Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/18/24 at 07:18:43




BEACON CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-02-00-01
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          James Forrestal School:
21-1356   Reconstruction               0-002-020  05/17/22     DONE    DONE       DONE      02/23/22   02/18/22   11/19/21   10/26/21   2,8,9,155,16             835,550       835,550  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         02/18/22           
22-0994   Reconstruction               0-002-021  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   01/19/22   10/26/21   2,155,15,16            1,897,450     1,897,450  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           

          South Ave Elementary School:
22-0995   Reconstruction               0-003-016  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   01/19/22   10/26/21   2,4,7,8,9,155,15,16    1,560,000     1,560,000  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           
23-1641   Reconstruction               0-003-017                         UNREVIEWED         03/15/24   03/15/24   03/01/24   02/26/24   9,16                     300,000       300,000  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         03/15/24           

          Rombout Middle School:
21-1304   Reconstruction               0-004-021  05/10/22     DONE    DONE       DONE      02/16/22   02/10/22   10/28/21   10/26/21   7                      2,706,850     2,706,850  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         02/10/22           
21-1357   Reconstruction               0-004-022  05/17/22     DONE    DONE       DONE      02/23/22   02/18/22   11/19/21   10/26/21   2,16                   1,800,300     1,800,300  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         02/18/22           
22-0996   Reconstruction               0-004-023  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   01/19/22   10/26/21   2,4,8,9,155,15,16      3,981,850     3,981,850  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           

          Glenham Elementary School:
21-1358   Reconstruction               0-006-021  05/17/22     DONE    DONE       DONE      02/23/22   02/18/22   11/19/21   10/26/21   2,155,16                 436,500       436,500  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         02/18/22           
  -    PR Additions and Alterations    0-006-022                                              /  /       /  /     01/19/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0997   Additions and Alterations    0-006-022  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   01/19/22   10/26/21   02 - 16                3,003,000     3,002,000  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           

          Sargent Elementary School:
21-1359   Reconstruction               0-008-019  05/17/22     DONE    DONE       DONE      02/23/22   02/18/22   11/19/21   10/26/21   2,9,155,16             1,183,200     1,183,200  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         02/18/22           
22-0998   Reconstruction               0-008-020  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   01/19/22   10/26/21   2,4,8,9,155,15,16      1,427,800     1,427,800  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           

          Beacon High School:
19-1835   Reconstruction               0-020-010  06/22/20     DONE    DONE       DONE      06/10/20   06/05/20   04/30/20   04/28/20   7                      2,970,000     2,970,000  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         06/05/20           
21-1305   Reconstruction               0-020-011  05/10/22     DONE    DONE       DONE      02/16/22   02/10/22   10/28/21   10/26/21   7                      1,309,800     1,309,800  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         02/10/22           
22-0999   Reconstruction               0-020-012  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   01/19/22   10/26/21   2,8,9,155,15,16        3,693,700     3,693,700  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           

          New Bus Maintenance/Storage:
  -    PR Additions and Alterations    5-018-006                                              /  /       /  /     08/12/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1000   Additions and Alterations    5-018-006  04/07/23     DONE    DONE       DONE      11/16/22   11/15/22   08/12/22   10/26/21   02 - 16                  683,500       683,500  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/15/22           

          District-Wide:
18-2123SB Reconstruction               7-999-002               DONE                           /  /       /  /     06/13/19     /  /     13,16                          0             0  JLB             0           0           0                                         0        /  /                           /  /             
20-0341   Reconstruction               7-999-002  11/23/20     DONE    DONE       DONE      09/04/20   08/27/20   06/13/19   11/04/14   13,16                  2,182,414     2,182,414  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         08/27/20           
23-0629FA Reconstruction               7-999-003  01/25/24     DONE    DONE       DONE      10/06/23   09/29/23   05/15/23   08/28/23                          1,000,000             0  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         09/29/23           

          xxTemp. Tent @ Sargent Elem.:
20-0519XX Reconstruction               8-025-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent 1 @ South Ave School:
20-0520XX Alterations                  8-026-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #2 @ South Ave School:
20-0521XX Alterations                  8-027-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          Tent #1 @ Beacon HS:
20-0522XX Alterations                  8-028-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #2 @ Beacon HS:
20-0523XX Alterations                  8-029-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #1 @ Glenham Elem.:
20-0524XX Reconstruction               8-030-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #2 @ Glenham Elem:
20-0525XX Reconstruction               8-031-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #1 @ Rombout MS:
20-0526XX Alterations                  8-032-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #2 @ Rombout MS:
20-0527XX Alterations                  8-033-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #1 @ James Forrestal:
20-0528XX Alterations                  8-034-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           

          xxTent #2 @ James Forrestal:
20-0529XX Alterations                  8-035-001                         CANCELLED          10/06/20   09/30/20   08/31/20     /  /                                    0             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/30/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DOVER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-05-02-02
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Dover Middle/High School:
18-0451   Reconstruction               0-001-019  05/13/19     DONE    DONE       DONE      09/17/18   08/22/18   06/28/18   02/07/17   16                       500,000             0  SLC             0           0           0 Rennia Engineering                      0      09/24/19                       08/22/18           
20-1328   Reconstruction               0-001-020  03/25/21     DONE    DONE       DONE      02/19/21   02/08/21   06/17/20   05/12/20   2,15                     100,000             0  JSS             0           0           0 Rennia Engineering                      0      06/17/21                       02/08/21           
  -    PR Additions and Alterations    0-001-021                                              /  /       /  /     06/01/21     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
23-0445   Additions and Alterations    0-001-021                       ADDENDUM REQ'D       09/13/23   09/12/23   06/01/21   05/18/23   02 - 16                4,282,697     3,701,131  WLC             0           0           0 Rennia Engineering                      0        /  /                         09/12/23           
21-1386   Reconstruction               0-001-022  06/28/22     DONE    DONE       DONE      02/28/22   02/22/22   06/01/21   05/18/21   4,7                    1,572,347     1,572,347  FMJ             0           0           0 Rennia Engineering                      0        /  /                         02/22/22           
22-1047   Reconstruction               0-001-023  04/18/23     DONE    DONE       DONE      11/18/22   11/18/22   03/23/22   03/22/22   7,9,15                   284,668       250,768  WLC             0           0           0 Rennia Engineering                      0        /  /                         11/18/22           
22-1048   Reconstruction               0-001-024  01/05/23     DONE    DONE       DONE      11/18/22   11/18/22   04/17/22   05/17/22   155                      200,000       200,000  WLC             0           0           0 Rennia Engineering                      0        /  /                         11/18/22           
23-0471   Reconstruction               0-001-025  12/21/23     DONE    DONE       DONE      09/15/23   09/14/23     /  /     05/16/23   155                      100,000       100,000  WLC             0           0           0 Rennia Engineering                      0        /  /                         09/14/23           
  -       Reconstruction               0-001-026                                              /  /       /  /     02/15/24     /  /     155                            0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Wingdale Elementary:
19-0065   Reconstruction               0-003-011  08/16/19     DONE    DONE       DONE      07/12/19   07/08/19   05/23/19   05/21/19   4                        100,000       100,000  SLC             0           0      17,242 Rennia Engineering                      0      06/22/20                       07/08/19           
21-1387   Reconstruction               0-003-012  06/28/22     DONE    DONE       DONE      02/28/22   02/22/22   06/01/21   05/18/21   4,7                    1,557,476     1,557,476  FMJ             0           0           0 Rennia Engineering                      0        /  /                         02/22/22           

          Dover Elementary School:
21-0114   Reconstruction               0-004-012  08/29/21     DONE    DONE       DONE      07/30/21   07/29/21   06/01/21   05/18/21   10                       100,000       100,000  SLC             0           0           0 Rennia Engineering                      0      06/30/22                       07/29/21           
21-1388   Reconstruction               0-004-013  06/28/22     DONE    DONE       DONE      02/28/22   02/22/22   06/01/21   05/18/21   4,7                    1,547,599     1,547,599  FMJ             0           0           0 Rennia Engineering                      0        /  /                         02/22/22           

          Storage Shed @ Dover Elem.:
21-1156PR New Construction             2-019-001  03/30/22     DONE    DONE       DONE      01/18/22   01/18/22   11/10/21     /  /     02 - 16                        0             0  FMJ             0           0           0 Rennia Engineering                      0        /  /                         01/18/22           

          MS/HS Irrigation Building:
21-0682DB Discovered Building          7-017-001  02/07/22     DONE    DONE       DONE      11/12/21   11/09/21   09/09/21     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         11/09/21           

          MS/HS Sewer Treatment Building:
21-0683DB Discovered Building          7-018-001  02/07/22     DONE    DONE       DONE      11/12/21   11/09/21   09/09/21     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         11/09/21           

          XXWingdale Elem. Tent (20-21 only):
20-0283TQ Temporary Quarters           8-013-001  09/15/20     DONE    DONE       DONE      09/01/20   08/31/20   08/14/20     /  /                                    0             0  JSS             0           0           0 Rennia Engineering                      0      09/14/20                       08/31/20           

          XXDover Elem. Tent (20-21 only):
20-0284TQ Temporary Quarters           8-014-001  09/15/20     DONE    DONE       DONE      08/31/20   08/31/20   08/14/20     /  /                                    0             0  JSS             0           0           0 Rennia Engineering                      0      09/14/20                       08/31/20           

          XXMiddle School Tent (20-21 only):
20-0285TQ Temporary Quarters           8-015-001  09/15/20     DONE    DONE       DONE      09/01/20   08/31/20   08/14/20     /  /                                    0             0  JSS             0           0           0 Rennia Engineering                      0      09/14/20                       08/31/20           

          XXHigh School Tent (20-21 only):
20-0286TQ Temporary Quarters           8-016-001  09/15/20     DONE    DONE       DONE      09/01/20   08/31/20   08/14/20     /  /                                    0             0  JSS             0           0           0 Rennia Engineering                      0      09/14/20                       08/31/20           

          XXThe Bell School - Sold July 2021:
  -    XX Reconstruction               9-012-001                         CANCELLED            /  /       /  /     08/11/20     /  /                                    0             0  JSS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HYDE PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-08-01-06
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Haviland Middle School(JrHigh):
18-1587   Reconstruction               0-001-029  08/05/19     DONE    DONE       DONE      03/05/19   02/20/19   09/24/18   05/15/18   2,4,9,10,155,15,16     5,199,679     5,199,679  BMJ             0           0           0 Collins & Scoville Architects           0      12/01/21                       02/20/19           
18-1691   Reconstruction               0-001-030  05/08/19     DONE    DONE       DONE      03/19/19   03/14/19   10/23/18   05/16/17   9,155,15,16              100,000       100,000  BMJ             0           0           0 Collins & Scoville Architects           0      05/26/20                       03/14/19           
22-0080   Reconstruction               0-001-031  10/26/22     DONE    DONE       DONE      07/13/22   07/12/22   03/17/22   05/18/21   9                        100,000       100,000  SLC             0           0           0 CS Arch                                 0      04/11/23                       07/12/22           
22-2155   Reconstruction               0-001-032  10/02/23     DONE    DONE       DONE      05/05/23   05/05/23   02/06/23   02/22/22   2,8,9,14,16            1,728,572     1,728,572  MSK             0           0           0 CS Arch                                 0        /  /                         05/05/23           

          Roosevelt High School:
18-1588   Alterations                  0-002-027  08/05/19     DONE    DONE       DONE      03/05/19   02/20/19   09/24/18   05/15/18   02 - 16               18,152,003    17,879,736  BMJ             0           0           0 Collins & Scoville Architects           0      05/03/23                       02/20/19           
19-1761   Reconstruction               0-002-028  06/16/20     DONE    DONE       DONE      05/26/20   03/13/20   05/02/19   05/21/19   2,16                   1,015,512     1,015,512  JSS             0           0           0 Collins & Scoville Architects           0      05/05/23                       03/13/20           
20-1588XX Reconstruction               0-002-029  05/25/21               CANCELLED          04/14/21   03/24/21   07/02/20   05/21/19   9,10,15,16               100,000       100,000  JSS             0           0           0 Collins & Scoville Architects           0        /  /                         03/24/21           
21-0802   Reconstruction               0-002-030  02/28/22     DONE    DONE       DONE      11/30/21   11/24/21   10/19/21   04/08/21   2                        100,000       100,000  SLC             0           0           0 CS Arch                                 0      06/27/22                       11/24/21           
22-0434   Reconstruction               0-002-031  04/12/23     DONE    DONE       DONE      09/08/22   09/08/22   05/26/22   02/22/22   2,7,155,15,16         13,168,582    13,168,582  JLB             0           0           0 CS Arch                                 0        /  /                         09/08/22           
23-1693   Reconstruction               0-002-032                         UNREVIEWED         03/28/24   03/25/24   06/26/23   02/22/22   2,8,9,155,16                   0             0  MSK             0           0           0 CS Arch                                 0        /  /                         03/25/24           

          Ralph R. Smith Elementary:
22-2156   Reconstruction               0-003-021  10/02/23     DONE    DONE       DONE      05/05/23   05/05/23   02/06/23   02/22/22   2,4,8,9,10,16          2,540,786     1,889,272  MSK             0           0           0 CS Arch                                 0        /  /                         05/05/23           

          Violet Avenue Elementary:
22-2157   Reconstruction               0-004-019  10/19/23     DONE    DONE       DONE      05/05/23   05/05/23   02/06/23   02/22/22   2,8,9,14,155,15,16     4,846,668     4,846,668  MSK             0           0           0 CS Arch                                 0        /  /                         05/05/23           

          Hyde Park Elementary:
22-0435   Reconstruction               0-005-024  04/12/23     DONE    DONE       DONE      09/08/22   09/08/22   05/26/22   02/22/22   2,7,155,15,16            903,649       903,649  JLB             0           0           0 CS Arch                                 0        /  /                         09/08/22           
23-1694   Reconstruction               0-005-025                         UNREVIEWED         03/28/24   03/25/24   06/26/23   02/22/22   2,8,9,155,15,16                0             0  MSK             0           0           0 CS Arch                                 0        /  /                         03/25/24           

          Netherwood Elementary School:
23-1695   Reconstruction               0-007-021                         UNREVIEWED         03/28/24   03/25/24   06/26/23   02/22/22   2,4,8,9,155,15,16              0             0  MSK             0           0           0 CS Arch                                 0        /  /                         03/25/24           

          North Park Elementary School:
22-0984   Reconstruction               0-013-024  01/22/23     DONE    DONE       DONE      11/16/22   11/15/22   09/01/22   05/17/22   9,14,16                  100,000       100,000  SLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/15/22           
23-1696   Reconstruction               0-013-025                         UNREVIEWED         03/28/24   03/25/24   06/26/23   02/22/22   2,4,8,9,155,15,16              0             0  MSK             0           0           0 CS Arch                                 0        /  /                         03/25/24           

          Administration (see 1-017):
23-1697   Reconstruction               1-016-003                         UNREVIEWED         03/28/24   03/25/24   06/26/23   02/22/22   2,8,9,155,15,16                0             0  MSK             0           0           0 CS Arch                                 0        /  /                         03/25/24           

          Concession Stand @ FDR HS:
19-1534DB Discovered Building          7-020-001                       ADDENDUM REQ'D       03/03/20   03/03/20   02/24/20     /  /                                    0             0  JSS             0           0           0                                         0        /  /                         03/03/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHEAST (WEBUTUCK) CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-11-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Webutuck Jr/Sr High School:
20-1186   Reconstruction               0-002-020  07/06/21     DONE    DONE       DONE      01/25/21   01/06/21   06/22/20   04/27/20   2,8,9,155,15,16          170,850       170,850  SLC             0           0           0 Clark Patterson Lee                     0      03/31/22                       01/06/21           
21-1565   Reconstruction               0-002-021  04/05/22     DONE    DONE       DONE      03/28/22   03/25/22   01/25/22   01/24/22   2,9,10,16              3,349,302             0  SLC             0           0           0 Bernier Carr Associates                 0      06/27/23                       03/25/22           
23-0063   Reconstruction               0-002-022  11/28/23     DONE    DONE       DONE      07/12/23   07/11/23   02/21/23   12/06/22   2,7,9,155,15,16       10,464,461    10,464,461  MSK             0           0           0 Bernier Carr & Associates               0        /  /                         07/11/23           

          Webutuck Elementary School:
22-2207FA Reconstruction               0-004-016  06/26/23     DONE    DONE       DONE      05/15/23   05/09/23   02/21/23   03/06/23   155,16                   750,000       750,000  MSK             0           0           0 Bernier Carr Associates                 0        /  /                         05/09/23           
23-0064   Reconstruction               0-004-017  11/28/23     DONE    DONE       DONE      07/12/23   07/11/23   02/21/23   12/06/22   2,7,155,15,16          2,095,539     2,095,539  MSK             0           0           0 Bernier Carr Associates                 0        /  /                         07/11/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PAWLING CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-12-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pawling Elementary School:
22-0974   Reconstruction               0-001-024  03/31/23     DONE    DONE       DONE      11/14/22   11/14/22   04/30/21   12/16/20   2,4,7,8,9,10,155,15,  12,253,000    12,229,600  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/14/22           
21-1242   Reconstruction               0-001-025  12/22/22     DONE    DONE       DONE      02/07/22   02/07/22   06/28/21   05/04/21   155,15,16              1,059,977     1,059,977  WLC             0           0           0 ECG Engineering, LLC            1,032,239        /  /                         02/07/22           

          Pawling High School:
  -    PR Additions and Alterations    0-002-021                                              /  /       /  /     04/30/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-1675   Additions and Alterations    0-002-021  12/30/22     DONE    DONE       DONE      04/20/22   04/14/22   04/30/21   12/16/20   02 - 16               12,007,000    10,167,000  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         04/14/22           
21-0028   Reconstruction               0-002-022  11/12/21     DONE    DONE       DONE      07/12/21   07/08/21   04/30/21   12/16/20   2,9                    4,862,500     4,468,950  JLB             0           0           0 Collins & Scoville Architects           0      06/15/23                       07/08/21           
21-1243   Reconstruction               0-002-023  12/22/22     DONE    DONE       DONE      02/09/22   02/07/22   06/28/21   05/04/21   155,16                   743,346       743,346  WLC             0           0           0 ECG Engineering, LLC              710,763        /  /                         02/07/22           

          Pawling Middle School:
  -    PR Additions and Alterations    0-006-007                                              /  /       /  /     04/30/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-0029   Reconstruction               0-006-008  11/12/21     DONE    DONE       DONE      07/12/21   07/08/21   04/30/21   12/16/20   2,8,9,10,155,15,16     4,577,500     3,912,639  JLB             0           0           0 Collins & Scoville Architects           0      06/15/23                       07/08/21           
21-1244   Reconstruction               0-006-009  12/22/22     DONE    DONE       DONE      02/07/22   02/07/22   06/28/21   05/04/21   2,7,155,15,16            433,936       433,936  WLC             0           0           0 ECG Engineering, LLC              398,908        /  /                         02/07/22           

          Storage Building:
21-0030   New Construction             2-015-001  11/12/21     DONE    DONE       DONE      07/12/21   07/08/21   04/30/21   12/16/20   02 - 16                  133,500             0  JLB             0           0           0 Collins & Scoville Architects           0      06/15/23                       07/08/21           

          New Transportation Facility:
  -    PR Additions and Alterations    5-013-002                                              /  /       /  /     12/05/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Press Box:
21-0031   New Construction             7-014-001  11/12/21     DONE    DONE       DONE      07/12/21   07/08/21   04/30/21   12/16/20   02 - 16                  340,500             0  JLB             0           0           0 Collins & Scoville Architects           0      06/15/23                       07/08/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PINE PLAINS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-13-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Seymour Smith School:
19-0745   Reconstruction               0-001-015  01/02/20     DONE    DONE       DONE      11/08/19   11/01/19   08/09/19   05/21/19   2,13,16                  100,000       100,000  SLC             0           0           0 Mosaic Associates                       0      06/10/20                       11/01/19           
21-0888FB Reconstruction               0-001-016  03/19/22     DONE    DONE       DONE      12/13/21   12/13/21   09/03/21   05/18/21   2,4,7,9,10,155,15,16   4,948,541     6,175,286  SLC             0           0           0 CS Arch                                 0      11/01/23                       12/13/21           
21-0633   Reconstruction               0-001-017  01/06/22     DONE    DONE       DONE      11/03/21   11/02/21   10/12/21   05/18/21   16                       100,000       100,000  SLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/02/21           
  -       Reconstruction               0-001-018                                              /  /       /  /       /  /       /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Cold Springs Elementary:
21-0889   Reconstruction               0-002-007  03/19/22     DONE    DONE       DONE      12/13/21   12/13/21   09/03/21   05/18/21   2,4,7,10,155,15,16     2,717,785     2,377,227  SLC             0           0           0 CS Arch                                 0      01/30/23                       12/13/21           
22-0925   Reconstruction               0-002-008  01/07/23     DONE    DONE       DONE      11/07/22   11/04/22   07/07/22   05/17/22   16                       100,000       100,000  SLC             0           0           0 CS Arch                                 0      07/19/23                       11/04/22           

          Stissing Mt Jr/Sr High School:
20-1711XX Reconstruction               0-009-016                         CANCELLED          05/13/21   04/12/21   02/19/21   06/16/20   9,155,16                 100,000       100,000  SLC             0           0           0 CS Arch                                 0        /  /                         04/12/21           
21-0890   Reconstruction               0-009-017  03/19/22     DONE    DONE       DONE      12/13/21   12/13/21   09/03/21   05/18/21   2,4,7,10,155,15,16       582,378       481,052  SLC             0           0           0 CS Arch                                 0      10/12/22                       12/13/21           

          Pole Barn (Storage):
22-2426DB Discovered Building          2-017-001  01/17/24     DONE    DONE       DONE      06/20/23   01/13/23   11/17/93     /  /                                    0             0  MSK             0           0           0                                         0        /  /                         01/13/23           

          Bus Garage (New):
23-1348   Reconstruction               5-013-002  03/15/24     DONE    DONE       DONE      01/12/24   01/04/24   11/08/23   05/16/23   155                      100,000       100,000  MSK             0           0           0 CS Arch                                 0        /  /                         01/04/24           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




POUGHKEEPSIE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-15-00-01
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Columbus School #3 (AdminBldg):
18-1922   Reconstruction               0-001-012  07/19/19     DONE    DONE       DONE      05/02/19   05/01/19   12/22/16   10/23/16   2,155,15,16              543,000       543,000  JLB             0           0           0 Clark Patterson Lee                     0      03/08/19                       05/01/19           
19-0280   Reconstruction               0-001-013  10/16/19     DONE    DONE       DONE      08/16/19   08/12/19   01/17/19   06/05/19   8,155,16                 207,000       207,000  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         08/12/19           
21-0742   Reconstruction               0-001-014  03/21/22     DONE    DONE       DONE      11/18/21   07/17/21   05/12/21   10/20/20   2,4,8,9,155,15,16      1,135,288             0  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         07/17/21           
22-0330   Reconstruction               0-001-015  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16             301,843             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
21-1857   Reconstruction               0-001-016  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,16                   253,401             0  JLB             0           0           0 Engineered Solutions              253,401        /  /                         05/10/22           

          SFB Morse School #5:
20-1334   Reconstruction               0-002-012  02/18/20     DONE    DONE       DONE      02/19/21   02/05/21   12/20/19   03/04/20   155                       90,000        90,000  JLB             0           0           0 Clark Patterson Lee                     0      03/05/20                       02/05/21           
20-1689   Reconstruction               0-002-013  06/05/21     DONE    DONE       DONE      05/07/21   05/05/21   02/12/21   10/20/20   7                      1,268,065     1,268,065  JLB             0           0           0 Clark Patterson Lee                     0      11/16/21                       05/05/21           
21-0743   Reconstruction               0-002-014  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   05/12/21   10/20/20   2,4,8,9,155,15,16      1,774,783     1,774,783  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0682FA Reconstruction               0-002-015  12/29/22     DONE    DONE       DONE      10/12/22   08/30/22   11/12/21   08/24/21   155,16                 1,077,979     1,077,979  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         08/30/22           
22-0331   Reconstruction               0-002-016  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16           2,270,085     2,270,085  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
21-1858   Reconstruction               0-002-017  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,16                   352,901       352,901  JLB             0           0           0 Engineered Solutions              352,901        /  /                         05/10/22           
23-0715   Reconstruction               0-002-018               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/13/23   10/12/23   09/01/22   10/20/20   2,8,9                          0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           
  -       Reconstruction               0-002-019                                              /  /       /  /     04/12/24     /  /     2,8,155,16                     0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Gov. Clinton School #8:
20-1690   Reconstruction               0-004-013  06/18/21     DONE    DONE       DONE      05/07/21   05/05/21   02/12/21   10/20/20   7                        582,665       582,665  JLB             0           0           0 Clark Patterson Lee                     0      11/09/21                       05/05/21           
21-0744   Reconstruction               0-004-014  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   05/12/21   10/20/20   2,4,8,9,155,15,16      1,714,750     1,714,750  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0683FA Reconstruction               0-004-015  12/29/22     DONE    DONE       DONE      10/12/22   08/30/22   11/18/21   08/24/21   155,16                   735,479       735,479  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         08/30/22           
22-0332   Reconstruction               0-004-016  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16           1,442,748     1,442,748  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
21-1859   Reconstruction               0-004-017  11/22/22     DONE    DONE       DONE      05/23/22   05/20/22   02/22/22   06/16/21   155,16                   232,578       232,578  JLB             0           0           0 Engineered Solutions              232,578        /  /                         05/20/22           
23-0716   Reconstruction               0-004-018               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/13/23   10/12/23   09/01/22   10/20/20   2,8,9                          0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           
  -       Reconstruction               0-004-019                                              /  /       /  /     04/12/24     /  /     2,9,14,155,15,16               0             0  WLC             0           0           0                                         0        /  /                           /  /             

          C.B. Warring School #10:
21-0745   Reconstruction               0-005-013  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   05/12/21   10/20/20   2,7,155,15,16          3,517,278     3,517,278  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0684FA Reconstruction               0-005-014  12/29/22     DONE    DONE       DONE      10/12/22   08/30/22   11/12/21   08/24/21   155,16                 1,186,542     1,186,542  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         08/30/22           
21-1860   Reconstruction               0-005-015  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,16                   264,220       264,220  JLB             0           0           0 Engineered Solutions              264,220        /  /                         05/10/22           
22-0333   Reconstruction               0-005-016  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   06/08/22   10/20/20   2,8,9,155,16             285,875       285,875  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
23-0717   Reconstruction               0-005-017               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/13/23   10/12/23   10/03/22   10/20/20   2,8,9,155,15,16                0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           
22-2142   Reconstruction               0-005-018  07/24/23     DONE    DONE       DONE      05/03/23   05/03/23   03/23/23   03/27/23   16                       250,000       250,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         05/03/23           
  -       Reconstruction               0-005-019                                              /  /       /  /     04/12/24     /  /     2,4,9,155,15,16                0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Krieger School No. 11:
21-0746   Reconstruction               0-006-014  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   05/12/21   10/20/20   2,4,7,8,9,14,155,15,   2,147,020     2,147,020  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0334   Reconstruction               0-006-015  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16             484,638       484,638  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
21-1861   Reconstruction               0-006-016  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,16                   899,858       899,858  JLB             0           0           0 Engineered Solutions              899,858        /  /                         05/10/22           
  -    XX Reconstruction               0-006-017                         CANCELLED            /  /       /  /     04/22/22     /  /     155,15,16                      0    14,669,150  JLB             0           0           0                                         0        /  /                           /  /             
23-0718   Reconstruction               0-006-018                         UNREVIEWED         10/13/23   10/12/23   09/01/22   10/20/20   2,8,9                          0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           

          Junior/Senior High School:
21-0747   Reconstruction               0-007-018  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   02/12/21   10/20/20   4,8,9,155,15,16        9,731,410     9,731,410  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0335   Reconstruction               0-007-019  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16             805,758       805,758  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
22-0624   Reconstruction               0-007-020  02/07/23     DONE    DONE       DONE      10/03/22   10/03/22   01/13/22   01/05/22   155,16                   310,000       310,000  WLC             0           0           0 Clark Patterson Lee                     0      11/29/23                       10/03/22           
22-1458   Reconstruction               0-007-021  05/03/23     DONE    DONE       DONE      01/09/23   01/09/23   01/13/22   12/01/21   15,16                     92,735        92,735  WLC             0           0           0 Clark Patterson Lee                     0      05/08/23                       01/09/23           
21-1862   Reconstruction               0-007-022  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,15,16              1,488,358     1,488,358  JLB             0           0           0 Engineered Solutions            1,488,358        /  /                         05/10/22           
23-0719   Reconstruction               0-007-023                         UNREVIEWED         10/13/23   10/12/23   09/01/22   10/20/20   2,8,9                          0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           
23-0644   Reconstruction               0-007-024  04/11/24     DONE    DONE       DONE      10/06/23   10/04/23   08/02/23   02/01/23   155                    4,500,000     4,500,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/04/23           
  -       Reconstruction               0-007-025                                              /  /       /  /     04/12/24     /  /     2,8,9,155,15,16                0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Early Learning Center (fka Smith ES):
  -       Reconstruction               0-008-020                                              /  /       /  /     12/20/19     /  /     155                            0             0  JLB             0           0           0                                         0        /  /                           /  /             
20-1691   Reconstruction               0-008-021  06/18/21     DONE    DONE       DONE      05/07/21   05/05/21   02/12/21   10/20/20   7                      1,485,950     1,485,950  JLB             0           0           0 Clark Patterson Lee                     0      11/09/21                       05/05/21           
21-0748   Reconstruction               0-008-022  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   05/12/21   10/20/20   2,4,8,9,155,15,16      1,725,208     1,725,208  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0336   Reconstruction               0-008-023  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16           1,399,088     1,399,088  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
21-1863   Reconstruction               0-008-024  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,16                   269,293       269,293  JLB             0           0           0 Engineered Solutions              269,293        /  /                         05/10/22           
23-0720   Reconstruction               0-008-025                         UNREVIEWED         10/13/23   10/12/23   09/01/22   10/20/20   2,8,9                          0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           
  -       Reconstruction               0-008-026                                              /  /       /  /     04/12/24     /  /     2,9,14,155,15,16               0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Middle School:
20-0866   Reconstruction               0-015-019  02/19/21     DONE    DONE       DONE      11/20/20   11/12/20   02/06/18   10/21/20   9,155,15,16              440,200             0  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/12/20           
22-0196   Reconstruction               0-015-020  11/16/22     DONE    DONE       DONE      07/29/22   07/29/22   06/13/19   03/19/20   4                         69,369        69,369  JLB             0           0           0 Clark Patterson Lee                     0      04/19/22                       07/29/22           
21-0749   Reconstruction               0-015-021  03/21/22     DONE    DONE       DONE      11/18/21   11/17/21   05/12/21   10/20/20   2,4,7,8,9,155,15,16    6,461,060     6,461,060  JLB             0           0           0 Clark Patterson Lee                     0        /  /                         11/17/21           
22-0337   Reconstruction               0-015-022  12/15/22     DONE    DONE       DONE      08/24/22   08/24/22   12/15/21   10/20/20   2,8,9,155,16             651,755       651,755  JJH             0           0           0 Clark Patterson Lee                     0        /  /                         08/24/22           
21-1864   Reconstruction               0-015-023  11/22/22     DONE    DONE       DONE      05/23/22   05/10/22   02/22/22   06/16/21   155,15,16              1,993,398     1,993,398  JLB             0           0           0 Engineered Solutions            1,993,398        /  /                         05/10/22           
22-1242   Reconstruction               0-015-024  03/03/23     DONE    DONE       DONE      12/14/22   12/13/22   08/03/22   08/17/22   14                       897,000       897,000  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         12/13/22           
23-0721   Reconstruction               0-015-025                         UNREVIEWED         10/13/23   10/12/23   09/01/22   10/20/20   2,8,9                          0             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/12/23           
  -       Reconstruction               0-015-026                                              /  /       /  /     04/12/24     /  /     2,8,9,155,15,16                0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Administration Building Demolition:
18-1689   Reconstruction               1-003-005  10/07/19     DONE    DONE       DONE      03/19/19   03/13/19   08/06/18   08/29/18   7                        379,000             0  MTM             0           0           0 Clark Patterson Lee                     0        /  /                         03/13/19           
  -       Reconstruction               1-003-006                                              /  /       /  /     04/19/21     /  /     2                              0             0  JLB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               1-003-007                                              /  /       /  /     01/17/24     /  /     2,4,7,8,9,155,15,16            0             0  WLC             0           0           0                                         0        /  /                           /  /             

          PCSD Admin Bldg:
  -    DB Discovered Building          1-026-001                                              /  /       /  /     06/21/22     /  /                                    0             0  FMJ             0           0           0                                         0        /  /                           /  /             

          XX Bus Garage Shops-DEMO XX:
  -       Reconstruction               5-009-003                                              /  /       /  /     03/06/24     /  /     2,4,155,15,16                  0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Poughkeepsie MS Cell Tower:
  -    PR New Construction             7-025-001                                              /  /       /  /     02/22/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             

          District Wide:
21-1669SB Reconstruction               7-999-003               DONE                           /  /       /  /     04/17/22     /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0461   Reconstruction               7-999-003  12/21/22     DONE    DONE       DONE      09/12/22   09/09/22   04/17/22   11/04/14   16                     3,097,000             0  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         09/09/22           

          UPK Classrooms:
  -    TQ Temporary Quarters           8-024-001                                              /  /       /  /     02/15/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          LittleWaterPrepChrtr(OurLadyMtCarmel:
22-0106TQ Temporary Quarters           8-001-001  12/09/22     DONE    DONE       DONE      07/18/22   07/18/22   02/07/22     /  /                                    0             0  SLC             0           0           0 Tinkelman Architecture PLLC             0        /  /                         07/18/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ARLINGTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-16-01-06
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Arthur S. May Elem School:
  -       Reconstruction               0-002-017                                              /  /       /  /     02/21/24     /  /     2,4                            0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Overlook Elementary School:
22-1760   Reconstruction               0-004-015  04/18/23     DONE    DONE       DONE      02/27/23   02/27/23   12/11/19   05/21/19   2,7,9,155,16           6,758,440     6,758,440  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/27/23           

          Traver Road Primary:
  -       Reconstruction               0-007-015                                              /  /       /  /     03/01/22     /  /     15                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Arlington HS (frmrly North CampusHS):
18-1227   Reconstruction               0-008-017  04/30/19     DONE    DONE       DONE      01/10/19   01/02/19   10/17/18   05/15/18   2,9,10,13,15,16        3,137,891     3,137,891  SLC             0           0           0 Tetra Tech Architects and Eng           0      04/30/21                       01/02/19           
18-1435   Reconstruction               0-008-018  04/30/19     DONE    DONE       DONE      02/12/19   02/11/19   10/29/18   05/15/18   155                      100,000       100,000  SLC             0           0           0 Tetra Tech Architects and Eng           0      05/08/20                       02/11/19           
22-1555   Reconstruction               0-008-019  05/22/23     DONE    DONE       DONE      01/25/23   01/23/23   11/04/22   05/17/22   2,4,7                  8,824,290     8,824,290  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         01/23/23           
  -       Reconstruction               0-008-020                                              /  /       /  /     02/21/24     /  /     2,155                          0             0  MSK             0           0           0                                         0        /  /                           /  /             

          LaGrange MS(fmlySouth Campus):
22-1330XX Reconstruction               0-009-012  05/11/23               CANCELLED          12/27/22   12/22/22   09/08/22   05/17/22   2,4,7,9,155,16           250,000       250,000  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         12/22/22           
22-1331   Reconstruction               0-009-013  03/30/23     DONE    DONE       DONE      12/27/22   12/22/22     /  /     05/17/22   2,9                      100,000       100,000  JLB             0           0           0 Tetra Tech Architects and Eng           0      08/31/23                       12/22/22           

          Titusville Elementary School:
  -       Reconstruction               0-010-014                                              /  /       /  /     02/21/24     /  /     2,15                           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Union Vale Middle School:
22-1556   Reconstruction               0-036-005  05/22/23     DONE    DONE       DONE      01/25/23   01/23/23   11/04/22   05/17/22   2,4,7                  9,470,941     9,470,941  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         01/23/23           
  -       Reconstruction               0-036-006                                              /  /       /  /     02/21/24     /  /     2,16                           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Vail Farm Elementary School:
22-1557   Reconstruction               0-037-005  05/22/23     DONE    DONE       DONE      01/25/23   01/23/23   11/04/22   05/17/22   2,4,7                  8,608,128     8,608,128  JLB             0           0           0 Tetra Tech Architects and Eng           0      06/23/23                       01/23/23           

          Press Box:
18-1228   New Construction             7-041-001  04/30/19     DONE    DONE       DONE      01/10/19   01/02/19   12/20/18   05/15/18   02 - 16                  137,109             0  SLC             0           0           0 Tetra Tech Architects and Eng           0      10/08/20                       01/02/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SPACKENKILL UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-16-02-02
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Orville Todd Jr High School:
20-0776   Reconstruction               0-002-017  03/30/21     DONE    DONE       DONE      01/06/21   10/22/20   01/05/21   05/05/20   2,13,16                   24,199             0  JSS             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                         10/22/20           
22-0858   Reconstruction               0-002-018  04/13/23     DONE    DONE       DONE      10/31/22   10/28/22   09/16/22   12/05/17   2,9,155,16             1,088,240     1,088,240  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/28/22           

          Nassau Road Elementary:
19-0161   Reconstruction               0-003-013  10/02/19     DONE    DONE       DONE      07/25/19   07/18/19   06/12/19   12/05/17   2,16                     129,600             0  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                         07/18/19           
22-0859   Reconstruction               0-003-014  04/13/23     DONE    DONE       DONE      10/31/22   10/28/22   09/16/22   12/05/17   2,9,16                   450,400       450,400  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/28/22           

          Hagan Elementary School:
22-0860   Reconstruction               0-004-017  04/13/23     DONE    DONE       DONE      10/31/22   10/28/22   09/16/22   12/05/17   2,9,16                   391,680       391,680  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/28/22           

          Spackenkill High School:
20-0775   Reconstruction               0-005-021  03/30/21     DONE    DONE       DONE      01/06/21   10/22/20   01/05/21   05/05/20   2,13,16                   24,199        24,199  JSS             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                         10/22/20           
22-0861   Reconstruction               0-005-022  04/13/23     DONE    DONE       DONE      10/31/22   10/28/22   09/16/22   12/05/17   2,9,10,16              1,120,680     1,120,680  WLC             0           0           0 Clark Patterson Lee                     0        /  /                         10/28/22           

          XXPortable-Todd Middle School Demoli:
21-0233   Reconstruction               0-008-003  09/07/21     DONE    DONE       DONE      08/26/21   08/25/21   08/10/21   08/17/21   2                         40,000             0  SLC             0           0           0 Clark Patterson Lee                     0        /  /                         08/25/21           

          Restroom / Storage Building:
19-1535   New Construction             7-012-001  06/15/20     DONE    DONE       DONE      03/03/20   02/27/20   02/05/20   12/05/17   02 - 16                  197,640             0  JSS             0           0           0 Clark Patterson Lee                     0        /  /                         02/27/20           

          District-Wide:
19-0875   Reconstruction               7-999-002  01/06/20     DONE    DONE       DONE      11/27/19   11/18/19   04/02/19   02/15/18   16                             0             0  BMJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                         11/18/19           
  -       Reconstruction               7-999-003                                              /  /       /  /     03/13/20     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RED HOOK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-17-01-06
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Linden Ave Middle School:
20-1566   Reconstruction               0-003-006  05/04/21     DONE    DONE       DONE      04/07/21   04/01/21   03/12/21   06/09/20   155                      100,000       100,000  JLB             0           0           0 Tetra Tech Engineers, Archite           0      06/30/21                       04/01/21           
22-0290   Reconstruction               0-003-007  02/22/23     DONE    DONE       DONE      08/17/22   08/17/22   11/18/21   06/21/19   16                       525,108       525,108  WLC             0           0           0 Whitman                                 0        /  /                         08/17/22           
21-1513   Reconstruction               0-003-008  04/13/22     DONE    DONE       DONE      03/15/22   03/14/22   03/07/22   05/18/21   16                       100,000       100,000  JLB             0           0           0 Tetra Tech Architects and Eng           0      06/29/22                       03/14/22           
22-0506   Reconstruction               0-003-009  01/20/23     DONE    DONE       DONE      09/16/22   09/15/22   05/04/22   02/22/22   2,7,8,9,155,16         2,100,000     2,100,000  WLC             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         09/15/22           

          Red Hook High School:
19-0123   Reconstruction               0-005-011  08/05/19     DONE    DONE       DONE      07/19/19   07/15/19     /  /     05/15/18   155,16                   100,000       100,000  JLB             0           0           0 Tetra Tech Architects and Eng           0      12/23/19                       07/15/19           
22-0291   Reconstruction               0-005-012  02/22/23     DONE    DONE       DONE      08/17/22   08/17/22   11/18/21   05/21/19   16                       536,018       536,018  WLC             0           0           0 Whitman                                 0        /  /                         08/17/22           
22-0598FC Reconstruction               0-005-013  11/10/22     DONE    DONE       DONE      09/28/22   07/22/22   01/26/22   06/08/22   9,10,155,15,16           450,000       450,000  WLC             0           0           0 Tetra Tech Engineers, Archite           0      09/20/23                       07/22/22           
22-0507   Reconstruction               0-005-014  01/20/23     DONE    DONE       DONE      09/16/22   09/15/22   05/04/22   02/22/22   2,4,8,9,155,16        13,650,000    13,650,000  WLC             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         09/15/22           
22-1817   Reconstruction               0-005-015  04/18/23     DONE    DONE       DONE      03/13/23   03/08/23   02/15/23   05/17/22   155,16                   100,000       100,000  WLC             0           0           0 Tetra Tech Engineers, Archite           0      06/28/23                       03/08/23           
23-1720   Reconstruction               0-005-016                         UNREVIEWED         04/01/24   03/28/24   03/01/24   04/12/23   16                       100,000             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         03/28/24           

          Mill Rd. Elementary:
22-0292   Reconstruction               0-006-011  02/22/23     DONE    DONE       DONE      08/17/22   08/17/22   11/18/21   05/21/19   16                       569,311       569,311  WLC             0           0           0 Whitman                                 0        /  /                         08/17/22           
22-0508   Reconstruction               0-006-012  01/20/23     DONE    DONE       DONE      09/16/22   09/15/22   05/04/22   02/22/22   2,8,9,155,16           6,170,000     6,170,000  WLC             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         09/15/22           
23-1490   Reconstruction               0-006-013                         UNREVIEWED         02/12/24   02/12/24   01/05/24   02/07/24   2                              0             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/12/24           

          Mill Road School Garden Gazebo:
21-0396   New Construction             7-027-001  12/01/21     DONE    DONE       DONE      09/22/21   09/22/21   07/02/21   08/11/21   02 - 16                   11,696             0  JLB             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         09/22/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RHINEBECK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-18-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
22-1502   Reconstruction               0-002-018  04/04/23     DONE    DONE       DONE      01/18/23   01/17/23   12/05/22   05/17/22   8,9                      100,000       100,000  JJH             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         01/17/23           

          Livingston Elem. School:
  -       Reconstruction               0-004-015                                              /  /       /  /       /  /       /  /     16                             0             0  JJH             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WAPPINGERS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-21-01-06
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Fishkill Plains Elementary:
19-0090   Reconstruction               0-001-017  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                 80,530        80,529  JSS             0           0           0 Engineered Solutions               80,530        /  /                         07/10/19           
21-1223   Reconstruction               0-001-019  05/23/22     DONE    DONE       DONE      02/02/22   02/02/22   10/12/21   05/17/16   2                        457,000       457,000  FMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         02/02/22           
22-1472   Reconstruction               0-001-020  04/03/23     DONE    DONE       DONE      01/11/23   12/08/22   08/02/22   05/17/22   2,7,8,9,10,155,15,16   3,104,110     3,104,110  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          Kinry Road Elementary:
19-0091   Reconstruction               0-002-020  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                 44,648             0  JSS             0           0           0 Engineered Solutions               44,648        /  /                         07/10/19           
22-1201   Reconstruction               0-002-022  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   16                        35,600        35,600  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          James Evans Elementary:
19-0092   Reconstruction               0-003-027  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,16                   415,830             0  JSS             0           0           0 Engineered Solutions              415,830        /  /                         07/10/19           
22-1202   Reconstruction               0-003-028  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   155,15,16                100,000       100,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          Junior High School:
19-0093   Reconstruction               0-004-034  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,16                    75,992        75,992  JSS             0           0           0 Engineered Solutions               75,992        /  /                         07/10/19           
22-1203   Reconstruction               0-004-035  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   2,4,8,9,10,155,15,16   2,050,000     2,050,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           
23-1102   Reconstruction               0-004-036                         UNREVIEWED         12/04/23   11/20/23   09/11/23   05/17/22   2,8,9,10,155,15,16             0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Fishkill Elementary School:
19-0094   Reconstruction               0-005-020  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   16                        43,364             0  JSS             0           0           0 Engineered Solutions               43,364        /  /                         07/10/19           
23-1103   Reconstruction               0-005-021                         UNREVIEWED         12/04/23   11/20/23   08/02/22   05/17/22   155,16                         0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Vassar Road Elementary:
19-0095   Reconstruction               0-008-025  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                478,626             0  JSS             0           0           0 Engineered Solutions              478,626        /  /                         07/10/19           
23-1104   Reconstruction               0-008-026                         UNREVIEWED         12/04/23   11/20/23   08/02/22   05/17/22   2,7,9,155,16                   0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Roy Ketcham High School:
19-0096   Reconstruction               0-012-035  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16              1,822,746     1,822,746  JSS             0           0           0 Engineered Solutions            1,822,746        /  /                         07/10/19           
19-0524   Reconstruction               0-012-036  01/27/20     DONE    DONE       DONE      10/07/19   09/26/19   02/27/19   05/15/18   2,4,7,9,155,15,16     10,344,000             0  BMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         09/26/19           
21-1224   Reconstruction               0-012-037  05/23/22     DONE    DONE       DONE      02/02/22   02/02/22   10/12/21   05/17/16   4                        206,000       206,000  FMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         02/02/22           
22-1204   Reconstruction               0-012-038  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   2,4,9,10,155,15,16       162,500       162,500  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           
23-1105   Reconstruction               0-012-039                         UNREVIEWED         12/04/23   11/20/23   09/11/23   05/17/22   2,9,10,155,15,16               0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Brinckerhoff Elementary:
19-0097   Reconstruction               0-013-023  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                734,575             0  JSS             0           0           0 Engineered Solutions              734,575        /  /                         07/10/19           
  -       Reconstruction               0-013-025                                              /  /       /  /     08/02/22     /  /     155,16                         0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Oak Grove Elementary:
19-0098   Reconstruction               0-014-022  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                 51,636        51,636  JSS             0           0           0 Engineered Solutions               51,636        /  /                         07/10/19           
22-1205   Reconstruction               0-014-023  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   2,155,16                 912,500       912,500  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          Gayhead Elementary:
19-0099   Reconstruction               0-016-024  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   16                       661,274        82,133  JSS             0           0           0 Engineered Solutions              661,274        /  /                         07/10/19           
  -       Reconstruction               0-016-026                                              /  /       /  /     08/02/22     /  /     155,16                         0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Van Wyck Junior High School:
19-0100   Reconstruction               0-017-026  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,16                 1,255,918     1,255,918  JSS             0           0           0 Engineered Solutions            1,255,918        /  /                         07/10/19           
23-1106   Reconstruction               0-017-027                         UNREVIEWED         12/04/23   11/20/23   08/02/22   05/17/22   2,4,7,8,9,155,15,16            0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Sheafe Road Elementary:
19-0101   Reconstruction               0-018-019  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                181,550       181,549  JSS             0           0           0 Engineered Solutions              181,550        /  /                         07/10/19           
21-1225   Reconstruction               0-018-021  05/23/22     DONE    DONE       DONE      02/02/22   02/02/22   10/12/21   05/17/16   2,4,155,15,16            819,000       819,000  FMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         02/02/22           
23-1107   Reconstruction               0-018-022                         UNREVIEWED         12/04/23   11/20/23   08/02/22   05/17/22   7,8,9,155,16                   0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Myers Corners Elementary:
19-0102   Reconstruction               0-019-025  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,16                    84,626             0  JSS             0           0           0 Engineered Solutions               84,626        /  /                         07/10/19           
19-0525   Reconstruction               0-019-027  01/27/20     DONE    DONE       DONE      10/07/19   09/26/19   02/27/19   05/15/18   2,4,7,9,155,15,16      2,728,000             0  BMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         09/26/19           
21-1226   Reconstruction               0-019-028  05/23/22     DONE    DONE       DONE      02/02/22   02/02/22   10/12/21   05/17/16   2,4,13                    59,000        59,000  FMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         02/02/22           
22-1206   Reconstruction               0-019-029  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   155,16                    35,600        35,600  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          John Jay High School:
19-0103   Reconstruction               0-020-036  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   08/03/18   05/08/17   155,15,16                317,491             0  JSS             0           0           0 Engineered Solutions              317,491        /  /                         07/10/19           
19-0526   Reconstruction               0-020-039  01/27/20     DONE    DONE       DONE      10/07/19   09/26/19   02/27/19   05/15/18   2,4,7,9,155,15,16     10,403,000             0  BMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         09/26/19           
20-1741   Reconstruction               0-020-040  06/30/21     DONE    DONE       DONE      05/21/21   05/20/21   04/14/21   04/19/21   2,7,10                   538,000             0  JLB             0           0           0 Rhinebeck Architecture                  0      08/31/21                       05/20/21           
21-1227   Reconstruction               0-020-041  05/23/22     DONE    DONE       DONE      02/02/22   02/02/22   10/12/21   05/17/16   2,4,13                   107,000       107,000  FMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         02/02/22           
22-1207   Reconstruction               0-020-042  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   2,4,7,9,13,155,15,16   3,937,240     3,937,240  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           
23-1108   Reconstruction               0-020-043                         UNREVIEWED         12/04/23   11/20/23   09/11/23   05/17/22   2,9,10,155,15,16               0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Facilities & Opps Bldg:
19-0104   Reconstruction               3-015-007  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   155,15,16                 36,304             0  JSS             0           0           0 Engineered Solutions               36,304        /  /                         07/10/19           
22-1208   Reconstruction               3-015-008  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   2,7,13,155,15            590,000             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          Salt Shed:
  -    PR New Construction             3-058-001                                              /  /       /  /     08/22/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-1209   New Construction             3-058-001  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/22/22   05/17/22   02 - 16                  281,250             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           

          Main Garage #1:
19-0105   Reconstruction               5-007-008  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   16                        16,934             0  JSS             0           0           0 Engineered Solutions               16,934        /  /                         07/10/19           
23-1109   Reconstruction               5-007-009                         UNREVIEWED         12/04/23   11/20/23   08/02/22   05/17/22   2,4,8,9,10,155,15,16           0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/20/23           

          Main Garage #2:
19-0106   Reconstruction               5-011-007  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   16                         7,726             0  JSS             0           0           0 Engineered Solutions                7,726        /  /                         07/10/19           

          Fishkill Plains Bus Garage:
19-0107   Reconstruction               5-047-002  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   16                        12,074             0  JSS             0           0           0 Engineered Solutions               12,074        /  /                         07/10/19           

          District-Wide:
  -    SB Reconstruction               7-999-006                                              /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA2               DONE                           /  /       /  /       /  /       /  /     10,16                          0             0  JSS             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               7-999-BA3                         CANCELLED            /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA4               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Dist. Office/Alt. HS @ 25 Corp Pk Dr:
19-0108   Reconstruction               8-052-002  09/20/19     DONE    DONE       DONE      07/18/19   07/10/19   07/09/18   05/08/17   16                        35,891             0  JSS             0           0           0 Engineered Solutions               35,891        /  /                         07/10/19           
  -       Reconstruction               8-052-003                                              /  /       /  /     10/12/21     /  /     2                              0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1210   Reconstruction               8-052-004  04/03/23     DONE    DONE       DONE      12/09/22   12/08/22   08/02/22   05/17/22   2,7,14,155,15,16         525,000             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         12/08/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MILLBROOK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-22-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elm Drive Elementary School:
20-0139   Reconstruction               0-010-016  09/30/20     DONE    DONE       DONE      07/29/20   07/17/20   05/21/20   06/09/20   16                       100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0      04/23/21                       07/17/20           
20-1688   Reconstruction               0-010-017  07/10/21     DONE    DONE       DONE      05/07/21   04/27/21   03/02/21   05/18/21   2,4,7,8,9,155,16         175,000       175,000  SLC             0           0           0 Bernier Carr Associates                 0        /  /                         04/27/21           

          Alden Place Elementary:
18-2036   Reconstruction               0-011-017  07/02/19     DONE    DONE       DONE      05/31/19   05/28/19   09/25/18   05/21/19   2,9,15                   175,000       175,000  BMJ             0           0           0 Bernier Carr Associates                 0      01/03/20                       05/28/19           
18-2057   Reconstruction               0-011-018  07/01/19     DONE    DONE       DONE      06/04/19   05/28/19   04/26/19   05/21/19   2,4,8,9,155,16           100,000       100,000  BMJ             0           0           0 Bernier Carr Associates                 0      04/20/20                       05/28/19           
20-0140   Reconstruction               0-011-019  09/30/20     DONE    DONE       DONE      07/29/20   07/17/20   05/21/20   06/09/20   16                       175,000       175,000  SLC             0           0           0 Bernier Carr Associates                 0      04/23/21                       07/17/20           

          Millbrook High School:
20-1655   Reconstruction               0-031-003  07/10/21     DONE    DONE       DONE      04/30/21   04/29/21   03/02/21   05/18/21   2,4,8,9,16               100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0      08/16/22                       04/29/21           
22-0204   Reconstruction               0-031-004  12/17/22     DONE    DONE       DONE      08/03/22   08/02/22   05/25/22   05/17/22   2,4,9                    100,000       100,000  SLC             0           0           0 Bernier Carr Associates                 0        /  /                         08/02/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES DUTCHESS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-90-00-00
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Salt Point Center(frmly Spec ed ctr):
19-0307PR Reconstruction               0-001-027               DONE                         08/28/19     /  /     04/22/19     /  /     2,4,7,8,9,10,155,15,           0             0  JSS             0           0           0                                         0        /  /                           /  /             
19-0464   Reconstruction               0-001-027  02/24/20     DONE    DONE       DONE      09/20/19   09/16/19   04/22/19   12/11/18   2,4,7,8,9,10,155,15,   1,030,000     1,030,000  JSS             0           0           0 Kaeyer, Garment & Davidson              0      12/12/22                       09/16/19           
19-1903   Reconstruction               0-001-028  08/18/20     DONE    DONE       DONE      06/29/20   06/11/20   04/23/20   05/13/20   2,9,155,15,16          1,210,852     1,210,852  JSS             0           0           0 Kaeyer, Garment & Davidson      1,210,852      12/13/21                       06/11/20           

          Area Occupational Center:
19-0308PR Additions and Alterations    0-003-027               DONE                         08/28/19     /  /     05/14/18     /  /     02 - 16                1,221,717             0  JSS             0           0           0                                 1,221,717        /  /                           /  /             
19-0465   Additions and Alterations    0-003-027  02/24/20     DONE    DONE       DONE      09/20/19   09/16/19   05/14/18   12/11/18   02 - 16               35,770,000    17,708,167  JSS             0           0           0 Kaeyer, Garment & Davidson              0      12/12/22                       09/16/19           
19-1904   Reconstruction               0-003-028  08/18/20     DONE    DONE       DONE      06/29/20   06/11/20   04/23/20   05/13/20   9,155,16               1,221,717     1,221,717  JSS             0           0           0 Kaeyer, Garment & Davidson      1,221,717      12/13/21                       06/11/20           
  -       Reconstruction               0-003-029                                              /  /       /  /     07/09/21     /  /     155,16                         0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0939   Reconstruction               0-003-030  04/11/23     DONE    DONE       DONE      11/09/22   11/04/22   07/18/22   08/25/22   9,155,16                 825,000       825,000  WLC             0           0           0 Kaeyer, Garment & Davidson              0        /  /                         11/04/22           

          Administration Bldg.:
19-1905   Reconstruction               1-002-014  08/18/20     DONE    DONE       DONE      06/29/20   06/11/20   04/23/20   05/13/20   9,155,16                  61,931             0  JSS             0           0           0 Kaeyer, Garment & Davidson         61,931      12/13/21                       06/11/20           

          New Facilities Building:
  -    PR New Construction             3-048-001                                              /  /       /  /     02/04/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             

          Greenhouse:
19-1058   New Construction             7-047-001  04/28/20     DONE    DONE       DONE      12/26/19   12/09/19   11/08/19   03/22/18   02 - 16                   25,000             0  JSS             0           0           0 Kaeyer, Garment & Davidson              0      09/02/20                       12/09/19           

          District-Wide:
21-0895   Reconstruction               7-999-004  03/14/22     DONE    DONE       DONE      12/13/21   12/13/21   01/21/20   11/10/21   15                       916,700       916,700  JLB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                         12/13/21           

          Dutchess C.C Cons.Swing.Space:
  -    SS Alterations                  8-049-001                                              /  /       /  /     06/07/21     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Ramapo for Children (Markus Lodge):
21-0170TQ Temporary Quarters           8-050-001  02/01/22     DONE    DONE       DONE      08/16/21   08/11/21   07/21/21     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         08/11/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED