REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
12-1067 Reconstruction 0-002-008 UNREVIEWED 04/19/13 04/04/13 11/27/12 11/08/12 13,16 0 8,990,202 JMB 0 0 0 Trautman King Markwart Assoc. 0 / / / /
Chenango Forks Elementary:
12-1068 Reconstruction 0-003-009 UNREVIEWED 04/19/13 04/04/13 11/27/12 11/08/12 13,16 0 7,506,576 JMB 0 0 0 Trautman King Markwart Assoc. 0 / / / /
12-0085 Reconstruction 0-003-010 02/04/13 DONE DONE DONE 09/06/12 08/01/12 04/23/12 04/05/12 155 99,210 99,210 JOD 0 0 0 C&S Companies 0 / / / /
Jr/Sr High School:
12-1069 Reconstruction 0-004-009 UNREVIEWED 04/19/13 04/04/13 11/27/12 11/08/12 13,16 0 28,931,595 JMB 0 0 0 Trautman King Markwart Assoc. 0 / / / /
Bus Garage:
12-1070 Reconstruction 5-001-004 UNREVIEWED 04/19/13 04/04/13 11/27/12 11/08/12 13,16 0 0 JMB 0 0 0 Trautman King Markwart Assoc. 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Calvin Coolidge Elementary:
08-0039 Reconstruction 0-001-014 02/24/09 DONE DONE DONE 07/21/08 07/03/08 07/09/08 05/15/08 2,9,10,16 624,638 624,638 HCM 0 0 16,865 Ashley McGraw Architects 0 / / / /
10-0604 Reconstruction 0-001-015 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/08/09 12/14/09 2,8,9,155,15,16 6,524,380 6,238,400 HCM 0 0 176,159 Ashley McGraw Architects 0 / / / /
Columbus School:
09-0485 Reconstruction 0-002-006 03/05/10 DONE DONE DONE 11/25/09 11/23/09 03/21/07 05/15/07 2,4,7,155,15,16 235,957 235,957 HCM 0 0 6,371 Ashley McGraw Architects 0 / / / /
West Middle School:
08-0041 Reconstruction 0-006-008 02/24/09 DONE DONE DONE 07/21/08 07/03/08 03/20/07 05/15/08 2,4,7,8,9,10,14,155, 5,746,760 3,895,000 HCM 0 0 155,163 Ashley McGraw Architects 0 / / / /
07-2320 Reconstruction 0-006-010 07/10/08 DONE DONE DONE 07/07/08 06/20/08 03/25/08 05/15/07 4 166,000 166,000 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
- Reconstruction 0-006-011 / / / / 06/20/08 / / 2,7 0 0 HCM 0 0 0 0 / / / /
10-0605 Reconstruction 0-006-012 04/20/11 DONE DONE DONE 12/22/10 12/14/10 / / 12/14/09 2,8,155,15,16 871,567 1,680,500 HCM 0 0 23,533 Ashley McGraw Architects 0 / / / /
Benjamin Franklin School:
08-0040 Reconstruction 0-008-012 02/24/09 DONE DONE DONE 07/21/08 07/03/08 06/20/08 05/15/08 2,9 614,865 215,000 HCM 0 0 16,601 Ashley McGraw Architects 0 / / / /
10-0411 Reconstruction 0-008-013 02/14/11 DONE DONE DONE 11/02/10 10/21/10 10/08/09 12/14/09 8,9 2,490,622 2,009,900 HCM 0 0 67,247 Ashley McGraw Architects 0 / / / /
Thomas Jefferson Elem.:
09-0486 Reconstruction 0-009-006 03/05/10 DONE DONE DONE 11/25/09 11/23/09 10/05/09 05/15/07 2,4,7,8,9,10,16 520,121 494,000 HCM 0 0 14,044 Ashley McGraw Architects 0 / / / /
10-0412 Reconstruction 0-009-007 02/14/11 DONE DONE DONE 11/02/10 10/21/10 10/07/09 12/14/09 2,9 889,998 1,127,800 HCM 0 0 24,030 Ashley McGraw Architects 0 / / / /
Theodore Roosevelt Elementary:
09-0487 Reconstruction 0-010-007 03/05/10 DONE DONE DONE 11/25/09 11/23/09 03/21/07 05/15/07 2,4,8,9,155,15,16 692,000 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
East Middle School (New):
08-1386 Reconstruction 0-011-008 04/01/09 DONE DONE DONE 03/16/09 03/10/09 01/20/09 01/13/09 9,155,16 946,416 946,416 HCM 0 0 0 Ashley McGraw Architects 0 / / 03/12/13
09-0568 Reconstruction 0-011-009 06/30/09 DONE DONE DONE 12/14/09 12/07/09 06/05/09 06/09/09 2,7 129,479 129,479 HCM 0 0 3,496 Ashley McGraw Architects 0 / / / /
09-0488 Reconstruction 0-011-010 03/05/10 DONE DONE DONE 11/25/09 11/23/09 10/05/09 05/15/07 8 1,568,674 1,672,000 HCM 0 0 42,355 Ashley McGraw Architects 0 / / / /
10-0606 Reconstruction 0-011-011 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/07/09 12/14/09 2,7,8,9,10,155,15,16 5,755,124 6,286,800 HCM 0 0 1,342,449 Ashley McGraw Architects 0 / / / /
High School:
08-0042 Additions and Alterations 0-014-022 02/24/09 DONE DONE DONE 07/21/08 07/03/08 07/21/08 05/15/08 02 - 16 12,145,172 7,346,000 HCM 0 0 327,920 Ashley McGraw Architects 0 / / / /
08-0043 Additions and Alterations 0-014-023 02/24/09 DONE DONE DONE 07/21/08 07/03/08 / / 05/15/08 02 - 16 1,094,060 871,000 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
08-1627 Reconstruction 0-014-024 06/12/09 DONE DONE DONE 05/12/09 05/11/09 08/27/08 10/14/08 2,9,155,16 609,348 609,348 HCM 0 0 16,453 Ashley McGraw Architects 0 / / / /
10-0607 Reconstruction 0-014-025 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/07/09 12/14/09 2,7,16 3,503,097 2,693,600 HCM 0 0 94,584 Ashley McGraw Architects 0 / / / /
Woodrow Wilson:
09-0489 Reconstruction 0-016-015 03/05/10 DONE DONE DONE 11/25/09 11/23/09 03/21/07 05/15/07 2,4,8,9,10,155,15,16 897,718 1,209,000 HCM 0 0 24,239 Ashley McGraw Architects 0 / / / /
10-0603 Reconstruction 0-016-017 04/01/11 DONE DONE DONE 12/22/10 12/14/10 10/12/10 05/18/10 9,16 350,000 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
MacArthur Elementary:
09-0490 Reconstruction 0-020-013 03/05/10 DONE DONE DONE 11/25/09 11/23/09 03/21/07 05/15/07 2,4,8,9,10,155,15,16 1,286,433 861,000 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
- XX Reconstruction 0-020-015 CANCELLED / / / / 09/13/11 / / 2,8,9,155,16 0 0 HCM 0 0 0 0 / / / /
Horace Mann School:
10-0608 Reconstruction 0-022-013 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/08/09 12/14/09 2,4,9,16 635,000 245,500 HCM 0 0 17,145 Ashley McGraw Architects 0 / / / /
New McArthur Elementary School:
12-0775PR New Construction 0-041-001 UNREVIEWED 02/06/13 02/06/13 08/21/12 / / 02 - 16 0 0 JMB 0 0 0 Ashley McGraw Architects 0 / / / /
Maintenance Building:
08-0136 Additions and Alterations 3-004-003 09/22/08 DONE DONE DONE 08/08/08 08/04/08 06/20/08 / / 02 - 16 540,952 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Chester B. Lord(See-0-007):
09-0571 Reconstruction 7-007-001 ADDENDUM REQ'D 12/14/09 12/07/09 03/06/89 07/01/09 2 0 0 CAE 0 0 0 Ashley McGraw Architects 0 / / / /
- Reconstruction 7-007-003 / / / / 06/05/09 / / 2,9 0 0 HCM 0 0 0 0 / / / /
09-0491 Reconstruction 7-007-004 03/05/10 DONE DONE DONE 11/25/09 11/23/09 10/05/09 05/15/07 2,8,155,16 134,500 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Fieldhouse Concession:
08-0044 Reconstruction 7-012-002 02/24/09 DONE DONE DONE 07/21/08 07/03/08 03/20/07 05/15/08 2,4,8,155,15,16 74,000 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
10-0609 Reconstruction 7-012-003 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/08/09 12/14/09 15 28,300 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Fieldhouse:
10-0610 Reconstruction 7-021-003 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/08/09 12/14/09 2,4,8,155,15,16 129,300 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
VisitorFieldHouse@East Middle School:
10-0611 New Construction 7-039-001 04/20/11 DONE DONE DONE 12/22/10 12/14/10 10/05/10 12/14/09 02 - 16 559,900 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
St Thomas Acquinas School:
11-0192TQ Temporary Quarters 8-039-001 03/01/12 DONE DONE DONE 09/23/11 09/22/11 09/16/11 / / 0 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
St Francis of Assisi School:
11-0191TQ Temporary Quarters 8-040-001 03/01/12 DONE DONE DONE 09/23/11 09/22/11 09/16/11 / / 0 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
07-1549 Reconstruction 0-001-011 10/06/08 DONE DONE DONE 02/06/08 02/04/08 08/18/06 02/12/07 2,7,9,10,155,15,16 1,723,074 1,723,074 HCM 0 0 35,000 SWBRArchitects 0 / / / /
11-1209 Reconstruction 0-001-012 06/01/12 DONE DONE DONE 04/26/12 04/24/12 03/23/11 05/09/11 15 14,000 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
12-1202 Reconstruction 0-001-014 UNREVIEWED 05/17/13 05/17/13 07/30/12 06/19/12 2,4,7,8,9,10,155,15, 0 12,161,687 MFS 0 0 0 Ashley McGraw Architects 0 / / / /
Olmsted Elementary School:
11-1210 Reconstruction 0-006-004 06/01/12 DONE DONE DONE 04/26/12 04/24/12 03/23/11 05/09/11 15 15,000 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
12-1203 Reconstruction 0-006-005 UNREVIEWED 05/17/13 05/17/13 07/30/12 06/19/12 2,4,7,8,9,10,155,15, 0 0 JMB 0 0 0 Ashley McGraw Architects 0 / / / /
Athletic Field Storage Building:
- DB Discovered Building 2-011-001 ADDENDUM REQ'D / / / / 10/14/11 / / 0 0 HCM 0 0 0 0 / / / /
Bus Garage:
11-1211 Reconstruction 5-008-002 06/01/12 DONE DONE DONE 04/26/12 04/24/12 04/14/11 05/09/11 15 21,000 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Athletic Field Restroom Facility:
12-1204 New Construction 7-011-001 UNREVIEWED 05/17/13 05/17/13 07/27/12 06/19/12 02 - 16 0 0 MFS 0 0 0 Ashley McGraw Architects 0 / / / /
Press Box at Field Bleachers:
12-1205 New Construction 7-012-001 UNREVIEWED 05/17/13 05/17/13 07/27/12 06/19/12 02 - 16 0 0 JMB 0 0 0 Ashley McGraw Architects 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Brookside Elementary:
09-0406 Reconstruction 0-003-009 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 2,4,8,9,10,155,15,16 4,351,720 4,101,817 DDJ 0 0 0 0 / / / /
10-1401 Reconstruction 0-003-010 09/20/11 DONE DONE DONE 06/17/11 06/09/11 06/08/11 12/09/08 2,4,7,8,9,10,14,16 3,653,025 0 DDJ 0 0 0 0 / / / /
Susquehanna Valley High School:
09-0407 Reconstruction 0-006-007 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 2,4,7,8,9,10,155,15, 5,401,104 5,401,104 DDJ 0 0 0 0 / / / /
10-1402 Reconstruction 0-006-008 09/20/11 DONE DONE DONE 06/17/11 06/09/11 06/08/11 12/09/08 2,4,7,8,9,16 2,147,970 0 DDJ 0 0 0 0 / / / /
12-0826 Reconstruction 0-006-009 03/01/13 DONE DONE DONE 02/13/13 02/12/13 08/17/12 12/09/08 9,10 100,000 0 DDJ 0 0 0 0 / / / /
Donnelly Elementary:
09-0408 Reconstruction 0-010-009 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 2,4,7,8,9,10,155,15, 4,367,302 3,679,444 DDJ 0 0 0 0 / / / /
10-1403 Reconstruction 0-010-010 09/20/11 DONE DONE DONE 06/17/11 06/09/11 06/08/11 12/09/08 2,4,8,9,10,14,16 1,296,330 0 DDJ 0 0 0 0 / / / /
Industrial Arts Bldg.:
09-0409 Reconstruction 0-012-004 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 2,8,9,15,16 149,406 149,406 DDJ 0 0 0 0 / / / /
10-1404 Reconstruction 0-012-005 09/20/11 DONE DONE DONE 06/17/11 06/09/11 06/08/11 12/09/08 7,8 408,750 0 DDJ 0 0 0 0 / / / /
Junior High School:
09-0410 Reconstruction 0-014-006 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 2,4,7,8,9,10,155,15, 6,472,464 6,472,464 DDJ 0 0 676,811 0 / / / /
10-1405 Reconstruction 0-014-007 09/20/11 DONE DONE DONE 06/17/11 06/09/11 06/08/11 12/09/08 2,4,7,8,9,10,16 1,968,045 0 DDJ 0 0 0 0 / / / /
Conklin Center(demolished):
09-1476 Reconstruction 3-004-001 06/27/11 DONE DONE DONE 06/01/10 05/25/10 04/21/10 01/20/10 2 123,970 0 DDJ 0 0 0 0 / / / /
Facilities Maintenance Building:
09-0411 New Construction 3-016-001 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 02 - 16 1,188,587 0 DDJ 0 0 0 0 / / / /
Brookside Bus Storage Building:
09-0412 New Construction 4-017-001 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 02 - 16 1,012,668 1,012,668 DDJ 0 0 0 0 / / / /
Bus Garage:
09-0413 Reconstruction 5-002-005 03/23/10 DONE DONE DONE 11/10/09 11/09/09 10/20/08 12/09/08 2,4,8,9,16 82,261 82,261 DDJ 0 0 0 0 / / / /
08-1601 Reconstruction 5-002-006 05/11/09 DONE DONE DONE 05/08/09 05/06/09 / / 03/05/09 4,9,10,15,16 275,000 275,000 DDJ 0 0 0 0 / / / /
10-1406 Reconstruction 5-002-007 09/20/11 DONE DONE DONE 06/17/11 06/09/11 06/08/11 12/09/08 2,4,7,8,9,10,155,15, 265,575 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Port Dickinson Elementary:
07-1068 Reconstruction 0-001-004 06/18/08 DONE DONE DONE 12/06/07 12/05/07 06/14/07 04/04/07 7,155 381,549 381,549 JOD 0 0 41,208 Clark Patterson Lee 0 / / / /
11-1262 Reconstruction 0-001-005 11/01/11 DONE DONE DONE 05/03/12 05/03/12 09/28/11 09/27/11 8,9,10 190,000 190,000 JOD 0 0 0 Ashley McGraw Architects 0 / / / /
Junior/Senior High School:
07-1069 Reconstruction 0-002-009 06/16/08 DONE DONE DONE 12/06/07 12/05/07 06/14/07 04/04/07 7,155 570,169 570,169 JOD 0 0 61,579 Clark Patterson Lee 0 / / / /
Chenango Bridge Elementary:
07-1070 Reconstruction 0-004-005 06/16/08 DONE DONE DONE 12/06/07 12/05/07 06/14/07 04/04/07 7,155 1,685,002 1,685,002 HCM 0 0 181,981 Clark Patterson Lee 0 / / / /
Bus Garage:
11-1263 Reconstruction 5-006-003 06/14/11 DONE DONE DONE 05/03/12 05/03/12 09/28/11 06/15/11 4,8,9,10,14 60,000 60,000 JOD 0 0 0 Ashley McGraw Architects 0 / / 10/03/12
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Homer Brink Elementary:
09-1098 Reconstruction 0-001-013 09/03/10 DONE DONE DONE 03/18/10 03/10/10 11/17/09 03/20/07 2,7,10,16 96,800 0 JOD 0 0 0 0 / / / /
Maine Memorial:
09-1099 Reconstruction 0-008-012 09/03/10 DONE DONE DONE 03/18/10 03/10/10 11/17/09 03/20/07 10 145,396 51,700 JOD 0 0 0 0 / / / /
Senior High School:
07-2339PR Additions and Alterations 0-010-015 UNREVIEWED 07/08/08 06/26/08 03/21/06 / / 02 - 16 0 0 JOD 0 0 0 0 / / / /
08-1179 Additions and Alterations 0-010-015 06/16/09 DONE DONE DONE 02/10/09 02/02/09 03/21/06 03/20/07 02 - 16 28,442,234 21,136,986 JOD 0 0 0 0 / / / /
08-1180 Reconstruction 0-010-016 06/16/09 DONE DONE DONE 02/10/09 02/02/09 09/22/06 03/20/07 8,10,13,16 6,058,807 4,915,400 JOD 0 0 0 0 / / / /
08-1420 Reconstruction 0-010-017 03/30/09 DONE DONE DONE 03/24/09 03/18/09 03/24/09 06/19/07 2 279,250 279,250 JOD 0 0 0 0 / / / /
09-1100 Reconstruction 0-010-018 05/25/10 DONE DONE DONE 03/18/10 03/10/10 11/17/09 03/20/07 2,7 1,262,200 0 JOD 0 0 0 0 / / / /
10-1251 Reconstruction 0-010-019 06/07/11 DONE DONE DONE 05/05/11 05/02/11 02/16/11 03/20/07 2,9,155,15,16 119,500 0 JOD 0 0 0 0 / / / /
Middle School:
07-1929 Additions and Alterations 0-015-011 09/22/08 DONE DONE DONE 04/04/08 03/26/08 03/21/06 03/20/07 02 - 16 19,547,524 17,515,172 JOD 0 0 834,157 0 / / / /
07-1930 Reconstruction 0-015-012 09/22/08 DONE DONE DONE 04/04/08 03/26/08 09/22/06 03/20/07 8,10,13,16 835,712 835,712 JOD 0 0 0 0 / / / /
09-1101 Reconstruction 0-015-013 05/25/10 DONE DONE DONE 03/18/10 03/10/10 11/17/09 03/20/07 2,7,9 1,043,900 0 JOD 0 0 0 0 / / / /
Material Storage Shed:
07-1931 Reconstruction 2-014-002 09/22/08 DONE DONE DONE 04/04/08 03/26/08 03/14/08 03/20/07 2,7,8,9,16 23,764 0 JOD 0 0 0 0 / / / /
Recycling Shed - Maine Memorial:
- DB Discovered Building 2-029-001 / / / / 06/22/11 / / 0 0 JOD 0 0 0 0 / / / /
Kindergarten Shed - Maine Memorial:
- DB Discovered Building 2-030-001 / / / / 06/22/11 / / 0 0 JOD 0 0 0 0 / / / /
Field Storage Shed - Maine Memorial:
- DB Discovered Building 2-032-001 / / / / 06/22/11 / / 0 0 JOD 0 0 0 0 / / / /
UPK Shed - Maine Memorial:
- DB Discovered Building 2-033-001 / / / / 06/22/11 / / 0 0 JOD 0 0 0 0 / / / /
Maintenance Facility 2:
- New Construction 3-034-001 / / / / 10/05/11 / / 02 - 16 0 0 JOD 0 0 0 0 / / / /
Field House Senior High School:
08-1181 Reconstruction 7-012-001 06/16/09 DONE DONE DONE 02/10/09 02/02/09 03/11/08 03/20/07 2,7,9,15 76,971 0 JOD 0 0 0 0 / / / /
New Press Box:
08-1182 New Construction 7-020-001 06/16/09 DONE DONE DONE 02/10/09 02/02/09 03/24/06 03/20/07 02 - 16 74,202 0 JOD 0 0 0 0 / / / /
Concession Building:
- DB Discovered Building 7-031-001 / / / / 06/22/11 / / 0 0 JOD 0 0 0 0 / / / /
Districtwide:
10-1384 Reconstruction 7-999-002 07/08/11 DONE DONE DONE 06/08/11 06/06/11 09/08/10 03/20/07 16 411,000 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Deposit Jr/Sr High School:
07-1345 Reconstruction 0-001-014 12/16/08 DONE DONE DONE 01/07/08 01/04/08 06/05/07 03/15/07 2,4,7,8,9,10,155,15, 2,315,997 2,315,997 HCM 0 0 526,854 0 / / / /
10-0526 Additions and Alterations 0-001-015 01/17/12 DONE DONE DONE 12/03/10 11/19/10 10/06/08 12/09/08 02 - 16 4,500,000 4,500,000 HCM 0 0 0 0 / / / /
- Reconstruction 0-001-016 / / / / 06/22/12 / / 2,4,8,9,10,155,15,16 0 0 HCM 0 0 0 0 / / / /
- Reconstruction 0-001-017 / / / / 06/22/12 / / 2,4,8,9,10,155,15,16 0 0 HCM 0 0 0 0 / / / /
Deposit Elementary:
07-1346 Reconstruction 0-002-002 12/16/08 DONE DONE DONE 01/07/08 01/04/08 06/05/07 03/15/07 7,9,155,15,16 134,003 134,003 HCM 0 0 0 0 / / / /
10-0527 Reconstruction 0-002-003 05/26/11 DONE DONE DONE 12/03/10 11/19/10 10/26/10 12/09/08 2,4,7,8,9,10,155,15, 1,350,000 1,350,000 HCM 0 0 0 0 / / / /
- Reconstruction 0-002-004 / / / / 06/22/12 / / 4,9,10,155,15,16 0 0 HCM 0 0 0 0 / / / /
Bus Garage:
07-1347 Reconstruction 4-004-003 12/16/08 DONE DONE DONE 01/07/08 01/04/08 06/05/07 03/15/07 2,4,7,8,9,10,155,15, 73,500 73,500 HCM 0 0 0 0 / / / /
10-0528 Additions and Alterations 4-004-004 05/26/11 DONE DONE DONE 12/03/10 11/19/10 10/26/10 12/09/08 02 - 16 3,150,000 3,150,000 HCM 0 0 0 0 / / / /
- Reconstruction 4-004-005 / / / / 06/22/12 / / 2,4,9 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Tioughnioga Riverside Acad (was MS):
09-0392 Additions and Alterations 0-001-015 04/06/10 DONE DONE DONE 11/05/09 11/04/09 02/26/08 05/06/08 02 - 16 12,384,326 11,962,033 HCM 0 0 400,910 Ashley McGraw Architects 0 / / 01/28/13
11-0766 Reconstruction 0-001-016 06/18/12 DONE DONE DONE 02/09/12 02/07/12 09/21/11 09/16/08 2,7,8,9,155,15,16 4,594,920 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Senior High School:
09-0393 Reconstruction 0-003-014 04/06/10 DONE DONE DONE 11/05/09 11/04/09 02/26/08 05/06/08 2,4,8,9,155,15,16 11,225,522 10,857,963 HCM 0 0 200,000 Ashley McGraw Architects 0 / / 01/28/13
09-0194 Reconstruction 0-003-015 05/09/08 DONE DONE DONE 09/14/09 09/04/09 04/25/08 03/11/08 2,10 765,211 765,211 HCM 0 0 0 SWBR Architects P.C. 0 / / / /
11-0767 Reconstruction 0-003-016 06/18/12 DONE DONE DONE 02/09/12 02/07/12 09/21/11 09/16/08 2,7,8,9,155,15,16 186,600 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Caryl E Adams Elem Sch:
09-0394 Additions and Alterations 0-004-008 04/06/10 DONE DONE DONE 11/05/09 11/04/09 02/26/08 05/06/08 02 - 16 5,629,813 4,894,002 HCM 0 0 0 Ashley McGraw Architects 0 / / 01/28/13
11-0768 Reconstruction 0-004-009 06/18/12 DONE DONE DONE 02/09/12 02/07/12 09/21/11 09/16/08 2,7,8,9,155,15,16 1,401,780 0 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
Bus Garage H.S.:
08-1374 Additions and Alterations 5-009-004 07/13/09 DONE DONE DONE 03/16/09 03/09/08 09/17/08 09/16/08 02 - 16 997,650 997,650 HCM 0 0 0 Ashley McGraw Architects 0 / / 12/31/09
11-0769 Reconstruction 5-009-005 06/18/12 DONE DONE DONE 02/09/12 02/07/12 11/08/11 09/16/08 2,7,8,9,155,15,16 481,444 481,444 HCM 0 0 0 Ashley McGraw Architects 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Linnaeus West Elementary:
08-1623 Reconstruction 0-004-011 06/10/09 DONE DONE DONE 05/12/09 05/11/09 03/30/09 05/19/09 2,155 516,000 516,000 DDJ 0 0 0 0 / / / /
09-0711 Reconstruction 0-004-012 02/10/10 DONE DONE DONE 01/08/10 01/06/10 11/09/09 05/19/09 7 930,000 930,000 DDJ 0 0 0 0 / / / /
Charles F Johnson Elementary:
12-1162 Reconstruction 0-006-014 STARTED DONE DONE 05/07/13 05/06/13 04/25/13 / / 2,8 0 7,442,260 DDJ 0 0 0 BCK-IBI Group, a New York Gen 0 / / / /
Senior High School:
08-1381 Reconstruction 0-011-028 04/16/09 DONE DONE DONE 03/16/09 03/10/09 09/25/08 10/14/08 2,14 3,725,000 3,725,000 DDJ 0 0 0 0 / / / /
08-1203 Reconstruction 0-011-029 05/21/09 DONE DONE DONE 02/11/09 02/05/09 10/22/08 12/04/04 2,4,7,8,9,16 211,000 211,000 DDJ 0 0 0 0 / / / /
08-1204 Reconstruction 0-011-030 03/12/09 DONE DONE DONE 02/11/09 02/05/09 01/09/09 12/04/04 2,4,7,16 370,205 370,205 DDJ 0 0 0 0 / / / /
10-0437 Reconstruction 0-011-031 01/28/11 DONE DONE DONE 11/05/10 10/29/10 09/20/10 05/18/10 2,8,10,155,16 890,000 890,000 DDJ 0 0 0 0 / / 08/27/12
Jennie F Snapp Middle:
08-0225 Additions and Alterations 0-012-012 02/04/09 DONE DONE DONE 08/28/08 08/20/08 07/25/06 01/30/07 02 - 16 23,062,166 22,722,377 DDJ 0 0 1,392,398 0 / / / /
10-0938 Reconstruction 0-012-015 05/12/11 DONE DONE DONE 03/04/11 02/18/11 03/02/11 01/30/07 10 542,640 542,640 DDJ 0 0 0 0 / / 02/08/13
- Reconstruction 0-012-016 / / / / 01/24/12 / / 155,15,16 0 0 DDJ 0 0 0 0 / / / /
Administration Office:
07-1783 Reconstruction 1-030-003 09/23/08 DONE DONE DONE 03/14/08 03/07/08 03/11/08 05/15/07 14 250,000 0 DDJ 0 0 0 0 / / / /
Storage Building:
12-0327 New Construction 2-034-001 11/30/12 DONE DONE DONE 10/29/12 10/25/12 09/12/12 09/16/12 02 - 16 10,000 0 DDJ 0 0 0 0 / / / /
Harvard St. Maint.Garage(now 3-020):
08-1507 Reconstruction 5-020-005 04/16/09 DONE DONE DONE 04/15/09 04/14/09 04/06/09 04/06/09 2 55,000 55,000 DDJ 0 0 0 0 / / / /
Bradley Creek Bus Garage:
10-1117 Reconstruction 5-021-007 04/11/11 DONE DONE DONE 03/29/11 03/28/11 03/02/11 02/14/11 15 153,000 153,000 DDJ 0 0 0 0 / / 04/01/13
11-0007 Reconstruction 5-021-008 09/27/11 DONE DONE DONE 07/08/11 07/07/11 06/30/11 05/19/09 155,15,16 57,000 57,000 DDJ 0 0 0 0 / / 08/17/12
New Field House @ High School:
12-1215 New Construction 7-027-001 UNREVIEWED 05/23/13 05/16/13 01/29/99 04/16/13 02 - 16 0 0 BJB 0 0 0 BCK-IBI Group, a New York Gen 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
07-1667 Reconstruction 0-011-010 10/09/08 DONE DONE DONE 02/23/08 02/15/08 05/08/07 06/19/07 2,4,7,8,9,155,15,16 10,197,600 7,828,642 DDJ 0 0 2,030,375 Highland Associates 0 / / / /
08-1717 Reconstruction 0-011-011 06/30/09 DONE DONE DONE 06/19/09 06/11/09 09/15/08 06/24/08 8,13,155,15,16 1,971,000 1,971,000 DDJ 0 0 0 Highland Associates 1,971,000 / / 11/14/11
09-1252 Reconstruction 0-011-012 12/17/10 DONE DONE DONE 04/06/10 03/31/10 02/09/10 06/24/08 155,15,16 2,844,910 0 DDJ 0 0 0 Highland Associates 2,844,910 / / / /
12-0128 Reconstruction 0-011-013 08/31/12 DONE DONE DONE 08/28/12 08/27/12 07/13/12 04/16/12 10,155,15,16 398,000 398,000 DDJ 0 0 0 Highland Associates 398,000 / / 04/29/13
12-0084XX Additions and Alterations 0-011-014 CANCELLED 08/06/12 08/03/12 08/06/12 04/16/12 02 - 16 0 0 DDJ 0 0 0 Highland Associates 0 / / / /
K-8 Elementary Middle:
07-1668 Additions and Alterations 0-020-003 10/09/08 DONE DONE DONE 02/23/08 02/15/08 05/08/07 06/19/07 02 - 16 1,867,800 1,867,800 DDJ 0 0 0 Highland Associates 0 / / / /
09-1253 Reconstruction 0-020-004 12/17/10 DONE DONE DONE 04/06/10 03/31/10 09/15/08 06/24/08 8,13,155,15,16 360,916 0 DDJ 0 0 0 Highland Associates 360,916 / / / /
- Reconstruction 0-020-005 / / / / 04/06/10 / / 155,16 0 0 DDJ 0 0 0 0 / / / /
Bus Storage South Building:
09-1255 Reconstruction 4-014-003 12/17/10 DONE DONE DONE 04/06/10 03/31/10 04/06/10 06/24/08 16 48,305 0 DDJ 0 0 0 Highland Associates 48,305 / / / /
Bus Storage North Building:
09-1256 Reconstruction 4-015-003 12/17/10 DONE DONE DONE 04/06/10 03/31/10 04/06/10 06/24/08 16 47,375 0 DDJ 0 0 0 Highland Associates 47,375 / / / /
Bus Garage:
09-1254 Reconstruction 5-010-003 12/17/10 DONE DONE DONE 04/06/10 03/31/10 09/15/08 06/24/08 8,13,155,15,16 28,494 0 DDJ 0 0 0 Highland Associates 28,494 / / / /
- Reconstruction 5-010-004 / / / / 04/06/10 / / 155,16 0 0 DDJ 0 0 0 0 / / / /
New Press Box:
09-1309DB Discovered Building 7-022-001 ADDENDUM REQ'D 04/14/10 04/05/10 02/16/01 / / 02 - 16 0 0 MAC 0 0 0 Highland Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central Jr. High School:
09-0972 Reconstruction 0-017-006 05/24/10 DONE DONE DONE 02/26/10 02/22/10 11/08/04 03/22/05 2,4,16 539,398 539,398 JOD 0 0 0 0 / / / /
12-0764 Reconstruction 0-017-007 10/03/12 DONE DONE DONE 02/05/13 02/04/13 10/09/12 10/04/12 155,16 92,000 92,000 DDJ 0 0 0 0 / / 04/15/13
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
09-0122 Reconstruction 0-003-007 01/05/10 DONE DONE DONE 08/14/09 08/13/09 03/04/09 01/15/09 2,8,9,10,155,15,16 3,426,274 3,141,025 JOD 0 0 0 SWBR Architects P.C. 0 / / / /
10-1013 Reconstruction 0-003-008 07/01/11 DONE DONE DONE 03/09/11 03/07/11 02/16/11 01/27/09 2,8,9,14,155,15 457,240 457,240 JOD 0 0 0 SWBRArchitects 0 / / 02/22/13
12-0593 Reconstruction 0-003-009 DONE DONE UNREVIEWED12/24/12 12/18/12 09/18/12 12/04/12 2,4,9,13,15,16 0 16,483,696 MFS 0 0 0 Ashley McGraw Architects 0 / / / /
Bell Elementary:
09-0123 Reconstruction 0-004-008 01/05/10 DONE DONE DONE 08/14/09 08/13/09 03/04/09 01/15/09 2,7,8,9,10,155,15,16 2,308,063 2,100,625 JOD 0 0 0 SWBR Architects P.C. 0 / / / /
10-1014 Reconstruction 0-004-009 07/01/11 DONE DONE DONE 03/07/11 03/07/11 02/15/11 01/27/09 4,8,9,10,155,16 16,084 16,084 JOD 0 0 0 SWBRArchitects 0 / / 02/22/13
Weeks Elementary School:
08-1433 Reconstruction 0-006-008 05/15/09 DONE DONE DONE 03/26/09 03/25/09 03/04/09 01/15/09 7 1,260,000 0 JOD 0 0 0 SWBR Architects P.C. 0 / / / /
09-0124 Reconstruction 0-006-009 01/05/10 DONE DONE DONE 08/14/09 08/13/09 08/05/09 01/15/09 15,16 2,159,464 1,693,486 JOD 0 0 0 SWBR Architects P.C. 0 / / / /
10-1015 Reconstruction 0-006-010 07/01/11 DONE DONE DONE 03/07/11 03/07/11 02/16/11 01/27/09 2,9,155,15,16 16,618 16,618 JOD 0 0 0 SWBRArchitects 0 / / 02/22/13
High School:
09-0125 Reconstruction 0-010-009 01/05/10 DONE DONE DONE 08/14/09 08/13/09 03/04/09 01/15/09 2,8,9,10,155,15,16 2,846,645 2,501,086 JOD 0 0 0 SWBR Architects P.C. 0 / / / /
10-1016 Reconstruction 0-010-010 07/01/11 DONE DONE DONE 03/07/11 03/07/11 02/15/11 01/27/09 2,9,10,155,15,16 317,182 317,182 JOD 0 0 0 SWBRArchitects 0 / / 02/22/13
New Bus Garage:
09-1354 Reconstruction 5-015-002 05/20/10 DONE DONE DONE 04/22/10 04/19/10 07/18/06 01/15/09 155,16 307,066 252,540 MGL 0 0 0 SWBR Architects P.C. 0 / / / /
Pavilion (open structure):
09-1349 New Construction 7-023-001 04/21/10 DONE DONE DONE 04/15/10 04/15/10 / / / / 02 - 16 0 0 JOD 0 0 0 SWBR Architects P.C. 0 / / 09/28/12
Concession Stand:
- PR New Construction 7-024-001 / / / / 07/28/10 / / 02 - 16 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Masonry Storage:
- Reconstruction 0-005-003 / / / / 10/04/12 / / 9,10,13,155,16 0 0 JMB 0 0 0 0 / / / /
Institutional Support Center:
- Reconstruction 0-008-002 / / / / 10/04/12 / / 9,13,155,15,16 0 0 JMB 0 0 0 0 / / / /
Educational Center:
- Reconstruction 0-009-011 / / / / 10/04/12 / / 13,155,16 0 0 JMB 0 0 0 0 / / / /
12-0672 Reconstruction 0-009-012 03/11/13 DONE DONE DONE 01/15/13 01/15/13 10/09/12 12/05/12 2,4,8,9,10,15,16 155,000 0 JMB 0 0 0 0 / / / /
Fairview church building:
09-1459TQ Temporary Quarters 1-050-001 09/27/10 DONE DONE DONE 05/20/10 05/17/10 05/27/09 / / 0 0 JOD 0 0 0 0 / / / /
Storage Building @ The Leslie F Dist:
08-0596 New Construction 2-049-001 03/19/09 DONE DONE DONE 10/27/08 10/24/08 05/27/08 07/09/08 02 - 16 400,000 0 JOD 0 0 0 Clark Patterson Lee 0 / / / /
Sarkisian Bros, inc storage bldg:
- TQ Temporary Quarters 2-051-001 / / / / 12/28/09 / / 0 0 JOD 0 0 0 0 / / / /
Maintenance Bldg.:
- Reconstruction 3-007-002 / / / / 10/04/12 / / 9,10,13,155,16 0 0 JMB 0 0 0 0 / / / /
Johnson City Learning Center:
08-1609TQ Temporary Quarters 8-048-001 06/29/09 DONE DONE DONE 05/11/09 05/04/09 04/29/08 / / 0 0 JOD 0 0 0 McElwain Engineering 0 / / / /
McKinley Ave Building:
- TQ Temporary Quarters 8-052-001 / / / / 06/19/12 / / 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED