GILBERTSVILLE-MT. UPTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-02-02-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Building:
08-0409   Additions and Alterations    0-012-003  03/27/09     DONE    DONE       DONE      09/26/08   09/25/08   07/12/02   12/12/07   02 - 16                8,490,000     8,288,470  DDJ             0           0     381,342 Teitsch-Kent                            0        /  /             /  /        
11-1431   Reconstruction               0-012-004  07/27/12     DONE    DONE       DONE      06/28/12   06/22/12   03/01/12   05/17/12   16                       100,000       100,000  DDJ             0           0           0 Teitsch-Kent                            0        /  /             /  /        
  -       Reconstruction               0-012-005                                              /  /       /  /     02/05/13     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-012-006                                              /  /       /  /     02/05/13     /  /     2,4,8,9,10,155,15,16           0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Storage Building:
  -    DB Discovered Building          2-016-001                                              /  /       /  /     01/29/09     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Bus Garage:
08-0410   Additions and Alterations    5-013-002  03/27/09     DONE    DONE       DONE      09/26/08   09/25/08   12/08/95   12/12/07   02 - 16                  671,019       671,019  DDJ             0           0           0 Teitsch-Kent                            0        /  /             /  /        
  -       Reconstruction               5-013-004                                              /  /       /  /     02/05/13     /  /     4,8,9,16                       0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Press Box:
08-1375   New Construction             7-017-001  03/27/09     DONE    DONE       DONE      03/16/09   03/16/09   01/29/09   12/12/07   02 - 16                    9,600             0  DDJ             0           0           0 Teitsch-Kent                            0        /  /             /  /        

          Concession Stant/Athletic Storage:
  -       New Construction             7-018-001                                              /  /       /  /     01/29/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EDMESTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-05-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
08-0406   Reconstruction               0-001-009  04/03/09     DONE    DONE       DONE      09/26/08   09/25/08   02/05/07   10/02/07   2,4,7,8,9,10,155,15,   4,907,000     4,907,000  JOD             0           0     348,397 King & King, Architects                 0        /  /             /  /        
12-0610   Reconstruction               0-001-010               STARTED DONE       UNREVIEWED12/26/12   12/19/12   03/07/12   08/28/12   2,7,8,9,155,15,16              0             0  JOD             0           0           0 King & King Architects                  0        /  /             /  /        

          Shop Bus Garage:
08-0407XX Reconstruction               0-003-003  04/03/09               CANCELLED          09/26/08   09/25/08   02/05/07   10/02/07   2,4,7,8,9,155,15,16      221,000       221,000  JOD             0           0      11,934 King & King, Architects                 0        /  /             /  /        
12-0611   Reconstruction               0-003-004               DONE    DONE       UNREVIEWED12/26/12   12/19/12   03/06/12   08/28/12   2,4,7,155,15                   0             0  JOD             0           0           0 King & King Architects                  0        /  /             /  /        

          Bus Garage:
08-0408   Reconstruction               5-004-002  04/03/09     DONE    DONE       DONE      09/26/08   09/25/08   02/05/07   10/02/07   2,4,7,8,9,155,15,16      393,000       393,000  JOD             0           0           0 King & King, Architects                 0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAURENS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-08-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-1337   Reconstruction               0-001-011  07/12/11     DONE    DONE       DONE      06/03/11   05/24/11   04/01/11   05/17/11   7,14,15,16               355,000       355,000  JOD             0           0           0 King & King Architects                  0        /  /           01/28/13      
  -       Reconstruction               0-001-012                                              /  /       /  /     02/22/13     /  /     2,4,8,9,155,15,16              0             0  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-013                                              /  /       /  /     02/22/13     /  /     155,16                         0             0  JOB             0           0           0                                         0        /  /             /  /        

          New Bus Garage:
10-1338   Reconstruction               5-011-002  07/12/11     DONE    DONE       DONE      06/03/11   05/24/11   08/12/02   05/17/11   2,13,15,16               217,000       217,000  JOD             0           0           0 King & King Architects                  0        /  /           01/28/13      
  -       Reconstruction               5-011-003                                              /  /       /  /     02/22/13     /  /     155,16                         0             0  JOB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHENEVUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-09-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Andrew Draper School:
07-2268   Reconstruction               0-001-008  08/08/08     DONE    DONE       DONE      06/16/08   06/06/08   04/18/07   02/05/08   2,4,7,8,9,155,15,16      100,000       100,000  DDJ             0           0           0 James Jordan Associates                 0        /  /             /  /        
11-0485   Reconstruction               0-001-009  01/11/12     DONE    DONE       DONE      12/13/11   12/01/11   12/08/09   08/30/11   2,4,7,8,9,155,15,16      945,000       945,000  DDJ             0           0     145,866 James Jordan Associates                 0        /  /           08/10/12      
08-1686SC Visual Structural Inspection 0-001-SC2  06/18/09     DONE    DONE       DONE      06/15/09   06/15/09     /  /       /  /     16                        12,594        12,594  JOD             0           0           0                                         0        /  /             /  /        

          Bus Garage & Maint. Facility:
  -       Reconstruction               5-007-002                                              /  /       /  /     04/02/10     /  /     2,4,7,8,9,155,15,16            0             0  HCM             0           0           0                                         0        /  /             /  /        

          Concession Stand:
11-1057DB Discovered Building          7-009-001  10/19/12     DONE    DONE       DONE      04/03/12   04/03/12   04/03/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MILFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-11-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Milford Central School:
11-0405   Additions and Alterations    0-010-007  01/13/12     DONE    DONE       DONE      11/17/11   11/14/11   05/01/08   12/07/10   02 - 16                2,010,000     2,010,000  DDJ             0           0     350,977 Sacco & McKinney Architects,            0        /  /             /  /        
08-1676   Reconstruction               0-010-008  09/18/09     DONE    DONE       DONE      06/09/09   06/04/09   09/03/08   05/15/09   9,16                     100,000             0  DDJ             0           0           0 Sacco & McKinney Architects,            0        /  /             /  /        
10-0452   Reconstruction               0-010-009  03/15/11     DONE    DONE       DONE      11/12/10   11/08/10   09/21/09   07/22/10   16                       272,980       272,980  DDJ             0           0           0 Sacco & Mckinney Architects             0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-12-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Morris Central School:
12-0474   Reconstruction               0-001-010               DONE    DONE       UNREVIEWED11/21/12   11/13/12   05/23/11   02/29/12   2,4,8,9,155,15,16              0    13,362,125  DDJ             0           0           0 William Taylor Architects, PL           0        /  /             /  /        

          Custodial/Maintenance(former I.A.):
12-0475   Reconstruction               0-002-006               STARTED DONE       UNREVIEWED11/21/12   11/13/12   05/23/11   02/29/12   2,4,8,155,16                   0       170,604  DDJ             0           0           0 William Taylor Architects, PL           0        /  /             /  /        

          Bus Garage:
  -       Reconstruction               5-005-007                                              /  /       /  /     05/03/13     /  /     7,155                          0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ONEONTA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-14-00-01
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Valley View Elementary:
07-1205   Reconstruction               0-004-007  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,155,15,16    1,805,112     1,805,112  DDJ             0           0     250,244 Keystone Assoc Architects, En           0        /  /             /  /        
12-0608   Reconstruction               0-004-008  12/29/12     DONE    DONE       DONE      12/26/12   12/23/12   12/14/12   12/19/12   2                         17,110        17,110  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /           03/11/13      
  -       Reconstruction               0-004-009                                              /  /       /  /     01/30/13     /  /     2,4,7,8,9,14,155,15,           0             0  JOB             0           0           0                                         0        /  /             /  /        

          Center Street Elementary:
07-1206   Reconstruction               0-006-011  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,10,155,15,   1,978,364     1,978,364  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
  -       Reconstruction               0-006-012                                              /  /       /  /     01/30/13     /  /     2,8,9,14,155,16                0             0  JOB             0           0           0                                         0        /  /             /  /        

          Oneonta Jr/Sr High:
07-1207   Reconstruction               0-014-017  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,10,155,15,   6,671,719     6,671,719  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
08-0549XX Reconstruction               0-014-019                         CANCELLED          10/17/08   10/15/08   11/26/07   11/14/07   155                            0    21,474,300  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
07-1858   Reconstruction               0-014-020  05/28/08     DONE    DONE       DONE      03/24/08   03/17/08   02/27/08   05/15/07   15                       304,200       304,200  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
  -       Reconstruction               0-014-021                                              /  /       /  /     01/30/13     /  /     2,4,7,8,9,155,15,16            0             0  JOB             0           0           0                                         0        /  /             /  /        

          Great Plains Elementary:
07-1208   Reconstruction               0-017-010  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,155,15,16      339,518       339,518  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
  -       Reconstruction               0-017-012                                              /  /       /  /     01/30/13     /  /     2,4,7,8,9,10,155,15,           0             0  JOB             0           0           0                                         0        /  /             /  /        

          Riverside Elementary:
07-1209   Reconstruction               0-018-010  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,10,155,15,     695,925       695,925  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
  -       Reconstruction               0-018-012                                              /  /       /  /     01/30/13     /  /     2,8,9,16                       0             0  JOB             0           0           0                                         0        /  /             /  /        

          New Bus Garage:
07-1210   Reconstruction               5-019-002  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   12/28/07   05/15/07   15                        26,469        26,469  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /     01/30/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




UNATEGO (OTEGO-UNADILLA) CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-16-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Otego Elementary School:
08-0520   Reconstruction               0-001-007  03/31/09     DONE    DONE       DONE      10/14/08   10/09/08   03/06/07   05/15/07   2,4,7,8,9,10,13,155,     109,680       109,680  HCM             0           0           0                                         0        /  /           01/11/13      
08-1213   Reconstruction               0-001-008  04/29/09     DONE    DONE       DONE      02/18/09   02/09/09   10/10/08   05/15/07   2,4,7,8,9,10,13,155,   3,676,695     3,676,695  HCM             0           0           0                                         0        /  /           01/11/13      
  -       Reconstruction               0-001-009                                              /  /       /  /     01/25/13     /  /     4,8,9,16                       0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Unadilla Elementary School:
10-0093   Reconstruction               0-009-007                         UNREVIEWED         08/10/10   07/23/10   02/17/00   07/05/06   155,16                         0     8,991,390  MGL             0           0           0                                         0        /  /             /  /        
08-0521   Reconstruction               0-009-008  03/31/09     DONE    DONE       DONE      10/14/08   10/09/08   07/05/06   05/15/07   8,9,155,15,16            122,220       122,220  HCM             0           0           0                                         0        /  /           01/11/13      
08-1214   Additions and Alterations    0-009-009  04/29/09     DONE    DONE       DONE      02/18/09   02/09/09   03/06/07   05/15/07   02 - 16                4,701,600     4,701,600  HCM             0           0           0                                         0        /  /           01/11/13      
10-1118   Reconstruction               0-009-010  05/31/11     DONE    DONE       DONE      03/29/11   03/28/11   03/23/11   05/15/07   2,4,8,9,10,13,155,16     470,000       470,000  HCM             0           0      25,000                                         0        /  /           01/11/13      
  -       Reconstruction               0-009-011                                              /  /       /  /     01/25/13     /  /     4,8,9,16                       0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Unatego Jr/Sr High:
08-0522   Reconstruction               0-015-010  03/31/09     DONE    DONE       DONE      10/14/08   10/09/08   03/06/07   05/15/07   2,16                   3,255,000     3,255,000  HCM             0           0           0                                         0        /  /           01/11/13      
  -       Reconstruction               0-015-014                                              /  /       /  /     01/25/13     /  /     4,8,9,16                       0             0  DDJ             0           0           0                                         0        /  /             /  /        
12-0864   Reconstruction               0-015-015  04/22/13     DONE    DONE       DONE      02/15/13   02/14/13   01/25/13   05/15/07   2,4,8,9,10,155,15,16     847,200             0  JMB             0           0      85,500 BCK-IBI Group, a New York Gen           0        /  /             /  /        

          Storage Bldg @ Unadilla Elementary:
08-0117   New Construction             2-019-001  12/10/08     DONE    DONE       DONE      08/04/08   07/30/08   03/08/07   05/15/07   02 - 16                   66,300             0  HCM             0           0           0                                         0        /  /             /  /        

          Storage Building @ Otego Elementary:
08-0118   New Construction             2-020-001  12/10/08     DONE    DONE       DONE      08/04/08   07/30/08   03/08/07   05/15/07   02 - 16                   59,000             0  HCM             0           0           0                                         0        /  /             /  /        

          Bus Garage:
08-1215   Reconstruction               5-006-005  04/29/09     DONE    DONE       DONE      02/18/09   02/09/09   03/06/07   05/15/07   2,4,7,8,16               546,000       546,000  HCM             0           0           0                                         0        /  /           01/11/13      

          :
11-1069   Reconstruction               7-999-001  06/08/12     DONE    DONE       DONE      04/04/12   03/29/12   12/01/11   05/17/07   16                       817,750             0  HCM             0           0      75,000                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COOPERSTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-17-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
07-1077   Reconstruction               0-002-010  05/28/08     DONE    DONE       DONE      12/10/07   12/07/07   12/29/06   05/15/07   2,4,7,8,9,10,14,155,     916,300       916,300  MGL             0           0     175,113                                         0        /  /             /  /        
08-0459   Reconstruction               0-002-011  04/10/09     DONE    DONE       DONE      10/06/08   10/02/08   04/22/08   05/15/07   2,4,8,9,10,155,15,16   1,906,301     1,861,565  HCM             0           0           0                                         0        /  /             /  /        

          Junior/Senior High School:
07-1078   Reconstruction               0-006-008  05/28/08     DONE    DONE       DONE      12/10/07   12/07/07   12/29/06   05/15/07   2,8,9,155,15,16          680,000       680,000  MGL             0           0     172,586                                         0        /  /             /  /        
08-0460   Reconstruction               0-006-009  04/10/09     DONE    DONE       DONE      10/06/08   10/02/08   04/22/08   05/15/07   2,4,8,9,10,155,15,16   2,372,980     2,372,980  HCM             0           0           0                                         0        /  /             /  /        

          Playground Storage Shed #2:
09-0725DB Discovered Building          2-013-001  01/13/10     DONE    DONE       DONE      01/12/10   01/11/10   10/26/09     /  /                                    0             0  HCM             0           0           0                                         0        /  /             /  /        

          Bus Garage:
07-1079   Reconstruction               5-003-009  05/28/08     DONE    DONE       DONE      12/10/07   12/07/07   12/29/06   05/15/07   2,4,7,8,9,10,13,155,     252,779       252,779  MGL             0           0           0                                         0        /  /             /  /        
08-0461   Reconstruction               5-003-010  04/10/09     DONE    DONE       DONE      10/06/08   10/02/08   04/22/08   05/15/07   2,4,8,9,13,155,15,16     585,424       585,424  HCM             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RICHFIELD SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-20-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-1374   Reconstruction               0-001-018  10/06/08     DONE    DONE       DONE      01/15/08   01/11/08   07/17/07   08/07/07   2,4,8,9,10,13,15,16    2,167,566     2,167,566  MGL             0           0     361,984 Clark Patterson Lee                     0        /  /             /  /        
12-0940   Reconstruction               0-001-020  04/18/13     DONE    DONE       DONE      03/01/13   03/01/13   10/05/11     /  /     2,4,7,8,9,10,155,15,   1,200,000             0  MFS             0           0           0 Clark Patterson Lee                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHERRY VALLEY-SPRINGFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-22-02-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Main Building:
08-1341   Reconstruction               0-004-003  10/07/09     DONE    DONE       DONE      03/13/09   03/03/09   02/27/07   12/12/07   2,7,8,9,155,15,16      8,050,180     8,050,180  MGL             0           0     161,004 William Taylor Architects, PL           0        /  /             /  /        
  -       Reconstruction               0-004-004                                              /  /       /  /     04/14/11     /  /     2,4,7,8,9,155,15,16            0    43,917,228  HCM             0           0           0                                         0        /  /             /  /        
12-0132   Reconstruction               0-004-005  01/15/13     DONE    DONE       DONE      08/31/12   08/29/12   06/15/12   05/15/12   2,8,155,15,16            100,000             0  HCM             0           0           0 Griffith Dardanelli,Architect           0        /  /             /  /        

          New Transportation Bldg.:
  -       Reconstruction               5-012-004                                              /  /       /  /     04/14/11     /  /     2,4,8,9,13,16                  0             0  HCM             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WORCESTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-25-06-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-0204   Additions and Alterations    0-001-005  12/18/09     DONE    DONE       DONE      09/14/09   09/10/09   09/30/03   03/12/08   02 - 16               15,677,889    14,037,466  DDJ             0           0     322,961 Keystone Assoc Architects, En           0        /  /             /  /        
09-0883   Reconstruction               0-001-007  06/23/10     DONE    DONE       DONE      02/11/10   02/08/10   03/11/09   03/12/08   2,4,7,8,9,10,14,155,  11,323,593    11,323,593  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
11-1305   Reconstruction               0-001-008  06/08/12     DONE    DONE       DONE      05/14/12   05/11/12   04/03/12   03/12/08   7,155,15,16              552,000       552,000  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        
12-0729   Reconstruction               0-001-009  02/13/13     DONE    DONE       DONE      01/29/13   01/28/13   11/29/12   03/12/08   2,9,16                   628,000             0  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        

          Annex/Bus Garage:
08-0176   Reconstruction               0-002-003  02/05/09     DONE    DONE       DONE      08/18/08   08/07/08   05/05/94   03/12/08   2,7,8                    278,600       278,600  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        

          Storage Building:
10-0602   New Construction             2-004-001  05/19/11     DONE    DONE       DONE      12/22/10   12/13/10   05/13/10   10/10/05   02 - 16                  401,503             0  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /           02/13/13      

          New Bus Garage:
08-0175   New Construction             5-003-001  02/05/09     DONE    DONE       DONE      08/18/08   08/07/08   08/30/02   03/12/08   02 - 16                2,495,754     2,495,754  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED