ELMIRA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-06-00-01
last updated on 08/26/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Coburn Elementary:
13-1250   Reconstruction               0-002-013  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   4,16                     182,800             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0424   Reconstruction               0-002-014  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,8,9,155,16            88,987             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Beecher Elementary:
13-1251   Reconstruction               0-005-010  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/25/12   08/30/06   4,155                    120,700       120,700  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/06/15                       09/28/15           
14-0425   Reconstruction               0-005-011  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,8,155,15,16           81,393             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Diven Elementary:
13-1252   Reconstruction               0-006-013  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   2,4                      257,800       257,800  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/06/15                       09/28/15           
14-0426   Reconstruction               0-006-014  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,9,15,16              107,468             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Fassett Elementary School:
13-1253   Reconstruction               0-008-006  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/25/12   08/30/06   4,155                    171,000       171,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/06/15                       09/28/15           
14-0427   Reconstruction               0-008-007  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   4,7,9,155,15,16          302,151             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1393   Reconstruction               0-008-008  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   4,7,9,155,15,16          217,785       217,785  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/07/15                       09/28/15           

          Riverside Elementary:
13-1254   Reconstruction               0-012-011  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   4                         96,500             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0428   Reconstruction               0-012-012  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,7,8,155,16            71,898             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Hendy Avenue Elementary:
13-1255   Reconstruction               0-014-015  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   7                        130,700             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0429   Reconstruction               0-014-016  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   2,4,7,8,16               397,972             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Southside HS (see files DEC issue):
12-0759SR Reconstruction               0-016-018  03/05/13     DONE    DONE       DONE      02/01/13   01/22/13   09/21/12   08/30/06   2,4,7,8,9,10,155,15,   6,122,925     4,640,889  DDJ             0           0           0                                         0        /  /                           /  /             
12-1227   Additions and Alterations    0-016-018  04/23/13     DONE    DONE       DONE      05/28/13   05/24/13     /  /     08/30/06   02 - 16                6,122,925     6,122,925  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/02/14                       09/02/14           
14-0430   Reconstruction               0-016-019  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,7,8,9,10,155,15,     452,150             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Pine City Elementary:
13-1256   Reconstruction               0-033-015  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   4                         20,600             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0431   Reconstruction               0-033-016  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,7,8,9,10,155,15,     104,887             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Broadway ES(K-6)/MS(7-8):
13-1257   Reconstruction               0-034-017  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   2,4,9,16                  50,000             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0432   Reconstruction               0-034-018  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,8,9,155,16           394,050             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          ErnieDavisfmr Elm Free(1-007 comb.):
  -       Reconstruction               0-038-020                                              /  /       /  /     09/21/12     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-0433   Reconstruction               0-038-021  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,8,9,10,155,15,16   1,792,521             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0792   Reconstruction               0-038-022  01/06/16     DONE    DONE       DONE      12/18/14   12/16/14   12/05/14   05/20/14   2,8,9,155,15,16        2,000,000             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1256   Reconstruction               0-038-023  08/05/14     DONE    DONE       DONE      03/10/15   03/06/15   02/06/15   08/30/06   16                        98,786        98,786  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1255   Reconstruction               0-038-024  05/15/15     DONE    DONE       DONE      03/10/15   03/06/15   02/17/15   05/20/14   7,9,155,15,16            774,229       774,229  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/30/15                       03/21/16           
14-1394   Reconstruction               0-038-025  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   155,15,16                345,250       345,250  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/18/15                       03/21/16           

          Admin Bldg (combined with 0038 2016):
13-1258   Reconstruction               1-007-007  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14     /  /     08/30/06   7,16                     218,000             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0434   Reconstruction               1-007-008  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,8,9,10,155,15,16     170,499             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1395   Reconstruction               1-007-009  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   7,8,155,15,16            170,499             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/23/15                       03/21/16           

          Maintenance Building:
  -       Reconstruction               3-028-003                                              /  /       /  /     09/21/12     /  /     4                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-0435   Reconstruction               3-028-004  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   4,7,8,10,155,15,16        58,100             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Bus Garage:
13-0507   Reconstruction               5-017-011  03/05/13     DONE    DONE       DONE      10/10/13   10/07/13   09/04/13   01/09/13   14                       298,223       298,223  DDJ             0           0           0 Hunt Engineers,Architects & l           0      07/19/13                       10/07/13           
14-0436   Reconstruction               5-017-012  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,8,9,10,155,15,16     287,592             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1396   Reconstruction               5-017-013  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   8,15,16                   65,650             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          District-Wide:
12-0906   Reconstruction               7-999-011  10/15/13     DONE    DONE       DONE      02/22/13   02/21/13   09/25/12   08/30/06   13,16                  3,662,235     3,662,235  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/02/14                       09/02/14           
  -       Reconstruction               7-999-012                                              /  /       /  /       /  /       /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1110SB Reconstruction               7-999-012               DONE                           /  /       /  /     01/25/16     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-999-013                                              /  /       /  /     08/19/16     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    SB Visual Structural Inspection 7-999-SB1               DONE                           /  /       /  /       /  /       /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Finn Academy:An Elmira Charter Schl:
  -       Reconstruction               0-001-001                                              /  /       /  /     06/02/15     /  /     2,4,7,8,9,10,13,14,1           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Lease @ frmr Elmira Ernie Davis MS:
15-0268TQ Temporary Quarters           8-003-001  09/02/15     DONE    DONE       DONE      08/06/15   08/06/15   06/12/15     /  /                                    0             0  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
16-0308TQ Temporary Quarters           8-003-002                         UNREVIEWED         08/24/16   08/24/16   08/24/16     /  /                                    0             0  AAA             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Storage Shed:
  -    TQ Temporary Quarters           8-004-001                                              /  /       /  /     08/19/16     /  /                                    0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Utility Access Outbuilding:
  -    TQ Temporary Quarters           8-005-001                                              /  /       /  /     08/19/16     /  /                                    0             0  AAA             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HORSEHEADS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-01-06
last updated on 08/26/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School South Wing:
12-0556   Reconstruction               0-001-018  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   155,15,16                346,600       346,600  JMB             0           0           0 Hunt Engineers,Architects & l           0      01/06/14                       12/22/14           
13-0495   Reconstruction               0-001-019  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,15,16        144,073       144,073  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
15-0612SB Alterations                  0-001-020                         UNREVIEWED         10/22/15   10/22/15   09/14/15     /  /     02 - 16                        0    23,928,984  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1722   Alterations                  0-001-020               DONE    STARTED    STARTED   05/13/16   05/13/16   09/14/15   11/04/14   02 - 16                        0    23,928,984  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Center Street Elementary:
12-0557   Reconstruction               0-003-011  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   2,8,9,15,16              199,790       199,790  MFS             0           0           0 Hunt Engineers,Architects & l           0      01/06/14                       12/22/14           
13-0496   Reconstruction               0-003-017  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,15,16        143,187       143,187  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           

          Broad Street Elementary:
12-0558   Reconstruction               0-004-014  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   7,15,16                   49,531        49,531  MFS             0           0           0 Hunt Engineers,Architects & l           0      01/06/14                       12/22/14           

          Big Flats Elementary:
12-0559   Reconstruction               0-006-009  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   2,16                     178,999       178,999  MFS             0           0           0 Hunt Engineers,Architects & l           0      01/06/14                       12/22/14           
11-0651   Reconstruction               0-006-013  04/26/12     DONE    DONE       DONE      01/12/12   01/10/12   11/08/11   05/17/11   2,4,8,9,15,16             92,300        92,300  JOD             0           0           0 McDonald & Monterose LLP                0      08/15/13                       08/26/13           
13-0497   Reconstruction               0-006-014  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,15,16        457,403       457,403  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
15-0336   Reconstruction               0-006-015  05/16/16     DONE    DONE       DONE      08/20/15   08/18/15   08/20/15   05/19/15   2,4,9,155,15,16        1,000,000             0  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Ridge Road Elementary:
12-0560   Reconstruction               0-008-012  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   2,8,16                   193,231       193,231  MFS             0           0           0 Hunt Engineers,Architects & l           0      08/01/14                       12/22/14           
11-0652   Reconstruction               0-008-015  04/26/12     DONE    DONE       DONE      01/12/12   01/10/12   11/08/11   05/17/11   15                        15,400        15,400  JOD             0           0           0 McDonald & Monterose LLP                0      10/25/12                       11/08/13           
13-0498   Reconstruction               0-008-016  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   4,8,9,155,16             160,896       160,896  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           

          Horseheads SHS North Wing:
12-0561   Reconstruction               0-009-013  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   2,8,9,155,16             442,060       442,060  MFS             0           0           0 Hunt Engineers,Architects & l           0      01/06/14                       12/22/14           
11-0653   Reconstruction               0-009-022  04/26/12     DONE    DONE       DONE      01/12/12   01/10/12   11/08/11   05/17/11   155                       24,500        24,500  JOD             0           0           0 McDonald & Monterose LLP                0      10/25/12                       11/08/13           
13-0499   Reconstruction               0-009-023  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,16           143,984       143,984  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
14-0525   Reconstruction               0-009-024  03/31/15     DONE    DONE       DONE      10/22/14   10/22/14   06/12/14   05/20/14   2,4,8,9,155,15,16        214,528       214,528  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-0613SB Alterations                  0-009-025                         UNREVIEWED         10/22/15   10/22/15   09/11/15     /  /     02 - 16                        0    45,057,120  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1723   Alterations                  0-009-025               DONE    STARTED    STARTED   05/13/16   05/13/16   09/11/15   11/04/14   02 - 16                        0    45,057,120  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Gardner Road Elementary:
12-0562   Reconstruction               0-012-011  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   155,15,16                 61,952        61,952  JMB             0           0           0 Hunt Engineers,Architects & l           0      08/01/14                       12/22/14           
11-0654   Reconstruction               0-012-014  04/26/12     DONE    DONE       DONE      01/12/12   01/10/12   12/05/07   05/17/11   7,155,15,16              849,400       849,400  JOD             0           0           0 McDonald & Monterose LLP                0      12/13/12                       11/08/13           
13-0500   Reconstruction               0-012-017  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,16           120,427       120,427  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           

          Middle School:
11-0655   Reconstruction               0-013-023  04/26/12     DONE    DONE       DONE      01/12/12   01/10/12   11/08/11   05/17/11   8,9,155,15,16            657,883       657,883  JOD             0           0           0 McDonald & Monterose LLP                0      08/15/13                       08/26/13           
13-0501   Reconstruction               0-013-024  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,16           292,657       292,657  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
14-0526   Reconstruction               0-013-025  03/31/15     DONE    DONE       DONE      10/22/14   10/22/14   06/12/14   05/20/14   2,4,8,9,155,15,16        785,472             0  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1724   Reconstruction               0-013-026               DONE    STARTED    STARTED   05/13/16   05/13/16   09/14/15   05/19/15   2,4,7,8,9,155,15,16            0             0  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
  -       Reconstruction               0-013-027                                              /  /       /  /     06/03/16     /  /     2,9,10,155,16                  0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Maintenance Dept:
12-0563   Reconstruction               3-007-001  05/17/13     DONE    DONE       DONE      12/14/12   12/12/12   11/27/12   05/21/12   2,4,7,8,9                 27,837             0  JMB             0           0           0 Hunt Engineers,Architects & l           0      01/06/14                       12/22/14           

          Bus Garage:
14-0669   Reconstruction               5-005-013  01/23/14     DONE    DONE       DONE      11/21/14   11/21/14   02/11/14   10/24/13   14                       565,961       565,961  MFS             0           0           0 Hunt Engineers,Architects & l           0      07/25/14                       02/17/15           

          Concession Stand @ MS:
  -       New Construction             7-041-001                                              /  /       /  /     05/06/16     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Press Box @ MS:
  -       New Construction             7-042-001                                              /  /       /  /     05/11/16     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Dugout @ MS:
  -       New Construction             7-043-001                                              /  /       /  /     05/06/16     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELMIRA HEIGHTS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-02-06
last updated on 08/26/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Edison Jr/Sr High School:
14-0826   Reconstruction               0-001-011  03/10/15     DONE    DONE       DONE      12/23/14   12/22/14   11/24/14   05/20/14   2,155,16                 100,000       100,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       07/06/15           
  -       Reconstruction               0-001-012                                              /  /       /  /       /  /       /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1214SB Reconstruction               0-001-012                                              /  /       /  /     02/11/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1372   Reconstruction               0-001-013  04/18/16     DONE    DONE       DONE      03/04/16   03/03/16   02/16/16   03/01/16   2,4,8,9,16             1,003,464             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
  -       Reconstruction               0-001-014                                              /  /       /  /     06/08/16     /  /     8,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Cohen Elementary/Middle School:
15-0621   Reconstruction               0-007-014  11/19/15     DONE    DONE       DONE      10/27/15   10/23/15   09/25/15   05/19/15   2,10,16                  100,000       100,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      06/10/16                       06/16/16           
  -       Additions and Alterations    0-007-015                         UNREVIEWED         01/26/16   01/26/16   01/27/16     /  /     02 - 16                        0    18,887,460  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1174PR Additions and Alterations    0-007-015                         UNREVIEWED         02/02/16   01/26/16   01/27/16     /  /     02 - 16                        0    18,887,460  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1211SB Additions and Alterations    0-007-015                         UNREVIEWED         02/11/16   02/11/16   01/27/16     /  /     02 - 16                        0    18,887,460  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1373   Reconstruction               0-007-016  04/18/16     DONE    DONE       DONE      03/04/16   03/03/16   02/16/16   03/01/16   2,7,9,10,155,16        1,524,582             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Bus Garage (lease @ horseheads):
12-1094   Reconstruction               5-014-L05  04/12/13     DONE    DONE       DONE      04/12/13   04/12/13     /  /     06/18/13                             73,270        73,270  JOB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED