Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 03/18/24 at 07:16:41




CROWN POINT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-02-03-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
21-0389   Reconstruction               0-001-018  09/29/21     DONE    DONE       DONE      09/22/21   09/21/21   08/24/21   08/24/21   2,7                      180,000       180,000  SLC             0           0           0 AES Northeast                           0      09/23/22                       09/21/21           
  -       Reconstruction               0-001-019                                              /  /       /  /     03/17/23     /  /     2,7,8,9,10,155,15,16           0             0  JLB             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-001-020                         CANCELLED            /  /       /  /     09/06/23     /  /     2,7,8,9,10,155,15,16           0             0  MSK             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




KEENE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-06-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
  -    PR Additions and Alterations    0-001-007                                              /  /       /  /     05/09/19     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
20-0426   Additions and Alterations    0-001-007  01/07/21     DONE    DONE       DONE      09/24/20   09/16/20   05/09/19   05/21/19   02 - 16                7,859,566     4,895,388  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         09/16/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MINERVA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-08-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Minerva Central School:
17-1487   Reconstruction               0-001-009  05/13/19     DONE    DONE       DONE      03/02/18   03/01/18   09/13/17   05/16/17   155,15,16                930,010       930,010  JLB             0           0           0 Mosaic Associates                 930,010      07/30/20                       03/01/18           
23-1272   Reconstruction               0-001-010                         UNREVIEWED         12/22/23   12/19/23   05/31/23   03/29/23   2,4,7,8,9,155,15,16            0             0  JJH             0           0           0 Mosaic Associates                       0        /  /                         12/19/23           
23-0157   Reconstruction               0-001-011  08/25/23     DONE    DONE       DONE      07/28/23   07/25/23   05/31/23   03/29/23   2                        100,000       100,000  JJH             0           0           0 Mosaic Associates                       0      12/01/23                       07/25/23           
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Conex Storage 1:
  -    PR New Construction             2-004-001                                              /  /       /  /     10/29/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
17-1488   Reconstruction               5-002-004  05/13/19     DONE    DONE       DONE      03/02/18   03/01/18   02/08/18   05/16/17   155,15,16                 11,636        11,636  JLB             0           0           0 Mosaic Associates                  11,636      07/30/20                       03/01/18           
23-1273   Reconstruction               5-002-005                         UNREVIEWED         12/22/23   12/19/23   05/31/23   03/29/23   2,155,15,16                    0             0  JJH             0           0           0 Mosaic Associates                       0        /  /                         12/19/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MORIAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-09-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -    PR Additions and Alterations    0-008-016                                              /  /       /  /     01/10/20     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
20-1035   Additions and Alterations    0-008-016  05/10/21     DONE    DONE       DONE      12/23/20   12/15/20   01/10/20   12/17/19   02 - 16               14,301,000    14,301,000  JLB             0           0           0 Synthesis Architects,L.L.P.             0      09/05/23                       12/15/20           
  -       Reconstruction               0-008-017                                              /  /       /  /     10/12/23     /  /     2                              0             0  JJH             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-018                                              /  /       /  /     10/17/23     /  /     2                              0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
20-1036   Additions and Alterations    5-007-006  05/10/21     DONE    DONE       DONE      12/23/20   12/15/20   01/10/20   12/17/19   02 - 16                  568,000             0  JLB             0           0           0 Synthesis Architects,L.L.P.             0        /  /                         12/15/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWCOMB CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-10-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -    PR Additions and Alterations    0-001-014                                              /  /       /  /     05/30/19     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
19-0984   Additions and Alterations    0-001-014  05/04/20     DONE    DONE       DONE      12/11/19   11/25/19   05/30/19   05/21/19   02 - 16                2,700,000     2,323,576  BMJ             0           0           0 Collins & Scoville Architects           0      09/30/22                       11/25/19           
  -       Reconstruction               0-001-015                                              /  /       /  /     11/04/21     /  /     15,16                          0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Graduation Tent:
20-1885TQ Temporary Quarters           8-005-001  06/15/21     DONE    DONE       DONE      06/16/21   06/15/21   06/07/21     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         06/15/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAKE PLACID CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-11-02-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
23-1510   Reconstruction               0-001-014                         UNREVIEWED         02/16/24   02/14/24   05/30/23   05/17/22   16                             0             0  WLC             0           0           0 Mosaic Associates                       0        /  /                         02/14/24           

          XXOval Support Building(Demolition):
20-0856DB Discovered Building          2-011-001  03/29/21     DONE    DONE       DONE      11/19/20     /  /     10/29/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Oval Support Building (New):
20-0857   New Construction             2-012-001  03/29/21     DONE    DONE       DONE      11/19/20   11/08/20   10/29/20   07/29/19   02 - 16               12,106,010             0  SLC             0           0           0 Cannon Design                           0        /  /                         11/08/20           

          Outting Club Storage Garage:
  -    PR New Construction             2-013-001                                              /  /       /  /     05/02/23     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHROON LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-14-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
20-0960   Reconstruction               0-001-008  06/08/20     DONE    DONE       DONE      12/11/20   12/03/20   04/07/20   03/26/20   2,4,16                   256,170       256,170  JLB             0           0           0 Bernier Carr Associates                 0      01/05/21                       12/03/20           
21-0386   Reconstruction               0-001-009  12/17/21     DONE    DONE       DONE      09/20/21   09/20/21   05/06/21   05/18/21   2,155                    368,000             0  JLB             0           0           0 Bernier Carr Associates                 0      09/15/22                       09/20/21           

          Outdoor Classroom (Pavilion):
  -    PR New Construction             0-004-001                                              /  /       /  /     08/09/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-1825XX New Construction             0-004-001  06/16/22               CANCELLED          05/18/22   03/22/22   08/09/21   04/28/22   02 - 16                   86,445             0  JLB             0           0           0 Bernier Carr Associates                 0        /  /                         03/22/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TICONDEROGA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-15-01-06
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
22-1568   Reconstruction               0-001-009  03/06/23     DONE    DONE       DONE      01/30/23   01/25/23   12/23/22   05/17/22   16                       100,000       100,000  JJH             0           0           0 Collins & Scoville Architects           0      06/26/23                       01/25/23           
23-0068   Reconstruction               0-001-010  11/27/23     DONE    DONE       DONE      07/12/23   07/12/23   06/09/23   05/16/23   8                        725,000       725,000  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         07/12/23           

          Elementary/Middle:
23-1213   Reconstruction               0-006-010  01/24/24     DONE    DONE       DONE      12/18/23   12/13/23   10/24/23   05/16/23   16                       100,000       100,000  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         12/13/23           

          Storage Dome:
19-1696DB Discovered Building          2-012-001  10/01/20     DONE    DONE       DONE      04/14/20   04/07/20   04/09/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         04/07/20           

          Multi-Purpose Field Storage:
20-0507DB Discovered Building          2-014-001  12/02/20     DONE    DONE       DONE      10/02/20   09/29/20   06/08/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         09/29/20           

          Bus Garage:
21-0965   Reconstruction               5-003-005  02/07/22     DONE    DONE       DONE      12/27/21   12/23/21   11/09/21   05/18/21   7,13                     100,000       100,000  JLB             0           0           0 Collins & Scoville Architects           0      10/30/22                       12/23/21           

          Snack Shack:
19-1697DB Discovered Building          7-013-001  10/01/20     DONE    DONE       DONE      04/14/20   04/07/20   04/09/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         04/07/20           

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WILLSBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-17-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 School:
21-0008XX Reconstruction               0-007-006  11/17/21               CANCELLED          07/06/21   07/02/21   05/24/21   05/18/21   16                       100,000       100,000  JLB             0           0           0 Tetra Tech Architects & Engin           0        /  /                         07/02/21           
22-0193   Reconstruction               0-007-007  12/21/22     DONE    DONE       DONE      07/29/22   07/29/22   06/21/22   05/17/22   9                        100,000       100,000  JJH             0           0           0 Tetra Tech Architects and Eng           0      04/25/23                       07/29/22           
22-0249   Reconstruction               0-007-008  11/29/22     DONE    DONE       DONE      08/15/22   08/08/22   06/21/22   05/17/22   16                       455,500       455,500  JLB             0           0           0 Tetra Tech Architects and Eng           0      10/03/23                       08/08/22           
23-0376   Reconstruction               0-007-009  10/06/23     DONE    DONE       DONE      09/05/23   09/01/23   06/02/23   05/16/23   16                       100,000       100,000  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/01/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOQUET VALLEY CSD @ ELIZ-LEWIS-WESTP STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-18-01-04
last updated on 03/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New K-12 Facility:
20-1516PR New Construction             0-014-001               DONE                         03/31/21     /  /     09/03/20     /  /     02 - 16                        0    29,336,241  SLC             0           0           0                                         0        /  /                           /  /             

          Lake View Campus - Large Storage:
20-1124DB Discovered Building          2-003-001                       ADDENDUM REQ'D       01/11/21   01/11/21   02/27/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/11/21           

          Lake View Campus - Small Storage:
20-1125DB Discovered Building          2-004-001                       ADDENDUM REQ'D       01/11/21   01/11/21   02/27/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/11/21           

          Mountain View Campus-Stg. Bldg. #1:
20-1126DB Discovered Building          2-005-001                       ADDENDUM REQ'D       01/11/21   01/11/21   02/27/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/11/21           

          Mountain View Campus-Stg. Bldg. #2:
20-1127DB Discovered Building          2-008-001                       ADDENDUM REQ'D       01/11/21   01/11/21   02/27/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/11/21           

          Mountain View Campus-Stg. Bldg. #3:
20-1128DB Discovered Building          2-009-001                       ADDENDUM REQ'D       01/11/21   01/11/21   02/27/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/11/21           

          Mountain View Campus-Youth Comm Stg:
20-1129DB Discovered Building          2-010-001                       ADDENDUM REQ'D       01/11/21   01/11/21   02/27/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         01/11/21           

          New Transportation Facility:
20-1517PR New Construction             5-015-001               DONE                         03/31/21     /  /     09/03/20     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTent 3 - cancelled:
  -    XX Reconstruction               7-014-001                         CANCELLED            /  /       /  /     10/15/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTent 1 - canceled:
20-0652XX Reconstruction               8-011-001                         CANCELLED          10/21/20   10/21/20   08/14/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         10/21/20           

          XXTent 2 - canceled:
20-0653XX Reconstruction               8-012-001                         CANCELLED          10/21/20   10/21/20   08/14/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         10/21/20           

          XXTent 3 - Canceled:
20-0654XX Reconstruction               8-013-001                         CANCELLED          10/21/20   10/21/20   08/14/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         10/21/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED