Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 06/24/16 at 10:55:22




MAHOPAC CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-01-01-06
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lakeview Elementary:
13-1615   Reconstruction               0-001-013  06/18/14     DONE    DONE       DONE      06/13/14   06/12/14   05/21/14   05/21/13   2,7                      285,850       285,850  JMB             0           0           0 Kaeyer, Garment & Davidson              0      11/07/14                       01/30/15           
15-1112   Reconstruction               0-001-014  06/02/16     DONE    DONE       DONE      01/27/16   01/27/16   08/19/15   05/19/15   15,16                    100,000       100,000  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Senior High:
12-1010   Reconstruction               0-004-015  09/26/13     DONE    DONE       DONE      03/21/13   03/20/13   01/22/13   02/12/08   4,7,8,9,155,15,16        243,119       243,119  JMB             0           0           0 Kaeyer, Garment & Davidson              0      05/07/14                       06/02/14           
14-0220   Reconstruction               0-004-016  10/07/14     DONE    DONE       DONE      08/22/14   08/22/14   07/30/14   05/21/14   2,9                      580,000       580,000  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
15-1113   Reconstruction               0-004-017  06/03/16     DONE    DONE       DONE      01/27/16   01/27/16   08/19/15   05/19/15   2,16                     135,000             0  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CARMEL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-01-02-06
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Kent Elementary School:
13-0621   Reconstruction               0-001-013  05/15/14     DONE    DONE       DONE      10/24/13   10/24/13   06/27/13   05/21/13   13,16                    294,860       294,860  MFS             0           0           0 Sammel Architecture                     0      01/19/16                       04/26/16           
14-0859   Reconstruction               0-001-014  11/03/15     DONE    DONE       DONE      12/30/14   12/29/14   12/15/14   11/18/14   155,16                    38,322             0  MFS             0           0           0 Sammel Architecture                38,322        /  /                           /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     03/29/16     /  /     2,9                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Carmel High School:
11-0217   Reconstruction               0-003-016  03/02/12     DONE    DONE       DONE      09/30/11   09/29/11   07/13/11   05/17/11   10                        99,869        99,869                  0           0           0 Sammel Architecture                     0      06/27/12                       06/07/13           
11-1155   Reconstruction               0-003-017  05/16/12     DONE    DONE       DONE      04/19/12   04/18/12   03/21/12   05/15/12   4,10                      99,841        99,841  HCM             0           0           0 Sammel Architecture                     0      08/10/12                       06/07/13           
  -       Reconstruction               0-003-018                                              /  /       /  /     09/11/12     /  /     4,7,8,9,10,155,15,16           0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0622   Reconstruction               0-003-019  05/15/14     DONE    DONE       DONE      10/24/13   10/24/13   06/27/13   05/21/13   2,155,15,16            4,794,475             0  MFS             0           0           0 Sammel Architecture                     0        /  /                           /  /             
14-0860   Reconstruction               0-003-020  11/03/15     DONE    DONE       DONE      12/30/14   12/29/14   12/15/14   11/18/14   155,16                   282,077             0  MFS             0           0           0 Sammel Architecture               282,077        /  /                           /  /             
  -       Reconstruction               0-003-021                                              /  /       /  /     03/23/16     /  /     10                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Kent Primary School:
13-0623   Reconstruction               0-004-011  05/15/14     DONE    DONE       DONE      10/24/13   10/24/13   06/27/13   05/21/13   2,4,10,13,16             427,285       427,285  MFS             0           0           0 Sammel Architecture                     0      01/19/16                       04/26/16           
14-0055   Reconstruction               0-004-012  01/07/15     DONE    DONE       DONE      07/25/14   07/16/14   01/31/14   05/20/14   2,9                      203,619             0  MFS             0           0           0 Sammel Architecture                     0        /  /                           /  /             
14-0861   Reconstruction               0-004-013  11/03/15     DONE    DONE       DONE      12/30/14   12/29/14   12/15/14   11/18/14   155,16                    76,586             0  MFS             0           0           0 Sammel Architecture                76,586        /  /                           /  /             
15-1796   Reconstruction               0-004-014                         UNREVIEWED         05/24/16   05/23/16   09/24/15   05/20/15   2,15                           0             0  MFS             0           0           0 Sammel Architecture                     0        /  /                           /  /             

          Industrial Arts Bldg:
14-0862   Reconstruction               0-006-005  11/03/15     DONE    DONE       DONE      12/30/14   12/29/14   12/15/14   11/18/14   155,16                       886             0  MFS             0           0           0 Sammel Architecture                   886        /  /                           /  /             

          Fine Arts Bldg:
14-0863   Reconstruction               0-007-005  11/03/15     DONE    DONE       DONE      12/29/14   12/29/14   12/15/14   11/08/14   155,16                     1,577             0  MFS             0           0           0 Sammel Architecture                 1,577        /  /                           /  /             

          George Fisher Middle School:
13-0624   Reconstruction               0-008-015  05/15/14     DONE    DONE       DONE      10/24/13   10/24/13   06/27/13   05/21/13   2,13,16                  716,900       716,900  MFS             0           0           0 Sammel Architecture                     0      01/19/16                       04/26/16           
14-0864   Reconstruction               0-008-016  11/03/15     DONE    DONE       DONE      12/29/14   12/29/14   12/15/14   11/18/14   155,16                 1,471,501             0  MFS             0           0           0 Sammel Architecture             1,471,501        /  /                           /  /             

          Mathew Patterson Elementary:
13-0625   Reconstruction               0-010-009  05/15/14     DONE    DONE       DONE      10/24/13   10/24/13   06/27/13   05/21/13   16                       299,160             0  MFS             0           0           0 Sammel Architecture                     0      01/19/16                         /  /             
14-0865   Reconstruction               0-010-010  11/03/15     DONE    DONE       DONE      12/29/14   12/29/14   12/15/14   11/18/14   155,16                   359,399             0  MFS             0           0           0 Sammel Architecture               359,399        /  /                           /  /             
  -       Reconstruction               0-010-011                                              /  /       /  /     03/23/16     /  /     2,155                          0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Administration Building:
13-0626   Reconstruction               1-002-007  05/15/14     DONE    DONE       DONE      10/24/13   10/24/13   06/27/13   05/21/13   13,16                    259,320             0  MFS             0           0           0 Sammel Architecture                     0      01/19/16                       04/26/16           
14-0866   Reconstruction               1-002-008  11/03/15     DONE    DONE       DONE      12/29/14   12/29/14   12/15/14   11/18/14   155,16                    13,759             0  MFS             0           0           0 Sammel Architecture                13,759        /  /                           /  /             

          Transportation Office:
14-0867   Reconstruction               1-013-002  11/03/15     DONE    DONE       DONE      12/29/14   12/29/14   12/15/14   11/18/14   155,16                     5,343             0  MFS             0           0           0 Sammel Architecture                 5,343        /  /                           /  /             

          Bus Garage:
14-0868   Reconstruction               5-005-007  11/03/15     DONE    DONE       DONE      12/29/14   12/29/14   12/15/14   11/18/14   155,16                    55,350             0  MFS             0           0           0 Sammel Architecture                55,350        /  /                           /  /             

          Concession Stand @ High School:
15-1213   New Construction             7-018-001                       ADDENDUM REQ'D       02/10/16   01/20/16   07/06/15   05/19/15   02 - 16                        0             0  MFS             0           0           0 Sammel Architecture                     0        /  /                           /  /             

          District-Wide:
15-1797   Reconstruction               7-999-003                         UNREVIEWED         05/24/16   05/23/16   03/11/16   05/21/13   16                             0   106,587,526  MFS             0           0           0 Sammel Architecture                     0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HALDANE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-04-01-04
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-1134   Reconstruction               0-001-015  02/27/12     DONE    DONE       DONE      04/13/11   03/30/11   01/20/11   10/26/10   2,8,9,155,15,16        1,647,643     1,647,643  HCM             0           0           0 Fuller and D'Angelo             1,647,643      06/05/13                       08/28/13           
12-0313   Reconstruction               0-001-016  11/13/12     DONE    DONE       DONE      10/24/12   10/16/12   06/29/12   11/18/08   8                         65,400        65,400  HCM             0           0           0 Fuller and D'Angelo                     0      09/01/13                       02/24/14           
12-0669   Reconstruction               0-001-017  04/17/13     DONE    DONE       DONE      01/15/13   01/15/13   11/27/12   11/13/12   2,7,8,9,15,16          2,000,000     2,000,000  JMB             0           0           0 Burton Behrendt Smith                   0      10/01/13                       02/07/14           
  -       Reconstruction               0-001-018                                              /  /       /  /     06/27/13     /  /     8,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1445   Reconstruction               0-001-019  03/06/15     DONE    DONE       DONE      04/15/14   04/11/14   10/02/13   06/18/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Merritt Building:
10-1135   Reconstruction               0-003-008  02/27/12     DONE    DONE       DONE      04/13/11   03/30/11   01/20/11   10/26/10   2,7,8,14,155,15          170,116       170,116  HCM             0           0           0 Fuller and D'Angelo               170,116      06/05/13                       08/28/13           

          Manufactured Building #1:
10-1136   Reconstruction               0-008-003  02/27/12     DONE    DONE       DONE      04/13/11   03/30/11   01/20/11   10/26/10   2,9,155,15                12,368             0  HCM             0           0           0 Fuller and D'Angelo                12,369      06/05/13                       08/28/13           

          New High School Annex:
10-1137   Reconstruction               0-016-002  02/27/12     DONE    DONE       DONE      04/13/11   03/30/11   01/20/11   10/26/10   2,8,9,155,15,16          207,576       207,576  HCM             0           0           0 Fuller and D'Angelo               207,577      06/05/13                       08/28/13           
  -       Reconstruction               0-016-003                                              /  /       /  /     06/27/13     /  /     8,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1447   Reconstruction               0-016-004  03/06/15     DONE    DONE       DONE      04/15/14   04/11/14   10/04/13   06/18/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Bus Garage/Admin. Bldg.:
10-1138   Reconstruction               5-006-010  02/27/12     DONE    DONE       DONE      04/13/11   03/30/11   01/20/11   10/26/10   2,9,15,16                 36,126        36,126  HCM             0           0           0 Fuller and D'Angelo                36,126      06/05/13                       08/28/13           
13-1446   Reconstruction               5-006-011  03/06/15     DONE    DONE       DONE      04/15/14   04/11/14   10/02/13   06/18/13   16                             0             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          St. Basil Academy:
  -    TQ Temporary Quarters           8-017-001                                              /  /       /  /     03/21/16     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GARRISON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-04-04-02
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
11-0640   Reconstruction               0-001-014  06/13/12     DONE    DONE       DONE      01/11/12   01/09/12   07/08/11   05/15/07   155                       88,900        88,900  HCM             0           0           0 C & F Consulting Engineering            0      02/21/13                       11/05/14         YES
                                                                                                                                                                                                                                                                                                                                   

          New Storage Building:
11-0179   New Construction             2-008-001  11/14/11     DONE    DONE       DONE      09/19/11   09/19/11   07/16/08   05/15/07   02 - 16                   95,000             0  HCM             0           0           0 Hudson Design                           0      07/11/12                       09/12/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PUTNAM VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-05-03-04
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
12-1099   Reconstruction               0-001-008  06/26/13     DONE    DONE       DONE      04/12/13   04/12/13   02/20/13   05/21/13   8,9,16                   299,340       299,340  DDJ             0           0           0 Kaeyer, Garment & Davidson              0      08/28/14                       11/04/15         YES
                                                                                                                                                                                                                                                                                                                                   

          Middle School:
12-1100   Reconstruction               0-004-010  06/26/13     DONE    DONE       DONE      04/12/13   04/12/13   02/20/13   05/21/13   2,8,9,13,16              147,720       147,720  DDJ             0           0           0 Kaeyer, Garment & Davidson              0      08/28/14                       11/04/15         YES
                                                                                                                                                                                                                                                                                                                                   
14-0801   Reconstruction               0-004-011  12/29/14     DONE    DONE       DONE      12/19/14   12/18/14   08/13/14   05/20/14   2,155,15,16              309,800       309,800  DDJ             0           0           0 Kaeyer, Garment & Davidson              0      09/11/15                       11/04/15         YES
                                                                                                                                                                                                                                                                                                                                   
15-0084   Reconstruction               0-004-012  07/24/15     DONE    DONE       DONE      07/15/15   07/14/15   06/29/15   05/20/09   4,7                      247,400       247,400  DDJ             0           0           0 Kaeyer, Garment & Davidson              0      09/04/15                       11/04/15         YES
                                                                                                                                                                                                                                                                                                                                   

          New 9-12 High School:
12-1101   Reconstruction               0-010-003  05/23/13     DONE    DONE       DONE      04/12/13   04/12/13   02/20/13   05/21/13   2,8,9,13,16            1,002,368     1,002,368  DDJ             0           0           0 Kaeyer, Garment & Davidson              0      08/28/14                       11/04/15         YES
                                                                                                                                                                                                                                                                                                                                   

          District-Wide:
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BREWSTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-06-01-06
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Henry Wells MS(plus CS STARR IS):
12-0144   Reconstruction               0-001-022  01/03/13     DONE    DONE       DONE      09/05/12   08/30/12   07/21/11   10/09/09   2,15,16                  753,000       753,000  HCM             0           0           0 Kaeyer, Garment & Davidson              0      01/07/14                       03/12/14           
14-1266   Reconstruction               0-001-023  03/25/15     DONE    DONE       DONE      03/16/15   03/13/15   02/11/15   12/09/14   4,7                    1,131,280     1,131,280  JMB             0           0           0 Kaeyer, Garment & Davidson              0      09/09/15                       10/22/15           
15-0367   Reconstruction               0-001-024  03/29/16     DONE    DONE       DONE      08/27/15   08/26/15   02/11/15   12/09/04   2,4,7,8,9,155,15,16    8,989,821             0  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          John F. Kennedy Elementary School:
15-0399   Reconstruction               0-003-010  05/20/16     DONE    DONE       DONE      09/03/15   08/31/15   02/11/15   12/09/14   2,4,7,8,9,155,15,16   17,631,954             0  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Brewster High School:
11-0913   Reconstruction               0-004-014  05/16/12     DONE    DONE       DONE      03/07/12   02/23/12   07/21/11   10/09/09   2,15,16                  211,000       211,000  HCM             0           0           0 Kaeyer, Garment & Davidson              0      06/19/13                       03/12/14           
15-0286   Reconstruction               0-004-015  01/22/16     DONE    DONE       DONE      08/14/15   08/12/15   02/11/15   12/09/14   2,4,8,9,10,155,15,16   6,311,423             0  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
14-1267   Reconstruction               0-004-016  03/25/15     DONE    DONE       DONE      03/16/15   03/13/15   02/11/15   12/09/14   2,4,7                  1,994,332     1,994,332  JMB             0           0           0 Kaeyer, Garment & Davidson              0      06/15/15                       10/22/15           

          Administration Bldg:
15-0279   Reconstruction               1-005-007  01/29/16     DONE    DONE       DONE      08/12/15   08/12/15   02/11/15   12/09/14   2,4,7,8,9,14,155,15,     572,959             0  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          Bus Garage:
14-1397   Reconstruction               5-006-009  04/28/15     DONE    DONE       DONE      04/13/15   04/08/15   02/11/15   12/09/14   2,155                    464,881       464,881  JMB             0           0           0 Kaeyer, Garment & Davidson              0      09/16/15                       05/20/16           

          Water Tank Bldg @ Middle School:
12-0145   New Construction             7-041-001  01/03/13     DONE    DONE       DONE      09/05/12   08/30/12   07/21/11   10/09/09   02 - 16                        0             0  HCM             0           0           0 Kaeyer, Garment & Davidson              0      01/07/14                       03/12/14           

          Water Tank Bldg @ High School:
  -       New Construction             7-042-001                                              /  /       /  /     07/21/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Restroom/Concession Building:
14-1468   New Construction             7-043-001  06/24/15     DONE    DONE       DONE      05/01/15   04/30/15   02/11/15   12/09/14   02 - 16                  437,326             0  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             

          District-Wide:
14-1341   Reconstruction               7-999-002  05/08/15     DONE    DONE       DONE      04/01/15   04/01/15   02/11/15   12/09/14   8,10,16                1,109,476     1,109,476  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES PUTNAM-WESTCHESTER STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-90-00-00
last updated on 06/24/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Special Ed Bldg B:
12-0633   Reconstruction               0-003-007  03/28/13     DONE    DONE       DONE      01/07/13   01/03/13     /  /     11/14/12   2,4,7                  2,129,369             0  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-003-008                                              /  /       /  /       /  /       /  /     155,15,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             
12-0588   Reconstruction               0-003-009  05/22/13     DONE    DONE       DONE      12/21/12   12/21/12     /  /     11/14/12   2,4,8,9,13,155,15,16   2,874,586     2,874,586  MFS             0           0           0 Mosaic Associates                       0      02/27/15                       03/19/15           

          Tech Bldg C:
12-0694   Reconstruction               0-004-005  05/21/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7,9,155,15,16        4,394,042             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Building D:
12-0688   Reconstruction               0-005-004  05/16/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7,9,155,15,16        2,119,627             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          School Services A:
12-0693   Reconstruction               0-006-001  05/22/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7,9,155,15,16        2,401,206             0  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Building E:
12-0692   Reconstruction               0-011-002  05/22/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7,9,155,15,16          865,092             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Fox Meadows - Building 7:
12-0689   Reconstruction               2-027-001  05/22/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7                      378,641             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Fox Meadows - Building 9:
12-0690   Reconstruction               2-028-001  05/22/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7                      802,746             0  MFS             0           0           0 Mosaic Associates                       0      12/02/13                       04/28/14           

          Fox Meadows - Building 8:
12-0691   Reconstruction               2-029-001  05/22/13     DONE    DONE       DONE      01/18/13   01/16/13   12/11/12   11/14/12   2,7                      333,229             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED