Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 10/17/14 at 16:21:17




AVON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-01-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Primary School:
10-0137   Reconstruction               0-001-013  11/29/10     DONE    DONE       DONE      08/20/10   08/10/10   09/09/09   12/01/09   155,15,16                265,644       265,644  JOD             0           0      31,121 Hunt Engineers & Architects &           0      08/18/11                       12/08/11           
14-0059   Reconstruction               0-001-014               UNREVIEWED
                                                                       STARTED    UNREVIEWED07/25/14   07/21/14   04/01/14   01/21/14   2,9,155,16                     0             0  MFS             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Jr/Sr High School:
10-0138   Reconstruction               0-002-014  11/29/10     DONE    DONE       DONE      08/20/10   08/10/10   09/09/09   12/01/09   13,15,16                 264,966       264,966  JOD             0           0       9,671 Hunt Engineers & Architects &           0      08/31/11                       12/08/11           
12-0211   Reconstruction               0-002-015  02/20/13     DONE    DONE       DONE      09/25/12   09/25/12   09/04/12   05/15/12   9,10,155,15,16           600,000             0  DDJ             0           0       7,305 Hunt Engineers & Architects &           0        /  /                           /  /             
14-0060   Reconstruction               0-002-016               STARTED STARTED    UNREVIEWED07/25/14   07/21/14   04/01/14   01/21/14   2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          Track Storage Facility:
14-0272   New Construction             2-012-001                         UNREVIEWED         09/10/14   09/09/14   06/25/14     /  /     02 - 16                        0             0  MFS             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             

          New Bus Maint. Facility:
11-0152   Reconstruction               5-010-004  11/18/11     DONE    DONE       DONE      09/01/11   08/31/11     /  /     05/17/11   15,16                     95,000        95,000  JOD             0           0           0 Hunt Engineers & Architects &           0      06/27/12                       09/27/12           

          Solar Array Electrical Building:
  -       New Construction             7-013-001                                              /  /       /  /     10/01/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CALEDONIA MUMFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-02-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
09-0625   Reconstruction               0-001-006  04/15/10     DONE    DONE       DONE      12/24/09   12/18/09   10/26/09   06/26/07   15,16                    170,782       170,782  JOD             0           0           0 Hunt Engineers & Architects &           0      12/31/10                         /  /             
12-1213   Reconstruction               0-001-007  05/29/13     DONE    DONE       DONE      05/23/13   05/16/13   02/15/13   05/21/13   8,16                      70,000        70,000  JOB             0           0           0 Hunt Engineers & Architects &           0      09/09/13                       11/21/13           
  -       Reconstruction               0-001-008                                              /  /       /  /     04/08/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Elementary School:
09-0626   Reconstruction               0-003-008  04/15/10     DONE    DONE       DONE      12/24/09   12/18/09   10/26/09   06/26/07   15,16                     54,357        54,357  JOD             0           0           0 Hunt Engineers & Architects &           0      12/31/10                         /  /             
12-1214XX Reconstruction               0-003-009  05/29/13               CANCELLED          05/23/13   05/16/13   02/15/13   05/21/13   8,16                      30,000        30,000  JOB             0           0           0 Hunt Engineers & Architects &           0        /  /                           /  /             
  -       Reconstruction               0-003-010                                              /  /       /  /     04/08/14     /  /     2,4,7,8,9,10,15,16             0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          District Office:
  -       Reconstruction               1-002-005                                              /  /       /  /     04/08/14     /  /     7,10                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          New Bus Garage:
  -       Reconstruction               5-006-004                                              /  /       /  /     04/08/14     /  /     10,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENESEO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-04-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-0861   Reconstruction               0-005-016  04/26/11     DONE    DONE       DONE      02/16/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,10,155,15,   3,385,870     3,385,870  HCM             0           0           0 Mosaic Associates                       0      01/04/12                       01/09/14         YES
                                                                                                                                                                                                                                                                                                                                   
11-0018   Reconstruction               0-005-017  11/04/11     DONE    DONE       DONE      07/14/11   07/14/11   03/24/11   10/07/10   2,4,7,8,9,10,155,15,   7,800,000     7,800,000  HCM             0           0           0 Mosaic Associates                       0      08/30/13                       10/07/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Field House Stor:
11-0019   Reconstruction               2-003-002  11/04/11     DONE    DONE       DONE      07/14/11   07/14/11   12/19/07   10/07/10   2,4,7,8,9,155,15,16      200,000             0  MGL             0           0           0 Mosaic Associates                       0      01/04/12                       01/17/14           

          Bus Garage Storage:
10-0862   Reconstruction               4-002-001  04/26/11     DONE    DONE       DONE      02/15/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,16              42,277        42,277  HCM             0           0           0 Mosaic Associates                       0      01/04/12                       01/09/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Bus Garage Maint:
10-0863   Reconstruction               5-001-002  04/26/11     DONE    DONE       DONE      02/16/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,155,15,16      119,500       119,500  HCM             0           0           0 Mosaic Associates                       0      01/04/12                       01/09/14         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               5-001-003                                              /  /       /  /     03/24/11     /  /     2,4,7,8,9,15,16                0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LIVONIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-08-01-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Connell Bldg (frmrly Intermed.Sch):
11-0461   Reconstruction               0-001-009  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   11/10/10   10/20/11   7                         18,869        18,869  DDJ             0           0       3,188 Gordon W. Jones Associates              0      04/26/13                       05/06/13           
  -       Reconstruction               0-001-010                                              /  /       /  /     09/02/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Livonia Elementary:
11-0462   Reconstruction               0-002-007  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   10/01/09   10/20/11   2,4,7,8                1,970,602     1,970,602  DDJ             0           0     219,063 Gordon W. Jones Associates              0      04/26/13                       05/06/13           
11-0728   Reconstruction               0-002-008  05/31/12     DONE    DONE       DONE      01/30/12   01/20/12   10/01/09   10/20/11   2,9,10,155,15,16          61,994        61,994  DDJ             0           0           0 Gordon W. Jones Associates              0      11/15/13                       11/18/13           
13-0778   Reconstruction               0-002-009  04/01/14     DONE    DONE       DONE      11/27/13   11/22/13   10/03/13   10/20/11   10,16                     30,844             0  DDJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-002-010                                              /  /       /  /     09/02/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Livonia MS/HS(frmrly High School):
11-0463   Reconstruction               0-007-007  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   10/01/09   10/20/11   7                         95,694        95,694  DDJ             0           0      16,172 Gordon W. Jones Associates              0      04/26/13                       05/06/13           
11-0729   Reconstruction               0-007-008  05/31/12     DONE    DONE       DONE      01/30/12   01/20/12   10/01/09   10/20/11   2,9,10,155,15,16       1,194,691     1,194,691  DDJ             0           0           0 Gordon W. Jones Associates              0      11/15/13                       11/18/13           
13-0779   Reconstruction               0-007-009  04/01/14     DONE    DONE       DONE      11/27/13   11/22/13   10/03/13   10/20/13   2,16                     286,125             0  DDJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-007-010                                              /  /       /  /     09/02/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Gym/Locker Facility @ High School:
  -    XX Reconstruction               0-008-004                         CANCELLED            /  /       /  /     11/10/10     /  /     9,15                           0       550,440  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-005                                              /  /       /  /     09/02/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Baseball Storage Facility:
  -       New Construction             2-014-001                                              /  /       /  /     12/10/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          ~TA Transporation Facility:
  -       Reconstruction               5-010-001                                              /  /       /  /     09/02/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0091   Reconstruction               5-010-L02  07/30/12     DONE    DONE       DONE      08/08/12   07/10/12     /  /     05/15/12                            435,000       435,000  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MOUNT MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-09-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Mt Morris Central:
14-0077   Reconstruction               0-001-010  07/31/14     DONE    DONE       DONE      07/29/14   07/25/14   03/26/10   05/20/14   4,8,9,10,155,15,16       100,000             0  JOD             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0103   Reconstruction               0-001-011               DONE    STARTED    UNREVIEWED08/06/14   08/04/14   11/13/13   12/17/13   2,4,7,8,9,155,15,16            0             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0078   Reconstruction               0-001-012  08/01/14     DONE    DONE       DONE      07/29/14   07/25/14   07/09/14   12/17/13   155,16                         0             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DANSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-10-01-06
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ellis B Hyde Elementary:
10-0592   Reconstruction               0-001-010  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/20/10   05/18/10   2,155,16                 108,613       108,613  JOD             0           0     108,613 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
10-0612   Reconstruction               0-001-011  05/12/11     DONE    DONE       DONE      12/23/10   12/10/10   11/18/10   01/30/07   2,155,16                  53,458        53,458  JOD             0           0           0 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
12-1297   Reconstruction               0-001-012  07/09/13     DONE    DONE       DONE      06/18/13   06/18/13   03/14/13   12/17/12   2,4,8,9,16               222,969       222,969  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             
13-0610   Reconstruction               0-001-013  04/09/14     DONE    DONE       DONE      10/23/13   10/18/13   03/14/13   12/17/12   2,4,8,9,155,15,16        746,915             0  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             

          Dansville Senior High School:
10-0593   Reconstruction               0-003-009  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/21/10   05/18/10   155,16                   123,931       123,931  JOD             0           0     123,931 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
10-0613   Reconstruction               0-003-010  05/12/11     DONE    DONE       DONE      12/23/10   12/10/10   11/18/10   01/30/07   155,16                   255,071       255,071  JOD             0           0           0 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
11-0008   Reconstruction               0-003-011  07/19/11     DONE    DONE       DONE      07/08/11   07/07/11   05/02/11   05/03/11   2,7                      462,575       462,575  JOD             0           0           0 Hunt Engineers,Architects & l           0      09/26/11                       07/12/13           
  -       Reconstruction               0-003-012                                              /  /       /  /     05/19/11     /  /     7,155,16                       0    19,060,081  JOD             0           0           0                                         0        /  /                           /  /             
12-1298   Reconstruction               0-003-013  07/09/13     DONE    DONE       DONE      06/18/13   06/18/13   03/14/13   12/17/12   2,4,8,9,16               613,160       613,160  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             
13-0611   Reconstruction               0-003-014  04/09/14     DONE    DONE       DONE      10/23/13   10/18/13   03/14/13   12/17/12   2,4,8,9,155,15,16      2,054,016             0  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             

          Middle School:
10-0594XX Reconstruction               0-004-011  05/12/11               CANCELLED          12/21/10   12/10/10   10/20/10   05/18/10   9,155,16                 123,848       123,848  JOD             0           0     123,848 Hunt Engineers,Architects & l           0        /  /                           /  /             
10-0635XX Reconstruction               0-004-012  05/12/11               CANCELLED          12/28/10   12/10/10   12/28/10   01/30/07   9,155,16                  45,283        45,283  JOD             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Primary School:
10-0595   Reconstruction               0-005-008  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/21/10   05/18/10   16                        17,184        17,184  JOD             0           0      17,184 Hunt Engineers,Architects & l           0      04/05/12                       10/01/12           
12-1299   Reconstruction               0-005-009  07/09/13     DONE    DONE       DONE      06/18/13   06/18/13   03/14/13   12/17/12   2,4,8,9,16               278,711       278,711  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             
13-0612   Reconstruction               0-005-010  04/09/14     DONE    DONE       DONE      10/23/13   10/18/13   03/14/13   12/17/12   2,4,8,9,155,15,16        933,644             0  DDJ             0           0           0 LaBella Associates, P.C.                0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DALTON-NUNDA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-11-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nunda Central (Jr/Sr High):
12-0907   Reconstruction               0-001-005  05/15/13     DONE    DONE       DONE      02/22/13   02/21/13   12/07/12   04/09/13   2,4,7                  2,758,185     2,758,185  MFS             0           0     204,105 Clark Patterson Lee                     0        /  /                           /  /             
12-0968   Reconstruction               0-001-010  06/05/13     DONE    DONE       DONE      03/14/13   03/13/13   02/06/13   04/09/12   8,9                      224,000       224,000  MFS             0           0     224,000 Clark Patterson Lee                     0        /  /                           /  /             
13-0256   Reconstruction               0-001-011  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   05/23/13   04/09/13   2,155,16               2,117,265             0  MFS             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
  -       Reconstruction               0-001-012                                              /  /       /  /     07/24/14     /  /     155,15,16                      0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Keshequa Career and Technical Facili:
10-0441   Reconstruction               0-002-003  12/01/10     DONE    DONE       DONE      11/08/10   11/01/10   08/26/10   05/18/10   2,7,15                   127,939       127,939  JOD             0           0           0 Clark Patterson Lee                     0      12/31/11                       12/05/12           

          Dalton Central (Elementary):
12-0908   Reconstruction               0-003-004  05/15/13     DONE    DONE       DONE      02/22/13   02/21/13   12/06/12   04/09/13   2,4,7                    832,858       832,858  MFS             0           0      61,631 Clark Patterson Lee                     0        /  /                           /  /             
13-0257   Reconstruction               0-003-008  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   05/23/13   04/09/13   2,16                     260,154       136,715  MFS             0           0      15,923 Clark Patterson Lee                     0        /  /                           /  /             

          New Bus Garage(Alt. Site):
13-0258   Reconstruction               5-008-002  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   03/01/13   04/09/13   155,15                    35,500             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0259   Reconstruction               5-008-003  03/25/14     DONE    DONE       DONE      08/23/13   08/22/13   05/23/13   04/09/13   2,16                      16,200             0  MFS             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




YORK CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-17-01-04
last updated on 10/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
13-0911   Reconstruction               0-001-010  04/10/14     DONE    DONE       DONE      12/19/13   12/18/13   10/03/12   02/11/14   2,7,8,9,10,155,15,16   2,491,767     2,491,767  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-0243   Reconstruction               0-001-011               DONE    DONE       UNREVIEWED09/04/14   09/02/14   06/12/14   02/11/14   2,8,9,10,155,15,16             0    27,619,778  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Athletic Storage:
06-1282DB Discovered Building          2-006-001  10/20/09     DONE    DONE       DONE      04/05/07   04/02/07   05/11/05     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
14-0244   Reconstruction               5-002-005               DONE    DONE       UNREVIEWED09/04/14   09/02/14   10/03/12   02/11/14   2,10,16                        0             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED