ALDEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-01-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Intermediate/Middle School:
19-0392 Reconstruction 0-004-020 12/13/19 DONE DONE DONE 09/10/19 09/04/19 12/10/18 12/12/17 2,4,7,8,9,10,155,15, 3,068,796 3,068,796 JLB 0 0 0 Young And Wright Architectura 0 10/09/20 09/04/19
19-0042 Reconstruction 0-004-021 09/05/19 DONE DONE DONE 07/09/19 07/01/19 03/28/19 05/21/19 2,8,9 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 05/19/20 07/01/19
19-1823 Reconstruction 0-004-022 09/08/20 DONE DONE DONE 06/09/20 05/28/20 03/09/20 06/09/20 2,8,9 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 04/29/21 05/28/20
21-0453 Reconstruction 0-004-023 01/28/22 DONE DONE DONE 09/30/21 09/30/21 04/02/21 12/12/17 2,8,9,15,16 916,625 916,625 JLB 0 0 0 Young And Wright Architectura 0 12/11/23 09/30/21
23-0162 Reconstruction 0-004-024 11/01/23 DONE DONE DONE 07/28/23 07/27/23 04/13/23 05/16/23 2,4,8,9 100,000 100,000 JJH 0 0 0 Young And Wright Architectura 0 / / 07/27/23
Townline Primary School:
19-0393 Reconstruction 0-008-016 12/13/19 DONE DONE DONE 09/10/19 09/04/19 12/10/18 12/12/17 2,4,7,8,9,155,15,16 2,219,431 2,219,431 JLB 0 0 0 Young And Wright Architectura 0 10/09/20 09/04/19
High School:
19-0394 Reconstruction 0-014-021 12/13/19 DONE DONE DONE 09/10/19 09/04/19 12/10/18 12/12/17 2,7,9,155,16 748,619 748,619 JLB 0 0 0 Young And Wright Architectura 0 10/09/22 09/04/19
21-0454 Reconstruction 0-014-022 01/28/22 DONE DONE DONE 01/28/22 09/30/21 04/02/21 12/12/17 2,4,8,9,10,155,15,16 1,165,550 1,165,550 JLB 0 0 0 Young And Wright Architectura 0 11/01/23 09/30/21
22-0231 Reconstruction 0-014-023 10/13/22 DONE DONE DONE 08/05/22 08/03/22 06/28/22 05/17/22 9 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 05/25/23 08/03/22
Bus Garage:
19-0395 Reconstruction 5-001-012 12/13/19 DONE DONE DONE 09/10/19 09/04/19 12/10/18 12/12/17 2,15,16 538,134 538,134 JLB 0 0 0 Young And Wright Architectura 0 10/09/20 09/04/19
20-1893 Reconstruction 5-001-013 07/02/21 DONE DONE DONE 06/16/21 06/14/21 05/19/21 05/18/21 4 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 05/11/22 06/14/21
New Bus Garage:
23-0587PR New Construction 5-023-001 DONE 10/02/23 / / 09/27/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
Tent #1 @ Alden Primary SChool:
- PR New Construction 7-020-001 / / / / 03/17/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-1845TQ Temporary Quarters 7-020-001 05/26/22 DONE DONE DONE 05/20/22 05/18/22 03/17/22 / / 02 - 16 0 0 JLB 0 0 0 Young And Wright Architectura 0 / / 05/18/22
Tent #1 @ Alden Intermediate:
- PR New Construction 7-021-001 / / / / 03/17/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-1846TQ Temporary Quarters 7-021-001 05/26/22 DONE DONE DONE 05/20/22 05/19/22 03/17/22 / / 02 - 16 0 0 JLB 0 0 0 Young And Wright Architectura 0 / / 05/19/22
Tent #1 @ Alden High School:
21-1900TQ Temporary Quarters 7-022-001 05/26/22 DONE DONE DONE / / / / 05/18/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
AMHERST CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-02-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School:
18-1910 Reconstruction 0-001-028 08/01/19 DONE DONE DONE 04/30/19 04/15/19 03/10/17 12/13/16 2,4,8,9,10,14,155,15 9,003,073 9,003,073 BMJ 0 0 0 Young And Wright Architectura 0 / / 04/15/19
Amherst Middle School:
19-0569 Reconstruction 0-002-023 12/10/19 DONE DONE DONE 10/17/19 09/30/19 08/29/19 04/16/19 2,15,16 100,000 100,000 BMJ 0 0 0 Young And Wright Architectura 0 10/01/20 09/30/19
- Reconstruction 0-002-024 / / / / 07/13/23 / / 2,4,7,8,9,13,155,15, 0 0 JJH 0 0 0 0 / / / /
Smallwood Drive Elementary:
23-0343 Reconstruction 0-004-023 03/04/24 DONE DONE DONE 08/29/23 08/24/23 03/24/23 12/13/22 2,8,9,10,155,15,16 5,124,227 5,124,227 JJH 0 0 0 Young And Wright Architectura 0 / / 08/24/23
- Reconstruction 0-004-024 / / / / 07/13/23 / / 2,8,9,155,15,16 0 17,715,780 JJH 0 0 0 0 / / / /
Windermere Elementary:
21-0569 Reconstruction 0-007-021 03/04/22 DONE DONE DONE 10/22/21 10/22/21 08/09/21 06/16/20 2,8 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 / / 10/22/21
23-0344 Reconstruction 0-007-022 03/04/24 DONE DONE DONE 08/29/23 08/24/23 03/24/23 12/13/22 2,7,8,9,10,155,15,16 5,100,006 5,100,006 JJH 0 0 0 Young And Wright Architectura 0 / / 08/24/23
- Reconstruction 0-007-023 / / / / 07/13/23 / / 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 0 / / / /
23-1310 Reconstruction 0-007-024 02/08/24 DONE DONE DONE 01/02/24 09/25/23 09/15/23 05/17/22 8 100,000 100,000 JJH 0 0 0 Young And Wright Architectura 0 / / 09/25/23
- SB Additions and Alterations 0-007-025 / / / / 10/05/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
23-0618SB Additions and Alterations 0-007-025 DONE / / / / 10/05/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
Concession Building:
- New Construction 7-017-001 / / / / 07/13/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
District Wide:
- XX Reconstruction 7-999-002 CANCELLED / / / / 11/26/19 / / 9,16 0 0 BMJ 0 0 0 0 / / / /
19-0864SB Reconstruction 7-999-002 DONE / / / / 11/26/19 / / 9,16 0 0 BMJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WILLIAMSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-02-03-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Dodge Elem. School 4:
18-1535 Reconstruction 0-002-016 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 212,303 212,303 MTM 0 0 0 Wendel Companies 212,303 08/12/21 01/17/19
20-1630 Reconstruction 0-002-017 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 1,024,393 984,509 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1749 Reconstruction 0-002-018 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2107 Reconstruction 0-002-019 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,7,9,10,155,15,16 9,882,760 9,882,760 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Maple East Elem:
18-1536 Reconstruction 0-003-019 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 228,139 228,139 MTM 0 0 0 Wendel Companies 228,139 08/12/21 01/17/19
20-1631 Reconstruction 0-003-020 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 5,201,177 3,908,279 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1750 Reconstruction 0-003-021 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2108 Reconstruction 0-003-022 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,7,9,10,155,15,16 9,829,357 9,829,357 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Mill Middle School 2:
19-0140 Reconstruction 0-004-025 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/14/17 12/13/18 4,8,9,10,155,15,16 1,449,650 1,449,650 JLB 0 0 0 Kideney Architects, P.C. 0 05/10/21 07/09/19
18-1537 Reconstruction 0-004-026 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 298,667 298,667 MTM 0 0 0 Wendel Companies 298,667 10/26/21 01/17/19
- PR Additions and Alterations 0-004-027 / / / / 12/10/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-1744 Additions and Alterations 0-004-027 10/04/21 DONE DONE DONE 05/21/21 04/26/21 12/10/19 06/09/20 02 - 16 1,641,939 1,641,939 JLB 0 0 0 Trautmn Associates Architects 0 / / 04/26/21
20-1751 Reconstruction 0-004-028 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
21-0366 Reconstruction 0-004-029 STARTED DONE DONE 09/17/21 09/16/21 08/06/21 12/13/18 7 2,394,000 0 JLB 0 0 0 Kideney Architects, P.C. 0 / / 09/16/21
South Senior High:
19-0141 Additions and Alterations 0-005-026 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/13/17 12/13/18 02 - 16 8,692,995 6,809,329 JLB 0 0 0 Kideney Architects, P.C. 0 09/07/21 07/09/19
18-1538 Reconstruction 0-005-027 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 405,736 405,736 MTM 0 0 0 Wendel Companies 405,736 12/07/21 01/17/19
20-1745 Reconstruction 0-005-028 10/04/21 DONE DONE DONE 05/21/21 04/26/21 12/10/19 06/09/20 2,4,8,9,10,155,15,16 2,257,088 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 04/26/21
20-1752 Reconstruction 0-005-029 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,888 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
Forest Elementary #5:
18-1539 Reconstruction 0-006-018 02/05/20 DONE DONE DONE 02/26/19 02/08/19 10/04/18 09/13/16 155,16 207,254 207,254 MTM 0 0 0 Wendel Companies 207,254 08/04/21 02/08/19
20-1632 Reconstruction 0-006-019 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 5,749,620 3,873,910 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1753 Reconstruction 0-006-020 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2109 Reconstruction 0-006-021 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,7,9,10,155,15,16 9,749,474 9,749,474 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Heim Middle School 7:
19-0144 Reconstruction 0-007-018 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/14/17 12/13/18 4,8,9,10,155,15,16 1,181,515 1,181,515 JLB 0 0 0 Kideney Architects, P.C. 0 05/10/21 07/09/19
18-1540 Reconstruction 0-007-019 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 233,455 233,455 MTM 0 0 0 Wendel Companies 233,455 10/28/21 01/17/19
20-1633 Reconstruction 0-007-020 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 2,100,834 0 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1754 Reconstruction 0-007-021 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
Heim Elem School (#8):
18-1541 Reconstruction 0-008-020 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 218,189 218,189 MTM 0 0 0 Wendel Companies 218,189 08/05/21 01/17/19
20-1634 Reconstruction 0-008-021 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 2,214,031 1,283,181 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1755 Reconstruction 0-008-022 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2110 Reconstruction 0-008-023 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,7,9,10,155,15,16 9,901,215 9,901,215 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Maple West Elementary School #9:
19-0145 Reconstruction 0-009-015 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/14/17 12/13/18 7 2,780,504 2,780,504 JLB 0 0 0 Kideney Architects, P.C. 0 01/01/22 07/09/19
18-1542 Reconstruction 0-009-016 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 225,926 225,926 MTM 0 0 0 Wendel Companies 225,926 08/17/21 01/17/19
20-1635 Reconstruction 0-009-017 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 1,519,292 1,330,939 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1756 Reconstruction 0-009-018 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2111 Reconstruction 0-009-019 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,7,9,10,155,15,16 10,218,310 10,218,310 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
North High School:
19-0142 Additions and Alterations 0-010-026 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/13/17 12/13/18 02 - 16 7,669,053 6,113,579 JLB 0 0 0 Kideney Architects, P.C. 0 09/07/21 07/09/19
18-1543 Reconstruction 0-010-027 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 672,345 672,345 MTM 0 0 0 Wendel Companies 672,345 08/19/21 01/17/19
- PR Additions and Alterations 0-010-028 / / / / 12/10/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-1746 Additions and Alterations 0-010-028 10/04/21 DONE DONE DONE 05/21/21 04/26/21 12/10/19 06/09/20 02 - 16 10,977,493 10,977,493 JLB 0 0 0 Trautmn Associates Architects 0 / / 04/26/21
20-1757 Reconstruction 0-010-029 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,888 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
Country Pkwy. Elem. 11:
18-1544 Reconstruction 0-011-016 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 230,894 230,894 MTM 0 0 0 Wendel Companies 230,894 08/19/21 01/17/19
- PR Additions and Alterations 0-011-017 / / / / 01/02/20 / / 02 - 16 0 11,829,240 JLB 0 0 0 0 / / / /
20-1636 Additions and Alterations 0-011-017 09/09/21 DONE DONE DONE 04/27/21 04/16/21 01/02/20 06/09/20 02 - 16 4,971,149 3,747,364 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1758 Reconstruction 0-011-018 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2112 Reconstruction 0-011-019 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,7,9,10,155,15,16 9,960,180 9,960,180 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Casey Middle School:
19-0146 Reconstruction 0-012-022 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/13/17 12/13/18 4,8,9,10,155,15,16 1,310,586 1,310,586 JLB 0 0 0 Kideney Architects, P.C. 0 09/07/21 07/09/19
18-1545 Reconstruction 0-012-023 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 393,505 393,505 MTM 0 0 0 Wendel Companies 393,505 08/19/21 01/17/19
20-1637 Reconstruction 0-012-024 09/09/21 DONE DONE DONE 04/27/21 04/16/21 12/26/19 06/09/20 2,4,7,8,9,10,155,15, 947,397 934,111 JLB 0 0 0 Wendel Companies 0 / / 04/16/21
20-1759 Reconstruction 0-012-025 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
23-1592 Reconstruction 0-012-026 UNREVIEWED 03/06/24 03/04/24 10/04/23 04/19/23 4,9 3,800,000 0 WLC 0 0 0 Wendel Companies 0 / / 03/04/24
Williamsville East H.S.:
19-0147 Additions and Alterations 0-016-024 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/14/17 12/13/18 02 - 16 8,445,951 7,219,152 JLB 0 0 0 Kideney Architects, P.C. 0 09/07/21 07/09/19
18-1546 Reconstruction 0-016-025 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 982,533 982,533 MTM 0 0 0 Wendel Companies 982,533 08/12/21 01/17/19
- PR Additions and Alterations 0-016-026 / / / / 12/10/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-1747 Additions and Alterations 0-016-026 10/04/21 DONE DONE DONE 05/21/21 04/26/21 12/10/19 06/09/20 02 - 16 1,704,014 1,704,014 JLB 0 0 0 Trautmn Associates Architects 0 / / 04/26/21
20-1760 Reconstruction 0-016-027 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 15,888 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
22-2113 Reconstruction 0-016-028 10/06/23 DONE DONE DONE 05/01/23 05/01/23 08/08/22 05/17/22 2,4,16 1,232,741 1,232,741 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Transit Middle School:
19-0143 Reconstruction 0-029-016 11/05/19 DONE DONE DONE 07/23/19 07/09/19 12/13/17 12/13/18 4,7,8,9,10,155,15,16 5,129,676 5,129,676 JLB 0 0 0 Kideney Architects, P.C. 0 09/07/21 07/09/19
18-1547 Reconstruction 0-029-017 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 319,895 319,895 MTM 0 0 0 Wendel Companies 319,895 08/05/21 01/17/19
- PR Additions and Alterations 0-029-018 / / / / 12/10/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-1748 Additions and Alterations 0-029-018 10/04/21 DONE DONE DONE 05/21/21 04/26/21 12/10/19 06/09/20 02 - 16 2,709,705 2,709,705 JLB 0 0 0 Trautmn Associates Architects 0 / / 04/26/21
20-1761 Reconstruction 0-029-019 09/17/21 DONE DONE DONE 05/21/21 05/10/21 05/03/21 06/09/20 10 19,600 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
Aim Building:
20-1762XX Reconstruction 0-041-007 CANCELLED 05/21/21 05/10/21 05/03/21 06/09/20 10 15,887 0 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/10/21
Dodge ES Boiler/Chiller Building:
- PR New Construction 0-060-001 / / / / 02/23/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2114 New Construction 0-060-001 10/06/23 DONE DONE DONE 05/01/23 05/01/23 02/23/23 05/17/22 02 - 16 557,378 554,681 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Maple East ES Boiler/Chiller Buildin:
- PR New Construction 0-061-001 / / / / 02/23/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2115 New Construction 0-061-001 10/06/23 DONE DONE DONE 05/01/23 05/01/23 02/23/23 05/17/22 02 - 16 556,872 554,584 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Forest ES Boiler/Chiller Building:
- PR New Construction 0-062-001 / / / / 02/23/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2116 New Construction 0-062-001 10/06/23 DONE DONE DONE 05/01/23 05/01/23 02/23/23 05/17/22 02 - 16 555,858 0 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Heim ES Boiler/Chiller Building:
- PR New Construction 0-063-001 / / / / 02/23/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2117 New Construction 0-063-001 10/06/23 DONE DONE DONE 05/01/23 05/01/23 02/23/23 05/17/22 02 - 16 557,378 0 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Maple West ES Boiler/Chiller Buildin:
- PR New Construction 0-064-001 / / / / 02/23/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2118 New Construction 0-064-001 10/06/23 DONE DONE DONE 05/01/23 05/01/23 02/23/23 05/17/22 02 - 16 559,911 555,166 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Country Parkway Boiler/Chiller Bldg.:
- PR New Construction 0-065-001 / / / / 02/23/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2119 New Construction 0-065-001 10/06/23 DONE DONE DONE 05/01/23 05/01/23 02/23/23 05/17/22 02 - 16 557,884 554,778 WLC 0 0 0 Kideney Architects, P.C. 0 / / 05/01/23
Bus Garage:
18-1548 Reconstruction 5-001-005 02/05/20 DONE DONE DONE 02/26/19 01/17/19 10/04/18 09/13/16 155,16 50,551 50,551 MTM 0 0 0 Wendel Companies 50,551 10/26/21 01/17/19
District-Wide:
- Reconstruction 7-999-007 / / / / 09/17/20 / / 16 0 0 JLB 0 0 0 0 / / / /
Maple West - Temp Classrooms:
23-0724TQ Temporary Quarters 8-066-001 UNREVIEWED
DONE DONE 10/16/23 10/13/23 06/21/23 / / 0 0 WLC 0 0 0 0 / / 10/13/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SWEET HOME CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-02-07-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Dexter Terrace Sch(AltEd&LsdToBOCES):
21-0018 Reconstruction 0-002-008 10/26/21 DONE DONE DONE 07/08/21 07/08/21 11/13/19 10/22/19 2,4,7,8,9,10,13,155, 2,537,060 2,537,060 SLC 0 0 0 Young And Wright Architectura 0 09/15/23 07/08/21
Sweet Home High School:
19-0424 Reconstruction 0-003-015 01/06/20 DONE DONE DONE 09/18/19 09/05/19 02/04/19 05/15/18 2,4,8,9,16 75,000 75,000 SLC 0 0 0 Young And Wright Architectura 0 06/23/20 09/05/19
21-0019 Reconstruction 0-003-016 10/26/21 DONE DONE DONE 07/08/21 07/08/21 11/13/19 10/22/19 2,4,7,8,9,10,13,155, 9,936,817 9,936,817 SLC 0 0 0 Young And Wright Architectura 0 10/15/23 07/08/21
19-1286 Reconstruction 0-003-017 02/11/20 DONE DONE DONE 01/27/20 01/27/20 11/18/19 12/17/19 2,4,7,9,15 694,979 694,979 SLC 0 0 0 Young And Wright Architectura 0 09/15/20 01/27/20
20-0477 Reconstruction 0-003-018 02/05/21 DONE DONE DONE 09/29/20 09/24/20 06/15/20 05/21/19 2,4,8,9,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/14/22 09/24/20
21-0490 Reconstruction 0-003-019 02/19/22 DONE DONE DONE 10/08/21 10/07/21 03/26/21 06/16/20 2,4,8,9,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/09/23 10/07/21
22-2141 Reconstruction 0-003-020 07/21/23 DONE DONE DONE 05/03/23 05/03/23 11/15/22 05/17/22 2,4,8,9,16 100,000 100,000 MSK 0 0 0 Young And Wright Architectura 0 / / 05/03/23
Glendale Elementary:
21-0020 Reconstruction 0-006-011 10/26/21 DONE DONE DONE 07/08/21 07/08/21 11/13/19 10/22/19 2,4,7,8,9,10,13,155, 2,537,060 2,537,060 SLC 0 0 0 Young And Wright Architectura 0 10/15/23 07/08/21
Maplemere Elementary:
21-0021 Reconstruction 0-007-011 10/26/21 DONE DONE DONE 07/08/21 07/08/21 11/13/19 10/22/19 2,4,7,8,9,10,13,155, 1,057,108 1,057,108 SLC 0 0 0 Young And Wright Architectura 0 10/15/23 07/08/21
Middle School:
- PR Additions and Alterations 0-008-012 / / / / 11/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-0022 Additions and Alterations 0-008-012 10/26/21 DONE DONE DONE 07/08/21 07/08/21 11/13/19 10/22/19 02 - 16 2,748,481 2,748,481 SLC 0 0 0 Young And Wright Architectura 0 10/15/23 07/08/21
Willow Ridge Elementary:
- PR Additions and Alterations 0-009-011 / / / / 11/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-0023 Additions and Alterations 0-009-011 10/26/21 DONE DONE DONE 07/08/21 07/08/21 11/13/19 10/22/19 02 - 16 1,057,108 1,057,108 SLC 0 0 0 Young And Wright Architectura 0 10/25/23 07/08/21
Heritage Heights Elementary:
20-0051 Reconstruction 0-012-011 10/23/20 DONE DONE DONE 07/14/20 06/30/20 11/13/19 08/20/19 2,4,7,8,9,10,13,155, 2,610,495 2,610,495 SLC 0 0 0 Young And Wright Architectura 0 05/10/22 06/30/20
21-0024 Reconstruction 0-012-012 10/26/21 DONE DONE DONE 07/08/21 07/08/21 06/24/21 10/22/19 2,4,7,8,9,10,13,155, 1,268,530 1,268,530 SLC 0 0 0 Young And Wright Architectura 0 10/15/23 07/08/21
Metal Storage Barn (Bus Garage):
20-0113DB Discovered Building 2-015-001 11/24/20 DONE DONE DONE 07/24/20 07/22/20 02/03/96 / / 0 0 MEM 0 0 0 0 / / 07/22/20
Athletic Storage Building:
20-0117DB Discovered Building 2-020-001 08/10/20 DONE DONE DONE 07/24/20 07/22/20 05/11/17 / / 02 - 16 0 0 SLC 0 0 0 0 / / 07/22/20
Service Ctr-Bus Garage,FoodServ,B&Gr:
18-2047PR Additions and Alterations 4-001-008 UNREVIEWED 06/03/19 06/03/19 05/21/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / 06/03/19
20-0052 Additions and Alterations 4-001-008 10/23/20 DONE DONE DONE 07/14/20 06/30/20 05/21/19 08/20/19 02 - 16 13,821,116 13,821,116 SLC 0 0 0 Young And Wright Architectura 0 08/31/22 06/30/20
- Additions and Alterations 4-001-009 / / / / 04/11/24 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
Pole Barn:
22-2411 New Construction 7-022-001 11/21/23 DONE DONE DONE 06/20/23 06/16/23 01/18/23 06/20/23 02 - 16 251,060 0 JLB 0 0 0 Young And Wright Architectura 0 12/20/23 06/16/23
District-Wide:
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
Maplemere Annex:
21-0102TQ Temporary Quarters 8-021-001 08/25/21 DONE DONE DONE 07/27/21 07/27/21 05/14/21 / / 0 0 SLC 0 0 0 0 / / 07/27/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EAST AURORA UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-03-01-03
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Parkdale Elementary School:
22-1628 Reconstruction 0-004-012 05/23/23 DONE DONE DONE 02/06/23 02/03/23 / / 12/14/22 8 18,800 18,800 JLB 0 0 0 Young And Wright Architectura 0 / / 02/03/23
22-2472 Reconstruction 0-004-013 11/15/23 DONE DONE DONE 06/28/23 06/28/23 01/18/23 12/14/22 2,7,9,155,15,16 755,953 755,953 MSK 0 0 0 Young And Wright Architectura 0 / / 06/28/23
23-0500 Reconstruction 0-004-014 11/15/23 DONE DONE DONE 09/18/23 09/14/23 04/21/23 05/16/23 2,16 100,000 100,000 MSK 0 0 0 Young And Wright Architectura 0 / / 09/14/23
Main Street Middle School:
19-0277 Reconstruction 0-006-021 11/13/19 DONE DONE DONE 08/16/19 08/01/19 06/25/19 05/21/19 2,8 100,000 100,000 JSS 0 0 0 Mach Architecture 0 06/05/20 08/01/19
19-1649 Reconstruction 0-006-022 07/07/20 DONE DONE DONE 04/02/20 03/27/20 02/05/20 03/11/20 2,4,7,8,155,15,16 202,000 202,000 JSS 0 0 0 Mach Architecture 0 01/18/21 03/27/20
19-1771 Reconstruction 0-006-023 07/13/20 DONE DONE DONE 05/27/20 05/14/20 02/05/20 06/09/20 9,155,15,16 100,000 100,000 JSS 0 0 0 Mach Architecture 0 01/18/21 05/14/20
21-0550 Reconstruction 0-006-024 01/18/22 DONE DONE DONE 10/20/21 10/19/21 07/07/21 05/18/21 8,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/20/22 10/19/21
22-2473 Reconstruction 0-006-025 11/15/23 DONE DONE DONE 06/28/23 06/28/23 01/18/23 12/14/22 2,7,8,9,10,14,155,15 4,829,838 4,829,838 MSK 0 0 0 Young And Wright Architectura 0 / / 06/28/23
23-0501 Reconstruction 0-006-026 09/18/23 DONE DONE DONE 09/18/23 09/14/23 07/27/23 12/14/22 2,4,15 350,000 350,000 MSK 0 0 0 Young And Wright Architectura 0 / / 09/14/23
- Reconstruction 0-006-027 / / / / 08/01/23 / / 2,4,8,9,10,14,155,15 0 0 MSK 0 0 0 0 / / / /
High School:
19-1650 Reconstruction 0-010-020 07/07/20 DONE DONE DONE 04/02/20 03/27/20 02/05/20 03/11/20 9,155,15,16 118,511 118,511 JSS 0 0 0 Mach Architecture 0 01/18/21 03/27/20
22-0135 Reconstruction 0-010-021 07/25/22 DONE DONE DONE 07/22/22 07/22/22 05/09/22 07/13/22 2 60,000 0 SLC 0 0 0 Young And Wright Architectura 0 11/09/22 07/22/22
22-0311 Reconstruction 0-010-022 09/28/22 DONE DONE DONE 08/22/22 08/22/22 06/14/22 05/17/22 2,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 05/25/23 08/22/22
22-1629 Reconstruction 0-010-023 05/23/23 DONE DONE DONE 02/06/23 02/03/23 12/16/22 12/14/22 8 111,200 111,200 JLB 0 0 0 Young And Wright Architectura 0 / / 02/03/23
22-2474 Reconstruction 0-010-024 11/15/23 DONE DONE DONE 06/28/23 06/28/23 01/18/23 12/14/22 2,8,9,16 849,929 849,929 MSK 0 0 0 Young And Wright Architectura 0 / / 06/28/23
- Reconstruction 0-010-025 / / / / 08/01/23 / / 2,4,10,15,16 0 0 MSK 0 0 0 0 / / / /
Tent @ East Aurora High School:
- PR New Construction 7-016-001 / / / / 03/30/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BUFFALO CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-06-00-01
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Public School 3:
18-2060 Reconstruction 0-003-011 06/19/19 DONE DONE DONE 06/04/19 05/24/19 02/08/19 12/19/18 2,4 183,250 183,250 BMJ 0 0 0 Trautmn Associates Architects 0 03/01/21 05/24/19
- Reconstruction 0-003-012 / / / / 09/22/20 / / 4 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-003-013 / / / / 05/23/22 / / 2,4,7,8,9,10,15,16 0 0 JLB 0 0 0 0 / / / /
#6 Elementary School of Technology:
22-2123FC Reconstruction 0-006-019 10/25/23 DONE DONE DONE 05/03/23 03/01/23 09/20/22 05/17/23 155,16 1,494,376 1,494,376 JJH 0 0 0 LaBella Associates 0 / / 03/01/23
Follow Thru School(#8):
23-0319 Reconstruction 0-008-012 09/20/23 DONE DONE DONE 08/24/23 08/23/23 03/09/23 04/19/23 2,4,7,8,9,155,15,16 10,000,000 10,000,000 JJH 0 0 0 Buffalo Board of Education 0 / / 08/23/23
Native American Magnet School:
18-2061 Reconstruction 0-019-012 06/19/19 DONE DONE DONE 06/04/19 05/24/19 02/08/19 12/19/18 2,4 392,875 392,875 BMJ 0 0 0 Trautmn Associates Architects 0 03/01/21 05/24/19
- Reconstruction 0-019-013 / / / / 11/17/23 / / 2 0 0 JJH 0 0 0 0 / / / /
Hilary Park Academy P.S.#27:
23-0347 Reconstruction 0-027-011 STARTED DONE DONE 08/29/23 08/25/23 02/21/23 11/16/22 7 0 0 JJH 0 0 0 Buffalo Board of Education 0 / / 08/25/23
Harriet Ross Tubman School #31:
19-0940 Reconstruction 0-031-017 06/05/20 DONE DONE DONE 12/09/19 09/19/19 07/19/19 01/18/17 4,9,15 174,200 0 BMJ 0 0 0 DiDonato Associates,P.E.,P.C. 0 / / 09/19/19
21-0063 Reconstruction 0-031-018 03/28/23 DONE DONE DONE 07/16/21 07/16/21 10/04/19 11/16/22 2,16 479,284 479,284 JLB 0 0 0 Trautmn Associates Architects 0 / / 07/16/21
- Reconstruction 0-031-019 / / / / 02/25/21 / / 2,4,7,8,9 0 0 JLB 0 0 0 0 / / / /
School #32 - Bennett Park Montessori:
19-1252 Reconstruction 0-032-013 03/02/20 DONE DONE DONE 01/22/20 12/23/19 07/24/19 09/18/19 9 100,000 100,000 BMJ 0 0 0 Board of education Architects 0 08/31/23 12/23/19
School #37 - Futures Academy:
20-1309 Reconstruction 0-037-012 04/07/21 DONE DONE DONE 02/18/21 02/12/21 01/08/20 08/19/20 2,8 999,999 999,999 JLB 0 0 0 Buffalo Board of Education 0 06/26/23 02/12/21
22-2124FC Reconstruction 0-037-013 10/25/23 DONE DONE DONE 05/03/23 03/01/23 / / 05/17/23 155,16 1,499,593 1,499,593 JJH 0 0 0 LaBella Associates 0 / / 03/01/23
School #38-Frank A Sedita Elem Schl:
- Reconstruction 0-038-015 / / / / 11/17/23 / / 2 0 0 JJH 0 0 0 0 / / / /
Schl #39-Dr King Multicultural Inst:
19-1772 Reconstruction 0-039-015 09/29/20 DONE DONE DONE 05/27/20 05/11/20 01/06/20 09/18/19 7 2,000,000 0 JLB 0 0 0 Buffalo Board of Education 0 / / 05/11/20
Lovejoy Discovery School:
23-1533 Reconstruction 0-043-014 UNREVIEWED 02/22/24 02/20/24 11/17/20 11/16/22 2,8 999,999 999,999 JJH 0 0 0 Board of education Architects 0 / / 02/20/24
Stanley M. Mackowski E.C.C.:
20-0194 Reconstruction 0-050-010 10/23/20 DONE DONE DONE 08/12/20 04/21/20 12/14/18 03/20/19 2,15,16 403,966 0 JLB 0 0 0 Foit-Albert Associates 0 / / 04/21/20
Public School #53:
19-0556 Reconstruction 0-053-009 01/31/20 DONE DONE DONE 10/10/19 09/06/19 02/08/19 12/19/18 4,7,155,15,16 1,100,000 0 BMJ 0 0 0 Board of education Architects 0 / / 09/06/19
- Reconstruction 0-053-010 / / / / 04/15/24 / / 2,7 0 0 JJH 0 0 0 0 / / / /
School #54 Blackman School of Excell:
21-0293 Reconstruction 0-054-009 11/15/21 DONE DONE DONE 09/03/21 09/03/21 10/29/20 04/21/21 2,7,155,15,16 1,135,070 0 JLB 0 0 0 Clark Patterson Lee 0 / / 09/03/21
Schl #59-Charles Drew Science Magnet:
20-0195 Reconstruction 0-059-011 10/23/20 DONE DONE DONE 08/12/20 04/21/20 08/07/14 03/18/19 2,16 549,393 0 JLB 0 0 0 Foit-Albert Associates 0 / / 04/21/20
School #61-Arthur O. Eve Schl of Dis:
- Reconstruction 0-061-012 / / / / 11/20/23 / / 2 0 0 JJH 0 0 0 0 / / / /
Public School #64:
- Reconstruction 0-064-014 / / / / 07/24/23 / / 2,4,8 0 0 JJH 0 0 0 0 / / / /
Schl #65-Roosevelt Early Childhood:
- Reconstruction 0-065-013 / / / / 07/24/23 / / 2,4,8 0 0 JJH 0 0 0 0 / / / /
North Park Academy #66:
19-1209 Additions and Alterations 0-066-013 05/14/20 DONE DONE DONE 01/13/20 01/07/20 03/12/18 11/15/17 02 - 16 6,775,000 3,902,836 BMJ 0 0 0 Stieglitz Snyder Architecture 0 02/21/23 YES 01/07/20
School #69 - Houghton Academy:
- Reconstruction 0-069-020 / / / / 02/25/21 / / 2,4,7,8,9 0 0 JLB 0 0 0 0 / / / /
Lorraine Elementary:
- Reconstruction 0-072-009 / / / / 03/08/24 / / 2,8 0 0 JJH 0 0 0 0 / / / /
School #74 - Hamlin Park:
22-0820 Reconstruction 0-074-011 01/27/23 DONE DONE DONE 10/26/22 10/17/22 06/07/21 08/17/22 2,155,15 30,000 30,000 WLC 0 0 0 DiDonato Associates,P.E.,P.C. 0 / / 10/17/22
Highgate Heights #80:
- Reconstruction 0-080-008 / / / / 03/08/24 / / 2,8 0 0 WLC 0 0 0 0 / / / /
St.Lawrence Adacemy(#86):
- Reconstruction 0-086-006 / / / / 03/17/23 / / 4,7 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-086-007 / / / / 05/30/23 / / 7 0 0 JJH 0 0 0 0 / / / /
Dr. Lydia T. Wright:
21-0064 Reconstruction 0-089-016 03/28/23 DONE DONE DONE 07/16/21 07/16/21 10/04/19 11/16/22 2,16 620,762 620,762 JLB 0 0 0 Trautmn Associates Architects 0 / / 07/16/21
- Reconstruction 0-089-017 / / / / 09/29/23 / / 4,7,8 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-089-018 / / / / 09/29/23 / / 4,7,8 0 0 JJH 0 0 0 0 / / / /
Early Childhood Ctr. Frmr C.L Drew s:
- Reconstruction 0-090-012 / / / / 11/20/23 / / 2 0 0 JJH 0 0 0 0 / / / /
Southside Elementary:
- Reconstruction 0-093-009 / / / / 10/25/19 / / 2,16 0 0 BMJ 0 0 0 0 / / / /
- Reconstruction 0-093-010 / / / / 02/22/21 / / 7 0 0 JLB 0 0 0 0 / / / /
West Hertel Middle:
19-0968 Reconstruction 0-094-017 10/28/20 DONE DONE DONE 12/10/19 11/04/19 01/21/14 02/15/17 2,4,7,8,9,155,15,16 842,000 842,000 BMJ 0 0 0 DiDonato Associates,P.E.,P.C. 0 / / 11/04/19
- Reconstruction 0-094-020 / / / / 03/22/24 / / 155,16 0 0 JJH 0 0 0 0 / / / /
Waterfront Elem (#95):
- Reconstruction 0-095-019 / / / / 02/23/21 / / 155,15,16 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-095-020 / / / / 09/29/23 / / 7,155 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-095-021 / / / / 09/29/23 / / 7,155 0 0 JJH 0 0 0 0 / / / /
BAVPA High School:
19-0969 Reconstruction 0-192-015 01/14/21 DONE DONE DONE 12/10/19 11/04/19 01/21/14 02/15/17 2,4,7,8,9,155,15,16 883,625 883,625 BMJ 0 0 0 DiDonato Associates,P.E.,P.C. 0 08/24/23 11/04/19
- Reconstruction 0-192-016 / / / / 10/25/19 / / 2,16 0 0 BMJ 0 0 0 0 / / / /
P.S. #195 - City Honors School:
- Reconstruction 0-195-029 / / / / 10/25/19 / / 2,16 0 0 BMJ 0 0 0 0 / / / /
- Reconstruction 0-195-030 / / / / 11/13/19 / / 4,7,8,9 0 0 BMJ 0 0 0 0 / / / /
20-0383 Reconstruction 0-195-031 12/17/20 DONE DONE DONE 09/16/20 08/31/20 01/30/20 09/18/19 2,4,15 30,400 30,400 JLB 0 0 0 DiDonato Associates,P.E.,P.C. 0 04/27/22 08/31/20
- Reconstruction 0-195-032 01/20/09 DONE DONE DONE 11/20/08 11/17/08 10/13/21 09/02/08 4,7,8,9,155,15,16 1,110,157 1,110,157 JLB 0 0 0 Anthony M. Pucillo 0 / / 11/17/08
22-0782 Reconstruction 0-195-033 06/01/23 DONE DONE DONE 10/21/22 10/19/22 01/19/22 11/18/15 4,8,9,155,15,16 5,090,583 5,090,583 JJH 0 0 0 Wendel Companies 0 / / 10/19/22
- Reconstruction 0-195-034 / / / / 04/15/24 / / 2,7 0 0 JJH 0 0 0 0 / / / /
School #200 - Bennett High School:
20-0196 Reconstruction 0-200-019 10/23/20 DONE DONE DONE 08/12/20 04/21/20 08/07/14 03/20/20 2,16 427,552 0 JLB 0 0 0 Foit-Albert Associates 0 / / 04/21/20
20-1725 Reconstruction 0-200-022 07/26/21 DONE DONE DONE 05/18/21 02/03/21 02/08/19 09/18/19 4 1,150,049 0 JLB 0 0 0 Carmina-Wood-Morris DPC 0 / / 02/03/21
Kensington High:
19-1822 Reconstruction 0-203-024 08/28/20 DONE DONE DONE 06/09/20 05/26/20 08/27/19 08/19/20 9,15,16 750,000 750,000 JLB 0 0 0 Trautmn Associates Architects 0 / / 05/26/20
Lafayette High School:
- Reconstruction 0-204-028 / / / / 10/25/19 / / 2,16 0 0 BMJ 0 0 0 0 / / / /
- Reconstruction 0-204-029 / / / / 04/15/24 / / 2,7 0 0 JJH 0 0 0 0 / / / /
Riverside HS #205:
20-1726 Reconstruction 0-205-017 07/26/21 DONE DONE DONE 05/18/21 02/03/21 02/08/19 09/18/19 4 885,449 0 JLB 0 0 0 Carmina-Wood-Morris DPC 0 / / 02/03/21
22-0821 Reconstruction 0-205-018 01/27/23 DONE DONE DONE 10/26/22 10/17/22 06/07/21 08/17/22 2,155,15 38,600 38,600 WLC 0 0 0 DiDonato Associates,P.E.,P.C. 0 / / 10/17/22
- Reconstruction 0-205-019 / / / / 10/23/23 / / 2 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-205-020 / / / / 03/08/24 / / 2,4,8 0 0 WLC 0 0 0 0 / / / /
South Park High(206):
18-1405 Reconstruction 0-206-017 04/30/19 DONE DONE DONE 02/07/19 07/11/18 01/21/14 02/15/17 2,4,7,8,9,155,15,16 801,950 801,950 BMJ 0 0 0 DiDonato Associates,P.E.,P.C. 0 01/18/21 07/11/18
18-2062 Reconstruction 0-206-020 06/19/19 DONE DONE DONE 06/04/19 05/24/19 02/08/19 11/15/17 2,4 340,900 340,900 BMJ 0 0 0 Trautmn Associates Architects 0 03/01/21 05/24/19
- Reconstruction 0-206-021 / / / / 02/12/21 / / 4,8 0 0 JLB 0 0 0 0 / / / /
Burgard Vocational HS #301:
- Reconstruction 0-301-019 / / / / 03/08/24 / / 2,4,8 0 0 WLC 0 0 0 0 / / / /
Harvey Austin School #97:
- Reconstruction 0-302-027 / / / / 08/14/23 / / 2,10,155,15 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-302-028 / / / / 03/22/24 / / 155,16 0 0 JJH 0 0 0 0 / / / /
Schl #304-Hutchinson Cent Tech HS:
22-0822 Reconstruction 0-304-021 01/27/23 DONE DONE DONE 10/26/22 10/17/22 06/07/21 08/17/22 2,155,15 40,300 40,300 WLC 0 0 0 DiDonato Associates,P.E.,P.C. 0 / / 10/17/22
- Reconstruction 0-304-022 / / / / 03/24/23 / / 2,4,155,16 0 0 JJH 0 0 0 0 / / / /
School #305 - McKinley High School:
19-0941 Reconstruction 0-305-014 02/27/20 DONE DONE DONE 12/09/19 11/12/19 07/18/19 09/18/19 4,9,10,16 75,000 75,000 BMJ 0 0 0 Buffalo Board of Education 0 01/22/21 11/12/19
- Reconstruction 0-305-015 / / / / 02/22/21 / / 7 0 0 JLB 0 0 0 0 / / / /
East High School:
18-2063 Reconstruction 0-307-015 06/19/19 DONE DONE DONE 06/04/19 05/24/19 02/08/19 12/19/18 2,4 235,225 235,225 BMJ 0 0 0 Trautmn Associates Architects 0 03/01/21 05/24/19
- Reconstruction 0-307-016 / / / / 04/15/24 / / 2,7 0 0 JJH 0 0 0 0 / / / /
William Grabiarz Prek-8:
20-0384 Reconstruction 0-607-007 12/17/20 DONE DONE DONE 09/16/20 08/31/20 01/30/20 09/18/19 2,4,15 25,300 25,300 JLB 0 0 0 DiDonato Associates,P.E.,P.C. 0 04/27/22 08/31/20
All High Stadium:
- Reconstruction 2-606-010 / / / / 03/11/24 / / 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 0 / / / /
All High Stadium - Track Storage:
- New Construction 2-689-001 / / / / 03/11/24 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
Central Commissary:
- DB Discovered Building 7-683-001 / / / / 11/17/22 / / 0 0 JJH 0 0 0 0 / / / /
All High Stadium - Visitor Grandstan:
- New Construction 7-685-001 / / / / 03/11/24 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
All High Stadium Coach VIP Box LULA:
- New Construction 7-686-001 / / / / 03/11/24 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
All High Stadium Concession/Ticket b:
- New Construction 7-687-001 / / / / 03/11/24 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
All High Stadium Team Room/Restroom:
- New Construction 7-688-001 / / / / 03/11/24 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
District-Wide:
- Reconstruction 7-999-025 / / / / 06/08/23 / / 0 0 JJH 0 0 0 0 / / / /
Middle Early College HS & SUNY Erie:
- TQ Temporary Quarters 8-236-001 / / / / 06/13/19 / / 0 0 BMJ 0 0 0 0 / / / /
Emerson Culinary Annex:
20-0647 Reconstruction 8-681-L01 01/28/20 DONE DONE DONE 10/20/20 03/20/18 07/25/16 12/18/19 48,579,828 29,189,624 JLB 0 0 0 Kideney Architects, P.C. 0 / / 03/20/18
Leonardo DaVinci High School #272:
23-0139TQ Temporary Quarters 8-682-001 DONE STARTED UNREVIEWED07/26/23 07/25/23 05/04/22 / / 0 0 JJH 0 0 0 0 / / 07/25/23
45 Jewett Ave:
- TQ Temporary Quarters 8-684-001 / / / / 07/25/23 / / 0 0 JJH 0 0 0 0 / / / /
REACH Academy Charter School Primary:
22-0149 New Construction 0-002-001 08/31/22 DONE DONE DONE 07/25/22 07/25/22 / / / / 02 - 16 0 0 SLC 0 0 0 0 / / 07/25/22
REACH Academy Charter School:
22-2163DB Discovered Building 0-003-001 02/05/24 DONE DONE DONE 05/08/23 05/08/23 03/03/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / 05/08/23
BuffAcadSciII (frmrDominicanNunsMona:
- TQ Temporary Quarters 0-001-001 / / / / 02/06/20 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
XXFormer Maritime Charter Sch-Cancld:
- XX New Construction 0-002-001 CANCELLED / / / / 01/14/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Buffalo Creek Acad Charter-528S Park:
21-0191TQ Temporary Quarters 8-001-001 ADDENDUM REQ'D 08/18/21 08/18/21 06/10/20 / / 02 - 16 3,425,712 0 SLC 0 0 0 0 / / 08/18/21
- XX Reconstruction 8-001-002 CANCELLED / / / / 05/19/21 / / 0 0 SLC 0 0 0 0 / / / /
Buffalo Creek Academy 2408 Main:
20-0067TQ Temporary Quarters 8-002-001 08/21/20 DONE DONE DONE 07/20/20 07/20/20 06/29/20 / / 0 0 SLC 0 0 0 0 / / 07/20/20
Buffalo Creek Academy - 514 S Park:
- TQ Temporary Quarters 8-003-001 / / / / 05/19/21 / / 0 0 SLC 0 0 0 0 / / / /
Urban Street:
20-0690 New Construction 0-001-001 12/03/20 DONE DONE DONE 10/23/20 08/05/20 07/01/20 06/11/20 02 - 16 7,665,000 0 SLC 0 0 0 M/E Engineering, P.C. 0 09/30/21 08/05/20
XXTemporary Modular due to COVID:
- XX Reconstruction 8-002-001 CANCELLED / / / / 07/21/20 / / 0 0 SLC 0 0 0 0 / / / /
Primary Hall Prep Charter-Lse:
- TQ Temporary Quarters 8-001-001 / / / / 02/23/98 / / 8,9,155,15,16 0 0 SLC 0 0 0 0 / / / /
21-0185TQ Temporary Quarters 8-001-001 08/08/22 DONE DONE DONE 08/18/21 08/16/21 11/30/20 / / 2,7,15 0 0 SLC 0 0 0 0 / / 08/16/21
22-0443TQ Temporary Quarters 8-001-002 02/02/23 DONE DONE DONE 09/09/22 09/08/22 07/22/22 / / 0 0 SLC 0 0 0 0 / / 09/08/22
23-0373TQ Temporary Quarters 8-001-003 02/16/24 DONE DONE DONE 09/05/23 09/01/23 08/04/22 / / 0 0 MSK 0 0 0 0 / / 09/01/23
- TQ Temporary Quarters 8-001-004 / / / / / / / / 0 0 MSK 0 0 0 0 / / / /
BuffaloCommonsCharterS FamilyLifeCtr:
22-0162TQ Temporary Quarters 8-001-001 08/19/22 DONE DONE DONE 07/25/22 / / 06/14/21 / / 0 0 SLC 0 0 0 0 / / / /
Brick Buffalo Academy:
22-2152TQ Temporary Quarters 8-001-001 DONE ADD. REQ'D DONE 05/05/23 / / 03/29/23 / / 2,8,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CHEEKTOWAGA-MARYVALE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-07-02-03
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Maryvale High School:
19-0290 Reconstruction 0-001-011 12/05/19 DONE DONE DONE 08/26/19 08/08/19 10/18/18 12/12/17 2,4,7,8,155,15,16 2,351,500 2,351,500 BMJ 0 0 0 Young And Wright Architectura 0 05/12/21 08/08/19
20-0440 Reconstruction 0-001-012 01/29/21 DONE DONE DONE 09/24/20 09/09/20 08/05/20 12/12/17 16 57,000 57,000 JLB 0 0 0 Young And Wright Architectura 0 10/04/21 09/09/20
22-0804 Reconstruction 0-001-013 03/16/23 DONE DONE DONE 10/24/22 10/24/22 02/07/22 12/07/21 2,4,7,8,9,10,155,15, 20,102,622 15,012,000 WLC 0 0 0 Young And Wright Architectura 0 / / 10/24/22
Grades 9-10(fmly Sr. HS):
19-0291 Reconstruction 0-002-014 12/05/19 DONE DONE DONE 08/26/19 08/08/19 10/18/18 12/12/17 2,4,8,155,15,16 1,722,200 1,722,200 BMJ 0 0 0 Young And Wright Architectura 0 05/12/21 08/08/19
20-0441 Reconstruction 0-002-015 01/29/21 DONE DONE DONE 09/24/20 09/09/20 04/24/20 12/12/17 2,9 2,496,700 2,496,700 JLB 0 0 0 Young And Wright Architectura 0 10/04/21 09/09/20
23-0596 Reconstruction 0-002-016 STARTED ADD. REQ'D DONE 10/04/23 10/02/23 05/19/23 12/07/21 2,9 1,321,648 0 WLC 0 0 0 Young And Wright Architectura 0 / / 10/02/23
Primary School:
19-0292 Reconstruction 0-005-014 12/05/19 DONE DONE DONE 08/26/19 08/08/19 10/18/18 12/12/17 2,4,155,16 291,400 291,400 BMJ 0 0 0 Young And Wright Architectura 0 05/12/21 08/08/19
22-0805 Reconstruction 0-005-015 03/16/23 DONE DONE DONE 10/24/22 10/24/22 02/07/22 12/07/21 2,15 1,059,860 1,059,860 JLB 0 0 0 Young And Wright Architectura 0 / / 10/24/22
22-0525 Reconstruction 0-005-016 11/16/22 DONE DONE DONE 09/19/22 09/19/22 07/25/22 05/17/22 9,10,15 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 04/11/23 09/19/22
23-1806 Reconstruction 0-005-017 UNREVIEWED 04/11/24 04/11/24 01/31/23 / / 9,10,15 100,000 0 WLC 0 0 0 Young And Wright Architectura 0 / / 04/11/24
Maryvale Middle-Intermediate:
19-0293 Reconstruction 0-007-016 12/05/19 DONE DONE DONE 08/26/19 08/08/19 10/18/18 12/12/17 2,4,7,8,16 3,188,500 3,188,500 BMJ 0 0 0 Young And Wright Architectura 0 05/12/21 08/08/19
19-1170 Reconstruction 0-007-017 03/09/20 DONE DONE DONE 01/07/20 12/19/19 06/27/19 05/21/19 2,9,10,15,16 100,000 100,000 BMJ 0 0 0 Young And Wright Architectura 0 06/26/20 12/19/19
20-0673 Reconstruction 0-007-018 01/07/21 DONE DONE DONE 10/22/20 10/21/20 07/14/20 06/09/20 2,9,10,15,16 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 06/02/21 10/21/20
20-1917 Reconstruction 0-007-019 08/02/21 DONE DONE DONE 06/25/21 06/24/21 04/16/21 05/18/21 7,15,16 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 03/15/22 06/24/21
23-0200 Reconstruction 0-007-020 10/03/23 DONE DONE DONE 08/04/23 07/21/23 03/30/23 05/16/23 7,8,9,10,155,16 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 / / 07/21/23
23-0597 Reconstruction 0-007-021 STARTED ADD. REQ'D DONE 10/04/23 10/02/23 05/19/23 12/07/21 2,9,10,155,15,16 4,745,823 4,745,823 WLC 0 0 0 Young And Wright Architectura 0 / / 10/02/23
23-0598 Reconstruction 0-007-022 STARTED ADD. REQ'D DONE 10/04/23 10/02/23 09/08/23 12/07/21 16 641,946 0 WLC 0 0 0 Young And Wright Architectura 0 / / 10/02/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
DEPEW UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-07-07-03
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Depew High School:
19-0432 Reconstruction 0-002-020 01/10/20 DONE DONE DONE 09/18/19 08/29/19 06/11/19 05/21/19 2,4,9,10 100,000 100,000 JSS 0 0 0 Young And Wright Architectura 0 06/25/20 08/29/19
20-0530 Reconstruction 0-002-021 02/21/21 DONE DONE DONE 10/06/20 09/24/20 03/06/20 03/17/20 2,9,10,16 100,000 100,000 JSS 0 0 0 Young And Wright Architectura 0 06/16/21 09/24/20
21-0043 Reconstruction 0-002-022 08/29/21 DONE DONE DONE 07/14/21 07/13/21 03/30/21 05/18/21 2,4,8,9,10,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/17/22 07/13/21
22-0837 Reconstruction 0-002-023 02/21/23 DONE DONE DONE 10/26/22 10/13/22 12/23/21 12/14/21 2,4,8,9,10,155,15,16 2,909,000 2,909,000 SLC 0 0 0 Young And Wright Architectura 0 / / 10/13/22
23-1653 Reconstruction 0-002-024 UNREVIEWED 03/21/24 03/20/24 01/20/22 12/14/21 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 Young And Wright Architectura 0 / / 03/20/24
23-0350 Reconstruction 0-002-025 02/27/24 DONE DONE DONE 08/30/23 08/28/23 05/03/23 12/14/21 2,15 2,335,000 2,335,000 MSK 0 0 0 Young And Wright Architectura 0 / / 08/28/23
Middle School:
22-0838 Reconstruction 0-004-018 02/21/23 DONE DONE DONE 10/26/22 10/13/22 12/23/21 12/14/21 2,8,9,10,155,15,16 1,400,000 1,400,000 SLC 0 0 0 Young And Wright Architectura 0 / / 10/13/22
23-1654 Reconstruction 0-004-019 UNREVIEWED 03/21/24 03/20/24 01/20/22 12/14/21 2,8,9,10,155,15,16 0 0 MSK 0 0 0 Young And Wright Architectura 0 / / 03/20/24
23-0711 Reconstruction 0-004-020 01/05/24 DONE DONE DONE 10/13/23 10/07/23 03/29/23 05/16/23 2,155,16 100,000 100,000 MSK 0 0 0 Young And Wright Architectura 0 / / 10/07/23
Cayuga Heights Elementary School:
21-2022PR Additions and Alterations 0-005-020 DONE 06/22/22 / / 12/23/21 / / 02 - 16 0 31,103,520 SLC 0 0 0 0 / / / /
22-0836FA Additions and Alterations 0-005-020 03/09/23 DONE DONE DONE 10/26/22 10/13/22 12/23/21 03/15/22 02 - 16 13,200,000 9,610,840 SLC 0 0 0 Young And Wright Architectura 0 / / 10/13/22
21-1822 Reconstruction 0-005-021 08/04/22 DONE DONE DONE 05/16/22 05/16/22 01/25/22 05/17/22 2,8,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/21/23 05/16/22
- XX Reconstruction 0-005-022 CANCELLED / / / / 04/27/22 / / 2,4,7,8,9,10,155,15, 0 29,867,940 SLC 0 0 0 0 / / / /
Quonset Hut:
- DB Discovered Building 2-011-001 / / / / 03/02/23 / / 0 0 SLC 0 0 0 0 / / / /
Bus Garage:
22-0839 Reconstruction 5-003-015 02/21/23 DONE DONE DONE 10/26/22 10/13/22 12/23/21 12/14/21 2,8,9,155,15,16 1,400,000 1,400,000 SLC 0 0 0 Young And Wright Architectura 0 / / 10/13/22
District-Wide:
18-2105 Reconstruction 7-999-003 08/09/19 DONE DONE DONE 06/11/19 05/20/19 / / 11/04/14 16 269,115 269,115 SLC 0 0 0 Young And Wright Architectura 0 / / 05/20/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CLARENCE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-08-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Harris Hill Elementary School:
20-1846 Reconstruction 0-001-013 10/26/21 DONE DONE DONE 06/07/21 06/03/21 08/29/19 12/03/19 2,4,8,9,10,155,15,16 902,940 902,940 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/23 06/03/21
Sheridan Hill Elementary School:
20-1847 Reconstruction 0-002-012 10/26/21 DONE DONE DONE 06/07/21 06/03/21 08/29/19 12/03/19 2,4,8,9,10,155,15,16 998,859 998,859 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/23 06/03/21
22-0561 Reconstruction 0-002-013 01/09/23 DONE DONE DONE 09/23/22 09/23/22 09/15/22 12/03/19 2,4,7,9,155,15,16 210,600 210,600 JLB 0 0 0 Kideney Architects, P.C. 0 / / 09/23/22
Clarence Center Elementary School:
- PR Additions and Alterations 0-003-015 / / / / 08/29/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-0385 Additions and Alterations 0-003-015 12/08/20 DONE DONE DONE 09/17/20 08/21/20 08/29/19 12/03/19 02 - 16 1,206,158 1,127,563 JLB 0 0 245,321 Kideney Architects, P.C. 0 06/01/22 08/21/20
Clarence High School:
- PR Additions and Alterations 0-004-019 / / / / 08/29/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-1848 Additions and Alterations 0-004-019 10/26/21 DONE DONE DONE 06/07/21 12/03/19 08/29/19 12/03/19 02 - 16 12,011,238 10,847,425 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/23 12/03/19
22-0562 Reconstruction 0-004-020 01/09/23 DONE DONE DONE 09/23/22 09/23/22 09/15/22 12/03/19 2,4,7,8,9,10,155,15, 1,789,400 1,789,400 JLB 0 0 0 Kideney Architects, P.C. 0 / / 09/23/22
Ledgeview Elementary School:
- PR Additions and Alterations 0-006-017 / / / / 08/29/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-0386 Additions and Alterations 0-006-017 12/08/20 DONE DONE DONE 09/17/20 08/21/20 08/29/19 12/03/19 02 - 16 1,440,006 1,439,303 JLB 0 0 458,000 Kideney Architects, P.C. 0 12/02/22 08/21/20
Clarence Middle School:
20-0387 Reconstruction 0-008-012 12/08/20 DONE DONE DONE 09/17/20 08/21/20 08/29/19 12/03/19 2,4,7,8,9,10,155,15, 6,916,951 6,916,951 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/22 08/21/20
23-1534 Reconstruction 0-008-013 03/26/24 DONE DONE DONE 02/22/24 02/20/24 12/28/23 05/16/23 15,16 28,000 28,000 JJH 0 0 0 Kideney Architects, P.C. 0 / / 02/20/24
Storage Building:
20-1849 New Construction 2-022-001 10/26/21 DONE DONE DONE 06/07/21 06/03/21 08/29/19 12/03/19 02 - 16 890,615 0 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/23 06/03/21
Bldgs & Grnds/Food Svc Offices:
20-0388 Reconstruction 3-005-003 12/08/20 DONE DONE DONE 09/17/20 08/21/20 08/29/19 12/03/19 2,4,8,9,10,155,15,16 283,078 0 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/22 08/21/20
Bus Garage:
20-0389 Reconstruction 5-017-005 12/08/20 DONE DONE DONE 09/17/20 08/21/20 08/29/19 12/03/19 2,4,7,8,9,10,155,15, 2,461,548 2,461,548 JLB 0 0 0 Kideney Architects, P.C. 0 06/01/22 08/21/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EDEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-12-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Eden Elementary School:
21-0605 Reconstruction 0-001-016 02/08/22 DONE DONE DONE 10/29/21 10/27/21 08/09/21 12/15/20 2,4,8,9,10,155,15,16 4,186,486 4,186,486 JLB 0 0 0 Young And Wright Architectura 0 10/31/23 10/27/21
22-0313 Reconstruction 0-001-017 09/26/22 DONE DONE DONE 08/22/22 08/22/22 03/03/22 12/15/20 2,4,7,8,9,10,155,15, 3,728,225 1,161,212 JLB 0 0 0 Young And Wright Architectura 0 / / 08/22/22
23-1159 Reconstruction 0-001-018 01/12/24 DONE DONE DONE 12/13/23 12/07/23 06/21/23 05/16/23 2,16 100,000 100,000 JJH 0 0 0 Young And Wright Architectura 0 / / 12/07/23
Grover L. Preiss Primary School:
21-0606XX Reconstruction 0-002-017 02/08/22 CANCELLED 10/29/21 10/27/21 08/09/21 12/15/20 2,7,8,9,155,15,16 384,983 384,983 JLB 0 0 0 Young And Wright Architectura 0 / / 10/27/21
22-0314 Reconstruction 0-002-018 09/26/22 DONE DONE DONE 08/22/22 08/22/22 03/03/22 12/15/20 2,8,9,16 238,766 238,766 JLB 0 0 0 Young And Wright Architectura 0 10/31/23 08/22/22
21-1889 Reconstruction 0-002-019 06/17/22 DONE DONE DONE 05/31/22 05/26/22 04/27/22 05/18/21 2,16 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 05/05/23 05/26/22
23-0433 Reconstruction 0-002-020 10/16/23 DONE DONE DONE 09/11/23 09/08/23 02/01/23 05/17/22 2,16 100,000 100,000 JJH 0 0 0 Young And Wright Architectura 0 / / 09/08/23
Jr/Sr High School:
19-1261 Reconstruction 0-006-015 02/19/20 DONE DONE DONE 01/24/20 01/17/20 02/01/18 06/19/18 2,8,9 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 06/17/20 01/17/20
19-1643 Reconstruction 0-006-016 05/28/20 DONE DONE DONE 03/30/20 03/19/20 06/12/19 05/21/19 8,9 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 01/21/21 03/19/20
20-1604 Reconstruction 0-006-017 05/26/21 DONE DONE DONE 04/20/21 04/13/21 02/18/21 07/28/20 2,8,9 100,000 100,000 JLB 0 0 0 Young And Wright Architectura 0 09/01/21 04/13/21
21-0607 Reconstruction 0-006-018 02/08/22 DONE DONE DONE 10/29/21 10/27/21 08/09/21 12/15/20 2,4,8,9,10,155,15,16 4,668,969 4,668,969 JLB 0 0 0 Young And Wright Architectura 0 10/31/23 10/27/21
21-1652 Reconstruction 0-006-019 06/13/22 DONE DONE DONE 04/11/22 04/08/22 03/03/22 12/15/20 2,9,16 890,690 890,690 JLB 0 0 0 Young And Wright Architectura 0 10/31/23 04/08/22
22-0315 Reconstruction 0-006-020 09/26/22 DONE DONE DONE 08/22/22 08/22/22 03/03/22 12/15/20 2,8,9,16 1,217,181 1,217,181 JLB 0 0 0 Young And Wright Architectura 0 10/31/23 08/22/22
- Reconstruction 0-006-021 / / / / 03/21/24 / / 2,4,8,9 0 0 JJH 0 0 0 0 / / / /
Cogeneration Plant @ GLP:
21-0608 Reconstruction 0-007-004 02/08/22 DONE DONE DONE 10/29/21 10/27/21 08/09/21 12/15/20 2,4,8,155,15,16 25,666 25,666 JLB 0 0 0 Young And Wright Architectura 0 10/31/23 10/27/21
Bus Garage:
21-0609XX Reconstruction 5-003-011 02/08/22 CANCELLED 10/29/21 10/27/21 08/09/21 12/15/20 2,4,7,16 239,156 239,156 JLB 0 0 0 Young And Wright Architectura 0 / / 10/27/21
- Reconstruction 5-003-012 / / / / 04/09/24 / / 2,15,16 0 0 JJH 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
IROQUOIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-13-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elma Elementary School:
20-1524 Reconstruction 0-001-012 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 2,9,155,16 615,327 615,327 SLC 0 0 0 Gordon W. Jones Associates 0 12/15/23 03/19/21
23-0258 Reconstruction 0-001-013 09/13/23 DONE DONE DONE 08/14/23 08/14/23 08/09/23 05/16/23 2,4,9,16 100,000 100,000 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/14/23
Middle School:
20-1525 Reconstruction 0-002-023 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 2,4,8,9,10,155,15,16 3,713,644 3,713,644 SLC 0 0 0 Gordon W. Jones Associates 0 12/15/23 03/19/21
23-1248 Reconstruction 0-002-024 UNREVIEWED 12/20/23 12/20/23 10/11/23 10/06/20 2,15 0 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 12/20/23
23-1865 Reconstruction 0-002-025 UNREVIEWED 04/18/24 04/18/24 11/01/23 / / 7,10,16 0 0 WLC 0 0 0 SEI Design Group 0 / / 04/18/24
Wales Elementary School:
20-1526 Reconstruction 0-003-019 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 2,8,9,155,15,16 699,667 699,667 SLC 0 0 0 Gordon W. Jones Associates 0 12/15/23 03/19/21
Iroquois Intermediate:
20-1527 Reconstruction 0-004-014 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 2,4,7,9,15,16 2,937,463 2,937,463 SLC 0 0 0 Gordon W. Jones Associates 0 12/15/23 03/19/21
21-0780 Reconstruction 0-004-015 01/25/22 DONE DONE DONE 11/30/21 11/23/21 09/29/21 05/18/21 2,9,16 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 01/24/23 11/23/21
22-1214 Reconstruction 0-004-016 02/03/23 DONE DONE DONE 12/09/22 12/09/22 10/04/22 05/17/22 2,9,16 100,000 100,000 WLC 0 0 0 Gordon W. Jones Associates 0 / / 12/09/22
Marilla Elementary School:
19-0407 Reconstruction 0-005-016 02/07/20 DONE DONE DONE 09/13/19 09/05/19 08/20/19 05/21/19 2,9 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 10/26/20 09/05/19
20-0567 Reconstruction 0-005-017 12/24/20 DONE DONE DONE 10/09/20 09/30/20 08/31/20 06/16/20 2,4,8 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 10/29/21 09/30/20
20-1528 Reconstruction 0-005-018 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 2,8,9,155,15,16 1,197,050 1,197,050 SLC 0 0 0 Gordon W. Jones Associates 0 12/15/23 03/19/21
21-0492 Reconstruction 0-005-019 01/11/22 DONE DONE DONE 10/08/21 10/06/21 05/13/21 10/06/20 7,13,16 513,832 513,832 SLC 0 0 0 SEI Design Group 513,832 12/28/23 10/06/21
23-1249 Reconstruction 0-005-020 UNREVIEWED 12/20/23 12/20/23 10/11/23 10/06/20 2,15 0 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 12/20/23
High School:
20-1529 Reconstruction 0-007-024 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 2,4,7,8,9,10,155,15, 8,236,934 8,236,934 SLC 0 0 0 Gordon W. Jones Associates 0 12/15/23 03/19/21
Iroquois Press Box:
20-1530 New Construction 7-022-001 08/09/21 DONE DONE DONE 04/02/21 03/19/21 11/10/20 10/06/20 02 - 16 123,686 0 SLC 0 0 0 Gordon W. Jones Associates 0 02/07/23 03/19/21
Marilla Pavilion:
- New Construction 7-023-001 / / / / 04/19/24 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
District-Wide:
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EVANS-BRANT CSD (LAKE SHORE CSD) STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-14-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Lake Shore Sr High School:
18-2088 Additions and Alterations 0-001-016 11/13/19 DONE DONE DONE 06/10/19 05/29/19 06/19/18 05/16/17 02 - 16 12,709,108 6,174,650 JSS 0 0 0 Young And Wright Architectura 0 08/27/21 05/29/19
20-0079 Reconstruction 0-001-018 11/03/20 DONE DONE DONE 07/20/20 07/10/20 07/19/19 05/16/17 2,4,7,8,9,10,155,15, 12,663,645 12,663,645 JSS 0 0 0 Young And Wright Architectura 0 08/26/22 07/10/20
22-0747 Reconstruction 0-001-019 04/27/23 DONE DONE DONE 10/17/22 10/17/22 03/29/22 05/16/17 2,4,7,8,9,155,15,16 1,982,399 1,982,399 WLC 0 0 0 Young And Wright Architectura 0 / / 10/17/22
23-0277 Reconstruction 0-001-020 09/28/23 DONE DONE DONE 08/18/23 08/16/23 06/16/23 05/16/23 2,8,9,15 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 / / 08/16/23
23-1311 Reconstruction 0-001-021 UNREVIEWED 01/02/24 12/01/23 08/23/23 05/16/23 2,7,8,9 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 12/01/23
- Reconstruction 0-001-022 / / / / 01/12/24 / / 2,7,9,155,16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-001-023 / / / / 02/12/24 / / 2,4,7,9,13,155,15,16 0 0 WLC 0 0 0 0 / / / /
J.T.Waugh Elem School (G K-5):
19-1119 Reconstruction 0-002-014 01/31/20 DONE DONE DONE 01/02/20 12/19/19 07/19/19 05/21/19 2,4,9 100,000 100,000 SLC 0 0 0 Young Wright Architectural 0 06/10/20 12/19/19
20-0080 Reconstruction 0-002-015 11/03/20 DONE DONE DONE 07/20/20 07/10/20 07/19/19 05/16/17 2,4,7,8,9,10,14,155, 4,361,840 4,361,441 JSS 0 0 0 Young And Wright Architectura 0 08/26/22 07/10/20
22-0748 Reconstruction 0-002-016 04/27/23 DONE DONE DONE 10/17/22 10/17/22 03/29/22 05/16/17 2,7,9,155,15,16 1,599,019 1,599,019 WLC 0 0 0 0 / / 10/17/22
W.T.Hoag ES(K-4)(only3PKcl 10/16:
20-1582 Reconstruction 0-004-013 07/21/21 DONE DONE DONE 04/13/21 04/09/21 03/20/20 05/16/17 2,4,7,8,9,10,155,15, 3,106,683 932,364 JSS 0 0 0 Young And Wright Architectura 0 08/26/22 04/09/21
22-0749 Reconstruction 0-004-014 04/27/23 DONE DONE DONE 10/17/22 10/17/22 03/29/22 05/16/17 2,4,7,8,9,155,15,16 811,251 761,531 WLC 0 0 0 Young And Wright Architectura 0 / / 10/17/22
Highland ES (K-5):
20-1583 Reconstruction 0-005-010 07/21/21 DONE DONE DONE 04/13/21 04/09/21 03/18/20 05/16/17 2,4,7,8,9,10,155,15, 3,368,441 3,368,441 JSS 0 0 0 Young And Wright Architectura 0 08/26/22 04/09/21
21-0663 Reconstruction 0-005-011 01/18/22 DONE DONE DONE 11/08/21 11/05/21 08/05/21 05/18/21 2,8,9 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/16/22 11/05/21
22-0750 Reconstruction 0-005-012 04/27/23 DONE DONE DONE 10/17/22 10/17/22 03/29/22 05/16/17 2,4,7,8,9,155,15,16 252,184 252,184 WLC 0 0 0 Young And Wright Architectura 0 / / 10/17/22
23-1312 Reconstruction 0-005-013 UNREVIEWED 01/02/24 12/01/23 08/23/23 05/16/23 2,7 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 12/01/23
A.J.Schmidt ES (K-5):
20-1584 Reconstruction 0-008-012 07/21/21 DONE DONE DONE 04/13/21 04/09/21 03/18/20 05/16/17 2,4,7,8,9,10,155,15, 4,146,921 3,868,944 JSS 0 0 0 Young And Wright Architectura 0 08/26/22 04/09/21
22-0751 Reconstruction 0-008-013 04/27/23 DONE DONE DONE 10/17/22 10/17/22 03/29/22 05/16/17 2,4,7,8,9,155,15,16 882,180 882,180 WLC 0 0 0 Young And Wright Architectura 0 / / 10/17/22
W.G. Houston MS (Lake Shore 7-9):
18-2089 Additions and Alterations 0-015-014 11/13/19 DONE DONE DONE 06/10/19 05/29/19 06/19/18 05/16/17 02 - 16 9,685,302 8,970,755 JSS 0 0 0 Young And Wright Architectura 0 10/01/21 05/29/19
20-1068 Reconstruction 0-015-015 02/01/21 DONE DONE DONE 12/29/20 12/23/20 10/15/20 06/16/20 2,155,15,16 100,000 100,000 JSS 0 0 0 Young And Wright Architectura 0 06/03/21 12/23/20
22-0067 Reconstruction 0-015-016 11/10/22 DONE DONE DONE 07/11/22 07/11/22 04/28/22 05/17/22 2,15,16 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 04/14/23 07/11/22
- Reconstruction 0-015-017 / / / / 02/12/24 / / 2,4,7,9,13,16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-015-018 / / / / 04/22/24 / / 2,9 0 0 WLC 0 0 0 0 / / / /
Bus Garage #1 Includes 5-012:
23-1326 Reconstruction 5-011-009 UNREVIEWED 01/05/24 01/05/24 08/23/23 05/16/23 2,4,7 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 01/05/24
23-1733 Reconstruction 5-011-010 UNREVIEWED 04/02/24 04/01/24 01/12/24 05/16/23 2,15,16 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 04/01/24
- Reconstruction 5-011-011 / / / / / / / / 2,4,7,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
XXBus Garage #2 Use 5-011 BldgsJoind:
22-0752XX Reconstruction 5-012-009 04/27/23 CANCELLED 10/17/22 10/17/22 03/29/22 05/11/17 2,7,155,15,16 1,645,716 1,645,716 WLC 0 0 0 Young And Wright Architectura 0 / / 10/17/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HAMBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-16-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Union Pleasant Elementary:
- Reconstruction 0-003-009 / / / / 05/12/21 / / 2,4,8,9,10,155,15,16 0 0 SLC 0 0 0 0 / / / /
22-2410 Reconstruction 0-003-010 07/27/23 DONE DONE DONE 06/20/23 06/16/23 05/02/23 05/16/23 2,9 100,000 100,000 WLC 0 0 0 Gordon W. Jones Associates 0 / / 06/16/23
- Reconstruction 0-003-011 / / / / 05/11/23 / / 2,8,9,10,13,155,15,1 0 0 WLC 0 0 0 0 / / / /
Charlotte Ave. Elem.:
- Reconstruction 0-006-013 / / / / 05/12/21 / / 2,4,9,155,15,16 0 0 SLC 0 0 0 0 / / / /
23-0303 Reconstruction 0-006-014 03/12/24 DONE DONE DONE 08/23/23 08/23/23 05/11/23 10/13/21 2,4,8,9,10,13,155,15 1,239,123 1,239,123 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/23/23
Middle School:
21-0395PR Additions and Alterations 0-008-018 DONE 09/22/21 / / 03/11/20 / / 02 - 16 0 31,365,885 SLC 0 0 0 0 / / / /
- PR Additions and Alterations 0-008-019 / / / / 05/12/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-0040 Additions and Alterations 0-008-019 02/07/23 DONE DONE DONE 07/05/22 07/05/22 05/12/21 10/13/21 02 - 16 4,821,091 4,821,091 WLC 0 0 0 Gordon W. Jones Associates 0 / / 07/05/22
High School:
21-0376 Reconstruction 0-009-016 12/07/21 DONE DONE DONE 09/20/21 09/17/21 03/11/20 05/18/21 2,4,7,8,9,10,13,155, 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 06/30/22 09/17/21
22-0041 Reconstruction 0-009-017 02/07/23 DONE DONE DONE 07/05/22 07/05/22 05/12/21 10/13/21 2,4,8,9,10,155,15,16 8,491,710 7,634,459 WLC 0 0 0 Gordon W. Jones Associates 0 / / 07/05/22
22-0746 Reconstruction 0-009-018 11/16/22 DONE DONE DONE 10/17/22 10/17/22 05/19/22 05/17/22 2,10,16 100,000 100,000 JJH 0 0 0 Gordon W. Jones Associates 0 04/05/23 10/17/22
23-0304 Reconstruction 0-009-019 03/12/24 DONE DONE DONE 08/23/23 08/23/23 05/11/23 10/13/21 2,9,155,15,16 11,263,626 11,263,626 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/23/23
- Reconstruction 0-009-020 / / / / 02/16/24 / / 10 0 0 WLC 0 0 0 0 / / / /
Boston Valley Elementary:
- Reconstruction 0-010-011 / / / / 05/12/21 / / 2,4,8,9,155,15,16 0 7,567,320 WLC 0 0 0 Gordon W. Jones Associates 0 / / / /
23-0305 Reconstruction 0-010-012 03/12/24 DONE DONE DONE 08/23/23 08/23/23 05/11/23 10/13/21 2,4,8,9,10,13,155,15 1,495,644 1,495,644 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/23/23
Armor Elementary School:
- Reconstruction 0-011-008 / / / / 05/12/21 / / 2,4,9,155,15,16 0 0 SLC 0 0 0 0 / / / /
22-1992 Reconstruction 0-011-009 06/28/23 DONE DONE DONE 04/03/23 03/31/23 01/20/23 05/17/22 2 178,200 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 03/31/23
23-0306 Reconstruction 0-011-010 03/12/24 DONE DONE DONE 08/23/23 08/23/23 05/11/23 10/13/21 2,8,9,10,13,155,15,1 1,434,603 1,434,603 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/23/23
Storage Barn:
23-1553 Alterations 2-020-001 UNREVIEWED 02/26/24 02/26/24 01/08/24 10/13/21 0 0 MSK 0 0 0 Gordon W. Jones Associates 0 / / 02/26/24
Giving Garden-Shelter:
- New Construction 7-022-001 UNREVIEWED 05/10/19 05/07/19 06/12/19 04/10/19 02 - 16 0 0 SLC 0 0 0 Tetra Tech Engineers, Archite 0 / / 05/07/19
Softball Dugout 1:
- PR New Construction 7-023-001 / / / / 08/19/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-0800 New Construction 7-023-001 02/07/23 DONE DONE DONE 10/24/22 10/18/22 08/19/22 10/13/21 02 - 16 59,125 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 10/18/22
Softball Dugout 2:
- PR New Construction 7-024-001 / / / / 08/19/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-0801 New Construction 7-024-001 02/07/23 DONE DONE DONE 10/24/22 10/18/22 08/19/22 10/13/21 02 - 16 59,125 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 10/18/22
Baseball Dugout 1:
- PR New Construction 7-025-001 / / / / 08/19/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-0802 New Construction 7-025-001 02/07/23 DONE DONE DONE 10/24/22 10/18/22 08/19/22 10/13/21 02 - 16 62,325 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 10/18/22
Baseball Dugout 2:
- Alterations 7-026-000 / / / / / / / / 0 0 WLC 0 0 0 0 / / / /
- PR New Construction 7-026-001 / / / / 08/19/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-0803 New Construction 7-026-001 02/07/23 DONE DONE DONE 10/24/22 10/18/22 08/19/22 10/13/21 02 - 16 59,125 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 10/18/22
District - Wide:
23-1027SB Reconstruction 7-999-001 DONE / / / / 11/16/23 / / 16 0 0 WLC 0 0 0 0 / / / /
23-1794 Reconstruction 7-999-001 UNREVIEWED 04/09/24 04/09/24 / / 11/04/14 16 0 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 04/09/24
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
FRONTIER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-16-04-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Blasdell Elementary School:
19-0740 Reconstruction 0-004-021 02/25/20 DONE DONE DONE 11/08/19 11/01/19 09/19/19 05/16/17 4,7 262,000 262,000 SLC 0 0 0 Gordon W. Jones Associates 0 09/25/20 11/01/19
21-0788 Reconstruction 0-004-022 03/09/22 DONE DONE DONE 11/30/21 11/23/21 08/09/21 07/20/21 2,9,155,15,16 289,265 289,265 SLC 0 0 0 Gordon W. Jones Associates 0 12/08/23 11/23/21
21-1761 Reconstruction 0-004-023 08/04/22 DONE DONE DONE 05/04/22 05/02/22 12/15/21 07/20/21 2,15,16 2,734,440 2,734,440 WLC 0 0 0 Gordon W. Jones Associates 0 10/27/23 YES 05/02/22
Cloverbank Elementary School:
19-0741 Reconstruction 0-005-021 02/25/20 DONE DONE DONE 11/08/19 11/01/19 09/19/19 05/16/17 4,7 783,000 783,000 SLC 0 0 0 Gordon W. Jones Associates 0 09/25/20 11/01/19
21-0789 Reconstruction 0-005-022 03/09/22 DONE DONE DONE 11/30/21 11/23/21 08/09/21 07/20/21 2,9,155,15,16 1,454,720 1,454,720 SLC 0 0 0 Gordon W. Jones Associates 0 12/08/23 11/23/21
High School:
18-1981 Reconstruction 0-006-033 06/13/19 DONE DONE DONE 05/16/19 05/15/19 06/07/18 09/27/18 2,10,15 829,563 829,563 SLC 0 0 0 Young And Wright Architectura 0 10/26/20 05/15/19
20-0950 Reconstruction 0-006-034 04/05/21 DONE DONE DONE 12/11/20 11/23/20 10/15/20 09/27/18 2,8 945,000 945,000 SLC 0 0 0 Gordon W. Jones Associates 0 06/20/22 11/23/20
21-0790 Reconstruction 0-006-035 03/09/22 DONE DONE DONE 11/30/21 11/23/21 08/09/21 07/20/21 2,4,7,8,9,10,13,155, 8,541,933 8,541,933 SLC 0 0 0 Gordon W. Jones Associates 0 12/08/23 11/23/21
21-1189 Reconstruction 0-006-036 03/29/22 DONE DONE DONE 01/24/22 01/21/22 12/15/21 05/18/21 8 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 06/24/22 01/21/22
21-1804 Reconstruction 0-006-037 12/01/22 DONE DONE DONE 05/11/22 05/09/22 03/22/22 09/27/18 10,16 290,813 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 05/09/22
22-2052 Reconstruction 0-006-038 08/18/23 DONE DONE DONE 04/17/23 04/17/23 03/28/23 07/20/21 2,8,9,16 2,119,742 2,119,742 WLC 0 0 0 Gordon W. Jones Associates 0 / / 04/17/23
23-1174 Reconstruction 0-006-039 UNREVIEWED 12/13/23 12/12/23 10/17/23 07/20/21 16 0 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 12/12/23
- Reconstruction 0-006-040 / / / / / / / / 2,4,7,8,9,10,14,155, 0 0 WLC 0 0 0 0 / / / /
Pinehurst Elementary:
19-0742 Reconstruction 0-007-021 02/25/20 DONE DONE DONE 11/08/19 11/01/19 09/19/19 05/16/17 4,7 1,105,000 1,105,000 SLC 0 0 0 Gordon W. Jones Associates 0 09/25/20 11/01/19
20-0699 Reconstruction 0-007-022 01/16/21 DONE DONE DONE 10/28/20 10/23/20 09/16/20 06/16/20 8 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 06/18/21 10/23/20
- XX Reconstruction 0-007-023 CANCELLED / / / / 10/05/20 / / 2 0 12,213,000 SLC 0 0 0 0 / / / /
21-0791 Reconstruction 0-007-024 03/09/22 DONE DONE DONE 11/30/21 11/23/21 08/09/21 07/20/21 2,4,8,9,10,13,155,15 5,845,851 5,845,851 SLC 0 0 0 Gordon W. Jones Associates 0 12/08/23 11/23/21
Big Tree Elementary School:
21-0792 Reconstruction 0-011-013 03/09/22 DONE DONE DONE 11/30/21 11/23/21 08/09/21 07/20/21 2,9,155,15,16 2,022,645 2,022,645 SLC 0 0 0 Gordon W. Jones Associates 0 12/08/23 11/23/21
22-0702 Reconstruction 0-011-014 12/01/22 DONE DONE DONE 10/12/22 10/11/22 07/28/22 05/17/22 2,9 100,000 100,000 WLC 0 0 0 Gordon W. Jones Associates 0 06/16/23 10/11/22
Amsdell Middle School:
18-2066 Reconstruction 0-013-023 06/28/19 DONE DONE DONE 06/05/19 05/24/19 01/29/19 05/21/19 2,8,9 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/29/20 05/24/19
22-0107 Reconstruction 0-013-024 01/30/23 DONE DONE DONE 07/18/22 07/18/22 08/09/21 07/20/21 2,4,7,8,9,10,13,155, 14,721,348 14,721,348 JJH 0 0 0 Gordon W. Jones Associates 0 / / 07/18/22
Frontier Educational Center:
21-0363 Reconstruction 1-010-005 09/16/21 DONE DONE DONE 09/15/21 09/14/21 07/22/21 09/07/21 2,155,15,16 500,000 0 SLC 0 0 0 Gordon W. Jones Associates 0 04/07/23 09/14/21
Bus Garage:
23-0523 Reconstruction 4-001-013 04/14/23 DONE DONE DONE 09/20/23 09/19/23 04/12/23 04/18/23 15 360,000 360,000 WLC 0 0 0 Gordon W. Jones Associates 0 / / 09/19/23
23-0727 Reconstruction 4-001-014 11/15/23 DONE DONE DONE 10/18/23 10/13/23 04/12/23 05/16/23 14 100,000 100,000 WLC 0 0 0 Gordon W. Jones Associates 0 / / 10/13/23
New Concession Stand:
21-0793SR New Construction 7-025-001 03/17/22 DONE DONE DONE 11/30/21 11/23/21 08/09/21 07/20/21 02 - 16 0 0 SLC 0 0 0 Gordon W. Jones Associates 0 04/05/23 11/23/21
New Home Softball Dugout:
21-0794 New Construction 7-026-001 03/17/22 DONE DONE DONE 11/30/21 11/23/21 08/31/21 07/20/21 02 - 16 69,721 0 SLC 0 0 0 Gordon W. Jones Associates 0 04/05/23 11/23/21
New Visitor Softball Dugout:
21-0795 New Construction 7-027-001 03/17/22 DONE DONE DONE 11/30/21 11/23/21 08/31/21 07/20/21 02 - 16 69,722 0 SLC 0 0 0 Gordon W. Jones Associates 0 04/05/23 11/23/21
New Home Baseball Dugout:
21-0796 New Construction 7-028-001 03/17/22 DONE DONE DONE 11/30/21 11/23/21 08/31/21 07/20/21 02 - 16 69,721 0 SLC 0 0 0 Gordon W. Jones Associates 0 04/05/23 11/23/21
New Visitor Baseball Dugout:
21-0797 New Construction 7-029-001 03/17/22 DONE DONE DONE 11/30/21 11/23/21 08/31/21 07/20/21 02 - 16 69,721 0 SLC 0 0 0 Gordon W. Jones Associates 0 04/05/23 11/23/21
New Softball Field Press Box:
- New Construction 7-030-001 / / / / 10/12/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
District-Wide:
19-1206 Reconstruction 7-999-002 03/05/20 DONE DONE DONE 01/13/20 01/07/20 06/22/17 11/04/14 2,8,9,155,15,16 3,056,630 3,056,630 SLC 0 0 0 Young And Wright Architectura 0 03/12/21 01/07/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HOLLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-17-01-04
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Brumstead Elementary School:
19-0902 Reconstruction 0-002-011 04/10/20 DONE DONE DONE 12/03/19 11/18/19 09/23/19 05/21/19 2,155,15,16 1,627,000 1,627,000 SLC 0 0 0 Gordon W. Jones Associates 0 05/28/21 11/18/19
22-0287 Reconstruction 0-002-012 01/06/23 DONE DONE DONE 08/17/22 08/17/22 01/31/22 05/18/21 2,7,9,155,15,16 3,408,890 2,303,212 SLC 0 0 0 Gordon W. Jones Associates 0 10/02/23 08/17/22
22-2149PR Reconstruction 0-002-013 DONE 05/05/23 / / 04/13/23 / / 2,4,7,8,9,10,155,15, 0 8,877,273 MSK 0 0 0 0 / / / /
23-0078 Reconstruction 0-002-014 09/14/23 DONE DONE DONE 07/14/23 07/12/23 06/12/23 05/16/23 8 100,000 100,000 MSK 0 0 0 Gordon W. Jones Associates 0 / / 07/12/23
High School:
19-0034 Reconstruction 0-003-021 09/06/19 DONE DONE DONE 07/09/19 07/01/19 12/18/18 11/13/18 2,4,8,9,10,155,15,16 1,586,250 1,586,250 SLC 0 0 0 Gordon W. Jones Associates 0 05/28/21 07/01/19
19-0484 Reconstruction 0-003-022 12/10/19 DONE DONE DONE 09/24/19 09/17/19 07/22/19 05/21/19 2,9,16 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 05/22/20 09/17/19
20-0557 Reconstruction 0-003-023 01/08/21 DONE DONE DONE 10/07/20 09/29/20 07/27/20 06/09/20 2,9,16 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 05/28/21 09/29/20
21-0281 Reconstruction 0-003-024 11/08/21 DONE DONE DONE 09/03/21 09/03/21 06/11/21 05/18/21 16 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 06/06/22 09/03/21
22-0288 Reconstruction 0-003-025 01/06/23 DONE DONE DONE 08/17/22 08/17/22 01/31/22 05/18/21 2,4,8,9,10,155,15,16 4,091,110 4,091,110 SLC 0 0 0 Gordon W. Jones Associates 0 10/02/23 08/17/22
22-0289 Reconstruction 0-003-026 11/14/22 DONE DONE DONE 08/17/22 08/17/22 07/12/22 05/17/22 16 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 05/26/23 08/17/22
22-2150PR Reconstruction 0-003-027 DONE 05/05/23 / / 04/13/23 / / 2,4,7,8,9,10,155,15, 0 11,797,230 MSK 0 0 0 0 / / / /
Middle School:
19-0035 Reconstruction 0-013-014 09/06/19 DONE DONE DONE 07/09/19 07/01/19 12/18/18 11/13/18 2,4,7,8,9,10,13,14,1 2,797,500 2,797,500 SLC 0 0 0 Gordon W. Jones Associates 0 05/28/21 07/01/19
19-0903 Reconstruction 0-013-015 04/10/20 DONE DONE DONE 12/03/19 11/18/19 09/23/19 05/21/19 2,9 638,000 638,000 SLC 0 0 0 Gordon W. Jones Associates 0 05/28/21 11/18/19
22-2151PR Reconstruction 0-013-016 DONE 05/05/23 / / 04/13/23 / / 2,4,7,8,9,10,155,15, 0 10,253,275 MSK 0 0 0 0 / / / /
Bus Garage:
19-0036 Reconstruction 5-004-007 09/06/19 DONE DONE DONE 07/09/19 07/01/19 12/18/18 11/13/18 2,4,7,8,9,10,155,15, 616,250 616,250 SLC 0 0 0 Gordon W. Jones Associates 0 05/28/21 07/01/19
Concession Stand:
19-0433DB Discovered Building 7-015-001 ADDENDUM REQ'D 09/18/19 09/18/19 05/30/96 / / 02 - 16 0 0 MGL 0 0 0 0 / / 09/18/19
District-Wide:
20-0271SB Reconstruction 7-999-002 DONE / / / / 08/26/20 / / 16 0 0 SLC 0 0 0 0 / / / /
20-1704 Reconstruction 7-999-002 10/07/21 DONE DONE DONE 05/12/21 04/30/21 08/26/20 11/04/14 16 690,786 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 04/30/21
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
XXTransportation Facility-Canceled:
- XX Reconstruction 8-018-001 CANCELLED / / / / 11/20/19 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LANCASTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-19-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School:
19-0632 Reconstruction 0-001-030 01/10/20 DONE DONE DONE 10/29/19 10/15/19 05/15/19 12/11/18 2,9,16 1,448,599 1,448,599 SLC 0 0 0 Young And Wright Architectura 0 02/01/21 10/15/19
19-1824 Reconstruction 0-001-031 07/13/20 DONE DONE DONE 06/09/20 05/29/20 05/21/20 06/09/20 2,9 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 04/14/21 05/29/20
20-1969 Reconstruction 0-001-032 10/08/21 DONE DONE DONE 06/30/21 06/30/21 12/07/20 12/11/18 2,4,7,8,9,10,14,155, 6,859,311 6,859,311 SLC 0 0 0 Young And Wright Architectura 0 11/28/23 06/30/21
20-1727 Reconstruction 0-001-033 06/14/21 DONE DONE DONE 05/18/21 05/17/21 04/27/21 12/11/18 2,16 516,250 516,250 SLC 0 0 0 Young And Wright Architectura 0 06/13/22 05/17/21
21-0027 Reconstruction 0-001-034 08/29/21 DONE DONE DONE 07/08/21 07/08/21 05/26/21 05/18/21 155,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/03/22 07/08/21
22-0116 Reconstruction 0-001-035 10/24/22 DONE DONE DONE 07/20/22 07/19/22 11/03/21 12/11/18 2,4,8,9,10,14,15,16 7,999,421 0 WLC 0 0 0 Young And Wright Architectura 0 / / 07/19/22
- Reconstruction 0-001-036 / / / / 07/27/23 / / 2,8,10,155,15,16 0 0 WLC 0 0 0 0 / / / /
Lancaster (Aurora) Middle School:
19-0044 Reconstruction 0-002-021 09/05/19 DONE DONE DONE 07/09/19 06/26/19 05/01/19 05/21/19 9,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 04/01/20 06/26/19
20-0153 Reconstruction 0-002-022 11/09/20 DONE DONE DONE 08/04/20 07/23/20 11/04/19 12/11/18 2,4,7,8,9,10,155,15, 10,967,688 10,967,688 SLC 0 0 0 Young And Wright Architectura 0 09/21/23 07/23/20
Como Park Elementary School:
19-0633 Reconstruction 0-005-018 01/10/20 DONE DONE DONE 10/29/19 10/15/19 05/16/19 12/11/18 2,8,10 735,277 735,277 SLC 0 0 0 Young And Wright Architectura 0 11/01/20 10/15/19
22-0117 Reconstruction 0-005-019 10/24/22 DONE DONE DONE 07/20/22 07/19/22 11/03/21 12/11/18 2,4,7,8,9,10,14,155, 8,426,344 8,426,344 WLC 0 0 0 Young And Wright Architectura 0 / / 07/19/22
22-0629PR Additions and Alterations 0-005-020 STARTED 10/05/22 / / 08/30/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
Court St. Elementary School:
20-1970 Reconstruction 0-006-022 10/08/21 DONE DONE DONE 06/30/21 06/30/21 12/07/20 12/11/18 2,4,7,8,9,10,155,15, 4,675,929 4,675,929 SLC 0 0 0 Young And Wright Architectura 0 05/01/23 06/30/21
22-0630PR Additions and Alterations 0-006-023 STARTED 10/05/22 / / 08/30/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
Hillview Elementary School:
19-0634 Reconstruction 0-007-018 01/10/20 DONE DONE DONE 10/29/19 10/15/19 05/15/19 12/11/18 2,8,9,15 464,847 464,847 SLC 0 0 0 Young And Wright Architectura 0 10/02/20 10/15/19
21-0344 Reconstruction 0-007-019 02/15/22 DONE DONE DONE 09/14/21 09/13/21 12/15/20 12/11/18 2,4,8,9,10,155,15,16 2,276,000 2,276,000 SLC 0 0 0 Young And Wright Architectura 0 11/28/23 09/13/21
20-1587SB Additions and Alterations 0-007-020 DONE / / / / 04/14/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-0489 Additions and Alterations 0-007-020 02/16/22 DONE DONE DONE 10/08/21 10/06/21 04/14/21 11/04/14 02 - 16 2,108,000 0 SLC 0 0 0 Young And Wright Architectura 0 11/28/23 10/06/21
22-0631PR Additions and Alterations 0-007-021 STARTED 10/05/22 / / 08/30/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
John A. Sciole Elem School:
19-0635 Reconstruction 0-008-015 01/10/20 DONE DONE DONE 10/29/19 10/15/19 05/15/19 12/11/18 2,8 494,749 494,749 SLC 0 0 0 Young And Wright Architectura 0 10/02/20 10/15/19
22-0632PR Additions and Alterations 0-008-016 STARTED 10/05/22 / / 08/30/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-0024 Reconstruction 0-008-017 11/07/23 DONE DONE DONE 07/07/23 07/05/23 01/30/23 12/11/18 2,4,7,8,9,10,155,15, 6,380,102 6,380,102 WLC 0 0 0 Young And Wright Architectura 0 / / 07/05/23
Central Ave Elem-PreK(09/10):
19-1506 Reconstruction 0-013-012 03/24/20 DONE DONE DONE 03/02/20 02/26/20 02/06/20 05/19/15 2,155,15,16 208,150 208,150 SLC 0 0 0 Young And Wright Architectura 0 11/18/20 02/26/20
William St. Elementary:
19-0636 Reconstruction 0-017-007 01/10/20 DONE DONE DONE 10/29/19 10/15/19 05/15/19 12/11/18 2,7,16 5,071,300 4,765,938 SLC 0 0 0 Young And Wright Architectura 0 10/02/20 10/15/19
19-0470 Reconstruction 0-017-008 09/23/19 DONE DONE DONE 09/23/19 09/20/19 08/29/19 12/11/18 155 59,700 59,700 SLC 0 0 0 Young And Wright Architectura 0 03/20/20 09/20/19
22-0359 Reconstruction 0-017-009 10/07/22 DONE DONE DONE 08/26/22 08/26/22 06/22/22 05/17/22 16 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 / / 08/26/22
22-0633PR Additions and Alterations 0-017-010 STARTED 10/05/22 / / 08/30/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-017-011 / / / / 07/27/23 / / 2,7,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
295 Pleasantview Bldg Admin(see5-004:
21-1964 Reconstruction 1-004-001 06/16/22 DONE DONE DONE 06/13/22 06/13/22 05/09/22 12/11/18 2,155 400,000 0 WLC 0 0 0 Young And Wright Architectura 0 04/04/23 06/13/22
23-0025 Reconstruction 1-004-002 11/07/23 DONE DONE DONE 07/07/23 07/05/23 01/30/23 12/11/18 2,155,15,16 321,686 0 WLC 0 0 0 Young And Wright Architectura 0 / / 07/05/23
HS Multi-Purpose Field Storage:
- PR New Construction 2-050-001 / / / / 04/06/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-0118 New Construction 2-050-001 10/24/22 DONE DONE DONE 07/20/22 07/19/22 04/06/22 12/11/18 02 - 16 288,868 0 WLC 0 0 0 Young And Wright Architectura 0 12/06/23 07/19/22
Maintenance Bldg.:
21-0801 Reconstruction 3-009-002 06/14/22 DONE DONE DONE 11/30/21 11/24/21 11/12/21 05/17/22 2,4,8,9,155,16 75,000 0 WLC 0 0 0 Young And Wright Architectura 0 03/01/23 11/24/21
XXBus garage - now 1-004 for Admin:
19-0028 Reconstruction 5-004-009 07/10/19 DONE DONE DONE 07/08/19 06/26/19 06/07/19 12/11/18 2 200,000 200,000 SLC 0 0 0 Young And Wright Architectura 0 09/13/19 06/26/19
20-1237 Reconstruction 5-004-010 03/16/21 DONE DONE DONE 02/04/21 02/02/21 01/19/21 12/11/18 2 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 08/18/21 02/02/21
XXTent #1 @ LHS (homecoming-Dismantl:
21-0535TQ Temporary Quarters 7-021-001 10/26/21 DONE DONE DONE 10/15/21 10/15/21 10/13/21 / / 02 - 16 0 0 SLC 0 0 0 0 10/20/21 10/15/21
XXTent #2 @ LHS (homecoming-Dismantl:
21-0536TQ Temporary Quarters 7-022-001 10/26/21 DONE DONE DONE 10/15/21 10/15/21 10/13/21 / / 02 - 16 0 0 SLC 0 0 0 0 10/20/21 10/15/21
District-Wide:
22-0360 Reconstruction 7-999-005 11/30/22 DONE DONE DONE 08/26/22 08/26/22 07/28/22 12/11/18 171,851 171,851 JJH 0 0 0 Young And Wright Architectura 0 06/23/23 08/26/22
Como Park Annex SS:
22-2028SS New Construction 8-023-001 06/15/23 DONE DONE DONE 04/14/23 04/13/23 12/01/22 12/11/18 02 - 16 1,724,000 0 WLC 0 0 0 Young And Wright Architectura 0 08/23/23 04/13/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
NORTH COLLINS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-22-01-04
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior/Senior High School:
19-0542 Reconstruction 0-001-010 02/06/20 DONE DONE DONE 10/10/19 09/27/19 02/11/19 12/11/18 2,8,9,155,15,16 4,300,000 4,300,000 BMJ 0 0 0 Young And Wright Architectura 0 03/17/21 09/27/19
19-0576 Reconstruction 0-001-011 12/19/19 DONE DONE DONE 10/18/19 10/02/19 08/01/19 05/21/19 4 100,000 100,000 BMJ 0 0 0 Young And Wright Architectura 0 06/25/20 10/02/19
21-0740 Reconstruction 0-001-012 01/06/22 DONE DONE DONE 11/17/21 11/16/21 11/01/21 05/18/21 16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/20/22 11/16/21
22-0396 Reconstruction 0-001-013 12/21/22 DONE DONE DONE 09/02/22 09/02/22 07/18/22 05/17/22 7 1,719,332 1,719,332 WLC 0 0 0 Young And Wright Architectura 0 10/01/23 09/02/22
22-2380 Reconstruction 0-001-014 11/02/23 DONE DONE DONE 06/14/23 06/14/23 01/31/23 05/17/22 2,4,7,8,9,10,155,15, 4,556,309 4,546,382 WLC 0 0 0 Young And Wright Architectura 0 / / 06/14/23
23-0722 Reconstruction 0-001-015 12/22/23 DONE DONE DONE 10/16/23 10/07/23 10/05/23 05/16/23 2,9 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 / / 10/07/23
Elementary School:
- PR Additions and Alterations 0-002-012 STARTED / / / / 09/17/19 / / 02 - 16 0 16,047,735 BMJ 0 0 0 0 / / / /
19-0543 Additions and Alterations 0-002-012 02/06/20 DONE DONE DONE 10/10/19 09/27/19 09/17/19 12/11/18 02 - 16 5,580,000 5,566,280 BMJ 0 0 0 Young And Wright Architectura 0 03/17/21 09/27/19
20-1268 Reconstruction 0-002-013 03/01/21 DONE DONE DONE 02/09/21 02/02/21 01/21/21 06/16/20 9,10,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/25/21 02/02/21
22-0244 Reconstruction 0-002-014 10/20/22 DONE DONE DONE 08/08/22 08/08/22 04/29/22 05/17/22 16 100,000 100,000 WLC 0 0 0 Young And Wright Architectura 0 05/24/23 08/08/22
22-0402 Reconstruction 0-002-015 01/09/23 DONE DONE DONE 09/02/22 09/02/22 07/18/22 05/17/22 7 469,914 469,914 JJH 0 0 0 Young And Wright Architectura 0 05/24/23 09/02/22
22-2381 Reconstruction 0-002-016 11/02/23 DONE DONE DONE 06/14/23 06/14/23 01/31/23 05/17/22 2,7,8,9,10,155,15,16 1,114,608 1,114,608 WLC 0 0 0 Young And Wright Architectura 0 / / 06/14/23
Bus Storage Facility:
19-0544 New Construction 4-006-002 02/06/20 DONE DONE DONE 10/10/19 09/27/19 02/11/19 12/11/18 02 - 16 633,500 633,500 SLC 0 0 0 Young And Wright Architectura 0 03/17/21 09/27/19
22-2382 Reconstruction 4-006-003 11/02/23 DONE DONE DONE 06/14/23 06/14/23 01/31/23 05/17/22 2,15,16 89,837 89,837 WLC 0 0 0 Young And Wright Architectura 0 / / 06/14/23
XXBus Garage - canceled:
- XX Reconstruction 5-005-002 02/06/20 CANCELLED 10/10/19 09/27/19 02/11/19 12/11/18 2,16 633,500 633,500 BMJ 0 0 0 Young And Wright Architectura 0 / / 09/27/19
20-0987XX Reconstruction 5-005-003 CANCELLED / / / / 09/01/20 12/11/18 4,8,9,155,15,16 133,500 133,500 SLC 0 0 0 Young And Wright Architectura 0 / / / /
District-Wide:
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ORCHARD PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-23-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Windom Elementary:
18-2131 Reconstruction 0-001-015 08/09/19 DONE DONE DONE 06/17/19 06/10/19 12/17/18 11/13/18 2,4,7,8,9,10,155,15, 4,850,505 4,850,505 SLC 0 0 0 Gordon W. Jones Associates 0 05/07/21 06/10/19
21-1248PR Additions and Alterations 0-001-016 DONE 02/09/22 / / 10/08/21 / / 02 - 16 0 18,289,877 SLC 0 0 0 0 / / / /
23-1869 Additions and Alterations 0-001-016 UNREVIEWED 04/19/24 04/19/24 10/08/21 05/17/22 02 - 16 0 18,289,877 MSK 0 0 0 Gordon W. Jones Associates 0 / / 04/19/24
22-1650FC Reconstruction 0-001-017 05/08/23 DONE DONE DONE 02/10/23 12/19/21 10/11/22 05/17/22 2,16 1,683,593 1,683,593 JLB 0 0 0 Gordon W. Jones Associates 0 / / 12/19/21
Senior High School:
18-2132 Reconstruction 0-002-025 08/09/19 DONE DONE DONE 06/17/19 06/10/19 / / 11/13/18 4,8,9,10,155,16 377,620 377,620 SLC 0 0 0 Gordon W. Jones Associates 0 05/07/21 06/10/19
21-1249PR Additions and Alterations 0-002-026 DONE 02/09/22 / / 10/12/21 / / 02 - 16 0 57,939,948 SLC 0 0 0 0 / / / /
22-1797 Additions and Alterations 0-002-026 05/23/23 DONE DONE DONE 03/08/23 03/06/23 10/12/21 05/17/22 02 - 16 39,520,014 17,834,459 JLB 0 0 0 Gordon W. Jones Associates 0 / / 03/06/23
22-0655 Reconstruction 0-002-027 02/22/23 DONE DONE DONE 10/07/22 09/30/22 09/08/22 05/17/22 2,9,16 5,090,650 5,090,650 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
23-1699 Reconstruction 0-002-028 UNREVIEWED 03/28/24 03/28/24 02/15/24 05/17/22 155,16 0 0 MSK 0 0 0 Gordon W. Jones Associates 0 / / 03/28/24
23-1870 Reconstruction 0-002-029 UNREVIEWED 04/19/24 04/19/24 03/05/24 05/17/22 8 0 0 MSK 0 0 0 Gordon W. Jones Associates 0 / / 04/19/24
Middle School:
18-2133 Reconstruction 0-003-021 08/09/19 DONE DONE DONE 06/17/19 06/10/19 12/17/18 11/13/18 2,4,7,8,9,10,155,15, 5,410,960 5,410,960 SLC 0 0 0 Gordon W. Jones Associates 0 05/07/21 06/10/19
21-1250PR Additions and Alterations 0-003-022 DONE 02/09/22 / / 10/12/21 / / 02 - 16 0 41,673,592 SLC 0 0 0 0 / / / /
22-1798 Reconstruction 0-003-023 05/23/23 DONE DONE DONE 03/08/23 03/06/23 10/24/22 05/17/22 2,16 5,326,202 5,326,202 JLB 0 0 0 Gordon W. Jones Associates 0 / / 03/06/23
23-1871 Reconstruction 0-003-024 UNREVIEWED 04/19/24 04/19/24 03/05/24 05/17/22 8 0 0 MSK 0 0 0 Gordon W. Jones Associates 0 / / 04/19/24
South Davis Elementary:
18-2134 Reconstruction 0-004-022 08/09/19 DONE DONE DONE 06/17/19 06/10/19 12/17/18 11/13/18 2,4,8,9,10,155,15,16 815,235 815,235 SLC 0 0 0 Gordon W. Jones Associates 0 05/07/21 06/10/19
21-1251PR Additions and Alterations 0-004-023 DONE 02/09/22 / / 10/08/21 / / 02 - 16 0 11,391,123 SLC 0 0 0 0 / / / /
23-1872 Additions and Alterations 0-004-023 UNREVIEWED 04/19/24 04/19/24 10/08/21 05/17/22 02 - 16 0 11,391,123 MSK 0 0 0 Gordon W. Jones Associates 0 / / 04/19/24
22-1651FC Reconstruction 0-004-024 05/08/23 DONE DONE DONE 02/10/23 12/19/21 10/11/22 05/17/22 2,16 1,680,324 1,327,345 JLB 0 0 0 Gordon W. Jones Associates 0 / / 12/19/21
22-1799 Reconstruction 0-004-025 05/23/23 DONE DONE DONE 03/08/23 03/06/23 10/24/22 05/17/22 2,8,16 1,650,902 1,305,228 JLB 0 0 0 Gordon W. Jones Associates 0 / / 03/06/23
Eggert Road Elementary:
18-2135 Reconstruction 0-006-013 08/08/19 DONE DONE DONE 06/17/19 06/10/19 12/17/18 11/13/18 2,4,8,9,10,155,15,16 211,515 211,515 SLC 0 0 0 Gordon W. Jones Associates 0 05/07/21 06/10/19
21-1252PR Additions and Alterations 0-006-014 DONE 02/09/22 / / 10/12/21 / / 02 - 16 0 18,957,737 SLC 0 0 0 0 / / / /
23-1873 Additions and Alterations 0-006-014 UNREVIEWED 04/19/24 04/19/24 10/12/21 05/17/22 02 - 16 0 18,957,737 MSK 0 0 0 Gordon W. Jones Associates 0 / / 04/19/24
22-1652FC Reconstruction 0-006-015 05/08/23 DONE DONE DONE 02/10/23 12/19/21 10/11/22 05/17/22 2,16 1,683,593 1,683,593 JLB 0 0 0 Gordon W. Jones Associates 0 / / 12/19/21
Ellicott Road Elementary School:
18-2136 Reconstruction 0-007-014 08/09/19 DONE DONE DONE 06/17/19 06/10/19 12/17/18 11/13/18 2,4,8,9,10,155,16 534,165 534,165 SLC 0 0 0 Gordon W. Jones Associates 0 05/07/21 06/10/19
19-0301 Reconstruction 0-007-015 01/02/20 DONE DONE DONE 08/27/19 08/15/19 12/26/18 05/21/19 2 100,000 100,000 SLC 0 0 0 Gordon W. Jones Associates 0 10/01/20 08/15/19
21-1253PR Additions and Alterations 0-007-016 DONE 02/09/22 / / 10/12/21 / / 02 - 16 0 20,668,698 SLC 0 0 0 0 / / / /
23-1874 Additions and Alterations 0-007-016 UNREVIEWED 04/19/24 04/19/24 10/12/21 05/17/22 02 - 16 0 20,668,698 MSK 0 0 0 Gordon W. Jones Associates 0 / / 04/19/24
22-1653FC Reconstruction 0-007-017 05/08/23 DONE DONE DONE 02/10/23 12/19/21 10/11/22 05/17/22 2,16 1,683,592 1,683,592 JLB 0 0 0 Gordon W. Jones Associates 0 / / 12/19/21
22-1800 Reconstruction 0-007-018 05/23/23 DONE DONE DONE 03/08/23 03/06/23 10/24/22 05/17/22 2,9,16 627,670 627,670 JLB 0 0 0 Gordon W. Jones Associates 0 / / 03/06/23
District Office Building:
- Reconstruction 1-016-003 / / / / 10/12/21 / / 2,16 0 0 SLC 0 0 0 0 / / / /
Athletic ShelterXX Demo:
22-0656 Reconstruction 2-009-001 02/18/23 DONE DONE DONE 10/07/22 09/30/22 07/29/22 05/17/22 2,4,7,8,9,155,15,16 76,298 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
Bus Garage:
22-1801 Reconstruction 5-005-010 05/23/23 DONE DONE DONE 03/08/23 03/06/23 10/12/21 05/17/22 16 572,094 572,094 JLB 0 0 0 Gordon W. Jones Associates 0 / / 03/06/23
HS Football Str ShedXX Demo:
22-0657 Reconstruction 7-021-002 02/18/23 DONE DONE DONE 10/07/22 09/30/22 07/29/22 05/17/22 2,7,8,9 11,760 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
High School Press Box demolition:
22-0658 Reconstruction 7-022-002 02/18/23 DONE DONE DONE 10/07/22 09/30/22 10/12/21 05/17/22 12,200 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
Visitor Concession @ HS XX Demo:
22-0659 Reconstruction 7-023-002 02/18/23 DONE DONE DONE 10/07/22 09/30/22 07/29/22 05/17/22 2,7,8,9 12,640 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
Athletic Locker Rooms & Concess. Bld:
22-0660 New Construction 7-031-001 02/20/23 DONE DONE DONE 10/07/22 09/30/22 10/14/21 05/17/22 02 - 16 6,997,586 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
HS Press Box (New):
22-0661 New Construction 7-032-001 02/20/23 DONE DONE DONE 10/07/22 09/30/22 10/14/21 05/17/22 02 - 16 213,501 0 SLC 0 0 0 Gordon W. Jones Associates 0 / / 09/30/22
District-Wide:
21-0108 Reconstruction 7-999-007 02/03/22 DONE DONE DONE 07/28/21 07/28/21 06/28/18 11/04/14 16 772,077 0 SLC 0 0 0 Gordon W. Jones Associates 0 12/14/23 07/28/21
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 0 0 SLC 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA3 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
KENMORE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-26-01-03
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Herbert Hoover Elementary School:
19-0558PR Additions and Alterations 0-006-016 DONE STARTED 10/16/19 / / 05/30/19 / / 02 - 16 0 17,608,603 JSS 0 0 0 0 / / / /
21-0080 Additions and Alterations 0-006-016 03/22/22 DONE DONE DONE 07/21/21 07/02/21 05/30/19 02/05/20 02 - 16 10,725,200 9,955,574 SLC 0 0 0 Clark Patterson Lee 0 / / 07/02/21
20-0763 Reconstruction 0-006-017 03/19/21 DONE DONE DONE 11/03/20 10/01/20 09/14/20 12/10/19 2,4,8,9,155,15,16 496,363 496,363 JSS 0 0 0 Clark Patterson Lee 0 09/02/22 10/01/20
Herbert Hoover Middle School:
21-0082 Reconstruction 0-007-020 03/22/22 DONE DONE DONE 07/21/21 07/02/21 04/12/21 02/05/20 2,4,7,8,9,10,155,15, 5,556,000 5,556,000 SLC 0 0 0 Clark Patterson Lee 0 / / 07/02/21
22-0774FC Reconstruction 0-007-021 02/15/23 DONE DONE DONE 10/21/22 08/25/22 03/21/22 12/14/21 7,9,155,15,16 426,300 0 SLC 0 0 0 Clark Patterson Lee 0 / / 08/25/22
Kenmore East Sr. High School:
20-0764 Reconstruction 0-009-021 03/19/21 DONE DONE DONE 11/03/20 10/01/20 09/14/20 12/10/19 2,4,7,8,9,10,13,155, 6,955,329 6,955,329 JSS 0 0 0 Clark Patterson Lee 0 06/10/22 10/01/20
22-0777FC Reconstruction 0-009-022 02/15/23 DONE DONE DONE 10/21/22 08/25/22 03/21/22 12/14/21 2,7,9,155,15,16 740,000 0 SLC 0 0 0 Clark Patterson Lee 0 / / 08/25/22
- Reconstruction 0-009-023 / / / / 03/21/22 / / 2,7,9,155,15,16 0 0 SLC 0 0 0 0 / / / /
22-2431 Reconstruction 0-009-024 12/04/23 DONE DONE DONE 06/21/23 06/21/23 12/16/22 02/05/20 2,4,7,8,9,10,155,15, 8,529,631 8,529,631 JLB 0 0 0 Clark Patterson Lee Architect 0 / / 06/21/23
23-0103FA Reconstruction 0-009-025 08/29/23 DONE DONE DONE 07/17/23 07/14/23 05/26/23 06/13/23 7,9,10,155,15,16 125,000 125,000 MSK 0 0 0 Clark Patterson Lee Architect 0 / / 07/14/23
23-0100FA Reconstruction 0-009-026 07/26/23 DONE DONE DONE 07/17/23 07/14/23 05/26/23 06/13/23 16 1,300,000 1,300,000 MSK 0 0 0 Clark Patterson Lee Architect 0 / / 07/14/23
Thomas Edison Elementary:
19-0559PR Reconstruction 0-010-014 DONE 10/16/19 / / 09/25/19 / / 2,4,7,8,9,10,155,15, 0 13,031,918 JSS 0 0 0 0 / / / /
21-0081 Reconstruction 0-010-014 03/22/22 DONE DONE DONE 07/21/21 07/02/21 09/25/19 02/05/20 2,4,7,8,9,10,155,15, 9,795,100 8,598,911 SLC 0 0 0 Clark Patterson Lee 0 / / 07/02/21
20-0584 Reconstruction 0-010-015 02/04/21 DONE DONE DONE 10/13/20 10/08/20 09/14/20 12/10/19 2,4,7,8,9,155,16 1,281,864 1,281,864 JSS 0 0 0 Clark Patterson Lee 0 12/20/22 10/08/20
Kenmore West Senior High:
20-1426 Reconstruction 0-014-026 04/13/21 DONE DONE DONE 03/11/21 03/03/21 01/21/21 03/10/20 2,8,155,15 100,000 100,000 JSS 0 0 0 Clark Patterson Lee 0 06/15/21 03/03/21
- PR Additions and Alterations 0-014-027 / / / / 04/12/21 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
21-0083 Additions and Alterations 0-014-027 03/22/22 DONE DONE DONE 07/21/21 07/02/21 04/12/21 02/05/20 02 - 16 10,514,850 10,514,850 SLC 0 0 0 Clark Patterson Lee 0 / / 07/02/21
22-0775FC Reconstruction 0-014-028 02/15/23 DONE DONE DONE 10/21/22 08/25/22 03/21/22 12/14/21 7,9,155,15,16 960,000 0 SLC 0 0 0 Clark Patterson Lee 0 / / 08/25/22
22-2461FA Reconstruction 0-014-029 07/31/23 DONE DONE DONE 06/26/23 04/21/23 04/04/23 04/11/23 4,8,9,10,16 600,000 600,000 MSK 0 0 0 Clark Patterson Lee 0 / / 04/21/23
23-0104FA Reconstruction 0-014-030 08/29/23 DONE DONE DONE 07/17/23 07/14/23 05/26/23 06/13/23 7,9,10,155,15,16 125,000 125,000 MSK 0 0 0 Clark Patterson Lee Architect 0 / / 07/14/23
Charles Lindbergh Elementary School:
19-0560PR Additions and Alterations 0-024-018 DONE 10/16/19 / / 09/25/19 / / 02 - 16 0 11,518,720 JSS 0 0 0 0 / / / /
20-0585 Reconstruction 0-024-019 02/04/21 DONE DONE DONE 10/13/20 10/08/20 09/14/20 12/14/19 2,4,7,8,9,155,15,16 1,683,134 1,683,134 JSS 0 0 0 Clark Patterson Lee 0 05/17/23 10/08/20
22-2432 Reconstruction 0-024-020 12/04/23 DONE DONE DONE 06/21/23 06/21/23 12/16/22 02/05/20 2,4,7,8,9,10,155,15, 905,284 905,284 JLB 0 0 0 Clark Patterson Lee Architect 0 / / 06/21/23
Benjamin Franklin Middle School:
19-1813 Reconstruction 0-025-019 09/11/20 DONE DONE DONE 06/03/20 05/12/20 03/31/20 12/10/19 2,4,7 414,611 414,611 JSS 0 0 0 Clark Patterson Lee 0 08/15/21 05/12/20
20-0765 Reconstruction 0-025-020 03/19/21 DONE DONE DONE 11/03/20 10/01/20 09/14/20 12/10/19 2,4,7,8,9,10,155,15, 3,089,906 3,089,906 JSS 0 0 0 Clark Patterson Lee 0 09/02/22 10/01/20
23-0101FA Reconstruction 0-025-021 07/26/23 DONE DONE DONE 07/17/23 07/14/23 05/26/23 06/13/23 16 501,936 501,936 MSK 0 0 0 Clark Patterson Lee Architect 0 / / 07/14/23
Benjamin Franklin Elementary School:
19-1814 Reconstruction 0-026-015 09/11/20 DONE DONE DONE 06/03/20 05/12/20 03/31/20 12/10/19 2,4,7 1,658,443 1,658,443 JSS 0 0 0 Clark Patterson Lee 0 08/15/21 05/12/20
20-0766 Reconstruction 0-026-016 03/19/21 DONE DONE DONE 11/03/20 10/01/20 09/14/20 12/10/19 2,4,7,8,9,10,155,15, 2,654,341 2,654,341 JSS 0 0 0 Clark Patterson Lee 0 09/02/22 10/01/20
23-0102FA Reconstruction 0-026-017 07/26/23 DONE DONE DONE 07/17/23 07/14/23 05/30/23 06/13/23 16 501,936 501,936 MSK 0 0 0 Clark Patterson Lee Architect 0 / / 07/14/23
Holmes Elementary:
19-1815 Reconstruction 0-030-011 09/11/20 DONE DONE DONE 06/03/20 05/12/20 03/31/20 12/10/19 2,4,7 2,223,952 2,223,952 JSS 0 0 0 Clark Patterson Lee 0 08/15/21 05/12/20
20-0767 Reconstruction 0-030-012 03/19/21 DONE DONE DONE 11/03/20 10/01/20 09/14/20 12/10/19 2,4,8,9,10,155,15,16 1,604,450 1,604,450 JSS 0 0 0 Clark Patterson Lee 0 06/10/22 10/01/20
Administration Building:
21-0084 Reconstruction 1-002-010 03/22/22 DONE DONE DONE 07/21/21 07/02/21 04/12/21 02/05/20 2,16 391,600 0 SLC 0 0 0 Clark Patterson Lee 0 / / 07/02/21
22-0776XX Reconstruction 1-002-011 CANCELLED 10/21/22 08/25/22 03/21/22 / / 2,7,9,155,15,16 0 0 SLC 0 0 0 Clark Patterson Lee 0 / / 08/25/22
Bus Garage @ Military Rd. 32%Admin:
22-0369 Reconstruction 5-034-006 01/12/23 DONE DONE DONE 08/29/22 08/26/22 07/08/22 05/17/22 2,15,16 100,000 100,000 SLC 0 0 0 Clark Patterson Lee 0 / / 08/26/22
Softball Dugout @ Ken East HS:
20-0768 New Construction 7-037-001 03/19/21 DONE DONE DONE 11/03/20 10/01/20 07/02/20 12/10/19 02 - 16 64,128 0 JSS 0 0 0 Clark Patterson Lee 0 06/10/22 10/01/20
Softball Pressbox @ Ken East HS:
20-0769 New Construction 7-038-001 03/19/21 DONE DONE DONE 11/03/20 10/01/20 07/02/20 12/10/19 02 - 16 195,145 0 JSS 0 0 0 Clark Patterson Lee 0 06/10/22 10/01/20
Baseball Dugout @ Ken East HS:
20-0770 New Construction 7-039-001 03/19/21 DONE DONE DONE 11/03/20 10/01/20 07/02/20 12/10/19 02 - 16 64,128 0 JSS 0 0 0 Clark Patterson Lee 0 06/10/22 10/01/20
Baseball Press Box @ Ken East HS:
20-0771 New Construction 7-040-001 03/19/21 DONE DONE DONE 11/03/20 10/01/20 07/02/20 12/10/19 02 - 16 195,145 0 JSS 0 0 0 Clark Patterson Lee 0 06/10/22 10/01/20
District-Wide:
21-0541 Reconstruction 7-999-006 03/25/22 DONE DONE DONE 10/18/21 10/15/21 / / 02/09/16 8,13,16 2,638,145 0 SLC 0 0 0 Clark Patterson Lee 0 / / 10/15/21
Const Swing Space @ Edison Elem:
20-0790SS New Construction 8-036-001 12/21/20 DONE DONE DONE 11/10/20 08/28/20 04/03/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / 08/28/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WEST SENECA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-28-01-06
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
West Senior High School:
19-0271 Reconstruction 0-001-026 12/17/19 DONE DONE DONE 08/16/19 07/31/19 01/22/19 12/04/18 2,4,9,16 7,956,650 7,956,650 SLC 0 0 0 Young And Wright Architectura 0 10/01/21 07/31/19
20-1027XX Reconstruction 0-001-027 CANCELLED 12/22/20 12/17/20 10/02/20 12/04/18 2,8,16 177,000 177,000 SLC 0 0 0 Young And Wright Architectura 0 / / 12/17/20
21-1890 Reconstruction 0-001-028 11/17/22 DONE DONE DONE 05/31/22 05/26/22 05/26/21 12/04/18 2,4,7,8,9,10,14,155, 4,900,000 4,900,000 SLC 0 0 0 Young And Wright Architectura 0 / / 05/26/22
21-0649 Reconstruction 0-001-029 01/18/22 DONE DONE DONE 11/04/21 11/03/21 08/30/21 05/18/21 2,15 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/15/22 11/03/21
23-1704 Reconstruction 0-001-030 UNREVIEWED 03/29/24 03/28/24 01/31/24 12/12/23 2,4,7,155,15,16 0 0 MSK 0 0 0 Young And Wright Architectura 0 / / 03/28/24
West Middle School:
19-0272 Reconstruction 0-002-018 12/17/19 DONE DONE DONE 08/16/19 07/31/19 01/22/19 12/04/18 2,7 776,725 776,725 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 07/31/19
19-0996 Reconstruction 0-002-019 02/07/20 DONE DONE DONE 12/13/19 11/26/19 08/01/19 05/21/19 2,9,15,16 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 05/15/20 11/26/19
- Additions and Alterations 0-002-020 UNREVIEWED 10/13/20 10/13/20 10/16/19 / / 02 - 16 0 27,669,976 SLC 0 0 0 0 / / 10/13/20
20-0595PR Additions and Alterations 0-002-020 UNREVIEWED 10/13/20 10/13/20 10/16/19 / / 02 - 16 0 27,669,976 SLC 0 0 0 0 / / 10/13/20
20-1010 Additions and Alterations 0-002-020 12/10/21 DONE DONE DONE 12/22/20 12/18/20 10/16/19 12/04/18 02 - 16 9,000,000 8,384,493 SLC 0 0 0 Young And Wright Architectura 0 03/01/23 12/18/20
20-0988 Reconstruction 0-002-021 02/11/21 DONE DONE DONE 12/17/20 12/17/20 10/02/20 06/09/20 2,15 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/24/21 12/17/20
Allendale Elementary:
19-0273 Reconstruction 0-003-019 12/17/19 DONE DONE DONE 08/16/19 07/31/19 01/22/19 12/04/18 2,7 2,364,900 2,364,900 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 07/31/19
23-0241 Reconstruction 0-003-020 02/28/24 DONE DONE DONE 08/11/23 08/08/23 09/22/22 12/04/18 2,4,7,8,9,155,15,16 2,200,000 2,200,000 MSK 0 0 0 Young And Wright Architectura 0 / / 08/08/23
Winchester Acad-LsdToErie1BOCES21-22:
21-1810 Reconstruction 0-009-021 06/02/22 DONE DONE DONE 05/13/22 03/11/22 03/03/22 01/12/22 2 250,000 0 SLC 0 0 0 Young And Wright Architectura 0 07/27/22 03/11/22
East Middle School:
20-0596PR Reconstruction 0-012-023 UNREVIEWED 10/13/20 10/13/20 10/16/19 / / 2,4,7,8,9,10,155,15, 0 26,277,687 SLC 0 0 0 0 / / 10/13/20
20-1011 Reconstruction 0-012-023 12/10/21 DONE DONE DONE 12/22/20 12/18/20 10/16/19 12/04/18 2,4,7,8,9,10,155,15, 7,362,300 7,362,300 SLC 0 0 0 Young And Wright Architectura 0 09/29/23 12/18/20
20-1590 Reconstruction 0-012-024 05/25/21 DONE DONE DONE 04/16/21 04/16/21 03/29/21 12/04/18 2,4,7,155,15,16 4,917,700 4,917,700 SLC 0 0 0 Young And Wright Architectura 0 12/01/21 04/16/21
Winchester-Potters Elementary School:
23-0243 Reconstruction 0-014-014 02/28/24 DONE DONE DONE 08/11/23 08/08/23 09/22/22 12/04/18 2,4,7,8,9,155,15,16 1,300,000 1,300,000 MSK 0 0 0 Young And Wright Architectura 0 / / 08/08/23
22-1533 Reconstruction 0-014-015 03/09/23 DONE DONE DONE 01/23/23 01/23/23 09/22/22 12/04/18 2,4,7,155,15,16 2,100,000 2,100,000 SLC 0 0 0 Young And Wright Architectura 0 / / 01/23/23
Clinton Street Elementary:
23-0242 Reconstruction 0-015-013 02/28/24 DONE DONE DONE 08/11/23 08/08/23 09/22/22 12/04/18 2,4,7,8,9,155,15,16 2,000,000 2,000,000 MSK 0 0 0 Young And Wright Architectura 0 / / 08/08/23
22-1534 Reconstruction 0-015-014 03/09/23 DONE DONE DONE 01/23/23 01/23/23 09/22/22 12/04/18 2,4,7,155,15,16 2,100,000 2,100,000 SLC 0 0 0 Young And Wright Architectura 0 / / 01/23/23
East Senior High School:
19-0274 Reconstruction 0-017-025 12/17/19 DONE DONE DONE 08/16/19 07/31/19 01/22/19 12/04/18 2,4,9,16 7,342,660 6,795,865 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 07/31/19
20-1028 Reconstruction 0-017-026 03/26/21 DONE DONE DONE 12/22/20 12/16/20 10/02/20 12/04/18 2,8,16 216,000 216,000 SLC 0 0 0 Young And Wright Architectura 0 12/01/21 12/16/20
- PR Additions and Alterations 0-017-027 / / / / 05/26/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-1891 Additions and Alterations 0-017-027 11/17/22 DONE DONE DONE 05/31/22 05/26/22 05/26/21 12/04/18 02 - 16 6,560,000 6,560,000 SLC 0 0 0 Young And Wright Architectura 0 / / 05/26/22
23-1705 Reconstruction 0-017-028 UNREVIEWED 03/29/24 03/28/24 01/31/24 12/12/23 2,4,7,8,155,15,16 0 0 MSK 0 0 0 Young And Wright Architectura 0 / / 03/28/24
Northwood Elementary School:
23-0244 Reconstruction 0-018-010 02/28/24 DONE DONE DONE 08/11/23 08/08/23 09/22/22 12/04/18 2,4,7,8,9,155,15,16 1,850,000 1,850,000 MSK 0 0 0 Young And Wright Architectura 0 / / 08/08/23
23-1706 Reconstruction 0-018-011 UNREVIEWED 03/29/24 03/28/24 01/31/24 12/12/23 2,4,7,155,15,16 0 0 MSK 0 0 0 Young And Wright Architectura 0 / / 03/28/24
West ES (frmrly1-006):
19-0275 Reconstruction 0-019-021 12/17/19 DONE DONE DONE 08/16/19 07/31/19 01/22/19 12/04/18 2,7 1,200,550 1,200,550 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 07/31/19
22-0358 Reconstruction 0-019-022 11/20/22 DONE DONE DONE 08/26/22 08/26/22 06/01/22 05/17/22 9 100,000 100,000 SLC 0 0 0 Young And Wright Architectura 0 06/01/23 08/26/22
22-1535 Reconstruction 0-019-023 03/09/23 DONE DONE DONE 01/23/23 01/23/23 09/22/22 12/04/18 2,4,7,155,15,16 695,000 695,000 SLC 0 0 0 Young And Wright Architectura 0 / / 01/23/23
23-0245 Reconstruction 0-019-024 02/28/24 DONE DONE DONE 08/11/23 08/08/23 09/22/22 12/04/18 2,4,7,8,9,155,15,16 1,735,000 1,735,000 MSK 0 0 0 Young And Wright Architectura 0 / / 08/08/23
23-0504 Reconstruction 0-019-025 11/06/23 DONE DONE DONE 09/18/23 09/14/23 05/18/23 05/16/23 2,8,9,10 100,000 100,000 MSK 0 0 0 Young And Wright Architectura 0 / / 09/14/23
- Reconstruction 0-019-026 / / / / 03/21/24 / / 2,9,10,16 0 0 MSK 0 0 0 0 / / / /
XXTent #1 @ ESHS - Dismantled:
21-0464TQ Temporary Quarters 0-026-001 10/26/21 DONE DONE DONE 10/04/21 10/04/21 09/27/21 / / 02 - 16 0 0 SLC 0 0 0 0 10/21/21 10/04/21
XXTent #1 @ WSHS - dismantled:
21-0465TQ Temporary Quarters 0-027-001 10/26/21 DONE DONE DONE 10/04/21 10/04/21 09/27/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / 10/04/21
XXStorage Shed West Demolished:
19-1001 Reconstruction 2-020-001 12/17/19 DONE DONE DONE 12/16/19 12/16/19 11/07/19 12/04/18 2,7,8,16 15,000 0 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 12/16/19
XXPress Box West Sr. Demolished 2020:
19-1002 Reconstruction 7-013-001 12/17/19 DONE DONE DONE 12/16/19 12/16/19 11/07/19 12/04/18 2,7,9,13,16 10,000 0 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 12/16/19
XXPress Box East Sr. Demolition:
19-1003 Reconstruction 7-016-001 12/17/19 DONE DONE DONE 12/16/19 12/16/19 11/07/19 12/04/19 2,7,8,9,13,16 10,000 0 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 12/16/19
East Sr. Press Box:
19-0813 New Construction 7-023-001 12/17/19 DONE DONE DONE 11/18/19 11/15/19 11/07/19 12/04/18 02 - 16 243,000 0 SLC 0 0 0 Young And Wright Architectura 0 12/01/20 11/15/19
West Sr. Press Box:
19-0814 New Construction 7-024-001 12/17/19 DONE DONE DONE 11/18/19 11/15/19 11/07/19 12/04/18 02 - 16 203,500 0 SLC 0 0 0 Young And Wright Architectura 0 10/01/21 11/15/19
Concession Stand:
20-0018 New Construction 7-025-001 09/16/20 DONE DONE DONE 07/02/20 06/22/20 02/03/20 12/04/18 02 - 16 800,000 0 SLC 0 0 0 Young And Wright Architectura 0 04/24/23 06/22/20
XX Special Event Tent #2 @HS:
- XX New Construction 7-028-001 CANCELLED / / / / 10/06/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
District-Wide:
19-0939 Reconstruction 7-999-004 04/22/20 DONE DONE DONE 12/09/19 11/13/19 10/19/18 05/07/18 7,8,9,155,15,16 3,745,525 3,745,525 SLC 0 0 0 Young And Wright Architectura 0 08/01/23 11/13/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES ERIE I STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-91-00-00
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Harkness Occupational Center:
20-0044 Reconstruction 0-001-016 09/01/20 DONE DONE DONE 07/09/20 06/29/20 10/23/19 03/13/19 2,4,7,8,9,155,15,16 8,637,968 8,637,968 JSS 0 0 0 Young And Wright Architectura 0 08/11/22 06/29/20
20-0807 Reconstruction 0-001-017 02/19/21 DONE DONE DONE 11/12/20 11/05/20 04/07/20 09/09/20 2,9,155,15,16 150,103 150,103 JSS 0 0 0 Young And Wright Architectura 0 09/07/21 11/05/20
23-1545 Reconstruction 0-001-018 UNREVIEWED 02/23/24 02/22/24 09/06/23 10/11/23 2,155,15,16 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 02/22/24
Potter School Occ Center:
20-0808 Reconstruction 0-008-018 02/19/21 DONE DONE DONE 11/12/20 11/05/20 04/07/20 09/09/20 2,8,9,155,15,16 101,750 101,750 JSS 0 0 0 Young And Wright Architectura 0 08/25/22 11/05/20
21-1982 Reconstruction 0-008-019 10/04/22 DONE DONE DONE 06/15/22 06/15/22 08/19/21 03/13/19 2,4,7,8,9,155,15,16 5,462,230 5,462,230 JLB 0 0 0 Young And Wright Architectura 0 / / 06/15/22
23-1546 Reconstruction 0-008-020 UNREVIEWED 02/23/24 02/22/24 09/06/23 10/11/23 2,155,15,16 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 02/22/24
- Reconstruction 0-008-021 / / / / / / / / 2,4,155,15,16 0 0 WLC 0 0 0 0 / / / /
Kenton Career & Tech Center:
20-0104 Reconstruction 0-009-015 12/01/20 DONE DONE DONE 07/21/20 07/06/20 03/13/20 / / 2,9,155,15,16 300,000 300,000 JSS 0 0 0 Young And Wright Architectura 0 09/03/21 07/06/20
20-0809 Reconstruction 0-009-016 02/19/21 DONE DONE DONE 11/12/20 11/05/20 04/07/20 09/09/20 2,9 42,745 42,745 JSS 0 0 0 Young And Wright Architectura 0 09/03/21 11/05/20
21-0172 Reconstruction 0-009-017 12/03/21 DONE DONE DONE 08/16/21 08/12/21 07/17/20 03/13/19 2,4,7,8,9,155,15,16 7,906,180 7,906,180 JLB 0 0 0 Young And Wright Architectura 0 / / 08/12/21
23-1547 Reconstruction 0-009-018 UNREVIEWED 02/23/24 02/22/24 09/06/23 10/11/23 2,155,15,16 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 02/22/24
Storage Trailer 1:
20-1890 New Construction 2-026-001 09/13/21 DONE DONE DONE 06/16/21 06/14/21 05/13/21 06/09/21 02 - 16 7,860 0 JLB 0 0 0 Young And Wright Architectura 0 09/07/21 06/14/21
Storage Trailer 2:
20-1891 New Construction 2-027-001 09/13/21 DONE DONE DONE 06/16/21 06/14/21 05/13/21 06/09/21 02 - 16 7,860 0 JLB 0 0 0 Young And Wright Architectura 0 09/07/21 06/14/21
Storage Trailer 3:
20-1892 New Construction 2-028-001 09/13/21 DONE DONE DONE 06/16/21 06/14/21 05/13/21 06/09/21 02 - 16 7,860 0 JLB 0 0 0 Young And Wright Architectura 0 09/07/21 06/14/21
Storage Trailer 4:
- PR New Construction 2-029-001 / / / / 06/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0172 New Construction 2-029-001 03/13/23 DONE DONE DONE 07/27/22 07/26/22 06/15/22 06/09/22 02 - 16 10,000 0 WLC 0 0 0 Young And Wright Architectura 0 05/17/23 07/26/22
Storage Trailer 5:
- PR New Construction 2-030-001 / / / / 06/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0173 New Construction 2-030-001 03/13/23 DONE DONE DONE 07/27/22 07/26/22 06/15/22 06/09/22 02 - 16 10,000 0 WLC 0 0 0 Young And Wright Architectura 0 05/17/23 07/26/22
Storage Trailer 6:
- PR New Construction 2-031-001 / / / / 06/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0174 New Construction 2-031-001 03/13/23 DONE DONE DONE 07/27/22 07/26/22 06/15/22 06/09/22 02 - 16 10,000 0 WLC 0 0 0 Young And Wright Architectura 0 05/17/23 07/26/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES ERIE II-CHAUTAUQUA-CATTARAUGUS STATUS REPORT ON CAPITAL PROJECTS
District No.: 14-92-00-00
last updated on 04/23/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Hewes C Building:
19-1790 Reconstruction 0-001-011 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 19,200 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-001-012 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
Hewes A Building:
18-1451 Reconstruction 0-002-013 05/15/19 DONE DONE DONE 02/13/19 02/11/19 01/07/19 05/20/14 9,155,15,16 1,150,000 1,004,800 JLB 0 0 0 Clark Patterson Lee 0 12/07/20 02/11/19
18-2096 Reconstruction 0-002-014 08/16/19 DONE DONE DONE 06/11/19 05/29/19 03/29/19 05/20/14 2,9,16 234,000 234,000 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1791 Reconstruction 0-002-015 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 28,080 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
Hewes B Building:
19-1792 Reconstruction 0-003-013 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 10,100 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-003-014 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
Hewes D Building:
19-1793 Reconstruction 0-004-009 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 5,250 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-004-010 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
Hewes E Building:
18-1452 Reconstruction 0-005-013 05/16/19 DONE DONE DONE 02/13/19 02/11/19 01/07/19 05/20/14 9,155,15,16 1,050,000 1,050,000 JLB 0 0 0 Clark Patterson Lee 0 12/07/20 02/11/19
18-2097 Reconstruction 0-005-014 08/16/19 DONE DONE DONE 06/11/19 05/29/19 / / 05/20/14 2,9 162,000 162,000 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1794 Reconstruction 0-005-015 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 22,600 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-005-016 / / / / / / / / 16 0 0 WLC 0 0 0 0 / / / /
Willis H Carrier:
18-2098 Reconstruction 0-006-018 08/16/19 DONE DONE DONE 06/11/19 05/29/19 03/29/19 05/20/14 2,8,9,10,155,15 918,600 918,600 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1795 Reconstruction 0-006-019 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 20,000 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-006-020 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
23-1236 Reconstruction 0-006-021 UNREVIEWED 12/20/23 12/18/23 07/10/23 05/10/23 8 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 12/18/23
Ormsby Voc. Tech. Ctr.:
18-2099 Reconstruction 0-007-014 08/16/19 DONE DONE DONE 06/11/19 05/29/19 03/29/19 05/20/14 2,8,10,155,15,16 566,400 566,400 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1796 Reconstruction 0-007-015 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 34,900 0 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-007-016 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
23-1237 Reconstruction 0-007-017 UNREVIEWED 12/20/23 12/18/23 07/10/23 05/10/23 8 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 12/18/23
Hewes T Building:
19-1797 Reconstruction 0-011-010 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 16 18,900 18,900 JSS 0 0 0 Clark Patterson Lee 0 / / 04/23/20
- Reconstruction 0-011-011 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
LoGuidice A Building:
18-1453 Reconstruction 0-013-015 05/16/19 DONE DONE DONE 02/13/19 02/11/19 01/07/19 05/20/14 9,155,15,16 1,300,000 1,300,000 JLB 0 0 0 Clark Patterson Lee 0 12/07/20 02/11/19
18-2100 Reconstruction 0-013-016 08/16/19 DONE DONE DONE 06/11/19 05/29/19 03/29/19 05/20/14 9,15,16 596,400 596,400 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1798 Reconstruction 0-013-017 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 2,8,9,15,16 173,000 173,000 JSS 0 0 0 Clark Patterson Lee 0 05/26/22 04/23/20
- Reconstruction 0-013-018 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
LoGuidice B Building:
18-2101 Reconstruction 0-014-013 08/16/19 DONE DONE DONE 06/11/19 05/29/19 03/29/19 05/20/14 8,9,155,15,16 297,600 297,600 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1799 Reconstruction 0-014-014 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 13,155,15,16 395,000 395,000 JSS 0 0 0 Clark Patterson Lee 0 05/26/22 04/23/20
- Reconstruction 0-014-015 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
LoGuidice C Building:
19-1800 Reconstruction 0-015-011 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 155,15,16 150,000 150,000 JSS 0 0 0 Clark Patterson Lee 0 05/26/22 04/23/20
- Reconstruction 0-015-012 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
LoGuidice D Building:
19-1801 Reconstruction 0-016-008 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 155,15,16 35,000 35,000 JSS 0 0 0 Clark Patterson Lee 0 05/26/22 04/23/20
- Reconstruction 0-016-009 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
LoGuidice E Building:
18-2102 Reconstruction 0-017-016 08/16/19 DONE DONE DONE 06/11/19 05/29/19 03/29/19 05/20/14 8,9,15,16 188,400 188,400 JLB 0 0 0 Clark Patterson Lee 0 12/11/20 05/29/19
19-1802 Reconstruction 0-017-017 03/04/21 DONE DONE DONE 06/01/20 04/23/20 02/24/20 05/14/14 7,8,9,15,16 1,082,100 1,082,100 JSS 0 0 0 Clark Patterson Lee 0 05/26/22 04/23/20
21-0496 Reconstruction 0-017-018 01/31/22 DONE DONE DONE 10/08/21 10/07/21 04/07/21 05/12/21 2,4,7,8,9,10 760,494 760,494 JLB 0 0 0 Young And Wright Architectura 0 05/24/23 10/07/21
21-2001 Reconstruction 0-017-019 09/06/22 DONE DONE DONE 06/17/22 06/17/22 04/11/22 05/11/22 2,4,7,8 1,500,000 1,500,000 JLB 0 0 0 Young And Wright Architectura 0 / / 06/17/22
LoGuidice T Building:
- Reconstruction 0-018-012 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
23-1238 Reconstruction 0-018-013 UNREVIEWED 12/20/23 12/18/23 07/10/23 05/10/23 7,9 0 0 WLC 0 0 0 Young And Wright Architectura 0 / / 12/18/23
Storage @ La Guidice:
- Reconstruction 2-020-002 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
Loguidice Bus Garage-storage maint.:
- Reconstruction 2-021-001 / / / / 05/19/23 / / 16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED