Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 08/17/18 at 08:45:34




ELMIRA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-06-00-01
last updated on 08/17/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Coburn Elementary:
13-1250   Reconstruction               0-002-013  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   4,16                     182,800       182,800  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0424   Reconstruction               0-002-014  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,8,9,155,16            88,987        88,987  DDJ             0           0           0 Hunt Engineers,Architects & l           0      12/22/16                       03/02/17           
16-1166   Reconstruction               0-002-015  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,16                   1,207,298     1,207,298  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
  -       Reconstruction               0-002-016                                              /  /       /  /     06/07/18     /  /     4,8,9,155                      0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Beecher Elementary:
13-1251   Reconstruction               0-005-010  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/25/12   08/30/06   4,155                    120,700       120,700  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/06/15                       09/28/15           
14-0425   Reconstruction               0-005-011  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,8,155,15,16           81,393        81,393  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/01/16                       11/04/16           
16-1167   Reconstruction               0-005-012  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,16                     172,000       172,000  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
  -       Reconstruction               0-005-013                                              /  /       /  /     06/07/18     /  /     4,8,9,155,16                   0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Diven Elementary:
13-1252   Reconstruction               0-006-013  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   2,4                      257,800       257,800  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/06/15                       09/28/15           
14-0426   Reconstruction               0-006-014  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,9,15,16              107,468       107,468  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/01/16                       12/05/16           
16-1168   Reconstruction               0-006-015  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,4,7,9,10,16          3,114,811     3,114,811  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           

          Fassett Elementary School:
13-1253   Reconstruction               0-008-006  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/25/12   08/30/06   4,155                    171,000       171,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/06/15                       09/28/15           
14-0427   Reconstruction               0-008-007  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   4,7,9,155,15,16          302,151       302,151  DDJ             0           0           0 Hunt Engineers,Architects & l           0      11/15/16                       03/02/17           
14-1393   Reconstruction               0-008-008  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   4,7,9,155,15,16          217,785       217,785  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/07/15                       09/28/15           
16-1169   Reconstruction               0-008-009  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,4,16                   515,561       515,561  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
  -       Reconstruction               0-008-010                                              /  /       /  /     06/07/18     /  /     155,15,16                      0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Thomas Natatorium Elmira Free Acad.:
  -       Reconstruction               0-009-006                                              /  /       /  /     02/08/18     /  /     7,9,155                        0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Riverside Elementary:
13-1254   Reconstruction               0-012-011  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   4                         96,500        96,500  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0428   Reconstruction               0-012-012  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,7,8,155,16            71,898        71,898  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/01/16                       11/04/16           
16-1170   Reconstruction               0-012-013  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,4,16                   179,000       179,000  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
  -       Reconstruction               0-012-014                                              /  /       /  /     06/07/18     /  /     2,7,155,15,16                  0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Hendy Avenue Elementary:
13-1255   Reconstruction               0-014-015  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   7                        130,700       130,700  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0429   Reconstruction               0-014-016  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   2,4,7,8,16               397,972       397,972  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/28/16                       03/02/17           
16-1171   Reconstruction               0-014-017  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,4,8,16               1,215,777     1,215,777  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           

          Southside HS (see files DEC issue):
14-0430   Reconstruction               0-016-019  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,7,8,9,10,155,15,     452,150       452,150  DDJ             0           0           0 Hunt Engineers,Architects & l           0      03/08/17                       05/03/17           
16-0924   Reconstruction               0-016-020  03/16/17     DONE    DONE       DONE      12/06/16   12/05/16   10/05/16   03/18/16   2,10,16                5,492,951     5,492,951  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
17-0585   Reconstruction               0-016-021  02/22/18     DONE    DONE       DONE      10/16/17   10/11/17   06/29/17   03/16/16   2,4,10                 3,038,910             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
18-0217   Reconstruction               0-016-022                         UNREVIEWED         08/09/18   08/06/18   06/07/18   03/16/16   4,7,8,9,155,15,16              0             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Pine City Elementary:
13-1256   Reconstruction               0-033-015  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   4                         20,600        20,600  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0431   Reconstruction               0-033-016  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,7,8,9,10,155,15,     104,887       104,887  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/06/16                       03/02/17           
16-1172   Reconstruction               0-033-017  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   11/29/16   03/16/16   2,16                     210,000       210,000  MTM             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
  -       Reconstruction               0-033-018                                              /  /       /  /     06/07/18     /  /     2,4,7,8,9,10,14,155,           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Broadway ES(K-6)/MS(7-8):
13-1257   Reconstruction               0-034-017  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14   09/21/12   08/30/06   2,4,9,16                  50,000        50,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0432   Reconstruction               0-034-018  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/14/14   08/30/06   4,7,8,9,155,16           394,050       394,050  DDJ             0           0           0 Hunt Engineers,Architects & l           0      11/05/16                       03/02/17           
16-0752   Reconstruction               0-034-019  02/17/17     DONE    DONE       DONE      11/10/16   11/09/16   10/05/16   03/16/16   2,7,8,9,10,155,15,16   8,206,242     8,206,242  MTM             0           0           0 Hunt Engineers,Architects & l           0      10/31/17                       07/05/18           
  -       Reconstruction               0-034-020                                              /  /       /  /     08/09/18     /  /     9,155,16                       0             0  MTM             0           0           0                                         0        /  /                           /  /             

          ErnieDavisfmr Elm Free(1-007 comb.):
14-0433   Reconstruction               0-038-021  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,8,9,10,155,15,16   1,792,521     1,792,521  DDJ             0           0           0 Hunt Engineers,Architects & l           0      03/09/17                       06/15/17           
14-0792   Reconstruction               0-038-022  01/06/16     DONE    DONE       DONE      12/18/14   12/16/14   12/05/14   05/20/14   2,8,9,155,15,16        2,000,000     2,000,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/16/16                       12/09/16           
14-1256   Reconstruction               0-038-023  08/05/14     DONE    DONE       DONE      03/10/15   03/06/15   02/06/15   08/06/14   16                        98,786        98,786  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/29/14                       05/03/17           
14-1255   Reconstruction               0-038-024  05/15/15     DONE    DONE       DONE      03/10/15   03/06/15   02/17/15   05/20/14   7,9,155,15,16            774,229       774,229  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/30/15                       03/21/16           
14-1394   Reconstruction               0-038-025  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   155,15,16                345,250       345,250  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/18/15                       03/21/16           
  -    PR Additions and Alterations    0-038-026                                              /  /       /  /     06/29/17     /  /     02 - 16                        0             0  MTM             0           0           0                                         0        /  /                           /  /             
17-0309   Additions and Alterations    0-038-026  04/06/18     DONE    DONE       DONE      08/28/17   08/28/17   06/29/17   03/16/16   02 - 16               20,759,120             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
17-0686   Reconstruction               0-038-027  02/14/18     DONE    DONE       DONE      11/01/17   11/01/17   10/04/17   03/16/16   2,155                    900,000             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
18-0043   Reconstruction               0-038-028               UNREVIEWED
                                                                       STARTED    UNREVIEWED07/09/18   07/02/18   06/07/18   03/16/16   2,4,8,9,10,13,155,15           0             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Admin Bldg (combined with 0038 2016):
13-1258   Reconstruction               1-007-007  06/11/14     DONE    DONE       DONE      02/21/14   02/20/14     /  /     08/30/06   7,16                     218,000             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0434   Reconstruction               1-007-008  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,8,9,10,155,15,16     170,499             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1395   Reconstruction               1-007-009  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   7,8,155,15,16            170,499             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/23/15                       03/21/16           

          Field House South Side:
18-0218   Reconstruction               2-044-001                         UNREVIEWED         08/09/18   08/06/18   06/07/18   03/16/16   7                              0             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Benjamin Building:
17-1121DB Discovered Building          2-076-002  02/08/18     DONE    DONE       DONE      01/04/18     /  /     11/06/17     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Maintenance Building:
16-1173   Reconstruction               3-028-003  04/07/17     DONE    DONE       DONE      01/12/17   01/12/17   09/21/12   03/16/16   4                        257,000             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       07/05/18           
14-0435   Reconstruction               3-028-004  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   4,7,8,10,155,15,16        58,100             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0      10/01/16                       03/02/17           
  -       Reconstruction               3-028-005                                              /  /       /  /     11/29/16     /  /     2                              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
13-0507   Reconstruction               5-017-011  03/05/13     DONE    DONE       DONE      10/10/13   10/07/13   09/04/13   01/09/13   14                       298,223       298,223  DDJ             0           0           0 Hunt Engineers,Architects & l           0      07/19/13                       10/07/13           
14-0436   Reconstruction               5-017-012  10/07/15     DONE    DONE       DONE      10/09/14   10/09/14   02/18/14   08/30/06   2,4,8,9,10,155,15,16     287,592       287,592  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/06/16                       03/02/17           
14-1396   Reconstruction               5-017-013  06/04/15     DONE    DONE       DONE      04/10/15   04/10/15   03/12/15   08/30/06   8,15,16                   65,650        65,650  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/10/16                       10/03/16           
  -       Reconstruction               5-017-014                                              /  /       /  /     06/07/18     /  /     2,4,7,8,9,155,15,16            0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
12-0906   Reconstruction               7-999-011  10/15/13     DONE    DONE       DONE      02/22/13   02/21/13   09/25/12   08/30/06   13,16                  3,549,481     3,549,481  DDJ             0           0           0 Hunt Engineers,Architects & l           0      09/02/14                       09/02/14           
15-1110SB Reconstruction               7-999-012               DONE                           /  /       /  /     01/25/16     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
16-0613   Reconstruction               7-999-012  05/04/17     DONE    DONE       DONE      10/12/16   10/11/16     /  /     11/04/14   16                     4,310,428             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
16-0428   Reconstruction               7-999-013  09/23/16     DONE    DONE       DONE      09/15/16   09/14/16   08/19/16   03/16/16   16                       536,096       536,096  DDJ             0           0           0 Hunt Engineers,Architects & l           0      01/06/17                       05/03/17           
  -    SB Alterations                  7-999-BA1               DONE                           /  /       /  /       /  /       /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Finn Academy:An Elmira Charter Schl:
  -       Reconstruction               0-001-001                                              /  /       /  /     06/02/15     /  /     2,4,7,8,9,10,13,14,1           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Lease @ frmr Elmira Ernie Davis MS:
15-0268TQ Temporary Quarters           8-003-001  09/02/15     DONE    DONE       DONE      08/06/15   08/06/15   06/12/15     /  /                                    0             0  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
16-0308TQ Temporary Quarters           8-003-002  09/05/17     DONE    DONE       DONE      08/24/16   08/24/16   08/24/16     /  /                                    0             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Storage Shed:
  -    TQ Temporary Quarters           8-004-001                                              /  /       /  /     08/19/16     /  /                                    0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Utility Access Outbuilding:
  -    TQ Temporary Quarters           8-005-001                                              /  /       /  /     08/19/16     /  /                                    0             0  AAA             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HORSEHEADS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-01-06
last updated on 08/17/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          XXSr HS S. Wing (combined w 0-009):
13-0495   Reconstruction               0-001-019  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,15,16        144,073       144,073  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
15-0612SB Alterations                  0-001-020                         UNREVIEWED         10/22/15   10/22/15   09/14/15     /  /     02 - 16                        0    23,928,984  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1722   Alterations                  0-001-020  02/02/17     DONE    DONE       DONE      05/13/16   05/13/16   09/14/15   11/04/14   02 - 16                1,464,931     1,464,931  MFS             0           0           0 Hunt Engineers,Architects & l           0      10/01/17                       04/18/18           

          Center Street Elementary:
13-0496   Reconstruction               0-003-017  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,15,16        143,187       143,187  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
16-2000   Reconstruction               0-003-018  12/20/17     DONE    DONE       DONE      06/07/17   06/07/17   05/30/17   05/16/17   7,155,16                 259,670       259,670  SLC             0           0           0 Hunt Engineers,Architects & l           0      05/16/17                         /  /             
17-0704   Reconstruction               0-003-019  02/26/18     DONE    DONE       DONE      11/03/17   11/01/17   11/01/17   10/17/17   2,7,9,155,16           1,329,357             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Big Flats Elementary:
13-0497   Reconstruction               0-006-014  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,15,16        457,403       457,403  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
15-0336   Reconstruction               0-006-015  05/16/16     DONE    DONE       DONE      08/20/15   08/18/15   08/20/15   05/19/15   2,4,9,155,15,16        1,000,000     1,000,000  MFS             0           0           0 Hunt Engineers,Architects & l           0      09/23/16                       11/28/16           
17-0705   Reconstruction               0-006-016  02/26/18     DONE    DONE       DONE      11/03/17   11/01/17   11/01/17   10/17/17   2,4,7,8,15,16          1,652,746             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Ridge Road Elementary:
13-0498   Reconstruction               0-008-016  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   4,8,9,155,16             160,896       160,896  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
17-0706   Reconstruction               0-008-017  02/26/18     DONE    DONE       DONE      11/03/17   11/01/17   10/23/17   10/17/17   2,4,7,8,9,155,15,16    2,575,879             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Senior High School (fmly North Wing):
13-0499   Reconstruction               0-009-023  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,16           143,984       143,984  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
14-0525   Reconstruction               0-009-024  03/31/15     DONE    DONE       DONE      10/22/14   10/22/14   06/12/14   05/20/14   2,4,8,9,155,15,16        264,602       264,602  MFS             0           0           0 Hunt Engineers,Architects & l           0      09/30/16                       06/08/17           
15-0613SB Alterations                  0-009-025                         UNREVIEWED         10/22/15   10/22/15   09/11/15     /  /     02 - 16                        0    45,057,120  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1723   Alterations                  0-009-025  02/02/17     DONE    DONE       DONE      05/13/16   05/13/16   09/11/15   11/04/14   02 - 16                1,464,931     1,464,931  MFS             0           0           0 Hunt Engineers,Architects & l           0      10/01/17                       04/18/18           
16-1707PR Additions and Alterations    0-009-026                                            04/20/17     /  /     04/05/17     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
16-2001   Reconstruction               0-009-027  12/20/17     DONE    DONE       DONE      06/07/17   06/07/17   05/30/17   05/16/17   7,155,16                 700,330       700,330  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Gardner Road Elementary:
13-0500   Reconstruction               0-012-017  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,16           120,427       120,427  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
17-0707   Reconstruction               0-012-018  02/26/18     DONE    DONE       DONE      11/03/17   11/01/17   11/01/17   10/17/17   2,8,155,15,16          2,902,263             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Middle School:
13-0501   Reconstruction               0-013-024  05/02/14     DONE    DONE       DONE      10/09/13   10/02/13   09/05/13   05/21/13   2,4,8,9,155,16           292,657       292,657  MFS             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       11/16/15           
14-0526   Reconstruction               0-013-025  03/31/15     DONE    DONE       DONE      10/22/14   10/22/14   06/12/14   05/20/14   2,4,8,9,155,15,16        785,472       785,472  MFS             0           0           0 Hunt Engineers,Architects & l           0      09/30/16                       06/19/17           
15-1724   Reconstruction               0-013-026  02/02/17     DONE    DONE       DONE      05/13/16   05/13/16   09/14/15   05/19/15   2,4,7,8,9,155,15,16    2,750,000     2,750,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      10/01/17                       04/18/18           
16-0387   Reconstruction               0-013-027  02/02/17     DONE    DONE       DONE      09/07/16   09/07/16   06/03/16   05/17/16   2,9,10,155,16          1,000,000     1,000,000  MFS             0           0           0 Hunt Engineers,Architects & l           0      09/01/17                       04/23/18           

          Bus Garage:
14-0669   Reconstruction               5-005-013  01/23/14     DONE    DONE       DONE      11/21/14   11/21/14   02/11/14   10/24/13   14                       565,961       565,961  MFS             0           0           0 Hunt Engineers,Architects & l           0      07/25/14                       02/17/15           
17-0708   Reconstruction               5-005-014  02/26/18     DONE    DONE       DONE      11/03/17   11/01/17   11/01/17   10/17/17   9,15,16                  158,965             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Concession Stand @ MS:
16-1214   New Construction             7-041-001  02/02/17     DONE    DONE       DONE      01/19/17   01/19/17   05/06/16   05/19/15   02 - 16                   98,800             0  SLC             0           0           0 Hunt Engineers,Architects & l           0      10/01/17                       04/18/18           

          Press Box @ MS:
16-1215   New Construction             7-042-001  02/02/17     DONE    DONE       DONE      01/19/17   01/19/17   05/11/16   05/19/15   02 - 16                   98,500             0  SLC             0           0           0 Hunt Engineers,Architects & l           0      10/01/17                       04/18/18           

          Dugout @ MS:
16-1216   New Construction             7-043-001  02/02/17     DONE    DONE       DONE      01/19/17   01/19/17   05/06/16   05/19/15   02 - 16                   52,700             0  SLC             0           0           0 Hunt Engineers,Architects & l           0      10/01/17                       04/18/18           

          Districtwide:
17-1281   Reconstruction               7-999-002  06/01/18     DONE    DONE       DONE      01/31/18   01/17/18   12/22/17   10/17/17   10,13,155,16           5,575,594     1,053,843  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELMIRA HEIGHTS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-02-06
last updated on 08/17/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Edison Jr/Sr High School:
14-0826   Reconstruction               0-001-011  03/10/15     DONE    DONE       DONE      12/23/14   12/22/14   11/24/14   05/20/14   2,155,16                 100,000       100,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      06/29/15                       07/06/15           
15-1214SB Reconstruction               0-001-012               DONE                           /  /       /  /     02/11/16     /  /     13,16                          0    27,582,264  DDJ             0           0           0                                         0        /  /                           /  /             
16-0744   Reconstruction               0-001-012  07/20/17     DONE    DONE       DONE      11/07/16   11/07/16     /  /     03/01/16   13,16                  4,212,854     4,212,854  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1372   Reconstruction               0-001-013  04/18/16     DONE    DONE       DONE      03/04/16   03/03/16   02/16/16   03/01/16   2,4,8,9,16             1,003,464     1,003,464  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/23/16                       09/26/16           
16-0498   Reconstruction               0-001-014  11/29/16     DONE    DONE       DONE      09/26/16   09/26/16   06/08/16   05/17/16   8,155,15,16              100,000       100,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      05/08/17                       06/19/17           
17-0013   Reconstruction               0-001-015  11/08/17     DONE    DONE       DONE      07/05/17   07/03/17   05/19/17   05/16/17   2,4,8,155,15,16          100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      05/11/18                       06/11/18           

          Cohen Elementary/Middle School:
15-0621   Reconstruction               0-007-014  11/19/15     DONE    DONE       DONE      10/27/15   10/23/15   09/25/15   05/19/15   2,10,16                  100,000       100,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      06/10/16                       06/16/16           
15-1174PR Additions and Alterations    0-007-015                         UNREVIEWED         02/02/16   01/26/16   01/27/16     /  /     02 - 16                        0    20,733,720  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1211SB Additions and Alterations    0-007-015                         UNREVIEWED         02/11/16   02/11/16   01/27/16     /  /     02 - 16                        0    20,733,720  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
16-0745   Additions and Alterations    0-007-015  07/20/17     DONE    DONE       DONE      11/07/16   11/07/16   01/27/16   03/01/16   02 - 16                5,610,741     5,305,449  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
15-1373   Reconstruction               0-007-016  04/18/16     DONE    DONE       DONE      03/04/16   03/03/16   02/16/16   03/01/16   2,7,9,10,155,16        1,524,582     1,524,582  DDJ             0           0           0 Hunt Engineers,Architects & l           0      08/23/16                       02/07/17           
18-0185   Reconstruction               0-007-017                         UNREVIEWED         08/03/18   07/27/18   06/20/18   05/15/18   16                             0    14,539,785  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED