BEACON CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-02-00-01
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
James Forrestal School:
21-1356 Reconstruction 0-002-020 05/17/22 DONE DONE DONE 02/23/22 02/18/22 11/19/21 10/26/21 2,8,9,155,16 835,550 835,550 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 02/18/22
22-0994 Reconstruction 0-002-021 04/07/23 DONE DONE DONE 11/16/22 11/15/22 01/19/22 10/26/21 2,155,15,16 1,897,450 1,897,450 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
South Ave Elementary School:
22-0995 Reconstruction 0-003-016 04/07/23 DONE DONE DONE 11/16/22 11/15/22 01/19/22 10/26/21 2,4,7,8,9,155,15,16 1,560,000 1,560,000 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
23-1641 Reconstruction 0-003-017 UNREVIEWED 03/15/24 03/15/24 03/01/24 02/26/24 9,16 300,000 300,000 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 03/15/24
Rombout Middle School:
21-1304 Reconstruction 0-004-021 05/10/22 DONE DONE DONE 02/16/22 02/10/22 10/28/21 10/26/21 7 2,706,850 2,706,850 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 02/10/22
21-1357 Reconstruction 0-004-022 05/17/22 DONE DONE DONE 02/23/22 02/18/22 11/19/21 10/26/21 2,16 1,800,300 1,800,300 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 02/18/22
22-0996 Reconstruction 0-004-023 04/07/23 DONE DONE DONE 11/16/22 11/15/22 01/19/22 10/26/21 2,4,8,9,155,15,16 3,981,850 3,981,850 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
Glenham Elementary School:
21-1358 Reconstruction 0-006-021 05/17/22 DONE DONE DONE 02/23/22 02/18/22 11/19/21 10/26/21 2,155,16 436,500 436,500 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 02/18/22
- PR Additions and Alterations 0-006-022 / / / / 01/19/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0997 Additions and Alterations 0-006-022 04/07/23 DONE DONE DONE 11/16/22 11/15/22 01/19/22 10/26/21 02 - 16 3,003,000 3,002,000 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
Sargent Elementary School:
21-1359 Reconstruction 0-008-019 05/17/22 DONE DONE DONE 02/23/22 02/18/22 11/19/21 10/26/21 2,9,155,16 1,183,200 1,183,200 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 02/18/22
22-0998 Reconstruction 0-008-020 04/07/23 DONE DONE DONE 11/16/22 11/15/22 01/19/22 10/26/21 2,4,8,9,155,15,16 1,427,800 1,427,800 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
Beacon High School:
19-1835 Reconstruction 0-020-010 06/22/20 DONE DONE DONE 06/10/20 06/05/20 04/30/20 04/28/20 7 2,970,000 2,970,000 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 06/05/20
21-1305 Reconstruction 0-020-011 05/10/22 DONE DONE DONE 02/16/22 02/10/22 10/28/21 10/26/21 7 1,309,800 1,309,800 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 02/10/22
22-0999 Reconstruction 0-020-012 04/07/23 DONE DONE DONE 11/16/22 11/15/22 01/19/22 10/26/21 2,8,9,155,15,16 3,693,700 3,693,700 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
New Bus Maintenance/Storage:
- PR Additions and Alterations 5-018-006 / / / / 08/12/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1000 Additions and Alterations 5-018-006 04/07/23 DONE DONE DONE 11/16/22 11/15/22 08/12/22 10/26/21 02 - 16 683,500 683,500 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 11/15/22
District-Wide:
18-2123SB Reconstruction 7-999-002 DONE / / / / 06/13/19 / / 13,16 0 0 JLB 0 0 0 0 / / / /
20-0341 Reconstruction 7-999-002 11/23/20 DONE DONE DONE 09/04/20 08/27/20 06/13/19 11/04/14 13,16 2,182,414 2,182,414 JLB 0 0 0 Tetra Tech Architects & Engin 0 / / 08/27/20
23-0629FA Reconstruction 7-999-003 01/25/24 DONE DONE DONE 10/06/23 09/29/23 05/15/23 08/28/23 1,000,000 0 JJH 0 0 0 Tetra Tech Architects & Engin 0 / / 09/29/23
xxTemp. Tent @ Sargent Elem.:
20-0519XX Reconstruction 8-025-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent 1 @ South Ave School:
20-0520XX Alterations 8-026-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #2 @ South Ave School:
20-0521XX Alterations 8-027-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
Tent #1 @ Beacon HS:
20-0522XX Alterations 8-028-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #2 @ Beacon HS:
20-0523XX Alterations 8-029-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #1 @ Glenham Elem.:
20-0524XX Reconstruction 8-030-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #2 @ Glenham Elem:
20-0525XX Reconstruction 8-031-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #1 @ Rombout MS:
20-0526XX Alterations 8-032-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #2 @ Rombout MS:
20-0527XX Alterations 8-033-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #1 @ James Forrestal:
20-0528XX Alterations 8-034-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
xxTent #2 @ James Forrestal:
20-0529XX Alterations 8-035-001 CANCELLED 10/06/20 09/30/20 08/31/20 / / 0 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 09/30/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HYDE PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-08-01-06
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Haviland Middle School(JrHigh):
18-1587 Reconstruction 0-001-029 08/05/19 DONE DONE DONE 03/05/19 02/20/19 09/24/18 05/15/18 2,4,9,10,155,15,16 5,199,679 5,199,679 BMJ 0 0 0 Collins & Scoville Architects 0 12/01/21 02/20/19
18-1691 Reconstruction 0-001-030 05/08/19 DONE DONE DONE 03/19/19 03/14/19 10/23/18 05/16/17 9,155,15,16 100,000 100,000 BMJ 0 0 0 Collins & Scoville Architects 0 05/26/20 03/14/19
22-0080 Reconstruction 0-001-031 10/26/22 DONE DONE DONE 07/13/22 07/12/22 03/17/22 05/18/21 9 100,000 100,000 SLC 0 0 0 CS Arch 0 04/11/23 07/12/22
22-2155 Reconstruction 0-001-032 10/02/23 DONE DONE DONE 05/05/23 05/05/23 02/06/23 02/22/22 2,8,9,14,16 1,728,572 1,728,572 MSK 0 0 0 CS Arch 0 / / 05/05/23
Roosevelt High School:
18-1588 Alterations 0-002-027 08/05/19 DONE DONE DONE 03/05/19 02/20/19 09/24/18 05/15/18 02 - 16 18,152,003 17,879,736 BMJ 0 0 0 Collins & Scoville Architects 0 05/03/23 02/20/19
19-1761 Reconstruction 0-002-028 06/16/20 DONE DONE DONE 05/26/20 03/13/20 05/02/19 05/21/19 2,16 1,015,512 1,015,512 JSS 0 0 0 Collins & Scoville Architects 0 05/05/23 03/13/20
20-1588XX Reconstruction 0-002-029 05/25/21 CANCELLED 04/14/21 03/24/21 07/02/20 05/21/19 9,10,15,16 100,000 100,000 JSS 0 0 0 Collins & Scoville Architects 0 / / 03/24/21
21-0802 Reconstruction 0-002-030 02/28/22 DONE DONE DONE 11/30/21 11/24/21 10/19/21 04/08/21 2 100,000 100,000 SLC 0 0 0 CS Arch 0 06/27/22 11/24/21
22-0434 Reconstruction 0-002-031 04/12/23 DONE DONE DONE 09/08/22 09/08/22 05/26/22 02/22/22 2,7,155,15,16 13,168,582 13,168,582 JLB 0 0 0 CS Arch 0 / / 09/08/22
23-1693 Reconstruction 0-002-032 UNREVIEWED 03/28/24 03/25/24 06/26/23 02/22/22 2,8,9,155,16 0 0 MSK 0 0 0 CS Arch 0 / / 03/25/24
Ralph R. Smith Elementary:
22-2156 Reconstruction 0-003-021 10/02/23 DONE DONE DONE 05/05/23 05/05/23 02/06/23 02/22/22 2,4,8,9,10,16 2,540,786 1,889,272 MSK 0 0 0 CS Arch 0 / / 05/05/23
Violet Avenue Elementary:
22-2157 Reconstruction 0-004-019 10/19/23 DONE DONE DONE 05/05/23 05/05/23 02/06/23 02/22/22 2,8,9,14,155,15,16 4,846,668 4,846,668 MSK 0 0 0 CS Arch 0 / / 05/05/23
Hyde Park Elementary:
22-0435 Reconstruction 0-005-024 04/12/23 DONE DONE DONE 09/08/22 09/08/22 05/26/22 02/22/22 2,7,155,15,16 903,649 903,649 JLB 0 0 0 CS Arch 0 / / 09/08/22
23-1694 Reconstruction 0-005-025 UNREVIEWED 03/28/24 03/25/24 06/26/23 02/22/22 2,8,9,155,15,16 0 0 MSK 0 0 0 CS Arch 0 / / 03/25/24
Netherwood Elementary School:
23-1695 Reconstruction 0-007-021 UNREVIEWED 03/28/24 03/25/24 06/26/23 02/22/22 2,4,8,9,155,15,16 0 0 MSK 0 0 0 CS Arch 0 / / 03/25/24
North Park Elementary School:
22-0984 Reconstruction 0-013-024 01/22/23 DONE DONE DONE 11/16/22 11/15/22 09/01/22 05/17/22 9,14,16 100,000 100,000 SLC 0 0 0 Collins & Scoville Architects 0 / / 11/15/22
23-1696 Reconstruction 0-013-025 UNREVIEWED 03/28/24 03/25/24 06/26/23 02/22/22 2,4,8,9,155,15,16 0 0 MSK 0 0 0 CS Arch 0 / / 03/25/24
Administration (see 1-017):
23-1697 Reconstruction 1-016-003 UNREVIEWED 03/28/24 03/25/24 06/26/23 02/22/22 2,8,9,155,15,16 0 0 MSK 0 0 0 CS Arch 0 / / 03/25/24
Concession Stand @ FDR HS:
19-1534DB Discovered Building 7-020-001 ADDENDUM REQ'D 03/03/20 03/03/20 02/24/20 / / 0 0 JSS 0 0 0 0 / / 03/03/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PAWLING CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-12-01-04
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Pawling Elementary School:
22-0974 Reconstruction 0-001-024 03/31/23 DONE DONE DONE 11/14/22 11/14/22 04/30/21 12/16/20 2,4,7,8,9,10,155,15, 12,253,000 12,229,600 WLC 0 0 0 Collins & Scoville Architects 0 / / 11/14/22
21-1242 Reconstruction 0-001-025 12/22/22 DONE DONE DONE 02/07/22 02/07/22 06/28/21 05/04/21 155,15,16 1,059,977 1,059,977 WLC 0 0 0 ECG Engineering, LLC 1,032,239 / / 02/07/22
Pawling High School:
- PR Additions and Alterations 0-002-021 / / / / 04/30/21 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-1675 Additions and Alterations 0-002-021 12/30/22 DONE DONE DONE 04/20/22 04/14/22 04/30/21 12/16/20 02 - 16 12,007,000 10,167,000 WLC 0 0 0 Collins & Scoville Architects 0 / / 04/14/22
21-0028 Reconstruction 0-002-022 11/12/21 DONE DONE DONE 07/12/21 07/08/21 04/30/21 12/16/20 2,9 4,862,500 4,468,950 JLB 0 0 0 Collins & Scoville Architects 0 06/15/23 07/08/21
21-1243 Reconstruction 0-002-023 12/22/22 DONE DONE DONE 02/09/22 02/07/22 06/28/21 05/04/21 155,16 743,346 743,346 WLC 0 0 0 ECG Engineering, LLC 710,763 / / 02/07/22
Pawling Middle School:
- PR Additions and Alterations 0-006-007 / / / / 04/30/21 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-0029 Reconstruction 0-006-008 11/12/21 DONE DONE DONE 07/12/21 07/08/21 04/30/21 12/16/20 2,8,9,10,155,15,16 4,577,500 3,912,639 JLB 0 0 0 Collins & Scoville Architects 0 06/15/23 07/08/21
21-1244 Reconstruction 0-006-009 12/22/22 DONE DONE DONE 02/07/22 02/07/22 06/28/21 05/04/21 2,7,155,15,16 433,936 433,936 WLC 0 0 0 ECG Engineering, LLC 398,908 / / 02/07/22
Storage Building:
21-0030 New Construction 2-015-001 11/12/21 DONE DONE DONE 07/12/21 07/08/21 04/30/21 12/16/20 02 - 16 133,500 0 JLB 0 0 0 Collins & Scoville Architects 0 06/15/23 07/08/21
New Transportation Facility:
- PR Additions and Alterations 5-013-002 / / / / 12/05/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
Press Box:
21-0031 New Construction 7-014-001 11/12/21 DONE DONE DONE 07/12/21 07/08/21 04/30/21 12/16/20 02 - 16 340,500 0 JLB 0 0 0 Collins & Scoville Architects 0 06/15/23 07/08/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
POUGHKEEPSIE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-15-00-01
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Columbus School #3 (AdminBldg):
18-1922 Reconstruction 0-001-012 07/19/19 DONE DONE DONE 05/02/19 05/01/19 12/22/16 10/23/16 2,155,15,16 543,000 543,000 JLB 0 0 0 Clark Patterson Lee 0 03/08/19 05/01/19
19-0280 Reconstruction 0-001-013 10/16/19 DONE DONE DONE 08/16/19 08/12/19 01/17/19 06/05/19 8,155,16 207,000 207,000 JLB 0 0 0 Clark Patterson Lee 0 / / 08/12/19
21-0742 Reconstruction 0-001-014 03/21/22 DONE DONE DONE 11/18/21 07/17/21 05/12/21 10/20/20 2,4,8,9,155,15,16 1,135,288 0 JLB 0 0 0 Clark Patterson Lee 0 / / 07/17/21
22-0330 Reconstruction 0-001-015 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 301,843 0 WLC 0 0 0 Clark Patterson Lee 0 / / 08/24/22
21-1857 Reconstruction 0-001-016 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,16 253,401 0 JLB 0 0 0 Engineered Solutions 253,401 / / 05/10/22
SFB Morse School #5:
20-1334 Reconstruction 0-002-012 02/18/20 DONE DONE DONE 02/19/21 02/05/21 12/20/19 03/04/20 155 90,000 90,000 JLB 0 0 0 Clark Patterson Lee 0 03/05/20 02/05/21
20-1689 Reconstruction 0-002-013 06/05/21 DONE DONE DONE 05/07/21 05/05/21 02/12/21 10/20/20 7 1,268,065 1,268,065 JLB 0 0 0 Clark Patterson Lee 0 11/16/21 05/05/21
21-0743 Reconstruction 0-002-014 03/21/22 DONE DONE DONE 11/18/21 11/17/21 05/12/21 10/20/20 2,4,8,9,155,15,16 1,774,783 1,774,783 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0682FA Reconstruction 0-002-015 12/29/22 DONE DONE DONE 10/12/22 08/30/22 11/12/21 08/24/21 155,16 1,077,979 1,077,979 WLC 0 0 0 Clark Patterson Lee 0 / / 08/30/22
22-0331 Reconstruction 0-002-016 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 2,270,085 2,270,085 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
21-1858 Reconstruction 0-002-017 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,16 352,901 352,901 JLB 0 0 0 Engineered Solutions 352,901 / / 05/10/22
23-0715 Reconstruction 0-002-018 UNREVIEWED
STARTED UNREVIEWED10/13/23 10/12/23 09/01/22 10/20/20 2,8,9 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
- Reconstruction 0-002-019 / / / / 04/12/24 / / 2,8,155,16 0 0 WLC 0 0 0 0 / / / /
Gov. Clinton School #8:
20-1690 Reconstruction 0-004-013 06/18/21 DONE DONE DONE 05/07/21 05/05/21 02/12/21 10/20/20 7 582,665 582,665 JLB 0 0 0 Clark Patterson Lee 0 11/09/21 05/05/21
21-0744 Reconstruction 0-004-014 03/21/22 DONE DONE DONE 11/18/21 11/17/21 05/12/21 10/20/20 2,4,8,9,155,15,16 1,714,750 1,714,750 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0683FA Reconstruction 0-004-015 12/29/22 DONE DONE DONE 10/12/22 08/30/22 11/18/21 08/24/21 155,16 735,479 735,479 WLC 0 0 0 Clark Patterson Lee 0 / / 08/30/22
22-0332 Reconstruction 0-004-016 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 1,442,748 1,442,748 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
21-1859 Reconstruction 0-004-017 11/22/22 DONE DONE DONE 05/23/22 05/20/22 02/22/22 06/16/21 155,16 232,578 232,578 JLB 0 0 0 Engineered Solutions 232,578 / / 05/20/22
23-0716 Reconstruction 0-004-018 UNREVIEWED
STARTED UNREVIEWED10/13/23 10/12/23 09/01/22 10/20/20 2,8,9 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
- Reconstruction 0-004-019 / / / / 04/12/24 / / 2,9,14,155,15,16 0 0 WLC 0 0 0 0 / / / /
C.B. Warring School #10:
21-0745 Reconstruction 0-005-013 03/21/22 DONE DONE DONE 11/18/21 11/17/21 05/12/21 10/20/20 2,7,155,15,16 3,517,278 3,517,278 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0684FA Reconstruction 0-005-014 12/29/22 DONE DONE DONE 10/12/22 08/30/22 11/12/21 08/24/21 155,16 1,186,542 1,186,542 WLC 0 0 0 Clark Patterson Lee 0 / / 08/30/22
21-1860 Reconstruction 0-005-015 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,16 264,220 264,220 JLB 0 0 0 Engineered Solutions 264,220 / / 05/10/22
22-0333 Reconstruction 0-005-016 12/15/22 DONE DONE DONE 08/24/22 08/24/22 06/08/22 10/20/20 2,8,9,155,16 285,875 285,875 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
23-0717 Reconstruction 0-005-017 UNREVIEWED
STARTED UNREVIEWED10/13/23 10/12/23 10/03/22 10/20/20 2,8,9,155,15,16 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
22-2142 Reconstruction 0-005-018 07/24/23 DONE DONE DONE 05/03/23 05/03/23 03/23/23 03/27/23 16 250,000 250,000 WLC 0 0 0 Clark Patterson Lee 0 / / 05/03/23
- Reconstruction 0-005-019 / / / / 04/12/24 / / 2,4,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Krieger School No. 11:
21-0746 Reconstruction 0-006-014 03/21/22 DONE DONE DONE 11/18/21 11/17/21 05/12/21 10/20/20 2,4,7,8,9,14,155,15, 2,147,020 2,147,020 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0334 Reconstruction 0-006-015 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 484,638 484,638 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
21-1861 Reconstruction 0-006-016 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,16 899,858 899,858 JLB 0 0 0 Engineered Solutions 899,858 / / 05/10/22
- XX Reconstruction 0-006-017 CANCELLED / / / / 04/22/22 / / 155,15,16 0 14,669,150 JLB 0 0 0 0 / / / /
23-0718 Reconstruction 0-006-018 UNREVIEWED 10/13/23 10/12/23 09/01/22 10/20/20 2,8,9 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
Junior/Senior High School:
21-0747 Reconstruction 0-007-018 03/21/22 DONE DONE DONE 11/18/21 11/17/21 02/12/21 10/20/20 4,8,9,155,15,16 9,731,410 9,731,410 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0335 Reconstruction 0-007-019 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 805,758 805,758 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
22-0624 Reconstruction 0-007-020 02/07/23 DONE DONE DONE 10/03/22 10/03/22 01/13/22 01/05/22 155,16 310,000 310,000 WLC 0 0 0 Clark Patterson Lee 0 11/29/23 10/03/22
22-1458 Reconstruction 0-007-021 05/03/23 DONE DONE DONE 01/09/23 01/09/23 01/13/22 12/01/21 15,16 92,735 92,735 WLC 0 0 0 Clark Patterson Lee 0 05/08/23 01/09/23
21-1862 Reconstruction 0-007-022 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,15,16 1,488,358 1,488,358 JLB 0 0 0 Engineered Solutions 1,488,358 / / 05/10/22
23-0719 Reconstruction 0-007-023 UNREVIEWED 10/13/23 10/12/23 09/01/22 10/20/20 2,8,9 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
23-0644 Reconstruction 0-007-024 04/11/24 DONE DONE DONE 10/06/23 10/04/23 08/02/23 02/01/23 155 4,500,000 4,500,000 WLC 0 0 0 Clark Patterson Lee 0 / / 10/04/23
- Reconstruction 0-007-025 / / / / 04/12/24 / / 2,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Early Learning Center (fka Smith ES):
- Reconstruction 0-008-020 / / / / 12/20/19 / / 155 0 0 JLB 0 0 0 0 / / / /
20-1691 Reconstruction 0-008-021 06/18/21 DONE DONE DONE 05/07/21 05/05/21 02/12/21 10/20/20 7 1,485,950 1,485,950 JLB 0 0 0 Clark Patterson Lee 0 11/09/21 05/05/21
21-0748 Reconstruction 0-008-022 03/21/22 DONE DONE DONE 11/18/21 11/17/21 05/12/21 10/20/20 2,4,8,9,155,15,16 1,725,208 1,725,208 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0336 Reconstruction 0-008-023 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 1,399,088 1,399,088 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
21-1863 Reconstruction 0-008-024 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,16 269,293 269,293 JLB 0 0 0 Engineered Solutions 269,293 / / 05/10/22
23-0720 Reconstruction 0-008-025 UNREVIEWED 10/13/23 10/12/23 09/01/22 10/20/20 2,8,9 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
- Reconstruction 0-008-026 / / / / 04/12/24 / / 2,9,14,155,15,16 0 0 WLC 0 0 0 0 / / / /
Middle School:
20-0866 Reconstruction 0-015-019 02/19/21 DONE DONE DONE 11/20/20 11/12/20 02/06/18 10/21/20 9,155,15,16 440,200 0 JLB 0 0 0 Clark Patterson Lee 0 / / 11/12/20
22-0196 Reconstruction 0-015-020 11/16/22 DONE DONE DONE 07/29/22 07/29/22 06/13/19 03/19/20 4 69,369 69,369 JLB 0 0 0 Clark Patterson Lee 0 04/19/22 07/29/22
21-0749 Reconstruction 0-015-021 03/21/22 DONE DONE DONE 11/18/21 11/17/21 05/12/21 10/20/20 2,4,7,8,9,155,15,16 6,461,060 6,461,060 JLB 0 0 0 Clark Patterson Lee 0 / / 11/17/21
22-0337 Reconstruction 0-015-022 12/15/22 DONE DONE DONE 08/24/22 08/24/22 12/15/21 10/20/20 2,8,9,155,16 651,755 651,755 JJH 0 0 0 Clark Patterson Lee 0 / / 08/24/22
21-1864 Reconstruction 0-015-023 11/22/22 DONE DONE DONE 05/23/22 05/10/22 02/22/22 06/16/21 155,15,16 1,993,398 1,993,398 JLB 0 0 0 Engineered Solutions 1,993,398 / / 05/10/22
22-1242 Reconstruction 0-015-024 03/03/23 DONE DONE DONE 12/14/22 12/13/22 08/03/22 08/17/22 14 897,000 897,000 WLC 0 0 0 Clark Patterson Lee 0 / / 12/13/22
23-0721 Reconstruction 0-015-025 UNREVIEWED 10/13/23 10/12/23 09/01/22 10/20/20 2,8,9 0 0 WLC 0 0 0 Clark Patterson Lee 0 / / 10/12/23
- Reconstruction 0-015-026 / / / / 04/12/24 / / 2,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Administration Building Demolition:
18-1689 Reconstruction 1-003-005 10/07/19 DONE DONE DONE 03/19/19 03/13/19 08/06/18 08/29/18 7 379,000 0 MTM 0 0 0 Clark Patterson Lee 0 / / 03/13/19
- Reconstruction 1-003-006 / / / / 04/19/21 / / 2 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 1-003-007 / / / / 01/17/24 / / 2,4,7,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
PCSD Admin Bldg:
- DB Discovered Building 1-026-001 / / / / 06/21/22 / / 0 0 FMJ 0 0 0 0 / / / /
XX Bus Garage Shops-DEMO XX:
- Reconstruction 5-009-003 / / / / 03/06/24 / / 2,4,155,15,16 0 0 WLC 0 0 0 0 / / / /
Poughkeepsie MS Cell Tower:
- PR New Construction 7-025-001 / / / / 02/22/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
District Wide:
21-1669SB Reconstruction 7-999-003 DONE / / / / 04/17/22 / / 16 0 0 JLB 0 0 0 0 / / / /
22-0461 Reconstruction 7-999-003 12/21/22 DONE DONE DONE 09/12/22 09/09/22 04/17/22 11/04/14 16 3,097,000 0 WLC 0 0 0 Clark Patterson Lee 0 / / 09/09/22
UPK Classrooms:
- TQ Temporary Quarters 8-024-001 / / / / 02/15/22 / / 0 0 JLB 0 0 0 0 / / / /
LittleWaterPrepChrtr(OurLadyMtCarmel:
22-0106TQ Temporary Quarters 8-001-001 12/09/22 DONE DONE DONE 07/18/22 07/18/22 02/07/22 / / 0 0 SLC 0 0 0 Tinkelman Architecture PLLC 0 / / 07/18/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
RED HOOK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-17-01-06
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Linden Ave Middle School:
20-1566 Reconstruction 0-003-006 05/04/21 DONE DONE DONE 04/07/21 04/01/21 03/12/21 06/09/20 155 100,000 100,000 JLB 0 0 0 Tetra Tech Engineers, Archite 0 06/30/21 04/01/21
22-0290 Reconstruction 0-003-007 02/22/23 DONE DONE DONE 08/17/22 08/17/22 11/18/21 06/21/19 16 525,108 525,108 WLC 0 0 0 Whitman 0 / / 08/17/22
21-1513 Reconstruction 0-003-008 04/13/22 DONE DONE DONE 03/15/22 03/14/22 03/07/22 05/18/21 16 100,000 100,000 JLB 0 0 0 Tetra Tech Architects and Eng 0 06/29/22 03/14/22
22-0506 Reconstruction 0-003-009 01/20/23 DONE DONE DONE 09/16/22 09/15/22 05/04/22 02/22/22 2,7,8,9,155,16 2,100,000 2,100,000 WLC 0 0 0 Tetra Tech Engineers, Archite 0 / / 09/15/22
Red Hook High School:
19-0123 Reconstruction 0-005-011 08/05/19 DONE DONE DONE 07/19/19 07/15/19 / / 05/15/18 155,16 100,000 100,000 JLB 0 0 0 Tetra Tech Architects and Eng 0 12/23/19 07/15/19
22-0291 Reconstruction 0-005-012 02/22/23 DONE DONE DONE 08/17/22 08/17/22 11/18/21 05/21/19 16 536,018 536,018 WLC 0 0 0 Whitman 0 / / 08/17/22
22-0598FC Reconstruction 0-005-013 11/10/22 DONE DONE DONE 09/28/22 07/22/22 01/26/22 06/08/22 9,10,155,15,16 450,000 450,000 WLC 0 0 0 Tetra Tech Engineers, Archite 0 09/20/23 07/22/22
22-0507 Reconstruction 0-005-014 01/20/23 DONE DONE DONE 09/16/22 09/15/22 05/04/22 02/22/22 2,4,8,9,155,16 13,650,000 13,650,000 WLC 0 0 0 Tetra Tech Engineers, Archite 0 / / 09/15/22
22-1817 Reconstruction 0-005-015 04/18/23 DONE DONE DONE 03/13/23 03/08/23 02/15/23 05/17/22 155,16 100,000 100,000 WLC 0 0 0 Tetra Tech Engineers, Archite 0 06/28/23 03/08/23
23-1720 Reconstruction 0-005-016 UNREVIEWED 04/01/24 03/28/24 03/01/24 04/12/23 16 100,000 0 WLC 0 0 0 Tetra Tech Architects and Eng 0 / / 03/28/24
Mill Rd. Elementary:
22-0292 Reconstruction 0-006-011 02/22/23 DONE DONE DONE 08/17/22 08/17/22 11/18/21 05/21/19 16 569,311 569,311 WLC 0 0 0 Whitman 0 / / 08/17/22
22-0508 Reconstruction 0-006-012 01/20/23 DONE DONE DONE 09/16/22 09/15/22 05/04/22 02/22/22 2,8,9,155,16 6,170,000 6,170,000 WLC 0 0 0 Tetra Tech Engineers, Archite 0 / / 09/15/22
23-1490 Reconstruction 0-006-013 UNREVIEWED 02/12/24 02/12/24 01/05/24 02/07/24 2 0 0 WLC 0 0 0 Tetra Tech Architects and Eng 0 / / 02/12/24
Mill Road School Garden Gazebo:
21-0396 New Construction 7-027-001 12/01/21 DONE DONE DONE 09/22/21 09/22/21 07/02/21 08/11/21 02 - 16 11,696 0 JLB 0 0 0 Tetra Tech Engineers, Archite 0 / / 09/22/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WAPPINGERS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-21-01-06
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Fishkill Plains Elementary:
19-0090 Reconstruction 0-001-017 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 80,530 80,529 JSS 0 0 0 Engineered Solutions 80,530 / / 07/10/19
21-1223 Reconstruction 0-001-019 05/23/22 DONE DONE DONE 02/02/22 02/02/22 10/12/21 05/17/16 2 457,000 457,000 FMJ 0 0 0 Rhinebeck Architecture 0 / / 02/02/22
22-1472 Reconstruction 0-001-020 04/03/23 DONE DONE DONE 01/11/23 12/08/22 08/02/22 05/17/22 2,7,8,9,10,155,15,16 3,104,110 3,104,110 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
Kinry Road Elementary:
19-0091 Reconstruction 0-002-020 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 44,648 0 JSS 0 0 0 Engineered Solutions 44,648 / / 07/10/19
22-1201 Reconstruction 0-002-022 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 16 35,600 35,600 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
James Evans Elementary:
19-0092 Reconstruction 0-003-027 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,16 415,830 0 JSS 0 0 0 Engineered Solutions 415,830 / / 07/10/19
22-1202 Reconstruction 0-003-028 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 155,15,16 100,000 100,000 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
Junior High School:
19-0093 Reconstruction 0-004-034 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,16 75,992 75,992 JSS 0 0 0 Engineered Solutions 75,992 / / 07/10/19
22-1203 Reconstruction 0-004-035 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 2,4,8,9,10,155,15,16 2,050,000 2,050,000 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
23-1102 Reconstruction 0-004-036 UNREVIEWED 12/04/23 11/20/23 09/11/23 05/17/22 2,8,9,10,155,15,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Fishkill Elementary School:
19-0094 Reconstruction 0-005-020 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 16 43,364 0 JSS 0 0 0 Engineered Solutions 43,364 / / 07/10/19
23-1103 Reconstruction 0-005-021 UNREVIEWED 12/04/23 11/20/23 08/02/22 05/17/22 155,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Vassar Road Elementary:
19-0095 Reconstruction 0-008-025 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 478,626 0 JSS 0 0 0 Engineered Solutions 478,626 / / 07/10/19
23-1104 Reconstruction 0-008-026 UNREVIEWED 12/04/23 11/20/23 08/02/22 05/17/22 2,7,9,155,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Roy Ketcham High School:
19-0096 Reconstruction 0-012-035 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 1,822,746 1,822,746 JSS 0 0 0 Engineered Solutions 1,822,746 / / 07/10/19
19-0524 Reconstruction 0-012-036 01/27/20 DONE DONE DONE 10/07/19 09/26/19 02/27/19 05/15/18 2,4,7,9,155,15,16 10,344,000 0 BMJ 0 0 0 Rhinebeck Architecture 0 / / 09/26/19
21-1224 Reconstruction 0-012-037 05/23/22 DONE DONE DONE 02/02/22 02/02/22 10/12/21 05/17/16 4 206,000 206,000 FMJ 0 0 0 Rhinebeck Architecture 0 / / 02/02/22
22-1204 Reconstruction 0-012-038 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 2,4,9,10,155,15,16 162,500 162,500 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
23-1105 Reconstruction 0-012-039 UNREVIEWED 12/04/23 11/20/23 09/11/23 05/17/22 2,9,10,155,15,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Brinckerhoff Elementary:
19-0097 Reconstruction 0-013-023 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 734,575 0 JSS 0 0 0 Engineered Solutions 734,575 / / 07/10/19
- Reconstruction 0-013-025 / / / / 08/02/22 / / 155,16 0 0 WLC 0 0 0 0 / / / /
Oak Grove Elementary:
19-0098 Reconstruction 0-014-022 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 51,636 51,636 JSS 0 0 0 Engineered Solutions 51,636 / / 07/10/19
22-1205 Reconstruction 0-014-023 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 2,155,16 912,500 912,500 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
Gayhead Elementary:
19-0099 Reconstruction 0-016-024 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 16 661,274 82,133 JSS 0 0 0 Engineered Solutions 661,274 / / 07/10/19
- Reconstruction 0-016-026 / / / / 08/02/22 / / 155,16 0 0 WLC 0 0 0 0 / / / /
Van Wyck Junior High School:
19-0100 Reconstruction 0-017-026 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,16 1,255,918 1,255,918 JSS 0 0 0 Engineered Solutions 1,255,918 / / 07/10/19
23-1106 Reconstruction 0-017-027 UNREVIEWED 12/04/23 11/20/23 08/02/22 05/17/22 2,4,7,8,9,155,15,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Sheafe Road Elementary:
19-0101 Reconstruction 0-018-019 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 181,550 181,549 JSS 0 0 0 Engineered Solutions 181,550 / / 07/10/19
21-1225 Reconstruction 0-018-021 05/23/22 DONE DONE DONE 02/02/22 02/02/22 10/12/21 05/17/16 2,4,155,15,16 819,000 819,000 FMJ 0 0 0 Rhinebeck Architecture 0 / / 02/02/22
23-1107 Reconstruction 0-018-022 UNREVIEWED 12/04/23 11/20/23 08/02/22 05/17/22 7,8,9,155,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Myers Corners Elementary:
19-0102 Reconstruction 0-019-025 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,16 84,626 0 JSS 0 0 0 Engineered Solutions 84,626 / / 07/10/19
19-0525 Reconstruction 0-019-027 01/27/20 DONE DONE DONE 10/07/19 09/26/19 02/27/19 05/15/18 2,4,7,9,155,15,16 2,728,000 0 BMJ 0 0 0 Rhinebeck Architecture 0 / / 09/26/19
21-1226 Reconstruction 0-019-028 05/23/22 DONE DONE DONE 02/02/22 02/02/22 10/12/21 05/17/16 2,4,13 59,000 59,000 FMJ 0 0 0 Rhinebeck Architecture 0 / / 02/02/22
22-1206 Reconstruction 0-019-029 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 155,16 35,600 35,600 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
John Jay High School:
19-0103 Reconstruction 0-020-036 09/20/19 DONE DONE DONE 07/18/19 07/10/19 08/03/18 05/08/17 155,15,16 317,491 0 JSS 0 0 0 Engineered Solutions 317,491 / / 07/10/19
19-0526 Reconstruction 0-020-039 01/27/20 DONE DONE DONE 10/07/19 09/26/19 02/27/19 05/15/18 2,4,7,9,155,15,16 10,403,000 0 BMJ 0 0 0 Rhinebeck Architecture 0 / / 09/26/19
20-1741 Reconstruction 0-020-040 06/30/21 DONE DONE DONE 05/21/21 05/20/21 04/14/21 04/19/21 2,7,10 538,000 0 JLB 0 0 0 Rhinebeck Architecture 0 08/31/21 05/20/21
21-1227 Reconstruction 0-020-041 05/23/22 DONE DONE DONE 02/02/22 02/02/22 10/12/21 05/17/16 2,4,13 107,000 107,000 FMJ 0 0 0 Rhinebeck Architecture 0 / / 02/02/22
22-1207 Reconstruction 0-020-042 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 2,4,7,9,13,155,15,16 3,937,240 3,937,240 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
23-1108 Reconstruction 0-020-043 UNREVIEWED 12/04/23 11/20/23 09/11/23 05/17/22 2,9,10,155,15,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Facilities & Opps Bldg:
19-0104 Reconstruction 3-015-007 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 155,15,16 36,304 0 JSS 0 0 0 Engineered Solutions 36,304 / / 07/10/19
22-1208 Reconstruction 3-015-008 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 2,7,13,155,15 590,000 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
Salt Shed:
- PR New Construction 3-058-001 / / / / 08/22/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-1209 New Construction 3-058-001 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/22/22 05/17/22 02 - 16 281,250 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
Main Garage #1:
19-0105 Reconstruction 5-007-008 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 16 16,934 0 JSS 0 0 0 Engineered Solutions 16,934 / / 07/10/19
23-1109 Reconstruction 5-007-009 UNREVIEWED 12/04/23 11/20/23 08/02/22 05/17/22 2,4,8,9,10,155,15,16 0 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 11/20/23
Main Garage #2:
19-0106 Reconstruction 5-011-007 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 16 7,726 0 JSS 0 0 0 Engineered Solutions 7,726 / / 07/10/19
Fishkill Plains Bus Garage:
19-0107 Reconstruction 5-047-002 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 16 12,074 0 JSS 0 0 0 Engineered Solutions 12,074 / / 07/10/19
District-Wide:
- SB Reconstruction 7-999-006 / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 10,16 0 0 JSS 0 0 0 0 / / / /
- XX Reconstruction 7-999-BA3 CANCELLED / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA4 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
Dist. Office/Alt. HS @ 25 Corp Pk Dr:
19-0108 Reconstruction 8-052-002 09/20/19 DONE DONE DONE 07/18/19 07/10/19 07/09/18 05/08/17 16 35,891 0 JSS 0 0 0 Engineered Solutions 35,891 / / 07/10/19
- Reconstruction 8-052-003 / / / / 10/12/21 / / 2 0 0 JLB 0 0 0 0 / / / /
22-1210 Reconstruction 8-052-004 04/03/23 DONE DONE DONE 12/09/22 12/08/22 08/02/22 05/17/22 2,7,14,155,15,16 525,000 0 WLC 0 0 0 Rhinebeck Architecture 0 / / 12/08/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES DUTCHESS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-90-00-00
last updated on 04/18/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Salt Point Center(frmly Spec ed ctr):
19-0307PR Reconstruction 0-001-027 DONE 08/28/19 / / 04/22/19 / / 2,4,7,8,9,10,155,15, 0 0 JSS 0 0 0 0 / / / /
19-0464 Reconstruction 0-001-027 02/24/20 DONE DONE DONE 09/20/19 09/16/19 04/22/19 12/11/18 2,4,7,8,9,10,155,15, 1,030,000 1,030,000 JSS 0 0 0 Kaeyer, Garment & Davidson 0 12/12/22 09/16/19
19-1903 Reconstruction 0-001-028 08/18/20 DONE DONE DONE 06/29/20 06/11/20 04/23/20 05/13/20 2,9,155,15,16 1,210,852 1,210,852 JSS 0 0 0 Kaeyer, Garment & Davidson 1,210,852 12/13/21 06/11/20
Area Occupational Center:
19-0308PR Additions and Alterations 0-003-027 DONE 08/28/19 / / 05/14/18 / / 02 - 16 1,221,717 0 JSS 0 0 0 1,221,717 / / / /
19-0465 Additions and Alterations 0-003-027 02/24/20 DONE DONE DONE 09/20/19 09/16/19 05/14/18 12/11/18 02 - 16 35,770,000 17,708,167 JSS 0 0 0 Kaeyer, Garment & Davidson 0 12/12/22 09/16/19
19-1904 Reconstruction 0-003-028 08/18/20 DONE DONE DONE 06/29/20 06/11/20 04/23/20 05/13/20 9,155,16 1,221,717 1,221,717 JSS 0 0 0 Kaeyer, Garment & Davidson 1,221,717 12/13/21 06/11/20
- Reconstruction 0-003-029 / / / / 07/09/21 / / 155,16 0 0 JLB 0 0 0 0 / / / /
22-0939 Reconstruction 0-003-030 04/11/23 DONE DONE DONE 11/09/22 11/04/22 07/18/22 08/25/22 9,155,16 825,000 825,000 WLC 0 0 0 Kaeyer, Garment & Davidson 0 / / 11/04/22
Administration Bldg.:
19-1905 Reconstruction 1-002-014 08/18/20 DONE DONE DONE 06/29/20 06/11/20 04/23/20 05/13/20 9,155,16 61,931 0 JSS 0 0 0 Kaeyer, Garment & Davidson 61,931 12/13/21 06/11/20
New Facilities Building:
- PR New Construction 3-048-001 / / / / 02/04/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
Greenhouse:
19-1058 New Construction 7-047-001 04/28/20 DONE DONE DONE 12/26/19 12/09/19 11/08/19 03/22/18 02 - 16 25,000 0 JSS 0 0 0 Kaeyer, Garment & Davidson 0 09/02/20 12/09/19
District-Wide:
21-0895 Reconstruction 7-999-004 03/14/22 DONE DONE DONE 12/13/21 12/13/21 01/21/20 11/10/21 15 916,700 916,700 JLB 0 0 0 Kaeyer, Garment & Davidson 0 / / 12/13/21
Dutchess C.C Cons.Swing.Space:
- SS Alterations 8-049-001 / / / / 06/07/21 / / 0 0 JLB 0 0 0 0 / / / /
Ramapo for Children (Markus Lodge):
21-0170TQ Temporary Quarters 8-050-001 02/01/22 DONE DONE DONE 08/16/21 08/11/21 07/21/21 / / 0 0 JLB 0 0 0 0 / / 08/11/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED