Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/25/18 at 08:48:53




AUBURN CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-01-00-01
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Genesee Street School:
14-0656   Reconstruction               0-001-014  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   16                       179,150       179,150  MFS             0           0           0 SWBR ARCHITECTS                   184,587      06/05/17                       06/26/17           
15-0369   Reconstruction               0-001-015  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   2,7,8,9,14,155,15,16     845,648       845,648  MFS             0           0           0 SWBR ARCHITECTS                         0      10/01/17                       04/27/18           
  -       Reconstruction               0-001-016                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Herman Avenue School:
14-0657   Reconstruction               0-002-017  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   16                       300,394       300,394  MFS             0           0           0 SWBR ARCHITECTS                   309,513      06/05/17                       06/26/17           
15-0370   Reconstruction               0-002-018  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   8,9,15,16                250,895       250,895  MFS             0           0           0 SWBR ARCHITECTS                         0      09/02/17                       04/27/18           
  -       Reconstruction               0-002-019                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Auburn Junior High School:
14-0658   Reconstruction               0-004-028  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   155,16                   643,371       643,370  MFS             0           0           0 SWBR ARCHITECTS                   662,900      06/05/17                       06/26/17           
14-1072   Reconstruction               0-004-029  02/12/15     DONE    DONE       DONE      02/04/15   02/03/15   02/04/15   01/13/15   155                      151,650       151,650  MFS             0           0           0 SWBR ARCHITECTS                         0      07/31/15                       01/04/16           
15-0371   Reconstruction               0-004-030  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   2,8,9,10,155,15,16     1,271,050     1,271,050  MFS             0           0           0 SWBR ARCHITECTS                         0      10/01/17                       04/27/18           
16-0910   Reconstruction               0-004-031  03/01/17     DONE    DONE       DONE      12/01/16   12/01/16   03/04/16   01/13/16   2,9,16                 2,800,000     2,800,000  MFS             0           0           0 SWBR ARCHITECTS                         0      10/31/17                       04/12/18           
  -       Reconstruction               0-004-032                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Owasco Elementary:
14-0659   Reconstruction               0-010-019  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   16                       237,058       237,058  MFS             0           0           0 SWBR ARCHITECTS                   244,254      06/05/17                       06/26/17           
15-0372   Reconstruction               0-010-020  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   2,8,15,16                766,105       766,105  MFS             0           0           0 SWBR ARCHITECTS                         0      10/01/17                       04/27/18           
  -       Reconstruction               0-010-021                                              /  /       /  /     01/24/18     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Casey Park Elementary:
14-0660   Reconstruction               0-012-015  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   16                       287,726       287,726  MFS             0           0           0 SWBR ARCHITECTS                   296,460      06/05/17                       06/26/17           
15-0373   Reconstruction               0-012-016  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   2,155,15,16              112,208       112,208  MFS             0           0           0 SWBR ARCHITECTS                         0      09/01/17                       04/27/18           
  -       Reconstruction               0-012-017                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Auburn High School:
13-0302   Reconstruction               0-015-021  03/25/14     DONE    DONE       DONE      08/29/13   08/29/13   06/06/13   07/02/13   10,155,15,16             100,000       100,000  MFS             0           0           0 C&S Companies                           0      06/27/14                       07/10/14           
14-0479   Reconstruction               0-015-022  06/15/15     DONE    DONE       DONE      10/17/14   10/16/14   09/09/14   09/24/14   155,16                   100,000       100,000  MFS             0           0           0 C&S Companies                           0      06/30/15                       07/23/15           
14-0661   Reconstruction               0-015-023  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   16                       167,343       167,343  MFS             0           0           0 SWBR ARCHITECTS                   172,422      06/05/17                       06/26/17           
14-1287   Reconstruction               0-015-024  03/24/15     DONE    DONE       DONE      03/18/15   03/16/15   03/18/15   10/18/11   16                        43,000        43,000  MFS             0           0           0 SWBR Architects P.C.                    0      08/31/15                       01/04/16           
15-0374   Reconstruction               0-015-025  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   2,9,16                 1,126,114     1,126,114  MFS             0           0           0 SWBR ARCHITECTS                         0      10/01/17                       04/27/18           
15-0819   Reconstruction               0-015-026  06/15/16     DONE    DONE       DONE      12/01/15   11/27/15   11/04/15   10/29/15   16                       100,000       100,000  MFS             0           0           0 C&S Companies                           0      06/30/16                       05/26/17           
16-1487   Reconstruction               0-015-027  06/20/17     DONE    DONE       DONE      03/09/17   03/09/17   12/20/16   05/17/16   16                       100,000       100,000  BMJ             0           0           0 C&S Companies                           0      06/30/17                       07/21/17           
17-0158   Reconstruction               0-015-028  01/02/18     DONE    DONE       DONE      08/03/17   08/03/17   01/23/17   06/27/17   2,9,10,16                100,000       100,000  BMJ             0           0           0 SWBR ARCHITECTS                         0        /  /                           /  /             
  -       Reconstruction               0-015-029                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             
17-1241   Reconstruction               0-015-030                         UNREVIEWED         01/24/18   12/22/17   01/05/18   12/12/17   15                             0    61,757,804  BMJ             0           0           0 INTELLIGENT CONVERTED ENERGY,           0        /  /                           /  /             

          Seward Elementary:
14-0662   Reconstruction               0-017-018  05/18/16     DONE    DONE       DONE      11/21/14   11/21/14   09/09/14   02/28/12   16                       161,657       161,657  MFS             0           0           0 SWBR ARCHITECTS                   166,563      06/05/17                       06/26/17           
15-0375   Reconstruction               0-017-019  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   2,16                      89,777        89,777  MFS             0           0           0 SWBR ARCHITECTS                         0        /  /                           /  /             
  -       Reconstruction               0-017-020                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Administration Building:
15-0376   Reconstruction               1-005-011  09/08/16     DONE    DONE       DONE      08/28/15   08/28/15   07/23/15   10/18/11   16                        47,777             0  MFS             0           0           0 SWBR ARCHITECTS                         0      08/31/17                       04/27/18           
  -       Reconstruction               1-005-012                                              /  /       /  /     11/24/17     /  /     9,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
15-0982   Reconstruction               7-999-001  01/11/16     DONE    DONE       DONE      12/30/15   12/23/15   11/13/15   05/12/15   13,16                  1,405,344     1,405,344  MFS             0           0           0 SWBR Architects P.C.                    0      08/31/16                       05/05/17           
16-0136SB Reconstruction               7-999-002               DONE                           /  /       /  /     07/21/16     /  /     13,16                          0             0  AAA             0           0           0                                         0        /  /                           /  /             
17-0157   Reconstruction               7-999-002  05/02/18     DONE    DONE       DONE      08/03/17   08/03/17     /  /     07/19/16   13,16                  2,300,596             0  BMJ             0           0           0 SWBR ARCHITECTS                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  AAA             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WEEDSPORT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-03-01-04
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
12-1144   Reconstruction               0-001-016  10/04/13     DONE    DONE       DONE      05/01/13   04/29/13   04/02/13   03/26/13   16                       212,000       212,000  MFS             0           0       9,749 King & King Architects                  0      11/24/14                       01/28/15           
13-1498   Reconstruction               0-001-017  12/11/14     DONE    DONE       DONE      05/07/14   05/05/14   07/11/13   12/09/13   8,9,155,15,16            774,232       774,232  MFS             0           0           0 King & King Architects            774,232      12/01/15                       02/08/16           
14-0075   Reconstruction               0-001-018  01/21/15     DONE    DONE       DONE      07/29/14   07/22/14   11/15/13   11/12/13   16                       184,000       184,000  MFS             0           0           0 King & King Architects                  0      01/15/16                       10/26/16           
14-0413   Reconstruction               0-001-019  11/24/14     DONE    DONE       DONE      10/06/14   10/06/14   05/22/14   05/20/14   9                        100,000       100,000  MFS             0           0           0 King & King Architects                  0      06/15/15                       06/26/15           
14-1591   Reconstruction               0-001-020  06/09/15     DONE    DONE       DONE      06/08/15   06/04/15   05/22/15   05/19/15   9                        100,000       100,000  MFS             0           0           0 King & King Architects                  0      10/01/15                       05/16/16           
15-1785   Reconstruction               0-001-021  06/01/16     DONE    DONE       DONE      05/23/16   05/19/16   01/05/16   12/15/15   16                       122,000       122,000  MFS             0           0           0 King & King Architects                  0      08/31/17                       11/17/17           
16-1255   Reconstruction               0-001-022  11/06/17     DONE    DONE       DONE      01/25/17   01/25/17   01/05/16   12/15/15   2,4,7,8,9,155,15,16    5,273,000             0  MFS             0           0           0 King & King Architects                  0        /  /                           /  /             
16-0350   Reconstruction               0-001-023  10/21/16     DONE    DONE       DONE      09/01/16   09/01/16   05/20/16   05/17/16   2,4                      100,000       100,000  MFS             0           0           0 King & King Architects                  0      06/15/17                       06/29/17           

          Junior/Senior High School:
12-1145   Reconstruction               0-002-023  10/04/13     DONE    DONE       DONE      05/01/13   04/29/13   04/02/13   03/26/13   16                       288,000       288,000  MFS             0           0       9,750 King & King Architects                  0      11/24/14                       01/28/15           
12-1331   Reconstruction               0-002-024  09/18/13     DONE    DONE       DONE      06/27/13   06/27/13   05/09/13   05/21/13   8,9                      100,000       100,000  MFS             0           0           0 King & King Architects                  0      05/15/14                       08/18/14           
13-1499   Reconstruction               0-002-025  12/11/14     DONE    DONE       DONE      05/07/14   05/05/14   07/11/13   12/09/13   8,9,155,15,16          1,610,838     1,610,838  MFS             0           0           0 King & King Architects          1,610,838      12/01/15                       02/08/16           
14-0076   Reconstruction               0-002-026  01/21/15     DONE    DONE       DONE      07/29/14   07/22/14   11/15/13   11/12/13   2,4,7,8,9,10,155,15,   3,944,743     3,944,743  MFS             0           0           0 King & King Architects                  0      01/15/16                       10/26/16           
15-1786   Reconstruction               0-002-027  06/01/16     DONE    DONE       DONE      05/23/16   05/19/16   01/05/16   12/15/15   2,14,16                  351,000       351,000  MFS             0           0           0 King & King Architects                  0      08/31/17                       11/17/17           
16-1256   Reconstruction               0-002-028  11/06/17     DONE    DONE       DONE      01/25/17   01/25/17   01/05/16   12/15/15   2,4,8,9,155,15,16      8,284,000             0  MFS             0           0           0 King & King Architects                  0        /  /                           /  /             
17-0388   Reconstruction               0-002-029  09/25/17     DONE    DONE       DONE      09/13/17   09/13/17   05/22/17   05/16/17   2,9                      100,000             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             

          New Bus Garage Storage/Maint:
13-1500   Reconstruction               5-009-003  12/11/14     DONE    DONE       DONE      05/07/14   05/05/14   07/11/13   12/09/13   8,9,155,15,16             24,245        24,245  MFS             0           0           0 King & King Architects             24,245      12/01/15                       02/08/16           
16-1257   Reconstruction               5-009-004  11/06/17     DONE    DONE       DONE      01/25/17   01/25/17   01/05/16   12/15/15   2,7,9,155,15,16          575,000             0  MFS             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CATO-MERIDIAN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-04-01-04
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary/Middle School:
13-0454   Reconstruction               0-001-022  02/07/14     DONE    DONE       DONE      10/04/13   09/24/13   06/20/13   05/21/13   2,4,7,8,9,155,15,16    2,325,888     2,325,888  JMB             0           0           0 Teitsch-Kent                            0      09/14/15                       12/09/15           
15-0674   Reconstruction               0-001-023  08/04/16     DONE    DONE       DONE      11/02/15   10/30/15   09/19/13   05/21/13   2,4,7,8,9,155,15,16       50,000        50,000  JMB             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
17-0776   Reconstruction               0-001-024  03/08/18     DONE    DONE       DONE      11/15/17   11/07/17   03/16/17   03/13/17   2,4,15,16                 89,500             0  MTM             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
17-0505   Reconstruction               0-001-025  03/06/18     DONE    DONE       DONE      10/04/17   09/28/17   05/18/17   05/16/17   2,4,7,8,9,155,15,16      100,000             0  MTM             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
  -       Reconstruction               0-001-026                                              /  /       /  /     12/15/17     /  /     2,4,7,8,9,10,155,15,           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          High School:
12-1306   Reconstruction               0-004-015  07/12/13     DONE    DONE       DONE      06/20/13   06/19/13   01/17/13   05/12/13   2,4,9,155,15,16          100,000       100,000  JMB             0           0           0 Teitsch-Kent                            0      04/01/14                       04/07/14           
13-0455   Reconstruction               0-004-016  02/07/14     DONE    DONE       DONE      10/04/13   09/24/13   06/20/13   05/21/13   2,4,7,8,9,155,15,16      588,995       588,995  JMB             0           0           0 Teitsch-Kent                            0      09/14/15                       12/09/15           
15-0675   Reconstruction               0-004-017  08/04/16     DONE    DONE       DONE      11/02/15   10/30/15   09/19/13   05/21/13   2,4,7,8,9,155,15,16      372,643       372,643  JMB             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
17-0775   Reconstruction               0-004-018  03/08/18     DONE    DONE       DONE      11/15/17   11/07/17   06/29/17   06/26/17   2,4,13,15                 63,800             0  MTM             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
  -       Reconstruction               0-004-019                                              /  /       /  /     12/15/17     /  /     2,4,7,8,9,10,155,15,           0    17,799,911  MTM             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
13-1663   Reconstruction               5-002-005  07/22/14     DONE    DONE       DONE      06/25/14   06/24/14   01/29/14   05/20/14   2,4,7,8,9,155,15,16      100,000       100,000  JMB             0           0           0 Teitsch Kent fay architects             0      09/14/15                       12/09/15           
15-0281   Reconstruction               5-002-006  11/02/15     DONE    DONE       DONE      08/12/15   08/12/15   01/15/15   05/19/15   2,4,7,8,9,155,15,16      100,000       100,000  JMB             0           0           0 Teitsch-Kent                            0      06/22/16                       10/23/17           
16-0328   Reconstruction               5-002-007  02/23/17     DONE    DONE       DONE      08/30/16   08/29/16   05/24/16   05/17/16   2,4,7,8,9,10,155,15,     100,000       100,000  JMB             0           0           0 Teitsch-Kent                            0      06/22/17                       09/05/17           

          District-Wide:
  -       Reconstruction               7-999-002                                              /  /       /  /     12/10/17     /  /     2,4,9,16                       0             0  MTM             0           0           0                                         0        /  /                           /  /             
17-0936SB Reconstruction               7-999-002               STARTED                        /  /       /  /     12/10/17     /  /     2,4,9,16                       0             0  MTM             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTHERN CAYUGA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-07-01-04
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Poplar Ridge School (fmly Jr/Sr HS):
13-0295   Reconstruction               0-007-020  03/24/14     DONE    DONE       DONE      08/28/13   08/21/13   06/20/13   05/21/13   13,15                    100,000       100,000  MFS             0           0           0 King & King Architects                  0      06/16/14                       08/04/14           
14-0022   Reconstruction               0-007-021  11/19/14     DONE    DONE       DONE      07/15/14   07/07/14   06/19/14   05/20/14   15,16                    100,000       100,000  MFS             0           0           0 King & King Architects                  0      06/15/15                       07/29/15           
14-0301   Reconstruction               0-007-022  06/01/15     DONE    DONE       DONE      09/15/14   09/09/14   06/19/14   05/20/14   2,9,155,15,16          2,931,432     2,931,432  MFS             0           0           0 King & King Architects                  0      09/01/16                       09/29/16           
15-0288   Reconstruction               0-007-023  02/01/15     DONE    DONE       DONE      08/18/15   08/18/15   01/30/15   01/26/15   2,9,15                    95,098        95,098  MFS             0           0           0 King & King Architects                  0      07/03/15                       11/18/15           
15-0181   Reconstruction               0-007-024  10/14/15     DONE    DONE       DONE      07/31/15   06/25/15   07/20/15   05/19/15   2,8                      100,000       100,000  MFS             0           0           0 King & King Architects                  0      05/01/16                       07/08/16           
16-0237   Reconstruction               0-007-025  02/03/17     DONE    DONE       DONE      08/09/16   08/09/16   05/16/16   05/17/16   2,4,8,9                  100,000       100,000  MFS             0           0           0 King & King Architects                  0      06/15/17                       06/22/17           
16-2010   Reconstruction               0-007-026  08/22/17     DONE    DONE       DONE      06/08/17   06/08/17   02/21/17   05/16/17   9,155,16                 100,000             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             
17-0038   Reconstruction               0-007-027  03/30/18     DONE    DONE       DONE      07/07/17   07/07/17   05/24/17   05/16/17   7,8,9,10,155,15,16     1,250,000             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             
  -    SB Reconstruction               0-007-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0    21,243,803  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-007-BA2               DONE                           /  /       /  /     06/26/17     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Agriculture Structure:
  -    PR New Construction             0-011-001                                              /  /       /  /     07/12/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
17-0383   New Construction             0-011-001  01/08/18     DONE    DONE       DONE      09/12/17   09/11/17   07/12/17   08/28/17   02 - 16                   25,000             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             

          Observatory:
17-1188   Reconstruction               7-009-002  04/03/18     DONE    DONE       DONE      01/17/18   01/12/18   12/14/17   12/11/17   7                         85,800             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PORT BYRON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-11-01-04
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main School Building K-12:
13-0791   Reconstruction               0-004-013  07/22/13     DONE    DONE       DONE      11/29/13   11/29/13   11/27/13   05/21/13   2                         19,760        19,760  DDJ             0           0           0 elark Patterson Lee                     0      08/20/13                       02/10/14           
13-1650   Reconstruction               0-004-014  07/21/14     DONE    DONE       DONE      06/25/14   06/20/14   05/22/14   05/20/14   16                       100,000       100,000  DDJ             0           0           0 elark Patterson Lee                     0      01/03/15                       03/06/15           
14-0073   Reconstruction               0-004-015  01/22/15     DONE    DONE       DONE      07/28/14   07/18/14   07/24/14   05/20/14   16                       832,000       832,000  DDJ             0           0           0 elark Patterson Lee                     0      10/28/15                       11/09/15           
15-0147   Reconstruction               0-004-016  08/18/15     DONE    DONE       DONE      07/23/15   07/22/15   07/06/15   05/19/15   155                      100,000       100,000  DDJ             0           0           0 elark Patterson Lee                     0      05/18/16                       06/10/16           
16-0445   Reconstruction               0-004-017  11/25/16     DONE    DONE       DONE      09/16/16   09/15/16   07/20/16   05/17/16   8,10                     100,000       100,000  DDJ             0           0           0 elark Patterson Lee                     0      06/16/17                       06/29/17           
  -    PR Additions and Alterations    0-004-018                                              /  /       /  /     03/10/17     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             
16-1819   Additions and Alterations    0-004-018  01/09/18     DONE    DONE       DONE      05/12/17   05/12/17   03/10/17   08/25/16   02 - 16                        0             0  DDJ             0           0           0 elark Patterson Lee                     0        /  /                           /  /             
16-1554   Reconstruction               0-004-019  11/22/17     DONE    DONE       DONE      03/27/17   03/27/17   03/10/17   08/25/16   8,155,16                 837,905       837,905  DDJ             0           0           0 elark Patterson Lee               837,905        /  /                           /  /             
16-2077   Reconstruction               0-004-020  08/28/17     DONE    DONE       DONE      06/19/17   06/19/17   05/22/17   05/16/17   9,16                     100,000       100,000  MTM             0           0           0 elark Patterson Lee                     0      05/04/18                       05/11/18           
  -    SB Reconstruction               0-004-BA1               STARTED                        /  /       /  /       /  /       /  /     13                             0    32,673,090  DDJ             0           0           0                                         0        /  /                           /  /             

          XXAthletic Stg. Bldg. (Demo'd 2017):
  -       Reconstruction               2-012-002                                              /  /       /  /     03/10/17     /  /     2,7,8                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
13-0597   Reconstruction               5-011-004  03/18/14     DONE    DONE       DONE      10/22/13   10/02/13   10/22/13   05/21/13   2,15,16                  100,000       100,000  DDJ             0           0           0 elark Patterson Lee                     0      06/26/14                       06/30/14           
14-0074   Reconstruction               5-011-005  01/22/15     DONE    DONE       DONE      07/28/14   07/18/14   05/22/14   05/20/14   16                        66,000        66,000  DDJ             0           0           0 elark Patterson Lee                     0      10/28/15                       11/09/15           
16-1820   Additions and Alterations    5-011-006  01/09/18     DONE    DONE       DONE      05/12/17   05/12/17   03/10/17   08/25/16   02 - 16                        0             0  DDJ             0           0           0 elark Patterson Lee                     0        /  /                           /  /             
16-1555   Reconstruction               5-011-007  11/22/17     DONE    DONE       DONE      03/27/17   03/27/17   03/10/17   08/25/16   16                        20,895             0  DDJ             0           0           0 elark Patterson Lee                20,895        /  /                           /  /             

          XXConcession Stand (Demo'd 2017):
  -       Reconstruction               7-014-002                                              /  /       /  /     03/10/17     /  /     2,7,8                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Concession Building:
16-1821   New Construction             7-015-001  01/09/18     DONE    DONE       DONE      05/12/17   05/12/17   03/10/17   08/25/16   02 - 16                        0             0  DDJ             0           0           0 elark Patterson Lee                     0        /  /                           /  /             

          Press Box:
16-1822   New Construction             7-016-001  01/09/18     DONE    DONE       DONE      05/12/17   05/12/17   03/20/17   08/25/16   02 - 16                        0             0  DDJ             0           0           0 elark Patterson Lee                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MORAVIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-13-01-04
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle/High School:
14-0696   Reconstruction               0-002-008  12/24/14     DONE    DONE       DONE      12/01/14   11/25/14   10/23/14   05/20/14   2,7,9,16                 100,000       100,000  JMB             0           0           0 Hunt Engineers,Architects & l           0      06/30/15                       08/14/15           
14-0981   Reconstruction               0-002-009  06/12/15     DONE    DONE       DONE      01/20/15   01/16/15   10/23/14   05/20/14   2,8                      100,000       100,000  JMB             0           0           0 Hunt Engineers,Architects & l           0      01/05/16                       07/06/16           
15-0066   Reconstruction               0-002-010  01/12/17     DONE    DONE       DONE      07/15/15   07/10/15   06/16/15   12/02/14   2,4,7,8,9,155,15,16    1,748,554     1,748,554  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1155   Reconstruction               0-002-011  02/11/16     DONE    DONE       DONE      01/29/16   01/25/16   12/21/15   12/04/15   2,4,7,155,16           2,137,121     2,137,121  JMB             0           0           0 Hunt Engineers,Architects & l           0      09/30/16                       12/18/17           
15-1640   Reconstruction               0-002-012  05/25/16     DONE    DONE       DONE      04/28/16   04/28/16   03/25/16   05/17/16   8,9,16                   100,000       100,000  JMB             0           0           0 Hunt Engineers,Architects & l           0      05/03/17                       05/25/17           
17-0138   Reconstruction               0-002-013  11/07/17     DONE    DONE       DONE      07/28/17   07/28/17   06/05/17   05/16/16   2,16                     100,000             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Fillmore ES:
15-0067   Reconstruction               0-012-007  01/12/17     DONE    DONE       DONE      07/15/15   07/10/15   07/07/15   12/02/14   2,4,8,9,155,15,16        432,975             0  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1156   Reconstruction               0-012-008  02/11/16     DONE    DONE       DONE      01/29/16   01/25/16   12/21/15   12/04/15   2,4,9,15               1,232,314     1,232,314  JMB             0           0           0 Hunt Engineers,Architects & l           0      07/01/16                       10/12/16           
  -       Reconstruction               0-012-009                                              /  /       /  /     06/05/17     /  /     2,16                           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
15-1906SB Reconstruction               7-999-001               DONE                           /  /       /  /     06/10/16     /  /     13,16                          0             0  AAA             0           0           0                                         0        /  /                           /  /             
16-1352   Reconstruction               7-999-001  04/13/17     DONE    DONE       DONE      02/08/17   02/08/17     /  /     11/04/14   13,16                  1,081,921             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




UNION SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-19-01-04
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle/High School:
14-1616   Reconstruction               0-001-013  06/24/15     DONE    DONE       DONE      06/10/15   06/01/15   02/26/15   05/19/15   4,9,16                   100,000       100,000  DDJ             0           0           0 King & King Architects                  0      05/01/16                       06/22/16           
15-1843   Reconstruction               0-001-014  06/29/16     DONE    DONE       DONE      06/01/16   05/24/16   01/15/16   05/17/16   2,4,8,9,10               100,000       100,000  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             
17-1160   Reconstruction               0-001-015  04/23/18     DONE    DONE       DONE      01/09/18   12/21/17   11/09/16   11/07/16   2,7                       25,000        25,000  SLC             0           0           0 King & King Architects                  0        /  /                           /  /             
  -       Reconstruction               0-001-016                                              /  /       /  /     10/12/17     /  /     155,15,16                      0             0  SLC             0           0           0                                         0        /  /                           /  /             
17-1795   Reconstruction               0-001-017                         UNREVIEWED         05/02/18   04/30/18   03/14/18     /  /     15                             0             0  SLC             0           0           0 elark Patterson Lee                     0        /  /                           /  /             

          A.J. Smith Elementary School:
15-0864PR Reconstruction               0-006-011                         UNREVIEWED         12/11/15   12/10/15   10/28/15     /  /     2,4,7,8,9,155,15,16    8,653,000     7,776,914  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             
16-0682   Reconstruction               0-006-011  07/19/17     DONE    DONE       DONE      10/28/16   10/28/16   10/28/15   03/16/16   2,4,7,8,9,155,15,16    8,653,000     8,126,253  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             
16-0757SB Reconstruction               0-006-012               DONE                           /  /       /  /     11/10/16     /  /     13,16                          0     6,384,475  SLC             0           0           0                                         0        /  /                           /  /             
16-1432   Reconstruction               0-006-012  09/28/17     DONE    DONE       DONE      02/24/17   02/24/17     /  /     11/04/14   13,16                    376,001       376,001  SLC             0           0           0 King & King Architects                  0        /  /                           /  /             
17-1674   Reconstruction               0-006-013  01/25/17     DONE    DONE       DONE      04/09/18   04/09/18   02/14/17   01/09/17   2                         28,201             0  SLC             0           0           0 King & King Architects                  0        /  /                           /  /             
17-0282   Reconstruction               0-006-014  12/29/17     DONE    DONE       DONE      08/24/17   08/24/17   06/20/17   05/16/17   9                        100,000             0  SLC             0           0           0 King & King Architects                  0        /  /                           /  /             

          Storage Building:
15-1121DB Discovered Building          2-009-001  07/01/16     DONE    DONE       DONE      01/28/16   01/25/16   10/19/15     /  /                                    0             0  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             

          Bus Garage:
  -       Reconstruction               5-003-004                                              /  /       /  /     03/14/18     /  /     2,4,7,8,9,10,14,155,           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Baseball Dugout w Storage:
15-1122DB Discovered Building          7-010-001  07/01/16     DONE    DONE       DONE      01/28/16   01/25/16   11/30/15     /  /                                    0             0  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             

          Softball Dugout w Storage:
15-1123DB Discovered Building          7-011-001  07/01/16     DONE    DONE       DONE      01/28/16   01/25/16   11/30/15     /  /                                    0             0  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES CAYUGA-ONONDAGA STATUS REPORT ON CAPITAL PROJECTS
District No.: 05-90-00-00
last updated on 05/25/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alburn LDC / Access Center:
16-1883   Reconstruction               8-020-002  06/29/17     DONE    DONE       DONE      05/22/17   05/22/17   12/09/16   12/15/16   4,7,8                    194,928             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Auburn YMCA Classrooms:
16-0548TQ Temporary Quarters           8-033-001  05/23/17     DONE    DONE       DONE      10/03/16     /  /     07/28/16     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Instructional Support Center:
  -    TQ Temporary Quarters           8-035-001                                              /  /       /  /     05/04/18     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED