Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 08/28/15 at 09:37:24




AVON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-01-01-04
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Primary School:
10-0137   Reconstruction               0-001-013  11/29/10     DONE    DONE       DONE      08/20/10   08/10/10   09/09/09   12/01/09   155,15,16                265,644       265,644  JOD             0           0      31,121 Hunt Engineers & Architects &           0      08/18/11                       12/08/11           
14-0059   Reconstruction               0-001-014  03/16/15     DONE    DONE       DONE      07/25/14   07/21/14   04/01/14   01/21/14   2,9,155,16               808,306             0  MFS             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Jr/Sr High School:
10-0138   Reconstruction               0-002-014  11/29/10     DONE    DONE       DONE      08/20/10   08/10/10   09/09/09   12/01/09   13,15,16                 264,966       264,966  JOD             0           0       9,671 Hunt Engineers & Architects &           0      08/31/11                       12/08/11           
12-0211   Reconstruction               0-002-015  02/20/13     DONE    DONE       DONE      09/25/12   09/25/12   09/04/12   05/15/12   9,10,155,15,16           600,000       600,000  DDJ             0           0       7,305 Hunt Engineers & Architects &           0      10/12/14                       11/12/14           
14-0060   Reconstruction               0-002-016  03/16/15     DONE    DONE       DONE      07/25/14   07/21/14   04/01/14   01/21/14   2,4,7,8,9,10,155,15,   9,756,694     9,756,694  MFS             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Track Storage Facility:
14-0272   New Construction             2-012-001  03/16/15     DONE    DONE       DONE      09/10/14   09/09/14   06/25/14     /  /     02 - 16                   50,000             0  MFS             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          New Bus Maint. Facility:
11-0152   Reconstruction               5-010-004  11/18/11     DONE    DONE       DONE      09/01/11   08/31/11     /  /     05/17/11   15,16                     95,000        95,000  JOD             0           0           0 Hunt Engineers & Architects &           0      06/27/12                       09/27/12           

          Solar Array Electrical Building:
14-1325   New Construction             7-013-001                         UNREVIEWED         03/25/15   03/25/15   10/01/14     /  /     02 - 16                        0             0  MFS             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CALEDONIA MUMFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-02-01-04
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
12-1213   Reconstruction               0-001-007  05/29/13     DONE    DONE       DONE      05/23/13   05/16/13   02/15/13   05/21/13   8,16                      70,000        70,000  JOB             0           0           0 Hunt Engineers & Architects &           0      09/09/13                       11/21/13           
14-1646   Reconstruction               0-001-008               DONE    DONE       UNREVIEWED06/12/15   06/11/15   04/08/14   10/14/14   2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
14-1488   Reconstruction               0-001-009  05/21/15     DONE    DONE       DONE      05/06/15   05/06/15   12/04/14   05/19/15   8,16                     100,000             0  DDJ             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Elementary School:
12-1214XX Reconstruction               0-003-009  05/29/13               CANCELLED          05/23/13   05/16/13   02/15/13   05/21/13   8,16                      30,000        30,000  JOB             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             
14-1647   Reconstruction               0-003-010               DONE    DONE       UNREVIEWED06/12/15   06/11/15   04/08/14   10/14/14   2,4,7,8,9,10,15,16             0    13,241,625  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          District Office:
14-1648   Reconstruction               1-002-005               DONE    DONE       UNREVIEWED06/12/15   06/11/15   04/08/14   10/14/14   7,10                           0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          New Bus Garage:
14-1649   Reconstruction               5-006-004               DONE    DONE       UNREVIEWED06/12/15   06/11/15   04/08/14   10/14/14   10,16                          0             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Dugout-Baseball #1:
15-0354   New Construction             7-015-001               DONE    DONE       UNREVIEWED08/27/15   08/26/15   07/24/15   10/14/14   02 - 16                        0             0  DDJ             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Dugout-Baseball #2:
15-0355   New Construction             7-016-001               DONE    DONE       UNREVIEWED08/27/15   08/26/15   07/24/15   10/14/14   02 - 16                        0             0  DDJ             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Dugout-Softball #1:
15-0356   New Construction             7-017-001               DONE    DONE       UNREVIEWED08/27/15   08/26/15   07/24/15   10/14/14   02 - 16                        0             0  DDJ             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Dugout-Softball #2:
15-0357   New Construction             7-018-001               DONE    DONE       UNREVIEWED08/27/15   08/26/15   07/24/15   10/14/14   02 - 16                        0             0  DDJ             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENESEO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-04-01-04
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-0861   Reconstruction               0-005-016  04/26/11     DONE    DONE       DONE      02/16/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,10,155,15,   3,385,870     3,385,870  HCM             0           0           0 Mosaic Associates                       0      01/04/12                       01/09/14         YES
                                                                                                                                                                                                                                                                                                                                   
11-0018   Reconstruction               0-005-017  11/04/11     DONE    DONE       DONE      07/14/11   07/14/11   03/24/11   10/07/10   2,4,7,8,9,10,155,15,   7,800,000     7,800,000  HCM             0           0           0 Mosaic Associates                       0      08/30/13                       10/07/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Field House Stor:
11-0019   Reconstruction               2-003-002  11/04/11     DONE    DONE       DONE      07/14/11   07/14/11   12/19/07   10/07/10   2,4,7,8,9,155,15,16      200,000             0  MGL             0           0           0 Mosaic Associates                       0      01/04/12                       01/17/14           

          Bus Garage Storage:
10-0862   Reconstruction               4-002-001  04/26/11     DONE    DONE       DONE      02/15/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,16              42,277        42,277  HCM             0           0           0 Mosaic Associates                       0      01/04/12                       01/09/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage Maint:
10-0863   Reconstruction               5-001-002  04/26/11     DONE    DONE       DONE      02/16/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,155,15,16      119,500       119,500  HCM             0           0           0 Mosaic Associates                       0      01/04/12                       01/09/14         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               5-001-003                                              /  /       /  /     03/24/11     /  /     2,4,7,8,9,15,16                0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Transportation Facility:
  -       New Construction             5-010-001                                              /  /       /  /     01/14/15     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LIVONIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-08-01-06
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Connell Bldg (frmrly Intermed.Sch):
11-0461   Reconstruction               0-001-009  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   11/10/10   10/20/11   7                         18,869        18,869  DDJ             0           0       3,188 Gordon W. Jones Associates              0      04/26/13                       05/06/13           
14-1463   Reconstruction               0-001-010               DONE    DONE       UNREVIEWED05/01/15   04/30/15   09/02/14   01/12/15   155,16                         0             0  DDJ             0           0           0 M/E Engineering                         0        /  /                           /  /             

          Livonia Elementary:
11-0462   Reconstruction               0-002-007  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   10/01/09   10/20/11   2,4,7,8                1,970,602     1,970,602  DDJ             0           0     219,063 Gordon W. Jones Associates              0      04/26/13                       05/06/13           
11-0728   Reconstruction               0-002-008  05/31/12     DONE    DONE       DONE      01/30/12   01/20/12   10/01/09   10/20/11   2,9,10,155,15,16          61,994        61,994  DDJ             0           0           0 Gordon W. Jones Associates              0      11/15/13                       11/18/13           
13-0778   Reconstruction               0-002-009  04/01/14     DONE    DONE       DONE      11/27/13   11/22/13   10/03/13   10/20/11   10,16                     30,844             0  DDJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
14-1464   Reconstruction               0-002-010               DONE    DONE       UNREVIEWED05/01/15   04/30/15   09/02/14   01/12/15   155,16                         0             0  DDJ             0           0           0 M/E Engineering                         0        /  /                           /  /             

          Livonia MS/HS(frmrly High School):
11-0463   Reconstruction               0-007-007  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   10/01/09   10/20/11   7                         95,694        95,694  DDJ             0           0      16,172 Gordon W. Jones Associates              0      04/26/13                       05/06/13           
11-0729   Reconstruction               0-007-008  05/31/12     DONE    DONE       DONE      01/30/12   01/20/12   10/01/09   10/20/11   2,9,10,155,15,16       1,194,691     1,194,691  DDJ             0           0           0 Gordon W. Jones Associates              0      11/15/13                       11/18/13           
13-0779   Reconstruction               0-007-009  04/01/14     DONE    DONE       DONE      11/27/13   11/22/13   10/03/13   10/20/13   2,16                     286,125       286,125  DDJ             0           0           0 Gordon W. Jones Associates              0      06/01/15                       06/25/15           
14-1465   Reconstruction               0-007-010               DONE    DONE       UNREVIEWED05/01/15   04/30/15   09/02/14   01/12/15   155,16                         0             0  DDJ             0           0           0 M/E Engineering                         0        /  /                           /  /             

          Gym/Locker Facility @ High School:
  -    XX Reconstruction               0-008-004                         CANCELLED            /  /       /  /     11/10/10     /  /     9,15                           0       550,440  DDJ             0           0           0                                         0        /  /                           /  /             
14-1466   Reconstruction               0-008-005               DONE    DONE       UNREVIEWED05/01/15   04/30/15   09/02/14   01/12/15   155,16                         0             0  DDJ             0           0           0 M/E Engineering                         0        /  /                           /  /             

          Bus Garage:
14-1467   Reconstruction               5-009-002               DONE    DONE       UNREVIEWED05/01/15   04/30/15   01/28/15   01/12/15   155,16                         0             0  DDJ             0           0           0 M/E Engineering                         0        /  /                           /  /             

          ~TA Transporation Facility:
  -    XX Reconstruction               5-010-001                         CANCELLED            /  /       /  /     09/02/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0091   Reconstruction               5-010-L02  07/30/12     DONE    DONE       DONE      08/08/12   07/10/12     /  /     05/15/12                            435,000       435,000  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MOUNT MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-09-01-04
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Mt Morris Central:
14-0077   Reconstruction               0-001-010  07/31/14     DONE    DONE       DONE      07/29/14   07/25/14   03/26/10   05/20/14   4,8,9,10,155,15,16       100,000       100,000  JOD             0           0           0 SEI Design Group                        0      06/29/15                       06/29/15         YES
                                                                                                                                                                                                                                                                                                                                   
14-0103   Reconstruction               0-001-011  03/26/15     DONE    DONE       DONE      08/06/14   08/04/14   11/13/13   12/17/13   2,4,7,8,9,155,15,16    3,900,000             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0078   Reconstruction               0-001-012  08/01/14     DONE    DONE       DONE      07/29/14   07/25/14   07/09/14   12/17/13   155,16                   100,000       100,000  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-013                                              /  /       /  /     05/13/15     /  /     8,155                          0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DANSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-10-01-06
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ellis B Hyde Elementary:
10-0592   Reconstruction               0-001-010  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/20/10   05/18/10   2,155,16                 108,613       108,613  JOD             0           0     108,613 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
10-0612   Reconstruction               0-001-011  05/12/11     DONE    DONE       DONE      12/23/10   12/10/10   11/18/10   01/30/07   2,155,16                  53,458        53,458  JOD             0           0           0 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
12-1297   Reconstruction               0-001-012  07/09/13     DONE    DONE       DONE      06/18/13   06/18/13   03/14/13   12/17/12   2,4,8,9,16               222,969       222,969  DDJ             0           0           0 LaBella Associates, P.C.                0      09/11/14                       06/01/15           
13-0610   Reconstruction               0-001-013  04/09/14     DONE    DONE       DONE      10/23/13   10/18/13   03/14/13   12/17/12   2,4,8,9,155,15,16        746,915             0  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             

          Dansville Senior High School:
10-0593   Reconstruction               0-003-009  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/21/10   05/18/10   155,16                   123,931       123,931  JOD             0           0     123,931 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
10-0613   Reconstruction               0-003-010  05/12/11     DONE    DONE       DONE      12/23/10   12/10/10   11/18/10   01/30/07   155,16                   255,071       255,071  JOD             0           0           0 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
11-0008   Reconstruction               0-003-011  07/19/11     DONE    DONE       DONE      07/08/11   07/07/11   05/02/11   05/03/11   2,7                      462,575       462,575  JOD             0           0           0 Hunt Engineers,Architects & l           0      09/26/11                       07/12/13           
  -       Reconstruction               0-003-012                                              /  /       /  /     05/19/11     /  /     7,155,16                       0    19,060,081  JOD             0           0           0                                         0        /  /                           /  /             
12-1298   Reconstruction               0-003-013  07/09/13     DONE    DONE       DONE      06/18/13   06/18/13   03/14/13   12/17/12   2,4,8,9,16               613,160       613,160  DDJ             0           0           0 LaBella Associates, P.C.                0      08/06/14                       06/01/15           
13-0611   Reconstruction               0-003-014  04/09/14     DONE    DONE       DONE      10/23/13   10/18/13   03/14/13   12/17/12   2,4,8,9,155,15,16      2,054,016             0  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             

          Middle School:
10-0594XX Reconstruction               0-004-011  05/12/11               CANCELLED          12/21/10   12/10/10   10/20/10   05/18/10   9,155,16                 123,848       123,848  JOD             0           0     123,848 Hunt Engineers,Architects & l           0        /  /                           /  /             
10-0635XX Reconstruction               0-004-012  05/12/11               CANCELLED          12/28/10   12/10/10   12/28/10   01/30/07   9,155,16                  45,283        45,283  JOD             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Primary School:
10-0595   Reconstruction               0-005-008  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/21/10   05/18/10   16                        17,184        17,184  JOD             0           0      17,184 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
12-1299   Reconstruction               0-005-009  07/09/13     DONE    DONE       DONE      06/18/13   06/18/13   03/14/13   12/17/12   2,4,8,9,16               278,711       278,711  DDJ             0           0           0 LaBella Associates, P.C.                0      09/11/14                       06/04/15           
13-0612   Reconstruction               0-005-010  04/09/14     DONE    DONE       DONE      10/23/13   10/18/13   03/14/13   12/17/12   2,4,8,9,155,15,16        933,644       933,644  DDJ             0           0           0 LaBella Associates, P.C.                0      04/30/15                       06/01/15           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DALTON-NUNDA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-11-01-04
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nunda Central (Jr/Sr High):
12-0907   Reconstruction               0-001-005  05/15/13     DONE    DONE       DONE      02/22/13   02/21/13   12/07/12   04/09/13   2,4,7                  2,758,185     2,758,185  MFS             0           0     204,105 Clark Patterson Lee                     0        /  /                           /  /             
12-0968   Reconstruction               0-001-010  06/05/13     DONE    DONE       DONE      03/14/13   03/13/13   02/06/13   04/09/12   8,9                      224,000       224,000  MFS             0           0     224,000 Clark Patterson Lee                     0      06/18/14                       12/30/14           
13-0256   Reconstruction               0-001-011  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   05/23/13   04/09/13   2,155,16               2,117,265     2,117,265  MFS             0           0           0 Clark Patterson Lee                     0      12/16/14           YES         02/09/15           
14-0920   Reconstruction               0-001-012  07/28/14     DONE    DONE       DONE      01/05/15   01/02/15   07/24/14   07/28/14   155,15,16                 93,000        93,000  MFS             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          Keshequa Career and Technical Facili:
10-0441   Reconstruction               0-002-003  12/01/10     DONE    DONE       DONE      11/08/10   11/01/10   08/26/10   05/18/10   2,7,15                   127,939       127,939  JOD             0           0           0 Clark Patterson Lee                     0      12/31/11                       12/05/12           

          Dalton Central (Elementary):
12-0908   Reconstruction               0-003-004  05/15/13     DONE    DONE       DONE      02/22/13   02/21/13   12/06/12   04/09/13   2,4,7                    832,858       832,858  MFS             0           0      61,631 Clark Patterson Lee                     0        /  /                           /  /             
13-0257   Reconstruction               0-003-008  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   05/23/13   04/09/13   2,16                     260,154       260,154  MFS             0           0      15,923 Clark Patterson Lee                     0      12/16/14                       02/09/15           

          New Bus Garage(Alt. Site):
13-0258   Reconstruction               5-008-002  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   03/01/13   04/09/13   155,15                    35,500        35,500  MFS             0           0           0                                         0      12/16/14                       03/20/15           
13-0259   Reconstruction               5-008-003  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   05/23/13   04/09/13   2,16                      16,200        16,200  MFS             0           0           0 Clark Patterson Lee                     0      12/16/14                       03/20/15           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




YORK CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-17-01-04
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
13-0911   Reconstruction               0-001-010  04/10/14     DONE    DONE       DONE      12/19/13   12/18/13   10/03/12   02/11/14   2,7,8,9,10,155,15,16   2,491,767     2,491,767  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-0243   Reconstruction               0-001-011  05/11/15     DONE    DONE       DONE      09/04/14   09/02/14   06/12/14   02/11/14   2,8,9,10,155,15,16     2,361,793             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-1008   Reconstruction               0-001-012  10/15/14     DONE    DONE       DONE      01/23/15   01/22/15   12/17/14   02/11/14   8,9                      219,000             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage:
14-0244   Reconstruction               5-002-005  05/11/15     DONE    DONE       DONE      09/04/14   09/02/14   10/03/12   02/11/14   2,10,16                   16,208             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES GENESEE VALLEY (GEN-LIV-STEU-) STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-90-00-00
last updated on 08/28/15
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Container #1-Batavia Bldg Trades:
14-1621TQ Temporary Quarters           2-047-001  06/29/15     DONE    DONE       DONE      06/10/15   06/03/15   03/06/15     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Container #2-Batavia Bldg Trades:
14-1622TQ Temporary Quarters           2-048-001  06/29/15     DONE    DONE       DONE      06/29/15   06/03/15   03/06/15     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Container #3-Batavia Bldg Trades:
14-1623TQ Temporary Quarters           2-049-001  06/29/15     DONE    DONE       DONE      06/10/15   06/03/15   03/06/15     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Container #4-Mt Morris Metal Trades:
14-1624TQ Temporary Quarters           2-050-001  06/29/15     DONE    DONE       DONE      06/10/15   06/03/15   03/06/15     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Container #5-Mt Morris Metal Trades:
14-1625TQ Temporary Quarters           2-051-001  06/29/15     DONE    DONE       DONE      06/10/15   06/03/15   03/06/15     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED