SOUTH JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-01-01-04
last updated on 08/17/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wilson Elementary:
17-1181   Reconstruction               0-001-009               DONE    DONE       UNREVIEWED01/17/18   12/21/17   06/02/17   05/16/17   2,4,9,155,15                   0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Clarke Jr/Sr High School:
14-0215   Reconstruction               0-005-006  04/23/15     DONE    DONE       DONE      08/22/14   08/22/14   05/30/14   12/04/07   8,9,155,15,16            917,053       917,053  JMB             0           0           0 Ashley McGraw                           0      08/28/15                       06/30/16           
16-0660   Reconstruction               0-005-007  11/07/16     DONE    DONE       DONE      10/25/16   10/24/16   08/22/16   05/17/16   16                       100,000       100,000  BMJ             0           0           0 Ashley McGraw                           0      05/19/17                       06/02/17           
16-0934   Reconstruction               0-005-008  01/12/17     DONE    DONE       DONE      12/08/16   12/08/16   11/08/16   12/04/07   2,9                       70,000        70,000  BMJ             0           0           0 Ashley McGraw                           0      06/29/17                       09/21/17           
17-1182   Reconstruction               0-005-009               DONE    DONE       UNREVIEWED01/17/18   12/21/17   06/02/17   05/16/17   2,4,9,10,155,15,16             0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             
17-0764   Reconstruction               0-005-010  02/16/18     DONE    DONE       DONE      11/14/17   10/26/17   06/06/17   05/16/17   16                       100,000       100,000  BMJ             0           0           0 Ashley McGraw                           0      06/25/18                       06/29/18           
  -       Reconstruction               0-005-011                                              /  /       /  /     08/16/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Mannsville Elementary:
14-0216   Reconstruction               0-006-006  04/23/15     DONE    DONE       DONE      08/22/14   08/22/14   05/30/14   12/04/07   9,155                    252,000       252,000  JMB             0           0           0 Ashley McGraw                           0      08/28/16                       06/30/16           
17-1183   Reconstruction               0-006-007               DONE    DONE       UNREVIEWED01/17/18   12/21/17   06/02/17   05/16/17   2,8,9,155,15                   0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Mannsville Bus Garage:
17-1184   Reconstruction               4-008-002               DONE    DONE       UNREVIEWED01/17/18   12/27/17   06/02/17   05/16/17   7                              0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Adams Center Bus Garage:
14-0217   Reconstruction               5-002-006  04/23/15     DONE    DONE       DONE      08/22/14   08/22/14   05/30/14   12/04/07   155                       96,000        96,000  JMB             0           0           0 Ashley McGraw                           0      08/28/15                       06/30/16           
17-1185   Reconstruction               5-002-007               DONE    DONE       UNREVIEWED01/17/18   12/21/17   06/02/17   05/16/17   2,16                           0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Concession/Storage Building:
14-0499DB Discovered Building          7-011-001  09/09/15     DONE    DONE       DONE      10/21/14   10/17/14   09/26/14     /  /                                    0             0  JMB             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Storage Building #2:
14-0500DB Discovered Building          7-012-001  09/09/15     DONE    DONE       DONE      10/21/14   10/17/14   09/26/14     /  /                                    0             0  JMB             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Press Box @ Jr/Sr High School:
17-1186   New Construction             7-017-001               DONE    DONE       UNREVIEWED01/17/18   12/21/17   12/11/17   05/16/17   02 - 16                        0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ALEXANDRIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-02-02-04
last updated on 08/17/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alexandria Central:
13-0106   Reconstruction               0-001-012  08/21/13     DONE    DONE       DONE      07/29/13   07/29/13   06/05/13   05/21/13   9,15,16                  100,000       100,000  DDJ             0           0           0 King & King Architects                  0      01/15/14                       03/21/14           
13-1621   Reconstruction               0-001-013  06/27/14     DONE    DONE       DONE      06/18/14   06/13/14   04/25/14   05/20/14   9,15,16                  100,000       100,000  DDJ             0           0           0 King & King Architects                  0      01/15/15                       06/01/15           
15-0006   Reconstruction               0-001-014  05/10/16     DONE    DONE       DONE      07/02/15   07/01/15   01/08/15   12/17/14   2,8,9,10,14,155,15,1   5,610,000     5,610,000  DDJ             0           0           0 King & King Architects                  0      04/27/18                       05/24/18           
15-1361   Reconstruction               0-001-015  02/02/16     DONE    DONE       DONE      03/04/16   03/02/16   01/29/16   02/02/16   9,155,15,16              380,000       380,000  DDJ             0           0           0 King & King Architects                  0      07/15/17                       11/15/17           
17-1094   Reconstruction               0-001-016  02/27/18     DONE    DONE       DONE      01/02/18   12/21/17   06/05/17   05/16/17   2,8,9,155,15,16          100,000       100,000  BMJ             0           0           0 King & King Architects                  0      06/01/18                       06/30/18           
  -       Reconstruction               0-001-017                                              /  /       /  /     08/14/18     /  /     8,9                            0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage/Agriculture Clrm:
15-0005   Reconstruction               0-004-004  05/10/16     DONE    DONE       DONE      07/02/15   07/01/15   01/08/15   12/17/14   2,8,9,15,16              590,000       590,000  DDJ             0           0           0 King & King Architects                  0      04/27/18                       05/24/18           

          Greenhouse:
16-0312   Reconstruction               0-005-002  09/12/16     DONE    DONE       DONE      08/24/16   08/24/16   07/27/16   05/17/16   155,16                    50,000        50,000  DDJ             0           0           0 King & King Architects                  0      01/15/17                       11/17/17           

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1284SB Reconstruction               7-999-001                                              /  /       /  /     02/24/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




INDIAN RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-03-01-06
last updated on 08/17/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMP