Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/25/24 at 06:56:33




AUSABLE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-02-01-04
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Keeseville Elementary School:
  -       Reconstruction               0-003-015                                              /  /       /  /     04/05/24     /  /     2,4,7,8,9,155,15,16            0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-016                                              /  /       /  /     04/19/24     /  /     2,4,7,8,9,10,155,15,           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Middle High School:
  -       Reconstruction               0-011-018                                              /  /       /  /     04/05/24     /  /     2,7,8,9,10,155,15,16           0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-011-019                                              /  /       /  /     04/19/24     /  /     2,4,7,8,9,10,14,155,           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          AuSable Forks Elementary School:
  -       Reconstruction               0-012-011                                              /  /       /  /     04/05/24     /  /     2,7,8,9,10,155,15,16           0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-012-012                                              /  /       /  /     04/19/24     /  /     2,8,9,155,16                   0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Keeseville Bus Garage:
  -       Reconstruction               5-004-008                                              /  /       /  /     04/05/24     /  /     16                             0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               5-004-009                                              /  /       /  /     04/19/24     /  /     2,4,7,8,9,15,16                0             0  MSK             0           0           0                                         0        /  /                           /  /             

          AuSable Forks Bus Garage:
  -       Reconstruction               5-019-003                                              /  /       /  /     04/05/24     /  /     16                             0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               5-019-004                                              /  /       /  /     04/19/24     /  /     2,8                            0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Biomass Boiler Bldg. @ High School:
  -       Reconstruction               7-024-002                                              /  /       /  /     04/05/24     /  /     16                             0             0  MSK             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BEEKMANTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-03-01-06
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
20-0759   Reconstruction               0-003-017  02/10/21     DONE    DONE       DONE      10/30/20   10/23/20   06/04/20   06/09/20   4,8,9,10,16              100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      06/25/21                       10/23/20           
21-0364   Reconstruction               0-003-018  11/15/21     DONE    DONE       DONE      09/15/21   09/14/21   08/02/21   05/18/21   8,9                      100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      06/17/22                       09/14/21           
21-2017   Reconstruction               0-003-019  09/06/22     DONE    DONE       DONE      06/22/22   06/21/22   04/04/22   05/17/22   2,8,15,16                100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      05/18/23                       06/21/22           
  -    PR Additions and Alterations    0-003-020                                              /  /       /  /     11/15/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
23-0294   Reconstruction               0-003-021  11/28/23     DONE    DONE       DONE      08/21/23   08/21/23   04/20/23   05/16/23   8,9                      100,000       100,000  JJH             0           0           0 Bernier Carr Associates                 0        /  /                         08/21/23           

          Cumberland Head Elementary:
18-1667   Reconstruction               0-004-018  04/26/19     DONE    DONE       DONE      03/15/19   03/12/19   02/11/19   05/15/18   8                        100,000       100,000  JLB             0           0           0 Tetra Tech Engineers, Archite           0      06/18/20                       03/12/19           
  -    XX Reconstruction               0-004-019                         CANCELLED            /  /       /  /     06/04/19     /  /     8                              0    14,992,350  JLB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-020                                              /  /       /  /     02/10/23     /  /     9,155,16                       0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Storage Bldg 1:
  -    PR New Construction             2-012-001                                              /  /       /  /     11/15/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Storage Bldg 2:
  -    DB Discovered Building          2-013-001                                              /  /       /  /     11/15/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Office Bldg:
  -    DB Discovered Building          7-014-001                                              /  /       /  /       /  /       /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          District-Wide:
22-2206FC Reconstruction               7-999-002  06/13/23     DONE    DONE       DONE      05/15/23   03/01/23   02/16/23   05/16/23                          1,024,500     1,024,500  JJH             0           0           0 Bernier Carr Associates                 0        /  /                         03/01/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHEASTERN CLINTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-05-01-04
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle High School:
20-1163   Reconstruction               0-001-011  06/16/21     DONE    DONE       DONE      01/19/21   01/14/21   05/08/20   12/17/19   2,4,8,9,10,13,155,15   3,910,000     3,910,000  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         01/14/21           
21-0304   Reconstruction               0-001-012  12/13/21     DONE    DONE       DONE      09/08/21   08/25/21   05/08/20   12/17/19   2,4,8,9,10,13,155,15   6,665,200     6,665,200  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         08/25/21           
22-0646   Reconstruction               0-001-013  05/31/23     DONE    DONE       DONE      10/05/22   10/05/22   06/22/22   01/13/22   8,9,155,16             1,813,018     1,813,018  JJH             0           0           0 Burton Behrendt Smith           1,813,018        /  /                         10/05/22           
22-1050   Reconstruction               0-001-014  05/08/23     DONE    DONE       DONE      11/18/22   11/18/22   06/22/22   12/17/19   2,155,15,16            5,960,000     5,960,000  JJH             0           0           0 Burton Behrendt Smith                   0        /  /                         11/18/22           

          Rouses Point Elem.:
22-1051   Reconstruction               0-002-013  05/08/23     DONE    DONE       DONE      11/18/22   11/18/22   05/08/20   12/17/19   2,4,7,8,9,10,13,155,   1,020,755     1,020,755  JJH             0           0           0 Burton Behrendt Smith                   0        /  /                         11/18/22           
21-2042   Reconstruction               0-002-014  05/01/23     DONE    DONE       DONE      06/27/22   06/23/22   03/02/22   05/17/22   2,9                      100,000       100,000  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         06/23/22           
22-0647   Reconstruction               0-002-015  05/31/23     DONE    DONE       DONE      10/05/22   10/05/22   06/22/22   01/13/22   8,9,155,16                45,627        45,627  JJH             0           0           0 Burton Behrendt Smith              45,627        /  /                         10/05/22           
  -       Reconstruction               0-002-016                                              /  /       /  /     05/31/23     /  /     9                              0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Mooers Elementary School:
18-1778   Reconstruction               0-005-019  05/31/19     DONE    DONE       DONE      04/02/19   03/11/19   12/05/18   05/21/19   2,9                      100,000       100,000  BMJ             0           0           0 Collins & Scoville Architects           0      08/29/19                       03/11/19           
22-1052   Reconstruction               0-005-020  05/08/23     DONE    DONE       DONE      11/18/22   11/18/22   05/08/20   12/17/19   2,4,7,8,9,10,13,155,   1,020,755     1,020,755  JJH             0           0           0 Burton Behrendt Smith                   0        /  /                         11/18/22           
  -       Reconstruction               0-005-021                                              /  /       /  /     05/08/20     /  /     2,9                            0             0  JSS             0           0           0                                         0        /  /                           /  /             
21-0314   Reconstruction               0-005-022  12/01/21     DONE    DONE       DONE      09/09/21   08/25/21   01/27/21   05/18/21   2,15                     100,000       100,000  JLB             0           0           0 Burton Behrendt Smith                   0      05/15/22                       08/25/21           
22-0648   Reconstruction               0-005-023  05/31/23     DONE    DONE       DONE      10/05/22   10/05/22   06/22/22   01/13/22   8,9,155,16               239,238       239,238  JJH             0           0           0 Burton Behrendt Smith             239,238        /  /                         10/05/22           

          Senior High School:
  -       Reconstruction               0-009-017                                              /  /       /  /     05/08/20     /  /     2,4,7,8,9,10,13,155,           0             0  JSS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-009-018                                              /  /       /  /     05/08/20     /  /     2,4,8,9,10,13,155,15           0             0  JSS             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-009-019                                              /  /       /  /     05/08/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             
20-1164   Additions and Alterations    0-009-019  06/16/21     DONE    DONE       DONE      01/19/21   01/14/21   05/08/20   12/17/19   02 - 16               12,036,800    10,277,172  JLB             0           0           0 Burton Behrendt Smith                   0      10/08/21                       01/14/21           

          Athletic Storage Building:
  -    DB Discovered Building          2-025-001                                              /  /       /  /     05/19/21     /  /                                    0             0  JSS             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
20-1165   Additions and Alterations    5-004-008  06/16/21     DONE    DONE       DONE      01/19/21   01/14/21   06/02/20   12/17/19   02 - 16                1,020,000     1,020,000  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         01/14/21           
21-0305   Reconstruction               5-004-009  12/13/21     DONE    DONE       DONE      09/08/21   08/25/21   06/02/20   12/17/19   2,15,16                  582,000       582,000  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         08/25/21           
22-0649   Reconstruction               5-004-010  05/31/23     DONE    DONE       DONE      10/05/22   10/05/22   08/02/22   01/13/22   7,8,155,16                17,579        17,579  JJH             0           0           0 Burton Behrendt Smith                   0        /  /                         10/05/22           

          Concession Building:
  -    PR New Construction             7-016-001                                              /  /       /  /     05/19/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             
20-1166   New Construction             7-016-001  06/16/21     DONE    DONE       DONE      01/19/21   01/14/21   05/19/20   12/17/19   02 - 16                  600,000             0  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         01/14/21           

          Press Box:
20-1167   New Construction             7-024-001  06/16/21     DONE    DONE       DONE      01/19/21   01/14/21   10/23/20   12/17/19   02 - 16                   50,000             0  JLB             0           0           0 Burton Behrendt Smith                   0        /  /                         01/14/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHAZY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-06-01-02
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Chazy Rural Sch/Indust.Arts Bldg.:
18-1648   Reconstruction               0-001-017  06/14/19     DONE    DONE       DONE      03/14/19   03/08/19   07/07/17   05/15/18   2                         15,000             0  MTM             0           0           0 Beardsley Design Associates             0        /  /                         03/08/19           
20-0152   Reconstruction               0-001-018  08/25/20     DONE    DONE       DONE      08/04/20   07/30/20   02/28/20   06/09/20   2,4,7,8,9,155,15,16      100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      06/01/21                       07/30/20           
20-1899   Reconstruction               0-001-019  07/07/21     DONE    DONE       DONE      06/18/21   06/15/21   04/27/21   05/18/21   9,15,16                  100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      01/12/22                       06/15/21           
21-1807   Reconstruction               0-001-020  08/03/22     DONE    DONE       DONE      05/11/22   05/10/22   02/14/22   05/17/22   4,7,8,9,155,15,16        100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      05/18/23                       05/10/22           
  -       Reconstruction               0-001-021                                              /  /       /  /     10/28/22     /  /     2,4,7,8,9,155,15,16            0             0  JLB             0           0           0                                         0        /  /                           /  /             
23-0963   Reconstruction               0-001-022                         UNREVIEWED         11/10/23   11/09/23   10/28/22   02/07/23   2,4,7,8,9,10,155,15,           0             0  JJH             0           0           0 Bernier Carr Associates                 0        /  /                         11/09/23           
22-1964   Reconstruction               0-001-023  05/24/23     DONE    DONE       DONE      03/29/23   03/28/23   03/02/23   05/16/23   4,8,9,10,155,15,16       100,000       100,000  JJH             0           0           0 Bernier Carr Associates                 0      09/06/23                       03/28/23           
  -       Reconstruction               0-001-024                                              /  /       /  /     12/01/23     /  /     155                            0             0  JJH             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-025                                              /  /       /  /     03/22/24     /  /     2,4,7,8,9,10,155,15,           0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
23-1397   Reconstruction               5-004-003                         UNREVIEWED         01/22/24   01/19/24   10/28/22   05/16/23   2,4,7,8,9,155,15,16            0             0  JJH             0           0           0 Bernier Carr Associates                 0        /  /                         01/19/24           
  -       Reconstruction               5-004-004                                              /  /       /  /     10/28/22     /  /     2,4,7,8,9,10,155,15,           0             0  JLB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHERN ADIRONDACK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-09-01-04
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
22-1802   Reconstruction               0-001-014  04/28/23     DONE    DONE       DONE      03/08/23   03/07/23   01/18/23   05/17/22   2,8                      100,000       100,000  JLB             0           0           0 AES Northeast                           0        /  /                         03/07/23           

          Jr/Sr High School:
18-1824   Reconstruction               0-007-013  06/12/19     DONE    DONE       DONE      04/09/19   04/05/19   08/03/18   11/04/14   16                        10,000             0  SLC             0           0           0 AES Northeast                           0        /  /                         04/05/19           
  -       Reconstruction               0-007-014                                              /  /       /  /     01/18/23     /  /     2,8,16                         0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Bus Garage & Maint.:
21-0213   Reconstruction               5-002-008  02/08/22     DONE    DONE       DONE      08/25/21   08/23/21   04/28/21   05/18/21   2,7                      100,000       100,000  SLC             0           0           0 AES Northeast                           0      05/03/22                       08/23/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PERU CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-11-01-06
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Peru Elementary School:
19-1044   Reconstruction               0-004-016  02/20/20     DONE    DONE       DONE      12/26/19   12/06/19   09/04/19   05/15/18   16                       203,000       203,000  SLC             0           0           0 Bernier Carr Associates                 0      11/24/21                       12/06/19           
20-1037   Reconstruction               0-004-017  02/11/21     DONE    DONE       DONE      12/23/20   12/11/20   10/15/20   05/15/18   2,4,7,8,9,10,155,15,   3,279,065     3,279,065  SLC             0           0           0 Bernier Carr Associates                 0      02/14/22                       12/11/20           
  -    PR Reconstruction               0-004-018                                              /  /       /  /     10/20/20     /  /     2,4,7,8,9,10,155,15,           0    24,167,393  SLC             0           0           0                                         0        /  /                           /  /             
23-0755   Reconstruction               0-004-019  01/30/24     DONE    DONE       DONE      10/20/23   10/13/23   10/05/23   05/16/23   2,8,9,155,15,16          100,000       100,000  WLC             0           0           0 Bernier Carr & Associates               0        /  /                         10/13/23           
23-1420   Reconstruction               0-004-020                         UNREVIEWED         01/25/24   01/23/24   01/09/24   01/09/24   7,155,16                       0             0  WLC             0           0           0 Bernier Carr & Associates Arc           0        /  /                         01/23/24           

          XXIntermediate Sch-MergerW0-004:
19-0294   Reconstruction               0-005-020  08/30/19     DONE    DONE       DONE      08/26/19   08/26/19   06/28/19   08/13/18   155,15,16                300,000       300,000  SLC             0           0           0 Bernier Carr Associates                 0      01/15/20                       08/26/19           
19-1045   Reconstruction               0-005-021  02/20/20     DONE    DONE       DONE      12/26/19   12/06/19   09/04/19   05/15/18   16                       203,000       203,000  SLC             0           0           0 Bernier Carr Associates                 0      11/24/21                       12/06/19           

          Junior/Senior High School:
19-0134   Reconstruction               0-007-023  09/12/19     DONE    DONE       DONE      07/23/19   07/17/19   04/17/19   05/21/19   9,10,16                  100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0      03/01/20                       07/17/19           
19-1046   Reconstruction               0-007-024  02/20/20     DONE    DONE       DONE      12/26/19   12/06/19   05/06/19   05/15/18   2,8,9,10,14,155,15,1   6,259,642     6,259,642  SLC             0           0           0 Bernier Carr Associates                 0      11/24/21                       12/06/19           
21-0449   Reconstruction               0-007-025  01/28/22     DONE    DONE       DONE      09/30/21   09/28/21   09/02/21   05/18/21   2,9                      100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0      05/02/22                       09/28/21           
22-0510   Reconstruction               0-007-026  12/02/22     DONE    DONE       DONE      09/16/22   09/16/22   08/18/22   05/17/22   9                        100,000       100,000  WLC             0           0           0 Bernier Carr & Associates               0      06/09/23                       09/16/22           

          Bus Garage:
19-1410   Reconstruction               5-012-015  02/13/20     DONE    DONE       DONE      02/13/20   02/13/20   02/13/20   05/15/18   2,16                      96,000        96,000  SLC             0           0           0 Bernier Carr Associates                 0      03/10/20                       02/13/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PLATTSBURGH CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-12-00-01
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bailey Avenue School:
19-1108   Reconstruction               0-001-007  06/05/20     DONE    DONE       DONE      01/02/20   12/18/19   10/10/19   05/21/19   2,8,15,16              1,164,000     1,164,000  JSS             0           0           0 Bernier Carr Associates                 0      08/22/22                       12/18/19           

          Momot Elementary:
19-1109   Reconstruction               0-004-008  06/05/20     DONE    DONE       DONE      01/02/20   12/18/19   10/10/19   05/21/19   2,8,16                   954,000       954,000  JSS             0           0           0 Bernier Carr Associates                 0      08/22/22                       12/18/19           

          Oak Street School:
19-0369   Reconstruction               0-005-007  12/05/19     DONE    DONE       DONE      09/04/19   08/27/19   08/13/19   05/21/19   7                        460,000       460,000  JSS             0           0           0 Bernier Carr Associates                 0      08/18/20                       08/27/19           
19-1110   Reconstruction               0-005-008  06/05/20     DONE    DONE       DONE      01/02/20   12/18/19   10/10/19   05/21/19   2,155,16               1,069,000     1,069,000  JSS             0           0           0 Bernier Carr Associates                 0      08/22/22                       12/18/19           
22-1734   Reconstruction               0-005-009  05/23/23     DONE    DONE       DONE      02/22/23   02/21/23   12/20/21   05/16/23   7,15                     100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0        /  /                         02/21/23           

          Senior High School:
18-1986   Reconstruction               0-007-014  06/14/19     DONE    DONE       DONE      05/20/19   05/14/19   09/19/18   10/11/18   2,8                      456,721       456,721  SLC             0           0           0 Bernier Carr Associates                 0      06/05/20                       05/14/19           
19-0630   Reconstruction               0-007-015  12/13/19     DONE    DONE       DONE      10/29/19   10/15/19   09/23/19   05/21/19   2,9                      100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0      05/29/20                       10/15/19           
19-1111   Reconstruction               0-007-016  06/05/20     DONE    DONE       DONE      01/02/20   12/18/19   10/10/19   05/21/19   2,8,155,16             4,369,000     4,369,000  JSS             0           0           0 Bernier Carr Associates                 0      08/22/22                       12/18/19           
20-1472   Reconstruction               0-007-017  04/01/21     DONE    DONE       DONE      03/24/21   03/19/21   02/08/21   06/09/20   9                         84,379        84,379  JSS             0           0           0 Bernier Carr Associates                 0      06/17/21                       03/19/21           
21-0014   Reconstruction               0-007-018  07/12/21     DONE    DONE       DONE      07/08/21   07/02/21   06/30/21   05/21/19   16                       213,000       213,000  SLC             0           0           0 Bernier Carr Associates                 0      12/20/22                       07/02/21           
21-1654   Reconstruction               0-007-019  05/13/22     DONE    DONE       DONE      04/13/22   04/11/22   04/11/22   05/18/21   2                        100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0      05/18/23                       04/11/22           

          Stafford Middle School:
19-1112   Reconstruction               0-013-010  06/05/20     DONE    DONE       DONE      01/02/20   12/18/19   10/10/19   05/21/19   2,155,15,16            1,129,000     1,129,000  JSS             0           0           0 Bernier Carr Associates                 0      08/22/22                       12/18/19           
21-1494   Reconstruction               0-013-011  06/22/22     DONE    DONE       DONE      03/11/22   03/10/22   12/23/21   02/10/22   16                       400,000             0  SLC             0           0           0 Bernier Carr Associates                 0      12/15/23                       03/10/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SARANAC CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-14-02-06
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Saranac Elem School K-6:
19-0723   Reconstruction               0-001-012  02/18/20     DONE    DONE       DONE      11/06/19   10/18/19   04/04/19   01/29/19   2,4,7,8,9,10,155,15,   4,222,484     4,222,484  BMJ             0           0           0 Tetra Tech Engineers, Archite           0      06/22/22                       10/18/19           
21-1341   Reconstruction               0-001-013  08/08/22     DONE    DONE       DONE      02/22/22   02/17/22   07/23/21   01/29/19   2,4,8,9,155,15,16      1,363,800     1,363,800  SLC             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/17/22           
  -       Reconstruction               0-001-014                                              /  /       /  /     01/25/24     /  /     155,15,16                      0             0  MSK             0           0           0                                         0        /  /                           /  /             
23-1880   Reconstruction               0-001-015                         UNREVIEWED         04/22/24   04/22/24   03/01/24   02/12/24   4,9,155                        0             0  MSK             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         04/22/24           

          Saranac Jr/Sr HS 7-12:
19-0724   Reconstruction               0-002-017  02/18/20     DONE    DONE       DONE      11/06/19   11/05/19   04/04/19   01/29/19   2,7,8,9,10,155,15,16   5,461,956     5,461,956  BMJ             0           0           0 Tetra Tech Engineers, Archite           0      06/22/22                       11/05/19           
  -    XX Reconstruction               0-002-018                         CANCELLED            /  /       /  /     07/07/20     /  /     15,16                          0    16,733,304  JSS             0           0           0                                         0        /  /                           /  /             
21-1342   Reconstruction               0-002-019  08/08/22     DONE    DONE       DONE      02/22/22   02/17/22   07/23/21   01/29/19   2,4,8,9,10,155,15,16   1,861,400     1,861,400  SLC             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/17/22           
21-0450   Reconstruction               0-002-020  12/29/21     DONE    DONE       DONE      09/30/21   09/29/21   07/23/21   05/18/21   16                       100,000       100,000  SLC             0           0           0 Tetra Tech Architects and Eng           0      06/21/23                       09/29/21           
22-1265   Reconstruction               0-002-021  05/05/22     DONE    DONE       DONE      12/15/22   12/15/22   06/23/22   02/17/22   8,14,16                  168,167       168,167  SLC             0           0           0 Tetra Tech Architects and Eng           0      04/13/23                       12/15/22           
23-0662   Reconstruction               0-002-022  11/15/23     DONE    DONE       DONE      10/10/23   10/06/23   04/19/23   05/16/23   9,155                    100,000       100,000  MSK             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/06/23           

          Morrisonville Elementary:
19-0725   Reconstruction               0-004-013  02/18/20     DONE    DONE       DONE      11/06/19   10/18/19   04/04/19   01/29/19   2,8,9,10,155,15,16     3,293,165     3,142,184  BMJ             0           0           0 Tetra Tech Engineers, Archite           0      06/22/22                       10/18/19           
21-1343   Reconstruction               0-004-014  08/08/22     DONE    DONE       DONE      02/22/22   02/17/22   07/23/21   01/29/19   2,4,8,9,14,155,15,16     524,800       524,800  SLC             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/17/22           

          Football Storage @ HS:
23-0879DB Discovered Building          2-021-001                         UNREVIEWED         11/06/23   11/01/23   07/01/15     /  /                                    0             0  MSK             0           0           0                                         0        /  /                         11/01/23           

          Sports Shed @ Bus Garage:
23-0880DB Discovered Building          2-022-001                         UNREVIEWED         11/06/23   11/01/23   07/01/15     /  /                                    0             0  MSK             0           0           0                                         0        /  /                         11/01/23           

          Varsity Soccer Storage Shed:
23-0881DB Discovered Building          2-023-001                         UNREVIEWED         11/06/23   11/01/23   04/28/23     /  /     02 - 16                        0             0  MSK             0           0           0                                         0        /  /                         11/01/23           

          Middle School Gym Storage:
  -    DB Discovered Building          2-024-001                                              /  /       /  /       /  /       /  /                                    0             0  MSK             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES CLINTON-ESSEX-WARR-WASH STATUS REPORT ON CAPITAL PROJECTS
District No.: 09-90-00-00
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Yandon Dillon Education Ctr.:
17-1841   Reconstruction               0-001-009  04/30/19     DONE    DONE       DONE      05/09/18   05/08/18   02/12/18   01/25/18   16                       128,060       128,060  JLB             0           0           0 Tetra Tech Architects and Eng           0      09/29/22                       05/08/18           
19-0416   Reconstruction               0-001-010  02/13/20     DONE    DONE       DONE      09/18/19   09/06/19   07/19/19   12/11/18   2,4,8,9,155,15,16      2,437,289     2,437,289  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/01/21                       09/06/19           
22-1617   Reconstruction               0-001-011  09/19/23     DONE    DONE       DONE      02/03/23   02/02/23   09/01/22   12/11/18   2,4,7,9,10,155,15,16   2,474,343     2,474,343  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/02/23           

          Harrold Education Center:
17-1842   Reconstruction               0-007-007  04/30/19     DONE    DONE       DONE      05/09/18   05/08/18   02/12/18   01/25/18   16                       271,940       271,940  JLB             0           0           0 Tetra Tech Architects and Eng           0      09/29/22                       05/08/18           
19-0417   Reconstruction               0-007-008  02/13/20     DONE    DONE       DONE      09/18/19   09/06/19   07/19/19   12/11/18   2,4,7,8,9,10,155,15,  15,329,519    14,882,054  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/01/21                       09/06/19           
19-1266   Reconstruction               0-007-009  03/20/20     DONE    DONE       DONE      01/27/20   12/26/19   12/13/19   11/13/19   2,8,9                    669,000       669,000  JSS             0           0           0 Tetra Tech Architects and Eng           0      05/26/22                       12/26/19           
22-1618   Reconstruction               0-007-010  09/19/23     DONE    DONE       DONE      02/03/23   02/02/23   09/01/22   12/11/18   2,4,7,8,9,10,155,15,   5,152,528     5,152,528  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/02/23           

          CVES Satellite Campus-South Building:
  -    PR Additions and Alterations    0-024-001                                              /  /       /  /     07/19/19     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
19-0418   Additions and Alterations    0-024-001  02/13/20     DONE    DONE       DONE      09/18/19   09/06/19   07/19/19   12/11/18   02 - 16               10,696,089     2,393,388  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/01/21                       09/06/19           
22-1619   Reconstruction               0-024-002  09/19/23     DONE    DONE       DONE      02/03/23   02/02/23   09/01/22   12/11/18   2,4,7,8,9,10,155,15,     904,283       904,283  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/02/23           

          CVES Satellite Campus-North Building:
  -    PR Alterations                  0-025-001                                              /  /       /  /     07/19/19     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             
19-0419   Alterations                  0-025-001  02/13/20     DONE    DONE       DONE      09/18/19   09/06/19   07/19/19   12/11/18   02 - 16                1,387,104       757,936  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/01/21                       09/06/19           

          Sibley Hall (SUNY Plattsbugh):
  -    TQ Temporary Quarters           8-032-001                                              /  /       /  /     08/10/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          XXDuken Bldg (Plattsburgh CSD 1-002):
  -    TQ Temporary Quarters           8-033-001                                              /  /       /  /       /  /       /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Mt View Campus-Boquet Valley CSD:
  -    TQ Temporary Quarters           8-034-001                                              /  /       /  /     09/14/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Plattsburgh Air Force Base #104:
  -    TQ Temporary Quarters           8-035-001                                              /  /       /  /     05/09/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Classrooms @ Plattsburgh High School:
  -    TQ Temporary Quarters           8-036-001                                              /  /       /  /     05/23/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          WIOA Title 1:
  -    TQ Temporary Quarters           8-037-001                                              /  /       /  /     10/05/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          OWS PIT:
  -    TQ Temporary Quarters           8-038-001                                              /  /       /  /     10/05/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Essex County Literacy Zone - ACAP:
  -    TQ Temporary Quarters           8-039-001                                              /  /       /  /     10/24/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          CVES CTE Facility:
  -    TQ Temporary Quarters           8-040-001                                              /  /       /  /     03/26/24     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED