Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/23/13 at 14:42:25




TUPPER LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-01-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior/Senior High School:
08-1090   Reconstruction               0-001-006  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   05/10/07   03/04/08   2,8,155,15,16          1,061,720     1,061,720  HCM             0           0     173,186 SEI Design Group                        0        /  /             /  /        
11-0395   Reconstruction               0-001-007  04/04/12     DONE    DONE       DONE      11/17/11   11/10/11   05/27/11   11/08/11   155,16                   636,325             0  HCM             0           0           0 Turner Engineering                175,825        /  /             /  /        

          L.P. Quinn Elementary School:
08-1091   Reconstruction               0-006-006  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   11/01/06   03/04/08   155,15,16                738,273       738,273  HCM             0           0      98,365 SEI Design Group                        0        /  /             /  /        
11-0396   Reconstruction               0-006-007  04/04/12     DONE    DONE       DONE      11/17/11   11/10/11   05/27/11   11/08/11   155,16                   777,014             0  HCM             0           0           0 Turner Engineering                345,514        /  /             /  /        

          Bus Garage:
08-1092   Reconstruction               5-002-004  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   11/01/06   03/04/08   15,16                    191,754       191,754  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        
11-0397   Reconstruction               5-002-005  04/04/12     DONE    DONE       DONE      11/17/11   11/10/11   05/27/11   11/08/11   155,16                   136,320             0  HCM             0           0           0 Turner Engineering                 71,321        /  /             /  /        

          Goff Nelson Memorial Library:
08-1095   Reconstruction               6-004-003  06/08/09     DONE    DONE       DONE      01/21/09   01/09/09   12/16/08   03/04/08   4,7,155,16               265,755             0  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        

          Gym @ Civic Center:
08-1093   Reconstruction               8-007-002  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   11/01/06   03/04/08   16                        26,644             0  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        
11-0398   Reconstruction               8-007-003  04/04/12     DONE    DONE       DONE      11/17/11   11/10/11   05/27/11   11/08/11   155,16                    70,805             0  HCM             0           0           0 Turner Engineering                 27,805        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHATEAUGAY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-08-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-0806   Additions and Alterations    0-001-009  06/17/11     DONE    DONE       DONE      02/07/11   01/26/11   09/01/09   11/17/09   02 - 16                6,709,000     6,671,417  HCM             0           0     406,666 Bernier Carr Associates                 0        /  /             /  /        
09-1359   Reconstruction               0-001-010  05/24/10     DONE    DONE       DONE      04/23/10   04/09/10   04/19/10   11/07/09   7                      1,731,000     1,731,000  HCM             0           0      88,281                                         0        /  /           12/18/12      

          Bus Garage:
10-0807   Reconstruction               5-002-006  06/17/11     DONE    DONE       DONE      02/07/11   01/26/11   08/27/10   11/17/09   2,15                      60,000        60,000  HCM             0           0           0 Bernier Carr Associates                 0        /  /             /  /        

          New Bus Garage with Maint.:
  -       Reconstruction               5-003-002                                              /  /       /  /     05/03/13     /  /     2,4,9,14,15,16                 0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SALMON RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-12-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg. Campus:
08-0560   Additions and Alterations    0-001-016  08/03/09     DONE    DONE       DONE      10/20/08   10/16/08   12/14/07   02/28/08   02 - 16               47,372,554    47,352,939  DDJ             0           0     453,648 Collins & Scoville Architects           0        /  /             /  /        
11-0140   Reconstruction               0-001-018  08/19/11     DONE    DONE       DONE      08/25/11   08/18/11   08/24/11   08/24/11   2                              0             0  DDJ             0           0           0 Spectra Engineering, Architec           0        /  /             /  /        
  -       Reconstruction               0-001-019                                              /  /       /  /     12/07/12     /  /     2,4,7,8,9,10,14,155,           0             0  DDJ             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-020                                              /  /       /  /     03/06/13     /  /     2,15                           0    37,590,867  DDJ             0           0           0                                         0        /  /             /  /        

          Sewage Treatment Plant(frmrly 7-009):
11-1342   Reconstruction               0-009-002  06/26/12     DONE    DONE       DONE      05/24/12   05/22/12   03/20/12   05/17/11   2                        100,000       100,000  DDJ             0           0           0 Bernier Carr Associates                 0        /  /           03/22/13      
  -       Reconstruction               0-009-003                                              /  /       /  /     12/18/12     /  /     2                              0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Maintenance Building:
  -    DB Discovered Building          3-012-001                                              /  /       /  /     07/15/08     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Bus Garage:
  -    PR Additions and Alterations    5-008-006                                              /  /       /  /     12/07/12     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SARANAC LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-14-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Petrova Avenue School:
09-0397   Reconstruction               0-002-015  01/19/10     DONE    DONE       DONE      11/06/09   11/04/09     /  /     05/20/08   8,10                   1,000,000     1,000,000  JOD             0           0           0 348 Lake Street                         0        /  /             /  /        
10-0950   Reconstruction               0-002-016  05/26/11     DONE    DONE       DONE      03/07/11   02/25/11     /  /     05/17/11   2,155,15,16              494,303       494,303  JOD             0           0           0 Bernier Carr Associates                 0        /  /             /  /        
  -       Reconstruction               0-002-017                                              /  /       /  /     01/06/11     /  /     2,155,15,16                    0             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MALONE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-15-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Malone Junior High School:
09-0845   Additions and Alterations    0-001-010  06/11/10     DONE    DONE       DONE      02/03/10   02/01/10   02/28/08   04/07/09   02 - 16               16,072,045    13,907,335  JOD             0           0   1,313,556 Collins & Scoville Architects           0        /  /           12/20/12      
  -       Reconstruction               0-001-011                                              /  /       /  /     01/19/11     /  /     2,9                            0             0  JOD             0           0           0                                         0        /  /             /  /        
11-0809   Reconstruction               0-001-012  06/19/12     DONE    DONE       DONE      02/14/12   02/13/12   02/10/11   04/07/09   2,9,10,16              1,201,627     1,201,627  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      

          St.Joseph's Elem. School:
09-0846   Reconstruction               0-011-005  06/11/10     DONE    DONE       DONE      02/03/10   02/01/10   09/30/09   04/07/09   2,4,7,8,9,10,155,15,   4,131,501     3,658,708  JOD             0           0     352,139 Collins & Scoville Architects           0        /  /           12/20/12      
11-0810   Reconstruction               0-011-006  06/19/12     DONE    DONE       DONE      02/14/12   02/13/12   02/10/11   04/07/09   2,4,9,10,16              718,277       718,277  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      

          Flanders Elementary School:
09-0847   Reconstruction               0-017-006  06/11/10     DONE    DONE       DONE      02/03/10   02/01/10   07/28/09   04/07/09   2,7,8,9,155,15,16      3,347,032     3,347,032  JOD             0           0     131,993 Collins & Scoville Architects           0        /  /           12/20/12      
11-0811   Reconstruction               0-017-007  06/18/12     DONE    DONE       DONE      02/14/12   02/13/12   02/10/11   04/07/09   2,4,9,10,13,16           866,023       866,023  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      
12-0989   Reconstruction               0-017-008  04/29/13     DONE    DONE       DONE      03/19/13   03/19/13   01/23/13   01/22/13   10,155,15,16             120,000       120,000  JOB             0           0           0 Tisdel Associates consulting            0        /  /             /  /        

          Davis Elementary School Pre - K - 2:
09-0848   Reconstruction               0-018-003  06/11/10     DONE    DONE       DONE      02/03/10   02/01/10   02/28/08   04/07/09   2,4,7,8,9,10,14,155,     144,574       144,574  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      
10-0917   Reconstruction               0-018-004  05/10/11     DONE    DONE       DONE      02/28/11   02/24/11   04/26/10   04/07/09   2,8,9,16               1,400,000     1,400,000  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      
11-0812   Reconstruction               0-018-005  06/19/12     DONE    DONE       DONE      02/14/12   02/13/12   02/14/12   04/07/09   9,16                     329,635       329,635  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      

          Franklin Acad:HS 9-12:
08-0098   Reconstruction               0-019-012  02/23/09     DONE    DONE       DONE      07/25/08   07/24/08   05/21/07   05/20/08   4,155,15,16              100,000       100,000  JOD             0           0           0 Tisdel Associates consulting            0        /  /             /  /        
09-0849   Reconstruction               0-019-013  06/11/10     DONE    DONE       DONE      02/03/10   02/01/10   02/28/08   04/07/09   2,155,15,16              680,300       680,300  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      
11-0813   Reconstruction               0-019-014  06/18/12     DONE    DONE       DONE      02/14/12   02/13/12   01/31/12   04/07/09   2,9,15,16                142,318       142,318  JOD             0           0           0 Collins & Scoville Architects           0        /  /           10/20/12      
  -       Reconstruction               0-019-015                                              /  /       /  /     02/14/12     /  /     2,9,15,16                      0             0  JOD             0           0           0                                         0        /  /             /  /        

          Storage Building #1 @ St. Joseph's:
  -    DB Discovered Building          2-030-001                                              /  /       /  /     05/13/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Storage Shed #2 @ St. Joseph's:
  -    DB Discovered Building          2-031-001                                              /  /       /  /     05/13/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Storage Building No. 3 @ St Joseph's:
  -    DB Discovered Building          2-032-001                                              /  /       /  /     05/12/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Storage Building No.1 @ Flanders:
  -    DB Discovered Building          2-033-001                                              /  /       /  /     05/12/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Bus Garage:
09-0850   Reconstruction               5-006-005  06/11/10     DONE    DONE       DONE      02/03/10   02/01/10   05/18/06   04/07/09   15,16                     85,695        85,695  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      
11-1289   Reconstruction               5-006-006  08/03/12     DONE    DONE       DONE      05/10/12   05/09/12   03/28/12   05/17/11   2,13,16                  189,400       189,400  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      

          Media Tower:
  -    PR New Construction             7-014-001                                              /  /       /  /     03/25/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
11-0814   New Construction             7-014-001  06/19/12     DONE    DONE       DONE      02/14/12   02/13/12   03/25/11   04/07/09   02 - 16                  239,270             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /           12/20/12      

          :
  -       Reconstruction               7-999-001                                              /  /       /  /     04/14/11     /  /     13,16                          0             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRUSHTON MOIRA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-16-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School Building:
09-1294   Reconstruction               0-001-009  08/27/10     DONE    DONE       DONE      04/14/10   04/07/10   03/02/09   11/17/09   2,4,7,9,155,15,16      1,381,908     1,381,908  DDJ             0           0      27,638 SEI Design Group                        0        /  /             /  /        
10-0312   Additions and Alterations    0-001-010  02/25/11     DONE    DONE       DONE      10/04/10   09/22/10   08/26/10   11/17/09   02 - 16                4,963,099     4,655,472  DDJ             0           0     395,830 SEI Design Group                        0        /  /             /  /        

          Bus Garage:
09-1295   Additions and Alterations    5-003-009  08/27/10     DONE    DONE       DONE      04/14/10   04/07/10   03/02/09   11/17/09   02 - 16                  125,000       125,000  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        
09-0396   Reconstruction               5-003-010  03/24/09     DONE    DONE       DONE      11/06/09   11/04/09   03/10/09   03/09/09   10,13                     67,967        67,967  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        
10-0313   Additions and Alterations    5-003-011  02/25/11     DONE    DONE       DONE      10/05/10   09/20/10   08/26/10   11/17/09   02 - 16                1,989,631     1,989,631  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES FRANKLIN-ESSEX-HAMILTON STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-90-00-00
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Franklin Educ. Ctr.:
11-0831   Reconstruction               0-002-008  05/22/12     DONE    DONE       DONE      02/22/12   02/21/12   11/21/11   04/16/11   2,10,155                 515,000       515,000  JOD             0           0           0 Beardsley Design Associates             0        /  /           04/25/13      

          Adirondack Educ. Ctr.:
08-1168   Reconstruction               0-004-009  03/18/09     DONE    DONE       DONE      02/06/09   01/30/09   12/15/08   08/28/08   9,10,155,15,16           478,500       478,500  JOD             0           0           0 348 Lake Street                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED