Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 08/26/14 at 16:10:36




ELIZABETHTOWN-LEWIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-03-01-04
last updated on 08/26/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
13-1355   Reconstruction               0-001-005  04/22/14     DONE    DONE       DONE      03/17/14   03/14/14   02/01/13   03/05/13   2,9,155,15,16            651,293             0  DDJ             0           0     114,083 AES Northeast                           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-1491   Reconstruction               0-001-006                         UNREVIEWED         04/28/14   04/28/14   03/24/14   03/05/13                                  0    13,582,650  DDJ             0           0           0 AES Northeast                           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MORIAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-09-01-04
last updated on 08/26/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
12-0745   Reconstruction               0-008-011  05/15/13     DONE    DONE       DONE      01/31/13   01/30/13   12/11/12   03/03/10   2,155,15,16              607,338       607,338  JMB             0           0      20,552 Synthesis Architects,L.L.P.             0        /  /                           /  /             
10-0697   Reconstruction               0-008-014  07/14/11     DONE    DONE       DONE      12/31/10   12/24/10   09/07/10   03/03/10   2,4,8,9,10,155,15,16   1,334,342     1,334,342  HCM             0           0      70,000 Synthesis Architects,L.L.P.             0      11/01/12                       06/05/14           
10-0906   Reconstruction               0-008-015  03/22/11     DONE    DONE       DONE      02/24/11   02/24/11   11/09/10   03/03/10   16                       169,097       169,097  HCM             0           0           0 Synthesis Architects,L.L.P.             0      07/05/11                       05/24/13           

          Bus Garage:
12-0746   Reconstruction               5-007-005  05/15/13     DONE    DONE       DONE      01/31/13   01/30/13   12/11/12   03/03/10   2,7,155,16               278,224             0  JMB             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWCOMB CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-10-01-04
last updated on 08/26/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
12-0642   Reconstruction               0-001-013  05/10/13     DONE    DONE       DONE      01/09/13   01/08/13   04/15/11   08/21/12   2,4,155,15             1,929,330             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAKE PLACID CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-11-02-04
last updated on 08/26/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
11-0094   Reconstruction               0-001-010  08/12/11     DONE    DONE       DONE      08/12/11   08/09/11   05/19/11   05/17/11   4,155                    176,000       176,000  JOD             0           0           0 Mosaic Associates                       0      07/24/12                       09/07/12           
12-1134   Reconstruction               0-001-011                       ADDENDUM REQ'D       04/26/13   04/26/13   12/12/12   03/19/13   2,155,15,16                    0    13,738,567  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Lake Placid Elementary:
12-1135   Reconstruction               0-007-008                       ADDENDUM REQ'D       04/26/13   04/26/13   12/12/12   03/19/13   4,8,9,155,15,16                0     6,470,982  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Annex Building - Jr./Sr. High School:
12-1136   Reconstruction               1-008-004                       ADDENDUM REQ'D       04/26/13   04/26/13   12/12/12   03/19/13   8,155,15,16                    0             0  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WESTPORT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-16-01-04
last updated on 08/26/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
12-0189   Reconstruction               0-001-006  01/16/13     DONE    DONE       DONE      09/18/12   09/17/12   07/13/09   05/15/12   2,8,9,13,16              455,200       455,200  JOD             0           0      81,396 AES Northeast                           0      08/27/13                       09/19/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Utility Garage:
11-0073   New Construction             3-004-001  09/08/11     DONE    DONE       DONE      07/28/11   07/28/11   05/26/11   07/17/11   02 - 16                   50,000             0  JOD             0           0           0 AES Northeast                           0      12/09/11                       06/28/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WILLSBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 15-17-01-04
last updated on 08/26/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Storage Shed:
09-0706DB Discovered Building          2-009-001                       ADDENDUM REQ'D       01/07/10   01/07/10   09/02/03     /  /                                    0             0  MAC             0           0           0                                         0        /  /                           /  /             

          Barn:
09-0707DB Discovered Building          2-010-001                       ADDENDUM REQ'D       01/07/10   01/07/10   09/02/03     /  /                                    0             0  MAC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED