REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Boonville Central:
07-1516 Reconstruction 0-002-006 08/11/08 DONE DONE DONE 02/01/08 01/31/08 03/07/07 05/15/07 2,4,7,8,9,10,155,15, 2,500,000 2,500,000 HCM 0 0 50,000 March Associates 0 / / / /
West Leyden School:
07-1517 Reconstruction 0-013-006 08/11/08 DONE DONE DONE 02/01/08 01/31/08 03/07/07 05/15/07 2,4,7,8,9,155,15,16 1,015,052 1,015,052 HCM 0 0 20,301 March Associates 0 / / / /
Forestport Elementary:
07-1518 Reconstruction 0-016-006 08/11/08 DONE DONE DONE 02/01/08 01/31/08 03/08/07 05/15/07 2,4,7,8,9,155,15,16 700,240 700,240 HCM 0 0 14,000 March Associates 0 / / / /
Senior High School:
07-1519 Reconstruction 0-017-006 08/11/08 DONE DONE DONE 02/01/08 01/31/08 03/07/07 05/15/07 2,4,7,8,9,10,155,15, 4,891,027 4,891,027 HCM 0 0 97,821 March Associates 0 / / / /
New West Leyden Bus Garage:
07-1520 New Construction 4-022-001 08/11/08 DONE DONE DONE 02/01/08 01/31/08 03/15/07 05/15/07 02 - 16 351,968 351,968 HCM 0 0 0 March Associates 0 / / / /
Bus Garage:
07-1521 Reconstruction 5-001-004 08/11/08 DONE DONE DONE 02/01/08 01/31/08 03/08/07 05/15/07 2,4,8,9,155,15,16 245,953 245,953 HCM 0 0 0 March Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
08-1592 Reconstruction 0-001-021 10/15/09 DONE DONE DONE 05/05/09 05/01/09 05/24/07 05/20/08 2,4,8,9,155,15,16 1,671,794 1,671,794 HCM 0 0 33,436 King & King, Architects 0 / / 10/29/12
10-0676 Reconstruction 0-001-022 05/23/11 DONE DONE DONE 12/31/10 12/23/10 08/31/10 05/20/08 2,4,7,8,9,155,15,16 9,086,336 9,086,336 JMB 0 0 272,590 King & King, Architects 0 / / / /
12-0463 Reconstruction 0-001-023 STARTED ADD. REQ'D STARTED 11/20/12 11/20/12 09/28/12 05/15/07 2,8,9,10,14,155,15,1 0 17,222,276 JMB 0 0 0 King & King Architects 0 / / / /
Camden Elementary:
07-1743 Reconstruction 0-003-016 11/05/08 DONE DONE DONE 03/04/08 02/29/08 05/23/07 05/15/07 2,8,9,155,15,16 629,009 629,009 HCM 0 0 15,725 King & King, Architects 0 / / / /
10-0677 Reconstruction 0-003-017 05/23/11 DONE DONE DONE 12/31/10 12/23/10 08/31/10 05/20/08 2,4,7,8,9,13,155,15, 2,508,209 2,508,209 HCM 0 0 75,246 King & King, Architects 0 / / / /
12-0464 Reconstruction 0-003-018 STARTED ADD. REQ'D STARTED 11/20/12 11/20/12 09/28/12 05/15/07 4,9,10 0 9,838,920 JMB 0 0 0 King & King Architects 0 / / / /
Annsville Area School:
07-1744 Reconstruction 0-004-013 11/05/08 DONE DONE DONE 03/04/08 02/29/08 05/23/07 05/15/07 2,8,9,155,15,16 996,271 996,271 HCM 0 0 24,907 King & King, Architects 0 / / / /
10-0678 Reconstruction 0-004-014 05/23/11 DONE DONE DONE 12/31/10 12/23/10 08/31/10 05/20/10 2,7,13,155,15,16 1,672,139 1,672,139 HCM 0 0 50,164 King & King, Architects 0 / / / /
12-0465 Reconstruction 0-004-015 STARTED ADD. REQ'D STARTED 11/20/12 11/20/12 09/28/12 05/17/07 10,15,16 0 6,051,634 JMB 0 0 0 King & King Architects 0 / / / /
North Bay Area School:
07-1745 Reconstruction 0-005-012 11/05/08 DONE DONE DONE 03/04/08 02/29/08 / / 05/15/07 2,8,9,155,15,16 1,191,060 1,191,060 HCM 0 0 29,777 King & King, Architects 0 / / / /
10-0679 Reconstruction 0-005-013 05/23/11 DONE DONE DONE 12/31/10 12/23/10 08/31/10 05/20/08 2,4,7,8,9,13,155,15, 2,090,017 0 HCM 0 0 62,700 King & King, Architects 0 / / / /
McConnellsville Elementary:
07-1746 Reconstruction 0-007-007 11/05/08 DONE DONE DONE 03/04/08 02/29/08 05/24/07 05/15/07 8,9,155,16 637,189 637,189 HCM 0 0 15,930 King & King, Architects 0 / / / /
10-0680 Reconstruction 0-007-008 05/23/11 DONE DONE DONE 12/31/10 12/23/10 08/31/10 05/20/08 2,7,13,155,15,16 1,671,139 1,671,139 HCM 0 0 50,134 King & King, Architects 0 / / / /
12-0466 Reconstruction 0-007-009 STARTED ADD. REQ'D STARTED 11/20/12 11/20/12 09/28/12 / / 2,4,9,10,155,15,16 0 5,950,722 JMB 0 0 0 King & King Architects 0 / / / /
Camden High School:
09-1149 Reconstruction 0-012-017 10/26/10 DONE DONE DONE 03/25/10 03/19/10 05/24/07 05/15/07 2,4,8,9,155,15,16 17,512,721 15,602,221 HCM 0 0 350,254 King & King Architects 0 / / 04/27/12
10-1055 Reconstruction 0-012-018 06/01/11 DONE DONE DONE 03/23/11 03/11/11 03/21/11 03/08/11 2,8,9,10 1,680,000 1,680,000 HCM 0 0 0 King & King Architects 0 / / 02/28/13
12-0467 Reconstruction 0-012-019 STARTED ADD. REQ'D STARTED 11/20/12 11/20/12 09/28/12 05/15/07 2,4,8,9,10,155,15,16 0 22,194,526 JMB 0 0 0 King & King Architects 0 / / / /
Bus Maintenance Facility:
- Reconstruction 5-008-007 / / / / 08/31/10 / / 7,9,13,155,15,16 0 0 HCM 0 0 0 0 / / / /
12-0468 Reconstruction 5-008-008 STARTED ADD. REQ'D STARTED 11/20/12 11/20/12 09/28/12 / / 2,155,16 0 0 JMB 0 0 0 King & King Architects 0 / / / /
Administration:
08-1593 Reconstruction 9-002-002 10/09/09 DONE DONE DONE 05/05/09 05/01/09 02/23/09 05/20/08 2,4,8,155,15,16 160,000 0 HCM 0 0 0 King & King, Architects 0 / / 10/29/12
- Reconstruction 9-002-003 / / / / 08/31/10 / / 2,4,8,9,13,155,15,16 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Clinton Elementary:
08-1001 Reconstruction 0-001-008 06/03/09 DONE DONE DONE 01/02/09 12/23/08 08/29/08 02/27/08 2,7,8,9,10,155,15,16 991,903 991,903 JOD 0 0 167,906 Bernier Carr Associates 0 / / / /
09-1001 Reconstruction 0-001-009 11/12/10 DONE DONE DONE 03/03/10 02/26/10 11/18/09 01/26/10 10,13,155,16 1,227,086 1,227,086 JOD 0 0 0 Einhorn Yaffee Prescott P.C. 0 / / / /
- Reconstruction 0-001-010 / / / / 07/06/11 / / 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0 0 / / / /
Junior High:
08-1002 Reconstruction 0-002-009 06/03/09 DONE DONE DONE 01/02/09 12/23/08 08/29/08 02/27/08 2,4,7,8,9,10,155,15, 525,924 525,924 JOD 0 0 68,000 Bernier Carr Associates 0 / / / /
09-1002 Reconstruction 0-002-010 11/12/10 DONE DONE DONE 03/03/10 02/26/10 11/18/09 01/26/10 10,13,155,16 1,030,650 0 JOD 0 0 0 Einhorn Yaffee Prescott P.C. 0 / / / /
- Reconstruction 0-002-011 / / / / 07/06/11 / / 2,4,8,9,10,155,15,16 0 0 JOD 0 0 0 0 / / / /
Senior High:
08-1003 Reconstruction 0-005-008 06/03/09 DONE DONE DONE 01/02/09 12/23/08 08/29/08 02/27/08 2,4,7,8,9,10,155,15, 1,166,924 1,166,924 JOD 0 0 191,979 Bernier Carr Associates 0 / / / /
09-1003 Reconstruction 0-005-009 11/12/10 DONE DONE DONE 03/03/10 02/26/10 11/18/09 01/26/10 10,13,155,16 800,060 0 JOD 0 0 0 Einhorn Yaffee Prescott P.C. 0 / / / /
- Reconstruction 0-005-010 / / / / 07/06/11 / / 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Storage Garage:
12-0126DB Discovered Building 2-016-001 09/24/12 DONE DONE DONE 08/28/12 08/28/12 05/17/12 / / 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
K-12 School:
08-0573 Additions and Alterations 0-002-008 04/03/09 DONE DONE DONE 10/23/08 10/20/08 06/22/07 05/20/08 02 - 16 2,696,113 2,696,113 DDJ 0 0 192,916 March Associates 0 / / / /
10-0301 Reconstruction 0-002-009 12/16/10 DONE DONE DONE 09/29/10 09/23/10 03/23/10 05/20/08 2,16 42,774 42,774 DDJ 0 0 0 March Associates 0 / / 09/13/11
Beekman Gym:
08-0574 Additions and Alterations 0-005-006 04/03/09 DONE DONE DONE 10/23/08 10/20/08 06/22/07 05/20/08 02 - 16 240,512 240,512 DDJ 0 0 0 March Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Sulphur Springs Elementary:
07-1798 Reconstruction 0-002-011 12/08/08 DONE DONE DONE 03/15/08 03/13/08 11/30/06 09/25/07 2,4,8,9,10,155,15,16 867,242 867,242 MGL 0 0 42,160 King & King, Architects 0 / / 05/13/13
11-0141 Reconstruction 0-002-012 10/31/11 DONE DONE DONE 08/25/11 08/25/11 12/11/06 09/25/07 2,4,8,9,10,155,15,16 234,300 234,300 DDJ 0 0 22,258 King & King Architects 0 / / 05/20/13
Jr/Sr High School:
07-1799 Reconstruction 0-003-010 12/08/08 DONE DONE DONE 03/15/08 03/13/08 11/30/06 09/25/07 2,4,8,9,10,155,15,16 1,242,330 1,242,330 MGL 0 0 61,000 King & King, Architects 0 / / 04/13/13
11-0142 Reconstruction 0-003-011 10/31/11 DONE DONE DONE 08/25/11 08/25/11 12/11/06 09/25/07 2,4,8,9,10,155,15,16 237,000 237,000 DDJ 0 0 22,515 King & King Architects 0 / / 05/20/13
Middle School:
07-1800 Reconstruction 0-007-006 12/08/08 DONE DONE DONE 03/15/08 03/13/08 11/30/06 09/25/07 2,4,8,10,13,155,15,1 907,837 907,837 MGL 0 0 44,000 King & King, Architects 0 / / 05/13/13
11-0143 Reconstruction 0-007-007 10/31/11 DONE DONE DONE 08/25/11 08/25/11 12/11/06 09/25/07 2,4,8,10,155,15,16 121,700 121,700 DDJ 0 0 11,561 King & King Architects 0 / / 05/20/13
Storage Building-Oneida Street:
07-1113DB Discovered Building 2-010-001 12/08/08 DONE DONE DONE 12/13/07 12/07/07 12/11/07 / / 0 0 MGL 0 0 0 King & King, Architects 0 / / / /
New Press Box:
07-1114DB Discovered Building 7-009-001 10/17/08 DONE DONE DONE 12/13/07 12/07/07 12/11/07 / / 0 0 MGL 0 0 0 King & King, Architects 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior Senior High School:
07-2295 Reconstruction 0-001-011 08/27/08 DONE DONE DONE 07/01/08 06/16/08 04/10/08 04/26/07 7 250,260 250,260 HCM 0 0 34,535 Bernier Carr Associates 0 / / / /
08-1541 Reconstruction 0-001-012 08/12/09 DONE DONE DONE 04/24/09 04/21/09 01/02/09 05/15/07 8,16 184,807 184,807 HCM 0 0 25,504 Bernier Carr Associates 0 / / / /
09-0745 Reconstruction 0-001-013 05/24/10 DONE DONE DONE 01/20/10 01/19/10 01/07/10 05/15/07 155,15 45,000 0 HCM 0 0 0 Bernier Carr Associates 0 / / / /
Remsen Elementary School:
08-1542 Reconstruction 0-006-007 08/12/09 DONE DONE DONE 04/24/09 04/21/09 01/02/09 05/15/07 8,16 64,933 64,933 HCM 0 0 8,961 Bernier Carr Associates 0 / / / /
09-1474 Reconstruction 0-006-008 09/13/10 DONE DONE DONE 05/28/10 05/24/10 03/31/10 05/18/10 155,15,16 177,000 177,000 HCM 0 0 0 Bernier Carr Associates 0 / / 07/18/12
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Francis Bellamy School:
08-1300 Additions and Alterations 0-001-007 03/25/09 DONE DONE DONE 02/26/09 02/25/09 02/05/07 07/17/08 02 - 16 11,760,000 8,012,795 JOD 0 0 3,915,833 March Associates 0 / / / /
Jerry C. Clough Elementary:
08-1586 Reconstruction 0-004-010 06/01/09 DONE DONE DONE 05/05/09 04/27/09 02/01/07 06/20/00 2,4,7,8,9,10,155,15, 1,057,451 1,057,451 JOD 0 0 0 March Associates 0 / / / /
10-0351 Reconstruction 0-004-011 01/25/11 DONE DONE DONE 10/12/10 10/05/10 11/23/09 01/26/10 2,4,7,8,9,10,155,15, 2,240,741 1,700,000 JOD 0 0 0 March Associates 0 / / / /
Gansevoort Elementary:
10-0835 Reconstruction 0-008-012 06/09/11 DONE DONE DONE 02/08/11 02/07/11 02/05/07 01/26/10 2,4,7,8,9,10,14,155, 6,600,000 0 JOD 0 0 0 March Associates 0 / / / /
Strough Junior High:
07-2321 Reconstruction 0-012-020 01/28/09 DONE DONE DONE 07/08/08 06/20/08 02/05/07 06/20/00 2,4,7,8,9,10,13,155, 6,702,352 6,702,352 JOD 0 0 0 March Associates 0 / / / /
12-0525 Reconstruction 0-012-021 STARTED DONE UNREVIEWED12/11/12 12/10/12 10/21/11 12/06/11 2,4,7,8,9,10,13,14,1 0 27,724,320 DDJ 0 0 0 March Associates 0 / / / /
Ridge Mills School:
08-0855 Reconstruction 0-013-006 11/10/08 DONE DONE DONE 12/04/08 12/01/08 02/05/07 10/15/08 7 82,552 82,552 JOD 0 0 0 March Associates 0 / / / /
09-1084 Reconstruction 0-013-007 08/04/10 DONE DONE DONE 03/16/10 03/09/10 11/23/09 01/26/10 2,4,7,8,9,10,13,155, 5,900,000 5,900,000 JOD 0 0 0 March Associates 0 / / 03/06/13
John Joy Elementary:
11-0190 Reconstruction 0-018-012 UNREVIEWED
STARTED UNREVIEWED09/20/11 09/16/11 02/05/07 / / 2,4,7,8,9,10,155,15, 0 5,800,140 JOD 0 0 0 March Associates 0 / / / /
Denti Elementary:
08-1299 Reconstruction 0-023-011 03/25/09 DONE DONE DONE 02/26/09 02/25/09 02/01/07 06/17/08 2,4,7,8,9,10,155,15, 3,900,000 3,900,000 JOD 0 0 81,900 March Associates 0 / / / /
11-0740 Reconstruction 0-023-012 06/22/12 DONE DONE DONE 01/31/12 01/31/12 11/23/09 01/26/10 2,4,7,8,9,10,13,155, 9,800,000 0 JOD 0 0 0 March Associates 0 / / / /
Consolidated Maintenance Facility:
11-1158DB Discovered Building 3-030-001 ADDENDUM REQ'D 04/20/12 04/19/12 06/11/03 / / 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Memorial Park School:
07-1835 Reconstruction 0-003-011 12/17/08 DONE DONE DONE 03/19/08 03/13/08 11/09/07 06/28/05 8,13 38,500 38,500 DDJ 0 0 0 Ashley McGraw Architects 0 / / / /
08-0935 Reconstruction 0-003-012 07/16/09 DONE DONE DONE 12/16/08 12/12/08 11/21/07 06/24/08 2,7,8,9,10,155,15,16 1,099,604 1,099,604 DDJ 0 0 54,980 Ashley McGraw Architects 0 / / / /
11-1411 Reconstruction 0-003-013 07/12/12 DONE DONE DONE 06/18/12 06/15/12 02/24/12 06/25/05 16 145,000 145,000 DDJ 0 0 0 March Associates 0 / / 06/22/13
MS/High School:
07-1836 Reconstruction 0-008-010 12/17/08 DONE DONE DONE 03/19/08 03/13/08 11/09/07 06/28/05 8,13 136,500 136,500 DDJ 0 0 0 Ashley McGraw Architects 0 / / / /
08-0936 Reconstruction 0-008-011 07/16/09 DONE DONE DONE 12/16/08 12/12/08 11/21/07 06/24/08 2,7,8,9,10,155,15,16 3,722,396 3,722,396 DDJ 0 0 186,120 Ashley McGraw Architects 0 / / / /
11-1412 Reconstruction 0-008-012 07/12/12 DONE DONE DONE 06/18/12 06/15/12 02/24/12 06/25/08 16 203,000 203,000 DDJ 0 0 0 March Associates 0 / / 06/03/13
New Waterville Library:
- PR Additions and Alterations 6-014-002 / / / / 07/28/09 / / 02 - 16 0 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
W.A. Wettel ES:
07-1173 Reconstruction 0-002-006 08/13/08 DONE DONE DONE 12/21/07 12/19/07 07/24/07 10/17/07 2,4,7,8,9,10,155,15, 878,913 878,913 HCM 0 0 72,949 King & King, Architects 0 / / / /
J.D. George ES:
07-1174 Reconstruction 0-005-006 08/13/08 DONE DONE DONE 12/21/07 12/19/07 07/24/07 10/17/07 2,4,7,8,9,10,155,15, 668,910 668,910 HCM 0 0 55,519 King & King, Architects 0 / / / /
VVS MS/HS:
07-1175 Reconstruction 0-006-010 08/13/08 DONE DONE DONE 12/21/07 12/19/07 07/24/07 10/17/07 2,4,7,8,9,10,155,15, 1,950,288 1,950,288 HCM 0 0 161,873 King & King, Architects 0 / / / /
09-1386 Reconstruction 0-006-011 05/12/10 DONE DONE DONE 05/06/10 04/30/10 07/24/07 02/08/10 2,4,7,8,9,10,155,15, 138,750 138,750 HCM 0 0 0 King & King Architects 0 / / / /
E.A. McAllister Elementary:
07-1176 Reconstruction 0-007-006 08/13/08 DONE DONE DONE 12/21/07 12/19/07 07/24/07 10/17/07 2,4,7,8,9,10,155,15, 984,334 984,334 HCM 0 0 81,699 King & King, Architects 0 / / / /
Maintenance Building:
07-1178 Reconstruction 3-004-001 08/13/08 DONE DONE DONE 12/21/07 12/19/07 01/21/09 10/17/07 2,13 163,491 0 HCM 0 0 0 King & King, Architects 0 / / / /
Bus Garage:
07-1177 Reconstruction 5-003-002 08/13/08 DONE DONE DONE 12/21/07 12/19/07 07/24/07 10/17/07 2,4,7,8,9,10,13,14,1 1,154,064 1,154,064 HCM 0 0 0 King & King, Architects 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Gen. Wm. Floyd Elementary:
07-1244 Reconstruction 0-001-009 07/22/08 DONE DONE DONE 12/27/07 12/24/07 01/11/07 03/21/07 16 270,037 269,450 HCM 0 0 25,613 King & King, Architects 0 / / 01/24/11
09-0920 Reconstruction 0-001-010 05/06/10 DONE DONE DONE 02/19/10 02/16/10 12/10/09 05/15/07 2,155,15,16 790,666 774,375 HCM 0 0 0 King & King Architects 0 / / 01/24/11
10-0933 Reconstruction 0-001-011 06/09/11 DONE DONE DONE 03/04/11 02/18/11 02/10/11 05/15/07 2,7,9,15,16 260,003 323,330 HCM 0 0 0 King & King Architects 0 / / / /
- Reconstruction 0-001-012 / / / / 05/06/11 / / 7,9,155,15 0 0 HCM 0 0 0 0 / / / /
12-0345 Reconstruction 0-001-013 DONE DONE ADD. REQ'D10/29/12 10/29/12 06/20/12 09/19/12 2,8,9,10,13,155,15,1 0 7,492,716 MFS 0 0 0 King & King Architects 787,644 / / / /
Middle School:
07-1245 Reconstruction 0-003-012 07/22/08 DONE DONE DONE 12/27/07 12/24/07 01/12/07 03/21/07 2,9,155,15,16 950,397 950,347 HCM 0 0 91,085 King & King, Architects 0 / / 01/24/11
12-0346 Reconstruction 0-003-013 DONE DONE ADD. REQ'D10/29/12 10/29/12 06/20/12 09/19/12 2,8,9,10,155,15,16 0 11,904,760 MFS 0 0 0 King & King Architects 531,341 / / / /
Garage and Shop:
12-0347 Reconstruction 0-004-009 DONE DONE ADD. REQ'D10/29/12 10/29/12 06/20/12 09/19/12 2,8,9,10,13,155,15,1 0 1,434,888 MFS 0 0 0 King & King Architects 98,518 / / / /
Holland Patent Elementary:
07-1246 Additions and Alterations 0-005-009 07/22/08 DONE DONE DONE 12/27/07 12/24/07 01/12/07 03/21/07 02 - 16 3,671,948 1,882,890 HCM 0 0 109,936 King & King, Architects 0 / / 01/24/11
12-0348 Reconstruction 0-005-011 DONE DONE ADD. REQ'D10/29/12 10/29/12 06/20/12 09/19/12 2,8,9,10,13,155,15,1 0 7,353,962 MFS 0 0 0 King & King Architects 265,227 / / / /
Senior High School:
07-1247 Reconstruction 0-008-010 07/22/08 DONE DONE DONE 12/27/07 12/24/07 01/11/07 03/21/07 2,4,7,8,9,10,155,15, 3,564,452 3,566,161 HCM 0 0 342,182 King & King, Architects 0 / / 01/24/11
11-0200 Reconstruction 0-008-011 05/16/11 DONE DONE DONE 09/26/11 09/26/11 05/19/11 05/03/11 9,15 197,632 197,632 HCM 0 0 0 King & King Architects 0 / / / /
12-0349 Reconstruction 0-008-012 DONE DONE ADD. REQ'D10/29/12 10/29/12 06/20/12 09/19/12 2,8,9,10,13,155,15,1 0 17,956,706 MFS 0 0 0 King & King Architects 851,648 / / / /
Bus Garage:
09-0921 Reconstruction 5-006-007 05/06/10 DONE DONE DONE 02/19/10 02/16/10 / / 05/15/07 2,4,7,8,9,155,15,16 376,487 376,487 HCM 0 0 0 King & King Architects 0 / / 01/24/11
12-0350 Reconstruction 5-006-008 DONE DONE ADD. REQ'D10/29/12 10/29/12 06/20/12 09/19/12 2,8,9,10,13,155,15,1 0 0 MFS 0 0 0 King & King Architects 98,950 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Utica Sr. Academy At Proctor:
10-0302 Additions and Alterations 0-002-007 01/20/11 DONE DONE DONE 09/30/10 09/29/10 11/04/08 07/29/08 02 - 16 45,000,000 0 HCM 0 0 900,000 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-002-008 / / / / 11/04/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
Albany Street School:
09-0213 Additions and Alterations 0-003-006 01/15/10 DONE DONE DONE 09/14/09 09/14/09 11/04/08 07/29/08 02 - 16 7,486,000 6,828,392 HCM 0 0 781,968 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-003-007 / / / / 11/04/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
Chris Columbus School:
08-1539 Reconstruction 0-007-007 05/07/09 DONE DONE DONE 04/24/09 04/20/09 11/04/08 07/29/08 2,4,7,8,9,10,155,15, 1,344,072 1,344,072 HCM 0 0 26,881 Stieglitz Snyder Architecture 0 / / / /
11-0589 Reconstruction 0-007-008 03/08/13 DONE DONE DONE 01/05/12 12/30/11 11/04/08 07/29/08 10,13,16 7,175,970 0 DDJ 0 0 143,519 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-007-009 / / / / 03/24/09 / / 7 0 0 HCM 0 0 0 0 / / / /
Roscoe Conkling School:
09-0212 Reconstruction 0-008-006 12/28/09 DONE DONE DONE 09/14/09 09/14/09 11/04/08 07/29/08 2,4,7,155,15,16 9,396,800 8,784,450 HCM 0 0 583,322 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-008-007 / / / / 11/04/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
John F Hughes School:
08-1540 Reconstruction 0-009-006 05/07/09 DONE DONE DONE 04/24/09 04/20/09 11/04/08 07/29/08 2,4,7,8,9,10,155,15, 708,497 708,497 HCM 0 0 14,170 Stieglitz Snyder Architecture 0 / / / /
11-0569 Reconstruction 0-009-007 04/19/12 DONE DONE DONE 12/30/11 12/28/11 11/04/08 07/29/08 10,13,16 9,547,430 0 HCM 0 0 190,949 Stieglitz Snyder Architecture 0 / / / /
Thomas Jefferson School:
09-0256 Additions and Alterations 0-010-008 01/15/10 DONE DONE DONE 09/22/09 09/21/09 11/04/08 07/29/08 02 - 16 8,288,200 7,785,588 HCM 0 0 365,292 Stieglitz Snyder Architecture 0 / / / /
Hugh R. Jones School:
11-0590 Reconstruction 0-011-008 04/24/12 DONE DONE DONE 01/05/12 12/30/11 11/04/08 07/29/08 2,4,7,8,9,10,155,15, 7,139,690 0 HCM 0 0 142,794 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-011-009 / / / / 11/04/08 / / 10,13,16 0 3,311,526 HCM 0 0 0 0 / / / /
Kernan School:
11-0570 Reconstruction 0-013-007 04/25/13 DONE DONE DONE 12/30/11 12/28/11 11/04/08 07/29/08 2,4,7,8,10,155,15,16 12,476,240 0 HCM 0 0 249,525 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-013-008 / / / / 11/04/08 / / 10,13,16 0 0 DDJ 0 0 0 0 / / / /
- Reconstruction 0-013-009 / / / / 11/05/08 / / 10,13,16 0 0 DDJ 0 0 0 0 / / / /
- Reconstruction 0-013-010 / / / / 03/24/09 / / 7 0 0 HCM 0 0 0 0 / / / /
Watson Williams - New K-6:
- Reconstruction 0-015-007 / / / / 07/16/08 / / 10,16 0 0 HCM 0 0 0 0 / / / /
11-0591 Additions and Alterations 0-015-008 03/06/13 DONE DONE DONE 01/05/12 12/30/11 11/04/08 07/29/08 02 - 16 7,471,830 0 HCM 0 0 149,436 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-015-009 / / / / 11/05/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
M. L. King School:
11-0571 Reconstruction 0-016-008 04/18/12 DONE DONE DONE 12/30/11 12/28/11 11/04/08 07/29/08 2,4,7,8,9,10,155,15, 6,947,170 5,904,222 HCM 0 0 138,943 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-016-009 / / / / 11/05/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
Gen. Herkimer School:
09-0214 Additions and Alterations 0-022-008 01/05/10 DONE DONE DONE 09/14/09 09/14/09 11/04/08 07/29/08 02 - 16 9,506,900 8,456,734 HCM 0 0 507,753 Stieglitz Snyder Architecture 0 / / / /
- Reconstruction 0-022-009 / / / / 11/05/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
Wetmore Street School:
- Reconstruction 0-023-001 / / / / 11/04/08 / / 2,4,7,8,9,10,155,15, 0 0 HCM 0 0 0 0 / / / /
- Reconstruction 0-023-002 / / / / 11/05/08 / / 10,13,16 0 0 HCM 0 0 0 0 / / / /
John F Kennedy Junior H.S.:
08-1323 Additions and Alterations 0-026-008 05/13/09 DONE DONE DONE 03/10/09 03/02/09 11/04/08 07/29/08 02 - 16 409,000 409,000 HCM 0 0 8,180 Stieglitz Snyder Architecture 0 / / / /
09-0255 Additions and Alterations 0-026-009 12/15/09 DONE DONE DONE 09/22/09 09/21/09 11/04/08 07/29/08 02 - 16 1,543,591 1,543,591 HCM 0 0 30,872 Stieglitz Snyder Architecture 0 / / / /
10-0303 Reconstruction 0-026-010 12/22/10 DONE DONE DONE 09/30/10 09/29/10 11/05/08 07/29/08 10,13,16 13,491,000 13,491,000 HCM 0 0 269,820 Stieglitz Snyder Architecture 0 / / / /
J. Donovan Junior High School:
09-0254 Additions and Alterations 0-031-006 11/12/09 DONE DONE DONE 09/22/09 09/21/09 11/04/08 07/29/08 02 - 16 128,250 128,250 HCM 0 0 2,565 Stieglitz Snyder Architecture 0 / / / /
11-0572 Reconstruction 0-031-007 05/08/12 DONE DONE DONE 12/30/11 12/28/11 11/05/08 07/29/08 10,13,16 12,751,850 12,751,850 DDJ 0 0 255,037 Stieglitz Snyder Architecture 0 / / / /
:
09-0894 Reconstruction 1-017-L01 02/24/10 DONE DONE DONE 02/17/10 02/10/10 02/12/10 / / 0 0 HCM 0 0 0 Stieglitz Snyder Architecture 0 / / / /
Leased Bus Garage:
10-0929TQ Temporary Quarters 5-043-001 05/11/11 DONE DONE DONE 03/03/11 03/03/11 03/14/08 / / 0 0 HCM 0 0 0 0 / / / /
Districtwide:
09-0458 New Construction 7-999-001 01/15/10 DONE DONE DONE ***SHPO RESPONSE*** 4,890,000 HCM 0 0 93,500 Stieglitz Snyder Architecture 0 / / / /
10-0458 Reconstruction 7-999-002 01/20/11 DONE DONE DONE 11/12/10 11/12/10 11/12/10 07/29/08 13,16 8,110,000 0 HCM 0 0 162,200 Stieglitz Snyder Architecture 0 / / / /
11-0573 Reconstruction 7-999-003 06/27/12 DONE DONE DONE 12/30/11 12/28/11 09/27/11 07/29/08 10,16 8,711,000 0 HCM 0 0 174,220 Stieglitz Snyder Architecture 0 / / / /
11-0592 Reconstruction 7-999-004 ADDENDUM REQ'D 01/05/12 12/30/11 09/27/11 07/29/08 10,16 0 0 HCM 0 0 0 Stieglitz Snyder Architecture 0 / / / /
Westminster Presbyterian Church:
10-0804TQ Temporary Quarters 8-044-001 04/05/11 DONE DONE DONE 02/07/11 01/21/11 09/08/10 / / 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Westmoreland Jr/SrHigh School:
12-0872 Reconstruction 0-001-012 05/15/13 DONE DONE DONE 02/20/13 02/19/13 01/17/12 11/14/12 2,4,7,8 1,470,000 1,470,000 MFS 0 0 0 March Associates 0 / / / /
Elementary School:
12-0871 Reconstruction 0-003-010 05/15/13 DONE DONE DONE 02/20/13 02/19/13 01/17/12 11/14/12 2,4,7,9 2,510,000 2,510,000 MFS 0 0 0 March Associates 0 / / / /
New Middle School:
12-0873 Reconstruction 0-012-004 05/15/13 DONE DONE DONE 02/20/13 02/19/13 12/07/12 11/13/12 2,4,8,9,16 44,000 44,000 DDJ 0 0 0 March Associates 0 / / / /
New Storage Building:
- New Construction 2-015-001 / / / / 01/17/12 / / 02 - 16 0 0 DDJ 0 0 0 0 / / / /
Bus Garage:
12-0874 Reconstruction 5-004-006 05/15/13 DONE DONE DONE 02/20/13 02/19/13 12/07/12 11/13/12 4,8 30,000 30,000 MFS 0 0 0 March Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior Senior High:
10-0008 Reconstruction 0-004-011 02/28/11 DONE DONE DONE 07/08/10 07/01/10 08/19/09 02/23/10 2,4,7,8,9,10,155,15, 998,637 998,637 JOD 0 0 87,337 March Associates 0 / / 12/23/12
N. Walbran Elementary:
10-0009 Reconstruction 0-005-010 02/28/11 DONE DONE DONE 07/08/10 07/01/10 08/19/09 02/23/10 2,4,7,8,9,10,155,15, 1,207,799 1,207,799 JOD 0 0 0 March Associates 0 / / 12/23/12
Upper Bus Garage:
10-0010 Reconstruction 4-003-006 02/28/11 DONE DONE DONE 07/08/10 07/01/10 11/10/09 02/23/10 8 9,065 0 JOD 0 0 0 March Associates 0 / / 12/23/12
Lower Bus Garage:
09-1316 Reconstruction 5-002-005 06/15/10 DONE DONE DONE 04/15/10 04/09/10 08/19/09 12/12/06 2,15,16 42,000 42,000 JOD 0 0 0 March Associates 0 / / / /
10-0011 Reconstruction 5-002-006 02/28/11 DONE DONE DONE 07/08/10 07/01/10 06/02/10 02/23/10 8 7,620 0 JOD 0 0 0 March Associates 0 / / 12/23/12
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Parkway School:
09-1296 Additions and Alterations 0-001-011 09/23/10 DONE DONE DONE 04/14/10 04/08/10 11/12/08 04/28/09 02 - 16 2,878,697 2,878,697 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
09-0133 Reconstruction 0-001-012 02/02/10 DONE DONE DONE 08/19/09 08/17/09 07/02/09 04/28/09 10,16 92,194 92,194 DDJ 0 0 10,790 Tetra Tech Architects And Eni 0 / / / /
- Reconstruction 0-001-013 / / / / 01/21/11 / / 2,9,16 0 0 DDJ 0 0 0 0 / / / /
10-1309 Reconstruction 0-001-014 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,9,16 141,000 141,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
12-0498 Reconstruction 0-001-015 STARTED DONE UNREVIEWED11/29/12 11/13/12 09/04/12 04/28/09 2,4,7,8,9,10,155,15, 0 0 DDJ 0 0 0 March Associates 0 / / / /
Whitesboro Middle School:
09-1297 Additions and Alterations 0-002-011 09/23/10 DONE DONE DONE 04/14/10 04/08/10 11/12/08 04/28/09 02 - 16 3,494,025 5,524,650 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
08-1775 Reconstruction 0-002-012 07/03/09 DONE DONE DONE 07/01/09 06/29/09 05/29/09 04/28/09 2,4,7,8,9,16 343,765 343,765 DDJ 0 0 42,283 Tetra Tech Architects And Eni 0 / / / /
09-0134 Reconstruction 0-002-013 02/02/10 DONE DONE DONE 08/19/09 08/17/09 05/29/09 04/28/09 2,155,15,16 2,224,194 2,224,194 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-0979 Reconstruction 0-002-014 06/27/11 DONE DONE DONE 03/08/11 02/28/11 01/20/11 04/28/09 2,4,7,8,9,16 1,123,235 1,123,235 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-1310 Reconstruction 0-002-015 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,9,16 200,000 200,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
- Reconstruction 0-002-016 / / / / 09/04/12 / / 2,7,8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
Harts Hill Elementary:
09-0342 Additions and Alterations 0-004-015 02/03/10 DONE DONE DONE 10/26/09 10/21/09 11/12/08 04/28/09 02 - 16 2,579,075 2,579,075 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-0980 Reconstruction 0-004-016 06/21/11 DONE DONE DONE 03/08/11 02/28/11 01/20/11 04/28/09 2,4,7,8,9,15,16 13,988 13,988 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-1311 Reconstruction 0-004-017 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,4,7,9,10,155,15,16 182,000 182,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
Marcy Elementary School:
09-0343 Additions and Alterations 0-006-014 02/03/10 DONE DONE DONE 10/26/09 10/21/09 11/12/08 04/28/09 02 - 16 3,088,102 3,088,102 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-0981 Reconstruction 0-006-015 06/21/11 DONE DONE DONE 03/08/11 02/28/11 01/20/11 04/28/09 2,4,7,8,9,16 475,374 475,374 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-1312 Reconstruction 0-006-016 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,4,7,9,155,16 182,000 182,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
- Reconstruction 0-006-017 / / / / 09/04/12 / / 7,16 0 0 DDJ 0 0 0 0 / / / /
Deerfield Elementary:
09-1298 Additions and Alterations 0-009-012 09/23/10 DONE DONE DONE 04/14/10 04/08/10 11/12/08 04/28/09 02 - 16 2,336,652 2,336,652 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-0982 Reconstruction 0-009-013 06/21/11 DONE DONE DONE 03/08/11 02/28/11 01/20/11 04/28/09 2,4,7,8,9,15,16 176,063 176,063 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-1313 Reconstruction 0-009-014 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,9,16 115,000 115,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
Westmoreland Rd Elementary:
09-1299 Additions and Alterations 0-010-010 09/23/10 DONE DONE DONE 04/14/10 04/08/10 11/12/08 04/28/09 02 - 16 3,255,927 3,255,927 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-0983 Reconstruction 0-010-011 06/21/11 DONE DONE DONE 03/08/11 02/28/11 01/20/11 04/28/09 2,4,7,8,9,16 171,731 171,731 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-1314 Reconstruction 0-010-012 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,8,9,10,155,16 408,000 408,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
12-1049 Reconstruction 0-010-013 04/08/13 DONE DONE DONE 04/01/13 04/01/13 10/30/12 04/28/09 10,16 33,000 0 JOB 0 0 0 March Associates 0 / / / /
Senior High School:
09-0284PR Additions and Alterations 0-012-022 UNREVIEWED 10/05/09 10/02/09 11/12/08 / / 02 - 16 0 0 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
09-0344 Additions and Alterations 0-012-022 02/03/10 DONE DONE DONE 10/26/09 10/21/09 11/12/08 04/28/09 02 - 16 9,974,503 9,974,503 DDJ 0 0 973,335 Tetra Tech Architects And Eni 0 / / / /
09-0135 Reconstruction 0-012-023 02/02/10 DONE DONE DONE 08/19/09 08/17/09 05/29/09 04/28/09 2,155,15,16 1,211,372 1,211,372 DDJ 0 0 150,000 Tetra Tech Architects And Eni 0 / / / /
10-0984 Reconstruction 0-012-024 06/21/11 DONE DONE DONE 03/08/11 02/28/11 01/20/11 04/28/09 2,4,7,8,9,10,16 2,443,915 2,443,915 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
10-1315 Reconstruction 0-012-025 08/02/11 DONE DONE DONE 05/19/11 05/15/11 03/14/11 04/28/09 2,9,10,16 350,000 350,000 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
12-0499 Reconstruction 0-012-026 DONE DONE UNREVIEWED11/29/12 11/13/12 09/04/12 04/28/09 2,4,7,8,9,10,155,15, 0 25,058,775 DDJ 0 0 0 March Associates 0 / / / /
Administration Bldg:
- Additions and Alterations 1-003-006 / / / / 11/12/08 / / 02 - 16 0 0 DDJ 0 0 0 0 / / / /
- Reconstruction 1-003-007 / / / / 01/21/11 / / 2,4,7,8,9,16 0 0 DDJ 0 0 0 0 / / / /
- Reconstruction 1-003-008 / / / / 03/14/11 / / 2,9,16 0 0 DDJ 0 0 0 0 / / / /
Maintenance Garage:
10-1316 Reconstruction 3-005-003 08/02/11 DONE DONE DONE 05/19/11 05/15/11 01/21/11 04/28/09 2,4,7,8,9,16 52,000 0 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
Bus Garage:
09-1300 Additions and Alterations 5-008-007 09/23/10 DONE DONE DONE 04/14/10 04/08/10 11/12/08 04/28/09 02 - 16 399,163 399,163 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / / /
Concession Stand/Middle School:
10-1317 Additions and Alterations 7-015-002 08/02/11 DONE DONE DONE 05/19/11 05/15/11 01/21/11 04/28/09 02 - 16 402,000 0 DDJ 0 0 0 Tetra Tech Architects And Eni 0 / / 06/14/13
12-0500 Reconstruction 7-015-003 DONE DONE UNREVIEWED11/29/12 11/13/12 09/04/12 04/28/09 2,4,8,9,10,155,15,16 0 0 DDJ 0 0 0 March Associates 0 / / / /
District-Wide:
- Reconstruction 7-999-001 / / / / 09/04/12 / / 16 0 0 DDJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Occ Education Bldg:
07-1015 Additions and Alterations 0-011-006 06/24/08 DONE DONE DONE 12/03/07 12/03/07 05/05/06 05/15/07 02 - 16 38,550,000 38,550,000 JOD 0 0 0 March Associates 0 / / 03/08/13
Cims Proj. Ed. Comm.:
12-0928 Reconstruction 1-001-002 05/16/13 DONE DONE DONE 02/28/13 02/19/13 01/17/13 02/13/13 2,7,9,15,16 110,000 0 MFS 0 0 0 March Associates 0 / / / /
Brodock Press Building:
08-0897TQ Temporary Quarters 1-029-001 10/06/11 DONE DONE DONE 12/09/08 12/08/08 03/06/03 / / 0 0 MAC 0 0 0 0 / / / /
Holy Trinity Elementary School:
02-1131TQ Temporary Quarters 8-028-001 07/14/09 DONE DONE DONE 01/23/03 / / 08/15/02 / / 0 0 MAC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED