-326 1,392 03/17/08 08/06/08 PEARL RIVER PLUMBING, HEATING & E
2-PC-405 571 10/05/07 11/09/07 Pearl River Plumbing,Heating &ELE
2-PC-407 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-412 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-413 2,312 06/02/08 09/29/08 Pearl River Plumbing
04-1075 Reconstruction 0-010-013 04/12/05 *CO No.* Amount Disallowed Received Approved Contractor
101A-080 -579 08/04/06 08/31/06 S and M Management
102A -1,082 08/04/06 08/31/06 S and M Management
103a 1,253 08/04/06 08/31/06 S and M Management
104 0 08/04/06 08/31/06 S and M Managment
106A 0 08/04/06 08/31/06 S and M managment
09-0143 Reconstruction 0-010-015 11/20/09 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0810 Reconstruction 0-010-016 04/21/11 *CO No.* Amount Disallowed Received Approved Contractor
001 -6,968 04/20/12 10/19/12 BBR CONTRACTING CORP
02-2168FP Reconstruction 0-010-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Greenbush Academy:
09-0144 Reconstruction 0-011-007 11/20/09 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0811 Reconstruction 0-011-008 04/21/11 *CO No.* Amount Disallowed Received Approved Contractor
001 -1,057 04/20/12 10/19/12 WB CONTRACTING CORP
William Schaefer Elementary:
98-0118 Additions and Alterations 0-012-005 10/30/98 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0231 Reconstruction 0-012-006 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1430 Reconstruction 0-012-007 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0526 Additions and Alterations 0-012-008 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2-EC 238 2,176 02/28/08 04/15/08 FANSHAWE
2-EC 239 2,840 02/28/08 04/15/08 FANSHAWE
2-EC-225 -360 05/01/07 05/15/07 Fanshawe, Inc.
2-GC-120 -12,034 05/29/07 06/20/07 Fourmen Construction, Inc.
2-GC-160 -29,519 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-MC-309 -16,391 05/01/07 07/27/07 Pearl River Plumbing,Heating Ele.
04-1076 Reconstruction 0-012-010 04/12/05 *CO No.* Amount Disallowed Received Approved Contractor
102B -1,083 08/04/06 08/31/06 S and M Management
103B 1,253 08/04/06 08/31/06 S and M Management
106B 0 08/04/06 08/31/06 S and M Management
108 6,475 08/04/06 08/31/06 S and M Managment
1afo109 0 08/04/06 09/06/06 S&M Management Inc.
q01B -579 08/04/06 08/31/06 S and M Management
09-0145 Reconstruction 0-012-011 11/20/09 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0812 Reconstruction 0-012-012 04/21/11 *CO No.* Amount Disallowed Received Approved Contractor
001 7,250 08/25/11 09/07/11 AMB CONSTRUCTION
002 10,000 08/25/11 09/07/11 AMB CONSTRUCTION INC
003 -3,241 04/30/12 10/19/12 AMB Construction, Inc
02-2169FP Reconstruction 0-012-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Middle School:
98-0520 Additions and Alterations 0-013-010 03/11/99 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0232 Reconstruction 0-013-011 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1434 Reconstruction 0-013-012 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0860 Reconstruction 0-013-013 03/05/01 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1160 Reconstruction 0-013-014 05/10/05 *CO No.* Amount Disallowed Received Approved Contractor
1BPC-401 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
1BPC-402 0 10/05/07 10/23/07 PEARL RIVER PLUMBING, HEATING & ELEC
1BPC-403 0 10/05/07 10/23/07 PEARL RIVER PLUMBING, HEATING & ELEC
1BPC-404 -649 10/05/07 10/23/07 PEARL RIVER PLUMBING, HEATING & ELEC
EC 221 2,649 03/06/07 03/23/07 Fanshawe Inc
EC 222 479 03/06/07 03/23/07 Fanshawe Inc
EC 223 463 03/06/07 03/23/07 Fanshawe Inc
EC 224 691 03/06/07 03/23/07 Fanshawe Inc
EC 225 432 03/06/07 03/23/07 Fanshawe Inc
EC 226 3,817 03/06/07 03/23/07 Fanshawe Inc
EC-208 0 08/04/06 08/25/06 Fansshawe
EC-217 1,237 08/25/06 10/13/06 Fanshawe, inc.
EC202 5,137 08/04/06 08/25/06 Fanshawe
EC203 -19,948 08/04/06 08/25/06 Fanshawe
EC206 0 08/04/06 08/25/06 Fanshawe
EC207 0 08/04/06 08/25/06 Fanshawe
EC209 0 3 08/25/06 10/13/06 Fanshawe
EC210 7,792 08/25/06 10/13/06 Fanshawe
EC213 0 08/25/06 / / Fanshawe
EC216 0 08/25/06 10/13/06 Fanshawe
EC218 1,639 08/25/06 10/13/06 Fanshawe
EC219 9,821 03/06/07 03/23/07 Fanshawe Inc
EC220 3,069 03/06/07 03/23/07 Fanshawe Inc
GC-113 18,687 08/04/06 08/25/06 Fourmen Construction
GC-115 3,994 08/04/06 08/25/06 Fourmen Construction
GC-116 4,165 08/04/06 08/25/06 Fourmen Construction
GC-117 0 08/04/06 08/25/06 Fourmen Construction
GC-122 0 08/04/06 08/25/06 Fourmen Construction
GC114 0 08/04/06 08/25/06 Fourmen Construction
GC118 0 08/25/06 10/13/06 Fourmen Construction
GC121 9,044 08/25/06 10/13/06 Fourmen Construction
GC123 0 08/25/06 10/13/06 Fourmen Construction
GC124 0 08/25/06 10/13/06 Fourmen Construction
GC125 9,911 08/25/06 10/13/06 Fourmen Construction
GC128 1,877 12/27/06 01/23/07 fourmen Construction
GC129 1,568 12/27/06 01/23/07 Fourmen Construction
MC-307 -2,000 05/11/07 05/14/07 David Kempton
MC301 -10,749 05/11/07 05/14/07 David Kempton Inc
MC302 -10,000 05/11/07 05/14/07 David Kempton
MC303 3,000 05/11/07 05/14/07 David Kempton
MC306 -5,000 05/11/07 05/14/07 David Kempton
04-1096 Reconstruction 0-013-017 04/12/05 *CO No.* Amount Disallowed Received Approved Contractor
101C-080 -579 08/04/06 12/18/06 S and M Management
102C -1,082 08/04/06 12/18/06 S and M Management
103C 1,253 08/04/06 12/18/06 S and M Managment
105 0 08/04/06 12/18/06 S and M Management
106C 0 08/04/06 12/18/06 S and M management
07-1076 Additions and Alterations 0-013-018 07/21/08 *CO No.* Amount Disallowed Received Approved Contractor
001 2,605 11/26/08 02/10/09 HVS ELECTRIC, LLC
001 29,500 11/26/08 01/30/12 THOMAS J. KEMPTON JR. INC.
001 2,000 11/26/08 02/16/09 MARQUISE CONSTRUCTION CORP
001 0 02/17/09 08/19/09 PEARL RIVER PLUMBING & HEATING
001 35,684 07/14/09 05/10/10 Pearl river plumbing
002 2,500 11/26/08 01/30/12 HVS ELECTRIC, LLC
002 1,165 01/07/09 02/26/09 THOMAS J. KEMPTON JR. INC.
002 1,624 01/07/09 04/10/09 MARQUISE CONSTRUCTION CORP.
002 -6,000 04/02/09 07/28/09 Pearl River Plumbing & Heating
003 3,484 02/17/09 04/10/09 MARQUISE CONSTRUCTION CORP.
003 46,500 02/17/09 04/10/09 THOMAS J. KEMPTON JR., INC.
003 17,750 02/17/09 04/10/09 HVS ELECTRIC, LLC
003 8,695 06/01/09 08/14/09 PEARL RIVER PLUMBING & HEATING
004 0 02/17/09 04/10/09 MARQUISE CONSTRUCTION CORP.
004 -1,165 02/17/09 04/23/09 THOMAS J. KEMPTON JR., INC.
004 811 02/17/09 04/10/09 HVS ELECTRIC, LLC
004 3,595 07/17/09 01/30/12 PEARL RIVER d/b/a BERTUSSI'S
005 22,000 04/09/09 04/10/09 Marquise Construction Corp
005 22,000 04/02/09 / / MARQUISE CONSTRUCTION CORP.
005 -10,501 06/01/09 08/14/09 THOMAS J KEMPTON JR INC
005 0 06/01/09 08/14/09 HVS ELECTRIC LLC
006 0 06/01/09 08/14/09 THOMAS J KEMPTON JR INC
006 -5,000 06/01/09 08/14/09 HVS ELECTRIC LLC
006 1,165 06/01/09 08/18/09 MARQUISE CONSTRUCTION CORP
007 -20,000 06/01/09 08/18/09 MARQUISE CONSTRUCTION CORP
007 -2,045 08/09/10 11/30/10 THOMAS J KEMPTON JR INC
008 6,674 06/01/09 08/18/09 MARQUISE CONSTRUCTION CORP
009 2,740 06/01/09 08/18/09 MARQUISE CONSTRUCTION CORP
010 2,957 06/01/09 08/18/09 MARQUISE CONSTRUCTION CORP
011 24,900 06/01/09 08/18/09 MARQUISE CONSTRUCTION CORP
012 -1,500 07/17/09 08/19/09 MARQUISE CONSTRUCTION CORP
013 -25,000 06/11/12 12/26/12 MARQUISE CONSTRUCTION CORP
09-0146 Reconstruction 0-013-019 11/20/09 NO CHANGE ORDERS ON ELECTRONIC FILE
09-1447 Reconstruction 0-013-020 06/14/10 *CO No.* Amount Disallowed Received Approved Contractor
002-MS -13,975 07/08/11 09/15/11 AMB CONSTRUCTION INC
02-2167FP Reconstruction 0-013-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Field House:
04-1479 New Construction 7-019-001 06/28/05 *CO No.* Amount Disallowed Received Approved Contractor
2-GC-101 -438 11/07/06 01/09/07 Fourmen Construction Inc.
NYACK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-04-03
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Valley Cottage Elementary:
01-0811 Reconstruction 0-001-004 03/27/02 *CO No.* Amount Disallowed Received Approved Contractor
01 1,950 09/04/02 10/21/02 Universal Construction
03-1502 Reconstruction 0-001-005 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0800 Reconstruction 0-001-007 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
08-1718 Reconstruction 0-001-008 06/22/09 *CO No.* Amount Disallowed Received Approved Contractor
01 4,180 03/12/10 06/01/10 BEST ROOFING OF NEW JERSEY INC
09-1358 Reconstruction 0-001-009 07/16/10 *CO No.* Amount Disallowed Received Approved Contractor
001 291,000 03/28/12 03/28/12 Arrow Steel Window Corp
002 78,700 07/27/12 04/22/13 ARROW STEEL WINDOW CORP
02-0347FP Reconstruction 0-001-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Nyack High School:
92-0199 Reconstruction 0-003-004 09/02/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0578 Reconstruction 0-003-005 01/04/95 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0158 Reconstruction 0-003-006 09/26/00 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0676 Reconstruction 0-003-007 12/05/02 *CO No.* Amount Disallowed Received Approved Contractor
H-1 524 05/23/03 06/05/03 David L. Kempton
H-2 1,200 05/23/03 06/05/03 David L. Kempton
H-3 262 05/23/03 06/05/03 David L. Kempton
H-4 3,487 05/23/03 06/05/03 David L. Kempton
H-5 106 05/23/03 06/05/03 David L. Kempton
H-6 942 05/23/03 06/05/03 David L. Kempton
H-7 4,741 05/23/03 06/05/03 David L. Kempton
H-8 5,306 05/23/03 06/05/03 David L. Kempton
02-2255 Reconstruction 0-003-008 05/27/03 *CO No.* Amount Disallowed Received Approved Contractor
R-1 -11,029 12/23/05 02/23/06 DME Construction Assoc
03-1194 Reconstruction 0-003-009 06/30/04 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 6,885 05/24/05 05/24/05 Fanshawe Inc
EC-02 14,933 12/23/05 02/23/06 Fanshawe
EC-03 6,960 12/23/05 01/19/06 Fanshawe
EC-04 13,290 12/23/05 01/19/06 Fanshawe Inc
EC-05 5,212 06/23/06 11/30/06 Fanshawe
EC-06 2,496 06/23/06 11/30/06 Fanshawe
EC-07 2,335 01/10/07 03/23/07 Fasnshaws Inc
GW-06 18,260 03/28/06 06/13/06 Holt Construction
GW-07 -7,994 10/08/08 03/19/09 HOLT CONSTRUCTION
GW-08 0 10/08/08 03/19/09 HOLT CONSTRUCTION
GW-09 -5,000 10/08/08 03/19/09 HOLT CONSTRUCTION
GW-1 12,691 12/23/05 05/24/06 Holt Construction
GW-2 10,096 12/23/05 02/23/06 Holt Construction
GW-3 5,900 12/23/05 02/23/06 Holt Construction
GW-4 6,445 12/23/05 02/23/06 Holt Construction
GW-5 4,955 12/23/05 02/23/06 Holt Construction
HC-01 15,900 05/24/05 05/24/05 David Kempton
HW-02 -6,850 06/23/06 03/09/07 David Kempton
HW-03 9,440 06/23/06 02/05/10 DAVID KEMPTON
HW-04 4,322 02/14/08 / / DAVID L KEMPTON
HW-04 4,322 09/09/08 07/08/09 David L. Kempton
MC-01 25,800 03/28/06 06/13/06 Milcon Construction
MC-02 30,133 03/28/06 06/13/06 Milcon Construction
SW-01 12,777 12/23/05 05/24/06 Ascape Landscape Construction
SW-02 3,932 12/23/05 02/23/06 ASCApe Landscape Construction
03-1503 Reconstruction 0-003-010 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0436 Reconstruction 0-003-011 02/02/11 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
0 / / / /
GC-01 2,000 01/30/12 12/04/12 Arrow Steel Window Corp.
GC-02 -590 01/30/12 12/04/12 Arrow Steel Window Company
02-0344 Reconstruction 0-003-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Nyack Jr. High School:
94-0476 Reconstruction 0-004-003 12/13/94 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1504 Reconstruction 0-004-004 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0103 Reconstruction 0-004-005 03/03/06 *CO No.* Amount Disallowed Received Approved Contractor
1 10,260 09/29/06 10/19/06 JMK enterprises
2 3,652 03/13/06 06/18/07 JMK Enterprises
3 28,542 01/16/08 01/23/08 JMK Enterprises
4 18,260 01/16/08 01/23/08 JMK Enterprises
07-0801 Reconstruction 0-004-008 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0345FP Reconstruction 0-004-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Hilltop Intermediate:
90-1667 Reconstruction 0-005-002 06/05/91 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1505 Reconstruction 0-005-004 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0802 Reconstruction 0-005-005 12/10/07 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 8,612 09/12/08 11/06/08 HVS Electric and Construction
EC-5 6,191 11/14/08 07/07/09 HVS ELECTRIC AND CONSTRUCTION
12-0512 Reconstruction 0-005-006 12/20/12 NO CHANGE ORDERS ON ELECTRONIC FILE
Liberty Elementary School:
01-0813 Reconstruction 0-006-006 03/27/02 *CO No.* Amount Disallowed Received Approved Contractor
1 13,500 09/04/02 10/21/02 Universal Construction
03-1506 Reconstruction 0-006-007 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0803 Reconstruction 0-006-008 12/10/07 *CO No.* Amount Disallowed Received Approved Contractor
EC-03 1,508 09/12/08 11/06/08 HVS Electric & Construction
08-1719 Reconstruction 0-006-009 06/22/09 NO CHANGE ORDERS ON ELECTRONIC FILE
11-1390 Reconstruction 0-006-010 06/14/12 *CO No.* Amount Disallowed Received Approved Contractor
GC-01 4,000 01/28/13 04/26/13 LORENCIN CONTRACTING CORP
02-0348FP Reconstruction 0-006-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Upper Nyack Elementary:
90-1668 Reconstruction 0-007-007 06/05/91 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0812 Reconstruction 0-007-009 03/27/02 *CO No.* Amount Disallowed Received Approved Contractor
1 2,100 09/04/02 10/21/02 Universal Construction
03-1507 Reconstruction 0-007-010 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0024 Reconstruction 0-007-011 07/12/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0804 Reconstruction 0-007-012 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0346FP Reconstruction 0-007-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
New High School:
03-1508 Reconstruction 0-021-003 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0805 Reconstruction 0-021-005 12/10/07 *CO No.* Amount Disallowed Received Approved Contractor
EC-02 2,761 09/12/08 11/06/08 HVS Electric & Construction
EC-04 1,243 09/12/08 11/06/08 HVS Electric & Construction
11-0927 Reconstruction 0-021-006 03/14/12 *CO No.* Amount Disallowed Received Approved Contractor
GC-01 -79,842 01/28/13 04/26/13 LORENCIN CONSTRUCTION CORP
District Wide:
91-1552 Reconstruction 7-999-002 07/14/92 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1740 Reconstruction 7-999-003 08/08/94 NO CHANGE ORDERS ON ELECTRONIC FILE
PEARL RIVER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-08-03
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Evans Park School:
91-0352 Reconstruction 0-002-003 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1191 Reconstruction 0-002-004 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1505 Reconstruction 0-002-005 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0841 Reconstruction 0-002-006 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0624 Additions and Alterations 0-002-008 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-04 3,240 01/23/08 04/02/08 FANSHAWE INC
08-0552 Reconstruction 0-002-009 03/03/09 NO CHANGE ORDERS ON ELECTRONIC FILE
09-1303 Reconstruction 0-002-010 12/02/10 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0727 Reconstruction 0-002-011 05/19/11 *CO No.* Amount Disallowed Received Approved Contractor
01-001 -5,073 11/26/12 / / PEARL RIVER P/H/E dba BERTUSSI'S
Lincoln Ave.Elementary School:
91-0353 Reconstruction 0-003-003 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1192 Reconstruction 0-003-005 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1504 Reconstruction 0-003-006 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0842 Reconstruction 0-003-007 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0625 Additions and Alterations 0-003-009 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-05 2,439 01/23/08 04/02/08 FANSHAWE INC
CO-EC-06 2,630 07/14/08 08/26/08 FANSHAWE, INC. DBA ROCKLAND ELECTRIC
EC-01 3,466 07/15/08 07/29/08 Richard Parker Electrical
EC-03 19,300 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
PC-12 3,608 05/18/09 09/22/09 PEARL RIVER PLUMBING HEATING & ELECT
03-1448 Reconstruction 0-003-010 06/01/04 *CO No.* Amount Disallowed Received Approved Contractor
Roof 01 61,565 05/24/06 06/23/06 Best roofing of new Jersey
Root 02 7,028 05/24/06 06/23/06 Best Roofing
09-1304 Reconstruction 0-003-011 12/02/10 NO CHANGE ORDERS ON ELECTRONIC FILE
Senior High School:
91-0354 Reconstruction 0-009-007 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1193 Reconstruction 0-009-009 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1502 Reconstruction 0-009-010 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0843 Reconstruction 0-009-011 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0478 Additions and Alterations 0-009-012 03/22/00 *CO No.* Amount Disallowed Received Approved Contractor
1 3,500 08/07/01 01/08/02 DeRosa Tennis Contractors
1 25,280 08/07/01 01/08/02 Key Interiors
1 31,000 10/16/01 03/15/02 Pearl River Plumbing
2 55,164 08/07/01 02/11/02 Key Interiors
3 18,500 08/07/01 02/21/02 Key Interiors
4 26,700 10/16/01 03/15/02 Key Interiors
E-1 21,500 07/31/01 03/28/02 Fanshawe
E-2 13,500 10/16/01 02/21/02 Fanshawe
02-2083 Reconstruction 0-009-013 05/01/03 *CO No.* Amount Disallowed Received Approved Contractor
1 85,972 85,972 09/17/03 09/22/03 W. Harris & Sons
04-0626 Additions and Alterations 0-009-014 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-01 977 01/23/08 04/02/08 FANSHAWE INC
CO-EC-17 7,639 03/27/09 07/03/09 Helmer-Cornin Construction,Inc
EC-04 5,279 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-05 19,664 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-06 19,800 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-09 2,751 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-10 365 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-13 178 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-14 1,900 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-15 1,697 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
GC-05 7,721 03/27/09 07/03/09 HELMER CRONIN CONSTRUCTION, INC.
GC-13 15,170 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-17 7,639 03/27/09 / / HELMER-CRONIN CONSTRUCTION, INC.
MC-01 19,674 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-02 12,841 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-03 10,132 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-06 19,380 10/29/07 01/25/08 Pearl River Plumbing,Heating & Elect
MC-09 14,667 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-10 19,674 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-17 13,536 10/29/07 01/28/08 PEARL RIVER PLUMBING HEATING
MC-18 14,037 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
MC-19 17,436 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
PC-05 1,072 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-06 2,344 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-07 524 05/18/09 07/30/09 PEARL RIVER HEATING
PC-09 1,802 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-11 362 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-13 19,829 05/18/09 09/22/09 PEARL RIVER PLUMB, HEAT & ELECT
PC-14 -1,060 05/18/09 09/22/09 PEARL RIVER PLUMB HEAT ELECT
PC-15 8,245 05/18/09 09/22/09 PEARL RIVER PLUMB HEAT ELECT
RC-03 10,323 07/31/07 08/20/07 Milcon Construction
RC-06 4,743 07/31/07 08/20/07 Milcon Construction
RC-08 10,998 07/31/07 08/20/07 Milcon Construction
RC-09 2,800 07/31/07 08/20/07 Milcon Construction
RC-10 -14,037 07/31/07 08/20/07 Milcon Construction Corp
SC-01 7,269 04/16/09 07/29/09 W. HARRIS & SON INC
SC-02 17,735 04/16/09 07/29/09 W. HARRIS & SON INC
SC-03 8,680 04/16/09 07/29/09 W. HARRIS & SON INC
SC-04 48,413 04/16/09 07/29/09 W. HARRIS & SON INC
SC-05 8,093 04/16/09 07/29/09 W. HARRIS & SON INC
SC-06 9,782 04/16/09 07/29/09 W. HARRIS & SON INC
SC-14 42,157 04/16/09 07/29/09 W. HARRIS & SON INC
SC-16 42,989 04/16/09 07/30/09 W. HARRIS & SON INC
SC-19 5,748 04/16/09 07/29/09 W. HARRIS & SON INC
03-1447 Reconstruction 0-009-015 06/01/04 NO CHANGE ORDERS ON ELECTRONIC FILE
08-1055 Reconstruction 0-009-016 06/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
09-1305 Reconstruction 0-009-017 12/02/10 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0728 Reconstruction 0-009-018 05/19/11 *CO No.* Amount Disallowed Received Approved Contractor
01-001 34,410 11/26/12 / / PEARL RIVER P/H/E dba BERTUSSI'S
11-0567 Reconstruction 0-009-019 04/09/12 *CO No.* Amount Disallowed Received Approved Contractor
01-001 -47,300 08/23/12 12/10/12 KEY INTERIORS LLC
01-002 10,196 09/28/12 02/15/13 KEY INTERIORS LLC
02-001 -29,200 07/19/12 01/15/13 PEARL RIVER P/H/E INC dba BERTUSSI'S
02-002 10,262 11/09/12 02/25/13 Pearl River Plumbing Heating & Elect
03-001 10,529 11/09/12 02/25/13 Pearl River Plumbing Heating & Elect
04-001 -21,000 09/18/12 01/08/13 HVS LLC ELECTRICAL CONSTRUCTION
04-002 9,661 09/28/12 / / HVS LLC ELECTRICAL CONSTRUCTION
Franklin Ave. Elementary:
91-0355 Reconstruction 0-010-002 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1503 Reconstruction 0-010-004 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0844 Reconstruction 0-010-005 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0479 Additions and Alterations 0-010-006 03/22/00 *CO No.* Amount Disallowed Received Approved Contractor
E-01 3,830 05/09/03 05/20/03 All Bright Electric
04-0627 Additions and Alterations 0-010-007 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-03 1,795 01/23/08 04/02/08 FANSHAWE INC
EC-07 2,630 07/15/08 07/29/08 Rockland Electric
EC-11 1,142 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
GC-06 13,013 03/27/09 07/03/09 HELMER CRONIN CONSTRUCTION, INC.
GC-10 18,064 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-15 16,687 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-16 9,264 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-18 13,707 06/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-19 15,372 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
MC-04 10,132 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-11 5,301 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-16 12,252 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
MC-17 13,536 10/29/07 / / Pearl River Plumbing, Heating & Elec
MC-21 18,033 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-22 18,033 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-23 6,099 10/29/07 01/25/08 Pearl River Plumbing, Heating & elec
PC-03 177 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-04 1,072 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-08 1,375 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
08-0553 Reconstruction 0-010-008 03/03/09 NO CHANGE ORDERS ON ELECTRONIC FILE
09-1306 Reconstruction 0-010-009 12/02/10 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0729 Reconstruction 0-010-010 05/19/11 NO CHANGE ORDERS ON ELECTRONIC FILE
Middle School:
91-0356 Reconstruction 0-011-004 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1194 Reconstruction 0-011-006 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1375 Reconstruction 0-011-007 05/15/95 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1500 Reconstruction 0-011-008 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0845 Reconstruction 0-011-009 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0480 Additions and Alterations 0-011-010 03/22/00 *CO No.* Amount Disallowed Received Approved Contractor
1 20,000 05/09/03 05/20/03 B&R Roofing
2 46,974 05/09/03 05/20/03 B&R Roofing
3 46,500 05/09/03 05/20/03 B&R Roofing
4 39,600 05/09/03 05/20/03 B&R Roofing
5 29,400 10/16/01 03/15/02 B&R Roofing
6 38,700 05/09/03 05/20/03 B&R Roofing
02-2082 Reconstruction 0-011-011 05/01/03 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0628 Additions and Alterations 0-011-012 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-02 1,300 01/23/08 04/02/08 FANSHAWE INC
CO-GC-05 7,721 04/16/09 07/29/09 HELMER-CRONIN CONSTRUCTION INC
EC-02 4,021 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-07 3,899 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-08 1,250 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
EC-12 716 03/27/09 07/03/09 ALL BRIGHT ELECTRIC
GC-01 7,094 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-02 10,557 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-03 17,296 03/27/09 07/03/09 HELMER CRONIN CONSTRUCTION, INC.
GC-04 2,408 03/27/09 07/03/09 HELMER CRONIN CONSTRUCTION, INC.
GC-07 19,998 03/27/09 07/03/09 HELMER CRONIN CONSTRUCTION, INC.
GC-07A 10,722 03/27/09 07/03/09 HELMER CRONIN CONSTRUCTION, INC.
GC-08 0 / / / /
GC-08 -2,762 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-09 1,309 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-11 4,388 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-12 -1,200 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
GC-14 647 03/27/09 07/03/09 HELMER-CRONIN CONSTRUCTION, INC.
MC-05 17,613 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-07 1,590 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-08 19,439 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-12 3,000 10/29/07 01/24/08 Pearl River Plumbing, Heating & elec
MC-13 3,000 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
MC-14 11,230 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
MC-15 18,536 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
MC-20 1,178 10/29/07 / / Pearl River Plumbing, Heating & Elec
PC-01 1,100 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
PC-10 969 05/18/09 07/30/09 PEARL RIVER PLUMBING HEATING
RC-04 2,300 07/31/07 08/20/07 Milcon Construction
RC-07 2,177 07/31/07 08/20/07 Milcon Construction
08-1056 Reconstruction 0-011-013 06/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0550 Reconstruction 0-011-014 12/15/08 *CO No.* Amount Disallowed Received Approved Contractor
CO-PC-01 -3,887 05/04/10 07/21/10 PEARL RIVER dba BERTUSSI'S
CO-RC-01 9,501 02/09/10 04/30/10 VMG GROUP
CO-RC-02 4,060 02/09/10 04/30/10 VMG GROUP
09-1307 Reconstruction 0-011-015 12/02/10 NO CHANGE ORDERS ON ELECTRONIC FILE
William St. Bldg. (Admin.):
95-0846 Reconstruction 1-001-004 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0623 Additions and Alterations 1-001-005 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
PC-02 10,153 05/18/09 09/22/09 PEARL RIVER PLUMB HEAT ELECT
RC-02 1,458 07/31/07 08/20/07 Milcon Construction
RC-05 -1,719 07/31/07 08/20/07 Milcon Construction
Nauraushaun Building:
91-0436 Reconstruction 3-004-002 06/22/92 NO CHANGE ORDERS ON ELECTRONIC FILE
90-1243 Reconstruction 3-004-003 04/24/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1501 Reconstruction 3-004-005 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0847 Reconstruction 3-004-006 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0629 Additions and Alterations 3-004-008 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
RC-01 3,697 07/31/07 08/20/07 Milcon Construction
SC-07 11,413 04/16/09 07/30/09 W. HARRIS & SON INC
SC-08 1,835 04/16/09 07/30/09 W. HARRIS & SON INC
SC-09 4,480 04/16/09 07/30/09 W. HARRIS & SON INC
SC-10 32,557 04/16/09 07/30/09 W. HARRIS & SON INC
SC-11 1,290 04/16/09 07/30/09 W. HARRIS & SON INC
SC-12 3,284 04/16/09 07/30/09 W. HARRIS & SON INC
SC-13 12,693 04/16/09 07/30/09 W. HARRIS & SON INC
SC-15 14,603 04/16/09 07/30/09 W. HARRIS & SON INC
SC-17 47,024 04/16/09 07/30/09 W. HARRIS & SON INC
SC-18 -32,000 04/16/09 07/30/09 W. HARRIS & SON INC
09-1308 Reconstruction 3-004-009 12/02/10 NO CHANGE ORDERS ON ELECTRONIC FILE
RAMAPO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-01-06
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Suffern Middle School:
90-0693 Reconstruction 0-002-005 01/22/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0982 Reconstruction 0-002-006 04/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1144 Reconstruction 0-002-007 06/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1106 Reconstruction 0-002-010 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
96-0578 Reconstruction 0-002-011 12/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1266 Additions and Alterations 0-002-013 07/10/00 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
CCD EC-1 -8,628 02/07/03 06/10/03 All Bright Electric
CCD-1 -15,062 03/04/03 03/05/03 Fratello Const.
CCD-2 930 08/15/06 09/29/06 Fratello Construction
CCD-CIV1 -5,000 11/17/05 11/23/05 Hauser Brothers
CCD-GC-3 -8,628 01/14/03 03/05/03 Fratello Const.
CCD-GC4 -905 01/14/03 03/05/03 Fratello Const.
CCD-GC5 -12,324 01/14/03 03/05/03 Fratello Const.
CCD-GC6 -18,000 01/14/03 03/05/03 Fratello Const.
CCD-HC1 -6,000 02/06/03 02/13/03 Hauser Bros.
CCD-HC11 -50,000 11/17/05 11/23/05 Hauser Brothers Inc
CCD-HC2 -8,628 02/06/03 02/13/03 Hauser Bros.
CCD-PC-1 -8,628 03/11/03 05/23/03 David L. Kempton
E-1 14,880 06/21/02 07/12/02 All Bright Electric
E-2 15,482 06/21/02 07/12/02 All Bright Electric
E-3 -2,843 06/21/02 07/12/02 All Bright Electric
EC-10 -2,144 08/15/06 09/29/06 Allbright Electric
EC-11 4,500 09/09/02 12/09/02 All Bright Electric
EC-12 356 09/09/02 10/21/02 All Bright Electric
EC-13 10,679 09/09/02 12/09/02 All Bright Electric
EC-14 4,269 09/09/02 12/09/02 All Bright Electric
EC-14.1 4,270 02/06/03 02/13/03 All Bright Electric
EC-15 34,514 02/06/03 02/13/03 All Bright Electric
EC-16 4,106 02/07/03 02/13/03 All Bright Electric
EC-17 6,810 02/07/03 02/13/03 All Bright Electric
EC-18 2,820 02/06/03 02/13/03 All Bright Electric
EC-19 905 02/06/03 02/13/03 All Bright Electric
EC-20 4,415 02/06/03 02/13/03 All Bright Electric
EC-21 4,600 02/07/03 02/13/03 All Bright Electric
EC-22 11,000 02/07/03 02/13/03 All Bright Electric
EC-23 2,945 02/06/03 02/13/03 All Bright Electric
EC-24 9,606 02/06/03 02/13/03 All Bright Electric
EC-25 2,826 02/06/03 02/13/03 All Bright Electric
EC-26 -1,186 02/07/03 02/13/03 All Bright Electric
EC-27 2,772 02/06/03 02/13/03 All Bright Electric
EC-28 -65,000 05/16/03 06/03/03 All Bright Electric
EC-29 8,025 03/04/03 05/23/03 All Bright Electric
EC-30 5,160 03/04/03 05/23/03 All Bright Electric
EC-31 2,628 03/04/03 05/23/03 All Bright Electric
EC-32 3,277 03/04/03 05/23/03 All Bright Electric
EC-33 569 03/04/03 05/23/03 All Bright Electric
EC-34 2,900 03/04/03 05/23/03 All Bright Electric
EC-35 -10,000 05/16/03 / / All Bright Electric
EC-35 -10,000 11/17/05 11/23/05 Aubright electric
EC-36 2,814 05/16/03 06/03/03 All Bright Electric
EC-37 1,587 05/16/03 06/03/03 All Bright Electric
EC-38 998 05/16/03 06/03/03 All Bright Electric
EC-39 4,500 05/16/03 06/03/03 All Bright Electric
EC-4 982 09/09/02 12/09/02 All Bright Electric
EC-40 9,100 05/16/03 06/03/03 All Bright Electric
EC-41 2,782 05/27/03 06/10/03 All Bright Electric
EC-42 3,570 05/27/03 06/10/03 All Bright Electric
EC-43 301 05/27/03 06/10/03 All Bright Electric
EC-44 1,914 05/27/03 06/10/03 All Bright Electric
EC-45 646 05/27/03 06/10/03 All Bright Electric
EC-46 5,000 05/27/03 06/10/03 All Bright Electric
EC-5 3,650 09/09/02 12/09/02 All Bright Electric
EC-6 3,386 09/09/02 12/09/02 All Bright Electric
EC-7 11,900 09/09/02 12/09/02 All Bright Electric
EC-8 -3,648 09/09/02 10/21/02 All Bright Electric
EC-9 1,028 09/09/02 12/09/02 All Bright Electric
GC-10 2,050 06/17/02 07/10/02 Fratello Const.
GC-11 2,875 06/17/02 07/10/02 Fratello Const.
GC-12 2,950 06/17/02 07/10/02 Fratello Const.
GC-13 460 06/17/02 07/10/02 Fratello Const.
GC-14 1,075 06/17/02 07/10/02 Fratello Const.
GC-16 1,300 06/17/02 07/10/02 Fratello Const.
GC-17 6,632 06/17/02 07/10/02 Fratello Const.
GC-18 2,047 06/17/02 07/10/02 Fratello Const.
GC-19 17,475 01/14/03 02/05/03 Fratello Const.
GC-21 633 08/15/06 09/29/06 Fratello Construction
GC-22 15,000 08/15/06 09/29/06 Fratello Construction
GC-23 12,375 01/14/03 02/05/03 Thomas Management Services
GC-25 703 09/27/02 11/01/02 Fratello Const.
GC-26 -356 09/27/02 11/01/02 Fratello Const.
GC-27 1,200 09/27/02 11/01/02 Fratello Const.
GC-28 12,698 01/14/03 02/05/03 Thomas Management Services
GC-29 9,905 01/14/03 02/05/03 Thomas Management Services
GC-31 2,871 01/14/03 02/05/03 Thomas Management Services
GC-32 2,992 01/14/03 02/05/03 Thomas Management Services
GC-33 1,316 01/14/03 02/05/03 Thomas Management Services
GC-34 9,978 01/14/03 02/05/03 Thomas Management Services
GC-35 -2,700 01/14/03 02/05/03 Thomas Management Services
GC-36 2,798 01/14/03 02/05/03 Thomas Management Services
GC-37 4,340 01/14/03 02/05/03 Thomas Management Services
GC-38 2,402 01/14/03 02/05/03 Thomas Management Services
GC-39 1,642 01/14/03 02/05/03 Thomas Management Services
GC-40 1,988 01/14/03 02/05/03 Thomas Management Services
GC-41 1,818 01/14/03 01/23/03 Fratello Const.
GC-42 1,584 01/14/03 01/23/03 Fratello Const.
GC-43 1,429 01/14/03 01/23/03 Fratello Const.
GC-44 11,593 01/14/03 01/23/03 Fratello Const.
GC-45 1,642 01/14/03 01/23/03 Fratello Const.
GC-46 3,402 01/14/03 01/23/03 Fratello Const.
GC-47 2,815 01/14/03 01/23/03 Fratello Const.
GC-48 -1,500 08/15/06 09/29/06 Fratello Construction
GC-50 1,321 01/14/03 01/23/03 Fratello Const.
GC-51 -7,540 01/14/03 01/23/03 Fratello Const.
GC-52 1,276 01/14/03 01/23/03 Fratello Const.
GC-53 -6,546 01/14/03 01/23/03 Fratello Const.
GC-54 -441 01/14/03 02/05/03 Thomas Management Services
GC-55 3,200 02/19/03 02/19/03 Fratello Const.
GC-57 14,659 02/19/03 02/19/03 Fratello Const.
GC-58 1,408 02/19/03 02/19/03 Fratello Const.
GC-59 28,000 02/19/03 02/19/03 Fratello Const.
GC-60 7,200 02/19/03 02/19/03 Fratello Const.
GC-61 6,493 11/17/05 12/06/05 Fratello Construction
GC-62 3,399 02/19/03 02/19/03 Fratello Const.
GC-63 5,496 08/15/06 09/29/06 Fratello Construction
GC-64 25,176 03/24/03 03/28/03 Fratello Const.
GC-65 -130,000 3 08/15/06 09/29/06 Fratello Construction
GC-66 4,250 03/04/03 12/06/05 Fratello Const.
GC-66 4,250 11/17/05 / / Fratello Construction
GC-67 -19,609 03/04/03 03/19/03 Fratello Const.
GC-68 660 11/17/05 12/06/05 Fratello Construction Corp
GC-69 821 03/04/03 03/19/03 Fratello Const.
GC-7 24,000 06/17/02 / / Fratello Const.
GC-7 24,000 11/17/05 12/06/05 Fratello Construction
GC-70 706 03/04/03 03/19/03 Fratello Const.
GC-71 8,597 03/04/03 03/19/03 Fratello Const.
GC-72 2,076 03/04/03 03/19/03 Fratello Const.
GC-73 786 03/04/03 03/19/03 Fratello Const.
GC-74 877 03/04/03 03/19/03 Fratello Const.
GC-75 2,000 03/04/03 03/19/03 Fratello Const.
GC-76 1,500 03/04/03 03/19/03 Fratello Const.
GC-77 -1,562 03/11/03 03/19/03 Fratello Const.
GC-78 854 03/11/03 03/19/03 Fratello Const.
GC-79 1,300 03/11/03 03/28/03 Fratello Const.
GC-8 3,000 06/17/02 07/10/02 Fratello Const.
GC-80 -8,628 09/21/04 10/01/04 Fratello Const.
GC-81 -905 09/21/04 10/01/04 Fratello Const.
GC-82 -15,062 09/21/04 10/01/04 Fratello Const.
GC-83 -12,325 09/21/04 10/01/04 Fratello Const.
GC-84 -18,000 09/21/04 10/01/04 Fratello Const.
GC-85 5,496 09/21/04 10/01/04 Fratello Const.
GC-86 -5,496 09/21/04 10/01/04 Fratello Const.
GC-87 -1,500 09/21/04 10/01/04 Fratello Const.
GC-88 -11,900 09/21/04 10/01/04 Fratello Const.
GC-89 35,899 09/21/04 10/01/04 Fratello Const.
GC-9 615 06/17/02 07/10/02 Fratello Const.
GC-90 7,957 09/21/04 10/01/04 Fratello Const.
GC-91 1,379 09/21/04 10/01/04 Fratello Const.
GC-92 27,267 09/21/04 10/01/04 Fratello Const.
GC-93 4,399 09/21/04 10/01/04 Fratello Const.
GC-94 12,390 09/21/04 10/01/04 Fratello Const.
GC-95 2,240 09/21/04 10/01/04 Fratello Const.
GC-96 37,163 09/21/04 10/01/04 Fratello Const.
GC-97 12,122 09/21/04 10/01/04 Fratello Const.
GC-98 27,130 09/21/04 10/01/04 Fratello Const.
GC-99 12,122 09/21/04 10/01/04 Fratello Const.
GC25A 11,385 08/15/06 09/29/06 Fratello Construction
H-1 6,334 06/17/02 07/10/02 Hauser Bros.
H-2 15,861 06/17/02 06/30/06 Hauser Bros.
HC-10 5,383 02/06/03 02/13/03 Fratello Const.
HC-13 2,513 05/16/03 05/27/03 Hauser Bros.
HC-14 20,477 05/16/03 05/27/03 Hauser Bros.
HC-15 2,505 05/16/03 05/27/03 Hauser Bros.
HC-16 3,239 05/16/03 05/27/03 Hauser Bros.
HC-17 3,366 05/16/03 05/27/03 Hauser Bros.
HC-18 9,368 05/16/03 05/27/03 Hauser Bros.
HC-19 6,458 05/16/03 05/27/03 Hauser Bros.
HC-20 6,627 05/16/03 05/27/03 Hauser Bros.
HC-21 2,929 05/16/03 05/27/03 Hauser Bros.
HC-22 8,910 05/16/03 05/27/03 Hauser Bros.
HC-23 1,583 12/12/03 01/13/04 Hauser Bros.
HC-24 1,487 12/12/03 01/13/04 Hauser Bros.
HC-25 5,780 12/12/03 01/13/04 Hauser Bros.
HC-26 5,943 12/12/03 01/13/04 Hauser Bros.
HC-3 1,029 09/09/02 10/21/02 Hauser Bros.
HC-4 -1,145 09/09/02 12/09/02 Hauser Bros.
HC-5 14,273 09/09/02 12/09/02 Hauser Bros.
HC-6 3,142 09/09/02 12/09/02 Hauser Bros.
HC-7 2,671 09/09/02 12/09/02 Hauser Bros.
HC-8 12,889 09/09/02 02/13/03 Hauser Bros.
HC-9 3,381 02/06/03 02/13/03 Hauser Bros.
KE-2 -950 / / 12/06/05 BRC COMMERCIAL KITCHENS CORP.
KE-3 4,760 11/17/05 12/06/05 BRC Commercial Kitchens
KE1 2,770 11/20/03 11/24/03 BRC Commercial Kitchens
MS-1 2,444 05/20/02 06/04/02 Fratello Const.
MS-2 958 05/20/02 06/04/02 Fratello Const.
MS-3 5,964 05/20/02 06/04/02 Fratello Const.
MS-4 1,567 05/20/02 06/04/02 Fratello Const.
MS-5 11,860 05/20/02 06/04/02 Fratello Const.
MS-6 2,018 05/20/02 06/04/02 Fratello Const.
MS-P1 1,204 03/11/03 03/19/03 David L.Kempton
PC-10 12,220 05/16/03 06/03/03 David L.Kempton
PC-2 -5,500 03/11/03 03/19/03 David L.Kempton
PC-3 -1,710 03/11/03 03/19/03 David L.Kempton
PC-4 17,600 03/11/03 03/19/03 David L. Kempton
PC-5 4,350 03/11/03 03/19/03 David L. Kempton
PC-6 5,091 03/11/03 03/19/03 David L. Kempton
PC-7 3,766 03/11/03 03/19/03 David L. Kempton
PC-8 1,254 03/11/03 03/19/03 David L. Kempton
PC-9 -25,000 08/15/06 09/29/06 David Kempton
00-0353 Reconstruction 0-002-014 11/14/00 *CO No.* Amount Disallowed Received Approved Contractor
1 3,466 01/10/02 03/13/02 BML Stage Lighting
2 936 02/19/02 03/29/02 BML Stage Lighting
00-0243 Reconstruction 0-002-015 11/08/00 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0609 Reconstruction 0-002-016 03/25/02 *CO No.* Amount Disallowed Received Approved Contractor
01 3,850 11/12/02 11/13/02 Profex, Inc.
02 720 11/12/02 11/13/02 Profex, Inc.
02-2242 Reconstruction 0-002-017 10/06/03 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1031 Reconstruction 0-002-018 05/20/04 *CO No.* Amount Disallowed Received Approved Contractor
EC-001 2,254 10/27/06 12/18/06 Fanshawe
M-001 -510 05/15/07 08/28/07 Pearl River Plumbing heating
04-0462 Additions and Alterations 0-002-019 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
001 -2,100 04/26/10 05/11/10 KOKO CONTRACTING, INC.
1 -1,866 04/16/07 08/28/07 Eagle Electric
1 51,000 12/19/07 04/03/08 THE LANDTEK GROUP,INC
1 -51,000 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
10 1,200 12/19/07 04/03/08 THE LANDTEK GROUP,INC
10 1,200 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
11 -8,000 01/08/08 04/04/08 THE LANDTEK GROUP, INCOPRATED
2 180,000 12/19/07 04/03/08 THE LANDTEK GROUP,INC
2 180,000 12/19/07 04/03/08 THE LAND TEK GROUP, INC.
3 13,500 12/19/07 04/03/08 THE LANDTEK GROUP,INC
3 13,500 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
4 4,500 12/19/07 04/03/08 THE LANDTEK GROUP,INC
4 4,500 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
5 6,890 12/19/07 04/03/08 THE LANDTEK GROUP,INC
5 6,890 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
6 7,500 12/19/07 04/03/08 THE LANDTEK GROUP,INC
6 7,500 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
7 2,750 12/19/07 04/03/08 THE LANDTEK GROUP,INC
7 2,750 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
8 4,600 12/19/07 04/03/08 THE LANDTEK GROUP,INC
8 4,600 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
9 3,200 12/19/07 04/03/08 THE LANDTEK GROUP,INC
9 3,200 12/19/07 04/03/08 THE LANDTEK GROUP, INC.
AACO-006 17,927 12/24/07 02/23/08 FOUR STRONG BUILDERS, INC
AC-002 13,800 11/25/05 12/06/05 Bojan Development
AC-003 5,800 11/25/05 12/06/05 bojan Development
AC-004 4,995 11/25/05 12/06/05 Bojan Development
AC-005 4,200 11/25/05 12/06/05 Bojan Development
AC-01 4,400 09/27/05 10/13/05 Bojan Development
EC-003 -1,274 02/09/07 08/15/07 Fanshawe Inc
EC-004 1,665 02/08/07 08/15/07 Fanshawe Inc
EC-005 8,500 02/08/07 08/15/07 Fanshawe Inc
GC-001 6,300 04/16/08 08/12/08 ADVANCED POLYMER SURFACING
GC-015 -68,389 01/07/08 08/06/08 Aark Contractors
M-002 4,218 04/20/07 08/15/07 Pearl River Plumbing
MC-013 -187 10/30/07 08/07/08 Pearl River Plumbing
05-0353 Reconstruction 0-002-020 03/30/06 *CO No.* Amount Disallowed Received Approved Contractor
GC-001 6,300 01/30/08 03/19/08 advanceed polymer sufacing
GC-002 4,231 05/17/07 06/22/07 Lorencin Contracting Corp
07-0156 Reconstruction 0-002-021 09/05/07 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 2,440 04/07/08 04/11/08 EAGLE ELECTRIC
GC-01 -1,300 06/06/08 08/07/08 Lorencin Contracting corp
HVAC -01 -136 03/20/08 03/28/08 Pearl River Plumbing Heating & Elect
07-1441 Reconstruction 0-002-022 07/30/08 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 -2,500 04/10/09 / / FANSHAWE, INC.
HVAC-01 -30,716 03/30/09 01/30/12 PEARL RIVER PLUMBING, HEATING & ELEC
SR-02 -2,500 03/18/10 06/14/10 SYRACUSE SCENERY & STAGE LIGHTING CO
08-1004 Reconstruction 0-002-023 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
01-001 7,114 08/24/09 09/14/09 MACE CONTRACTING CORPORATION
01-005 3,287 01/12/10 04/02/10 MACE CONTRACTING CORPORATION
01-006MS -5,000 03/29/10 05/28/10 MACE CONTRACTING CORPORATION
06-001 6,705 11/15/10 11/17/10 NICKERSON CORPORATION
06-002 -11,300 11/15/10 11/17/10 NICKERSON CORPORATION
06-004 -1,600 01/23/12 04/13/12 NICKERSON CORPORATION
10-1150 Reconstruction 0-002-025 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0832 Additions and Alterations 0-002-026 06/26/12 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 2,191 03/13/13 / / FANSHAWE INC dba ROCKLAND ELECTRIC
GC-01 20,212 01/23/13 04/15/13 DM RESTORATION INC
PC-01 22,584 01/23/13 / / PEARL RIVER P/H/E INC dba BERTUSSI'S
02-0439FP Reconstruction 0-002-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
RP Connor Elementary School:
90-0694 Reconstruction 0-005-004 01/22/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0983 Reconstruction 0-005-005 04/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1145 Reconstruction 0-005-006 06/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1392 Reconstruction 0-005-007 06/14/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1368 Reconstruction 0-005-009 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1108 Reconstruction 0-005-010 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0947 Additions and Alterations 0-005-012 01/02/03 *CO No.* Amount Disallowed Received Approved Contractor
CC-011 -26,755 09/18/06 10/19/06 Parsippany Construction
CO-GC-95 -15,781 06/17/10 12/06/10 PARSIPPANY CONSTRUCTION CO INC
EC-003 -14,210 01/13/04 04/08/04 Mehl Elec.
EC-010 692 01/13/04 02/03/04 Mehl Elec.
EC-026 -6,342 10/18/04 12/21/04 Mehl Elec.
EC-042 54,624 01/14/05 02/01/05 Mehl Electric Company
EC-043 12,462 07/26/05 08/16/05 Mehl Electric Co
EC-074 -2,084 05/04/05 07/13/05 Mehl Electric Co
EC-075 1,750 04/15/05 / / Mehl Electric Co
EC-075 1,750 05/04/05 07/13/05 Mehl Electric Co
EC-076 511 04/15/05 04/26/05 Mehl Electric Co
EC-083 831 06/22/05 07/11/05 Mehl Electric Co
EC-084 637 06/22/05 07/11/05 Mehl Electric Co
EC-087 2,186 10/17/05 05/08/07 Mehl Electric Co
EC-094 22,478 10/17/05 05/08/07 Mehl Electric Co
EC-097 3,314 01/09/06 05/08/07 Mehl Electric Co
EC-77 2,933 04/15/05 04/26/05 Mehl Electric Co
GC-050 -14,040 08/15/05 08/31/05 Parsippany Construction Co
GC-051 -1,600 08/15/05 08/31/05 Parsippany Construction Co
GC-052 -1,386 08/15/05 08/31/05 Parsippany Construction Co
GC-053 -7,616 08/15/05 08/31/05 Parsippany Construction
GC-055 -1,000 08/15/05 08/31/05 Parsippany Construction Co
GC-098 22,735 05/20/10 05/25/10 PARSIPPANY CONSTRUCTION CO INC
GC-54 -6,175 08/15/05 08/31/05 Parsippany Construction Co
GC-56 -975 08/15/05 08/31/05 Parsippany Construction
HC-004 -2,091 01/14/05 02/08/05 Lawton Burns mechanical Contractors
HC-009 1,155 04/20/05 04/26/05 Lawton Burns Mechanical
HC-010 2,265 04/20/05 04/26/05 Lawton Burns Mechanical
HC-011 5,076 04/20/05 04/26/05 Lawton Burns Mechanical
HC-032 16,394 10/17/05 10/25/05 Lawton Burns mechanical
HC-036 -7,188 05/03/11 05/20/11 LAWTON & BURNS MECHANICAL CONTRACTOR
PC-002 19,920 01/29/04 03/03/04 Lawton and Burns Mech.
PC-003 3,838 01/29/04 04/13/04 Lawton and Burns Mech.
PC-010 53,900 08/27/04 09/24/04 Lawton and Burns Mech.
PC-012 -1,620 10/05/04 10/18/04 Lawton and Burns Mech.
PC-018 6,608 01/14/05 02/08/05 Lawton Burns Mechanical
PC-019 17,506 06/10/05 07/13/05 Lawton Burns Mechanical
PC-029 3,880 06/10/05 07/13/05 Lawton Burns Mechanical
RP-001 36,068 06/21/04 06/28/04 Parsippany Const.
02-2243 Reconstruction 0-005-013 10/06/03 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0463 Reconstruction 0-005-014 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
003 -3,000 04/26/10 05/11/10 KOKO CONTRACTING, INC.
AA-CO001 -3,200 12/24/07 02/23/08 FOUR STRONG BUILDERS, INC
CO-EC-11 -2,500 03/08/10 02/02/11 FANSHAWE INC dba ROCKLAND ELECTRIC
GC-009 -675 -675 07/16/07 01/25/08 AArk Contractors
GC-017 -4,720 01/07/08 08/06/08 Aark Contractors
GC-01RPC -3,544 03/29/10 06/01/10 FIELD PRO ENTERPRISES LLC
MC-010 -28,155 10/30/07 08/07/08 Pearl River Plumbing
PC-015 -288 10/30/07 / / Pearl River Plumbing
07-1442 Reconstruction 0-005-015 07/30/08 *CO No.* Amount Disallowed Received Approved Contractor
EC-02 915 10/29/09 12/24/09 FANSHAWE INC dba ROCKLAND ELECTRIC
EC-09 -750 12/03/09 01/30/12 FANSHAWE, INC. D/B/A ROCKLAND
HVAC2RPC -10,000 06/24/09 08/14/09 PEARL RIVER d/b/a BERTUSSI'S
HVAC7RPC -2,000 12/23/09 02/04/10 PEARL RIVER d/b/a BERTUSSI'S
PC-03 -833 12/07/09 02/04/10 JAC MECHANICAL SERVICES,IC
08-1005 Reconstruction 0-005-016 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
05-001 -4,968 12/21/09 01/12/10 HAYDEN BUILDING MAINTENANCE CORP
05-003 2,330 01/12/10 04/02/10 HAYDEN BUILDING MAINTENANCE CORP
10-1151 Reconstruction 0-005-017 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0435FP Reconstruction 0-005-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Sloatsburg Elementary:
90-0695 Reconstruction 0-007-006 01/22/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0984 Reconstruction 0-007-007 04/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1146 Reconstruction 0-007-008 06/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1109 Reconstruction 0-007-010 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0948 Additions and Alterations 0-007-012 01/02/03 *CO No.* Amount Disallowed Received Approved Contractor
AA-CO-05 13,246 12/24/07 02/23/08 FOUR STRONG BUILDERS INC
CC-012 -2,819 09/18/06 10/19/06 Parisippany Construction Co., INc.
CO-EC-01 15,300 08/25/06 05/25/10 ALL BRIGHT ELECTRIC
CO-GC-18 -29,445 01/07/08 08/06/08 AARK CONTRACTORS INC
CO-HC-01 -245 05/20/10 06/01/10 LAWTON & BURNS MECHANICAL CONTRACTOR
COGC096 -238 11/23/05 11/29/05 Parsippany Construction
EC-004 -24,230 01/13/04 01/26/04 Mehl Elec.
EC-007 688 01/13/04 01/26/04 Mehl Elec.
EC-008 5,570 01/13/04 02/03/04 Mehl Elec.
EC-011 392 01/13/04 02/03/04 Mehl Elec.
EC-014 2,135 01/13/04 02/03/04 Mehl Elec.
EC-078 -1,375 04/15/05 / / Mehl Electric Co
EC-078 -1,375 04/15/05 04/26/05 Mehl Electric Co
EC-079 831 06/22/05 07/11/05 Mehl Electric Co
GC-002 18,529 12/22/04 02/01/05 Parsippany Const.
GC-003 13,854 02/11/05 03/14/05 Parsippany Construction
GC-010 -138 07/16/07 08/07/07 AARK CONTRACTORS INC
GC-015 2,948 06/10/05 07/13/05 parsippany construction
GC-016 3,157 06/10/05 07/13/05 Parsippany Construction
GC-017 10,245 06/10/05 07/13/05 Parsippany construction
GC-018 2,482 06/10/05 07/13/05 Parsippany construction
GC-019 19,461 06/10/05 07/13/05 Parsippany Construction
GC-021 8,175 06/10/05 07/13/05 Parsippany Construction
GC-022 -2,016 06/10/05 07/13/05 Parsippany Construction
GC-023 650 06/10/05 07/13/05 parsippany Construction
GC-024 8,195 06/10/05 07/13/05 parsiappany construction
GC-025 19,500 06/10/05 07/13/05 parsippany Construction
GC-026 7,400 06/10/05 07/13/05 Parsippany Construction
GC-027 -1,000 06/10/05 07/13/05 Parsippany Construction
GC-028 -288 06/10/05 07/13/05 Parsippany Construction
GC-029 -2,259 08/02/05 08/16/05 Parsippany Construction
GC-030 -1,344 08/02/05 08/16/05 Parsippany Construction
GC-031 -7,344 08/02/05 08/16/05 Parsippany Conhstruction
GC-032 -1,000 08/02/05 08/16/05 Parsippany Construction
GC-033 -8,647 08/02/05 08/16/05 Parsippany Construction
GC-034 -1,885 08/02/05 08/16/05 Parsippany Construction
GC-035 655 08/02/05 08/16/05 Parsippany Construction
GC-036 4,805 08/02/05 08/16/05 Parsippany Construction
GC-037 422 08/02/05 08/15/05 Parsippany Construction
GC-038 1,429 08/02/05 08/15/05 Parsippany Construction
GC-039 1,932 08/15/05 08/31/05 Parsippany Construction
GC-040 2,135 08/15/05 08/31/05 Parsippany Construction
GC-044 -12,000 08/15/05 08/31/05 Parsippany Construction
GC-046 476 08/15/05 08/31/05 Parsippany Construction Co
GC-047 -510 08/15/05 08/31/05 Parsippany Construction Co
GC-049 3,434 08/15/05 08/31/05 Parsippany Construction
GC-41 450 08/15/05 08/31/05 Parsippany Construction Co
GC-42 1,245 08/15/05 08/31/05 Parsippany Construction
GC-43 -4,968 08/15/05 08/31/05 Parsippany Construction Co
GC-45 18,176 08/15/05 08/31/05 Parsippany Construction
GC-48 11,650 08/15/05 08/31/05 Parsippany Construction Co
GC020 5,315 06/10/05 07/13/05 parsippany construction
HC-005 5,877 04/20/05 04/26/05 Lawton Burns Mechanical
HC-018 6,653 04/20/05 04/26/05 Lawton Burns Mechanical
HC-019 6,445 04/20/05 04/26/05 Lawton Burns Mechanical
HC-020 854 04/20/05 04/26/05 Lawton Burns Mechanical
MC-005 -6,000 05/15/07 07/17/07 Pearl River Plumbing Heating
PC-013 19,204 10/05/04 12/10/04 Lawton & Burns Mech.
02-2244 Reconstruction 0-007-013 10/06/03 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0464 Reconstruction 0-007-014 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
005 -5,100 04/26/10 05/11/10 KOKO CONTRACTING, INC.
CO-01-SL -3,544 03/29/10 06/01/10 FIELD PRO ENTERPRISES LLC
EC-008 -1,245 01/07/08 / / Fanshawe Inc
MC-015 -798 10/30/07 08/07/08 Pearl River Plumbing
PC-016 0 10/30/07 01/16/08 Pearl River Plumbing
07-1443 Reconstruction 0-007-015 07/30/08 *CO No.* Amount Disallowed Received Approved Contractor
EC-03 1,687 10/29/09 12/24/09 FANSHAWE INC dba ROCKLAND ELECTRIC
EC-08 -750 12/03/09 01/30/12 FANSHAWE, INC. D/B/A ROCKLAND
HVAC-03 3,011 07/13/09 08/10/09 PEARL RIVER PLUMBING, HEATING
HVAC-04 -12,969 08/24/09 09/14/09 PEARL RIVER d/b/a BERTUSSI'S
HVAC-05 -344 08/14/09 01/30/12 PEARL RIVER d/b/a BERTUSSI'S
HVAC-06 1,659 12/23/09 02/04/10 PEARL RIVER dba BERTUSSI'S
HVAC02SL -10,000 06/24/09 08/14/09 PEARL RIVER d/b/a BERTUSSI'S
HVAC07SL 5,000 12/23/09 02/04/10 PEARL RIVER d/b/a BERTUSSI'S
PC-01 912 10/23/09 10/28/09 JAC MECHANICAL SERVICES, INC.
PC-02 -833 12/07/09 02/04/10 JAC MECHANICAL SERVICES,INC
08-1006 Reconstruction 0-007-016 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
03-001 7,451 12/07/09 02/05/10 PEARL RIVER PLUMBING
05-002 23,800 07/16/10 09/07/10 HAYDEN BUILDING MAINTENANCE CORP
05-004 -17,231 11/08/10 11/12/10 HAYDEN BUILDING MAINTENANCE CORP
10-0633 Reconstruction 0-007-017 01/20/11 *CO No.* Amount Disallowed Received Approved Contractor
GC-01 19,403 08/15/11 08/26/11 LORENCIN CONTRACTING CORP
GC-02 -4,900 10/12/11 12/06/11 LORENCIN CONTRACTING CORP
GC-03 3,256 10/12/11 12/28/11 LOURENCIN CONTRACTING CORP
10-1152 Reconstruction 0-007-018 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0437FP Reconstruction 0-007-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Cherry Lane Elementary:
90-0696 Reconstruction 0-011-004 01/22/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0985 Reconstruction 0-011-006 04/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0504 Reconstruction 0-011-007 01/09/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1107 Reconstruction 0-011-008 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
96-0019 Reconstruction 0-011-009 07/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0001 Reconstruction 0-011-012 07/11/97 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0949 Additions and Alterations 0-011-013 01/02/03 *CO No.* Amount Disallowed Received Approved Contractor
001 -6,000 04/26/10 05/11/10 KOKO CONTRACTING, INC.
AA-CO-04 -9,297 12/24/07 01/07/08 FOUR STRONG BUILDERS INC
CC-009 -20,000 09/18/06 10/19/06 Parsippany Construction
CO-PC-16 1,607 05/20/10 08/23/10 LAWTON & BURNS MECHANICAL CONTRACTOR
CO-PC-17 2,650 05/03/11 / / LAWTON & BURNS MECHANICAL CONTRACTOR
EC-001 -34,675 01/13/04 02/03/04 Mehl Elec.
EC-013 251 01/13/04 01/26/04 Mehl Elec.
EC-034 880 01/14/05 02/08/05 Mehl Electric Co
EC-063 -1,830 04/22/05 / / Mehl Electric Co
EC-063 -1,830 05/04/05 07/13/05 Mehl Electric Co
EC-064 2,333 04/22/05 / / Mehl Electric Co
EC-064 2,333 05/04/05 07/13/05 Mehl Electric Co
EC-065 544 04/22/05 / / Mehl Electric Co
EC-065 544 05/04/05 07/13/05 Mehl Electric Co
EC-066 3,063 04/22/05 / / Mehl Electric Co
EC-066 3,063 05/04/05 07/13/05 Mehl Electric Co
EC-067 2,431 04/22/05 / / Mehl Electric Co
EC-067 2,431 05/04/05 07/13/05 Mehl Electric Co
EC-068 730 04/15/05 / / Mehl Electric Company
EC-068 730 05/04/05 07/13/05 Mehl Electric Co
EC-069 7,635 04/15/05 04/26/05 Mehl Electric Co
EC-082 1,436 06/22/05 07/11/05 Mehl Electric Co
EC-095 1,341 10/17/05 10/25/05 Mehl Electric Co
GC-079 -2,083 05/20/10 05/25/10 PARSIPPANY CONSTRUCTION CO INC
GC-080 -800 08/15/05 08/31/05 Parsippany Construction
GC-081 -2,000 08/15/05 08/31/05 Parsippany Construction Co
GC-082 -2,450 08/15/05 08/31/05 Parsippany Construction Co
GC-083 -1,911 08/15/05 08/31/05 Parsippany Construction Co
GC-086 -1,834 08/15/05 08/31/05 Parsippany Construction
GC-088 -1,755 08/15/05 08/31/05 Parsippany Construction
GC-089 -1,560 08/15/05 08/31/05 Parsippany Construction Co
GC-84 -1,200 08/15/05 08/31/05 Parsippany Construction
GC-85 -13,365 08/15/05 08/31/05 Parsippany Construction
GC-87 -1,000 08/15/05 08/31/05 Parsippany Construction
GC-93 -68,374 11/23/05 11/25/05 Parsippany Construction
HC-006 9,850 04/20/05 04/26/05 Lawton Burns Mechanical
HC-024 1,261 04/20/05 04/26/05 Lawton Burns Mechanical
HC-025 -1,266 04/20/05 04/26/05 Lawton Burns Mechanical
HC-026 922 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
HC-027 2,576 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
HC-028 1,026 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
HC-035 -5,225 08/11/10 11/26/10 LAWTON & BURNS MECHANICAL CONTRACTOR
KC-001 -960 06/01/05 07/13/05 BRC Commerical Kitchens Corp
KC-002 1,908 06/01/05 07/13/05 BRC Commercial Kitchen Corp
M2-001 1,027 05/15/07 10/22/07 Pearl River Plumbing Heating
M2-002 0 04/24/07 10/22/07 Pearl River Plumbing Heating & Eleac
PC-011 10,365 10/05/04 10/18/04 Lawton and Burns Mech.
PC-014 9,965 01/14/05 02/08/05 Lawton Burns Mechanical Contractors
PC-030 13,685 06/10/05 07/13/05 Lawton Burns Mechanical
02-2245 Reconstruction 0-011-014 10/06/03 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0465 Reconstruction 0-011-015 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
3 4,995 08/13/08 09/29/08 FIELD PRO ENTERPRISES, LLC
CO-01-CL -10,440 03/29/10 06/01/10 FIELD PRO ENTERPRISES LLC
EC-010 -2,500 01/07/08 04/09/08 Fanshawe Inc
EC-011 -2,500 01/07/08 04/09/08 Fanshawe Inc
GC-004 -6,882 06/04/07 06/18/07 AARk Contractors
GC-007 -657 2,880 07/16/07 01/25/08 AArk Contractors
GC-016 -3,768 01/07/08 08/06/08 Aark Contractors
GC-021 -904 03/17/08 04/01/08 AARK CONTRACTORS, INC.
MC-001 49,992 09/11/06 04/11/07 Bertussi Plumbing
MC-009 563 10/30/07 01/16/08 Pearl River Plumbing
PC-003 3,067 12/19/06 04/11/07 Pearl River Plumbing
PC-020 -922 01/22/08 08/04/08 PEARLRIVER PLUMBING HEATING&ELECTRIC
Pc-001 893 12/19/06 01/24/07 Pearl River Plumbing
Pc-002 1,103 12/19/06 01/24/07 Pearl River Plumbing
07-1444 Reconstruction 0-011-016 07/30/08 *CO No.* Amount Disallowed Received Approved Contractor
EC-05 557 12/03/09 03/19/10 FANSHAWE, INC.
EC-06 348 12/03/09 01/30/12 FANSHAWE, INC. D/B/A ROCKLAND
EC-07 -750 12/03/09 01/30/12 FANSHAWE, INC. D/B/A ROCKLAND
EC-07 -750 03/18/10 06/14/10 FANSHAWE INC dba ROCKLAND ELECTRIC
HVAC02CL -3,000 06/24/09 08/14/09 PEARL RIVER d/b/a BERTUSSI'S
HVAC07CL -2,000 12/23/09 02/04/10 PEARL RIVER d/b/a BERTUSSI'S
08-0430 Reconstruction 0-011-017 02/18/09 *CO No.* Amount Disallowed Received Approved Contractor
EC-001 -1,520 08/14/09 09/03/09 HVS LLC
EC-002 6,490 10/23/09 10/28/09 HVS, LLC
GC-001 31,690 12/23/09 02/04/10 DOYLE CONTRACTING INC
HVAC-001 -2,515 08/24/09 09/14/09 PEARL RIVER P/H/E dba BERTUSSI'S
HVAC-002 -5,983 12/23/09 02/04/10 PEARL RIVER P/H/E dba BERTUSSI'S INC
HVAC-003 -6,016 12/23/09 02/09/10 PARK RIVER P/H/E dba BERTUSSI'S
PC-001 -146 08/24/09 09/14/09 JAC MECHANICAL SERVICES INC
PC-002 -894 10/23/09 10/28/09 JAC MECHANCIAL SERVICES, INC.
PC-003 1,640 10/29/09 12/24/09 JAC MECHANICAL SERVICES INC
10-1153 Reconstruction 0-011-018 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0434FP Reconstruction 0-011-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Montebello Elementary:
91-0986 Reconstruction 0-019-004 04/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1147 Reconstruction 0-019-005 06/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0505 Reconstruction 0-019-006 01/09/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1110 Reconstruction 0-019-007 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0531 Reconstruction 0-019-009 11/03/97 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0950 Additions and Alterations 0-019-010 01/02/03 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
002 13,055 10/05/04 10/18/04 Lawton and Burns Mech.
Cc-010 -6,012 09/18/06 10/19/06 Parsippany Construction
EC-002 -15,187 01/13/04 01/26/04 Mehl Elec.
EC-015 43,247 04/26/04 05/11/04 Mehl Elec.
EC-017 43,247 06/23/04 07/27/04 Mehl Elec.
EC-024 -1,619 10/18/04 12/21/04 Mehl Elec.
EC-033 -3,553 01/14/05 02/08/05 Mehl Eletric Ci
EC-057 420 05/04/05 07/13/05 Mehl Electric Co
EC-058 573 05/04/05 07/13/05 Mehl Electric Co
EC-059 2,726 05/04/05 07/13/05 Mehl Electric Co
EC-060 1,660 05/04/05 07/13/05 Mehl Electric Co
EC-061 5,213 05/04/05 07/13/05 Mehl Electric Company
EC-062 3,378 04/22/05 07/13/05 Mehl Electric Co
EC-085 815 06/22/05 07/11/05 Mehl Electric Co
EC-086 831 06/22/05 07/11/05 Mehl Electric Co
EC-098 4,275 01/09/06 05/08/07 Mehl Electric Co
EC-099 17,549 09/25/06 02/21/07 Mehl Electric
EC-16 1,054 01/13/04 01/26/04 Mehl Elec.
Ec-062 3,378 05/04/05 / / Mehl Electric Co
Ec-093 74,188 10/17/05 05/08/07 Mehl Electric Co
GC-072 -1,435 08/15/05 08/31/05 Parsippany Construction Co
GC-077 -2,793 08/15/05 08/31/05 Parsippany Construction
GC-078 -1,995 08/15/05 08/31/05 Parsippany Construction Co
GC-73 -47,821 08/15/05 08/31/05 Parsippany Construction Co
GC-74 600 08/15/05 08/31/05 Parsippany Construction Co
GC-75 -1,000 08/15/05 08/31/05 Parsippany Construction Co
GC-76 -288 08/15/05 08/31/05 Parsippany Construction
GC-79 -2,083 08/15/05 08/31/05 Parsippany Construction Co
Gc-094 -16,623 11/23/05 11/25/05 Parsippany Construction
HC-007 14,100 04/20/05 04/26/05 Lawton Burns Mechanical
HC-029 3,370 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
HC-030 485 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
HC-033 15,336 10/17/05 05/08/07 Lawton Burns Mechanical Contractors
HC-034 2,420 09/25/06 02/21/07 Lawton Burns Mechanical
PC-001 850 01/29/04 03/03/04 Lawton and Burns Mech.
PC-015 8,388 01/14/05 02/08/05 Lawton Burns Mechanical Contractors
PC-026 816 06/10/05 07/13/05 Lawton Burns Mechanical
02-2246 Reconstruction 0-019-011 10/06/03 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0466 Reconstruction 0-019-012 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
004 -12,600 04/26/10 05/11/10 KOKO CONTRACTING, INC.
AACO 003 7,900 12/24/07 02/23/08 FOUR STRONG BUILDERS INC
CO-PC021 2,090 06/06/08 03/06/09 pearl River Plumbingheating&Electric
EC-007 2,692 01/07/08 10/07/08 FANSHAWE, INC dba ROCKLAND ELECTRIC
GC-003 1,690 06/04/07 06/18/07 AArk Contractors
GC-008 9,922 9,922 07/16/07 01/25/08 AArk Contractors
GC-019 -858 01/07/08 08/06/08 Aark Contractors
GC-20 -8,000 03/17/08 03/16/10 Aark Contractors, Inc.
MC-002 22,353 02/16/07 08/06/10 Bertussi Plumbing
MC-003 881 02/16/07 08/15/07 Bertussi Plumbing
MC-004 2,387 02/16/07 08/15/07 Bertussi Plumbing
MC-011 4,121 01/30/08 08/04/08 pearl river plumbing & heating
PC-006 1,104 12/19/06 01/24/07 Pearl River
PC-007 904 12/19/06 01/24/07 Pearl River
PC-008 1,981 12/19/06 01/24/07 Pearl River Plumbing
Pc-005 1,832 12/19/06 01/30/07 Pearl River Plumbing
pc-019 125 01/22/08 08/04/08 PEARLRIVER PLUMBING HEATING&ELECTRIC
10-1154 Reconstruction 0-019-014 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0436FP Reconstruction 0-019-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Suffern High School:
90-0697 Reconstruction 0-020-007 01/22/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0987 Reconstruction 0-020-008 04/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1148 Reconstruction 0-020-009 06/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1393 Reconstruction 0-020-010 06/14/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1369 Reconstruction 0-020-011 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1104 Reconstruction 0-020-012 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
96-0519 Reconstruction 0-020-013 12/05/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0532 Reconstruction 0-020-015 11/03/97 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0951 Additions and Alterations 0-020-016 01/02/03 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
0 / / / /
001 -38,128 08/23/10 11/26/10 PEARL RIVER P/H/E INC dba BERTUSSI'S
CC-004 42,623 01/09/06 06/26/06 Parsippany Construction Co
CC-007 -4,787 02/22/06 07/21/06 Parsippany Construction
CC-008 -7,256 07/27/06 08/10/06 Parsippany Construction
CC-013 -905 09/18/06 10/19/06 Parsippany Construction
CO-CC-05 11,332 05/20/10 08/23/10 PARSIPPANY CONSTRUCTION CO INC
EC-005 -48,122 01/13/04 01/26/04 Mehl Elec.
EC-009 1,119 01/13/04 01/26/04 Mehl Elec.
EC-015 1,489 01/13/04 01/26/04 Mehl Elec.
EC-018 23,538 06/23/04 07/27/04 Mehl Elec.
EC-019 963 08/27/04 09/24/04 Mehl Elec.
EC-020 5,418 08/27/04 09/24/04 Mehl Elec.
EC-021 17,134 08/27/04 09/24/04 Mehl Elec.
EC-022 2,039 10/18/04 12/21/04 Mehl Elec.
EC-025 1,552 10/18/04 12/21/04 Mehl Elec.
EC-027 2,359 10/18/04 12/21/04 Mehl Elec.
EC-028 4,674 10/18/04 12/21/04 Mehl Elec.
EC-029 4,457 10/18/04 12/21/04 Mehl Elec.
EC-030 8,233 10/18/04 12/21/04 Mehl Elec.
EC-035 7,457 01/14/05 02/08/05 Mehl Electric Co
EC-036 4,722 01/14/05 02/08/05 Mehl Electric Co
EC-037 2,202 01/14/05 02/08/05 Mehl Electric Co
EC-038 1,974 01/14/05 02/08/05 Mehl Electric Co
EC-039 1,878 01/14/05 02/08/05 Mehl Electric Co
EC-040 104,393 01/14/05 02/08/05 Mehl Electric Co
EC-041 31,252 01/14/05 02/08/05 Mehl Electric Co
EC-044 4,739 05/04/05 07/13/05 Mehl Electric Co
EC-046 12,837 05/04/05 07/13/05 Mehl Electric Co
EC-047 7,398 05/04/05 07/13/05 Mehl Electric Co
EC-048 2,866 05/04/05 07/13/05 Mehl Electric Co
EC-049 1,032 05/04/05 07/13/05 Mehl Electric Co
EC-050 6,926 05/04/05 07/13/05 Mehl Electric Co
EC-051 4,201 05/04/05 07/13/05 Mehl Electric Co
EC-052 768 05/04/05 07/13/05 Mehl Electric Co
EC-053 4,175 05/04/05 07/13/05 Mehl Electric Co
EC-054 1,408 05/04/05 07/13/05 Mehl Electric Co
EC-055 3,468 05/04/05 07/13/05 Mehl Electric Co
EC-056 9,736 05/04/05 07/13/05 Mehl Electric Co
EC-081 1,299 06/22/05 07/11/05 Mehl Electric Co
EC-089 2,843 10/17/05 10/25/05 Mehl Electric Co
EC-090 2,362 10/17/05 10/25/05 Mehl Electric Co
EC-091 1,024 10/17/05 05/08/07 Mehl Electric Co
EC-096 5,444 01/09/06 05/08/07 Mehl Electric Co
EC-099 17,549 05/20/10 05/25/10 MEHL ELECTRIC COMPANY INC
EC-32 3,397 01/14/05 02/08/05 Mehl Electric Co
EC-45 1,968 05/04/05 07/13/05 Mehl Electric Co
EC-92 36,157 10/17/05 05/08/07 Mehl Elecric Co
Ec-049 1,032 04/22/05 / / Mehl Electric Co
GC-001 -36,504 06/10/05 07/13/05 Parsippany Construction
GC-002 -620 06/10/05 07/13/05 Parsippany Construction
GC-003 -12,000 06/10/05 07/13/05 Parsippany Construction
GC-004 -7,208 06/10/05 07/13/05 Parsippany construction
GC-005 -1,247 06/10/05 07/13/05 Parsippany construction
GC-006 -17,557 06/10/05 07/13/05 parsippany Construction
GC-007 -9,405 06/10/05 07/13/05 parsippany Construction
GC-008 -6,034 06/10/05 07/13/05 Parsippany Construction
GC-009 -2,000 06/10/05 07/13/05 Parsippany Construction
GC-010 -312 06/10/05 07/13/05 Parsippany Construction
GC-011 -1,000 06/10/05 07/13/05 parsippany Construction
GC-012 -10,000 06/10/05 07/13/05 parsippany Construction
GC-013 -6,500 06/10/05 07/13/05 parsippany Construction
GC-014 -1,400 06/10/05 07/13/05 parsippany Construction
GC-090 8,612 11/23/05 02/14/06 Parsippany Construction Co
GC-91 5,220 11/23/05 05/08/07 Parsippany Construction
GC-92 -2,859 01/09/06 06/26/06 Parsippany Construction Co
HC-008 34,800 04/20/05 04/26/05 Lawton Burns Mechanical
HC-012 5,280 04/20/05 04/26/05 Lawton Burns Mechanical
HC-013 12,936 04/20/05 04/26/05 Lawton Burns Mechanical
HC-014 3,612 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
HC-015 2,874 05/20/10 05/25/10 LAWTON & BURNS MECHANICAL CONTRACTOR
HC-016 687 04/20/05 04/26/05 Lawton Burns Mechanical
HC-017 7,974 04/20/05 04/26/05 Lawton Burns Mechanical
HC-031 56,877 04/20/05 04/26/05 Lawton Burns Mechanical Contractors
M-001 -1,102 05/15/07 10/22/07 Pearl River Plumbing Heating
PC-007 448 01/29/04 03/03/04 Lawton and Burns Mech.
PC-008 -15,250 01/29/04 03/12/04 Lawton and Burns Mech.
PC-009 821 01/29/04 03/03/04 Lawton and Burns Mech.
PC-020 -1,820 06/10/05 07/13/05 Lawton Burns Mechanical
PC-021 498 06/10/05 07/13/05 lawton Burns Mechanical
PC-022 1,523 06/10/05 07/13/05 Lawton Burns mechanical
PC-023 3,854 06/10/05 07/13/05 Lawton Burns Mechanical
PC-024 3,144 06/10/05 07/13/05 Lawton Burns Mechanical
PC-025 937 06/10/05 07/13/05 lawton Burns Mechanical
cc-06 3,406 02/22/06 07/21/06 Parsippany Construction
98-1689 Reconstruction 0-020-017 07/21/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1087 Reconstruction 0-020-018 04/28/00 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0496 Reconstruction 0-020-019 03/12/01 *CO No.* Amount Disallowed Received Approved Contractor
M-01 11,432 05/09/02 05/14/02 Joe Lombardo Plumbing
00-0352 Reconstruction 0-020-020 11/14/00 *CO No.* Amount Disallowed Received Approved Contractor
1 850 12/27/01 02/28/02 CES Corp.
1 788 01/10/02 03/13/02 BML Stage Lighting
2 495 12/27/01 02/28/02 CES Corp.
2 7,245 05/17/02 05/17/02 BML Stage Lighting
3 901 03/22/02 04/12/02 BML Stage Lighting
01-0831 Reconstruction 0-020-021 05/17/02 *CO No.* Amount Disallowed Received Approved Contractor
GC-1 -3,096 05/19/03 06/02/03 Empire Energy
S-01 21,950 01/24/03 01/28/03 Opti-Gro Division
S-02 1,350 04/17/03 05/07/03 Opti-Gro Division
03-0211 Reconstruction 0-020-022 02/18/04 *CO No.* Amount Disallowed Received Approved Contractor
01 21,232 12/06/04 01/03/05 Jones Turf Management
RC-001 67,325 67,325 11/17/05 Disapproved DME Construction Associates
04-0467 Additions and Alterations 0-020-023 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
002 1,200 04/26/10 05/11/10 KOKO CONTRACTING, INC.
AA-008 2,200 04/26/10 05/18/10 FOUR STING BUILDERS, INC.
AACO-007 12,333 12/24/07 02/23/08 FOUR STRONG BUILDERS, INC
CO-01 -5,000 03/29/10 06/01/10 PEARL RIVER P/H/E INC dba BERTUSSI'S
CO-EC-01 5,792 02/08/07 07/20/10 FANSHAWE INC dba ROCKLAND ELECTRIC
EC-001 2,160 10/27/05 12/07/05 Naber Electric
EC-001 5,792 02/08/07 08/15/07 Fanshawe
EC-002 14,451 10/18/06 04/23/07 naber Electric
EC-002 1,635 02/08/07 08/22/07 Fanshawe Inc
EC-004 2,024 10/18/06 12/18/06 Naber Electric
EC-006 4,922 01/07/07 10/07/08 FANSHAWE,INC. dba ROCKLAND ELECTRIC
Ec-003 3,656 10/18/06 12/18/06 Naber Electric
GC-001 17,660 12/06/05 08/08/06 Glomar Construction
GC-001 36 06/04/07 06/18/07 Aark Contractors
GC-002 10,642 12/06/05 08/08/06 Glomar Construction
GC-002 0 06/04/07 06/18/07 AARk Contractors
GC-003 3,450 10/11/06 10/19/06 Glomar Construction
GC-004 -77 10/27/06 02/21/07 Glomar Construction
GC-006 7,288 06/04/07 06/18/07 AARk Contractors
GC-011 23,783 23,783 07/16/07 01/25/08 AArk Contractors
GC-014 6,001 01/07/08 08/06/08 Aark Contractors
MC-005 13,071 03/15/07 08/06/10 Pearl River
MC-006 4,571 03/15/07 08/06/10 Pearl River Plumbing
MC-007 -14,914 03/15/07 08/06/10 Pearl River Plumbing
MC-008 -2,009 10/30/07 01/16/08 Pearl River Plumbing
MC-012 -711 10/30/07 01/16/08 Pearl River Plumbing
PC-001 -276 07/26/06 / / Norco
PC-002 -15,000 07/26/06 08/25/06 Norco
PC-004 6,013 07/26/06 08/25/06 Norco
PC-005 6,218 07/26/06 08/25/06 Norco
PC-006 956 07/26/06 08/25/06 Norco
PC-009 673 12/19/06 01/24/07 Pearl River Plumbing
PC-013 1,020 12/19/06 01/24/07 Pearl River
PC-014 1,353 12/19/06 01/24/07 Pearl River Plumbing
PC-017 3,109 10/30/07 08/07/08 Pearl River Plumbing
PC-11 623 12/19/06 01/30/07 Pearl River Plumbing
Pc-003 9,251 07/26/06 08/25/06 Norco
Pc-010 716 12/19/06 01/24/07 Pearl River Plumbing
Pc-012 700 12/19/06 01/24/07 Pearl river Plumbing
RC-001 67,325 03/08/10 05/11/10 DME CONSTRUCTION ASSOCIATES
RC-002 15,224 02/14/06 07/24/06 DME Construction
RC-003 11,930 02/14/06 07/24/06 DME Construction
RC-004 45,053 02/12/07 05/16/07 DME Construction
RC-5 15,456 03/29/10 06/01/10 DME CONSTRUCTION ASSOCIATION INC
05-0354 Reconstruction 0-020-024 03/30/06 *CO No.* Amount Disallowed Received Approved Contractor
GC001 2,833 05/17/07 06/22/07 Lorencin Contracting Corp
MC-001 2,526 03/17/08 03/31/08 PEARL RIVER PLUMBING HEATING & ELECT
06-0434 Reconstruction 0-020-025 03/26/07 *CO No.* Amount Disallowed Received Approved Contractor
GC-01 -76,000 -76,000 07/19/07 01/25/08 Lorencin Contracting Corp
PLUMB-02 -2,225 05/19/08 02/24/09 PEARL RIVER PLUMBING
Plumb 01 -6,000 07/19/07 08/28/07 Pearl River Plumbing
07-1445 Reconstruction 0-020-026 07/30/08 *CO No.* Amount Disallowed Received Approved Contractor
SR-01 -2,500 10/05/09 10/29/09 SYRACUSE SCENERY & STAGE LIGHTING CO
08-1007 Reconstruction 0-020-027 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
06-003 -10,000 11/15/10 11/17/10 NICKERSON CORPORATION
07-001 0 11/08/10 11/12/10 NICKERSON CORPORATION
10-1155 Reconstruction 0-020-028 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
11-0833 Additions and Alterations 0-020-029 06/26/12 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0440FP Reconstruction 0-020-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Viola Elementary:
94-0506 Reconstruction 0-026-006 01/09/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1105 Reconstruction 0-026-007 05/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0533 Reconstruction 0-026-009 11/03/97 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0952 Additions and Alterations 0-026-010 01/02/03 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
AA-CO-02 2,090 12/24/07 02/23/08 FOUR STRONG BUILDERS INC
CC-014 -10,906 09/18/06 10/19/06 Parsippany Construction
EC-006 -17,072 01/13/04 02/03/04 Mehl Elec.
EC-012 3,333 01/13/04 01/26/04 Mehl Elec.
EC-023 -284 10/18/04 12/21/04 Mehl Elec.
EC-070 7,458 04/15/05 04/26/05 Mehl Electric Co
EC-071 1,570 05/04/05 07/13/05 Mehl Electric Co
EC-072 1,409 05/04/05 07/13/05 Mehl Electric Co
EC-073 1,700 04/15/05 04/26/05 Mehl Electric
EC-080 1,549 06/22/05 07/11/05 Mehl Electric Co
EC-088 4,265 10/17/05 10/25/05 Mehl Electric Co
EC-31 49,328 10/18/04 12/21/04 Mehl Elec.
FT-001 4,435 01/05/07 01/19/07 American Petroleum
GC-057 -4,698 08/02/05 08/16/05 Parsippany Construction
GC-058 -2,520 08/02/05 05/08/07 Parsippany Construction
GC-059 -54,000 08/02/05 08/16/05 Parsippany Construction
GC-060 -8,170 08/02/05 08/16/05 Parsippany Construction
GC-061 -500 08/02/05 08/16/05 Parsippany Construction
GC-065 -1,246 08/02/05 08/16/05 Parsippany Construction
GC-066 -354 08/02/05 08/16/05 Parsippany Construction
GC-067 -245 08/02/05 08/16/05 Parsippany Construction
GC-069 -1,400 08/02/05 08/16/05 Parsippany Construction Co
GC-071 -1,000 08/02/05 08/16/05 Parsippany construction
GC-097 24,252 11/23/05 05/08/07 Parsippany Construction Co., Inc.
GC-62 -11,080 08/02/05 05/08/07 Parsippany Construction
GC-63 -3,768 08/02/05 08/16/05 Parsippany Construction
GC-64 -3,957 08/02/05 08/16/05 Parsippany Construction
GC-68 -488 08/02/05 08/16/05 Parsippany Construction
GC-70 -2,346 08/02/05 08/16/05 Parsippany Construction
HC-003 22,664 10/05/04 10/18/04 Lawton and Burns Mech.
HC-021 2,873 04/20/05 04/26/05 Lawton Burns Mechanical
HC-023 1,664 04/20/05 04/26/05 Lawton Burns Mechanical
HC-22 1,903 04/20/05 04/26/05 Lawton Burns Mechanical
PC-004 3,463 01/29/04 03/12/04 Lawton and Burns Mech.
PC-005 464 01/29/04 03/12/04 Lawton and Burns Mech.
PC-006 1,703 01/29/04 03/12/04 Lawton and Burns Mech.
PC-027 840 06/10/05 07/13/05 Lawton Burns Mechanical
PC-028 871 06/10/05 07/13/05 Lawton Burns Mechanical
02-2247 Reconstruction 0-026-011 10/06/03 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0468 Reconstruction 0-026-012 05/19/05 *CO No.* Amount Disallowed Received Approved Contractor
2 5,500 01/30/08 03/08/08 FIELD PRO ENTERPRISES, LLC
CO-01-V -6,404 03/29/10 06/01/10 FIELD PRO ENTERPRISES LLC
CO-PC022 876 06/06/08 03/06/09 Pearl RiverPlumbing heating&electric
EC-009 -423 01/07/08 08/12/08 FANSHAWE, INC DBA ROCKLAND ELECTRIC
GC-005 0 06/04/07 06/18/07 AARk Contractors
GC-012 0 08/16/07 08/23/07 Aark Contractors
GC-013 28,114 01/07/08 03/31/08 AARK CONTRACTORS, INC
MC-014 -7,520 10/30/07 01/16/08 Pearl River Plumbing
PC-004 700 12/19/06 01/24/07 Pearl River Plumbing
PC-018 14,597 01/22/08 08/12/08 PEARL RIVER PLUMBING HEATING & ELEC
07-1446 Reconstruction 0-026-014 07/30/08 *CO No.* Amount Disallowed Received Approved Contractor
EC-04 670 10/29/09 12/24/09 FANSHAWE INC dba ROCKLAND ELECTRIC
EC-10 -750 12/03/09 01/30/12 FANSHAWE, INC. D/B/A ROCKLAND
HVAC-07V -1,000 12/23/09 02/04/10 PEARL RIVER d/b/a BERTUSSI'S
HVAC02V -9,042 06/24/09 08/14/09 PEARL RIVER P/H/E
PC-04 -834 12/07/09 02/04/10 JAC MECHANICAL SERVICES,INC
10-1156 Reconstruction 0-026-015 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0438FP Reconstruction 0-026-FP1 12/24/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Airmont Elementary:
92-0161 Reconstruction 0-027-001 08/25/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-0263 Alterations 0-027-002 10/07/92 NO CHANGE ORDERS ON ELECTRONIC FILE
DISTRICTWIDE TECHNOLOGY WIRING:
94-1439 Reconstruction 0-999-001 06/09/95 NO CHANGE ORDERS ON ELECTRONIC FILE
Hillburn Administration Building:
90-0714 Reconstruction 1-006-005 01/24/91 NO CHANGE ORDERS ON ELECTRONIC FILE
10-0634 Reconstruction 1-006-008 01/20/11 *CO No.* Amount Disallowed Received Approved Contractor
SC-01 29,102 10/12/11 12/06/11 BEN CICCONE INC
10-1157 Reconstruction 1-006-009 08/26/11 NO CHANGE ORDERS ON ELECTRONIC FILE
Salt Storage Shed:
08-1008 New Construction 2-035-001 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
01 -29,400 02/11/11 03/01/11 DTM DEVELOPMENT LTD
Storage Building:
08-1009 New Construction 2-036-001 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
01-002 -12,857 08/24/09 09/14/09 MACE CONTRACTING CORPORATION
01-003 13,990 10/23/09 / / MACHE CONTRACTING CORPORATION
01-004 5,776 12/21/09 01/12/10 mace contracting corporation
01-006SB -50,000 03/29/10 05/28/10 MACE CONTRACTING CORPORATION
02-001SB -665 08/11/10 / / PEARL RIVER P/H/E INC dba BERTUSSI'S
03-002 -1,500 04/26/10 05/11/10 PEARL RIVER PLUMBING HEATING
04-001 4,358 12/21/09 01/12/10 FANSHAWE
04-002 1,136 12/21/09 01/12/10 FANSHAWE
Comfort Station:
06-1248 New Construction 7-032-001 07/20/07 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 1,450 09/05/08 02/27/09 PARKER ELECTRIC, INC.
EC-2 2,120 11/25/08 12/04/08 PARKER ELECTRIC, INC.
EC-3 1,985 11/25/08 12/04/08 PARKER ELECTRIC, INC.
GC-1 18,000 08/22/08 03/17/09 TURCO GOLF, INC.
PC-1 -1,400 09/23/08 10/30/08 JAC MECHANCIAL SERVICE
Press Box:
08-1010 New Construction 7-034-001 05/13/09 *CO No.* Amount Disallowed Received Approved Contractor
01-006PB -20,000 03/29/10 05/28/10 MACE CONTRACTING CORPORATION
02-001 -1,000 02/12/10 05/11/10 PEARL RIVER PLUMBING HEATING & ELECT
02-001PB -335 08/11/10 09/28/10 PEARL RIVER P/H/E INC dba BERTUSSI'S
04-003 -2,926 01/25/10 09/30/11 FANSHAWE INC dba ROCKLAND ELECTRIC
Districtwide:
99-1658 Reconstruction 7-999-002 06/12/00 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1721 Reconstruction 7-999-003 04/24/08 *CO No.* Amount Disallowed Received Approved Contractor
001 8,633 03/30/09 04/23/09 SECUIRTY INTEGRATIONS, INC.
EAST RAMAPO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-02-06
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Spring Valley Senior High:
91-0237 Reconstruction 0-003-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0217 Reconstruction 0-003-002 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1248 Reconstruction 0-003-004 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1206 Reconstruction 0-003-005 04/10/98 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0972 Reconstruction 0-003-006 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0705 Reconstruction 0-003-007 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0394 Reconstruction 0-003-008 02/15/00 *CO No.* Amount Disallowed Received Approved Contractor
1 12,946 03/22/02 04/18/02 Fanshawe Electric
98-1292 Reconstruction 0-003-009 04/26/99 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
1 -974 09/20/04 12/04/06 New York Power Aurthority
99-1232 Reconstruction 0-003-011 05/09/00 NO CHANGE ORDERS ON ELECTRONIC FILE
12-0623 Reconstruction 0-003-012 03/13/13 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0899 Reconstruction 0-003-013 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0368 Reconstruction 0-003-014 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1368 Reconstruction 0-003-015 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0419 Reconstruction 0-003-016 10/06/08 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0965 Reconstruction 0-003-017 05/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1574FP Reconstruction 0-003-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Admin. Bldg.(fmly S.Madison):
91-0218 Reconstruction 0-005-001 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0238 Reconstruction 0-005-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0973 Reconstruction 0-005-004 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0706 Reconstruction 0-005-005 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0167 Reconstruction 0-005-006 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0369 Reconstruction 0-005-010 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1565FP Reconstruction 0-005-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Hempstead School:
91-0239 Reconstruction 0-006-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0219 Reconstruction 0-006-002 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1249 Reconstruction 0-006-003 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1171 Reconstruction 0-006-004 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0974 Reconstruction 0-006-006 03/20/01 *CO No.* Amount Disallowed Received Approved Contractor
1 -4,500 12/31/01 02/28/02 All Bright Elec.
1 -17,000 02/20/02 04/05/02 Netrix, Inc
1 -2,400 12/19/02 02/18/03 Arbe Contracting
03-0168 Reconstruction 0-006-008 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1369 Reconstruction 0-006-009 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-1202 Reconstruction 0-006-010 04/26/06 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0370 Reconstruction 0-006-011 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1569FP Reconstruction 0-006-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Pomona Middle(fmlyPomonaJR):
91-0240 Reconstruction 0-008-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0507 Reconstruction 0-008-004 12/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0962 Reconstruction 0-008-005 03/13/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1250 Reconstruction 0-008-006 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0707 Reconstruction 0-008-007 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0975 Reconstruction 0-008-008 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0169 Reconstruction 0-008-009 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0900 Reconstruction 0-008-011 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0371 Reconstruction 0-008-013 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0966 Reconstruction 0-008-014 05/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1572FP Reconstruction 0-008-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Hillcrest Elementary:
91-0241 Reconstruction 0-011-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0220 Reconstruction 0-011-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0976 Reconstruction 0-011-005 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
02-2481 Reconstruction 0-011-006 07/08/03 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0170 Reconstruction 0-011-007 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0671 Reconstruction 0-011-008 03/06/06 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0372 Reconstruction 0-011-009 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0901 Reconstruction 0-011-010 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1370 Reconstruction 0-011-011 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0967 Reconstruction 0-011-012 05/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
Ramapo Fresh.Ctr.(frmlyKakiat):
91-0242 Reconstruction 0-013-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0221 Reconstruction 0-013-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-1051 Reconstruction 0-013-004 04/17/92 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1416 Reconstruction 0-013-005 06/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1251 Reconstruction 0-013-006 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1172 Reconstruction 0-013-007 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0977 Reconstruction 0-013-008 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0708 Reconstruction 0-013-009 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
12-0624 Reconstruction 0-013-010 03/13/13 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0171 Reconstruction 0-013-011 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0902 Reconstruction 0-013-012 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1371 Reconstruction 0-013-013 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0373 Reconstruction 0-013-014 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1573FP Reconstruction 0-013-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Fleetwood Elementary School:
91-0243 Reconstruction 0-014-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0222 Reconstruction 0-014-002 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-0591 Reconstruction 0-014-003 04/20/94 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1417 Reconstruction 0-014-004 06/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0508 Reconstruction 0-014-005 12/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1252 Reconstruction 0-014-006 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0709 Reconstruction 0-014-007 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0709 Reconstruction 0-014-008 03/12/02 *CO No.* Amount Disallowed Received Approved Contractor
1 -1,632 08/18/03 08/27/03 Best Roofing of NJ
02-1971 Reconstruction 0-014-009 04/28/03 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0172 Reconstruction 0-014-010 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0903 Reconstruction 0-014-011 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0374 Reconstruction 0-014-012 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1372 Reconstruction 0-014-013 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
Summit Park Elementary:
91-0244 Reconstruction 0-015-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0223 Reconstruction 0-015-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-1052 Reconstruction 0-015-004 04/17/92 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1418 Reconstruction 0-015-005 06/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0341 Reconstruction 0-015-006 11/16/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1253 Reconstruction 0-015-007 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0710 Reconstruction 0-015-008 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0978 Reconstruction 0-015-009 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0173 Reconstruction 0-015-010 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0904 Reconstruction 0-015-011 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0960 Reconstruction 0-015-012 01/30/09 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0375 Reconstruction 0-015-013 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Grandview Elementary:
91-0245 Reconstruction 0-016-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0224 Reconstruction 0-016-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1173 Reconstruction 0-016-005 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0979 Reconstruction 0-016-006 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0905 Reconstruction 0-016-009 04/06/07 *CO No.* Amount Disallowed Received Approved Contractor
1 -802 10/12/07 10/23/07 TOTAL PLUMBING CONCEPTS
05-0376 Reconstruction 0-016-010 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0961 Reconstruction 0-016-011 01/30/09 NO CHANGE ORDERS ON ELECTRONIC FILE
Margetts Road Elementary:
91-0246 Reconstruction 0-020-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1419 Reconstruction 0-020-003 06/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1254 Reconstruction 0-020-004 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0980 Reconstruction 0-020-005 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0174 Additions and Alterations 0-020-006 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0906 Reconstruction 0-020-007 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1373 Reconstruction 0-020-008 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0377 Reconstruction 0-020-009 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0968 Reconstruction 0-020-010 05/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1571FP Reconstruction 0-020-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Ramapo Senior High School:
90-1156 Reconstruction 0-022-001 04/15/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0247 Reconstruction 0-022-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0225 Reconstruction 0-022-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1255 Reconstruction 0-022-004 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1174 Reconstruction 0-022-005 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0836 Reconstruction 0-022-007 07/19/02 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0711 Reconstruction 0-022-008 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0981 Reconstruction 0-022-010 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1233 Reconstruction 0-022-011 05/09/00 *CO No.* Amount Disallowed Received Approved Contractor
1 -11,134 12/31/01 05/28/02 Enviro Techniques
1 -37,816 04/09/02 05/06/02 Zugibe Const.
1 -7,000 05/30/02 06/05/02 Lombardo Plumbing and Heating
1 -9,728 05/30/02 06/05/02 Lombardo Plumbing and Heating
03-0175 Additions and Alterations 0-022-012 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0907 Reconstruction 0-022-013 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0378 Reconstruction 0-022-014 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1374 Reconstruction 0-022-015 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1575FP Reconstruction 0-022-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Lime Kiln School:
91-0248 Reconstruction 0-027-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0226 Reconstruction 0-027-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1360 Reconstruction 0-027-004 06/10/94 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1420 Reconstruction 0-027-005 06/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1175 Reconstruction 0-027-006 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0176 Reconstruction 0-027-009 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0908 Reconstruction 0-027-010 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0379 Reconstruction 0-027-011 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1375 Reconstruction 0-027-012 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1570FP Reconstruction 0-027-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Elmwood Elementary School:
91-0249 Reconstruction 0-030-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0227 Reconstruction 0-030-002 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0963 Reconstruction 0-030-003 03/13/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1256 Reconstruction 0-030-004 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0982 Reconstruction 0-030-005 03/20/01 *CO No.* Amount Disallowed Received Approved Contractor
1 -19,500 10/02/01 01/08/02 Ray Tyrrell Paving
4 70,000 10/12/01 01/08/02 ACL Const.
03-0177 Reconstruction 0-030-007 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0909 Reconstruction 0-030-008 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0380 Reconstruction 0-030-009 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1376 Reconstruction 0-030-010 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1568FP Reconstruction 0-030-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Bluefield Elementary School:
91-0250 Reconstruction 0-033-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0228 Reconstruction 0-033-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
Chestnut Ridge Middle(frmlySpring Va:
91-0251 Reconstruction 0-034-003 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0964 Reconstruction 0-034-005 03/13/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1257 Reconstruction 0-034-006 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1549 Reconstruction 0-034-007 05/28/98 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1003 Reconstruction 0-034-008 04/10/00 *CO No.* Amount Disallowed Received Approved Contractor
1 -7,900 03/04/02 04/29/02 Best Roofing of NJ
00-0983 Reconstruction 0-034-009 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0178 Reconstruction 0-034-010 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1234 Reconstruction 0-034-011 05/09/00 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0910 Reconstruction 0-034-014 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1377 Additions and Alterations 0-034-015 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0381 Reconstruction 0-034-016 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Eldorado Elementary:
91-0252 Reconstruction 0-037-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0229 Reconstruction 0-037-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0965 Reconstruction 0-037-005 03/13/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1258 Reconstruction 0-037-006 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0712 Reconstruction 0-037-007 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0179 Reconstruction 0-037-009 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0911 Reconstruction 0-037-010 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0382 Reconstruction 0-037-011 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0969 Reconstruction 0-037-013 05/01/09 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1567FP Reconstruction 0-037-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Colton Elementary School:
91-0253 Reconstruction 0-038-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0230 Reconstruction 0-038-003 09/13/91 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1259 Reconstruction 0-038-005 05/01/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0713 Reconstruction 0-038-006 03/30/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0984 Reconstruction 0-038-007 03/20/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0180 Reconstruction 0-038-009 08/11/03 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0912 Reconstruction 0-038-010 04/06/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0383 Reconstruction 0-038-011 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1566FP Reconstruction 0-038-FP1 04/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Little Red Schoolhouse Museum:
91-0254 Reconstruction 0-048-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
Transportation Office:
05-0384 Reconstruction 1-010-003 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Central Warehouse Bldg.:
97-1787 Reconstruction 2-009-001 08/04/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0837 Reconstruction 2-009-002 07/19/02 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0385 Reconstruction 2-009-004 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Bldgs Grounds Bldg 1:
91-0255 Reconstruction 3-002-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1788 Reconstruction 3-002-002 08/04/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0838 Additions and Alterations 3-002-004 07/19/02 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0386 Reconstruction 3-002-007 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Bldgs Grounds Bldg 2:
91-0256 Reconstruction 3-004-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
Transportation Garage:
91-0257 Reconstruction 5-001-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0509 Reconstruction 5-001-003 12/15/94 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1789 Reconstruction 5-001-004 08/04/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0839 Additions and Alterations 5-001-005 07/19/02 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0387 Reconstruction 5-001-008 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Finkelstein Memorial Library:
98-0548 Reconstruction 6-012-002 02/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-1780 Additions and Alterations 6-012-003 05/18/01 NO CHANGE ORDERS ON ELECTRONIC FILE
Central Kitchen Bldg 1:
91-0258 Reconstruction 7-017-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1790 Reconstruction 7-017-002 08/04/98 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0388 Reconstruction 7-017-003 03/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Central Kitchen Bldg 2:
97-1791 Reconstruction 7-018-002 08/04/98 NO CHANGE ORDERS ON ELECTRONIC FILE
Central Kitchen Bldg 3:
91-0259 Reconstruction 7-019-001 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
Central Kitchen #4:
91-0260 Reconstruction 7-039-002 09/30/91 NO CHANGE ORDERS ON ELECTRONIC FILE
New Central Kitchen:
02-2129 New Construction 7-053-001 09/19/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Press Box (NOT BUILT-see 7055DB):
07-0383 New Construction 7-054-001 09/18/07 NO CHANGE ORDERS ON ELECTRONIC FILE
EDWIN GOULD ACAD-LAKESIDE RAMAPO UFS STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-14-02
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Main Building:
95-1300 Reconstruction 0-002-004 09/17/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0100 Reconstruction 0-002-005 08/05/97 NO CHANGE ORDERS ON ELECTRONIC FILE
Gymanisum-Social Hall:
96-0072 Reconstruction 0-003-002 07/25/96 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1025 Reconstruction 0-003-003 04/16/02 NO CHANGE ORDERS ON ELECTRONIC FILE
GED Program South Bldg.:
91-0333 Reconstruction 0-004-002 02/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0995 Reconstruction 0-004-003 04/08/99 NO CHANGE ORDERS ON ELECTRONIC FILE
GED Program North:
91-0728 Reconstruction 0-005-002 02/25/92 NO CHANGE ORDERS ON ELECTRONIC FILE
Intake Building:
91-0385 Reconstruction 8-007-002 01/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
Shrady Cottage:
90-1741 Reconstruction 8-008-003 08/29/91 NO CHANGE ORDERS ON ELECTRONIC FILE
BOCES ROCKLAND STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-90-00-00
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Bldg #1,Ctr Of Occ:
99-0801 Reconstruction 0-001-003 04/11/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1170 Reconstruction 0-001-004 05/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
#2 Ctr Of Occ Educ:
99-0802 Reconstruction 0-002-003 04/11/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1171 Reconstruction 0-002-006 05/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
#3 Ctr Of Occ Educ:
99-0803 Reconstruction 0-003-004 04/11/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1172 Reconstruction 0-003-006 05/20/04 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 7,777 04/05/05 04/20/06 Fanshawe Inc
EC-04 -23,500 10/04/05 10/13/05 Fanshawe Inc
MC-01 18,069 01/10/06 12/05/06 Platinum Mechanical
05-0675 Reconstruction 0-003-007 06/20/06 *CO No.* Amount Disallowed Received Approved Contractor
EC-03 890 11/30/07 01/28/08 Parker Electric, Inc.
EC-05 2,320 11/29/07 01/28/08 Parker Electric, Inc.
EC-07 1,200 11/29/07 01/28/08 Parker Electric, Corp.
GC-01 9,565 03/08/07 08/20/07 Nikko Construction
GC-02 -2,608 07/31/07 08/20/07 Nikko Construction
GC-03 3,509 11/30/07 12/27/07 Nikko Construction Corp
GC-04 -182 11/30/07 12/27/07 Nikko Construction Corp
PC-01 716 05/09/08 08/04/08 VARDON, INC.
Bldg#6 Ctr Of Occ Ed:
03-1173 Reconstruction 0-006-002 05/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Jessie J Kaplan #9:
03-1175 Reconstruction 0-010-003 05/20/04 *CO No.* Amount Disallowed Received Approved Contractor
MC-02 8,588 01/10/06 05/25/06 Platinum Mechanical
05-0676 Reconstruction 0-010-004 06/20/06 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 475 04/02/07 08/15/07 Richard parker Electrical
EC-02 595 04/02/07 08/15/07 Richard parker Electrical
EC-04 310 11/30/07 01/28/08 Parker Electric, Inc.
EC-06 2,475 11/29/07 01/28/08 Parker Electric, Inc.
08-1580 Additions and Alterations 0-010-005 09/18/09 NO CHANGE ORDERS ON ELECTRONIC FILE
Bldg #10 Ctr Of Occ (NOW 1-012):
98-1061 Reconstruction 0-012-002 06/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
Administration Bldg:
03-1177 Reconstruction 1-007-005 05/20/04 *CO No.* Amount Disallowed Received Approved Contractor
EC-02 6,030 04/05/05 04/26/05 Fanshawe Inc
Bldg #7 Administration:
03-1178 Reconstruction 1-008-003 05/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Bldg.10 Conference Center:
03-1176 Reconstruction 1-012-003 05/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Maint & Equipment #8:
03-1174 Reconstruction 3-014-001 05/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage Bldg #5:
97-1458 Reconstruction 5-009-002 05/01/98 *CO No.* Amount Disallowed Received Approved Contractor
FT-01 268,542 07/09/03 07/14/03 Ira Conklin
FT-02 -7,000 07/09/03 07/14/03 Ira Conklin
FT-03 3,832 07/09/03 07/14/03 Ira Conklin
FT-04 -3,200 07/09/03 07/14/03 Ira Conklin
FT-05 22,015 07/09/03 07/14/03 Ira Conklin
03-1179 Reconstruction 5-009-003 05/20/04 *CO No.* Amount Disallowed Received Approved Contractor
EC-03 7,245 04/05/05 04/26/05 Fanshawe Inc