Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/20/13 at 09:48:17




AVON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-01-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
10-0137   Reconstruction               0-001-013  11/29/10     DONE    DONE       DONE      08/20/10   08/10/10   09/09/09   12/01/09   155,15,16                265,644       265,644  JOD             0           0      31,121 Hunt Engineers & Architects &           0        /  /           12/08/11      

          Jr/Sr High School:
10-0138   Reconstruction               0-002-014  11/29/10     DONE    DONE       DONE      08/20/10   08/10/10   09/09/09   12/01/09   13,15,16                 264,966       264,966  JOD             0           0       9,671 Hunt Engineers & Architects &           0        /  /           12/08/11      
12-0211   Reconstruction               0-002-015  02/20/13     DONE    DONE       DONE      09/25/12   09/25/12   09/04/12   05/15/12   9,10,155,15,16           600,000             0  DDJ             0           0       7,305 Hunt Engineers & Architects &           0        /  /             /  /        

          Maintenance Facility:
  -       Reconstruction               5-003-004                       ADDENDUM REQ'D         /  /       /  /     05/27/11     /  /     15,16                          0             0  JOD             0           0           0 Hunt Engineers & Architects &           0        /  /             /  /        

          New Bus Maint. Facility:
11-0152   Reconstruction               5-010-004  11/18/11     DONE    DONE       DONE      09/01/11   08/31/11     /  /     05/17/11   15,16                     95,000        95,000  JOD             0           0           0 Hunt Engineers & Architects &           0        /  /           09/27/12      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CALEDONIA MUMFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-02-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
09-0625   Reconstruction               0-001-006  04/15/10     DONE    DONE       DONE      12/24/09   12/18/09   10/26/09   06/26/07   15,16                    170,782       170,782  JOD             0           0           0 Hunt Engineers & Architects &           0        /  /             /  /        
  -       Reconstruction               0-001-007                                              /  /       /  /     02/15/13     /  /     8,16                           0             0  JOB             0           0           0                                         0        /  /             /  /        

          Elementary School:
09-0626   Reconstruction               0-003-008  04/15/10     DONE    DONE       DONE      12/24/09   12/18/09   10/26/09   06/26/07   15,16                     54,357        54,357  JOD             0           0           0 Hunt Engineers & Architects &           0        /  /             /  /        
  -       Reconstruction               0-003-009                                              /  /       /  /     02/15/13     /  /     8,16                           0             0  JOB             0           0           0                                         0        /  /             /  /        

          Maintenance Shed #2 @ Middle School:
01-0080DB Discovered Building          2-010-001  07/30/09     DONE    DONE       DONE      07/19/01     /  /     05/23/01     /  /                                    0             0  BJB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENESEO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-04-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-0861   Reconstruction               0-005-016  04/26/11     DONE    DONE       DONE      02/16/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,10,155,15,   3,270,631     3,270,631  HCM             0           0           0 Mosaic Associates                       0        /  /             /  /        
11-0018   Reconstruction               0-005-017  11/04/11     DONE    DONE       DONE      07/14/11   07/14/11   03/24/11   10/07/10   2,4,7,8,9,10,155,15,   7,800,000     7,800,000  HCM             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Field House Stor:
11-0019   Reconstruction               2-003-002  11/04/11     DONE    DONE       DONE      07/14/11   07/14/11   12/19/07   10/07/10   2,4,7,8,9,155,15,16      200,000             0  MGL             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Bus Garage Storage:
10-0862   Reconstruction               4-002-001  04/26/11     DONE    DONE       DONE      02/15/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,16             119,500             0  HCM             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Bus Garage Maint:
10-0863   Reconstruction               5-001-002  04/26/11     DONE    DONE       DONE      02/16/11   02/15/11   11/16/10   10/07/10   2,4,7,8,9,155,15,16      119,500             0  HCM             0           0           0 Mosaic Associates                       0        /  /             /  /        
  -       Reconstruction               5-001-003                                              /  /       /  /     03/24/11     /  /     2,4,7,8,9,15,16                0             0  HCM             0           0           0                                         0        /  /             /  /        

          Press Box:
09-0215DB Discovered Building          7-008-001  10/06/09     DONE    DONE       DONE      09/15/09   09/14/09   07/03/09     /  /     02 - 16                        0             0  HCM             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Concession Stand:
09-0216DB Discovered Building          7-009-001  10/06/09     DONE    DONE       DONE      09/15/09   09/14/09   07/03/09     /  /     02 - 16                        0             0  HCM             0           0           0 Mosaic Associates                       0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LIVONIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-08-01-06
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Connell Bldg (frmrly Intermed.Sch):
11-0461   Reconstruction               0-001-009  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   11/10/10   10/20/11   7                         18,869        18,869  DDJ             0           0       3,188 Gordon W. Jones Associates              0        /  /           05/06/13      

          Livonia Elementary:
11-0462   Reconstruction               0-002-007  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   10/01/09   10/20/11   2,4,7,8                1,970,602     1,970,602  DDJ             0           0     219,063 Gordon W. Jones Associates              0        /  /           05/06/13      
11-0728   Reconstruction               0-002-008  05/31/12     DONE    DONE       DONE      01/30/12   01/20/12   10/01/09   10/20/11   2,9,10,155,15,16          61,994             0  DDJ             0           0           0 Gordon W. Jones Associates              0        /  /             /  /        

          Livonia MS/HS(frmrly High School):
11-0463   Reconstruction               0-007-007  12/09/11     DONE    DONE       DONE      12/02/11   12/02/11   10/01/09   10/20/11   7                         95,694        95,694  DDJ             0           0      16,172 Gordon W. Jones Associates              0        /  /           05/06/13      
11-0729   Reconstruction               0-007-008  05/31/12     DONE    DONE       DONE      01/30/12   01/20/12   10/01/09   10/20/11   2,9,10,155,15,16       1,194,691             0  DDJ             0           0           0 Gordon W. Jones Associates              0        /  /             /  /        

          Gym/Locker Facility @ High School:
  -    XX Reconstruction               0-008-004                         CANCELLED            /  /       /  /     11/10/10     /  /     9,15                           0       550,440  DDJ             0           0           0                                         0        /  /             /  /        

          Storage Facility:
07-0691   New Construction             2-011-001  10/28/08     DONE    DONE       DONE      11/01/07   10/29/07   07/25/07   09/24/07   02 - 16                    5,000             0  MGL             0           0           0 Habiterra Associates                    0        /  /             /  /        

          Concession Stand @ High School:
08-0853DB Discovered Building          2-012-001  03/31/09     DONE    DONE       DONE      12/04/08   11/27/08   09/05/07     /  /     02 - 16                        0             0  MGL             0           0           0 Habiterra Associates                    0        /  /             /  /        

          Athletic Storage #2 @ High School:
08-0854DB Discovered Building          2-013-001  03/31/09     DONE    DONE       DONE      12/04/08   11/27/08   09/05/07     /  /     02 - 16                        0             0  MGL             0           0           0 Habiterra Associates                    0        /  /             /  /        

          Baseball Storage Facility:
  -       New Construction             2-014-001                                              /  /       /  /     12/10/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        

          STA Transporation Facility:
12-0091   Reconstruction               5-010-LO2  07/30/12     DONE    DONE       DONE      08/08/12   07/10/12     /  /     05/15/12                            435,000       435,000  DDJ             0           0           0                                         0        /  /             /  /        

          Bru-Mar Bus Garage:
  -    TQ Temporary Quarters           5-015-001                                              /  /       /  /     07/27/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MOUNT MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-09-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Mt Morris Central:
07-1472   Reconstruction               0-001-009  12/05/08     DONE    DONE       DONE      01/26/08   01/24/08   02/01/07   12/12/07   2,8,9,10,155,15,16     5,643,000     5,643,000  JOD             0           0     456,815                                         0        /  /             /  /        
  -       Reconstruction               0-001-010                                              /  /       /  /     03/26/10     /  /     4,8,9,10,155,15,16             0             0  JOD             0           0           0                                         0        /  /             /  /        

          Storage/Concessions Bldg.:
07-1531   New Construction             7-004-001  10/14/08     DONE    DONE       DONE      02/04/08   01/22/08   02/01/07   12/12/07   02 - 16                  600,000             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DANSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-10-01-06
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ellis B Hyde Elementary:
10-0592   Reconstruction               0-001-010  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/20/10   05/18/10   2,155,16                 108,613       108,613  JOD             0           0     108,613 Hunt Engineers,                         0        /  /           10/01/12      
10-0612   Reconstruction               0-001-011  05/12/11     DONE    DONE       DONE      12/23/10   12/10/10   11/18/10   01/30/07   2,155,16                  27,470        27,470  JOD             0           0           0 Hunt Engineers,                         0        /  /           10/01/12      
  -       Reconstruction               0-001-012                                              /  /       /  /     03/14/13     /  /     2,4,8,9,16                     0             0  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-013                                              /  /       /  /     03/14/13     /  /     2,4,8,9,155,15,16              0             0  JOB             0           0           0                                         0        /  /             /  /        

          Dansville Senior High School:
10-0593   Reconstruction               0-003-009  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/21/10   05/18/10   155,16                   123,931       123,931  JOD             0           0     123,931 Hunt Engineers,                         0        /  /           10/01/12      
10-0613   Reconstruction               0-003-010  05/12/11     DONE    DONE       DONE      12/23/10   12/10/10   11/18/10   01/30/07   155,16                   174,148       174,148  JOD             0           0           0 Hunt Engineers,                         0        /  /           10/01/12      
11-0008   Reconstruction               0-003-011  07/19/11     DONE    DONE       DONE      07/08/11   07/07/11   05/02/11   05/03/11   2,7                      462,575       462,575  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        
  -       Reconstruction               0-003-012                                              /  /       /  /     05/19/11     /  /     7,155,16                       0    19,060,081  JOD             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-003-013                                              /  /       /  /     03/14/13     /  /     2,4,8,9,16                     0             0  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-003-014                                              /  /       /  /     03/14/13     /  /     2,4,8,9,155,15,16              0             0  JOB             0           0           0                                         0        /  /             /  /        

          Middle School:
10-0594XX Reconstruction               0-004-011  05/12/11               CANCELLED          12/21/10   12/10/10   10/20/10   05/18/10   9,155,16                 123,848       123,848  JOD             0           0     123,848 Hunt Engineers,                         0        /  /             /  /        
10-0635XX Reconstruction               0-004-012  05/12/11               CANCELLED          12/28/10   12/10/10   12/28/10   01/30/07   9,155,16                  45,283        45,283  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        

          Primary School:
10-0595   Reconstruction               0-005-008  05/12/11     DONE    DONE       DONE      12/21/10   12/10/10   10/21/10   05/18/10   16                        17,184        17,184  JOD             0           0      17,184 Hunt Engineers,                         0        /  /           10/01/12      
  -       Reconstruction               0-005-009                                              /  /       /  /     03/14/13     /  /     2,4,8,9,16                     0             0  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-005-010                                              /  /       /  /     03/14/13     /  /     2,4,8,9,155,15,16              0             0  JOB             0           0           0                                         0        /  /             /  /        

          Press Box:
08-0767DB Discovered Building          7-021-001  11/20/08     DONE    DONE       DONE      11/19/08   11/06/08   11/14/08     /  /     02 - 16                        0             0  JOD             0           0           0 Hunt Engineers,                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DALTON-NUNDA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-11-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nunda Central (Jr/Sr High):
12-0907   Reconstruction               0-001-005  05/15/13     DONE    DONE       DONE      02/22/13   02/21/13   12/07/12   04/09/13   2,4,7                  2,758,185     2,758,185  MFS             0           0     204,105 Clark Patterson Lee                     0        /  /             /  /        
07-1191   Reconstruction               0-001-009  06/05/08     DONE    DONE       DONE      12/24/07   12/21/07   04/17/07   03/20/07   2,4,7,8,9,10,14,155,   4,638,518     4,782,046  JOD             0           0      95,641                                         0        /  /             /  /        
12-0968   Reconstruction               0-001-010               DONE    STARTED    STARTED   03/14/13   03/13/13   02/06/13   04/09/12   8,9                      224,000             0  MFS             0           0     224,000 Clark Patterson Lee                     0        /  /             /  /        

          Keshequa Career and Technical Facili:
10-0441   Reconstruction               0-002-003  12/01/10     DONE    DONE       DONE      11/08/10   11/01/10   08/26/10   05/18/10   2,7,15                   127,939       140,000  JOD             0           0           0 Clark Patterson Lee                     0        /  /           12/05/12      

          Dalton Central (Elementary):
12-0908   Reconstruction               0-003-004  05/15/13     DONE    DONE       DONE      02/22/13   02/21/13   12/06/12   04/09/13   2,4,7                    746,753       746,753  MFS             0           0      55,259 Clark Patterson Lee                     0        /  /             /  /        
07-1192   Reconstruction               0-003-007  06/05/08     DONE    DONE       DONE      12/24/07   12/21/07   04/17/07   03/20/07   2,4,7,8,9,10,14,155,   3,673,637     3,932,954  JOD             0           0      78,659                                         0        /  /             /  /        

          New Bus Garage(Alt. Site):
  -       Reconstruction               5-008-002                                              /  /       /  /     03/01/13     /  /     155,15                         0             0  MFS             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




YORK CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-17-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-2149   Additions and Alterations    0-001-009  01/27/09     DONE    DONE       DONE      05/23/08   05/16/08   01/05/07   12/18/07   02 - 16                5,785,688     5,670,348  DDJ             0           0     305,077 Clark Patterson Lee                     0        /  /             /  /        
  -       Reconstruction               0-001-010                                              /  /       /  /     10/03/12     /  /     2,7,8,9,10,155,15,16           0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Athletic Storage:
06-1282DB Discovered Building          2-006-001  10/20/09     DONE    DONE       DONE      04/05/07   04/02/07   05/11/05     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Bus Garage:
  -       Reconstruction               5-002-005                                              /  /       /  /     10/03/12     /  /     2,7,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES GENESEE VALLEY (GEN-LIV-STEU-) STATUS REPORT ON CAPITAL PROJECTS
District No.: 24-90-00-00
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lease at 450 North Main Street:
08-1137TQ Temporary Quarters           8-046-001  02/27/09     DONE    DONE       DONE      01/27/09   01/26/09   10/20/08     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED