Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/26/17 at 06:46:37




ALBANY CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-01-00-01
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Scotland Elementary (PS #19):
13-1154   Reconstruction               0-019-007  10/24/14     DONE    DONE       DONE      01/30/14   01/29/13   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1124   Reconstruction               0-019-008  04/29/16     DONE    DONE       DONE      01/28/16   01/26/15   07/20/15   05/19/15   2,4,8,16                 292,000       292,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          North Albany Academy (PS #20):
12-1150   Reconstruction               0-020-004  05/16/13     DONE    DONE       DONE      05/01/13   04/30/13   03/06/13   02/06/07   2,7                      300,000       300,000  JMB             0           0           0 Collins & Scoville Architects           0      09/05/14                       11/14/14           
13-1155   Reconstruction               0-020-005  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1125   Reconstruction               0-020-006  04/29/16     DONE    DONE       DONE      01/28/16   01/26/16   07/20/15   05/19/15   4,8                      172,000       172,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Albany Schl of Humanities (PS #23):
12-0008   Reconstruction               0-023-011  07/20/12     DONE    DONE       DONE      07/09/12   07/06/12   06/08/12   06/07/12   155,16                   195,000       195,000  HCM             0           0           0 Collins & Scoville Architects           0      08/23/13                       11/14/14           
13-1156   Reconstruction               0-023-012  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1126   Reconstruction               0-023-013  04/29/16     DONE    DONE       DONE      01/28/16   01/26/16   07/20/15   05/19/15   2,7                    1,886,000     1,886,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-1771   Reconstruction               0-023-014  03/09/17     DONE    DONE       DONE      05/19/16   05/19/16   07/20/15   05/19/15   155,16                   110,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Thomas O'Brien Acad of Sci (PS #24):
13-1157   Reconstruction               0-024-008  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14     /  /     10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1772   Reconstruction               0-024-009  03/09/17     DONE    DONE       DONE      05/19/16   05/19/16   07/20/15   05/19/15   2,8,9,155,16           1,255,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Eagle Point Elementary (PS #27):
12-1151   Reconstruction               0-027-006  05/16/13     DONE    DONE       DONE      05/01/13   04/30/13   03/06/13   02/06/07   2,7,16                   110,000       110,000  JMB             0           0           0 Collins & Scoville Architects           0      01/06/14                       11/14/14           
15-1127   Reconstruction               0-027-007  04/29/16     DONE    DONE       DONE      01/28/16   01/26/15   07/20/15   05/19/15   2                         40,000        40,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Hackett Middle School:
13-1243   Reconstruction               0-044-012  08/29/14     DONE    DONE       DONE      02/17/14   02/14/14   03/06/13   02/06/07   2,16                     475,000       475,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1158   Reconstruction               0-044-013  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Giffen Memorial Elementary School:
12-0657   Reconstruction               0-046-008  06/05/13     DONE    DONE       DONE      01/10/13   01/08/13   08/12/11   05/17/09   2,4,7,8,9,155,15,16      900,000       890,831  HCM             0           0     294,300 Collins & Scoville Architects           0      10/18/13                       10/21/13           
13-1159   Reconstruction               0-046-009  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1128   Reconstruction               0-046-010  04/29/16     DONE    DONE       DONE      01/28/16   01/26/15   07/20/15   05/19/15   2,8,16                   401,000       401,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Arbor Hill Elementary:
13-0854   Reconstruction               0-047-007  07/15/14     DONE    DONE       DONE      12/09/13   12/05/13   03/16/12   05/18/10   155,16                   300,000       300,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-047-008                                              /  /       /  /     03/06/13     /  /     155,16                         0    16,133,580  JMB             0           0           0                                         0        /  /                           /  /             
13-1160   Reconstruction               0-047-009  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1773   Reconstruction               0-047-010  03/09/17     DONE    DONE       DONE      05/19/16   05/19/16   07/20/15   05/19/15   2,9,155,16             1,564,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Albany High School:
  -    PR Additions and Alterations    0-048-017                                              /  /       /  /     03/08/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
14-1548   Reconstruction               0-048-018  06/17/15     DONE    DONE       DONE      05/26/15   05/21/15   05/01/15   05/19/15   2,13,16                2,412,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-0834   Reconstruction               0-048-019  08/03/16     DONE    DONE       DONE      12/07/15   12/04/15   07/20/15   05/19/15   4,7,8,9,155,15,16      4,070,000     4,070,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-1668   Reconstruction               0-048-020  05/06/16     DONE    DONE       DONE      05/03/16   05/03/16   03/07/16   02/09/16   7                      2,600,000     2,600,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -    PR Additions and Alterations    0-048-021                                              /  /       /  /     07/15/16     /  /     02 - 16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-048-022                                              /  /       /  /     07/15/16     /  /     02 - 16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-048-023                                              /  /       /  /     07/15/16     /  /     02 - 16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Abrookin Vocational Tech. Center:
13-1161   Reconstruction               0-049-005  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0     5,652,500  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-1774   Reconstruction               0-049-006  03/09/17     DONE    DONE       DONE      05/19/16   05/19/16   07/20/15   05/19/15   2,15,16                  765,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Schuyler Achievmt Academy (PSES "A"):
15-1129   Reconstruction               0-056-003  04/29/16     DONE    DONE       DONE      01/28/16   01/26/16   07/20/15   05/19/15   4,9                      160,000       160,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Sheridan Prep Academy (PSES "B"):
15-1130   Reconstruction               0-057-002  04/29/16     DONE    DONE       DONE      01/28/16   01/26/16   07/20/15   05/19/15   9                         20,600        20,600  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Meyers Middle School:
13-1162   Reconstruction               0-061-002  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-0835   Reconstruction               0-061-003  08/03/16     DONE    DONE       DONE      12/07/15   12/04/15   07/20/15   05/19/15   9,155,15,16              688,000       688,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Montessori Magnet School:
13-1163   Reconstruction               0-062-002  10/24/14     DONE    DONE       DONE      01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Middle School (09/2016 fmly 8-076):
16-0904   Reconstruction               0-076-001  05/02/17     DONE    DONE       DONE      12/01/16   12/01/16   09/02/16   01/10/17   4,7,8,9,155,15,16      6,525,000     6,525,000  BMJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Administration @ Academy Park:
15-1131   Reconstruction               1-001-003  04/29/16     DONE    DONE       DONE      01/28/16   01/26/16   07/20/15   05/19/15   4,7,8                    820,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Administration @ Harriet Gibbons:
14-1664   Reconstruction               1-064-001  04/28/16     DONE    DONE       DONE      06/16/15   06/10/15   03/31/15   05/20/14   16                       165,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-1132   Reconstruction               1-064-002  04/29/16     DONE    DONE       DONE      01/28/16   01/26/16   07/20/15   05/19/15   2,7,8,155,16           1,234,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Shed 3 @ Myers MS:
  -       New Construction             2-080-001                                              /  /       /  /     01/27/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Maintenance Bldg @ Harriet Gibbons:
15-1775   New Construction             3-079-001  03/09/17     DONE    DONE       DONE      05/19/16   05/19/16   07/20/15   05/19/15   02 - 16                  225,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Press Box @ HS:
14-1549   New Construction             7-077-001  06/17/15     DONE    DONE       DONE      05/26/15   05/21/15   05/01/15   05/19/15   02 - 16                   72,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-004                                              /  /       /  /     11/24/15     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-0767SB Reconstruction               7-999-004                         UNREVIEWED         11/24/15   11/24/15     /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Visual Structural Inspection 7-999-SB1                                              /  /       /  /       /  /       /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          New Covenant (9/2/16 see 0-076):
12-0865   Reconstruction               8-076-001  02/27/13     DONE    DONE       DONE      02/15/13   02/15/13     /  /       /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          West Hill Middle School:
14-1572   Reconstruction               8-078-L01  08/26/15     DONE    DONE       DONE      06/01/15   05/29/15   05/22/15     /  /                              777,515       777,515  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BERNE-KNOX-WESTERLO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-02-01-04
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Berne Elementary:
16-1564   Reconstruction               0-001-018  04/18/17     DONE    DONE       DONE      03/29/17   03/29/17   01/09/17   03/13/17   155,15,16                 63,700             0  DDJ             0           0           0 M/E ENGINEERIN, P.C                     0        /  /                           /  /             

          Jr/Sr High School:
13-0294   Reconstruction               0-004-017  09/06/13     DONE    DONE       DONE      08/28/13   08/23/13   07/08/13   07/15/13   2,9,16                   167,500       167,500  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      04/02/14                       06/23/14           

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1426SB Reconstruction               7-999-001               DONE                           /  /       /  /     03/11/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BETHLEHEM CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-03-06-06
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Glenmont Elementary:
13-0413   Reconstruction               0-002-013  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,7,9,155,15,16        1,910,022     1,910,022  JMB             0           0           0 Ashley McGraw Architects                0      08/26/15                       11/02/15           
14-0991   Reconstruction               0-002-014  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   16                       191,840       191,840  JMB             0           0           0 ECG Engineering, LLC              191,840        /  /                           /  /             
  -       Reconstruction               0-002-015                                              /  /       /  /     04/20/17     /  /     2,4,7,8,9,10,14,155,           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Hamagrael Elementary:
13-0414   Reconstruction               0-003-016  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,9,10,155,15,16   1,045,493     1,045,493  JMB             0           0           0 Ashley McGraw Architects                0      09/15/15                       11/02/15           
14-0992   Reconstruction               0-003-017  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   16                       154,991       154,991  JMB             0           0           0 ECG Engineering, LLC              154,991        /  /                           /  /             
  -       Reconstruction               0-003-018                                              /  /       /  /     04/19/17     /  /     2,7,16                         0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Clarksville Elementary:
13-0415   Reconstruction               0-004-016  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,7,10,155,15,16         356,800             0  JMB             0           0           0 Ashley McGraw Architects                0      11/14/14                       11/02/15           

          Middle School:
  -    PR Additions and Alterations    0-005-019                                              /  /       /  /     04/24/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0416   Additions and Alterations    0-005-019  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                1,584,047     1,584,047  JMB             0           0           0 Ashley McGraw Architects                0      12/31/14                       11/02/15           
  -    PR Additions and Alterations    0-005-020                                              /  /       /  /     04/24/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0417   Additions and Alterations    0-005-020  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                1,217,095     1,217,095  JMB             0           0           0 Ashley McGraw Architects                0      11/06/15                       11/12/15           
14-0993   Reconstruction               0-005-021  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   155,15,16                675,692       675,692  JMB             0           0           0 ECG Engineering, LLC              675,692        /  /                           /  /             
15-0526   Reconstruction               0-005-022  11/19/15     DONE    DONE       DONE      10/05/15   09/30/15   06/16/15   06/17/15   2,4                       95,000             0  JMB             0           0           0 Ashley McGraw Architects                0      10/21/15                       12/11/15           
  -       Reconstruction               0-005-023                                              /  /       /  /       /  /       /  /     13,16                          0    29,019,954  SLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-005-024                                              /  /       /  /     04/20/17     /  /     2,4,7,8,9,10,13,155,           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Senior High School:
13-0418   Reconstruction               0-006-027  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,8,9,10,155,15,   5,307,062     5,307,062  JMB             0           0     752,165 Ashley McGraw Architects                0      12/31/14                       11/02/15           
13-0419   Reconstruction               0-006-028  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,8,9,10,155,15,   3,571,648     3,571,648  JMB             0           0           0 Ashley McGraw Architects                0      09/16/15                       11/02/15           
13-0970   Reconstruction               0-006-029  04/22/14     DONE    DONE       DONE      12/27/13   12/27/13   05/23/13   05/21/13   8,9,10,16                100,000       100,000  JMB             0           0           0 Ashley McGraw Architects                0      07/30/14                       09/03/14           
14-0542   Reconstruction               0-006-030  12/22/14     DONE    DONE       DONE      10/28/14   10/28/14   07/16/14   05/20/14   8,9,10                   100,000       100,000  JMB             0           0           0 Ashley McGraw Architects                0      07/27/15                       10/21/15           
14-0994   Reconstruction               0-006-031  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   155,15,16              2,203,778     2,203,778  JMB             0           0           0 ECG Engineering, LLC            2,203,778        /  /                           /  /             
15-0730   Reconstruction               0-006-032  11/20/15     DONE    DONE       DONE      11/17/15   11/17/15   10/19/15   05/19/15   2,8,13                   100,000       100,000  JMB             0           0           0 Ashley McGraw Architects                0      06/28/16                       07/15/16           
16-0651   Reconstruction               0-006-033  12/06/16     DONE    DONE       DONE      10/20/16   10/20/16   09/28/16   05/17/16   13                       100,000       100,000  SLC             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-006-034                                              /  /       /  /     04/20/17     /  /     2,4,7,8,9,10,13,155,           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Elsmere Elementary:
13-0420   Reconstruction               0-008-017  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,9,10,155,15,16       1,332,897     1,332,897  JMB             0           0           0 Ashley McGraw Architects                0      09/15/15                       11/02/15           
14-0995   Reconstruction               0-008-018  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   8,16                     441,143       441,143  JMB             0           0           0 ECG Engineering, LLC              441,143        /  /                           /  /             
  -       Reconstruction               0-008-019                                              /  /       /  /     04/19/17     /  /     2,4,7,8,9,10,14,15,1           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Slingerlands Elementary:
13-0421   Reconstruction               0-009-012  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,9,155,15,16      1,139,126     1,139,126  JMB             0           0           0 Ashley McGraw Architects                0      08/26/15                       11/02/15           
14-0996   Reconstruction               0-009-013  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   16                       177,418       177,418  JMB             0           0           0 ECG Engineering, LLC              177,418        /  /                           /  /             
  -       Reconstruction               0-009-014                                              /  /       /  /     04/19/17     /  /     2,4,7,8,9,10,155,15,           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Eagle Elementary School:
13-0422   Reconstruction               0-026-003  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,16                     267,508       267,508  JMB             0           0           0 Ashley McGraw Architects                0      12/31/14                       11/02/15           
14-0997   Reconstruction               0-026-004  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   16                       253,169       253,169  JMB             0           0           0 ECG Engineering, LLC              253,169        /  /                           /  /             
  -       Reconstruction               0-026-005                                              /  /       /  /     04/19/17     /  /     2,8,9,155,16                   0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Softball Shed @ High School:
12-0045DB Discovered Building          2-030-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   07/15/08     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ Eagle Elementary:
12-0046DB Discovered Building          2-031-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ Middle School:
12-0047DB Discovered Building          2-032-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ High School:
12-0048DB Discovered Building          2-033-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Farmers Market Shed:
12-0049DB Discovered Building          2-034-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Track & Field Storage:
12-0050DB Discovered Building          2-035-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Baseball Shed:
12-0051DB Discovered Building          2-036-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               2-036-002                                              /  /       /  /     04/19/17     /  /     4,7,8                          0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Project Adventure Trailer:
12-0052DB Discovered Building          2-037-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Football Container:
12-0053DB Discovered Building          2-039-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #1 @ O&M:
12-0054DB Discovered Building          2-040-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #2 @ O&M:
12-0055DB Discovered Building          2-041-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #1 @ Transportation:
12-0056DB Discovered Building          2-042-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #2 @ Transportation:
12-0057DB Discovered Building          2-043-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed #2 @ Middle School:
12-0058DB Discovered Building          2-044-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   06/06/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          O&M Equipment Shed:
13-0423   New Construction             2-045-001  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   05/02/13   03/12/13   02 - 16                  164,800             0  JMB             0           0           0 Ashley McGraw Architects                0      07/22/15                       11/02/15           

          Town Library Shed:
13-0714DB Discovered Building          2-046-001  03/19/14     DONE    DONE       DONE      11/15/13   11/04/13   08/27/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          XXPop Warner Shed @ MS:
  -    XX New Construction             2-047-001                         CANCELLED            /  /       /  /     12/18/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Tennis Storage Shed:
15-0949   New Construction             2-048-001  05/05/16     DONE    DONE       DONE      12/23/15   12/21/15   06/10/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Eagle Storage Shed:
14-0745   New Construction             2-049-001  02/17/15     DONE    DONE       DONE      12/15/14   12/11/14   06/10/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Storage Shed #2 @ Hamagrael ES:
15-0950   New Construction             2-050-001  05/05/16     DONE    DONE       DONE      12/23/15   12/21/15   10/28/15     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Athletic Storage Bldg @ MS:
  -       New Construction             2-052-001                                              /  /       /  /     04/21/17     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Storage Bldg @ Elsmere ES:
  -       New Construction             2-053-001                                              /  /       /  /     04/21/17     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Maintenance & Storage Facility:
13-0424   Additions and Alterations    3-012-006  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                  155,500             0  JMB             0           0           0 Ashley McGraw Architects                0      12/31/14                       11/02/15           
14-0998   Reconstruction               3-012-007  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   16                        31,434             0  JMB             0           0           0 ECG Engineering, LLC               31,434      09/22/16                       12/06/16           
  -       Reconstruction               3-012-008                                              /  /       /  /     04/19/17     /  /     2,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
13-0425   Additions and Alterations    5-010-009  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                1,242,718     1,242,718  JMB             0           0           0 Ashley McGraw Architects                0      05/31/15                       11/02/15           
14-0999   Reconstruction               5-010-010  04/29/16     DONE    DONE       DONE      01/22/15   01/20/15   07/25/14   06/18/14   16                       112,519       112,519  JMB             0           0           0 ECG Engineering, LLC              112,519        /  /                           /  /             
  -       Reconstruction               5-010-011                                              /  /       /  /     04/19/17     /  /     2,4,7,8,9,155,15,16            0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Public Library:
16-0287   Reconstruction               6-021-008  12/16/16     DONE    DONE       DONE      08/18/16   08/15/16   11/13/15   09/14/15   2,155,16                 753,828             0  JMB             0           0           0 M/E ENGINEERIN, P.C                     0        /  /                           /  /             
16-1440   Reconstruction               6-021-009                         UNREVIEWED         02/27/17   02/27/17   08/31/16   07/11/16   2,16                           0             0  AAA             0           0           0 M/E ENGINEERIN, P.C                     0        /  /                           /  /             

          Toilet/Storage Bldg @ HS Field:
  -       New Construction             7-051-001                                              /  /       /  /     04/20/17     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAVENA COEYMANS SELKIRK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-04-02-06
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pieter B. Coeymans Elementary School:
  -       Reconstruction               0-005-008                                              /  /       /  /     02/27/13     /  /     16                             0     8,818,575  JOB             0           0           0                                         0        /  /                           /  /             
13-0900   Reconstruction               0-005-009  02/20/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0     9,230,846  JMB             0           0           0 Collins & Scoville Architects           0      03/27/14                       04/04/14           
15-0247   Reconstruction               0-005-010  05/31/16     DONE    DONE       DONE      08/06/15   07/31/15   03/27/15   01/13/15   2,7,8,9,10,155,15,16   1,434,800     1,434,800  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-0242   Reconstruction               0-005-011  11/25/15     DONE    DONE       DONE      08/05/15   07/31/15   07/10/15   01/13/15   2,4,7,8,9,10           1,651,500     1,651,500  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-005-012                                              /  /       /  /     05/19/17     /  /     2,8,9,10,155,15,16             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          A.W. Becker Elementary School:
  -       Reconstruction               0-009-009                                              /  /       /  /     02/27/13     /  /     16                             0     9,169,305  JOB             0           0           0                                         0        /  /                           /  /             
13-0901   Reconstruction               0-009-010  02/20/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0     9,597,973  JMB             0           0           0 Collins & Scoville Architects           0      03/25/14                       06/04/14           
15-0248   Reconstruction               0-009-011  05/31/16     DONE    DONE       DONE      08/06/15   07/31/15   03/27/15   01/13/15   2,7,8,9,10,155,15,16   1,346,500     1,346,500  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-0243   Reconstruction               0-009-012  11/25/15     DONE    DONE       DONE      08/05/15   07/31/15   07/10/15   01/13/15   2,4,7,8,9,10           1,516,100     1,516,100  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-009-013                                              /  /       /  /     05/19/17     /  /     2,8,9,10,155,15,16             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          High School:
12-1304   Reconstruction               0-013-017  07/25/13     DONE    DONE       DONE      06/19/13   06/17/13   02/27/13   05/21/13   2,9                      150,400       150,400  JOB             0           0           0 BCK-IBI Group, a New York Gen           0      08/07/14                       03/25/15           
  -       Reconstruction               0-013-018                                              /  /       /  /     02/27/13     /  /     10,155,16                      0    22,142,936  JOB             0           0           0                                         0        /  /                           /  /             
13-0902   Reconstruction               0-013-019  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/25/14                       04/02/14           
15-0249   Reconstruction               0-013-020  05/31/16     DONE    DONE       DONE      08/06/15   07/31/15   03/27/15   01/13/15   2,8,9,10,155,15,16     1,807,900     1,807,900  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-0244   Reconstruction               0-013-021  11/25/15     DONE    DONE       DONE      08/05/15   07/31/15   07/10/15   01/13/15   2,4,7,8,9,10           1,771,000     1,771,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-0529   Reconstruction               0-013-022               STARTED DONE       ADD. REQ'D09/30/16   09/30/16   10/19/15   01/13/15   2,4,7,8,9,10,155,15,           0    27,541,695  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Middle School:
  -       Reconstruction               0-014-006                                              /  /       /  /     02/27/13     /  /     10,155,16                      0    17,921,024  JOB             0           0           0                                         0        /  /                           /  /             
13-0903   Reconstruction               0-014-007  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/20/14                       06/04/14           
  -       Reconstruction               0-014-008                                              /  /       /  /     03/10/15     /  /     155,16                         0    17,921,024  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-014-009                                              /  /       /  /     03/27/15     /  /     2,7,8,9,10,155,15,16           0    17,921,024  JMB             0           0           0                                         0        /  /                           /  /             
15-0245   Reconstruction               0-014-010  11/25/15     DONE    DONE       DONE      08/05/15   07/31/15   07/15/15   01/13/15   2,4,7,8,9,10             251,000       251,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-0530   Reconstruction               0-014-011               STARTED DONE       ADD. REQ'D09/30/16   09/30/16   10/19/15   01/13/15   2,4,7,8,9,10,155,15,           0    17,921,024  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-014-012                                              /  /       /  /     05/19/17     /  /     2,8,9,10,155,15,16             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
  -       Reconstruction               5-001-013                                              /  /       /  /     02/27/13     /  /     155,15,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0904   Reconstruction               5-001-014  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/20/14                       06/04/14           
15-0250   Reconstruction               5-001-015  05/31/16     DONE    DONE       DONE      08/06/15   07/31/15   03/27/15   01/13/15   2,7,8,9,13,155,15,16     760,800       760,800  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-0246   Reconstruction               5-001-016  11/25/15     DONE    DONE       DONE      08/05/15   07/31/15   07/10/15   01/13/15   2,7,8,9                  863,100       863,100  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Concession Stand:
12-1243   New Construction             7-020-001  03/23/17     DONE    DONE       DONE      06/04/13   06/04/13   01/10/13     /  /     02 - 16                  125,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COHOES CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-05-00-01
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cohoes Middle School:
12-0357   Reconstruction               0-001-020  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,   1,049,261     1,049,261  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-021                                              /  /       /  /     03/11/14     /  /     2,8,9,155,16                   0    16,843,804  DDJ             0           0           0                                         0        /  /                           /  /             

          Abram Lansing School:
12-0358   Reconstruction               0-002-015  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     446,839       446,839  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Van Schaick Elementary:
12-0359   Reconstruction               0-005-017  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/12   2,4,7,8,9,14,155,15,           0     4,884,228  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          High School:
12-0360   Reconstruction               0-006-021  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     107,052       107,052  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Harmony Hill School:
12-0361   Reconstruction               0-010-009  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     309,733       309,733  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          XXBaseball Booth/Stg (Demo'd 2016):
16-0324   Reconstruction               7-012-002  09/02/16     DONE    DONE       DONE      08/30/16   08/26/16   07/28/16   08/24/16   2                         20,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      09/29/16                       10/14/16           

          District-Wide:
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13                             0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-01-06
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Colonie High School:
12-0605   Reconstruction               0-001-025  04/19/13     DONE    DONE       DONE      12/26/12   12/20/12   07/13/12   10/10/12   2,7,8,9,13             1,875,000     1,875,000  JOD             0           0           0 Mosaic Associates                       0      06/15/15                       07/29/15           
13-0912   Reconstruction               0-001-026  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   12/15/13   16                             0    51,002,944  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-0403   Reconstruction               0-001-027  04/13/16     DONE    DONE       DONE      09/03/15   09/01/15   04/13/15   10/21/14   2,4,7,8,9,10,155,15,   6,500,000     6,500,000  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Lisha Kill Jr High School:
13-0913   Reconstruction               0-002-015  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0    19,880,225  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Veeder Elementary School:
13-0914   Reconstruction               0-003-014  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     9,736,600  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
16-0765   Reconstruction               0-003-015                       ADDENDUM REQ'D       11/10/16   11/10/16   08/03/16   08/23/16   2,16                           0     9,443,115  BMJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Saddlewood Elementary:
13-0915   Reconstruction               0-008-013  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     7,054,582  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Shaker Rd. Elementary:
13-0916   Reconstruction               0-009-014  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     6,762,396  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Forest Park Elementary School:
13-0917   Reconstruction               0-014-012  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     6,804,139  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-0401PR Additions and Alterations    0-014-013                         UNREVIEWED         09/03/15   09/01/15   04/13/15     /  /     02 - 16                        0     5,611,680  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-0404   Additions and Alterations    0-014-013  04/13/16     DONE    DONE       DONE      09/03/15   09/01/15   04/13/15   10/21/14   02 - 16                1,550,000     1,550,000  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Sand Creek School:
12-0606   Reconstruction               0-015-014  04/19/13     DONE    DONE       DONE      12/26/12   12/20/12   07/13/12   10/10/12   7                        625,000       625,000  JOD             0           0           0 Mosaic Associates                       0      08/30/13                       10/11/13           
13-0292   Reconstruction               0-015-015  02/19/14     DONE    DONE       DONE      08/27/13   08/23/13   06/06/13   10/10/12   2,7,155,15,16          1,875,000     1,875,000  JOB             0           0           0 Mosaic Associates                       0      10/15/14                       11/03/14           
13-0918   Reconstruction               0-015-016  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0    35,754,275  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Roessleville Elementary:
13-0919   Reconstruction               0-017-010  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     6,386,708  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
14-1153   Reconstruction               0-017-011  05/12/15     DONE    DONE       DONE      02/17/15   02/17/15   12/05/14   10/21/14   2,4,7,8,9,155,15,16      950,000       950,000  MFS             0           0           0 Mosaic Associates                       0      03/14/16                       04/11/16           
15-0402PR Additions and Alterations    0-017-012                         UNREVIEWED         09/03/15   09/01/15   04/13/15     /  /     02 - 16                        0     5,962,410  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
15-0405   Additions and Alterations    0-017-012  04/13/16     DONE    DONE       DONE      09/03/15   09/01/15   04/13/15   10/21/14   02 - 16                1,450,000     1,450,000  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Pine Grove United Methodist Church:
  -    TQ Temporary Quarters           0-035-001                                              /  /       /  /     01/04/17     /  /                                    0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          District Offices:
13-0920   Reconstruction               1-005-002  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/12/13   16                             0             0  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               1-005-003                                              /  /       /  /     02/07/17     /  /     7,16                           0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Storage Building:
13-1165   Reconstruction               4-007-005  10/16/14     DONE    DONE       DONE      01/30/14   01/30/14   01/07/14     /  /     16                             0             0  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Bus Maintenance Building:
  -       Reconstruction               5-006-008                                              /  /       /  /     10/02/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          District Wide:
14-1152   Reconstruction               7-999-005  04/07/16     DONE    DONE       DONE      02/17/15   02/17/15   12/05/14   10/21/14   2,16                   3,600,000     3,600,000  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MENANDS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-15-02
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -    PR Additions and Alterations    0-001-009                                              /  /       /  /     07/07/16     /  /     02 - 16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-23-06
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Blue Creek Elementary:
12-0147   Reconstruction               0-003-003  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   7,8,9,10                  65,000        65,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       02/11/14           
13-0371   Reconstruction               0-003-004  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,4,7,8,9,155,16         275,000       275,000  JOB             0           0           0 Collins & Scoville Architects           0      11/01/14                       06/12/15           
14-0167   Reconstruction               0-003-005  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/29/14   05/20/14   2,8,9,155,15,16           70,500        70,500  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
15-0090   Reconstruction               0-003-006  12/14/15     DONE    DONE       DONE      07/16/15   07/14/15   03/17/15   05/19/15   2,7,9,155,15,16          445,000       445,000  JMB             0           0           0 Collins & Scoville Architects           0      09/06/16                       12/01/16           
  -    PR Additions and Alterations    0-003-007                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1001   Reconstruction               0-003-008  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/29/16   05/17/16   16                       150,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Loudonville School:
12-0148   Reconstruction               0-004-004  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   2,9,155,16               222,000       222,000  DDJ             0           0      40,250 Collins & Scoville Architects           0      12/04/13                       05/21/14           
13-0372   Reconstruction               0-004-005  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   4,9                      197,935       197,935  JOB             0           0           0 Collins & Scoville Architects           0      11/01/14                       06/12/15           
14-0168   Reconstruction               0-004-006  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/20/14   05/20/14   8,9                      151,394       151,394  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
15-0091   Reconstruction               0-004-007  12/14/15     DONE    DONE       DONE      07/16/15   07/14/15   03/17/15   05/19/15   7                         80,000        80,000  JMB             0           0           0 Collins & Scoville Architects           0      09/06/16                       01/09/17           
  -    PR Additions and Alterations    0-004-008                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-009                                              /  /       /  /     05/18/17     /  /     7                              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Shaker High School:
12-0149   Reconstruction               0-005-005  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   9,155,16                 145,000       145,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       05/21/14           
13-0373   Reconstruction               0-005-006  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   4,8,9,10,16              105,000       105,000  JOB             0           0           0 Collins & Scoville Architects           0      11/01/14                       06/12/15           
13-1298   Reconstruction               0-005-007  06/17/14     DONE    DONE       DONE      03/04/14   03/04/14   02/25/14   05/20/14   155,16                   100,000       100,000  JMB             0           0           0 Collins & Scoville Architects           0      06/26/15                       08/06/15           
14-0169   Reconstruction               0-005-008  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/30/14   05/20/14   2,8,9,13,155,15,16     1,701,409     1,701,409  JMB             0           0     209,188 Collins & Scoville Architects           0      05/09/16                       06/30/16           
  -       Reconstruction               0-005-009                                              /  /       /  /     06/17/14     /  /     155                            0    57,965,452  JMB             0           0           0                                         0        /  /                           /  /             
15-0092   Reconstruction               0-005-010  01/06/16     DONE    DONE       DONE      07/16/15   07/14/15   03/17/15   05/19/15   2,4,9,155,15,16        1,115,000     1,115,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -    PR Additions and Alterations    0-005-011                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1002   Reconstruction               0-005-012  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/30/16   05/17/16   2,4,9,155,16             745,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-005-013                                              /  /       /  /     05/18/17     /  /     2,9,155,16                     0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Southgate School:
13-0374   Reconstruction               0-006-004  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   8,9,16                    45,000        45,000  JOB             0           0           0 Collins & Scoville Architects           0      11/01/14                       06/12/15           
14-0170   Reconstruction               0-006-005  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/30/14   05/20/14   8,9                       15,500        15,500  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
  -    PR Additions and Alterations    0-006-006                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1003   Reconstruction               0-006-007  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/30/16   05/17/16   7                        100,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-006-008                                              /  /       /  /     05/18/17     /  /     2,9,16                         0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Boght Hills:
12-0150   Reconstruction               0-007-002  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   9,155,16                  35,000        35,000  DDJ             0           0           0 Collins & Scoville Architects           0      04/16/14                       05/21/14           
14-0171   Reconstruction               0-007-003  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/29/14   05/20/14   8,9                       28,000        28,000  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
  -    PR Additions and Alterations    0-007-004                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1004   Reconstruction               0-007-005  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/29/16   05/17/16   7,10,16                  290,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-007-006                                              /  /       /  /     05/18/17     /  /     9,15,16                        0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Fort Ferry School:
12-0151   Reconstruction               0-008-003  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   8,9,10                    15,000        15,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       02/11/14           
14-0172   Reconstruction               0-008-004  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/29/14   05/20/14   2,8,9                     50,500        50,500  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
15-0093   Reconstruction               0-008-005  12/14/15     DONE    DONE       DONE      07/16/15   07/14/15   03/17/15   05/19/15   4                         35,000        35,000  JMB             0           0           0 Collins & Scoville Architects           0      09/06/16                       01/09/17           
  -    PR Additions and Alterations    0-008-006                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1005   Reconstruction               0-008-007  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/29/16   05/17/16   2,7,9,155,16              75,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-008-008                                              /  /       /  /     05/18/17     /  /     2,4,7,9,10,155,16              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Shaker Junior High:
12-0152   Reconstruction               0-009-002  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   2,9,10,155,16            907,000       907,000  DDJ             0           0     200,000 Collins & Scoville Architects           0      04/16/14                       05/21/14           
13-0375   Reconstruction               0-009-003  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,4,7,8,9,16             285,000       285,000  JOB             0           0           0 Collins & Scoville Architects           0      11/01/14                       06/12/15           
14-0173   Reconstruction               0-009-004  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/30/14   05/20/14   2,8,9,155,16             114,500       114,500  JMB             0           0           0 Collins & Scoville Architects           0      09/06/16                       12/22/16           
  -       Reconstruction               0-009-005                                              /  /       /  /     03/17/15     /  /     9                              0    27,203,584  JMB             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-009-006                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1687SB Reconstruction               0-009-007               DONE                           /  /       /  /     05/05/16     /  /     2,13,16                        0    27,203,584  JMB             0           0           0                                         0        /  /                           /  /             
15-1972   Reconstruction               0-009-007  10/07/16     DONE    DONE       DONE      06/23/16   06/23/16     /  /     05/23/16   2,13,16                   37,387        37,387  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-1006   Reconstruction               0-009-008  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/30/16   05/17/16   8,16                      40,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-009-009                                              /  /       /  /     05/18/17     /  /     4,7,9,13,14,16                 0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Latham Ridge Elementary:
13-0376   Reconstruction               0-011-003  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,7,9,155,16             718,911       718,911  JOB             0           0           0 Collins & Scoville Architects           0      11/01/14                       06/12/15           
14-0174   Reconstruction               0-011-004  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/29/14   05/20/14   2,7,8,9,155,16            80,500        80,500  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
15-0094   Reconstruction               0-011-005  12/14/15     DONE    DONE       DONE      07/16/15   07/14/15   03/17/15   05/19/15   7                        750,000       750,000  JMB             0           0           0 Collins & Scoville Architects           0      09/06/16                       01/09/17           
  -    PR Additions and Alterations    0-011-006                                              /  /       /  /     04/26/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1007   Reconstruction               0-011-007  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/30/16   05/17/16   15                        15,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-011-008                                              /  /       /  /     05/18/17     /  /     2,8,9,10,155,15,16             0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Goodrich School:
13-0378   Reconstruction               1-002-001  07/22/14     DONE    DONE       DONE      09/19/13   09/16/13   04/22/13   05/15/12   7,9,155,16                59,500             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               1-002-002                                              /  /       /  /     09/21/15     /  /     4,7,9,155,16                   0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1837   Reconstruction               1-002-003                         UNREVIEWED         05/16/17   05/16/17   02/24/16   05/17/16   2,7,8,9,10,155,15,16           0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Storage Shed - Latham Ridge ES:
11-1458DB Discovered Building          2-032-001  08/21/12     DONE    DONE       DONE      07/09/12   06/28/12   06/06/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Maintenance Garage:
  -       Reconstruction               3-014-002                                              /  /       /  /     04/26/16     /  /     2,4,7,8,9,155,15,16            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
13-0377   Reconstruction               5-015-002  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,9                      130,000       130,000  JOB             0           0           0 Collins & Scoville Architects           0      09/01/15                       06/12/15           
14-0175   Reconstruction               5-015-003  05/04/15     DONE    DONE       DONE      08/14/14   08/08/14   05/30/14   05/20/14   9,155,15,16              145,000       145,000  JMB             0           0           0 Collins & Scoville Architects           0      05/09/16                       06/30/16           
  -       Reconstruction               5-015-004                                              /  /       /  /     04/26/16     /  /     2,4,7,8,9,155,15,16            0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1008   Reconstruction               5-015-005  03/30/17     DONE    DONE       DONE      12/20/16   12/19/16   09/30/16   05/17/16   7,155,16                 500,000             0  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               5-015-006                                              /  /       /  /     05/18/17     /  /     4,155                          0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
16-1009   Reconstruction               7-999-002                       ADDENDUM REQ'D       12/20/16   12/19/16   09/30/16   05/17/16   13,16                          0   122,158,118  MTM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREEN ISLAND UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-07-01-03
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Heatly School:
  -       Reconstruction               0-001-008                                              /  /       /  /     07/24/14     /  /     10,155,15,16                   0    11,536,384  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GUILDERLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-08-02-06
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Altamont Elementary School:
14-0107   Reconstruction               0-001-019  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16      1,253,300     1,253,300  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1146   Reconstruction               0-001-020  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   4,8                      170,110       170,110  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Westmere Elementary:
14-0108   Reconstruction               0-003-010  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16      1,221,750     1,221,750  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1147   Reconstruction               0-003-011  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   2,8                      216,550       216,550  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Guilderland High School:
12-0302   Reconstruction               0-005-024  11/19/12     DONE    DONE       DONE      10/23/12   10/23/12   02/22/12   11/13/07   10                       155,000       155,000  DDJ             0           0           0 Collins & Scoville Architects           0      09/24/13                       09/24/13           
12-0596   Reconstruction               0-005-025  01/29/13     DONE    DONE       DONE      12/24/12   12/18/12   03/14/12   05/17/11   16                       100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      02/14/14                       07/03/14           
  -       Reconstruction               0-005-026                                              /  /       /  /     06/05/13     /  /     16                             0    50,841,564  DDJ             0           0           0                                         0        /  /                           /  /             
14-0109   Reconstruction               0-005-027  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16      5,569,120     5,569,120  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-0479   Reconstruction               0-005-028  12/18/15     DONE    DONE       DONE      09/18/15   09/14/15   07/10/15   05/19/15   4,9,16                 1,160,000     1,160,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1148   Reconstruction               0-005-029  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   2,7,8,9,155,16           772,930       772,930  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Lynwood Elementary:
14-0110   Additions and Alterations    0-007-008  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   02 - 16                2,044,330     2,044,330  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1149   Reconstruction               0-007-009  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   2,8,9                    128,930       128,930  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Farnsworth Middle School:
11-1405   Reconstruction               0-009-018  02/21/12     DONE    DONE       DONE      06/14/12   05/22/12   02/23/12   04/03/12   10                       100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0111   Reconstruction               0-009-019  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,8,9,155,15,16        2,612,150     2,612,150  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1150   Reconstruction               0-009-020  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   7                        100,610       100,610  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Guilderland Elementary School:
14-0112   Reconstruction               0-012-015  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,8,9,10,155,15,16       668,870       668,870  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1151   Reconstruction               0-012-016  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   2,8                      110,690       110,690  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Pine Bush Elementary School:
14-0113   Reconstruction               0-015-004  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16      3,059,130     3,059,130  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1152   Reconstruction               0-015-005  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   2,8,9,155                399,220       399,220  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          District Office (demolition):
  -       Reconstruction               1-008-001                                              /  /       /  /     01/14/17     /  /     2,15,16                        0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Snyder Field Press Box:
12-0129   New Construction             2-022-001  07/30/13     DONE    DONE       DONE      08/28/12   08/27/12   05/01/12   07/14/12   02 - 16                   82,450             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Maintance Bldg #2 (frmrly 4-006):
14-0114   Reconstruction               3-006-002  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   8,16                      28,220             0  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Maintenance Bldg #3 (frmrly 5-010):
14-0115   Reconstruction               3-010-005  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,16                 256,900             0  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Transportation Facility:
14-0116   Reconstruction               5-016-002  02/20/15     DONE    DONE       DONE      08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,16                 610,880       610,880  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
15-1153   Reconstruction               5-016-003  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   11/02/15   11/14/13   2,4                       91,560        91,560  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           

          Guilderland Public Library:
14-0931   Reconstruction               6-014-008  01/09/15     DONE    DONE       DONE      01/09/15   01/09/15   08/27/14   07/31/14   4,8,15                    44,150             0  DDJ             0           0           0 Schafer Engineering Associate           0      11/30/16                       12/07/16           
15-1154   Reconstruction               6-014-009  02/12/16     DONE    DONE       DONE      01/29/16   01/29/16   07/30/15   11/14/13   7                        363,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      11/30/16                       12/07/16           
  -       Reconstruction               6-014-010                                              /  /       /  /     03/13/17     /  /     155,15,16                      0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VOORHEESVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-10-03-06
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Clayton A. Bouton Jr/Sr High School:
13-1317   Reconstruction               0-001-016  04/11/14     DONE    DONE       DONE      03/07/14   03/07/14   11/28/12   12/17/13   2,4,7,8,9,155,15,16    2,423,200     2,423,200  DDJ             0           0           0 Mosaic Associates                       0      11/20/14                       06/30/15           
13-1371   Reconstruction               0-001-017  08/25/14     DONE    DONE       DONE      03/18/14   03/14/14   10/09/13   12/17/13   16                       139,750       139,750  DDJ             0           0           0 Mosaic Associates                       0      04/15/15                       04/22/15           
14-0360   Reconstruction               0-001-018  10/15/14     DONE    DONE       DONE      09/30/14   09/26/14   03/28/14   05/20/14   8                         99,800        99,800  DDJ             0           0           0 Mosaic Associates                       0      06/09/15                       06/19/15           
15-1056   Reconstruction               0-001-019  03/04/16     DONE    DONE       DONE      01/14/16   01/11/16   09/08/15   11/17/15   15                        75,000        75,000  DDJ             0           0           0 Mosaic Associates                       0      06/20/16                       06/24/16           

          Elementary School/Bus Garage:
13-1372   Reconstruction               0-002-011  08/25/14     DONE    DONE       DONE      03/18/14   03/14/14   11/28/12   12/17/13   2,4,7,8,9,155,15,16      139,750       139,750  DDJ             0           0           0 Mosaic Associates                       0      04/15/15                       06/26/15           
15-0277   Reconstruction               0-002-014  09/01/15     DONE    DONE       DONE      08/11/15   08/10/15   04/09/15   05/19/15   2,4,8                    203,000       203,000  DDJ             0           0           0 Mosaic Associates                       0      09/01/16                       09/22/16           
  -       Reconstruction               0-002-015                                              /  /       /  /       /  /       /  /     8,9,155,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             
16-1516SB Reconstruction               0-002-015                                              /  /       /  /     03/16/17     /  /     8,9,155,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Public Library:
  -    XX New Construction             6-014-001                         CANCELLED            /  /       /  /     08/09/12     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA2               STARTED                        /  /       /  /       /  /       /  /     13                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERVLIET CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-12-00-01
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
12-0352   Reconstruction               0-001-013  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   04/17/12   12/20/11   2,4,8,9,155,15,16      9,766,555     9,766,555  DDJ             0           0           0 Collins & Scoville Architects           0      05/21/15                       07/31/15           
16-0034   Reconstruction               0-001-014  04/01/16     DONE    DONE       DONE      07/08/16   07/07/16   05/03/16   03/28/16   2,8                      148,500       148,500  MFS             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Watervliet Elementary:
12-0353   Reconstruction               0-006-011  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   04/17/12   12/20/11   2,4,7,8,9,155,15,16    8,181,245     8,181,245  DDJ             0           0           0                                         0      05/21/15                       07/21/15           
16-0035   Reconstruction               0-006-012  04/01/16     DONE    DONE       DONE      07/08/16   07/07/16   05/03/16   03/28/16   2,8,16                    51,500        51,500  MFS             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Storage Bldg @ Jr/Sr High:
12-0354   New Construction             2-011-001  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   10/18/12   12/20/11   02 - 16                   42,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      05/21/15                       12/28/15           

          Press Box/ Grandstand:
12-0355   Reconstruction               7-010-002  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   10/17/12   12/20/11   2,7,8,9,13,16             35,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      05/21/15                       07/31/15           

          District-Wide:
15-0994SB Reconstruction               7-999-002               DONE                           /  /       /  /     12/31/15     /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             
15-1973   Reconstruction               7-999-002  09/20/16     DONE    DONE       DONE      06/23/16   06/23/16     /  /     03/17/16   13,16                    110,000       110,000  MFS             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Watervliet Civic Center:
13-1122TQ Temporary Quarters           8-012-001  05/07/14     DONE    DONE       DONE      01/29/14   01/28/14   12/19/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ALBANY-SCHOH-SCHEN STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-90-00-00
last updated on 05/26/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          NERIC Offices:
12-1305TQ Temporary Quarters           1-061-001  09/19/13     DONE    DONE       DONE      06/19/13   06/17/13   07/27/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Rosewood Plaza Nursing 2:
  -    TQ Temporary Quarters           8-061-001                                              /  /       /  /     02/05/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Tech Valley HS @ CSNE NanoFab East:
13-1489TQ Temporary Quarters           8-062-001  07/25/14     DONE    DONE       DONE      04/28/14   04/28/14   01/31/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Text Books/Science Kits:
14-1282TQ Temporary Quarters           8-063-001  05/04/15     DONE    DONE       DONE      03/18/15   03/12/15   10/10/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          North Country NERIC Building 2:
15-0528TQ Temporary Quarters           8-064-001  03/29/16     DONE    DONE       DONE      10/06/15   09/28/15   10/27/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED