Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 10/17/14 at 16:21:14




ALBANY CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-01-00-01
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          PHILIP SCHUYLER ACHIEVEMENT ACADEMY:
  -    PR New Construction             0-002-001                                              /  /       /  /     06/01/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Public School #18:
11-0076   Additions and Alterations    0-018-009               DONE    DONE       ADD. REQ'D07/29/11   07/28/11   07/06/10   06/07/11   02 - 16                        0     3,602,368  HCM             0           0           0 PB Americas, Inc.                       0        /  /                           /  /             

          New Scotland Elem (was School 19):
13-1154   Reconstruction               0-019-007                       ADDENDUM REQ'D       01/30/14   01/29/13   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          North Albany Academy (PS #20):
12-1150   Reconstruction               0-020-004  05/16/13     DONE    DONE       DONE      05/01/13   04/30/13   03/06/13   02/06/07   2,7                      300,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1155   Reconstruction               0-020-005                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Public School #23, S of Humanities:
08-0239   Reconstruction               0-023-009  05/26/10     DONE    DONE       DONE      09/03/08   08/26/08   01/04/08   08/05/08   10,155,16                797,587             0  HCM             0           0           0 PB Power                          770,615        /  /                           /  /             
12-0008   Reconstruction               0-023-011  07/20/12     DONE    DONE       DONE      07/09/12   07/06/12   06/08/12   06/07/12   155,16                   195,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1156   Reconstruction               0-023-012                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Thomas O'Brien #24:
13-1157   Reconstruction               0-024-008                       ADDENDUM REQ'D       01/30/14   01/29/14     /  /     10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Eagle Point Elementary (PS #27):
12-1151   Reconstruction               0-027-006  05/16/13     DONE    DONE       DONE      05/01/13   04/30/13   03/06/13   02/06/07   2,7,16                   110,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Hackett Middle School:
13-1243   Reconstruction               0-044-012  08/29/14     DONE    DONE       DONE      02/17/14   02/14/14   03/06/13   02/06/07   2,16                     475,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1158   Reconstruction               0-044-013                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Giffen Memorial Elementary:
12-0657   Reconstruction               0-046-008  06/05/13     DONE    DONE       DONE      01/10/13   01/08/13   08/12/11   05/17/09   2,4,7,8,9,155,15,16      900,000       887,658  HCM             0           0     294,300 Collins & Scoville Architects           0      10/18/13                       10/21/13           
13-1159   Reconstruction               0-046-009                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Arbor Hill Elementary:
13-0854   Reconstruction               0-047-007  07/15/14     DONE    DONE       DONE      12/09/13   12/05/13   03/16/12   05/18/10   155,16                   300,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-047-008                                              /  /       /  /     03/06/13     /  /     155,16                         0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1160   Reconstruction               0-047-009                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Albany High School:
09-1505   Reconstruction               0-048-013  06/10/10     DONE    DONE       DONE      06/09/10   06/08/10   06/01/10   05/18/10   9                        675,000       675,000  HCM             0           0           0 Collins & Scoville Architects           0      08/16/13                       06/30/14           
10-0443   Reconstruction               0-048-014  03/11/11     DONE    DONE       DONE      11/08/10   11/03/10   10/05/10   05/18/10   2,7,8,9,10,155,15,16   6,975,000     6,975,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
11-0077   Reconstruction               0-048-015               DONE    DONE       ADD. REQ'D07/29/11   07/28/11   04/13/11   06/07/11   10,155,16                      0             0  HCM             0           0           0 PB Americas, Inc.                       0        /  /                           /  /             
11-1148   Additions and Alterations    0-048-016  05/14/12     DONE    DONE       DONE      04/16/12   04/16/12   08/12/11   05/13/10   02 - 16                  400,000       400,000  HCM             0           0           0 Collins & Scoville Architects           0      03/06/13                       06/30/14           
  -    PR Additions and Alterations    0-048-017                                              /  /       /  /     03/08/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Albany Occupational Ctr.:
11-0756   Reconstruction               0-049-004  05/14/12     DONE    DONE       DONE      02/07/12   02/06/12   08/12/11   05/07/11   2,4,7,8,9,155,15,16    3,809,933     4,300,000  HCM             0           0     826,756 Collins & Scoville Architects           0        /  /                           /  /             
13-1161   Reconstruction               0-049-005                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          PSES "A":
11-0078   Reconstruction               0-056-002               DONE    DONE       ADD. REQ'D07/29/11   07/28/11   06/01/11   06/07/11   155,16                         0             0  HCM             0           0           0 PB Americas, Inc.                       0        /  /                           /  /             

          New Middle School @ Kelton Bhol Site:
13-1162   Reconstruction               0-061-002                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Montessori Magnet School:
13-1163   Reconstruction               0-062-002                       ADDENDUM REQ'D       01/30/14   01/29/14   10/07/13   10/07/13   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Shed #1 @ Hackett MS:
07-1501DB Discovered Building          2-066-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Philip Schuyler Ach. Acad.:
07-1502DB Discovered Building          2-067-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Pine Hills:
07-1503DB Discovered Building          2-068-001  04/08/10     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Sheridan:
07-1504DB Discovered Building          2-069-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Montessori Magnet School:
07-1505DB Discovered Building          2-070-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Harriet Gibbons:
07-1506DB Discovered Building          2-071-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #2 @ Harriet Gibbons:
07-1507DB Discovered Building          2-072-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #1 @ Myers MS:
07-1508DB Discovered Building          2-073-001  04/08/10     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          Shed #2 @ Myers:
07-1509DB Discovered Building          2-074-001  11/09/09     DONE    DONE       DONE      02/01/08   01/23/08   02/01/08     /  /                                    0             0  HCM             0           0           0 Hamlin Design Group                     0        /  /                           /  /             

          NEW COVENANT:
12-0865DB Discovered Building          8-076-001  02/27/13     DONE    DONE       DONE      02/15/13   02/15/13     /  /       /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BERNE-KNOX-WESTERLO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-02-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Berne Elementary:
08-1479   Reconstruction               0-001-014  12/31/09     DONE    DONE       DONE      04/10/09   02/25/09   11/30/06   12/18/07   2,4,7,8,9,10,155,15,     364,309       364,309  DDJ             0           0      24,008 Griffith Dardanelli,Architect           0      09/06/11                       10/04/11           
09-1568   Reconstruction               0-001-017  11/08/10     DONE    DONE       DONE      06/23/10   06/15/10   02/05/10   03/31/10   2,155,15,16              442,640       442,640  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin     442,640      09/16/12                       09/16/12           

          Jr/Sr High School:
08-1307   Additions and Alterations    0-004-015  12/31/09     DONE    DONE       DONE      03/02/09   02/25/09   11/30/06   12/18/07   02 - 16               10,492,766    10,351,106  DDJ             0           0           0 Griffith Dardanelli,Architect           0      09/28/12                       10/18/12           
09-1569   Reconstruction               0-004-016  11/08/10     DONE    DONE       DONE      06/23/10   06/15/10   02/01/10   03/31/10   2,155,15,16            1,421,931     1,421,931  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin   1,421,931      09/16/12                       10/29/12           
13-0294   Reconstruction               0-004-017  09/06/13     DONE    DONE       DONE      08/28/13   08/23/13   07/08/13   07/15/13   2,9,16                   167,500       167,500  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      04/02/14                       06/23/14           

          Bus Garage:
09-1570   Reconstruction               5-003-009  11/08/10     DONE    DONE       DONE      06/23/10   06/15/10   02/01/10   03/31/10   2,155,16                 372,750       372,750  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin     372,750      06/16/12                       10/29/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BETHLEHEM CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-03-06-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Glenmont Elementary:
13-0413   Reconstruction               0-002-013  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,7,9,155,15,16        1,880,045             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-002-014                                              /  /       /  /     07/25/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Hamagrael Elementary (Playground):
13-0414   Reconstruction               0-003-016  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,9,10,155,15,16   1,402,004             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-003-017                                              /  /       /  /     07/25/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Clarksville Elementary:
13-0415   Reconstruction               0-004-016  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,7,10,155,15,16         356,800             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Middle School:
  -    PR Additions and Alterations    0-005-019                                              /  /       /  /     04/24/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0416   Additions and Alterations    0-005-019  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                1,588,257             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -    PR Additions and Alterations    0-005-020                                              /  /       /  /     04/24/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0417   Additions and Alterations    0-005-020  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                2,540,645             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-005-021                                              /  /       /  /     07/25/14     /  /     155,15,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Senior High School:
13-0418   Reconstruction               0-006-027  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,8,9,10,155,15,   3,647,199             0  JMB             0           0     752,165 Ashley McGraw Architects                0        /  /                           /  /             
13-0419   Reconstruction               0-006-028  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,8,9,10,155,15,   4,211,250             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
13-0970   Reconstruction               0-006-029  04/22/14     DONE    DONE       DONE      12/27/13   12/27/13   05/23/13   05/21/13   8,9,10,16                100,000       100,000  JMB             0           0           0 Ashley McGraw Architects                0      07/30/14                       09/03/14           
  -       Reconstruction               0-006-030                                              /  /       /  /     07/16/14     /  /     8,9,10                         0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-006-031                                              /  /       /  /     07/25/14     /  /     155,15,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Elsmere Elementary:
13-0420   Reconstruction               0-008-017  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,9,10,155,15,16       1,415,843             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-008-018                                              /  /       /  /     07/25/14     /  /     8,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Slingerlands Elementary:
13-0421   Reconstruction               0-009-012  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,4,7,9,155,15,16      1,281,895             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-009-013                                              /  /       /  /     07/25/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Eagle Elementary School:
13-0422   Reconstruction               0-026-003  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   2,16                     267,508             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               0-026-004                                              /  /       /  /     07/25/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Softball Shed @ High School:
12-0045DB Discovered Building          2-030-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   07/15/08     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ Eagle Elementary:
12-0046DB Discovered Building          2-031-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ Middle School:
12-0047DB Discovered Building          2-032-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed @ High School:
12-0048DB Discovered Building          2-033-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Farmers Market Shed:
12-0049DB Discovered Building          2-034-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Track & Field Storage:
12-0050DB Discovered Building          2-035-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Baseball Shed:
12-0051DB Discovered Building          2-036-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Project Adventure Trailer:
12-0052DB Discovered Building          2-037-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Football Container:
12-0053DB Discovered Building          2-039-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #1 @ O&M:
12-0054DB Discovered Building          2-040-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #2 @ O&M:
12-0055DB Discovered Building          2-041-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #1 @ Transportation:
12-0056DB Discovered Building          2-042-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Container #2 @ Transportation:
12-0057DB Discovered Building          2-043-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   11/04/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Garden Shed #2 @ Middle School:
12-0058DB Discovered Building          2-044-001  09/28/12     DONE    DONE       DONE      07/25/12   07/13/12   06/06/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          O&M Equipment Shed:
13-0423   New Construction             2-045-001  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   05/02/13   03/12/13   02 - 16                  164,800             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Town Library Shed:
13-0714DB Discovered Building          2-046-001  03/19/14     DONE    DONE       DONE      11/15/13   11/04/13   08/27/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Pop Warner Shed @ MS:
  -       New Construction             2-047-001                                              /  /       /  /     12/18/13     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Tennis Storage Shed:
  -       New Construction             2-048-001                                              /  /       /  /     06/10/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Eagle Storage Shed:
  -       New Construction             2-049-001                                              /  /       /  /     06/10/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Maintenance & Storage Facility:
13-0424   Additions and Alterations    3-012-006  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                  155,500             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               3-012-007                                              /  /       /  /     07/25/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
13-0425   Additions and Alterations    5-010-009  04/11/14     DONE    DONE       DONE      09/24/13   09/24/13   04/24/13   03/12/13   02 - 16                1,264,653             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               5-010-010                                              /  /       /  /     07/25/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAVENA COEYMANS SELKIRK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-04-02-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ravena B. Coeymans:
10-1296   Reconstruction               0-005-007  05/23/11     DONE    DONE       DONE      05/16/11   05/12/11   03/29/11   05/06/11   4,13                      50,000        50,000  JOD             0           0           0 Zaremba-Sopko Associates, PLL           0      08/31/11                       04/01/13           
  -       Reconstruction               0-005-008                                              /  /       /  /     02/27/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0900   Reconstruction               0-005-009  02/20/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0     9,204,343  JMB             0           0           0 Collins & Scoville Architects           0      03/27/14                       04/04/14           

          A.W. Becker Elementary:
11-0227   Reconstruction               0-009-008  10/05/11     DONE    DONE       DONE      09/30/11   09/30/11   09/21/11   09/06/11   13                        20,000        20,000  JOD             0           0           0 Zaremba-Sopko Associates, PLL           0      11/30/11                       04/01/13           
  -       Reconstruction               0-009-009                                              /  /       /  /     02/27/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0901   Reconstruction               0-009-010  02/20/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0     9,570,416  JMB             0           0           0 Collins & Scoville Architects           0      03/25/14                       06/04/14           

          Senior High School:
10-0962   Reconstruction               0-013-015  03/10/11     DONE    DONE       DONE      03/08/11   03/02/11   02/08/11   01/24/11                             35,000        35,000  JOD             0           0           0 Mosaic Associates                       0      05/19/11                         /  /             
  -       Reconstruction               0-013-016                                              /  /       /  /     03/14/11     /  /     155,16                         0    22,065,475  JOD             0           0           0                                         0        /  /                           /  /             
12-1304   Reconstruction               0-013-017  07/25/13     DONE    DONE       DONE      06/19/13   06/17/13   02/27/13   05/21/13   2,9                      144,455             0  JOB             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
  -       Reconstruction               0-013-018                                              /  /       /  /     02/27/13     /  /     10,155,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0902   Reconstruction               0-013-019  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/25/14                       04/02/14           

          Junior High School:
10-1307   Reconstruction               0-014-005  05/23/11     DONE    DONE       DONE      05/18/11   05/12/11   03/30/11   04/26/11   4                         20,000             0  JOD             0           0           0 Zaremba-Sopko Associates, PLL           0      08/31/11                       04/01/13           
  -       Reconstruction               0-014-006                                              /  /       /  /     02/27/13     /  /     10,155,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0903   Reconstruction               0-014-007  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/20/14                       06/04/14           

          Village of Ravena Office:
10-0433TQ Temporary Quarters           1-019-001  11/17/10     DONE    DONE       DONE      11/05/10   10/26/10   08/27/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
  -       Reconstruction               5-001-013                                              /  /       /  /     02/27/13     /  /     155,15,16                      0             0  JOB             0           0           0                                         0        /  /                           /  /             
13-0904   Reconstruction               5-001-014  02/18/14     DONE    DONE       DONE      12/18/13   12/13/13   10/22/13   10/15/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/20/14                       06/04/14           

          Concession Stand:
12-1243   New Construction             7-020-001                       ADDENDUM REQ'D       06/04/13   06/04/13   01/10/13     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COHOES CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-05-00-01
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cohoes Middle School:
  -    PR Additions and Alterations    0-001-017                                              /  /       /  /     05/21/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-001-018                                              /  /       /  /     09/08/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
10-1189   Reconstruction               0-001-019  04/19/11     DONE    DONE       DONE      04/13/11   04/11/11   01/10/11   01/20/10   16                       396,000       396,000  JOD             0           0           0 Plumb Excel Group                       0        /  /                           /  /             
12-0357   Reconstruction               0-001-020  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,   1,049,261             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-021                                              /  /       /  /     03/11/14     /  /     2,8,9,155,16                   0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Abram Lansing School:
12-0358   Reconstruction               0-002-015  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     446,839             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Van Schaick Elementary:
12-0359   Reconstruction               0-005-017  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/12   2,4,7,8,9,14,155,15,           0     4,742,900  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          High School:
  -    PR Additions and Alterations    0-006-019                                              /  /       /  /     05/21/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
10-1302   Additions and Alterations    0-006-020  06/01/11     DONE    DONE       DONE      05/18/11   05/13/11   09/08/10   10/20/10   02 - 16                  217,796             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
12-0360   Reconstruction               0-006-021  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     107,052       107,052  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Harmony Hill School:
12-0361   Reconstruction               0-010-009  04/26/13     DONE    DONE       DONE      10/31/12   10/24/12   01/25/12   06/24/08   2,4,7,8,9,14,155,15,     309,733             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Van Schaick @ Strage Garage:
09-1441DB Discovered Building          2-020-001  08/05/10     DONE    DONE       DONE      05/18/10   05/18/10   12/10/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
09-1320   Reconstruction               2-020-002  08/19/10     DONE    DONE       DONE      04/15/10   04/12/10   02/02/10   06/24/08   4,7,8,16                  50,000             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-01-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Colonie High School:
12-0605   Reconstruction               0-001-025  04/19/13     DONE    DONE       DONE      12/26/12   12/20/12   07/13/12   10/10/12   2,7,8,9,13             1,875,000     1,875,000  JOD             0           0           0 Mosaic Associates                       0      08/30/13                       10/29/13           
13-0912   Reconstruction               0-001-026  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   12/15/13   16                             0    48,093,000  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Lisha Kill Jr High School:
13-0913   Reconstruction               0-002-015  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0    18,744,870  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Veeder Elementary School:
13-0914   Reconstruction               0-003-014  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     9,180,702  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Saddlewood Elementary:
13-0915   Reconstruction               0-008-013  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     6,651,816  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Shaker Rd. Elementary:
13-0916   Reconstruction               0-009-014  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     6,376,320  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Forest Park Elementary School:
13-0917   Reconstruction               0-014-012  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     5,667,840  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Sand Creek School:
12-0606   Reconstruction               0-015-014  04/19/13     DONE    DONE       DONE      12/26/12   12/20/12   07/13/12   10/10/12   7                        625,000       625,000  JOD             0           0           0 Mosaic Associates                       0      08/30/13                       10/11/13           
13-0292   Reconstruction               0-015-015  02/19/14     DONE    DONE       DONE      08/27/13   08/23/13   06/06/13   10/10/12   2,7,155,15,16          1,875,000             0  JOB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
13-0918   Reconstruction               0-015-016  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0    33,712,346  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Roessleville Elementary:
13-0919   Reconstruction               0-017-010  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/15/13   16                             0     6,022,080  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          District Offices:
13-0920   Reconstruction               1-005-002  10/16/14     DONE    DONE       DONE      12/19/13   12/18/13   10/02/13   10/12/13   16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Storage Garage @ Sand Creek Middle:
09-1102DB Discovered Building          2-021-001  03/19/10     DONE    DONE       DONE      03/18/10   03/24/08   05/25/07     /  /     02 - 16                        0             0  MGL             0           0           0 Dodge Chamberlin Luzine Weber           0        /  /                           /  /             

          Bus Storage Building:
13-1165   Reconstruction               4-007-005  10/16/14     DONE    DONE       DONE      01/30/14   01/30/14   01/07/14     /  /     16                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Bus Maintenance Building:
  -       Reconstruction               5-006-008                                              /  /       /  /     10/02/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MENANDS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-15-02
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-0960   Reconstruction               0-001-008  03/29/10     DONE    DONE       DONE      02/25/10   02/18/10   12/07/09   03/16/10   7,8,9                    335,000       335,000  DDJ             0           0      74,346 Griffith Dardanelli,Architect           0      10/05/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-23-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Blue Creek Elementary:
11-0459   Reconstruction               0-003-002  02/21/12     DONE    DONE       DONE      12/02/11   12/02/11   09/15/11   05/17/11   2,4,8,9,10,155,15,16     250,000       250,000  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/26/13           
12-0147   Reconstruction               0-003-003  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   7,8,9,10                  65,000        65,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       02/11/14           
13-0371   Reconstruction               0-003-004  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,4,7,8,9,155,16         275,000       275,000  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0167   Reconstruction               0-003-005               DONE    STARTED    UNREVIEWED08/14/14   08/08/14   05/29/14   05/20/14   2,8,9,155,15,16                0     7,421,467  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Loudonville School:
  -       Reconstruction               0-004-003                                              /  /       /  /     11/09/09     /  /     2,9,155,16                     0     5,952,656  DDJ             0           0           0                                         0        /  /                           /  /             
09-0661   Reconstruction               0-004-003  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09     /  /     05/19/09                            330,000       330,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
12-0148   Reconstruction               0-004-004  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   2,9,155,16               222,000       222,000  DDJ             0           0      40,250 Collins & Scoville Architects           0      12/04/13                       05/21/14           
13-0372   Reconstruction               0-004-005  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   4,9                      105,000       105,000  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0168   Reconstruction               0-004-006               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/20/14   05/20/14   8,9                            0     6,051,952  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Shaker High School:
09-0217   Reconstruction               0-005-002  10/26/09     DONE    DONE       DONE      09/15/09   09/14/09   06/23/09   05/19/09   16                       135,000       135,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
09-0662   Reconstruction               0-005-003  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09   11/09/09   05/19/09   9,155,16                 170,000        95,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
11-0460   Reconstruction               0-005-004  02/21/12     DONE    DONE       DONE      12/02/11   12/02/11   09/15/11   05/17/11   2,4,9,155,15,16          175,000       175,000  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/21/13           
12-0149   Reconstruction               0-005-005  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   9,155,16                 145,000       145,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       05/21/14           
13-0373   Reconstruction               0-005-006  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   4,8,9,10,16              105,000       105,000  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1298   Reconstruction               0-005-007  06/17/14     DONE    DONE       DONE      03/04/14   03/04/14   02/25/14   05/20/14   155,16                   100,000       100,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0169   Reconstruction               0-005-008               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/30/14   05/20/14   2,8,9,13,155,15,16             0    58,205,280  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-005-009                                              /  /       /  /     06/17/14     /  /     155                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Southgate School:
09-0663   Reconstruction               0-006-003  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09   11/09/09   05/19/09   2,9                       64,410        64,410  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/21/13           
13-0374   Reconstruction               0-006-004  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   8,9,16                    45,000        45,000  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0170   Reconstruction               0-006-005               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/30/14   05/20/14   8,9                            0     6,338,898  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Boght Hills:
12-0150   Reconstruction               0-007-002  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   9,155,16                  35,000        35,000  DDJ             0           0           0 Collins & Scoville Architects           0      04/16/14                       05/21/14           
14-0171   Reconstruction               0-007-003               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/29/14   05/20/14   8,9                            0     7,043,220  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Fort Ferry School:
09-0664   Reconstruction               0-008-002  05/05/10     DONE    DONE       DONE      12/30/09   12/23/09   11/09/09   05/19/09   2,9,16                   282,069       282,069  DDJ             0           0           0 Collins & Scoville Architects           0      03/18/13                       03/21/13           
12-0151   Reconstruction               0-008-003  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   8,9,10                    15,000        15,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/04/13                       02/11/14           
14-0172   Reconstruction               0-008-004               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/29/14   05/20/14   2,8,9                          0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Shaker Junior High:
12-0152   Reconstruction               0-009-002  01/03/13     DONE    DONE       DONE      09/05/12   09/05/12   08/14/12   05/15/12   2,9,10,155,16            907,000       907,000  DDJ             0           0     200,000 Collins & Scoville Architects           0      04/16/14                       05/21/14           
13-0375   Reconstruction               0-009-003  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,4,7,8,9,16             285,000             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0173   Reconstruction               0-009-004               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/30/14   05/20/14   2,8,9,155,16                   0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Latham Ridge Elementary:
10-0233   Reconstruction               0-011-002  02/24/11     DONE    DONE       DONE      09/17/10   09/17/10   07/09/10   05/18/10   2,9,15,16                982,472       982,472  DDJ             0           0     314,110 Collins & Scoville Architects           0      03/18/13                       03/21/13           
13-0376   Reconstruction               0-011-003  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,7,9,155,16             500,000       500,000  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0174   Reconstruction               0-011-004               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/29/14   05/20/14   2,7,8,9,155,16                 0     7,395,381  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Goodrich School:
13-0378   Reconstruction               1-002-001  07/22/14     DONE    DONE       DONE      09/19/13   09/16/13   04/22/13   05/15/12   7,9,155,16                59,500             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Storage Shed - Latham Ridge ES:
11-1458DB Discovered Building          2-032-001  08/21/12     DONE    DONE       DONE      07/09/12   06/28/12   06/06/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
10-0091   Reconstruction               5-015-001  08/12/10     DONE    DONE       DONE      08/10/10   07/27/10   07/09/10   05/18/10   15                        25,000        25,000  DDJ             0           0           0 Collins & Scoville Architects           0      11/20/12                       12/31/12           
13-0377   Reconstruction               5-015-002  04/09/14     DONE    DONE       DONE      09/19/13   09/16/13   06/05/13   05/21/13   2,9                      130,000             0  JOB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0175   Reconstruction               5-015-003               STARTED STARTED    UNREVIEWED08/14/14   08/08/14   05/30/14   05/20/14   9,155,15,16                    0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREEN ISLAND UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-07-01-03
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Heatly School:
  -       Reconstruction               0-001-008                                              /  /       /  /     07/24/14     /  /     10,155,15,16                   0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GUILDERLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-08-02-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Altamont Elementary School:
09-0922   Reconstruction               0-001-018  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   7                        108,260       108,260  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0107   Reconstruction               0-001-019               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16              0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Westmere Elementary:
09-0923   Reconstruction               0-003-009  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   8,9                       94,220        94,220  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0108   Reconstruction               0-003-010               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16              0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Guilderland High School:
  -       Reconstruction               0-005-022                                              /  /       /  /     11/20/09     /  /     7,16                           0    45,977,280  DDJ             0           0           0                                         0        /  /                           /  /             
09-0924   Reconstruction               0-005-023  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   2,7,8,10,13            1,475,018     1,475,018  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
12-0302   Reconstruction               0-005-024  11/19/12     DONE    DONE       DONE      10/23/12   10/23/12   02/22/12   11/13/07   10                       155,000       155,000  DDJ             0           0           0 Collins & Scoville Architects           0      09/24/13                       09/24/13           
12-0596   Reconstruction               0-005-025  01/29/13     DONE    DONE       DONE      12/24/12   12/18/12   03/14/12   05/17/11   16                       100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      02/14/14                       07/03/14           
  -       Reconstruction               0-005-026                                              /  /       /  /     06/05/13     /  /     16                             0    51,051,900  DDJ             0           0           0                                         0        /  /                           /  /             
14-0109   Reconstruction               0-005-027               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16              0    51,051,900  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Lynwood Elementary:
09-0925   Reconstruction               0-007-007  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   2,7,15                   585,750       585,750  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0110   Additions and Alterations    0-007-008               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   02 - 16                        0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Farnsworth Middle School:
11-0149   Reconstruction               0-009-016  09/28/11     DONE    DONE       DONE      08/26/11   08/26/11   08/26/11   11/13/07   7,9,155,16                92,168        92,168  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
09-0926   Reconstruction               0-009-017  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   2                        172,660       172,660  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
11-1405   Reconstruction               0-009-018  02/21/12     DONE    DONE       DONE      06/14/12   05/22/12   02/23/12   04/03/12   10                       100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0111   Reconstruction               0-009-019               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,8,9,155,15,16                0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Guilderland Elementary School:
09-0927   Reconstruction               0-012-014  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   7                        397,620       397,620  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0112   Reconstruction               0-012-015               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,8,9,10,155,15,16             0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Pine Bush Elementary School:
09-0928   Reconstruction               0-015-003  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/28/09   11/13/07   9,16                      48,280        48,280  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0113   Reconstruction               0-015-004               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,9,155,15,16              0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Snyder Field Press Box:
12-0129   New Construction             2-022-001  07/30/13     DONE    DONE       DONE      08/28/12   08/27/12   05/01/12   07/14/12   02 - 16                   82,450             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Maintance Bldg #2 (frmrly 4-006):
09-0929   Reconstruction               3-006-001  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   01/15/10   11/13/07   16                        24,320             0  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0114   Reconstruction               3-006-002               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   8,16                           0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Maintenance Bldg #3 (frmrly 5-010):
09-0930   Reconstruction               3-010-004  08/04/10     DONE    DONE       DONE      02/19/10   02/16/10   12/29/09   11/13/07   16                        24,320        24,320  DDJ             0           0           0 Collins & Scoville Architects           0      12/05/12                       06/30/13           
14-0115   Reconstruction               3-010-005               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,16                       0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Transportation Facility:
14-0116   Reconstruction               5-016-002               DONE    STARTED    UNREVIEWED08/06/14   08/05/14   04/22/14   11/14/13   2,7,8,16                       0             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Guilderland Public Library:
  -       Reconstruction               6-014-008                                              /  /       /  /     08/27/14     /  /     4,8,15                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VOORHEESVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-10-03-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Clayton A. Bouton High School:
09-1460   Reconstruction               0-001-014  06/24/10     DONE    DONE       DONE      05/20/10   05/18/10   02/24/10   05/18/10   9,15,16                   70,000        70,000  DDJ             0           0           0 Mosaic Associates                       0      11/26/10                         /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     04/19/11     /  /     9,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             
13-1317   Reconstruction               0-001-016  04/11/14     DONE    DONE       DONE      03/07/14   03/07/14   11/28/12   12/17/13   2,4,7,8,9,155,15,16    2,423,200             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
13-1371   Reconstruction               0-001-017  08/25/14     DONE    DONE       DONE      03/18/14   03/14/14   10/09/13   12/17/13   16                       139,750             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
14-0360   Reconstruction               0-001-018  10/15/14     DONE    DONE       DONE      09/30/14   09/26/14   03/28/14   05/20/14   8                         99,800             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Elementary School/Bus Garage:
13-1372   Reconstruction               0-002-011  08/25/14     DONE    DONE       DONE      03/18/14   03/14/14   11/28/12   12/17/13   2,4,7,8,9,155,15,16      139,750       139,750  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
09-0962   Reconstruction               0-002-013  04/16/10     DONE    DONE       DONE      02/25/10   02/18/10   10/02/09   09/19/06   2,15,16                  230,000       230,000  DDJ             0           0           0 Mosaic Associates                       0      09/03/10                         /  /             

          Public Library:
  -    XX New Construction             6-014-001                         CANCELLED            /  /       /  /     08/09/12     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERVLIET CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-12-00-01
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
12-0352   Reconstruction               0-001-013  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   04/17/12   12/20/11   2,4,8,9,155,15,16     10,624,433    10,624,433  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Watervliet Elementary:
12-0353   Reconstruction               0-006-011  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   04/17/12   12/20/11   2,4,7,8,9,155,15,16    8,248,567     8,248,567  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Storage Bldg @ Jr/Sr High:
12-0354   New Construction             2-011-001  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   10/18/12   12/20/11   02 - 16                   42,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      08/28/14           YES           /  /             

          Press Box/ Grandstand:
12-0355   Reconstruction               7-010-002  02/22/13     DONE    DONE       DONE      10/30/12   10/29/12   10/17/12   12/20/11   2,7,8,9,13,16             35,000             0  DDJ             0           0           0 Collins & Scoville Architects           0      08/28/14           YES           /  /             

          Watervliet Civic Center:
13-1122TQ Temporary Quarters           8-012-001  05/07/14     DONE    DONE       DONE      01/29/14   01/28/14   12/19/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ALBANY-SCHOH-SCHEN STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-90-00-00
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Schoharie Center:
  -       Reconstruction               0-001-004                                              /  /       /  /     03/19/10     /  /     2,7                            0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Albany Vo-Tec Center Bldg. A:
09-1374   Reconstruction               0-007-005  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      350,650       350,650  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Center Bldg. B:
09-1375   Reconstruction               0-008-007  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      309,000       309,000  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Center Bldg. C:
09-1376   Reconstruction               0-009-005  06/22/10     DONE    DONE       DONE      05/03/10   04/20/10   03/19/10   04/20/09   2,7                      301,700       301,700  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany VOTECH Building D:
09-1377   Reconstruction               0-010-003  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,4,7                    344,650       344,650  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Voc-Tech Center Bldg.E:
09-1378   Reconstruction               0-011-004  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      251,000       251,000  JOD             0           0           0 Griffith Dardanelli,Architect           0      08/31/11                         /  /             

          Albany Center Bldg. F:
09-1379   Reconstruction               0-012-003  06/22/10     DONE    DONE       DONE      05/03/10   04/26/10   03/19/10   04/20/09   2,7                      141,400             0  JOD             0           0           0 Griffith Dardanelli,Architect           0        /  /                           /  /             

          Maywood School:
09-0665   Reconstruction               0-018-012  01/26/10     DONE    DONE       DONE      12/30/09   12/21/09   11/02/09   02/12/09   2,4,8,9                  255,000       255,000  JOD             0           0           0 Griffith Dardanelli,Architect           0      07/28/10                         /  /             

          NERIC Offices:
12-1305TQ Temporary Quarters           1-061-001  09/19/13     DONE    DONE       DONE      06/19/13   06/17/13   07/27/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Science Kit Program:
10-0543TQ Temporary Quarters           7-059-001  09/16/11     DONE    DONE       DONE      12/06/10   11/22/10   04/27/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Alburtus Hall Rm106 St. Rose:
10-0432TQ Temporary Quarters           8-060-001  11/18/10     DONE    DONE       DONE      11/05/10   11/01/10   09/01/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Rosewood Plaza Nursing 2:
  -    TQ Temporary Quarters           8-061-001                                              /  /       /  /     02/05/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Tech Valley HS @ CSNE NanoFab East:
13-1489TQ Temporary Quarters           8-062-001  07/25/14     DONE    DONE       DONE      04/28/14   04/28/14   01/31/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Text Books/Science Kits:
  -    TQ Temporary Quarters           8-063-001                                              /  /       /  /     10/10/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED