Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 03/27/24 at 07:54:53




ALFRED ALMOND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-01-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
19-0336   Reconstruction               0-001-023  09/26/18     DONE    DONE       DONE      08/30/19   08/13/19   11/14/18   09/12/18   155                       40,000        40,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/15/18                       08/13/19           
18-1654   Reconstruction               0-001-024  05/20/19     DONE    DONE       DONE      03/15/19   03/01/19   11/27/18   11/04/14   8,16                     609,287       609,287  SLC             0           0           0 Hunt Engineers,Architects & l           0      06/06/22                       03/01/19           
19-1251   Reconstruction               0-001-025  02/13/20     DONE    DONE       DONE      01/22/20   01/14/20   08/12/19   05/21/19   9,16                     100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      01/11/21                       01/14/20           
19-1571   Reconstruction               0-001-026  06/05/20     DONE    DONE       DONE      03/13/20   03/03/20   11/25/19   05/21/19   2,4,7,8,9,10,155,15,   3,433,080     3,433,080  JSS             0           0           0 Hunt Engineers,Architects & l           0      09/02/21                       03/03/20           
19-1555   Reconstruction               0-001-027  05/01/20     DONE    DONE       DONE      03/11/20   02/28/20   11/25/19   05/21/19   8,155,15,16              755,105       755,105  JLB             0           0           0 Hunt Engineers,Architects & l     755,105      04/30/21                       02/28/20           
20-1523   Reconstruction               0-001-028  05/27/21     DONE    DONE       DONE      04/01/21   03/31/21   03/05/21   06/09/20   9,16                     100,000       100,000  JSS             0           0           0 Hunt Engineers,Architects & l           0      02/28/22                       03/31/21           
21-1743   Reconstruction               0-001-029  07/26/22     DONE    DONE       DONE      05/02/22   04/28/22   04/05/22   05/18/21   16                       100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0      05/31/23                       04/28/22           
22-1130   Reconstruction               0-001-030  02/07/23     DONE    DONE       DONE      12/02/22   11/30/22   10/03/22   05/17/22   2,7,8,9,155,15,16      4,340,000     4,340,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/30/22           
22-2209   Reconstruction               0-001-031  06/13/23     DONE    DONE       DONE      05/15/23   05/15/23   04/20/23   05/17/22   16                       100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         05/15/23           
22-2214   Reconstruction               0-001-032  06/13/23     DONE    DONE       DONE      05/15/23   05/15/23   04/20/23   05/16/23   16                       100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         05/15/23           
23-1377   Reconstruction               0-001-033                         UNREVIEWED         01/16/24   01/16/24   06/05/23   02/07/23   14                       150,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/16/24           
23-1041   Reconstruction               0-001-034                         UNREVIEWED         11/17/23   11/15/23   06/05/23   03/16/23   155,16                   215,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/15/23           
23-1408   Reconstruction               0-001-035               DONE    DONE       UNREVIEWED01/24/24   01/22/24   12/07/23   05/16/23   8,9,10                   100,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/22/24           

          Bus Garage:
19-1572   Reconstruction               5-002-007  06/05/20     DONE    DONE       DONE      03/13/20   03/03/20   11/25/19   05/21/19   8,9,15,16                182,500       182,500  JSS             0           0           0 Hunt Engineers,Architects & l           0      09/02/21                       03/03/20           
19-1556   Reconstruction               5-002-008  05/01/20     DONE    DONE       DONE      03/11/20   02/28/20   11/25/19   05/21/19   16                        14,895        14,895  JLB             0           0           0 Hunt Engineers,Architects & l      14,895      04/30/21                       02/28/20           
19-1873   Reconstruction               5-002-009  09/11/19     DONE    DONE       DONE      06/25/20   06/19/20   04/10/20   09/11/19   14,16                    200,000       200,000  JSS             0           0           0 Hunt Engineers,Architects & l           0      11/02/20                       06/19/20           
22-1131   Reconstruction               5-002-010  02/07/23     DONE    DONE       DONE      12/02/22   11/30/22   10/03/22   05/17/22   2,16                     815,000       815,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/30/22           

          Concession Stand:
22-1132   Reconstruction               7-006-002  02/07/23     DONE    DONE       DONE      12/02/22   11/30/22   10/13/22   05/17/22   16                        45,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/30/22           

          Classroom Pavillion:
21-0709FB New Construction             7-010-001  03/09/22     DONE    DONE       DONE      11/15/21   11/15/21   09/30/21   11/10/21   02 - 16                  696,328             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/15/21           

          Main Pavillion:
21-0710FB New Construction             7-011-001  03/09/22     DONE    DONE       DONE      11/15/21   11/15/21   09/30/21   11/10/21   02 - 16                  924,678             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/15/21           

          Amphitheater:
21-0711XX New Construction             7-012-001                         CANCELLED          11/15/21   11/15/21   09/30/21   11/10/21   02 - 16                  940,539             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/15/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ANDOVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-06-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
18-2029   Reconstruction               0-001-013  07/09/19     DONE    DONE       DONE      05/30/19   04/03/19   02/26/19   05/21/19   8                        100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      04/21/20                       04/03/19           
19-1743   Reconstruction               0-001-014  07/13/20     DONE    DONE       DONE      05/22/20   05/11/20   03/10/20   06/09/20   8,9,155,15,16            100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      03/01/21                       05/11/20           
20-0001   Reconstruction               0-001-015  08/26/20     DONE    DONE       DONE      07/01/20   06/16/20   05/15/20   05/16/17   7,155,15,16              154,700       154,700  SLC             0           0           0 Clark Patterson Lee                     0      05/01/21                       06/16/20           
20-1729   Reconstruction               0-001-016  07/16/21     DONE    DONE       DONE      05/18/21   05/12/21   03/09/21   05/18/21   2,8,9,155,15,16          100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      06/15/22                       05/12/21           
21-1605   Reconstruction               0-001-017  06/01/22     DONE    DONE       DONE      04/06/22   04/05/22   03/22/22   05/17/22   8,9,155,16               100,000       100,000  WLC             0           0           0 Clark Patterson Lee                     0      10/04/22                       04/05/22           
21-1961   Reconstruction               0-001-018  11/29/22     DONE    DONE       DONE      06/10/22   06/10/22   05/11/22   05/16/17   7,9,155,16               778,626       778,626  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         06/10/22           
22-2000   Reconstruction               0-001-019  07/19/23     DONE    DONE       DONE      04/05/23   04/04/23   03/02/23   05/16/23   8                        100,000       100,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         04/04/23           
  -       Reconstruction               0-001-020                                              /  /       /  /     05/22/23     /  /     15                             0             0  WLC             0           0           0                                         0        /  /                           /  /             
23-0410   Reconstruction               0-001-021  03/21/24     DONE    DONE       DONE      09/06/23   08/30/23   05/22/23   12/06/22   7,8,9,16               2,695,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/30/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENESEE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-07-02-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pre-K-12 Main Campus:
18-1779   Reconstruction               0-012-013  07/10/19     DONE    DONE       DONE      04/02/19   03/13/19   03/05/19   05/21/19   8,9,10,155,15,16         100,000       100,000  BMJ             0           0           0 Collins & Scoville Architects           0      06/19/20                       03/13/19           
19-1754   Reconstruction               0-012-014  10/07/19     DONE    DONE       DONE      05/22/20   05/11/20   05/16/19   04/01/19   4,8,9,13,155,15,16       452,519       452,519  JLB             0           0           0 Hunt Engineers,Architects & l           0      03/01/20                       05/11/20           
19-1615   Reconstruction               0-012-015  07/23/20     DONE    DONE       DONE      03/20/20   02/19/20   02/13/20   05/19/20   8,10                     100,000       100,000  JSS             0           0           0 Hunt Engineers,Architects & l           0      06/08/21                       02/19/20           
19-1568   Reconstruction               0-012-016  05/19/20     DONE    DONE       DONE      03/13/20   03/03/20   02/25/20   10/12/16   8,9,155,15,16            275,000       275,000  JSS             0           0           0 Hunt Engineers,Architects & l           0      06/08/21                       03/03/20           
20-1519   Reconstruction               0-012-017  05/20/21     DONE    DONE       DONE      04/01/21   03/31/21   03/12/21   05/18/21   2,8,9,16                 100,000       100,000  JSS             0           0           0 Hunt Engineers,Architects & l           0      06/01/22                       03/31/21           
21-0406FC Reconstruction               0-012-018  03/05/22     DONE    DONE       DONE      09/23/21   09/22/21   08/24/21   02/14/22   8,9,16                   391,200             0  SLC             0           0           0 Hunt Engineers,Architects & l           0      08/19/22                       09/22/21           
22-1268FA Reconstruction               0-012-019  03/08/23     DONE    DONE       DONE      12/15/22   12/13/22   03/02/22   02/14/22   2,155,16                 585,584       585,584  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         12/13/22           
  -       Reconstruction               0-012-020                                              /  /       /  /     10/20/22     /  /     7,155,16                       0             0  SLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-012-021                                              /  /       /  /     03/19/24     /  /     2,7,8,9,10,155,15,16           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Storage Building:
  -       New Construction             2-020-001                                              /  /       /  /     03/19/24     /  /     02 - 16                        0             0  MSK             0           0           0                                         0        /  /                           /  /             

          2002 Bus Garage:
22-0644   Reconstruction               5-011-005  12/07/22     DONE    DONE       DONE      10/05/22   10/04/22   09/26/22   05/17/22   8,16                     100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      05/22/23                       10/04/22           
  -       Reconstruction               5-011-006                                              /  /       /  /     10/20/22     /  /     7,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-2294   Reconstruction               5-011-007  11/30/23     DONE    DONE       DONE      05/30/23   05/26/23   05/12/23   05/16/23   8,16                     100,000       100,000  MSK             0           0           0 Hunt Engineers,Architects & l           0      12/27/23                       05/26/23           
  -       Reconstruction               5-011-008                                              /  /       /  /     03/19/24     /  /     2,7,155,15,16                  0             0  MSK             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BELFAST CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-08-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
18-2199   Reconstruction               0-001-018  10/21/19     DONE    DONE       DONE      06/26/19   06/19/19   03/07/19   10/23/18   2,4,7,8,9,10,13,155,   5,160,535     5,160,535  SLC             0           0           0 Clark Patterson Lee                     0      11/30/20                       06/19/19           
18-1874   Reconstruction               0-001-019  06/14/19     DONE    DONE       DONE      04/18/19   04/08/19   03/15/19   05/21/19   2,9                      100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      06/05/20                       04/08/19           
19-1362SB Reconstruction               0-001-020               DONE                           /  /       /  /     02/05/20     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             
20-0020   Reconstruction               0-001-020  10/26/20     DONE    DONE       DONE      07/06/20   06/26/20   02/05/20   11/04/14   16                       251,939       251,939  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         06/26/20           
19-1776   Reconstruction               0-001-021  09/23/20     DONE    DONE       DONE      05/27/20   05/19/20   02/24/20   06/09/20   2,9,10,15,16              83,000        83,000  SLC             0           0           0 Clark Patterson Lee                     0      04/20/21                       05/19/20           
20-1560   Reconstruction               0-001-022  06/09/21     DONE    DONE       DONE      04/06/21   04/01/21   02/22/21   05/18/21   2,9,10                   100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      06/30/21                       04/01/21           
21-1581FB Reconstruction               0-001-023  05/10/22     DONE    DONE       DONE      03/30/22   03/10/22   01/19/22   09/14/21   7,9,155,15,16          1,324,763     1,324,763  FMJ             0           0           0 Clark Patterson Lee                     0        /  /                         03/10/22           
21-1606   Reconstruction               0-001-024  06/02/22     DONE    DONE       DONE      04/06/22   04/05/22   03/14/22   05/17/22   2,9,10                   100,000       100,000  WLC             0           0           0 Clark Patterson Lee                     0      05/01/23                       04/05/22           
22-0081PR Reconstruction               0-001-025                         UNREVIEWED         07/13/22   07/13/22   04/20/22     /  /     2,4,7,8,9,10,155,15,           0    19,903,516  WLC             0           0           0                                         0        /  /                         07/13/22           
  -       Reconstruction               0-001-026                                              /  /       /  /     05/10/22     /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-1408   Reconstruction               0-001-027  05/02/23     DONE    DONE       DONE      01/06/23   01/04/23   11/30/22   11/02/22   2,7                    1,315,600     1,315,600  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         01/04/23           
22-2313   Reconstruction               0-001-028  10/18/23     DONE    DONE       DONE      06/02/23   05/31/23   01/26/23   11/02/22   2,4,8,9,10,14,155,15   3,902,200     3,902,200  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/31/23           
22-2024   Reconstruction               0-001-029  07/20/23     DONE    DONE       DONE      04/12/23   04/11/23   02/24/23   05/16/23   8                        100,000       100,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         04/11/23           
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          New Bus Garage:
22-2314   Reconstruction               5-007-006  10/18/23     DONE    DONE       DONE      06/02/23   05/31/23   01/26/23   11/02/22   10                         7,200             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/31/23           

          Grandstand/Bleachers:
19-1854SB Reconstruction               7-004-005               DONE                           /  /       /  /     06/17/20     /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             
20-0021XX Reconstruction               7-004-005                         CANCELLED          07/06/20   06/26/20   06/17/20   11/04/14   8,16                           0             0  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         06/26/20           
  -    SB Reconstruction               7-004-BA1               DONE                           /  /       /  /       /  /       /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXGrowing Dome - sold 11/1/19:
19-0652   Reconstruction               7-008-002  10/21/19     DONE    DONE       DONE      11/01/19   11/01/19   09/06/19   10/23/18                              1,000             0  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         11/01/19           

          Greenhouse:
18-2200   New Construction             7-009-001  09/12/19     DONE    DONE       DONE      06/26/19   06/19/19   03/08/19   10/23/18   02 - 16                   57,500             0  SLC             0           0           0 Clark Patterson Lee                     0      11/30/20                       06/19/19           
19-1777XX Reconstruction               7-009-002  09/23/20               CANCELLED          05/27/20   05/19/20   02/24/20   06/09/20   15,16                     17,000             0  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/19/20           

          Concession Stand:
20-1181DB Discovered Building          7-010-001               UNREVIEWED
                                                                       DONE       DONE      01/25/21   01/22/21     /  /       /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/22/21           

          Athletic Restroom Building:
22-2315   New Construction             7-012-001  10/18/23     DONE    DONE       DONE      06/02/23   05/31/23   01/26/23   11/02/22   02 - 16                  275,000             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/31/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CANASERAGA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-11-02-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
20-0293   Reconstruction               0-001-008  01/06/21     DONE    DONE       DONE      09/01/20   07/30/20   01/07/20   12/19/19   2,4,7,8,9,10,155,15,   4,651,037     4,651,037  JSS             0           0           0 LaBella Associates P.C.                 0      01/22/22                       07/30/20           
20-0293SB Reconstruction               0-001-008                         UNREVIEWED         07/30/20   07/30/20   01/07/20   12/19/19   2,4,7,8,9,10,155,15,   4,651,037     4,651,037  JSS             0           0           0 LaBella Associates P.C.                 0      01/22/22                       07/30/20           
22-1564   Reconstruction               0-001-009  06/20/23     DONE    DONE       DONE      01/27/23   01/24/23   10/28/22   03/03/22   2,155,15,16              105,000       105,000  JJH             0           0           0 LaBella Associates P.C.                 0        /  /                         01/24/23           
23-0700   Reconstruction               0-001-010               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/13/23   10/05/23   09/08/23   12/15/22   2,4,8,9,155,15,16              0             0  JJH             0           0           0 LaBella Associates P.C.                 0        /  /                         10/05/23           

          Bus Garage(fmly Indust. Arts Bus Gar:
20-0294   Reconstruction               5-002-008  01/06/21     DONE    DONE       DONE      09/01/20   07/30/20   01/07/20   12/19/19   2,4,8,9,155,15,16        215,862       215,862  JSS             0           0           0 LaBella Associates P.C.                 0      01/22/22                       07/30/20           
20-0294SB Reconstruction               5-002-008                         UNREVIEWED         07/30/20   07/30/20   01/07/20   12/19/19   2,4,8,9,155,15,16        204,098       204,098  JSS             0           0           0 LaBella Associates P.C.                 0      01/22/22                       07/30/20           
23-0701   Reconstruction               5-002-009               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/13/23   10/05/23   09/08/23   12/15/22   2,4,7,8,9,155,15,16            0             0  JJH             0           0           0 LaBella Associates P.C.                 0        /  /                         10/05/23           

          District-Wide:
  -       Reconstruction               7-999-002                                              /  /       /  /     04/21/20     /  /     16                             0             0  JSS             0           0           0                                         0        /  /                           /  /             
19-1701SB Reconstruction               7-999-002               DONE                           /  /       /  /     04/21/20     /  /     16                             0             0  JSS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FRIENDSHIP CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-16-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
20-0945   Reconstruction               0-001-021  04/09/21     DONE    DONE       DONE      12/10/20   12/07/20   08/19/20   03/12/20   2,4,7,8,9,155,15,16    2,140,000     2,140,000  JSS             0           0           0 Clark Patterson Lee                     0      09/30/22                       12/07/20           
22-0594FA Reconstruction               0-001-022  10/25/22     DONE    DONE       DONE      09/28/22   09/12/22     /  /     08/16/22   2                        126,000       126,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         09/12/22           
  -       Reconstruction               0-001-023                                              /  /       /  /     02/27/24     /  /     155,16                         0             0  JJH             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JSS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FILLMORE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-20-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
18-1909   Reconstruction               0-001-012  08/14/19     DONE    DONE       DONE      04/29/19   04/19/19   03/19/19   05/21/19   10,16                    100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      03/09/20                       04/19/19           
19-0913   Reconstruction               0-001-013  03/05/20     DONE    DONE       DONE      12/03/19   11/13/19   09/13/19   05/21/19   2,4,7,8,9,10,155,15,   2,852,400     2,852,400  SLC             0           0           0 Clark Patterson Lee                     0      05/25/21                       11/13/19           
19-1848   Reconstruction               0-001-014  09/02/20     DONE    DONE       DONE      06/16/20   05/14/20   03/13/20   06/09/20   15                       100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      06/10/21                       05/14/20           
  -    PR Additions and Alterations    0-001-015                                              /  /       /  /     09/01/20     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
20-0834   Additions and Alterations    0-001-015  03/23/21     DONE    DONE       DONE      11/17/20   11/12/20   09/01/20   05/21/19   02 - 16                4,939,346     4,939,346  SLC             0           0           0 Clark Patterson Lee                     0      01/13/22                       11/12/20           
21-1329FA Reconstruction               0-001-016  03/24/22     DONE    DONE       DONE      02/18/22   12/23/21   11/18/21   05/21/19   2,4,7,9,155,16         2,088,273     2,088,273  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         12/23/21           
  -       Reconstruction               0-001-017                                              /  /       /  /     11/18/21     /  /     2,4,7,9,155,16                 0             0  SLC             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-001-018                                              /  /       /  /     04/04/23     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
23-0872   Additions and Alterations    0-001-018                         UNREVIEWED         11/03/23   11/01/23   04/04/23   05/16/23   02 - 16                        0             0  MSK             0           0           0 Clark Patterson Lee Architect           0        /  /                         11/01/23           

          Bus Garage:
20-0835   Reconstruction               5-002-004  03/23/21     DONE    DONE       DONE      11/17/20   11/12/20   09/01/20   05/21/19   2,4,7,8,9,14,155,15,     806,548       806,548  SLC             0           0           0 Clark Patterson Lee                     0      01/13/22                       11/12/20           
20-1852   Reconstruction               5-002-005  07/24/21     DONE    DONE       DONE      06/10/21   05/24/21   04/28/21   05/18/21   8,9                      100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      06/27/22                       05/24/21           
22-0233   Reconstruction               5-002-006  11/15/22     DONE    DONE       DONE      08/05/22   08/03/22   06/22/22   05/17/22   8,16                     100,000       100,000  SLC             0           0           0 Clark Patterson Lee Architect           0      05/26/23                       08/03/22           
22-2029   Reconstruction               5-002-007  06/06/23     DONE    DONE       DONE      04/14/23   04/13/23   03/17/23   05/16/23   8,16                     100,000       100,000  JLB             0           0           0 Clark Patterson Lee Architect           0        /  /                         04/13/23           
23-0873   Reconstruction               5-002-008                         UNREVIEWED         11/03/23   11/01/23   10/23/23   05/16/23   2,4,8,9,155,16                 0             0  MSK             0           0           0 Clark Patterson Lee Architect           0        /  /                         11/01/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WHITESVILLE CENTRAL SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-21-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
18-1913   Reconstruction               0-001-016  07/16/19     DONE    DONE       DONE      04/30/19   04/29/19   03/01/19   05/21/19   2,4,8,9,155,16           100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0      06/12/20                       04/29/19           
19-1774   Reconstruction               0-001-017  07/29/20     DONE    DONE       DONE      05/27/20   05/11/20   04/14/20   06/09/20   2,9,155,15,16            100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0      06/22/21                       05/11/20           
20-1581   Reconstruction               0-001-018  07/09/21     DONE    DONE       DONE      04/13/21   04/09/21   02/22/21   05/18/21   2,9,16                   100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         04/09/21           
21-1017FC Reconstruction               0-001-019  01/18/22     DONE    DONE       DONE      01/03/22   11/26/21   08/12/21   09/14/21   2                        192,277             0  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/26/21           
22-0681   Reconstruction               0-001-020  12/01/22     DONE    DONE       DONE      10/07/22   10/07/22   04/25/22   05/17/22   2,4,9,155,16             100,000       100,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         10/07/22           
22-0757FA Reconstruction               0-001-021  12/14/22     DONE    DONE       DONE      10/19/22   10/17/22   08/18/22   09/13/22   9,155,15,16              100,000       100,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/17/22           
22-1360   Reconstruction               0-001-022  05/02/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/22   10/18/22   2,9                      420,000       420,000  WLC             0           0           0                                         0        /  /                         12/23/22           
22-2356   Reconstruction               0-001-023  07/14/23     DONE    DONE       DONE      06/12/23   06/12/23   02/28/23   05/16/23   2,9,155,15,16            100,000       100,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         06/12/23           
22-2197   Reconstruction               0-001-024  10/26/23     DONE    DONE       DONE      05/12/23   05/09/23   04/10/23   10/18/22   2,4,7,8,9,155,15,16    2,530,000     2,530,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/09/23           

          New Bus Garage:
22-2198   Reconstruction               5-009-004  10/23/23     DONE    DONE       DONE      05/12/23   05/09/23   04/10/23   10/18/22   16                        50,000        50,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/09/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CUBA-RUSHFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-23-02-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cuba-Rushford Elementary:
21-0852PR Additions and Alterations    0-001-012               DONE                         12/07/21     /  /     10/15/21     /  /     02 - 16                        0    19,039,104  SLC             0           0           0                                         0        /  /                           /  /             
21-1835   Reconstruction               0-001-013  06/29/22     DONE    DONE       DONE      05/20/22   05/20/22   02/14/22   05/18/21   155,15,16                100,000       100,000  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                         05/20/22           
  -       Reconstruction               0-001-014                                              /  /       /  /     02/18/22     /  /     16                             0    15,782,865  SLC             0           0           0                                         0        /  /                           /  /             
22-2055   Reconstruction               0-001-015  09/18/23     DONE    DONE       DONE      04/19/23   04/17/23   01/09/23   12/13/22   2,4,7,9,155,15,16      2,500,000     2,500,000  MSK             0           0           0 SWBR Architects P.C.                    0        /  /                         04/17/23           
22-1965   Reconstruction               0-001-016  06/07/23     DONE    DONE       DONE      03/29/23   03/28/23   03/01/23   05/16/23   155,16                   100,000       100,000  JLB             0           0           0 SWBR Architects P.C.                    0        /  /                         03/28/23           

          Elm St Acad-LsdToBOCES,BusiOff,Stora:
  -       Alterations                  0-002-007                                              /  /       /  /     10/15/21     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-2056   Reconstruction               0-002-008  09/18/23     DONE    DONE       DONE      04/19/23   04/17/23   01/09/23   12/13/22   2,4,7,9,155,15,16      1,100,000     1,100,000  MSK             0           0           0 SWBR Architects P.C.                    0        /  /                         04/17/23           

          Cuba-Rushford Middle/High School:
18-1332   Reconstruction               0-020-013  04/01/19     DONE    DONE       DONE      01/24/19   01/22/19   11/09/18   09/25/18   16                       100,000       100,000  SLC             0           0           0 C&S Companies                           0      06/30/19                       01/22/19           
21-0161   Reconstruction               0-020-014  11/18/21     DONE    DONE       DONE      08/12/21   07/19/21   08/17/21   05/18/21   2,16                     100,000       100,000  SLC             0           0           0 Clark Patterson Lee                     0      06/15/22                       07/19/21           
21-0528   Reconstruction               0-020-015  03/16/22     DONE    DONE       DONE      10/15/21   10/13/21   08/17/21   12/15/16   2,8,10                   210,000       210,000  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/13/21           
21-0853PR Additions and Alterations    0-020-016               DONE                         12/07/21     /  /     10/15/21     /  /     02 - 16                        0    30,312,466  SLC             0           0           0                                         0        /  /                           /  /             
22-2057   Reconstruction               0-020-017  09/18/23     DONE    DONE       DONE      04/19/23   04/17/23   01/09/23   12/13/22   2,4,9,155,15,16        2,500,000     2,500,000  MSK             0           0           0 SWBR Architects P.C.                    0        /  /                         04/17/23           
  -       Reconstruction               0-020-018                                              /  /       /  /     12/13/23     /  /     16                             0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-020-019                                              /  /       /  /     02/16/24     /  /     2,4,8,155,15,16                0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Outdoor Wildlife Center:
22-0455DB Discovered Building          0-022-001                       STARTED              09/12/22     /  /     05/11/00     /  /     02 - 16                   73,900             0  SLC             0           0           0                                         0        /  /                           /  /             

          Cuba-Rushford Bus Garage:
  -       Reconstruction               5-021-004                                              /  /       /  /     01/09/23     /  /     2,4,155,15,16                  0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Concession Building @ HS:
22-0456DB Discovered Building          7-023-001                       DONE       DONE      09/12/22     /  /     01/23/07     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Press Box:
22-0457DB Discovered Building          7-024-001                       DONE       DONE      09/12/22     /  /     12/29/08     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Fish Hatchery:
22-0458DB Discovered Building          7-025-001                       STARTED              09/12/22     /  /     12/29/08     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          District-Wide:
19-1195   Reconstruction               7-999-001  02/19/20     DONE    DONE       DONE      01/10/20   01/09/20   01/14/19   11/04/14   9,16                   1,249,193     1,249,193  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                         01/09/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCIO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-24-01-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
19-1409   Reconstruction               0-001-020  05/15/20     DONE    DONE       DONE      02/13/20   02/11/20   12/17/19   06/08/17   2,9                      176,340       176,340  JSS             0           0           0 Clark Patterson Lee                     0      09/01/20                       02/11/20           
21-1887   Reconstruction               0-001-021  07/20/22     DONE    DONE       DONE      05/25/22   05/25/22   03/22/22   05/17/22   9,15,16                  100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0      05/31/23                       05/25/22           
22-0073FA Reconstruction               0-001-022  09/06/22     DONE    DONE       DONE      07/13/22   06/08/22   05/10/22   04/19/22   2,16                     277,200       277,200  JLB             0           0           0 Clark Patterson Lee                     0      07/13/23                       06/08/22           
22-1297   Reconstruction               0-001-023  03/23/23     DONE    DONE       DONE      12/21/22   12/20/22   11/09/22   10/18/22   2,8,9                    932,360       932,360  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         12/20/22           
22-1173SB Reconstruction               0-001-024               DONE                           /  /       /  /     12/06/22     /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1918   Reconstruction               0-001-024  07/18/23     DONE    DONE       DONE      03/21/23   03/21/23   12/06/22   11/04/14   16                       332,500       332,500  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         03/21/23           
22-2212   Reconstruction               0-001-025  10/02/23     DONE    DONE       DONE      05/15/23   05/15/23   01/05/23   10/18/22   2,4,7,8,9,10,155,15,   4,122,840     4,122,840  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         05/15/23           
22-2159   Reconstruction               0-001-026  07/20/23     DONE    DONE       DONE      05/08/23   05/05/23   04/03/23   05/16/23   8,9                      100,000       100,000  MSK             0           0           0 Clark Patterson Lee                     0        /  /                         05/05/23           

          Bus Garage:
22-1172SB Reconstruction               5-002-009               DONE                           /  /       /  /     12/06/22     /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1919   Reconstruction               5-002-009  07/18/23     DONE    DONE       DONE      03/21/23   03/21/23   12/06/22   12/14/22   16                        17,500        17,500  JJH             0           0           0                                         0        /  /                         03/21/23           
22-2213   Reconstruction               5-002-010  10/02/23     DONE    DONE       DONE      05/15/23   05/15/23   01/05/23   10/18/22   4,7,8,9,155,15,16        694,800       694,800  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         05/15/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WELLSVILLE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-26-01-06
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Washington Primary/Inter.:
18-0744   Reconstruction               0-003-013  05/15/19     DONE    DONE       DONE      10/29/18   10/25/18   04/18/17   12/20/16   2,4,8,9,10,155,15,16   4,211,532     4,211,532  BMJ             0           0           0 Young And Wright Architectura           0      03/03/21                       10/25/18           
21-1198FC Reconstruction               0-003-015  03/29/22     DONE    DONE       DONE      01/28/22   01/24/22   12/07/21   01/03/22   7,9,155,15,16          1,020,000     1,020,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         01/24/22           
22-0012   Reconstruction               0-003-016  09/28/22     DONE    DONE       DONE      07/01/22   07/01/22   03/24/22   05/17/22   9,10,16                  100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0      05/18/23                       07/01/22           
22-0742   Reconstruction               0-003-017  04/11/23     DONE    DONE       DONE      10/17/22   10/17/22   09/13/22   05/17/22   4,9,15,16                 89,000        89,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         10/17/22           
22-2025   Reconstruction               0-003-018  07/18/23     DONE    DONE       DONE      04/14/23   04/12/23   03/02/23   05/16/23   8,9,155,16               100,000       100,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         04/12/23           
22-2225   Reconstruction               0-003-019  09/05/23     DONE    DONE       DONE      05/17/23   05/16/23   04/24/23   03/28/23   2,7,155,15,16          2,941,000     2,941,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         05/16/23           
23-1203   Reconstruction               0-003-020                         UNREVIEWED         12/18/23   12/12/23   11/17/23   03/28/23   2,4,8,9,155,15,16              0             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         12/12/23           

          High School/Middle School:
18-0745   Reconstruction               0-004-016  05/15/19     DONE    DONE       DONE      10/29/18   10/25/18   04/17/17   12/20/16   2,4,8,9,10,14,155,15   4,817,314     4,386,605  BMJ             0           0           0 Young And Wright Architectura           0      03/03/21                       10/25/18           
21-1199FC Reconstruction               0-004-018  03/29/22     DONE    DONE       DONE      01/28/22   01/24/22   12/07/21   01/03/22   7,155,15,16              255,000       255,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         01/24/22           
22-0509FA Reconstruction               0-004-019  12/06/22     DONE    DONE       DONE      09/16/22   09/12/22   05/09/22   03/01/22   7,9,155,15,16          2,011,000     2,011,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         09/12/22           
22-2226   Reconstruction               0-004-020  09/05/23     DONE    DONE       DONE      05/17/23   05/16/23   04/24/23   03/28/23   7                        173,000       173,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         05/16/23           
23-1204   Reconstruction               0-004-021                         UNREVIEWED         12/18/23   12/12/23   11/17/23   03/28/23   2,4,7,8,9,155,15,16            0             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         12/12/23           

          XXPress Box (Athl Track) Demo:
22-0743   Reconstruction               7-012-002  04/11/23     DONE    DONE       DONE      10/17/22   10/17/22   09/09/22     /  /                               20,981             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         10/17/22           

          Athletic Pavilion:
  -    PR New Construction             7-014-001                                              /  /       /  /     09/09/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0744   New Construction             7-014-001  04/11/23     DONE    DONE       DONE      10/17/22   10/17/22   09/09/22   05/17/22   02 - 16                1,990,019             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         10/17/22           

          White Building (DEMO):
23-1410   Reconstruction               7-015-001                         UNREVIEWED         01/24/24   01/19/24   12/07/23   03/28/23                                  0             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         01/19/24           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOLIVAR-RICHBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-29-02-04
last updated on 03/27/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bolivar High School (Gr 6-12):
18-1912   Reconstruction               0-001-029  05/15/18     DONE    DONE       DONE      04/30/19   04/25/19   02/09/18   02/06/18   2,9                      260,000       260,000  BMJ             0           0           0 Clark Patterson Lee                     0      02/01/19                       04/25/19           
20-1170   Reconstruction               0-001-030  03/25/21     DONE    DONE       DONE      01/19/21   01/18/21   12/15/20   06/16/20   2,4,7,9,10,13,14,155     100,000             0  JSS             0           0           0 Clark Patterson Lee                     0      06/25/21                       01/18/21           
20-1843   Reconstruction               0-001-031  06/25/21     DONE    DONE       DONE      06/04/21   06/04/21   04/28/21   05/18/21   4,8,9,10,15,16           100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0      06/30/22                       06/04/21           
21-0211PR Additions and Alterations    0-001-032                         UNREVIEWED         08/25/21   08/20/21   08/04/21     /  /     02 - 16                        0       632,544  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         08/20/21           
22-0581FA Additions and Alterations    0-001-032  04/17/23     DONE    DONE       DONE      09/26/22   09/02/22   08/04/21   12/08/21   02 - 16                9,174,764     7,536,635  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           
21-1186   Reconstruction               0-001-033  05/05/22     DONE    DONE       DONE      01/21/22   01/19/22   12/29/21   12/08/21   2,9,10,16              1,297,440     1,297,440  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         01/19/22           
21-1758   Reconstruction               0-001-034  06/08/22     DONE    DONE       DONE      05/04/22   05/02/22   03/24/22   05/17/22   9,155,15,16              100,000       100,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         05/02/22           
23-0022   Reconstruction               0-001-035  07/07/21     DONE    DONE       DONE      07/07/23   07/06/23   08/23/22   05/18/21   155,15,16                100,000       100,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         07/06/23           
22-2377   Reconstruction               0-001-036  09/19/23     DONE    DONE       DONE      06/14/23   06/14/23   02/28/23   05/16/23   9,155,15,16              100,000       100,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         06/14/23           

          Richburg Elementary (Gr K-5):
21-1187   Reconstruction               0-011-021  05/05/22     DONE    DONE       DONE      01/21/22   01/19/22   12/29/21   12/08/21   2,10,16                   69,120        69,120  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         01/19/22           
22-0582FA Reconstruction               0-011-022  04/17/23     DONE    DONE       DONE      09/26/22   09/02/22   06/21/22   12/08/21   2,4,7,8,9,10,155,15,   4,058,579     4,058,579  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           

          Pre-Kindergarten:
22-0583   Reconstruction               0-018-008  04/13/23     DONE    DONE       DONE      09/26/22   09/02/22   06/21/22   12/08/21   2,8,9,155,15,16          400,750       400,750  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           

          Baseball Grandstand/Equipment Shed:
22-0584   Reconstruction               2-003-002  04/13/23     DONE    DONE       DONE      09/26/22   09/02/22   06/21/22   12/08/21   4,7,8,9,155,15,16        389,300             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           

          Athletic Storage Shed (Richburg):
22-0585   Reconstruction               2-013-003  04/13/23     DONE    DONE       DONE      09/26/22   09/02/22   06/21/22   12/08/21   8,9,155,15,16             48,090             0  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           

          Bus Garage (Richburg) (see 4-012):
22-0586   Reconstruction               5-012-012  04/13/23     DONE    DONE       DONE      09/26/22   09/02/22   06/21/22   12/08/21   4,7,8,9,155,15,16        206,100       206,100  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           

          Bus Garage (Bolivar):
22-0587   Reconstruction               5-016-009  04/13/23     DONE    DONE       DONE      09/26/22   09/02/22   06/21/22   12/08/21   4,7,8,9,155,15,16        687,000       687,000  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           
22-1928   Reconstruction               5-016-010  05/17/22     DONE    DONE       DONE      03/22/23   03/22/23   08/23/22   05/17/22   9,14,15,16               350,000       350,000  JJH             0           0           0 Clark Patterson Lee                     0      06/30/23                       03/22/23           

          Sugar Shack:
  -    PR New Construction             7-026-001                                              /  /       /  /     06/21/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0588XX New Construction             7-026-001                         CANCELLED          09/26/22   09/02/22   06/21/22   12/08/21   02 - 16                        0             0  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         09/02/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED