Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 12/17/14 at 12:21:19




CINCINNATUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 11-01-01-04
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
12-0301   Reconstruction               0-001-013  04/26/13     DONE    DONE       DONE      10/23/12   10/23/12   07/20/12   04/26/12   10,155,16                100,000       100,000  DDJ             0           0           0 C&S Companies                           0      06/28/13                       07/13/13           
13-0388   Reconstruction               0-001-014  03/20/14     DONE    DONE       DONE      09/19/13   09/18/13   06/05/13   08/08/13   16                       100,000       100,000  DDJ             0           0           0 C&S Companies                           0      06/27/14                       06/30/14           
14-0402   Reconstruction               0-001-015               DONE    STARTED    UNREVIEWED10/06/14   10/03/14   02/19/14   02/11/14   2,4,7,8,9,10,13,155,           0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0464   Reconstruction               0-001-016                         UNREVIEWED         10/15/14   10/14/14   09/17/14   09/11/14   16                             0             0  DDJ             0           0           0 INTELLIGENT CONVERTED ENERGY,           0        /  /                           /  /             

          New Bus Garage:
14-0403   Reconstruction               5-010-002               DONE    STARTED    UNREVIEWED10/06/14   10/03/14   02/19/14   02/11/14   2,4,9,13,15,16                 0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CORTLAND CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 11-02-00-01
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          F.E. Smith Elementary School:
09-0726   Reconstruction               0-001-004  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,8,9,155,15,16    2,674,770     2,674,770  HCM             0           0     125,000 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0662   Reconstruction               0-001-005  02/27/13     DONE    DONE       DONE      01/11/13   01/11/13   12/21/12   02/12/08   2,7                    1,714,164             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0135   Reconstruction               0-001-006               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   2,10,16                        0     7,635,093  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Randall Elementary School:
09-0727   Reconstruction               0-002-005  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,8,9,14,155,15,   5,016,359     4,966,830  HCM             0           0     150,000 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0663   Reconstruction               0-002-006  02/27/13     DONE    DONE       DONE      01/11/13   01/11/13   12/21/12   02/12/08   2,7                    1,115,970             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0136   Reconstruction               0-002-007               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   2,9,155,15,16                  0             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          F.S. Barry Elementary School:
09-0728   Reconstruction               0-004-005  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,8,9,14,155,15,   2,454,300     2,576,873  HCM             0           0      75,000 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0664   Reconstruction               0-004-006  02/27/13     DONE    DONE       DONE      01/11/13   01/11/13   12/21/12   02/12/08   2,7                    1,822,562             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0137   Reconstruction               0-004-007               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   2,10,16                        0             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          A.B. Parker Elementary School:
09-0729   Reconstruction               0-006-005  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,8,9,14,155,15,   3,436,046     3,567,379  HCM             0           0      75,000 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0665   Reconstruction               0-006-006  02/27/13     DONE    DONE       DONE      01/11/13   01/11/13   12/21/12   02/12/08   2,7                      668,614             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0138   Reconstruction               0-006-007               DONE    STARTED    UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   2,16                           0             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Cortland Jr-Sr HS:
09-0730   Reconstruction               0-007-004  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,8,9,14,155,15,  17,685,068    17,672,824  HCM             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0666   Reconstruction               0-007-005  02/27/13     DONE    DONE       DONE      01/11/13   01/11/13   12/21/12   02/12/08   2,7                      699,302       699,302  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0023   Reconstruction               0-007-006                       ADDENDUM REQ'D       07/16/14   07/10/14   12/30/13   05/20/14   16                             0    36,684,000  DDJ             0           0           0 C&S Companies                           0        /  /                           /  /             
14-0139   Reconstruction               0-007-007               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/06   2,4,8,9,10,155,15,16           0    36,684,000  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Virgil Elementary School:
09-0731   Reconstruction               0-009-005  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,8,9,14,155,15,   4,650,401     2,171,364  HCM             0           0   1,761,798 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0667   Reconstruction               0-009-006  02/27/13     DONE    DONE       DONE      01/11/13   01/11/13   12/21/12   02/12/08   2,7                      367,941       367,941  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0140   Reconstruction               0-009-008               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   2,16                           0             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Storage Building @ Cortland Jr-Sr Hs:
09-0732   New Construction             2-018-001  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   01/07/10   02/12/08   02 - 16                  223,700             0  HCM             0           0           0 Tetra Tech Architects and Eng           0      09/05/11           YES           /  /             

          Maint Storage:
14-0141   Reconstruction               3-005-001               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   7                              0             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Bus Garage:
09-0733   Reconstruction               5-003-004  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   05/21/07   02/12/08   2,4,7,155,15,16        1,002,199     2,280,042  HCM             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
14-0142   Reconstruction               5-003-005               DONE    DONE       UNREVIEWED08/12/14   08/12/14   05/30/14   02/12/08   7,16                           0             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Concession Stand:
09-1524   Additions and Alterations    7-014-001  06/25/10     DONE    DONE       DONE      06/14/10   06/14/10   05/21/10   02/12/08   02 - 16                  228,700             0  HCM             0           0           0 Tetra Tech Architects and Eng           0      09/05/11           YES           /  /             

          Press Box @ Cortland Jr-St Highschoo:
09-0734   New Construction             7-017-001  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   01/07/10   02/12/08   02 - 16                   96,000             0  HCM             0           0           0 Tetra Tech Architects and Eng           0      09/05/11           YES           /  /             

          Ticket Booth @ Cortland Jr-Sr School:
09-0735   New Construction             7-019-001  06/25/10     DONE    DONE       DONE      01/12/10   01/11/10   01/07/10   02/12/08   02 - 16                   13,850             0  HCM             0           0           0 Tetra Tech Architects and Eng           0      01/02/13           YES           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MCGRAW CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 11-03-04-04
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          McGraw High School:
10-0660   Reconstruction               0-002-009  05/09/11     DONE    DONE       DONE      12/30/10   12/23/10   11/24/10   03/18/08   2,7,8,10,155,15,16     1,296,829     1,296,829  JOD             0           0      55,155 Hunt Engineers,Architects & l           0      08/30/12                       10/09/12           
12-0428   Reconstruction               0-002-010  06/18/13     DONE    DONE       DONE      11/01/12   11/01/12   07/20/12   09/12/12   10,155,16                100,000       100,000  DDJ             0           0           0                                         0      06/28/13                       07/10/13           
13-0318   Reconstruction               0-002-011  03/12/14     DONE    DONE       DONE      09/04/13   08/28/13   06/05/13   08/14/13   16                       100,000       100,000  JOB             0           0           0 INTELLIGENT CONVERTED ENERGY,           0      06/27/14                       07/01/14           
14-0237   Reconstruction               0-002-012                         UNREVIEWED         09/03/14   09/03/14   07/10/14   07/23/14   16                             0     6,920,758  JMB             0           0           0 C&S Companies                           0        /  /                           /  /             

          Elementary School:
10-0661   Reconstruction               0-004-011  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   11/24/10   03/18/08   2,8,9,10,155,15,16     1,338,138     1,338,138  JOD             0           0      56,845 Hunt Engineers,Architects & l           0      08/30/12                       10/09/12           

          District Wide:
09-1445   Reconstruction               7-999-003  05/26/10     DONE    DONE       DONE      05/19/10   05/13/10   04/21/10   03/18/08   13,16                    285,036       285,036  JOD             0           0      12,121 Hunt Engineers,Architects & l           0      03/29/13                       02/18/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HOMER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 11-07-01-06
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
14-0709   Reconstruction               0-002-010                         UNREVIEWED         12/02/14   12/02/14   03/28/14   12/12/13   2,4,7,8,9,10,14,155,           0    19,647,630  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Bus Gar/Stor.Maint/Music Bldg:
14-0710   Reconstruction               0-003-004                         UNREVIEWED         12/02/14   12/02/14   03/28/14   12/12/13   2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Homer Elementary School:
14-0711   Reconstruction               0-006-010                         UNREVIEWED         12/02/14   12/02/14   03/28/14   12/12/13   2,4,8,9,10,155,15,16           0     9,885,745  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Intermediate Jr. High School:
13-0895   Reconstruction               0-007-008  03/11/14     DONE    DONE       DONE      12/13/13   12/12/13   11/19/13   05/21/13   16                       100,000       100,000  DDJ             0           0           0 Hunt Engineers,Architects & l           0      06/09/14                       06/24/14           
14-0712   Reconstruction               0-007-009                         UNREVIEWED         12/02/14   12/02/14   03/28/14   12/12/13   2,4,8,9,10,13,155,15           0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-0596   Reconstruction               0-007-010               STARTED DONE       UNREVIEWED11/06/14   11/06/14   09/23/14   05/20/14   10,155,16                      0    28,277,648  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Hartnett Elementary:
14-0713   Reconstruction               0-008-007                         UNREVIEWED         12/02/14   12/02/14   03/28/14   12/12/13   2,4,8,9,10,155,15,16           0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Pressbox High School:
14-0714   Reconstruction               7-015-002                         UNREVIEWED         12/02/14   12/02/14   11/24/14   12/12/13   16                             0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARATHON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 11-09-01-04
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
09-1092   Reconstruction               0-001-012  09/03/10     DONE    DONE       DONE      03/18/10   03/10/10   01/11/10   05/19/09   2,4,7,8,9,10,155,15,   3,004,000     3,004,000  HCM             0           0      60,080 King & King Architects                  0      10/01/12                         /  /             
11-0759   Reconstruction               0-001-013  05/03/12     DONE    DONE       DONE      02/08/12   02/08/12   01/31/12   05/19/09   2,4,7,9,155,15,16        282,900       282,900  HCM             0           0       5,658 King & King Architects                  0      10/01/12                       06/30/14           
13-0592   Reconstruction               0-001-014  06/18/14     DONE    DONE       DONE      10/21/13   10/15/13   05/02/13   11/01/12   2,7,9,155,15,16        5,977,000             0  MFS             0           0           0 King & King Architects                  0        /  /                           /  /             

          Appleby Elementary:
09-1093   Additions and Alterations    0-005-011  09/03/10     DONE    DONE       DONE      03/18/10   03/10/10   08/15/07   05/19/09   02 - 16                2,494,928     2,390,282  MFS             0           0      66,771 King & King, Architects                 0      10/01/12                         /  /             
11-0760   Reconstruction               0-005-012  05/03/12     DONE    DONE       DONE      02/08/12   02/08/12   06/09/09   05/19/09   2,10,15                  267,900       267,900  HCM             0           0       5,358 King & King Architects                  0      10/01/12                       06/30/14           
09-0334   Reconstruction               0-005-013  02/09/10     DONE    DONE       DONE      10/23/09   10/19/09   07/31/09   05/19/09   2,15                     310,827       310,827  HCM             0           0     310,827 King & King Architects                  0      07/01/10                         /  /             
13-0593   Reconstruction               0-005-014  06/18/14     DONE    DONE       DONE      10/21/13   10/15/13   05/02/13   11/01/12   2,7,9,155,15,16        2,279,000             0  MFS             0           0           0 King & King Architects                  0        /  /                           /  /             
13-1297   Reconstruction               0-005-015  02/13/14     DONE    DONE       DONE      03/04/14   03/04/14   12/19/13   10/24/12   2,9,15                   188,400       188,400  MFS             0           0           0 King & King Architects                  0      05/14/14                       06/03/14           

          Heated Storage Building:
09-1094   New Construction             2-009-001  09/03/10     DONE    DONE       DONE      03/18/10   03/10/10   12/31/09   05/19/09   02 - 16                  178,312             0  HCM             0           0           0 King & King Architects                  0      10/01/12                       06/30/14           

          New Bus Garage:
09-1095   Reconstruction               5-006-004  09/03/10     DONE    DONE       DONE      03/18/10   03/10/10   08/15/07   05/19/09   2,7,15,16                156,477       156,477  HCM             0           0           0 King & King, Architects                 0      10/01/12                       06/30/14           
  -       Reconstruction               5-006-005                                              /  /       /  /     01/11/10     /  /     2,7,155,16                     0             0  HCM             0           0           0                                         0        /  /                           /  /             
13-0594   Reconstruction               5-006-006  06/18/14     DONE    DONE       DONE      10/21/13   10/15/13   05/02/13   11/01/12   2,7,155,15,16            344,000             0  MFS             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED