Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/16/14 at 17:29:43




ALBANY CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-01-00-01
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          PHILIP SCHUYLER ACHIEVEMENT ACADEMY:
  -    PR New Construction             0-002-001                                              /  /       /  /     06/01/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Public School #18:
11-0076   Additions and Alterations    0-018-009               DONE    DONE       ADD. REQ'D07/29/11   07/28/11   07/06/10   06/07/11   02 - 16                        0     3,602,368  HCM             0           0           0 PB Americas, Inc.                       0        /  /                           /  /             

          New Scotland Elem (was School 19):
13-1154   Reconstruction               0-019-007                         UNREVIEWED         01/30/14   01/29/13   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          North Albany Academy (PS #20):
12-1150   Reconstruction               0-020-004  05/16/13     DONE    DONE       DONE      05/01/13   04/30/13   03/06/13   02/06/07   2,7                      300,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1155   Reconstruction               0-020-005                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Public School #23, S of Humanities:
08-0239   Reconstruction               0-023-009  05/26/10     DONE    DONE       DONE      09/03/08   08/26/08   01/04/08   08/05/08   10,155,16                797,587             0  HCM             0           0           0 PB Power                          770,615        /  /                           /  /             
12-0008   Reconstruction               0-023-011  07/20/12     DONE    DONE       DONE      07/09/12   07/06/12   06/08/12   06/07/12   155,16                   195,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1156   Reconstruction               0-023-012                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Thomas O'Brien #24:
13-1157   Reconstruction               0-024-008                         UNREVIEWED         01/30/14   01/29/14     /  /     10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Eagle Point Elementary (PS #27):
12-1151   Reconstruction               0-027-006  05/16/13     DONE    DONE       DONE      05/01/13   04/30/13   03/06/13   02/06/07   2,7,16                   110,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Hackett Middle School:
13-1243   Reconstruction               0-044-012                         UNREVIEWED         02/17/14   02/14/14   03/06/13   02/06/07   2,16                           0    21,102,606  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1158   Reconstruction               0-044-013                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Giffen Memorial Elementary:
12-0657   Reconstruction               0-046-008  06/05/13     DONE    DONE       DONE      01/10/13   01/08/13   08/12/11   05/17/09   2,4,7,8,9,155,15,16      900,000       890,831  HCM             0           0     294,300 Collins & Scoville Architects           0      10/18/13                       10/21/13           
13-1159   Reconstruction               0-046-009                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Arbor Hill Elementary:
13-0854   Reconstruction               0-047-007                         UNREVIEWED         12/09/13   12/05/13   03/16/12   05/18/10   155,16                         0             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-047-008                                              /  /       /  /     03/06/13     /  /     155,16                         0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1160   Reconstruction               0-047-009                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Albany High School:
09-1505   Reconstruction               0-048-013  06/10/10     DONE    DONE       DONE      06/09/10   06/08/10   06/01/10   05/18/10   9                        675,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
10-0443   Reconstruction               0-048-014  03/11/11     DONE    DONE       DONE      11/08/10   11/03/10   10/05/10   05/18/10   2,7,8,9,10,155,15,16   6,975,000     6,975,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
11-0077   Reconstruction               0-048-015               DONE    DONE       ADD. REQ'D07/29/11   07/28/11   04/13/11   06/07/11   10,155,16                      0             0  HCM             0           0           0 PB Americas, Inc.                       0        /  /                           /  /             
11-1148   Additions and Alterations    0-048-016  05/14/12     DONE    DONE       DONE      04/16/12   04/16/12   08/12/11   05/13/10   02 - 16                  400,000       400,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -    PR Additions and Alterations    0-048-017                                              /  /       /  /     03/08/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Albany Occupational Ctr.:
11-0756   Reconstruction               0-049-004  05/14/12     DONE    DONE       DONE      02/07/12   02/06/12   08/12/11   05/07/11   2,4,7,8,9,155,15,16    3,809,933     4,300,000  HCM             0           0     826,756 Collins & Scoville Architects           0        /  /                           /  /             
13-1161   Reconstruction               0-049-005                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          PSES "A":
11-0078   Reconstruction               0-056-002               DONE    DONE       ADD. REQ'D07/29/11   07/28/11   06/01/11   06/07/11   155,16                         0             0  HCM             0           0           0 PB Americas, Inc.                       0        /  /                           /  /             

          New Middle School @ Kelton Bhol Site:
13-1162   Reconstruction               0-061-002                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Montessori Magnet School:
13-1163   Reconstruction               0-062-002                         UNREVIEWED         01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Shed #1 @ Hackett MS:
07-1501DB Discovered Building          2-066-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Philip Schuyler Ach. Acad.:
07-1502DB Discovered Building          2-067-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Pine Hills:
07-1503DB Discovered Building          2-068-001  04/08/10     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Sheridan:
07-1504DB Discovered Building          2-069-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Montessori Magnet School:
07-1505DB Discovered Building          2-070-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Harriet Gibbons:
07-1506DB Discovered Building          2-071-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #2 @ Harriet Gibbons:
07-1507DB Discovered Building          2-072-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Myers MS:
07-1508DB Discovered Building          2-073-001  04/08/10     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #2 @ Myers:
07-1509DB Discovered Building          2-074-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          NEW COVENANT:
12-0865DB Discovered Building          8-076-001  02/27/13     DONE    DONE       DONE      02/15/13   02/15/13     /  /       /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BERNE-KNOX-WESTERLO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-02-01-04
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Berne Elementary:
08-1479   Reconstruction               0-001-014  12/31/09     DONE    DONE       DONE      04/10/09   02/25/09   11/30/06   12/18/07   2,4,7,8,9,10,155,15,     364,309       364,309  DDJ             0           0      24,008 Griffith Dardanelli,Architect           0      09/06/11                       10/04/11           
08-1098   Reconstruction               0-001-016  05/01/09     DONE    DONE       DONE      01/21/09   01/12/09   11/14/08   12/18/07   9,16                     146,000       146,000  DDJ             0           0     146,000 Griffith Dardanelli,Architect           0      09/02/09                         /  /             
09-1568   Reconstruction               0-001-017  11/08/10     DONE    DONE       DONE      06/23/10   06/15/10   02/05/10   03/31/10   2,155,15,16              442,640       442,640  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin     442,640      09/16/12                       09/16/12           

          Jr/Sr High School:
08-1307   Additions and Alterations    0-004-015  12/31/09     DONE    DONE       DONE      03/02/09   02/25/09   11/30/06   12/18/07   02 - 16               10,454,353    10,411,855  DDJ             0           0           0 Griffith Dardanelli,Architect           0      09/28/12                       10/18/12           
09-1569   Reconstruction               0-004-016  11/08/10     DONE    DONE       DONE      06/23/10   06/15/10   02/01/10   03/31/10   2,155,15,16            1,421,931     1,421,931  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin   1,421,931      09/16/12                       10/29/12           
13-0294   Reconstruction               0-004-017  09/06/13     DONE    DONE       DONE      08/28/13   08/23/13   07/08/13   07/15/13   2,9,16                   120,000             0  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Bus Garage:
08-1222   Reconstruction               5-003-008  05/27/09     DONE    DONE       DONE      02/19/09   02/10/09   11/30/06   12/18/07   2,8,9,155,15,16          100,390       100,390  MGL             0           0           0 Griffith Dardanelli,Architect           0      09/29/09                         /  /             
09-1570   Reconstruction               5-003-009  11/08/10     DONE    DONE       DONE      06/23/10   06/15/10   02/01/10   03/31/10   2,155,16                 372,750       372,750  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin     372,750      06/16/12                       10/29/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BETHLEHEM CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-03-06-06
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Glenmont Elementary:
13-0413   Reconstruction               0-002-013  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,7,9,155,15,16                0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Hamagrael Elementary (Playground):
13-0414   Reconstruction               0-003-016  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,9,10,155,15,16           0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Clarksville Elementary:
13-0415   Reconstruction               0-004-016  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,7,10,155,15,16               0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Middle School:
  -    PR Additions and Alterations    0-005-019                                              /  /       /  /     04/24/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0416   Additions and Alterations    0-005-019  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                        0    30,343,857  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -    PR Additions and Alterations    0-005-020                                              /  /       /  /     04/24/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0417   Additions and Alterations    0-005-020  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                        0    30,343,857  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Senior High School:
13-0418   Reconstruction               0-006-027  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,8,9,10,155,15,           0    51,969,456  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
13-0419   Reconstruction               0-006-028  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,8,9,10,155,15,           0    51,969,456  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
13-0970   Reconstruction               0-006-029                         UNREVIEWED         12/27/13   12/27/13   05/23/13   05/21/13   8,9,10,16                      0    51,969,456  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Elsmere Elementary:
13-0420   Reconstruction               0-008-017  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,9,10,155,15,16               0     6,581,277  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Slingerlands Elementary:
13-0421   Reconstruction               0-009-012  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,9,155,15,16              0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Eagle Elementary School:
13-0422   Reconstruction               0-026-003  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,16                           0     8,640,354  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Softball Shed @ High School:
12-0045DB Discovered Building          2-030-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   07/15/08     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ Eagle Elementary:
12-0046DB Discovered Building          2-031-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ Middle School:
12-0047DB Discovered Building          2-032-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ High School:
12-0048DB Discovered Building          2-033-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Farmers Market Shed:
12-0049DB Discovered Building          2-034-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Track & Field Storage:
12-0050DB Discovered Building          2-035-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Baseball Shed:
12-0051DB Discovered Building          2-036-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Project Adventure Trailer:
12-0052DB Discovered Building          2-037-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Football Container:
12-0053DB Discovered Building          2-039-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #1 @ O&M:
12-0054DB Discovered Building          2-040-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #2 @ O&M:
12-0055DB Discovered Building          2-041-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #1 @ Transportation:
12-0056DB Discovered Building          2-042-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #2 @ Transportation:
12-0057DB Discovered Building          2-043-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed #2 @ Middle School:
12-0058DB Discovered Building          2-044-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   06/06/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          O&M Equipment Shed:
13-0423   New Construction             2-045-001  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   05/02/13   03/12/13   02 - 16                        0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Town Library Shed:
13-0714DB Discovered Building          2-046-001  03/19/14     DONE    DONE       DONE      11/15/13   11/04/13   08/27/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Pop Warner Shed @ MS:
  -       New Construction             2-047-001                                              /  /       /  /     12/18/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Maintenance & Storage Facility:
13-0424   Additions and Alterations    3-012-006  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                        0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Bus Garage:
13-0425   Additions and Alterations    5-010-009  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                        0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAVENA COEYMANS SELKIRK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-04-02-06
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ravena B. Coeymans:
10-1296   Reconstruction               0-005-007  05/23/11     DONE    DONE       DONE      05/16/11   05/12/11   03/29/11   05/06/11   4,13                      50,000        50,000  JOD             0           0           0 Zaremba-Sopko Associates, PLL           0      08/31/11                       04/01/13           
  -       Reconstruction               0-005-008                                              /  /       /  /     02/27/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0900   Reconstruction               0-005-009  02/20/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0     9,204,343  JMB             0           0           0 Collins & Scoville Architects           0      03/27/14                       04/04/14           

          A.W. Becker Elementary:
11-0227   Reconstruction               0-009-008  10/05/11     DONE    DONE       DONE      09/30/11   09/30/11   09/21/11   09/06/11   13                        20,000        20,000  JOD             0           0           0 Zaremba-Sopko Associates, PLL           0      11/30/11                       04/01/13           
  -       Reconstruction               0-009-009                                              /  /       /  /     02/27/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0901   Reconstruction               0-009-010  02/20/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0     9,074,296  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Senior High School:
10-0962   Reconstruction               0-013-015  03/10/11     DONE    DONE       DONE      03/08/11   03/02/11   02/08/11   01/24/11                             35,000        35,000  JOD             0           0           0 Mosaic Associates                       0      05/19/11                         /  /             
  -       Reconstruction               0-013-016                                              /  /       /  /     03/14/11     /  /     155,16                         0    22,065,475  JOD             0           0           0                                         0        /  /                           /  /             
12-1304   Reconstruction               0-013-017  07/25/13     DONE    DONE       DONE      06/19/13   06/17/13   02/27/13   05/21/13   2,9                      144,455             0  JOB             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
  -       Reconstruction               0-013-018                                              /  /       /  /     02/27/13     /  /     10,155,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0902   Reconstruction               0-013-019  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/25/14                       04/02/14           

          Junior High School:
10-1307   Reconstruction               0-014-005  05/23/11     DONE    DONE       DONE      05/18/11   05/12/11   03/30/11   04/26/11   4                         20,000             0  JOD             0           0           0 Zaremba-Sopko Associates, PLL           0      08/31/11                       04/01/13           
  -       Reconstruction               0-014-006                                              /  /       /  /     02/27/13     /  /     10,155,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0903   Reconstruction               0-014-007  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Village of Ravena Office:
10-0433TQ Temporary Quarters           1-019-001  11/17/10     DONE    DONE       DONE      11/05/10   10/26/10   08/27/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
09-0098   Reconstruction               5-001-012  08/27/09     DONE    DONE       DONE      07/31/09   07/27/09   06/04/09   06/01/09   2,15,16                   15,000        15,000  JOD             0           0           0 Mosaic Associates                       0      05/17/10                         /  /             
  -       Reconstruction               5-001-013                                              /  /       /  /     02/27/13     /  /     155,15,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0904   Reconstruction               5-001-014  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Concession Stand:
12-1243   New Construction             7-020-001                       ADDENDUM REQ'D       06/04/13   06/04/13   01/10/13     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COHOES CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-05-00-01
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cohoes Middle School:
08-1267   Additions and Alterations    0-001-016  07/30/09     DONE    DONE       DONE      02/23/09   02/18/09   05/29/08   06/24/08   02 - 16                1,890,000     1,890,000  JOD             0           0      41,345 Collins & Scoville Architects           0      08/26/10           YES           /  /             
  -    PR Additions and Alterations    0-001-017                                              /  /       /  /     05/21/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-001-018                                              /  /       /  /     09/08/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
10-1189   Reconstruction               0-001-019  04/19/11     DONE    DONE       DONE      04/13/11   04/11/11   01/10/11   01/20/10   16                       396,000       396,000  JOD             0           0           0 Plumb Excel Group                       0        /  /                           /  /             
12-0357   Reconstruction               0-001-020  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,   1,049,261             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-021                                              /  /       /  /     03/11/14     /  /     2,8,9,155,16                   0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Abram Lansing School:
08-1268   Additions and Alterations    0-002-014  07/30/09     DONE    DONE       DONE      02/23/09   02/18/09   05/29/08   06/24/08   02 - 16                4,220,000     4,220,000  JOD             0           0      92,316 Collins & Scoville Architects           0      08/26/10           YES           /  /             
12-0358   Reconstruction               0-002-015  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     446,839             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Van Schaick Elementary:
08-1269   Additions and Alterations    0-005-015  07/30/09     DONE    DONE       DONE      02/23/09   02/18/09   05/29/08   06/24/08   02 - 16                1,100,000             0  JOD             0           0      24,063 Collins & Scoville Architects           0        /  /                           /  /             
12-0359   Reconstruction               0-005-017  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/12   2,4,7,8,9,14,155,15,           0     4,742,900  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          High School:
08-1270   Additions and Alterations    0-006-018  07/30/09     DONE    DONE       DONE      02/23/09   02/18/09   05/29/08   06/24/08   02 - 16               13,489,000    13,489,000  JOD             0           0     295,085 Collins & Scoville Architects           0      02/24/11           YES           /  /             
  -    PR Additions and Alterations    0-006-019                                              /  /       /  /     05/21/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
10-1302   Additions and Alterations    0-006-020  06/01/11     DONE    DONE       DONE      05/18/11   05/13/11   09/08/10   10/20/10   02 - 16                  217,796             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
12-0360   Reconstruction               0-006-021  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     107,052       107,052  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
08-1648SC Visual Structural Inspection 0-006-SC2  05/28/09     DONE    DONE       DONE      08/05/08   08/05/08     /  /       /  /     16                        24,750             0  JOD             0           0           0                                         0      09/20/06                         /  /             

          Harmony Hill School:
08-1271   Reconstruction               0-010-008  07/30/09     DONE    DONE       DONE      02/23/09   02/18/09     /  /     06/24/08   2,4,7,8,9,155,15,16    2,494,000     2,390,186  JOD             0           0      39,400 Collins & Scoville Architects           0      11/10/10           YES           /  /             
12-0361   Reconstruction               0-010-009  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     309,733             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Van Schaick @ Strage Garage:
09-1441DB Discovered Building          2-020-001  08/05/10     DONE    DONE       DONE      05/18/10   05/18/10   12/10/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
09-1320   Reconstruction               2-020-002  08/19/10     DONE    DONE       DONE      04/15/10   04/12/10   02/02/10   06/24/08   4,7,8,16                  50,000             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-01-06
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Colonie High School:
12-0605   Reconstruction               0-001-025  04/19/13     DONE    DONE       DONE      12/26/12   12/20/12   07/13/12   10/10/12   2,7,8,9,13             1,875,000     1,875,000  JOD             0           0           0 Mosaic Associates                       0      08/30/13                       10/29/13           
13-0912   Reconstruction               0-001-026               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   12/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Lisha Kill Jr High School:
13-0913   Reconstruction               0-002-015               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Veeder Elementary School:
13-0914   Reconstruction               0-003-014               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Saddlewood Elementary:
13-0915   Reconstruction               0-008-013               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Shaker Rd. Elementary:
13-0916   Reconstruction               0-009-014               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Forest Park Elementary School:
13-0917   Reconstruction               0-014-012               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Sand Creek School:
12-0606   Reconstruction               0-015-014  04/19/13     DONE    DONE       DONE      12/26/12   12/20/12   07/13/12   10/10/12   7                        625,000       625,000  JOD             0           0           0 Mosaic Associates                       0      08/30/13                       10/11/13           
13-0292   Reconstruction               0-015-015  02/19/14     DONE    DONE       DONE      08/27/13   08/23/13   06/06/13   10/10/12   2,7,155,15,16          1,875,000             0  JOB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
13-0918   Reconstruction               0-015-016               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Roessleville Elementary:
13-0919   Reconstruction               0-017-010               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/15/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          District Offices:
13-0920   Reconstruction               1-005-002               DONE    STARTED    UNREVIEWED12/19/13   12/18/13   10/02/13   10/12/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Storage Garage @ Sand Creek Middle:
09-1102DB Discovered Building          2-021-001  03/19/10     DONE    DONE       DONE      03/18/10   03/24/08   05/25/07     /  /     02 - 16                        0             0  MGL             0           0           0 Dodge Chamberlin Luzine Weber           0        /  /                           /  /             

          Track Shed:
08-1282DB Discovered Building          2-022-001  09/17/09     DONE    DONE       DONE      02/25/09   02/25/09   02/28/08     /  /                                    0             0  MGL             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Field Storage Building:
08-1283DB Discovered Building          2-023-001  09/17/09     DONE    DONE       DONE      02/25/09   02/25/09   02/28/08     /  /                                    0             0  MGL             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Ppo Warner Shed:
08-1288DB Discovered Building          2-027-001  09/17/09     DONE    DONE       DONE      02/25/09   02/25/09   08/27/08     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Storage Trailer @ Sand Creek MS:
08-1287DB Discovered Building          2-028-001  10/02/09     DONE    DONE       DONE      02/25/09   02/25/09   08/27/08     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Archery Storage Shed:
08-1285DB Discovered Building          2-029-001  10/02/09     DONE    DONE       DONE      02/25/09   02/25/09   08/27/08     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Baseball Storage Building:
08-1286DB Discovered Building          2-031-001  09/17/09     DONE    DONE       DONE      02/25/09   02/25/09   08/29/08     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Storage Trailer @ Roessleville K-4:
08-1289DB Discovered Building          2-033-001  09/17/09     DONE    DONE       DONE      02/25/09   02/25/09   08/29/08     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          SC Bike Shed:
09-0265DB Discovered Building          2-034-001  10/02/09     DONE    DONE       DONE      09/28/09   09/25/09   04/23/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Storage Building:
13-1165   Reconstruction               4-007-005               DONE    STARTED    UNREVIEWED01/30/14   01/30/14   01/07/14     /  /     16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Bus Maintenance Building:
  -       Reconstruction               5-006-008                                              /  /       /  /     10/02/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Press Box:
08-1393   Reconstruction               7-012-001  05/28/09     DONE    DONE       DONE      03/19/09   03/16/09   02/12/09   05/20/08   2,4,7,8,9,13,16           90,000             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Soccer Score Building:
08-1284DB Discovered Building          7-024-001  09/17/09     DONE    DONE       DONE      02/25/09   02/25/09   02/28/08     /  /                                    0             0  MGL             0           0           0 Mosaic Associates                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MENANDS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-15-02
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-0960   Reconstruction               0-001-008  03/29/10     DONE    DONE       DONE      02/25/10   02/18/10   12/07/09   03/16/10   7,8,9                    335,000       335,000  DDJ             0           0      74,346 Griffith Dardanelli,Architect           0      10/05/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-23-06
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Blue Creek Elementary:
08-0633   Reconstruction               0-003-001  05/06/09     DONE    DONE       DONE      10/30/08   10/29/08   08/11/08   03/03/08   2,4,15,16                591,000       591,000  DDJ             0           0     157,800 Collins & Scoville Architects           0      12/12/12                       12/31/12           
11-0459   Reconstruction               0-003-002  02/21/12     DONE    DONE       DONE      12/02/11   12/02/11   09/15/11   05/17/11   2,4,8,9,10,155,15,16     250,000       250,000  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/26/13           
12-0147   Reconstruction               0-003-003  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   7,8,9,10                  65,000        65,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       02/11/14           
13-0371   Reconstruction               0-003-004  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,4,7,8,9,155,16               0     7,299,701  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Loudonville School:
08-0634   Reconstruction               0-004-002  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08     /  /     03/03/08                            241,000       241,000                  0           0      64,300 Collins & Scoville Architects           0      11/20/12                       12/31/12           
  -       Reconstruction               0-004-003                                              /  /       /  /     11/09/09     /  /     2,9,155,16                     0     5,952,656  DDJ             0           0           0                                         0        /  /                           /  /             
09-0661   Reconstruction               0-004-003  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09     /  /     05/19/09                            330,000       330,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
12-0148   Reconstruction               0-004-004  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   2,9,155,16               222,000       222,000  DDJ             0           0      40,250 Collins & Scoville Architects           0        /  /                           /  /             
13-0372   Reconstruction               0-004-005  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   4,9                            0     5,952,656  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Shaker High School:
08-0635   Reconstruction               0-005-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   2,4,7,8,9,15,16        3,762,791     3,762,791  DDJ             0           0     443,856 Collins & Scoville Architects           0      10/28/13                       12/10/13           
09-0217   Reconstruction               0-005-002  10/26/09     DONE    DONE       DONE      09/15/09   09/14/09   06/23/09   05/19/09   16                       135,000       135,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
09-0662   Reconstruction               0-005-003  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09   11/09/09   05/19/09   9,155,16                 170,000        95,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
11-0460   Reconstruction               0-005-004  02/21/12     DONE    DONE       DONE      12/02/11   12/02/11   09/15/11   05/17/11   2,4,9,155,15,16          175,000       175,000  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/21/13           
12-0149   Reconstruction               0-005-005  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   9,155,16                 145,000       145,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0373   Reconstruction               0-005-006  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   4,8,9,10,16                    0    56,942,928  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1298   Reconstruction               0-005-007               STARTED DONE       DONE      03/04/14   03/04/14   02/25/14     /  /     155,16                         0    56,942,928  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Southgate School:
08-0636   Reconstruction               0-006-002  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08     /  /     03/03/08                          1,043,000     1,043,000  DDJ             0           0     241,100 Collins & Scoville Architects           0      11/20/12                       12/31/12           
09-0663   Reconstruction               0-006-003  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09   11/09/09   05/19/09   2,9                       64,410        64,410  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/21/13           
13-0374   Reconstruction               0-006-004  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   8,9,16                         0             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Boght Hills:
08-0637   Reconstruction               0-007-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   2,8,9,15,16              265,000       265,000  DDJ             0           0      60,600 Collins & Scoville Architects           0      11/20/12                       04/10/13           
12-0150   Reconstruction               0-007-002  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   9,155,16                  35,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Fort Ferry School:
08-0638   Reconstruction               0-008-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   2,15,16                  123,000       123,000  DDJ             0           0      32,800 Collins & Scoville Architects           0      11/20/12                       12/31/12           
09-0664   Reconstruction               0-008-002  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09   11/09/09   05/19/09   2,9,16                   282,069       282,069  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/21/13           
12-0151   Reconstruction               0-008-003  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   8,9,10                    15,000        15,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       02/11/14           

          Shaker Junior High:
08-0639   Reconstruction               0-009-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   2,8,9,15,16              502,000       502,000  DDJ             0           0     127,400 Collins & Scoville Architects           0      11/20/12                       12/31/12           
12-0152   Reconstruction               0-009-002  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   2,9,10,155,16            907,000       907,000  DDJ             0           0     200,000 Collins & Scoville Architects           0        /  /                           /  /             
13-0375   Reconstruction               0-009-003  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,4,7,8,9,16                   0    26,833,096  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Latham Ridge Elementary:
08-0640   Reconstruction               0-011-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   2,15,16                  248,000       248,000  DDJ             0           0      66,200 Collins & Scoville Architects           0      11/20/12                       12/31/12           
10-0233   Reconstruction               0-011-002  02/24/11     DONE    DONE       DONE      09/17/10   09/17/10   07/09/10   05/18/10   2,9,15,16                982,472       982,472  DDJ             0           0     314,110 Collins & Scoville Architects           0      03/18/13                       03/21/13           
13-0376   Reconstruction               0-011-003  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,7,9,155,16                   0             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Maplewood Elementary:
08-0641   Reconstruction               0-030-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   4,7,8,9,14,15,16         650,000       647,027  DDJ             0           0     160,200 Collins & Scoville Architects           0      11/30/12                       12/31/12           

          Goodrich School:
13-0378   Reconstruction               1-002-001                       ADDENDUM REQ'D       09/19/13   09/16/13   04/22/13   05/15/12   7,9,155,16                     0             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Storage Shed - Latham Ridge ES:
11-1458DB Discovered Building          2-032-001  08/21/12     DONE    DONE       DONE      07/09/12   06/28/12   06/06/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Maintenance Garage:
08-0642   Reconstruction               3-014-001  05/06/09     DONE    DONE       DONE      02/11/09   10/29/08   08/11/08   03/03/08   15,16                     15,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/12                       12/31/12           

          Bus Garage:
10-0091   Reconstruction               5-015-001  08/12/10     DONE    DONE       DONE      08/10/10   07/27/10   07/09/10   05/18/10   15                        25,000        25,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
13-0377   Reconstruction               5-015-002  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,9                            0             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GUILDERLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-08-02-06
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Altamont Elementary School:
09-0922   Reconstruction               0-001-018  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   7                        108,260       108,260  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Westmere Elementary:
09-0923   Reconstruction               0-003-009  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   8,9                       94,220        94,220  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Guilderland High School:
09-0179   Reconstruction               0-005-021  09/17/09     DONE    DONE       DONE      08/31/09   08/28/09   04/09/09   05/19/09   4,155                    100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       12/20/12           
  -       Reconstruction               0-005-022                                              /  /       /  /     11/20/09     /  /     7,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             
09-0924   Reconstruction               0-005-023  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   2,7,8,10,13            1,475,018     1,475,018  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
12-0302   Reconstruction               0-005-024  11/19/12     DONE    DONE       DONE      10/23/12   10/23/12   02/22/12   11/13/07   10                       155,000       155,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
12-0596   Reconstruction               0-005-025  01/29/13     DONE    DONE       DONE      12/24/12   12/18/12   03/14/12   05/17/11   16                       100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-005-026                                              /  /       /  /     06/05/13     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Lynwood Elementary:
09-0925   Reconstruction               0-007-007  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   2,7,15                   585,750       585,750  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Farnsworth Middle School:
11-0149   Reconstruction               0-009-016  09/28/11     DONE    DONE       DONE      08/26/11   08/26/11   08/26/11   11/13/07   7,9,155,16                92,168        92,168  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
09-0926   Reconstruction               0-009-017  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   2                        172,660       172,660  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
11-1405   Reconstruction               0-009-018  12/05/12     DONE    DONE       DONE      06/14/12   05/22/12   02/23/12   04/03/12   10                       100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Guilderland Elementary School:
09-0927   Reconstruction               0-012-014  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   7                        397,620       397,620  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Pine Bush Elementary School:
09-0928   Reconstruction               0-015-003  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   9,16                      48,280        48,280  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Snyder Field Press Box:
12-0129   New Construction             2-022-001  07/30/13     DONE    DONE       DONE      08/28/12   08/27/12   05/01/12   07/14/12   02 - 16                   82,450             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Maintance Bldg #2 (frmrly 4-006):
09-0929   Reconstruction               3-006-001  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   01/15/10   11/13/07   16                        24,320             0  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Maintenance Bldg #3 (frmrly 5-010):
09-0930   Reconstruction               3-010-004  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   16                        24,320        24,320  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           

          Guilderland Public Library:
08-1779   Additions and Alterations    6-014-007  07/16/09     DONE    DONE       DONE      07/01/09   06/30/09   06/10/09   03/12/09   02 - 16                   46,685             0  DDJ             0           0           0 Peter Gisolfi Associates                0      01/20/11                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VOORHEESVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-10-03-06
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Clayton A. Bouton High School:
09-1460   Reconstruction               0-001-014  06/24/10     DONE    DONE       DONE      05/20/10   05/18/10   02/24/10   05/18/10   9,15,16                   70,000        70,000  DDJ             0           0           0 Mosaic Associates                       0      11/26/10                         /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     04/19/11     /  /     9,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             
13-1317   Reconstruction               0-001-016  04/11/14     DONE    DONE       DONE      03/07/14   03/07/14   11/28/12   12/17/13   2,4,7,8,9,155,15,16    2,423,200             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
13-1371   Reconstruction               0-001-017                         UNREVIEWED         03/18/14   03/14/14   10/09/13   12/17/13   16                             0             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
  -       Reconstruction               0-001-018                                              /  /       /  /     03/28/14     /  /     8                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Elementary School/Bus Garage:
13-1372   Reconstruction               0-002-011                         UNREVIEWED         03/18/14   03/14/14   11/28/12   12/17/13   2,4,7,8,9,155,15,16            0    11,600,280  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
09-0962   Reconstruction               0-002-013  04/16/10     DONE    DONE       DONE      02/25/10   02/18/10   10/02/09   09/19/06   2,15,16                  230,000       230,000  DDJ             0           0           0 Mosaic Associates                       0      09/03/10                         /  /             

          Public Library:
  -    XX New Construction             6-014-001                         CANCELLED            /  /       /  /     08/09/12     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERVLIET CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-12-00-01
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
08-1171   Reconstruction               0-001-011  06/22/09     DONE    DONE       DONE      02/09/09   02/02/09     /  /     03/04/08                         14,237,906    14,237,906  JOD             0           0     352,391 Collins & Scoville Architects           0      10/15/12                       10/22/12           
08-1656   Reconstruction               0-001-012  06/10/09     DONE    DONE       DONE      06/01/09   05/27/09   05/29/09   06/02/09   2,4,7,8,9,155,16         600,000       600,000  JOD             0           0           0 Collins & Scoville Architects           0      09/02/10                         /  /             
12-0352   Reconstruction               0-001-013  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   04/17/12   12/20/11   2,4,8,9,155,15,16     10,624,433    10,624,433  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Watervliet Elementary:
08-1172   Reconstruction               0-006-010  06/22/09     DONE    DONE       DONE      02/09/09   02/02/09     /  /     03/04/08                            127,209       127,209  JOD             0           0           0 Collins & Scoville Architects           0      12/07/12                       12/21/12           
12-0353   Reconstruction               0-006-011  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   04/17/12   12/20/11   2,4,7,8,9,155,15,16    8,248,567     8,248,567  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Storage Bldg @ Jr/Sr High:
12-0354   New Construction             2-011-001  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   10/18/12   12/20/11   02 - 16                   42,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Press Box/ Grandstand:
12-0355   Reconstruction               7-010-002  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   10/17/12   12/20/11   2,7,8,9,13,16             35,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Watervliet Civic Center:
13-1122TQ Temporary Quarters           8-012-001                         UNREVIEWED         01/29/14   01/28/14   12/19/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ALBANY-SCHOH-SCHEN STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-90-00-00
last updated on 04/16/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Schoharie Center:
  -       Reconstruction               0-001-004                                              /  /       /  /     03/19/10     /  /     2,7                            0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Albany Vo-Tec Center Bldg. A:
09-1374   Reconstruction               0-007-005  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      350,650       350,650  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Center Bldg. B:
09-1375   Reconstruction               0-008-007  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      309,000       309,000  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Center Bldg. C:
09-1376   Reconstruction               0-009-005  06/22/10     DONE    DONE       DONE      05/03/10   04/20/10   03/19/10   04/20/09   2,7                      301,700       301,700  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany VOTECH Building D:
09-1377   Reconstruction               0-010-003  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,4,7                    344,650       344,650  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Voc-Tech Center Bldg.E:
09-1378   Reconstruction               0-011-004  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      251,000       251,000  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Center Bldg. F:
09-1379   Reconstruction               0-012-003  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      141,400             0  JOD             0           0           0 Griffith Dardanelli,Architect           0        /  /                           /  /             

          Maywood School:
09-0665   Reconstruction               0-018-012  01/26/10     DONE    DONE       DONE      12/30/09   12/21/09   11/02/09   02/12/09   2,4,8,9                  255,000       255,000  JOD             0           0           0 Griffith Dardanelli,Architect           0      07/28/10                         /  /             

          NERIC Offices:
12-1305TQ Temporary Quarters           1-061-001  09/19/13     DONE    DONE       DONE      06/19/13   06/17/13   07/27/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Science Kit Program:
10-0543TQ Temporary Quarters           7-059-001  09/16/11     DONE    DONE       DONE      12/06/10   11/22/10   04/27/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Technology Valley High School:
09-0136TQ Temporary Quarters           8-044-001  08/24/09     DONE    DONE       DONE      08/19/09   08/19/09   11/14/08     /  /                                    0             0  JOD             0           0           0 Entek Environmental and Tech.           0        /  /                           /  /             

          Alburtus Hall Rm106 St. Rose:
10-0432TQ Temporary Quarters           8-060-001  11/18/10     DONE    DONE       DONE      11/05/10   11/01/10   09/01/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Rosewood Plaza Nursing 2:
  -    TQ Temporary Quarters           8-061-001                                              /  /       /  /     02/05/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Tech Valley HS @ CSNE NanoFab East:
  -    TQ Temporary Quarters           8-062-001                                              /  /       /  /     01/31/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED