AFTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-01-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-1574   Reconstruction               0-001-009  02/10/11     DONE    DONE       DONE      07/02/10   06/22/10   10/07/08   01/09/09   2,4,7,8,9,155,15,16   10,750,000    10,750,000  JOD             0           0     533,858                                         0      06/14/12                       11/02/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-1091   Reconstruction               0-001-011  06/29/12     DONE    DONE       DONE      04/06/12   04/05/12   02/02/12   01/09/09   2,4,8,9,155,15,16      3,458,480     3,458,480  JOD             0           0     273,220                                         0        /  /                           /  /             
13-0719   Reconstruction               0-001-012  07/14/14     DONE    DONE       DONE      11/18/13   11/13/13   03/07/13   02/21/13   2,4,9,13               1,251,500             0  DDJ             0           0           0 BIVENS ARCHITECTS                       0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-013                                              /  /       /  /     01/29/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage Annex:
12-0618   Reconstruction               4-006-002  02/22/13     DONE    DONE       DONE      12/26/12   12/23/12   07/18/11   11/03/11   7,16                     124,450             0  DDJ             0           0           0 BIVENS ARCHITECTS                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BAINBRIDGE-GUILFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-02-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
  -       Reconstruction               0-001-018                                              /  /       /  /     06/30/11     /  /     2,16                           0             0  HCM             0           0           0                                         0        /  /                           /  /             
12-0130   Reconstruction               0-001-019  08/20/11     DONE    DONE       DONE      08/30/12   07/30/12   08/21/12   07/30/07   15                        46,375        46,375  JMB             0           0           0                                         0      05/04/12                       02/23/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Greenlawn Elementary:
  -       Reconstruction               0-002-013                                              /  /       /  /     06/30/11     /  /     2,15,16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Elementary School:
  -       Reconstruction               0-003-011                                              /  /       /  /     07/18/11     /  /     2                              0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREENE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-06-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 6-12:
10-0544   Reconstruction               0-002-018  09/06/11     DONE    DONE       DONE      12/06/10   11/24/10   11/05/10   12/11/07   2,4,7,8,9,10,14,155,   1,961,980     1,961,980  HCM             0           0           0 Tetra Tech Architects And Eni           0      03/15/13                       11/29/13           
11-0882   Reconstruction               0-002-019  04/17/12     DONE    DONE       DONE      03/06/12   03/02/12   02/07/12   12/11/07   7                        231,000       231,000  HCM             0           0           0 Tetra Tech Architects And Eni           0      07/01/13                       06/09/14           

          Intermediate School:
10-0545   Reconstruction               0-003-015  03/31/11     DONE    DONE       DONE      12/06/10   11/24/10   11/05/10   12/11/07   2,7,8,9,10,155,15,16     687,792       687,792  HCM             0           0           0 Tetra Tech Architects And Eni           0      03/15/13                       11/29/13           

          Primary School:
10-0546   Reconstruction               0-004-015  03/31/11     DONE    DONE       DONE      12/06/10   11/24/10   11/05/10   12/11/07   2,4,8,9,10,155,15,16   1,283,299     1,283,299  HCM             0           0           0 Tetra Tech Architects And Eni           0      03/15/13                       11/29/13           
10-1040   Reconstruction               0-004-016  04/14/11     DONE    DONE       DONE      03/15/11   03/10/11   02/16/11   12/22/10   2,8,9,16                 140,000             0  HCM             0           0           0 Tetra Tech Architects And Eni           0        /  /                           /  /             

          Bus Garage:
10-0547   Reconstruction               5-005-012  03/31/11     DONE    DONE       DONE      12/06/10   11/24/10   11/05/10   12/11/07   2,8,9,155,16             275,611       275,611  HCM             0           0           0 Tetra Tech Architects And Eni           0      03/15/13                       11/29/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




UNADILLA VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-10-03-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Pre K-12 Building:
12-0429   Reconstruction               0-014-005  12/17/12     DONE    DONE       DONE      11/16/12   11/01/12     /  /     06/19/12   8,16                     100,000       100,000  DDJ             0           0           0 King & King Architects                  0      04/22/13                       05/06/13           
13-0100   Reconstruction               0-014-006  08/07/13     DONE    DONE       DONE      07/24/13   07/24/13   05/09/13   05/13/13   16                       100,000       100,000  DDJ             0           0           0 King & King Architects                  0      01/01/14                       02/24/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORWICH CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-12-00-05
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Guernsey Mem. Library:
  -       Reconstruction               6-022-004                                              /  /       /  /     08/05/13     /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OTSELIC VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-14-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Bldg (frmrly Jr/Sr High School):
11-0997PR Additions and Alterations    0-001-007                         UNREVIEWED         03/20/12   03/20/12   04/22/11     /  /     02 - 16                        0    11,339,052  DDJ             0           0           0 Teitsch-Kent-Fay Architects             0        /  /                           /  /             
11-0998SR Reconstruction               0-001-007  03/28/12     DONE    DONE       DONE      03/20/12   03/06/12     /  /       /  /                           12,650,900    11,365,123  DDJ             0           0     333,856 Teitsch-Kent-Fay Architects             0        /  /                           /  /             
11-1335   Additions and Alterations    0-001-007  01/15/13     DONE    DONE       DONE      05/24/12   05/17/12   04/22/11   09/28/11   02 - 16               12,650,900    11,879,310  DDJ             0           0     333,856 Teitsch-Kent-Fay Architects             0      12/01/13           YES           /  /             
11-1376   Reconstruction               0-001-008  05/08/12     DONE    DONE       DONE      06/01/12   05/25/12   05/01/12   09/28/11   7                        308,000       308,000  DDJ             0           0           0 Teitsch-Kent-Fay Architects             0      04/17/13                       04/17/13           
12-0192   Reconstruction               0-001-009  11/15/12     DONE    DONE       DONE      09/18/12   09/17/12   09/05/12   05/15/12   2,4,13,15,16             100,000       100,000  DDJ             0           0           0 Teitsch-Kent                            0      04/17/13                       06/11/13           
13-0809   Reconstruction               0-001-010  03/11/14     DONE    DONE       DONE      12/02/13   11/25/13   09/11/13   05/21/13   2,7,8,9,10,155,15,16     100,000             0  DDJ             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
  -       Reconstruction               0-001-011                                              /  /       /  /     04/01/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Agricultural Technology Building:
12-0205   New Construction             0-008-001  01/15/13     DONE    DONE       DONE      09/24/12   09/21/12   05/01/12   09/28/11   02 - 16                   80,000             0  DDJ             0           0           0 Teitsch-Kent                            0      04/16/14                       06/03/14           

          Storage Building:
12-0206   New Construction             2-009-001  01/15/13     DONE    DONE       DONE      09/24/12   09/21/12   05/01/12   09/28/11   02 - 16                   52,000             0  DDJ             0           0           0 Teitsch-Kent                            0      04/16/14                       06/03/14           

          Bus Garage (frmrly ES):
11-1336   Reconstruction               5-006-005  01/15/13     DONE    DONE       DONE      05/24/12   05/17/12   04/25/11   09/28/11   2,4,7,8,9,10,14,155,   3,517,000     3,517,000  DDJ             0           0           0 Teitsch-Kent                            0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OXFORD ACADEMY & CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-15-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Oxford Middle School:
08-1319   Additions and Alterations    0-002-016  04/07/09     DONE    DONE       DONE      03/03/09   03/02/09   02/23/09   05/20/08   02 - 16                  204,422       204,422  HCM             0           0           0 Bernier Carr Associates                 0      11/20/09                         /  /             
09-1590   Reconstruction               0-002-017  12/16/10     DONE    DONE       DONE      07/06/10   06/30/10   01/11/10   09/24/09   2,4,7,8,9,10,155,15,   1,930,948     1,930,948  HCM             0           0      90,101 Bernier Carr Associates                 0      01/20/12                       06/02/14           
11-1307   Reconstruction               0-002-018  12/31/12     DONE    DONE       DONE      05/16/12   05/14/12   11/15/11   06/23/11   2,4,7,8,9,155,15,16    6,886,238     6,886,238  HCM             0           0     593,114 Bernier Carr Associates                 0        /  /                           /  /             
12-0269   Reconstruction               0-002-019  04/03/13     DONE    DONE       DONE      10/11/12   10/02/12   08/21/12   09/24/09   4,8,9,10,155,15,16       594,280       594,280  JMB             0           0      77,049 Bernier Carr Associates                 0        /  /                           /  /             

          Oxford High School:
09-1591   Reconstruction               0-007-010  12/16/10     DONE    DONE       DONE      07/06/10   06/30/10   01/11/10   09/24/09   4,8,9,10,155,15,16       372,348       372,348  HCM             0           0      22,832 Bernier Carr Associates                 0      01/20/12                       06/02/14           
11-0994   Reconstruction               0-007-011  09/04/12     DONE    DONE       DONE      03/20/12   03/16/12   11/15/11   06/23/11   2,4,8,9,155,15,16      3,354,562             0  HCM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
12-0270   Reconstruction               0-007-012  04/03/13     DONE    DONE       DONE      10/11/12   10/02/12   08/21/12   09/24/09   4,7,8,9,155,15,16        301,641       301,641  JMB             0           0      25,941 Bernier Carr Associates                 0        /  /                           /  /             

          Primary School:
09-1592   Reconstruction               0-010-013  12/16/10     DONE    DONE       DONE      07/06/10   06/30/10   01/11/10   09/24/09   2,4,8,9,10,16            745,659       745,659  HCM             0           0      25,479 Bernier Carr Associates                 0      01/20/12                       06/02/14           
11-0995   Reconstruction               0-010-014  09/04/12     DONE    DONE       DONE      03/23/12   03/16/12   11/15/11   06/23/11   2,8,9,155,15,16          433,840       433,840  HCM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
12-0271   Reconstruction               0-010-015  04/03/13     DONE    DONE       DONE      10/11/12   10/02/12   08/21/12   09/24/12   8,9,155,15,16            158,000       158,000  JMB             0           0      13,588 Bernier Carr Associates                 0        /  /                           /  /             

          concession Building:
11-0996   New Construction             7-019-001  09/12/12     DONE    DONE       DONE      03/23/12   03/16/12   02/07/12   06/23/11   02 - 16                  310,230             0  HCM             0           0           0 Bernier Carr Associates                 0      09/18/13                       09/26/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHERBURNE EARLVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-20-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
09-0190   Reconstruction               0-012-010  01/15/10     DONE    DONE       DONE      09/04/09   09/02/09   11/16/07   12/18/07   2,4,7,8,9,10,155,15,  19,632,800    19,632,800  DDJ             0           0           0                                         0      01/24/14                       06/23/14           

          New Elementary School:
09-0191   Reconstruction               0-018-006  01/15/10     DONE    DONE       DONE      09/04/09   09/02/09   04/25/08   12/18/07   2,9,155,15,16            607,200             0  DDJ             0           0           0                                         0      01/24/14                       06/23/14           

          New Bus Maintenance:
09-0129   Reconstruction               5-019-004  10/16/09     DONE    DONE       DONE      08/18/09   08/17/09   07/17/09   12/18/07   4,9,10,15,16             177,936       177,936  DDJ             0           0           0                                         0      01/03/12                       07/24/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED