FRANKLIN COUNTY

FRANKLIN COUNTY

TUPPER LAKE 160101
CHATEAUGAY 160801
SALMON RIVER 161201
SARANAC LAKE 161401
MALONE 161501
BRUSHTON MOIRA 161601
ST REGIS FALLS 161801
FRANKLIN BOCES 169000
















Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/21/18 at 09:15:52




TUPPER LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-01-01-06
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior/Senior High School:
14-1348   Reconstruction               0-001-008  05/14/15     DONE    DONE       DONE      04/02/15   03/20/15   01/20/15   11/18/14   2,4,7,8,9,155,15,16      912,000       912,000  JMB             0           0           0 SEI Design Group                        0      09/15/15                       12/22/15           
15-0485   Reconstruction               0-001-009  09/12/16     DONE    DONE       DONE      09/23/15   09/16/15   01/20/15   11/18/14   2,7                    2,177,640     2,177,640  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          L.P. Quinn Elementary School:
14-1349   Reconstruction               0-006-008  05/14/15     DONE    DONE       DONE      04/02/15   03/20/15   12/17/14   11/18/14   2,7                       50,000        50,000  JMB             0           0           0 SEI Design Group                        0      12/22/15                       09/15/15           
15-0486   Reconstruction               0-006-009  09/12/16     DONE    DONE       DONE      09/23/15   09/16/15   01/20/15   11/18/14   2,4,7,8,9,155,15,16    2,866,980     2,866,980  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0944   Reconstruction               0-006-010  02/23/18     DONE    DONE       DONE      12/12/17   11/30/17   10/18/17   05/16/17   155,16                   100,000             0  SLC             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Bus Garage:
13-0803   Reconstruction               5-002-006  12/16/13     DONE    DONE       DONE      12/02/13   11/26/13   09/16/13   10/07/13   4,13                     100,000       100,000  JMB             0           0           0 SEI Design Group                        0      04/08/14                       04/23/14           
15-0487   Reconstruction               5-002-007  09/12/16     DONE    DONE       DONE      09/23/15   09/16/15   01/20/15   11/18/14   2,8,9,15,16              272,160       272,160  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Goff-Nelson Memorial Library:
  -       Reconstruction               6-004-004                                              /  /       /  /     11/05/13     /  /     9,15,16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               6-004-005                                              /  /       /  /     09/16/15     /  /     8,9,15,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Toilet/Storage Building:
15-0488   New Construction             7-009-001  09/12/16     DONE    DONE       DONE      09/23/15   09/16/15   07/24/15   11/18/14   02 - 16                  203,160             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          District-Wide:
14-1353   Reconstruction               7-999-002  08/25/15     DONE    DONE       DONE      04/02/15   04/02/15   03/02/15   11/18/14   10,16                    759,360       759,360  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               7-999-003                                              /  /       /  /     05/31/16     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1836SB Reconstruction               7-999-003               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Gym @ Civic Center:
15-0489   Reconstruction               8-007-004  09/12/16     DONE    DONE       DONE      09/23/15   09/16/15   01/20/15   11/18/14   2,7,8,9,14,155,15,16     706,680             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHATEAUGAY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-08-01-04
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
17-0656   Reconstruction               0-001-011                       ADDENDUM REQ'D       10/26/17   10/06/17   06/25/13   02/28/17   2,4,7,8,9,155,15,16            0    10,570,880  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Annex (fmly Bus Garage):
17-0657   Reconstruction               0-002-002                       ADDENDUM REQ'D       10/31/17   10/24/17   12/28/17   02/28/17   2,4,7,8,9,10,155,15,           0     1,013,808  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          XXBus Garage (see 0-002 Annex):
  -       Reconstruction               5-002-007                         UNREVIEWED         10/26/17   10/24/17   06/25/13   02/28/17   2,4,7,8,9,155,15,16            0             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          New Bus Garage with Maint.:
12-1324   Reconstruction               5-003-002  06/28/13     DONE    DONE       DONE      06/26/13   06/26/13   05/03/13   03/25/13   2,4,9,14,15,16           200,000       200,000  JMB             0           0           0                                         0        /  /                           /  /             
17-0658   Reconstruction               5-003-003                       ADDENDUM REQ'D       10/26/17   10/24/17   06/25/13   02/28/17   2,4,7,8,9,155,15,16            0             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          District-Wide:
16-1624SB Reconstruction               7-999-001                         UNREVIEWED         11/29/17   11/29/17   04/04/17   11/04/14   2,4,7,8,9,13,155,15,           0             0  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
17-0882   Reconstruction               7-999-001                         UNREVIEWED         11/30/17   11/29/17   04/04/17   11/04/14   2,4,7,8,9,13,155,15,           0             0  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SALMON RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-12-01-04
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg. Campus:
14-0129   Reconstruction               0-001-019  04/09/15     DONE    DONE       DONE      08/12/14   08/12/14   12/07/12   10/22/13   2,4,7,8,9,10,14,155,  35,343,000    35,343,000  DDJ             0           0     704,660 March Associates                        0      12/23/16           YES         01/05/16           
13-0469   Reconstruction               0-001-020  03/24/13     DONE    DONE       DONE      10/07/13   10/04/13   03/06/13   03/25/13   2,15                   1,400,000     1,400,000  DDJ             0           0           0 March Associates                        0      11/24/14                       12/15/14           
14-0803   Reconstruction               0-001-021  04/07/15     DONE    DONE       DONE      12/19/14   12/18/14   10/23/14   12/01/14   2,4,8,9,10,155,16        100,000       100,000  DDJ             0           0           0 March Associates                        0      12/30/15                       05/23/16           

          Sewage Treatment Plant(frmrly 7-009):
12-1242   Reconstruction               0-009-003  06/07/13     DONE    DONE       DONE      06/04/13   06/04/13   12/18/12   05/17/11   2                         99,999        99,999  DDJ             0           0           0 Bernier Carr Associates                 0      10/10/13                       03/28/14           

          Tire Storage Building:
14-0130   New Construction             2-017-001  04/09/15     DONE    DONE       DONE      08/12/14   08/12/14   07/03/14   10/22/13   02 - 16                   25,000             0  DDJ             0           0           0 March Associates                        0        /  /                           /  /             

          Garage @ Mohawk School:
13-0472DB Discovered Building          3-013-001                       ADDENDUM REQ'D       10/08/13   10/04/13   10/08/13     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
14-0131   Additions and Alterations    5-008-006  04/09/15     DONE    DONE       DONE      08/12/14   08/12/14   12/07/12   10/22/13   02 - 16                1,670,000     1,670,000  DDJ             0           0           0 March Associates                        0        /  /                           /  /             

          Booster Pump Station:
14-0132   New Construction             7-014-001  04/09/15     DONE    DONE       DONE      08/12/14   08/12/14   06/03/14   10/22/13   02 - 16                        0             0  DDJ             0           0           0 March Associates                        0        /  /                           /  /             

          Dugout #1:
14-0133   New Construction             7-015-001  04/09/15     DONE    DONE       DONE      08/12/14   08/12/14   06/26/14   10/22/13   02 - 16                   16,000             0  DDJ             0           0           0 March Associates                        0        /  /                           /  /             

          Dugout #2:
14-0134   New Construction             7-016-001  04/09/15     DONE    DONE       DONE      08/12/14   08/12/14   06/26/14   10/22/13   02 - 16                   16,000             0  DDJ             0           0           0 March Associates                        0        /  /                           /  /             

          Press Box:
  -       New Construction             7-018-001                       DONE                   /  /       /  /     10/07/14     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SARANAC LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-14-01-06
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Petrova Avenue School:
  -       Reconstruction               0-002-018                                              /  /       /  /     10/14/15     /  /     155                            0    14,311,890  MFS             0           0           0                                         0        /  /                           /  /             
16-1174SB Reconstruction               0-002-019               DONE                           /  /       /  /     01/13/17     /  /     16                             0    14,311,890  SLC             0           0           0                                         0        /  /                           /  /             
16-1430   Reconstruction               0-002-019  10/05/17     DONE    DONE       DONE      02/23/17   02/23/17   01/13/17   01/04/17   16                       330,729       330,729  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1641   Reconstruction               0-002-020  05/17/17     DONE    DONE       DONE      04/07/17   04/07/17   02/21/17   01/10/17   2,7                    1,048,400     1,048,400  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
17-0190   Reconstruction               0-002-021  02/01/18     DONE    DONE       DONE      08/09/17   08/09/17   04/05/17   01/10/17   2,4,8,9,10,155,15,16   3,816,391             0  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
17-0056   Reconstruction               0-002-022  05/25/17     DONE    DONE       DONE      07/13/17   07/13/17   05/19/17   08/16/17   2,9,16                 1,967,000             0  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          XXLake Colby Schl (now day care us:
17-0191   Reconstruction               0-006-006  01/31/18     DONE    DONE       DONE      08/09/17   08/09/17   04/05/17   01/10/17   2,4,9,15,16              236,988       236,988  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Bloomingdale Elementary:
17-0192   Reconstruction               0-013-008  01/31/18     DONE    DONE       DONE      08/09/17   08/09/17   04/06/17   01/10/17   2,7,8,9,10,155,15,16     516,027             0  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Middle/High School:
16-1175SB Reconstruction               0-014-010               DONE                           /  /       /  /       /  /       /  /     16                             0    15,185,999  SLC             0           0           0                                         0        /  /                           /  /             
16-1431   Reconstruction               0-014-010  10/05/17     DONE    DONE       DONE      02/23/17   02/23/17   01/13/17   01/04/17   16                       376,871       376,871  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1642   Reconstruction               0-014-011  05/13/17     DONE    DONE       DONE      04/07/17   04/07/17   02/21/17   01/10/17   2,7,8,9,10,13            743,395       743,395  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
17-0193   Reconstruction               0-014-012  01/31/18     DONE    DONE       DONE      08/09/17   08/09/17   04/05/17   01/10/17   2,4,7,8,9,10,155,15,   6,993,678             0  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Bus Garage:
17-0194   Reconstruction               5-001-004  01/31/18     DONE    DONE       DONE      08/09/17   08/09/17   04/06/17   01/10/17   2,8,9,15,16               44,803             0  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MALONE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-15-01-06
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Malone Junior High School:
14-0812   Reconstruction               0-001-013  08/11/15     DONE    DONE       DONE      12/23/14   12/22/14   12/03/14   05/20/14   4                        112,000       112,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-014                                              /  /       /  /     02/20/18     /  /     14                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Harrison Gymnasium:
14-0813   Reconstruction               0-002-001  08/11/15     DONE    DONE       DONE      12/23/14   12/22/14   12/03/14   05/20/14   2,4,8,9,155,15,16        547,445       547,445  JMB             0           0           0 Collins & Scoville Architects           0      05/02/17                       06/14/17           

          Flanders Elementary School:
14-0814   Reconstruction               0-017-009  08/11/15     DONE    DONE       DONE      12/23/14   12/22/14   12/03/14   05/20/14   4                         56,000        56,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-1455   Reconstruction               0-017-010  12/22/17     DONE    DONE       DONE      03/02/17   03/02/17   12/20/16   05/19/15   2,8,9,13,155,16          100,000             0  BMJ             0           0           0 Tim McCarthy Architect P.C.             0        /  /                           /  /             

          Davis Elementary School Pre-K-2:
  -       Additions and Alterations    0-018-006                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-018-006                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1440SB Additions and Alterations    0-018-006               DONE                           /  /       /  /     03/16/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Franklin Acad:HS 9-12:
13-0894   Reconstruction               0-019-016  02/27/14     DONE    DONE       DONE      12/13/13   12/12/13   10/21/13   05/21/13   14,155,15,16              98,500        98,500  JMB             0           0           0 Tisdel Associates consulting            0      06/01/16                       09/19/16           
14-0815   Reconstruction               0-019-017  08/11/15     DONE    DONE       DONE      12/23/14   12/22/14   12/03/14   05/20/14   2,16                   3,192,714     3,192,714  JMB             0           0           0 Collins & Scoville Architects           0      05/02/17                       06/14/17           

          Bus Garage:
14-0816   Additions and Alterations    5-006-007  08/11/15     DONE    DONE       DONE      12/23/14   12/22/14   12/03/14   05/20/14   02 - 16               11,818,607    11,818,607  JMB             0           0           0 Collins & Scoville Architects           0      05/02/17                       06/14/17           

          Wead Library:
17-1829   Reconstruction               6-020-001                         UNREVIEWED         05/07/18   05/04/18   01/04/16   04/16/18   2,4,9,14,155,15,16             0             0  JMB             0           0           0 Beardsley Design Associates             0        /  /                           /  /             

          District-Wide:
14-0205   Reconstruction               7-999-002  05/08/15     DONE    DONE       DONE      08/21/14   08/18/14   10/21/13   05/20/14   2,155,15,16              234,000       234,000  JMB             0           0           0 M/E ENGINEERIN, P.C                     0      05/31/17                       06/14/17           
15-1441SB Reconstruction               7-999-003               DONE                           /  /       /  /     03/16/16     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-0697   Reconstruction               7-999-003  04/06/17     DONE    DONE       DONE      11/02/16   11/02/16     /  /     11/04/14   13,16                    397,926             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRUSHTON-MOIRA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-16-01-04
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School Building:
  -       Reconstruction               0-001-011                                              /  /       /  /     09/14/16     /  /     4,8,9,155,15,16                0    33,209,310  BMJ             0           0           0                                         0        /  /                           /  /             
16-0422SB Reconstruction               0-001-011               DONE                           /  /       /  /     09/14/16     /  /     4,8,9,155,15,16                0    33,209,310  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-012                                              /  /       /  /     09/14/16     /  /     13,16                          0    33,209,310  BMJ             0           0           0                                         0        /  /                           /  /             
16-0423SB Reconstruction               0-001-012               DONE                           /  /       /  /     09/14/16     /  /     13,16                          0    33,209,310  BMJ             0           0           0                                         0        /  /                           /  /             
17-1038PR Additions and Alterations    0-001-013                                            12/21/17     /  /     08/31/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
17-1250   Additions and Alterations    0-001-013               STARTED STARTED    UNREVIEWED01/25/18   01/23/18   08/31/17   03/16/17   02 - 16                        0             0  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0897   Reconstruction               0-001-014  04/25/18     DONE    DONE       DONE      12/04/17   11/30/17   08/31/17   03/16/17   7,9,155,15,16          1,909,749     1,909,749  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     03/01/18     /  /     2,15,16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Storage Building #1:
14-1677   New Construction             2-007-001  09/16/15     DONE    DONE       DONE      06/17/15   06/12/15   12/02/14   05/19/15   02 - 16                    5,000             0  DDJ             0           0           0 SEI Design Group                        0      12/15/16                       12/11/17           

          Storage Building #2:
14-1678   New Construction             2-008-001  09/16/15     DONE    DONE       DONE      06/17/15   06/12/15   12/02/14   05/19/15   02 - 16                    5,000             0  DDJ             0           0           0 SEI Design Group                        0      12/15/16                       12/11/17           

          Storage Building #3:
14-1679   New Construction             2-009-001  09/16/15     DONE    DONE       DONE      06/17/15   06/12/15   12/02/14   05/19/15   02 - 16                    5,000             0  DDJ             0           0           0 SEI Design Group                        0      12/15/16                       12/11/17           

          Storage Building #4:
14-1680   New Construction             2-010-001  09/16/15     DONE    DONE       DONE      06/17/15   06/12/15   12/02/14   05/19/15   02 - 16                    5,000             0  DDJ             0           0           0 SEI Design Group                        0      12/15/16                       12/11/17           

          Storage Shed 1:
  -       New Construction             2-012-001                                              /  /       /  /     10/03/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Storage Shed 2:
  -       New Construction             2-013-001                                              /  /       /  /     10/03/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
17-1251   Reconstruction               5-003-012               STARTED STARTED    UNREVIEWED01/25/18   01/23/18   08/31/17   03/16/17   15                             0             0  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0898   Reconstruction               5-003-013  04/25/18     DONE    DONE       DONE      12/04/17   11/30/17   08/31/17   09/16/17   155,15,16                 28,413        28,413  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ST. REGIS FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-18-01-04
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New PK-12:
16-1739PR Additions and Alterations    0-002-002                                            04/27/17     /  /     07/28/16     /  /     02 - 16                        0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0160   Additions and Alterations    0-002-002               DONE    ADD. REQ'D DONE      08/04/17   08/03/17   07/28/16   12/06/16   02 - 16                        0    11,867,263  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               0-002-003               DONE                           /  /       /  /       /  /       /  /     16                             0    15,683,368  AAA             0           0           0                                         0        /  /                           /  /             
16-0164SB Reconstruction               0-002-003               DONE                           /  /       /  /     07/28/16     /  /     16                             0    15,683,368  AAA             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-004               DONE                           /  /       /  /     08/04/16     /  /     16                             0    15,683,368  AAA             0           0           0                                         0        /  /                           /  /             
16-0210SB Reconstruction               0-002-004               STARTED                        /  /       /  /     08/04/16     /  /     16                             0    15,683,368  MTM             0           0           0                                         0        /  /                           /  /             
17-0846   Reconstruction               0-002-005  02/07/18     DONE    DONE       DONE      11/27/17   11/22/17   11/07/17   12/06/16   2,16                      40,476             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES FRANKLIN-ESSEX-HAMILTON STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-90-00-00
last updated on 05/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Franklin Educ. Ctr.:
14-0693   Reconstruction               0-002-009  09/21/15     DONE    DONE       DONE      12/01/14   11/28/14   08/27/14   08/21/14   10,155,15,16              98,200        98,200  MFS             0           0           0 Tisdel Associates consulting            0      08/31/16                       06/08/17           
15-1997PR Additions and Alterations    0-002-010                         UNREVIEWED         06/28/16   06/27/16   06/24/16     /  /     02 - 16                        0    16,622,424  AAA             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Adirondack Educ. Ctr.:
15-1998PR Additions and Alterations    0-004-010               DONE                         06/28/16     /  /     06/24/16     /  /     02 - 16                        0     8,402,544  AAA             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
17-1578   Additions and Alterations    0-004-010                         UNREVIEWED         03/22/18   03/22/18   06/24/16   09/21/17   02 - 16                        0     8,818,200  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Maintenance Building:
15-1999PR New Construction             3-007-001               DONE                         06/28/16     /  /     06/24/16     /  /     02 - 16                        0             0  AAA             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED