Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/20/13 at 09:48:20




BERLIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-01-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Berlin Elementary:
  -       Reconstruction               0-007-008                                              /  /       /  /     12/12/12     /  /     2,4,7,8,9,10,14,155,           0     4,541,040  JMB             0           0           0                                         0        /  /             /  /        
09-1161   Reconstruction               0-007-009  04/29/10     DONE    DONE       DONE      03/26/10   03/23/10   03/03/10   05/19/09   4,8                      100,000       100,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /           05/04/11      
10-1199   Reconstruction               0-007-010  12/21/10     DONE    DONE       DONE      04/18/11   04/13/11   01/03/11   11/17/10   10                       324,000       324,000  HCM             0           0     324,000 Collins & Scoville Architects           0        /  /             /  /        
12-0395   Reconstruction               0-007-011  12/14/12     DONE    DONE       DONE      11/06/12   11/01/12   12/06/11   12/13/11   2,4,7,8,9,155,15,16    1,094,000     1,094,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Cherry Plain Jr/Sr High:
08-0551   Reconstruction               0-009-005  01/02/09     DONE    DONE       DONE      10/17/08   10/15/08   12/29/04   05/20/08   2,4,7,8,9,155,15,16      100,000       100,000  MGL             0           0           0 Collins & Scoville Architects           0        /  /           07/14/09      
12-1116   Reconstruction               0-009-006  05/07/13     DONE    DONE       DONE      04/17/13   04/17/13   12/06/11   12/13/11   2,4,7,9,155,15,16        335,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-009-007                                              /  /       /  /     04/23/13     /  /     2,4,7,8,9,155,15,16            0             0  JMB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-009-008                                              /  /       /  /     04/23/13     /  /     16                             0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRUNSWICK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-02-02-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Tamarac MS/HS High School:
  -       Reconstruction               0-003-021                                              /  /       /  /     03/20/13     /  /     16                             0             0  JMB             0           0           0                                         0        /  /             /  /        

          Waste Treatment Plant fmly 2-004:
09-1496   Reconstruction               0-004-004  06/16/10     DONE    DONE       DONE      06/07/10   05/28/10   07/31/09   03/25/10   13                       734,600       664,599  HCM             0           0           0 C.T. Male Associates, P.C.              0        /  /             /  /        

          Tamarac Elementary:
  -       Reconstruction               0-009-016                                              /  /       /  /     03/20/13     /  /     16                             0             0  JMB             0           0           0                                         0        /  /             /  /        

          Bus Garage:
  -       Reconstruction               5-005-006                                              /  /       /  /     03/20/13     /  /     16                             0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST GREENBUSH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-03-01-06
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Goff Middle School:
07-1924   Reconstruction               0-001-010  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,4,8,9,10,155,15,16   1,008,790     1,008,790  HCM             0           0     168,550 Envision Architects                     0        /  /             /  /        
12-1137   Reconstruction               0-001-011  05/07/13     DONE    DONE       DONE      04/30/13   04/24/13   02/19/10   01/09/13   7,9,155,16               178,496       178,496  JMB             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Green Meadow School:
07-1919   Reconstruction               0-002-013  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,7,8,10,15,16           507,661       507,661  HCM             0           0     109,761 Envision Architects                     0        /  /             /  /        

          Citizen Genet School:
07-1920   Reconstruction               0-003-011  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,4,7,8,9,10,155,15,   3,072,430     3,072,430  HCM             0           0     735,000 Envision Architects                     0        /  /           01/16/13      
09-0600   Reconstruction               0-003-012  09/24/09     DONE    DONE       DONE      12/22/09   12/15/09   09/24/09   09/23/09   4,7,9,13,15,16         1,500,000     1,500,000  HCM             0           0     172,759 Envision Architects                     0        /  /             /  /        

          Sutherland School:
07-1925   Reconstruction               0-006-011  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,4,8,9,10,15,16       1,142,781     1,142,781  HCM             0           0     200,478 Envision Architects                     0        /  /             /  /        

          Red Mill School:
07-1926   Reconstruction               0-007-009  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,8,10,15,16             618,499       618,499  HCM             0           0     124,519 Envision Architects                     0        /  /             /  /        

          Bell Top School:
07-1927   Reconstruction               0-008-009  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,8,9,10,15,16           607,078       607,078  HCM             0           0     111,372 Envision Architects                     0        /  /             /  /        

          Columbia High School:
07-1921   Reconstruction               0-009-007  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   07/03/07   02/24/07   4,9,10,155,16             58,642        58,642  HCM             0           0      10,976 Envision Architects                     0        /  /             /  /        
  -       Reconstruction               0-009-008                                              /  /       /  /     02/19/10     /  /     8,9,155                        0             0  HCM             0           0           0                                         0        /  /             /  /        
10-0797   Reconstruction               0-009-009  03/17/11     DONE    DONE       DONE      02/04/11   02/01/11   10/26/10   01/13/11   2                         75,000        75,000  HCM             0           0           0 Envision Architects                     0        /  /             /  /        
12-1200   Reconstruction               0-009-010                         UNREVIEWED         05/16/13   05/14/13   11/21/11   11/09/11   10                             0    56,570,390  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Grounds Shop:
07-1928   Reconstruction               3-012-003  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,7,8,10,155,15,16       176,923             0  HCM             0           0           0 Envision Architects                     0        /  /             /  /        

          Bus Storage:
07-1922   Reconstruction               4-011-001  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   03/06/08   02/24/07   13                        74,302        85,325  HCM             0           0           0 Envision Architects                     0        /  /             /  /        

          Bus Garage:
07-1923   Reconstruction               5-010-006  01/14/09     DONE    DONE       DONE      04/04/08   03/28/08   08/04/06   02/24/07   2,10,13,15,16            221,016       221,016  HCM             0           0           0 Envision Architects                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HOOSICK FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-05-01-06
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pressbox @ Athletic Field:
09-0830   New Construction             7-006-001  02/02/10     DONE    DONE       DONE      01/28/10   01/27/10   07/01/09   10/24/06   02 - 16                   79,648             0  JOD             0           0           0 Clark Patterson Lee                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LANSINGBURGH CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-06-01-06
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lansingburgh Elementary:
  -       Reconstruction               0-003-005                                              /  /       /  /     12/07/09     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0           0                                         0        /  /             /  /        

          Knickerbacker Middle School:
08-0256   Reconstruction               0-006-008  04/09/09     DONE    DONE       DONE      09/08/08   08/29/08   12/11/07   02/26/08   4,10,155,15,16           656,574       656,574  HCM             0           0      32,172 SEI Design Group                        0        /  /             /  /        
10-1351   Reconstruction               0-006-009  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   01/17/08   12/07/10   2,155,16                 400,000       400,000  HCM             0           0      29,160 SEI Design Group                        0        /  /           03/26/13      
11-0219   Reconstruction               0-006-010  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   12/07/09   12/07/10   2,4,7,8,9,155,15,16    3,553,826     3,553,826  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        
  -       Reconstruction               0-006-011                                              /  /       /  /     09/27/10     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0           0                                         0        /  /             /  /        

          Lansingburgh High School:
08-0257   Reconstruction               0-010-014  04/09/09     DONE    DONE       DONE      09/08/08   08/29/08   12/06/07   02/29/08   2,4,8,10,155,15,16       861,986       861,986  HCM             0           0      42,237 SEI Design Group                        0        /  /             /  /        
10-1352   Reconstruction               0-010-015  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   01/17/08   12/07/10   2,9,155,15,16            400,000       400,000  HCM             0           0      29,160 SEI Design Group                        0        /  /           03/26/13      
11-0220   Reconstruction               0-010-016  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   12/04/09   12/07/10   2,4,7,8,9,155,15,16    6,101,619     6,101,619  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        
  -       Reconstruction               0-010-017                                              /  /       /  /     02/22/10     /  /     2,15,16                        0             0  HCM             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-010-018                                              /  /       /  /     10/30/12     /  /     155,15,16                      0    18,291,725  JMB             0           0           0                                         0        /  /             /  /        

          Rensselaer Park Elementary:
08-0258   Reconstruction               0-014-008  04/09/09     DONE    DONE       DONE      09/08/08   08/29/08   03/12/08   02/26/08   2,4,10,155,15,16          73,197        73,197  HCM             0           0       3,587 SEI Design Group                        0        /  /             /  /        
10-1353   Reconstruction               0-014-009  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   12/07/09   12/07/10   2,4,8,9,155,15,16        350,000       350,000  HCM             0           0      24,840 SEI Design Group                        0        /  /           03/26/13      
11-0221   Reconstruction               0-014-010  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   09/27/10   12/07/10   2,4,8,9,155,15,16      3,515,952     3,515,952  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        

          Turnpike Elem School:
08-0259   Reconstruction               0-015-009  04/09/09     DONE    DONE       DONE      09/08/08   08/29/08   12/11/07   02/26/08   2,8,10,15,16           1,308,243     1,308,243  HCM             0           0      64,104 SEI Design Group                        0        /  /             /  /        
10-1354   Reconstruction               0-015-010  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   12/07/09   12/07/10   2,4,8,9,155,15,16        350,000       350,000  HCM             0           0      24,840 SEI Design Group                        0        /  /           03/26/13      
11-0222   Reconstruction               0-015-011  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   09/27/10   12/07/10   2,4,8,9,155,15,16      3,798,590             0  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        

          Storage Building:
11-0223   New Construction             2-020-001  12/21/11     DONE    DONE       DONE      09/30/11   09/28/11   09/16/11   12/07/10   02 - 16                   30,000             0  HCM             0           0           0 SEI Design Group                        0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WYNANTSKILL UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-08-04-02
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Gardner Dickinson:
09-0285   Reconstruction               0-004-008  02/26/10     DONE    DONE       DONE      10/05/09   10/05/09   04/09/09   05/15/07   2,7,8,155,15,16          738,440       738,440  JOD             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-004-009                                              /  /       /  /     05/03/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RENSSELAER CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-12-00-01
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Van Rensselaer Elementary:
  -       Reconstruction               0-003-015                                              /  /       /  /     12/19/12     /  /     2,4,8,10,13,16                 0    12,442,116  DDJ             0           0           0                                         0        /  /             /  /        

          New Pre-K-12 Building:
08-0001   Reconstruction               0-013-002  03/31/06     DONE    DONE       DONE      07/09/08   07/07/08   10/17/07   10/23/07   8                         75,000        75,000  JOD             0           0      75,000 Dodge Chamberlin Luzine Weber           0        /  /             /  /        
12-0951   Reconstruction               0-013-003               UNREVIEWED
                                                                       STARTED    UNREVIEWED03/11/13   03/05/13   01/02/13   11/01/05   2,4,10,13,16           3,575,000             0  MFS             0           0     721,119 Mosaic Associates                       0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




AVERILL PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-13-02-06
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
10-0492   Reconstruction               0-001-008  11/30/10     DONE    DONE       DONE      11/18/10   11/12/10   10/14/10   11/16/10   16                       291,211       291,211  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
08-1683   Visual Structural Inspection 0-001-SC1  06/18/09     DONE    DONE       DONE      06/12/09   06/12/09     /  /       /  /     16                         2,875         2,875  JOD             0           0           0                                         0        /  /             /  /        
08-1699SC Visual Structural Inspection 0-001-SC2  06/18/09     DONE    DONE       DONE      05/28/09   05/28/09     /  /       /  /     16                         1,140         1,140  JOD             0           0           0                                         0        /  /             /  /        
08-1700SC Visual Structural Inspection 0-001-SC3  06/18/09     DONE    DONE       DONE      05/28/09   05/28/09     /  /       /  /     16                         2,460         2,460  JOD             0           0           0                                         0        /  /             /  /        

          Poestenkill Elementary:
12-0007   Reconstruction               0-004-005  08/24/12     DONE    DONE       DONE      07/09/12   07/05/12   06/16/11   05/15/12   2,15                      90,000        90,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /           02/15/13      
08-1698SC Visual Structural Inspection 0-004-SC2  06/18/09     DONE    DONE       DONE      05/28/09   05/28/09     /  /       /  /     16                           514             0  JOD             0           0           0                                         0        /  /             /  /        

          West Sand Lake Elementary:
08-1684SC Visual Structural Inspection 0-006-SC1  06/18/09     DONE    DONE       DONE      06/12/09   06/12/09     /  /       /  /     16                         5,900             0  JOD             0           0           0                                         0        /  /             /  /        

          algonguin middle school:
08-1697SC Visual Structural Inspection 0-009-SC1  06/18/09     DONE    DONE       DONE      05/28/09   05/28/09     /  /       /  /     16                           705             0  JOD             0           0           0                                         0        /  /             /  /        

          Miller Hill Elementary:
08-1685SC Visual Structural Inspection 0-010-SC1  06/18/09     DONE    DONE       DONE      06/12/09   06/12/09     /  /       /  /     16                         1,530             0  JOD             0           0           0                                         0        /  /             /  /        

          New Bus Garage:
08-1748   Reconstruction               5-016-002  06/30/09     DONE    DONE       DONE      06/29/09   06/29/09   03/26/09   06/23/09   13                       150,000       150,000  HCM             0           0           0 Professional Service Indusrie           0        /  /             /  /        
09-0877   Reconstruction               5-016-003  03/10/10     DONE    DONE       DONE      02/10/10   02/05/10   02/05/10   02/27/07   16                        20,000        20,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
08-1695SC Visual Structural Inspection 5-016-SC2  06/18/09     DONE    DONE       DONE      05/28/09   05/28/09     /  /       /  /     16                         1,150             0  JOD             0           0           0                                         0        /  /             /  /        
08-1696SC Visual Structural Inspection 5-016-SC3  06/18/09     DONE    DONE       DONE      05/28/09   05/28/09     /  /       /  /     16                           753             0  JOD             0           0           0                                         0        /  /             /  /        

          Greenhouse # Highschool:
09-1355   New Construction             7-024-001  05/26/11     DONE    DONE       DONE      04/22/10   04/19/10   10/16/09   02/27/07   02 - 16                   31,500             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HOOSIC VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-14-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
12-1164   Reconstruction               0-001-006                         UNREVIEWED         05/07/13   05/03/13   12/21/12   12/14/06   2,155,16                       0    12,164,145  JMB             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-001-010                                              /  /       /  /     01/24/13     /  /     13,16                          0             0  JOB             0           0           0                                         0        /  /             /  /        

          Junior Senior High School:
12-1165   Reconstruction               0-002-012                         UNREVIEWED         05/07/13   05/03/13   12/21/12   12/14/06   2,4,9,10,16                    0    12,620,076  JMB             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-002-016                                              /  /       /  /     01/24/13     /  /     13,16                          0    14,349,608  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-002-017                                              /  /       /  /     01/25/13     /  /     13,16                          0    14,349,608  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-002-018                                              /  /       /  /     03/05/13     /  /     7                              0    14,349,608  JMB             0           0           0                                         0        /  /             /  /        
12-0986   Reconstruction               0-002-019  04/16/13     DONE    DONE       DONE      03/18/13   03/15/13   03/05/13   12/14/06   9,10                     155,900             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          New Transportation Facility:
  -       Reconstruction               5-009-003                                              /  /       /  /     01/24/13     /  /     13,16                          0             0  JOB             0           0           0                                         0        /  /             /  /        

          Districtwide:
  -       Reconstruction               7-999-002                                              /  /       /  /     02/14/13     /  /     16                             0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHODACK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-15-01-04
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Castleton Elementary:
11-0516   Reconstruction               0-001-015  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0    11,842,577  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /             /  /        

          Maple Hill High School:
11-0517   Reconstruction               0-002-018  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0    13,637,617  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /             /  /        

          Middle School:
11-0518   Reconstruction               0-004-011  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0    11,310,056  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /             /  /        
11-1442   Reconstruction               0-004-012  07/03/12     DONE    DONE       DONE      06/28/12   06/26/12   06/14/12   06/21/12   2,9                      289,500       289,500  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /           02/26/13      

          Bus Garage:
11-0519   Reconstruction               5-005-008  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0             0  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TROY CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-17-00-01
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          School #1:
07-2107   Reconstruction               0-001-005  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   2,155,15,16              569,402       569,402  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        

          Public School #2:
07-2108   Reconstruction               0-002-007  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   2,7,8,9,15,16             88,177        88,177  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        

          Public School #12:
07-2109   Reconstruction               0-005-010  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   16                        39,887             0  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        
  -    PR Additions and Alterations    0-005-011                                              /  /       /  /     01/09/09     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          School-14:
07-2110   Reconstruction               0-006-007  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   04/24/08   05/16/00   9,15,16                1,111,491     1,111,491  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        

          Public School #16:
07-2111   Reconstruction               0-008-009  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   2,7,9,155,15,16          614,180       614,180  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        
  -    PR Additions and Alterations    0-008-010                                              /  /       /  /     01/09/09     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          School #18:
07-2112   Reconstruction               0-010-010  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   2,155,15,16              347,398       347,398  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        
12-0011   Reconstruction               0-010-011  01/30/12     DONE    DONE       DONE      07/09/12   07/03/12   09/06/11   01/18/12   155                      193,950       193,950  JOD             0           0           0 Mosaic Associates                       0        /  /           12/17/12      
  -       Reconstruction               0-010-012                                              /  /       /  /     03/13/13     /  /     10,16                          0             0  JOB             0           0           0                                         0        /  /             /  /        

          Troy High School:
07-2113   Reconstruction               0-011-022  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   2,4,155,15,16          3,569,927     3,569,927  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        
  -       Reconstruction               0-011-023                                              /  /       /  /     02/19/09     /  /     2,4,7,8,9,155,15,16            0             0  JOD             0           0           0                                         0        /  /             /  /        
10-0582   Reconstruction               0-011-024  04/25/11     DONE    DONE       DONE      12/13/10   12/08/10   02/02/10   02/10/10   2,4,7,8,9,155,15,16    4,933,059             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        

          W. K. Doyle Middle School:
07-1754   Reconstruction               0-012-012  06/03/08     DONE    DONE       DONE      03/06/08   02/29/08   11/09/07   03/08/00   2,15,16                  100,000       100,000  JOD             0           0           0 Thomas Associates                       0        /  /           06/30/12      
07-2114   Reconstruction               0-012-013  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   04/24/08   05/16/00   9,16                     321,191       321,191  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        
10-1056   Reconstruction               0-012-014  08/23/11     DONE    DONE       DONE      03/17/11   03/11/11   02/03/10   02/10/10   2,4,7,8,9,10,13,14,1  51,420,000    51,420,000  JOD             0           0   3,422,611 Mosaic Associates                       0        /  /           09/07/12      

          Carroll Hill School:
07-2115   Reconstruction               0-016-007  01/30/09     DONE    DONE       DONE      05/16/08   05/08/08   11/09/07   05/16/00   2,4,8,9,16               205,741       205,741  JOD             0           0           0 Thomas Associates                       0        /  /             /  /        

          Athlet Field Storage:
10-0583   Reconstruction               2-004-002  04/25/11     DONE    DONE       DONE      12/13/10   12/08/10   12/07/99   02/10/10   16                        10,000             0  BJB             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Metal Storage Building @ School #14:
  -    DB Discovered Building          2-029-001                                              /  /       /  /     03/09/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Metal Atheletic Storage Building:
  -    DB Discovered Building          2-030-001                                              /  /       /  /     03/03/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Metal Maintenance Storage Buiolding:
  -    DB Discovered Building          2-068-001                                              /  /       /  /     03/05/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          YMCA:
11-0289TQ Temporary Quarters           8-031-001  12/01/11     DONE    DONE       DONE      10/26/11   10/25/11   09/07/11     /  /                                    0             0  JOD             0           0           0 Chazen Engineering & Land Sur           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES QUESTAR III STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-90-00-00
last updated on 05/20/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Columbia-Green VoTec Center:
07-2306   Reconstruction               0-021-003  12/17/08     DONE    DONE       DONE      07/03/08   06/18/08   04/03/08   06/10/08   2,4,8                    557,000       557,000  JOD             0           0           0 Collins & Scoville Architects           0        /  /           01/07/13      
10-1325   Reconstruction               0-021-004  08/05/11     DONE    DONE       DONE      05/20/11   05/18/11   05/26/11   05/12/11   4,7,8,9,155,16           400,000       400,000  JOD             0           0           0                                         0        /  /           02/21/13      
12-1071   Reconstruction               0-021-005                         UNREVIEWED         04/05/13   04/02/13   02/13/13   02/13/13   2,8,9                          0             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /             /  /        
12-0926   Reconstruction               0-021-006  04/11/13     DONE    DONE       DONE      02/28/13   02/25/13   02/13/13   02/13/13   2,8,9,155,16             110,000             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /             /  /        

          Rensselaer Educational Center:
12-0927   Reconstruction               0-030-002  04/11/13     DONE    DONE       DONE      02/28/13   02/25/13   09/15/11   02/13/13   2,4,7,8,9,10,155,15,      62,000             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED