Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/24/24 at 08:10:45




BROOKFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-01-09-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -    PR Additions and Alterations    0-001-014                                              /  /       /  /     08/08/23     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Storage Garage:
  -       Reconstruction               2-005-001                                              /  /       /  /     08/08/23     /  /     8                              0             0  WLC             0           0           0                                         0        /  /                           /  /             

          (DEMO)Bus Garage:
  -       Reconstruction               5-004-007                                              /  /       /  /     08/08/23     /  /     2,4,7,8,9,10,14,155,           0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Bus Maintenance Facility:
  -       New Construction             5-007-001                                              /  /       /  /     08/08/23     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CAZENOVIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-02-01-06
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Burton Street School:
19-0377   Reconstruction               0-002-009  12/24/19     DONE    DONE       DONE      09/06/19   08/29/19   01/22/19   12/18/18   2,4,7,8,9,10,155,15,   7,329,941     7,329,941  JSS             0           0           0 Tetra Tech Architects and Eng           0      11/01/21                       08/29/19           
19-0213XX Reconstruction               0-002-010  09/17/19               CANCELLED          08/06/19   07/16/19   04/26/19   05/21/19   8,16                           0             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         07/16/19           
20-0348   Reconstruction               0-002-011  12/04/20     DONE    DONE       DONE      09/04/20   08/07/20   05/21/20   01/14/20   2,7,8,155,16             674,666       674,666  JSS             0           0           0 Tetra Tech Architects and Eng     674,666      02/08/23                       08/07/20           
  -       Reconstruction               0-002-012                                              /  /       /  /     02/02/24     /  /     2,7,9,155,15,16                0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Emory Avenue Complex (MS/HS):
19-0378   Reconstruction               0-005-012  12/24/19     DONE    DONE       DONE      09/06/19   08/29/19   01/22/19   12/18/18   2,4,7,8,9,10,14,155,   7,670,059     7,670,059  JSS             0           0           0 Tetra Tech Architects and Eng           0      11/01/21                       08/29/19           
19-0214XX Reconstruction               0-005-013  09/17/19               CANCELLED          08/06/19   07/16/19   04/26/19   05/21/19   8,16                           0             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         07/16/19           
20-0349   Reconstruction               0-005-014  12/04/20     DONE    DONE       DONE      09/04/20   08/07/20   05/21/20   01/14/20   2,7,8,155,16           1,022,385     1,022,385  JSS             0           0           0 Tetra Tech Architects and Eng   1,022,385      02/08/23                       08/07/20           
20-1373   Reconstruction               0-005-015  03/24/21     DONE    DONE       DONE      03/05/21   03/02/21   02/10/21   06/09/20   15                       100,000       100,000  JSS             0           0           0 Tetra Tech Architects and Eng           0      06/24/21                       03/02/21           
21-1278   Reconstruction               0-005-016  03/29/22     DONE    DONE       DONE      02/14/22   02/09/22   11/19/21   05/18/21   2,16                     100,000       100,000  JLB             0           0           0 Tetra Tech Architects and Eng           0      06/24/22                       02/09/22           
21-1420   Reconstruction               0-005-017  05/11/22     DONE    DONE       DONE      03/02/22   02/28/22   01/07/22   12/18/18   155,16                   600,000       600,000  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/28/22           
22-0708   Reconstruction               0-005-018  02/07/23     DONE    DONE       DONE      10/12/22   10/11/22   07/27/22   03/30/22   2,4,9,10,13,15,16     10,401,466     8,772,191  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/11/22           
22-1218   Reconstruction               0-005-019  04/13/23     DONE    DONE       DONE      12/12/22   12/09/22   10/03/22   02/28/22   2,16                     100,000       100,000  JJH             0           0           0 Tetra Tech Architects and Eng           0      09/12/23                       12/09/22           
23-0912   Reconstruction               0-005-020  12/08/23     DONE    DONE       DONE      11/08/23   11/06/23   09/27/23   05/16/23   2,16                     100,000       100,000  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         11/06/23           
  -       Reconstruction               0-005-021                                              /  /       /  /     02/02/24     /  /     155,16                         0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
  -       Reconstruction               5-014-008                                              /  /       /  /     04/03/24     /  /     2,9,14,15,16                   0             0  JJH             0           0           0                                         0        /  /                           /  /             

          XXPress Box  Demo:
22-0709   Reconstruction               7-008-002  02/07/23     DONE    DONE       DONE      10/12/22   10/11/22   07/27/22   03/30/22                             18,606             0  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/11/22           

          Concession Stand-Fenner Rd. Complex:
20-0350   Reconstruction               7-012-005  12/04/20     DONE    DONE       DONE      09/04/20   01/14/20   05/21/20   01/14/20   16                         7,406             0  JSS             0           0           0 Tetra Tech Architects and Eng       7,406      02/08/23                       01/14/20           

          Buckley Field Utility Bldg.:
22-0710   Reconstruction               7-013-003  02/07/23     DONE    DONE       DONE      10/12/22   10/11/22   08/10/22   03/30/22   2,16                      76,743             0  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/11/22           

          Press Box (New):
  -    PR New Construction             7-016-001                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0711   New Construction             7-016-001  02/07/23     DONE    DONE       DONE      10/12/22   10/11/22     /  /     03/30/22   02 - 16                  216,504             0  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/11/22           

          District-Wide:
19-0735   Reconstruction               7-999-003  11/15/19     DONE    DONE       DONE      11/07/19   10/29/19   10/03/19   05/21/19   8,16                     100,000       100,000  JSS             0           0           0 Tetra Tech Architects and Eng           0      08/27/20                       10/29/19           
  -    XX Reconstruction               7-999-004                         CANCELLED            /  /       /  /     02/27/20     /  /     16                             0             0  JSS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DERUYTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-03-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building K-12:
18-1947   Reconstruction               0-001-013  09/30/19     DONE    DONE       DONE      05/13/19   05/09/19   02/06/19   12/06/18   2,4,7,8,9,10,155,15,   4,818,330     4,818,330  SLC             0           0           0 March Associates                        0      09/30/20                       05/09/19           
19-1460   Reconstruction               0-001-014  04/09/20     DONE    DONE       DONE      02/21/20   02/18/20   10/10/19   05/21/19   4                        100,000       100,000  SLC             0           0           0 March Associates                        0      06/29/20                       02/18/20           
20-1564   Reconstruction               0-001-015  06/14/21     DONE    DONE       DONE      04/07/21   03/31/21   12/01/20   06/09/20   10,15                    100,000       100,000  SLC             0           0           0 March Associates                        0      06/29/21                       03/31/21           
21-1266   Reconstruction               0-001-016  03/08/22     DONE    DONE       DONE      02/11/22   02/09/22   01/14/22   04/19/21   9,10,155,16              100,000       100,000  SLC             0           0           0 King & King Architects                  0      06/30/22                       02/09/22           
22-0136FA Reconstruction               0-001-017  01/28/23     DONE    DONE       DONE      07/25/22   07/22/22   05/26/22   07/13/22   2                        200,000             0  SLC             0           0           0 Ashley McGraw                           0      10/15/23                       07/22/22           
23-0804   Reconstruction               0-001-018               UNREVIEWED
                                                                       DONE       UNREVIEWED10/25/23   10/19/23   06/02/22   09/13/23   4,8,9,155,15,16                0             0  MSK             0           0           0 Ashley McGraw                           0        /  /                         10/19/23           
22-0381   Reconstruction               0-001-019  11/23/22     DONE    DONE       DONE      08/31/22   08/30/22   07/18/22   05/17/22   16                       100,000       100,000  SLC             0           0           0 Ashley McGraw                           0      06/27/23                       08/30/22           
22-1573SB Reconstruction               0-001-020               DONE                           /  /       /  /     01/30/23     /  /     8,16                           0    16,158,552  SLC             0           0           0                                         0        /  /                           /  /             
23-1600   Reconstruction               0-001-020                         UNREVIEWED         03/08/24   03/07/24   01/30/23   06/29/23   8,16                           0    16,158,552  MSK             0           0           0 Ashley McGraw                           0        /  /                         03/07/24           
23-0894   Reconstruction               0-001-021  01/16/24     DONE    DONE       DONE      11/06/23   10/25/23   06/12/23   05/16/23   9                        100,000       100,000  MSK             0           0           0 Ashley McGraw                           0        /  /                         10/25/23           
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Annex Building:
18-1948   Reconstruction               0-007-006  09/30/19     DONE    DONE       DONE      05/13/19   05/09/19   02/06/19   12/06/18   2,4,8,9,10,155,15,16      15,625        15,625  SLC             0           0           0 March Associates                        0      09/30/20                       05/09/19           

          XXStorage Barn Demolition:
19-0508   Reconstruction               2-005-002  09/30/19     DONE    DONE       DONE      09/30/19   09/25/19   09/05/19   12/06/18   2                         31,250             0  SLC             0           0           0 March Associates                        0      07/17/20                       09/25/19           

          Storage Building:
18-1949   New Construction             2-010-001  09/30/19     DONE    DONE       DONE      05/13/19   05/09/19   02/06/19   12/06/18   02 - 16                   69,500             0  SLC             0           0           0 March Associates                        0      07/17/20                       05/09/19           

          School Bus Garage:
18-1950   Reconstruction               5-002-005  09/30/19     DONE    DONE       DONE      05/13/19   05/09/19   02/06/19   12/06/18   2,4,8,9,10,14,16         388,750       388,750  SLC             0           0           0 March Associates                        0      09/30/20                       05/09/19           

          District-Wide:
20-0698   Reconstruction               7-999-001  02/02/21     DONE    DONE       DONE      10/28/20   10/06/20     /  /     05/26/20   13,16                    313,750             0  SLC             0           0           0 March Associates                        0      09/03/21                       10/06/20           
22-1526XX Reconstruction               7-999-002                         CANCELLED            /  /       /  /     01/23/23     /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MORRISVILLE EATON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-04-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Edward R Andrews ES:
19-0585   Reconstruction               0-003-019  12/23/19     DONE    DONE       DONE      10/21/19   10/08/19     /  /     05/21/19   8                        100,000       100,000  SLC             0           0           0 Ashley McGraw                           0      06/29/20                       10/08/19           
  -       Reconstruction               0-003-020                                              /  /       /  /     11/07/19     /  /     8                              0             0  SLC             0           0           0                                         0        /  /                           /  /             
20-1771   Reconstruction               0-003-021  07/09/21     DONE    DONE       DONE      05/25/21   05/21/21   04/28/21   05/18/21   15                       100,000       100,000  SLC             0           0           0 Ashley McGraw                           0      11/08/21                       05/21/21           
21-1528   Reconstruction               0-003-022  09/15/21     DONE    DONE       DONE      03/16/22   03/16/22   07/07/21   06/30/21   7                         16,500        16,500  SLC             0           0           0 Ashley McGraw                           0      09/29/21                       03/16/22           
22-2135   Reconstruction               0-003-023  08/04/23     DONE    DONE       DONE      05/03/23   05/02/23   04/07/23   12/13/22   15,16                     75,000        75,000  MSK             0           0           0 LaBella Associates P.C.                 0        /  /                         05/02/23           
23-0793   Reconstruction               0-003-024               STARTED STARTED    UNREVIEWED10/25/23   10/20/23   05/12/23   12/13/22   2,4,7,8,9,10,155,15,           0             0  MSK             0           0           0 LaBella Associates P.C.                 0        /  /                         10/20/23           
23-1247   Reconstruction               0-003-025  01/19/24     DONE    DONE       DONE      12/20/23   12/20/23   12/15/23   05/16/23   2,155,15,16              100,000       100,000  MSK             0           0           0 LaBella Associates P.C.                 0        /  /                         12/20/23           

          Jr/Sr High School:
20-1399   Reconstruction               0-005-018  04/26/21     DONE    DONE       DONE      03/09/21   03/04/21   02/22/21   06/16/20   155                      100,000       100,000  SLC             0           0           0 Ashley McGraw                           0      06/15/21                       03/04/21           
21-0671   Reconstruction               0-005-019  05/27/21     DONE    DONE       DONE      11/10/21   11/09/21   07/07/21   06/30/21   16                        53,500        53,500  SLC             0           0           0 King & King Architects                  0      11/24/21                       11/09/21           
22-2074   Reconstruction               0-005-020  05/22/23     DONE    DONE       DONE      04/19/23   04/19/23   06/14/22   05/17/22   155                      100,000       100,000  JLB             0           0           0 LaBella Associates P.C.                 0        /  /                         04/19/23           
22-2136   Reconstruction               0-005-021  08/04/23     DONE    DONE       DONE      05/03/23   03/02/23   03/27/23   12/13/22   2,16                     553,800       553,800  MSK             0           0           0 LaBella Associates P.C.                 0        /  /                         03/02/23           
23-0794   Reconstruction               0-005-022               STARTED STARTED    UNREVIEWED10/25/23   10/20/23   05/12/23   12/13/22   2,4,8,9,10,155,15,16           0             0  MSK             0           0           0 LaBella Associates P.C.                 0        /  /                         10/20/23           

          Pop Warner Shed:
  -    DB Discovered Building          2-018-001                                              /  /       /  /     11/18/19     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          High School Bus Garage:
23-0795   Reconstruction               5-001-008               STARTED STARTED    UNREVIEWED10/25/23   10/20/23   05/12/23   12/13/22   2,7,10,14                      0             0  MSK             0           0           0 LaBella Associates P.C.                 0        /  /                         10/20/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HAMILTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-07-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Bldg:
19-0150   Reconstruction               0-003-010  09/30/19     DONE    DONE       DONE      07/23/19   07/18/19   04/30/19   12/18/18   2,4,7,9,155,15,16      7,500,000     7,500,000  JSS             0           0           0 King & King Architects                  0      08/28/20                       07/18/19           
19-1775   Reconstruction               0-003-011  09/08/20     DONE    DONE       DONE      05/27/20   05/11/20   04/23/20   12/18/18   8                        308,330       308,330  JLB             0           0      33,703 King & King Architects                  0      11/08/21                       05/11/20           
21-0362   Reconstruction               0-003-012  01/18/22     DONE    DONE       DONE      09/15/21   09/14/21   12/19/20   12/18/18   2,4,7,8,9,10,155,15,   7,602,000     7,602,000  JLB             0           0           0 King & King Architects                  0      04/28/23                       09/14/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CANASTOTA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-09-01-06
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Roberts Street School Complex:
20-0183   Reconstruction               0-001-025  11/23/20     DONE    DONE       DONE      08/12/20   07/23/20   12/18/19   12/05/19   2,4,7,8,9,10,155,15,  18,899,700    18,899,700  SLC             0           0           0 King & King Architects                  0        /  /                         07/23/20           
20-0002   Reconstruction               0-001-026  08/10/20     DONE    DONE       DONE      07/01/20   06/26/20   02/24/20   06/16/20   2,9                      100,000       100,000  SLC             0           0           0 King & King Architects                  0      04/15/21                       06/26/20           
20-1343   Reconstruction               0-001-027  05/26/21     DONE    DONE       DONE      02/22/21   02/05/21   12/18/20   05/18/21   2,9                      100,000       100,000  SLC             0           0           0 King & King Architects                  0      08/13/21                       02/05/21           
21-1303   Reconstruction               0-001-028  07/27/22     DONE    DONE       DONE      02/16/22   02/10/22   12/23/21   12/05/19   7,155,16                 500,000       500,000  WLC             0           0           0 King & King Architects                  0      08/18/23                       02/10/22           
22-0423   Reconstruction               0-001-029  02/13/23     DONE    DONE       DONE      09/07/22   09/02/22   09/07/22   05/17/22   2,9                      100,000       100,000  WLC             0           0           0 King & King Architects                  0      05/01/23                       09/02/22           

          South Side School:
20-0184   Reconstruction               0-004-011  11/23/20     DONE    DONE       DONE      08/12/20   07/23/20   12/18/19   12/05/19   2,4,7,8,9,155,15,16    3,365,700     3,365,700  SLC             0           0           0 King & King Architects                  0        /  /                         07/23/20           

          Peterboro Street School:
18-2125   Reconstruction               0-005-015  07/10/19     DONE    DONE       DONE      06/13/19   06/11/19   03/13/19   05/21/19   2,8                      100,000       100,000  SLC             0           0           0 King & King Architects                  0      06/01/20                       06/11/19           
20-0185   Reconstruction               0-005-016  11/23/20     DONE    DONE       DONE      08/12/20   07/23/20   12/18/19   12/05/19   2,4,7,8,9,10,155,15,   2,589,000     2,589,000  SLC             0           0           0 King & King Architects                  0        /  /                         07/23/20           
22-2310   Reconstruction               0-005-017  07/05/23     DONE    DONE       DONE      05/31/23   05/31/23   04/13/23   05/16/23   9                        100,000       100,000  WLC             0           0           0 King & King Architects                  0        /  /                         05/31/23           
23-1497   Reconstruction               0-005-018               STARTED DONE       DONE      02/15/24   02/14/24     /  /       /  /     9                        100,000             0  WLC             0           0           0 King & King Architects                  0        /  /                         02/14/24           

          Bus Garage (fmly 0-002):
20-0186   Reconstruction               5-002-010  11/23/20     DONE    DONE       DONE      08/12/20   07/23/20   12/18/19   12/05/19   2,4,8,9,10,155,15,16   1,035,600     1,035,600  SLC             0           0           0 King & King Architects                  0        /  /                         07/23/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MADISON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-11-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main K-12 Building:
  -       Reconstruction               0-001-022                                              /  /       /  /     02/14/22     /  /     2                              0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-1124   Reconstruction               0-001-023  03/29/23     DONE    DONE       DONE      12/02/22   11/30/22   10/19/22   05/17/22   2,7,8,9,10,155,15,16   6,100,000     6,100,000  JLB             0           0           0 March Associates                        0        /  /                         11/30/22           
  -    SB Reconstruction               0-001-BA5               DONE                           /  /       /  /     03/06/23     /  /     10                             0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ONEIDA CITY SD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-14-00-01
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
19-0085   Reconstruction               0-001-019  08/29/19     DONE    DONE       DONE      07/16/19   07/10/19     /  /     05/21/19   8,9,16                   100,000       100,000  BMJ             0           0           0 King & King Architects                  0      05/29/20                       07/10/19           
  -    PR Additions and Alterations    0-001-020                                              /  /       /  /     02/01/21     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
21-0369   Additions and Alterations    0-001-020  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   02 - 16               12,479,850    10,793,070  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           
22-2282   Reconstruction               0-001-021  07/12/23     DONE    DONE       DONE      05/24/23   05/23/23   03/10/23   05/16/23   155,16                   100,000       100,000  MSK             0           0           0 King & King Architects                  0        /  /                         05/23/23           
23-0072   Reconstruction               0-001-022  11/09/23     DONE    DONE       DONE      07/14/23   07/12/23   06/16/23   12/09/20   9                         75,000        75,000  JLB             0           0           0 King & King Architects                  0        /  /                         07/12/23           

          Willard F Prior Elementary:
20-0191   Reconstruction               0-004-008  10/11/20     DONE    DONE       DONE      08/12/20   08/07/20   05/15/20   06/09/20   8,9,16                   100,000       100,000  SLC             0           0           0 King & King Architects                  0      04/09/21                       08/07/20           
21-0370   Reconstruction               0-004-009  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   2,4,8,9,155,15,16      1,642,000     1,642,000  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           
23-0073   Reconstruction               0-004-010  11/09/23     DONE    DONE       DONE      07/14/23   07/12/23   06/16/23   12/09/20   155,16                   240,000       240,000  JLB             0           0           0 King & King Architects                  0        /  /                         07/12/23           

          North Broad Street:
21-0371   Reconstruction               0-005-013  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   2,4,8,9,10,155,15,16   1,450,000     1,450,000  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           

          Seneca Street School:
21-0372   Reconstruction               0-006-011  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   2,4,8,9,10,155,15,16   1,350,000     1,350,000  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           

          Durhamville Elementary School:
21-0373   Reconstruction               0-008-009  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   2,4,8,9,155,15,16      1,570,000     1,570,000  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           
21-0381   Reconstruction               0-008-010  12/14/21     DONE    DONE       DONE      09/20/21   09/17/21   06/21/21   05/18/21   9                        100,000       100,000  SLC             0           0           0 King & King Architects                  0      06/02/22                       09/17/21           
23-0074   Reconstruction               0-008-011  11/09/23     DONE    DONE       DONE      07/14/23   07/12/23   06/16/23   12/09/20   155,16                   240,000       240,000  JLB             0           0           0 King & King Architects                  0        /  /                         07/12/23           

          Otto Shortell Middle School:
21-0374   Reconstruction               0-010-010  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   2,8,9,10,155,15,16     2,765,000     2,765,000  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           
22-0129   Reconstruction               0-010-011  10/05/22     DONE    DONE       DONE      07/22/22   07/20/22   06/09/22   05/17/22   9,10                     100,000       100,000  SLC             0           0           0 King & King Architects                  0      06/21/23                       07/20/22           
23-0075   Reconstruction               0-010-012  11/09/23     DONE    DONE       DONE      07/14/23   07/12/23   06/16/23   12/09/20   155,16                   235,000       235,000  JLB             0           0           0 King & King Architects                  0        /  /                         07/12/23           

          2003 Bus Maintenance Garage:
21-0375   Reconstruction               5-024-003  02/22/22     DONE    DONE       DONE      09/17/21   09/16/21   02/01/21   12/09/20   8,9,155,16               343,150       343,150  SLC             0           0           0 King & King Architects                  0        /  /                         09/16/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




STOCKBRIDGE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-15-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Building (Main Building):
19-0206   Reconstruction               0-010-008  08/07/19     DONE    DONE       DONE      08/01/19   08/01/19   07/18/19   06/11/19   16                       100,000       100,000  JSS             0           0           0 Bernier Carr & Associates               0      03/25/20                       08/01/19           
19-1778   Reconstruction               0-010-009  08/13/20     DONE    DONE       DONE      05/28/20   05/07/20   12/17/19   12/16/14                            127,740       127,740  JLB             0           0           0 Bernier Carr Associates                 0      07/06/21                       05/07/20           
21-0244   Reconstruction               0-010-010  08/30/21     DONE    DONE       DONE      08/30/21   08/30/21   05/17/21   03/10/15   8,155,16                 375,000       375,000  SLC             0           0           0 King & King Architects                  0      02/02/22                       08/30/21           
23-0824   Reconstruction               0-010-011               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/30/23   10/25/23   04/18/23   03/14/23   2,4,7,8,9,155,15,16            0             0  MSK             0           0           0 King & King Architects                  0        /  /                         10/25/23           

          Greenhouse/Ag. Lab:
23-0825   Reconstruction               0-014-005               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/30/23   10/25/23   04/18/23   03/14/23   7,8,155,16                     0       144,630  MSK             0           0           0 King & King Architects                  0        /  /                         10/25/23           

          Bus Garage:
  -       Reconstruction               5-013-006                                              /  /       /  /     12/17/19     /  /     16                             0             0  JSS             0           0           0                                         0        /  /                           /  /             
23-0826   Reconstruction               5-013-007               UNREVIEWED
                                                                       STARTED    UNREVIEWED10/30/23   10/25/23   04/18/23   03/14/23   2,155,15,16                    0             0  MSK             0           0           0 King & King Architects                  0        /  /                         10/25/23           

          District-Wide:
  -    SB Reconstruction               7-999-BA2               DONE                           /  /       /  /       /  /       /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHITTENANGO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-16-01-06
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
19-1891   Reconstruction               0-001-024  07/27/20     DONE    DONE       DONE      06/29/20   06/16/20   03/20/20   06/09/20   7                        100,000       100,000  JSS             0           0           0 King & King Architects                  0      09/01/20                       06/16/20           
21-1326   Reconstruction               0-001-025  03/15/22     DONE    DONE       DONE      02/17/22   02/11/22   12/02/21   05/16/17   9,16                     490,000       490,000  JLB             0           0           0 King & King Architects                  0      09/01/22                       02/11/22           
22-0944   Reconstruction               0-001-026  03/03/23     DONE    DONE       DONE      11/09/22   11/07/22   07/06/22   11/01/22   2,7                    4,500,000     4,500,000  JJH             0           0           0 King & King Architects                  0      10/11/23                       11/07/22           
22-2257   Reconstruction               0-001-027  06/29/23     DONE    DONE       DONE      05/22/23   05/18/23   02/21/23   05/16/23   16                       100,000       100,000  JJH             0           0           0 King & King Architects                  0      01/02/24                       05/18/23           
23-0169   Reconstruction               0-001-028  01/25/24     DONE    DONE       DONE      07/28/23   07/28/23   03/20/23   11/01/22   2,4,7,8,9,155,15,16   14,107,000    12,610,200  JJH             0           0           0 King & King Architects                  0        /  /                         07/28/23           

          Bolivar Road Elementary:
23-0170   Reconstruction               0-003-014  01/25/24     DONE    DONE       DONE      07/28/23   07/28/23   03/20/23   11/01/22   2,4,7,8,9,155,15,16    1,087,000     1,087,000  JJH             0           0           0 King & King Architects                  0        /  /                         07/28/23           

          Bridgeport Elementary:
19-0030   Reconstruction               0-004-015  07/31/19     DONE    DONE       DONE      07/08/19   06/28/19   05/31/19   05/22/19   155                      100,000       100,000  JSS             0           0           0 King & King Architects                  0      06/10/20                       06/28/19           
23-0171   Reconstruction               0-004-016  01/25/24     DONE    DONE       DONE      07/28/23   07/28/23   03/20/23   11/01/22   2,4,7,8,9,155,15,16    4,351,000     4,351,000  JJH             0           0           0 King & King Architects                  0        /  /                         07/28/23           

          Chittenango Middle School:
20-1845   Reconstruction               0-005-015  06/25/21     DONE    DONE       DONE      06/07/21   06/03/21   04/14/21   05/18/21   16                       100,000       100,000  JLB             0           0           0 King & King Architects                  0      03/01/21                       06/03/21           
21-1874   Reconstruction               0-005-016  06/30/22     DONE    DONE       DONE      05/23/22   05/23/22   04/20/22   05/17/22   9                        100,000       100,000  JLB             0           0           0 King & King Architects                  0      09/01/22                       05/23/22           
23-0172   Reconstruction               0-005-017  01/25/24     DONE    DONE       DONE      07/28/23   07/28/23   03/20/23   11/01/22   2,4,7,8,9,155,15,16    2,175,000     2,175,000  JJH             0           0           0 King & King Architects                  0        /  /                         07/28/23           

          Bus Garage:
23-0173   Reconstruction               5-015-003  01/25/24     DONE    DONE       DONE      07/28/23   07/28/23   03/20/23   11/01/22   155,16                    30,000        30,000  JJH             0           0           0 King & King Architects                  0        /  /                         07/28/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES MADISON-ONEIDA STATUS REPORT ON CAPITAL PROJECTS
District No.: 25-90-00-00
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Rossetti Occup. Ed. Center:
18-1702   Reconstruction               0-002-018  05/10/19     DONE    DONE       DONE      03/22/19   03/18/19   10/30/18   11/01/18   8,9,155,15,16            900,605       900,605  JLB             0           0           0 King & King Architects                  0      01/21/21                       03/18/19           
20-1540   Reconstruction               0-002-019  04/08/21     DONE    DONE       DONE      04/05/21   04/02/21   02/10/21   03/05/21   2,7,9,155,16             608,678       608,678  JSS             0           0           0 King & King Architects                  0      02/23/23                       04/02/21           
21-1739   Reconstruction               0-002-020  06/03/22     DONE    DONE       DONE      05/02/22   04/27/22   02/14/22   03/04/22   2,7,9,155,16             669,704       669,704  JLB             0           0           0 King & King Architects                  0      12/15/23                       04/27/22           
22-1342   Reconstruction               0-002-021  05/04/23     DONE    DONE       DONE      12/27/22   12/23/22   10/06/22   11/03/22   2,4,7,8,9,10,155,15,   3,150,256     3,150,256  WLC             0           0           0 King & King Architects                  0        /  /                         12/23/22           

          MVCC Leased Space:
  -    TQ Temporary Quarters           8-040-001                                              /  /       /  /     05/03/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Utica Center for Development:
  -    TQ Temporary Quarters           8-041-001                                              /  /       /  /     05/03/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          NYS School for the Deaf:
  -    TQ Temporary Quarters           8-042-001                                              /  /       /  /     08/03/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED