AVON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-01-01-04
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary School:
10-0137 Reconstruction 0-001-013 11/29/10 DONE DONE DONE 08/20/10 08/10/10 09/09/09 12/01/09 155,15,16 265,644 265,644 JOD 0 0 31,121 Hunt Engineers & Architects & 0 / / 12/08/11
Jr/Sr High School:
10-0138 Reconstruction 0-002-014 11/29/10 DONE DONE DONE 08/20/10 08/10/10 09/09/09 12/01/09 13,15,16 264,966 264,966 JOD 0 0 9,671 Hunt Engineers & Architects & 0 / / 12/08/11
12-0211 Reconstruction 0-002-015 02/20/13 DONE DONE DONE 09/25/12 09/25/12 09/04/12 05/15/12 9,10,155,15,16 600,000 0 DDJ 0 0 7,305 Hunt Engineers & Architects & 0 / / / /
Maintenance Facility:
- Reconstruction 5-003-004 ADDENDUM REQ'D / / / / 05/27/11 / / 15,16 0 0 JOD 0 0 0 Hunt Engineers & Architects & 0 / / / /
New Bus Maint. Facility:
11-0152 Reconstruction 5-010-004 11/18/11 DONE DONE DONE 09/01/11 08/31/11 / / 05/17/11 15,16 95,000 95,000 JOD 0 0 0 Hunt Engineers & Architects & 0 / / 09/27/12
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
GENESEO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-04-01-04
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
10-0861 Reconstruction 0-005-016 04/26/11 DONE DONE DONE 02/16/11 02/15/11 11/16/10 10/07/10 2,4,7,8,9,10,155,15, 3,270,631 3,270,631 HCM 0 0 0 Mosaic Associates 0 / / / /
11-0018 Reconstruction 0-005-017 11/04/11 DONE DONE DONE 07/14/11 07/14/11 03/24/11 10/07/10 2,4,7,8,9,10,155,15, 7,800,000 7,800,000 HCM 0 0 0 Mosaic Associates 0 / / / /
Field House Stor:
11-0019 Reconstruction 2-003-002 11/04/11 DONE DONE DONE 07/14/11 07/14/11 12/19/07 10/07/10 2,4,7,8,9,155,15,16 200,000 0 MGL 0 0 0 Mosaic Associates 0 / / / /
Bus Garage Storage:
10-0862 Reconstruction 4-002-001 04/26/11 DONE DONE DONE 02/15/11 02/15/11 11/16/10 10/07/10 2,4,7,8,9,16 119,500 0 HCM 0 0 0 Mosaic Associates 0 / / / /
Bus Garage Maint:
10-0863 Reconstruction 5-001-002 04/26/11 DONE DONE DONE 02/16/11 02/15/11 11/16/10 10/07/10 2,4,7,8,9,155,15,16 119,500 0 HCM 0 0 0 Mosaic Associates 0 / / / /
- Reconstruction 5-001-003 / / / / 03/24/11 / / 2,4,7,8,9,15,16 0 0 HCM 0 0 0 0 / / / /
Press Box:
09-0215DB Discovered Building 7-008-001 10/06/09 DONE DONE DONE 09/15/09 09/14/09 07/03/09 / / 02 - 16 0 0 HCM 0 0 0 Mosaic Associates 0 / / / /
Concession Stand:
09-0216DB Discovered Building 7-009-001 10/06/09 DONE DONE DONE 09/15/09 09/14/09 07/03/09 / / 02 - 16 0 0 HCM 0 0 0 Mosaic Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LIVONIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-08-01-06
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Connell Bldg (frmrly Intermed.Sch):
11-0461 Reconstruction 0-001-009 12/09/11 DONE DONE DONE 12/02/11 12/02/11 11/10/10 10/20/11 7 18,869 18,869 DDJ 0 0 3,188 Gordon W. Jones Associates 0 / / 05/06/13
Livonia Elementary:
11-0462 Reconstruction 0-002-007 12/09/11 DONE DONE DONE 12/02/11 12/02/11 10/01/09 10/20/11 2,4,7,8 1,970,602 1,970,602 DDJ 0 0 219,063 Gordon W. Jones Associates 0 / / 05/06/13
11-0728 Reconstruction 0-002-008 05/31/12 DONE DONE DONE 01/30/12 01/20/12 10/01/09 10/20/11 2,9,10,155,15,16 61,994 0 DDJ 0 0 0 Gordon W. Jones Associates 0 / / / /
Livonia MS/HS(frmrly High School):
11-0463 Reconstruction 0-007-007 12/09/11 DONE DONE DONE 12/02/11 12/02/11 10/01/09 10/20/11 7 95,694 95,694 DDJ 0 0 16,172 Gordon W. Jones Associates 0 / / 05/06/13
11-0729 Reconstruction 0-007-008 05/31/12 DONE DONE DONE 01/30/12 01/20/12 10/01/09 10/20/11 2,9,10,155,15,16 1,194,691 0 DDJ 0 0 0 Gordon W. Jones Associates 0 / / / /
Gym/Locker Facility @ High School:
- XX Reconstruction 0-008-004 CANCELLED / / / / 11/10/10 / / 9,15 0 550,440 DDJ 0 0 0 0 / / / /
Storage Facility:
07-0691 New Construction 2-011-001 10/28/08 DONE DONE DONE 11/01/07 10/29/07 07/25/07 09/24/07 02 - 16 5,000 0 MGL 0 0 0 Habiterra Associates 0 / / / /
Concession Stand @ High School:
08-0853DB Discovered Building 2-012-001 03/31/09 DONE DONE DONE 12/04/08 11/27/08 09/05/07 / / 02 - 16 0 0 MGL 0 0 0 Habiterra Associates 0 / / / /
Athletic Storage #2 @ High School:
08-0854DB Discovered Building 2-013-001 03/31/09 DONE DONE DONE 12/04/08 11/27/08 09/05/07 / / 02 - 16 0 0 MGL 0 0 0 Habiterra Associates 0 / / / /
Baseball Storage Facility:
- New Construction 2-014-001 / / / / 12/10/09 / / 02 - 16 0 0 DDJ 0 0 0 0 / / / /
STA Transporation Facility:
12-0091 Reconstruction 5-010-LO2 07/30/12 DONE DONE DONE 08/08/12 07/10/12 / / 05/15/12 435,000 435,000 DDJ 0 0 0 0 / / / /
Bru-Mar Bus Garage:
- TQ Temporary Quarters 5-015-001 / / / / 07/27/12 / / 0 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MOUNT MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-09-01-04
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Mt Morris Central:
07-1472 Reconstruction 0-001-009 12/05/08 DONE DONE DONE 01/26/08 01/24/08 02/01/07 12/12/07 2,8,9,10,155,15,16 5,643,000 5,643,000 JOD 0 0 456,815 0 / / / /
- Reconstruction 0-001-010 / / / / 03/26/10 / / 4,8,9,10,155,15,16 0 0 JOD 0 0 0 0 / / / /
Storage/Concessions Bldg.:
07-1531 New Construction 7-004-001 10/14/08 DONE DONE DONE 02/04/08 01/22/08 02/01/07 12/12/07 02 - 16 600,000 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
DANSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-10-01-06
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Ellis B Hyde Elementary:
10-0592 Reconstruction 0-001-010 05/12/11 DONE DONE DONE 12/21/10 12/10/10 10/20/10 05/18/10 2,155,16 108,613 108,613 JOD 0 0 108,613 Hunt Engineers, 0 / / 10/01/12
10-0612 Reconstruction 0-001-011 05/12/11 DONE DONE DONE 12/23/10 12/10/10 11/18/10 01/30/07 2,155,16 27,470 27,470 JOD 0 0 0 Hunt Engineers, 0 / / 10/01/12
- Reconstruction 0-001-012 / / / / 03/14/13 / / 2,4,8,9,16 0 0 JOB 0 0 0 0 / / / /
- Reconstruction 0-001-013 / / / / 03/14/13 / / 2,4,8,9,155,15,16 0 0 JOB 0 0 0 0 / / / /
Dansville Senior High School:
10-0593 Reconstruction 0-003-009 05/12/11 DONE DONE DONE 12/21/10 12/10/10 10/21/10 05/18/10 155,16 123,931 123,931 JOD 0 0 123,931 Hunt Engineers, 0 / / 10/01/12
10-0613 Reconstruction 0-003-010 05/12/11 DONE DONE DONE 12/23/10 12/10/10 11/18/10 01/30/07 155,16 174,148 174,148 JOD 0 0 0 Hunt Engineers, 0 / / 10/01/12
11-0008 Reconstruction 0-003-011 07/19/11 DONE DONE DONE 07/08/11 07/07/11 05/02/11 05/03/11 2,7 462,575 462,575 JOD 0 0 0 Hunt Engineers, 0 / / / /
- Reconstruction 0-003-012 / / / / 05/19/11 / / 7,155,16 0 19,060,081 JOD 0 0 0 0 / / / /
- Reconstruction 0-003-013 / / / / 03/14/13 / / 2,4,8,9,16 0 0 JOB 0 0 0 0 / / / /
- Reconstruction 0-003-014 / / / / 03/14/13 / / 2,4,8,9,155,15,16 0 0 JOB 0 0 0 0 / / / /
Middle School:
10-0594XX Reconstruction 0-004-011 05/12/11 CANCELLED 12/21/10 12/10/10 10/20/10 05/18/10 9,155,16 123,848 123,848 JOD 0 0 123,848 Hunt Engineers, 0 / / / /
10-0635XX Reconstruction 0-004-012 05/12/11 CANCELLED 12/28/10 12/10/10 12/28/10 01/30/07 9,155,16 45,283 45,283 JOD 0 0 0 Hunt Engineers, 0 / / / /
Primary School:
10-0595 Reconstruction 0-005-008 05/12/11 DONE DONE DONE 12/21/10 12/10/10 10/21/10 05/18/10 16 17,184 17,184 JOD 0 0 17,184 Hunt Engineers, 0 / / 10/01/12
- Reconstruction 0-005-009 / / / / 03/14/13 / / 2,4,8,9,16 0 0 JOB 0 0 0 0 / / / /
- Reconstruction 0-005-010 / / / / 03/14/13 / / 2,4,8,9,155,15,16 0 0 JOB 0 0 0 0 / / / /
Press Box:
08-0767DB Discovered Building 7-021-001 11/20/08 DONE DONE DONE 11/19/08 11/06/08 11/14/08 / / 02 - 16 0 0 JOD 0 0 0 Hunt Engineers, 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
DALTON-NUNDA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-11-01-04
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Nunda Central (Jr/Sr High):
12-0907 Reconstruction 0-001-005 05/15/13 DONE DONE DONE 02/22/13 02/21/13 12/07/12 04/09/13 2,4,7 2,758,185 2,758,185 MFS 0 0 204,105 Clark Patterson Lee 0 / / / /
07-1191 Reconstruction 0-001-009 06/05/08 DONE DONE DONE 12/24/07 12/21/07 04/17/07 03/20/07 2,4,7,8,9,10,14,155, 4,638,518 4,782,046 JOD 0 0 95,641 0 / / / /
12-0968 Reconstruction 0-001-010 DONE STARTED STARTED 03/14/13 03/13/13 02/06/13 04/09/12 8,9 224,000 0 MFS 0 0 224,000 Clark Patterson Lee 0 / / / /
Keshequa Career and Technical Facili:
10-0441 Reconstruction 0-002-003 12/01/10 DONE DONE DONE 11/08/10 11/01/10 08/26/10 05/18/10 2,7,15 127,939 140,000 JOD 0 0 0 Clark Patterson Lee 0 / / 12/05/12
Dalton Central (Elementary):
12-0908 Reconstruction 0-003-004 05/15/13 DONE DONE DONE 02/22/13 02/21/13 12/06/12 04/09/13 2,4,7 746,753 746,753 MFS 0 0 55,259 Clark Patterson Lee 0 / / / /
07-1192 Reconstruction 0-003-007 06/05/08 DONE DONE DONE 12/24/07 12/21/07 04/17/07 03/20/07 2,4,7,8,9,10,14,155, 3,673,637 3,932,954 JOD 0 0 78,659 0 / / / /
New Bus Garage(Alt. Site):
- Reconstruction 5-008-002 / / / / 03/01/13 / / 155,15 0 0 MFS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
YORK CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-17-01-04
last updated on 05/20/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
07-2149 Additions and Alterations 0-001-009 01/27/09 DONE DONE DONE 05/23/08 05/16/08 01/05/07 12/18/07 02 - 16 5,785,688 5,670,348 DDJ 0 0 305,077 Clark Patterson Lee 0 / / / /
- Reconstruction 0-001-010 / / / / 10/03/12 / / 2,7,8,9,10,155,15,16 0 0 DDJ 0 0 0 0 / / / /
Athletic Storage:
06-1282DB Discovered Building 2-006-001 10/20/09 DONE DONE DONE 04/05/07 04/02/07 05/11/05 / / 0 0 DDJ 0 0 0 0 / / / /
Bus Garage:
- Reconstruction 5-002-005 / / / / 10/03/12 / / 2,7,8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED