REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
08-0262 Reconstruction 0-005-018 01/27/09 DONE DONE DONE 09/08/08 09/02/08 03/11/08 03/25/08 2,4,9,10,15,16 2,804,643 2,804,643 JOD 0 0 21,773 Gordon W. Jones Associates 0 / / 05/13/13
09-1012 Reconstruction 0-005-019 05/11/10 DONE DONE DONE 03/04/10 03/01/10 01/20/10 03/25/08 2,4,8,9,10,155,15,16 754,522 754,522 JOD 0 0 0 Gordon W. Jones Associates 0 / / / /
- XX Reconstruction 0-005-020 CANCELLED / / / / 02/02/12 / / 2,9 0 11,286,912 JOD 0 0 0 0 / / / /
- XX Reconstruction 0-005-021 CANCELLED / / / / 02/02/12 / / 2,9,155,15,16 0 11,286,912 JOD 0 0 0 0 / / / /
Middle School:
08-0263 Reconstruction 0-006-012 01/27/09 DONE DONE DONE 09/08/08 09/02/08 02/12/08 03/25/08 2,4,7,9,15,16 1,564,983 1,564,983 JOD 0 0 0 Gordon W. Jones Associates 0 / / 05/13/13
09-1013 Reconstruction 0-006-013 05/11/10 DONE DONE DONE 03/04/10 03/01/10 01/20/10 03/25/08 16 60,375 60,375 JOD 0 0 0 Gordon W. Jones Associates 0 / / / /
- XX Reconstruction 0-006-014 CANCELLED / / / / 02/02/12 / / 155,15,16 0 15,206,400 JOD 0 0 0 0 / / / /
New Elementary School:
08-0264 Reconstruction 0-011-005 01/27/09 DONE DONE DONE 09/08/08 09/02/08 02/12/08 03/25/08 10,16 184,431 184,431 JOD 0 0 0 Gordon W. Jones Associates 0 / / 05/13/13
09-1014 Reconstruction 0-011-006 05/11/10 DONE DONE DONE 03/04/10 03/01/10 01/20/10 03/25/08 155,16 67,620 67,620 JOD 0 0 0 Gordon W. Jones Associates 0 / / / /
- XX Reconstruction 0-011-007 CANCELLED / / / / 02/02/12 / / 155,15,16 0 15,206,400 JOD 0 0 0 0 / / / /
Utility Building:
08-0099 New Construction 7-014-001 07/28/08 DONE DONE DONE 07/25/08 07/10/08 06/13/08 10/24/06 02 - 16 15,000 0 JOD 0 0 0 Gordon W. Jones Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Robert H Jackson Elementary:
12-0193 Reconstruction 0-002-009 11/21/12 DONE DONE DONE 09/18/12 09/17/12 12/10/10 03/08/12 2,8,9,155,15,16 508,026 508,026 JOD 0 0 0 Sandberg Kessler Architecture 0 / / / /
- Reconstruction 0-002-010 / / / / 09/21/12 / / 2,8,9,10,155,15,16 0 0 JMB 0 0 0 0 / / / /
STEEL POLE MAINT BLDG:
06-1608DB Discovered Building 2-012-001 07/17/08 DONE DONE DONE 06/13/07 06/07/07 02/03/00 / / 02 - 16 0 0 MGL 0 0 0 Harrington/Sandberg Arch. 0 / / / /
New Bus Maintenance/ Storage Facilty:
- PR New Construction 5-014-001 / / / / 12/15/10 / / 02 - 16 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
- Reconstruction 0-005-008 / / / / 11/21/11 / / 2 0 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
New PK-12:
09-1302 Reconstruction 0-012-005 11/05/10 DONE DONE DONE 04/14/10 04/08/10 07/31/09 12/09/10 2,4,7,8,9,155,15,16 4,375,000 4,375,000 HCM 0 0 281,043 Mach Architecture & Engineeri 0 / / / /
New Bus Garage:
- Reconstruction 5-013-003 / / / / 07/31/09 / / 2,9,155,15,16 0 0 HCM 0 0 0 0 / / / /
Alternative Energy Plant:
- PR New Construction 7-020-001 / / / / 08/07/09 / / 02 - 16 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior/Senior High School:
12-1113 Reconstruction 0-001-010 UNREVIEWED 04/17/13 04/17/13 10/07/10 11/21/11 10,13,155,15,16 0 11,708,295 DDJ 0 0 0 Clark Patterson Lee 0 / / / /
Pine Valley Elementary:
12-0325 Reconstruction 0-005-010 05/21/13 DONE DONE DONE 10/25/12 10/25/12 10/07/10 11/21/11 10,13,155,15,16 0 0 DDJ 0 0 0 Habiterra Associates 0 / / / /
Bus Garage:
12-1114 Reconstruction 5-002-007 UNREVIEWED 04/17/13 04/17/13 10/07/10 11/21/11 10,13,155,15,16 0 0 DDJ 0 0 0 Clark Patterson Lee 0 / / / /
Water Treatment Building:
12-0326 New Construction 7-008-001 05/21/13 DONE DONE DONE 10/25/12 10/25/12 07/18/12 11/21/11 02 - 16 0 0 DDJ 0 0 0 Habiterra Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Clymer Central School:
11-1254 Reconstruction 0-002-012 11/13/12 DONE DONE DONE 05/01/12 04/27/12 08/30/11 01/09/12 2,4,7,8,9,10,155,15, 401,300 0 HCM 0 0 31,789 Sandberg Kessler Architecture 0 / / / /
Equipment Storage Building:
10-0144DB Discovered Building 2-008-001 09/22/10 DONE DONE DONE 08/26/10 08/23/10 08/11/10 / / 0 0 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / / /
Clymer Bus Garage:
11-1255 Reconstruction 5-005-006 11/14/12 DONE DONE DONE 05/01/12 04/27/12 08/30/11 01/09/12 2,4,7,8,9,155,15,16 302,700 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
School #3:
09-1525 Additions and Alterations 0-002-007 10/19/10 DONE DONE DONE 06/15/10 06/07/10 08/10/07 03/31/09 02 - 16 3,890,901 3,716,028 HCM 0 0 183,340 Harrington/Sandberg Arch. 0 / / 09/04/12
12-0105 Reconstruction 0-002-008 01/23/13 DONE DONE DONE 08/14/12 08/03/12 04/11/12 12/06/11 2,9,155,16 267,437 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
School #4:
09-1391 Alterations 0-003-007 06/07/10 DONE DONE DONE 05/06/10 05/03/10 08/13/07 03/31/09 02 - 16 323,500 0 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / / /
09-1526 Additions and Alterations 0-003-008 10/19/10 DONE DONE DONE 06/15/10 06/07/10 05/12/10 03/31/09 02 - 16 5,500,641 4,644,977 HCM 0 0 682,596 Harrington/Sandberg Arch. 0 / / 03/29/13
12-0106 Reconstruction 0-003-009 01/23/13 DONE DONE DONE 08/14/12 08/03/12 04/11/12 12/06/11 2 45,729 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
School #5:
09-1392 Alterations 0-004-008 06/07/10 DONE DONE DONE 05/06/10 05/03/10 08/13/07 03/31/09 02 - 16 323,500 0 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / / /
09-1527 Additions and Alterations 0-004-009 10/19/10 DONE DONE DONE 06/15/10 06/07/10 05/12/10 03/31/09 02 - 16 5,274,349 4,621,859 HCM 0 0 529,113 Harrington/Sandberg Arch. 0 / / 03/29/13
12-0107 Reconstruction 0-004-010 01/23/13 DONE DONE DONE 08/14/12 08/03/12 04/11/12 12/06/11 2 218,780 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
School #7:
09-1528 Additions and Alterations 0-006-008 10/19/10 DONE DONE DONE 06/15/10 06/07/10 08/13/07 03/31/09 02 - 16 1,349,955 1,349,955 HCM 0 0 20,350 Harrington/Sandberg Arch. 0 / / 03/29/13
12-0108 Additions and Alterations 0-006-009 01/23/13 DONE DONE DONE 08/14/12 08/03/12 04/11/12 12/06/11 02 - 16 1,617,721 1,617,721 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
Middle School:
09-1529 Additions and Alterations 0-008-008 10/19/10 DONE DONE DONE 06/15/10 06/07/10 08/13/07 03/31/09 02 - 16 2,180,720 2,180,720 HCM 0 0 32,872 Harrington/Sandberg Arch. 0 / / 03/29/13
08-0763 Reconstruction 0-008-009 04/13/09 DONE DONE DONE 11/17/08 11/14/08 09/27/07 03/11/08 155,16 1,848,398 1,848,398 HCM 0 0 36,968 Harrington/Sandberg Arch. 0 / / / /
08-0058 Reconstruction 0-008-010 08/06/08 DONE DONE DONE 07/21/08 07/09/08 06/05/08 06/17/08 15 106,868 106,868 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / / /
09-1165 Reconstruction 0-008-011 05/06/10 DONE DONE DONE 03/31/10 03/24/10 02/19/10 03/11/08 2,4,7,8,9 134,732 134,732 HCM 0 0 2,695 Harrington/Sandberg Arch. 0 / / / /
10-0457 Reconstruction 0-008-012 03/08/11 DONE DONE DONE 11/12/10 11/08/10 08/03/10 11/05/08 2,8,9,155,15,16 920,300 920,300 HCM 0 0 18,406 Harrington/Sandberg Arch. 0 / / 03/29/13
11-0178 Reconstruction 0-008-013 10/05/11 DONE DONE DONE 09/19/11 09/19/11 06/30/11 04/01/09 7 974,250 974,250 HCM 0 0 19,490 Sandberg Kessler Architecture 0 / / / /
11-1064 Reconstruction 0-008-014 08/14/12 DONE DONE DONE 04/04/12 03/28/12 / / 04/02/09 2,8,9,155,15,16 370,800 370,800 HCM 0 0 7,416 Sandberg Kessler Architecture 0 / / / /
12-0109 Reconstruction 0-008-015 01/23/13 DONE DONE DONE 08/14/12 08/03/12 04/11/12 12/06/11 2,4,8,9,10,155,15,16 5,175,833 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
12-0201 Reconstruction 0-008-016 11/09/12 DONE DONE DONE 09/19/12 09/11/12 08/30/12 04/01/09 16 43,600 0 JMB 0 0 0 Sandberg Kessler Architecture 0 / / / /
Senior High School:
09-0530 Additions and Alterations 0-009-016 05/28/10 DONE DONE DONE 12/02/09 11/30/09 08/13/07 03/31/09 02 - 16 11,908,559 9,082,759 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / 09/06/12
08-0764 Reconstruction 0-009-017 04/13/09 DONE DONE DONE 11/17/08 11/14/08 09/27/07 03/11/08 155,16 5,671,602 5,619,502 HCM 0 0 113,432 Harrington/Sandberg Arch. 0 / / / /
12-0110 Reconstruction 0-009-018 01/23/13 DONE DONE DONE 08/14/12 08/03/12 04/11/12 12/06/11 2,9,155,15,16 982,500 982,500 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
Maintenance/Storage Building:
09-0531 New Construction 2-019-001 05/28/10 DONE DONE DONE 12/02/09 11/30/09 12/29/08 03/31/09 02 - 16 840,145 0 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / / /
Athletic Field Ticket Booth:
09-0504XX Reconstruction 7-021-001 CANCELLED 11/27/09 11/20/09 10/27/09 / / 0 0 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / / /
09-0532 Reconstruction 7-021-002 05/28/10 DONE DONE DONE 12/02/09 11/30/09 11/25/09 03/31/09 2,4,7,8,9,16 53,600 0 HCM 0 0 0 Harrington/Sandberg Arch. 0 / / 09/14/12
St. Hyacinth's Parochial School:
- XX Alterations 8-020-001 CANCELLED / / / / 10/27/09 / / 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bemus Point Elem.K-6:
12-0458 Reconstruction 0-002-008 DONE DONE UNREVIEWED11/20/12 11/19/12 05/21/12 03/25/12 16 0 10,144,922 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
- Reconstruction 0-002-009 / / / / 03/21/13 / / 2,4,7,8,9,10,155,15, 0 0 JOB 0 0 0 0 / / / /
Maple Grove High School:
12-0459 Reconstruction 0-005-008 DONE DONE UNREVIEWED11/20/12 11/19/12 05/21/12 03/25/12 16 0 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
12-0930 Reconstruction 0-005-009 10/05/12 DONE DONE DONE 02/28/13 02/27/13 10/18/12 10/22/12 2,15,16 450,000 0 JOB 0 0 0 Sandberg Kessler Architecture 0 / / / /
- PR Additions and Alterations 0-005-010 / / / / 03/21/13 / / 02 - 16 0 0 JOB 0 0 0 0 / / / /
Bus Garage:
12-0460 Reconstruction 5-001-005 DONE DONE UNREVIEWED11/20/12 11/19/12 05/21/12 03/25/12 16 0 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
- Additions and Alterations 5-001-006 / / / / 03/21/13 / / 02 - 16 0 0 JOB 0 0 0 0 / / / /
Athletic/Maintenance Storage:
12-0461 Reconstruction 7-010-002 DONE DONE UNREVIEWED11/20/12 11/19/12 05/21/12 03/25/12 16 0 0 HCM 0 0 0 Sandberg Kessler Architecture 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
11-0340 Reconstruction 0-001-009 01/05/12 DONE DONE DONE 11/03/11 11/02/11 05/19/11 06/14/11 2,4,9,155,16 1,790,759 1,637,620 JOD 0 0 0 Sandberg Kessler Architecture 0 / / / /
HARVEY C FENNER ELEMENTARY SCHOOL:
11-0341 Reconstruction 0-002-006 01/05/12 DONE DONE DONE 11/03/11 11/02/11 05/19/11 06/14/11 2,4,7,8,9,155,15,16 590,883 744,896 JOD 0 0 0 Sandberg Kessler Architecture 0 / / / /
Temple Elementary School:
11-0342 Reconstruction 0-007-006 01/05/12 DONE DONE DONE 11/03/11 11/02/11 05/19/11 06/14/11 2,4,9,155,16 204,334 214,400 JOD 0 0 0 Sandberg Kessler Architecture 0 / / / /
Track & Field Storage Building:
05-0113DB Discovered Building 2-010-001 12/23/09 DONE DONE DONE 08/09/05 08/09/05 05/05/05 / / 02 - 16 0 0 JOD 0 0 0 0 / / / /
Bus Garage:
11-0343 Reconstruction 5-003-004 01/05/12 DONE DONE DONE 11/03/11 11/02/11 05/19/11 06/14/11 4,16 114,024 103,084 JOD 0 0 0 Sandberg Kessler Architecture 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
K-12 Building(frmrly 6-12):
07-1349 Reconstruction 0-002-012 09/30/08 DONE DONE DONE 01/09/08 01/08/08 10/04/06 03/13/07 2,4,7,8,9,10,155,15, 8,702,733 8,702,733 DDJ 0 0 410,894 Habiterra Associates 0 / / / /
09-0131 Reconstruction 0-002-014 12/16/09 DONE DONE DONE 08/18/09 08/17/09 12/29/08 03/13/07 4,7,9,155,15,16 1,047,549 1,047,549 DDJ 0 0 0 Habiterra Associates 0 / / / /
- Reconstruction 0-002-015 / / / / 11/24/10 / / 8,10,13,16 0 27,213,294 DDJ 0 0 0 0 / / / /
11-1162 Reconstruction 0-002-016 09/18/12 DONE DONE DONE 04/25/12 04/20/12 03/16/11 03/24/11 2,4,7,8,9,10,13,155, 10,859,694 0 DDJ 0 0 449,163 Habiterra Associates 0 / / / /
10-1407 Reconstruction 0-002-017 07/26/11 DONE DONE DONE 06/17/11 06/14/11 04/15/11 03/24/11 2,7 1,701,050 1,701,050 DDJ 0 0 68,204 Habiterra Associates 0 / / / /
Bus Garage:
07-1350 Reconstruction 5-003-003 09/30/08 DONE DONE DONE 01/09/08 01/08/08 10/04/06 03/13/07 2,8,15,16 82,128 82,128 DDJ 0 0 0 Habiterra Associates 0 / / / /
09-0132 Reconstruction 5-003-005 12/16/09 DONE DONE DONE 08/18/09 08/17/09 05/07/09 03/13/07 8 15,000 0 DDJ 0 0 0 Habiterra Associates 0 / / / /
11-1163 Reconstruction 5-003-006 09/18/12 DONE DONE DONE 04/25/12 04/20/12 11/01/11 03/24/12 2,8,9,155,15,16 1,076,105 0 DDJ 0 0 0 Habiterra Associates 0 / / / /
- Reconstruction 5-003-007 / / / / / / / / 0 0 0 0 0 0 / / / /
New Press Box:
07-1351 New Construction 7-007-001 09/30/08 DONE DONE DONE 01/09/08 01/08/08 / / 03/13/07 02 - 16 51,900 0 DDJ 0 0 0 Habiterra Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary Building:
07-1717 Additions and Alterations 0-001-006 10/15/08 DONE DONE DONE 02/28/08 02/26/08 08/19/04 04/24/07 02 - 16 564,864 564,864 JOD 0 0 0 Trautman King Markwart Assoc. 0 / / / /
09-0595 Reconstruction 0-001-007 01/30/09 DONE DONE DONE 12/22/09 12/21/09 10/22/09 10/01/09 9 95,665 95,665 JOD 0 0 0 Trautman King Markwart Assoc. 0 / / 12/20/12
09-1425 Reconstruction 0-001-008 12/01/10 DONE DONE DONE 05/11/10 05/06/10 01/14/10 02/01/10 2,155,15,16 416,199 416,199 JOD 0 0 0 Trautman King Markwart Assoc. 416,199 / / / /
Forestville High School:
07-1718 Additions and Alterations 0-002-006 10/15/08 DONE DONE DONE 02/28/08 02/26/08 08/20/04 04/24/07 02 - 16 9,751,796 9,751,796 JOD 0 0 484,831 Trautman King Markwart Assoc. 0 / / / /
09-1426 Reconstruction 0-002-007 12/01/10 DONE DONE DONE 05/11/10 05/06/10 01/14/10 02/01/10 2,155,16 178,569 178,569 JOD 0 0 0 Trautman King Markwart Assoc. 178,569 / / / /
New Bus Garage:
07-1719 New Construction 5-004-002 10/15/08 DONE DONE DONE 02/28/08 02/26/08 01/05/05 04/24/07 02 - 16 1,450,590 1,450,590 JOD 0 0 0 Trautman King Markwart Assoc. 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Panama Central School:
08-0886 Additions and Alterations 0-002-010 04/30/09 DONE DONE DONE 12/09/08 12/08/08 08/20/07 06/24/08 02 - 16 6,680,000 6,680,000 MGL 0 0 221,758 Habiterra Associates 0 / / / /
12-0431 Reconstruction 0-002-011 12/31/12 DONE DONE DONE 11/16/12 11/13/12 07/05/12 06/24/08 4,9 130,000 130,000 HCM 0 0 0 Habiterra Associates 0 / / / /
12-1192 Reconstruction 0-002-012 UNREVIEWED 05/15/13 05/15/13 04/16/13 01/07/13 15,16 0 21,487,469 JMB 0 0 0 Clark Patterson Lee 0 / / / /
New Bus Garage:
12-1193 Reconstruction 5-010-003 UNREVIEWED 05/15/13 05/15/13 04/09/13 01/07/13 15,16 0 0 JMB 0 0 0 Clark Patterson Lee 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
New Technical Academy (Admin):
08-0576 Reconstruction 0-004-002 11/23/09 DONE DONE DONE 10/23/08 10/21/08 11/14/07 10/25/05 2,8,9,155,15,16 200,000 200,000 DDJ 0 0 3,922 Habiterra Associates 0 / / 07/05/12
High School:
08-0513PR Reconstruction 0-005-010 UNREVIEWED 10/14/08 10/08/08 11/14/07 / / 2,4,8,9,155,15,16 0 38,906,043 DDJ 0 0 0 Habiterra Associates 0 / / / /
08-0577 Reconstruction 0-005-010 11/23/09 DONE DONE DONE 10/23/08 10/21/08 11/14/07 10/25/05 2,4,8,9,155,15,16 5,375,000 5,375,000 DDJ 0 0 105,392 Habiterra Associates 0 / / 07/05/12
11-1134 Reconstruction 0-005-011 08/31/12 DONE DONE DONE 04/16/12 04/13/12 12/22/11 11/14/11 2,4,7,8,9,10,13,155, 3,950,000 3,950,000 DDJ 0 0 77,451 Habiterra Associates 0 / / / /
Lincoln School:
- Reconstruction 0-007-005 / / / / 03/27/09 / / 8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
- Reconstruction 0-007-006 / / / / 06/29/12 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
Carlyle Ring Elementary:
- Reconstruction 0-009-007 / / / / 03/27/09 / / 8,9,155,15,16 0 8,987,502 DDJ 0 0 0 0 / / / /
12-0763 Reconstruction 0-009-008 DONE DONE UNREVIEWED02/05/13 02/04/13 06/29/12 11/14/11 2,4,8,9,155,15,16 0 8,987,502 DDJ 0 0 0 Clark Patterson Lee 0 / / / /
12-0967 Reconstruction 0-009-009 03/18/13 DONE DONE DONE 03/14/13 03/13/13 02/15/13 11/14/12 2 100,000 0 DDJ 0 0 1,961 Clark Patterson Lee 0 / / / /
Clinton V Bush Elementary:
- Reconstruction 0-010-007 / / / / 03/27/09 / / 8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
11-0544 Reconstruction 0-010-008 11/29/11 DONE DONE DONE 12/22/11 12/22/11 12/01/11 10/25/05 155 75,000 75,000 DDJ 0 0 0 Habiterra Associates 0 / / 08/02/12
12-0506PR Reconstruction 0-010-009 UNREVIEWED 12/05/12 12/05/12 06/29/12 11/14/11 2,4,8,9,155,15,16 4,441,050 4,441,050 DDJ 0 0 87,079 Habiterra Associates 0 / / / /
Milton J. Fletcher School:
09-0749PR Additions and Alterations 0-012-007 UNREVIEWED 01/21/10 01/19/10 03/27/09 / / 02 - 16 6,550,000 6,550,000 DDJ 0 0 128,431 Habiterra Associates 0 / / / /
10-0822 Additions and Alterations 0-012-007 04/01/11 DONE DONE DONE 02/08/11 01/31/11 03/27/09 10/25/05 02 - 16 8,162,000 8,162,000 DDJ 0 0 160,039 Habiterra Associates 0 / / 09/24/12
Samuel G. Love School:
- Reconstruction 0-013-006 / / / / 03/27/09 / / 8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
Persell School:
08-0575 Reconstruction 0-014-005 11/23/09 DONE DONE DONE 10/23/08 10/21/08 11/14/07 10/25/05 2,4,7,8,9,155,15,16 3,200,000 3,105,451 DDJ 0 0 62,745 Habiterra Associates 0 / / 07/05/12
11-1135 Reconstruction 0-014-006 09/05/12 DONE DONE DONE 04/16/12 04/13/12 12/22/11 11/14/11 2,4,7,8,9,10,155,15, 3,000,000 3,000,000 DDJ 0 0 58,824 Habiterra Associates 0 / / / /
Roger Elementary:
- Reconstruction 0-018-008 / / / / 03/27/09 / / 8,9,155,15,16 0 7,859,712 DDJ 0 0 0 0 / / / /
Bus Garage:
11-1133 Reconstruction 5-021-002 09/05/12 DONE DONE DONE 04/16/12 04/13/12 12/22/11 11/14/11 4,13,155,15,16 500,000 500,000 DDJ 0 0 0 Habiterra Associates 0 / / / /
District Wide:
- Reconstruction 7-999-005 / / / / 12/11/12 / / 16 0 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Wheelock School K-3:
11-0663 Reconstruction 0-001-009 DONE DONE ADD. REQ'D01/17/12 01/11/12 09/02/11 10/11/11 2,10,155,16 0 10,932,625 HCM 0 0 0 Trautman King Markwart Assoc. 0 / / / /
Main Street Campus 3-12:
11-0664 Reconstruction 0-009-011 DONE DONE ADD. REQ'D01/17/12 01/11/12 09/02/11 10/11/11 2,10,155,16 0 40,360,238 HCM 0 0 0 Trautman King Markwart Assoc. 0 / / / /
12-0086 Reconstruction 0-009-012 09/13/12 DONE DONE DONE 08/08/12 08/01/12 03/15/12 03/27/12 4 147,300 0 HCM 0 0 0 RWArchitects 0 / / / /
- Reconstruction 0-009-013 / / / / 05/15/13 / / 2,4,7,9,15 0 0 JMB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Brocton Central:
11-0547 Reconstruction 0-001-008 04/18/12 DONE DONE DONE 12/22/11 12/22/11 11/06/06 02/15/11 2,4,7,8,9,10,13,14,1 16,000,000 16,000,000 DDJ 0 0 536,971 Sandberg Kessler Architecture 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
07-2116 Additions and Alterations 0-001-007 12/22/08 DONE DONE DONE 05/16/08 05/09/08 07/27/07 08/28/07 02 - 16 3,858,293 3,858,293 HCM 0 0 217,000 Habiterra Associates 0 / / / /
11-0800 Alterations 0-001-008 06/26/12 DONE DONE DONE 02/13/12 02/09/12 03/19/10 05/17/11 02 - 16 1,825,529 1,825,529 HCM 0 0 54,765 Habiterra Associates 0 / / / /
11-0083 Reconstruction 0-001-009 08/12/11 DONE DONE DONE 08/04/11 08/04/11 07/08/11 05/17/11 155,15 207,485 207,485 HCM 0 0 4,149 Habiterra Associates 0 / / 08/30/12
11-0387 Additions and Alterations 0-001-010 11/29/11 DONE DONE DONE 11/15/11 11/14/11 09/29/11 05/17/11 02 - 16 564,904 564,904 HCM 0 0 16,947 Habiterra Associates 0 / / / /
- Reconstruction 0-001-011 / / / / 04/10/13 / / 155,16 0 0 JMB 0 0 0 0 / / / /
Metal Storage Building:
- DB Discovered Building 2-005-001 / / / / / / / / 0 0 HCM 0 0 0 0 / / / /
- DB Discovered Building 2-005-001 / / / / 12/29/08 / / 0 0 HCM 0 0 0 0 / / / /
Athletic/Phys Ed Storage:
- DB Discovered Building 2-007-001 / / / / 12/29/08 / / 0 0 HCM 0 0 0 0 / / / /
Bus Garage/Ag Shop:
07-1820XX Reconstruction 5-002-001 12/22/08 CANCELLED 03/17/08 03/10/08 07/27/07 08/28/07 4,7,8,9,155,15,16 2,022,000 2,022,000 HCM 0 0 0 Habiterra Associates 0 / / / /
New Bus Garage:
08-1734 New Construction 5-004-001 12/22/08 DONE DONE DONE 06/24/09 06/24/09 12/02/08 08/05/08 02 - 16 1,963,707 1,963,707 HCM 0 0 0 Habiterra Associates 0 / / / /
- Reconstruction 5-004-002 / / / / 04/10/13 / / 155,16 0 0 JMB 0 0 0 0 / / / /
Press Box:
08-0591XX New Construction 7-003-001 12/22/08 CANCELLED 10/23/08 10/14/08 02/28/08 08/28/07 02 - 16 16,500 0 HCM 0 0 0 Habiterra Associates 0 / / / /
Concession Stand:
- DB Discovered Building 7-006-001 / / / / 12/29/08 / / 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Westfield Academy:
07-1252 Reconstruction 0-001-009 06/20/08 DONE DONE DONE 12/31/07 12/24/07 12/11/06 03/06/07 8,9,10,155,15 4,768,223 4,768,223 MGL 0 0 538,810 Habiterra Associates 0 / / / /
Wayside Building:
07-1253 Reconstruction 0-002-002 06/20/08 DONE DONE DONE 12/31/07 12/24/07 01/19/07 03/06/07 2,4,7,8,9,10,155,15, 13,000 0 MGL 0 0 0 Habiterra Associates 0 / / / /
Bus Garage:
07-1254 Reconstruction 5-003-004 06/20/08 DONE DONE DONE 12/31/07 12/24/07 12/11/06 03/06/07 2,7,8,9,155,15,16 496,000 496,000 MGL 0 0 0 Habiterra Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED