Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 10/17/14 at 16:21:17




GLOVERSVILLE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-05-00-01
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Boulevard School:
10-0683   Reconstruction               0-004-008  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   11/04/10   02/08/07   16                       171,762             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          McNab School:
10-0684   Reconstruction               0-007-007  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   11/04/10   02/08/07   16                       121,916       121,916  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Park Terrace Elem.:
10-0685   Reconstruction               0-009-008  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   11/04/10   02/08/07   16                        63,308        63,308  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          High School:
10-0686   Reconstruction               0-010-016  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   09/27/10   02/08/07   2,7                      350,000       350,000  DDJ             0           0           0 Collins & Scoville Architects           0      01/31/12                       09/26/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Kingsborough Elementary:
10-0687   Reconstruction               0-015-009  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   11/04/10   02/08/07   16                        99,243        99,243  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Middle School:
10-0688   Reconstruction               0-019-007  05/09/11     DONE    DONE       DONE      12/31/10   12/23/10   09/27/10   02/08/07   2,7,16                 3,124,459     3,124,459  DDJ             0           0           0 Collins & Scoville Architects           0      01/31/12                       09/26/13         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




JOHNSTOWN CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-06-00-01
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Warren Street School:
09-1350   Reconstruction               0-003-006  01/20/10     DONE    DONE       DONE      04/22/10   04/19/10   03/03/10   03/04/10   13,15,16                  49,486        49,486  HCM             0           0           0 Bonacci Architects                      0      06/10/10                         /  /             

          Pleasant Ave. School:
10-0135   Reconstruction               0-007-012  08/09/10     DONE    DONE       DONE      08/20/10   08/09/10   07/28/10   07/29/10   13,155,16                500,000       500,000  HCM             0           0           0 Bonacci Architects pllc                 0      05/05/11                         /  /             

          Senior High School:
09-1351   Reconstruction               0-009-008  01/20/10     DONE    DONE       DONE      04/22/10   04/19/10   03/03/10   03/04/10   13,15,16                  12,562        12,562  HCM             0           0           0 Bonacci Architects                      0      06/10/10                         /  /             

          Transportation & Maint. Facility:
09-1466TQ Temporary Quarters           5-038-L02  05/19/10     DONE    DONE       DONE      05/27/10   05/27/10   03/25/10     /  /                              533,406       533,406  HCM             0           0           0                                         0        /  /                           /  /             

          Bus Maintenance & Storage Facility:
  -    TQ Temporary Quarters           5-041-001                                              /  /       /  /     03/24/10     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MAYFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-08-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
14-0012   Reconstruction               0-001-017                       ADDENDUM REQ'D       07/03/14   07/02/14   01/07/14   08/20/13   16                             0             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Elementary School:
14-0013   Reconstruction               0-002-012                       ADDENDUM REQ'D       07/03/14   07/02/14   01/07/14   08/20/13   16                             0             0  DDJ             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-09-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Northville Central School:
09-1319   Reconstruction               0-001-010  06/28/10     DONE    DONE       DONE      04/15/10   04/09/10   11/12/08   02/23/10   2,4,7,8,9,10,155,15,   1,549,016     1,549,016  HCM             0           0     173,048 Mosaic Associates                       0      07/05/12                       02/20/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-0131   Reconstruction               0-001-011  01/18/11     DONE    DONE       DONE      08/20/10   08/02/10   04/30/10   02/23/10   8,9,10,155,15,16       2,055,120     2,055,120  HCM             0           0           0 Mosaic Associates                       0      03/01/13                       07/09/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-012                                              /  /       /  /     10/26/11     /  /     4,7,8,14,16                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
10-0132   Reconstruction               5-004-004  01/18/11     DONE    DONE       DONE      08/20/10   08/02/10   06/18/10   02/23/10   155,15                   248,978       248,978  HCM             0           0           0 Mosaic Associates                       0      03/01/13                       07/09/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               5-004-005                                              /  /       /  /     10/28/11     /  /     4,7,8,16                       0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OPPENHEIM EPHRATAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-10-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg:
10-1109   Reconstruction               0-001-007  05/19/11     DONE    DONE       DONE      03/25/11   03/23/11   03/02/11   11/03/10   9,16                      32,000        32,000  HCM             0           0           0 King & King Architects                  0      09/30/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BROADALBIN-PERTH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-11-02-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          ES/HS Broadalbin:
12-1080   Reconstruction               0-001-018  06/17/13     DONE    DONE       DONE      04/09/13   04/09/13   03/05/13   02/05/13   7,16                   1,185,000     1,185,000  JOB             0           0     201,629 Ashley McGraw Architects                0      12/03/13                       12/16/13           

          Main Building Perth:
12-1081   Reconstruction               0-003-013  06/17/13     DONE    DONE       DONE      04/09/13   04/09/13   03/05/13   02/05/13   7,16                     780,000       780,000  JOB             0           0     120,000 Ashley McGraw Architects                0      12/03/13                       12/16/13           

          Bus Repair/Training Center:
12-1082   Reconstruction               5-014-004  06/17/13     DONE    DONE       DONE      04/09/13   04/09/13   03/08/13   02/05/13   7,16                      90,000        90,000  JOB             0           0           0 Ashley McGraw Architects                0      12/03/13                       12/16/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED