Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/22/17 at 08:53:13




SOUTH JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-01-01-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wilson Elementary:
  -       Reconstruction               0-001-009                                              /  /       /  /     06/02/17     /  /     2,4,9,155,15                   0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Clarke Jr/Sr High School:
14-0215   Reconstruction               0-005-006  04/23/15     DONE    DONE       DONE      08/22/14   08/22/14   05/30/14   12/04/07   8,9,155,15,16            917,053       917,053  JMB             0           0           0 Ashley McGraw                           0      08/28/15                       06/30/16           
16-0660   Reconstruction               0-005-007  11/07/16     DONE    DONE       DONE      10/25/16   10/24/16   08/22/16   05/17/16   16                       100,000       100,000  BMJ             0           0           0 Ashley McGraw                           0      05/19/17                       06/02/17           
16-0934   Reconstruction               0-005-008  01/12/17     DONE    DONE       DONE      12/08/16   12/08/16   11/08/16   12/04/07   2,9                       70,000        70,000  BMJ             0           0           0 Ashley McGraw                           0      06/29/17                       09/21/17           
  -       Reconstruction               0-005-009                                              /  /       /  /     06/02/17     /  /     2,4,9,10,155,15,16             0             0  BMJ             0           0           0                                         0        /  /                           /  /             
17-0764   Reconstruction               0-005-010                         UNREVIEWED         11/14/17   10/26/17   06/06/17   05/16/17   16                             0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Mannsville Elementary:
14-0216   Reconstruction               0-006-006  04/23/15     DONE    DONE       DONE      08/22/14   08/22/14   05/30/14   12/04/07   9,155                    252,000       252,000  JMB             0           0           0 Ashley McGraw                           0      08/28/16                       06/30/16           
  -       Reconstruction               0-006-007                                              /  /       /  /     06/02/17     /  /     2,8,9,155,15                   0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Storage Mannsville Manor:
  -       Reconstruction               4-008-002                                              /  /       /  /     06/02/17     /  /     7                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Adams Center Bus Garage:
14-0217   Reconstruction               5-002-006  04/23/15     DONE    DONE       DONE      08/22/14   08/22/14   05/30/14   12/04/07   155                       96,000        96,000  JMB             0           0           0 Ashley McGraw                           0      08/28/15                       06/30/16           
  -       Reconstruction               5-002-007                                              /  /       /  /     06/02/17     /  /     2,16                           0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Concession/Storage Building:
14-0499DB Discovered Building          7-011-001  09/09/15     DONE    DONE       DONE      10/21/14   10/17/14   09/26/14     /  /                                    0             0  JMB             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Storage Building #2:
14-0500DB Discovered Building          7-012-001  09/09/15     DONE    DONE       DONE      10/21/14   10/17/14   09/26/14     /  /                                    0             0  JMB             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ALEXANDRIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-02-02-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alexandria Central:
13-0106   Reconstruction               0-001-012  08/21/13     DONE    DONE       DONE      07/29/13   07/29/13   06/05/13   05/21/13   9,15,16                  100,000       100,000  DDJ             0           0           0 King & King Architects                  0      01/15/14                       03/21/14           
13-1621   Reconstruction               0-001-013  06/27/14     DONE    DONE       DONE      06/18/14   06/13/14   04/25/14   05/20/14   9,15,16                  100,000       100,000  DDJ             0           0           0 King & King Architects                  0      01/15/15                       06/01/15           
15-0006   Reconstruction               0-001-014  05/10/16     DONE    DONE       DONE      07/02/15   07/01/15   01/08/15   12/17/14   2,8,9,10,14,155,15,1   5,610,000     5,610,000  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             
15-1361   Reconstruction               0-001-015  02/02/16     DONE    DONE       DONE      03/04/16   03/02/16   01/29/16   02/02/16   9,155,15,16              380,000       380,000  DDJ             0           0           0 King & King Architects                  0      07/15/17                       11/15/17           
  -       Reconstruction               0-001-016                                              /  /       /  /     06/05/17     /  /     2,8,9,155,15,16                0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage/Agriculture Clrm:
15-0005   Reconstruction               0-004-004  05/10/16     DONE    DONE       DONE      07/02/15   07/01/15   01/08/15   12/17/14   2,8,9,15,16              590,000       590,000  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             

          Greenhouse:
16-0312   Reconstruction               0-005-002  09/12/16     DONE    DONE       DONE      08/24/16   08/24/16   07/27/16   05/17/16   155,16                    50,000        50,000  DDJ             0           0           0 King & King Architects                  0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1284SB Reconstruction               7-999-001                                              /  /       /  /     02/24/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




INDIAN RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-03-01-06
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Antwerp Primary School:
13-1579   Reconstruction               0-001-012  03/25/15     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,8,9,13,15,16           378,890       378,890  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          Evans Mills Primary School:
14-0299   Additions and Alterations    0-004-015  06/29/15     DONE    DONE       DONE      09/15/14   09/10/14   11/21/13   01/22/14   02 - 16                5,542,248     4,357,340  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          Philadelphia Primary School:
13-1580   Reconstruction               0-005-013  03/25/15     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,4,9,16                 244,321       244,321  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          Indian River High School:
14-0547   Additions and Alterations    0-007-016  11/24/15     DONE    DONE       DONE      10/28/14   10/27/14   11/21/13   01/22/14   02 - 16               14,678,954    14,412,719  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Theresa Primary School:
13-1581   Reconstruction               0-008-011  03/25/15     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,4,9,16                 276,984       276,984  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          Indian River Middle 5-8):
14-0548   Additions and Alterations    0-010-012  11/24/15     DONE    DONE       DONE      10/28/14   10/27/14   11/21/13   01/22/14   02 - 16                8,165,142     6,958,748  MFS             0           0           0 March Associates                        0        /  /                           /  /             

          Calcium Primary School:
13-1582   Reconstruction               0-027-009  03/25/15     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,9,13,15,16             151,301       151,301  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          New Grade 4-5 Building:
14-0300   Additions and Alterations    0-032-003  06/29/15     DONE    DONE       DONE      09/15/14   09/10/14   11/21/13   01/22/14   02 - 16                3,418,242       881,129  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          Toilet/Storage Building:
14-0549   New Construction             2-044-001  11/24/15     DONE    DONE       DONE      10/28/14   10/27/14   03/27/14   01/22/14   02 - 16                  943,341             0  MFS             0           0           0 March Associates                        0      02/28/17                       05/02/17           

          XXMaintenance Center (see 3-002):
13-1583   Reconstruction               5-002-006  03/25/15     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   2,4,8,16                 117,196       117,196  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          New Transportation Facility:
13-1584   Reconstruction               5-031-005  03/25/15     DONE    DONE       DONE      05/27/14   05/23/14   11/21/13   01/22/14   4,9,13,155,16            252,177       252,177  MFS             0           0           0 March Associates                        0      12/30/16                       05/17/17           

          Press Box @ HS:
15-0744   New Construction             7-045-001  11/24/15     DONE    DONE       DONE      11/19/15   11/12/15   02/10/15   01/22/14   02 - 16                  131,019             0  MFS             0           0           0 March Associates                        0      10/07/16                       11/07/17           

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     13,16                          0             0  SLC             0           0           0                                         0        /  /                           /  /             
16-0622SB Reconstruction               7-999-001               DONE                           /  /       /  /     10/14/16     /  /     13,16                          0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENERAL BROWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-04-01-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Brownville-Glen Park Elementary:
14-1447   Reconstruction               0-001-006  06/30/16     DONE    DONE       DONE      04/28/15   04/22/15   03/04/15   12/08/14   7,8,155,16               373,425       373,425  JMB             0           0           0 Bernier Carr Associates           373,425      03/02/17                       03/08/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-0330   Reconstruction               0-001-007                         UNREVIEWED         09/01/17   09/01/17   11/14/16   02/13/17   2,7,10,15                      0     5,407,200  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Dexter Elementary:
14-1448   Reconstruction               0-002-005  06/30/16     DONE    DONE       DONE      04/28/15   04/22/15   03/04/15   12/08/14   7,8,155,16               959,814       959,814  JMB             0           0           0 Bernier Carr Associates           959,814      03/02/17                       03/08/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-0331   Reconstruction               0-002-006                         UNREVIEWED         09/01/17   09/01/17   11/14/16   02/13/17   10                             0     5,407,200  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          High School:
14-1449   Reconstruction               0-003-005  06/30/16     DONE    DONE       DONE      04/28/15   04/22/15   03/04/15   12/08/14   7,8,155,16               545,996       545,996  JMB             0           0           0 Bernier Carr Associates           545,996      03/02/17                       03/08/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-0332   Reconstruction               0-003-006                         UNREVIEWED         09/01/17   09/01/17   11/14/16   02/13/17   2,7                            0    22,451,833  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage:
14-1450   Reconstruction               5-004-005  06/30/16     DONE    DONE       DONE      04/28/15   04/22/15   03/04/15   12/08/14   7,8                       36,850        36,850  JMB             0           0           0 Bernier Carr Associates            36,850      03/02/17                       03/08/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-0333   Reconstruction               5-004-006                         UNREVIEWED         09/01/17   09/01/17   11/14/16   02/13/17   2,7,13,15                      0             0  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          District-Wide:
15-1543SB Reconstruction               7-999-001               DONE                           /  /       /  /     04/09/16     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-0909   Reconstruction               7-999-001  05/04/17     DONE    DONE       DONE      12/01/16   12/01/16     /  /     11/04/14   13,16                  1,256,750             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




THOUSAND ISLANDS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-07-01-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Guardino Elem. (fmly Clayton):
14-0002   Reconstruction               0-003-006  12/03/14     DONE    DONE       DONE      07/03/14   07/01/14   01/16/14   12/10/10   2,4,8,9,13,155,15,16     750,000       750,000  MFS             0           0           0 Ashley McGraw                           0      10/31/15                       07/12/17           
13-1312   Reconstruction               0-003-007  08/20/14     DONE    DONE       DONE      03/07/14   03/05/14   01/24/14   12/10/13   15                        75,000        75,000  MFS             0           0           0 Ashley McGraw                           0      10/31/15                       07/12/17           
15-0822   Reconstruction               0-003-008  12/15/15     DONE    DONE       DONE      12/03/15   12/02/15   11/02/15   05/19/15   9                        100,000       100,000  MFS             0           0           0 Ashley McGraw                           0      05/02/16                       06/15/16           
16-2149   Reconstruction               0-003-009               DONE    DONE       UNREVIEWED06/28/17   06/28/17   01/26/17   12/13/16   4,155,15,16                    0     9,747,300  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             
17-0719   Reconstruction               0-003-010               STARTED DONE       DONE      11/07/17   10/27/17   07/18/17   07/05/17   4                              0     9,847,758  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             
17-0801   Reconstruction               0-003-011                         UNREVIEWED         11/20/17   11/17/17   07/18/17   05/16/17   2,16                           0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Cape Vincent Elem:
14-0003   Reconstruction               0-005-006  12/03/14     DONE    DONE       DONE      07/03/14   07/01/14   01/16/14   12/13/10   2,8,9,13,155,15,16       512,700       512,700  MFS             0           0           0 Ashley McGraw                           0      10/31/15                       07/12/17           
13-1313   Reconstruction               0-005-007  08/20/14     DONE    DONE       DONE      03/07/14   03/05/14   01/24/14   12/10/13   15                        75,000        75,000  MFS             0           0           0 Ashley McGraw                           0      10/31/15                       07/12/17           
16-2150   Reconstruction               0-005-008               DONE    DONE       UNREVIEWED06/28/17   06/28/17   01/26/17   12/13/16   4,15,16                        0     2,060,520  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Middle School/High School:
13-0207   Reconstruction               0-011-012  01/14/14     DONE    DONE       DONE      08/14/13   08/14/13   06/18/13   05/21/13   155                      100,000       100,000  MFS             0           0           0 Ashley McGraw                           0      06/30/14                       07/28/14           
14-0004   Reconstruction               0-011-013  12/03/14     DONE    DONE       DONE      07/03/14   07/01/14   01/16/14   12/13/10   2,4,8,9,10,13,155,15   2,227,000     2,227,000  MFS             0           0           0 Ashley McGraw                           0        /  /                           /  /             
14-0423   Reconstruction               0-011-014  11/04/14     DONE    DONE       DONE      11/04/14   11/04/14   08/26/14   05/20/14   9,10                     100,000       100,000  MFS             0           0           0 Ashley McGraw                           0      04/30/15                       06/11/15           
16-0662   Reconstruction               0-011-015  11/07/16     DONE    DONE       DONE      10/25/16   10/25/16   06/08/16   05/17/16   9                        100,000       100,000  MFS             0           0           0 Ashley McGraw                           0      05/22/17                       06/30/17           
16-2151   Reconstruction               0-011-016               DONE    DONE       UNREVIEWED06/28/17   06/28/17   01/26/17   12/13/16   2,7,8,155,15,16                0    15,102,516  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Storage Building -Clayton:
14-0005   Additions and Alterations    2-012-002  12/03/14     DONE    DONE       DONE      07/03/14   07/01/14   01/16/14   12/13/10   02 - 16                1,052,500             0  MFS             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Bus Garage/Clayton:
14-0006   Reconstruction               5-001-008  12/03/14     DONE    DONE       DONE      07/03/14   07/01/14   01/16/14   12/13/10   16                        28,900        28,900  MFS             0           0           0 Ashley McGraw                           0      10/31/15                       07/12/17           
16-1515   Reconstruction               5-001-009               DONE    DONE       ADD. REQ'D03/16/17   03/16/17   06/08/16   06/21/16   14,155,15,16                   0             0  MFS             0           0           0 Ashley McGraw                           0        /  /                           /  /             
  -       Reconstruction               5-001-010                                              /  /       /  /     01/26/17     /  /     15,16                          0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage @ Cape Vincent:
14-0007   Reconstruction               5-004-006  12/03/14     DONE    DONE       DONE      07/03/14   07/01/14   01/16/14   12/13/10   16                        28,900        28,900  MFS             0           0           0 Ashley McGraw                           0      10/31/15                       07/12/17           

          Concession Building:
16-2152   New Construction             7-015-001               DONE    DONE       UNREVIEWED06/28/17   06/28/17   01/30/17   12/13/16   02 - 16                        0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             

          Press Box @ HS/MS:
16-2153   New Construction             7-016-001               DONE    DONE       UNREVIEWED06/28/17   06/28/17   05/17/17   12/13/16   02 - 16                        0             0  BMJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BELLEVILLE HENDERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-09-09-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 School:
14-1289   Reconstruction               0-010-007  04/30/15     DONE    DONE       DONE      03/18/15   03/17/15   08/14/14   02/11/15   2,9,10,155,16            900,000       900,000  DDJ             0           0           0 AUBERTINE AND CURRIER ARCHITE           0      05/13/16                       06/06/16           
15-0344   Reconstruction               0-010-008  03/10/16     DONE    DONE       DONE      08/24/15   08/21/15   08/14/14   02/11/15   2,9                    1,322,000     1,322,000  DDJ             0           0           0 AUBERTINE AND CURRIER ARCHITE           0      11/15/16                       08/16/17           
15-1688SB Reconstruction               0-010-008               DONE                           /  /       /  /     05/05/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-010-009                                              /  /       /  /     08/31/17     /  /     2,13,155,15,16                 0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Bus Garage-Belleville:
14-1290   Reconstruction               5-004-002  04/30/15     DONE    DONE       DONE      03/18/15   03/17/15   11/18/10   02/11/15   2,9,15                   541,000       541,000  DDJ             0           0           0 AUBERTINE AND CURRIER ARCHITE           0      10/08/15                       10/19/15           
15-0345   Reconstruction               5-004-003  03/10/16     DONE    DONE       DONE      08/24/15   08/21/15   08/20/15   02/11/15   155,16                    80,100        80,100  DDJ             0           0           0 AUBERTINE AND CURRIER ARCHITE           0      11/15/16                       08/16/17           
  -       Reconstruction               5-004-004                                              /  /       /  /     08/31/17     /  /     2,7,155,15,16                  0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    XX Reconstruction               7-999-BA1                         CANCELLED            /  /       /  /       /  /       /  /     13,16                          0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SACKETS HARBOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-10-01-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building K-12:
17-0313   Reconstruction               0-001-009  10/25/17     DONE    DONE       DONE      08/29/17   08/29/17   08/18/17   05/16/17   7,8,9                  2,710,762     2,710,762  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0379   Reconstruction               0-001-010                         UNREVIEWED         09/12/17   09/11/17   09/05/17   05/16/17   2,4,9,10,14,155,15,1           0    17,054,162  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage:
17-0314   Reconstruction               5-002-003  10/25/17     DONE    DONE       DONE      08/29/17   08/29/17   08/18/17   05/16/17   4,7                      229,120       229,120  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0380   Reconstruction               5-002-004                         UNREVIEWED         09/12/17   09/11/17   09/05/17   05/16/17   4,155,16                       0             0  MTM             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LYME CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-13-01-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
12-1211   Reconstruction               0-002-007  05/24/13     DONE    DONE       DONE      05/21/13   05/16/13   02/05/13   03/26/13   2,4,7,10                 875,800       875,800  JOB             0           0           0 Bernier Carr Associates                 0      10/24/13                       11/12/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-1148   Reconstruction               0-002-008  08/04/14     DONE    DONE       DONE      01/29/14   01/29/14   12/19/13   03/26/13   4,7,8,9,10,155,15,16     261,600       261,600  JMB             0           0           0 Bernier Carr Associates                 0      04/15/16                       06/07/16         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAFARGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-14-01-04
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
17-0010   Reconstruction               0-001-010                         UNREVIEWED         07/05/17   07/03/17   02/07/17   05/16/17   2,16                           0    19,537,895  BMJ             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0493   Reconstruction               0-001-011  10/05/17     DONE    DONE       DONE      10/02/17   09/27/17   06/19/17   06/23/17   2                        100,000             0  BMJ             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          District-Wide:
16-0298SB Reconstruction               7-999-001               DONE                           /  /       /  /       /  /       /  /     4,8,9,155,16                   0             0  AAA             0           0           0                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0011   Reconstruction               7-999-001               DONE    DONE       UNREVIEWED07/05/17   07/03/17   08/22/16   11/04/14   4,8,9,155,16                   0             0  AAA             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERTOWN CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-20-00-01
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Elementary:
15-0118   Reconstruction               0-010-010  05/27/16     DONE    DONE       DONE      07/21/15   07/21/15   06/18/15   09/23/14   4,155,16                 733,562       733,562  JMB             0           0     119,570 Bernier Carr Associates                 0        /  /                           /  /             

          Knickerbocker Elementary:
15-0119   Reconstruction               0-011-006  05/27/16     DONE    DONE       DONE      07/21/15   07/21/15   06/18/15   09/23/14   7,8,155,15,16            938,307       938,307  JMB             0           0     152,944 Bernier Carr Associates                 0        /  /                           /  /             

          Sherman Elementary School:
15-0120   Reconstruction               0-012-007  05/27/16     DONE    DONE       DONE      07/21/15   07/21/15   06/18/15   09/23/14   4,16                     772,791       772,791  JMB             0           0     125,964 Bernier Carr Associates                 0        /  /                           /  /             

          Watertown High School:
14-0984   Reconstruction               0-015-010  02/04/16     DONE    DONE       DONE      01/21/15   01/21/15   09/29/14   09/23/14   4                         29,500        29,500  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
15-0121   Reconstruction               0-015-011  05/27/16     DONE    DONE       DONE      07/21/15   07/21/15   06/18/15   09/23/14   4,7,8,155,15,16        4,115,640     4,115,640  JMB             0           0     670,849 Bernier Carr Associates                 0        /  /                           /  /             

          Ohio Street Elementary:
15-0122   Reconstruction               0-016-007  05/27/16     DONE    DONE       DONE      07/21/15   07/21/15     /  /     09/23/14   7,8,16                   460,894       460,894  JMB             0           0      75,125 Bernier Carr Associates                 0        /  /                           /  /             

          Wiley Intermediate School:
15-0123   Reconstruction               0-021-012  05/27/16     DONE    DONE       DONE      07/21/15   07/21/15   06/18/15   09/23/14   7,8,155,16             2,065,662     2,065,662  JMB             0           0     336,702 Bernier Carr Associates                 0        /  /                           /  /             

          New Middle School:
16-0987   Reconstruction               0-023-003  09/25/17     DONE    DONE       DONE      12/16/16   12/16/16   12/05/16   09/23/14   7                      1,939,242             0  MTM             0           0     241,077 Bernier Carr Associates                 0        /  /                           /  /             

          District Learning Center:
15-1662DB Discovered Building          0-030-001  08/24/16     DONE    DONE       DONE      05/03/16   05/02/16   12/16/14     /  /                                    0             0  JMB             0           0           0 BCAArchitects&Engineers                 0        /  /                           /  /             

          Storage Bldg. #3:
14-0985   New Construction             2-026-001  02/04/16     DONE    DONE       DONE      01/21/15   01/21/15   12/03/14   09/23/14   02 - 16                  410,850             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          :
  -       New Construction             2-027-001                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Garage #1 - Watertown City Schl Dist:
15-1663DB Discovered Building          2-028-001  08/24/16     DONE    DONE       DONE      05/03/16   05/02/16   12/16/14     /  /                                    0             0  JMB             0           0           0 BCAArchites&Engineers                   0        /  /                           /  /             

          Garage #2 - Watertown City Schl Dist:
15-1664DB Discovered Building          2-029-001  08/24/16     DONE    DONE       DONE      05/03/16   05/02/16   12/16/14     /  /                                    0             0  JMB             0           0           0 BCAArchitects&Engineers                 0        /  /                           /  /             

          Field House:
  -       Reconstruction               7-004-002                                              /  /       /  /     09/29/14     /  /     4,7,8,9,155,15,16              0             0  JMB             0           0           0                                         0        /  /                           /  /             
14-0986   Reconstruction               7-004-003  02/04/16     DONE    DONE       DONE      01/21/15   01/21/15   12/02/14   09/23/14   2,8,16                    59,500             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Press Box:
14-0987   New Construction             7-027-001  02/04/16     DONE    DONE       DONE      01/21/15   01/21/15   12/03/14   09/23/14   02 - 16                  132,000             0  JMB             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CARTHAGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-22-01-06
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
13-0284   Reconstruction               0-001-014  08/01/13     DONE    DONE       DONE      08/26/13   08/26/13   04/30/13   04/22/13   10,16                    422,400       422,400  MFS             0           0           0                                         0      02/11/13                       02/28/14           
15-0463   Reconstruction               0-001-015  05/20/16     DONE    DONE       DONE      09/17/15   09/16/15   02/23/15   01/20/15   2,4,7,8,9,14,155,15,   4,052,835     4,052,835  MFS             0           0           0                                         0        /  /                           /  /             
16-0753   Reconstruction               0-001-016  01/12/17     DONE    DONE       DONE      11/10/16   11/09/16   10/01/16   05/17/16   9                        100,000       100,000  BMJ             0           0           0 BCAArchitects&Engineers                 0      06/20/17                       08/01/17           
16-1766   Reconstruction               0-001-017  05/26/17     DONE    DONE       DONE      05/02/17   05/02/17   05/01/17   05/16/17   9                        100,000       100,000  BMJ             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             

          Middle School:
12-1335   Reconstruction               0-002-006  06/19/13     DONE    DONE       DONE      06/27/13   06/27/13   04/30/13   04/22/13   10,16                    100,000       100,000  MFS             0           0           0                                         0      11/21/13                       12/11/13           
15-0464   Reconstruction               0-002-007  05/20/16     DONE    DONE       DONE      09/17/15   09/16/15   02/23/15   01/20/15   2,4,7,8,9,155,15,16      905,190       905,190  MFS             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-002-008                         CANCELLED            /  /       /  /     10/01/16     /  /     9                              0    25,022,085  BMJ             0           0           0                                         0        /  /                           /  /             

          Black River Elementary:
15-0465   Reconstruction               0-003-007  05/20/16     DONE    DONE       DONE      09/17/15   09/16/15   02/23/15   01/20/15   2,4,7,8,9,155,15,16    2,622,860     2,622,860  MFS             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-003-008                         CANCELLED            /  /       /  /     10/01/16     /  /     9                              0     4,702,380  BMJ             0           0           0                                         0        /  /                           /  /             

          West Carthage Elementary:
15-0466   Reconstruction               0-004-004  05/20/16     DONE    DONE       DONE      09/17/15   09/16/15   02/23/15   01/20/15   2,7,8,9,155,15,16        702,309       702,309  MFS             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-004-005                         CANCELLED            /  /       /  /     10/01/16     /  /     9                              0     4,702,380  BMJ             0           0           0                                         0        /  /                           /  /             

          Carthage Elementary:
15-0467   Reconstruction               0-012-007  05/20/16     DONE    DONE       DONE      09/17/15   09/16/15   02/23/15   01/20/15   2,4,7,8,9,155,15,16    1,779,956     1,779,956  MFS             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-012-008                         CANCELLED            /  /       /  /     10/01/16     /  /     9                              0     9,898,380  BMJ             0           0           0                                         0        /  /                           /  /             

          Storage Building @ Transp. Dept.:
  -       New Construction             2-019-001                                              /  /       /  /     04/26/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
15-0468   Reconstruction               5-005-004  05/20/16     DONE    DONE       DONE      09/17/15   09/16/15   02/23/15   01/20/15   2,4,7,9                  564,850       564,850  MFS             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               5-005-005                         CANCELLED            /  /       /  /     10/01/16     /  /     9                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
13-1563   Reconstruction               7-999-002  07/01/14     DONE    DONE       DONE      05/23/14   05/20/14   03/24/14   05/21/13   8,16                     100,000       100,000  MFS             0           0           0                                         0        /  /                           /  /             
13-1564   Reconstruction               7-999-003  07/01/14     DONE    DONE       DONE      05/23/14   05/21/14   05/16/14   05/21/14   8,10,16                  100,000       100,000  MFS             0           0           0                                         0        /  /                           /  /             
14-1319   Reconstruction               7-999-004  04/15/15     DONE    DONE       DONE      03/25/15   03/24/15   02/23/15   11/17/14   10,16                  1,352,000     1,352,000  MFS             0           0           0                                         0      03/16/17                       06/12/17           
15-0898   Reconstruction               7-999-005  03/28/16     DONE    DONE       DONE      12/17/15   12/16/15   08/19/15   08/03/15   10,16                    100,000       100,000  MFS             0           0           0                                         0      06/22/16                       11/09/16           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES JEF-LEW-HAM-HERK-ONEIDA STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-90-00-00
last updated on 11/22/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Storage Barn:
  -       New Construction             2-022-001                                              /  /       /  /     09/13/17     /  /     02 - 16                        0             0  MTM             0           0           0                                         0        /  /                           /  /             

          K-Solar PPA Array-Ground Mounted:
16-0504   Reconstruction               7-021-001  09/27/16     DONE    DONE       DONE      09/27/16   09/27/16   09/08/15     /  /     2,13,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Lewis County Extension:
12-1272TQ Temporary Quarters           8-020-001  08/06/13     DONE    DONE       DONE      06/11/13   06/11/13   04/12/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED