GLEN COVE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-01-00-01
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Finley Middle School:
19-1820 Reconstruction 0-003-016 07/30/20 DONE DONE DONE 06/08/20 06/04/20 04/22/19 05/21/19 10 100,000 0 SLC 0 0 0 Mark Design Studios 0 02/16/22 06/04/20
20-0578 Reconstruction 0-003-018 01/16/21 DONE DONE DONE 10/13/20 09/30/20 06/22/20 06/09/20 10,16 282,000 282,000 SLC 0 0 0 Mark Design Studios 0 12/10/21 09/30/20
20-0579 Reconstruction 0-003-019 01/16/21 DONE DONE DONE 10/13/20 09/30/20 06/22/20 06/09/20 2,8,9,10,15,16 122,000 122,000 SLC 0 0 0 Mark Design Studios 0 05/05/22 09/30/20
20-0517 Reconstruction 0-003-020 12/15/20 DONE DONE DONE 10/05/20 08/20/20 07/17/20 05/21/19 2,155,16 250,000 0 SLC 0 0 0 Mark Design Studios 0 / / 08/20/20
21-0442 Reconstruction 0-003-021 01/21/23 DONE DONE DONE 09/29/21 09/28/21 05/24/21 05/18/21 2,8,9,10,155,15,16 100,000 100,000 SLC 0 0 0 Mark Design Studios 0 / / 09/28/21
21-1443 Reconstruction 0-003-022 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 599,087 599,087 SLC 0 0 0 ECG Engineering, LLC 599,087 / / 03/07/22
- Reconstruction 0-003-023 / / / / 06/29/22 / / 2,8 0 0 SLC 0 0 0 0 / / / /
22-0503 Reconstruction 0-003-024 01/09/23 DONE DONE DONE 09/16/22 09/15/22 07/06/22 05/17/22 2,4,155,16 700,000 700,000 SLC 0 0 0 John A. Grillo 0 / / 09/15/22
22-2045 Reconstruction 0-003-025 06/15/23 DONE DONE DONE 04/17/23 03/01/23 12/07/22 12/06/22 8 427,594 427,594 MSK 0 0 0 John A. Grillo 0 / / 03/01/23
23-1257 Reconstruction 0-003-026 UNREVIEWED 12/21/23 12/21/23 06/07/23 05/16/23 16 0 0 MSK 0 0 0 John A. Grillo 0 / / 12/21/23
Deasy School:
19-1344 Reconstruction 0-005-009 03/31/20 DONE DONE DONE 02/03/20 01/27/20 11/18/19 05/21/19 16 140,000 140,000 SLC 0 0 0 Mark Design Studios 0 / / 01/27/20
20-1095 Reconstruction 0-005-010 02/10/21 DONE DONE DONE 01/07/21 01/06/21 10/21/20 12/16/20 4,155,16 550,000 550,000 SLC 0 0 0 Mark Design Studios 0 / / 01/06/21
21-1444 Reconstruction 0-005-011 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 380,521 380,521 SLC 0 0 0 ECG Engineering, LLC 380,521 / / 03/07/22
- Reconstruction 0-005-012 / / / / 07/06/22 / / 16 0 0 SLC 0 0 0 0 / / / /
- PR Additions and Alterations 0-005-013 / / / / 08/01/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1720FC Additions and Alterations 0-005-013 04/24/23 DONE DONE DONE 02/22/23 01/24/23 08/01/22 05/17/22 02 - 16 8,788,229 4,096,235 JLB 0 0 0 John A. Grillo 0 / / 01/24/23
22-2046 Reconstruction 0-005-014 06/15/23 DONE DONE DONE 04/17/23 03/01/23 12/07/22 12/06/22 8 200,000 200,000 MSK 0 0 0 John A. Grillo 0 / / 03/01/23
Connolly Elementary School:
20-0580 Reconstruction 0-007-016 01/16/21 DONE DONE DONE 10/13/20 09/30/20 06/22/20 06/09/20 2,8,9,10,15,16 70,000 70,000 SLC 0 0 0 Mark Design Studios 0 05/02/22 09/30/20
21-0443 Reconstruction 0-007-017 01/21/23 DONE DONE DONE 09/29/21 09/28/21 05/24/21 05/18/21 2,8,9,10,155,15,16 250,000 250,000 SLC 0 0 0 Mark Design Studios 0 / / 09/28/21
21-1445 Reconstruction 0-007-018 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 889,377 889,377 SLC 0 0 0 ECG Engineering, LLC 889,377 / / 03/07/22
22-2047 Reconstruction 0-007-019 06/15/23 DONE DONE DONE 04/17/23 03/01/23 12/07/22 12/06/22 8 200,000 200,000 MSK 0 0 0 John A. Grillo 0 / / 03/01/23
Landing Elementary School:
19-0567 Reconstruction 0-008-015 02/11/20 DONE DONE DONE 10/17/19 09/30/19 07/15/19 05/21/19 7,16 160,000 160,000 SLC 0 0 0 Mark Design Studios 0 10/28/20 09/30/19
21-1446 Reconstruction 0-008-016 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 482,184 482,184 SLC 0 0 0 ECG Engineering, LLC 482,184 / / 03/07/22
- Reconstruction 0-008-017 / / / / 06/29/22 / / 2 0 0 SLC 0 0 0 0 / / / /
- PR Additions and Alterations 0-008-018 / / / / 08/01/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1721FA Additions and Alterations 0-008-018 04/24/23 DONE DONE DONE 02/22/23 01/24/23 08/01/22 05/17/22 02 - 16 5,778,228 5,022,621 JLB 0 0 0 John A. Grillo 0 / / 01/24/23
22-2048 Reconstruction 0-008-019 06/15/23 DONE DONE DONE 04/17/23 03/01/23 12/07/22 12/06/22 8 200,000 200,000 MSK 0 0 0 John A. Grillo 0 / / 03/01/23
Glen Cove High School:
19-0928 Reconstruction 0-010-024 04/01/20 DONE DONE DONE 12/05/19 10/18/19 04/22/19 05/21/19 10 150,000 150,000 SLC 0 0 0 Mark Design Studios 0 01/29/21 10/18/19
20-0581 Reconstruction 0-010-025 01/16/21 DONE DONE DONE 10/13/20 09/30/20 06/22/20 06/16/20 10,155,16 126,000 126,000 SLC 0 0 0 Mark Design Studios 0 10/15/21 09/30/20
- XX Additions and Alterations 0-010-026 CANCELLED / / / / 03/12/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
- Additions and Alterations 0-010-027 / / / / 03/12/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
20-1444SB Additions and Alterations 0-010-027 DONE / / / / 03/12/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-0444 Reconstruction 0-010-028 01/21/23 DONE DONE DONE 09/29/21 09/28/21 05/24/21 05/18/21 7,8,155,15,16 400,000 400,000 SLC 0 0 0 Mark Design Studios 0 / / 09/28/21
21-0445 Reconstruction 0-010-029 01/21/23 DONE DONE DONE 09/29/21 09/28/21 05/24/21 05/18/21 8,10,15,16 100,000 100,000 SLC 0 0 0 Mark Design Studios 0 / / 09/28/21
21-1447 Reconstruction 0-010-030 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 3,055,005 3,055,005 SLC 0 0 0 ECG Engineering, LLC 3,033,905 / / 03/07/22
- Reconstruction 0-010-031 / / / / 01/19/22 / / 2,155,15,16 0 0 SLC 0 0 0 0 / / / /
- Reconstruction 0-010-032 / / / / 06/29/22 / / 2,8,155,15,16 0 0 SLC 0 0 0 0 / / / /
22-2049 Reconstruction 0-010-033 06/15/23 DONE DONE DONE 04/17/23 03/01/23 12/07/22 12/06/22 2,8,13 3,763,799 3,763,799 MSK 0 0 0 John A. Grillo 0 / / 03/01/23
22-2154 Reconstruction 0-010-034 07/26/23 DONE DONE DONE 05/05/23 05/05/23 12/27/22 12/06/22 2,8 2,635,131 2,635,131 MSK 0 0 0 John A. Grillo 0 / / 05/05/23
23-1029 Reconstruction 0-010-035 UNREVIEWED 11/16/23 11/15/23 06/07/23 12/06/22 2,4,7,8,9,10,13,155, 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/15/23
Eugene J. Gribbin Elementary:
21-1448 Reconstruction 0-013-010 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 780,447 780,447 SLC 0 0 0 ECG Engineering, LLC 780,447 / / 03/07/22
22-2050 Reconstruction 0-013-011 06/15/23 DONE DONE DONE 04/17/23 04/17/23 12/07/22 12/06/22 8 200,000 200,000 MSK 0 0 0 John A. Grillo 0 / / 04/17/23
Thayer House:
21-1449 Reconstruction 1-001-007 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 15,027 0 SLC 0 0 0 ECG Engineering, LLC 15,027 / / 03/07/22
Carriage House:
21-1450 Reconstruction 1-002-004 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 4,736 0 SLC 0 0 0 ECG Engineering, LLC 4,736 / / 03/07/22
BusGarage-NextProjUse3-009Bldgs&Grds:
21-1451 Reconstruction 5-009-006 12/30/22 DONE DONE DONE 03/07/22 03/07/22 09/27/21 10/20/21 16 13,854 13,854 SLC 0 0 0 ECG Engineering, LLC 13,854 / / 03/07/22
Supplemental Nurse Fac @ Connolly:
20-0821 Reconstruction 7-023-001 02/19/21 DONE DONE DONE 11/16/20 11/16/20 10/15/20 11/04/20 227,340 0 SLC 0 0 0 Mark Design Studios 0 02/17/21 11/16/20
Supplemental Nurse Fac @ Landing:
20-0822 Reconstruction 7-024-001 02/19/21 DONE DONE DONE 11/16/20 11/16/20 10/15/20 11/04/20 227,340 0 SLC 0 0 0 Mark Design Studios 0 02/17/21 11/16/20
Supplemental Nurse Fac @ Gribbin:
20-0823 Reconstruction 7-025-001 02/19/21 DONE DONE DONE 11/16/20 11/16/20 10/15/20 11/04/20 227,340 0 SLC 0 0 0 Mark Design Studios 0 02/17/21 11/16/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HEMPSTEAD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-01-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School (AlvertaB Gray Schultz:
20-0639 Reconstruction 0-001-027 06/02/22 DONE DONE DONE 10/20/20 10/02/20 05/15/20 11/21/19 155,15,16 3,932,003 3,932,003 SLC 0 0 0 Burton Behrendt Smith 3,879,790 / / 10/02/20
22-0675 Reconstruction 0-001-028 02/06/23 DONE DONE DONE 10/07/22 10/06/22 06/15/22 05/17/22 2,4,7 3,073,885 3,073,885 SLC 0 0 0 Burton Behrendt Smith 0 / / 10/06/22
- PR Additions and Alterations 0-001-029 / / / / 06/15/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
23-0673 Additions and Alterations 0-001-029 UNREVIEWED
STARTED UNREVIEWED10/11/23 10/03/23 06/15/22 05/17/22 02 - 16 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 10/03/23
McNeil ES (Franklin Street):
- PR Reconstruction 0-002-015 STARTED / / / / 07/09/19 / / 0 13,273,542 SLC 0 0 0 0 / / / /
20-0640 Reconstruction 0-002-016 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 915,360 915,360 SLC 0 0 0 Burton Behrendt Smith 874,418 / / 10/02/20
- Reconstruction 0-002-017 / / / / 12/07/21 / / 2,7 0 0 SLC 0 0 0 0 / / / /
Paterson ES (Fulton Street):
- PR Reconstruction 0-003-016 STARTED / / / / / / / / 0 0 SLC 0 0 0 0 / / / /
20-0641 Reconstruction 0-003-017 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 81,033 81,033 SLC 0 0 0 Burton Behrendt Smith 80,319 / / 10/02/20
22-0676FC Reconstruction 0-003-018 02/06/23 DONE DONE DONE 10/07/22 10/06/22 11/23/21 05/17/22 2,7 2,067,501 2,067,501 SLC 0 0 0 Burton Behrendt Smith 0 / / 10/06/22
Jackson Elem Main School:
20-0642 Reconstruction 0-004-015 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 169,687 169,687 SLC 0 0 0 Burton Behrendt Smith 161,960 / / 10/02/20
- Reconstruction 0-004-016 / / / / 12/07/21 / / 2,7 0 0 SLC 0 0 0 0 / / / /
22-0591 Reconstruction 0-004-017 01/28/23 DONE DONE DONE 09/26/22 09/26/22 06/15/22 05/17/22 2,8 883,750 883,750 SLC 0 0 0 Burton Behrendt Smith 0 / / 09/26/22
Jackson Annex:
20-0643 Reconstruction 0-005-012 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 42,094 42,094 SLC 0 0 0 Burton Behrendt Smith 40,778 / / 10/02/20
Barack Obama ES (Ludlam):
20-0644 Reconstruction 0-006-017 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 852,407 852,407 SLC 0 0 0 Burton Behrendt Smith 823,712 / / 10/02/20
22-0592 Reconstruction 0-006-018 01/28/23 DONE DONE DONE 09/26/22 09/26/22 06/15/22 05/17/22 2,8 1,055,280 1,055,280 SLC 0 0 0 Burton Behrendt Smith 0 / / 09/26/22
Marshall School:
20-0645 Reconstruction 0-007-015 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 107,762 0 SLC 0 0 0 Burton Behrendt Smith 105,710 / / 10/02/20
Jack Annex Temp Demolition:
20-0427 Reconstruction 0-013-001 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 134,370 0 SLC 0 0 0 Burton Behrendt Smith 0 11/21/22 09/08/20
Jack Annex Temp W Demolition:
20-0428 Reconstruction 0-015-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 212,752 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 09/08/20
Jack Annex/So. Port Demolition:
20-0429 Reconstruction 0-017-004 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 134,370 0 SLC 0 0 0 Burton Behrendt Smith 0 11/21/22 09/08/20
Senior High School:
20-0646 Reconstruction 0-020-029 06/02/22 DONE DONE DONE 10/20/20 10/02/20 01/15/20 11/21/19 155,15,16 4,650,667 4,650,667 SLC 0 0 0 Burton Behrendt Smith 4,545,856 / / 10/02/20
22-0677 Reconstruction 0-020-030 02/06/23 DONE DONE DONE 10/07/22 10/06/22 06/15/22 05/17/22 2,4,7 9,780,638 9,780,638 SLC 0 0 0 Burton Behrendt Smith 0 / / 10/06/22
22-1378 Reconstruction 0-020-031 03/10/23 DONE DONE DONE 01/03/23 12/29/22 06/15/22 05/17/22 2,9,13,14,155,16 6,698,000 6,698,000 JLB 0 0 0 Burton Behrendt Smith 0 08/16/23 12/29/22
Port #3 @ Jack Annex Demolition:
20-0430 Reconstruction 0-078-003 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 212,752 0 SLC 0 0 0 Burton Behrendt Smith 0 11/21/22 09/08/20
Multiple Portables #2 @ ABGS Demo:
22-1973 Reconstruction 0-081-002 05/02/23 DONE DONE DONE 03/31/23 03/30/23 10/17/22 05/17/22 2,16 123,585 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 03/30/23
Multiple Portables #3 @ ABGS Demo:
22-1974 Reconstruction 0-082-002 05/02/23 DONE DONE DONE 03/31/23 03/30/23 10/17/22 05/17/22 2,16 123,585 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 03/30/23
Modular Bldg rm913-14 Demo:
22-1975 Reconstruction 0-083-002 05/02/23 DONE DONE DONE 03/31/23 03/30/23 10/17/22 05/17/22 2,16 61,790 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 03/30/23
Portable @ Franklin Demolition:
20-0431 Reconstruction 0-084-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 134,370 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 09/08/20
Port #1 @ Jack Main Demolition:
20-0432 Reconstruction 0-086-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 134,370 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 09/08/20
Port #2 @ Jack Main Demolition:
20-0433 Reconstruction 0-087-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 134,370 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 09/08/20
New Rhodes Elem School P-5:
18-1482 New Construction 0-092-001 06/14/19 DONE DONE DONE 02/20/19 02/19/19 12/16/15 05/15/18 02 - 16 42,508,688 16,791,400 SLC 0 0 2,116,293 Burton Behrendt Smith 0 12/14/22 02/19/19
St.LadislausConvent-LsdPupilPersonne:
17-1908TQ Temporary Quarters 1-029-002 12/17/20 DONE DONE DONE 05/31/18 / / 05/29/18 / / 0 0 SLC 0 0 0 0 / / / /
Grounds Blue Storage Container:
- DB Discovered Building 2-095-001 / / / / 07/08/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC 20290:
- DB Discovered Building 2-096-001 / / / / 07/08/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC9992:
- DB Discovered Building 2-097-001 / / / / 07/08/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC25759:
- DB Discovered Building 2-098-001 / / / / 07/08/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC10389:
- DB Discovered Building 2-099-001 / / / / 07/08/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Conatiner CC24668:
- DB Discovered Building 2-100-001 / / / / 07/09/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC24634:
- DB Discovered Building 2-101-001 / / / / 07/09/20 / / 0 0 SLC 0 0 0 0 / / / /
XXStorage Container CC6178:
- XX Reconstruction 2-102-001 CANCELLED / / / / 07/09/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC3024:
- DB Discovered Building 2-103-001 / / / / 07/09/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CCH9305:
- DB Discovered Building 2-104-001 / / / / 07/09/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC7179:
- DB Discovered Building 2-105-001 / / / / 07/10/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC8798:
- DB Discovered Building 2-106-001 / / / / 07/10/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC9289:
- DB Discovered Building 2-107-001 / / / / 07/10/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC9991:
- DB Discovered Building 2-108-001 / / / / 07/10/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC24575:
- DB Discovered Building 2-109-001 / / / / 07/10/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC24761:
- DB Discovered Building 2-110-001 / / / / 07/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC22127:
- DB Discovered Building 2-111-001 / / / / 07/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC21871:
- DB Discovered Building 2-112-001 / / / / 07/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC21058:
- DB Discovered Building 2-113-001 / / / / 07/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC20666:
- DB Discovered Building 2-114-001 / / / / 07/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Storage Container CC10427:
- DB Discovered Building 2-115-001 / / / / 07/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Outdoor Restroom Facilities HS:
22-1380DB Discovered Building 7-021-001 ADDENDUM REQ'D 01/03/23 12/29/22 12/19/89 / / 02 - 16 0 0 MSK 0 0 0 0 / / 12/29/22
Fieldhouse/Press Box:
22-1381DB Discovered Building 7-035-001 ADDENDUM REQ'D 01/03/23 12/29/22 10/23/96 / / 0 0 MSK 0 0 0 0 / / 12/29/22
Press Box:
- PR New Construction 7-116-001 / / / / 11/15/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1379 New Construction 7-116-001 03/10/23 DONE DONE DONE 01/03/23 12/29/22 11/15/22 05/17/22 02 - 16 270,000 0 JLB 0 0 0 Burton Behrendt Smith 0 09/15/23 12/29/22
St. Ladislaus Elem (Front St.) Schoo:
17-1907TQ Temporary Quarters 8-027-002 12/17/20 DONE DONE DONE 05/31/18 / / 05/29/18 / / 0 6,495,114 SLC 0 0 0 0 / / / /
- PR Reconstruction 8-027-003 / / / / / / / / 0 0 SLC 0 0 0 0 / / / /
Port #1-Jack Annex Demolition:
20-0434 Reconstruction 8-051-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 106,376 0 SLC 0 0 0 Burton Behrendt Smith 0 11/21/22 09/08/20
Port 2-Jack Annex Demolition:
20-0435 Reconstruction 8-052-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 106,376 0 SLC 0 0 0 Burton Behrendt Smith 0 11/21/22 09/08/20
Portable-Franklin Demolition:
20-0436 Reconstruction 8-057-002 11/30/20 DONE DONE DONE 09/24/20 09/08/20 06/19/19 05/15/18 2 134,370 0 SLC 0 0 0 Burton Behrendt Smith 0 11/21/22 09/08/20
Portable Double-ABGS-Clasrms Demo:
22-1976 Reconstruction 8-060-002 05/02/23 DONE DONE DONE 03/31/23 03/30/23 10/17/22 05/17/22 2,16 123,585 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 03/30/23
XXEvergreen Charter Secondary School:
- XX New Construction 0-001-001 CANCELLED / / / / 07/29/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
UNIONDALE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-02-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Northern Parkway Elementary School:
19-1201 Additions and Alterations 0-002-042 05/28/20 DONE DONE DONE 01/13/20 12/27/19 06/19/18 03/15/18 02 - 16 22,990,730 12,017,297 BMJ 0 0 0 H2M Group 0 / / 12/27/19
18-2204 Reconstruction 0-002-043 08/07/19 DONE DONE DONE 06/26/19 06/13/19 12/06/18 11/13/18 2 41,720 41,720 BMJ 0 0 0 H2M Group 0 01/13/20 06/13/19
19-1390 Reconstruction 0-002-044 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 8,9 103,000 103,000 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1092 Reconstruction 0-002-045 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 4,8,9,155,15,16 107,176 107,176 FMJ 0 0 0 H2M Group 0 / / 01/11/22
California Avenue Elementary:
19-1202 Additions and Alterations 0-003-040 05/28/20 DONE DONE DONE 01/13/20 12/27/19 06/19/18 03/15/18 02 - 16 15,536,016 7,634,505 BMJ 0 0 0 H2M Group 0 06/19/23 12/27/19
18-2205 Reconstruction 0-003-041 08/08/19 DONE DONE DONE 06/26/19 06/13/19 12/06/18 11/13/18 2 41,720 41,720 BMJ 0 0 0 H2M Group 0 01/13/20 06/13/19
19-1391 Reconstruction 0-003-042 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 8 18,000 18,000 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1093 Reconstruction 0-003-043 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 4,8,9,155,16 91,531 91,531 FMJ 0 0 0 H2M Group 0 / / 01/11/22
22-0078FC Reconstruction 0-003-044 12/06/22 DONE DONE DONE 07/13/22 07/07/22 01/05/22 06/21/22 2,4,9,155,15,16 2,327,000 2,327,000 WLC 0 0 0 H2M Group 0 / / 07/07/22
Smith Street School:
19-1522 Additions and Alterations 0-004-035 07/03/20 DONE DONE DONE 03/03/20 02/05/20 06/19/18 03/15/18 02 - 16 9,047,264 6,963,592 SLC 0 0 0 H2M Group 0 05/27/22 02/05/20
18-2206 Reconstruction 0-004-036 08/07/19 DONE DONE DONE 06/26/19 06/13/19 12/06/18 11/13/18 2 41,720 41,720 BMJ 0 0 0 H2M Group 0 01/13/20 06/13/19
19-1392 Reconstruction 0-004-037 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 4,8,9 312,750 312,750 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1094 Reconstruction 0-004-038 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 4,8,9,155,16 164,000 164,000 FMJ 0 0 0 H2M Group 0 / / 01/11/22
22-2098 Reconstruction 0-004-039 07/28/23 DONE DONE DONE 04/26/23 04/24/23 07/13/22 05/17/22 2,9,10,16 194,066 194,066 WLC 0 0 0 H2M Group 0 / / 04/24/23
Cornelius Court School:
19-1521 Additions and Alterations 0-005-022 07/03/20 DONE DONE DONE 03/03/20 02/05/20 06/19/18 03/15/18 02 - 16 3,868,723 2,719,705 SLC 0 0 0 H2M Group 0 / / 02/05/20
19-1393 Reconstruction 0-005-023 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 8 5,400 0 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1095 Reconstruction 0-005-024 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 4,8,9,155,16 91,814 91,814 FMJ 0 0 0 H2M Group 0 / / 01/11/22
Grand Avenue School:
19-1203 Additions and Alterations 0-006-032 05/28/20 DONE DONE DONE 01/13/20 12/27/19 06/19/18 09/26/18 02 - 16 9,214,438 6,733,388 BMJ 0 0 0 H2M Group 0 08/30/22 12/27/19
18-2207 Reconstruction 0-006-034 08/07/19 DONE DONE DONE 06/26/19 06/13/19 12/06/18 11/13/18 2 41,720 41,720 BMJ 0 0 0 H2M Group 0 01/13/20 06/13/19
19-1394 Reconstruction 0-006-035 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 2,4,8,9 151,700 151,700 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1096 Reconstruction 0-006-036 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 2,4,8,9,155,16 264,000 264,000 FMJ 0 0 0 H2M Group 0 / / 01/11/22
Walnut Street Elementary:
19-1520 Additions and Alterations 0-007-036 07/03/20 DONE DONE DONE 03/03/20 02/05/20 06/19/18 03/15/18 02 - 16 14,133,908 8,811,565 SLC 0 0 0 H2M Group 0 / / 02/05/20
18-2208 Reconstruction 0-007-038 08/07/19 DONE DONE DONE 06/26/19 06/13/19 12/06/18 11/13/18 2 41,720 41,720 BMJ 0 0 0 H2M Group 0 01/13/20 06/13/19
19-1395 Reconstruction 0-007-039 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 8 33,500 33,500 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1097 Reconstruction 0-007-040 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 4,8,9,155,16 126,000 0 FMJ 0 0 0 H2M Group 0 / / 01/11/22
Lawrence Road Middle School:
21-0716 Additions and Alterations 0-008-040 06/21/22 DONE DONE DONE 11/16/21 11/12/21 06/19/18 03/15/18 02 - 16 17,478,092 12,156,888 WLC 0 0 0 H2M Group 0 / / 11/12/21
19-1155 Reconstruction 0-008-041 02/28/20 DONE DONE DONE 01/03/20 12/30/19 12/06/18 03/15/18 2,4,7,8,155,15,16 1,078,697 1,078,697 BMJ 0 0 0 H2M Group 0 05/22/21 12/30/19
19-1396 Reconstruction 0-008-042 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 2,4,8,9,13 139,500 139,500 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1098 Reconstruction 0-008-043 06/30/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 2,4,8,9,155,16 237,190 237,190 FMJ 0 0 0 H2M Group 0 / / 01/11/22
22-1987 Reconstruction 0-008-044 08/15/23 DONE DONE DONE 04/03/23 03/31/23 07/13/22 05/17/22 2,4,7,8,9,10,155,15, 84,157 84,157 WLC 0 0 0 H2M Group 0 / / 03/31/23
- Reconstruction 0-008-045 / / / / 11/01/23 / / 10,16 0 0 WLC 0 0 0 0 / / / /
Uniondale High School:
21-0949 Alterations 0-009-064 08/03/22 DONE DONE DONE 12/22/21 12/22/21 06/19/18 03/15/18 02 - 16 43,968,411 8,521,476 FMJ 0 0 0 H2M Group 0 / / 12/22/21
19-1154 Reconstruction 0-009-065 02/28/20 DONE DONE DONE 01/03/20 12/30/19 12/06/18 03/15/18 2,4,7,8,155,15,16 1,022,152 1,022,152 BMJ 0 0 0 H2M Group 0 04/20/21 12/30/19
19-1397 Reconstruction 0-009-066 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 4,8,9 323,000 323,000 BMJ 0 0 0 H2M Group 0 08/01/20 01/31/20
21-1099 Reconstruction 0-009-067 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 2,14,16 268,000 268,000 FMJ 0 0 0 H2M Group 0 / / 01/11/22
22-1988 Reconstruction 0-009-068 08/15/23 DONE DONE DONE 04/03/23 03/31/23 07/13/22 05/17/22 2,4,7,8,9,10,155,15, 600,000 600,000 WLC 0 0 0 H2M Group 0 / / 03/31/23
- Reconstruction 0-009-069 / / / / 09/05/23 / / 4,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-009-070 / / / / 11/01/23 / / 9,10,155,15,16 0 0 WLC 0 0 0 0 / / / /
Turtle Hook Junior High:
21-0738 Additions and Alterations 0-010-036 08/03/22 DONE DONE DONE 11/17/21 11/17/21 06/19/18 03/15/18 02 - 16 17,651,965 2,769,351 FMJ 0 0 0 H2M Group 0 / / 11/17/21
19-1398 Reconstruction 0-010-037 03/13/20 DONE DONE DONE 02/11/20 01/31/20 07/09/19 05/21/19 2,4,8,9 100,000 100,000 BMJ 0 0 0 H2M Group 0 08/21/20 01/31/20
21-1100 Reconstruction 0-010-038 06/23/22 DONE DONE DONE 01/12/22 01/11/22 08/05/21 05/18/21 4,8,9,155,16 152,408 152,408 FMJ 0 0 0 H2M Group 0 / / 01/11/22
- Reconstruction 0-010-039 / / / / 07/13/22 / / 2 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-010-040 / / / / 11/01/23 / / 10,16 0 0 WLC 0 0 0 0 / / / /
Grand Ave Portable Demolition:
19-1557 Reconstruction 0-012-002 03/26/20 DONE DONE DONE 03/11/20 03/02/20 06/21/18 09/26/18 2 44,450 44,450 BMJ 0 0 0 H2M Group 0 08/30/22 03/02/20
Northern Pky Portbl Demolition:
19-1558 Reconstruction 0-016-001 03/26/20 DONE DONE DONE 03/11/20 03/02/20 06/21/18 03/15/18 2 44,450 44,450 BMJ 0 0 0 H2M Group 0 01/27/22 03/02/20
Walnut St Portable 2 Demolition:
19-1518 Reconstruction 0-017-001 06/11/20 DONE DONE DONE 03/03/20 03/02/20 06/21/18 03/15/18 2 44,450 0 SLC 0 0 0 H2M Group 0 / / 03/02/20
Walnut St Portable 1 Demolition:
19-1519 Reconstruction 0-019-001 06/11/20 DONE DONE DONE 03/03/20 03/02/20 06/21/18 03/15/18 2 44,450 0 SLC 0 0 0 H2M Group 0 / / 03/02/20
Northern Pkwy Portable Demolition:
19-1559 Reconstruction 0-028-002 03/26/20 DONE DONE DONE 03/11/20 03/02/20 06/21/18 03/15/18 2 44,450 44,450 BMJ 0 0 0 H2M Group 0 01/27/22 03/02/20
Concession Stand:
21-0950 New Construction 7-039-001 08/03/22 DONE DONE DONE 12/22/21 12/22/21 06/19/18 03/15/18 02 - 16 1,252,751 0 FMJ 0 0 0 H2M Group 0 / / 12/22/21
Shubert Elementary School:
18-2190TQ Temporary Quarters 8-038-002 07/03/19 DONE DONE DONE 06/24/19 / / 06/21/19 / / 339,600 0 BMJ 0 0 0 0 / / / /
20-0237TQ Temporary Quarters 8-038-003 08/26/20 DONE DONE DONE 07/16/20 07/16/20 06/26/20 06/23/20 709,788 0 SLC 0 0 0 0 / / 07/16/20
21-0093TQ Temporary Quarters 8-038-004 08/04/21 DONE DONE DONE 07/23/21 07/23/21 03/26/21 / / 384,767 0 SLC 0 0 0 0 / / 07/23/21
XXGraduation Tent 1 - Removed:
20-1911TQ Temporary Quarters 8-040-001 06/24/21 DONE DONE DONE 06/23/21 06/23/21 06/11/21 / / 0 0 SLC 0 0 0 0 / / 06/23/21
XXGraduation Tent 2 - Removed:
20-1912TQ Temporary Quarters 8-041-001 06/24/21 DONE DONE DONE 06/23/21 06/23/21 06/11/21 / / 0 0 SLC 0 0 0 0 / / 06/23/21
XXGraduation Tent 3 - Removed:
20-1913TQ Temporary Quarters 8-042-001 06/24/21 DONE DONE DONE 06/23/21 06/23/21 06/11/21 / / 0 0 SLC 0 0 0 0 / / 06/23/21
Steam Fair Tent #1:
- XX Alterations 8-043-001 CANCELLED / / / / 05/19/22 / / 0 0 SLC 0 0 0 0 / / / /
Steam Fair Tent #2:
- XX Alterations 8-044-001 CANCELLED / / / / 05/19/22 / / 0 0 SLC 0 0 0 0 / / / /
Steam Tent 1 @UHS:
- TQ Temporary Quarters 8-045-001 / / / / 05/31/23 / / 0 0 WLC 0 0 0 0 / / / /
Steam Tent 2 @UHS:
- TQ Temporary Quarters 8-046-001 / / / / 05/31/23 / / 0 0 WLC 0 0 0 0 / / / /
TACS Uniondale High School:
23-0175TQ Temporary Quarters 8-001-001 STARTED DONE DONE 08/01/23 07/28/23 06/15/23 / / 7,8,9,14,155,15,16 0 0 JLB 0 0 0 0 / / 07/28/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EAST MEADOW UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-03-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Parkway Elementary:
16-1080 Reconstruction 0-001-034 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 938,883 0 BMJ 0 0 0 John A. Grillo 938,883 / / 12/27/16
18-0365 Reconstruction 0-001-035 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 7 247,800 247,800 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1126 Reconstruction 0-001-036 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 7,9,155,15,16 177,000 0 JLB 0 0 0 John A. Grillo 0 / / 12/19/19
21-1836 Reconstruction 0-001-037 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 29,388 29,388 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0446 Reconstruction 0-001-038 03/07/24 DONE DONE DONE 09/13/23 08/24/23 09/06/23 03/07/17 2,16 150,000 150,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
Meadowbrook Elementary:
16-1081 Reconstruction 0-002-033 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 377,516 0 BMJ 0 0 0 John A. Grillo 377,516 / / 12/27/16
18-0366 Reconstruction 0-002-034 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 2,7 384,090 384,090 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1127 Reconstruction 0-002-035 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 7,9,155,15,16 511,176 511,176 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/19/19
21-1837 Reconstruction 0-002-036 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 29,388 29,388 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0447 Reconstruction 0-002-037 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 150,000 150,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
W T Clarke Middle/High School:
16-1082 Reconstruction 0-004-045 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 2,367,914 0 BMJ 0 0 0 John A. Grillo 2,367,914 / / 12/27/16
18-0367 Reconstruction 0-004-047 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 10,13,155,16 1,355,820 1,355,820 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1128 Reconstruction 0-004-048 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 7,9,155,15,16 2,847,899 2,847,899 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/19/19
- Reconstruction 0-004-049 / / / / 06/15/20 / / 7,16 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-004-050 / / / / 06/23/20 / / 2,16 0 0 JLB 0 0 0 0 / / / /
21-1838 Reconstruction 0-004-051 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 87,715 87,715 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0448 Reconstruction 0-004-052 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 250,000 250,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
Barnum Woods Elementary:
16-1083 Reconstruction 0-006-034 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 950,589 0 BMJ 0 0 0 John A. Grillo 950,589 / / 12/27/16
18-0368 Reconstruction 0-006-036 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 7,155,16 2,342,300 2,342,300 BMJ 0 0 0 John A. Grillo 0 09/04/20 08/30/18
19-1129 Reconstruction 0-006-037 12/18/20 DONE DONE DONE 01/02/20 12/17/19 06/24/18 03/07/17 7,9,155,15,16 615,393 615,393 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/17/19
21-1839 Reconstruction 0-006-038 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 53,877 53,877 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0449 Reconstruction 0-006-039 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 200,000 200,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
East Meadow High School:
16-1084 Reconstruction 0-007-047 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 1,940,392 0 BMJ 0 0 0 John A. Grillo 1,940,392 / / 12/27/16
18-0369 Reconstruction 0-007-050 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 2,7,155 1,327,500 1,327,500 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1130 Reconstruction 0-007-051 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 2,7,9,155,15,16 4,499,823 4,499,823 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/19/19
- Reconstruction 0-007-052 / / / / 06/15/20 / / 7,16 0 0 JLB 0 0 0 0 / / / /
21-1840 Reconstruction 0-007-053 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 66,122 66,122 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0450 Reconstruction 0-007-054 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 300,000 300,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
Woodland Middle School:
16-1085 Reconstruction 0-009-039 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 2,982,945 0 BMJ 0 0 0 John A. Grillo 2,982,945 / / 12/27/16
18-0370 Reconstruction 0-009-040 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 7,155,16 4,507,600 4,507,600 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1131 Reconstruction 0-009-041 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 2,7,9,155,15,16 1,051,380 1,051,380 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/19/19
21-1841 Reconstruction 0-009-042 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 63,673 63,673 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0451 Reconstruction 0-009-043 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 200,000 200,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
George McVey Elementary:
16-1086 Reconstruction 0-011-031 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 481,485 0 BMJ 0 0 0 John A. Grillo 481,485 / / 12/27/16
18-0371 Reconstruction 0-011-033 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 7 1,740,500 1,740,500 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1132 Reconstruction 0-011-034 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 7,9,155,15,16 1,020,936 1,020,936 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/19/19
21-1842 Reconstruction 0-011-035 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 78,367 78,367 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
- PR Additions and Alterations 0-011-036 / / / / / / / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1816 Additions and Alterations 0-011-036 STARTED DONE DONE 03/13/23 03/08/23 / / 05/17/22 02 - 16 5,495,820 0 JJH 0 0 0 John A. Grillo 0 / / 03/08/23
23-0452 Reconstruction 0-011-037 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 150,000 150,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
Bowling Green Elementary:
16-1087 Reconstruction 0-012-033 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/14/16 07/28/16 2,7,155,15,16 1,877,506 0 BMJ 0 0 0 John A. Grillo 1,877,506 / / 12/27/16
18-0372 Reconstruction 0-012-034 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 7,155,16 4,383,700 4,383,700 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
19-1133 Reconstruction 0-012-035 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 7,9,155,15,16 840,396 840,396 BMJ 0 0 0 John A. Grillo 0 10/06/22 12/19/19
21-1843 Reconstruction 0-012-036 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 53,877 53,877 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
23-0453 Reconstruction 0-012-037 03/07/24 DONE DONE DONE 09/13/23 08/24/23 07/03/23 03/07/17 2,16 1,150,000 1,150,000 JJH 0 0 0 John A. Grillo 0 / / 08/24/23
Salisbury Center:
16-1088 Reconstruction 1-019-013 10/22/21 DONE DONE DONE 12/27/16 12/27/16 10/21/16 07/28/16 2,7,15,16 342,480 0 BMJ 0 0 0 John A. Grillo 342,480 / / 12/27/16
18-0373 Reconstruction 1-019-016 05/08/19 DONE DONE DONE 09/06/18 08/30/18 10/11/17 03/07/17 2,13 708,000 0 BMJ 0 0 0 John A. Grillo 0 06/17/20 08/30/18
19-1134 Reconstruction 1-019-017 12/18/20 DONE DONE DONE 01/02/20 12/19/19 06/24/18 03/07/17 7,9,155,15,16 206,500 0 BMJ 0 0 0 John A. Grillo 0 / / 12/19/19
21-1844 Reconstruction 1-019-018 08/09/22 DONE DONE DONE 05/20/22 05/20/22 02/22/21 03/07/17 2,15,16 24,489 0 JLB 0 0 0 John A. Grillo 0 / / 05/20/22
Press Box:
18-0374 New Construction 7-025-001 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 02 - 16 118,000 0 BMJ 0 0 0 John A. Grillo 0 06/17/20 08/30/18
Toliet/Concession Bldg.:
18-0375 New Construction 7-026-001 05/08/19 DONE DONE DONE 09/06/18 08/30/18 04/18/17 03/07/17 02 - 16 472,000 0 BMJ 0 0 0 John A. Grillo 0 02/13/23 08/30/18
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LEVITTOWN UNION FREE SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-05-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Memorial Education Center:
22-1875 Reconstruction 0-001-024 09/19/23 DONE DONE DONE 03/20/23 03/15/23 11/15/22 05/17/22 2,7,8,9,10,155,15,16 300,000 0 MSK 0 0 0 John A. Grillo 0 / / 03/15/23
22-2186 Reconstruction 0-001-025 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 2,000,000 2,000,000 SLC 0 0 0 John A. Grillo 0 / / 05/09/23
23-0941 Reconstruction 0-001-026 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 2,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0079 Reconstruction 0-001-027 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 75,332 0 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-001-028 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Jonas E. Salk Middle School/High Ssc:
22-2187 Reconstruction 0-002-027 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 2,141,700 2,141,700 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0942 Reconstruction 0-002-028 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0080 Reconstruction 0-002-029 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 74,554 74,554 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-002-030 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Division Avenue High School:
19-1464 Reconstruction 0-003-031 07/01/20 DONE DONE DONE 02/21/20 02/18/20 02/14/20 06/09/20 2,4,8,9 1,465,000 1,465,000 SLC 0 0 0 John A. Grillo 0 07/28/22 02/18/20
- Reconstruction 0-003-032 / / / / 02/18/20 / / 2,9,16 0 0 SLC 0 0 0 0 / / / /
22-2188 Reconstruction 0-003-033 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 2,952,400 2,952,400 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0943 Reconstruction 0-003-034 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 2,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0081 Reconstruction 0-003-035 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 98,482 98,482 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
23-1263 Reconstruction 0-003-036 UNREVIEWED 12/21/23 12/21/23 09/15/23 05/16/23 2,4,7,9 0 0 MSK 0 0 0 John A. Grillo 0 / / 12/21/23
- Reconstruction 0-003-037 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Summit Lane Elementary School:
22-2189 Reconstruction 0-005-019 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 663,000 663,000 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0944 Reconstruction 0-005-020 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 9,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0082 Reconstruction 0-005-021 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 75,447 75,447 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-005-022 / / / / 09/15/23 / / 2,9 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-005-023 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Seaman Neck School (Leased to BOCES):
22-2298 Reconstruction 0-006-012 STARTED DONE DONE 05/31/23 05/25/23 01/24/23 05/16/23 2,155 250,000 0 MSK 0 0 0 John A. Grillo 0 / / 05/25/23
- Reconstruction 0-006-013 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Northside School:
22-2190 Reconstruction 0-008-021 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 745,000 745,000 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0945 Reconstruction 0-008-022 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 9,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0083 Reconstruction 0-008-023 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 99,440 99,440 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-008-024 / / / / 09/15/23 / / 2,9 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-008-025 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Lee Road Elementary School:
22-2191 Reconstruction 0-009-017 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 620,000 620,000 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0946 Reconstruction 0-009-018 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0084 Reconstruction 0-009-019 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 87,465 87,465 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-009-020 / / / / 09/15/23 / / 2,9 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-009-021 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Wisdom Lane Middle School:
22-2192 Reconstruction 0-011-022 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 2,098,140 2,098,140 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0947 Reconstruction 0-011-023 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 2,15,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0085 Reconstruction 0-011-024 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 64,260 64,260 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
23-1284 Reconstruction 0-011-025 UNREVIEWED 12/26/23 12/26/23 09/15/23 05/16/23 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 John A. Grillo 0 / / 12/26/23
- Reconstruction 0-011-026 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Gardiners Avenue Elementary School:
22-2193 Reconstruction 0-013-018 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 1,152,000 1,152,000 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0948 Reconstruction 0-013-019 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0086 Reconstruction 0-013-020 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 79,386 79,386 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-013-021 / / / / 09/15/23 / / 2,9 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-013-022 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
East Broadway Elementary School:
22-2194 Reconstruction 0-014-021 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 862,520 862,520 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0949 Reconstruction 0-014-022 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 2,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0087 Reconstruction 0-014-023 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 47,945 47,945 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
23-1345 Reconstruction 0-014-024 UNREVIEWED 01/12/24 01/10/24 09/15/23 05/16/23 2,9 0 0 MSK 0 0 0 John A. Grillo 0 / / 01/10/24
- Reconstruction 0-014-025 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Abbey Lane School:
22-2195 Reconstruction 0-015-019 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 1,003,340 1,003,340 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0950 Reconstruction 0-015-020 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 2,9,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0088 Reconstruction 0-015-021 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 98,177 98,177 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
23-1346 Reconstruction 0-015-022 UNREVIEWED 01/12/24 01/10/23 09/15/23 05/16/23 2,4,7,9,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 01/10/23
- Reconstruction 0-015-023 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
Douglas MacArthur High School:
19-1303 Reconstruction 0-018-033 05/13/20 DONE DONE DONE 01/29/20 01/24/20 11/27/18 05/16/17 2,4,8,9,10,15,16 1,000,000 1,000,000 SLC 0 0 0 John A. Grillo 0 / / 01/24/20
22-2196 Reconstruction 0-018-034 09/25/23 DONE DONE DONE 05/10/23 05/09/23 12/07/22 05/16/23 16 2,330,460 2,330,460 MSK 0 0 0 John A. Grillo 0 / / 05/09/23
23-0951 Reconstruction 0-018-035 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 2,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
23-0089 Reconstruction 0-018-036 01/03/24 DONE DONE DONE 07/14/23 07/13/23 05/31/23 05/16/23 16 71,715 71,715 MSK 0 0 0 John A. Grillo 0 / / 07/13/23
- Reconstruction 0-018-037 / / / / 03/04/24 / / 16 0 0 MSK 0 0 0 0 / / / /
:
- DB Discovered Building 0-061-001 / / / / 04/24/23 / / 0 0 JLB 0 0 0 0 / / / /
Transportation Office:
23-0952 Reconstruction 1-035-007 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
Container @ Maint.:
- DB Discovered Building 2-057-001 / / / / 03/25/11 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
MacArthur High School Container:
- DB Discovered Building 2-058-001 / / / / 03/25/11 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Containter 1 @ Divison:
- DB Discovered Building 2-059-001 / / / / 03/25/11 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Container 2 @ Divison:
- PR New Construction 2-060-001 / / / / 03/25/11 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Bus Garage:
23-0953 Reconstruction 5-033-007 UNREVIEWED 11/10/23 11/07/23 01/31/23 01/13/23 16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/07/23
Levittown Public Library:
- Reconstruction 6-019-013 / / / / 10/25/23 / / 2,15,16 0 0 MSK 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SEAFORD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-06-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Seaford High School:
18-2070 Reconstruction 0-001-030 07/15/19 DONE DONE DONE 06/05/19 05/29/19 04/22/19 05/21/19 2,8 1,500,000 1,500,000 JLB 0 0 0 John A. Grillo 0 07/19/21 05/29/19
20-0048 Reconstruction 0-001-031 05/18/21 DONE DONE DONE 07/10/20 07/08/20 01/27/20 01/22/20 2,16 14,528 0 JSS 0 0 0 John A. Grillo 0 / / 07/08/20
21-0157 Reconstruction 0-001-032 09/28/21 DONE DONE DONE 08/11/21 08/06/21 08/09/21 05/18/21 2,4,8,9,10,155,15,16 396,812 396,812 JLB 0 0 0 John A. Grillo 0 06/08/23 08/06/21
21-1263FC Reconstruction 0-001-033 03/24/22 DONE DONE DONE 02/10/22 02/08/22 10/12/21 03/09/22 2,7,8,9,155,15,16 1,138,343 1,138,343 JLB 0 0 0 John A. Grillo 0 02/05/24 02/08/22
21-1992 Reconstruction 0-001-034 12/01/22 DONE DONE DONE 06/17/22 06/16/22 05/23/22 05/17/22 2,9 4,850,000 4,850,000 WLC 0 0 0 John A. Grillo 0 11/27/23 06/16/22
- Reconstruction 0-001-035 / / / / 08/24/22 / / 16 0 0 WLC 0 0 0 0 / / / /
Seaford Manor Elementary:
21-0158 Reconstruction 0-002-017 09/28/21 DONE DONE DONE 08/11/21 08/06/21 08/09/21 05/18/21 8 169,100 0 JLB 0 0 0 John A. Grillo 0 / / 08/06/21
22-0732 Reconstruction 0-002-018 03/01/23 DONE DONE DONE 10/17/22 09/19/22 10/11/22 05/17/22 4,8,9,155,15,16 115,000 115,000 WLC 0 0 0 John A. Grillo 0 02/05/24 09/19/22
Seaford Harbor Elementary:
19-1204 Reconstruction 0-005-023 03/06/20 DONE DONE DONE 01/13/20 01/10/20 09/19/19 05/21/19 9 560,000 560,000 JSS 0 0 0 John A. Grillo 0 07/19/21 01/10/20
20-0379 Reconstruction 0-005-024 12/16/20 DONE DONE DONE 09/16/20 09/03/20 06/18/20 06/16/20 9,16 750,000 750,000 JSS 0 0 0 John A. Grillo 0 08/05/22 09/03/20
21-0159 Reconstruction 0-005-025 09/28/21 DONE DONE DONE 08/11/21 08/06/21 08/09/21 05/18/21 8 142,044 0 JLB 0 0 0 John A. Grillo 0 / / 08/06/21
22-0733 Reconstruction 0-005-026 03/01/23 DONE DONE DONE 10/17/22 09/19/22 10/11/22 05/17/22 2,4,9,155,15,16 300,000 300,000 WLC 0 0 0 John A. Grillo 0 11/27/23 09/19/22
Seaford Middle School:
21-0160 Reconstruction 0-006-026 09/28/21 DONE DONE DONE 08/11/21 08/06/21 08/09/21 05/18/21 8 142,044 142,044 JLB 0 0 0 John A. Grillo 0 11/27/23 08/06/21
21-1264FC Reconstruction 0-006-027 03/24/22 DONE DONE DONE 02/10/22 02/08/22 10/12/21 03/09/22 2,7,8,9,10,155,15,16 607,602 607,602 JLB 0 0 0 John A. Grillo 0 02/05/24 02/08/22
Seaford Public Library:
20-1608 Reconstruction 6-004-006 06/14/21 DONE DONE DONE 04/21/21 04/14/21 01/27/21 06/09/20 2,7 323,109 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 04/14/21
21-0145 Reconstruction 6-004-007 09/15/21 DONE DONE DONE 08/04/21 08/04/21 01/27/21 02/08/21 2,8,9,155,16 654,812 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 08/04/21
21-2057 Reconstruction 6-004-008 04/18/23 DONE DONE DONE 06/29/22 06/27/22 02/14/22 06/13/22 16 399,496 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 06/27/22
Field House:
- PR New Construction 7-024-001 / / / / 03/22/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-2353 New Construction 7-024-001 10/20/23 DONE DONE DONE 06/09/23 06/09/23 03/22/23 05/16/23 02 - 16 1,000,000 0 WLC 0 0 0 John A. Grillo 0 / / 06/09/23
District-Wide:
18-1808SB Reconstruction 7-999-001 DONE / / / / 04/08/19 / / 16 0 0 JLB 0 0 0 0 / / / /
19-0069 Reconstruction 7-999-001 08/27/19 DONE DONE DONE 07/15/19 06/19/19 04/08/19 11/04/14 16 551,921 551,921 JLB 0 0 0 John A. Grillo 0 / / 06/19/19
XXSeaford H.S Tent #1 365 DaysLapsed:
20-0255TQ Temporary Quarters 8-016-001 10/28/20 DONE DONE DONE 08/21/20 08/21/20 07/31/20 / / 0 0 JSS 0 0 0 John A. Grillo 0 10/27/20 08/21/20
XXSeaford M.S Tent #2 365DaysLapsed:
20-0256TQ Temporary Quarters 8-017-001 10/28/20 DONE DONE DONE 08/21/20 08/21/20 07/31/20 / / 0 0 JSS 0 0 0 John A. Grillo 0 10/27/20 08/21/20
XXSeaford Manor E.S Tent #3 365DaysL:
20-0257TQ Temporary Quarters 8-018-001 08/21/20 DONE DONE DONE 08/21/20 08/21/20 07/31/20 / / 0 0 JSS 0 0 0 John A. Grillo 0 10/27/20 08/21/20
XXSeaford Harbor ES Tent #4 365DaysL:
20-0258TQ Temporary Quarters 8-019-001 10/28/20 DONE DONE DONE 08/21/20 08/21/20 07/31/20 / / 0 0 JSS 0 0 0 John A. Grillo 0 10/27/20 08/21/20
XXSeaford HS Tent #2 (Grad.-Removed):
20-1656TQ Temporary Quarters 8-020-001 06/04/21 DONE DONE DONE 04/30/21 04/29/21 04/14/21 / / 0 0 JSS 0 0 0 0 / / 04/29/21
Seaford HS Tent (New):
21-0276TQ Temporary Quarters 8-021-001 12/10/21 DONE DONE DONE 09/03/21 09/03/21 09/01/21 / / 0 0 JLB 0 0 0 0 / / 09/03/21
Seaford Harbor ES Tent (New):
21-0277TQ Temporary Quarters 8-022-001 12/10/21 DONE DONE DONE 09/03/21 09/03/21 09/01/21 / / 0 0 JLB 0 0 0 0 / / 09/03/21
Seaford Manor ES Tent (New):
21-0278TQ Temporary Quarters 8-023-001 12/10/21 DONE DONE DONE 09/03/21 09/03/21 09/01/21 / / 0 0 JLB 0 0 0 0 / / 09/03/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
FREEPORT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-09-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Freeport Senior High School:
18-1647 Reconstruction 0-001-035 04/24/19 DONE DONE DONE 03/14/19 02/28/19 12/12/17 05/15/18 8,9,16 158,800 158,800 BMJ 0 0 0 Mark Design Studios 0 09/03/19 02/28/19
18-0816 Reconstruction 0-001-036 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 2,083,560 2,083,560 BMJ 0 0 0 ECG Engineering, LLC 2,083,560 02/01/21 11/06/18
19-1150 Reconstruction 0-001-037 02/11/20 DONE DONE DONE 01/03/20 12/23/19 05/15/19 09/26/18 8,9,15,16 281,510 281,510 BMJ 0 0 0 H2M Group 0 04/24/20 YES 12/23/19
- Reconstruction 0-001-038 / / / / 12/19/19 / / 2,4,7,8,9,10,155,15, 0 0 BMJ 0 0 0 0 / / / /
20-1628 Reconstruction 0-001-039 11/18/21 DONE DONE DONE 04/27/21 04/19/21 09/25/20 05/21/19 8 884,856 884,856 JLB 0 0 0 H2M Group 0 / / 04/19/21
- Reconstruction 0-001-040 / / / / 09/25/20 / / 8,9,155,16 0 0 JLB 0 0 0 0 / / / /
21-1101FC Reconstruction 0-001-041 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 2,155,16 63,000 63,000 JLB 0 0 0 H2M Group 0 / / 01/11/22
22-1827 Reconstruction 0-001-042 09/07/22 DONE DONE DONE 03/13/23 03/13/23 08/24/22 09/07/22 4 317,876 317,876 JJH 0 0 0 H2M Group 0 11/04/22 03/13/23
23-1202 Reconstruction 0-001-043 UNREVIEWED 12/18/23 10/04/23 09/19/22 03/16/22 2,8,9,10,155,15,16 0 0 JJH 0 0 0 H2M Group 0 / / 10/04/23
22-2419 Reconstruction 0-001-044 10/23/23 DONE DONE DONE 06/20/23 06/20/23 09/19/22 03/18/22 2,4,7,9,155,16 2,638,650 2,638,650 JJH 0 0 0 H2M Group 0 / / 06/20/23
23-1443FA Reconstruction 0-001-045 UNREVIEWED
STARTED ADD. REQ'D01/31/24 01/30/24 07/31/23 03/16/22 2,9,10,15,16 0 67,775,521 JJH 0 0 0 H2M Group 0 / / 01/30/24
23-1647 Reconstruction 0-001-046 UNREVIEWED 03/20/24 03/18/24 11/16/23 05/25/22 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 H2M Group 0 / / 03/18/24
John W.Dodd Junior High:
18-0817 Reconstruction 0-002-028 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 1,186,251 1,186,251 BMJ 0 0 0 ECG Engineering, LLC 1,186,251 02/01/21 11/06/18
21-1102 Reconstruction 0-002-029 11/09/21 DONE DONE DONE 01/12/22 01/11/22 11/16/21 09/22/21 2,9,10 449,208 449,208 JLB 0 0 0 H2M Group 0 12/16/21 01/11/22
22-2075 Reconstruction 0-002-030 11/15/23 DONE DONE DONE 04/21/23 04/20/23 09/19/22 05/17/22 2,4,7,8,9,10,155,15, 1,689,450 1,689,450 JJH 0 0 0 H2M Group 0 / / 04/20/23
23-1362 Reconstruction 0-002-031 UNREVIEWED 01/16/24 01/08/24 06/22/23 05/16/23 2,8,9,10,155,15,16 0 0 JJH 0 0 0 H2M Group 0 / / 01/08/24
Archer St School:
18-2185 Reconstruction 0-004-020 09/09/19 DONE DONE DONE 06/24/19 05/13/19 05/17/17 05/15/18 9,16 121,000 121,000 BMJ 0 0 0 Mark Design Studios 0 09/10/20 05/13/19
18-0818 Reconstruction 0-004-022 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 480,973 480,973 BMJ 0 0 0 ECG Engineering, LLC 480,973 02/01/21 11/06/18
19-1574 Reconstruction 0-004-024 09/04/20 DONE DONE DONE 03/13/20 03/05/20 12/19/19 05/21/19 8,9 249,375 0 JLB 0 0 0 Mark Design Studios 0 / / 03/05/20
20-1735 Reconstruction 0-004-025 08/09/21 DONE DONE DONE 05/18/21 05/14/21 12/15/20 06/09/20 2,4,7,8,9,10,15,16 985,760 985,760 JLB 0 0 0 H2M Group 0 05/15/23 05/14/21
21-1274FA Reconstruction 0-004-026 05/05/22 DONE DONE DONE 02/11/22 01/11/22 10/19/21 03/16/22 2,155,16 1,000,000 1,000,000 JLB 0 0 0 H2M Group 0 / / 01/11/22
21-1103FA Reconstruction 0-004-027 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 05/18/21 2,9,155,16 168,000 168,000 JLB 0 0 0 H2M Group 0 / / 01/11/22
23-0486 Reconstruction 0-004-028 03/27/24 DONE DONE DONE 09/15/23 09/13/23 09/19/22 09/22/21 2,9,16 1,464,000 1,464,000 JJH 0 0 0 H2M Group 0 / / 09/13/23
- Reconstruction 0-004-029 / / / / 08/17/23 / / 2,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Field House:
18-0819 Reconstruction 0-005-006 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,16 37,513 0 BMJ 0 0 0 ECG Engineering, LLC 37,513 02/01/21 11/06/18
23-1409 Reconstruction 0-005-007 UNREVIEWED 01/24/24 01/22/24 08/17/23 05/16/23 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 H2M Group 0 / / 01/22/24
Caroline Atkinson Elementary:
19-1667 Reconstruction 0-006-029 07/20/20 DONE DONE DONE 04/09/20 03/09/20 08/08/18 05/21/19 2,8,9,16 165,900 0 JLB 0 0 0 H2M Group 0 / / 03/09/20
18-0820 Reconstruction 0-006-030 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 741,734 741,734 BMJ 0 0 0 ECG Engineering, LLC 741,734 02/01/21 11/06/18
18-2186 Reconstruction 0-006-032 09/09/19 DONE DONE DONE 07/29/19 05/13/19 03/07/19 05/15/18 9,16 189,250 189,250 BMJ 0 0 0 Mark Design Studios 0 08/20/20 05/13/19
- Reconstruction 0-006-033 / / / / 09/25/20 / / 2,8,9,155,15,16 0 0 JLB 0 0 0 0 / / / /
21-1123 Reconstruction 0-006-034 08/22/23 DONE DONE DONE 01/14/22 01/12/22 10/19/21 05/18/21 2,7 834,750 834,750 JJH 0 0 0 H2M Group 0 / / 01/12/22
21-1104FC Reconstruction 0-006-035 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 2,155,16 52,500 52,500 JLB 0 0 0 H2M Group 0 09/15/23 01/11/22
21-1275FA Reconstruction 0-006-036 05/05/22 DONE DONE DONE 02/14/22 01/11/22 02/11/22 03/16/22 2,155,16 1,260,000 1,260,000 JLB 0 0 0 H2M Group 0 / / 01/11/22
23-1437 Reconstruction 0-006-037 UNREVIEWED 01/29/24 01/29/24 09/19/22 05/25/22 155 0 0 JJH 0 0 0 H2M Group 0 / / 01/29/24
22-2449FC Reconstruction 0-006-038 08/09/23 DONE DONE DONE 06/23/23 03/29/23 02/01/23 05/17/23 155 625,800 625,800 JJH 0 0 0 H2M Group 0 / / 03/29/23
23-1201FA Reconstruction 0-006-039 STARTED ADD. REQ'D DONE 12/18/23 10/04/23 06/14/23 03/29/23 2 1,464,000 0 JJH 0 0 0 H2M Group 0 / / 10/04/23
- Reconstruction 0-006-040 / / / / 08/17/23 / / 2,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Bayview Ave School:
19-1668 Reconstruction 0-007-025 07/20/20 DONE DONE DONE 04/09/20 03/09/20 08/08/18 05/21/19 2,8,9,16 131,250 0 JLB 0 0 0 H2M Group 0 / / 03/09/20
18-0821 Reconstruction 0-007-026 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 564,751 564,751 BMJ 0 0 0 ECG Engineering, LLC 564,751 02/01/21 11/06/18
18-2187 Reconstruction 0-007-027 09/09/19 DONE DONE DONE 06/24/19 05/13/19 03/07/19 05/15/18 9,16 89,850 89,850 BMJ 0 0 0 Mark Design Studios 0 08/20/20 05/13/19
20-1629 Reconstruction 0-007-028 11/28/21 DONE DONE DONE 04/27/21 04/19/21 09/25/20 05/21/19 8 315,560 315,560 JLB 0 0 0 H2M Group 0 / / 04/19/21
21-1105FA Reconstruction 0-007-029 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 2,4,8,9,10,155,15,16 210,000 210,000 JLB 0 0 0 H2M Group 0 / / 01/11/22
22-1828 Reconstruction 0-007-030 08/15/23 DONE DONE DONE 03/13/23 03/13/23 09/19/22 03/17/21 4 74,500 74,500 JJH 0 0 0 H2M Group 0 / / 03/13/23
22-2450FC Reconstruction 0-007-031 08/09/23 DONE DONE DONE 06/23/23 03/29/23 02/01/23 05/17/22 155 1,045,800 1,045,800 JJH 0 0 0 H2M Group 0 / / 03/29/23
23-1429 Reconstruction 0-007-032 UNREVIEWED 01/26/24 01/26/24 08/17/23 05/16/23 2,4,9,10,15,16 0 0 JJH 0 0 0 H2M Group 0 / / 01/26/24
Columbus Avenue School:
19-1669 Reconstruction 0-009-022 07/20/20 DONE DONE DONE 04/09/20 03/09/20 08/08/18 05/21/19 2,8,9,16 65,625 0 JLB 0 0 0 H2M Group 0 / / 03/09/20
18-0822 Reconstruction 0-009-023 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 423,781 423,781 BMJ 0 0 0 ECG Engineering, LLC 423,781 02/01/21 11/06/18
18-2188 Reconstruction 0-009-025 09/09/19 DONE DONE DONE 06/24/19 05/13/19 03/07/19 05/15/18 9,16 106,140 106,140 BMJ 0 0 0 Mark Design Studios 0 09/10/20 05/13/19
19-0399 Reconstruction 0-009-026 01/10/20 DONE DONE DONE 09/11/19 06/11/19 03/21/19 05/21/19 4 982,500 982,500 BMJ 0 0 0 Mark Design Studios 0 04/14/23 06/11/19
20-0396 Reconstruction 0-009-027 01/08/21 DONE DONE DONE 09/18/20 09/03/20 08/03/20 05/21/19 2,4,8,9,155,16 892,500 892,500 JLB 0 0 0 H2M Group 0 09/19/23 09/03/20
21-1106FA Reconstruction 0-009-028 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 2,4,8,9,10,15,16 157,500 157,500 JLB 0 0 0 H2M Group 0 / / 01/11/22
21-1276FA Reconstruction 0-009-029 05/05/22 DONE DONE DONE 02/11/22 01/11/22 10/19/21 03/16/22 2,155,16 1,160,000 1,160,000 JLB 0 0 0 H2M Group 0 / / 01/11/22
22-2280 Reconstruction 0-009-030 09/13/23 DONE DONE DONE 05/24/23 05/22/23 09/19/22 05/17/22 7 133,350 133,350 JJH 0 0 0 H2M Group 0 / / 05/22/23
- Reconstruction 0-009-031 / / / / 08/17/23 / / 2,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Leo F. Giblyn Elementary:
18-0823 Reconstruction 0-010-027 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 293,010 293,010 BMJ 0 0 0 ECG Engineering, LLC 293,010 02/01/21 11/06/18
18-2189 Reconstruction 0-010-029 09/09/19 DONE DONE DONE 06/24/19 05/13/19 03/07/19 05/15/18 9,16 111,500 111,500 BMJ 0 0 0 Mark Design Studios 0 08/20/20 05/13/19
19-1575 Reconstruction 0-010-031 09/04/20 DONE DONE DONE 03/13/20 03/05/20 12/19/19 05/21/19 8,9 249,375 0 JLB 0 0 0 Mark Design Studios 0 / / 03/05/20
22-1829 Reconstruction 0-010-032 08/15/23 DONE DONE DONE 03/13/23 03/13/23 09/25/20 06/17/20 2,8,9,155,15,16 276,039 276,039 JJH 0 0 0 H2M Group 0 / / 03/13/23
21-1107FC Reconstruction 0-010-033 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 2,155,16 73,500 73,500 JLB 0 0 0 H2M Group 0 09/19/23 01/11/22
22-2099 Reconstruction 0-010-034 09/12/23 DONE DONE DONE 04/26/23 04/24/23 09/19/22 03/17/21 2,4,8 457,800 457,800 JJH 0 0 0 H2M Group 0 / / 04/24/23
New Visions School @ Raynor Field:
19-1670 Reconstruction 0-016-007 07/20/20 DONE DONE DONE 04/09/20 03/09/20 08/08/18 05/21/19 2,8,9,16 65,625 0 JLB 0 0 0 H2M Group 0 / / 03/09/20
18-0824 Reconstruction 0-016-008 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,155,16 324,758 324,758 BMJ 0 0 0 ECG Engineering, LLC 324,758 02/01/21 11/06/18
21-1108FC Reconstruction 0-016-009 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 2,155,16 63,000 63,000 JLB 0 0 0 H2M Group 0 09/15/23 01/11/22
21-1109FA Reconstruction 0-016-010 04/18/22 DONE DONE DONE 01/12/22 01/11/22 10/19/21 03/16/22 155 324,450 324,450 JLB 0 0 0 H2M Group 0 / / 01/11/22
- Reconstruction 0-016-011 / / / / 11/16/23 / / 2,8 0 0 JJH 0 0 0 0 / / / /
Freeport Admin. Bldg.:
18-0825 Reconstruction 1-003-012 05/23/19 DONE DONE DONE 11/14/18 11/06/18 08/21/18 07/03/18 2,16 147,582 0 BMJ 0 0 0 ECG Engineering, LLC 147,582 02/01/21 11/06/18
- Reconstruction 1-003-013 / / / / 08/17/23 / / 2 0 0 JJH 0 0 0 0 / / / /
Freeport Memorial Library:
22-0579 Reconstruction 6-008-015 10/17/22 DONE DONE DONE 09/26/22 09/19/22 01/31/22 08/03/22 7,155 500,000 0 JLB 0 0 0 WFC Architects, LLP 0 / / 09/19/22
(DEMO) High School Press Box:
- Reconstruction 7-017-002 / / / / 10/05/23 / / 0 0 JJH 0 0 0 0 / / / /
HS Pressbox:
23-1444 New Construction 7-023-001 UNREVIEWED
STARTED ADD. REQ'D01/31/24 10/30/23 09/28/23 05/16/23 02 - 16 0 0 JJH 0 0 0 H2M Group 0 / / 10/30/23
HS Guard Booth:
- New Construction 7-024-001 / / / / 09/28/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
HS Field Bath/Concession:
23-1445 New Construction 7-025-001 UNREVIEWED
STARTED ADD. REQ'D01/31/24 10/30/23 09/28/23 05/16/23 02 - 16 0 0 JJH 0 0 0 H2M Group 0 / / 10/30/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BALDWIN UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-10-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Brookside Elementary:
18-1436 Reconstruction 0-001-021 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 473,903 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
22-1386 Reconstruction 0-001-022 03/06/23 DONE DONE DONE 01/03/23 12/30/22 06/21/22 05/17/22 2,4,7,9,10,155,15,16 428,895 428,895 JLB 0 0 0 H2M Group 0 / / 12/30/22
- PR Additions and Alterations 0-001-023 / / / / 05/24/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Lenox School:
18-1437 Reconstruction 0-005-023 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 407,715 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
22-1387 Reconstruction 0-005-024 03/06/23 DONE DONE DONE 01/03/23 12/30/22 06/21/22 05/17/22 2,4,7,9,10,155,15,16 856,575 856,575 JLB 0 0 0 H2M Group 0 / / 12/30/22
- PR Additions and Alterations 0-005-025 / / / / 05/24/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Milburn Sch-LsdOut-NoBldgAid-JustKid:
18-1438 Reconstruction 0-006-024 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 251,513 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
Plaza Elementary:
18-1439 Reconstruction 0-007-023 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 920,025 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
- PR Additions and Alterations 0-007-024 / / / / 10/21/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
20-0122 Additions and Alterations 0-007-024 11/18/20 DONE DONE DONE 07/24/20 07/03/20 10/21/19 05/21/19 02 - 16 1,140,168 574,026 SLC 0 0 0 H2M Group 0 05/03/22 07/03/20
21-1489 Reconstruction 0-007-025 04/14/22 DONE DONE DONE 03/10/22 03/10/22 01/13/22 05/18/21 2,8,9 1,275,849 1,275,849 SLC 0 0 0 H2M Group 0 / / 03/10/22
22-1388 Reconstruction 0-007-026 03/06/23 DONE DONE DONE 01/03/23 12/30/22 06/21/22 05/17/22 2,4,7,9,10,155,15,16 713,813 713,813 JLB 0 0 0 H2M Group 0 / / 12/30/22
- PR Additions and Alterations 0-007-027 / / / / 05/24/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Baldwin Senior HS:
18-1440 Reconstruction 0-009-040 04/16/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,4,7,8,9,10,13,155, 1,900,008 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
21-2011 Reconstruction 0-009-041 08/03/22 DONE DONE DONE 06/21/22 06/21/22 03/07/22 11/10/21 2,4,7,8,9,155,15,16 240,000 0 SLC 0 0 0 H2M Group 0 / / 06/21/22
22-1464 Reconstruction 0-009-042 03/27/23 DONE DONE DONE 01/11/23 01/10/23 06/21/22 05/17/22 2,4,7,9,10,155,15,16 7,065,071 7,065,071 JLB 0 0 0 H2M Group 0 / / 01/10/23
Shubert ES Alt Ed LsdToUniondale1Yr:
18-1441 Reconstruction 0-010-021 04/16/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,155,16 1,457,280 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
- Reconstruction 0-010-022 / / / / 01/15/20 / / 2,7,9,16 0 0 SLC 0 0 0 0 / / / /
22-1389 Reconstruction 0-010-023 03/06/23 DONE DONE DONE 01/03/23 12/30/22 06/21/22 05/17/22 2,4,7,8,9,10,155,15, 3,028,684 0 JLB 0 0 0 H2M Group 0 / / 12/30/22
Steele Elementary:
18-1442 Reconstruction 0-011-027 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 549,266 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
- PR Additions and Alterations 0-011-028 / / / / 08/05/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-1539 Additions and Alterations 0-011-028 05/31/22 DONE DONE DONE 03/21/22 03/21/22 08/05/21 05/18/21 02 - 16 1,140,168 840,311 SLC 0 0 0 H2M Group 0 / / 03/21/22
22-1390 Reconstruction 0-011-029 03/06/23 DONE DONE DONE 01/03/23 12/30/22 06/21/22 05/17/22 2,4,7,9,10,155,15,16 642,431 642,431 JLB 0 0 0 H2M Group 0 / / 12/30/22
- PR Additions and Alterations 0-011-030 / / / / 05/24/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Baldwin Middle School:
18-1443 Reconstruction 0-012-033 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,4,7,8,9,10,15,16 1,945,680 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
22-1391 Reconstruction 0-012-034 03/06/23 DONE DONE DONE 01/03/23 12/30/22 06/21/22 05/17/22 2,4,7,9,10,155,15,16 999,337 999,337 SLC 0 0 0 H2M Group 0 / / 12/30/22
- Reconstruction 0-012-035 / / / / 09/29/22 / / 2,4,7,8,9,10,155,15, 0 0 SLC 0 0 0 0 / / / /
22-1934FC Reconstruction 0-012-036 06/21/23 DONE DONE DONE 03/24/23 03/03/23 01/31/23 02/15/23 2,7,9,155,16 1,452,149 1,452,149 MSK 0 0 0 H2M Group 0 / / 03/03/23
23-1655 Reconstruction 0-012-037 UNREVIEWED 03/21/24 03/20/24 08/11/23 05/16/23 2,4,16 0 0 MSK 0 0 0 H2M Group 0 / / 03/20/24
Meadow Elementary School:
18-1444 Reconstruction 0-013-025 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 1,080,742 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
22-1620 Reconstruction 0-013-026 03/07/23 DONE DONE DONE 02/03/23 02/02/23 06/21/22 05/17/22 2,4,7,9,10,155,15,16 1,675,080 1,675,080 JLB 0 0 0 H2M Group 0 / / 02/02/23
- PR Additions and Alterations 0-013-027 / / / / 05/24/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
District Office:
18-1445 Reconstruction 1-002-012 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 2,8,16 338,800 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
22-1621 Reconstruction 1-002-013 03/07/23 DONE DONE DONE 02/03/23 02/02/23 06/21/22 05/17/22 2,4,7,9,10,155,15,16 678,122 0 JLB 0 0 0 H2M Group 0 / / 02/02/23
Grounds Garage:
18-1446 Reconstruction 2-003-004 04/08/19 DONE DONE DONE 02/13/19 02/04/19 07/20/18 05/15/18 16 47,655 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
Plaza Shed Demolition:
20-0463 Reconstruction 2-017-001 11/18/20 DONE DONE DONE 09/28/20 09/14/20 08/19/20 05/21/19 2 20,000 0 SLC 0 0 0 H2M Group 0 / / 09/14/20
New Storage Bldg:
- PR New Construction 2-053-001 / / / / 11/09/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1465 New Construction 2-053-001 03/27/23 DONE DONE DONE 01/11/23 01/10/23 11/09/22 05/17/22 02 - 16 68,575 0 JLB 0 0 0 H2M Group 0 / / 01/10/23
Public Library:
19-1378 Reconstruction 6-023-008 04/10/20 DONE DONE DONE 02/06/20 01/27/20 10/09/19 12/19/19 7 538,600 0 SLC 0 0 0 H2M Group 0 / / 01/27/20
22-0050 Reconstruction 6-023-009 10/03/22 DONE DONE DONE 07/06/22 07/06/22 02/14/22 03/23/22 8 249,504 0 SLC 0 0 0 H2M Group 0 07/28/23 07/06/22
22-2471 Reconstruction 6-023-010 09/19/23 DONE DONE DONE 06/28/23 06/28/23 05/18/23 05/17/23 2,10,16 74,000 0 MSK 0 0 0 H2M Group 0 / / 06/28/23
23-1567 Reconstruction 6-023-011 UNREVIEWED 03/04/24 03/01/24 01/23/24 05/16/23 7,8,9,10,155,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 03/01/24
XXPress Box Demo:
22-1466 Reconstruction 7-030-002 03/27/23 DONE DONE DONE 01/11/23 01/10/23 09/22/22 05/17/22 2,7,8,9,10,13,155,15 79,125 0 JLB 0 0 0 H2M Group 0 / / 01/10/23
XX H.S. Ticket Booth:
22-1467 Reconstruction 7-031-004 03/27/23 DONE DONE DONE 01/11/23 01/10/23 11/02/22 05/17/22 2,7,8,9,16 17,935 0 JLB 0 0 0 H2M Group 0 / / 01/10/23
Guard Booth:
18-1447 New Construction 7-034-001 04/16/19 DONE DONE DONE 02/13/19 02/04/19 11/13/18 05/15/18 02 - 16 248,865 0 SLC 0 0 0 H2M Group 0 / / 02/04/19
Press Box/Stand @HS (New):
22-1468 New Construction 7-036-001 03/27/23 DONE DONE DONE 01/11/23 01/10/23 09/22/22 05/17/22 02 - 16 316,500 0 JLB 0 0 0 H2M Group 0 / / 01/10/23
Tent @ Baldwin MS:
- TQ Temporary Quarters 8-035-001 / / / / 04/27/21 / / 0 0 SLC 0 0 0 0 / / / /
Tent @ Baldwin Senior HS:
- TQ Temporary Quarters 8-036-001 / / / / 04/27/21 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
OCEANSIDE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-11-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Schl #3 - Oaks Road Elementary:
22-0571 Reconstruction 0-003-021 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 1,920,638 1,920,638 JJH 0 0 0 ECG Engineering, LLC 1,895,892 / / 09/23/22
- Reconstruction 0-003-022 / / / / 03/14/24 / / 2,8,9,16 0 0 JJH 0 0 0 0 / / / /
Oceanside School #4:
19-0046 Reconstruction 0-004-018 10/09/19 DONE DONE DONE 07/10/19 05/22/19 / / 04/10/19 2,4,8 386,245 0 BMJ 0 0 0 H2M Group 0 10/20/20 05/22/19
22-0572 Reconstruction 0-004-019 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 1,547,759 1,547,759 JJH 0 0 0 ECG Engineering, LLC 1,529,390 / / 09/23/22
North Oceanside Road School #5:
22-0573 Reconstruction 0-006-022 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 2,033,791 2,033,791 JJH 0 0 0 ECG Engineering, LLC 2,008,421 / / 09/23/22
Kindergarten Ctr/Castleton School #6:
22-0574 Reconstruction 0-007-023 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 1,771,848 1,771,848 JJH 0 0 0 ECG Engineering, LLC 1,724,125 / / 09/23/22
Senior High School #7:
19-0047 Reconstruction 0-008-035 10/09/19 DONE DONE DONE 07/10/19 05/22/19 01/28/19 04/10/19 2,4,8 236,732 0 BMJ 0 0 0 H2M Group 0 10/20/20 05/22/19
19-0048 Reconstruction 0-008-036 11/25/19 DONE DONE DONE 07/10/19 05/22/19 01/28/19 04/10/19 2,4 485,275 0 BMJ 0 0 0 H2M Group 0 08/13/21 05/22/19
18-2003 Reconstruction 0-008-037 06/24/19 DONE DONE DONE 05/23/19 05/20/19 04/04/19 05/21/19 2,8 800,000 800,000 BMJ 0 0 0 John A. Grillo 0 01/27/20 05/20/19
20-0876 Reconstruction 0-008-038 03/09/21 DONE DONE DONE 11/20/20 11/17/20 06/18/20 06/09/20 2,4,7,8,9,10,155,15, 3,309,782 3,309,782 JLB 0 0 0 John A. Grillo 0 09/28/22 11/17/20
21-0427 Reconstruction 0-008-039 11/29/21 DONE DONE DONE 09/24/21 09/24/21 06/17/21 05/18/21 2,4,7,8,9,10,155,15, 5,505,644 5,505,644 JLB 0 0 0 John A. Grillo 0 / / 09/24/21
22-0575 Reconstruction 0-008-040 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 4,648,469 4,648,469 JJH 0 0 0 ECG Engineering, LLC 4,548,777 / / 09/23/22
22-0589 Reconstruction 0-008-041 03/06/23 DONE DONE DONE 09/26/22 09/26/22 06/09/22 05/17/22 2,4,7,8,9,10,155,15, 1,989,755 1,989,755 JLB 0 0 0 John A. Grillo 0 / / 09/26/22
- PR Additions and Alterations 0-008-042 / / / / 06/05/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-008-043 / / / / 03/14/24 / / 2,13,155,16 0 0 JJH 0 0 0 0 / / / /
Fulton Ave. Elementary #8:
19-0049 Reconstruction 0-009-022 10/09/19 DONE DONE DONE 07/10/19 05/22/19 01/28/19 04/10/19 2,4,8 271,732 0 BMJ 0 0 0 H2M Group 0 10/20/20 05/22/19
22-0576 Reconstruction 0-009-023 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 995,545 995,545 JJH 0 0 0 ECG Engineering, LLC 969,948 / / 09/23/22
School #9 Middle/Elementary:
19-0050 Reconstruction 0-010-025 10/09/19 DONE DONE DONE 07/10/19 05/22/19 01/28/19 04/10/19 2,4,8 781,732 0 BMJ 0 0 0 H2M Group 0 08/10/21 05/22/19
22-0577 Reconstruction 0-010-026 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 1,789,764 1,789,764 JJH 0 0 0 ECG Engineering, LLC 1,749,154 / / 09/23/22
23-0726 Reconstruction 0-010-027 UNREVIEWED 10/18/23 10/12/23 06/05/23 05/16/23 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/12/23
Florence Smith School #2:
22-0578 Reconstruction 0-011-022 02/17/23 DONE DONE DONE 09/23/22 09/23/22 07/08/21 06/16/21 155,16 954,372 954,372 JJH 0 0 0 ECG Engineering, LLC 926,813 / / 09/23/22
Storage Container 26229 (baseball):
23-1153DB Discovered Building 2-036-001 12/08/23 DONE DONE DONE 12/08/23 12/08/23 10/31/23 / / 0 0 JJH 0 0 0 0 / / 12/08/23
Storage Container 190097 (Scouts):
23-1154DB Discovered Building 2-037-001 12/08/23 DONE DONE DONE 12/08/23 12/08/23 10/31/23 / / 0 0 JJH 0 0 0 0 / / 12/08/23
Storage Container 486604 (football):
23-1155DB Discovered Building 2-038-001 12/08/23 DONE DONE DONE 12/08/23 12/08/23 10/31/23 / / 0 0 JJH 0 0 0 0 / / 12/08/23
Storage Container 486638 (athletics):
23-1156DB Discovered Building 2-039-001 12/08/23 DONE DONE DONE 12/08/23 12/08/23 10/31/23 / / 0 0 JJH 0 0 0 0 / / 12/08/23
Storage Container 486675 (building):
23-1157DB Discovered Building 2-040-001 12/08/23 DONE DONE DONE 12/08/23 12/08/23 10/31/23 / / 0 0 JJH 0 0 0 0 / / 12/08/23
Storage Container 486575 (band):
23-1158DB Discovered Building 2-041-001 12/08/23 DONE DONE DONE 12/08/23 12/08/23 10/31/23 / / 0 0 JJH 0 0 0 0 / / 12/08/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
VALLEY STREAM 13 UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-13-02
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
James A. Dever School:
20-1919 Reconstruction 0-001-039 07/29/21 DONE DONE DONE 06/28/21 06/24/21 04/15/21 05/18/21 2,9 51,192 51,192 SLC 0 0 0 Mark Design Studios 0 09/17/21 06/24/21
21-0808 Additions and Alterations 0-001-040 03/29/22 DONE DONE DONE 11/30/21 11/24/21 05/04/21 05/18/21 02 - 16 2,134,324 378,977 SLC 0 0 0 Mark Design Studios 0 07/10/23 YES 11/24/21
22-0815 Reconstruction 0-001-041 03/28/23 DONE DONE DONE 10/26/22 10/24/22 09/13/22 05/17/22 2,8,10 106,100 106,100 JLB 0 0 0 Mark Design Studios 0 / / 10/24/22
22-1763FC Reconstruction 0-001-042 06/02/23 DONE DONE DONE 03/01/23 02/28/23 01/04/23 05/23/23 9,155,16 252,625 252,625 MSK 0 0 0 Mark Design Studios 0 / / 02/28/23
- Reconstruction 0-001-043 / / / / 02/14/23 / / 2,9,16 0 0 SLC 0 0 0 0 / / / /
Howell Road School:
20-1379 Reconstruction 0-002-027 04/26/21 DONE DONE DONE 03/05/21 03/02/21 09/29/20 06/09/20 7,9,155,16 100,000 100,000 SLC 0 0 0 Burton Behrendt Smith 0 07/01/23 03/02/21
21-1919 Reconstruction 0-002-028 06/14/22 DONE DONE DONE 06/03/22 06/03/22 04/28/22 05/17/22 2,9 93,342 93,342 SLC 0 0 0 Mark Design Studios 0 08/26/22 06/03/22
22-0816 Reconstruction 0-002-029 03/28/23 DONE DONE DONE 10/26/22 10/24/22 09/13/22 05/17/22 2,7,10,155,15 50,955 50,955 JLB 0 0 0 Mark Design Studios 0 / / 10/24/22
22-1764FC Reconstruction 0-002-030 06/02/23 DONE DONE DONE 03/01/23 02/28/23 01/04/23 05/23/23 9,155,16 252,625 252,625 MSK 0 0 0 Mark Design Studios 0 / / 02/28/23
23-0572 Reconstruction 0-002-031 03/07/24 DONE DONE DONE 09/29/23 09/27/23 02/14/23 05/16/23 2,9,16 130,710 130,710 MSK 0 0 0 Mark Design Studios 0 / / 09/27/23
Wheeler Avenue School:
20-1349 Reconstruction 0-003-031 06/17/21 DONE DONE DONE 02/24/21 02/12/21 12/14/20 07/28/20 8,9,10,16 225,475 225,475 SLC 0 0 0 Mark Design Studios 0 / / 02/12/21
22-0817 Reconstruction 0-003-032 03/28/23 DONE DONE DONE 10/26/22 10/24/22 09/13/22 05/17/22 2,8,10 64,715 64,715 JLB 0 0 0 Mark Design Studios 0 / / 10/24/22
22-1932FC Reconstruction 0-003-033 05/31/23 DONE DONE DONE 03/24/23 02/21/23 01/04/23 05/16/23 2,8,9,155,16 200,165 200,165 JLB 0 0 0 Mark Design Studios 0 / / 02/21/23
23-0573 Reconstruction 0-003-034 03/07/24 DONE DONE DONE 09/29/23 09/27/23 02/14/23 05/16/23 2,9,16 113,625 113,625 MSK 0 0 0 Mark Design Studios 0 / / 09/27/23
Willow Road School:
20-1350 Reconstruction 0-004-024 06/17/21 DONE DONE DONE 02/24/21 02/12/21 12/14/20 07/28/20 8,9,10,16 164,950 164,950 SLC 0 0 0 Mark Design Studios 0 / / 02/12/21
22-0818 Reconstruction 0-004-025 03/28/23 DONE DONE DONE 10/26/22 10/24/22 09/13/22 05/17/22 2,8,10 55,790 55,790 JLB 0 0 0 Mark Design Studios 0 / / 10/24/22
22-1765FC Reconstruction 0-004-026 06/02/23 DONE DONE DONE 03/01/23 02/28/23 01/04/23 05/23/23 9,155,16 252,625 252,625 MSK 0 0 0 Mark Design Studios 0 / / 02/28/23
23-0574 Reconstruction 0-004-027 03/07/24 DONE DONE DONE 09/29/23 09/27/23 02/14/23 05/16/23 2,9,155,16 127,560 127,560 MSK 0 0 0 Mark Design Studios 0 / / 09/27/23
District-Wide:
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HEWLETT-WOODMERE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-14-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Franklin Early Childhood Center:
20-1943 Reconstruction 0-001-024 11/16/21 DONE DONE DONE 06/30/21 06/28/21 05/03/21 05/19/15 2,4,7 2,030,000 2,030,000 JLB 0 0 0 John A. Grillo 0 / / 06/28/21
21-2046 Reconstruction 0-001-025 03/20/23 DONE DONE DONE 06/27/22 06/23/22 01/27/22 06/09/20 2,4,7,8,9,10,155,15, 790,000 790,000 JLB 0 0 0 John A. Grillo 0 / / 06/23/22
21-1589 Reconstruction 0-001-026 06/07/22 DONE DONE DONE 04/04/22 03/30/22 01/27/22 05/17/16 7,155,15,16 400,000 400,000 JLB 0 0 0 John A. Grillo 0 / / 03/30/22
22-0766 Reconstruction 0-001-027 01/24/23 DONE DONE DONE 10/19/22 10/18/22 09/02/22 05/17/22 4,9,14,16 300,000 300,000 JLB 0 0 0 John A. Grillo 0 / / 10/18/22
Hewlett Elementary School:
18-1360 Reconstruction 0-002-019 03/29/19 DONE DONE DONE 01/30/19 01/25/19 09/13/18 05/16/17 2,4,7,8,9 5,350,000 5,350,000 MTM 0 0 0 John A. Grillo 0 05/13/21 01/25/19
19-1056 Reconstruction 0-002-020 04/27/20 DONE DONE DONE 12/26/19 12/18/19 09/23/19 05/21/19 2,7,16 2,000,000 0 JSS 0 0 0 John A. Grillo 0 / / 12/18/19
22-0767 Reconstruction 0-002-021 01/24/23 DONE DONE DONE 10/19/22 10/18/22 09/02/22 06/09/20 4,9,14,16 300,000 300,000 JLB 0 0 0 John A. Grillo 0 / / 10/18/22
23-1656 Reconstruction 0-002-022 UNREVIEWED 03/21/24 03/21/24 03/08/24 05/16/23 10 0 0 JJH 0 0 0 John A. Grillo 0 / / 03/21/24
George W. Hewlett High School:
18-1723 Reconstruction 0-006-026 09/17/19 DONE DONE DONE 03/27/19 03/19/19 09/13/18 05/16/17 2,4,7,9,155,15,16 10,500,000 10,500,000 MTM 0 0 0 John A. Grillo 0 02/03/22 03/19/19
19-0439 Reconstruction 0-006-028 02/11/20 DONE DONE DONE 09/19/19 09/13/19 06/24/19 05/15/18 8 6,000,000 6,000,000 JSS 0 0 0 John A. Grillo 0 02/03/22 09/13/19
21-0730 Reconstruction 0-006-029 03/01/22 DONE DONE DONE 11/16/21 11/16/21 11/01/21 05/11/21 4,7 645,000 645,000 JLB 0 0 0 John A. Grillo 0 09/21/22 11/16/21
21-1566 Reconstruction 0-006-030 06/06/22 DONE DONE DONE 03/28/22 03/25/22 11/10/21 06/16/20 16 21,236 21,236 JLB 0 0 0 John A. Grillo 0 05/08/23 03/25/22
21-1783 Reconstruction 0-006-031 08/08/22 DONE DONE DONE 05/09/22 05/05/22 01/27/22 06/09/20 15 600,000 600,000 JLB 0 0 0 John A. Grillo 0 / / 05/05/22
21-1590 Reconstruction 0-006-032 06/07/22 DONE DONE DONE 04/04/22 03/30/22 01/27/22 06/09/20 7,9,155,15,16 325,000 325,000 JLB 0 0 0 John A. Grillo 0 / / 03/30/22
22-0481 Reconstruction 0-006-033 01/04/23 DONE DONE DONE 09/14/22 09/12/22 09/08/22 05/17/22 2,4,7,8,9,155,15,16 2,650,000 2,650,000 JJH 0 0 0 John A. Grillo 0 09/01/23 09/12/22
23-0810 Reconstruction 0-006-034 UNREVIEWED 10/25/23 10/18/23 05/25/23 05/16/23 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/18/23
23-0886 Reconstruction 0-006-035 UNREVIEWED 11/06/23 11/03/23 05/25/23 05/16/23 2,4,7,8,9,13,155,15, 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/03/23
23-1476 Reconstruction 0-006-036 UNREVIEWED 02/06/24 02/05/24 09/29/23 05/16/23 7 0 0 JJH 0 0 0 John A. Grillo 0 / / 02/05/24
Woodmere Middle School:
18-2175 Reconstruction 0-008-018 09/24/19 DONE DONE DONE 06/20/19 06/18/19 09/13/18 05/16/17 2,4,8,9,10,155,15,16 2,025,000 2,025,000 JLB 0 0 0 John A. Grillo 0 02/03/22 06/18/19
20-0706 Reconstruction 0-008-019 01/29/21 DONE DONE DONE 10/28/20 10/05/20 10/05/20 06/16/20 14,16 277,300 0 JSS 0 0 0 John A. Grillo 0 / / 10/05/20
- Reconstruction 0-008-020 / / / / 01/27/22 / / 16 0 0 JLB 0 0 0 0 / / / /
23-0811 Reconstruction 0-008-021 UNREVIEWED 10/25/23 10/18/23 05/25/23 05/16/23 2,4,7,8,9,13,155,15, 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/18/23
Woodmere Educational Center:
21-0530 Reconstruction 1-004-022 03/02/22 DONE DONE DONE 10/15/21 10/14/21 05/28/21 05/11/21 4,8 335,000 0 JLB 0 0 0 John A. Grillo 0 09/21/22 10/14/21
22-1508 Reconstruction 1-004-023 05/11/23 DONE DONE DONE 01/18/23 01/18/23 04/05/22 05/11/21 2 625,000 0 JJH 0 0 0 John A. Grillo 0 / / 01/18/23
22-1898 Reconstruction 1-004-024 06/23/23 DONE DONE DONE 03/20/23 03/16/23 09/02/22 05/17/22 2,4,8,9,10,15,16 750,000 0 JJH 0 0 0 John A. Grillo 0 / / 03/16/23
STORAGE BUILDING:
23-0857 New Construction 2-027-001 UNREVIEWED 11/01/23 10/30/23 09/25/18 05/16/17 02 - 16 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/30/23
Public Library:
18-1805 Reconstruction 6-013-009 01/10/20 DONE DONE DONE 04/05/19 03/28/19 10/26/18 09/01/18 155,16 820,594 0 JLB 0 0 0 Barile Gallagher & Associates 0 / / 03/28/19
Districtwide:
- Reconstruction 7-999-004 / / / / 11/25/20 / / 16 0 0 JSS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LAWRENCE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-15-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Public School 2:
- Reconstruction 0-002-029 / / / / 09/28/23 / / 15 0 0 MSK 0 0 0 0 / / / /
Public School 4:
- Reconstruction 0-004-029 / / / / 09/28/23 / / 15 0 0 MSK 0 0 0 0 / / / /
XXPublic School 5 (sold):
- XX Reconstruction 0-005-028 CANCELLED / / / / 09/28/23 / / 15 0 9,951,624 MSK 0 0 0 0 / / / /
Lawrence MS-BroadwayCampus(FrmrlyJHS:
17-1718 Reconstruction 0-007-041 12/18/19 DONE DONE DONE 04/18/18 04/18/18 09/13/16 05/16/17 4,7,8,9,10,16 1,016,950 0 SLC 0 0 0 Mark Design Studios 0 / / 04/18/18
19-0073 Reconstruction 0-007-043 09/23/19 DONE DONE DONE 07/15/19 07/05/19 08/16/17 05/21/19 2,8,9,15,16 693,079 0 SLC 0 0 0 Mark Design Studios 0 / / 07/05/19
19-0471 Reconstruction 0-007-044 03/16/20 DONE DONE DONE 09/23/19 09/17/19 02/06/19 05/21/19 2,4,7,8,9,10,155,15, 3,218,589 0 SLC 0 0 0 Mark Design Studios 0 / / 09/17/19
19-0473 Reconstruction 0-007-045 03/12/20 DONE DONE DONE 09/23/19 08/20/19 07/11/19 05/15/18 2,4,7,8,9,10,155,15, 2,302,255 0 SLC 0 0 0 Mark Design Studios 0 / / 08/20/19
19-0323 Reconstruction 0-007-046 11/26/19 DONE DONE DONE 08/29/19 08/20/19 08/07/19 05/16/17 2,7 943,205 0 SLC 0 0 0 Mark Design Studios 0 / / 08/20/19
20-0833 Reconstruction 0-007-047 06/09/21 DONE DONE DONE 11/16/20 10/30/20 09/16/20 06/16/20 2,4,7,8,9,155,15,16 1,677,000 1,677,000 SLC 0 0 0 Mark Design Studios 0 / / 10/30/20
20-1894 Reconstruction 0-007-048 09/02/21 DONE DONE DONE 06/16/21 06/11/21 05/11/21 05/11/21 2,4,7,8,9,10,155,15, 4,226,089 4,226,089 SLC 0 0 0 Mark Design Studios 0 / / 06/11/21
22-0970 Reconstruction 0-007-049 03/13/23 DONE DONE DONE 11/14/22 11/14/22 11/03/22 05/16/17 7 1,123,000 1,123,000 SLC 0 0 0 Mark Design Studios 0 / / 11/14/22
22-1523 Reconstruction 0-007-050 06/28/23 DONE DONE DONE 01/20/23 01/20/23 11/03/22 05/11/21 2,4,8,9,155,15,16 2,992,800 2,992,800 MSK 0 0 0 Mark Design Studios 0 / / 01/20/23
- Reconstruction 0-007-051 / / / / 09/27/23 / / 8 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-007-052 / / / / 09/28/23 / / 155 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-007-053 / / / / 09/28/23 / / 15 0 0 MSK 0 0 0 0 / / / /
Lawrence Senior High School:
19-0472 Reconstruction 0-008-043 03/16/20 DONE DONE DONE 09/23/19 09/17/19 02/01/19 05/21/19 2,4,7,8,9,10,14,155, 4,993,889 0 SLC 0 0 0 Mark Design Studios 0 / / 09/17/19
20-1428 Reconstruction 0-008-044 03/06/22 DONE DONE DONE 03/11/21 12/01/20 02/12/20 05/24/19 2,13,15,16 14,421,615 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
20-1346 Reconstruction 0-008-045 12/24/21 DONE DONE DONE 02/23/21 12/03/20 02/12/20 12/14/20 2,9,13,155,15,16 10,087,692 0 SLC 0 0 0 Mark Design Studios 0 / / 12/03/20
- Reconstruction 0-008-046 / / / / 09/28/23 / / 15 0 0 MSK 0 0 0 0 / / / /
Maint. Storage Building:
20-1429 New Construction 2-031-001 03/06/22 DONE DONE DONE 03/11/21 12/01/20 01/27/21 05/24/19 02 - 16 115,000 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
Peninsula Public Library:
20-1537 Reconstruction 6-003-002 06/09/21 DONE DONE DONE 04/02/21 03/29/21 02/22/21 10/30/20 2,8,9,155,16 110,250 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 03/29/21
- Reconstruction 6-003-003 / / / / 12/13/23 / / 2,155 0 0 MSK 0 0 0 0 / / / /
Concession Building:
20-1430 New Construction 7-030-001 03/06/22 DONE DONE DONE 03/11/21 12/01/20 01/27/21 05/24/19 02 - 16 350,000 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
Pump House #1:
20-1431 New Construction 7-032-001 03/06/22 DONE DONE DONE 03/11/21 12/01/20 01/27/21 05/24/19 02 - 16 125,000 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
Pump House #2:
20-1432 New Construction 7-033-001 03/06/22 DONE DONE DONE 03/11/21 12/01/20 01/27/21 05/24/19 02 - 16 125,000 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
Pump House #3:
20-1433 New Construction 7-034-001 03/06/22 DONE DONE DONE 03/11/21 12/01/20 01/27/21 05/24/19 02 - 16 125,000 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
Grandstand Press Box:
20-1434 New Construction 7-035-001 03/06/22 DONE DONE DONE 03/11/21 12/01/20 01/27/21 05/24/19 02 - 16 165,000 0 SLC 0 0 0 Mark Design Studios 0 / / 12/01/20
Residence/Garage:
- DB Discovered Building 7-036-001 / / / / 07/07/22 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ELMONT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-16-02
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Alden Terrace School:
- XX Reconstruction 0-001-016 CANCELLED / / / / 08/14/20 / / 2,9,155,15,16 0 8,187,410 JSS 0 0 0 0 / / / /
- XX Reconstruction 0-001-017 CANCELLED / / / / 04/12/21 / / 2,16 0 8,187,410 JSS 0 0 0 0 / / / /
21-1633 Reconstruction 0-001-018 10/03/22 DONE DONE DONE 04/08/22 04/08/22 03/09/22 11/30/21 2,8,9,155,16 98,225 98,225 SLC 0 0 0 H2M Group 0 / / 04/08/22
22-0277 Reconstruction 0-001-019 04/12/23 DONE DONE DONE 08/17/22 08/15/22 06/01/22 11/30/21 2,7,9,155,16 5,665,923 5,665,923 SLC 0 0 0 H2M Group 0 / / 08/15/22
22-0426 Reconstruction 0-001-020 06/02/23 DONE DONE DONE 09/08/22 09/07/22 06/01/22 11/30/21 2,8,9,10,15,16 2,334,173 2,334,173 JLB 0 0 0 H2M Group 0 / / 09/07/22
- Reconstruction 0-001-021 / / / / / / / / 2,7 0 0 JJH 0 0 0 0 / / / /
Clara H Carlson School:
- XX Reconstruction 0-002-024 CANCELLED / / / / 04/12/21 / / 2,16 0 18,379,224 JSS 0 0 0 0 / / / /
21-1634 Reconstruction 0-002-025 10/03/22 DONE DONE DONE 04/08/22 04/08/22 03/09/22 11/30/21 2,8,9,155,16 103,429 103,429 SLC 0 0 0 H2M Group 0 / / 04/08/22
22-0278 Reconstruction 0-002-026 04/12/23 DONE DONE DONE 08/17/22 08/15/22 06/01/22 11/30/21 2,7,9,155,16 4,947,232 4,947,232 SLC 0 0 0 H2M Group 0 / / 08/15/22
22-0427 Reconstruction 0-002-027 06/02/23 DONE DONE DONE 09/08/22 09/07/22 06/01/22 11/30/21 2,8,9,10,15,16 2,686,027 2,686,027 JLB 0 0 0 H2M Group 0 / / 09/07/22
- Reconstruction 0-002-028 / / / / 04/03/23 / / 7 0 0 JJH 0 0 0 0 / / / /
Covert Ave School:
19-1298 Reconstruction 0-003-021 04/23/20 DONE DONE DONE 01/29/20 01/22/20 11/18/16 05/16/17 2,9 1,012,292 1,012,292 JSS 0 0 0 H2M Group 0 09/01/20 01/22/20
- XX Reconstruction 0-003-022 CANCELLED / / / / 04/12/21 / / 2,16 0 13,978,965 JSS 0 0 0 0 / / / /
21-1635 Reconstruction 0-003-023 10/03/22 DONE DONE DONE 04/08/22 04/08/22 03/09/22 11/30/21 2,8,9,155,16 111,073 111,073 SLC 0 0 0 H2M Group 0 / / 04/08/22
22-0279 Reconstruction 0-003-024 04/12/23 DONE DONE DONE 08/17/22 08/15/22 06/01/22 11/30/21 2,7,9,155,16 4,782,110 4,782,110 SLC 0 0 0 H2M Group 0 / / 08/15/22
22-0428 Reconstruction 0-003-025 06/02/23 DONE DONE DONE 09/08/22 09/07/22 06/01/22 11/30/21 2,8,9,10,15,16 2,579,685 2,579,685 JLB 0 0 0 H2M Group 0 / / 09/07/22
- Reconstruction 0-003-026 / / / / 04/03/23 / / 2,7,9,155,15,16 0 0 JJH 0 0 0 0 / / / /
Dutch Broadway School:
- XX Reconstruction 0-004-021 CANCELLED / / / / 04/12/21 / / 2,16 0 8,187,410 JSS 0 0 0 0 / / / /
21-1636 Reconstruction 0-004-022 10/03/22 DONE DONE DONE 04/08/22 04/08/22 03/09/22 11/30/21 2,8,9,155,16 96,436 96,436 SLC 0 0 0 H2M Group 0 / / 04/08/22
22-0280 Reconstruction 0-004-023 04/12/23 DONE DONE DONE 08/17/22 08/15/22 06/01/22 11/30/21 2,7,9,155,16 5,347,224 5,347,224 SLC 0 0 0 H2M Group 0 / / 08/15/22
22-0429 Reconstruction 0-004-024 06/02/22 DONE DONE DONE 09/08/22 09/07/22 06/01/22 11/30/21 2,8,9,10,15,16 3,334,241 3,334,241 JLB 0 0 0 H2M Group 0 / / 09/07/22
- Reconstruction 0-004-025 / / / / 04/03/23 / / 2,7,8 0 0 JJH 0 0 0 0 / / / /
Gotham Avenue School:
- XX Reconstruction 0-006-024 CANCELLED / / / / 10/27/20 / / 2,155,15,16 0 9,470,230 JSS 0 0 0 0 / / / /
- XX Reconstruction 0-006-025 CANCELLED / / / / 04/12/21 / / 2,16 0 9,470,230 JSS 0 0 0 0 / / / /
21-1637 Reconstruction 0-006-026 10/03/22 DONE DONE DONE 04/08/22 04/08/22 03/09/22 11/30/21 2,8,9,155,16 98,469 98,469 SLC 0 0 0 H2M Group 0 / / 04/08/22
22-0281 Reconstruction 0-006-027 04/12/23 DONE DONE DONE 08/17/22 08/15/22 06/01/22 11/30/21 2,7,9,155,16 4,789,153 4,789,153 SLC 0 0 0 H2M Group 0 / / 08/15/22
22-0430 Reconstruction 0-006-028 06/02/23 DONE DONE DONE 09/08/22 09/07/22 06/01/22 11/30/21 2,8,9,10,15,16 3,116,300 3,116,300 JLB 0 0 0 H2M Group 0 / / 09/07/22
- Reconstruction 0-006-029 / / / / 04/03/23 / / 7,15 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-006-030 / / / / 04/03/23 / / 155,16 0 0 JJH 0 0 0 0 / / / /
Stewart Manor School:
- XX Reconstruction 0-007-015 CANCELLED / / / / 04/12/21 / / 2,16 0 8,857,116 JSS 0 0 0 0 / / / /
21-1638 Reconstruction 0-007-016 10/03/22 DONE DONE DONE 04/08/22 04/08/22 03/09/22 11/30/21 2,8,9,155,16 101,314 101,314 SLC 0 0 0 H2M Group 0 / / 04/08/22
22-0282 Reconstruction 0-007-017 04/12/23 DONE DONE DONE 08/17/22 08/15/22 06/01/22 11/30/21 2,7,9,155,16 3,406,983 3,406,983 SLC 0 0 0 H2M Group 0 / / 08/15/22
22-0431 Reconstruction 0-007-018 06/02/23 DONE DONE DONE 09/08/22 09/07/22 06/01/22 11/30/21 2,8,9,10,15,16 1,585,002 1,585,002 JLB 0 0 0 H2M Group 0 / / 09/07/22
- Reconstruction 0-007-019 / / / / 04/03/23 / / 2,7 0 0 JJH 0 0 0 0 / / / /
Pupil Personnel Srvcs./Frmr Pub. Lib:
- PR Additions and Alterations 6-016-007 / / / / 02/29/24 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
Elmont Memorial Library:
- Reconstruction 6-022-004 / / / / 08/16/23 / / 7 0 0 MSK 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
GARDEN CITY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-18-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Homestead School:
22-1622 Reconstruction 0-001-013 04/18/23 DONE DONE DONE 02/03/23 02/02/23 06/17/22 05/17/22 2,8,15,16 400,000 400,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/23
23-0978 Reconstruction 0-001-014 UNREVIEWED 11/14/23 11/10/23 09/15/23 05/16/23 155,16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/10/23
Locust School:
22-1623 Reconstruction 0-003-012 04/18/23 DONE DONE DONE 02/03/23 02/02/23 06/17/22 05/17/22 2,8,15,16 400,000 400,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/23
23-0979 Reconstruction 0-003-013 UNREVIEWED 11/14/23 11/10/23 09/15/23 05/16/23 155,16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/10/23
Stewart Avenue School:
19-1004 Reconstruction 0-004-014 01/31/20 DONE DONE DONE 12/16/19 12/03/19 09/04/19 05/21/19 15,16 50,000 50,000 BMJ 0 0 0 Burton Behrendt Smith 0 10/26/21 12/03/19
21-0786 Reconstruction 0-004-015 03/10/22 DONE DONE DONE 11/30/21 11/23/21 06/25/21 05/18/21 9,155,15,16 325,000 325,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 11/23/21
21-0817 Reconstruction 0-004-016 03/10/22 DONE DONE DONE 12/02/21 11/30/21 09/02/21 05/18/21 4 198,750 198,750 SLC 0 0 0 Burton Behrendt Smith 0 12/19/23 11/30/21
22-1094 Reconstruction 0-004-017 03/16/23 DONE DONE DONE 11/29/22 11/28/22 06/17/22 05/17/22 2,7 3,000,000 3,000,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/28/22
22-1455 Reconstruction 0-004-018 03/08/23 DONE DONE DONE 01/09/23 01/09/23 06/17/22 05/17/22 2,4,7,8,9,155,15,16 1,895,000 1,895,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 01/09/23
Stratford Ave. School:
19-1005 Reconstruction 0-005-018 01/31/20 DONE DONE DONE 12/16/19 12/03/19 09/04/19 05/21/19 4,8,9,10,155,15,16 200,000 0 BMJ 0 0 0 Burton Behrendt Smith 0 / / 12/03/19
21-0787 Reconstruction 0-005-019 03/10/22 DONE DONE DONE 11/30/21 11/23/21 06/25/21 05/18/21 9,155,15,16 325,000 325,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 11/23/21
21-0818 Reconstruction 0-005-020 03/10/22 DONE DONE DONE 12/02/21 11/30/21 09/02/21 05/18/21 2,4,155 1,175,000 1,175,000 SLC 0 0 0 Burton Behrendt Smith 0 12/19/23 11/30/21
22-1456 Reconstruction 0-005-021 03/08/23 DONE DONE DONE 01/09/23 01/09/23 06/17/22 05/17/22 2,4,7,8,9,155,15,16 2,450,000 2,450,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 01/09/23
Garden City Middle School:
19-1006 Reconstruction 0-006-024 01/31/20 DONE DONE DONE 12/16/19 12/03/19 09/04/19 05/21/19 155 500,000 500,000 BMJ 0 0 0 Burton Behrendt Smith 0 09/16/22 12/03/19
21-0726 Reconstruction 0-006-025 03/11/22 DONE DONE DONE 11/16/21 11/15/21 10/19/20 06/09/20 4,8,9,155,16 2,525,000 2,525,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 11/15/21
21-0819 Reconstruction 0-006-026 03/10/22 DONE DONE DONE 12/02/21 11/30/21 09/02/21 05/18/21 2,4 346,000 346,000 SLC 0 0 0 Burton Behrendt Smith 0 12/19/23 11/30/21
22-1095 Reconstruction 0-006-027 03/16/23 DONE DONE DONE 11/29/22 11/28/22 06/17/22 05/17/22 4 210,000 210,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/28/22
Garden City High School:
19-1007 Reconstruction 0-007-027 01/31/20 DONE DONE DONE 12/16/19 11/08/19 09/04/19 05/21/19 2,8,9,16 1,352,400 1,352,400 BMJ 0 0 0 Burton Behrendt Smith 0 09/16/22 11/08/19
20-1359 Reconstruction 0-007-028 04/02/21 DONE DONE DONE 03/04/21 02/26/21 10/19/20 06/09/20 8,9,155,15,16 300,000 300,000 SLC 0 0 0 Burton Behrendt Smith 0 08/04/22 02/26/21
- XX Additions and Alterations 0-007-029 CANCELLED / / / / 06/24/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1457 Reconstruction 0-007-030 02/22/23 DONE DONE DONE 01/09/23 01/09/23 06/17/22 05/17/22 2,4,7,8,9,15,16 1,200,000 1,200,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 01/09/23
22-1096 Reconstruction 0-007-031 03/16/23 DONE DONE DONE 11/29/22 11/28/22 06/17/22 05/17/22 4 300,000 300,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/28/22
- PR Additions and Alterations 0-007-032 / / / / 05/19/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-0693 Additions and Alterations 0-007-032 STARTED DONE UNREVIEWED10/13/23 10/07/23 05/19/23 05/17/22 02 - 16 3,500,000 3,500,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 10/07/23
23-1011 Reconstruction 0-007-033 UNREVIEWED 11/15/23 11/13/23 09/15/23 05/16/23 13,16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/13/23
Hemlock School:
22-1624 Reconstruction 0-018-011 04/18/23 DONE DONE DONE 02/03/23 02/02/23 06/17/22 05/17/22 2,8,15,16 400,000 400,000 WLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/23
23-0980 Reconstruction 0-018-012 UNREVIEWED 11/14/23 11/10/23 09/15/23 05/16/23 155,16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 11/10/23
Administration Building:
21-0820 Reconstruction 1-008-009 03/10/22 DONE DONE DONE 12/02/21 11/30/21 09/02/21 05/18/21 4,155 66,500 0 SLC 0 0 0 Burton Behrendt Smith 0 12/19/23 11/30/21
Locust Storage Bldg.:
- PR New Construction 2-044-001 / / / / 09/18/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1466 New Construction 2-044-001 UNREVIEWED 02/05/24 02/02/24 09/18/23 05/16/23 02 - 16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/24
Homestead Storage Bldg:
- PR New Construction 2-045-001 / / / / 09/18/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1467 New Construction 2-045-001 UNREVIEWED 02/05/24 02/02/24 09/18/23 05/16/23 02 - 16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/24
Hemlock Storage Building:
- PR New Construction 2-046-001 / / / / 09/18/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1468 New Construction 2-046-001 UNREVIEWED 02/05/24 02/02/24 09/18/23 05/16/23 02 - 16 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/24
Bus Garage:
19-1008 Reconstruction 5-009-011 01/31/20 DONE DONE DONE 12/16/19 12/03/19 09/04/19 05/21/19 2,16 60,000 60,000 BMJ 0 0 0 Burton Behrendt Smith 0 06/13/22 12/03/19
23-1252 Reconstruction 5-009-012 UNREVIEWED 12/21/23 12/20/23 09/15/23 05/16/23 2,9 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 12/20/23
XXGarden City HS Greenhouse-Canceled:
- XX New Construction 7-043-001 CANCELLED / / / / 06/25/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EAST ROCKAWAY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-19-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior Senior High School:
20-1038 Reconstruction 0-001-039 03/25/21 DONE DONE DONE 12/23/20 12/15/20 12/13/19 11/14/19 2,13,16 9,637,635 4,101,005 JLB 0 0 0 John A. Grillo 0 08/11/22 12/15/20
20-0393 Reconstruction 0-001-040 11/18/20 DONE DONE DONE 09/18/20 08/31/20 07/15/20 08/11/20 2,16 5,609,828 0 JLB 0 0 0 Tetra Tech 0 10/14/21 08/31/20
20-1247 Reconstruction 0-001-041 05/21/21 DONE DONE DONE 02/05/21 02/01/21 07/24/20 11/14/19 4,8,9,10,155,15,16 9,283,080 9,283,080 JLB 0 0 0 John A. Grillo 0 02/08/23 02/01/21
- Reconstruction 0-001-042 / / / / 04/05/22 / / 2,9,155 0 0 SLC 0 0 0 0 / / / /
23-1151 Reconstruction 0-001-043 UNREVIEWED 12/08/23 12/07/23 09/29/23 11/14/19 2,4,8,9,15,16 0 0 WLC 0 0 0 John A. Grillo 0 / / 12/07/23
23-0882 Reconstruction 0-001-044 UNREVIEWED 11/06/23 11/03/23 09/29/23 11/14/19 4,9,16 0 0 WLC 0 0 0 John A. Grillo 0 / / 11/03/23
Rhame Avenue Elementary School:
21-0839 Reconstruction 0-002-018 04/26/22 DONE DONE DONE 12/06/21 12/02/21 12/03/21 11/14/19 4,7,9,13,155,16 903,300 903,300 JLB 0 0 0 John A. Grillo 0 / / 12/02/21
21-1966 Reconstruction 0-002-019 11/09/22 DONE DONE DONE 06/13/22 06/13/22 03/23/22 11/15/21 4,7,8,9,10,155,15,16 3,025,000 3,025,000 WLC 0 0 0 John A. Grillo 0 / / 06/13/22
Centre Ave School:
19-1060 Reconstruction 0-003-018 04/10/20 DONE DONE DONE 12/26/19 12/19/19 08/30/19 05/21/19 8,9 122,440 122,440 JLB 0 0 0 John A. Grillo 0 01/06/21 12/19/19
19-1503 Reconstruction 0-003-019 04/24/20 DONE DONE DONE 03/02/20 02/28/20 12/13/19 11/14/19 4 1,156,990 1,156,990 JLB 0 0 0 John A. Grillo 0 07/22/22 02/28/20
19-1867 Reconstruction 0-003-020 09/18/20 DONE DONE DONE 06/24/20 06/22/20 12/13/19 11/14/19 7,9,155,15,16 1,532,469 1,532,469 JLB 0 0 0 John A. Grillo 0 08/11/22 06/22/20
21-1967 Reconstruction 0-003-021 11/09/22 DONE DONE DONE 06/13/22 06/13/22 03/22/22 11/15/21 4,7,8,13,155,15,16 2,452,019 2,452,019 WLC 0 0 0 John A. Grillo 0 09/01/23 06/13/22
22-1085 Reconstruction 0-003-022 04/18/23 DONE DONE DONE 11/29/22 11/18/22 08/15/22 11/14/19 9 245,009 245,009 WLC 0 0 0 John A. Grillo 0 09/01/23 11/18/22
Technology Education Building:
20-1248 Reconstruction 0-004-003 05/21/21 DONE DONE DONE 02/05/21 02/01/21 07/24/20 11/14/19 2,4,8,9,10,155,15,16 2,592,000 1,170,765 JLB 0 0 0 John A. Grillo 0 02/07/23 02/01/21
Press Box:
20-1039 New Construction 7-015-001 03/25/21 DONE DONE DONE 12/23/20 12/15/20 12/13/19 11/14/19 02 - 16 140,000 0 JLB 0 0 0 John A. Grillo 0 10/14/21 12/15/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LYNBROOK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-20-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Lynbrook High School:
18-1376 Additions and Alterations 0-001-025 07/24/19 DONE DONE DONE 02/01/19 01/30/19 10/11/17 10/03/17 02 - 16 29,109,750 18,095,622 BMJ 0 0 0 John A. Grillo 0 06/10/22 01/30/19
19-0829 Reconstruction 0-001-026 03/02/20 DONE DONE DONE 11/19/19 10/21/19 06/17/19 05/21/19 2,4,7,8,10,155,15,16 375,000 375,000 BMJ 0 0 0 John A. Grillo 0 10/05/22 10/21/19
21-1658 Reconstruction 0-001-027 06/27/22 DONE DONE DONE 04/13/22 04/12/22 06/29/20 06/09/20 2,7,8,10,155,15,16 1,400,000 1,400,000 JLB 0 0 0 John A. Grillo 0 / / 04/12/22
23-0663 Reconstruction 0-001-028 UNREVIEWED
STARTED UNREVIEWED10/10/23 10/06/23 06/22/23 05/16/23 14 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/06/23
South Lynbrook Middle School:
23-0664 Reconstruction 0-002-024 UNREVIEWED
STARTED UNREVIEWED10/10/23 10/06/23 06/22/23 05/16/23 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/06/23
Atlantic Ave Admin. & Kindergarten:
19-1788 Reconstruction 0-003-021 06/02/20 DONE DONE DONE 05/29/20 05/11/20 02/28/20 03/11/20 8,9,14,16 125,000 125,000 JSS 0 0 0 John A. Grillo 0 04/29/22 05/11/20
20-0700 Reconstruction 0-003-022 02/09/21 DONE DONE DONE 10/28/20 10/05/20 06/29/20 06/16/20 2,155,15,16 1,000,000 1,000,000 JSS 0 0 0 John A. Grillo 0 05/01/23 10/05/20
Marion Elementary School:
18-1361 Reconstruction 0-004-022 04/01/19 DONE DONE DONE 01/30/19 01/15/19 06/20/18 05/15/18 2,4,9,10,155,15,16 596,000 596,000 BMJ 0 0 0 John A. Grillo 0 01/02/20 01/15/19
19-1840 Reconstruction 0-004-023 08/28/20 DONE DONE DONE 06/12/20 06/10/20 06/17/19 05/21/19 2,4,7,8,9,14,155,15, 2,000,000 1,391,425 JSS 0 0 0 John A. Grillo 0 06/10/22 06/10/20
22-1159 Reconstruction 0-004-024 05/02/23 DONE DONE DONE 12/05/22 12/02/22 08/09/22 05/18/21 2,4,8,9,155,15,16 2,850,000 2,404,000 JJH 0 0 0 John A. Grillo 0 / / 12/02/22
23-0665 Reconstruction 0-004-025 UNREVIEWED
STARTED UNREVIEWED10/10/23 10/06/23 06/22/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/06/23
Waverly Park Elementary:
18-1468 Reconstruction 0-005-018 05/02/19 DONE DONE DONE 02/19/19 02/15/19 06/20/18 05/15/18 2,4,7,8,9,14,155,15, 1,000,000 0 BMJ 0 0 0 John A. Grillo 0 07/14/22 02/15/19
21-1173 Reconstruction 0-005-019 05/10/22 DONE DONE DONE 01/19/22 01/19/22 06/28/21 05/18/21 2,8,9 783,780 766,430 JLB 0 0 0 John A. Grillo 0 / / 01/19/22
West End Elementary:
18-1362 Reconstruction 0-006-025 04/01/19 DONE DONE DONE 01/30/19 01/15/19 / / 05/15/18 2,8,9,10,155,15,16 100,000 100,000 BMJ 0 0 0 John A. Grillo 0 01/02/20 01/15/19
22-0989 Reconstruction 0-006-026 04/19/23 DONE DONE DONE 11/16/22 11/16/22 08/09/22 05/17/22 2,4,7 144,000 144,000 JJH 0 0 0 John A. Grillo 0 / / 11/16/22
23-0666 Reconstruction 0-006-027 UNREVIEWED
STARTED UNREVIEWED10/10/23 10/06/23 06/22/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 10/06/23
North Lynbrook Middle:
19-0830 Reconstruction 0-007-021 03/02/20 DONE DONE DONE 12/20/19 10/21/19 06/17/19 05/21/19 2,4,8,9,10,155,15,16 75,000 75,000 BMJ 0 0 0 John A. Grillo 0 07/14/22 10/21/19
22-0990 Reconstruction 0-007-022 04/19/23 DONE DONE DONE 11/16/22 11/16/22 06/28/21 05/17/22 2,9 2,800,000 2,800,000 JJH 0 0 0 John A. Grillo 0 / / 11/16/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
FLORAL PARK-BELLEROSE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-22-02
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
John Lewis Childs Elementary:
18-1935 Additions and Alterations 0-001-045 12/12/19 DONE DONE DONE 05/10/19 05/06/19 11/24/17 10/23/18 02 - 16 9,304,837 3,678,414 SLC 0 0 0 Campbell Cassetta Architects 0 / / 05/06/19
18-0922XX Reconstruction 0-001-046 07/02/19 CANCELLED 11/26/18 07/16/18 03/15/18 08/29/18 2,155,16 214,000 214,000 SLC 0 0 0 Campbell Cassetta Architects 0 / / 07/16/18
18-1701 Reconstruction 0-001-048 07/08/19 DONE DONE DONE 03/22/19 03/15/19 01/31/19 05/15/18 7,155,16 160,000 160,000 SLC 0 0 0 Campbell Cassetta Architects 0 06/30/22 03/15/19
19-1009 Reconstruction 0-001-049 04/24/20 DONE DONE DONE 12/16/19 12/04/19 10/30/19 05/21/19 2,4,8,9,10,15,16 515,000 515,000 SLC 0 0 0 Campbell Cassetta Architects 0 11/08/22 12/04/19
20-1376 Reconstruction 0-001-050 12/17/21 DONE DONE DONE 03/05/21 03/04/21 09/01/20 06/09/20 9,10,155,15,16 355,000 355,000 SLC 0 0 0 Campbell Cassetta Architects 0 08/27/23 03/04/21
20-1337 Reconstruction 0-001-051 07/29/21 DONE DONE DONE 02/22/21 02/16/21 01/19/21 12/07/20 2,15,16 1,477,211 1,477,211 SLC 0 0 0 ECG Engineering, LLC 1,277,211 07/15/22 02/16/21
21-0920 Reconstruction 0-001-052 06/21/22 DONE DONE DONE 12/17/21 12/17/21 11/23/21 05/18/21 9,15 35,000 35,000 SLC 0 0 0 Campbell Cassetta Architects 0 10/18/23 12/17/21
22-1645 Reconstruction 0-001-053 05/31/23 DONE DONE DONE 02/08/23 02/08/23 08/10/22 05/17/22 2,9 508,000 508,000 JLB 0 0 0 Campbell Cassetta Architects 0 12/07/23 02/08/23
Floral Pk-Bellerose School:
18-1936 Additions and Alterations 0-002-044 12/12/19 DONE DONE DONE 05/10/19 05/06/19 11/24/17 10/23/18 02 - 16 8,450,863 2,529,761 SLC 0 0 0 Campbell Cassetta Architects 0 / / 05/06/19
19-1010 Reconstruction 0-002-046 04/24/20 DONE DONE DONE 12/16/19 12/04/19 10/30/19 05/21/19 4,7,8,9,10,155,15,16 425,000 425,000 SLC 0 0 0 Campbell Cassetta Architects 0 10/20/21 12/04/19
20-1377 Reconstruction 0-002-047 05/26/21 DONE DONE DONE 03/05/21 03/04/21 09/01/20 06/09/20 9,10,155,15,16 575,000 575,000 SLC 0 0 0 Campbell Cassetta Architects 0 08/10/22 03/04/21
20-1338 Reconstruction 0-002-048 07/29/21 DONE DONE DONE 02/22/21 02/16/21 01/19/21 12/07/20 2,15,16 1,040,045 1,040,045 SLC 0 0 0 ECG Engineering, LLC 1,040,045 07/15/22 02/16/21
21-0921 Reconstruction 0-002-049 06/21/22 DONE DONE DONE 12/17/21 12/17/21 11/23/21 05/18/21 2,4,8,9,155,15 605,000 605,000 SLC 0 0 0 Campbell Cassetta Architects 0 10/31/23 12/17/21
21-1335 Reconstruction 0-002-050 06/21/22 DONE DONE DONE 02/18/22 02/15/22 01/07/22 05/18/21 4,8,9,10,15,16 400,000 400,000 SLC 0 0 0 Campbell Cassetta Architects 0 / / 02/15/22
22-1766 Reconstruction 0-002-051 DONE ADD. REQ'D DONE 03/01/23 02/28/23 03/02/22 04/11/22 2,9 220,590 251,734 MSK 0 0 0 Campbell Cassetta Architects 0 / / 02/28/23
22-1646 Reconstruction 0-002-052 05/31/23 DONE DONE DONE 02/08/23 02/08/23 08/10/22 05/17/22 2,9 863,000 863,000 JLB 0 0 0 Campbell Cassetta Architects 0 12/07/23 02/08/23
- Reconstruction 0-002-053 / / / / 06/16/23 / / 15,16 0 0 MSK 0 0 0 0 / / / /
Administration:
20-1339 Reconstruction 1-003-004 07/29/21 DONE DONE DONE 02/22/21 02/16/21 01/19/21 12/07/20 2,16 38,178 0 SLC 0 0 0 ECG Engineering, LLC 38,178 / / 02/16/21
Storage Container #1 CC7534:
21-0781DB Discovered Building 2-010-001 12/10/21 DONE DONE DONE 11/30/21 11/23/21 11/08/21 / / 0 0 SLC 0 0 0 0 / / 11/23/21
Storage Container #2 CC40816:
21-0782DB Discovered Building 2-011-001 12/10/21 DONE DONE DONE 11/30/21 11/23/21 11/08/21 / / 0 0 SLC 0 0 0 0 / / 11/23/21
Storage Container #3 CC40724:
21-0783DB Discovered Building 2-012-001 12/10/21 DONE DONE DONE 11/30/21 11/23/21 11/08/21 / / 0 0 SLC 0 0 0 0 / / 11/23/21
Storage Container #4 CC40897:
21-0784DB Discovered Building 2-013-001 12/10/21 DONE DONE DONE 11/30/21 11/23/21 11/08/21 / / 0 0 SLC 0 0 0 0 / / 11/23/21
Storage Container #1@Elizabeth St.:
21-0785DB Discovered Building 2-014-001 12/10/21 DONE DONE DONE 11/30/21 11/23/21 11/08/21 / / 0 0 SLC 0 0 0 0 / / 11/23/21
District-Wide:
- XX Reconstruction 7-999-003 CANCELLED / / / / 08/15/19 / / 4,8,9,10,155,15,16 0 0 SLC 0 0 0 0 / / / /
19-0262XX Reconstruction 7-999-003 CANCELLED / / / / / / / / 4,8,9,10,155,15,16 0 0 SLC 0 0 0 0 / / / /
Tent #1 @ JL Childs ES:
20-0465TQ Temporary Quarters 8-008-001 12/16/20 DONE DONE DONE 09/28/20 09/28/20 09/02/20 / / 8,590 0 SLC 0 0 0 0 / / 09/28/20
Tent #2 @ FP-Bellerose ES:
20-0466TQ Temporary Quarters 8-009-001 12/16/20 DONE DONE DONE 09/28/20 09/28/20 09/02/20 / / 8,590 0 SLC 0 0 0 0 11/18/20 09/28/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WANTAGH UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-23-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Wantagh Senior High:
18-1618 Reconstruction 0-001-037 04/17/19 DONE DONE DONE 03/11/19 03/01/19 01/25/19 05/21/19 2,9 472,000 472,000 BMJ 0 0 0 John A. Grillo 0 10/03/19 03/01/19
20-0979 Reconstruction 0-001-038 03/04/21 DONE DONE DONE 12/16/20 11/23/20 09/02/20 05/15/18 2,4,7,155,16 289,100 289,100 JSS 0 0 0 John A. Grillo 0 11/17/22 11/23/20
22-0386 Reconstruction 0-001-039 01/04/23 DONE DONE DONE 08/31/22 08/31/22 07/18/22 05/17/22 8,9,16 600,000 600,000 JLB 0 0 0 Mark Design Studios 0 09/13/23 08/31/22
- Reconstruction 0-001-040 / / / / 10/13/22 / / 9,15,16 0 0 JLB 0 0 0 0 / / / /
22-2252 Reconstruction 0-001-041 09/05/23 DONE DONE DONE 05/22/23 05/18/23 01/12/23 12/06/22 2,8,9,10,15,16 761,440 761,440 JJH 0 0 0 Mark Design Studios 0 / / 05/18/23
23-0126 Reconstruction 0-001-042 02/26/24 DONE DONE DONE 07/24/23 07/24/23 02/21/23 12/06/22 7,9,155,16 4,997,622 4,997,622 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
22-2393 Reconstruction 0-001-043 10/17/23 DONE DONE DONE 06/16/23 06/15/23 02/21/23 05/16/23 4,8,16 727,725 727,725 JJH 0 0 0 Mark Design Studios 0 / / 06/15/23
22-2421 Reconstruction 0-001-044 10/12/23 DONE DONE DONE 06/20/23 06/20/23 02/21/23 05/16/23 2,7 830,842 830,842 JJH 0 0 0 Mark Design Studios 0 / / 06/20/23
23-0606 Reconstruction 0-001-045 UNREVIEWED
STARTED DONE 10/04/23 09/25/23 02/21/23 12/06/22 2,4,8,9,10,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 09/25/23
23-0127 Reconstruction 0-001-046 02/26/24 DONE DONE DONE 07/24/23 07/24/23 03/07/23 12/06/22 2,9,16 848,640 848,640 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
23-0754 Reconstruction 0-001-047 UNREVIEWED 10/20/23 10/11/23 07/25/23 12/06/22 2,8,9,10,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 10/11/23
23-0806 Reconstruction 0-001-048 UNREVIEWED 10/25/23 10/18/23 07/25/23 12/06/22 2,8,9,10,15,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 10/18/23
Mandalay Elementary School:
21-1564 Reconstruction 0-004-015 08/31/22 DONE DONE DONE 03/25/22 03/25/22 02/14/22 02/10/22 2,4,8 353,000 353,000 JLB 0 0 0 Mark Design Studios 0 06/30/23 03/25/22
22-2253 Reconstruction 0-004-016 09/05/23 DONE DONE DONE 05/22/23 05/18/23 01/12/23 12/06/22 2,9,10,15,16 528,800 528,800 JJH 0 0 0 Mark Design Studios 0 / / 05/18/23
23-0128 Reconstruction 0-004-017 02/26/24 DONE DONE DONE 07/24/23 07/24/23 02/21/23 12/06/22 7,9,155,16 0 10,792,896 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
22-2394 Reconstruction 0-004-018 10/17/23 DONE DONE DONE 06/16/23 06/15/23 02/21/23 05/16/23 4,8,16 230,000 230,000 JJH 0 0 0 Mark Design Studios 0 / / 06/15/23
23-0609 Reconstruction 0-004-019 UNREVIEWED
STARTED DONE 10/04/23 09/25/23 02/21/23 12/06/22 2,4,8,9,10,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 09/25/23
23-0129 Reconstruction 0-004-020 02/26/24 DONE DONE DONE 07/24/23 07/24/23 03/07/23 12/06/22 2,9,16 0 10,792,896 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
23-0807 Reconstruction 0-004-021 UNREVIEWED 10/25/23 10/18/23 07/25/23 12/06/22 2,8,9,10,15,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 10/18/23
23-0917 Reconstruction 0-004-022 UNREVIEWED 11/08/23 11/06/23 10/24/23 12/06/22 2,8,9,10,15,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 11/06/23
Forest Lake Elementary School:
19-0562 Reconstruction 0-005-018 10/31/19 DONE DONE DONE 10/16/19 10/08/19 10/02/19 09/19/19 2 250,000 0 JSS 0 0 0 John A. Grillo 0 / / 10/08/19
22-1920 Reconstruction 0-005-019 07/05/23 DONE DONE DONE 03/21/23 03/21/23 01/10/23 09/15/22 2,16 291,600 291,600 JJH 0 0 0 Mark Design Studios 0 / / 03/21/23
22-2254 Reconstruction 0-005-020 09/05/23 DONE DONE DONE 05/22/23 05/18/23 01/12/23 12/06/22 2,9,10,15,16 528,800 528,800 JJH 0 0 0 Mark Design Studios 0 / / 05/18/23
23-0130 Reconstruction 0-005-021 02/26/24 DONE DONE DONE 07/24/23 07/24/23 02/21/23 12/06/22 7,9,155,16 2,606,912 2,606,912 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
22-2395 Reconstruction 0-005-022 10/17/23 DONE DONE DONE 06/16/23 06/15/23 02/21/23 05/16/23 4,8,16 240,000 240,000 JJH 0 0 0 Mark Design Studios 0 / / 06/15/23
23-0610 Reconstruction 0-005-023 UNREVIEWED
STARTED DONE 10/04/23 09/25/23 02/21/23 12/06/22 2,4,8,9,10,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 09/25/23
23-0131 Reconstruction 0-005-024 02/26/24 DONE DONE DONE 07/24/23 07/24/23 03/07/23 12/06/22 2,9,16 0 12,657,123 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
23-0808 Reconstruction 0-005-025 UNREVIEWED 10/25/23 10/18/23 07/25/23 12/06/22 2,8,9,10,15,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 10/18/23
23-0918 Reconstruction 0-005-026 UNREVIEWED 11/08/23 11/06/23 10/24/23 12/06/22 2,8,9,10,15,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 11/06/23
Middle School:
- Reconstruction 0-006-026 / / / / 10/13/22 / / 9,15,16 0 0 JLB 0 0 0 0 / / / /
22-2255 Reconstruction 0-006-027 09/05/23 DONE DONE DONE 05/22/23 05/18/23 01/12/23 12/06/22 2,8,9,10,15,16 561,440 561,440 JJH 0 0 0 Mark Design Studios 0 / / 05/18/23
23-0132 Reconstruction 0-006-028 02/26/24 DONE DONE DONE 07/24/23 07/24/23 02/21/23 12/06/22 7,9,155,16 3,456,023 3,456,023 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
22-2396 Reconstruction 0-006-029 10/17/23 DONE DONE DONE 06/16/23 06/15/23 02/21/23 05/16/23 4,8,16 587,275 587,275 JJH 0 0 0 Mark Design Studios 0 / / 06/15/23
23-0607 Reconstruction 0-006-030 UNREVIEWED
STARTED DONE 10/04/23 09/25/23 02/21/23 12/06/22 2,4,8,9,10,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 09/25/23
23-0133 Reconstruction 0-006-031 02/26/24 DONE DONE DONE 07/24/23 07/24/23 03/07/23 12/06/22 2,9,16 456,960 456,960 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
Wantagh Elementary:
22-2256 Reconstruction 0-008-021 09/05/23 DONE DONE DONE 05/22/23 05/18/23 01/12/23 12/06/22 8,9,10,15,16 384,000 384,000 JJH 0 0 0 Mark Design Studios 0 / / 05/18/23
23-0134 Reconstruction 0-008-022 02/26/24 DONE DONE DONE 07/24/23 07/24/23 02/21/23 12/06/22 7,9,155,16 0 20,761,141 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
22-2422 Reconstruction 0-008-023 10/12/23 DONE DONE DONE 06/20/23 06/20/23 02/21/23 05/16/23 2,7 473,390 473,390 JJH 0 0 0 Mark Design Studios 0 / / 06/20/23
23-0608 Reconstruction 0-008-024 UNREVIEWED
STARTED DONE 10/04/23 09/25/23 02/21/23 12/06/22 2,8,9,10 0 0 JJH 0 0 0 Mark Design Studios 0 / / 09/25/23
22-2397 Reconstruction 0-008-025 10/17/23 DONE DONE DONE 06/16/23 06/15/23 02/21/23 05/16/23 4,8,16 245,000 245,000 JJH 0 0 0 Mark Design Studios 0 / / 06/15/23
23-0135 Reconstruction 0-008-026 02/26/24 DONE DONE DONE 07/24/23 07/24/23 03/07/23 12/06/22 2,9,16 860,420 860,420 JJH 0 0 0 Mark Design Studios 0 / / 07/24/23
23-0809 Reconstruction 0-008-027 UNREVIEWED 10/25/23 10/18/23 07/25/23 12/06/22 2,8,9,10,15,16 0 0 JJH 0 0 0 Mark Design Studios 0 / / 10/18/23
Wantagh Public Library:
- Reconstruction 6-010-010 / / / / 08/23/19 / / 8,10,16 0 0 JSS 0 0 0 0 / / / /
20-0248 Reconstruction 6-010-011 04/13/21 DONE DONE DONE 08/21/20 08/17/20 07/08/20 06/30/20 155,16 1,150,000 0 JSS 0 0 0 John Tanzi Architects 0 / / 08/17/20
21-2007 Reconstruction 6-010-012 07/11/22 DONE DONE DONE 06/21/22 06/21/22 02/14/22 03/21/22 16 195,000 0 SLC 0 0 0 John Tanzi Architects 0 / / 06/21/22
- Reconstruction 6-010-013 / / / / 03/05/24 / / 2,15,16 0 0 JJH 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ISLAND TREES UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-26-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Stokes Elementary:
18-1593 Reconstruction 0-001-026 04/29/19 DONE DONE DONE 03/05/19 02/28/19 08/09/18 03/15/16 2,4 439,800 439,800 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
18-1589 Reconstruction 0-001-027 05/14/19 DONE DONE DONE 03/05/19 02/28/19 08/30/18 03/15/16 8,9,14,16 1,268,500 1,268,500 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
19-1473 Reconstruction 0-001-028 04/17/20 DONE DONE DONE 02/24/20 02/18/20 12/20/19 03/15/16 9,15,16 805,800 0 JSS 0 0 0 Michael J. Guido Jr. 0 / / 02/18/20
21-0109 Reconstruction 0-001-029 08/19/21 DONE DONE DONE 07/28/21 07/28/21 06/14/21 03/15/16 2,8 800,000 0 JLB 0 0 0 Michael J. Guido Jr. 0 / / 07/28/21
23-1003 Reconstruction 0-001-030 UNREVIEWED 11/14/23 11/14/23 12/22/22 03/15/16 8 0 0 WLC 0 0 0 Michael J. Guido Jr. 0 / / 11/14/23
Sparke Elementary:
18-1594 Reconstruction 0-002-020 04/29/19 DONE DONE DONE 03/05/19 02/28/19 08/09/18 03/15/16 2,4,10 40,320 40,320 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
18-1590 Reconstruction 0-002-021 05/14/19 DONE DONE DONE 03/05/19 02/28/19 08/30/18 03/15/16 8,155,16 235,000 235,000 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
19-1474 Reconstruction 0-002-022 04/17/20 DONE DONE DONE 02/24/20 02/18/20 12/20/19 03/15/16 2,9,155,15,16 992,400 0 JSS 0 0 0 Michael J. Guido Jr. 0 / / 02/18/20
22-1576 Reconstruction 0-002-023 05/15/23 DONE DONE DONE 01/30/23 01/27/23 11/09/22 05/18/21 7 960,000 960,000 WLC 0 0 0 Michael J. Guido Jr. 0 / / 01/27/23
Island Trees High School:
18-1595 Reconstruction 0-003-040 04/29/19 DONE DONE DONE 03/05/19 02/28/19 08/09/18 03/15/16 2,4,9,10 604,680 604,680 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
18-1591 Reconstruction 0-003-041 05/14/19 DONE DONE DONE 03/05/19 02/28/19 08/30/18 03/15/16 8,9,16 1,441,600 1,441,600 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
19-1475 Reconstruction 0-003-042 04/17/20 DONE DONE DONE 02/24/20 02/18/20 12/20/19 03/15/16 2,4,9,155,16 1,060,080 0 JSS 0 0 0 Michael J. Guido Jr. 0 / / 02/18/20
21-1134 Reconstruction 0-003-043 04/27/22 DONE DONE DONE 01/18/22 01/13/22 12/15/21 05/18/21 2,7 2,256,000 2,256,000 JLB 0 0 0 Michael J. Guido Jr. 0 / / 01/13/22
- PR Additions and Alterations 0-003-044 / / / / 11/09/22 / / 02 - 16 0 30,806,190 WLC 0 0 0 0 / / / /
22-1659 Additions and Alterations 0-003-044 DONE ADD. REQ'D DONE 02/13/23 02/10/23 11/09/22 05/18/21 02 - 16 5,583,600 395,600 WLC 0 0 0 Michael J. Guido Jr. 0 / / 02/10/23
23-1512 Reconstruction 0-003-045 UNREVIEWED 02/16/24 02/16/24 12/07/23 05/18/21 7 0 0 WLC 0 0 0 Michael J. Guido Jr. 0 / / 02/16/24
Island Trees Memorial Middle School:
18-1596 Reconstruction 0-004-037 04/29/19 DONE DONE DONE 03/05/19 02/28/19 08/09/18 03/15/16 2,4,10 459,000 459,000 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
18-1592 Reconstruction 0-004-038 05/14/19 DONE DONE DONE 03/05/19 02/28/19 08/29/18 03/15/16 8,9,155,16 1,311,447 1,311,447 BMJ 0 0 0 Michael J. Guido Jr. 0 05/12/22 02/28/19
19-1476 Reconstruction 0-004-039 04/17/20 DONE DONE DONE 02/24/20 02/18/20 12/20/19 03/15/16 2,9,155,16 1,302,552 0 JSS 0 0 0 Michael J. Guido Jr. 0 / / 02/18/20
22-1577 Reconstruction 0-004-040 05/15/23 DONE DONE DONE 01/30/23 01/27/23 11/09/22 05/18/21 2,7,155,16 3,628,800 3,628,800 WLC 0 0 0 Michael J. Guido Jr. 0 / / 01/27/23
23-1513 Reconstruction 0-004-041 UNREVIEWED 02/16/24 02/16/24 12/07/23 05/18/21 7 0 0 WLC 0 0 0 Michael J. Guido Jr. 0 / / 02/16/24
Gallow Elementary:
19-1477 Reconstruction 0-005-013 04/17/20 DONE DONE DONE 02/24/20 02/18/20 12/20/19 03/15/16 2,4,15,16 681,240 0 JSS 0 0 0 Michael J. Guido Jr. 0 / / 02/18/20
23-1514 Reconstruction 0-005-014 UNREVIEWED 02/16/24 02/16/24 12/07/23 05/18/21 7 0 0 WLC 0 0 0 Michael J. Guido Jr. 0 / / 02/16/24
Karopczyc Library/frm Karopczyc Elem:
17-0722 Reconstruction 7-008-007 04/08/19 DONE DONE DONE 11/07/17 10/30/17 10/01/16 01/20/16 2,4,8,9,10,155,15,16 10,935,664 0 BMJ 0 0 0 Michael J. Guido Jr. 0 / / 10/30/17
23-1515 Reconstruction 7-008-008 UNREVIEWED 02/16/24 02/16/24 12/07/23 05/18/21 7 0 0 WLC 0 0 0 Michael J. Guido Jr. 0 / / 02/16/24
Press Box @ ITHS:
18-1306 New Construction 7-016-001 04/02/19 DONE DONE DONE 01/22/19 01/10/19 03/01/18 / / 02 - 16 100,000 0 BMJ 0 0 0 Michael J. Guido Jr. 0 / / 01/10/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
VALLEY STREAM 30 UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-30-02
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Forest Road ES:
18-2037 Reconstruction 0-002-016 07/23/19 DONE DONE DONE 06/03/19 05/28/19 04/12/19 04/29/19 2,155,15,16 1,885,414 1,885,414 SLC 0 0 0 ECG Engineering, LLC 1,885,414 02/15/21 05/28/19
20-0189 Reconstruction 0-002-017 04/21/21 DONE DONE DONE 08/12/20 08/07/20 11/27/19 06/09/20 2,4,7,8,9,10,13,155, 2,182,282 936,896 SLC 0 0 0 John A. Grillo 0 08/23/22 08/07/20
20-1488 Reconstruction 0-002-018 04/25/21 DONE DONE DONE 03/26/21 03/11/21 07/14/20 06/16/20 2,8,9,10,155,15,16 292,236 292,236 SLC 0 0 0 John A. Grillo 0 09/08/22 03/11/21
22-0111 Reconstruction 0-002-019 11/20/22 DONE DONE DONE 07/20/22 07/19/22 02/14/22 05/17/22 2,4,7,9,155,15,16 2,552,340 2,552,340 SLC 0 0 0 John A. Grillo 0 / / 07/19/22
- Reconstruction 0-002-020 / / / / 12/19/23 / / 2,4,8,155,16 0 0 MSK 0 0 0 0 / / / /
Shaw Avenue Elementary:
17-0350 Additions and Alterations 0-003-015 04/17/19 DONE DONE DONE 09/06/17 09/05/17 08/11/17 05/16/17 02 - 16 2,520,000 1,915,096 SLC 0 0 0 John A. Grillo 0 04/30/20 09/05/17
18-2038 Reconstruction 0-003-016 07/23/19 DONE DONE DONE 06/03/19 05/28/19 04/12/19 04/29/19 2,155,15,16 2,190,243 2,190,243 SLC 0 0 0 ECG Engineering, LLC 2,190,243 02/15/21 05/28/19
20-1489 Reconstruction 0-003-017 04/25/21 DONE DONE DONE 03/26/21 03/11/21 07/14/20 06/16/20 2,8,9,10,155,15,16 801,486 801,486 SLC 0 0 0 John A. Grillo 0 09/08/22 03/11/21
22-0112 Reconstruction 0-003-018 11/20/22 DONE DONE DONE 07/20/22 07/19/22 02/14/22 05/17/22 2,4,7,9,155,15,16 4,112,300 4,112,300 SLC 0 0 0 John A. Grillo 0 / / 07/19/22
- PR Additions and Alterations 0-003-019 / / / / 12/19/23 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
Clearstream Avenue School:
18-2039 Reconstruction 0-005-016 07/23/19 DONE DONE DONE 06/03/19 05/28/19 04/12/19 04/29/19 2,155,15,16 1,131,970 1,131,970 SLC 0 0 0 ECG Engineering, LLC 1,131,970 02/15/21 05/28/19
20-1490 Reconstruction 0-005-017 04/25/21 DONE DONE DONE 03/26/21 03/11/21 07/14/20 06/16/20 2,8,9,10,155,15,16 223,986 223,986 SLC 0 0 0 John A. Grillo 0 09/08/22 03/11/21
22-0113 Reconstruction 0-005-018 11/20/22 DONE DONE DONE 07/20/22 07/19/22 02/14/22 05/17/22 2,4,9,155,15,16 2,533,460 2,533,460 SLC 0 0 0 John A. Grillo 0 / / 07/19/22
- Reconstruction 0-005-019 / / / / 12/19/23 / / 2,4,8,9,10,155,16 0 0 MSK 0 0 0 0 / / / /
Washington Ave Sch-Admin(NoAidBldg):
18-2040 Reconstruction 0-007-004 07/23/19 DONE DONE DONE 06/03/19 05/28/19 04/12/19 04/29/19 155,16 99,520 0 SLC 0 0 0 ECG Engineering, LLC 99,520 02/15/21 05/28/19
- Reconstruction 0-007-005 / / / / 02/14/22 / / 7,9,10,13,14 0 0 SLC 0 0 0 0 / / / /
District-Wide:
- Reconstruction 7-999-001 / / / / 12/06/22 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ISLAND PARK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-31-02
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Francis X Hegarty Elementary School:
19-1361 Reconstruction 0-001-020 03/17/20 DONE DONE DONE 02/04/20 01/29/20 01/22/20 01/27/17 2,4,8,9,10,15 225,000 225,000 JSS 0 0 0 Burton Behrendt Smith 0 04/30/21 01/29/20
22-0131 Reconstruction 0-001-021 10/18/22 DONE DONE DONE 07/22/22 07/20/22 03/22/22 03/21/22 16 457,881 457,881 JLB 0 0 0 ECG Engineering, LLC 457,881 10/11/23 07/20/22
- Reconstruction 0-001-022 / / / / 10/25/23 / / 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Lincoln Orens Middle School:
19-0602 Reconstruction 0-002-018 03/16/20 DONE DONE DONE 10/22/19 10/08/19 09/17/19 01/27/17 2,8,9,10,155,15,16 676,000 676,000 JSS 0 0 0 Burton Behrendt Smith 0 09/02/20 10/08/19
19-1022 Reconstruction 0-002-019 05/27/20 DONE DONE DONE 12/18/19 12/03/19 11/20/19 01/27/17 2,4,8,9,10,155,15,16 553,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 12/03/19
19-1233 Reconstruction 0-002-020 03/17/20 DONE DONE DONE 01/16/20 01/13/20 11/27/19 01/27/17 2,4,8,9,10,155,15,16 143,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 01/13/20
19-1234 Reconstruction 0-002-021 03/17/20 DONE DONE DONE 01/16/20 01/13/20 12/11/19 01/27/17 2,4,8,9,10,155,15,16 671,000 671,000 JSS 0 0 0 Burton Behrendt Smith 0 05/10/21 01/13/20
22-0132 Reconstruction 0-002-022 10/18/22 DONE DONE DONE 07/22/22 07/20/22 03/22/22 03/21/22 16 2,443,769 2,443,769 JLB 0 0 0 ECG Engineering, LLC 2,443,769 10/11/23 07/20/22
- Reconstruction 0-002-023 / / / / 03/22/22 / / 4,7,8,9,10,155,15,16 0 20,971,570 JJH 0 0 0 0 / / / /
- Reconstruction 0-002-024 / / / / 10/25/23 / / 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Conference Center (frmly library):
- Reconstruction 6-002-007 / / / / 01/24/20 / / 2,7,155,15,16 0 0 JSS 0 0 0 0 / / / /
22-0133 Reconstruction 6-002-008 10/18/22 DONE DONE DONE 07/22/22 07/20/22 03/22/22 03/21/22 4,7,8,9,10,155,15,16 55,189 0 JLB 0 0 0 ECG Engineering, LLC 55,189 10/11/23 07/20/22
23-0140 Reconstruction 6-002-009 11/09/23 DONE DONE DONE 07/26/23 07/26/23 03/28/23 10/01/21 7,155,15,16 0 0 JLB 0 0 0 EMTEC Consultants, P.C. 0 / / 07/26/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
VALLEY STREAM CHSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-51-07
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central High School:
86-0423 Reconstruction 0-001-001 10/02/86 DONE DONE DONE / / / / 12/11/20 / / 2,155,15,16 21,450 21,450 SLC 0 0 0 0 05/09/88 / /
18-1098 Reconstruction 0-001-042 04/11/19 DONE DONE DONE 12/18/18 12/05/18 06/19/18 12/06/16 2,9,10 2,015,667 2,015,667 SLC 0 0 0 Burton Behrendt Smith 0 10/08/19 12/05/18
18-1079 Reconstruction 0-001-044 04/11/19 DONE DONE DONE 12/14/18 12/11/18 07/09/18 05/15/18 2,4,8,9,155,15,16 2,000,000 2,000,000 SLC 0 0 0 Burton Behrendt Smith 0 01/30/20 12/11/18
18-2078XX Reconstruction 0-001-045 CANCELLED 06/10/19 06/04/19 02/11/19 02/12/19 9,10,155,15,16 0 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 06/04/19
19-0653 Reconstruction 0-001-046 03/27/20 DONE DONE DONE 11/01/19 10/22/19 06/13/19 05/21/19 8,9,155,16 250,000 250,000 SLC 0 0 0 Burton Behrendt Smith 0 10/22/21 10/22/19
19-1161 Reconstruction 0-001-047 03/30/20 DONE DONE DONE 01/07/20 12/04/19 06/13/19 05/21/19 155,16 280,000 280,000 SLC 0 0 0 Burton Behrendt Smith 0 03/02/21 12/04/19
20-1354 Reconstruction 0-001-048 03/01/21 DONE DONE DONE 02/26/21 02/26/21 12/11/20 01/12/21 2,155,15,16 1,825,000 1,825,000 SLC 0 0 0 Burton Behrendt Smith 0 12/07/21 02/26/21
22-1160 Reconstruction 0-001-049 04/03/23 DONE DONE DONE 12/05/22 12/05/22 08/09/22 05/17/22 2,16 890,000 890,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/05/22
- Reconstruction 0-001-050 / / / / 10/31/22 / / 2,9,15,16 0 0 SLC 0 0 0 0 / / / /
23-1628 Reconstruction 0-001-051 UNREVIEWED 03/14/24 03/13/24 05/23/23 05/16/23 10 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 03/13/24
23-1119 Reconstruction 0-001-052 UNREVIEWED 12/05/23 11/27/23 05/23/23 05/16/23 2,8,9,10,155,15,16 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 11/27/23
Memorial Junior High School:
19-1159 Reconstruction 0-002-039 04/27/20 DONE DONE DONE 01/07/20 12/18/19 01/17/18 12/06/16 2,4,8,9,155,15,16 1,955,000 1,955,000 SLC 0 0 0 Burton Behrendt Smith 0 09/07/21 12/18/19
18-1100 Reconstruction 0-002-040 07/15/19 DONE DONE DONE 12/18/18 12/05/18 06/19/18 05/15/18 14 384,000 384,000 SLC 0 0 0 Burton Behrendt Smith 0 08/27/21 12/05/18
18-2079XX Reconstruction 0-002-042 CANCELLED 06/10/19 06/04/19 02/11/19 02/12/19 9,10,155,15,16 0 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 06/04/19
19-0654 Reconstruction 0-002-043 03/27/20 DONE DONE DONE 11/01/19 10/22/19 06/13/19 05/21/19 8,9,155,16 250,000 250,000 SLC 0 0 0 Burton Behrendt Smith 0 10/22/21 10/22/19
19-1162 Reconstruction 0-002-044 03/30/20 DONE DONE DONE 01/07/20 12/04/19 06/13/19 05/21/19 155,16 230,000 230,000 SLC 0 0 0 Burton Behrendt Smith 0 03/02/21 12/04/19
20-0940 Reconstruction 0-002-045 04/14/21 DONE DONE DONE 12/08/20 11/04/20 07/01/20 06/09/20 2,4,7,8,9,155,15,16 1,500,000 1,500,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 11/04/20
20-1355 Reconstruction 0-002-046 03/01/21 DONE DONE DONE 02/26/21 02/26/21 12/15/20 01/12/21 2,155,15,16 1,825,000 1,825,000 SLC 0 0 0 Burton Behrendt Smith 0 12/07/21 02/26/21
21-1676 Reconstruction 0-002-047 08/17/22 DONE DONE DONE 04/20/22 04/15/22 11/09/21 12/06/16 2,155,15 850,000 850,000 SLC 0 0 0 Burton Behrendt Smith 0 09/06/23 04/15/22
22-1161 Reconstruction 0-002-048 04/03/23 DONE DONE DONE 12/05/22 12/05/22 08/09/22 05/17/22 2,16 890,000 890,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/05/22
- Reconstruction 0-002-049 / / / / 10/31/22 / / 2,9,15,16 0 0 SLC 0 0 0 0 / / / /
23-1629 Reconstruction 0-002-050 UNREVIEWED 03/14/24 03/13/24 05/23/23 05/16/23 10 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 03/13/24
23-1120 Reconstruction 0-002-051 UNREVIEWED 12/05/23 11/27/23 05/23/23 05/16/23 2,8,9,10,155,15,16 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 11/27/23
North High School:
18-1101 Reconstruction 0-003-038 07/15/19 DONE DONE DONE 12/18/18 12/05/18 06/19/18 05/15/18 14 382,000 382,000 SLC 0 0 0 Burton Behrendt Smith 0 10/29/20 12/05/18
18-2216 Reconstruction 0-003-039 11/14/19 DONE DONE DONE 06/28/19 06/11/19 06/19/18 05/15/18 2,4,9,15,16 751,000 751,000 SLC 0 0 0 Burton Behrendt Smith 0 09/09/20 06/11/19
18-2080XX Reconstruction 0-003-041 CANCELLED 06/10/19 06/04/19 02/11/19 02/12/19 2,9,10,155,15,16 0 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 06/04/19
19-0655 Reconstruction 0-003-042 03/27/20 DONE DONE DONE 11/01/19 10/22/19 06/13/19 05/21/19 8,9,155,16 250,000 250,000 SLC 0 0 0 Burton Behrendt Smith 0 10/22/21 10/22/19
19-1163 Reconstruction 0-003-043 03/30/20 DONE DONE DONE 01/07/20 12/04/19 06/13/19 05/21/19 155,16 240,000 240,000 SLC 0 0 0 Burton Behrendt Smith 0 03/02/21 12/04/19
19-1160 Reconstruction 0-003-044 04/27/20 DONE DONE DONE 01/07/20 12/18/19 11/21/19 12/06/16 2,4,8,9,155,15,16 1,775,000 1,775,000 SLC 0 0 0 Burton Behrendt Smith 0 09/07/21 12/18/19
20-0941 Reconstruction 0-003-045 04/14/21 DONE DONE DONE 12/08/20 11/04/20 07/01/20 06/09/20 9,10,16 730,000 730,000 SLC 0 0 0 Burton Behrendt Smith 0 09/10/21 11/04/20
21-1171 Reconstruction 0-003-046 04/12/22 DONE DONE DONE 01/19/22 01/18/22 06/11/21 05/18/21 2,155,15,16 1,625,000 1,625,000 SLC 0 0 0 Burton Behrendt Smith 0 03/20/23 01/18/22
21-1677 Reconstruction 0-003-047 08/17/22 DONE DONE DONE 04/20/22 04/15/22 11/09/21 12/06/16 2,155,15 910,000 910,000 SLC 0 0 0 Burton Behrendt Smith 0 09/06/23 04/15/22
22-1162 Reconstruction 0-003-048 04/03/23 DONE DONE DONE 12/05/22 12/05/22 08/09/22 05/17/22 2,16 3,661,077 3,661,077 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/05/22
22-1755 Reconstruction 0-003-049 06/29/23 DONE DONE DONE 02/27/23 02/23/23 / / 05/17/22 2,9,15,16 320,000 320,000 MSK 0 0 0 Burton Behrendt Smith 0 / / 02/23/23
23-1630 Reconstruction 0-003-050 UNREVIEWED 03/14/24 03/13/24 05/23/23 05/16/23 10 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 03/13/24
23-1450 Reconstruction 0-003-051 UNREVIEWED 01/31/24 01/30/24 05/23/23 05/16/23 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 01/30/24
South Jr/Sr High School:
18-1099 Reconstruction 0-004-035 04/11/19 DONE DONE DONE 12/18/18 12/18/18 01/17/18 12/06/16 2,4,8,9,155,15,16 1,044,167 1,044,167 SLC 0 0 0 Burton Behrendt Smith 0 10/18/19 12/18/18
18-1102 Reconstruction 0-004-036 07/15/19 DONE DONE DONE 12/18/18 12/05/18 06/19/18 05/15/18 14 332,000 332,000 SLC 0 0 0 Burton Behrendt Smith 0 10/29/20 12/05/18
18-2217 Reconstruction 0-004-037 11/14/19 DONE DONE DONE 06/28/19 06/11/19 06/19/18 05/15/18 2,9,15,16 836,000 836,000 SLC 0 0 0 Burton Behrendt Smith 0 09/09/20 06/11/19
18-2081XX Reconstruction 0-004-039 CANCELLED 06/10/19 06/04/19 02/11/19 02/12/19 2,8,9,10,155,15,16 0 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 06/04/19
19-0656 Reconstruction 0-004-040 03/27/20 DONE DONE DONE 11/01/19 10/22/19 06/13/19 05/21/19 8,9,155,16 250,000 250,000 SLC 0 0 0 Burton Behrendt Smith 0 10/22/21 10/22/19
19-1164 Reconstruction 0-004-041 03/30/20 DONE DONE DONE 01/07/20 12/04/19 06/13/19 05/21/19 155,16 280,000 280,000 SLC 0 0 0 Burton Behrendt Smith 0 03/02/21 12/04/19
20-0942 Reconstruction 0-004-042 04/14/21 DONE DONE DONE 12/08/20 11/04/20 07/01/20 06/09/20 9,10,16 465,000 465,000 SLC 0 0 0 Burton Behrendt Smith 0 09/10/21 11/04/20
21-1172 Reconstruction 0-004-043 04/12/22 DONE DONE DONE 01/19/22 01/18/22 06/11/21 05/18/21 2,155,15,16 1,625,000 1,625,000 SLC 0 0 0 Burton Behrendt Smith 0 03/23/23 01/18/22
22-1163 Reconstruction 0-004-044 04/03/23 DONE DONE DONE 12/05/22 12/05/22 08/09/22 05/17/22 2,16 2,831,103 2,831,103 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/05/22
22-1756 Reconstruction 0-004-045 06/29/23 DONE DONE DONE 02/27/23 02/23/23 10/31/22 05/17/22 2,9,15,16 320,000 320,000 MSK 0 0 0 Burton Behrendt Smith 0 / / 02/23/23
23-1631 Reconstruction 0-004-046 UNREVIEWED 03/14/24 03/13/24 05/23/23 05/16/23 10 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 03/13/24
23-1451 Reconstruction 0-004-047 UNREVIEWED 01/31/24 01/30/24 05/23/23 05/16/23 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 Burton Behrendt Smith 0 / / 01/30/24
Auto Shop ValleyStreamCHS:
21-1568FC Reconstruction 0-005-003 06/06/22 DONE DONE DONE 03/28/22 03/22/22 10/08/21 01/11/22 8,9,10,155,15,16 1,300,000 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 03/22/22
Storage Garage @ South High School:
- New Construction 2-019-001 / / / / 05/22/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Memorial JHS Press Box:
19-0583 New Construction 7-014-001 02/14/20 DONE DONE DONE 10/21/19 10/04/19 06/13/19 05/21/19 02 - 16 285,000 0 SLC 0 0 0 Burton Behrendt Smith 0 05/26/21 10/04/19
South HS Press Box:
19-0584 New Construction 7-015-001 02/14/20 DONE DONE DONE 10/21/19 10/04/19 06/13/19 05/21/19 02 - 16 285,000 0 SLC 0 0 0 Burton Behrendt Smith 0 05/26/21 10/04/19
XXTemporary Structure-removed:
- TQ Temporary Quarters 8-016-001 DONE DONE / / / / 04/27/21 / / 0 0 SLC 0 0 0 0 / / / /
Temporary Structure:
- TQ Temporary Quarters 8-017-001 / / / / 01/26/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Graduation Tent:
22-1986TQ Temporary Quarters 8-018-001 05/30/23 DONE DONE DONE 04/03/23 04/03/23 02/24/23 / / 02 - 16 0 0 MSK 0 0 0 0 05/27/23 04/03/23
Graduation Tent 2024:
23-1621TQ Temporary Quarters 8-019-001 03/13/24 DONE DONE DONE 03/13/24 02/29/24 / / / / 0 0 MSK 0 0 0 0 / / 02/29/24
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SEWANHAKA CENTRAL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-02-52-07
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Sewanhaka High School:
20-1825 Reconstruction 0-002-048 09/08/21 DONE DONE DONE 06/03/21 05/27/21 11/13/20 06/09/20 8,9,16 112,850 112,850 JLB 0 0 0 H2M Group 0 04/03/23 05/27/21
22-0274 Reconstruction 0-002-049 11/02/22 DONE DONE DONE 08/17/22 08/12/22 01/25/22 05/17/22 2,7,8,9,10,155,15,16 1,156,025 1,156,025 JLB 0 0 0 Mark Design Studios 0 / / 08/12/22
21-1951 Reconstruction 0-002-050 07/21/22 DONE DONE DONE 06/10/22 06/09/22 03/24/22 05/17/22 9,10,16 50,844 50,844 JLB 0 0 0 Mark Design Studios 0 / / 06/09/22
22-0007 Reconstruction 0-002-051 09/12/22 DONE DONE DONE 07/01/22 06/30/22 06/13/22 05/17/22 2,4,7,8,9,10,14,155, 107,583 107,583 JLB 0 0 0 Mark Design Studios 0 / / 06/30/22
22-2458 Reconstruction 0-002-052 11/06/23 DONE DONE DONE 06/26/23 06/26/23 05/31/23 05/16/23 7,9,10 126,600 126,600 JJH 0 0 0 Mark Design Studios 0 / / 06/26/23
Floral Park Memorial High:
20-1826 Reconstruction 0-003-043 09/08/21 DONE DONE DONE 06/03/21 05/27/21 11/13/20 06/09/20 8,9,16 58,000 58,000 JLB 0 0 0 H2M Group 0 04/03/23 05/27/21
- Reconstruction 0-003-044 / / / / 10/05/22 / / 2,4,8,9,10,155,15,16 0 0 JLB 0 0 0 0 / / / /
Hyde Park Memorial High:
20-1827 Reconstruction 0-004-043 09/08/21 DONE DONE DONE 06/03/21 05/27/21 11/13/20 06/09/20 8,9,16 95,000 95,000 JLB 0 0 0 H2M Group 0 04/03/23 05/27/21
- Reconstruction 0-004-044 / / / / 10/05/22 / / 2,4,8,9,10,155,15,16 0 0 JLB 0 0 0 0 / / / /
H. Frank Carey HS:
20-1828 Reconstruction 0-005-042 09/08/21 DONE DONE DONE 06/03/21 05/27/21 11/13/20 06/09/20 8,9,16 83,000 83,000 JLB 0 0 0 H2M Group 0 04/03/23 05/27/21
- Reconstruction 0-005-043 / / / / 10/05/22 / / 2,4,8,9,10,155,15,16 0 0 JLB 0 0 0 0 / / / /
Elmont Memorial High School:
20-1829 Reconstruction 0-006-049 09/08/21 DONE DONE DONE 06/03/21 05/27/21 11/13/20 06/09/20 8,9,16 95,000 95,000 JLB 0 0 0 H2M Group 0 04/03/23 05/27/21
20-1824 Reconstruction 0-006-050 02/02/22 DONE DONE DONE 06/03/21 06/01/21 04/09/21 05/18/21 155,15,16 999,114 999,114 JLB 0 0 0 Mark Design Studios 0 / / 06/01/21
- Reconstruction 0-006-051 / / / / 10/05/22 / / 2,4,8,9,10,155,15,16 0 0 JLB 0 0 0 0 / / / /
Cosmetology Bldg:
- PR New Construction 0-045-001 / / / / 08/15/22 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
22-1520 New Construction 0-045-001 09/20/23 DONE DONE DONE 01/20/23 01/19/23 08/15/22 05/17/22 02 - 16 3,459,490 1,981,588 JJH 0 0 0 Mark Design Studios 0 / / 01/19/23
Snack Shack:
22-1722DB Discovered Building 7-046-001 08/11/23 DONE DONE DONE 02/22/23 02/21/23 01/26/23 / / 0 0 JJH 0 0 0 0 / / 02/21/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LONG BEACH CITY SD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-03-00-01
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Lido School (EL/MS):
18-1464 Reconstruction 0-001-040 04/11/19 DONE DONE DONE 02/19/19 02/12/19 11/19/18 05/15/18 8 100,000 100,000 BMJ 0 0 0 John A. Grillo 0 05/21/21 02/12/19
19-1625 Reconstruction 0-001-041 06/12/20 DONE DONE DONE 03/24/20 03/18/20 11/25/19 05/21/19 2 918,696 0 JLB 0 0 0 John A. Grillo 0 / / 03/18/20
20-0458 Reconstruction 0-001-042 12/01/20 DONE DONE DONE 09/28/20 09/22/20 08/10/20 06/09/20 2,4,7,8,155,15,16 875,000 875,000 JLB 0 0 0 John A. Grillo 0 / / 09/22/20
21-0034 Reconstruction 0-001-043 08/11/21 DONE DONE DONE 07/12/21 07/09/21 05/25/21 05/18/21 2,9,16 135,000 135,000 JLB 0 0 0 John A. Grillo 0 / / 07/09/21
22-0991 Reconstruction 0-001-044 04/25/23 DONE DONE DONE 11/16/22 11/15/22 06/22/22 05/17/22 2,4,7,9,155,15,16 6,814,288 6,814,288 WLC 0 0 0 John A. Grillo 0 / / 11/15/22
23-1175 Reconstruction 0-001-045 UNREVIEWED 12/13/23 12/13/23 07/26/23 05/16/22 2,4,7,9,155,15,16 0 0 WLC 0 0 0 John A. Grillo 0 / / 12/13/23
West Elementary School:
22-1507 Reconstruction 0-003-028 05/09/23 DONE DONE DONE 01/18/23 01/18/23 06/22/22 05/17/22 155,16 60,000 60,000 WLC 0 0 0 John A. Grillo 0 / / 01/18/23
East School:
18-1465 Reconstruction 0-004-025 04/11/19 DONE DONE DONE 02/19/19 02/12/19 / / 05/15/18 8 100,000 100,000 BMJ 0 0 0 John A. Grillo 0 05/21/21 02/12/19
20-1492 Reconstruction 0-004-026 06/29/21 DONE DONE DONE 03/26/21 03/12/21 11/24/20 06/09/20 2,4,9,155,16 908,600 908,600 JLB 0 0 0 John A. Grillo 0 / / 03/12/21
- Reconstruction 0-004-027 / / / / 05/25/21 / / 4 0 0 JLB 0 0 0 0 / / / /
Lindell School:
19-0334 Reconstruction 0-005-032 11/27/19 DONE DONE DONE 08/30/19 08/26/19 06/10/19 05/21/19 9,10 250,000 250,000 BMJ 0 0 0 John A. Grillo 0 05/17/21 08/26/19
- Reconstruction 0-005-033 / / / / 10/18/19 / / 2 0 0 BMJ 0 0 0 0 / / / /
20-0828 Reconstruction 0-005-034 02/22/21 DONE DONE DONE 11/16/20 11/02/20 07/13/20 06/09/20 4,7,8,9,155,15,16 175,000 175,000 JLB 0 0 0 John A. Grillo 0 / / 11/02/20
23-1637 Reconstruction 0-005-035 UNREVIEWED 03/15/24 03/15/24 07/26/23 05/16/23 2,15 0 0 WLC 0 0 0 John A. Grillo 0 / / 03/15/24
High School:
18-1466 Reconstruction 0-011-050 04/11/19 DONE DONE DONE 02/19/19 02/12/19 08/29/18 05/15/18 8 200,000 200,000 BMJ 0 0 0 John A. Grillo 0 05/21/21 02/12/19
18-1532 Reconstruction 0-011-051 04/18/19 DONE DONE DONE 02/22/19 02/21/19 08/29/18 05/15/18 7,8,9,10,13,155,15,1 600,000 0 BMJ 0 0 0 John A. Grillo 0 / / 02/21/19
19-1626 Reconstruction 0-011-052 06/12/20 DONE DONE DONE 03/24/20 03/18/20 11/25/19 05/21/19 2 263,804 0 JLB 0 0 0 John A. Grillo 0 / / 03/18/20
21-1124 Reconstruction 0-011-053 04/22/22 DONE DONE DONE 01/14/22 01/12/22 05/25/21 05/18/21 2,7 1,382,664 1,382,664 JLB 0 0 0 John A. Grillo 0 / / 01/12/22
22-0701 Reconstruction 0-011-054 02/08/23 DONE DONE DONE 10/12/22 10/11/22 06/22/22 05/17/22 2,4,7,8,9,155,15,16 2,333,400 2,333,400 WLC 0 0 0 John A. Grillo 0 / / 10/11/22
23-1638 Reconstruction 0-011-055 UNREVIEWED 03/15/24 03/15/24 07/26/23 05/16/23 16 0 0 WLC 0 0 0 John A. Grillo 0 / / 03/15/24
Environmental Center:
- Reconstruction 0-012-007 / / / / 07/25/19 / / 2,10 0 0 BMJ 0 0 0 0 / / / /
21-1045 Reconstruction 0-012-008 04/06/22 DONE DONE DONE 01/05/22 01/05/22 05/27/21 01/08/13 2 1,535,636 0 JLB 0 0 0 CS Arch 0 05/10/23 01/05/22
22-1588 Reconstruction 0-012-009 05/09/23 DONE DONE DONE 02/01/23 01/30/23 06/22/22 05/17/22 2 265,600 0 WLC 0 0 0 John A. Grillo 0 / / 01/30/23
Adult Education Building:
- DB Discovered Building 0-039-001 / / / / 11/06/19 / / 0 0 BMJ 0 0 0 0 / / / /
Tire Shop A Demo:
22-2030 Reconstruction 2-019-001 08/21/23 DONE DONE DONE 04/14/23 04/13/23 06/22/22 05/17/22 10,000 0 WLC 0 0 0 John A. Grillo 0 / / 04/13/23
:
- DB Discovered Building 2-042-001 / / / / 01/13/23 / / 0 0 WLC 0 0 0 0 / / / /
Tire Shop A (New):
- PR New Construction 2-043-001 / / / / 06/22/22 / / 02 - 16 0 0 FMJ 0 0 0 0 / / / /
22-2031 New Construction 2-043-001 08/21/23 DONE DONE DONE 04/14/23 04/13/23 06/22/22 05/17/22 02 - 16 462,000 0 WLC 0 0 0 John A. Grillo 0 / / 04/13/23
Storage Cont@Nike Bldg:
- DB Discovered Building 2-044-001 / / / / 01/13/23 / / 0 0 WLC 0 0 0 0 / / / /
Bus Maint. Garage (Transp. Faci1ity:
21-1201 Reconstruction 5-013-005 06/16/22 DONE DONE DONE 01/28/22 01/26/22 05/25/21 05/18/21 4,8 1,218,000 1,218,000 FMJ 0 0 0 John A. Grillo 0 / / 01/26/22
22-1589 Reconstruction 5-013-006 05/09/23 DONE DONE DONE 02/01/23 01/30/23 06/22/22 05/17/22 2 400,000 400,000 WLC 0 0 0 John A. Grillo 0 / / 01/30/23
Lowenstein Public Library:
21-0209 Reconstruction 6-021-005 11/03/21 DONE DONE DONE 08/25/21 08/20/21 07/29/21 05/18/21 7,155,16 500,000 0 JLB 0 0 0 John A. Grillo 0 / / 08/20/21
- Reconstruction 6-021-006 / / / / 03/01/22 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
22-0368 Reconstruction 6-021-007 01/12/23 DONE DONE DONE 08/29/22 08/26/22 06/22/22 05/17/22 155,16 1,000,000 0 WLC 0 0 0 John A. Grillo 0 / / 08/26/22
Bathroom Building @ HS:
19-0137 New Construction 7-036-001 09/10/19 DONE DONE DONE 07/23/19 07/17/19 03/20/18 02/06/19 02 - 16 426,000 0 BMJ 0 0 0 John A. Grillo 0 / / 07/17/19
Green House (CXL Per Dist):
- XX New Construction 7-038-001 CANCELLED / / / / 10/18/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
Guard Booth @ Lido School:
19-1627 New Construction 7-040-001 06/12/20 DONE DONE DONE 03/18/20 03/18/20 11/25/19 / / 02 - 16 20,000 0 JLB 0 0 0 John A. Grillo 0 / / 03/18/20
Guard Booth @ Long Beach HS:
19-1628 New Construction 7-041-001 06/12/20 DONE DONE DONE 03/24/20 03/18/20 11/25/19 / / 02 - 16 20,000 0 JLB 0 0 0 John A. Grillo 0 / / 03/18/20
Green House B:
- PR New Construction 7-042-001 / / / / 06/22/22 / / 02 - 16 0 0 FMJ 0 0 0 0 / / / /
23-0151 New Construction 7-042-001 STARTED DONE DONE 07/28/23 07/27/23 06/22/22 05/17/22 02 - 16 0 0 WLC 0 0 0 John A. Grillo 0 / / 07/27/23
High School Press Box:
- DB Discovered Building 7-045-001 / / / / 01/10/20 / / 0 0 WLC 0 0 0 0 / / / /
Graduation Tent @ Lido ES:
- TQ Temporary Quarters 8-046-001 / / / / 06/06/23 / / 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WESTBURY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-04-01-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Drexel Elementary:
19-1434 Reconstruction 0-001-017 05/26/21 DONE DONE DONE 02/19/20 02/11/20 07/30/19 05/18/21 2,8,9,16 488,750 488,750 SLC 0 0 0 H2M Group 0 09/06/22 02/11/20
- Reconstruction 0-001-018 / / / / 01/21/21 / / 9,13,15,16 0 0 SLC 0 0 0 0 / / / /
21-0046FA Reconstruction 0-001-019 12/14/21 DONE DONE DONE 07/16/21 07/14/21 06/24/21 05/20/21 16 2,540,333 2,540,333 SLC 0 0 0 ECG Engineering, LLC 457,974 05/12/23 07/14/21
21-1012 Reconstruction 0-001-020 04/28/22 DONE DONE DONE 01/03/22 12/30/21 07/29/21 05/18/21 155 257,400 257,400 SLC 0 0 0 H2M Group 0 / / 12/30/21
- Reconstruction 0-001-021 / / / / 03/08/24 / / 4,8,9,155,16 0 0 MSK 0 0 0 0 / / / /
Westbury Middle/Jr High 6-8:
18-1696 Additions and Alterations 0-002-022 07/26/19 DONE DONE DONE 03/20/19 03/19/19 01/25/18 05/15/18 02 - 16 39,670,000 24,579,283 SLC 0 0 0 Wiedersum Associates Architec 0 02/24/22 03/19/19
18-1996SR Reconstruction 0-002-022 06/06/19 DONE DONE DONE / / / / 01/25/18 05/15/18 7 0 0 SLC 0 0 0 Wiedersum Associates Architec 0 / / / /
- Reconstruction 0-002-023 / / / / 02/03/21 / / 9,13,15,16 0 0 SLC 0 0 0 0 / / / /
21-0133FA Reconstruction 0-002-024 12/14/21 DONE DONE DONE 08/04/21 07/14/21 06/24/21 05/20/21 16 1,438,274 1,438,274 SLC 0 0 0 ECG Engineering, LLC 1,403,996 05/12/23 07/14/21
21-1575 Reconstruction 0-002-025 08/05/22 DONE DONE DONE 03/28/22 03/28/22 12/02/21 05/18/21 2,9 731,701 731,701 SLC 0 0 0 H2M Group 0 08/07/23 03/28/22
- Reconstruction 0-002-026 / / / / 03/08/24 / / 4,8,9,155,16 0 0 MSK 0 0 0 0 / / / /
Powell's Lane Elementary:
- Reconstruction 0-005-017 / / / / 01/21/21 / / 9,13,15,16 0 0 SLC 0 0 0 0 / / / /
21-0047FA Reconstruction 0-005-018 12/14/21 DONE DONE DONE 07/16/21 07/14/21 06/24/21 05/20/21 16 836,306 836,306 SLC 0 0 0 ECG Engineering, LLC 432,884 05/12/23 07/14/21
21-1013 Reconstruction 0-005-019 04/28/22 DONE DONE DONE 01/03/22 12/30/21 07/29/21 05/18/21 155 264,000 264,000 SLC 0 0 0 H2M Group 0 / / 12/30/21
- Reconstruction 0-005-020 / / / / 03/08/24 / / 4,8,9,155,16 0 0 MSK 0 0 0 0 / / / /
Westbury High School:
19-0505 Reconstruction 0-007-025 11/07/19 DONE DONE DONE 09/27/19 09/11/19 07/02/19 09/20/18 2,8,9,15,16 150,000 0 SLC 0 0 0 H2M Group 0 / / 09/11/19
- Reconstruction 0-007-026 / / / / 01/21/21 / / 9,13,15,16 0 0 SLC 0 0 0 0 / / / /
21-0134FA Reconstruction 0-007-027 12/14/21 DONE DONE DONE 08/04/21 07/14/21 06/24/21 05/20/21 16 4,488,472 4,488,472 SLC 0 0 0 ECG Engineering, LLC 3,724,842 05/12/23 07/14/21
21-1540 Reconstruction 0-007-028 08/01/22 DONE DONE DONE 03/21/22 03/21/22 08/13/21 05/18/21 2,16 2,836,800 2,836,800 SLC 0 0 0 H2M Group 0 08/17/23 03/21/22
22-0108FA Reconstruction 0-007-029 12/18/22 DONE DONE DONE 07/20/22 07/18/22 12/15/21 01/18/22 155,16 900,000 0 SLC 0 0 0 H2M Group 0 / / 07/18/22
- Reconstruction 0-007-030 / / / / 03/08/24 / / 4,8,9,155,16 0 0 MSK 0 0 0 0 / / / /
Park Avenue School:
19-1435 Reconstruction 0-010-019 05/26/21 DONE DONE DONE 02/19/20 02/11/20 07/30/19 05/18/21 2,8,9,16 451,250 451,250 SLC 0 0 0 H2M Group 0 09/06/22 02/11/20
- Reconstruction 0-010-020 / / / / 01/21/21 / / 9,13,15,16 0 0 SLC 0 0 0 0 / / / /
21-0048FA Reconstruction 0-010-021 12/14/21 DONE DONE DONE 07/16/21 07/14/21 06/24/21 05/20/21 16 951,102 951,102 SLC 0 0 0 ECG Engineering, LLC 394,570 05/12/23 07/14/21
21-1014 Reconstruction 0-010-022 04/28/22 DONE DONE DONE 01/03/22 12/30/21 07/29/21 05/18/21 155 294,200 294,200 SLC 0 0 0 H2M Group 0 / / 12/30/21
- Reconstruction 0-010-023 / / / / 03/08/24 / / 4,8,9,155,16 0 0 MSK 0 0 0 0 / / / /
Dryden St ES(K/Pre Sch):
- Reconstruction 0-012-015 / / / / 01/21/21 / / 9,13,15,16 0 0 SLC 0 0 0 0 / / / /
21-0049FA Reconstruction 0-012-016 12/14/21 DONE DONE DONE 07/16/21 07/14/21 06/24/21 05/20/21 16 1,749,716 1,749,716 SLC 0 0 0 ECG Engineering, LLC 1,357,495 05/12/23 07/14/21
21-1015 Reconstruction 0-012-017 04/28/22 DONE DONE DONE 01/03/22 12/30/21 07/29/21 05/18/21 155 183,900 183,900 SLC 0 0 0 H2M Group 0 / / 12/30/21
- Reconstruction 0-012-018 / / / / 03/08/24 / / 4,8,155,16 0 0 MSK 0 0 0 0 / / / /
Administration Building:
21-0050FA Reconstruction 1-003-009 12/14/21 DONE DONE DONE 07/16/21 07/14/21 06/24/21 05/20/21 16 28,569 0 SLC 0 0 0 ECG Engineering, LLC 27,099 05/12/23 07/14/21
Facilities Operations:
- Reconstruction 3-004-005 / / / / 11/20/19 / / 4,8,9,155,16 0 0 SLC 0 0 0 0 / / / /
21-0051FA Reconstruction 3-004-006 12/14/21 DONE DONE DONE 07/16/21 07/14/21 06/24/21 05/20/21 16 46,728 0 SLC 0 0 0 ECG Engineering, LLC 43,322 05/12/23 07/14/21
21-1452 Reconstruction 3-004-007 06/09/22 DONE DONE DONE 03/08/22 03/07/22 08/04/21 05/18/21 155 110,300 0 SLC 0 0 0 H2M Group 0 / / 03/07/22
Nassau Comm College-North Annex:
19-0208TQ Temporary Quarters 8-033-002 06/17/21 DONE DONE DONE 08/05/19 08/01/19 07/18/19 / / 9,16 0 0 SLC 0 0 0 H2M Group 0 09/01/19 08/01/19
XXPowells Lane Tent 1 - canceled:
- XX Reconstruction 8-035-001 CANCELLED / / / / 06/03/21 / / 0 0 SLC 0 0 0 0 / / / /
XXDrexel Avenue Tent 1-cancelled:
- XX Reconstruction 8-036-001 CANCELLED / / / / 06/03/21 / / 0 0 SLC 0 0 0 0 / / / /
XXDryden K Tent 1-Canceled:
- XX Reconstruction 8-037-001 CANCELLED / / / / 06/03/21 / / 0 0 SLC 0 0 0 0 / / / /
xxDryden PreK Tent 2-Cancelled:
- XX Reconstruction 8-038-001 CANCELLED / / / / 06/03/21 / / 0 0 SLC 0 0 0 0 / / / /
XXPark Ave Tent 1 - Cancelled:
- XX Reconstruction 8-039-001 CANCELLED / / / / 06/03/21 / / 0 0 SLC 0 0 0 0 / / / /
xxTemp. Admin. Space @ Powells:
21-0699TQ Temporary Quarters 8-040-001 01/21/22 DONE DONE DONE 11/12/21 11/12/21 07/28/21 / / 130,000 0 SLC 0 0 0 0 / / 11/12/21
xxTemp. Admin. Space @ Drexel:
21-0700TQ Temporary Quarters 8-041-001 12/23/21 DONE DONE DONE 11/12/21 11/12/21 07/28/21 / / 130,000 0 SLC 0 0 0 0 / / 11/12/21
xxTemp. Admin. Space @ Dryden:
21-0701TQ Temporary Quarters 8-042-001 12/23/21 DONE DONE DONE 11/12/21 11/12/21 07/28/21 / / 130,000 0 SLC 0 0 0 0 / / 11/12/21
xxTemp. Admin. Space @ Park:
21-0702TQ Temporary Quarters 8-043-001 12/23/21 DONE DONE DONE 11/12/21 11/12/21 07/28/21 / / 130,000 0 SLC 0 0 0 0 / / 11/12/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EAST WILLISTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-04-02-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Wheatley High School:
19-0667 Reconstruction 0-001-034 02/26/20 DONE DONE DONE 11/04/19 10/23/19 06/12/19 05/21/19 2,15,16 5,507,691 5,092,734 BMJ 0 0 0 John A. Grillo 0 11/12/20 10/23/19
20-1352 Reconstruction 0-001-035 05/04/21 DONE DONE DONE 02/26/21 02/18/21 07/13/20 06/16/20 2,4,7,8,9,155,15,16 1,200,000 500,000 JSS 0 0 0 John A. Grillo 0 07/27/22 02/18/21
21-0204 Reconstruction 0-001-036 02/04/22 DONE DONE DONE 08/23/21 08/18/21 05/25/21 05/17/16 8 133,545 133,545 SLC 0 0 0 John A. Grillo 0 / / 08/18/21
21-1063 Reconstruction 0-001-037 06/02/22 DONE DONE DONE 01/07/22 01/07/22 08/26/21 05/18/21 2,15,16 520,000 520,000 SLC 0 0 0 John A. Grillo 0 06/29/23 01/07/22
22-1899 Reconstruction 0-001-038 06/21/23 DONE DONE DONE 03/20/23 03/17/23 06/24/22 05/17/22 2,4,7,8,9,10,155,15, 2,498,000 2,498,000 MSK 0 0 0 John A. Grillo 0 / / 03/17/23
22-2390 Reconstruction 0-001-039 09/25/23 DONE DONE DONE 06/16/23 06/15/23 04/12/23 05/17/22 2,4,7,8,9,10,155,15, 2,100,000 2,100,000 JLB 0 0 0 John A. Grillo 0 / / 06/15/23
Northside Elementary School:
18-1481 Reconstruction 0-002-030 04/11/19 DONE DONE DONE 02/20/19 02/15/19 06/28/18 05/15/18 2 450,000 0 BMJ 0 0 0 John A. Grillo 0 / / 02/15/19
21-0205 Reconstruction 0-002-031 02/04/22 DONE DONE DONE 08/23/21 08/18/21 05/25/21 05/17/16 8 177,300 177,300 SLC 0 0 0 John A. Grillo 0 / / 08/18/21
21-0892FA Reconstruction 0-002-032 05/12/22 DONE DONE DONE 12/13/21 12/13/21 07/14/21 06/16/20 4,9,155,16 330,000 330,000 SLC 0 0 0 John A. Grillo 0 08/28/23 12/13/21
22-1361 Reconstruction 0-002-033 03/27/23 DONE DONE DONE 12/28/22 12/23/22 06/24/22 05/17/22 7 1,080,000 1,080,000 JLB 0 0 0 John A. Grillo 0 / / 12/23/22
23-0616 Reconstruction 0-002-034 STARTED DONE STARTED 10/04/23 10/02/23 06/07/23 05/16/23 4,7,9,155,16 528,000 0 MSK 0 0 0 John A. Grillo 0 / / 10/02/23
Willets Road School:
21-0206 Reconstruction 0-003-027 02/04/22 DONE DONE DONE 08/23/21 08/18/21 05/25/21 05/21/19 8 94,155 94,155 SLC 0 0 0 John A. Grillo 0 / / 08/18/21
21-0893 Reconstruction 0-003-028 05/12/22 DONE DONE DONE 12/13/21 12/13/21 08/26/21 05/18/21 155,15,16 480,000 480,000 SLC 0 0 0 John A. Grillo 0 / / 12/13/21
21-0894FC Reconstruction 0-003-029 05/12/22 DONE DONE DONE 12/13/21 12/13/21 09/14/21 04/25/22 9,15,16 244,532 0 SLC 0 0 0 John A. Grillo 0 08/24/23 12/13/21
22-0600 Reconstruction 0-003-030 01/08/23 DONE DONE DONE 09/28/22 09/27/22 06/24/22 05/17/22 155,15,16 328,715 328,715 SLC 0 0 0 John A. Grillo 0 / / 09/27/22
Press Box:
- PR New Construction 7-016-001 / / / / 06/17/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
19-0668 New Construction 7-016-001 02/26/20 DONE DONE DONE 11/04/19 10/23/19 06/17/19 05/21/19 02 - 16 80,000 0 BMJ 0 0 0 John A. Grillo 0 11/12/20 10/23/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ROSLYN UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-04-03-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
East Hills School:
21-1487 Reconstruction 0-001-027 06/22/22 DONE DONE DONE 03/10/22 03/07/22 12/02/21 06/16/20 2,10 1,250,000 1,250,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 03/07/22
- Reconstruction 0-001-028 / / / / 01/13/23 / / 2,155,15,16 0 0 JLB 0 0 0 0 / / / /
Roslyn High School:
18-1620 Reconstruction 0-002-043 05/13/19 DONE DONE DONE 03/12/19 03/04/19 11/28/18 05/03/18 8,9,10,155,15,16 1,030,407 1,030,407 MTM 0 0 0 Burton Behrendt Smith 0 08/25/20 03/04/19
19-1023 Reconstruction 0-002-044 03/19/20 DONE DONE DONE 12/18/19 12/04/19 06/11/19 05/21/19 2,4,8,9,10,155,15,16 1,498,693 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/04/19
20-0582 Reconstruction 0-002-045 12/17/20 DONE DONE DONE 10/13/20 10/02/20 02/10/20 05/21/19 2,4,8,9,10,155,15,16 4,972,347 4,972,347 JLB 0 0 0 Burton Behrendt Smith 0 / / 10/02/20
22-1044 Reconstruction 0-002-046 02/07/23 DONE DONE DONE 11/18/22 11/17/22 07/18/22 05/17/22 2,4,7,8,9,155,15,16 3,631,190 3,631,190 JLB 0 0 0 Burton Behrendt Smith 0 / / 11/17/22
23-0926 Reconstruction 0-002-047 UNREVIEWED 11/08/23 11/03/23 06/02/23 05/16/23 2,9,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/03/23
Roslyn Middle School:
18-1621 Reconstruction 0-006-034 05/13/19 DONE DONE DONE 03/12/19 03/04/19 11/28/18 05/03/18 155 125,000 125,000 JLB 0 0 0 Burton Behrendt Smith 0 08/04/20 03/04/19
19-0995 Reconstruction 0-006-035 04/07/20 DONE DONE DONE 12/13/19 11/08/19 06/11/19 05/21/19 8 1,650,135 1,650,135 JLB 0 0 0 Burton Behrendt Smith 0 / / 11/08/19
- Reconstruction 0-006-036 / / / / 08/25/20 / / 9,10 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-006-037 / / / / 12/21/23 / / 2,15,16 0 0 JJH 0 0 0 0 / / / /
Roslyn Heights Elementary:
19-0850 Reconstruction 0-007-026 02/19/20 DONE DONE DONE 11/21/19 11/08/19 11/30/18 05/21/19 2,10 518,254 0 JLB 0 0 0 Burton Behrendt Smith 0 05/07/21 11/08/19
20-1234 Reconstruction 0-007-027 06/01/21 DONE DONE DONE 02/02/21 02/01/21 08/25/20 05/21/19 2,4,9,14,16 150,421 150,421 JLB 0 0 0 Burton Behrendt Smith 0 / / 02/01/21
Harbor Hill Elementary:
19-0851 Reconstruction 0-009-027 02/19/20 DONE DONE DONE 11/21/19 11/08/19 11/30/18 05/21/19 2,10 397,698 0 JLB 0 0 0 Burton Behrendt Smith 0 05/07/21 11/08/19
19-1360 Reconstruction 0-009-028 03/27/20 DONE DONE DONE 02/04/20 01/13/20 06/11/19 05/21/19 155,16 255,548 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 01/13/20
19-1210 Reconstruction 0-009-029 04/29/20 DONE DONE DONE 01/13/20 12/20/19 12/05/19 05/21/19 2 739,745 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/20/19
23-0571 Reconstruction 0-009-030 STARTED DONE DONE 09/29/23 09/26/23 06/06/23 05/16/23 2,155 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 09/26/23
Administration Bldg:
- Reconstruction 0-010-010 / / / / 08/25/20 / / 2,15 0 0 JLB 0 0 0 0 / / / /
Storage Container 1 @ East Hills:
- DB Discovered Building 2-023-001 / / / / 05/07/21 / / 0 0 JLB 0 0 0 0 / / / /
Storage Container 1 @ Heights School:
- DB Discovered Building 2-024-001 / / / / 05/07/21 / / 0 0 JLB 0 0 0 0 / / / /
Storage Container 1 @ Harbor Hill:
- DB Discovered Building 2-025-001 / / / / 05/07/21 / / 0 0 JLB 0 0 0 0 / / / /
Storage Container 1 @ Middle School:
- DB Discovered Building 2-026-001 / / / / 05/07/21 / / 0 0 JLB 0 0 0 0 / / / /
Storage Container 1 @ Roslyn HS:
- DB Discovered Building 2-027-001 / / / / 05/07/21 / / 0 0 JLB 0 0 0 0 / / / /
HS Athletic Storage Shed:
- PR New Construction 2-028-001 / / / / 09/21/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1045 New Construction 2-028-001 02/07/23 DONE DONE DONE 11/18/22 11/17/22 09/21/22 05/17/22 02 - 16 127,774 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 11/17/22
HS Security Guard Booth:
- PR New Construction 7-023-001 / / / / 10/24/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Guard Booth @ High School:
- PR New Construction 7-029-001 / / / / 06/06/23 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
23-0975 New Construction 7-029-001 UNREVIEWED 11/13/23 11/08/23 06/06/23 05/16/23 02 - 16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/08/23
Lsd Trans Ofc & Bus Prk Lot:
22-2160TQ Temporary Quarters 8-021-002 DONE STARTED UNREVIEWED05/08/23 05/08/23 05/02/23 / / 0 0 JJH 0 0 0 0 / / 05/08/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PORT WASHINGTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-04-04-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Paul D Schreiber High School:
19-1030 Additions and Alterations 0-001-040 05/05/20 DONE DONE DONE 12/18/19 11/06/19 07/13/16 03/10/15 02 - 16 7,082,801 1,480,735 JSS 0 0 0 Burton Behrendt Smith 0 09/01/22 11/06/19
19-1077 Reconstruction 0-001-043 01/16/20 DONE DONE DONE 12/26/19 12/13/19 10/10/18 05/16/17 155,16 300,000 300,000 JSS 0 0 0 Burton Behrendt Smith 0 03/01/22 12/13/19
18-1581 Reconstruction 0-001-044 05/28/19 DONE DONE DONE 03/01/19 02/27/19 12/20/18 05/21/19 13,16 115,000 0 BMJ 0 0 0 John A. Grillo 0 12/21/21 02/27/19
21-0680 Reconstruction 0-001-045 01/31/22 DONE DONE DONE 11/12/21 11/09/21 06/07/21 05/18/21 2,7 1,046,890 1,046,890 JLB 0 0 0 John A. Grillo 0 08/03/23 11/09/21
23-1287 Reconstruction 0-001-046 UNREVIEWED 12/26/23 12/26/23 09/08/23 / / 2,8,9,155,15,16 0 0 WLC 0 0 0 John A. Grillo 0 / / 12/26/23
- Reconstruction 0-001-047 / / / / / / / / 155,15,16 0 0 WLC 0 0 0 0 / / / /
John Philip Sousa Elementary:
20-1107 Reconstruction 0-003-029 02/03/21 DONE DONE DONE 01/07/21 11/02/20 12/18/20 06/16/20 4,7 660,800 660,800 JSS 0 0 0 John A. Grillo 0 06/17/22 11/02/20
21-1160 Reconstruction 0-003-030 08/22/22 DONE DONE DONE 01/19/22 01/18/22 06/30/21 03/10/15 2,9,155,16 4,159,629 584,491 WLC 0 0 0 Burton Behrendt Smith 0 10/30/23 YES 01/18/22
- Reconstruction 0-003-031 / / / / 03/22/24 / / 9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Manorhaven Elementary School:
21-1161 Reconstruction 0-005-028 08/22/22 DONE DONE DONE 01/19/22 01/18/22 06/30/21 03/10/15 2,9,155,16 300,000 300,000 FMJ 0 0 0 Burton Behrendt Smith 0 / / 01/18/22
22-1495 Reconstruction 0-005-029 05/09/23 DONE DONE DONE 01/17/23 01/17/23 10/03/22 05/17/22 4,7 78,300 78,300 WLC 0 0 0 John A. Grillo 0 08/16/23 01/17/23
- Reconstruction 0-005-030 / / / / 03/22/24 / / 9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Carrie Palmer Weber Middle School:
22-1496 Reconstruction 0-006-040 05/09/23 DONE DONE DONE 01/17/23 01/17/23 09/29/22 05/17/22 4,7 837,400 837,400 WLC 0 0 0 John A. Grillo 0 08/16/23 01/17/23
- Reconstruction 0-006-041 / / / / 03/22/24 / / 155,15,16 0 0 WLC 0 0 0 0 / / / /
John J. Daly Elementary:
19-0403PR Additions and Alterations 0-007-025 DONE 09/12/19 / / 07/13/16 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
19-1026 Additions and Alterations 0-007-025 05/18/20 DONE DONE DONE 12/18/19 10/25/19 07/13/16 03/10/15 02 - 16 6,109,032 2,459,787 JSS 0 0 0 Burton Behrendt Smith 0 06/26/23 10/25/19
22-1497 Reconstruction 0-007-027 05/09/23 DONE DONE DONE 01/17/23 01/17/23 09/29/22 05/17/22 4,7 1,123,800 1,123,800 WLC 0 0 0 John A. Grillo 0 08/16/23 01/17/23
23-1340 Reconstruction 0-007-028 UNREVIEWED 01/11/24 01/08/24 09/08/23 05/18/22 7 0 0 WLC 0 0 0 John A. Grillo 0 / / 01/08/24
- Reconstruction 0-007-029 / / / / 03/22/24 / / 155,15,16 0 0 WLC 0 0 0 0 / / / /
South Salem Elementary:
19-0401 Reconstruction 0-008-008 10/04/19 DONE DONE DONE 09/11/19 09/06/19 06/24/19 05/21/19 2,15 189,000 189,000 JSS 0 0 0 John A. Grillo 0 12/13/21 09/06/19
20-1106 Reconstruction 0-008-009 02/03/21 DONE DONE DONE 01/07/21 11/02/20 12/18/20 06/16/20 7 224,200 224,200 JSS 0 0 0 John A. Grillo 0 06/17/22 11/02/20
21-0681 Reconstruction 0-008-010 01/31/22 DONE DONE DONE 11/12/21 11/09/21 06/07/21 05/18/21 2,7 976,198 976,198 JLB 0 0 0 John A. Grillo 0 06/03/23 11/09/21
21-1162 Reconstruction 0-008-011 08/22/22 DONE DONE DONE 01/19/22 01/18/22 06/30/21 03/10/15 2,9,155,16 250,000 250,000 FMJ 0 0 0 Burton Behrendt Smith 0 / / 01/18/22
- Reconstruction 0-008-012 DONE ADD. REQ'D DONE 03/15/23 02/28/23 04/12/23 03/02/23 2,4,7,8,9,14,155,15, 0 0 WLC 0 0 0 March Associates 0 / / 02/28/23
- PR Additions and Alterations 0-008-013 / / / / 05/18/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-0259 Additions and Alterations 0-008-013 03/11/24 DONE DONE DONE 08/14/23 08/04/23 05/18/23 03/10/15 02 - 16 1,999,110 1,209,501 WLC 0 0 0 Burton Behrendt Smith 0 / / 08/04/23
- Reconstruction 0-008-014 / / / / 09/08/23 / / 7 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-008-015 / / / / 03/22/24 / / 155,15,16 0 0 WLC 0 0 0 0 / / / /
F.E. Guggenheim Elementary:
- Reconstruction 0-010-033 / / / / 03/22/24 / / 155,15,16 0 0 WLC 0 0 0 0 / / / /
Daly School Port 1 Demolition:
19-1027 Reconstruction 0-026-001 04/27/20 DONE DONE DONE 12/18/19 12/16/19 11/14/19 03/10/15 2,155,15,16 20,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 12/16/19
Daly School Port 2 Demolition:
19-1028 Reconstruction 0-027-001 04/27/20 DONE DONE DONE 12/18/19 12/16/19 11/14/19 03/10/15 2,155,15,16 20,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 12/16/19
Daly School Port 3 Demolition:
19-1029 Reconstruction 0-028-001 04/27/20 DONE DONE DONE 12/18/19 12/16/19 11/14/19 03/10/15 2,155,15,16 20,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 12/16/19
John Daly ES Port 1 Demolition:
- Reconstruction 0-040-002 / / / / 11/07/19 / / 2,155,15,16 0 0 JSS 0 0 0 0 / / / /
Administration Building:
- Reconstruction 1-013-009 / / / / 03/22/24 / / 155,15,16 0 0 WLC 0 0 0 0 / / / /
Port Washington Public Library:
18-1116 Reconstruction 6-032-010 11/06/19 DONE DONE DONE 12/19/18 09/17/18 01/31/18 12/20/17 4,8,9,155,15,16 240,000 0 BMJ 0 0 0 Steven Zalben, Architect 0 / / 09/17/18
19-0616 Reconstruction 6-032-011 02/12/20 DONE DONE DONE 10/24/19 10/09/19 03/27/19 06/19/19 7 245,700 0 JSS 0 0 0 John A. Grillo 0 / / 10/09/19
20-1922 Reconstruction 6-032-012 08/23/21 DONE DONE DONE 06/28/21 06/14/21 09/16/20 02/10/21 4,7,8 1,300,000 0 JLB 0 0 0 H2M Group 0 / / 06/14/21
District-Wide:
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 BMJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MANHASSET UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-04-06-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Munsey Park Elementary School:
19-0873 Reconstruction 0-001-026 03/19/20 DONE DONE DONE 11/27/19 11/22/19 09/06/19 05/21/19 2,4,7,8,9,155,15,16 2,262,000 2,262,000 BMJ 0 0 0 John A. Grillo 0 01/04/24 11/22/19
22-1749 Reconstruction 0-001-027 06/07/23 DONE DONE DONE 02/24/23 02/22/23 12/29/22 12/08/22 4,7 1,105,000 1,105,000 MSK 0 0 0 John A. Grillo 0 / / 02/22/23
22-1743 Reconstruction 0-001-028 05/23/23 DONE DONE DONE 02/24/23 02/22/23 01/18/23 12/08/22 8 385,000 385,000 JLB 0 0 0 John A. Grillo 0 05/31/23 02/22/23
23-0555 Reconstruction 0-001-029 UNREVIEWED
STARTED STARTED 09/27/23 09/25/23 04/25/23 03/16/23 155,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 09/25/23
23-0438 Reconstruction 0-001-030 03/07/24 DONE DONE DONE 09/11/23 09/11/23 04/25/23 12/08/22 155,16 1,668,750 1,668,750 MSK 0 0 0 John A. Grillo 0 / / 09/11/23
23-0884 Reconstruction 0-001-031 UNREVIEWED 11/06/23 11/03/23 05/04/23 12/08/22 2,4,7,8,9,10,15,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 11/03/23
Manhasset Jr/Sr High School:
18-2018 Reconstruction 0-004-048 06/24/19 DONE DONE DONE 05/29/19 05/23/19 02/22/19 05/21/19 8,9 65,000 65,000 BMJ 0 0 0 John A. Grillo 0 01/04/24 05/23/19
18-2058 Reconstruction 0-004-049 07/15/19 DONE DONE DONE 06/04/19 05/30/19 03/25/19 11/02/18 2,16 0 0 BMJ 0 0 0 John A. Grillo 0 / / 05/30/19
19-1403 Reconstruction 0-004-050 08/10/20 DONE DONE DONE 02/11/20 02/07/20 09/06/19 05/21/19 2,7,8,9,155,15,16 1,376,000 1,376,000 SLC 0 0 0 John A. Grillo 0 01/04/24 02/07/20
- PR Additions and Alterations 0-004-051 DONE / / / / 09/06/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
19-1166 Additions and Alterations 0-004-051 03/20/20 DONE DONE DONE 01/07/20 12/30/19 09/06/19 05/21/19 02 - 16 1,400,000 962,215 BMJ 0 0 0 John A. Grillo 0 01/04/24 12/30/19
21-1514 Reconstruction 0-004-052 07/06/22 DONE DONE DONE 03/15/22 03/14/22 01/19/22 05/17/22 2,9,16 2,035,000 2,035,000 SLC 0 0 0 John A. Grillo 0 / / 03/14/22
22-0395 Reconstruction 0-004-053 11/21/22 DONE DONE DONE 09/02/22 09/02/22 03/17/22 05/17/22 2,16 663,389 0 SLC 0 0 0 John A. Grillo 0 / / 09/02/22
22-1631FB Reconstruction 0-004-054 03/22/23 DONE DONE DONE 02/06/23 01/11/23 05/09/22 04/26/22 155,16 459,091 0 JLB 0 0 0 John A. Grillo 0 / / 01/11/23
22-1578 Reconstruction 0-004-055 05/01/23 DONE DONE DONE 01/30/23 01/27/23 12/29/22 12/08/22 2 1,364,750 1,364,750 JLB 0 0 0 John A. Grillo 0 / / 01/27/23
22-1744 Reconstruction 0-004-056 05/23/23 DONE DONE DONE 02/24/23 02/22/23 01/18/23 12/08/22 8 914,375 914,375 JLB 0 0 0 John A. Grillo 0 / / 02/22/23
22-2210 Reconstruction 0-004-057 08/17/23 DONE DONE DONE 05/15/23 05/15/23 01/18/23 12/08/22 2,9 2,624,835 2,624,835 MSK 0 0 0 John A. Grillo 0 / / 05/15/23
23-0556 Reconstruction 0-004-058 UNREVIEWED
STARTED STARTED 09/27/23 09/25/23 04/25/23 03/16/23 155,16 0 1,427,909 MSK 0 0 0 John A. Grillo 0 / / 09/25/23
23-0439 Reconstruction 0-004-059 03/07/24 DONE DONE DONE 09/11/23 09/11/23 04/25/23 12/08/22 155,16 1,720,000 0 MSK 0 0 0 John A. Grillo 0 / / 09/11/23
23-1199 Reconstruction 0-004-060 UNREVIEWED 12/15/23 12/15/23 05/04/23 12/08/22 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 John A. Grillo 0 / / 12/15/23
- Reconstruction 0-004-061 / / / / 03/13/24 / / 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
Shelter Rock Elementary:
19-0128 Reconstruction 0-005-026 09/10/19 DONE DONE DONE 07/23/19 07/16/19 02/22/19 05/21/19 2,4,7,8,9,10,15,16 727,000 727,000 BMJ 0 0 0 John A. Grillo 0 01/04/24 07/16/19
- Reconstruction 0-005-027 / / / / 09/06/19 / / 2,4,7,8,9,155,15,16 0 0 BMJ 0 0 0 0 / / / /
20-1607 Reconstruction 0-005-028 06/04/21 DONE DONE DONE 04/21/21 04/09/21 03/09/21 05/18/21 7 428,000 428,000 SLC 0 0 0 John A. Grillo 0 01/04/24 04/09/21
22-1636 Reconstruction 0-005-029 05/09/23 DONE DONE DONE 02/06/23 02/06/23 12/29/22 12/08/22 2,9,16 567,000 567,000 JLB 0 0 0 John A. Grillo 0 08/16/23 02/06/23
22-1745 Reconstruction 0-005-030 05/23/23 DONE DONE DONE 02/24/23 02/22/23 01/18/23 12/08/22 8 411,250 411,250 JLB 0 0 0 John A. Grillo 0 / / 02/22/23
23-0557 Reconstruction 0-005-031 UNREVIEWED
STARTED STARTED 09/27/23 09/25/23 04/25/23 03/16/23 155,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 09/25/23
23-0440 Reconstruction 0-005-032 03/07/24 DONE DONE DONE 09/11/23 09/11/23 04/25/23 12/08/22 155,16 781,000 0 MSK 0 0 0 John A. Grillo 0 / / 09/11/23
23-1603 Reconstruction 0-005-033 UNREVIEWED 03/11/24 03/08/24 05/04/23 12/08/22 7,9,10,155,15,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 03/08/24
- Reconstruction 0-005-034 / / / / 03/13/24 / / 2,4,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
Administration Bldg (fmly 5-012):
23-0558 Reconstruction 1-012-001 UNREVIEWED
STARTED STARTED 09/27/23 09/25/23 05/03/23 03/16/23 155,16 0 0 MSK 0 0 0 John A. Grillo 0 / / 09/25/23
Manhasset Public Library:
19-1349 Reconstruction 6-008-005 04/23/20 DONE DONE DONE 02/04/20 02/03/20 08/20/19 12/05/19 8,9,155,15,16 1,097,264 0 BMJ 0 0 0 MDA Design Group Architects & 0 09/14/21 02/03/20
Press Box (2) @ Basketball Ct:
21-0685 New Construction 7-033-001 05/23/22 DONE DONE DONE 11/12/21 11/10/21 03/08/21 11/03/21 02 - 16 95,000 0 FMJ 0 0 0 John A. Grillo 0 09/01/22 11/10/21
Security Guard Booth:
- New Construction 7-035-001 / / / / 05/09/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Munsey Park Tent:
21-1702TQ Temporary Quarters 8-034-001 06/29/22 DONE DONE DONE 04/27/22 / / 03/07/22 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
GREAT NECK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-04-07-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
E. M. Baker School:
21-0235PR Additions and Alterations 0-003-020 DONE 08/26/21 / / 09/04/20 / / 02 - 16 0 15,988,692 JLB 0 0 0 0 / / / /
21-0594 Additions and Alterations 0-003-020 06/14/22 DONE DONE DONE 10/27/21 10/26/21 09/04/20 05/21/19 02 - 16 8,272,176 1,473,446 JLB 0 0 0 Burton Behrendt Smith 0 / / 10/26/21
22-1078 Reconstruction 0-003-021 04/17/23 DONE DONE DONE 11/28/22 11/21/22 06/10/22 05/17/22 2,4,9,14,16 100,000 100,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/21/22
- Reconstruction 0-003-022 / / / / 07/05/22 / / 2,4,9,14,16 0 12,351,825 JLB 0 0 0 0 / / / /
23-0694 Reconstruction 0-003-023 UNREVIEWED
STARTED STARTED 10/13/23 10/05/23 05/25/23 05/16/23 2,4 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/05/23
Clover Drive School:
21-0712 Reconstruction 0-005-011 01/28/22 DONE DONE DONE 11/15/21 11/15/21 10/19/20 05/16/17 2,8,155 1,476,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 11/15/21
22-0523 Reconstruction 0-005-012 12/06/22 DONE DONE DONE 09/19/22 09/19/22 06/22/22 05/11/21 7,9,16 270,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 09/19/22
23-1091 Reconstruction 0-005-013 UNREVIEWED 12/04/23 11/22/23 05/25/23 05/16/23 2,4,15 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/22/23
Lakeville Elementary:
19-0998 Reconstruction 0-010-024 05/04/20 DONE DONE DONE 12/13/19 11/12/19 09/25/19 05/16/17 2,4,7 2,494,000 2,494,000 BMJ 0 0 0 Burton Behrendt Smith 0 08/31/21 11/12/19
20-1172 Reconstruction 0-010-025 04/14/21 DONE DONE DONE 01/21/21 12/22/20 11/06/19 05/16/17 2,4,7,8,9,155,16 2,052,000 2,052,000 JLB 0 0 0 Burton Behrendt Smith 0 09/01/22 12/22/20
21-0230PR Additions and Alterations 0-010-026 STARTED 08/26/21 / / 09/04/20 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-0595 Additions and Alterations 0-010-026 04/14/22 DONE DONE DONE 10/27/21 10/26/21 09/04/20 12/03/19 02 - 16 1,872,393 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 10/26/21
21-0837 Reconstruction 0-010-027 03/21/22 DONE DONE DONE 12/17/21 11/30/21 07/09/21 06/16/20 4 1,208,000 1,208,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 11/30/21
22-1246 Reconstruction 0-010-028 05/18/23 DONE DONE DONE 12/15/22 12/14/22 06/10/22 05/17/22 2,4,8,9,155,15,16 195,000 195,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 12/14/22
- Reconstruction 0-010-029 / / / / 07/05/22 / / 2,4,8,9,155,15,16 0 0 JLB 0 0 0 0 / / / /
23-0695 Reconstruction 0-010-030 UNREVIEWED
STARTED STARTED 10/13/23 10/05/23 05/25/23 05/16/23 2,4 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/05/23
North Middle School:
19-1041 Reconstruction 0-011-032 04/17/20 DONE DONE DONE 12/24/19 12/09/19 09/25/19 05/16/17 2,4,7 1,626,000 1,626,000 BMJ 0 0 0 Burton Behrendt Smith 0 07/29/22 12/09/19
19-1359 Reconstruction 0-011-033 12/03/20 DONE DONE DONE 02/04/20 01/29/20 11/06/19 05/16/18 2,4,8 2,064,000 2,064,000 JLB 0 0 0 Burton Behrendt Smith 0 03/26/22 01/29/20
20-1353 Reconstruction 0-011-034 09/09/21 DONE DONE DONE 02/26/21 02/22/21 11/06/19 05/16/17 2,4,7,9,155,15,16 2,475,000 2,475,000 JLB 0 0 0 Burton Behrendt Smith 0 06/21/23 02/22/21
- Reconstruction 0-011-035 / / / / 10/19/20 / / 2,155,15,16 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-011-036 / / / / 06/10/22 / / 4,8,10 0 0 JLB 0 0 0 0 / / / /
22-0790 Reconstruction 0-011-037 04/03/23 DONE DONE DONE 10/24/22 10/20/22 07/05/22 05/11/21 4,8,10 5,507,000 5,507,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/20/22
22-0938 Reconstruction 0-011-038 04/24/23 DONE DONE DONE 11/09/22 11/04/22 07/05/22 05/17/22 2,4,8,9,10,155,15,16 450,000 450,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/04/22
23-1182 Reconstruction 0-011-039 UNREVIEWED 12/14/23 12/08/23 05/25/23 05/16/23 2,7,155,15,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 12/08/23
North Senior High:
18-1270 Reconstruction 0-012-022 04/25/19 DONE DONE DONE 01/15/19 01/11/19 11/15/18 05/17/16 2,8 669,700 669,700 BMJ 0 0 0 Burton Behrendt Smith 0 09/11/20 01/11/19
- Reconstruction 0-012-023 / / / / 10/19/20 / / 155,15,16 0 0 JLB 0 0 0 0 / / / /
22-1660 Reconstruction 0-012-024 05/15/23 DONE DONE DONE 02/13/23 02/10/23 05/31/22 05/11/21 8,9 325,000 325,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 02/10/23
22-1097 Reconstruction 0-012-025 05/09/23 DONE DONE DONE 11/29/22 11/28/22 05/31/22 05/16/17 2,4,8,9,10,13,155,15 2,975,800 2,975,800 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/28/22
22-0167 Reconstruction 0-012-026 10/13/22 DONE DONE DONE 07/27/22 07/26/22 05/31/22 05/17/22 4,7,8,14,16 450,000 450,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 07/26/22
22-2217 Reconstruction 0-012-027 08/01/23 DONE DONE DONE 05/17/23 10/19/22 10/24/22 05/17/22 7 150,000 150,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/19/22
23-1183 Reconstruction 0-012-028 UNREVIEWED 12/14/23 12/08/23 05/25/23 05/16/23 2,4,9,15,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 12/08/23
Parkville Annex Pub Lib/leased:
20-1705 Reconstruction 0-013-009 11/22/21 DONE DONE DONE 05/12/21 05/03/21 10/29/20 06/01/18 9,15,16 583,100 0 JLB 0 0 0 MDA Design Group Architects & 0 / / 05/03/21
Parkville School:
19-1240 Reconstruction 0-014-017 03/20/20 DONE DONE DONE 01/17/20 01/10/20 09/25/19 05/16/19 2,4,8,9,155,15,16 1,135,000 1,135,000 BMJ 0 0 0 Burton Behrendt Smith 0 03/03/21 01/10/20
22-1079 Reconstruction 0-014-018 04/24/23 DONE DONE DONE 11/28/22 11/21/22 09/21/22 05/17/20 2,4,8,9,155,15,16 468,000 468,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/21/22
Saddle Rock Elementary School:
19-0882 Reconstruction 0-015-026 03/06/20 DONE DONE DONE 11/27/19 11/08/19 09/25/19 05/16/17 2,4,7 3,641,000 3,641,000 BMJ 0 0 0 Burton Behrendt Smith 0 01/21/21 11/08/19
19-1299 Reconstruction 0-015-027 06/01/20 DONE DONE DONE 01/29/20 01/21/20 11/06/19 05/16/18 2,4,7,8,9,155,16 2,025,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 01/21/20
21-1731 Reconstruction 0-015-028 09/12/22 DONE DONE DONE 04/29/22 04/27/22 10/19/20 06/09/20 2,4,8,9,10,155,16 540,000 540,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 04/27/22
23-1092 Reconstruction 0-015-029 UNREVIEWED 12/04/23 11/22/23 05/25/23 05/16/23 2,15 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/22/23
J.F. Kennedy Elementary School:
18-1642 Reconstruction 0-016-019 04/18/19 DONE DONE DONE 03/14/19 03/05/19 09/26/18 05/16/17 2,4 2,950,000 2,950,000 BMJ 0 0 0 Burton Behrendt Smith 0 11/13/20 03/05/19
19-1663 Reconstruction 0-016-021 05/22/20 DONE DONE DONE 04/07/20 04/07/20 01/16/20 01/13/20 155,15,16 400,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 04/07/20
- Reconstruction 0-016-022 / / / / 10/19/20 / / 155,16 0 0 JLB 0 0 0 0 / / / /
22-0319 Reconstruction 0-016-023 12/13/22 DONE DONE DONE 08/24/22 08/23/22 06/22/22 05/11/21 2,4,7,8,9,14,155,16 725,000 725,000 JLB 0 0 0 Burton Behrendt Smith 0 / / 08/23/22
22-1562 Reconstruction 0-016-024 05/18/23 DONE DONE DONE 01/27/23 01/24/23 10/13/22 05/15/18 2,4,8,9,155,15,16 400,000 400,000 JJH 0 0 0 Burton Behrendt Smith 0 / / 01/24/23
23-0792 Reconstruction 0-016-025 UNREVIEWED 10/25/23 10/20/23 05/25/23 05/16/23 2,7,155,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/20/23
23-1045 Reconstruction 0-016-026 UNREVIEWED 11/17/23 11/16/23 05/25/23 05/16/23 2,4,8,9,155,15,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/16/23
Youth Center (Village School):
21-1979 Reconstruction 0-017-011 09/20/22 DONE DONE DONE 06/15/22 06/15/22 10/19/20 05/16/17 2,4,8,9,10,14,155,15 838,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 06/15/22
South Senior High:
19-0204 Reconstruction 0-018-031 12/03/19 DONE DONE DONE 08/01/19 07/22/19 03/01/19 05/16/17 2,4,8,9,10,155,16 1,598,000 1,598,000 BMJ 0 0 0 Burton Behrendt Smith 0 03/03/21 07/22/19
- Reconstruction 0-018-032 / / / / 10/19/20 / / 155,15,16 0 0 JLB 0 0 0 0 / / / /
23-1101 Reconstruction 0-018-033 UNREVIEWED 12/04/23 11/17/23 05/25/23 05/11/21 2,9,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/17/23
South Middle School:
18-1433 Reconstruction 0-019-031 04/19/19 DONE DONE DONE 02/12/19 02/06/19 12/10/18 02/17/17 2,4,9,10,155,16 663,000 663,000 BMJ 0 0 0 Burton Behrendt Smith 0 07/24/20 02/06/19
19-0232 Reconstruction 0-019-032 12/09/19 DONE DONE DONE 08/08/19 07/29/19 03/01/19 05/16/17 2,4,9,10,155,16 1,177,400 1,177,400 BMJ 0 0 0 Burton Behrendt Smith 0 03/03/21 07/29/19
- Reconstruction 0-019-033 / / / / 10/19/20 / / 2,155,16 0 0 JLB 0 0 0 0 / / / /
22-0965 Reconstruction 0-019-034 04/03/23 DONE DONE DONE 11/14/22 11/10/22 07/26/22 06/30/20 2,4,8,9,10,155,15,16 660,000 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/10/22
23-1265 Reconstruction 0-019-035 UNREVIEWED 12/22/23 12/21/23 05/25/23 05/17/22 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 12/21/23
Administration Building:
20-0962 Reconstruction 1-001-010 01/25/22 DONE DONE DONE 12/11/20 12/03/20 10/19/20 05/16/17 8,155 1,855,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/03/20
22-1098 Reconstruction 1-001-011 12/22/22 DONE DONE DONE 11/29/22 11/28/22 08/25/22 05/17/22 155,16 1,343,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 11/28/22
North Field House:
- Reconstruction 7-026-023 / / / / 10/19/20 / / 7,9,16 0 0 JLB 0 0 0 0 / / / /
Grace Avenue Senior Center:
22-0312 Reconstruction 7-040-019 10/27/22 DONE DONE DONE 08/22/22 08/22/22 05/31/22 05/16/17 8 300,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 08/22/22
23-1093 Reconstruction 7-040-020 UNREVIEWED 12/04/23 11/22/23 05/25/23 05/16/23 2,15 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/22/23
South HS Press Box:
- PR New Construction 7-045-001 / / / / 06/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-2218 New Construction 7-045-001 08/01/23 DONE DONE DONE 05/17/23 10/19/22 06/15/22 05/17/22 02 - 16 540,000 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/19/22
North HS Press Box:
- PR New Construction 7-046-001 / / / / 06/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-2219 New Construction 7-046-001 08/01/23 DONE DONE DONE 05/17/23 10/19/22 06/15/22 05/17/22 02 - 16 0 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 10/19/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
NORTH SHORE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-01-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
North Shore Middle School:
19-0070PR Additions and Alterations 0-001-035 STARTED 07/15/19 / / 04/10/19 / / 02 - 16 0 16,298,670 JSS 0 0 0 0 / / / /
20-0661 Additions and Alterations 0-001-035 01/12/21 DONE DONE DONE 10/22/20 10/16/20 04/10/19 12/10/19 02 - 16 10,736,877 6,197,273 JLB 0 0 0 Memasi Design 0 01/16/23 10/16/20
- Reconstruction 0-001-036 / / / / 07/22/19 / / 2,15,16 0 0 BMJ 0 0 0 0 / / / /
20-0662 Reconstruction 0-001-037 01/12/21 DONE DONE DONE 10/22/20 10/16/20 02/03/20 06/09/20 155,16 822,330 822,330 JLB 0 0 0 Memasi Design 0 08/23/22 10/16/20
20-0663 Reconstruction 0-001-038 01/12/21 DONE DONE DONE 10/22/20 10/16/20 02/03/20 06/09/20 2,8,9,155,15,16 2,371,727 2,371,727 JLB 0 0 0 Memasi Design 0 08/23/22 10/16/20
20-1099 Reconstruction 0-001-039 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,155,16 1,975,549 1,975,549 JLB 0 0 0 MEMASI 1,975,549 / / 12/17/20
Glen Head Elementary School:
20-0664 Reconstruction 0-002-028 01/12/21 DONE DONE DONE 10/22/20 10/16/20 04/10/19 12/10/19 4,7,8,9,155,15,16 905,737 905,737 JLB 0 0 0 Memasi Design 0 08/23/22 10/16/20
- Reconstruction 0-002-029 / / / / 02/03/20 / / 2,8,9,155,15,16 0 0 BMJ 0 0 0 0 / / / /
20-1100 Reconstruction 0-002-030 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,155,16 960,535 0 JLB 0 0 0 MEMASI 963,535 / / 12/17/20
21-0338 Reconstruction 0-002-032 02/02/22 DONE DONE DONE 09/14/21 09/09/21 11/20/20 12/10/19 2,4,8,9,155,15,16 3,328,987 3,328,987 JLB 0 0 0 MEMASI 0 08/23/22 YES 09/09/21
Glenwood Landing School:
20-0665 Reconstruction 0-003-025 01/12/21 DONE DONE DONE 10/22/20 10/16/20 04/10/19 12/10/19 4,7,8,9,155,15,16 1,387,971 1,387,971 JLB 0 0 0 Memasi Design 0 08/23/22 10/16/20
20-1101 Reconstruction 0-003-026 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,155,16 427,302 0 JLB 0 0 0 MEMASI 427,302 / / 12/17/20
21-0339 Reconstruction 0-003-027 02/02/22 DONE DONE DONE 09/14/21 09/09/21 11/20/20 12/10/20 2,4,8,9,155,15,16 3,773,296 3,773,296 JLB 0 0 0 MEMASI 0 08/23/22 YES 09/09/21
North Shore High School:
- PR Additions and Alterations 0-004-036 / / / / 04/10/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-0666 Additions and Alterations 0-004-036 01/12/21 DONE DONE DONE 10/22/20 10/16/20 04/10/19 12/10/19 02 - 16 972,845 972,845 JLB 0 0 0 Memasi Design 0 08/23/22 10/16/20
- Reconstruction 0-004-037 / / / / 07/22/19 / / 2,15,16 0 0 BMJ 0 0 0 0 / / / /
20-1102 Reconstruction 0-004-038 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,155,16 3,586,877 0 JLB 0 0 0 MEMASI 3,586,877 / / 12/17/20
- PR Additions and Alterations 0-004-039 / / / / 11/20/20 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-0340 Additions and Alterations 0-004-039 02/02/22 DONE DONE DONE 09/14/21 09/09/21 11/20/20 12/10/20 02 - 16 15,098,620 12,780,545 JLB 0 0 0 MEMASI 0 08/23/22 YES 09/09/21
Sea Cliff Elementary School:
20-0667 Reconstruction 0-005-021 01/12/21 DONE DONE DONE 10/22/20 10/16/20 04/10/19 12/10/19 4,7,8,9,155,15,16 1,242,059 1,242,059 JLB 0 0 0 Memasi Design 0 08/23/22 10/16/20
20-1103 Reconstruction 0-005-022 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,155,16 162,062 162,062 JLB 0 0 0 MEMASI 162,062 / / 12/17/20
21-0341 Reconstruction 0-005-023 02/02/22 DONE DONE DONE 09/14/21 09/09/21 11/20/20 12/10/20 2,4,8,9,155,15,16 3,627,835 3,627,835 JLB 0 0 0 MEMASI 0 08/23/22 09/09/21
XXMaintenance Storage Demo:
- Reconstruction 0-006-001 / / / / 09/28/22 / / 7,8,9,155,15,16 0 0 JLB 0 0 0 0 / / / /
Victorian School House:
- Reconstruction 0-038-002 / / / / 04/10/19 / / 8,9,155,15,16 0 0 BMJ 0 0 0 0 / / / /
Administration Building:
- Reconstruction 1-009-006 / / / / 04/10/19 / / 8,9,155,15,16 0 0 BMJ 0 0 0 0 / / / /
20-1104 Reconstruction 1-009-007 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,155,16 27,274 0 JLB 0 0 0 MEMASI 27,274 / / 12/17/20
21-0342 Reconstruction 1-009-008 02/02/22 DONE DONE DONE 09/14/21 09/09/21 11/20/20 12/10/20 2,4,7,8,9,15 332,672 0 JLB 0 0 0 MEMASI 0 / / 09/09/21
Garage:
20-1105 Reconstruction 2-012-002 08/04/21 DONE DONE DONE 01/07/21 12/17/20 09/16/20 12/10/19 10,16 47,402 0 JLB 0 0 0 MEMASI 47,402 / / 12/17/20
Press Box:
21-0343 Reconstruction 2-013-001 02/02/22 DONE DONE DONE 09/14/21 09/09/21 04/28/21 12/10/20 4,7,8,9,16 112,136 0 JLB 0 0 0 MEMASI 0 / / 09/09/21
Glen Head Maint. Storage:
- PR New Construction 2-053-001 / / / / 07/02/21 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Glen Head Maintenance Storage:
- PR New Construction 2-055-001 / / / / 04/11/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0070 New Construction 2-055-001 12/05/22 DONE DONE DONE 07/11/22 07/11/22 04/11/22 12/01/22 02 - 16 755,027 0 JLB 0 0 0 MEMASI 0 06/20/23 07/11/22
Tent @ HS Cafeteria Courtyard:
20-1767TQ Temporary Quarters 8-051-001 05/25/21 DONE DONE DONE / / / / 04/19/21 / / 28,170 0 JLB 0 0 0 0 / / / /
Tent @ HS School House Courtyard:
20-1768TQ Temporary Quarters 8-052-001 05/25/21 DONE DONE DONE / / / / 04/19/21 / / 7,380 0 JLB 0 0 0 0 / / / /
Tent @ NSMS:
21-0393TQ Temporary Quarters 8-054-001 10/26/21 DONE DONE DONE 09/22/21 09/21/21 08/25/21 / / 0 0 JLB 0 0 0 0 / / 09/21/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SYOSSET CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-02-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
XXSouth Grove Elem.Annex-partOf0-011:
18-1735 Reconstruction 0-002-014 08/07/19 DONE DONE DONE 03/27/19 03/20/19 06/04/18 02/13/18 7,155,16 178,500 178,500 BMJ 0 0 0 H2M Group 0 12/02/20 03/20/19
18-1567 Reconstruction 0-002-015 04/12/19 DONE DONE DONE 02/27/19 02/20/19 06/04/18 03/13/18 2,8,9,155,15,16 95,200 95,200 BMJ 0 0 0 H2M Group 0 09/04/20 02/20/19
18-1761 Reconstruction 0-002-016 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 1,342,134 0 JSS 0 0 0 H2M Group 1,342,134 / / 03/22/19
Willits Elementary:
18-1736 Reconstruction 0-004-023 08/08/19 DONE DONE DONE 03/27/19 03/20/19 06/04/18 02/13/18 7,155,16 499,800 499,800 BMJ 0 0 0 H2M Group 0 01/05/21 03/20/19
18-1635 Reconstruction 0-004-024 04/17/19 DONE DONE DONE 03/14/19 03/08/19 06/04/18 02/13/18 2,8,9,155,15,16 285,600 285,600 BMJ 0 0 0 H2M Group 0 09/04/20 03/08/19
18-1762 Reconstruction 0-004-025 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 1,479,076 0 JSS 0 0 0 H2M Group 1,479,076 / / 03/22/19
- Reconstruction 0-004-026 / / / / 01/22/20 / / 2,8,9,16 0 0 JSS 0 0 0 0 / / / /
Berry Hill Elementary:
18-1066 Reconstruction 0-005-021 04/30/19 DONE DONE DONE 12/14/18 12/10/18 06/04/18 02/13/18 7,155,16 648,550 648,550 BMJ 0 0 0 H2M Group 0 12/02/20 12/10/18
18-1568 Reconstruction 0-005-022 04/12/19 DONE DONE DONE 02/27/19 02/20/19 06/04/18 02/13/18 2,8,9,155,15,16 238,000 238,000 BMJ 0 0 0 H2M Group 0 09/04/20 02/20/19
18-1763 Reconstruction 0-005-024 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/16/18 02/13/18 7,8,9,155,15,16 875,046 0 JSS 0 0 0 H2M Group 875,046 / / 03/22/19
South Woods Middle School:
18-1866 Reconstruction 0-006-025 09/04/19 DONE DONE DONE 04/16/19 04/11/19 06/04/18 02/13/18 7,155,16 400,000 400,000 SLC 0 0 0 H2M Group 0 05/17/21 04/11/19
18-1370 Reconstruction 0-006-026 05/09/19 DONE DONE DONE 01/31/19 01/29/19 06/04/18 02/13/18 2,8,9,155,15,16 571,200 571,200 BMJ 0 0 0 H2M Group 0 09/04/20 01/29/19
18-1764 Reconstruction 0-006-027 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 1,691,954 0 JSS 0 0 0 H2M Group 1,691,954 / / 03/22/19
19-1438 Reconstruction 0-006-028 03/26/20 DONE DONE DONE 02/19/20 02/10/20 01/31/19 05/21/19 2,4,7,9 885,360 885,360 BMJ 0 0 0 H2M Group 0 07/24/20 02/10/20
19-1176 Reconstruction 0-006-029 02/27/20 DONE DONE DONE 01/07/20 12/30/19 04/05/19 02/13/18 7,155,16 1,022,050 191,529 BMJ 0 0 0 H2M Group 0 / / 12/30/19
- XX Reconstruction 0-006-030 CANCELLED / / / / 01/22/20 / / 2,8,9,16 0 32,293,422 JSS 0 0 0 0 / / / /
20-0198 Reconstruction 0-006-031 12/11/20 DONE DONE DONE 08/13/20 08/03/20 05/08/20 06/17/20 15,16 375,000 375,000 JSS 0 0 0 H2M Group 0 10/10/22 08/03/20
- PR Additions and Alterations 0-006-032 / / / / 09/22/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
20-1271 Additions and Alterations 0-006-032 03/03/21 DONE DONE DONE 02/09/21 02/03/21 09/22/20 06/17/20 02 - 16 1,635,000 1,635,000 JSS 0 0 0 H2M Group 0 11/07/22 02/03/21
21-1331 Reconstruction 0-006-033 09/08/22 DONE DONE DONE 02/18/22 02/14/22 09/30/20 05/18/21 4 468,700 468,700 SLC 0 0 0 H2M Group 0 / / 02/14/22
21-0166 Reconstruction 0-006-034 11/12/21 DONE DONE DONE 08/12/21 08/03/21 03/23/21 06/16/20 7 654,000 654,000 SLC 0 0 0 H2M Group 0 10/05/22 08/03/21
23-1505 Reconstruction 0-006-035 UNREVIEWED 02/16/24 02/07/24 04/04/22 05/16/23 2 0 0 MSK 0 0 0 H2M Group 0 / / 02/07/24
22-0098 Reconstruction 0-006-036 10/28/22 DONE DONE DONE 07/15/22 07/14/22 04/29/22 05/17/22 4,8,9,16 523,854 523,854 SLC 0 0 0 H2M Group 0 06/06/23 07/14/22
- Reconstruction 0-006-037 / / / / 02/14/23 / / 2,4,8,9,155,15,16 0 0 SLC 0 0 0 0 / / / /
Village Elementary School:
18-1759 Reconstruction 0-009-023 08/08/19 DONE DONE DONE 03/29/19 03/20/19 06/04/18 02/13/18 7,155,16 714,000 714,000 BMJ 0 0 0 H2M Group 0 12/04/20 03/20/19
18-1636 Reconstruction 0-009-024 04/17/19 DONE DONE DONE 03/14/19 03/08/19 06/04/18 02/13/18 2,8,9,155,15,16 238,000 238,000 BMJ 0 0 0 H2M Group 0 08/30/19 03/08/19
18-1765 Reconstruction 0-009-025 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 1,390,899 0 JSS 0 0 0 H2M Group 1,390,899 / / 03/22/19
22-2127 Reconstruction 0-009-026 08/28/23 DONE DONE DONE 05/03/23 05/01/23 02/14/23 02/13/18 2,4,7 710,000 710,000 MSK 0 0 0 H2M Group 0 / / 05/01/23
Syosset High School:
18-1639 Reconstruction 0-010-047 09/04/19 DONE DONE DONE 03/14/19 03/13/19 06/04/18 02/13/18 7,155,16 3,425,350 3,425,350 SLC 0 0 0 H2M Group 0 04/19/21 03/13/19
18-1371 Reconstruction 0-010-048 05/13/19 DONE DONE DONE 01/31/19 01/29/19 06/04/18 02/13/18 2,8,9,155,15,16 1,142,400 1,142,400 BMJ 0 0 0 H2M Group 0 01/20/20 01/29/19
18-1026 Reconstruction 0-010-049 06/19/19 DONE DONE DONE 12/06/18 12/03/18 06/04/18 02/13/18 2,4,7,8,9,155,15,16 4,950,000 922,360 BMJ 0 0 0 H2M Group 0 09/18/20 12/03/18
18-1760 Reconstruction 0-010-051 05/23/19 DONE DONE DONE 03/29/19 03/22/19 06/19/18 05/15/18 9 217,000 0 BMJ 0 0 0 H2M Group 0 01/06/20 03/22/19
18-1766 Reconstruction 0-010-052 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 4,463,778 0 JSS 0 0 0 H2M Group 4,463,778 / / 03/22/19
18-1576 Additions and Alterations 0-010-053 04/18/19 DONE DONE DONE 02/28/19 02/25/19 10/26/18 02/13/18 02 - 16 1,594,600 337,800 BMJ 0 0 0 H2M Group 0 08/30/20 02/25/19
18-1796 Reconstruction 0-010-054 05/30/19 DONE DONE DONE 04/04/19 03/27/19 01/31/19 05/21/19 2,9 157,080 157,080 BMJ 0 0 0 H2M Group 0 06/15/20 03/27/19
- XX Reconstruction 0-010-056 CANCELLED / / / / 10/08/19 / / 2,8 0 0 JSS 0 0 0 0 / / / /
19-1860 Reconstruction 0-010-057 07/20/20 DONE DONE DONE 06/18/20 06/10/20 04/09/20 06/09/20 2 320,000 0 JSS 0 0 0 H2M Group 0 09/22/20 06/10/20
- PR Additions and Alterations 0-010-058 / / / / 09/22/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
20-0946 Additions and Alterations 0-010-058 01/05/21 DONE DONE DONE 12/10/20 12/08/20 09/22/20 06/17/20 02 - 16 2,000,000 2,000,000 JSS 0 0 0 H2M Group 0 11/07/22 12/08/20
20-1699 Reconstruction 0-010-059 07/16/21 DONE DONE DONE 05/11/21 05/10/21 04/14/21 06/16/20 7 654,000 654,000 SLC 0 0 0 H2M Group 0 08/19/22 05/10/21
21-1332 Reconstruction 0-010-060 09/08/22 DONE DONE DONE 02/18/22 02/14/22 09/17/21 06/16/20 2,155 773,900 773,900 SLC 0 0 0 H2M Group 0 / / 02/14/22
21-1742 Reconstruction 0-010-061 08/01/22 DONE DONE DONE 05/02/22 04/28/22 09/23/21 05/17/22 16 708,500 0 SLC 0 0 0 H2M Group 0 / / 04/28/22
21-1817 Reconstruction 0-010-062 09/08/22 DONE DONE DONE 05/16/22 05/12/22 01/19/22 06/16/20 4,7 218,000 218,000 SLC 0 0 0 H2M Group 0 09/07/23 05/12/22
21-1853 Reconstruction 0-010-063 08/01/22 DONE DONE DONE 05/20/22 05/20/22 04/04/22 05/17/22 2 545,000 0 SLC 0 0 0 H2M Group 0 12/06/23 05/20/22
21-1854 Reconstruction 0-010-064 08/01/22 DONE DONE DONE 05/20/22 05/20/22 04/25/22 05/17/22 2,13 436,000 0 SLC 0 0 0 H2M Group 0 05/20/22 05/20/22
22-2128 Reconstruction 0-010-065 07/18/23 DONE DONE DONE 05/03/23 05/01/23 10/13/22 02/13/18 8,9,155,16 213,000 213,000 MSK 0 0 0 H2M Group 0 08/25/23 05/01/23
22-2303 Reconstruction 0-010-066 12/19/23 DONE DONE DONE 05/31/23 05/30/23 04/14/23 05/16/23 4,7,155,15,16 772,125 772,125 MSK 0 0 0 H2M Group 0 / / 05/30/23
23-1180 Reconstruction 0-010-067 UNREVIEWED 12/14/23 12/08/23 05/18/23 05/16/23 2,4,7,8,9,155,16 0 0 MSK 0 0 0 H2M Group 0 / / 12/08/23
- Reconstruction 0-010-068 / / / / 05/18/23 / / 4,7,8,9,155,15,16 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-010-069 / / / / 07/06/23 / / 2 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-010-070 / / / / 01/26/24 / / 16 0 0 MSK 0 0 0 0 / / / /
South Grove Elementary:
18-1067 Reconstruction 0-011-019 04/30/19 DONE DONE DONE 12/14/18 12/10/18 06/04/18 02/13/18 7,155,16 571,200 571,200 BMJ 0 0 0 H2M Group 0 11/04/20 12/10/18
18-1569 Reconstruction 0-011-020 04/12/19 DONE DONE DONE 02/27/19 02/20/19 06/04/18 02/13/18 2,8,9,155,15,16 238,000 238,000 BMJ 0 0 0 H2M Group 0 09/04/20 02/20/19
18-1767 Reconstruction 0-011-021 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 641,217 0 JSS 0 0 0 H2M Group 641,217 / / 03/22/19
18-1797 Reconstruction 0-011-022 05/30/19 DONE DONE DONE 04/05/19 03/27/19 01/31/19 05/21/19 2,9,16 47,600 47,600 BMJ 0 0 0 H2M Group 0 01/03/20 03/27/19
19-1665 Reconstruction 0-011-023 07/17/19 DONE DONE DONE 04/09/20 02/26/20 07/23/19 05/13/19 4 230,338 230,338 JSS 0 0 0 H2M Group 0 12/26/19 02/26/20
23-0203 Reconstruction 0-011-024 01/10/24 DONE DONE DONE 08/04/23 08/02/23 02/14/23 05/16/23 2,4,7 1,368,137 1,368,137 MSK 0 0 0 H2M Group 0 / / 08/02/23
23-1478 Reconstruction 0-011-025 UNREVIEWED 02/06/24 02/06/24 10/12/23 11/06/23 155 0 0 MSK 0 0 0 H2M Group 0 / / 02/06/24
JI Baylis Elementary:
18-1068 Reconstruction 0-012-024 04/30/19 DONE DONE DONE 12/14/18 12/10/18 06/04/18 02/13/18 7,155,16 648,550 648,550 BMJ 0 0 0 H2M Group 0 12/02/20 12/10/18
18-1570 Reconstruction 0-012-025 04/12/19 DONE DONE DONE 02/27/19 02/20/19 06/04/18 02/13/18 2,8,9,155,15,16 428,400 428,400 BMJ 0 0 0 H2M Group 0 09/04/20 02/20/19
18-1768 Reconstruction 0-012-027 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/16/18 02/13/18 7,8,9,155,15,16 2,305,535 0 JSS 0 0 0 H2M Group 2,305,535 / / 03/22/19
Walt Whitman Elementary:
18-1732 Reconstruction 0-013-020 08/08/19 DONE DONE DONE 03/27/19 03/20/19 06/04/18 02/13/18 7,155,16 487,900 487,900 BMJ 0 0 0 H2M Group 0 11/23/20 03/20/19
18-1637 Reconstruction 0-013-021 04/17/19 DONE DONE DONE 03/14/19 03/08/19 06/04/18 02/13/18 2,8,9,155,15,16 214,200 214,200 BMJ 0 0 0 H2M Group 0 08/30/19 03/08/19
18-1769 Reconstruction 0-013-023 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 1,164,153 0 JSS 0 0 0 H2M Group 1,164,153 / / 03/22/19
18-1794 Reconstruction 0-013-024 05/30/19 DONE DONE DONE 04/04/19 03/29/19 01/31/19 05/21/19 2,7,9,16 35,700 35,700 BMJ 0 0 0 H2M Group 0 01/03/20 03/29/19
Robbins Lane Elementary:
18-1069 Reconstruction 0-015-020 04/30/19 DONE DONE DONE 12/14/18 12/10/18 06/04/18 02/13/18 7,155,16 606,900 606,900 BMJ 0 0 0 H2M Group 0 12/04/20 12/10/18
18-1638 Reconstruction 0-015-021 04/17/19 DONE DONE DONE 03/14/19 03/08/19 06/04/18 02/13/18 2,8,9,155,15,16 428,400 428,400 BMJ 0 0 0 H2M Group 0 08/30/19 03/08/19
18-1770 Reconstruction 0-015-022 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/16/18 02/13/18 7,8,9,155,15,16 3,091,577 0 JSS 0 0 0 H2M Group 3,091,577 / / 03/22/19
19-0372 Reconstruction 0-015-023 11/06/19 DONE DONE DONE 09/04/19 07/08/19 11/21/18 02/13/18 15,16 714,000 0 JSS 0 0 0 H2M Group 0 / / 07/08/19
Thompson Middle School:
19-1175 Reconstruction 0-016-027 02/27/20 DONE DONE DONE 01/07/20 12/30/19 06/04/18 02/13/18 7,155,16 1,874,250 0 BMJ 0 0 0 H2M Group 0 / / 12/30/19
18-1372 Reconstruction 0-016-028 05/13/19 DONE DONE DONE 01/31/19 01/29/19 06/04/18 02/13/18 2,8,9,155,15,16 892,500 892,500 BMJ 0 0 0 H2M Group 0 09/04/20 01/29/19
18-1771 Reconstruction 0-016-029 05/18/20 DONE DONE DONE 03/29/19 03/22/19 08/17/18 02/13/18 7,8,9,155,15,16 1,543,879 0 JSS 0 0 0 H2M Group 1,543,879 / / 03/22/19
19-0373 Reconstruction 0-016-030 ADDENDUM REQ'D 09/04/19 07/08/19 01/31/19 05/21/19 2,155,16 0 34,997,985 JSS 0 0 0 H2M Group 0 / / 07/08/19
- PR Additions and Alterations 0-016-031 / / / / 09/22/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
20-1024 Additions and Alterations 0-016-031 01/08/21 DONE DONE DONE 12/22/20 12/21/20 09/22/20 06/17/20 02 - 16 1,900,000 1,900,000 JSS 0 0 0 H2M Group 0 / / 12/21/20
22-2304 Reconstruction 0-016-032 09/28/23 DONE DONE DONE 05/31/23 05/30/23 04/14/23 05/16/23 7,155,15,16 820,050 820,050 JLB 0 0 0 H2M Group 0 / / 05/30/23
23-0699 Reconstruction 0-016-033 DONE STARTED UNREVIEWED10/13/23 10/06/23 04/14/23 05/16/23 2,8,9,16 804,927 0 MSK 0 0 0 H2M Group 0 / / 10/06/23
HS Testing Center:
23-1610 New Construction 0-082-001 UNREVIEWED 03/12/24 02/06/24 08/07/23 05/16/23 02 - 16 0 0 MSK 0 0 0 H2M Group 0 / / 02/06/24
Container-Baylis-1:
- DB Discovered Building 2-044-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-Berry Hill-1:
- DB Discovered Building 2-045-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-HBT-1:
- DB Discovered Building 2-046-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-HBT-2:
- DB Discovered Building 2-047-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-HBT-3:
- DB Discovered Building 2-048-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Shed-HBT Shed-1:
- DB Discovered Building 2-049-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Shed-Village Shed:
- DB Discovered Building 2-050-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-South Grove-1:
- DB Discovered Building 2-051-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-1:
- DB Discovered Building 2-052-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
container-High School-2:
- DB Discovered Building 2-053-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-3:
- DB Discovered Building 2-054-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-4:
- DB Discovered Building 2-055-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-5:
- DB Discovered Building 2-056-001 / / / / 04/28/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-6:
- DB Discovered Building 2-057-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-7:
- DB Discovered Building 2-058-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High SChool-8:
- DB Discovered Building 2-059-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-9:
- DB Discovered Building 2-060-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-10:
- DB Discovered Building 2-061-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-11:
- DB Discovered Building 2-062-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-12:
- DB Discovered Building 2-063-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-13:
- DB Discovered Building 2-064-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-14:
- DB Discovered Building 2-065-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-15:
- DB Discovered Building 2-066-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-16:
- DB Discovered Building 2-067-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-17:
- DB Discovered Building 2-068-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High SChool-18:
- DB Discovered Building 2-069-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High SChool-19:
- DB Discovered Building 2-070-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-20:
- DB Discovered Building 2-071-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-21:
- DB Discovered Building 2-072-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-22:
- DB Discovered Building 2-073-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-23:
- DB Discovered Building 2-074-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-24:
- DB Discovered Building 2-075-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High SChool-25:
- DB Discovered Building 2-076-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-High School-26:
- DB Discovered Building 2-077-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Shed-High School Softball Shed-1:
22-0975DB Discovered Building 2-078-001 UNREVIEWED
ADD. REQ'D DONE 11/14/22 11/14/22 04/30/20 / / 0 0 SLC 0 0 0 0 / / 11/14/22
Container-Hill Top-12:
- DB Discovered Building 2-079-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Container-Hill Top-13:
- DB Discovered Building 2-080-001 / / / / 04/30/20 / / 0 0 JSS 0 0 0 0 / / / /
Maintenance Garage - 3-003 onFSPortl:
21-0326 Reconstruction 3-001-001 02/08/22 DONE DONE DONE 09/13/21 09/10/21 09/30/20 06/16/20 155 220,000 0 SLC 0 0 0 H2M Group 0 / / 09/10/21
Public Library:
19-1147 Reconstruction 6-036-009 04/27/20 DONE DONE DONE 01/03/20 12/13/19 07/09/19 10/15/19 2,8,155,16 913,802 0 JSS 0 0 0 SMITH & PUCILLO ARCHITECTS 0 08/11/22 12/13/19
Security Guard Booth @ Syosset HS:
18-1871 New Construction 7-043-001 07/11/19 DONE DONE DONE 04/16/19 04/03/19 01/11/19 02/13/18 02 - 16 54,500 0 BMJ 0 0 0 H2M Group 0 04/28/21 04/03/19
District-Wide:
- Reconstruction 7-999-006 / / / / 08/25/20 / / 16 0 0 JSS 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 JSS 0 0 0 0 / / / /
(DEMO)T 6 Relocatable High School:
23-0981 Reconstruction 8-014-001 UNREVIEWED 11/14/23 11/07/23 08/07/23 05/16/23 2,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/07/23
XXSyosset HS (Leased)-cancelled:
- XX Reconstruction 8-081-001 CANCELLED / / / / 11/09/20 / / 0 0 JSS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LOCUST VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-03-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bayville Intermediate School:
21-1543 Reconstruction 0-002-017 08/25/22 DONE DONE DONE 03/21/22 03/21/22 10/19/21 05/18/21 9,155,16 205,000 205,000 SLC 0 0 0 Campbell Cassetta Architects 0 11/14/22 03/21/22
23-0002 Reconstruction 0-002-018 12/12/23 DONE DONE DONE 07/03/23 07/03/23 03/20/23 05/16/23 2,9,10,13 382,000 382,000 JLB 0 0 0 Campbell Cassetta Architects 0 / / 07/03/23
Locust Valley Intermediate:
19-1504 Reconstruction 0-003-019 05/08/20 DONE DONE DONE 03/02/20 02/26/20 02/07/19 05/21/19 7 400,000 400,000 SLC 0 0 0 Campbell Cassetta Architects 0 09/22/20 02/26/20
21-1694 Reconstruction 0-003-020 10/28/22 DONE DONE DONE 04/25/22 04/18/22 10/19/21 05/18/21 8,9,13,155,15,16 350,000 350,000 SLC 0 0 0 Campbell Cassetta Architects 0 07/19/23 04/18/22
23-0004 Reconstruction 0-003-021 11/28/23 DONE DONE DONE 07/03/23 07/03/23 03/20/23 05/16/23 2,9,10,16 370,000 370,000 JLB 0 0 0 Campbell Cassetta Architects 0 / / 07/03/23
Bayville Primary:
- PR Additions and Alterations 0-009-012 / / / / 07/09/20 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
20-1117 Additions and Alterations 0-009-012 04/27/21 DONE DONE DONE 01/08/21 12/29/20 07/09/20 06/16/20 02 - 16 462,000 370,120 SLC 0 0 0 Campbell Cassetta Architects 0 05/06/22 12/29/20
21-1510 Reconstruction 0-009-013 08/25/22 DONE DONE DONE 03/15/22 03/14/22 10/20/21 05/18/21 155 175,000 175,000 SLC 0 0 0 Campbell Cassetta Architects 0 11/28/23 03/14/22
Ann M MacArthur School:
19-1501 Reconstruction 0-010-019 05/08/20 DONE DONE DONE 02/28/20 02/25/20 02/07/19 05/21/19 9 150,000 150,000 SLC 0 0 0 Campbell Cassetta Architects 0 08/11/20 02/25/20
21-1511 Reconstruction 0-010-020 08/25/22 DONE DONE DONE 03/15/22 03/14/22 10/19/21 05/18/21 155 175,000 175,000 SLC 0 0 0 Campbell Cassetta Architects 0 11/28/23 03/14/22
23-0005 Reconstruction 0-010-021 11/27/23 DONE DONE DONE 07/05/23 07/03/23 03/20/23 05/16/23 2,9,10,16 460,000 460,000 JLB 0 0 0 Campbell Cassetta Architects 0 / / 07/03/23
Middle/High School:
19-0848 Reconstruction 0-012-046 04/20/21 DONE DONE DONE 11/21/19 08/01/19 12/06/18 05/15/18 7 2,606,540 2,606,540 SLC 0 0 0 Campbell Cassetta Architects 0 05/11/22 08/01/19
19-0792 Reconstruction 0-012-047 05/13/20 DONE DONE DONE 11/14/19 08/01/19 12/06/18 05/21/19 8,9,155,15,16 275,000 0 BMJ 0 0 0 H2M Group 0 / / 08/01/19
18-1904 Reconstruction 0-012-048 05/23/19 DONE DONE DONE 04/25/19 04/23/19 02/07/19 05/21/19 9 635,000 635,000 BMJ 0 0 0 Campbell Cassetta Architects 0 10/15/19 04/23/19
19-0793 Reconstruction 0-012-049 11/08/21 DONE DONE DONE 08/01/19 08/01/19 04/17/19 05/21/19 16 639,000 0 BMJ 0 0 0 Campbell Cassetta Architects 0 / / 08/01/19
- XX Reconstruction 0-012-050 CANCELLED / / / / 04/17/19 / / 155 0 43,972,880 BMJ 0 0 0 0 / / / /
19-0849 Reconstruction 0-012-051 05/06/20 DONE DONE DONE 11/21/19 08/01/19 04/17/19 05/21/19 8 1,199,000 0 BMJ 0 0 0 Campbell Cassetta Architects 0 / / 08/01/19
19-1539 Reconstruction 0-012-052 06/03/20 DONE DONE DONE 03/05/20 02/28/20 07/02/19 05/21/19 2,4,7,10,155,15,16 1,000,000 1,000,000 SLC 0 0 0 Campbell Cassetta Architects 0 / / 02/28/20
20-1794 Reconstruction 0-012-053 07/27/21 DONE DONE DONE 05/28/21 05/27/21 01/24/20 05/18/21 2,9,10 2,705,000 2,705,000 SLC 0 0 0 Campbell Cassetta Architects 0 06/24/22 05/27/21
22-0807 Reconstruction 0-012-054 01/04/23 DONE DONE DONE 10/24/22 10/24/22 05/18/22 05/17/22 2,10,13,16 2,355,000 0 SLC 0 0 0 Campbell Cassetta Architects 0 / / 10/24/22
23-1390 Reconstruction 0-012-055 UNREVIEWED 01/17/24 01/17/24 07/19/23 05/16/23 7,155,16 0 0 MSK 0 0 0 Campbell Cassetta Architects 0 / / 01/17/24
23-1344 Reconstruction 0-012-056 UNREVIEWED 01/12/24 01/11/24 07/19/23 05/16/23 4,8,9,10,155,15,16 0 0 MSK 0 0 0 Campbell Cassetta Architects 0 / / 01/11/24
MS/HS FldStorageShed-ToBeDemo'd:
22-1351 Reconstruction 2-044-001 01/03/23 DONE DONE DONE 12/28/22 12/20/22 / / 05/17/22 20,000 0 JLB 0 0 0 Campbell Cassetta Architects 0 / / 12/20/22
MSHS Field Stor Cont 1:
- PR New Construction 2-046-001 / / / / 01/12/23 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
MSHS Field Stor Mant 3:
- PR New Construction 2-047-001 / / / / 01/12/23 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
HSHS Field Stor Cont 2:
- PR New Construction 2-048-001 / / / / 01/12/23 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
MSHS Field Stor Cont 4:
- PR New Construction 2-049-001 / / / / 01/12/23 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
MSHS Field Stor Container 5:
- PR New Construction 2-050-001 / / / / 02/08/23 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
MSHS Field Stor Container 6:
- PR New Construction 2-051-001 / / / / 02/08/23 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
HS/MS Field Press Box:
22-1352PR New Construction 7-045-001 01/11/23 DONE DONE DONE 12/28/22 12/20/22 11/18/22 05/17/22 02 - 16 125,000 0 JLB 0 0 0 Campbell Cassetta Architects 0 / / 12/20/22
District Wide:
- Reconstruction 7-999-003 / / / / 07/09/20 / / 16 0 0 SLC 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 8,10,16 0 0 SLC 0 0 0 0 / / / /
- Reconstruction 7-999-BA2 DONE / / / / 04/18/22 / / 16 0 0 SLC 0 0 0 0 / / / /
XXTent #1 @AnnMacArthurPrimarySch:
20-0292TQ Temporary Quarters 8-030-001 11/03/20 DONE DONE DONE 09/01/20 08/31/20 08/14/20 08/12/20 20,025 0 SLC 0 0 0 Campbell Cassetta Architects 0 09/15/20 08/31/20
XXTent #2 @ Bayville Interm Sch:
20-0291TQ Temporary Quarters 8-031-001 11/03/20 DONE DONE DONE 09/01/20 08/31/20 08/14/20 08/12/20 20,025 0 SLC 0 0 0 Campbell Cassetta Architects 0 09/15/20 08/31/20
XXTent #3 @Bayville Primary Sch:
20-0290TQ Temporary Quarters 8-032-001 11/03/20 DONE DONE DONE 09/01/20 08/31/20 08/14/20 08/12/20 20,025 0 SLC 0 0 0 Campbell Cassetta Architects 0 09/15/20 08/31/20
XXTent 4 @ Locust Valley Interm Sch:
20-0289TQ Temporary Quarters 8-033-001 11/03/20 DONE DONE DONE 09/01/20 08/31/20 08/14/20 08/12/20 20,025 0 SLC 0 0 0 Campbell Cassetta Architects 0 09/15/20 08/31/20
XXTent #5 @ Locust Valley MS/HS Nort:
20-0288TQ Temporary Quarters 8-034-001 11/03/20 DONE DONE DONE 09/01/20 08/31/20 08/14/20 08/12/20 20,025 0 SLC 0 0 0 Campbell Cassetta Architects 0 09/15/20 08/31/20
XXTent #6 @ Locust Valley MS/HS Sout:
20-0287TQ Temporary Quarters 8-035-001 11/03/20 DONE DONE DONE 09/01/20 08/31/20 08/14/20 08/12/20 20,035 0 SLC 0 0 0 Campbell Cassetta Architects 0 09/15/20 08/31/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PLAINVIEW-OLD BETHPAGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-04-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Old Bethpage Elementary:
19-0191 Reconstruction 0-002-033 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 365,000 365,000 JSS 0 0 0 Burton Behrendt Smith 0 04/30/21 07/03/19
20-0470 Reconstruction 0-002-034 02/09/21 DONE DONE DONE 09/29/20 09/21/20 10/08/19 05/21/19 2,9,15,16 325,000 325,000 JSS 0 0 0 Burton Behrendt Smith 0 06/16/23 09/21/20
20-0531 Reconstruction 0-002-035 02/04/21 DONE DONE DONE 10/06/20 09/28/20 10/15/19 05/21/19 2,9,16 250,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 09/28/20
21-1370 Reconstruction 0-002-036 06/14/22 DONE DONE DONE 02/24/22 02/22/22 10/12/21 05/18/21 7,16 69,225 69,225 SLC 0 0 0 H2M Group 0 12/15/22 02/22/22
- Reconstruction 0-002-037 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
23-1110 Reconstruction 0-002-038 UNREVIEWED 12/05/23 11/27/23 10/11/23 05/16/23 9,10,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/27/23
Jamaica ES(2015 daycare-rental):
21-1371 Reconstruction 0-004-023 06/14/22 DONE DONE DONE 02/24/22 02/22/22 10/12/21 05/18/21 155,15,16 426,000 0 SLC 0 0 0 H2M Group 0 03/28/23 02/22/22
- Reconstruction 0-004-024 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
ParkwayElementary:
18-1342 Reconstruction 0-008-034 04/02/19 DONE DONE DONE 01/28/19 01/18/19 03/23/18 05/15/18 7 600,000 600,000 BMJ 0 0 0 Burton Behrendt Smith 0 11/21/19 01/18/19
19-0192 Reconstruction 0-008-035 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 309,000 309,000 JSS 0 0 0 Burton Behrendt Smith 0 04/30/21 07/03/19
20-0471 Reconstruction 0-008-036 02/09/21 DONE DONE DONE 09/29/20 09/21/20 10/08/19 05/21/19 2,9,15,16 325,000 325,000 JSS 0 0 0 Burton Behrendt Smith 0 06/16/23 09/21/20
20-0532 Reconstruction 0-008-037 02/04/21 DONE DONE DONE 10/06/20 09/28/20 10/15/19 05/21/19 2,9,16 250,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 09/28/20
21-1372 Reconstruction 0-008-038 06/14/22 DONE DONE DONE 02/24/22 02/22/22 10/12/21 05/18/21 155,15,16 479,250 479,250 SLC 0 0 0 H2M Group 0 / / 02/22/22
- Reconstruction 0-008-039 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
23-1111 Reconstruction 0-008-040 UNREVIEWED 12/05/23 11/27/23 10/11/23 05/16/23 9,10,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/27/23
Stratford Road School:
18-2094 Reconstruction 0-011-035 10/07/19 DONE DONE DONE 06/10/19 05/22/19 03/23/18 05/15/18 7,155,16 725,000 725,000 BMJ 0 0 0 Burton Behrendt Smith 0 10/01/20 05/22/19
19-0193 Reconstruction 0-011-036 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 164,000 164,000 JSS 0 0 0 Burton Behrendt Smith 0 12/09/21 07/03/19
20-0473 Reconstruction 0-011-037 02/09/21 DONE DONE DONE 09/29/20 09/23/20 10/08/19 06/09/20 2,9,15,16 325,000 325,000 JSS 0 0 0 Burton Behrendt Smith 0 10/04/23 09/23/20
20-0503 Reconstruction 0-011-038 02/16/21 DONE DONE DONE 10/01/20 09/28/20 10/15/19 06/09/20 2,9,16 250,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 09/28/20
21-0511 Reconstruction 0-011-039 03/14/22 DONE DONE DONE 10/13/21 10/12/21 04/16/21 06/09/20 16 372,750 372,750 SLC 0 0 0 H2M Group 0 / / 10/12/21
22-1790 Reconstruction 0-011-040 08/24/23 DONE DONE DONE 03/06/23 03/06/23 10/20/22 05/17/22 2,9,10,155,15,16 840,007 840,007 MSK 0 0 0 H2M Group 0 / / 03/06/23
- Reconstruction 0-011-041 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
Plainview Old Bethpage Middle Sch.:
19-0194 Reconstruction 0-012-047 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 164,000 164,000 JSS 0 0 0 Burton Behrendt Smith 0 04/30/21 07/03/19
19-0353 Reconstruction 0-012-048 01/24/20 DONE DONE DONE 09/03/19 08/27/19 07/12/19 12/09/14 16 435,000 435,000 JSS 0 0 0 Burton Behrendt Smith 0 05/19/21 08/27/19
19-0914 Reconstruction 0-012-049 05/04/20 DONE DONE DONE 12/03/19 11/12/19 08/29/19 12/09/14 9 194,000 194,000 JSS 0 0 0 Burton Behrendt Smith 0 09/08/20 11/12/19
20-0504 Reconstruction 0-012-050 02/16/21 DONE DONE DONE 10/01/20 09/28/20 09/03/19 05/21/19 16 400,000 400,000 JSS 0 0 0 Burton Behrendt Smith 0 01/05/24 09/28/20
21-0753 Reconstruction 0-012-051 03/16/22 DONE DONE DONE 11/19/21 11/18/21 04/16/21 06/09/20 2,9,155,16 1,487,500 1,487,500 SLC 0 0 0 H2M Group 0 10/23/22 11/18/21
21-0512 Reconstruction 0-012-052 03/14/22 DONE DONE DONE 10/13/21 10/12/21 04/16/21 06/09/20 16 399,375 399,375 SLC 0 0 0 H2M Group 0 / / 10/12/21
22-1935 Reconstruction 0-012-053 10/18/23 DONE DONE DONE 03/24/23 03/24/23 10/20/22 05/17/22 2,8,9,10,155,15,16 997,515 997,515 MSK 0 0 0 H2M Group 0 / / 03/24/23
22-1759 Reconstruction 0-012-054 08/24/23 DONE DONE DONE 02/27/23 02/27/23 10/20/22 05/17/22 2,8,9,155,16 709,223 709,223 MSK 0 0 0 H2M Group 0 / / 02/27/23
- Reconstruction 0-012-055 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
23-1112 Reconstruction 0-012-056 UNREVIEWED 12/05/23 11/27/23 10/11/23 05/16/23 9,10,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/27/23
Mattlin Middle School:
18-2095 Reconstruction 0-014-044 10/07/19 DONE DONE DONE 06/10/19 05/22/19 03/23/18 05/15/18 7,155,16 545,000 545,000 BMJ 0 0 0 Burton Behrendt Smith 0 10/01/20 05/22/19
19-0195 Reconstruction 0-014-045 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 240,000 240,000 JSS 0 0 0 Burton Behrendt Smith 0 10/24/23 07/03/19
19-0354 Reconstruction 0-014-046 01/24/20 DONE DONE DONE 09/03/19 08/27/19 07/12/19 12/09/14 16 175,000 175,000 JSS 0 0 0 Burton Behrendt Smith 0 05/19/21 08/27/19
20-0506 Reconstruction 0-014-047 04/08/21 DONE DONE DONE 10/01/20 09/29/20 10/08/19 05/21/19 2,9,15,16 325,000 325,000 JSS 0 0 0 Burton Behrendt Smith 0 / / 09/29/20
20-0505 Reconstruction 0-014-048 02/16/21 DONE DONE DONE 10/01/20 09/28/20 10/15/19 05/21/19 2,9,16 250,000 250,000 JSS 0 0 0 Burton Behrendt Smith 0 01/05/24 09/28/20
22-0059 Reconstruction 0-014-049 12/19/22 DONE DONE DONE 07/11/22 07/07/22 10/12/21 05/18/21 15 127,800 127,800 SLC 0 0 0 H2M Group 0 07/26/23 07/07/22
- Reconstruction 0-014-050 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
23-1113 Reconstruction 0-014-051 UNREVIEWED 12/05/23 11/27/23 10/11/23 05/16/23 9,10,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/27/23
John F. Kennedy High School:
19-0196 Reconstruction 0-015-058 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 95,000 95,000 JSS 0 0 0 Burton Behrendt Smith 0 12/09/21 07/03/19
19-0355 Reconstruction 0-015-059 01/24/20 DONE DONE DONE 09/03/19 08/27/19 07/12/19 12/09/14 16 185,000 185,000 JSS 0 0 0 Burton Behrendt Smith 0 05/19/21 08/27/19
20-1840 Reconstruction 0-015-060 11/16/21 DONE DONE DONE 06/04/21 06/02/21 10/08/19 05/19/15 2,9,15,16 400,000 400,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 06/02/21
21-1016 Reconstruction 0-015-061 08/30/22 DONE DONE DONE 01/03/22 12/30/21 10/15/19 05/16/17 2,4,7,9,155,15,16 347,000 347,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 12/30/21
20-0726 Reconstruction 0-015-062 01/22/21 DONE DONE DONE 10/29/20 10/29/20 10/15/19 05/17/16 2,4,7,8,9,10,155,15, 780,000 780,000 JSS 0 0 0 Burton Behrendt Smith 0 03/01/23 10/29/20
21-0513 Reconstruction 0-015-063 03/14/22 DONE DONE DONE 10/13/21 10/12/21 04/16/21 06/09/20 16 399,375 399,375 SLC 0 0 0 H2M Group 0 / / 10/12/21
22-0060 Reconstruction 0-015-064 12/19/22 DONE DONE DONE 07/11/22 07/07/22 10/12/21 05/18/21 9 266,250 266,250 SLC 0 0 0 H2M Group 0 / / 07/07/22
22-1831 Reconstruction 0-015-065 10/16/23 DONE DONE DONE 03/15/23 03/13/23 10/20/22 05/17/22 2,7,8,9,10,155,15,16 2,283,377 2,283,377 MSK 0 0 0 H2M Group 0 / / 03/13/23
23-0408 Reconstruction 0-015-066 ADDENDUM REQ'D 09/06/23 09/01/23 05/18/23 08/14/23 155,16 1,000,000 0 MSK 0 0 0 H2M Group 0 / / 09/01/23
- Reconstruction 0-015-067 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
23-1114 Reconstruction 0-015-068 UNREVIEWED 12/05/23 11/27/23 10/11/23 05/16/23 9,10,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/27/23
- Reconstruction 0-015-069 / / / / 11/07/23 / / 4,9 0 0 MSK 0 0 0 0 / / / /
Pasadena Elementary School:
18-1343 Reconstruction 0-021-023 04/02/19 DONE DONE DONE 01/28/19 01/18/19 03/23/18 05/15/18 7 600,000 600,000 BMJ 0 0 0 Burton Behrendt Smith 0 11/21/19 01/18/19
19-0197 Reconstruction 0-021-024 11/05/19 DONE DONE DONE 07/30/19 07/03/19 03/21/19 05/15/18 2,4,8,9,155,16 309,000 309,000 JSS 0 0 0 Burton Behrendt Smith 0 03/09/22 07/03/19
- PR Additions and Alterations 0-021-025 / / / / 06/25/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
20-0476XX Additions and Alterations 0-021-025 04/22/21 CANCELLED 09/29/20 09/18/20 06/25/19 05/21/19 02 - 16 2,786,568 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 09/18/20
19-0356 Reconstruction 0-021-026 01/24/20 DONE DONE DONE 09/03/19 08/27/19 07/12/19 12/09/14 16 135,000 135,000 JSS 0 0 0 Burton Behrendt Smith 0 05/19/21 08/27/19
20-0472 Reconstruction 0-021-027 02/09/21 DONE DONE DONE 09/29/20 09/21/20 10/08/19 05/21/19 2,9,15,16 325,000 325,000 JSS 0 0 0 Burton Behrendt Smith 0 06/16/23 09/21/20
20-0533 Reconstruction 0-021-028 02/04/21 DONE DONE DONE 10/06/20 09/28/20 10/15/19 05/21/19 2,9,16 250,000 0 JSS 0 0 0 Burton Behrendt Smith 0 / / 09/28/20
21-1373 Reconstruction 0-021-029 06/15/22 DONE DONE DONE 02/24/22 02/22/22 10/12/21 05/18/21 155,15,16 191,700 191,700 SLC 0 0 0 H2M Group 0 / / 02/22/22
22-0781 Reconstruction 0-021-030 05/31/23 DONE DONE DONE 10/21/22 10/19/22 03/30/22 05/21/19 2,4,7,8,9,10,155,15, 2,716,347 0 MSK 0 0 0 H2M Group 0 / / 10/19/22
- Reconstruction 0-021-031 / / / / 09/05/23 / / 9,155,16 0 0 MSK 0 0 0 0 / / / /
23-1115 Reconstruction 0-021-032 UNREVIEWED 12/05/23 11/27/23 10/11/23 05/16/23 9,10,15,16 0 0 MSK 0 0 0 H2M Group 0 / / 11/27/23
Storage Trailer 1 @ MS:
- DB Discovered Building 2-029-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer 2 @ MS:
- DB Discovered Building 2-030-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #3 @ MS:
- DB Discovered Building 2-031-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #1 @ Pasadena Elem.:
- DB Discovered Building 2-032-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #2 @ Pasadena Elem.:
- DB Discovered Building 2-033-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #3 @ Pasadena Elem.:
- DB Discovered Building 2-034-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #1 @ Parkway Elem.:
- DB Discovered Building 2-035-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #2 @ Parkway Elem.:
- DB Discovered Building 2-036-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #1 @ Old Bethpage:
- DB Discovered Building 2-037-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer # 2 @ Old Bethpage:
- DB Discovered Building 2-038-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #3 @ Old Bethpage:
- DB Discovered Building 2-039-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #1 @ H.B Mattlin:
- DB Discovered Building 2-040-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #2 @ H.B Mattlin:
- DB Discovered Building 2-041-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #1 @ JFK H.S:
- DB Discovered Building 2-042-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Storage Trailer #2 @ JFK H.S:
- DB Discovered Building 2-043-001 / / / / 08/20/20 / / 0 0 JSS 0 0 0 0 / / / /
Plainview-Old Bethpage Publ Library:
19-1868 Reconstruction 6-007-015 08/13/20 DONE DONE DONE 06/24/20 06/22/20 01/06/20 01/15/20 2,8,9,13,155,15,16 1,085,225 0 JSS 0 0 0 John A. Grillo 0 / / 06/22/20
20-1222 Reconstruction 6-007-016 04/12/21 DONE DONE DONE 01/29/21 01/14/21 01/19/21 10/21/20 16 70,000 0 JSS 0 0 0 John A. Grillo 0 / / 01/14/21
21-0013 Reconstruction 6-007-017 07/14/21 DONE DONE DONE 07/08/21 07/02/21 04/15/21 05/05/21 2,9,14,155,16 203,280 0 SLC 0 0 0 John A. Grillo 0 06/15/22 07/02/21
21-1948 Reconstruction 6-007-018 07/11/22 DONE DONE DONE 06/08/22 06/07/22 11/29/21 12/15/21 2,16 720,555 0 SLC 0 0 0 John A. Grillo 0 / / 06/07/22
23-0210 Reconstruction 6-007-019 09/19/23 DONE DONE DONE 08/07/23 08/07/23 04/20/23 / / 8,9,13,155,15,16 975,098 0 MSK 0 0 0 John A. Grillo 0 / / 08/07/23
JFK HS Comfort Station:
- PR New Construction 7-044-001 / / / / 12/07/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1758 New Construction 7-044-001 08/24/23 DONE DONE DONE 02/27/23 02/27/23 12/07/22 05/17/22 02 - 16 833,400 0 MSK 0 0 0 H2M Group 0 / / 02/27/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
JERICHO UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-15-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
George Jackson ES K-5:
18-1019 Reconstruction 0-001-016 05/14/19 DONE DONE DONE 12/06/18 12/04/18 10/25/18 05/15/18 2,8,9,10,155,15,16 4,185,000 4,185,000 BMJ 0 0 0 John A. Grillo 0 09/22/20 12/04/18
21-0356 Reconstruction 0-001-017 12/06/21 DONE DONE DONE 09/14/21 09/13/21 08/19/21 05/15/18 2,7,9,10,155,15,16 582,000 582,000 JLB 0 0 0 John A. Grillo 0 09/14/22 09/13/21
22-0865 Reconstruction 0-001-018 03/22/23 DONE DONE DONE 10/31/22 10/31/22 06/17/22 05/17/22 7,9,10,155,15,16 608,679 608,679 JJH 0 0 0 John A. Grillo 0 08/26/23 10/31/22
23-0308 Reconstruction 0-001-019 03/15/24 DONE DONE DONE 08/23/23 08/23/23 03/20/23 05/16/23 2,4,8,9,10,155,15,16 553,375 553,375 JJH 0 0 0 John A. Grillo 0 / / 08/23/23
- Reconstruction 0-001-020 / / / / 02/29/24 / / 2,4,7,8,9,10,155,15, 0 0 JJH 0 0 0 0 / / / /
Jericho Middle/High School:
17-1678 Reconstruction 0-003-043 04/08/19 DONE DONE DONE 04/10/18 04/09/18 04/04/18 05/17/16 7,15,16 590,000 0 BMJ 0 0 0 John A. Grillo 0 / / 04/09/18
18-1429 Reconstruction 0-003-044 05/21/19 DONE DONE DONE 02/12/19 02/08/19 10/25/18 05/15/18 2,4,9,155,15,16 5,800,434 0 BMJ 0 0 0 John A. Grillo 0 / / 02/08/19
19-0468 Reconstruction 0-003-045 02/26/20 DONE DONE DONE 09/20/19 09/18/19 05/14/19 05/21/19 2,4,7,8,9,10,155,15, 10,095,130 0 JSS 0 0 0 John A. Grillo 0 / / 09/18/19
20-1033 Reconstruction 0-003-046 12/29/21 DONE DONE DONE 12/23/20 12/14/20 09/18/20 05/18/21 2,4,7,8,9,10,155,15, 3,077,676 3,077,676 JLB 0 0 0 John A. Grillo 0 09/14/22 12/14/20
20-0961 Reconstruction 0-003-047 03/01/21 DONE DONE DONE 12/11/20 11/23/20 09/18/20 06/16/20 2,155,15,16 700,000 700,000 JSS 0 0 0 John A. Grillo 0 / / 11/23/20
21-0033 Reconstruction 0-003-048 08/18/21 DONE DONE DONE 07/12/21 07/09/21 05/06/21 05/18/21 2,4 3,004,420 0 JLB 0 0 0 John A. Grillo 0 / / 07/09/21
21-1214 Reconstruction 0-003-049 09/13/22 DONE DONE DONE 01/31/22 01/28/22 08/19/21 05/18/21 2,4,7,8,9,10,155,15, 3,663,360 3,663,360 JLB 0 0 0 John A. Grillo 0 08/26/23 01/28/22
22-1450 Reconstruction 0-003-050 05/17/23 DONE DONE DONE 01/09/23 01/05/23 06/17/22 05/17/22 2,4,7,8,9,10,155,15, 7,065,005 7,065,005 JJH 0 0 0 John A. Grillo 0 / / 01/05/23
23-0309 Reconstruction 0-003-051 03/15/24 DONE DONE DONE 08/23/23 08/23/23 03/20/23 05/17/22 2,4,8,9,10,155,15,16 7,222,201 7,222,201 JJH 0 0 0 John A. Grillo 0 / / 08/23/23
23-1198 Reconstruction 0-003-052 UNREVIEWED 12/15/23 12/15/23 06/29/23 05/17/22 14,16 0 0 JJH 0 0 0 John A. Grillo 0 / / 12/15/23
- Reconstruction 0-003-053 / / / / 02/26/24 / / 16 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-003-054 / / / / 02/29/24 / / 16 0 0 JJH 0 0 0 0 / / / /
Robert Williams ES-(Leased to..) ppp:
22-0866 Reconstruction 0-004-015 03/22/23 DONE DONE DONE 10/31/22 10/31/22 06/17/22 05/17/22 10,16 93,810 0 JJH 0 0 0 John A. Grillo 0 08/28/23 10/31/22
23-0310 Reconstruction 0-004-016 03/15/24 DONE DONE DONE 08/23/23 08/23/23 03/20/23 05/16/23 8 58,000 0 JJH 0 0 0 John A. Grillo 0 / / 08/23/23
- Reconstruction 0-004-017 / / / / 02/29/24 / / 2,15 0 0 JJH 0 0 0 0 / / / /
Cantiague ES K-5:
20-1276 Reconstruction 0-005-020 05/18/21 DONE DONE DONE 02/10/21 02/04/21 12/02/20 05/21/19 9,16 485,000 0 JSS 0 0 0 John A. Grillo 0 / / 02/04/21
21-0357 Reconstruction 0-005-021 12/06/21 DONE DONE DONE 09/14/21 09/13/21 08/19/21 05/18/21 4,7,155,15,16 557,500 557,500 JLB 0 0 0 John A. Grillo 0 09/14/22 09/13/21
22-0867 Reconstruction 0-005-022 03/22/23 DONE DONE DONE 10/31/22 10/31/22 06/17/22 05/17/22 7,9,10,155,15,16 464,492 464,492 JJH 0 0 0 John A. Grillo 0 08/26/23 10/31/22
23-0311 Reconstruction 0-005-023 03/15/24 DONE DONE DONE 08/23/23 08/23/23 03/20/23 05/16/23 2,4,8,9,10,155,15,16 2,819,635 2,819,635 JJH 0 0 0 John A. Grillo 0 / / 08/23/23
- Reconstruction 0-005-024 / / / / 02/29/24 / / 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
- SB Reconstruction 0-005-BA1 DONE / / / / / / / / 16 0 0 JSS 0 0 0 0 / / / /
Robert Seaman ES-K-5:
21-0358 Reconstruction 0-014-019 12/06/21 DONE DONE DONE 09/14/21 09/13/21 08/19/21 05/18/21 4,7 2,764,480 2,764,480 JLB 0 0 0 John A. Grillo 0 09/14/22 09/13/21
22-0868 Reconstruction 0-014-020 03/22/23 DONE DONE DONE 10/31/22 10/31/22 06/17/22 05/17/22 7,9,10,155,15,16 776,869 776,869 JJH 0 0 0 John A. Grillo 0 08/28/23 10/31/22
23-0312 Reconstruction 0-014-021 03/15/24 DONE DONE DONE 08/23/23 08/23/23 03/20/23 05/16/23 2,4,8,9,10,155,15,16 629,640 629,640 JJH 0 0 0 John A. Grillo 0 / / 08/23/23
- Reconstruction 0-014-022 / / / / 02/29/24 / / 2,8,15 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-014-023 / / / / 03/04/24 / / 0 4,036,824 JJH 0 0 0 0 / / / /
Maintenance Facility:
18-0880 New Construction 3-023-001 06/12/19 DONE DONE DONE 11/20/18 10/31/18 05/26/16 05/16/17 02 - 16 536,250 0 BMJ 0 0 0 John A. Grillo 0 06/16/21 10/31/18
Bus Garage:
19-0138 Additions and Alterations 5-006-002 09/26/19 DONE DONE DONE 07/23/19 07/17/19 01/28/19 05/16/17 02 - 16 295,000 295,000 JSS 0 0 0 John A. Grillo 0 09/21/20 07/17/19
Jericho Public Library:
22-1091 Reconstruction 6-013-006 06/21/23 DONE DONE DONE 11/29/22 11/28/22 06/13/22 / / 2,8,9,16 1,089,110 0 JJH 0 0 0 Burton Behrendt Smith 0 / / 11/28/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HICKSVILLE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-17-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Burns Avenue Elementary:
18-1789 Reconstruction 0-001-027 05/02/19 DONE DONE DONE 04/04/19 03/29/19 08/15/18 05/15/18 2,8 101,988 101,988 BMJ 0 0 0 John A. Grillo 0 01/31/20 03/29/19
19-0234 Reconstruction 0-001-028 10/08/19 DONE DONE DONE 08/09/19 08/05/19 02/26/19 05/15/18 2,7,9,10,15,16 64,900 64,900 BMJ 0 0 0 John A. Grillo 0 12/11/20 08/05/19
19-1333 Reconstruction 0-001-029 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 7,15,16 207,680 207,680 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
21-0863 Reconstruction 0-001-030 03/09/22 DONE DONE DONE 12/07/21 12/06/21 12/07/21 05/18/21 2,4,8 669,100 669,100 JLB 0 0 0 John A. Grillo 0 / / 12/06/21
23-1057 Reconstruction 0-001-031 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Dutch Lane School:
19-0235 Reconstruction 0-002-027 10/08/19 DONE DONE DONE 08/09/19 08/05/19 02/26/19 05/15/18 2,7,9,10,15,16 64,900 64,900 MTM 0 0 0 John A. Grillo 0 12/11/20 08/05/19
19-1334 Reconstruction 0-002-028 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 7,15,16 56,640 56,640 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
21-0864 Reconstruction 0-002-029 03/09/22 DONE DONE DONE 12/07/21 12/06/21 12/07/21 05/18/21 2,4,8 386,377 386,377 JLB 0 0 0 John A. Grillo 0 / / 12/06/21
23-1058 Reconstruction 0-002-030 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
East Street Elementary:
19-0031 Reconstruction 0-003-032 08/15/19 DONE DONE DONE 07/08/19 06/27/19 02/26/19 11/14/17 2,4,7,8,9,10,155,15, 1,390,000 1,390,000 MTM 0 0 0 John A. Grillo 0 12/11/20 06/27/19
19-0236 Reconstruction 0-003-033 10/08/19 DONE DONE DONE 08/09/19 08/05/19 02/26/19 05/15/18 2,7,9,10,15,16 64,900 64,900 MTM 0 0 0 John A. Grillo 0 12/11/20 08/05/19
19-1335 Reconstruction 0-003-034 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 2,4,7,8,9,10,15,16 584,100 584,100 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
21-0865 Reconstruction 0-003-035 03/09/22 DONE DONE DONE 12/07/21 12/06/21 12/07/21 05/18/21 2,4,8 174,750 174,750 JLB 0 0 0 John A. Grillo 0 / / 12/06/21
22-2238FA Reconstruction 0-003-036 07/05/23 DONE DONE DONE 05/19/23 05/15/23 01/23/23 08/24/22 2,7,9,10,13,155,16 613,746 0 JJH 0 0 0 John A. Grillo 0 / / 05/15/23
23-1059 Reconstruction 0-003-037 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Fork Lane School:
19-1336 Reconstruction 0-004-027 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 7,15,16 151,040 151,040 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
23-1060 Reconstruction 0-004-028 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Lee Ave Elementary School:
19-0032 Reconstruction 0-005-032 08/15/19 DONE DONE DONE 07/08/19 06/27/19 02/26/19 11/14/17 2,4,7,8,9,10,155,15, 704,000 704,000 BMJ 0 0 0 John A. Grillo 0 12/11/20 06/27/19
19-1337 Reconstruction 0-005-033 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 2,4,7,8,9,10,15,16 259,600 259,600 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
21-0866 Reconstruction 0-005-034 03/09/22 DONE DONE DONE 12/07/21 12/06/21 12/07/21 05/18/21 2,4,8 311,769 311,769 JLB 0 0 0 John A. Grillo 0 / / 12/06/21
22-1054FC Reconstruction 0-005-035 03/02/23 DONE DONE DONE 11/28/22 11/18/22 04/29/22 08/24/22 2,7,9,10,155,16 1,000,000 1,000,000 JJH 0 0 0 John A. Grillo 0 / / 11/18/22
23-1061 Reconstruction 0-005-036 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Old Country Rd Elem School:
19-0237 Reconstruction 0-007-030 10/08/19 DONE DONE DONE 08/09/19 08/05/19 02/26/19 05/15/18 2,7,9,10,15,16 129,800 129,800 BMJ 0 0 0 John A. Grillo 0 12/11/20 08/05/19
19-1338 Reconstruction 0-007-031 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 7,15,16 169,920 169,920 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
23-1062 Reconstruction 0-007-032 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Woodland Avenue School:
19-0033 Reconstruction 0-008-031 08/15/19 DONE DONE DONE 07/08/19 06/27/19 02/26/19 11/14/17 2,4,7,8,9,10,155,15, 732,000 732,000 BMJ 0 0 0 John A. Grillo 0 12/11/20 06/27/19
19-1339 Reconstruction 0-008-032 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 2,4,7,8,9,10,15,16 584,100 584,100 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
21-0867 Reconstruction 0-008-033 03/09/22 DONE DONE DONE 12/07/21 12/06/21 12/07/21 05/18/21 4,8 255,000 255,000 JLB 0 0 0 John A. Grillo 0 / / 12/06/21
22-2239FA Reconstruction 0-008-034 07/05/23 DONE DONE DONE 05/19/23 05/15/23 01/23/23 08/24/22 2,7,9,10,13,155,16 613,747 0 JJH 0 0 0 John A. Grillo 0 / / 05/15/23
23-1063 Reconstruction 0-008-035 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Hicksville Middle School:
18-1790 Reconstruction 0-009-046 05/02/19 DONE DONE DONE 04/04/19 03/29/19 08/15/18 05/15/18 2,8 305,676 305,676 BMJ 0 0 0 John A. Grillo 0 05/15/23 03/29/19
19-0238 Reconstruction 0-009-047 10/08/19 DONE DONE DONE 08/09/19 08/05/19 02/26/19 05/15/18 2,7,9,10,15,16 672,600 672,600 MTM 0 0 0 John A. Grillo 0 12/11/20 08/05/19
19-1340 Reconstruction 0-009-048 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 2,4,7,8,9,10,15,16 59,000 59,000 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
22-1055FC Reconstruction 0-009-049 03/02/23 DONE DONE DONE 11/28/22 11/18/22 04/29/22 08/24/22 2,7,9,10,155,16 1,500,000 1,500,000 JJH 0 0 0 John A. Grillo 0 / / 11/18/22
23-1064 Reconstruction 0-009-050 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Hicksville High School:
18-1075 Additions and Alterations 0-010-048 05/15/19 DONE DONE DONE 12/14/18 12/12/18 04/13/18 11/14/17 02 - 16 14,740,000 0 BMJ 0 0 0 John A. Grillo 0 08/20/21 12/12/18
18-1827 Reconstruction 0-010-049 05/22/19 DONE DONE DONE 04/10/19 04/04/19 10/17/18 05/21/19 2,9 1,357,000 1,357,000 BMJ 0 0 0 John A. Grillo 0 09/15/23 04/04/19
19-0820 Reconstruction 0-010-050 03/02/20 DONE DONE DONE 11/19/19 11/08/19 02/26/19 11/14/17 2,4,7,8,9,10,155,15, 3,887,327 3,887,327 BMJ 0 0 0 John A. Grillo 0 12/11/20 11/08/19
19-0239 Reconstruction 0-010-051 10/08/19 DONE DONE DONE 08/09/19 08/05/19 02/26/19 05/15/18 2,7,9,10,15,16 755,200 755,200 BMJ 0 0 0 John A. Grillo 0 12/15/23 08/05/19
19-1341 Reconstruction 0-010-052 02/26/20 DONE DONE DONE 02/03/20 01/27/20 08/23/19 05/21/19 2,4,7,8,9,10,15,16 112,100 112,100 BMJ 0 0 0 John A. Grillo 0 11/03/23 01/27/20
20-0260 Reconstruction 0-010-053 10/14/20 DONE DONE DONE 08/24/20 08/13/20 06/22/20 06/09/20 2,7 950,000 950,000 JLB 0 0 0 John A. Grillo 0 12/21/22 08/13/20
21-1411 Reconstruction 0-010-054 05/19/22 DONE DONE DONE 03/01/22 02/16/22 03/01/22 05/18/21 2,4,7,8,9,10,155,15, 436,000 436,000 JLB 0 0 0 John A. Grillo 0 09/01/22 02/16/22
21-1976 Reconstruction 0-010-055 09/13/22 DONE DONE DONE 06/15/22 06/14/22 03/07/22 05/17/22 2,9 1,522,490 1,094,196 JLB 0 0 0 John A. Grillo 0 / / 06/14/22
22-1056FC Reconstruction 0-010-056 03/02/23 DONE DONE DONE 11/28/22 11/18/22 04/29/22 08/24/22 2,7,9,10,155,16 1,899,776 1,899,776 JJH 0 0 0 John A. Grillo 0 / / 11/18/22
22-1305 Reconstruction 0-010-057 05/08/23 DONE DONE DONE 12/21/22 12/21/22 06/27/22 05/17/22 2,7,8,9,10,155,15,16 642,510 642,510 JJH 0 0 0 John A. Grillo 0 / / 12/21/22
23-1065 Reconstruction 0-010-058 UNREVIEWED 11/28/23 11/22/23 10/26/23 05/16/23 8 0 0 JJH 0 0 0 John A. Grillo 0 / / 11/22/23
Hicksville Public Library:
22-2309 Reconstruction 6-018-013 09/21/23 DONE DONE DONE 05/31/23 05/30/23 01/20/23 05/16/23 2,7 182,865 0 JJH 0 0 0 Mark Design Studios 0 / / 05/30/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PLAINEDGE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-18-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Schwarting Elementary:
18-1579 Reconstruction 0-002-017 04/23/19 DONE DONE DONE 03/01/19 02/27/19 01/23/19 05/15/18 8,9,10,155,15,16 200,000 200,000 JLB 0 0 0 Mark Design Studios 0 09/03/19 02/27/19
18-2111 Reconstruction 0-002-018 07/09/19 DONE DONE DONE 06/13/19 06/03/19 04/12/19 05/21/19 10 217,215 217,215 JLB 0 0 0 Mark Design Studios 0 04/17/23 06/03/19
- Reconstruction 0-002-019 / / / / 04/15/21 / / 8 0 0 JLB 0 0 0 0 / / / /
21-1724 Reconstruction 0-002-020 12/01/22 DONE DONE DONE 04/29/22 04/26/22 06/11/21 05/11/21 155,16 889,524 889,524 WLC 0 0 0 ECG Engineering, LLC 889,524 / / 04/26/22
21-0847 Reconstruction 0-002-021 10/25/22 DONE DONE DONE 12/06/21 12/06/21 09/13/21 06/18/21 2,155,16 345,000 345,000 WLC 0 0 0 Mark Design Studios 0 / / 12/06/21
22-0840 Reconstruction 0-002-022 03/01/23 DONE DONE DONE 10/26/22 10/25/22 09/14/22 05/17/22 2,8,9,10,155,15,16 300,000 300,000 WLC 0 0 0 Mark Design Studios 0 / / 10/25/22
23-0231 Reconstruction 0-002-023 02/20/24 DONE DONE DONE 08/09/23 08/08/23 06/16/23 05/16/23 2,8,9,10,16 374,000 374,000 WLC 0 0 0 Mark Design Studios 0 / / 08/08/23
Plainedge High School:
18-2112 Reconstruction 0-003-027 07/09/19 DONE DONE DONE 06/13/19 06/03/19 04/12/19 05/21/19 10 436,086 436,086 JLB 0 0 0 Mark Design Studios 0 04/17/23 06/03/19
18-2106 Reconstruction 0-003-028 08/16/19 DONE DONE DONE 06/12/19 06/03/19 05/13/19 05/21/19 2,9,155,16 3,399,320 3,399,320 JLB 0 0 0 Mark Design Studios 0 09/25/20 06/03/19
19-1179 Reconstruction 0-003-029 04/20/20 DONE DONE DONE 01/08/20 01/03/20 07/31/19 05/18/19 2,4,8 899,811 899,811 JLB 0 0 0 Mark Design Studios 0 11/01/21 01/03/20
- PR Additions and Alterations 0-003-030 / / / / 07/07/20 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-0832 Additions and Alterations 0-003-030 05/13/21 DONE DONE DONE 11/16/20 11/05/20 07/07/20 06/09/20 02 - 16 3,182,498 2,463,874 JLB 0 0 0 Mark Design Studios 0 04/29/22 11/05/20
- PR Additions and Alterations 0-003-031 / / / / 07/07/20 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-1246 Additions and Alterations 0-003-031 06/18/21 DONE DONE DONE 02/05/21 01/14/21 07/07/20 06/09/20 02 - 16 4,395,303 1,042,762 JLB 0 0 0 Mark Design Studios 0 / / 01/14/21
- Reconstruction 0-003-032 / / / / 04/15/21 / / 8 0 0 JLB 0 0 0 0 / / / /
21-1725 Reconstruction 0-003-033 12/01/22 DONE DONE DONE 04/29/22 04/26/22 06/11/21 05/11/21 8,155,16 4,057,321 4,057,321 WLC 0 0 0 ECG Engineering, LLC 4,057,321 / / 04/26/22
21-0510 Reconstruction 0-003-034 12/06/21 DONE DONE DONE 10/13/21 10/12/21 09/13/21 06/09/20 2,4,8,10 2,106,750 2,106,750 JLB 0 0 0 Mark Design Studios 0 02/24/23 10/12/21
22-1519 Reconstruction 0-003-035 02/22/24 DONE DONE DONE 01/20/23 01/19/23 09/13/21 05/17/22 2,8,9,10,155,15,16 3,300,000 2,604,069 WLC 0 0 0 Mark Design Studios 0 / / 01/19/23
23-1267PR Reconstruction 0-003-035 DONE 12/22/23 / / 09/13/21 05/17/22 2,8,9,10,155,15,16 3,300,000 2,604,069 WLC 0 0 0 Mark Design Studios 0 / / / /
22-0692 Reconstruction 0-003-036 02/03/23 DONE DONE DONE 10/12/22 10/11/22 09/16/22 05/17/22 2,9,10,15,16 625,400 625,400 WLC 0 0 0 Mark Design Studios 0 / / 10/11/22
22-1615 Reconstruction 0-003-037 05/31/23 DONE DONE DONE 02/03/23 02/01/23 12/07/22 05/17/22 4,8,9,10,16 738,602 738,602 WLC 0 0 0 Mark Design Studios 0 10/07/22 02/01/23
22-2204 Reconstruction 0-003-038 09/05/23 DONE DONE DONE 05/12/23 05/12/23 02/02/23 05/18/21 2,4,8,9,10,155,15,16 1,985,197 1,985,197 WLC 0 0 0 Mark Design Studios 0 / / 05/12/23
23-0768 Reconstruction 0-003-039 UNREVIEWED 10/20/23 10/16/23 02/28/23 05/17/22 16 0 0 WLC 0 0 0 Mark Design Studios 0 / / 10/16/23
Eastplain Elementary School:
18-2113 Reconstruction 0-004-020 07/09/19 DONE DONE DONE 06/13/19 06/03/19 04/12/19 05/21/19 10 144,142 144,142 JLB 0 0 0 Mark Design Studios 0 04/17/23 06/03/19
18-2071 Reconstruction 0-004-021 07/09/19 DONE DONE DONE 06/06/19 05/29/19 05/21/19 05/21/19 8,9,10,15,16 200,000 200,000 JLB 0 0 0 Mark Design Studios 0 07/31/20 05/29/19
21-1726 Reconstruction 0-004-022 12/01/22 DONE DONE DONE 04/29/22 04/26/22 06/11/21 05/11/21 155,16 349,366 349,366 WLC 0 0 0 ECG Engineering, LLC 349,366 / / 04/26/22
21-0848 Reconstruction 0-004-023 10/25/22 DONE DONE DONE 12/06/21 12/06/21 09/13/21 05/18/21 2,155,16 345,000 345,000 WLC 0 0 0 Mark Design Studios 0 08/10/23 12/06/21
23-0232 Reconstruction 0-004-024 02/20/24 DONE DONE DONE 08/09/23 08/08/23 06/16/23 05/16/23 2,8,9,10,16 374,000 374,000 WLC 0 0 0 Mark Design Studios 0 / / 08/08/23
Plainedge M.S.(formerly Northedge ES:
18-2114 Reconstruction 0-009-008 07/09/19 DONE DONE DONE 06/13/19 06/03/19 04/12/19 05/21/19 10 409,549 409,549 JLB 0 0 0 Mark Design Studios 0 04/17/23 06/03/19
18-2107 Reconstruction 0-009-009 08/16/19 DONE DONE DONE 06/12/19 06/03/19 05/13/19 05/21/19 155,16 310,527 310,527 JLB 0 0 0 Mark Design Studios 0 09/25/20 06/03/19
- Reconstruction 0-009-010 / / / / 04/15/21 / / 8 0 0 JLB 0 0 0 0 / / / /
21-1727 Reconstruction 0-009-011 12/01/22 DONE DONE DONE 04/29/22 04/26/22 06/11/21 05/11/21 155,16 2,195,478 2,195,478 WLC 0 0 0 ECG Engineering, LLC 2,195,478 / / 04/26/22
21-0854 Reconstruction 0-009-012 03/17/22 DONE DONE DONE 12/07/21 11/29/21 12/07/21 05/18/21 2,4,16 606,320 606,320 WLC 0 0 0 Mark Design Studios 0 03/10/23 11/29/21
23-0233 Reconstruction 0-009-013 02/20/24 DONE DONE DONE 08/09/23 08/08/23 06/16/23 05/16/23 2,8,9,10,16 519,000 519,000 WLC 0 0 0 Mark Design Studios 0 / / 08/08/23
John H. West Elementary:
18-1580 Reconstruction 0-011-017 04/23/19 DONE DONE DONE 03/01/19 02/27/19 01/23/19 05/15/18 8,9,10,155,15,16 200,000 200,000 JLB 0 0 0 Mark Design Studios 0 09/03/19 02/27/19
18-2115 Reconstruction 0-011-018 07/09/19 DONE DONE DONE 06/13/19 06/03/19 04/12/19 05/21/19 10 215,136 215,136 JLB 0 0 0 Mark Design Studios 0 04/17/23 06/03/19
- Reconstruction 0-011-019 / / / / 04/15/21 / / 8 0 0 JLB 0 0 0 0 / / / /
21-1728 Reconstruction 0-011-020 12/01/22 DONE DONE DONE 04/29/22 04/26/22 06/11/21 05/11/21 16 1,234,281 1,234,281 WLC 0 0 0 ECG Engineering, LLC 1,234,281 / / 04/26/22
21-0849 Reconstruction 0-011-021 10/25/22 DONE DONE DONE 12/06/21 12/06/21 09/13/21 05/18/21 2,155,16 345,000 345,000 WLC 0 0 0 Mark Design Studios 0 / / 12/06/21
21-1809 Reconstruction 0-011-022 06/28/22 DONE DONE DONE 05/13/22 05/11/22 04/27/22 06/09/20 2,9 202,976 202,976 FMJ 0 0 0 Mark Design Studios 0 08/25/22 05/11/22
23-0234 Reconstruction 0-011-023 02/20/24 DONE DONE DONE 08/09/23 08/08/23 06/16/23 05/16/23 2,8,9,10,16 3,024,000 3,024,000 WLC 0 0 0 Mark Design Studios 0 / / 08/08/23
Plainedge Athletic Facility:
21-1729 Reconstruction 7-027-002 12/01/22 DONE DONE DONE 04/29/22 04/26/22 06/11/21 05/11/21 155,16 39,235 0 WLC 0 0 0 ECG Engineering, LLC 39,235 / / 04/26/22
District Wide:
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BETHPAGE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-21-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bethpage High School:
17-0405 Reconstruction 0-001-042 04/24/19 DONE DONE DONE 09/15/17 09/15/17 08/02/17 05/31/17 155,16 1,121,654 1,121,654 MTM 0 0 0 John A. Grillo 1,121,654 05/10/21 09/15/17
18-1792 Reconstruction 0-001-045 05/07/19 DONE DONE DONE 04/04/19 03/27/19 02/12/19 05/15/18 8 120,000 120,000 JLB 0 0 0 John A. Grillo 0 05/10/21 03/27/19
20-1684 Reconstruction 0-001-046 05/21/21 DONE DONE DONE 05/07/21 05/03/21 02/24/21 02/09/21 2,4 1,145,338 1,145,338 JLB 0 0 0 Burton Behrendt Smith 0 08/27/21 YES 05/03/21
22-0323 Reconstruction 0-001-047 01/06/23 DONE DONE DONE 08/24/22 08/23/22 08/03/21 02/09/21 2,4,8,9,10,155,15,16 525,000 525,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 08/23/22
21-1806 Reconstruction 0-001-048 10/26/22 DONE DONE DONE 05/11/22 05/10/22 01/31/22 02/09/21 2,4,8,9,10,155,15,16 1,940,400 1,940,400 SLC 0 0 0 Burton Behrendt Smith 0 / / 05/10/22
John F. Kennedy Middle School:
17-0406 Reconstruction 0-002-036 04/24/19 DONE DONE DONE 09/15/17 09/15/17 08/02/17 05/31/17 155,16 500,788 500,788 MTM 0 0 0 John A. Grillo 500,788 05/10/21 09/15/17
- XX Reconstruction 0-002-038 CANCELLED / / / / 02/25/21 / / 2,9 0 0 JLB 0 0 0 0 / / / /
21-0882 Reconstruction 0-002-039 03/30/22 DONE DONE DONE 12/10/21 12/10/21 04/21/21 02/09/21 2,9,16 6,240,710 5,420,820 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/10/21
- XX Reconstruction 0-002-040 CANCELLED / / / / 06/25/21 / / 2,9,16 0 0 JLB 0 0 0 0 / / / /
22-0324 Reconstruction 0-002-041 01/06/23 DONE DONE DONE 08/24/22 08/23/22 08/03/21 02/09/21 2,8,9 297,675 297,675 SLC 0 0 0 Burton Behrendt Smith 0 / / 08/23/22
22-1611 Reconstruction 0-002-042 04/04/23 DONE DONE DONE 02/03/23 02/01/23 09/29/22 02/09/21 2,4,8,9,155,15,16 1,393,895 1,393,895 JLB 0 0 0 Burton Behrendt Smith 0 / / 02/01/23
Central Blvd Elementary:
17-0407 Reconstruction 0-003-026 04/24/19 DONE DONE DONE 09/15/17 09/15/17 08/03/17 05/31/17 155,16 373,343 373,343 MTM 0 0 0 John A. Grillo 373,343 05/10/21 09/15/17
21-1228 Reconstruction 0-003-028 05/05/22 DONE DONE DONE 02/02/22 02/02/22 09/29/21 02/09/21 2,9,16 134,000 134,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/22
22-1612 Reconstruction 0-003-029 04/04/23 DONE DONE DONE 02/03/23 02/01/23 09/29/22 02/09/21 2,4,9,15 594,415 594,415 JLB 0 0 0 Burton Behrendt Smith 0 / / 02/01/23
Kramer Lane Elementary:
17-0408 Reconstruction 0-004-022 04/24/19 DONE DONE DONE 09/15/17 09/15/17 08/03/17 05/31/17 9,155,16 413,964 413,964 MTM 0 0 0 John A. Grillo 413,964 05/10/21 09/15/17
22-0325 Reconstruction 0-004-024 01/06/23 DONE DONE DONE 08/24/22 08/23/22 08/03/21 02/09/21 2,4,9,15,16 534,610 534,610 SLC 0 0 0 Burton Behrendt Smith 0 / / 08/23/22
21-1229 Reconstruction 0-004-025 05/05/22 DONE DONE DONE 02/02/22 02/02/22 09/29/21 02/09/21 2,9,16 84,000 84,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/22
Charles Campagne Elementary:
17-0409 Reconstruction 0-007-023 04/24/19 DONE DONE DONE 09/15/17 09/15/17 08/03/17 05/31/17 155,16 282,508 282,508 MTM 0 0 0 John A. Grillo 282,508 05/10/21 09/15/17
- XX Reconstruction 0-007-025 CANCELLED / / / / 08/03/21 / / 2,4,8,9 0 13,166,469 JLB 0 0 0 0 / / / /
21-1230 Reconstruction 0-007-026 05/05/22 DONE DONE DONE 02/02/22 02/02/22 09/29/21 02/09/21 2,9,16 134,000 134,000 SLC 0 0 0 Burton Behrendt Smith 0 / / 02/02/22
22-1613 Reconstruction 0-007-027 04/04/23 DONE DONE DONE 02/03/23 02/01/23 09/29/22 02/09/21 2,4,9,155,15 548,644 548,644 JLB 0 0 0 Burton Behrendt Smith 0 / / 02/01/23
Athletic Building:
- PR New Construction 0-016-001 / / / / 08/03/21 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-1353 New Construction 0-016-001 08/22/22 DONE DONE DONE 02/23/22 02/18/22 08/03/21 12/15/20 02 - 16 1,449,887 0 JLB 0 0 0 Burton Behrendt Smith 0 09/29/23 02/18/22
Administration Building:
18-1333 Reconstruction 1-005-006 04/24/19 DONE DONE DONE 01/24/19 01/02/19 12/17/18 05/31/17 16 18,894 0 JLB 0 0 0 John A. Grillo 18,894 05/10/21 01/02/19
Athletic Storage @ HS:
- PR New Construction 2-017-001 / / / / 06/15/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-0934 New Construction 2-017-001 02/18/23 DONE DONE DONE 11/09/22 11/04/22 06/15/22 02/09/21 02 - 16 42,000 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 11/04/22
Robotics Storage @ HS:
- PR New Construction 2-018-001 / / / / 06/15/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-0935 New Construction 2-018-001 03/07/23 DONE DONE DONE 11/09/22 11/04/22 06/15/22 02/09/21 02 - 16 42,000 0 SLC 0 0 0 Burton Behrendt Smith 0 / / 11/04/22
Storage Bldg 1:
23-0323DB Discovered Building 2-019-001 02/06/24 DONE DONE DONE 08/25/23 08/24/23 10/21/22 / / 0 0 MSK 0 0 0 0 / / 08/24/23
Storage Bldg 2:
23-0324DB Discovered Building 2-020-001 02/06/24 DONE DONE DONE 08/25/23 08/24/23 10/21/22 / / 0 0 MSK 0 0 0 0 / / 08/24/23
Bethpage Public Library:
18-2191 Reconstruction 6-011-010 08/16/19 DONE DONE DONE 06/24/19 06/17/19 04/20/18 05/07/18 9,10,155,16 220,590 0 JLB 0 0 0 John A. Grillo 0 / / 06/17/19
Pre-Fab Comfort Station:
21-0883 New Construction 7-015-001 03/30/22 DONE DONE DONE 12/10/21 12/10/21 06/25/21 02/09/21 02 - 16 600,000 0 JLB 0 0 0 Burton Behrendt Smith 0 / / 12/10/21
District-Wide:
- XX Reconstruction 7-999-004 CANCELLED / / / / 04/27/21 / / 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
FARMINGDALE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-22-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Weldon E. Howitt Middle Schl-East:
18-0980 Reconstruction 0-001-029 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 9,155,15,16 227,852 227,852 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
22-0089 Reconstruction 0-001-030 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 933,556 933,556 WLC 0 0 0 H2M Group 933,556 / / 07/13/22
22-2270FC Reconstruction 0-001-031 07/19/23 DONE DONE DONE 05/24/23 05/04/23 02/01/23 02/08/23 155 865,000 0 WLC 0 0 0 H2M Group 0 / / 05/04/23
Albany Ave. Elementary School:
18-0981 Reconstruction 0-003-027 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 2,7,155,15,16 1,117,863 1,117,863 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
22-0090 Reconstruction 0-003-028 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 1,185,711 1,185,711 WLC 0 0 0 H2M Group 1,185,711 / / 07/13/22
Woodward Parkway Elementary:
18-0982 Reconstruction 0-006-025 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 10,15,16 559,430 559,430 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
22-0091 Reconstruction 0-006-026 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 1,527,787 1,527,787 WLC 0 0 0 H2M Group 1,527,787 / / 07/13/22
22-2271FC Reconstruction 0-006-027 07/19/23 DONE DONE DONE 05/24/23 05/04/23 02/01/23 02/08/23 155 595,000 0 WLC 0 0 0 H2M Group 0 / / 05/04/23
Farmingdale High School:
18-0983 Reconstruction 0-007-043 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 9,155,15,16 867,515 867,515 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
19-1666 Reconstruction 0-007-044 07/10/20 DONE DONE DONE 04/09/20 03/09/20 08/29/19 05/15/07 155 105,138 105,138 JLB 0 0 105,138 H2M Group 0 02/18/21 03/09/20
22-0092 Reconstruction 0-007-045 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 5,274,687 5,274,687 WLC 0 0 0 H2M Group 5,274,687 / / 07/13/22
22-2272FC Reconstruction 0-007-046 07/19/23 DONE DONE DONE 05/24/23 05/04/23 02/01/23 02/08/23 155 870,000 0 WLC 0 0 0 H2M Group 0 / / 05/04/23
- Reconstruction 0-007-047 / / / / 04/10/23 / / 2,4,7,8,9 0 0 WLC 0 0 0 0 / / / /
Northside Elementary School:
18-0984 Reconstruction 0-008-026 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 155,15,16 357,536 357,536 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
22-0093 Reconstruction 0-008-027 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 1,144,516 1,144,516 WLC 0 0 0 H2M Group 1,144,516 / / 07/13/22
Salzman East Memorial Elem School:
18-0985 Reconstruction 0-009-026 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 9,155,15,16 1,016,707 1,016,707 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
22-0094 Reconstruction 0-009-027 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 1,686,988 1,686,988 WLC 0 0 0 H2M Group 1,686,988 / / 07/13/22
22-2273FC Reconstruction 0-009-028 07/19/23 DONE DONE DONE 05/24/23 05/04/23 02/01/23 02/08/23 155 670,000 0 WLC 0 0 0 H2M Group 0 / / 05/04/23
Weldon E. Howitt Middle Schl-West:
18-0986 Reconstruction 0-010-030 06/01/20 DONE DONE DONE 12/03/18 11/05/18 04/09/18 05/16/17 9,155,15,16 849,004 849,004 MTM 0 0 0 H2M Group 0 10/23/23 11/05/18
22-0095 Reconstruction 0-010-031 04/27/23 DONE DONE DONE 07/15/22 07/13/22 11/03/20 12/04/19 2,8,16 967,821 801,528 WLC 0 0 0 H2M Group 967,821 / / 07/13/22
Maintenance Building:
19-0404DB Discovered Building 3-021-001 10/13/20 DONE DONE DONE 09/12/19 09/11/19 05/28/19 / / 0 0 JLB 0 0 0 0 / / 09/11/19
New Farmingdale Public Library:
22-0322 Reconstruction 6-017-007 09/27/22 DONE DONE DONE 08/24/22 08/23/22 08/08/22 08/17/22 7,155,16 871,500 0 SLC 0 0 0 BHC Architects 0 / / 08/23/22
Farmingdale Public Library Pavilion:
19-0880 New Construction 7-022-001 05/18/20 DONE DONE DONE 11/27/19 10/15/19 07/09/19 06/18/19 02 - 16 28,897 0 JLB 0 0 0 Beatty Harvey Coco Architects 0 / / 10/15/19
District-Wide:
- XX Reconstruction 7-999-010 CANCELLED / / / / 10/19/20 / / 16 0 0 JLB 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MASSAPEQUA UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-05-23-03
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Birch Lane Elementary:
19-0991 Reconstruction 0-001-027 04/24/20 DONE DONE DONE 12/13/19 11/21/19 10/19/18 01/23/18 2,9,10,155,15,16 5,568,223 5,568,223 BMJ 0 0 0 H2M Group 0 01/14/22 11/21/19
21-1778FC Reconstruction 0-001-028 06/14/22 DONE DONE DONE 05/09/22 05/04/22 11/10/21 02/10/22 9,155,16 211,215 211,215 JLB 0 0 0 H2M Group 0 09/22/23 05/04/22
23-0552 Reconstruction 0-001-029 UNREVIEWED
STARTED STARTED 09/25/23 09/19/23 05/18/23 03/16/23 155 0 0 JJH 0 0 0 H2M Group 0 / / 09/19/23
23-0579 Reconstruction 0-001-030 UNREVIEWED
DONE DONE 09/29/23 09/25/23 07/24/23 03/16/23 2,13 0 0 JJH 0 0 0 H2M Group 0 / / 09/25/23
23-1351 Reconstruction 0-001-031 UNREVIEWED 01/12/24 01/03/24 10/24/23 10/19/23 7 0 0 JJH 0 0 0 H2M Group 0 / / 01/03/24
East Lake Elementary:
18-1312 Reconstruction 0-003-027 05/20/19 DONE DONE DONE 01/23/19 01/02/19 10/19/18 01/23/18 2,9,10,155,15,16 4,904,085 4,904,085 BMJ 0 0 0 H2M Group 0 01/15/22 01/02/19
- PR Additions and Alterations 0-003-028 / / / / 09/06/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
20-0335 Additions and Alterations 0-003-028 10/22/20 DONE DONE DONE 09/03/20 08/28/20 09/06/19 05/21/19 02 - 16 251,543 251,543 JLB 0 0 0 H2M Group 0 12/17/21 08/28/20
22-0664FC Reconstruction 0-003-029 11/29/22 DONE DONE DONE 10/07/22 10/05/22 11/10/21 02/10/22 9,155,16 339,300 339,300 JJH 0 0 0 H2M Group 0 / / 10/05/22
- Reconstruction 0-003-030 / / / / 01/22/24 / / 2,7,8 0 0 JJH 0 0 0 0 / / / /
Fairfield Elementary:
19-0992 Reconstruction 0-004-031 04/24/20 DONE DONE DONE 12/13/19 12/12/19 10/19/18 01/23/18 2,9,10,155,15,16 4,429,502 4,429,502 BMJ 0 0 0 H2M Group 0 01/14/22 12/12/19
22-1269FC Reconstruction 0-004-032 02/22/23 DONE DONE DONE 12/19/22 12/01/22 11/10/21 02/10/22 9,155,16 690,000 690,000 JJH 0 0 0 H2M Group 0 / / 12/01/22
23-0797 Reconstruction 0-004-033 UNREVIEWED 10/25/23 10/19/23 05/18/23 03/16/23 155 0 0 JJH 0 0 0 H2M Group 0 / / 10/19/23
23-0580 Reconstruction 0-004-034 UNREVIEWED
DONE DONE 09/29/23 09/25/23 07/24/23 03/16/23 2,13 0 0 JJH 0 0 0 H2M Group 0 / / 09/25/23
23-1393 Reconstruction 0-004-035 UNREVIEWED 01/18/24 01/17/24 10/24/23 10/19/23 8 0 0 JJH 0 0 0 H2M Group 0 / / 01/17/24
- Reconstruction 0-004-036 / / / / 01/22/24 / / 2,7 0 0 JJH 0 0 0 0 / / / /
Hawthorn School:
- Reconstruction 0-005-017 / / / / 02/08/24 / / 2,7,15 0 0 JJH 0 0 0 0 / / / /
Lockhart Elementary School:
19-0746 Reconstruction 0-006-024 02/12/20 DONE DONE DONE 11/08/19 10/31/19 10/19/18 01/23/18 2,4,9,10,155,15,16 3,614,319 3,614,319 BMJ 0 0 0 H2M Group 0 01/15/22 10/31/19
21-1779FC Reconstruction 0-006-025 06/14/22 DONE DONE DONE 05/09/22 05/04/22 11/10/21 02/10/22 9,155,16 178,133 178,133 JLB 0 0 0 H2M Group 0 09/22/23 05/04/22
- Reconstruction 0-006-026 / / / / 01/22/24 / / 2,7,8 0 0 JJH 0 0 0 0 / / / /
Unqua Elementary School:
18-2178 Reconstruction 0-007-031 08/02/19 DONE DONE DONE 06/20/19 06/07/19 10/19/18 01/23/18 2,9,10,155,15,16 4,229,251 4,229,251 BMJ 0 0 0 H2M Group 0 01/15/22 06/07/19
21-1569FC Reconstruction 0-007-032 05/31/22 DONE DONE DONE 03/28/22 03/11/22 11/10/21 02/10/22 9,155,16 119,760 119,760 JLB 0 0 0 H2M Group 0 02/28/23 03/11/22
23-1352 Reconstruction 0-007-033 UNREVIEWED 01/12/24 01/03/24 11/06/23 10/19/23 7 0 0 JJH 0 0 0 H2M Group 0 / / 01/03/24
- Reconstruction 0-007-034 / / / / 01/24/24 / / 2,155 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-007-035 / / / / 02/14/24 / / 2,8 0 0 JJH 0 0 0 0 / / / /
McKenna Elem. (f'ly JHS):
19-0338 Reconstruction 0-008-032 12/04/19 DONE DONE DONE 08/30/19 08/12/19 10/19/18 01/23/18 2,9,10,155,15,16 4,645,759 4,645,759 BMJ 0 0 0 H2M Group 0 08/31/21 08/12/19
20-0674 Reconstruction 0-008-033 04/30/21 DONE DONE DONE 10/22/20 10/22/20 09/06/19 05/21/19 16 1,152,945 0 JLB 0 0 0 H2M Group 0 / / 10/22/20
21-1570FC Reconstruction 0-008-034 05/31/22 DONE DONE DONE 03/28/22 03/11/22 11/10/21 02/10/22 9,155,16 84,000 84,000 JLB 0 0 0 H2M Group 0 / / 03/11/22
23-1394 Reconstruction 0-008-035 UNREVIEWED 01/18/24 01/17/24 10/24/23 10/19/23 8 0 0 JJH 0 0 0 H2M Group 0 / / 01/17/24
- Reconstruction 0-008-036 / / / / 01/22/24 / / 2,7 0 0 JJH 0 0 0 0 / / / /
Ames High School:
18-1313 Reconstruction 0-009-024 05/20/19 DONE DONE DONE 01/23/19 01/02/19 10/19/18 01/23/18 2,9,10,155,15,16 1,472,131 1,472,131 BMJ 0 0 0 H2M Group 0 01/15/21 01/02/19
21-1410 Reconstruction 0-009-025 05/18/22 DONE DONE DONE 03/01/22 02/25/22 06/28/19 05/21/19 2,7,14,155,15,16 429,746 368,312 JLB 0 0 0 H2M Group 0 03/10/23 02/25/22
22-0665FC Reconstruction 0-009-026 11/29/22 DONE DONE DONE 10/07/22 10/05/22 11/10/21 02/10/22 9,155,16 255,324 255,324 JJH 0 0 0 H2M Group 0 / / 10/05/22
23-1522 Reconstruction 0-009-027 UNREVIEWED 02/20/24 02/16/24 10/24/23 10/19/23 7,155,16 0 0 JJH 0 0 0 H2M Group 0 / / 02/16/24
- Reconstruction 0-009-028 / / / / 01/22/24 / / 8 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-009-029 / / / / 01/24/24 / / 155 0 0 JJH 0 0 0 0 / / / /
Massapequa High School:
18-1671 Reconstruction 0-010-042 07/10/19 DONE DONE DONE 03/18/19 03/18/19 10/19/18 01/23/18 155,16 2,025,720 2,025,720 BMJ 0 0 0 H2M Group 0 08/24/21 03/18/19
19-1597 Reconstruction 0-010-043 07/15/20 DONE DONE DONE 03/16/20 03/10/20 06/28/19 05/23/19 8,9,155,15,16 1,819,722 1,819,722 JLB 0 0 0 H2M Group 0 10/22/21 03/10/20
21-1780FC Reconstruction 0-010-044 06/14/22 DONE DONE DONE 05/09/22 05/04/22 11/10/21 02/10/22 9,155,16 335,908 335,908 JLB 0 0 0 H2M Group 0 / / 05/04/22
23-1353 Reconstruction 0-010-045 UNREVIEWED 01/12/24 01/03/24 10/24/23 10/19/23 7 0 0 JJH 0 0 0 H2M Group 0 / / 01/03/24
Berner Middle School:
18-1314 Reconstruction 0-011-032 05/20/19 DONE DONE DONE 01/23/19 01/02/19 10/19/18 01/23/18 2,9,10,155,15,16 6,273,462 6,273,462 BMJ 0 0 0 H2M Group 0 09/04/19 YES 01/02/19
19-1741 Reconstruction 0-011-033 07/10/20 DONE DONE DONE 05/22/20 05/06/20 06/28/19 05/21/19 8,9,155,15,16 1,645,002 1,645,002 JLB 0 0 0 H2M Group 0 01/24/22 05/06/20
21-1571FC Reconstruction 0-011-034 05/31/22 DONE DONE DONE 03/28/22 03/11/22 11/10/21 02/10/22 9,155,16 2,865,620 2,865,620 JLB 0 0 0 H2M Group 0 02/28/23 03/11/22
23-1523 Reconstruction 0-011-035 UNREVIEWED 02/20/24 02/15/24 10/24/23 10/19/23 2,7 0 0 JJH 0 0 0 H2M Group 0 / / 02/15/24
Field House @ High School:
19-1598 Additions and Alterations 2-016-001 07/15/20 DONE DONE DONE 03/16/20 03/10/20 01/27/20 05/23/19 02 - 16 309,287 0 JLB 0 0 0 H2M Group 0 / / 03/10/20
Storage Container A:
20-0720DB Discovered Building 2-031-001 04/22/21 DONE DONE DONE 10/29/20 10/23/20 07/01/20 / / 0 0 JLB 0 0 0 0 / / 10/23/20
Storage Container B:
20-0721DB Discovered Building 2-032-001 04/22/21 DONE DONE DONE 10/29/20 10/23/20 07/01/20 / / 0 0 JLB 0 0 0 0 / / 10/23/20
Bar Harbor Library:
19-0565 Reconstruction 6-018-007 12/23/19 DONE DONE DONE 10/16/19 10/04/19 07/26/18 10/01/19 8,9,155,15,16 1,285,000 0 BMJ 0 0 0 FPM Engineering Group, P.C. 0 / / 10/04/19
- Reconstruction 6-018-008 / / / / 05/17/21 / / 2 0 0 JLB 0 0 0 0 / / / /
Massapequa HS Comfort Station:
- XX New Construction 7-030-001 CANCELLED / / / / 06/28/19 / / 02 - 16 0 0 BMJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
NASSAU BOCES STATUS REPORT ON CAPITAL PROJECTS
District No.: 28-90-00-00
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Rosemary Kennedy Ctr Bldg:
20-1603 Reconstruction 0-017-026 06/15/21 DONE DONE DONE 04/19/21 04/08/21 11/06/20 05/26/11 9,16 1,039,977 1,039,977 JLB 0 0 0 H2M Group 0 01/11/22 YES 04/08/21
- Reconstruction 0-017-027 / / / / 11/06/20 / / 8,9,155,16 0 3,922,620 JSS 0 0 0 0 / / / /
21-1159 Reconstruction 0-017-028 10/24/22 DONE DONE DONE 01/18/22 01/18/22 06/01/21 02/13/20 9,14,16 368,500 368,500 JLB 0 0 0 Mark Design Studios 0 / / 01/18/22
22-0375FA Reconstruction 0-017-029 10/06/22 DONE DONE DONE 08/29/22 08/29/22 04/11/22 05/05/22 9 580,000 580,000 JLB 0 0 0 H2M Group 0 / / 08/29/22
J.M Barry Career & Tec Edu. Cntr:
20-1329 Reconstruction 0-030-026 06/15/21 DONE DONE DONE 02/19/21 02/08/21 11/06/20 02/13/20 7,155,16 4,244,934 4,244,934 JSS 0 0 0 H2M Group 0 / / 02/08/21
20-1357 Reconstruction 0-030-027 03/12/21 DONE DONE DONE 03/03/21 03/02/21 02/16/21 02/13/21 155,16 202,909 0 JSS 0 0 0 H2M Group 0 / / 03/02/21
- Reconstruction 0-030-028 / / / / 01/11/24 / / 155,16 0 0 WLC 0 0 0 0 / / / /
Carmen Road School:
18-0072 Reconstruction 0-067-007 08/26/19 DONE DONE DONE 07/16/18 07/13/18 02/01/18 03/07/19 16 694,200 694,200 MTM 0 0 0 Burton Behrendt Smith 0 04/01/21 07/13/18
18-1940 Reconstruction 0-067-009 06/24/19 DONE DONE DONE 05/13/19 05/08/19 11/13/18 12/21/17 16 278,600 278,600 MTM 0 0 0 Burton Behrendt Smith 0 / / 05/08/19
18-2065 Reconstruction 0-067-010 06/28/19 DONE DONE DONE 06/05/19 05/22/19 11/13/18 12/21/17 4 643,600 643,600 MTM 0 0 0 Burton Behrendt Smith 0 11/23/21 05/22/19
18-1930 Reconstruction 0-067-011 05/14/19 DONE DONE DONE 05/07/19 05/07/19 03/21/19 04/04/19 2,155,16 7,530,000 7,407,096 JLB 0 0 0 Burton Behrendt Smith 0 / / 05/07/19
21-0407 Reconstruction 0-067-012 11/19/21 DONE DONE DONE 09/23/21 09/22/21 03/13/20 02/13/20 8 624,500 624,500 JLB 0 0 0 Burton Behrendt Smith 0 / / 09/22/21
21-1831 Reconstruction 0-067-013 08/10/22 DONE DONE DONE 05/18/22 05/18/22 09/13/21 02/11/21 2,4,8,9,10,155,15,16 1,801,800 1,801,800 JLB 0 0 0 Burton Behrendt Smith 0 / / 05/18/22
22-1940 Reconstruction 0-067-014 06/26/23 DONE DONE DONE 03/27/23 03/27/23 01/12/23 03/09/23 2,16 346,331 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 03/27/23
23-0709 Reconstruction 0-067-015 UNREVIEWED 10/13/23 10/11/23 01/18/23 04/04/19 2,15 0 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 10/11/23
Long Island HS for Arts:
- PR Additions and Alterations 0-080-009 / / / / 08/11/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
23-0094 Reconstruction 0-080-010 12/22/23 DONE DONE DONE 07/17/23 07/14/23 08/11/22 03/09/23 8,9,10,155,16 3,127,900 1,673,030 WLC 0 0 0 Mark Design Studios 0 / / 07/14/23
22-1923 Reconstruction 0-080-011 07/21/23 DONE DONE DONE 03/22/23 03/21/23 08/11/22 03/17/22 8,9,10,16 223,560 223,560 WLC 0 0 0 Mark Design Studios 0 / / 03/21/23
22-1924 Reconstruction 0-080-012 07/21/23 DONE DONE DONE 03/22/23 03/21/23 08/11/22 03/17/22 8,9,13,155,16 99,663 99,663 WLC 0 0 0 Mark Design Studios 0 / / 03/21/23
23-1602 Reconstruction 0-080-013 UNREVIEWED 03/08/24 03/07/24 08/23/22 03/09/23 8,9,13,155,16 0 0 WLC 0 0 0 Mark Design Studios 0 / / 03/07/24
- Reconstruction 0-080-014 / / / / 08/23/22 / / 2,4,7,16 0 0 JLB 0 0 0 0 / / / /
22-2072 Reconstruction 0-080-015 07/19/23 DONE DONE DONE 04/19/23 04/18/23 02/08/23 03/09/23 7,8 400,000 400,000 WLC 0 0 0 Mark Design Studios 0 03/13/24 04/18/23
Jerusalem Avenue School (fmly 8-116):
18-2034DB Discovered Building 0-116-001 06/19/19 DONE DONE DONE 05/31/19 05/31/19 04/09/19 / / 0 0 JLB 0 0 0 0 / / 05/31/19
20-1538 Reconstruction 0-116-002 10/14/21 DONE DONE DONE 04/02/21 02/26/21 07/05/19 02/13/20 2,4,7 3,749,513 0 JLB 0 0 0 Burton Behrendt Smith 0 09/30/22 02/26/21
23-0044 Reconstruction 0-116-003 02/14/24 DONE DONE DONE 07/10/23 07/10/23 03/13/20 / / 2,8,9,10,155,16 3,831,600 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 07/10/23
22-1977 Reconstruction 0-116-004 01/03/24 DONE DONE DONE 04/03/23 03/29/23 03/13/20 03/09/23 2,16 779,400 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 03/29/23
22-1565 Reconstruction 0-116-005 01/03/24 DONE DONE DONE 01/27/23 01/25/23 01/19/22 03/17/22 2,8,9,155,15,16 3,809,856 0 WLC 0 0 0 Burton Behrendt Smith 0 / / 01/25/23
- Reconstruction 0-116-006 / / / / 08/11/23 / / 2,10 0 0 WLC 0 0 0 0 / / / /
Hawthorn School:
- TQ Temporary Quarters 0-175-001 / / / / / / / / 0 0 WLC 0 0 0 0 / / / /
Haskett Dr Complex Bldg-C:
18-0073 Reconstruction 1-001-002 08/16/19 DONE DONE DONE 07/16/18 07/13/18 02/01/18 03/07/19 16 166,167 0 MTM 0 0 0 Burton Behrendt Smith 0 11/06/20 07/13/18
George Farber Administrative Center:
19-0860 Reconstruction 1-137-008 05/29/20 DONE DONE DONE 11/21/19 11/12/19 09/12/17 12/22/16 4 400,200 0 JSS 0 0 0 H2M Group 0 / / 11/12/19
18-0503 Reconstruction 1-137-010 05/08/19 DONE DONE DONE 09/24/18 09/13/18 02/01/18 11/09/17 15,16 884,600 0 MTM 0 0 0 Burton Behrendt Smith 0 / / 09/13/18
20-1179 Reconstruction 1-137-012 04/21/21 DONE DONE DONE 01/25/21 01/19/21 12/02/20 02/13/20 155,16 1,306,600 0 JSS 0 0 0 H2M Group 0 09/14/22 01/19/21
21-1346 Reconstruction 1-137-013 01/09/23 DONE DONE DONE 02/22/22 02/17/22 10/13/21 / / 4,8,9,10,15,16 754,198 0 JLB 0 0 0 Mark Design Studios 0 / / 02/17/22
- Reconstruction 1-137-014 / / / / / / / / 155,16 0 0 WLC 0 0 0 0 / / / /
Haskett Drive Complex-Bldg F:
18-0074 Reconstruction 2-004-002 08/16/19 DONE DONE DONE 07/16/18 07/13/18 02/01/18 03/07/19 16 135,633 0 MTM 0 0 0 Burton Behrendt Smith 0 11/06/20 07/13/18
CIT Center (Westbury):
- Reconstruction 8-155-006 / / / / 01/11/24 / / 155,16 0 0 WLC 0 0 0 0 / / / /
Robert Williams School:
19-0029TQ Temporary Quarters 8-165-001 09/16/19 DONE DONE DONE 07/08/19 / / 05/31/19 / / 0 0 JLB 0 0 0 0 / / / /
19-1420 Reconstruction 8-165-002 05/08/20 DONE DONE DONE 02/18/20 01/24/20 12/31/19 02/13/20 8,9,155,16 624,600 0 JSS 0 0 0 H2M Group 0 02/26/21 01/24/20
Gerald Claps Career & Technical Ctr:
19-0003TQ Temporary Quarters 8-166-001 01/28/20 DONE DONE DONE 07/01/19 / / / / / / 0 0 JSS 0 0 0 0 / / / /
Island Trees High School:
- TQ Temporary Quarters 8-167-001 / / / / 09/21/21 / / 0 0 JLB 0 0 0 0 / / / /
J. Fred Sparke Elementary School:
- TQ Temporary Quarters 8-168-001 / / / / 10/04/21 / / 0 0 JLB 0 0 0 0 / / / /
Island Trees Middle School:
- TQ Temporary Quarters 8-169-001 / / / / 10/04/21 / / 0 0 JLB 0 0 0 0 / / / /
JW Dodd MS Freeport Public Schools:
- TQ Temporary Quarters 8-170-001 / / / / 10/14/21 / / 0 0 JLB 0 0 0 0 / / / /
XXTemp. Brookville Police Dept. HQ:
- XX Alterations 8-171-001 CANCELLED / / / / 11/08/21 / / 0 0 JLB 0 0 0 0 / / / /
St. Mary School:
23-0156XX Reconstruction 8-173-001 CANCELLED 07/28/23 07/28/23 02/02/23 / / 0 0 WLC 0 0 0 0 / / 07/28/23
Endo Building:
22-2318TQ Temporary Quarters 8-174-001 STARTED STARTED UNREVIEWED06/05/23 06/02/23 05/18/23 / / 0 0 WLC 0 0 0 0 / / 06/02/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED