Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 06/17/13 at 15:21:06




ALFRED ALMOND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-01-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
08-0062   Reconstruction               0-001-006  01/13/09     DONE    DONE       DONE      07/21/08   07/10/08   03/05/07   11/13/07   2,4,8,9,10,13,155,15   2,428,425     2,428,425  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        
08-0063   Reconstruction               0-001-007  01/13/09     DONE    DONE       DONE      07/21/08   07/10/08   03/14/08   11/13/07   2,9,10,15,16           3,802,483     3,802,483  JOD             0           0     222,078 Hunt Engineers,                         0        /  /             /  /        
09-1125   Reconstruction               0-001-008  04/27/10     DONE    DONE       DONE      03/25/10   03/16/10   09/18/09   12/08/09   2,7                    3,468,755     3,468,755  JOD             0           0           0 Hunt Engineers,                         0        /  /           11/28/12      
09-1229   Reconstruction               0-001-009  08/17/10     DONE    DONE       DONE      04/05/10   03/31/10   03/15/10   11/13/07   16                        90,300        90,300  JOD             0           0           0 Hunt Engineers,                         0        /  /           11/28/12      
11-0872   Reconstruction               0-001-010  07/06/12     DONE    DONE       DONE      03/05/12   02/29/12   01/10/12   12/06/11   2,4,8,9,10,155,15,16     735,149             0  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        
  -    XX Reconstruction               0-001-011                         CANCELLED            /  /       /  /     02/02/12     /  /     2,4,8,9,10,155,15,16           0    18,940,728  JOD             0           0           0                                         0        /  /             /  /        
12-0534   Reconstruction               0-001-012               DONE    DONE       UNREVIEWED12/12/12   12/03/12   02/02/12   12/06/11   2,4,8,9,10,155,15,16           0    19,427,790  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        
  -       Reconstruction               0-001-013                                              /  /       /  /     02/02/12     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0           0                                         0        /  /             /  /        
12-0299   Reconstruction               0-001-014  11/16/12     DONE    DONE       DONE      10/19/12   10/19/12   09/25/12   12/06/11   2,155,15,16              100,000       100,000  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        
  -    XX Reconstruction               0-001-015                         CANCELLED            /  /       /  /     02/02/12     /  /     2,4,7,8,9,10,155,15,           0    18,940,728  JOD             0           0           0                                         0        /  /             /  /        
12-1240   Reconstruction               0-001-016                         UNREVIEWED         06/03/13   06/03/13   05/09/13   05/21/13   155,15,16                      0             0  MFS             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          Athletic Field Storage Building:
08-0090   New Construction             2-007-001  01/13/09     DONE    DONE       DONE      07/24/08   07/10/08   07/17/08   11/13/07   02 - 16                   60,000             0  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          Bus Garage:
08-0064   Reconstruction               5-002-004  01/13/09     DONE    DONE       DONE      07/21/08   07/10/08   03/05/07   11/13/07   2,9,10,13,15,16          313,542       313,542  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        
09-1126   Reconstruction               5-002-005  04/27/10     DONE    DONE       DONE      03/25/10   03/16/10   09/18/09   12/08/09   2,7,10                   231,245       231,245  JOD             0           0           0 Hunt Engineers,                         0        /  /           01/07/13      
09-1230   Reconstruction               5-002-006  08/17/10     DONE    DONE       DONE      04/05/10   03/31/10   03/15/10   11/13/07   15,16                     77,635        77,635  JOD             0           0           0 Hunt Engineers,                         0        /  /           03/14/13      

          New Concession Stand:
08-0065   New Construction             7-006-001  01/13/09     DONE    DONE       DONE      07/21/08   07/10/08   04/24/07   11/13/07   02 - 16                  195,550             0  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ANDOVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-06-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MAIN BUILDING:
07-1326   Reconstruction               0-001-006  08/05/08     DONE    DONE       DONE      01/04/08   01/02/08   08/15/06   03/27/07   2,4,7,8,9,10,155,15,   3,446,470     3,446,470  HCM             0           0      68,382 Habiterra Associates                    0        /  /             /  /        
11-1284   Reconstruction               0-001-007  09/21/12     DONE    DONE       DONE      05/09/12   05/02/12   02/17/12   02/14/12   2,4,8,9,16               990,750             0  HCM             0           0      33,685 Habiterra Associates                    0        /  /             /  /        

          Bus Garage Maintenance:
07-1327   Reconstruction               5-002-002  08/05/08     DONE    DONE       DONE      01/04/08   01/02/08   08/15/06   03/27/07   4,7,8,155,15,16          183,530       183,530  HCM             0           0           0 Habiterra Associates                    0        /  /             /  /        
11-1285   Reconstruction               5-002-003  09/21/12     DONE    DONE       DONE      05/09/12   05/02/12   02/17/12   02/14/12   7,16                      75,500             0  HCM             0           0           0 Habiterra Associates                    0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENESEE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-07-02-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Pre-K-12:
12-0153   Additions and Alterations    0-012-003  03/04/13     DONE    DONE       DONE      09/05/12   09/05/12   02/21/08   02/16/12   02 - 16                5,695,000             0  DDJ             0           0     120,000 Clark Patterson Lee                     0        /  /             /  /        
10-0141   Reconstruction               0-012-004  08/24/10     DONE    DONE       DONE      08/24/10   08/16/10   07/20/10   07/26/10   15,16                    160,000             0  DDJ             0           0           0 Habiterra Associates                    0        /  /             /  /        

          Track Storage:
10-1416DB Discovered Building          2-015-001  08/01/11     DONE    DONE       DONE      06/23/11   06/20/11   02/28/08     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        

          TRANSPORATION STORAGE:
  -       New Construction             4-019-001                                              /  /       /  /     08/27/08     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        

          New Bus Garage:
12-0154   Reconstruction               5-011-003  03/04/13     DONE    DONE       DONE      09/13/12   09/05/12   09/13/12   02/16/12   2,4,7,8,9,10,13,155,     994,000       994,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        

          Consessions & Restroom:
12-0155   New Construction             7-018-001  03/04/13     DONE    DONE       DONE      09/05/12   09/05/12   05/27/08   02/16/12   02 - 16                  150,000             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BELFAST CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-08-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-1962   Additions and Alterations    0-001-009  11/04/08     DONE    DONE       DONE      04/15/08   04/04/08   02/12/07   06/21/07   02 - 16                9,455,542     8,682,512  MGL             0           0     332,299 Clark Patterson Lee                     0        /  /             /  /        

          Steel Storage Bldg.:
07-1963   Reconstruction               2-003-001  11/04/08     DONE    DONE       DONE      04/15/08   04/04/08   02/12/07   06/21/07   7,16                      18,750             0  MGL             0           0           0 Clark Patterson Lee                     0        /  /             /  /        

          New Bus Garage:
07-1964   Reconstruction               5-007-002  11/04/08     DONE    DONE       DONE      04/15/08   04/04/08     /  /     06/21/07                          3,262,122     3,262,122                  0           0           0 Clark Patterson Lee                     0        /  /             /  /        

          Growing Dome:
10-1130   New Construction             7-008-001                       ADDENDUM REQ'D       04/04/11   03/29/11   01/21/11   06/21/07   02 - 16                        0             0  HCM             0           0           0 Clark Patterson Lee                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CANASERAGA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-11-02-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-0427   Reconstruction               0-001-004  03/16/11     DONE    DONE       DONE      11/05/10   10/26/10   11/27/07   06/15/10   2,4,7,8,9,10,155,15,   2,468,846     2,468,846  DDJ             0           0     118,944 SWBR Architects P.C.                    0        /  /             /  /        
  -       Reconstruction               0-001-005                                              /  /       /  /     09/10/10     /  /     7                              0             0  DDJ             0           0           0                                         0        /  /             /  /        
10-0400   Reconstruction               0-001-006  12/07/10     DONE    DONE       DONE      10/29/10   10/19/10   09/20/10   06/05/10   7                        652,050       652,050  DDJ             0           0      32,716 SWBR Architects P.C.                    0        /  /           06/22/12      
12-0404   Reconstruction               0-001-007  02/25/13     DONE    DONE       DONE      11/07/12   11/07/12   09/26/12   06/15/10   2,4,7,8,9,10,155,15,   1,430,500             0  DDJ             0           0      69,354 SWBR Architects P.C.                    0        /  /             /  /        

          Bus Garage(fmly Indust. Arts Bus Gar:
10-0428   Additions and Alterations    5-002-004  03/16/11     DONE    DONE       DONE      11/05/10   10/26/10   07/17/09   06/15/10   02 - 16                2,703,091     2,703,091  DDJ             0           0           0 SWBR Architects P.C.                    0        /  /             /  /        
  -       Reconstruction               5-002-005                                              /  /       /  /     09/10/10     /  /     7                              0             0  DDJ             0           0           0                                         0        /  /             /  /        
10-0401   Reconstruction               5-002-006  12/07/10     DONE    DONE       DONE      10/29/10   10/19/10   09/20/10   06/15/10   7                         73,987        73,987  DDJ             0           0           0 SWBR Architects P.C.                    0        /  /           02/19/13      
12-0405   Reconstruction               5-002-007  02/25/13     DONE    DONE       DONE      11/07/12   11/07/12   09/26/12   06/15/10   9,155,15,16               19,500             0  DDJ             0           0           0 SWBR Architects P.C.                    0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FRIENDSHIP CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-16-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
08-0066   Reconstruction               0-001-018  05/18/09     DONE    DONE       DONE      07/21/08   07/11/08   02/01/07   08/29/07   2,4,7,8,9,10,13,155,   8,307,755     8,121,444  HCM             0           0     282,294 Clark Patterson Lee                     0        /  /             /  /        
09-0163   Reconstruction               0-001-020  09/10/09     DONE    DONE       DONE      08/25/09   08/24/09   08/05/09   08/29/07   2                        180,150       180,150  HCM             0           0           0 Clark Patterson Lee                     0        /  /           10/01/12      

          New Bus Garage:
08-0067   Additions and Alterations    5-005-002  05/18/09     DONE    DONE       DONE      08/04/08   07/30/08   07/09/08   08/29/07   02 - 16                1,804,420     1,804,420  HCM             0           0           0 Clark Patterson Lee                     0        /  /           10/01/12      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FILLMORE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-20-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Fillmore Main Building:
10-1017   Reconstruction               0-001-007  05/23/11     DONE    DONE       DONE      03/09/11   03/08/11   02/10/11   01/13/05   2,16                      52,700        52,700  HCM             0           0           0 Habiterra Associates                    0        /  /             /  /        
  -       Reconstruction               0-001-008                                              /  /       /  /     06/14/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WHITESVILLE CENTRAL SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-21-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-1404   Reconstruction               0-001-008  09/13/10     DONE    DONE       DONE      05/07/10   05/03/10   04/02/10   12/21/06   155                      122,550       122,550  HCM             0           0       2,451 Hunt Engineers,                         0        /  /             /  /        

          New Bus Garage:
09-1405   Reconstruction               5-009-002  09/13/10     DONE    DONE       DONE      05/07/10   05/03/10   04/02/10   12/20/06   155                       12,875        12,875  HCM             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          Concession Building:
11-0949DB Discovered Building          7-010-001  04/16/12     DONE    DONE       DONE      ***ASBESTOS CERTIFICATION MISSING***                                                     0  HCM             0           0           0 Hunt Engineers,                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CUBA-RUSHFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-23-02-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cuba Campus K-5 Bldg:
10-1207   Reconstruction               0-001-010  02/02/12     DONE    DONE       DONE      04/20/11   04/15/11   02/26/10   12/07/10   7,8,9,10,155,15,16     4,521,640             0  HCM             0           0     303,597 Clark Patterson Lee                     0        /  /             /  /        

          Rushford K-5 Building:
10-1208   Reconstruction               0-015-011  02/02/12     DONE    DONE       DONE      04/20/11   04/15/11   02/26/10   12/07/10   7,8,9,10,155,15,16     1,708,130     1,708,130  HCM             0           0     128,608 Clark Patterson Lee                     0        /  /             /  /        

          New MS/HS 6-12:
10-1209   Reconstruction               0-020-006  02/02/12     DONE    DONE       DONE      04/20/11   04/15/11   02/26/10   12/07/10   7,8,9,10,13,155,15,1   4,560,888             0  HCM             0           0     310,995 Clark Patterson Lee                     0        /  /             /  /        

          Storage Building:
  -    PR New Construction             2-026-001                                              /  /       /  /     06/07/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /             /  /        
12-0131   New Construction             2-026-001  05/28/13     DONE    DONE       DONE      08/31/12   08/31/12   06/07/11   12/07/10   02 - 16                   24,300             0  HCM             0           0           0 Clark Patterson Lee                     0        /  /             /  /        

          New Bus Garage '96:
10-1210   Additions and Alterations    5-021-002  02/02/12     DONE    DONE       DONE      04/20/11   04/15/11   01/23/07   12/07/10   02 - 16                   85,042        85,042  HCM             0           0           0 Clark Patterson Lee                     0        /  /             /  /        

          Press Box:
  -    DB Discovered Building          7-024-001                                              /  /       /  /     12/29/08     /  /                                    0             0  HCM             0           0           0                                         0        /  /             /  /        

          Fish Hatchery:
  -    DB Discovered Building          7-025-001                                              /  /       /  /     12/29/08     /  /                                    0             0  HCM             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCIO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-24-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-0278   Reconstruction               0-001-014  08/25/09     DONE    DONE       DONE      10/02/09   10/02/09   08/25/09   08/25/09   4,8                       85,840        85,840  HCM             0           0           0 Clark Patterson Lee                     0        /  /             /  /        
11-0384   Additions and Alterations    0-001-015  07/07/11     DONE    DONE       DONE      11/15/11   11/14/11   07/21/11   06/15/11   02 - 16                  103,500       103,500  HCM             0           0           0 Clark Patterson Lee                     0        /  /           06/29/12      
  -    PR Additions and Alterations    0-001-016                                              /  /       /  /     07/26/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /             /  /        

          Bus Garage:
11-0385   Reconstruction               5-002-006  07/27/11     DONE    DONE       DONE      11/15/11   11/14/11   08/29/05   06/15/11   15                        59,880        59,880  HCM             0           0           0 Clark Patterson Lee                     0        /  /           06/29/12      
  -       Reconstruction               5-002-007                                              /  /       /  /     08/19/11     /  /     7                              0             0  HCM             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WELLSVILLE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-26-01-06
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Washington Primary/Inter.:
08-0696XX Reconstruction               0-003-008                         CANCELLED          11/05/08   11/04/08   11/14/07   02/12/08   2,4,7,8,9,10,155,15,           0    14,610,174  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        
08-0697   Reconstruction               0-003-009  04/29/09     DONE    DONE       DONE      11/05/08   11/04/08   06/04/08   02/12/08   2,4,7,8,9,10,155,15,   7,534,945     7,534,945  DDJ             0           0     318,531 Hunt Engineers,                         0        /  /             /  /        
09-1329   Reconstruction               0-003-010  10/28/10     DONE    DONE       DONE      04/16/10   04/15/10   07/13/09   05/19/09   2,4,7,8,9,10,155,15,     596,073       596,073  DDJ             0           0     596,073 Hunt Engineers,                         0        /  /             /  /        
10-0360   Reconstruction               0-003-011  04/14/11     DONE    DONE       DONE      10/14/10   10/06/10   03/19/10   02/12/08   2,4,7,8,9,10,155,15,   2,926,372     2,926,372  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          High School/Middle School:
08-0698   Reconstruction               0-004-012  04/29/09     DONE    DONE       DONE      11/05/08   11/04/08   11/14/07   02/12/08   2,4,7,8,9,10,155,15,   3,703,336     3,703,336  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        
08-0699   Reconstruction               0-004-013  04/29/09     DONE    DONE       DONE      11/05/08   11/04/08   06/04/08   02/12/08   2,4,7,8,9,10,155,15,   2,693,782     2,693,782  DDJ             0           0     150,000 Hunt Engineers,                         0        /  /             /  /        
10-0361   Reconstruction               0-004-014  04/14/11     DONE    DONE       DONE      10/14/10   10/06/10   07/13/09   02/12/08   2,4,7,8,9,10,155,15,   1,344,119     1,344,119  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        
12-0351   Reconstruction               0-004-015  11/02/12     DONE    DONE       DONE      10/30/12   10/22/12   10/24/12   02/12/08   2,7,155,16               113,200       113,200  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          New Bus Garage:
08-1514   New Construction             5-011-001  10/27/09     DONE    DONE       DONE      04/16/09   04/16/09   11/14/07   02/12/08   02 - 16                5,880,718     5,880,718  DDJ             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          Temporary Bus garage:
09-1609TQ Temporary Quarters           5-013-001  12/07/10     DONE    DONE       DONE      07/06/10   05/10/10   06/02/10     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Press Box (New):
09-0790   New Construction             7-012-001  05/27/10     DONE    DONE       DONE      01/25/10   01/22/10   10/27/09   02/12/08   02 - 16                  190,000             0  DDJ             0           0           0 Hunt Engineers,                         0        /  /           08/06/12      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOLIVAR-RICHBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-29-02-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bolivar 6-12 Building:
09-0562   Reconstruction               0-001-021  11/05/09     DONE    DONE       DONE      12/07/09   12/04/09   10/15/09   05/15/07   4                         17,125        19,000  HCM             0           0      17,125 Clark Patterson Lee                     0        /  /             /  /        
09-1575   Reconstruction               0-001-022  08/03/10     DONE    DONE       DONE      07/02/10   06/22/10   04/20/10   05/15/07   4                        231,940       300,000  HCM             0           0     231,940 Clark Patterson Lee                     0        /  /             /  /        

          Richburg K-5 Building:
11-0642   Reconstruction               0-011-013  04/24/12     DONE    DONE       DONE      01/11/12   01/09/12   03/25/11   05/15/07   2,15,16                  350,000       350,000  HCM             0           0           0 Clark Patterson Lee                     0        /  /           06/10/13      

          Richburg Bus Garage:
09-0529   Reconstruction               5-012-008  02/22/08     DONE    DONE       DONE      11/30/09   11/23/09   10/30/07   05/15/07   4,15,16                   80,800       107,000  HCM             0           0           0 Clark Patterson Lee                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED