Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/20/14 at 13:08:10




WASHINGTONVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-01-02-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Washingtonville 5/6 School:
11-0259   Reconstruction               0-001-017  10/17/11     DONE    DONE       DONE      10/17/11   10/13/11   09/28/11   10/11/11   2,9,10                   230,000       230,000  JOD             0           0           0 Kaeyer, Garment & Davidson              0      08/14/12                       05/02/13           

          Senior High School:
10-0751   Reconstruction               0-007-018               STARTED DONE       ADD. REQ'D01/27/11   01/13/11   04/06/09   05/17/10   10                             0             0  JOD             0           0           0 Fellenzer Engineering                   0        /  /                           /  /             
13-0629   Reconstruction               0-007-019  01/06/14     DONE    DONE       DONE      10/25/13   10/25/13   09/04/13   05/20/08   2,13,155,15,16           462,000       462,000  MFS             0           0           0 Keystone Assoc Architects, En           0      10/13/14                       11/17/14           
13-1570   Reconstruction               0-007-020  06/09/14     DONE    DONE       DONE      05/27/14   05/23/14   04/25/14   05/20/14   8                        100,000             0  MFS             0           0           0 Keystone Assoc Architects, En           0        /  /                           /  /             

          Administration:
13-0794   Reconstruction               1-016-006  03/25/14     DONE    DONE       DONE      11/29/13   11/29/13   09/04/13   05/20/13   2,7                      171,000             0  MFS             0           0           0 Keystone Assoc Architects, En           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHESTER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-02-01-02
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
08-1520   Reconstruction               0-001-006  12/24/09     DONE    DONE       DONE      04/20/09   04/17/09   09/10/08   05/20/08   4,8,10,155,16            600,250             0  DDJ             0           0     600,250 Collins & Scoville Architects           0      08/31/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0870   Reconstruction               0-001-007  04/11/14     DONE    DONE       DONE      12/09/13   12/06/13   11/04/13   05/20/08   2,9                      200,000             0  MFS             0           0     200,000 Collins & Scoville Architects           0        /  /                           /  /             

          Chester Academy NEW MIDDLE/HS:
08-1521   Additions and Alterations    0-009-002  12/24/09     DONE    DONE       DONE      04/20/09   04/17/09   09/10/08   05/20/08   02 - 16                  289,750             0  DDJ             0           0     289,750 Collins & Scoville Architects           0      08/31/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0389   Reconstruction               0-009-003  03/19/14     DONE    DONE       DONE      09/19/13   09/18/13   08/20/13   08/07/13   155,16                   315,000       315,000  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CORNWALL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-03-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cornwall M.S.(fmly HS):
09-1105   Reconstruction               0-001-022  05/21/10     DONE    DONE       DONE      03/18/10   03/11/10   02/05/10   01/12/10   2,8,9,10,155,15,16       726,227       726,227  HCM             0           0     287,648 McGoey, Hauser and Edsall               0      02/15/11                         /  /             
13-0268   Reconstruction               0-001-023  04/02/14     DONE    DONE       DONE      08/23/13   08/22/13   05/10/13   07/15/13   8,10,155               2,761,558     2,761,558  MFS             0           0           0 Guth DeConzo Consutlting, P.C           0        /  /                           /  /             

          Elementary School:
13-0269   Reconstruction               0-002-013  04/02/14     DONE    DONE       DONE      08/23/13   08/22/13     /  /     07/15/13   8,10,155,15,16           436,391       436,391  MFS             0           0           0 Guth DeConzo Consutlting, P.C           0        /  /                           /  /             

          Willow Ave Elementary School:
13-0270   Reconstruction               0-004-013  04/02/14     DONE    DONE       DONE      08/23/13   08/22/13   05/10/13   07/15/13   10,155,16                944,233       944,233  MFS             0           0           0 Guth DeConzo Consutlting, P.C           0        /  /                           /  /             
13-1466   Reconstruction               0-004-014  05/22/14     DONE    DONE       DONE      04/18/14   04/16/14   02/19/14   05/20/14   2,7                      250,000       250,000  MFS             0           0           0 McGoey, Hauser and Edsall               0        /  /                           /  /             

          Cornwall Elementary:
13-0271   Reconstruction               0-006-013  04/02/14     DONE    DONE       DONE      08/23/13   08/22/13   05/10/13   07/15/13   10,155,16                534,592       534,592  MFS             0           0           0 Guth DeConzo Consutlting, P.C           0        /  /                           /  /             

          New High School:
13-0272   Reconstruction               0-012-004  04/02/14     DONE    DONE       DONE      08/23/13   08/22/13   05/10/13   07/15/13   10,155                   708,415       708,415  MFS             0           0           0 Guth DeConzo Consutlting, P.C           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PINE BUSH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-04-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Crispell SHOP:
12-1166   Reconstruction               0-001-004  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   155,15,16                 67,500        67,500  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
10-1003XX Reconstruction               0-001-006  06/02/11               CANCELLED          03/08/11   03/02/11   02/16/11   05/20/08   2,7                       40,573        40,573  HCM             0           0       7,303 Collins & Scoville Architects           0        /  /                           /  /             
13-1101   Reconstruction               0-001-007  01/28/14     DONE    DONE       DONE      01/27/14   01/24/14   01/13/14   04/02/13   7,8                      170,545       170,545  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          E.J. Russell School:
12-1167   Reconstruction               0-002-005  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   16                       118,125       118,125  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
09-0421   Reconstruction               0-002-009  03/16/10     DONE    DONE       DONE      11/18/09   11/10/09   08/22/08   05/20/09   2,7,8,9,10,155,15,16   1,610,050     1,610,050  HCM             0           0     289,809 Collins & Scoville Architects           0      10/12/12                       12/21/12           
11-0554XX Reconstruction               0-002-010  03/21/12               CANCELLED          12/27/11   12/23/11   12/19/11   05/20/08   2,9                      153,522       153,522  HCM             0           0      27,634 Collins & Scoville Architects           0        /  /                           /  /             
13-0475   Reconstruction               0-002-011  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,8,9,10                 506,727             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0632   Reconstruction               0-002-012  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/27/13   05/21/13   2,4,9,155,15,16          625,216             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Senior High School:
09-0422   Reconstruction               0-007-017  03/16/10     DONE    DONE       DONE      11/18/09   11/10/09   08/22/08   05/20/09   2,7,8,9,10,155,15,16   1,763,200     1,763,200  HCM             0           0     317,376 Collins & Scoville Architects           0      10/12/12                       12/21/12           
10-1004   Reconstruction               0-007-018  06/02/11     DONE    DONE       DONE      03/08/11   03/02/11   02/16/11   05/20/08   2,16                   1,096,913     1,096,913  HCM             0           0     197,444 Collins & Scoville Architects           0      10/18/12                       10/25/13           
10-1139   Reconstruction               0-007-019  06/13/11     DONE    DONE       DONE      04/07/11   04/01/11   02/16/11   05/20/08   2,7                       95,252        95,252  HCM             0           0      17,145 Collins & Scoville Architects           0      01/22/13                       10/25/13           
12-0232   Reconstruction               0-007-020  11/07/11     DONE    DONE       DONE      10/01/12   09/21/12   03/01/12   09/13/11   155,16                   617,911       617,911  DDJ             0           0           0 Fellenzer Engineering                   0      05/31/13                       10/23/13           
12-1168   Reconstruction               0-007-021  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   16                        39,375             0  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
13-0476   Reconstruction               0-007-022  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,7,8                  3,313,253             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0633   Reconstruction               0-007-023  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/26/13   05/21/13   2,7,155,15,16            652,405             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Circleville Primary:
12-1169   Reconstruction               0-009-008  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   16                        45,000        45,000  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
09-0423   Reconstruction               0-009-011  03/16/10     DONE    DONE       DONE      11/18/09   11/10/09   08/22/08   05/20/09   2,7,8,9,10,155,15,16   1,830,160     1,830,160  HCM             0           0     329,429 Collins & Scoville Architects           0      10/12/12                       12/21/12           
11-0555XX Reconstruction               0-009-012  04/04/12               CANCELLED          12/27/11   12/23/11   12/19/11   05/20/08   2,9                      252,720       252,720  HCM             0           0      45,490 Collins & Scoville Architects           0        /  /                           /  /             
13-0477   Reconstruction               0-009-013  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,8,9                    483,113             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0634   Reconstruction               0-009-014  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/27/13   05/21/13   2,4,7,8,9,155,15,16    1,612,021             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Pakanasink Elementary:
  -       Reconstruction               0-012-006                                              /  /       /  /     12/21/12     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0478   Reconstruction               0-012-011  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,7,8                    732,880             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0635   Reconstruction               0-012-012  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/27/13   05/21/13   2,155,15,16              323,070             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Crispell Middle School:
09-1422   Reconstruction               0-013-005  07/14/10     DONE    DONE       DONE      05/11/10   05/04/10   11/09/07   04/14/10   10,155                   202,000       202,000  HCM             0           0           0 J. Robert Folchetti & Associa           0      04/22/11                         /  /             
10-1005XX Reconstruction               0-013-007  06/02/11               CANCELLED          03/08/11   03/02/11   02/16/11   05/20/08   2,8,9                     89,299        89,299  HCM             0           0      16,074 Collins & Scoville Architects           0        /  /                           /  /             
12-1170   Reconstruction               0-013-008  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   155,15,16                855,000             0  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
13-0479   Reconstruction               0-013-009  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,7,8,9,10               792,283             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0636   Reconstruction               0-013-010  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/27/13   05/21/13   2,4,7,155,15,16        1,192,788             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Circleville Middle School:
11-0556XX Reconstruction               0-014-009  04/04/12               CANCELLED          12/27/11   12/23/11   12/19/11   05/20/08   2,9                      173,428       173,428  HCM             0           0      31,217 Collins & Scoville Architects           0        /  /                           /  /             
12-1171   Reconstruction               0-014-010  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   16                       258,750             0  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
13-0480   Reconstruction               0-014-011  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,7,8,9                  864,034             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0637   Reconstruction               0-014-012  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/26/13   05/21/13   2,155,15,16            1,301,479             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Pine Bush Elementary School:
12-1172   Reconstruction               0-015-009  03/10/14     DONE    DONE       DONE      05/07/13   05/07/13   12/21/12   04/25/13   16                        11,250             0  JMB             0           0           0 SHUTE Engineering, PLLC                 0        /  /                           /  /             
09-0424   Reconstruction               0-015-011  03/16/10     DONE    DONE       DONE      11/18/09   11/10/09   08/22/08   05/20/09   2,7,8,9,10,155,15,16     621,775       621,775  HCM             0           0     111,920 Collins & Scoville Architects           0      10/12/12                       12/21/12           
13-0481   Reconstruction               0-015-012  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   06/26/13   04/02/13   2,7,8                    768,380             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0638   Reconstruction               0-015-013  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/27/13   05/21/13   2,155,15,16              170,198             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          District Offices:
  -       Reconstruction               1-004-003                                              /  /       /  /     12/21/12     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0482   Reconstruction               1-004-004  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   07/26/13   04/02/13   155,16                    23,590             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             
13-0639   Reconstruction               1-004-005  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/27/13   05/21/13   2,155,15,16              134,879             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          District Storage:
  -       Reconstruction               2-008-002                                              /  /       /  /     12/21/12     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0753   Reconstruction               2-008-003  01/28/14     DONE    DONE       DONE      11/22/13   11/18/13   07/26/13   04/02/13   2,7,13,16                103,958             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Athletic Stor Bldg:
13-0483   Reconstruction               2-011-001  01/28/14     DONE    DONE       DONE      10/08/13   10/04/13   07/26/13   04/02/13   7,8                       66,640             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          District Storage Barn:
13-0640   New Construction             2-020-001  05/09/14     DONE    DONE       DONE      10/25/13   10/25/13   08/28/13   05/21/13   02 - 16                  145,275             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             

          Districtwide-NYPA:
09-0335   Reconstruction               7-999-002  12/14/09     DONE    DONE       DONE      10/23/09   10/20/09   02/23/09   05/20/08   2,10,13,16               562,500       562,500  HCM             0           0     101,250 Collins & Scoville Architects           0      10/12/12                       12/21/12           
10-1140   Reconstruction               7-999-003  06/27/11     DONE    DONE       DONE      04/07/11   04/01/11   03/16/11   05/20/08   16                       366,608       366,608  HCM             0           0      65,989 Collins & Scoville Architects           0      06/29/12                       10/25/13           
13-0410   Reconstruction               7-999-004  03/28/14     DONE    DONE       DONE      09/24/13   09/23/13   06/26/13   04/02/13   16                     1,749,525             0  JMB             0           0           0 Fuller and D'Angelo                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GOSHEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-06-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Charles J.Hooker Middle:
09-0843   Reconstruction               0-001-012  03/17/10     DONE    DONE       DONE      02/02/10   02/01/10   12/04/09   05/20/08   2,4                      135,000       135,000  HCM             0           0           0 Kaeyer, Garment & Davidson              0      09/10/10                         /  /             
14-0027   Reconstruction               0-001-013               STARTED DONE       UNREVIEWED01/16/14   01/10/14   02/04/14   01/28/14   2,14,155,15,16                 0    17,201,513  JMB             0           0           0 LAN Associates                          0        /  /                           /  /             

          Main Street School (see 1-002):
  -       Reconstruction               0-002-008                                              /  /       /  /     12/04/09     /  /     2,4,7                          0             0  HCM             0           0           0                                         0        /  /                           /  /             
09-0844   Reconstruction               0-002-008  03/17/10     DONE    DONE       DONE      02/02/10   02/01/10     /  /     05/20/08                            151,000       151,000                  0           0           0 Kaeyer, Garment & Davidson              0      10/09/10                         /  /             
10-1219   Reconstruction               0-002-009  05/24/11     DONE    DONE       DONE      04/22/11   04/21/11   04/22/11   05/20/08   2                        144,000             0  HCM             0           0           0 Kaeyer, Garment & Davidson              0      08/12/11                         /  /             

          Scotchtown Ave. Elementary School:
14-0028   Reconstruction               0-003-007               STARTED DONE       UNREVIEWED07/16/14   07/10/14   02/04/14   01/28/14   2,4,7,155,16                   0    13,269,669  JMB             0           0           0 LAN Associates                          0        /  /                           /  /             

          Intermediate School:
14-0030   Reconstruction               0-006-008               STARTED DONE       UNREVIEWED07/16/14   07/10/14   02/04/14   01/28/14   2,7,14,155,15,16               0     5,686,748  JMB             0           0           0 LAN Associates                          0        /  /                           /  /             

          High School:
14-0029   Reconstruction               0-008-010               STARTED DONE       UNREVIEWED07/16/14   07/10/14   02/04/14   01/28/14   2,9,14,155,15,16               0    30,671,900  JMB             0           0           0 LAN Associates                          0        /  /                           /  /             

          Main Street - Admin (fmly 0-002):
14-0031   Reconstruction               1-002-001               STARTED DONE       UNREVIEWED07/16/14   07/10/14   02/04/14   01/28/14   2,4,7,8,9,14,155,15,           0             0  JMB             0           0           0 LAN Associates                          0        /  /                           /  /             

          Bus Garage:
14-0032   Reconstruction               5-007-005               STARTED DONE       UNREVIEWED07/10/14   07/10/14   02/04/14   01/28/14   2                              0             0  JMB             0           0           0 LAN Associates                          0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HIGHLAND FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-09-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
  -       Reconstruction               0-004-013                                              /  /       /  /     05/04/12     /  /     2,4,7                          0             0  JOD             0           0           0                                         0        /  /                           /  /             

          James O'Neill High School:
09-0853   Reconstruction               0-008-013  04/19/10     DONE    DONE       DONE      02/03/10   02/01/10   11/19/09   01/20/09   2,7,8,9,10,16            586,889       586,889  JOD             0           0     114,044 Kaeyer, Garment & Davidson              0      10/24/13                       06/19/14           
  -       Reconstruction               0-008-014                                              /  /       /  /     05/04/12     /  /     2,8,9,10                       0             0  JOD             0           0           0                                         0        /  /                           /  /             
12-1154   Reconstruction               0-008-015  07/02/13     DONE    DONE       DONE      05/02/13   05/02/13   12/06/12   05/17/11   2,8,9,155,15,16          607,834             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          District Wide:
09-0949   Reconstruction               7-999-001  06/16/10     DONE    DONE       DONE      02/22/10   02/18/10   04/17/07   01/20/09   10,16                    199,845             0  JOD             0           0           0 Kaeyer, Garment & Davidson              0      09/12/13                       09/20/13           
  -       Reconstruction               7-999-002                                              /  /       /  /     03/23/11     /  /     13,16                          0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0103   Reconstruction               7-999-003  08/05/13     DONE    DONE       DONE      07/26/13   07/25/13   03/14/12   05/15/12   16                       257,750             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MIDDLETOWN CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-10-00-01
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Twin Towers Middle School (JHS):
10-0186   Reconstruction               0-001-025  10/26/10     DONE    DONE       DONE      08/31/10   08/27/10   09/04/09   08/27/09   4                        175,000       175,000  HCM             0           0           0 Robertson Strong Apgar Archit           0      08/24/11                       08/24/11           
10-1186   Additions and Alterations    0-001-026  08/17/11     DONE    DONE       DONE      04/12/11   04/08/11   03/26/10   05/18/10   02 - 16                   55,000        55,000  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0      11/20/13                       01/28/14           
11-0701   Reconstruction               0-001-027  03/19/12     DONE    DONE       DONE      01/23/12   01/23/12   09/02/11   05/17/11   8,155,16                 100,000       100,000  HCM             0           0           0 Robertson Strong Apgar Archit           0      06/27/12                       07/20/12           
11-1125   Reconstruction               0-001-028  06/26/13     DONE    DONE       DONE      04/12/12   04/12/12   09/19/11   09/01/11   2,4,9                    252,798       252,798  HCM             0           0           0 KSQ ARCHITECTS PC                 252,798      05/20/14                       07/16/14           
13-0627   Reconstruction               0-001-029  05/19/14     DONE    DONE       DONE      10/25/13   10/24/13   06/27/13   05/21/13   4,8,9,14,155,16        1,115,000     1,115,000  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Senior High School:
09-1514   Additions and Alterations    0-002-023  06/09/10     DONE    DONE       DONE      06/09/10   06/08/10   03/26/10   05/20/10   02 - 16                  100,000       100,000  HCM             0           0           0 Robertson Strong Apgar Archit           0      06/30/10                         /  /             
10-1183   Reconstruction               0-002-024  08/17/11     DONE    DONE       DONE      04/12/11   04/08/11   12/29/10   12/22/10   14                        80,000        80,000  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0      05/10/12                       06/05/12           
11-1126   Reconstruction               0-002-025  06/26/13     DONE    DONE       DONE      04/12/12   04/12/12   09/02/11   09/01/11   8,155,16                 990,027       990,027  HCM             0           0           0 KSQ ARCHITECTS PC                 990,027      05/20/14                       07/16/14           
13-0996   Reconstruction               0-002-026               DONE    DONE       ADD. REQ'D01/13/14   01/07/14   06/26/13   05/21/13   2,8,9,10,16                    0             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Moon Elementary School:
11-1127   Reconstruction               0-010-024  06/26/13     DONE    DONE       DONE      04/12/12   04/12/12   09/02/11   09/01/11   8,155,16                 258,190       258,190  HCM             0           0           0 KSQ ARCHITECTS PC                 258,190      05/20/14                       07/16/14           
13-0997   Reconstruction               0-010-025               DONE    DONE       ADD. REQ'D01/13/14   01/07/14   06/27/13   05/21/13   2,8,9,10,16                    0             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
13-1426   Reconstruction               0-010-026  03/13/14     DONE    DONE       DONE      04/02/14   03/28/14   02/21/14   02/21/14   2                         40,000        40,000  MFS             0           0           0 Kaeyer, Garment & Davidson              0      03/20/14                       06/09/14           

          William A. Carter (Mechanicstown):
11-1128   Reconstruction               0-012-015  06/26/13     DONE    DONE       DONE      04/12/12   04/12/12   09/02/11   09/01/11   8,155,16               1,205,672     1,205,672  HCM             0           0           0 KSQ ARCHITECTS PC               1,205,672      05/20/14                       07/16/14           
13-0998   Reconstruction               0-012-016               DONE    DONE       ADD. REQ'D01/13/14   01/07/14   06/27/13   05/21/13   2,8,9,10,16                    0             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Monhagen Middle School:
09-0588   Reconstruction               0-030-006  12/30/09     DONE    DONE       DONE      12/21/09   12/10/09   09/04/09   08/27/09   7                        250,000       250,000  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0      05/16/12                       10/23/12           
10-1185   Additions and Alterations    0-030-007  08/17/11     DONE    DONE       DONE      04/12/11   04/08/11   03/02/10   08/27/09   02 - 16                   45,000        45,000  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0      11/20/13                       01/26/14           
11-1129   Reconstruction               0-030-008  06/26/13     DONE    DONE       DONE      04/12/12   04/12/12   09/02/11   09/01/11   8,155,16                 381,353       381,353  HCM             0           0           0 KSQ ARCHITECTS PC                 381,353      05/20/14                       07/16/14           
13-0999   Reconstruction               0-030-009               DONE    DONE       ADD. REQ'D01/13/14   01/07/14   06/27/13   05/21/13   2,8,9,10,16                    0    25,359,948  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Maple Hill Elementary School:
11-1130   Reconstruction               0-032-009  06/26/13     DONE    DONE       DONE      04/12/12   04/12/12   09/02/11   09/01/11   8,155,16                 395,105       395,105  HCM             0           0           0 KSQ ARCHITECTS PC                 395,105      05/20/14                       07/16/14           
13-0995   Reconstruction               0-032-010  11/19/14     DONE    DONE       DONE      01/13/14   01/07/14   06/27/13   05/21/13   2,8,9,155,16           2,005,000             0  MFS             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          New Elementary School:
09-0373   New Construction             0-041-001  01/26/11     DONE    DONE       DONE      10/30/09   10/30/09   11/12/08   12/05/08   02 - 16               66,100,000    34,055,690  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0      08/02/13                       08/16/13           

          Circular Pavilion:
  -    DB Discovered Building          0-042-001                                              /  /       /  /     03/23/10     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Clemson Park House:
  -       Alterations                  1-043-001                                              /  /       /  /     03/24/10     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             
10-0900DB Discovered Building          1-043-001  03/15/11     DONE    DONE       DONE      02/23/11   02/15/11   03/23/10     /  /                                    0             0  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0        /  /                           /  /             

          Food Storage Building:
10-1184   Additions and Alterations    2-021-005  08/17/11     DONE    DONE       DONE      04/12/11   04/08/11   12/29/10     /  /     02 - 16                  175,000             0  HCM             0           0           0 RSA  (Robertson Strong Apgar)           0      05/10/12                         /  /             

          Land/Sea Storage Container:
02-1124DB Discovered Building          2-036-001  12/21/09     DONE    DONE       DONE      01/15/03     /  /     09/11/00     /  /     02 - 16                        0             0  BJB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MINISINK VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-11-01-04
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Slate Hill ES/MS:
10-0830   Reconstruction               0-001-008  04/07/11     DONE    DONE       DONE      02/08/11   02/07/11   02/08/11   02/05/08   2,8,9                    857,000     1,625,993  HCM             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          High School:
10-0831   Reconstruction               0-005-009  04/07/11     DONE    DONE       DONE      02/08/11   02/07/11   02/08/11   02/05/08   2,9,16                   394,332       603,826  HCM             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
13-1023   Reconstruction               0-005-010  07/16/14     DONE    DONE       DONE      01/15/14   01/14/14   12/17/13   02/05/08   8,9,16                   249,400             0  JMB             0           0      37,410 Tetra Tech Architects & Engin           0        /  /                           /  /             

          Middle School:
10-0832   Reconstruction               0-012-009  04/07/11     DONE    DONE       DONE      02/08/11   02/07/11   02/08/11   02/05/08   2,9,16                    93,742        93,742  HCM             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
13-1024   Reconstruction               0-012-010  07/16/14     DONE    DONE       DONE      01/15/14   01/14/14   12/17/13   02/05/08   155,15,16                409,000             0  JMB             0           0      61,350 Tetra Tech Architects & Engin           0        /  /                           /  /             

          Sewer Treatmnt Bldg(frmr7-018):
13-1025   Reconstruction               0-018-002  07/16/14     DONE    DONE       DONE      01/15/14   01/14/14   12/17/13   02/05/08   15,16                    171,600             0  JMB             0           0      25,740 Tetra Tech Architects & Engin           0        /  /                           /  /             

          Bus Maintenance Facility:
09-0583TQ Temporary Quarters           5-024-001  12/17/09     DONE    DONE       DONE      12/17/09   12/17/09     /  /       /  /                                    0             0  HCM             0           0           0 Fellenzer Engineering                   0        /  /                           /  /             

          New Bus Garage:
09-1048   New Construction             5-025-001  08/04/10     DONE    DONE       DONE      03/10/10   03/05/10   01/26/10   02/05/08   02 - 16                4,500,000     4,500,000  HCM             0           0           0 Tetra Tech Architects and Eng           0      08/15/11                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MONROE - WOODBURY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-12-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Main St. School:
09-0692   Reconstruction               0-002-008  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/16/09   12/09/09   2,155,15,16            2,306,805     2,306,805  JOD             0           0           0 ECG Engineering, LLC            2,306,805      07/01/11                       06/28/13           
10-1267   Reconstruction               0-002-009  07/26/11     DONE    DONE       DONE      05/10/11   05/05/11     /  /     03/18/09   2,4,8,9,14,155,15,16     330,000             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-002-010                                              /  /       /  /     03/23/11     /  /     2,4,8,9,14,155,15,16           0     8,210,592  JOD             0           0           0                                         0        /  /                           /  /             

          Central Valley Elem.(fmly Middle):
09-0693   Reconstruction               0-004-009  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/16/09   12/09/09   2,155,15,16            2,483,812     2,483,812  JOD             0           0           0 ECG Engineering, LLC            2,483,812      07/01/11                       06/28/13           

          Harriman Kindergarten Center:
09-0694   Reconstruction               0-005-004  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   155,16                   314,608       314,608  JOD             0           0           0 ECG Engineering, LLC              314,608      07/01/11                       06/28/13           

          Pine Tree Elementary:
09-0695   Reconstruction               0-006-007  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   11/06/09   12/09/09   2,155,15,16              415,716       415,716  JOD             0           0           0 ECG Engineering, LLC              415,716      07/01/11                       06/28/13           
10-1268   Reconstruction               0-006-009  07/26/11     DONE    DONE       DONE      05/10/11   05/05/11   03/24/11   03/18/09   2,9,155,15,16            822,000       822,000  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Middle School (fmly Sr. High):
09-0696   Reconstruction               0-009-014  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/16/09   12/09/09   2,8,155,15,16          2,791,018     2,791,018  JOD             0           0           0 ECG Engineering, LLC            2,791,018      07/01/11                       06/28/13           
10-1269   Reconstruction               0-009-015  07/26/11     DONE    DONE       DONE      05/10/11   05/05/11   03/24/11   03/18/09   2,9,14,16                420,000       420,000  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Smith Clove Elem.(fmly Cent.Valley):
09-0697   Reconstruction               0-012-007  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   2,155,15,16              403,207       403,207  JOD             0           0           0 ECG Engineering, LLC              403,207      07/01/11                       06/28/13           
10-1270   Reconstruction               0-012-008  07/26/11     DONE    DONE       DONE      05/10/11   05/05/11   03/24/11   03/18/09   2,9,155,15,16            630,000             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Sapphire Lake Elementary School:
09-0698   Reconstruction               0-015-007  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   2,155,16                 939,060       939,060  JOD             0           0           0 ECG Engineering, LLC              939,060      07/01/11                       08/20/13           
10-1271   Additions and Alterations    0-015-010  07/26/11     DONE    DONE       DONE      05/10/11   05/05/11   03/24/11   03/18/09   02 - 16                  661,275             0  JOD             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          New High School:
09-0699   Reconstruction               0-021-006  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/16/09   12/09/09   2,155,15,16            1,495,604     1,495,604  JOD             0           0           0 ECG Engineering, LLC            1,495,604      07/01/11                       06/28/13           

          Education Center:
09-0700   Reconstruction               1-001-003  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   2,155,15,16              123,651             0  JOD             0           0           0 ECG Engineering, LLC              123,651      07/01/11                       06/28/13           

          Dormitory/Admin. Bldg:
09-0701   Reconstruction               1-018-004  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   2,155,15,16              522,516             0  JOD             0           0           0 ECG Engineering, LLC              522,516      07/01/11                       06/28/13           

          Garage/ Utility Bldg.:
09-0702   Reconstruction               2-019-002  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   2,155,15,16              165,937             0  JOD             0           0           0 ECG Engineering, LLC              165,937      07/01/11                       06/28/13           

          Revised Bus Garage Storage:
09-0703XX Reconstruction               4-010-002                         CANCELLED          01/07/10   01/06/10   10/21/09   12/09/09   2,155,16                       0             0  JOD             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Bus Garage Maint. Bldg.:
09-0704   Reconstruction               5-003-003  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   2,155,16                 141,964       141,964  JOD             0           0           0 ECG Engineering, LLC              141,964      07/01/11                       06/28/13           

          Micro Computer Center (former lease0:
09-0705   Reconstruction               8-017-002  06/29/10     DONE    DONE       DONE      01/07/10   01/06/10   10/21/09   12/09/09   155,16                    21,102             0  JOD             0           0           0 ECG Engineering, LLC               21,102      07/01/11                       06/28/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




KIRYAS JOEL VILLAGE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-12-02-02
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Kiryas Joel Public School (fmly 8-01:
09-1223   Reconstruction               0-012-001  10/07/10     DONE    DONE       DONE      04/05/10   03/30/10   07/13/09   08/24/06   2,15,16                  181,325       181,325  DDJ             0           0     181,325 PENDERGAST & TERACH ARCHITECT           0      07/02/12                       02/21/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-13-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Maybrook Elementary School:
11-0606   Reconstruction               0-002-012  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   8,9,16                    39,550        39,550  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           

          Montgomery Elementary:
11-0607   Reconstruction               0-004-013  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   2,8,9,155,15,16          147,700       147,700  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           
  -       Reconstruction               0-004-014                                              /  /       /  /     10/30/14     /  /     155,15,16                      0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Walden Elementary School:
10-1305   Reconstruction               0-009-015  06/17/11     DONE    DONE       DONE      05/20/11   05/16/11   03/30/11   04/11/11   2                        295,198       295,198  JOD             0           0           0 Quality Environmental Solutio           0      10/05/11                       12/13/12           
  -       Reconstruction               0-009-016                                              /  /       /  /     04/13/11     /  /     2                              0     8,701,824  JOD             0           0           0                                         0        /  /                           /  /             
11-0608   Reconstruction               0-009-017  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   2,8,9,155,15,16           97,800        97,800  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           
  -       Reconstruction               0-009-018                                              /  /       /  /     10/30/14     /  /     4,155,15,16                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          East Coldenham Elementary:
11-0609   Reconstruction               0-013-016  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   4,8                       81,750        81,750  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           
12-1188   Reconstruction               0-013-017  05/15/13     DONE    DONE       DONE      05/13/13   05/13/13   04/17/13   05/17/11   2                        353,780       353,780  MFS             0           0           0 Bernier Carr Associates                 0      08/30/13                       01/23/14           
  -       Reconstruction               0-013-018                                              /  /       /  /     10/30/14     /  /     155,15,16                      0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Valley Central High School:
10-1214   Reconstruction               0-015-020  05/16/11     DONE    DONE       DONE      04/21/11   04/18/11   03/30/11   05/17/10   7                        907,154       907,154  JOD             0           0           0 Bernier Carr Associates                 0      10/26/11                         /  /             
10-1204   Reconstruction               0-015-021  10/28/10     DONE    DONE       DONE      04/19/11   04/14/11   03/31/11   10/12/10   7                        183,583       183,583  HCM             0           0           0 Bernier Carr Associates                 0      12/17/10                         /  /             
11-0610   Reconstruction               0-015-022  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   2,4,7,8,9,10,155,15,   2,144,588     2,144,588  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           
11-0531   Reconstruction               0-015-023  03/07/12     DONE    DONE       DONE      12/22/11   12/16/11   11/21/11   05/17/11   9,155,15,16              901,200       901,200  JOD             0           0           0 Bernier Carr Associates                 0      06/11/13                       07/09/13           
13-0820   Reconstruction               0-015-024  04/22/14     DONE    DONE       DONE      12/04/13   12/02/13   11/08/13   05/17/13   15                        56,000             0  MFS             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
  -       Reconstruction               0-015-025                                              /  /       /  /     10/29/14     /  /     2,4,8,9,13,155,15,16           0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-015-026                                              /  /       /  /     10/30/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Valley Middle School:
11-0611   Reconstruction               0-016-018  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   2,7                    1,905,485     1,905,485  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           
  -       Reconstruction               0-016-019                                              /  /       /  /     10/30/14     /  /     4,8,9,10,155,15,16             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Berea Elementary:
11-0612   Reconstruction               0-017-011  04/25/12     DONE    DONE       DONE      01/06/12   01/04/12   07/18/11   05/17/11   8,155                     63,580        63,580  JOD             0           0           0 Bernier Carr Associates                 0      12/03/13                       01/30/14           
11-0613   Reconstruction               0-017-012  05/03/12     DONE    DONE       DONE      01/06/12   01/04/12   10/18/11   05/17/11   2,9,155,16               961,193             0  JOD             0           0           0 Bernier Carr Associates                 0        /  /                           /  /             
  -       Reconstruction               0-017-013                                              /  /       /  /     10/30/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWBURGH CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-16-00-01
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Newburgh Free Academy:
10-0319   Reconstruction               0-001-020  02/15/11     DONE    DONE       DONE      10/05/10   09/29/10   09/24/09   03/27/07   2,4,8,9,10,155,15,16   3,368,200     3,368,200  HCM             0           0     530,535 Collins & Scoville Architects           0      09/12/11                       11/20/13           
12-0758   Reconstruction               0-001-021  09/17/13     DONE    DONE       DONE      02/01/13   01/25/13   10/04/12   03/27/07   2,4,7,8,9,10,155,15,     696,188       696,188  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-022                                              /  /       /  /     07/03/13     /  /     2,155,15,16                    0             0  JMB             0           0           0                                         0        /  /                           /  /             
14-0599   Reconstruction               0-001-023  11/17/14     DONE    DONE       DONE      11/10/14   11/07/14   10/01/14   03/27/07   4,7,16                   282,800             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          South Junior High School:
09-0736   Reconstruction               0-003-015  05/18/10     DONE    DONE       DONE      01/13/10   01/11/10   03/04/09   03/27/07   2,4,8,9,10,155,15,16   6,561,700     6,561,700  HCM             0           0   1,123,147 Sammel Architecture                     0        /  /                           /  /             

          NFA Auto Body Shop:
10-0320   Reconstruction               0-004-003  02/15/11     DONE    DONE       DONE      10/05/10   09/29/10   08/24/07   03/27/07   16                        60,737        60,737  MGL             0           0           0 Collins & Scoville Architects           0      09/12/11                       11/20/13           

          Chestnut Street:
09-0457   Additions and Alterations    0-005-004  12/08/09     DONE    DONE       DONE      11/20/09   11/17/09   01/19/05   02/15/05   02 - 16                   95,709        95,709  MGL             0           0           0 Sammel Architecture                     0      06/15/10                         /  /             

          Gidney Ave Memorial School:
09-0399   Reconstruction               0-006-009  04/30/10     DONE    DONE       DONE      11/06/09   11/04/09   08/24/07   03/13/07   2,4,8,9,10,155,15,16  10,243,125    10,243,125  MGL             0           0   1,672,112 Sammel Architecture                     0        /  /                           /  /             
10-1330   Reconstruction               0-006-010  08/12/11     DONE    DONE       DONE      05/24/11   05/17/11   05/19/11   03/21/07   2,4,8,9,10,155,15,16   4,089,094     4,089,094  HCM             0           0     572,473 Sammel Architecture                     0        /  /                           /  /             
12-0917   Alterations                  0-006-011  05/14/13     DONE    DONE       DONE      02/27/13   02/20/13   02/27/13   03/27/07   02 - 16                  450,772       450,772  JMB             0           0           0 Sammel Architecture                     0        /  /                           /  /             
13-0039   Reconstruction               0-006-012  07/19/13     DONE    DONE       DONE      07/11/13   07/11/13   06/19/13   06/18/13   8,9,155,15,16             39,000        39,000  JMB             0           0           0 Sammel Architecture                     0        /  /                           /  /             

          Horizons on the Hudson:
10-0321   Reconstruction               0-017-012  02/15/11     DONE    DONE       DONE      10/05/10   09/29/10   09/24/09   03/27/07   2,4,9,155,15,16        2,556,300     2,556,300  HCM             0           0     394,710 Collins & Scoville Architects           0      09/12/11                       11/20/13           

          Vails Gate Elementary:
08-0972   Reconstruction               0-018-005  10/26/11     DONE    DONE       DONE      12/26/08   12/18/08   03/23/04   03/27/07   2,4,8,9,10,155,15,16   1,632,580     1,632,580  MGL             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             
10-0668   Reconstruction               0-018-007  02/15/11     DONE    DONE       DONE      12/30/10   12/23/10   08/24/07   03/27/07   2,8,9,10,155,15,16     1,051,800     1,130,000  MGL             0           0     112,773 Minuta Architecture, PLLC               0        /  /                           /  /             

          Fostertown School:
12-0604   Reconstruction               0-026-008  04/02/13     DONE    DONE       DONE      12/26/12   12/23/12   08/24/07   03/27/07   2,4,9,155,15,16          789,000             0  MGL             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             
09-1322   Reconstruction               0-026-009  06/22/10     DONE    DONE       DONE      04/16/10   04/12/10   02/05/10   02/15/05   4,7                      247,706       213,061  HCM             0           0           0 Sammel Architecture                     0      12/01/10                         /  /             
10-1308   Reconstruction               0-026-010  07/26/11     DONE    DONE       DONE      05/19/11   05/04/11   05/17/11   03/13/07   9,10                     170,693       170,693  HCM             0           0      23,897 Sammel Architecture                     0        /  /                           /  /             

          Temple Hill School:
  -       Reconstruction               0-036-013                                              /  /       /  /     02/17/12     /  /     2,4                            0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Heritage Junior High School:
  -       Reconstruction               0-039-006                                              /  /       /  /     11/09/12     /  /     2,4,7,8,9,155,16               0    12,801,184  JMB             0           0           0                                         0        /  /                           /  /             
12-0612   Reconstruction               0-039-007  12/16/13     DONE    DONE       DONE      12/26/12   12/23/12   08/24/07   03/27/07   4,8,9,16                 415,000             0  MGL             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             
11-0005   Reconstruction               0-039-009  08/25/11     DONE    DONE       DONE      07/06/11   07/05/11   06/30/11   03/13/07   4,7,9,10                 555,817       555,817  HCM             0           0      77,814 Sammel Architecture                     0      02/22/13                       11/20/13           

          District-Wide:
13-1614   Reconstruction               7-999-002                       ADDENDUM REQ'D       06/13/14   06/12/14   04/04/14   05/21/13   16                             0   115,852,774  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Newburgh Preparatory Charter High Sc:
13-0066TQ Temporary Quarters           8-001-001  09/05/13     DONE    DONE       DONE      07/19/13   07/17/13   07/26/13     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PORT JERVIS CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-18-00-05
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School 7-8:
08-1763XX Additions and Alterations    0-005-011  01/11/10               CANCELLED          06/29/09   06/29/09   04/23/09   05/16/09   02 - 16                   74,875        74,875  DDJ             0           0           0 Collins & Scoville Architects           0      01/17/11                         /  /             
10-0523   Reconstruction               0-005-012  03/21/11     DONE    DONE       DONE      12/03/10   11/19/10   04/07/10   02/23/10   2,9,155,16               321,681       321,681  DDJ             0           0           0 Collins & Scoville Architects           0      11/15/11                       06/26/13           
11-0762   Reconstruction               0-005-013  06/07/12     DONE    DONE       DONE      02/08/12   02/07/12   11/01/11   12/13/11   2,7                      510,600       510,600  DDJ             0           0           0 Highland Associates                     0      09/01/12                       12/09/13           

          Hamilton Bicentennial ES K-6:
10-0524   Reconstruction               0-011-008  03/21/11     DONE    DONE       DONE      12/03/10   11/19/10   04/07/10   02/23/10   2,9,155,16               563,267       563,267  DDJ             0           0           0 Collins & Scoville Architects           0      11/15/11                       06/26/13           
09-1327   Reconstruction               0-011-009  06/16/10     DONE    DONE       DONE      04/16/10   04/13/10   04/07/10   02/23/10   2,8                    1,038,494     1,038,494  DDJ             0           0           0 Collins & Scoville Architects           0      08/31/11                       06/26/13           
10-0681   Reconstruction               0-011-010  05/10/11     DONE    DONE       DONE      12/31/10   12/23/10   11/30/10   02/23/10   4,8,9,10,155,15,16       261,445       261,445  DDJ             0           0           0 Highland Associates                     0      05/07/12                       12/09/13           
11-0434   Reconstruction               0-011-011  03/27/12     DONE    DONE       DONE      11/23/11   11/21/11   06/29/11   03/13/10   155,15,16              1,100,058     1,100,058  DDJ             0           0           0 Highland Associates                     0      10/15/12                       03/18/13           
11-0763   Reconstruction               0-011-012  06/07/12     DONE    DONE       DONE      02/09/12   02/07/12   11/01/11   12/13/11   2,4,8,9,155,15,16        698,700       698,700  DDJ             0           0           0 Highland Associates                     0      10/01/12                       03/18/13           
14-0461   Reconstruction               0-011-013                         UNREVIEWED         10/15/14   10/15/14   06/26/14   05/20/14   10                             0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
  -       Reconstruction               0-011-014                                              /  /       /  /     06/26/14     /  /     10                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Kuhl ES K-6/PJHS 9-12:
08-1739XX Additions and Alterations    0-012-021  01/11/10               CANCELLED          06/26/09   06/18/09   04/23/09   05/16/09   02 - 16                   74,875        74,875  DDJ             0           0           0 Collins & Scoville Architects           0      01/17/11                         /  /             
09-1328   Reconstruction               0-012-022  06/16/10     DONE    DONE       DONE      04/16/10   04/13/10   04/07/10   02/23/10   2,8,10                 2,713,446     2,713,446  DDJ             0           0     225,500 Collins & Scoville Architects           0      08/31/11                       06/26/13           
10-0525   Reconstruction               0-012-023  03/21/11     DONE    DONE       DONE      12/03/10   11/19/10   04/07/10   02/23/10   2,9,155,15,16          4,443,022     4,443,022  DDJ             0           0     450,918 Collins & Scoville Architects           0      11/15/11                       06/26/13           
09-1326   Reconstruction               0-012-024  06/03/10     DONE    DONE       DONE      04/16/10   04/13/10   04/07/10   02/23/10   2,155,15               1,126,263     1,126,263  DDJ             0           0           0 Collins & Scoville Architects           0      01/03/11                       06/26/13           
10-0682   Reconstruction               0-012-025  05/10/11     DONE    DONE       DONE      12/31/10   12/23/10   11/16/10   02/23/10   2,4,8,9,10,155,15,16   1,168,786     1,168,786  DDJ             0           0           0 Highland Associates                     0      05/07/12                       12/09/13           
11-0435   Reconstruction               0-012-026  03/27/12     DONE    DONE       DONE      11/23/11   11/21/11   06/29/11   03/13/10   2,4,8,9,10,155,15,16     299,714       299,714  DDJ             0           0           0 Highland Associates                     0      10/15/12                       03/18/13           
11-0764   New Construction             0-012-027  06/07/12     DONE    DONE       DONE      02/09/12   02/07/12   11/01/11   12/13/11   02 - 16                  640,700       640,700  DDJ             0           0           0 Highland Associates                     0      10/01/12                       03/18/13           
12-0876   Reconstruction               0-012-028  11/01/13     DONE    DONE       DONE      02/20/13   02/19/13   01/30/13   02/23/12   2,4,7,8,9,10,155,15,   1,077,395             0  MFS             0           0           0 Highland Associates                     0        /  /                           /  /             
14-0462   Reconstruction               0-012-029                         UNREVIEWED         10/15/14   10/15/14   06/26/14   05/20/14   2,4,8,9,10,155,15,16           0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
  -       Reconstruction               0-012-030                                              /  /       /  /     06/26/14     /  /     8                              0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-012-031                                              /  /       /  /     06/26/14     /  /     10                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Pupil Personnel Services @ High Scho:
10-0114   New Construction             0-038-001  10/28/10     DONE    DONE       DONE      08/18/10   07/15/10   04/07/10   02/23/10   02 - 16                  247,319             0  DDJ             0           0           0 Collins & Scoville Architects           0      07/31/11                       06/26/13           

          20' Container #13 @ HBE:
  -    DB Discovered Building          2-040-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          10' Container #11 @ Middle School:
  -    DB Discovered Building          2-041-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          10' Container #12 @ Middle School:
  -    DB Discovered Building          2-042-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          20' Container #1 @ 209 Complex:
  -    DB Discovered Building          2-043-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          20' Container #2 @ 209 Complex:
  -    DB Discovered Building          2-044-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          40' Container #3 @ 209 Complex:
  -    DB Discovered Building          2-045-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          40' Container #4 @ 209 Complex:
  -    DB Discovered Building          2-046-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          40' Container #5 @ 209 Complex:
  -    DB Discovered Building          2-047-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          40' Container #6 @ 209 Complex:
  -    DB Discovered Building          2-048-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          40' Container #7 @ 209 Complex:
  -    DB Discovered Building          2-049-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          40' Container #8 @ 209 Complex:
  -    DB Discovered Building          2-050-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          20' Container #9 @ 209 Complex:
  -    DB Discovered Building          2-051-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          10' Container #10 @ 209 Complex:
  -    DB Discovered Building          2-052-001                                              /  /       /  /     10/29/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Maintenance Facility:
12-0877   New Construction             3-025-001  11/01/13     DONE    DONE       DONE      02/20/13   02/19/13   02/01/13   05/15/12   02 - 16                  292,000             0  MFS             0           0           0 Highland Associates                     0        /  /                           /  /             

          Maintenance Building:
09-0372   New Construction             3-037-001  02/08/10     DONE    DONE       DONE      10/29/09   10/27/09   08/28/09   05/19/09   02 - 16                  384,207             0  DDJ             0           0           0 Collins & Scoville Architects           0      06/01/10                         /  /             

          Water Tank Building:
11-0990   New Construction             7-039-001  03/27/12     DONE    DONE       DONE      03/20/12     /  /     01/10/12   03/13/10   02 - 16                  335,000             0  DDJ             0           0           0 Highland Associates                     0      12/31/12                       03/18/13           

          District-Wide:
10-0040   Reconstruction               7-999-001  12/17/10     DONE    DONE       DONE      07/22/10   07/09/10   04/07/10   02/23/10   10,16                    559,775       559,775  DDJ             0           0           0 Collins & Scoville Architects           0      08/31/11                       06/26/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TUXEDO UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-19-03-02
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          George F. Baker High School:
09-0746   Reconstruction               0-002-007  02/25/10     DONE    DONE       DONE      01/20/10   01/19/10   07/31/09   05/19/09   2,4                       78,051        78,051  HCM             0           0           0 Clark Patterson Lee                     0      09/03/10                       09/27/10         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WARWICK VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-21-01-06
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
09-1289   Reconstruction               0-001-020  10/21/10     DONE    DONE       DONE      04/13/10   04/07/10   03/10/10   05/19/09   16                       261,059       261,059  DDJ             0           0      50,081 Eisenbach & Ruhnke Engineerin           0      09/29/12                       10/16/12           
10-0918   Reconstruction               0-001-021  05/06/11     DONE    DONE       DONE      02/28/11   02/24/11   10/29/10   01/11/10   2,155                  1,026,931     1,026,931  DDJ             0           0           0 Fuller and D'Angelo                     0      12/15/11                         /  /             
10-0753   Reconstruction               0-001-022  03/08/11     DONE    DONE       DONE      01/28/11   01/27/11   10/29/10   01/10/11   2,7,8                    762,002       762,002  DDJ             0           0     275,844 Eisenbach & Ruhnke Engineerin           0      09/12/11                         /  /             
10-0966   Reconstruction               0-001-023  03/18/13     DONE    DONE       DONE      03/07/11   03/01/11   10/29/10   10/18/10   2,10,16                1,983,215     1,983,215  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin   1,983,215      09/03/14                       09/17/14           
13-0037   Reconstruction               0-001-024  07/26/13     DONE    DONE       DONE      07/11/13   07/11/13   06/19/13   05/21/13   10,155                   100,000             0  MFS             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Park Avenue Elementary:
09-1290   Reconstruction               0-002-015  10/21/10     DONE    DONE       DONE      04/13/10   04/07/10   03/10/10   05/19/09   16                       156,725       156,725  DDJ             0           0      56,734 Eisenbach & Ruhnke Engineerin           0      09/29/12                       10/16/12           
10-0967   Reconstruction               0-002-016  03/18/13     DONE    DONE       DONE      03/07/11   03/01/11   10/29/10   10/18/10   2,10                     261,350       261,350  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin     261,350      09/03/14                       09/17/14           
11-0970   Reconstruction               0-002-017  06/15/12     DONE    DONE       DONE      03/16/12   03/14/12   10/29/10   01/10/11   2,8,9,155                470,000       470,000  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      04/28/14                       05/14/14           
10-0754   Reconstruction               0-002-018  03/08/11     DONE    DONE       DONE      01/28/11   01/27/11   10/29/10   01/10/11   2,8,9                    236,727       236,727  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      01/12/12                         /  /             
13-0399   Reconstruction               0-002-019  01/21/14     DONE    DONE       DONE      09/20/13   09/20/13   09/09/13   01/10/11   16                        35,000        35,000  MFS             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
13-0700   Reconstruction               0-002-020  11/13/13     DONE    DONE       DONE      11/13/13   11/08/13   10/31/13   11/04/13   2,155                     65,000        65,000  MFS             0           0           0 Eisenbach & Ruhnke Engineerin           0      01/27/14                       02/04/14           

          Pine Island Elementary:
09-1291   Reconstruction               0-004-011  10/21/10     DONE    DONE       DONE      04/13/10   04/07/10   03/10/10   05/19/09   16                       127,374       127,374  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
10-0968XX Reconstruction               0-004-012                         CANCELLED          03/07/11   03/01/11   11/01/10   10/18/10   2,10                           0     4,350,912  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Kings Elementary:
09-1292   Reconstruction               0-005-009  10/21/10     DONE    DONE       DONE      04/13/10   04/07/10   03/10/10   05/19/09   16                       178,153       178,153  DDJ             0           0      64,492 Eisenbach & Ruhnke Engineerin           0      09/29/12                       10/19/12           
10-0755   Reconstruction               0-005-010  03/08/11     DONE    DONE       DONE      01/28/11   01/27/11   10/29/10   01/10/11   2,8                      134,874       134,874  DDJ             0           0      48,824 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
10-0969   Reconstruction               0-005-011               DONE    DONE       ADD. REQ'D03/07/11   03/01/11   10/29/10   10/18/10   2,10                           0     8,855,028  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Warwick Middle School:
10-0175   Reconstruction               0-006-011  09/23/10     DONE    DONE       DONE      08/27/10   08/20/10   10/27/08   05/19/09   9,10,16                1,177,462     1,177,462  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      11/22/11                         /  /             
09-1293   Reconstruction               0-006-012  10/21/10     DONE    DONE       DONE      04/13/10   04/07/10   03/10/10   05/19/09   16                       240,045       240,045  DDJ             0           0      28,511 Eisenbach & Ruhnke Engineerin           0      09/29/12                       10/16/12           
10-0756   Reconstruction               0-006-013  03/08/11     DONE    DONE       DONE      01/28/11   01/27/11   10/29/10   01/11/11   2,8                       37,803        37,803  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
10-0888   Reconstruction               0-006-014  05/24/11     DONE    DONE       DONE      02/22/11   02/16/11   10/29/10   01/10/11   2,7,155                1,161,899     1,161,899  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
10-0970   Reconstruction               0-006-015  03/18/13     DONE    DONE       DONE      03/07/11   03/01/11   10/29/10   10/18/10   2,10                   1,129,708     1,129,708  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin   1,129,708      09/03/14                       09/17/14           

          Sanfordville Elementary:
10-0965   Reconstruction               0-019-003  03/18/13     DONE    DONE       DONE      03/07/11   03/01/11     /  /     10/18/10   10                       434,851       434,851  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin     434,851      09/03/14                       09/17/14           
13-0400   Reconstruction               0-019-004  01/21/14     DONE    DONE       DONE      09/20/13   09/20/13   09/12/13   01/10/11   16                        35,000        35,000  MFS             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Storage Building 1:
  -    DB Discovered Building          2-027-001                       ADDENDUM REQ'D         /  /       /  /     10/12/11     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Building 2:
  -    DB Discovered Building          2-028-001                       ADDENDUM REQ'D         /  /       /  /     10/12/11     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Custodial Maint.barn:
10-0971   Reconstruction               3-010-001  03/18/13     DONE    DONE       DONE      03/07/11   03/01/11   10/29/10   10/18/10   2,10                      11,859             0  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin      11,859      09/03/14                       09/17/14           

          Bus Storage Barn:
11-0497   Reconstruction               4-011-002  03/18/13     DONE    DONE       DONE      12/13/11   11/21/11   09/21/11   10/18/10   10                         6,000             0  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin       6,000      09/03/14                       09/17/14           

          Bus Garage:
10-0972   Reconstruction               5-012-004  03/18/13     DONE    DONE       DONE      03/07/11   03/01/11   10/29/10   10/18/10   2,10                      53,172        53,172  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin      53,172      09/03/14                       09/03/14           
14-0352   Reconstruction               5-012-005  10/07/14     DONE    DONE       DONE      09/25/14   09/24/14   06/26/14   07/07/14   7,155                    100,000             0  MFS             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Sanfordville Observatory:
11-0542   New Construction             7-029-001  04/12/12     DONE    DONE       DONE      12/27/11   12/27/11   12/27/11     /  /     02 - 16                        0             0  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      05/06/13                       05/14/13           

          District Wide:
10-0669   Reconstruction               7-999-002  04/28/11     DONE    DONE       DONE      12/30/10   12/23/10   07/08/10   05/19/09   13                     3,405,682     3,405,682  DDJ             0           0           0 Eisenbach & Ruhnke Engineerin           0      06/30/12                       08/31/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREENWOOD LAKE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-21-11-02
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
10-1158   Reconstruction               0-001-012  06/17/11     DONE    DONE       DONE      04/08/11   04/04/11   06/04/09   05/18/10   2,4,7                    162,402       162,402  HCM             0           0           0 Fellenzer Engineering                   0      07/02/13                       11/25/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-013                                              /  /       /  /     03/24/11     /  /     13                             0    15,945,150  HCM             0           0           0                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0553   Reconstruction               0-001-014  04/02/12     DONE    DONE       DONE      12/27/11   12/23/11   03/25/11   06/09/10   155,16                 1,975,616     1,975,616  HCM             0           0     135,642 Fellenzer Engineering                   0      02/25/14                       06/30/14         YES
                                                                                                                                                                                                                                                                                                                                   
13-1407   Reconstruction               0-001-015               DONE    DONE       ADD. REQ'D03/28/14   03/28/14   12/30/13   05/17/11   2,9,10,155,15,16               0    15,945,150  JMB             0           0           0 Fellenzer Engineering                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Elementary School:
13-1408   Reconstruction               0-002-008               STARTED DONE       ADD. REQ'D03/28/14   03/28/14   12/30/13   05/17/11   2,9,10,155,15,16               0     4,463,459  JMB             0           0           0 Fellenzer Engineering                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FLORIDA UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-21-15-02
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          SS Seward Institute:
09-0910   Reconstruction               0-001-010  06/14/10     DONE    DONE       DONE      02/19/10   02/16/10   11/05/09   03/31/08   2,9,10,13,14,155,16      299,765       299,765  JOD             0           0           0 Burton Behrendt Smith                   0      11/04/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-1387   Reconstruction               0-001-011  12/28/10     DONE    DONE       DONE      05/06/10   04/30/10   02/09/10   02/18/10   8,13,14,155,16           853,243       853,243  JOD             0           0           0 Burton Behrendt Smith             853,243      11/07/12                       01/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-0442   Reconstruction               0-001-012  04/25/14     DONE    DONE       DONE      10/03/13   09/27/13   03/22/13   03/12/13   2,4,7,8,9,13,14,155,   1,831,851             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Samuel S Seward Memorial Building:
09-1388   Reconstruction               0-003-006  12/28/10     DONE    DONE       DONE      05/06/10   04/30/10   02/09/10   02/18/10   8,155,15,16              162,150       162,150  JOD             0           0           0 Burton Behrendt Smith             162,150      11/07/12                       01/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-0443   Reconstruction               0-003-007  04/25/14     DONE    DONE       DONE      10/03/13   09/27/13   03/22/13   03/12/13   2,7,8,155,15,16           90,525             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Golden Hill Elementary:
09-0911   Reconstruction               0-004-008  06/14/10     DONE    DONE       DONE      02/19/10   02/16/10   11/05/09   03/31/08   8,9,10,15                218,599       218,599  JOD             0           0           0 Burton Behrendt Smith                   0      11/04/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-1389   Reconstruction               0-004-009  12/28/10     DONE    DONE       DONE      05/06/10   04/30/10   02/09/10   02/18/10   8,155,16                 959,607       959,607  JOD             0           0           0 Burton Behrendt Smith             959,607      11/07/12                       01/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-0444   Reconstruction               0-004-010  04/25/14     DONE    DONE       DONE      10/03/13   09/27/13   03/22/13   03/12/13   2,7,8,9,13,14,155,15   2,479,625             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Concession/Toilets:
09-1017DB Discovered Building          7-008-001  05/20/10     DONE    DONE       DONE      03/04/10   03/04/10   05/27/04     /  /     02 - 16                        0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          District-Wide:
13-0468   Reconstruction               7-999-001  04/24/14     DONE    DONE       DONE      10/07/13   10/04/13   03/22/13   03/12/13   13,16                    340,244       340,244  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ORANGE - ULSTER STATUS REPORT ON CAPITAL PROJECTS
District No.: 44-90-00-00
last updated on 11/20/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Occupational Bldg #400:
  -    XX Reconstruction               0-004-005                         CANCELLED            /  /       /  /     08/16/11     /  /     155,16                         0     3,608,100  JOD             0           0           0                                         0        /  /                           /  /             

          Special Ed Building:
10-0331   Reconstruction               0-009-023  03/18/11     DONE    DONE       DONE      10/06/10   10/01/10   12/15/08   02/08/07   13,155,16                277,125       277,125  JOD             0           0           0 LAN Associates                          0      05/15/13                       10/17/13           
  -       Reconstruction               0-009-024                                              /  /       /  /     04/21/10     /  /     155,16                         0    20,104,150  JOD             0           0           0                                         0        /  /                           /  /             
12-0021   Reconstruction               0-009-025                       ADDENDUM REQ'D       07/10/12   07/09/12   06/23/10   12/15/11   16                             0    20,104,150  JOD             0           0           0 LAN Associates                          0        /  /                           /  /             
12-0190   Reconstruction               0-009-026  03/04/13     DONE    DONE       DONE      09/18/12   09/17/12   06/23/10     /  /     13,15,16                  78,500        78,500  JOD             0           0           0 McGoey, Hauser and Edsall               0      09/30/13                       11/22/13           
  -    XX Reconstruction               0-009-027                         CANCELLED            /  /       /  /     08/03/10     /  /     2                              0    20,945,650  JOD             0           0           0                                         0        /  /                           /  /             
  -    XX Additions and Alterations    0-009-028                         CANCELLED            /  /       /  /     07/27/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-0918   Reconstruction               0-009-029  03/08/13     DONE    DONE       DONE      03/08/12   02/28/12   09/08/10   12/15/11   8                         74,150             0  JOD             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             
11-0917XX Reconstruction               0-009-030  05/29/12               CANCELLED          03/08/12   02/28/12   10/06/10   12/15/11   4,8                       42,250        42,250  JOD             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             
  -       Reconstruction               0-009-031                                              /  /       /  /     12/14/11     /  /     7                              0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-009-032                         CANCELLED            /  /       /  /     01/06/12     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Occ.Ed.Bldg(Career&Tech Cntr):
  -       Reconstruction               0-010-016                                              /  /       /  /     04/21/10     /  /     155,16                         0    27,414,000  JOD             0           0           0                                         0        /  /                           /  /             
11-0919   Reconstruction               0-010-017  03/08/13     DONE    DONE       DONE      03/08/12   02/28/12   09/08/10   12/15/11   8                         74,150             0  JOD             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             
10-1161   Reconstruction               0-010-018  04/19/11     DONE    DONE       DONE      04/07/11   04/05/11   12/24/10   05/08/10   2,4,10,16                361,000       361,000  JOD             0           0           0 Fellenzer Engineering                   0      02/21/12                         /  /             
12-0022XX Reconstruction               0-010-019                         CANCELLED          07/10/12   07/09/12   08/16/11     /  /     16                             0             0  JOD             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-010-020                                              /  /       /  /     12/14/11     /  /     7                              0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-010-021                         CANCELLED            /  /       /  /     01/06/12     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Green House - Arden Hill:
10-1382TQ Temporary Quarters           1-040-001  07/29/11     DONE    DONE       DONE      06/07/11   06/07/11   06/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Garage - Arden Hill:
10-1383TQ Temporary Quarters           2-041-001  07/29/11     DONE    DONE       DONE      06/07/11   06/07/11   06/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          O&M Office/Conf Center Bldg:
12-0191   Reconstruction               7-002-002  03/04/13     DONE    DONE       DONE      09/18/12   09/17/12   08/19/10     /  /     15,16                     78,500             0  JOD             0           0           0 McGoey, Hauser and Edsall               0      10/03/13                       11/22/13           
11-1444XX Reconstruction               7-002-003                         CANCELLED          06/29/12   06/20/12   08/19/10     /  /     2,4,7,8,9,155,15,16            0             0  JOD             0           0           0 Minuta Architecture, PLLC               0        /  /                           /  /             

          Pole Barn:
  -    PR New Construction             7-036-001                                              /  /       /  /     02/10/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Districtwide:
  -       Reconstruction               7-999-002                                              /  /       /  /     07/15/11     /  /     2,16                           0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Chester HS @ Chester UFSD:
11-0676   Reconstruction               8-033-004  05/08/12     DONE    DONE       DONE      01/18/12   01/17/12   08/16/11   03/01/11   155,16                   500,000             0  JOD             0           0           0 Fellenzer Engineering                   0        /  /                           /  /             
11-0441   Reconstruction               8-033-005  01/12/12     DONE    DONE       DONE      11/29/11   11/29/11   08/16/11     /  /     2                         88,250             0  JOD             0           0           0 LAN Associates                          0      07/30/12                       10/03/12           
11-0442   Reconstruction               8-033-006  01/12/12     DONE    DONE       DONE      11/29/11   11/29/11   09/13/11     /  /     7                        159,500             0  JOD             0           0           0 LAN Associates                          0        /  /                           /  /             

          Arden Hill - Main Building:
10-1378TQ Temporary Quarters           8-035-001  07/29/11     DONE    DONE       DONE      06/07/11   06/07/11   11/22/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-1136   Reconstruction               8-035-002  05/01/12     DONE    DONE       DONE      04/17/12   04/17/12   01/24/12   04/03/12   2,8,9,155,15,16        3,825,395     3,825,395  JOD             0           0           0 Kaeyer, Garment & Davidson              0      04/11/13                       10/15/13           
11-1384   Additions and Alterations    8-035-003  12/12/12     DONE    DONE       DONE      06/08/12   05/22/12   05/30/12   04/03/12   02 - 16               15,531,224    15,531,224  JOD             0           0           0 Kaeyer, Garment & Davidson              0      08/28/14                       09/25/14           
12-1107   Reconstruction               8-035-004  07/17/13     DONE    DONE       DONE      04/15/13   04/15/13   03/21/13   04/03/12   155,15,16              3,556,204             0  MFS             0           0           0 Fellenzer Engineering           3,556,204        /  /                           /  /             

          Building #1 - Arden Hill:
10-1379TQ Temporary Quarters           8-037-001  07/29/11     DONE    DONE       DONE      06/07/11   06/07/11   06/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-1092   Reconstruction               8-037-002               STARTED DONE       ADD. REQ'D04/06/12   04/05/12   01/24/12   04/03/12   4,7,8,9,14,155,15,16           0             0  JOD             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Building #2 - Arden Hill:
10-1380TQ Temporary Quarters           8-038-001  07/29/11     DONE    DONE       DONE      06/07/11   06/07/11   06/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               8-038-002                                              /  /       /  /     01/24/12     /  /     2                              0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Building #3 - Arden Hill:
10-1381TQ Temporary Quarters           8-039-001  07/29/11     DONE    DONE       DONE      06/07/11   06/07/11   06/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               8-039-002                                              /  /       /  /     01/24/12     /  /     2                              0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Goshen Christian School:
10-1436TQ Temporary Quarters           8-042-001  07/20/11     DONE    DONE       DONE      06/30/11   06/29/11   06/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Goshen Christian School Annex:
10-1437TQ Temporary Quarters           8-043-001  07/20/11     DONE    DONE       DONE      06/30/11   06/29/11   06/29/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          90 North Street:
12-0260TQ Temporary Quarters           8-044-001  01/18/13     DONE    DONE       DONE      10/09/12   10/01/12   10/09/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED