CAIRO-DURHAM CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-03-01-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Cairo-Durham Elementary School:
18-2116 Reconstruction 0-001-018 07/25/19 DONE DONE DONE 06/13/19 06/04/19 09/14/18 05/15/18 155,16 515,006 515,006 BMJ 0 0 0 Mosaic Associates 515,006 03/04/21 06/04/19
19-1689 Reconstruction 0-001-019 07/22/20 DONE DONE DONE 04/13/20 04/09/20 03/26/19 12/11/18 2,4,7,9,10,155,15,16 5,173,767 5,173,767 JSS 0 0 0 Mosaic Associates 0 05/25/23 04/09/20
19-0590 Reconstruction 0-001-020 01/03/20 DONE DONE DONE 10/21/19 10/07/19 07/31/19 05/21/19 7 100,000 100,000 JSS 0 0 0 Mosaic Associates 0 06/17/20 10/07/19
20-0419 Reconstruction 0-001-021 01/28/21 DONE DONE DONE 09/22/20 09/10/20 08/12/20 06/16/20 7 100,000 100,000 JSS 0 0 0 Mosaic Associates 0 04/21/21 09/10/20
22-0384 Reconstruction 0-001-022 10/25/22 DONE DONE DONE 08/31/22 08/31/22 12/08/21 12/11/18 2,7,8,9,10,155,15,16 1,231,586 1,231,586 SLC 0 0 0 Mosaic Associates 0 / / 08/31/22
22-1642 Reconstruction 0-001-023 04/04/23 DONE DONE DONE 02/08/23 02/07/23 01/09/23 05/18/21 2,9 100,000 100,000 MSK 0 0 0 Mosaic Associates 0 06/08/23 02/07/23
23-1052 Reconstruction 0-001-024 02/06/24 DONE DONE DONE 11/27/23 11/21/23 10/25/23 05/16/23 15 100,000 100,000 MSK 0 0 0 SEI Design Group 0 / / 11/21/23
- Reconstruction 0-001-025 / / / / / / / / 155,15,16 0 0 MSK 0 0 0 0 / / / /
High School-Middle School:
18-2117 Reconstruction 0-011-019 07/25/19 DONE DONE DONE 06/13/19 06/04/19 09/14/18 05/15/18 155,16 1,434,994 1,434,994 BMJ 0 0 0 Mosaic Associates 1,434,994 03/04/21 06/04/19
19-1690 Additions and Alterations 0-011-021 07/22/20 DONE DONE DONE 04/13/20 04/09/20 03/26/19 12/11/18 02 - 16 22,461,233 21,601,733 JSS 0 0 0 Mosaic Associates 0 05/25/23 04/09/20
22-0385 Reconstruction 0-011-022 10/25/22 DONE DONE DONE 08/31/22 08/31/22 12/08/21 12/11/18 2,7,8,9,10,155,15,16 3,923,120 3,923,120 SLC 0 0 0 Mosaic Associates 0 12/31/23 08/31/22
22-0099 Reconstruction 0-011-023 08/01/22 DONE DONE DONE 07/15/22 07/15/22 12/08/21 12/11/18 2,10,16 804,440 804,440 SLC 0 0 0 Mosaic Associates 0 06/19/23 YES 07/15/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CATSKILL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-04-01-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior/Junior High School:
- PR Additions and Alterations 0-005-021 / / / / 04/03/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
19-1102 Additions and Alterations 0-005-021 08/03/20 DONE DONE DONE 01/17/20 12/12/19 04/03/19 02/12/19 02 - 16 17,761,636 0 BMJ 0 0 0 Burton Behrendt Smith 0 09/24/21 12/12/19
20-0847 Reconstruction 0-005-022 04/12/21 DONE DONE DONE 11/19/20 11/14/20 04/03/19 02/12/19 2,8,9,10,155,15,16 11,885,017 11,885,017 JSS 0 0 0 Burton Behrendt Smith 0 / / 11/14/20
- Reconstruction 0-005-023 / / / / 02/18/20 / / 15 0 0 JSS 0 0 0 0 / / / /
22-2330 Reconstruction 0-005-024 12/22/22 DONE DONE DONE 06/07/23 06/05/23 12/05/22 12/14/22 155,15,16 700,000 700,000 JJH 0 0 0 Burton Behrendt Smith 0 02/03/23 06/05/23
New Elementary School/Broome Street:
19-1103 Reconstruction 0-028-004 08/03/20 DONE DONE DONE 01/02/20 12/12/19 04/03/19 02/12/19 2,8,9,155,15,16 10,303,338 10,303,338 BMJ 0 0 0 Burton Behrendt Smith 0 05/13/22 12/12/19
20-0848 Reconstruction 0-028-005 04/12/21 DONE DONE DONE 11/19/20 11/14/20 04/03/19 02/12/19 7,8,9,155,15,16 1,870,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 11/14/20
Superintendent Office:
20-0849 Reconstruction 1-003-002 04/12/21 DONE DONE DONE 11/19/20 11/14/20 04/03/19 02/12/19 2,9,155,15,16 195,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 11/14/20
Business Office:
20-0850 Reconstruction 1-007-002 04/12/21 DONE DONE DONE 11/19/20 11/14/20 04/03/19 02/12/19 2,9,155,15,16 285,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 11/14/20
Storage Container #1 - Athletics:
- DB Discovered Building 2-033-001 / / / / 05/06/21 / / 0 0 JSS 0 0 0 0 / / / /
Storage Container #2 - Athletics:
- DB Discovered Building 2-034-001 / / / / 05/06/21 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer:
- DB Discovered Building 2-035-001 / / / / 05/06/21 / / 0 0 JSS 0 0 0 0 / / / /
District-Wide:
21-1024SB Reconstruction 7-999-001 DONE / / / / 01/03/22 / / 16 0 0 JLB 0 0 0 0 / / / /
22-0176 Reconstruction 7-999-001 11/15/22 DONE DONE DONE 07/27/22 07/27/22 01/03/22 11/04/14 16 1,295,692 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 07/27/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
COXSACKIE-ATHENS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-05-01-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle/High School:
19-1660 Reconstruction 0-001-019 09/29/20 DONE DONE DONE 04/06/20 04/03/20 08/13/19 05/21/19 10,155,15,16 2,247,662 2,247,662 JLB 0 0 0 Collins & Scoville Architects 2,247,662 01/26/22 04/03/20
19-1458 Reconstruction 0-001-020 04/22/20 DONE DONE DONE 02/21/20 02/05/20 01/03/20 12/17/19 2,4,7,16 2,395,738 2,395,738 JLB 0 0 0 Collins & Scoville Architects 0 10/29/20 02/05/20
20-1079 Reconstruction 0-001-021 04/21/21 DONE DONE DONE 12/31/20 12/24/20 12/14/20 12/17/19 16 559,754 559,754 JLB 0 0 0 Collins & Scoville Architects 0 09/08/23 12/24/20
Elementary School:
19-1661 Reconstruction 0-006-016 09/29/20 DONE DONE DONE 04/06/20 04/03/20 08/13/19 05/21/19 10,155,15,16 226,994 226,994 JLB 0 0 0 Collins & Scoville Architects 226,994 01/26/22 04/03/20
20-1080 Reconstruction 0-006-017 04/21/21 DONE DONE DONE 12/31/20 12/24/20 12/14/20 12/17/19 16 406,374 406,374 JLB 0 0 0 Collins & Scoville Architects 0 09/08/23 12/24/20
22-0147 Reconstruction 0-006-018 10/07/22 DONE DONE DONE 07/25/22 07/22/22 06/29/22 05/17/22 2,8 70,000 70,000 JLB 0 0 0 Collins & Scoville Architects 0 09/30/23 07/22/22
Athens Elementary School:
19-1662 Reconstruction 0-007-017 09/29/20 DONE DONE DONE 04/06/20 04/03/20 08/13/19 05/21/19 10,155,15,16 225,343 225,343 JLB 0 0 0 Collins & Scoville Architects 225,343 01/26/22 04/03/20
20-1081 Reconstruction 0-007-018 04/21/21 DONE DONE DONE 12/31/20 12/24/20 12/14/20 12/17/19 16 413,134 413,134 JLB 0 0 0 Collins & Scoville Architects 0 09/08/23 12/24/20
20-1521 Reconstruction 0-007-019 05/21/21 DONE DONE DONE 04/01/21 03/31/21 03/23/21 05/18/21 14,16 88,250 88,250 JLB 0 0 0 Collins & Scoville Architects 0 10/29/21 03/31/21
21-0634 Reconstruction 0-007-020 12/07/21 DONE DONE DONE 11/03/21 11/02/21 07/14/21 05/18/21 16 182,500 182,500 JLB 0 0 0 Collins & Scoville Architects 0 09/08/23 11/02/21
22-0148XX Reconstruction 0-007-021 10/07/22 CANCELLED 07/25/22 07/22/22 06/29/22 05/17/22 2,8 30,000 30,000 JLB 0 0 0 Collins & Scoville Architects 0 / / 07/22/22
22-2485 Reconstruction 0-007-022 08/14/23 DONE DONE DONE 06/30/23 06/29/23 06/20/23 05/16/23 2,8 30,000 30,000 JJH 0 0 0 Collins & Scoville Architects 0 01/10/24 06/29/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
GREENVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-07-01-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Scott M Ellis Elementary:
20-1202 Reconstruction 0-001-030 05/24/21 DONE DONE DONE 01/27/21 01/15/21 07/17/20 06/09/20 2,9,16 285,000 285,000 JLB 0 0 0 SEI Design Group 0 01/14/22 01/15/21
- Reconstruction 0-001-031 / / / / 01/19/21 / / 2,8,9,15,16 0 0 JLB 0 0 0 0 / / / /
21-1827FC Reconstruction 0-001-032 07/05/22 DONE DONE DONE 05/18/22 05/05/22 02/14/22 10/18/21 2,4,9,155,16 344,300 282,600 JLB 0 0 0 SEI Design Group 0 09/05/23 05/05/22
23-0466 Additions and Alterations 0-001-033 03/14/24 DONE DONE DONE 09/13/23 09/13/23 01/12/23 12/06/22 02 - 16 11,628,615 11,201,903 JJH 0 0 0 SEI Design Group 0 / / 09/13/23
23-1464PR Additions and Alterations 0-001-033 DONE 02/05/24 / / 01/12/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
Middle School/High School:
21-1828FC Reconstruction 0-008-027 07/05/22 DONE DONE DONE 05/18/22 05/05/22 02/14/22 10/16/21 2 245,000 184,200 JLB 0 0 0 SEI Design Group 0 09/05/23 05/05/22
22-0075 Reconstruction 0-008-028 10/07/22 DONE DONE DONE 07/13/22 07/12/22 03/01/22 05/17/22 2,4,7,155,16 420,000 420,000 JLB 0 0 0 SEI Design Group 0 / / 07/12/22
23-0467 Additions and Alterations 0-008-029 03/14/24 DONE DONE DONE 09/13/23 09/13/23 01/12/23 12/06/22 02 - 16 2,442,055 2,279,982 JJH 0 0 0 SEI Design Group 0 / / 09/13/23
23-1465PR Additions and Alterations 0-008-029 DONE 02/05/24 / / 01/12/23 / / 02 - 16 2,442,055 0 JJH 0 0 0 0 / / / /
1st and 2nd Grade Modular Demolition:
19-0210 Reconstruction 0-030-001 09/03/19 DONE DONE DONE 08/05/19 07/30/19 07/15/19 05/15/18 2 50,300 0 JLB 0 0 0 Stieglitz Snyder Architecture 0 02/12/20 07/30/19
Ellis Pavilion:
18-2177 New Construction 7-029-001 09/05/19 DONE DONE DONE 06/20/19 05/29/19 03/21/19 05/15/18 02 - 16 121,200 0 JLB 0 0 0 Stieglitz Snyder Architecture 0 08/15/20 05/29/19
MS/HS Pavilion:
21-1043FC New Construction 7-031-001 01/14/22 DONE DONE DONE 01/05/22 12/21/21 09/23/21 10/18/21 02 - 16 174,400 0 JLB 0 0 0 SEI Design Group 0 10/17/22 12/21/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HUNTER-TANNERSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-09-01-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior Senior High:
21-0855 Reconstruction 0-001-014 05/16/22 DONE DONE DONE 12/07/21 12/06/21 10/25/21 12/15/20 2,4,7,8,9,10,14,155, 3,876,000 3,876,000 WLC 0 0 0 Rhinebeck Architecture 0 11/16/23 12/06/21
- PR Additions and Alterations 0-001-015 / / / / 08/01/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
Elementary School:
21-0856 Additions and Alterations 0-002-014 05/16/22 DONE DONE DONE 12/07/21 12/06/21 10/25/21 12/15/20 02 - 16 2,122,000 2,121,380 WLC 0 0 0 Rhinebeck Architecture 0 11/16/23 12/06/21
- PR Alterations 0-002-015 / / / / 08/01/23 / / 0 0 WLC 0 0 0 0 / / / /
Athletic Storage Shed:
19-1604DB Discovered Building 2-011-001 05/13/20 DONE DONE DONE 03/20/20 03/19/20 02/13/20 / / 0 0 BMJ 0 0 0 0 / / 03/19/20
Soccer Storage Shed:
19-1605DB Discovered Building 2-012-001 05/13/20 DONE DONE DONE 03/20/20 03/19/20 02/13/20 / / 0 0 BMJ 0 0 0 0 / / 03/19/20
Trash Storage Shed 1:
19-1606DB Discovered Building 2-013-001 05/13/20 DONE DONE DONE 03/20/20 03/19/20 02/13/20 / / 0 0 BMJ 0 0 0 0 / / 03/19/20
Trash Storage Shed 2:
19-1607DB Discovered Building 2-014-001 05/13/20 DONE DONE DONE 03/20/20 03/19/20 02/13/20 / / 0 0 BMJ 0 0 0 0 / / 03/19/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WINDHAM-ASHLAND-JEWETT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-14-01-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
22-0765 Reconstruction 0-001-014 03/06/23 DONE DONE DONE 10/19/22 10/18/22 07/08/22 05/17/22 2,7,8,9,155,16 5,572,000 5,572,000 SLC 0 0 0 IBI GROUP 0 / / 10/18/22
Pavilion:
23-0296 New Construction 7-012-001 09/27/23 DONE DONE DONE 08/21/23 08/16/23 03/27/23 05/17/22 02 - 16 83,000 0 MSK 0 0 0 IBI GROUP 0 / / 08/16/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES OTSEGO NORTHERN CATSKILLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 19-90-00-00
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Otsego Occupational Center:
19-1200 Reconstruction 0-016-020 04/17/20 DONE DONE DONE 01/13/20 01/09/20 12/12/19 05/21/19 2,8,9,16 1,747,899 11,000 JSS 0 0 0 Bernier Carr & Associates 0 11/13/20 01/09/20
20-1243 Reconstruction 0-016-021 02/10/21 DONE DONE DONE 02/05/21 02/05/21 02/01/21 08/19/20 7,155,16 38,500 0 JSS 0 0 0 Bernier Carr & Associates 0 / / 02/05/21
21-0934 Reconstruction 0-016-022 03/16/22 DONE DONE DONE 12/20/21 12/20/21 08/27/21 12/15/21 2,155,15,16 1,059,562 1,059,562 JLB 0 0 0 Bernier Carr Associates 0 / / 12/20/21
No. Catskills Occ. Ctr.:
20-0701 Reconstruction 0-018-016 01/29/21 DONE DONE DONE 10/28/20 10/16/20 08/14/20 08/19/20 155,16 500,000 0 JSS 0 0 0 Bernier Carr Associates 0 / / 10/16/20
20-1244 Reconstruction 0-018-017 02/10/21 DONE DONE DONE 02/05/21 02/05/21 02/01/21 08/19/20 7,8,155,16 159,500 0 JSS 0 0 0 Bernier Carr & Associates 0 / / 02/05/21
- XX Reconstruction 0-018-018 CANCELLED / / / / 08/27/21 / / 7 0 0 JLB 0 0 0 0 / / / /
22-0316 Reconstruction 0-018-019 10/24/22 DONE DONE DONE 08/22/22 08/22/22 05/27/22 04/20/22 7,155 1,247,400 0 JLB 0 0 0 Bernier Carr & Associates 0 / / 08/22/22
Building Trades Welding Storage:
21-1931DB Discovered Building 2-067-001 09/22/22 DONE DONE DONE 06/06/22 / / 02/10/21 / / 0 0 JLB 0 0 0 0 / / / /
Auto Storage:
21-1932DB Discovered Building 2-069-001 09/22/22 DONE DONE DONE 06/06/22 / / 02/10/21 / / 0 0 JLB 0 0 0 0 / / / /
Career Pathways Storage:
21-1933DB Discovered Building 2-070-001 09/22/22 DONE DONE DONE 06/06/22 / / 02/10/21 / / 0 0 JLB 0 0 0 0 / / / /
Maintenance Storage:
21-1934DB Discovered Building 2-071-001 09/22/22 DONE DONE DONE 06/06/22 / / 02/10/21 / / 0 0 JLB 0 0 0 0 / / / /
Animal Barn #1-Milford:
21-1935DB Discovered Building 7-040-002 09/22/22 DONE DONE DONE 06/06/22 / / 02/10/21 / / 0 0 JSS 0 0 0 0 / / / /
Greenhouse:
- PR New Construction 7-066-001 / / / / 06/27/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
19-1149 New Construction 7-066-001 11/10/21 DONE DONE DONE 01/03/20 12/26/19 06/27/19 05/21/19 02 - 16 22,729 0 JLB 0 0 0 Bernier Carr Associates 0 / / 12/26/19
District Wide:
20-0657XX Reconstruction 7-999-001 CANCELLED 10/21/20 10/16/20 06/30/20 08/19/20 16 0 0 JSS 0 0 0 Bernier Carr Associates 0 / / 10/16/20
ONC BOCES Admin Offices:
- TQ Temporary Quarters 8-072-001 / / / / 12/14/23 / / 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED