Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/20/14 at 13:08:06




SOUTH JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-01-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Clarke Jr/Sr High School:
14-0215   Reconstruction               0-005-006               DONE    DONE       UNREVIEWED08/22/14   08/22/14   05/30/14   12/04/07   8,9,155,15,16                  0    31,392,072  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Mannsville Elementary:
14-0216   Reconstruction               0-006-006               DONE    DONE       UNREVIEWED08/22/14   08/22/14   05/30/14   12/04/07   9,155                          0     8,750,650  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Adams Center Bus Garage:
14-0217   Reconstruction               5-002-006               DONE    DONE       UNREVIEWED08/22/14   08/22/14   05/30/14   12/04/07   155                            0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Concession/Storage Building:
14-0499DB Discovered Building          7-011-001                         UNREVIEWED         10/21/14   10/17/14   09/26/14     /  /                                    0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Storage Building #2:
14-0500DB Discovered Building          7-012-001                       ADDENDUM REQ'D       10/21/14   10/17/14   09/26/14     /  /                                    0             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ALEXANDRIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-02-02-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alexandria Central:
13-0106   Reconstruction               0-001-012  08/21/13     DONE    DONE       DONE      07/29/13   07/29/13   06/05/13   05/21/13   9,15,16                  100,000       100,000  DDJ             0           0           0 King & King Architects                  0      01/15/14                       03/21/14           
13-1621   Reconstruction               0-001-013  06/27/14     DONE    DONE       DONE      06/18/14   06/13/14   04/25/14   05/20/14   9,15,16                  100,000             0  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




INDIAN RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-03-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Antwerp Primary School:
13-1579   Reconstruction               0-001-012               STARTED DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,8,9,13,15,16                 0     4,927,608  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Evans Mills Primary School:
14-0299   Additions and Alterations    0-004-015               DONE    STARTED    UNREVIEWED09/15/14   09/10/14   11/21/13   01/22/14   02 - 16                        0    13,434,880  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Philadelphia Primary School:
11-1374   Reconstruction               0-005-012  07/13/12     DONE    DONE       DONE      05/31/12   05/25/12   02/15/12   05/15/12   7,155,15,16               75,000             0  HCM             0           0           0 March Associates                        0        /  /                           /  /             
13-1580   Reconstruction               0-005-013               STARTED DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,4,9,16                       0     3,558,828  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Indian River High School:
14-0547   Additions and Alterations    0-007-016                         UNREVIEWED         10/28/14   10/27/14   11/21/13   01/22/14   02 - 16                        0    33,968,457  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Theresa Primary School:
13-1581   Reconstruction               0-008-011  10/28/14     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,4,9,16                       0             0  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Indian River Middle 5-8):
11-1354   Reconstruction               0-010-011  06/01/12     DONE    DONE       DONE      05/25/12   05/25/12   04/11/12   05/15/12   15                        59,000             0  HCM             0           0           0 March Associates                        0        /  /                           /  /             
14-0548   Additions and Alterations    0-010-012                         UNREVIEWED         10/28/14   10/27/14   11/21/13   01/22/14   02 - 16                        0    24,899,300  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Calcium Primary School:
13-1582   Reconstruction               0-027-009               STARTED DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,9,13,15,16                   0             0  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          New Grade 4-5 Building:
14-0300   Additions and Alterations    0-032-003               DONE    STARTED    UNREVIEWED09/15/14   09/10/14   11/21/13   01/22/14   02 - 16                        0    15,101,080  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Toilet/Storage Building:
14-0549   New Construction             2-044-001                         UNREVIEWED         10/28/14   10/27/14   03/27/14   01/22/14   02 - 16                        0             0  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Maintenance Center (old bus garage):
13-1583   Reconstruction               5-002-006  10/28/14     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,4,8,16                       0             0  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          New Transportation Facility:
11-1375   Reconstruction               5-031-004  07/13/12     DONE    DONE       DONE      05/31/12   05/25/12   04/11/12   05/15/12   4,9,10,15                 12,200             0  HCM             0           0           0 March Associates                        0        /  /                           /  /             
13-1584   Reconstruction               5-031-005               STARTED DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   4,9,13,155,16                  0             0  MFS             0           0           0 March Associates                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENERAL BROWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-04-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Brownville Glen Elementary:
10-0858   Reconstruction               0-001-005  06/07/11     DONE    DONE       DONE      02/16/11   02/15/11   09/10/10   03/17/08   155,16                    80,367        80,367  HCM             0           0           0 Bernier Carr Associates                 0      11/29/12                       02/11/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Dexter Elementary:
10-0859   Reconstruction               0-002-004  06/07/11     DONE    DONE       DONE      02/16/11   02/15/11   09/10/10   03/18/08   155,16                   416,457       416,457  HCM             0           0           0 Bernier Carr Associates                 0      11/29/12                       02/11/13         YES
                                                                                                                                                                                                                                                                                                                                   

          General Brown High:
10-0860   Reconstruction               0-003-004  06/07/11     DONE    DONE       DONE      02/16/11   02/15/11   09/10/10   03/18/08   2,9,10,155,16          1,125,146     1,125,146  HCM             0           0           0 Bernier Carr Associates                 0      11/29/12                       02/11/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage:
09-1209   Reconstruction               5-004-004  01/18/11     DONE    DONE       DONE      04/02/10   03/30/10   03/03/10   11/09/10   2,8,9,16                 558,808       558,808  HCM             0           0           0 Bernier Carr Associates                 0      06/02/11                       06/24/13         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




THOUSAND ISLANDS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-07-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Guardino Elem. (fmly Clayton):
11-1026   Reconstruction               0-003-004  10/09/12     DONE    DONE       DONE      03/28/12   03/19/12   12/16/11   12/13/11   2,7,9,10,14,16         1,154,540     1,154,540  DDJ             0           0           0 Ashley McGraw Architects                0      05/01/14                       05/16/14           
11-1338   Reconstruction               0-003-005  05/29/12     DONE    DONE       DONE      05/24/12   05/17/12   05/11/12   12/13/11   7                        900,000       900,000  DDJ             0           0           0 Ashley McGraw Architects                0      11/24/12                       06/25/13           
14-0002   Reconstruction               0-003-006               DONE    DONE       ADD. REQ'D07/03/14   07/01/14   01/16/14   12/10/10   2,4,8,9,13,155,15,16           0             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
13-1312   Reconstruction               0-003-007  08/20/14     DONE    DONE       DONE      03/07/14   03/05/14   01/24/14   12/10/13   15                        75,000             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Cape Vincent Elem:
11-1027   Reconstruction               0-005-004  10/09/12     DONE    DONE       DONE      03/28/12   03/19/12   12/16/11   12/13/11   2,7,9,10,13,16           988,684       793,684  DDJ             0           0           0 Ashley McGraw Architects                0      05/01/14                       05/16/14           
11-1339   Reconstruction               0-005-005  05/29/12     DONE    DONE       DONE      05/24/12   05/17/12   05/11/12   12/13/11   7                        425,000       425,000  DDJ             0           0           0 Ashley McGraw Architects                0      11/24/12                       06/25/13           
14-0003   Reconstruction               0-005-006               DONE    DONE       ADD. REQ'D07/03/14   07/01/14   01/16/14   12/13/10   2,8,9,13,155,15,16             0             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
13-1313   Reconstruction               0-005-007  08/20/14     DONE    DONE       DONE      03/07/14   03/05/14   01/24/14   12/10/13   15                        75,000             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Cape Vincent Annex:
11-1028   Reconstruction               0-008-001  10/09/12     DONE    DONE       DONE      03/28/12   03/19/12   12/22/11   12/13/11   2                         25,000             0  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Middle School / High School:
10-1440   Reconstruction               0-011-010  07/20/11     DONE    DONE       DONE      06/30/11   06/27/11   06/07/11   05/17/11   7,13,16                  181,955       181,955  DDJ             0           0           0 ROBERT J. COMPANY                       0        /  /                           /  /             
11-1029   Reconstruction               0-011-011  10/09/12     DONE    DONE       DONE      03/28/12   03/19/12   12/16/11   12/13/11   2,9,16                   803,121       803,121  DDJ             0           0           0 Ashley McGraw Architects                0      05/01/14                       05/16/14           
13-0207   Reconstruction               0-011-012  01/14/14     DONE    DONE       DONE      08/14/13   08/14/13   06/18/13   05/21/13   155                      100,000       100,000  MFS             0           0           0 Ashley McGraw Architects                0      06/30/14                       07/28/14           
14-0004   Reconstruction               0-011-013               DONE    DONE       ADD. REQ'D07/03/14   07/01/14   01/16/14   12/13/10   2,4,8,9,10,13,155,15           0             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
14-0423   Reconstruction               0-011-014  11/04/14     DONE    DONE       DONE      11/04/14   11/04/14   08/26/14   05/20/14   9,10                     100,000       100,000  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Storage Building -Clayton:
14-0005   Additions and Alterations    2-012-002               DONE    DONE       ADD. REQ'D07/03/14   07/01/14   01/16/14   12/13/10   02 - 16                        0             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Bus Garage/Clayton:
14-0006   Reconstruction               5-001-008               DONE    DONE       ADD. REQ'D07/03/14   07/01/14   01/16/14   12/13/10   16                             0             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Bus Garage @ Cape Vincent:
14-0007   Reconstruction               5-004-006               DONE    DONE       ADD. REQ'D07/03/14   07/01/14   01/16/14   12/13/10   16                             0             0  MFS             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          New Wind Turbine on Middle / High:
  -    XX New Construction             7-014-001                         CANCELLED            /  /       /  /     06/18/10     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BELLEVILLE HENDERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-09-09-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 School:
09-1565   Additions and Alterations    0-010-005  03/02/11     DONE    DONE       DONE      06/22/10   06/14/10   08/12/08   02/27/09   02 - 16                6,897,466     6,871,919  DDJ             0           0     356,912 Bernier Carr Associates                 0      11/13/12                       06/30/14           
  -       Reconstruction               0-010-007                                              /  /       /  /     08/14/14     /  /     2,9,10,155,16                  0    14,377,865  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-010-008                                              /  /       /  /     08/14/14     /  /     2,9                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage-Belleville:
  -       Reconstruction               5-004-002                                              /  /       /  /     11/18/10     /  /     2,9,15                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LYME CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-13-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-0668   Additions and Alterations    0-002-005  04/29/10     DONE    DONE       DONE      01/04/10   12/29/09   01/16/08   03/03/09   02 - 16                4,020,000     4,020,000  MGL             0           0     283,272 Bernier Carr Associates                 0      02/20/14                       04/30/14         YES
                                                                                                                                                                                                                                                                                                                                   
12-1211   Reconstruction               0-002-007  05/24/13     DONE    DONE       DONE      05/21/13   05/16/13   02/05/13   03/26/13   2,4,7,10                 875,800       875,800  JOB             0           0           0 Bernier Carr Associates                 0      10/24/13                       11/12/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-1148   Reconstruction               0-002-008  08/04/14     DONE    DONE       DONE      01/29/14   01/29/14   12/19/13   03/26/13   4,7,8,9,10,155,15,16     261,600             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAFARGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-14-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
09-1301   Reconstruction               0-001-009  06/18/10     DONE    DONE       DONE      04/14/10   04/09/10   11/06/09   12/14/09   7,8,155,16             1,078,126     1,078,126  JOD             0           0           0 Bernier Carr Associates         1,078,126      07/02/12                       06/28/13         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERTOWN CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-20-00-01
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Elementary:
10-0413   Reconstruction               0-010-007  11/17/10     DONE    DONE       DONE      11/05/10   10/21/10     /  /     11/19/07   7                        185,000       185,000  HCM             0           0           0 Bernier Carr Associates                 0      08/11/11                         /  /             
11-0233   Reconstruction               0-010-008  08/09/11     DONE    DONE       DONE      10/06/11   10/04/11   08/16/11   08/02/11   2,7                      263,648       263,648  HCM             0           0           0 Bernier Carr Associates                 0      09/14/11                       09/14/11           
11-0837   Reconstruction               0-010-009  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   11/18/11   11/19/07   2,4,8,9,16               941,217       941,217  HCM             0           0     113,888 Bernier Carr Associates                 0      10/01/13                       02/19/14           

          Knickerbocker Elementary:
11-0838   Reconstruction               0-011-005  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   09/30/11   11/19/07   2,4                       78,635        78,635  HCM             0           0           0 Bernier Carr Associates                 0      10/01/13                       02/19/14           

          Sherman Elementary School:
11-0839   Reconstruction               0-012-006  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   09/30/11   11/19/07   2,9                      293,698       293,698  HCM             0           0           0 Bernier Carr Associates                 0      10/01/13                       02/19/14           

          Watertown High School:
11-0840   Reconstruction               0-015-009  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   09/30/11   11/19/07   2,8,9,155,16             712,488       712,488  HCM             0           0           0 Bernier Carr Associates                 0      10/01/13                       02/19/14           
  -       Reconstruction               0-015-010                                              /  /       /  /     09/29/14     /  /     4                              0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Ohio Street Elementary:
11-0841   Reconstruction               0-016-006  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   09/30/11   11/19/07   2,16                      36,159        36,159  HCM             0           0           0 Bernier Carr Associates                 0      10/01/13                       02/19/14           

          Starbuck Elementary School:
11-0842   Reconstruction               0-017-004  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   11/18/11   11/19/07   2,4                      106,914       106,914  HCM             0           0           0 Bernier Carr Associates                 0      10/01/13                       02/19/14           

          H.T.Wiley Elementary:
11-0843   Reconstruction               0-021-011  06/15/12     DONE    DONE       DONE      02/23/12   02/22/12   09/30/11   11/19/07   2,4,7,8,16               471,762       471,762  HCM             0           0           0 Bernier Carr Associates                 0      10/01/13                       02/19/14           

          Administration Building:
10-0346   Reconstruction               1-001-002  10/12/10     DONE    DONE       DONE      10/07/10   10/05/10     /  /     09/21/10   2                        650,000             0  HCM             0           0           0 Bernier Carr Associates                 0      07/13/11                         /  /             

          Field House:
  -       Reconstruction               7-004-002                                              /  /       /  /     09/29/14     /  /     4,7,8,9,155,15,16              0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CARTHAGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-22-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
09-1409XX Reconstruction               0-001-013  06/10/10               CANCELLED          05/10/10   04/27/10   02/18/10   05/06/06   13,16                    135,000       135,000  JOD             0           0           0 March Associates                        0        /  /                           /  /             
13-0284   Reconstruction               0-001-014  08/01/13     DONE    DONE       DONE      08/26/13   08/26/13   04/30/13   04/22/13   10,16                    422,400       422,400  MFS             0           0           0 SEI Design Group                        0      02/11/13                       02/28/14           

          Middle School:
12-1335   Reconstruction               0-002-006  06/19/13     DONE    DONE       DONE      06/27/13   06/27/13   04/30/13   04/22/13   10,16                    100,000       100,000  MFS             0           0           0 SEI Design Group                        0      11/21/13                       12/11/13           

          District-Wide:
13-1563   Reconstruction               7-999-002  07/01/14     DONE    DONE       DONE      05/23/14   05/20/14   03/24/14   05/21/13   8,16                     100,000             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             
13-1564   Reconstruction               7-999-003  07/01/14     DONE    DONE       DONE      05/23/14   05/21/14   05/16/14   05/21/14   8,10,16                  100,000             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES JEF-LEW-HAM-HERK-ONEIDA STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-90-00-00
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Voc Tech Center:
10-1111   Additions and Alterations    0-002-006  06/29/11     DONE    DONE       DONE      03/28/11   03/23/11   02/03/11   12/15/10   02 - 16                  181,955       181,955  JOD             0           0           0 Fourth Coast Inc.                       0      11/15/11                         /  /             

          Lewis County Extension:
12-1272TQ Temporary Quarters           8-020-001  08/06/13     DONE    DONE       DONE      06/11/13   06/11/13   04/12/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED