Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/01/16 at 07:26:40




AUSABLE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-02-01-04
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Keeseville Elementary School:
15-0732SB Reconstruction               0-003-014               DONE                           /  /       /  /     07/06/15     /  /     16                             0    11,882,562  MFS             0           0           0                                         0        /  /                           /  /             
15-1502   Reconstruction               0-003-014  05/17/16     DONE    DONE       DONE      03/29/16   02/16/16   07/06/15   01/20/16   16                       379,400       379,400  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Middle High School:
15-0733SB Reconstruction               0-011-017               DONE                           /  /       /  /     07/06/15     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             
15-1503   Reconstruction               0-011-017  05/17/16     DONE    DONE       DONE      03/29/16   02/16/16   07/06/15   01/20/16   16                       618,170       618,170  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             

          AuSable Forks Elementary School:
15-0734SB Reconstruction               0-012-010               DONE                           /  /       /  /     07/06/15     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             
15-1504   Reconstruction               0-012-010  05/17/16     DONE    DONE       DONE      03/29/16   02/16/16   07/06/15   01/20/16   16                       298,600       298,600  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Bus Garage:
11-0027   Reconstruction               5-004-007  09/01/10     DONE    DONE       DONE      07/19/11   07/15/11   02/18/11   01/18/11   2,15,16                  271,359       271,359  HCM             0           0           0 SEI Design Group                        0      02/01/13                       03/26/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BEEKMANTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-03-01-06
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
11-0344   Reconstruction               0-003-013  08/18/11     DONE    DONE       DONE      11/03/11   11/02/11   05/12/11   10/25/11   2,13,155,15,16           173,149       173,149  HCM             0           0     173,149 Tetra Tech Engineers, Archite           0      04/09/12                       07/23/12           
11-1372   Reconstruction               0-003-014  10/10/12     DONE    DONE       DONE      06/01/12   05/25/12   09/19/11   05/20/08   2,4,7,8,9,10,13,155,   1,423,827     1,423,827  HCM             0           0     286,453 Tetra Tech Engineers, Archite           0      03/10/14                       05/09/14           
15-1228   Reconstruction               0-003-015                         UNREVIEWED         02/11/16   02/08/16   01/11/16   12/08/15   2,4,8,9,10,155,15,16           0             0  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Cumberland Head Elementary:
11-1373   Reconstruction               0-004-012  10/10/12     DONE    DONE       DONE      05/31/12   05/25/12   09/19/11   05/20/08   2,4,7,8,9,10,13,155,     545,999       545,999  HCM             0           0     103,194 Tetra Tech Engineers, Archite           0      03/10/14                       05/09/14           
  -       Additions and Alterations    0-004-014                                              /  /       /  /     07/21/11     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1229   Reconstruction               0-004-015                         UNREVIEWED         02/11/16   02/08/16   01/11/16   12/08/15   2,4,8,9,10,155,15,16           0             0  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Middle School Annex:
15-1230   Reconstruction               0-009-003                         UNREVIEWED         02/11/16   02/08/16   01/11/16   12/08/15   2,4,7,8,9,10,155,15,           0             0  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Bus Garage:
15-1231   Reconstruction               5-002-005                         UNREVIEWED         02/11/16   02/08/16   01/11/16   12/08/15   2,4,8,9,10,155,15,16           0             0  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHEASTERN CLINTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-05-01-04
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Rouses Point Elem.:
11-0363   Reconstruction               0-002-009  02/17/12     DONE    DONE       DONE      11/08/11   11/08/11   05/26/11   01/23/07   7,10,16                   68,250        68,250  DDJ             0           0           0 Collins & Scoville Architects           0      09/05/12                       11/30/12           
11-0351   Reconstruction               0-002-010  11/22/11     DONE    DONE       DONE      11/07/11   11/04/11   07/07/11   06/07/11   8                        100,000       100,000  DDJ             0           0           0 Arch.&Eng. Design                       0      04/20/12                       05/07/12           
12-0212   Reconstruction               0-002-011  12/12/12     DONE    DONE       DONE      09/27/12   09/26/12   08/14/12   05/15/12   8                        100,000       100,000  DDJ             0           0           0 AES Northeast                           0      04/04/13                       07/09/13           
13-1130   Reconstruction               0-002-012  04/11/14     DONE    DONE       DONE      01/29/14   01/28/14   01/22/14   05/21/13   8                        100,000       100,000  DDJ             0           0           0 AES Northeast                           0      06/18/14                       07/28/14           

          Senior High School:
10-1018   Reconstruction               0-009-013  07/20/11     DONE    DONE       DONE      03/09/11   03/07/11   02/14/11   01/23/07   7,8,9                  1,133,000     1,133,000  DDJ             0           0           0 Collins & Scoville Architects           0      09/05/12                       06/30/15           
11-0364   Reconstruction               0-009-014  02/17/12     DONE    DONE       DONE      11/08/11   11/08/11   02/14/11   01/23/07   2,155,15,16              620,740       620,740  DDJ             0           0           0 Collins & Scoville Architects           0      09/05/12                       11/30/12           
12-1095   Reconstruction               0-009-015  04/12/13     DONE    DONE       DONE      04/12/13   04/12/13   04/04/13   03/26/13   155                       72,500        72,500  DDJ             0           0           0 WPS Consulting Engs.                    0      09/05/13                       09/12/13           
13-0390   Reconstruction               0-009-016  03/20/14     DONE    DONE       DONE      09/20/13   09/19/13   04/05/13   01/23/07   155                      106,500             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Bus Garage:
12-1262   Reconstruction               5-004-006  06/18/13     DONE    DONE       DONE      06/07/13   06/07/13   04/05/13   01/23/07   13                       192,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0850   Reconstruction               5-004-007  04/15/15     DONE    DONE       DONE      12/29/14   12/19/14   09/29/14   01/23/07   14                       274,964             0  DDJ             0           0           0 AES Northeast                           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHAZY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-06-01-02
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Chazy Rural Sch/Indust.Arts Bldg.:
11-0357   Reconstruction               0-001-014  08/16/11     DONE    DONE       DONE      11/08/11   11/07/11   08/26/11   08/16/11   2,9                       46,008        46,008  HCM             0           0           0 Bernier Carr Associates                 0      01/18/12                       06/27/12           
14-0640   Reconstruction               0-001-015  03/25/15     DONE    DONE       DONE      11/19/14   11/18/14   02/07/14   05/20/14   2,4,7,8,9,10,14,155,   1,585,000             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
14-0033   Reconstruction               0-001-016  08/01/14     DONE    DONE       DONE      07/15/14   07/15/14   06/17/14   05/20/14   15,16                    100,000       100,000  JMB             0           0           0 Bernier Carr Associates                 0      08/13/15                       10/09/15           

          Bus Storage Garage:
14-0187   Reconstruction               4-005-003  08/20/14     DONE    DONE       DONE      08/15/14   08/15/14   05/14/13   05/20/14   7                         65,000             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHERN ADIRONDACK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-09-01-04
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
15-0885   Reconstruction               0-001-013  02/25/16     DONE    DONE       DONE      12/15/15   12/14/15   02/10/15   05/19/15   7                        100,000             0  DDJ             0           0           0 AES Northeast                           0        /  /                           /  /             

          Jr/Sr High School:
12-1050   Reconstruction               0-007-011  07/14/12     DONE    DONE       DONE      04/02/13   03/26/13   11/20/12   03/22/10   2,9,13                   853,190       853,190  DDJ             0           0           0 Collins & Scoville Architects           0      12/30/12                       05/05/14           

          Bus Garage & Maint.:
10-0672   Reconstruction               5-002-007  11/21/11     DONE    DONE       DONE      12/30/10   12/23/10   04/21/10   11/21/11   155                      363,141       363,141  DDJ             0           0           0 Collins & Scoville Architects           0      02/17/14                       05/05/14           

          Solar Array:
  -       Reconstruction               7-008-001                                              /  /       /  /     11/24/15     /  /     2,13,16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PERU CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-11-01-06
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Primary School:
11-1239   Reconstruction               0-004-012  10/09/12     DONE    DONE       DONE      04/27/12   04/23/12   04/05/12   03/12/08   10                        38,700        38,700  HCM             0           0           0 Bernier Carr Associates                 0      02/25/14                       08/14/14           

          Intermediate School:
11-1240   Reconstruction               0-005-015  10/09/12     DONE    DONE       DONE      04/27/12   04/23/12   04/05/12   03/12/08   2,4,9,10,155,15,16       260,640       260,640  HCM             0           0           0 Bernier Carr Associates                 0      02/25/14                       07/14/14           
14-0650   Reconstruction               0-005-016  04/07/15     DONE    DONE       DONE      11/19/14   11/19/14   03/05/14   05/20/14   2,7,8,9,13,155,15,16   1,262,800     1,262,800  MFS             0           0           0 Bernier Carr Associates                 0      04/27/16                       06/10/16           

          Junior/Senior High School:
11-1241   Reconstruction               0-007-016  10/09/12     DONE    DONE       DONE      04/27/12   04/23/12   04/05/12   03/12/08   2,8,9,155,16             426,000       426,000  HCM             0           0           0 Bernier Carr Associates                 0      02/25/14                       07/14/14           
13-1616   Reconstruction               0-007-017  06/25/14     DONE    DONE       DONE      06/13/14   06/13/14   03/05/14   06/10/14   2,8,9,155,15,16           70,000        70,000  MFS             0           0           0 Bernier Carr Associates                 0      09/10/14                       10/06/14           
14-0651   Reconstruction               0-007-018  04/07/15     DONE    DONE       DONE      11/19/14   11/19/14   07/09/14   05/20/14   2,8,9,155,15,16          380,000       380,000  MFS             0           0           0 Bernier Carr Associates                 0      04/27/16                       06/10/16           
14-0691   Reconstruction               0-007-019  12/09/14     DONE    DONE       DONE      12/01/14   11/26/14   10/20/14   11/18/14   2,8,9                     31,500        31,500  MFS             0           0           0 Bernier Carr Associates                 0      01/13/15                       02/23/15           

          Bus Garage:
14-0652   Reconstruction               5-012-010  04/07/15     DONE    DONE       DONE      11/19/14   11/19/14   03/05/14   05/20/14   2,15,16                  102,200             0  MFS             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-002                                              /  /       /  /       /  /       /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             
15-1571SB Reconstruction               7-999-002                         UNREVIEWED         04/18/16   04/18/16   04/18/16     /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PLATTSBURGH CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-12-00-01
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bailey Avenue School:
14-0787   Reconstruction               0-001-006  03/05/15     DONE    DONE       DONE      12/18/14   12/15/14   08/28/14   08/14/14   9                        170,000       170,000  MFS             0           0           0 Bernier Carr Associates                 0      12/08/15                       02/04/16           

          Momot E.S.(formerly Monty Street):
14-0788   Reconstruction               0-004-005  03/05/15     DONE    DONE       DONE      12/18/14   12/15/14   08/28/14   08/14/14   2,7                      650,000       650,000  MFS             0           0           0 Bernier Carr Associates                 0      12/08/15                       02/04/16           
  -    PR Additions and Alterations    0-004-006                                              /  /       /  /     08/28/14     /  /     02 - 16                        0    11,047,950  MFS             0           0           0                                         0        /  /                           /  /             
15-1993   Additions and Alterations    0-004-006                         UNREVIEWED         06/28/16   06/27/16   08/28/14   08/14/14   02 - 16                        0    11,047,950  MFS             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Oak Street School:
14-0789   Reconstruction               0-005-006  09/18/15     DONE    DONE       DONE      12/18/14   12/15/14   08/28/14   08/14/14   155,16                   300,000             0  MFS             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Senior High School:
14-0198   Reconstruction               0-007-009  08/22/14     DONE    DONE       DONE      08/20/14   08/18/14   07/22/14   08/14/14   2,7                    3,700,000     3,700,000  MFS             0           0     367,347 Bernier Carr Associates                 0      10/08/15                       10/28/15           
  -    PR Additions and Alterations    0-007-010                                              /  /       /  /     08/28/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             
15-1994   Additions and Alterations    0-007-010                         UNREVIEWED         06/28/16   06/27/16   08/28/14   08/14/14   02 - 16                        0    18,144,654  MFS             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
15-1446   Reconstruction               0-007-011  04/08/16     DONE    DONE       DONE      03/17/16   03/16/16   02/10/16   08/14/14   155                      100,000             0  MFS             0           0           0                                         0        /  /                           /  /             

          Stafford Middle School:
14-0790   Reconstruction               0-013-008  03/05/15     DONE    DONE       DONE      12/18/14   12/15/14   08/28/14   08/14/14   2,4,7,8,9,10,15,16     2,420,000     2,420,000  MFS             0           0           0 Bernier Carr Associates                 0      12/08/15                       02/04/16           
15-1432   Reconstruction               0-013-009  03/28/16     DONE    DONE       DONE      03/15/16   03/15/16   02/10/16   08/14/14   15                       459,000             0  MFS             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Broad St. Admin. Bldg.(fmly 002):
  -       Reconstruction               1-002-004                                              /  /       /  /     02/10/16     /  /     155                            0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SARANAC CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-14-02-06
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Saranac Elem School K-6:
11-1018   Alterations                  0-001-007  08/03/12     DONE    DONE       DONE      03/27/12   03/26/12   09/30/09   12/13/11   02 - 16                  339,000       339,000  HCM             0           0     100,000 SEI Design Group                        0      10/09/14                       12/05/14           
12-0173   Reconstruction               0-001-009  03/19/13     DONE    DONE       DONE      09/18/12   09/17/12   04/24/12   12/13/11   2,4,7,8,10,15,16       2,834,800     2,834,800  HCM             0           0           0 SEI Design Group                        0      10/29/14                       12/05/14           
12-0182   Reconstruction               0-001-010  02/18/13     DONE    DONE       DONE      09/18/12   09/17/12   05/16/12   04/26/12   2,8,155,15,16            289,601       289,601  HCM             0           0      63,000 SEI Design Group                  219,913      06/02/15                       12/09/15           

          Saranac Jr/Sr HS 7-12:
11-1019   Alterations                  0-002-011  08/03/12     DONE    DONE       DONE      03/27/12   03/26/12   09/30/09   12/13/11   02 - 16                  549,000       549,000  HCM             0           0     357,245 SEI Design Group                        0      01/09/14                       02/28/14           
11-0709   Reconstruction               0-002-012  01/03/12     DONE    DONE       DONE      01/25/12   01/24/12   12/14/11   12/13/11   2,155,15,16              198,000       198,000  HCM             0           0           0 SEI Design Group                        0      05/31/12                       06/29/12           
12-0174   Reconstruction               0-002-013  03/19/13     DONE    DONE       DONE      09/18/12   09/17/12   04/24/12   12/13/11   2,4,8,9,155,15,16        532,100       532,100  HCM             0           0           0 SEI Design Group                        0      09/30/14                       01/06/16           
12-0183   Reconstruction               0-002-014  02/18/13     DONE    DONE       DONE      09/18/12   09/17/12   05/16/12   04/26/12   2,8,155,15,16          1,372,126     1,372,126  HCM             0           0     290,000 SEI Design Group                1,059,929      06/02/15                       12/09/15           
14-1318   Reconstruction               0-002-015  08/24/15     DONE    DONE       DONE      03/25/15   03/24/15   02/06/15   10/18/11   9,155,15,16              599,330             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Morrisonville Elementary:
11-1020   Alterations                  0-004-009  08/03/12     DONE    DONE       DONE      03/27/12   03/26/12   09/30/09   12/13/11   02 - 16                   87,000        87,000  HCM             0           0           0 SEI Design Group                        0      01/09/14                       02/28/14           
12-0175   Reconstruction               0-004-010  03/19/13     DONE    DONE       DONE      09/18/12   09/17/12   04/24/12   12/13/11   2,4,8,10,155,15,16       868,000       868,000  HCM             0           0           0 SEI Design Group                        0      09/30/14                       01/29/15           
12-0184   Reconstruction               0-004-011  02/18/13     DONE    DONE       DONE      09/18/12   09/17/12   05/16/12   04/26/12   2,8,155,15,16            501,514       501,514  HCM             0           0     104,245 SEI Design Group                  388,512      06/01/15                       12/10/15           

          Administrative Office:
11-1021   Reconstruction               1-016-003  08/03/12     DONE    DONE       DONE      03/27/12   03/26/12   09/30/09   12/13/11   2,155,15,16               46,500             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             
12-0185   Reconstruction               1-016-004  02/18/13     DONE    DONE       DONE      09/18/12   09/17/12   07/30/12   04/26/12   2,8,16                    10,204             0  JMB             0           0           0 SEI Design Group                   10,204      06/01/15                       12/09/15           

          Football Storage @ HS:
  -    DB Discovered Building          2-021-001                                              /  /       /  /     07/01/15     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Sports Shed @ Bus Garage:
  -    DB Discovered Building          2-022-001                                              /  /       /  /     07/01/15     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Saranac Maintenance Building:
11-1022   Reconstruction               4-013-005  08/03/12     DONE    DONE       DONE      03/27/12   03/26/12   09/30/09   12/13/11   7,155,15,16               46,500        46,500  HCM             0           0           0 SEI Design Group                        0      01/09/14                       02/28/14           
12-0176   Reconstruction               4-013-006  03/19/13     DONE    DONE       DONE      09/18/12   09/17/12   04/24/12   12/13/11   2,8,9,16                  18,500        18,500  HCM             0           0           0 SEI Design Group                        0      09/30/14                       01/29/15           
12-0186   Reconstruction               4-013-007  02/18/13     DONE    DONE       DONE      09/18/12   09/17/12   05/16/12   04/26/12   155,15,16                 36,132        36,132  HCM             0           0           0 SEI Design Group                   35,404      06/01/15                       12/10/15           

          Bus Garage:
11-1023   Reconstruction               5-012-005  08/03/12     DONE    DONE       DONE      03/27/12   03/26/12   09/30/09   12/13/11   2,8,155,15,16             53,500        53,500  HCM             0           0           0 SEI Design Group                        0      01/09/14                       02/28/14           
12-0177   Reconstruction               5-012-006  03/19/13     DONE    DONE       DONE      09/18/12   09/17/12   04/24/12   12/13/11   2,9,16                    25,100        25,100  HCM             0           0           0 SEI Design Group                        0      09/30/14                       01/06/16           
12-0187   Reconstruction               5-012-007  02/18/13     DONE    DONE       DONE      09/18/12   09/17/12   05/16/12   04/26/12   155,15,16                 33,121        33,121  HCM             0           0           0 SEI Design Group                   27,241      06/01/15                       12/10/15           
12-0246   Reconstruction               5-012-008  06/27/12     DONE    DONE       DONE      10/03/12   09/24/12   05/31/12   06/05/12   2                         68,000        68,000  HCM             0           0           0 SEI Design Group                        0      09/06/12                       01/02/13           
  -       Reconstruction               5-012-009                                              /  /       /  /     06/06/12     /  /     2                              0             0  HCM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1852SB Reconstruction               7-999-001               DONE                           /  /       /  /     06/02/16     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES CLINTON-ESSEX-WARR-WASH STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-90-00-00
last updated on 07/01/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Yandon Dillon Education Ctr.:
12-0914   Reconstruction               0-001-007  04/16/13     DONE    DONE       DONE      02/27/13   02/26/13   08/14/12   10/10/12   7                      1,010,800       399,200  MFS             0           0           0 McKenna Associates                      0        /  /                           /  /             
15-1177   Reconstruction               0-001-008  04/08/16     DONE    DONE       DONE      02/03/16   02/02/16   01/27/16     /  /     2,4,8,155,15,16          550,000             0  MFS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                           /  /             

          "Pressure House" Lab Facility:
13-1494   New Construction             7-031-001  04/30/14     DONE    DONE       DONE      11/04/13   11/04/13   02/10/11     /  /     02 - 16                        0             0  JOD             0           0           0 Earth Science Engineering               0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED