Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/20/14 at 13:08:06




ALEXANDER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-02-02-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alexander Jr/Sr High School:
  -       Reconstruction               0-002-010                                              /  /       /  /     08/22/14     /  /     155,15,16                      0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BATAVIA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-03-00-01
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Batavia Middle School:
13-0939   Reconstruction               0-002-011  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   06/06/13   05/21/13   2,4,7,155,15,16           92,622             0  MFS             0           0           0 Young Wright Architectural              0        /  /                           /  /             

          Robert Morris School-Closed 6/30/12:
13-0940   Reconstruction               0-005-009  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   06/06/13   05/21/13   2,15                      84,313             0  MFS             0           0           0 Young Wright Architectural              0        /  /                           /  /             

          Jackson School:
13-0941   Reconstruction               0-007-006  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   06/06/13   05/21/13   2,4,7,8,9,155,15,16      701,077             0  MFS             0           0           0 Young Wright Architectural              0        /  /                           /  /             

          John Kennedy School:
13-0942   Reconstruction               0-008-010  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   06/06/13   05/21/13   2,4,8,16                 169,953             0  MFS             0           0           0 Young Wright Architectural              0        /  /                           /  /             

          Senior High School:
13-0943   Reconstruction               0-015-012  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   06/06/13   05/21/13   2,4,7,8,9,155,15,16      446,860             0  MFS             0           0           0 Young And Wright Architectura           0        /  /                           /  /             
13-0630   Reconstruction               0-015-013  02/24/14     DONE    DONE       DONE      10/25/13   10/25/13   10/02/13   05/21/13   2,16                     365,978       365,978  MFS             0           0           0 Young Wright Architectural              0      09/09/14           YES           /  /             

          Richmond Memorial Library:
13-0944   Reconstruction               6-003-005  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   06/06/13   05/21/13   2,4,7,8,9,16             490,952             0  MFS             0           0     226,675 Young Wright Architectural              0        /  /                           /  /             
13-0631   Reconstruction               6-003-006  02/13/14     DONE    DONE       DONE      10/25/13   10/25/13   09/04/13   05/21/13   2,4,7                    582,554             0  MFS             0           0           0 Young And Wright Architectura           0        /  /                           /  /             

          Stadium:
13-0945   New Construction             7-016-002  07/02/14     DONE    DONE       DONE      12/24/13   12/23/13   07/08/13   05/21/13   02 - 16                1,124,617             0  MFS             0           0           0 Young Wright Architectural              0        /  /                           /  /             

          Concession Stand @ Vandetta Stadium:
  -       New Construction             7-025-001                       DONE                   /  /       /  /     05/07/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELBA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-09-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building K-12:
10-0090   Reconstruction               0-001-009  10/07/10     DONE    DONE       DONE      08/09/10   07/28/10   05/21/10   07/09/07   2,4,8,10                 314,678       314,678  JOD             0           0      15,171 Clark Patterson Lee                     0      10/16/12                       06/30/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-1539   Reconstruction               0-001-010  06/11/14     DONE    DONE       DONE      05/16/14   05/16/14   12/11/13   12/09/13   4,9,15,16                 35,498        35,498  MFS             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Sports Booster Concession Stand:
12-1247   New Construction             7-002-001  10/15/13     DONE    DONE       DONE      06/05/13   05/13/13   02/05/13   03/11/13   02 - 16                   10,800             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LEROY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-10-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wolcott Street School:
12-0695   Reconstruction               0-001-005  02/14/13     DONE    DONE       DONE      01/18/13   01/17/13   12/12/12   05/15/12   2,8                      100,000       100,000  DDJ             0           0           0 Clark Patterson Lee                     0      06/28/13                       09/10/14         YES
                                                                                                                                                                                                                                                                                                                                   
13-0255   Reconstruction               0-001-008  09/26/13     DONE    DONE       DONE      08/23/13   08/22/13   06/05/13   05/21/13   2,8                      100,000             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-009                                              /  /       /  /     07/16/14     /  /     2                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Jr/Sr High School 7-12:
12-0059   Reconstruction               0-017-003  08/01/12     DONE    DONE       DONE      07/26/12   07/16/12   06/08/12   07/10/12   2,7,155,15,16            310,000       310,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OAKFIELD-ALABAMA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-11-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 6-12:
14-0191   Reconstruction               0-005-010  03/25/14     DONE    DONE       DONE      08/19/14   08/14/14   03/07/14   03/11/14   4,7                      144,824       144,824  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PAVILION CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-12-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
14-0188   Reconstruction               0-001-006               STARTED STARTED    UNREVIEWED08/15/14   08/15/14   11/08/13   02/25/14   2,4,7,8,9,155,15,16            0    18,821,385  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          Indust. Arts & Equip. Stg. Building:
  -       Reconstruction               0-002-003                                              /  /       /  /     11/08/13     /  /     2,4,7,8,9,155,15,16            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Elementary School:
14-0189   Reconstruction               0-004-008               STARTED STARTED    UNREVIEWED08/15/14   08/15/14   11/08/13   02/25/14   2,4,7,8,9,155,15,16            0             0  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          New Bus Garage:
09-1465   Reconstruction               5-003-L04  05/24/10     DONE    DONE       DONE      05/24/10   05/24/10   05/19/10   05/15/12                            141,865       113,492  HCM             0           0           0                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Lease Bus Garage:
  -    XX Reconstruction               5-009-001                         CANCELLED            /  /       /  /     03/24/10     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PEMBROKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 18-13-02-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr. Sr. High School:
13-0984   Reconstruction               0-003-005  05/15/14     DONE    DONE       DONE      01/07/14   01/06/14   04/02/13   12/07/07   2,155                    288,390       288,390  JMB             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED