ELMIRA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-06-00-01
last updated on 05/22/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Coburn Elementary:
- Reconstruction 0-002-013 / / / / 09/21/12 / / 4,16 0 0 DDJ 0 0 0 0 / / / /
07-2194SC Visual Structural Inspection 0-002-SC1 09/30/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 3,992 0 JOD 0 0 0 0 / / / /
09-0010SC Visual Structural Inspection 0-002-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Booth Elementary:
08-0307 Reconstruction 0-003-013 03/11/09 DONE DONE DONE 09/11/08 09/08/08 02/23/06 10/09/06 2,4,7,8,9,155,15,16 1,530,000 1,530,000 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
07-2207SC Visual Structural Inspection 0-003-SC1 10/01/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 52,988 0 JOD 0 0 0 0 / / / /
09-0017SC Visual Structural Inspection 0-003-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Beecher Elementary:
- Reconstruction 0-005-010 / / / / 09/25/12 / / 4,155 0 0 DDJ 0 0 0 0 / / / /
08-0436SC Visual Structural Inspection 0-005-SC1 10/02/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 3,702 0 JOD 0 0 0 0 / / / /
09-0013SC Visual Structural Inspection 0-005-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Diven Elementary:
- Reconstruction 0-006-013 / / / / 09/21/12 / / 2,4 0 0 DDJ 0 0 0 0 / / / /
07-2193 Visual Structural Inspection 0-006-SC1 09/30/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 9,545 0 JOD 0 0 0 0 / / / /
09-0016SC Visual Structural Inspection 0-006-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Fassett Elementary School:
- Reconstruction 0-008-006 / / / / 09/25/12 / / 4,155 0 0 DDJ 0 0 0 0 / / / /
07-2195SC Visual Structural Inspection 0-008-SC1 09/30/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 11,541 0 JOD 0 0 0 0 / / / /
Thomas Natatorium Elmira Free Acad.:
07-2273 Reconstruction 0-009-005 01/12/09 DONE DONE DONE 06/23/08 06/12/08 02/23/06 10/19/06 2,4,7,8,9,155,15,16 92,190 92,190 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
08-0437SC Visual Structural Inspection 0-009-SC1 10/02/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 1,996 0 JOD 0 0 0 0 / / / /
Riverside Elementary:
- Reconstruction 0-012-011 / / / / 09/21/12 / / 4 0 0 DDJ 0 0 0 0 / / / /
09-0011SC Visual Structural Inspection 0-012-SC1 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Washington Elementary:
09-0009SC Visual Structural Inspection 0-013-SC1 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 10,500 0 JOD 0 0 0 0 / / / /
Hendy Avenue Elementary:
- Reconstruction 0-014-015 / / / / 09/21/12 / / 7 0 0 DDJ 0 0 0 0 / / / /
07-2197SC Visual Structural Inspection 0-014-SC1 09/30/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 5,988 0 JOD 0 0 0 0 / / / /
09-0015SC Visual Structural Inspection 0-014-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Ernie Davis Jr. High School:
08-0308 Reconstruction 0-015-015 03/11/09 DONE DONE DONE 09/11/08 09/08/08 02/23/06 10/09/06 2,4,7,8,9,155,15,16 670,000 670,000 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
07-2210SC Visual Structural Inspection 0-015-SC1 10/01/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 51,828 0 JOD 0 0 0 0 / / / /
09-0007SC Visual Structural Inspection 0-015-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 9,550 0 JOD 0 0 0 0 / / / /
Southside HS (see files DEC issue):
07-0539 Reconstruction 0-016-016 06/24/09 DONE DONE DONE 10/11/07 10/11/07 02/23/06 10/19/06 2,4,7,8,9,155,15,16 22,443,286 19,811,255 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
09-0852 Reconstruction 0-016-017 02/25/10 DONE DONE DONE 02/03/10 02/01/10 12/16/09 10/19/06 2 821,500 821,500 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
12-0759SR Reconstruction 0-016-018 03/05/13 DONE DONE DONE 02/01/13 01/22/13 09/21/12 08/30/06 2,4,7,8,9,10,155,15, 6,122,925 0 DDJ 0 0 0 0 / / / /
07-2208SC Visual Structural Inspection 0-016-SC1 10/01/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 74,475 0 JOD 0 0 0 0 / / / /
09-0005SC Visual Structural Inspection 0-016-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 9,750 0 JOD 0 0 0 0 / / / /
Pine City Elementary:
08-0309 Reconstruction 0-033-014 03/11/09 DONE DONE DONE 09/11/08 09/08/08 02/23/06 10/09/06 2,4,7,8,9,155,15,16 22,000 22,000 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
- Reconstruction 0-033-015 / / / / 09/21/12 / / 4 0 0 DDJ 0 0 0 0 / / / /
07-2196SC Visual Structural Inspection 0-033-SC1 09/30/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 1,996 0 JOD 0 0 0 0 / / / /
09-0012SC Visual Structural Inspection 0-033-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
Broadway ES(K-6)/MS(7-8):
08-0310 Reconstruction 0-034-016 03/11/09 DONE DONE DONE 09/11/08 09/08/08 02/23/06 10/09/06 2,4,7,8,9,155,15,16 1,545,000 1,545,000 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
- Reconstruction 0-034-017 / / / / 09/21/12 / / 2,4,9,16 0 0 DDJ 0 0 0 0 / / / /
07-2211SC Visual Structural Inspection 0-034-SC1 10/01/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 34,333 0 JOD 0 0 0 0 / / / /
09-0008SC Visual Structural Inspection 0-034-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 11,300 0 JOD 0 0 0 0 / / / /
Elmira Free Academy:
07-2274 Reconstruction 0-038-019 01/12/09 DONE DONE DONE 06/23/08 06/12/08 07/06/06 10/19/06 4,7,8,9,155,15,16 12,246,306 12,246,306 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
- Reconstruction 0-038-020 / / / / 09/21/12 / / 155,16 0 0 DDJ 0 0 0 0 / / / /
07-2209SC Visual Structural Inspection 0-038-SC1 10/01/08 DONE DONE DONE 05/19/08 05/19/08 / / / / 16 21,231 0 JOD 0 0 0 0 / / / /
09-0006SC Visual Structural Inspection 0-038-SC2 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 9,550 0 JOD 0 0 0 0 / / / /
Administration Building:
- Reconstruction 1-007-007 / / / / / / / / 7,16 0 0 DDJ 0 0 0 0 / / / /
Maintenance Building:
- Reconstruction 3-028-003 / / / / 09/21/12 / / 4 0 0 DDJ 0 0 0 0 / / / /
Bus Garage:
08-0311 Reconstruction 5-017-010 03/11/09 DONE DONE DONE 09/11/08 09/08/08 07/06/06 10/09/06 2,7,155,15,16 1,175,000 1,175,000 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
J Sloat Fassett School:
09-0014SC Visual Structural Inspection 7-008-SC1 07/29/09 DONE DONE DONE 06/29/09 06/29/09 / / / / 16 7,000 0 JOD 0 0 0 0 / / / /
District Wide:
07-1886 Reconstruction 7-999-009 05/29/08 DONE DONE DONE 03/31/08 03/21/08 07/19/07 01/17/07 10,13,16 8,798,212 8,798,212 DDJ 0 0 0 0 / / / /
09-1516 Reconstruction 7-999-010 09/30/10 DONE DONE DONE 06/09/10 06/03/10 03/24/10 03/17/10 16 977,000 977,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
12-0906 Reconstruction 7-999-011 UNREVIEWED 02/22/13 02/21/13 09/25/12 08/30/06 13,16 0 0 DDJ 0 0 0 Hunt Engineers, 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HORSEHEADS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-01-06
last updated on 05/22/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School South Wing:
09-0513 Reconstruction 0-001-016 02/26/10 DONE DONE DONE 11/27/09 11/24/09 12/05/07 05/19/09 2,4,7,8,9,155,15,16 56,947 56,947 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
10-0776 Reconstruction 0-001-017 05/24/11 DONE DONE DONE 01/26/11 01/26/11 04/07/10 05/18/10 2,4,8,9,16 88,726 88,726 JOD 0 0 0 0 / / / /
12-0556 Reconstruction 0-001-018 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 155,15,16 0 22,449,339 JMB 0 0 0 Hunt Engineers, 0 / / / /
08-1359SC Visual Structural Inspection 0-001-SC2 03/16/09 DONE DONE DONE 02/26/09 02/26/09 / / / / 16 31,675 0 JOD 0 0 0 0 / / / /
Center Street Elementary:
12-0557 Reconstruction 0-003-011 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 2,8,9,15,16 0 9,876,762 MFS 0 0 0 Hunt Engineers, 0 / / / /
09-0514 Reconstruction 0-003-016 02/26/10 DONE DONE DONE 11/27/09 11/24/09 07/31/09 05/19/09 2,4,7,9,13,155,15,16 77,473 77,473 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
Broad Street Elementary:
- Reconstruction 0-004-013 / / / / 04/07/10 / / 7 0 0 JOD 0 0 0 0 / / / /
12-0558 Reconstruction 0-004-014 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 7,15,16 0 9,876,762 MFS 0 0 0 Hunt Engineers, 0 / / / /
Big Flats Elementary:
12-0559 Reconstruction 0-006-009 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 2,16 0 9,876,762 MFS 0 0 0 Hunt Engineers, 0 / / / /
09-0515 Reconstruction 0-006-012 02/26/10 DONE DONE DONE 11/27/09 11/24/09 10/25/07 05/19/09 2,4,9,16 160,554 160,554 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
11-0651 Reconstruction 0-006-013 04/26/12 DONE DONE DONE 01/12/12 01/10/12 11/08/11 05/17/11 2,4,8,9,15,16 92,300 0 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
Ridge Road Elementary:
12-0560 Reconstruction 0-008-012 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 2,8,16 0 9,536,184 MFS 0 0 0 Hunt Engineers, 0 / / / /
11-0652 Reconstruction 0-008-015 04/26/12 DONE DONE DONE 01/12/12 01/10/12 11/08/11 05/17/11 15 15,400 0 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
worseheads SHS North Wing:
12-0561 Reconstruction 0-009-013 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 2,8,9,155,16 0 43,758,420 MFS 0 0 0 Hunt Engineers, 0 / / / /
09-0516 Reconstruction 0-009-020 02/26/10 DONE DONE DONE 11/27/09 11/24/09 12/05/07 05/19/09 2,4,8,9,155,15,16 133,017 133,017 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
10-0777 Reconstruction 0-009-021 05/24/11 DONE DONE DONE 01/26/11 01/26/11 12/06/10 05/18/10 2,4,155,15,16 312,986 312,986 JOD 0 0 0 0 / / / /
11-0653 Reconstruction 0-009-022 04/26/12 DONE DONE DONE 01/12/12 01/10/12 11/08/11 05/17/11 155 24,500 0 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
07-2179SC Visual Structural Inspection 0-009-SC2 09/26/08 DONE DONE DONE 04/30/08 04/30/08 / / / / 16 8,720 0 JOD 0 0 0 0 / / / /
07-2192SC Visual Structural Inspection 0-009-SC3 09/30/08 DONE DONE DONE 02/20/08 02/20/08 / / / / 16 13,000 0 JOD 0 0 0 0 / / / /
08-1358SC Visual Structural Inspection 0-009-SC4 03/16/09 DONE DONE DONE 02/26/09 02/26/09 / / / / 16 31,675 0 JOD 0 0 0 0 / / / /
Gardner Road Elementary:
12-0562 Reconstruction 0-012-011 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 155,15,16 0 8,410,203 JMB 0 0 0 Hunt Engineers, 0 / / / /
11-0654 Reconstruction 0-012-014 04/26/12 DONE DONE DONE 01/12/12 01/10/12 12/05/07 05/17/11 7,155,15,16 849,400 0 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
- Reconstruction 0-012-015 / / / / 08/25/09 / / 2,4,7,9,155,15,16 0 0 JOD 0 0 0 0 / / / /
- Reconstruction 0-012-016 / / / / 04/07/10 / / 4,9,16 0 0 JOD 0 0 0 0 / / / /
Middle School:
08-1053 Reconstruction 0-013-020 02/25/09 DONE DONE DONE 01/08/09 01/05/09 10/25/07 05/20/08 2,4,9,15,16 573,350 573,350 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
09-0517 Reconstruction 0-013-021 02/26/10 DONE DONE DONE 11/27/09 11/24/09 12/05/07 05/19/09 10,155,15,16 233,662 233,662 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
10-0778 Reconstruction 0-013-022 05/24/11 DONE DONE DONE 01/26/11 01/26/11 12/06/10 05/18/10 2,7,9,155,15,16 388,353 388,353 JOD 0 0 0 0 / / 09/14/12
11-0655 Reconstruction 0-013-023 04/26/12 DONE DONE DONE 01/12/12 01/10/12 11/08/11 05/17/11 8,9,155,15,16 657,883 418,400 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
Maintenance Dept:
12-0563 Reconstruction 3-007-001 05/17/13 DONE DONE DONE 12/14/12 12/12/12 11/27/12 05/21/12 2,4,7,8,9 0 0 JMB 0 0 0 Hunt Engineers, 0 / / / /
Bus Garage:
08-1054 Reconstruction 5-005-011 02/25/09 DONE DONE DONE 01/08/09 01/05/09 12/05/07 05/20/08 4,8,9,155,15,16 250,741 250,741 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
- Reconstruction 5-005-012 / / / / 04/07/10 / / 10,16 0 0 JOD 0 0 0 0 / / / /
Field House:
09-0518 Reconstruction 7-021-001 02/26/10 DONE DONE DONE 11/27/09 11/24/09 07/31/09 05/19/09 2,4,7,9,13,155,15,16 130,690 0 JOD 0 0 0 McDonald & Monterose LLP 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ELMIRA HEIGHTS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-02-06
last updated on 05/22/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Edison Jr/Sr High School:
09-0432 Reconstruction 0-001-009 03/23/10 DONE DONE DONE 11/18/09 11/13/09 07/17/09 03/20/07 2,7,8,9,10,155,15,16 1,428,962 1,428,962 JOD 0 0 0 Hunt Engineers, 0 / / / /
10-1114 Reconstruction 0-001-010 07/18/11 DONE DONE DONE 03/29/11 03/25/11 02/09/11 03/20/07 7,9,155,16 103,365 103,365 JOD 0 0 0 Hunt Engineers, 0 / / 09/24/12
Dr. N. Cohen Elementary:
09-0433 Reconstruction 0-007-013 03/23/10 DONE DONE DONE 11/18/09 11/13/09 07/17/09 03/20/07 2,7,9,155,15,16 1,275,365 1,275,365 JOD 0 0 0 Hunt Engineers, 0 / / / /
Bus Garage (lease @ horseheads):
12-1094 Reconstruction 5-014-L05 04/12/13 DONE DONE DONE 04/12/13 04/12/13 / / / / 21,647 21,647 JOB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED