Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/24/14 at 16:40:50




ANDES CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-01-02-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -       Reconstruction               0-001-008                                              /  /       /  /     09/27/10     /  /     2,155,15,16                    0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0003   Reconstruction               0-001-009  11/18/11     DONE    DONE       DONE      07/06/11   07/05/11   11/18/10   01/20/11   2,155,15,16              160,000       160,000  HCM             0           0           0 Glynn Spillane Griffing Archi           0      09/18/12                       11/05/12         YES
                                                                                                                                                                                                                                                                                                                                   
12-0122   Reconstruction               0-001-010  12/17/12     DONE    DONE       DONE      08/22/12   08/22/12   03/08/12   05/15/12   16                       100,000       100,000  HCM             0           0           0 Sacco & Mckinney Architects             0      09/20/13                       05/19/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage/AG Building:
  -       Reconstruction               0-003-006                                              /  /       /  /     09/27/10     /  /     2,14,155,15,16                 0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0004   Reconstruction               0-003-007  11/18/11     DONE    DONE       DONE      07/06/11   07/05/11   11/18/10   01/20/11   2,155,15,16               40,000        40,000  HCM             0           0           0 Glynn Spillane Griffing Archi           0      09/18/12                       11/05/12         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-003-008                                              /  /       /  /     03/28/12     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Red Schoolhouse:
  -       Reconstruction               0-004-003                                              /  /       /  /     03/28/12     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Storage Shed:
11-0781DB Discovered Building          2-007-001                       ADDENDUM REQ'D       02/10/12   01/09/12   01/17/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Districtwide:
  -       Reconstruction               7-999-001                                              /  /       /  /     02/15/12     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DOWNSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-03-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
09-0130   Additions and Alterations    0-001-013  12/01/09     DONE    DONE       DONE      08/18/09   08/17/09   05/01/08   06/11/08   02 - 16               10,738,850     7,912,878  DDJ             0           0           0                                         0      11/09/11                       06/28/13           

          New Bus Garage:
08-1456   New Construction             5-004-001  09/17/09     DONE    DONE       DONE      04/02/09   04/01/09   05/01/08   06/11/08   02 - 16                3,210,000     3,210,000  DDJ             0           0           0                                         0      11/09/11                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHARLOTTE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-04-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bus Garage:
11-0457   Reconstruction               5-002-003                       ADDENDUM REQ'D       12/01/11   11/28/11   09/21/11     /  /     13                             0             0  DDJ             0           0           0 McManus Engineering Group, LL           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DELAWARE ACADEMY CSD AT DELHI STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-05-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Delaware Academy:
13-0305   Reconstruction               0-001-008  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   02/19/13   02/12/13   2,4,7,8,9,155,15,16    5,447,000             0  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Delhi Elementary School:
13-0306   Reconstruction               0-004-005  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   02/19/13   02/12/13   2,4,7,8,9,155,15,16    1,751,000             0  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          A.L. Kellogg Elementary School:
10-0140   Reconstruction               0-009-003  08/23/10     DONE    DONE       DONE      08/23/10   08/23/10   02/11/10   06/13/05   7,8,9                     72,612             0  DDJ             0           0           0 Ashley McGraw Architects                0      02/29/12                         /  /             

          Storage Shed #2:
13-0307   New Construction             2-016-001  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   08/27/13   02/12/13   02 - 16                  124,500             0  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Bus/Maintenance Garage:
13-0308   Reconstruction               5-010-003  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   02/19/13   02/12/13   2,4,8,9,155,15,16        427,500             0  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Sap House:
  -    DB Discovered Building          7-014-001                                              /  /       /  /     08/27/13     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-014-002                                              /  /       /  /     08/27/13     /  /     10                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Press Box:
  -    DB Discovered Building          7-015-001                                              /  /       /  /     08/27/13     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FRANKLIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-07-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
13-1673   Reconstruction               0-001-017                         UNREVIEWED         06/19/14   06/19/14   05/30/14   05/20/14   2,15                           0     9,995,369  DDJ             0           0           0 IBI GROUP                               0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HANCOCK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-09-06-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
13-0892   Reconstruction               0-001-011  04/11/14     DONE    DONE       DONE      12/13/13   12/11/13   05/17/13   10/13/13   155                      100,000       100,000  DDJ             0           0           0 INTELLIGENT CONVERTED ENERGY,           0      06/27/14                       06/30/14           
  -       Reconstruction               0-001-012                                              /  /       /  /     07/16/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Elementary School:
  -    PR Additions and Alterations    0-004-010                                              /  /       /  /     07/16/14     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Bldg. #1 @ High School:
08-0666DB Discovered Building          2-010-001  10/19/09     DONE    DONE       DONE      11/04/08   10/30/08   03/19/07     /  /                                    0             0  JOD             0           0           0 RSA  (Robertson Strong Apgar)           0        /  /                           /  /             

          Storage Bldg. #2 @ High School:
08-0667DB Discovered Building          2-011-001  10/19/09     DONE    DONE       DONE      11/04/08   10/30/08   03/19/07     /  /                                    0             0  JOD             0           0           0 RSA  (Robertson Strong Apgar)           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARGARETVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-14-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Margaretville School:
  -       Reconstruction               0-001-011                                              /  /       /  /     12/01/11     /  /     4,8,9,10,155,15,16             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROXBURY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-15-02-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
09-0996   Reconstruction               0-001-012  03/30/10     DONE    DONE       DONE      03/02/10   02/24/10   11/23/09   02/02/10   7                        600,000       600,000  HCM             0           0           0 William Taylor Architects, PL           0      01/24/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-0586   Reconstruction               0-001-013  07/10/11     DONE    DONE       DONE      12/21/12   12/17/12   12/06/10   05/20/08   4                        177,153       177,153  HCM             0           0           0 William Taylor Architects, PL           0      03/01/13                       05/22/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-1236   Reconstruction               0-001-014  06/01/12     DONE    DONE       DONE      04/26/12   04/19/12   04/13/11   04/11/12   10,13,16                 250,000             0  HCM             0           0           0 William Taylor Architects, PL           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-015                                              /  /       /  /     01/17/12     /  /     4,8,9,155,15,16                0             0  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-016                                              /  /       /  /     06/03/14     /  /     2,4,7,8,9,10,155,15,           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
  -       Reconstruction               5-009-005                                              /  /       /  /     06/10/14     /  /     9,10                           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Shelter:
  -       New Construction             7-013-001                                              /  /       /  /     06/10/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SIDNEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-16-01-06
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sidney Senior High:
11-0668   Reconstruction               0-001-009  04/26/12     DONE    DONE       DONE      01/17/12   01/13/12   06/20/05   05/17/11   2,4,7,8,9,13,15,16       909,000       909,000  JOD             0           0     120,897                                         0      02/25/13                       01/08/14           
12-1216   Reconstruction               0-001-011  12/12/13     DONE    DONE       DONE      05/21/13   05/21/13   11/12/08   01/05/13   2,4,7,8,9,10,155,15,   1,428,000             0  JOD             0           0     189,924 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
12-1002   Reconstruction               0-001-012  08/22/13     DONE    DONE       DONE      03/21/13   03/20/13   01/24/13   01/15/13   2,8                    4,129,000             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
12-1300   Reconstruction               0-001-013  08/27/13     DONE    DONE       DONE      06/18/13   06/18/13   06/05/13   05/21/13   16                       100,000       100,000  MFS             0           0      16,900 BCK-IBI Group, a New York Gen           0      03/04/14                       06/16/14           

          Pearl Street Elementary:
11-0669   Reconstruction               0-003-009  04/26/12     DONE    DONE       DONE      01/17/12   01/13/12   11/04/08   05/17/11   2,4,7,8,9,10,155,15,     565,410       565,410  JOD             0           0      75,200                                         0      02/25/13                       01/08/14           
10-0108   Reconstruction               0-003-010  08/16/10     DONE    DONE       DONE      08/11/10   08/02/10   06/18/10   05/18/10   155                      105,000       105,000  JOD             0           0           0                                         0      07/06/11                         /  /             
12-1217   Reconstruction               0-003-011  12/12/13     DONE    DONE       DONE      05/21/13   05/21/13   01/24/13   01/05/13   2,9,155,16               360,000             0  MFS             0           0      47,880 BCK-IBI Group, a New York Gen           0        /  /                           /  /             

          Masonville Elementary:
10-1418   Reconstruction               0-006-009  07/11/11     DONE    DONE       DONE      06/23/11   06/06/11   05/19/11   05/17/11   7                        107,600             0  JOD             0           0           0                                         0      05/25/12                       12/17/12           

          Middle School:
11-0670   Reconstruction               0-007-010  04/26/12     DONE    DONE       DONE      01/17/12   01/13/12   07/24/07   05/17/11   2,4,7,8,10,15,16       1,121,590     1,121,590  JOD             0           0     149,171                                         0      02/25/13                       01/08/14           
12-1218   Reconstruction               0-007-011  12/12/13     DONE    DONE       DONE      05/21/13   05/21/13   11/12/08   01/05/13   2,4,7,8,9,10,155,15,   1,782,000             0  JOD             0           0     237,006 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
  -       Reconstruction               0-007-012                                              /  /       /  /     06/05/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH KORTRIGHT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-17-02-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
13-1695   Reconstruction               0-003-011                         UNREVIEWED         07/02/14   06/30/14   07/30/13   05/20/14   9,155,15,16                    0             0  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WALTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-19-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Townsend Elementary School:
08-1449   Reconstruction               0-006-017  07/31/09     DONE    DONE       DONE      04/01/09   03/30/09   06/04/07   05/15/07   2,4,8,9,10,155,15,16     777,840       777,840  HCM             0           0     125,859 Bell&Spina, P.C                         0      04/04/11                         /  /             
12-0485   Reconstruction               0-006-019  04/25/13     DONE    DONE       DONE      11/27/12   11/26/12   04/24/08   11/15/11   2,4,9,13,155,16        1,307,500     1,307,500  HCM             0           0           0 Bell&Spina, P.C                         0        /  /             YES           /  /             
12-0114   Reconstruction               0-006-020  08/29/12     DONE    DONE       DONE      08/17/12   08/15/12   07/30/12   08/07/12   2,9                       59,804        59,804  JMB             0           0           0 Bell&Spina, P.C                         0      01/07/13                       06/30/13           
  -    XX Reconstruction               0-006-021                         CANCELLED            /  /       /  /     08/02/12     /  /     2,9                            0    10,870,038  JMB             0           0           0                                         0        /  /                           /  /             

          O'Neill Jr/Sr High School:
08-1450   Reconstruction               0-007-016  08/27/09     DONE    DONE       DONE      04/01/09   03/30/09   04/24/08   05/15/07   2,4,8,9,155,15,16        826,978       826,978  HCM             0           0     153,062 Bell&Spina, P.C                         0      04/04/11                         /  /             
10-1326   Reconstruction               0-007-017  06/13/11     DONE    DONE       DONE      05/20/11   05/18/11   06/18/10   05/17/11   155                      425,815       412,000  HCM             0           0      34,189 Bell&Spina, P.C                         0      07/19/11                       02/21/13           
11-1247   Reconstruction               0-007-018  09/21/12     DONE    DONE       DONE      05/01/12   04/26/12   01/04/12   11/15/11   2,9                      490,600       490,600  HCM             0           0           0 Bell&Spina, P.C                         0        /  /                           /  /             
12-0486   Reconstruction               0-007-019  04/25/13     DONE    DONE       DONE      11/27/12   11/26/12   09/04/12   11/15/11   2,4,7,8,9,10,155,15,   1,759,900     1,759,900  JMB             0           0           0 Bell&Spina, P.C                         0        /  /             YES           /  /             

          Greenhouse:
10-0085   New Construction             0-018-001  10/25/10     DONE    DONE       DONE      08/04/10   07/21/10   04/30/10   05/21/10   02 - 16                   12,000             0  HCM             0           0           0 Bell&Spina, P.C                         0      07/07/11                         /  /             

          New Storage Building:
07-0545DB Discovered Building          2-016-002  10/20/09     DONE    DONE       DONE      10/12/07   10/12/07   11/22/06     /  /                                    0             0  HCM             0           0           0 Bell&Spina, P.C                         0        /  /                           /  /             

          Wood Athletic Storage Bldg.:
07-0546DB Discovered Building          2-017-001  10/20/09     DONE    DONE       DONE      10/12/07   10/12/07   11/22/06     /  /                                    0             0  HCM             0           0           0 Bell&Spina, P.C                         0        /  /                           /  /             

          Bus Garage:
12-0487   Reconstruction               5-003-009  04/25/13     DONE    DONE       DONE      11/27/12   11/26/12   04/25/08   11/15/11   8,9,16                    82,000             0  HCM             0           0           0 Bell&Spina, P.C                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES DEL-CHEN-MADISON-OTSEGO STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-90-00-00
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          W.Delaware Occ.Bldg. A:
10-0104   Reconstruction               0-001-019  09/23/10     DONE    DONE       DONE      08/11/10   07/30/10   03/19/10   04/29/10   15,16                    124,825       124,825  JOD             0           0           0                                         0      11/30/12                       02/21/13           
  -       Reconstruction               0-001-020                                              /  /       /  /     09/21/11     /  /     2,16                           0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-1122   Reconstruction               0-001-021  06/08/12     DONE    DONE       DONE      04/12/12   04/12/12   03/06/12     /  /     2,7,8,9                  152,000       152,000  JOD             0           0           0                                         0      03/07/13                       11/07/13           
  -       Reconstruction               0-001-022                                              /  /       /  /     04/11/14     /  /     2,4,9,13,16                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Chenango Campus (Occ Ctr 011):
11-1123   Reconstruction               0-002-023  06/08/12     DONE    DONE       DONE      04/12/12   04/12/12   03/06/12     /  /     2,4,8,9                   19,000        19,000  JOD             0           0           0                                         0      03/07/13                       11/07/13           
13-0140   Reconstruction               0-002-024  12/02/13     DONE    DONE       DONE      08/06/13   08/06/13   01/24/13   07/11/13   2,4,8,9,13,155,15,16     430,000             0  MFS             0           0           0 Teitsch-Kent                            0        /  /                           /  /             

          W. Delaware Ed. Campus Bldg. B:
10-0105   Reconstruction               0-003-014  09/23/10     DONE    DONE       DONE      08/11/10   07/30/10   03/19/10   04/29/10   8                        225,020       225,020  JOD             0           0           0                                         0      11/30/12                       02/20/13           
10-1115   Reconstruction               0-003-015  06/07/11     DONE    DONE       DONE      03/29/11   03/24/11   03/23/11     /  /     4,7,9                    250,000       250,000  JOD             0           0           0                                         0      11/30/12                       02/21/13           
11-1124   Reconstruction               0-003-016  06/08/12     DONE    DONE       DONE      04/12/12   04/12/12   03/06/12     /  /     2,4,7,8,9                259,000       259,000  JOD             0           0           0                                         0      03/07/13                       11/07/13           
12-0751   Reconstruction               0-003-017  03/22/13     DONE    DONE       DONE      02/01/13   01/25/13   09/25/12   01/24/13   2,4,8,9,13,155,15,16     430,000             0  MFS             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
  -       Reconstruction               0-003-018                                              /  /       /  /     04/11/14     /  /     2,4,9,13,16                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Support Service Building:
09-1346   Reconstruction               1-032-002  08/09/10     DONE    DONE       DONE      04/20/10   04/19/10   03/19/10   04/29/10   8,9,10,155,16            147,155             0  JOD             0           0           0                                         0      11/30/12                       02/20/13           

          Eaton Center:
09-0100TQ Temporary Quarters           8-041-002  08/18/09     DONE    DONE       DONE      08/04/09   08/03/09   08/04/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED