Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/30/15 at 09:18:41




ANDES CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-01-02-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -       Reconstruction               0-001-008                                              /  /       /  /     09/27/10     /  /     2,155,15,16                    0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0003   Reconstruction               0-001-009  11/18/11     DONE    DONE       DONE      07/06/11   07/05/11   11/18/10   01/20/11   2,155,15,16              160,000       160,000  HCM             0           0           0 Glynn Spillane Griffing Archi           0      09/18/12                       11/05/12         YES
                                                                                                                                                                                                                                                                                                                                   
12-0122   Reconstruction               0-001-010  12/17/12     DONE    DONE       DONE      08/22/12   08/22/12   03/08/12   05/15/12   16                       100,000       100,000  HCM             0           0           0 Sacco & Mckinney Architects             0      09/20/13                       05/19/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage/AG Building:
  -       Reconstruction               0-003-006                                              /  /       /  /     09/27/10     /  /     2,14,155,15,16                 0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0004   Reconstruction               0-003-007  11/18/11     DONE    DONE       DONE      07/06/11   07/05/11   11/18/10   01/20/11   2,155,15,16               40,000        40,000  HCM             0           0           0 Glynn Spillane Griffing Archi           0      09/18/12                       11/05/12         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-003-008                                              /  /       /  /     03/28/12     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Red Schoolhouse:
  -       Reconstruction               0-004-003                                              /  /       /  /     03/28/12     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Storage Shed:
11-0781DB Discovered Building          2-007-001                       ADDENDUM REQ'D       02/10/12   01/09/12   01/17/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Districtwide:
  -       Reconstruction               7-999-001                                              /  /       /  /     02/15/12     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHARLOTTE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-04-01-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bus Garage:
11-0457   Reconstruction               5-002-003                       ADDENDUM REQ'D       12/01/11   11/28/11   09/21/11     /  /     13                             0             0  DDJ             0           0           0 McManus Engineering Group, LL           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DELAWARE ACADEMY CSD AT DELHI STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-05-01-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Delaware Academy:
13-0305   Reconstruction               0-001-008  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   02/19/13   02/12/13   2,4,7,8,9,155,15,16    5,447,000     5,447,000  DDJ             0           0           0 Ashley McGraw Architects                0      08/26/14           YES           /  /             

          Delhi Elementary School:
13-0306   Reconstruction               0-004-005  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   02/19/13   02/12/13   2,4,7,8,9,155,15,16    1,751,000     1,751,000  DDJ             0           0           0 Ashley McGraw Architects                0      08/26/14           YES           /  /             

          A.L. Kellogg Elementary School:
10-0140   Reconstruction               0-009-003  08/23/10     DONE    DONE       DONE      08/23/10   08/23/10   02/11/10   06/13/05   7,8,9                     72,612             0  DDJ             0           0           0 Ashley McGraw Architects                0      02/29/12                         /  /             

          Storage Shed #2:
13-0307   New Construction             2-016-001  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   08/27/13   02/12/13   02 - 16                  124,500             0  DDJ             0           0           0 Ashley McGraw Architects                0      08/26/14           YES           /  /             

          Bus/Maintenance Garage:
13-0308   Reconstruction               5-010-003  04/01/14     DONE    DONE       DONE      08/30/13   08/16/13   02/19/13   02/12/13   2,4,8,9,155,15,16        427,500       427,500  DDJ             0           0           0 Ashley McGraw Architects                0      08/26/14           YES           /  /             

          Sap House:
  -    DB Discovered Building          7-014-001                                              /  /       /  /     08/27/13     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-014-002                                              /  /       /  /     08/27/13     /  /     10                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Press Box:
  -    DB Discovered Building          7-015-001                                              /  /       /  /     08/27/13     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FRANKLIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-07-01-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
13-1673   Reconstruction               0-001-017  08/07/14     DONE    DONE       DONE      06/19/14   06/19/14   05/30/14   05/20/14   2,15                     100,000       100,000  DDJ             0           0           0 IBI GROUP                               0      05/05/15                       05/18/15         YES
                                                                                                                                                                                                                                                                                                                                   
14-0902   Reconstruction               0-001-018  04/01/15     DONE    DONE       DONE      12/31/14   12/26/14   11/12/14   01/08/15   4,8,9,10,155,15,16       100,000       100,000  DDJ             0           0           0 IBI GROUP                               0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HANCOCK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-09-06-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
13-0892   Reconstruction               0-001-011  04/11/14     DONE    DONE       DONE      12/13/13   12/11/13   05/17/13   10/13/13   155                      100,000       100,000  DDJ             0           0           0 INTELLIGENT CONVERTED ENERGY,           0      06/27/14                       06/30/14           
15-0107   Reconstruction               0-001-012                         UNREVIEWED         07/16/15   07/16/15   07/16/14   01/26/15   2,4,7,8,9,10,155,15,           0    14,294,240  DDJ             0           0           0 Highland Associates                     0        /  /                           /  /             
14-0404   Reconstruction               0-001-013  06/08/15     DONE    DONE       DONE      10/06/14   10/03/14   09/11/14   05/20/14   10,155                    50,000        50,000  DDJ             0           0           0 C&S Companies                           0        /  /                           /  /             

          Elementary School:
  -    PR Additions and Alterations    0-004-010                                              /  /       /  /     07/16/14     /  /     02 - 16                        0     4,605,120  DDJ             0           0           0                                         0        /  /                           /  /             
15-0106   Additions and Alterations    0-004-010                         UNREVIEWED         07/16/15   07/16/15   07/16/14   01/26/15   02 - 16                        0     4,598,460  DDJ             0           0           0 Highland Associates                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARGARETVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-14-01-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Margaretville School:
  -       Reconstruction               0-001-011                                              /  /       /  /     12/01/11     /  /     4,8,9,10,155,15,16             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-1251   Reconstruction               0-001-012                         UNREVIEWED         03/09/15   03/06/15   09/04/14   11/19/14   2,7,8,9,155,15,16              0    19,958,347  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
15-0047   Reconstruction               0-001-013                         UNREVIEWED         07/13/15   07/09/15   03/23/15   12/09/14   2,4,7,8,9,155,15,16            0    19,806,720  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-014                                              /  /       /  /     03/27/15     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
15-0048   Reconstruction               5-002-004                         UNREVIEWED         07/13/15   07/09/15   09/04/14   12/09/14   2,155,15,16                    0             0  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROXBURY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-15-02-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
12-0586   Reconstruction               0-001-013  07/10/11     DONE    DONE       DONE      12/21/12   12/17/12   12/06/10   05/20/08   4                        177,153       177,153  HCM             0           0           0 William Taylor Architects, PL           0      03/01/13                       05/22/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-1236   Reconstruction               0-001-014  06/01/12     DONE    DONE       DONE      04/26/12   04/19/12   04/13/11   04/11/12   10,13,16                 250,000       250,000  HCM             0           0           0 William Taylor Architects, PL           0      10/30/14                       11/07/14         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-015                                              /  /       /  /     01/17/12     /  /     4,8,9,155,15,16                0    14,606,055  HCM             0           0           0                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-0653   Reconstruction               0-001-016               STARTED STARTED    UNREVIEWED11/21/14   11/21/14   06/03/14     /  /     2,4,7,8,9,10,155,15,           0    14,606,055  JMB             0           0           0 William Taylor Architects, PL           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage:
14-0654   Reconstruction               5-009-005               STARTED STARTED    UNREVIEWED11/21/14   11/21/14   06/10/14     /  /     9,10                           0             0  JMB             0           0           0 William Taylor Architects, PL           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          XXBus Shelter:
14-0655XX New Construction             7-013-001                         CANCELLED          11/21/14   11/21/14   06/10/14     /  /     02 - 16                        0             0  JMB             0           0           0 William Taylor Architects, PL           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SIDNEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-16-01-06
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sidney Senior High:
11-0668   Reconstruction               0-001-009  04/26/12     DONE    DONE       DONE      01/17/12   01/13/12   06/20/05   05/17/11   2,4,7,8,9,13,15,16       909,000       909,000  JOD             0           0     120,897 Bearsch Compeau Knudson Archi           0      02/25/13                       01/08/14           
12-1216   Reconstruction               0-001-011  12/12/13     DONE    DONE       DONE      05/21/13   05/21/13   11/12/08   01/05/13   2,4,7,8,9,10,155,15,   1,428,000     1,428,000  JOD             0           0     189,924 BCK-IBI Group, a New York Gen           0      11/21/14                       03/19/15           
12-1002   Reconstruction               0-001-012  08/22/13     DONE    DONE       DONE      03/21/13   03/20/13   01/24/13   01/15/13   2,8                    4,129,000     2,544,945  MFS             0           0           0 BCK-IBI Group, a New York Gen           0      11/11/14                       03/19/15           
12-1300   Reconstruction               0-001-013  08/27/13     DONE    DONE       DONE      06/18/13   06/18/13   06/05/13   05/21/13   16                       100,000       100,000  MFS             0           0      16,900 BCK-IBI Group, a New York Gen           0      03/04/14                       06/16/14           
14-0556XX Reconstruction               0-001-014  01/08/15               CANCELLED          10/31/14   10/30/14   10/02/14   05/20/14   2,9,10                   100,000       100,000  MFS             0           0           0 IBI GROUP                               0        /  /                           /  /             
14-1426   Reconstruction               0-001-015  NEED AUTH    DONE    DONE       DONE      04/23/15   04/23/15   03/31/15     /  /     7                              0             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             

          Pearl Street Elementary:
11-0669   Reconstruction               0-003-009  04/26/12     DONE    DONE       DONE      01/17/12   01/13/12   11/04/08   05/17/11   2,4,7,8,9,10,155,15,     565,410       565,410  JOD             0           0      75,200 Bearsch Compeau Knudson Archi           0      02/25/13                       01/08/14           
10-0108   Reconstruction               0-003-010  08/16/10     DONE    DONE       DONE      08/11/10   08/02/10   06/18/10   05/18/10   155                      105,000       105,000  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      07/06/11                         /  /             
12-1217   Reconstruction               0-003-011  12/12/13     DONE    DONE       DONE      05/21/13   05/21/13   01/24/13   01/05/13   2,9,155,16               360,000       360,000  MFS             0           0      47,880 BCK-IBI Group, a New York Gen           0      11/21/14                       03/19/15           
14-1427   Reconstruction               0-003-012  NEED AUTH    DONE    DONE       DONE      04/23/15   04/23/15   03/31/15     /  /     7                              0             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             

          Masonville Elementary:
10-1418   Reconstruction               0-006-009  07/11/11     DONE    DONE       DONE      06/23/11   06/06/11   05/19/11   05/17/11   7                        107,600             0  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      05/25/12                       12/17/12           

          Middle School:
11-0670   Reconstruction               0-007-010  04/26/12     DONE    DONE       DONE      01/17/12   01/13/12   07/24/07   05/17/11   2,4,7,8,10,15,16       1,121,590     1,121,590  JOD             0           0     149,171 Bearsch Compeau Knudson Archi           0      02/25/13                       01/08/14           
12-1218   Reconstruction               0-007-011  12/12/13     DONE    DONE       DONE      05/21/13   05/21/13   11/12/08   01/05/13   2,4,7,8,9,10,155,15,   1,782,000     1,782,000  JOD             0           0     237,006 BCK-IBI Group, a New York Gen           0      11/21/14                       03/19/15           
  -       Reconstruction               0-007-012                                              /  /       /  /     06/05/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             
14-1428   Reconstruction               0-007-013  NEED AUTH    DONE    DONE       DONE      04/23/15   04/23/15   03/31/15     /  /     7                              0             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




STAMFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-17-01-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg.:
14-1246   Reconstruction               0-001-007               DONE    DONE       UNREVIEWED03/06/15   03/05/15   12/02/14   01/29/15   2,4,8,9,10,13,155,15           0    12,137,609  JMB             0           0           0 March Associates                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH KORTRIGHT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-17-02-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
13-1695   Reconstruction               0-003-011  08/14/14     DONE    DONE       DONE      07/02/14   06/30/14   07/30/13   05/20/14   9,155,15,16              100,000       100,000  DDJ             0           0           0 Ashley McGraw Architects                0      06/26/15                       07/01/15         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-003-012                                              /  /       /  /     07/24/15     /  /     2,4,7,8,9,10,14,155,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WALTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-19-01-04
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Townsend Elementary School:
12-0485   Reconstruction               0-006-019  04/25/13     DONE    DONE       DONE      11/27/12   11/26/12   04/24/08   11/15/11   2,4,9,13,155,16        1,307,500     1,307,500  HCM             0           0           0 Bell&Spina, P.C                         0        /  /             YES           /  /             
12-0114   Reconstruction               0-006-020  08/29/12     DONE    DONE       DONE      08/17/12   08/15/12   07/30/12   08/07/12   2,9                       59,804        59,804  JMB             0           0           0 Bell&Spina, P.C                         0      01/07/13                       06/30/13           
  -    XX Reconstruction               0-006-021                         CANCELLED            /  /       /  /     08/02/12     /  /     2,9                            0    11,757,407  JMB             0           0           0                                         0        /  /                           /  /             

          O'Neill Jr/Sr High School:
10-1326   Reconstruction               0-007-017  06/13/11     DONE    DONE       DONE      05/20/11   05/18/11   06/18/10   05/17/11   155                      425,815       425,815  HCM             0           0      34,189 Bell&Spina, P.C                         0      07/19/11                       02/21/13           
11-1247   Reconstruction               0-007-018  09/21/12     DONE    DONE       DONE      05/01/12   04/26/12   01/04/12   11/15/11   2,9                      490,600       490,600  HCM             0           0           0 Bell&Spina, P.C                         0      07/28/14                       08/27/14           
12-0486   Reconstruction               0-007-019  04/25/13     DONE    DONE       DONE      11/27/12   11/26/12   09/04/12   11/15/11   2,4,7,8,9,10,155,15,   1,759,900     1,759,900  JMB             0           0           0 Bell&Spina, P.C                         0        /  /             YES           /  /             

          Greenhouse:
10-0085   New Construction             0-018-001  10/25/10     DONE    DONE       DONE      08/04/10   07/21/10   04/30/10   05/21/10   02 - 16                   12,000             0  HCM             0           0           0 Bell&Spina, P.C                         0      07/07/11                         /  /             

          Bus Garage:
12-0487   Reconstruction               5-003-009  04/25/13     DONE    DONE       DONE      11/27/12   11/26/12   04/25/08   11/15/11   8,9,16                    82,000             0  HCM             0           0           0 Bell&Spina, P.C                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES DEL-CHEN-MADISON-OTSEGO STATUS REPORT ON CAPITAL PROJECTS
District No.: 12-90-00-00
last updated on 07/30/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          W.Delaware Occ.Bldg. A:
10-0104   Reconstruction               0-001-019  09/23/10     DONE    DONE       DONE      08/11/10   07/30/10   03/19/10   04/29/10   15,16                    124,825       124,825  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      11/30/12                       02/21/13           
  -       Reconstruction               0-001-020                                              /  /       /  /     09/21/11     /  /     2,16                           0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-1122   Reconstruction               0-001-021  06/08/12     DONE    DONE       DONE      04/12/12   04/12/12   03/06/12     /  /     2,7,8,9                  152,000       152,000  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      03/07/13                       11/07/13           
14-0275   Reconstruction               0-001-022  02/09/15     DONE    DONE       DONE      09/10/14   09/09/14   04/11/14     /  /     2,4,9,13,16               91,000             0  MFS             0           0           0 Teitsch-Kent                            0        /  /                           /  /             

          Chenango Campus (Occ Ctr 011):
11-1123   Reconstruction               0-002-023  06/08/12     DONE    DONE       DONE      04/12/12   04/12/12   03/06/12     /  /     2,4,8,9                   19,000        19,000  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      03/07/13                       11/07/13           
13-0140   Reconstruction               0-002-024  12/02/13     DONE    DONE       DONE      08/06/13   08/06/13   01/24/13   07/11/13   2,4,8,9,13,155,15,16     430,000       430,000  MFS             0           0           0 Teitsch-Kent                            0      08/27/14                       04/23/15           
14-0780   Reconstruction               0-002-025  12/30/14     DONE    DONE       DONE      12/18/14   12/16/14   09/16/14     /  /     4,9,10,155,16            110,350             0  MFS             0           0           0 Teitsch-Kent                            0        /  /                           /  /             

          W. Delaware Ed. Campus Bldg. B:
10-0105   Reconstruction               0-003-014  09/23/10     DONE    DONE       DONE      08/11/10   07/30/10   03/19/10   04/29/10   8                        225,020       225,020  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      11/30/12                       02/20/13           
10-1115   Reconstruction               0-003-015  06/07/11     DONE    DONE       DONE      03/29/11   03/24/11   03/23/11     /  /     4,7,9                    250,000       250,000  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      11/30/12                       02/21/13           
11-1124   Reconstruction               0-003-016  06/08/12     DONE    DONE       DONE      04/12/12   04/12/12   03/06/12     /  /     2,4,7,8,9                259,000       259,000  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      03/07/13                       11/07/13           
12-0751   Reconstruction               0-003-017  03/22/13     DONE    DONE       DONE      02/01/13   01/25/13   09/25/12   01/24/13   2,4,8,9,13,155,15,16     430,000       430,000  MFS             0           0           0 Teitsch-Kent                            0      08/27/14                       09/24/14           
14-0276   Reconstruction               0-003-018  02/09/15     DONE    DONE       DONE      09/10/14   09/09/14   04/11/14     /  /     2,4,9,13,16              339,000             0  MFS             0           0           0 Teitsch-Kent                            0        /  /                           /  /             

          Support Service Building:
09-1346   Reconstruction               1-032-002  08/09/10     DONE    DONE       DONE      04/20/10   04/19/10   03/19/10   04/29/10   8,9,10,155,16            147,155             0  JOD             0           0           0 Bearsch Compeau Knudson Archi           0      11/30/12                       02/20/13           

          Storage Building:
14-0359   New Construction             2-042-001  NEED AUTH    DONE    DONE       DONE      09/26/14   09/25/14   09/16/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Eaton Center-Bldg 3 1st Floor:
  -    TQ Temporary Quarters           8-042-001                                              /  /       /  /     07/23/15     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED