Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/22/14 at 16:25:13




BEACON CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-02-00-01
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          James Forrestal School:
09-0075   Reconstruction               0-002-014  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,7,9,14,155,15,16     1,540,823     1,540,823  JOD             0           0     238,630 Rhinebeck Architecture                  0      09/02/11                       06/30/14           
09-1166   Reconstruction               0-002-015  10/06/10     DONE    DONE       DONE      03/31/10   03/24/10   03/15/10   12/16/08   4,16                     252,000             0  JOD             0           0      41,328 Rhinebeck Architecture                  0        /  /                           /  /             
10-1123   Reconstruction               0-002-016  06/17/11     DONE    DONE       DONE      03/30/11   03/22/11   03/28/11   12/16/08   2,155                     54,856        54,856  JOD             0           0           0 Rhinebeck Architecture                  0      12/16/11                       06/27/13           
13-0691   Reconstruction               0-002-017  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          South Ave. School:
09-0076   Reconstruction               0-003-010  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,7,9,155,15,16          759,919       759,919  JOD             0           0     117,227 Rhinebeck Architecture                  0      09/02/11                       06/30/14           
09-1167   Reconstruction               0-003-011  10/06/10     DONE    DONE       DONE      03/31/10   03/24/10   03/15/10   12/16/08   4,16                     483,000             0  JOD             0           0      79,212 Rhinebeck Architecture                  0        /  /                           /  /             
10-1124   Reconstruction               0-003-012  06/17/11     DONE    DONE       DONE      03/30/11   03/22/11   03/28/11   12/16/08   155                       55,588        55,588  JOD             0           0           0 Rhinebeck Architecture                  0      12/16/11                       06/27/13           
13-0692   Reconstruction               0-003-013  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   2,8,155,15,16                  0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Rombout Junior High School:
09-0077   Reconstruction               0-004-012  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,4,7,8,9,14,155,15,     945,154       925,926  JOD             0           0     144,702 Rhinebeck Architecture                  0      09/02/11                       06/30/14           
09-0097   Reconstruction               0-004-013  09/30/09     DONE    DONE       DONE      07/31/09   07/27/09   06/29/09   12/16/08   16                       197,522       197,522  JOD             0           0      30,671 Rhinebeck Architecture                  0      02/24/10                       06/30/14           
09-1168   Reconstruction               0-004-014  10/06/10     DONE    DONE       DONE      03/31/10   03/24/10   03/15/10   12/16/08   2,7,16                   788,000             0  JOD             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
10-1125   Reconstruction               0-004-015  06/17/11     DONE    DONE       DONE      03/30/11   03/22/11   03/30/11   12/16/08   155                        2,669        15,000  JOD             0           0           0 Rhinebeck Architecture                  0      12/16/11                       06/27/13           
  -       Reconstruction               0-004-017                                              /  /       /  /     03/30/11     /  /     155                            0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0693   Reconstruction               0-004-018  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Glenham Elementary School:
09-0078   Reconstruction               0-006-015  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,9,15,16                777,028       777,028  JOD             0           0     118,463 Rhinebeck Architecture                  0      09/02/11                       06/30/14           
09-1169   Reconstruction               0-006-016  10/06/10     DONE    DONE       DONE      03/31/10   03/24/10   03/15/10   12/16/08   9,155,16                 573,000             0  JOD             0           0      93,972 Rhinebeck Architecture                  0        /  /                           /  /             
10-1126   Reconstruction               0-006-017  06/17/11     DONE    DONE       DONE      03/30/11   03/22/11   03/28/11   12/16/08   155                       50,109        50,109  JOD             0           0           0 Rhinebeck Architecture                  0      12/16/11                       06/27/13           
13-0694   Reconstruction               0-006-018  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Sargent Elementary School:
09-0079   Reconstruction               0-008-013  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,7,9,14,155,15,16     1,659,364     1,474,499  JOD             0           0     355,142 Rhinebeck Architecture                  0      09/02/11                       06/30/14           
09-1170   Reconstruction               0-008-014  10/06/10     DONE    DONE       DONE      03/31/10   03/24/10   03/15/10   12/16/08   7,16                     358,000             0  JOD             0           0      58,712 Rhinebeck Architecture                  0        /  /                           /  /             
10-0167   Reconstruction               0-008-015  09/01/10     DONE    DONE       DONE      08/27/10   08/19/10   07/07/10   12/16/08   155                       87,472        87,472  JOD             0           0       7,783 Rhinebeck Architecture                  0      12/03/10                       06/30/14           
13-0695   Reconstruction               0-008-016  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          New High School:
09-0080   Reconstruction               0-020-004  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,4,9,15,16              580,322       580,322  JOD             0           0      92,178 Rhinebeck Architecture                  0      09/02/11                       06/30/14           
09-0113   Reconstruction               0-020-005  12/03/09     DONE    DONE       DONE      08/11/09   08/11/09   07/31/09   12/16/08   2,8                      262,015       262,015  JOD             0           0           0 Rhinebeck Architecture                  0      09/02/11                       06/27/13           
09-1171   Reconstruction               0-020-006  10/06/10     DONE    DONE       DONE      03/31/10   03/24/10   03/15/10   12/16/08   8,9,16                   580,000             0  JOD             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0696   Reconstruction               0-020-007  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   2,155,15,16                    0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Administration Building:
13-0697   Reconstruction               1-005-006  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Bus Storage Facility:
13-0698   Reconstruction               4-020-002  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          New Bus Maintenance/Storage:
09-0081   Reconstruction               5-018-003  12/03/09     DONE    DONE       DONE      07/23/09   07/20/09   12/15/08   12/16/08   2,155,16                  96,041        96,041  JOD             0           0           0 Rhinebeck Architecture                  0      09/02/11                       06/27/13           
  -       Reconstruction               5-018-004                                              /  /       /  /     10/25/11     /  /     2,13,155,16                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0699   Reconstruction               5-018-005  07/22/14     DONE    DONE       DONE      11/12/13   11/08/13   08/08/13   07/15/13   155,15,16                      0             0  DDJ             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DOVER UNION FREE SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-05-02-02
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Dover Middle/High School:
09-1153   Reconstruction               0-001-013  04/30/10     DONE    DONE       DONE      03/26/10   03/22/10   09/23/08   05/20/08   4,7                      608,597       608,597  JOD             0           0     200,228 Morris Associates                       0      09/10/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-1469   Reconstruction               0-001-014  08/04/10     DONE    DONE       DONE      05/27/10   05/21/10   03/15/10   05/18/10   2,9,15,16                100,000       100,000  JOD             0           0           0 Morris Associates                       0      11/04/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0070   Reconstruction               0-001-015  04/02/14     DONE    DONE       DONE      07/23/13   07/18/13   04/02/13   02/12/13   2,8,155,15,16          2,178,636     2,178,636  MFS             0           0           0 ECG Engineering, LLC            2,178,636        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-016                                              /  /       /  /     07/16/14     /  /     155,16                         0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Wingdale Elementary:
08-1764   Reconstruction               0-003-006  07/22/09     DONE    DONE       DONE      06/30/09   06/24/09   03/02/09   05/19/09   15,16                    100,000       100,000  JOD             0           0           0 Rennia Engineering                      0      10/13/09                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0641   Reconstruction               0-003-007  04/17/12     DONE    DONE       DONE      01/11/12   01/09/12   10/18/11   05/17/11   8,10,15                  100,000       100,000  JOD             0           0           0 Rennia Engineering                      0      06/28/12                       08/30/12         YES
                                                                                                                                                                                                                                                                                                                                   
12-0343   Reconstruction               0-003-008  03/12/13     DONE    DONE       DONE      10/26/12   10/26/12   07/10/12   05/15/12   13,155,15                100,000       100,000  DDJ             0           0           0 Rennia Engineering                      0      06/30/13                       08/23/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-0071   Reconstruction               0-003-009  04/02/14     DONE    DONE       DONE      07/23/13   07/18/13   04/02/13   02/12/13   2,155,15,16              416,795       416,795  MFS             0           0           0 ECG Engineering, LLC              416,795        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Dover Elem. School:
13-0072   Reconstruction               0-004-009  04/02/14     DONE    DONE       DONE      07/23/13   07/18/13   04/02/13   02/12/13   2,155,16                 241,977       241,977  MFS             0           0           0 ECG Engineering, LLC              241,977        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Sewage Treatment Bldg. (see 7-007):
12-1322   New Construction             4-007-001  09/12/13     DONE    DONE       DONE      06/26/13   06/26/13   06/26/13   06/25/13   02 - 16                  481,550       481,550  MFS             0           0           0 Rennia Engineering                      0      04/21/14                       07/07/14         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HYDE PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-08-01-06
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Haviland Middle School(JrHigh):
09-1341   Reconstruction               0-001-021  06/01/10     DONE    DONE       DONE      04/20/10   04/19/10   02/05/10   12/13/07   2,9,16                    54,900        54,900  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
10-0805   Reconstruction               0-001-022  05/25/11     DONE    DONE       DONE      02/07/11   01/20/11   10/05/10   05/20/10   2,9                    1,173,768     1,173,768  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/10/14           
10-1035   Reconstruction               0-001-023  04/01/11     DONE    DONE       DONE      03/15/11   03/10/11   02/18/11   01/13/11   2,15,16                  114,000       114,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/21/14           
11-0962   Reconstruction               0-001-024  07/19/12     DONE    DONE       DONE      03/15/12   03/13/12   09/13/11   12/06/11   155,15,16                980,000       980,000  HCM             0           0           0 TEtra Tech Engineers, Archite           0      02/18/14                       03/10/14           
12-1056   Reconstruction               0-001-025  04/29/13     DONE    DONE       DONE      03/29/13   03/29/13   01/30/13   12/13/07   9,155,16                 395,000             0  JMB             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Roosevelt High School:
09-0172   Reconstruction               0-002-020  08/31/09     DONE    DONE       DONE      08/27/09   08/25/09   07/17/09   06/25/09   16                       100,000       100,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      06/14/10                         /  /             
09-1342   Reconstruction               0-002-021  06/01/10     DONE    DONE       DONE      04/20/10   04/19/10   02/12/10   12/13/07   2,9,13,16                148,210        72,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
10-0874   Reconstruction               0-002-022  04/20/11     DONE    DONE       DONE      02/18/11   01/06/11   02/17/11   12/13/07   2,9,16                   445,663       445,663  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
11-0963   Reconstruction               0-002-023  07/19/12     DONE    DONE       DONE      03/15/12   03/13/12   09/13/11   12/06/11   2,15,16                1,680,000     1,680,000  HCM             0           0           0 TEtra Tech Engineers, Archite           0      02/18/14                       03/10/14           
12-0013   Reconstruction               0-002-024  11/14/12     DONE    DONE       DONE      07/09/12   07/06/12   05/04/12   03/20/12   2,4,10,15,16           4,563,500     4,563,500  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/07/14                       05/02/14           
  -       Reconstruction               0-002-025                                              /  /       /  /     05/07/12     /  /     2,4,10,15,16                   0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Ralph R. Smith Elementary:
10-0875   Reconstruction               0-003-018  04/20/11     DONE    DONE       DONE      02/18/11   01/06/11   03/25/10   12/13/07   2,9                      180,988       180,988  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
10-1036   Reconstruction               0-003-019  04/01/11     DONE    DONE       DONE      03/15/11   03/10/11   02/18/11   01/13/11   2,15,16                  114,000       114,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/10/14           
11-0964   Reconstruction               0-003-020  07/19/12     DONE    DONE       DONE      03/15/12   03/13/12   09/13/11   12/06/11   155,15,16                715,000       715,000  HCM             0           0           0 TEtra Tech Engineers, Archite           0      02/18/14                       03/10/14           

          Violet Avenue Elementary:
09-1343   Reconstruction               0-004-017  06/01/10     DONE    DONE       DONE      04/20/10   04/19/10   03/25/10   12/13/07   2,9                       29,591       107,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
11-0965   Reconstruction               0-004-018  07/19/12     DONE    DONE       DONE      03/15/12   03/13/12   09/13/11   12/06/11   155,15,16                806,025       806,025  HCM             0           0           0 TEtra Tech Engineers, Archite           0      02/18/14                       03/10/14           

          Hyde Park Elementary:
09-1344   Reconstruction               0-005-022  06/01/10     DONE    DONE       DONE      04/20/10   04/19/10   03/25/10   12/13/07   2                         15,809       106,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
11-0966   Reconstruction               0-005-023  07/19/12     DONE    DONE       DONE      03/15/12   03/13/12   09/13/11   12/06/11   155,15,16                853,975       853,975  HCM             0           0           0 TEtra Tech Engineers, Archite           0      02/18/14                       03/10/14           

          Netherwood Elementary School:
10-0876   Reconstruction               0-007-018  04/20/11     DONE    DONE       DONE      02/18/11   01/06/11   03/25/10   12/13/07   2                        159,563       159,563  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
10-1037   Reconstruction               0-007-019  04/01/11     DONE    DONE       DONE      03/15/11   03/10/11   02/18/11   01/13/11   2,15,16                  114,000       114,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/10/14           
  -       Reconstruction               0-007-020                                              /  /       /  /     09/13/11     /  /     155,15,16                      0             0  HCM             0           0           0                                         0        /  /                           /  /             

          North Park Elementary School:
09-1345   Reconstruction               0-013-019  06/01/10     DONE    DONE       DONE      04/20/10   04/19/10   02/05/10   12/13/07   2,9,16                   245,780       487,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/30/14                       05/20/14           
10-0462   Reconstruction               0-013-020  02/16/11     DONE    DONE       DONE      11/12/10   11/09/10   10/05/10   05/18/10   2,9                    1,620,000     1,254,540  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/10/14           
10-1038   Reconstruction               0-013-021  04/01/11     DONE    DONE       DONE      03/15/11   03/10/11   02/18/11   01/13/11   2,15,16                  113,000       113,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/10/14           
11-0967   Reconstruction               0-013-022  07/19/12     DONE    DONE       DONE      03/15/12   03/13/12   09/13/11   12/06/11   155,15,16                440,000       440,000  HCM             0           0           0 TEtra Tech Engineers, Archite           0      02/18/14                       03/10/14           

          Bus Garage:
10-1039   Reconstruction               4-006-009  04/01/11     DONE    DONE       DONE      03/15/11   03/10/11   02/18/11   01/13/11   2,15,16                  200,000       200,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0      02/18/14                       03/10/14           

          Press Box:
12-0014   New Construction             7-018-001  11/14/12     DONE    DONE       DONE      07/09/12   07/06/12   05/16/12   03/20/12   02 - 16                   87,500             0  HCM             0           0           0 Tetra  Tech Architects & Engi           0      04/07/14                       05/02/14           

          District Wide:
13-0628   Reconstruction               7-999-002  04/04/14     DONE    DONE       DONE      10/25/13   10/23/13   08/27/13   12/13/07   13,16                    250,000             0  JMB             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHEAST (WEBUTUCK) CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-11-01-04
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Webutuck Jr/Sr High School:
09-0431   Reconstruction               0-002-014  11/20/09     DONE    DONE       DONE      11/18/09   11/12/09   02/04/09   02/02/09   13                       255,079       255,079  JOD             0           0      64,989 Rhinebeck Architecture                  0      04/13/10                       06/29/11           
12-1206   Reconstruction               0-002-015                       ADDENDUM REQ'D       05/17/13   05/17/13   10/25/12   04/01/13   10,155,16                      0    16,705,854  DDJ             0           0           0 New York Power Authority                0        /  /                           /  /             
13-1475   Reconstruction               0-002-016               STARTED STARTED    UNREVIEWED04/21/14   04/14/14   08/30/13   10/24/13   2,15,16                        0    16,705,854  JMB             0           0           0 Morris Associates                       0        /  /                           /  /             
  -       Reconstruction               0-002-017                                              /  /       /  /     05/21/14     /  /     15,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Webutuck Elementary School:
12-1207   Reconstruction               0-004-013                       ADDENDUM REQ'D       05/17/13   05/17/13   10/25/12   04/01/13   10,155,16                      0             0  DDJ             0           0           0 New York Power Authority                0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PAWLING CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-12-01-04
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pawling Elementary School:
09-0108   Reconstruction               0-001-018  08/11/09     DONE    DONE       DONE      08/10/09   08/07/09   07/17/09   05/19/09   2                          9,500             0  JOD             0           0           0 Kaeyer, Garment & Davidson              0      06/14/10                       12/18/12           
10-0889   Reconstruction               0-001-019  03/02/11     DONE    DONE       DONE      02/22/11   01/27/11   12/08/10   05/20/08   15,16                     30,000        30,000  JOD             0           0           0 Hahn Engineering                        0      12/17/12                       04/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-020                                              /  /       /  /     08/14/12     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0121   Reconstruction               0-001-021  08/30/12     DONE    DONE       DONE      08/21/12   08/18/12   08/21/12   05/15/12   16                       289,300       289,300  DDJ             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-1244   Reconstruction               0-001-022  11/21/13     DONE    DONE       DONE      06/05/13   05/31/13   04/11/13   12/18/12   4,9,10,155,15,16         811,200             0  JOB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Pawling High School:
09-1321   Reconstruction               0-002-014  06/15/10     DONE    DONE       DONE      04/16/10   04/12/10   03/03/10   05/19/09   16                        60,000        60,000  JOD             0           0           0 Kaeyer, Garment & Davidson              0      03/14/11                       12/18/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-1406   Reconstruction               0-002-015  11/13/12     DONE    DONE       DONE      06/14/12   06/13/12   12/16/11   05/17/12   4,7,8,9,155,15,16        265,000       265,000  JOD             0           0           0 Kaeyer, Garment & Davidson              0      07/24/13                       08/14/13           
13-0124   Reconstruction               0-002-016               STARTED DONE       DONE      ***ENROLLMENT PROJECTIONS INCOMPLETE/INCORRECT***                                        0  JOB             0           0           0 Hahn Engineering                        0        /  /                           /  /             
12-1245   Reconstruction               0-002-017  11/21/13     DONE    DONE       DONE      06/05/13   05/31/13   04/11/13   12/18/12   4,9,155,16               498,700             0  JOB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Pawling Middle School:
13-0125   Reconstruction               0-006-004               STARTED DONE       DONE      08/02/13   08/01/13   04/11/13     /  /     15,16                          0    12,649,804  JOB             0           0           0 Hahn Engineering                        0        /  /                           /  /             
12-1246   Reconstruction               0-006-005  11/21/13     DONE    DONE       DONE      06/05/13   05/31/13   04/11/13   12/18/12   155,16                    92,000             0  JOB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Pawling Central School District    ,:
  -    TQ Temporary Quarters           1-012-001                                              /  /       /  /     11/10/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Leased Bus Garage:
13-1339   Reconstruction               5-009-L02  03/12/14     DONE    DONE       DONE      03/12/14   03/12/14     /  /       /  /                              690,000       690,000  JMB             0           0           0                                         0        /  /                           /  /             

          New Transportation Facility:
12-1249   New Construction             5-013-001  12/26/13     DONE    DONE       DONE      06/05/13   05/31/13   04/12/13   12/18/12   02 - 16                4,087,000             0  JOB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PINE PLAINS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-13-01-04
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Seymour Smith School:
09-0666   Reconstruction               0-001-011  03/30/10     DONE    DONE       DONE      12/30/09   12/18/09   08/11/05   05/19/08                          3,849,000     3,849,000  HCM             0           0     427,493 Mosaic Associates                       0      10/12/11                         /  /             
09-1081   Reconstruction               0-001-013  08/18/08     DONE    DONE       DONE      03/16/10   12/18/09   08/22/08   08/27/08   2,4,7,8,10,16            131,785       131,785  HCM             0           0           0 Mosaic Associates                       0      10/12/11                         /  /             

          Storage Shed @ Cold Springs:
12-1190DB Discovered Building          2-012-001  06/19/13     DONE    DONE       DONE      05/14/13   05/14/13   05/14/13     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




POUGHKEEPSIE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-15-00-01
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Columbus School #3:
10-0890   Reconstruction               0-001-010  09/16/11     DONE    DONE       DONE      02/23/11   02/16/11   07/22/09   11/18/09   2,4,8,9,155,15,16        362,229       362,229  JOD             0           0           0 Cannon Design                           0      02/28/13                       04/15/13           
10-0333   Reconstruction               0-001-011  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16           184,212       184,212  JOD             0           0           0 Cannon Design                     184,212        /  /                           /  /             

          SFB Morse School #5:
10-0891   Reconstruction               0-002-010  08/23/11     DONE    DONE       DONE      02/23/11   02/16/11   07/22/09   11/18/09   2,4,7,8,9,155,15,16      873,627       873,627  JOD             0           0     194,819 Cannon Design                           0      02/28/13                       04/15/13           
10-0334   Reconstruction               0-002-011  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16           346,649       346,649  JOD             0           0      77,303 Cannon Design                     269,346        /  /                           /  /             

          Gov. Clinton School #8:
10-0892   Reconstruction               0-004-010  09/16/11     DONE    DONE       DONE      02/23/11   02/16/11   07/22/09   11/18/09   2,4,7,8,9,155,15,16    1,502,441     1,502,441  JOD             0           0     335,044 Cannon Design                           0      02/28/13                       04/15/13           
10-0335   Reconstruction               0-004-011  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16           244,376       244,376  JOD             0           0      54,496 Cannon Design                     189,880        /  /                           /  /             
13-0214   Reconstruction               0-004-012  05/15/14     DONE    DONE       DONE      08/15/13   08/08/13   11/20/12   11/18/09   2,9,15                   152,500             0  DDJ             0           0      32,787 Cannon Design                           0        /  /                           /  /             

          C.B. Warring School #10:
10-0336   Reconstruction               0-005-010  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16           295,992       295,992  JOD             0           0      66,006 Cannon Design                     229,986        /  /                           /  /             
10-0893   Reconstruction               0-005-011  09/16/11     DONE    DONE       DONE      02/23/11   02/16/11   02/25/10   11/18/09   2,8,9,155,15,16          511,218       511,218  JOD             0           0     114,002 Cannon Design                           0      02/28/13                       04/15/13           
13-0215   Reconstruction               0-005-012  05/15/14     DONE    DONE       DONE      08/15/13   08/08/13   03/05/13   11/18/09   2,155,15,16              152,500             0  JOB             0           0      32,787 Cannon Design                           0        /  /                           /  /             

          Krieger School No. 11:
10-0894   Reconstruction               0-006-010  08/23/11     DONE    DONE       DONE      02/23/11   02/16/11   07/22/09   11/18/09   2,4,8,155,15,16          559,163       559,163  JOD             0           0     124,693 Cannon Design                           0      02/28/13                       04/15/13           
10-0337   Reconstruction               0-006-012  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16           382,254       382,254  JOD             0           0      85,242 Cannon Design                     297,012        /  /                           /  /             
13-0216   Reconstruction               0-006-013  05/15/14     DONE    DONE       DONE      08/15/13   08/08/13   03/05/13   11/18/09   2,155,15,16              152,500             0  JOB             0           0      32,787 Cannon Design                           0        /  /                           /  /             

          Junior/Senior High School:
10-0895   Reconstruction               0-007-013  07/25/11     DONE    DONE       DONE      02/23/11   02/16/11   07/22/09   11/18/09   2,7,8,9,10,155,15,16   4,362,068        50,000  JOD             0           0           0 Cannon Design                           0      02/28/13                       04/15/13           
10-0338   Reconstruction               0-007-014  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16         1,053,138     1,053,138  JOD             0           0      24,054 Cannon Design                   1,029,084        /  /                           /  /             
10-0896   Reconstruction               0-007-015  09/16/11     DONE    DONE       DONE      02/23/11   02/16/11   12/20/10   11/18/09   2,16                   2,009,300     2,009,300  JOD             0           0     448,074 Cannon Design                           0      02/28/13                       04/15/13           
11-1400   Reconstruction               0-007-016  06/21/11     DONE    DONE       DONE      06/12/12   06/11/12   07/08/11   06/22/11   2                         99,000        99,000  JOD             0           0           0 Cannon Design                           0      06/25/12                       02/15/13           
13-0217   Reconstruction               0-007-017  05/15/14     DONE    DONE       DONE      08/15/13   08/08/13     /  /     11/18/09   2,4,7,9,15               866,883             0  DDJ             0           0     186,379 Cannon Design                           0        /  /                           /  /             

          W.W. Smith Elementary:
13-0218   Reconstruction               0-008-015  05/15/14     DONE    DONE       DONE      08/15/13   08/08/13   07/22/09   11/18/09   2,4,7,8,9,155,15,16    1,034,552     1,034,552  JOD             0           0     222,428 Cannon Design                           0        /  /                           /  /             
10-0339XX Reconstruction               0-008-016  06/27/11               CANCELLED          10/06/10   10/01/10   02/22/10   11/18/09   2,13,155,15,16           252,448       252,448  JOD             0           0           0 Cannon Design                     252,448        /  /                           /  /             
13-1535   Reconstruction               0-008-017                       ADDENDUM REQ'D       05/14/14   05/14/14   10/18/13   11/19/09   2,7,8,155,15,16                0     4,836,356  JMB             0           0           0 Cannon Design                           0        /  /                           /  /             

          Middle School:
10-0897   Reconstruction               0-015-015  07/25/11     DONE    DONE       DONE      02/23/11   02/16/11   07/22/09   11/18/09   2,7,8,9,10,155,15,16   3,062,886     3,062,886  JOD             0           0     683,024 Cannon Design                           0      02/28/13                       04/15/13           
10-0340   Reconstruction               0-015-016  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,8,13,155,15,16       2,483,758     2,483,758  JOD             0           0     553,878 Cannon Design                   1,929,880        /  /                           /  /             

          Administration Building:
10-0341   Reconstruction               1-003-004  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,15,16                65,143             0  JOD             0           0           0 Cannon Design                      65,143        /  /                           /  /             

          HS Athl Field Stg/Toilet Facility:
10-0898PR New Construction             2-022-001  09/16/11     DONE    DONE       DONE      02/23/11   02/16/11   12/02/10   11/18/09   02 - 16                  272,159             0  JOD             0           0           0 Cannon Design                           0      09/14/12                       04/03/13           

          Bus Garage Shops:
10-0342   Reconstruction               5-009-002  06/27/11     DONE    DONE       DONE      10/06/10   10/01/10   02/22/10   11/18/09   2,13,16                   31,036             0  JOD             0           0           0 Cannon Design                      31,036        /  /                           /  /             

          High School - Press Box:
10-0899PR New Construction             7-021-001  09/16/11     DONE    DONE       DONE      02/23/11   02/16/11   11/22/10   11/18/09   02 - 16                   77,759             0  JOD             0           0           0 Cannon Design                           0      09/14/12                       04/03/13           

          Concession Building @ HS:
13-0219   New Construction             7-023-001  05/15/14     DONE    DONE       DONE      08/15/13   08/08/13     /  /     11/18/09   02 - 16                  628,275             0  DDJ             0           0           0 Cannon Design                           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ARLINGTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-16-01-06
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Arlington Middle School:
  -       Reconstruction               0-002-013                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Overlook Elementary School:
  -       Reconstruction               0-004-011                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Beekman Elementary School:
10-0208   Reconstruction               0-006-010  12/13/10     DONE    DONE       DONE      09/14/10   09/07/10   08/06/10   03/09/10   155,16                    96,560       221,000  HCM             0           0           0 Savin Engineers, P.C.                   0      11/27/12                       02/11/13           
  -    PR Additions and Alterations    0-006-011                                              /  /       /  /     06/30/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-006-012                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Traver Road Primary:
10-0207   Reconstruction               0-007-011  09/14/10     DONE    DONE       DONE      09/14/10   09/07/10   08/06/10   03/09/10   10,155,15,16             327,819       598,000  HCM             0           0           0 Savin Engineers, P.C.                   0      11/27/12                       02/11/13           
  -       Reconstruction               0-007-012                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          North Campus HS:
09-1450   Alterations                  0-008-011  08/05/10     DONE    DONE       DONE      05/20/10   05/14/10   07/27/07   11/01/09   02 - 16                  239,625       239,625  HCM             0           0           0 Mosaic Associates                       0      09/15/11                       04/23/14           
12-0043   Reconstruction               0-008-012  10/19/12     DONE    DONE       DONE      07/20/12   07/20/12   09/03/08   04/27/10   7,10                     108,000       108,000  HCM             0           0           0 Mosaic Associates                       0      02/19/14                       04/23/14           
  -       Reconstruction               0-008-013                                              /  /       /  /     07/16/14     /  /     2,8,9                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          LaGrange MS(fmlySouth Campus):
  -       Reconstruction               0-009-007                                              /  /       /  /     07/16/14     /  /     2,8,9                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Titusville Elementary School:
  -       Reconstruction               0-010-009                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          West Road Elem. School:
13-1536   Reconstruction               0-012-007  06/11/14     DONE    DONE       DONE      05/14/14   05/14/14   02/06/14   05/20/14   2,9                       49,500        49,500  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
  -       Reconstruction               0-012-008                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Noxon Road Elem. School:
13-1537   Reconstruction               0-013-004  06/11/14     DONE    DONE       DONE      05/14/14   05/14/14   02/06/14   05/20/14   2,9                      100,500       100,500  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
  -       Reconstruction               0-013-005                                              /  /       /  /     07/16/14     /  /     2,8,9                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Union Vale Middle School:
  -       Reconstruction               0-036-002                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Vail Parm Elementary School:
  -       Reconstruction               0-037-002                                              /  /       /  /     07/16/14     /  /     8,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Storage/Pump House (West Rd):
  -       Reconstruction               2-020-001                                              /  /       /  /     07/16/14     /  /     2,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Storage House #22:
  -       Reconstruction               2-022-001                                              /  /       /  /     07/16/14     /  /     2,9                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Admiral Moving & Storage:
09-1206   Reconstruction               5-039-L01  06/02/10     DONE    DONE       DONE      04/02/10   03/05/10   03/24/10   11/24/09                            309,900       309,900  HCM             0           0           0 MAURI ASSOCIATES                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SPACKENKILL UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-16-02-02
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Martha W. Lawrence Elementary:
13-0992   Reconstruction               0-001-006  04/24/14     DONE    DONE       DONE      01/09/14   01/08/14   11/01/13   05/21/13   2                        100,000             0  MFS             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          Todd Junior High School:
09-0913   Reconstruction               0-002-012  03/17/10     DONE    DONE       DONE      02/19/10   02/16/10   01/07/10   05/19/09   10                       100,000       100,000  JOD             0           0           0 Clark Patterson Lee                     0      08/27/10                         /  /             
11-1313   Reconstruction               0-002-013  06/06/12     DONE    DONE       DONE      05/22/12   05/16/12   03/21/12   05/17/11   155,16                   100,000       100,000  JOD             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
12-1316   Reconstruction               0-002-014  03/26/14     DONE    DONE       DONE      06/26/13   06/24/13   01/24/13   02/26/13   2,155,15,16            1,031,596       810,387  MFS             0           0           0 ECG Engineering, LLC            1,031,596        /  /                           /  /             

          Nassau Road Elementary:
12-1317   Reconstruction               0-003-010  03/26/14     DONE    DONE       DONE      06/26/13   06/24/13   01/24/13   02/26/13   2,155,15,16              909,500       909,500  MFS             0           0           0 ECG Engineering, LLC              909,500        /  /                           /  /             

          Hagan Elementary School:
12-0416   Reconstruction               0-004-012  02/27/13     DONE    DONE       DONE      11/14/12   11/14/12   07/31/12   08/27/12   2,10                     100,000             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
12-1318   Reconstruction               0-004-013  03/26/14     DONE    DONE       DONE      06/26/13   06/24/13   01/24/13   02/26/13   2,155,16                 649,073       649,073  MFS             0           0           0 ECG Engineering, LLC              649,073        /  /                           /  /             

          Spackenkill High School:
09-0376   Additions and Alterations    0-005-016  02/19/10     DONE    DONE       DONE      10/30/09   10/29/09   09/24/08   02/17/09   02 - 16               10,745,159    13,934,000  JOD             0           0     585,159 Clark Patterson Lee                     0      11/08/10           YES           /  /             
12-1319   Reconstruction               0-005-017  03/26/14     DONE    DONE       DONE      06/26/13   06/24/13   01/24/13   02/26/13   2,155,15,16              395,932       395,932  MFS             0           0           0 ECG Engineering, LLC              395,932        /  /                           /  /             

          Portable-Todd Middle School:
12-1320   Reconstruction               0-008-002  03/26/14     DONE    DONE       DONE      06/26/13   06/24/13   02/01/13   02/26/13   16                         6,954             0  MFS             0           0           0 ECG Engineering, LLC                6,954        /  /                           /  /             

          Dugout/Storage:
11-0999   New Construction             2-010-001  04/10/12     DONE    DONE       DONE      03/21/12   03/21/12   03/21/12     /  /     02 - 16                        0             0  JOD             0           0           0 D. Freeman Architect                    0        /  /                           /  /             

          Bus Storage Garage:
12-1321   Reconstruction               4-007-003  03/26/14     DONE    DONE       DONE      06/26/13   06/24/13   01/24/13   02/26/13   16                         7,588             0  MFS             0           0           0 ECG Engineering, LLC                7,588        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RED HOOK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-17-01-06
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
09-0294XX Additions and Alterations    0-005-008                         CANCELLED          10/09/09   10/05/09   10/05/09     /  /     02 - 16                        0             0  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /                           /  /             

          Mill Rd. Elementary:
13-0609   Reconstruction               0-006-008  06/05/14     DONE    DONE       DONE      10/23/13   10/18/13   09/19/13   05/21/13   2,8,9,155,16           5,649,219             0  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /                           /  /             

          Linden Ave Bus Garage:
09-1011   Reconstruction               5-007-006  03/15/10     DONE    DONE       DONE      03/03/10   03/01/10   02/05/10   05/15/09   2,4,7,9,15,16            100,000       100,000  DDJ             0           0           0 TEtra Tech Engineers, Archite           0      06/28/10                         /  /             

          DISTRICT WIDE:
13-0824   Reconstruction               7-999-001  03/19/14     DONE    DONE       DONE      12/04/13   11/27/13   09/19/13   05/21/13   16                     1,850,781             0  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WAPPINGERS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-21-01-06
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Fishkill Plains Elementary:
11-0365   Reconstruction               0-001-012  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              280,713       280,713  HCM             0           0           0 ECG Engineering, LLC              280,713      11/29/13                       12/11/13           
13-0842   Reconstruction               0-001-013  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,   1,123,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0855   Reconstruction               0-001-014  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     142,839             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1132   Reconstruction               0-001-015               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/27/13   05/21/13   2,8,9,155,16                   0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Kinry Road Elementary:
11-0366   Reconstruction               0-002-014  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,8,155,15,16             39,132        39,132  HCM             0           0           0 ECG Engineering, LLC               39,132      11/29/13                       12/11/13           
13-0843   Reconstruction               0-002-015  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,     102,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0856   Reconstruction               0-002-016  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     160,311             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1133   Reconstruction               0-002-017               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,7,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Evans Elementary School:
11-0367   Reconstruction               0-003-018  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              294,504       294,504  HCM             0           0           0 ECG Engineering, LLC              294,504      11/29/13                       12/11/13           
12-1296   Reconstruction               0-003-019  06/18/13     DONE    DONE       DONE      06/18/13   06/18/13   04/23/13   05/21/13   2,10                     214,532       214,532  MFS             0           0           0 Rhinebeck Architecture                  0      01/27/14                       02/13/14           
12-1274   Reconstruction               0-003-020  06/19/13     DONE    DONE       DONE      06/11/13   06/11/13   04/23/13   05/21/13   2,4,8,9,10,155,15,16      45,000        45,000  MFS             0           0           0 Rhinebeck Architecture                  0      01/03/14                       02/03/14           
13-0844   Reconstruction               0-003-021  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,     539,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0857   Reconstruction               0-003-022  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     171,506             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1134   Reconstruction               0-003-023               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,7,8,9,155,16               0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Junior High School:
  -       Reconstruction               0-004-026                                              /  /       /  /     11/25/09     /  /     4,8,9                          0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0368   Reconstruction               0-004-027  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              584,860       584,860  HCM             0           0           0 ECG Engineering, LLC              584,860      11/29/13                       12/11/13           
  -       Reconstruction               0-004-028                                              /  /       /  /     07/15/13     /  /     2,4,7,8,9,14,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0858   Reconstruction               0-004-029  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     287,403             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1135   Reconstruction               0-004-030               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,8,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Fishkill Elementary School:
11-0369   Reconstruction               0-005-014  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              825,839       825,839  HCM             0           0           0 ECG Engineering, LLC              825,839      11/29/13                       12/11/13           
13-0845   Reconstruction               0-005-015  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,     794,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0859   Reconstruction               0-005-016  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     166,488             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1136   Reconstruction               0-005-017               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   8,16                           0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Vassar Road Elementary:
11-0370   Reconstruction               0-008-019  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              191,008       191,008  HCM             0           0           0 ECG Engineering, LLC              191,008      11/29/13                       12/11/13           
13-0846   Reconstruction               0-008-020  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,     795,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0860   Reconstruction               0-008-021  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     154,535             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1137   Reconstruction               0-008-022               STARTED ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,7,8,9,155,16               0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Ketcham Senior High School:
  -       Reconstruction               0-012-024                                              /  /       /  /     11/25/09     /  /     2,4,8,9,16                     0             0  HCM             0           0           0                                         0        /  /                           /  /             
09-1116XX Reconstruction               0-012-025  10/25/10               CANCELLED          03/23/10   03/23/10   03/23/10   05/15/07   16                       100,000       100,000  HCM             0           0      42,000 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-012-026                                              /  /       /  /     04/02/10     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0371   Reconstruction               0-012-027  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              455,967       455,967  HCM             0           0           0 ECG Engineering, LLC              455,967      11/29/13                       12/11/13           
13-0847   Reconstruction               0-012-028  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,   6,783,500             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0861   Reconstruction               0-012-029  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     493,687             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1138   Reconstruction               0-012-030               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,8,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Brinckerhoff Elementary:
11-0372   Reconstruction               0-013-018  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,16                 318,835       318,835  HCM             0           0           0 ECG Engineering, LLC              318,835      11/29/13                       12/11/13           
13-0848   Reconstruction               0-013-019  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,      72,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0862   Reconstruction               0-013-020  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     189,976             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1139   Reconstruction               0-013-021               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,9,155,16                     0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Oak Grove Elementary:
11-0373   Reconstruction               0-014-017  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              256,074       256,074  HCM             0           0           0 ECG Engineering, LLC              256,074      11/29/13                       12/11/13           
13-0849   Reconstruction               0-014-018  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,     728,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0863   Reconstruction               0-014-019  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     177,906             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1140   Reconstruction               0-014-020               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,8,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Gayhead Elementary:
11-0374   Reconstruction               0-016-017  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              470,568       470,568  HCM             0           0           0 ECG Engineering, LLC              470,568      11/29/13                       12/11/13           
12-1275   Reconstruction               0-016-018  06/18/13     DONE    DONE       DONE      06/12/13   06/11/13   08/16/11   03/27/13   13,15                    103,300       103,300  MFS             0           0           0 Fellenzer Engineering                   0      10/18/13                       12/24/13           
  -       Reconstruction               0-016-019                                              /  /       /  /     07/15/13     /  /     2,4,7,8,9,14,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0864   Reconstruction               0-016-020  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     280,954             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1141   Reconstruction               0-016-021               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,8,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Van Wyck Junior High School:
  -       Reconstruction               0-017-019                                              /  /       /  /     11/25/09     /  /     4,8,9                          0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-0375   Reconstruction               0-017-020  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16            2,253,115     2,253,115  HCM             0           0           0 ECG Engineering, LLC            2,253,115      11/29/13                       12/11/13           
13-0850   Reconstruction               0-017-021  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,   4,700,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0865   Reconstruction               0-017-022  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     323,196             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1129   Reconstruction               0-017-023  02/24/14     DONE    DONE       DONE      01/29/14   01/29/14   12/03/13   02/10/14   4,13                     100,000             0  MFS             0           0           0 Fellenzer Engineering                   0        /  /                           /  /             
13-1142   Reconstruction               0-017-024               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,8,155,16                     0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Sheafe Road Elementary:
11-0376   Reconstruction               0-018-013  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              287,110       287,110  HCM             0           0           0 ECG Engineering, LLC              287,110      11/29/13                       12/11/13           
  -       Reconstruction               0-018-014                                              /  /       /  /     07/15/13     /  /     2,4,7,8,9,14,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0866   Reconstruction               0-018-015  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     182,286             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1143   Reconstruction               0-018-016               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,8,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Myers Corners Elementary:
11-0377   Reconstruction               0-019-017  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16              118,781       101,278  HCM             0           0           0 ECG Engineering, LLC              118,781      11/29/13                       12/11/13           
13-0851   Reconstruction               0-019-018  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,     195,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0867   Reconstruction               0-019-019  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     228,194             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1144   Reconstruction               0-019-020               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   4,8,9,155,16                   0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          John Jay High School:
11-0378   Reconstruction               0-020-028  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16            2,085,805     2,085,805  HCM             0           0           0 ECG Engineering, LLC            2,085,805      11/29/13                       12/11/13           
13-0852   Reconstruction               0-020-029  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,14,155,15,   1,297,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-0868   Reconstruction               0-020-030  04/04/14     DONE    DONE       DONE      12/09/13   12/06/13   07/15/13   05/21/13   2,4,7,8,9,10,14,155,     540,719             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
13-1145   Reconstruction               0-020-031               DONE    ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   2,4,8,9,155,16                 0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          New Admin Building:
  -    XX New Construction             1-049-001                         CANCELLED            /  /       /  /     05/23/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Central Warehouse:
11-0015   Reconstruction               3-015-005  08/25/11     DONE    DONE       DONE      07/11/11   07/11/11   03/25/11   04/19/11   2,16                      16,500             0  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
11-0379   Reconstruction               3-015-006  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16               61,712             0  HCM             0           0           0 ECG Engineering, LLC               61,712      11/29/13                       12/11/13           

          Bus Garage:
  -    XX Reconstruction               4-009-001                         CANCELLED            /  /       /  /     05/23/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Main Garage #1:
11-0380   Reconstruction               5-007-006  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16                7,359             0  HCM             0           0           0 ECG Engineering, LLC                7,359      11/29/13                       12/11/13           

          Main Garage #2:
11-0381   Reconstruction               5-011-004  06/29/12     DONE    DONE       DONE      11/09/11   11/02/11   05/19/11   07/25/11   2,155,15,16                9,252             0  HCM             0           0           0 ECG Engineering, LLC                9,252      11/29/13                       12/11/13           
13-0853   Reconstruction               5-011-005  04/03/14     DONE    DONE       DONE      12/09/13   12/06/13   07/16/13   05/21/13   2,4,7,8,9,14,155,15,     221,000             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             
  -       Reconstruction               5-011-006                                              /  /       /  /       /  /       /  /     2,7,8,155,16                   0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Fishkill Plains Bus Garage:
13-1146   New Construction             5-047-001               STARTED ADD. REQ'D STARTED   01/29/14   01/29/14   07/16/13   05/21/13   02 - 16                        0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          160 Airport Drive:
09-1278TQ Temporary Quarters           5-048-001  04/22/10     DONE    DONE       DONE      04/12/10   04/09/10   04/09/10     /  /                                    0             0  HCM             0           0           0 ADONI ENGINEERING                       0        /  /                           /  /             

          new bus garage:
  -       New Construction             5-050-001                                              /  /       /  /     05/23/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Transportation Driver Check-In Bldg:
13-1147   New Construction             7-051-001               STARTED ADD. REQ'D STARTED   01/29/14   01/29/14   12/17/13   05/21/13   02 - 16                        0             0  MFS             0           0           0 Rhinebeck Architecture                  0        /  /                           /  /             

          Orchard View School & Administration:
05-0225TQ Temporary Quarters           8-044-001  08/25/10     DONE    DONE       DONE      09/28/05   09/21/05   05/26/05     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MILLBROOK CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-22-01-04
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Millbrook Middle School:
08-1066   Reconstruction               0-008-009  03/24/10     DONE    DONE       DONE      01/08/09   01/06/08   08/11/08   07/01/08   2,8,155,15,16            723,947       723,947  HCM             0           0           0 ECG Engineering, LLC              723,947      11/30/11                         /  /             
11-1007   Reconstruction               0-008-010  07/23/12     DONE    DONE       DONE      03/23/12   03/16/12   10/05/11   12/06/11   2,13,16                3,487,580     3,487,580  HCM             0           0           0 Mosaic Associates                       0        /  /                           /  /             
11-1334   Reconstruction               0-008-011  10/12/12     DONE    DONE       DONE      05/24/12   05/18/12   01/25/12   12/06/11   2,10,15,16             3,829,500             0  HCM             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-008-012                                              /  /       /  /     01/25/12     /  /     155,15,16                      0    11,863,226  HCM             0           0           0                                         0        /  /                           /  /             

          Elm Drive Elementary School:
08-1067   Reconstruction               0-010-011  03/24/10     DONE    DONE       DONE      01/08/09   01/06/09   08/11/08   07/01/08   2,8,155,15,16            323,478       323,478  HCM             0           0           0 ECG Engineering, LLC              323,478      11/30/11                         /  /             
11-1009   Reconstruction               0-010-012  04/18/12     DONE    DONE       DONE      03/23/12   03/16/12   10/05/11   12/06/11   7                        662,000       662,000  HCM             0           0           0 Mosaic Associates                       0      09/04/12                       12/05/13           
  -       Reconstruction               0-010-013                                              /  /       /  /     01/25/12     /  /     7                              0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Alden Place Elementary:
08-1068   Reconstruction               0-011-010  03/24/10     DONE    DONE       DONE      01/08/09   01/06/09   08/11/08   07/01/08   2,8,155,15,16            843,296       843,296  HCM             0           0           0 ECG Engineering, LLC              843,296      11/30/11                         /  /             
11-1010   Reconstruction               0-011-011  04/18/12     DONE    DONE       DONE      03/23/12   03/16/12   10/05/11   12/06/11   7,155                    813,000       813,000  HCM             0           0           0 Mosaic Associates                       0      09/04/12                       12/05/13           
11-1011   Reconstruction               0-011-012  07/31/12     DONE    DONE       DONE      03/23/12   03/16/12   01/25/12   12/06/11   15,16                    325,000       325,000  HCM             0           0           0 Mosaic Associates                       0        /  /                           /  /             
11-1326   Reconstruction               0-011-013  10/03/12     DONE    DONE       DONE      05/21/12   05/18/12   01/25/12   12/06/11   155,16                   782,000             0  HCM             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-011-014                                              /  /       /  /     01/25/12     /  /     155,15,16                      0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Millbrook High School:
12-0080   Reconstruction               0-031-002  08/02/12     DONE    DONE       DONE      08/02/12   07/27/12   05/02/12   12/06/11   2,16                     750,000       750,000  HCM             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Press Box:
11-1008   New Construction             7-032-001  07/23/12     DONE    DONE       DONE      03/23/12   03/16/12   01/26/12   12/06/11   02 - 16                   40,000             0  HCM             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Concession Stand:
  -       New Construction             7-033-001                                              /  /       /  /     01/26/12     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES DUTCHESS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-90-00-00
last updated on 07/22/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Salt Point Center(frmly Spec ed ctr):
11-1300   Reconstruction               0-001-025  05/18/12     DONE    DONE       DONE      05/14/12   05/09/12   11/03/11   02/08/12   155,15,16                115,000       115,000  JOD             0           0           0 Kaeyer, Garment & Davidson              0      05/20/13                       10/24/13           
13-1506   Reconstruction               0-001-026                         UNREVIEWED         05/07/14   04/25/14   04/01/14   03/12/14   155,16                         0             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Area Occupational Center:
11-0415   Reconstruction               0-003-023  12/16/11     DONE    DONE       DONE      11/18/11   11/18/11   10/06/11   11/09/11   2,4,7                  2,600,260     2,600,260  JOD             0           0           0 Kaeyer, Garment & Davidson              0      11/28/12                       03/25/13           
11-1301   Reconstruction               0-003-024  05/18/12     DONE    DONE       DONE      05/14/12   05/09/12   04/19/12   02/08/12   15,16                     19,955        19,955  JOD             0           0           0 Kaeyer, Garment & Davidson              0      07/30/13                       10/24/13           
13-0762   Reconstruction               0-003-025  04/14/14     DONE    DONE       DONE      11/25/13   11/21/13   04/02/13   06/12/13   10,16                    350,000             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Administration Bldg.:
12-1001   Reconstruction               1-002-012  04/18/13     DONE    DONE       DONE      03/20/13   03/20/13   11/21/12   02/13/12   2,4,7                    283,000             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0      09/19/13                       12/20/13           

          Storage Shed:
  -       New Construction             2-045-001                                              /  /       /  /     04/05/12     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Districtwide:
13-1170   Reconstruction               7-999-001  04/14/14     DONE    DONE       DONE      02/03/14   01/31/14   11/26/13   01/08/14   16                       120,045             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          1 Civic Center:
10-1041TQ Temporary Quarters           8-043-001  05/04/11     DONE    DONE       DONE      03/11/11   03/04/11   02/25/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          BOCES Educ & Training Acad:
11-0269TQ Temporary Quarters           8-044-001  07/27/12     DONE    DONE       DONE      10/20/11   10/19/11   08/23/11     /  /                                    0             0  JOD             0           0           0 Chazen Engineering & Land Sur           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED