Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/24/14 at 16:40:58




BERLIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-01-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Berlin Elementary:
  -       Reconstruction               0-007-008                                              /  /       /  /     12/12/12     /  /     2,4,7,8,9,10,14,155,           0     4,541,040  JMB             0           0           0                                         0        /  /                           /  /             
09-1161   Reconstruction               0-007-009  04/29/10     DONE    DONE       DONE      03/26/10   03/23/10   03/03/10   05/19/09   4,8                      100,000       100,000  HCM             0           0           0 Collins & Scoville Architects           0      09/21/10                       05/04/11           
10-1199   Reconstruction               0-007-010  12/21/10     DONE    DONE       DONE      04/18/11   04/13/11   01/03/11   11/17/10   10                       324,000       324,000  HCM             0           0     324,000 Collins & Scoville Architects           0      01/10/11                         /  /             
12-0395   Reconstruction               0-007-011  12/14/12     DONE    DONE       DONE      11/06/12   11/01/12   12/06/11   12/13/11   2,4,7,8,9,155,15,16    1,094,000     1,094,000  JMB             0           0           0 Collins & Scoville Architects           0      09/05/13                       06/13/14           
12-1282   Reconstruction               0-007-012  12/04/13     DONE    DONE       DONE      06/13/13   06/13/13   06/17/13   12/13/11   2,4,7,8,9,10,14,155,   2,856,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Cherry Plain Jr/Sr High:
12-1116   Reconstruction               0-009-006  05/07/13     DONE    DONE       DONE      04/17/13   04/17/13   12/06/11   12/13/11   2,4,7,9,155,15,16        335,000       335,000  HCM             0           0           0 Collins & Scoville Architects           0      10/25/13                       05/06/14           
12-1283   Reconstruction               0-009-007  12/04/13     DONE    DONE       DONE      06/13/13   06/13/13   04/23/13   12/13/11   2,4,7,8,9,155,15,16    2,540,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0194   Reconstruction               0-009-008  08/29/13     DONE    DONE       DONE      08/14/13   08/12/13   04/23/13   05/15/12   16                       100,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRUNSWICK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-02-02-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Tamarac MS/HS High School:
12-1301   Reconstruction               0-003-021  07/19/13     DONE    DONE       DONE      06/19/13   06/17/13   03/20/13   03/07/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      11/12/13                       11/18/13           

          Waste Treatment Plant fmly 2-004:
09-1496   Reconstruction               0-004-004  06/16/10     DONE    DONE       DONE      06/07/10   05/28/10   07/31/09   03/25/10   13                       734,600       664,599  HCM             0           0           0 C.T. Male Associates, P.C.              0      01/11/11                         /  /             

          Tamarac Elementary:
12-1302   Reconstruction               0-009-016  07/19/13     DONE    DONE       DONE      06/19/13   06/17/13   03/20/13   03/07/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      11/12/13                       11/18/13           

          Bus Garage:
12-1303   Reconstruction               5-005-006  07/19/13     DONE    DONE       DONE      06/19/13   06/17/13   03/20/13   03/07/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      11/01/13                       11/18/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST GREENBUSH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-03-01-06
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Goff Middle School:
12-1137   Reconstruction               0-001-011  05/07/13     DONE    DONE       DONE      04/30/13   04/24/13   02/19/10   01/09/13   7,9,155,16               178,496       178,496  JMB             0           0           0 Collins & Scoville Architects           0      11/11/13                       11/25/13           
13-0347   Reconstruction               0-001-012  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   2,7,8,9,155,16         1,598,047     1,598,047  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1524   Reconstruction               0-001-013               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/09/13   05/21/13   2,8,9,155,15,16                0    21,560,214  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-014                                              /  /       /  /     07/16/14     /  /     155,16                         0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Green Meadow School:
13-0348   Reconstruction               0-002-015  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/02/13   05/21/13   2,7,8,9,155,16         1,212,764     1,212,764  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1525   Reconstruction               0-002-016               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/02/13   05/21/13   2,8,9,155,15,16                0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Citizen Genet School:
09-0600   Reconstruction               0-003-012  09/24/09     DONE    DONE       DONE      12/22/09   12/15/09   09/24/09   09/23/09   4,7,9,13,15,16         1,500,000     1,500,000  HCM             0           0     172,759 Envision Architects                     0      06/30/10                         /  /             
13-0349   Reconstruction               0-003-013  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   2,8,9,16               1,198,531     1,198,531  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0786   Reconstruction               0-003-014  03/14/14     DONE    DONE       DONE      11/27/13   11/22/13   08/01/13   05/21/13   155,16                 1,471,500     1,471,500  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1526   Reconstruction               0-003-015               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   2,8,9,155,16                   0     7,744,464  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Sutherland School:
  -       Reconstruction               0-006-012                                              /  /       /  /     08/01/13     /  /     2,8,9,155,15,16                0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0350   Reconstruction               0-006-013  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   2,7,8,9,155,16           537,735       537,735  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1527   Reconstruction               0-006-014               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   2,8,9,155,15,16                0     5,280,912  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1487   Reconstruction               0-006-015  04/07/14     DONE    DONE       DONE      04/25/14   04/17/14   03/13/14   03/26/14   4,7,9                    400,000       400,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Red Mill School:
13-0351   Reconstruction               0-007-010  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   2,7,8,9,155,16           874,192       874,192  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1528   Reconstruction               0-007-011               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   2,8,9,155,15,16                0     8,137,584  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Bell Top School:
13-0352   Reconstruction               0-008-010  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   2,7,8,9,155,16           740,404       740,404  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1529   Reconstruction               0-008-011               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   2,7,8,9,155,15,16              0     4,953,312  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-008-012                                              /  /       /  /     07/16/14     /  /     2                              0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Columbia High School:
  -       Reconstruction               0-009-008                                              /  /       /  /     02/19/10     /  /     8,9,155                        0    57,529,330  HCM             0           0           0                                         0        /  /                           /  /             
10-0797   Reconstruction               0-009-009  03/17/11     DONE    DONE       DONE      02/04/11   02/01/11   10/26/10   01/13/11   2                         75,000        75,000  HCM             0           0           0 Envision Architects                     0      01/12/12                         /  /             
12-1200   Reconstruction               0-009-010  11/08/11     DONE    DONE       DONE      05/16/13   05/14/13   11/21/11   11/09/11   10                       111,969       111,969  HCM             0           0           0 Collins & Scoville Architects           0      11/09/13                       11/26/13           
13-0353   Reconstruction               0-009-011  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   2,8,9,155,16             605,912             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1530   Reconstruction               0-009-012               STARTED STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   2,4,7,8,9,155,15,16            0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-009-013                                              /  /       /  /     02/28/14     /  /     10,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Grounds Shop:
13-1531   Reconstruction               3-012-004               DONE    STARTED    UNREVIEWED05/14/14   05/09/14   08/02/13   05/21/13   10,155,16                      0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -    XX Reconstruction               3-012-005                         CANCELLED            /  /       /  /     08/02/13     /  /     10,155,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Storage:
13-1532   Reconstruction               4-011-002               DONE    STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Bus Garage:
13-0354   Reconstruction               5-010-007  03/12/14     DONE    DONE       DONE      09/11/13   09/05/13   08/01/13   05/21/13   10,15,16                 479,251             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-1533   Reconstruction               5-010-008               DONE    STARTED    UNREVIEWED05/14/14   05/09/14   08/01/13   05/21/13   7,8                            0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Districtwide:
  -       Reconstruction               7-999-002                                              /  /       /  /     08/02/13     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-999-003                                              /  /       /  /     08/02/13     /  /     155                            0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HOOSICK FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-05-01-06
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
13-1075   Reconstruction               0-001-014  07/15/14     DONE    DONE       DONE      01/22/14   01/22/14   11/01/13   10/17/13   2,155,15,16              500,000             0  DDJ             0           0           0 Clark Patterson Lee               250,000        /  /                           /  /             

          Pressbox @ Athletic Field:
09-0830   New Construction             7-006-001  02/02/10     DONE    DONE       DONE      01/28/10   01/27/10   07/01/09   10/24/06   02 - 16                   79,648             0  JOD             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LANSINGBURGH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-06-01-06
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lansingburgh Elementary:
  -       Reconstruction               0-003-005                                              /  /       /  /     12/07/09     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Knickerbacker Middle School:
10-1351   Reconstruction               0-006-009  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   01/17/08   12/07/10   2,155,16                 400,000       400,000  HCM             0           0      29,160 SEI Design Group                        0      03/02/12                       03/26/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0219   Reconstruction               0-006-010  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   12/07/09   12/07/10   2,4,7,8,9,155,15,16    3,553,826     3,553,826  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0282   Reconstruction               0-006-011  03/24/14     DONE    DONE       DONE      08/26/13   08/26/13   09/27/10   05/21/13   2,4,8,9,155,15,16        597,500             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Lansingburgh High School:
10-1352   Reconstruction               0-010-015  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   01/17/08   12/07/10   2,9,155,15,16            400,000       400,000  HCM             0           0      29,160 SEI Design Group                        0      03/02/12                       03/26/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0220   Reconstruction               0-010-016  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   12/04/09   12/07/10   2,4,7,8,9,155,15,16    6,101,619     6,101,619  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0283   Reconstruction               0-010-017  03/24/14     DONE    DONE       DONE      08/26/13   08/26/13   02/22/10   05/21/13   2,15,16                  747,500             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-010-018                                              /  /       /  /     10/30/12     /  /     155,15,16                      0    18,291,725  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-010-019                                              /  /       /  /     07/30/13     /  /     2,8,9,13,155,16                0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Rensselaer Park Elementary:
10-1353   Reconstruction               0-014-009  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   12/07/09   12/07/10   2,4,8,9,155,15,16        350,000       350,000  HCM             0           0      24,840 SEI Design Group                        0      03/02/12                       03/26/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0221   Reconstruction               0-014-010  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   09/27/10   12/07/10   2,4,8,9,155,15,16      3,515,952     3,515,952  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Turnpike Elem School:
10-1354   Reconstruction               0-015-010  06/29/11     DONE    DONE       DONE      06/02/11   05/31/11   12/07/09   12/07/10   2,4,8,9,155,15,16        350,000       350,000  HCM             0           0      24,840 SEI Design Group                        0      03/02/12                       03/26/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0222   Reconstruction               0-015-011  12/21/11     DONE    DONE       DONE      10/03/11   09/28/11   09/27/10   12/07/10   2,4,8,9,155,15,16      3,798,590             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Storage Building:
11-0223   New Construction             2-020-001  12/21/11     DONE    DONE       DONE      09/30/11   09/28/11   09/16/11   12/07/10   02 - 16                   30,000             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Baseball Dugout #1:
13-1652DB Discovered Building          7-021-001  07/11/14     DONE    DONE       DONE      06/25/14   06/20/14   05/16/14     /  /                                    0             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Baseball Dugout #2:
13-1653DB Discovered Building          7-022-001  07/11/14     DONE    DONE       DONE      06/25/14   06/20/14   05/16/14     /  /                                    0             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Softball Dugout #1:
13-1654DB Discovered Building          7-023-001  07/11/14     DONE    DONE       DONE      06/25/14   06/20/14   05/16/14     /  /                                    0             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Softball Dugout #2:
13-1655DB Discovered Building          7-024-001  07/11/14     DONE    DONE       DONE      06/25/14   06/20/14   05/16/14     /  /                                    0             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Snack Shack:
13-1656DB Discovered Building          7-025-001  07/11/14     DONE    DONE       DONE      06/25/14   06/20/14   05/27/14     /  /                                    0             0  JMB             0           0           0 SEI Design Group                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WYNANTSKILL UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-08-04-02
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Gardner Dickinson:
09-0285   Reconstruction               0-004-008  02/26/10     DONE    DONE       DONE      10/05/09   10/05/09   04/09/09   05/15/07   2,7,8,155,15,16          738,440       738,440  JOD             0           0           0 Collins & Scoville Architects           0      09/24/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-004-009                                              /  /       /  /     05/03/13     /  /     16                             0             0  JOB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RENSSELAER CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-12-00-01
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Pre-K-12 Building:
12-0951   Reconstruction               0-013-003  09/20/13     DONE    DONE       DONE      03/11/13   03/05/13   01/02/13   11/01/05   2,4,10,13,16           3,575,000     3,575,000  MFS             0           0     721,119 Mosaic Associates                       0        /  /                           /  /             
13-0838   Reconstruction               0-013-004  12/13/13     DONE    DONE       DONE      12/05/13   12/04/13   10/01/13   10/01/13   16                             0    45,145,494  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




AVERILL PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-13-02-06
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
10-0492   Reconstruction               0-001-008  11/30/10     DONE    DONE       DONE      11/18/10   11/12/10   10/14/10   11/16/10   16                       291,211       291,211  HCM             0           0           0 Collins & Scoville Architects           0      08/25/11                         /  /             
13-0446   Reconstruction               0-001-009  02/26/14     DONE    DONE       DONE      10/03/13   09/27/13   08/07/13   05/21/13   155                    1,166,000             0  JMB             0           0     457,001 Collins & Scoville Architects           0        /  /                           /  /             
13-0538   Reconstruction               0-001-010  05/27/14     DONE    DONE       DONE      10/16/13   10/10/13   08/26/13   05/21/13   2,4,7,8,9,10,155,15,   6,185,300             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Poestenkill Elementary:
12-0007   Reconstruction               0-004-005  08/24/12     DONE    DONE       DONE      07/09/12   07/05/12   06/16/11   05/15/12   2,15                      90,000        90,000  HCM             0           0           0 Collins & Scoville Architects           0      09/20/13                       12/16/13           
13-0461   Reconstruction               0-004-006  01/03/14     DONE    DONE       DONE      10/07/13   10/04/13   08/15/13   05/21/13   2,7                      343,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0539   Reconstruction               0-004-007  05/27/14     DONE    DONE       DONE      10/16/13   10/10/13   08/26/13   05/21/13   155,16                   301,900             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-004-008                                              /  /       /  /     09/10/13     /  /     155,15                         0             0  JMB             0           0           0                                         0        /  /                           /  /             

          West Sand Lake Elementary:
13-0462   Reconstruction               0-006-008  01/03/14     DONE    DONE       DONE      10/07/13   10/04/13   08/15/13   05/21/13   9                         81,600             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0540   Reconstruction               0-006-009  05/27/14     DONE    DONE       DONE      10/16/13   10/10/13   08/26/13   05/21/13   155,16                   349,100             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Algonguin Middle School:
13-0541   Reconstruction               0-009-009  05/27/14     DONE    DONE       DONE      10/16/13   10/10/13   08/26/13   05/21/13   9,155,16                 693,600             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-009-010                                              /  /       /  /     09/10/13     /  /     2,9,155,15,16                  0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Miller Hill Elementary:
13-0445   Reconstruction               0-010-005  02/26/14     DONE    DONE       DONE      10/03/13   09/27/13   08/07/13   05/21/13   155                      612,500             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0463   Reconstruction               0-010-006  01/03/14     DONE    DONE       DONE      10/07/13   10/04/13   09/26/13   05/21/13   2,4,7                    525,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0542   Reconstruction               0-010-007  05/27/14     DONE    DONE       DONE      10/16/13   10/10/13   09/26/13   05/21/13   155,16                   316,600             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-010-008                                              /  /       /  /     09/26/13     /  /     155,15                         0             0  JMB             0           0           0                                         0        /  /                           /  /             

          George Washington School:
13-0464   Reconstruction               0-017-006  01/03/14     DONE    DONE       DONE      10/07/13   10/04/13   08/15/13   05/21/13   2,7                      167,400             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-017-007                                              /  /       /  /     09/10/13     /  /     4,15                           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          New Bus Garage:
09-0877   Reconstruction               5-016-003  03/10/10     DONE    DONE       DONE      02/10/10   02/05/10   02/05/10   02/27/07   16                        20,000        20,000  HCM             0           0           0 Collins & Scoville Architects           0      11/01/10                         /  /             
13-0465   Reconstruction               5-016-004  01/03/14     DONE    DONE       DONE      10/07/13   10/04/13   08/15/13   05/21/13   7                        413,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
13-0543   Reconstruction               5-016-005  05/27/14     DONE    DONE       DONE      10/16/13   10/10/13   08/26/13   05/21/13   155,16                   105,000             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Greenhouse # Highschool:
09-1355   New Construction             7-024-001  05/26/11     DONE    DONE       DONE      04/22/10   04/19/10   10/16/09   02/27/07   02 - 16                   31,500             0  HCM             0           0           0 Collins & Scoville Architects           0      08/29/11                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HOOSIC VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-14-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
12-1164   Reconstruction               0-001-006  09/11/13     DONE    DONE       DONE      05/07/13   05/03/13   12/21/12   12/14/06   2,155,16                 136,600       136,600  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-001-010                                              /  /       /  /     01/24/13     /  /     13,16                          0             0  JOB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-011                                              /  /       /  /     07/17/14     /  /     2,7,155,15,16                  0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Junior Senior High School:
12-1165   Reconstruction               0-002-012  07/18/13     DONE    DONE       DONE      05/07/13   05/03/13   12/21/12   12/14/06   2,4,9,10,16               33,550             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-002-016                                              /  /       /  /     01/24/13     /  /     13,16                          0    14,349,608  JOB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-017                                              /  /       /  /     01/25/13     /  /     13,16                          0    14,349,608  JOB             0           0           0                                         0        /  /                           /  /             
13-0105   Reconstruction               0-002-018  08/02/13     DONE    DONE       DONE      07/29/13   07/29/13   03/05/13   07/10/13   7                        150,250             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
12-0986   Reconstruction               0-002-019  04/16/13     DONE    DONE       DONE      03/18/13   03/15/13   03/05/13   12/14/06   9,10                     155,900             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          New Transportation Facility:
  -       Reconstruction               5-009-003                                              /  /       /  /     01/24/13     /  /     13,16                          0             0  JOB             0           0           0                                         0        /  /                           /  /             

          Districtwide:
12-1334   Reconstruction               7-999-002  10/01/13     DONE    DONE       DONE      06/27/13   06/27/13   02/14/13   10/15/12   16                             0             0  JMB             0           0           0 Collins & Scoville Architects           0      03/25/14                       05/05/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHODACK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-15-01-04
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Castleton Elementary:
11-0516   Reconstruction               0-001-015  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0    11,918,987  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             

          Maple Hill High School:
11-0517   Reconstruction               0-002-018  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0    13,725,610  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             
13-1585   Reconstruction               0-002-019  06/12/14     DONE    DONE       DONE      05/29/14   05/22/14   02/07/14   05/20/14   2,15                     913,360             0  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             

          Middle School:
11-0518   Reconstruction               0-004-011  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0    11,383,032  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             
11-1442   Reconstruction               0-004-012  07/03/12     DONE    DONE       DONE      06/28/12   06/26/12   06/14/12   06/21/12   2,9                      289,500       289,500  DDJ             0           0           0 Synthesis Architects,L.L.P.             0      10/10/12                       02/26/13           
13-1586   Reconstruction               0-004-013  06/26/14     DONE    DONE       DONE      05/29/14   05/22/14   02/07/14   05/20/14   7                        318,760             0  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             

          Bus Garage:
11-0519   Reconstruction               5-005-008  01/23/12     DONE    DONE       DONE      12/22/11   12/21/11   11/16/11   12/01/11   16                             0             0  DDJ             0           0           0 Synthesis Architects,L.L.P.             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TROY CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-17-00-01
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          School #18:
12-0011   Reconstruction               0-010-011  01/30/12     DONE    DONE       DONE      07/09/12   07/03/12   09/06/11   01/18/12   155                      193,950       193,950  JOD             0           0           0 Mosaic Associates                       0      05/14/12                       12/17/12           
13-0085   Reconstruction               0-010-012  07/18/14     DONE    DONE       DONE      07/24/13   07/23/13   03/13/13   03/12/13   10,16                    100,000             0  JOB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Troy High School:
10-0582   Reconstruction               0-011-024  04/25/11     DONE    DONE       DONE      12/13/10   12/08/10   02/02/10   02/10/10   2,4,7,8,9,155,15,16    4,933,059     4,933,059  JOD             0           0           0 Mosaic Associates                       0      04/30/13                       02/28/14           
  -       Reconstruction               0-011-025                                              /  /       /  /     07/16/14     /  /     10                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          W.K. Doyle Middle School:
10-1056   Reconstruction               0-012-014  08/23/11     DONE    DONE       DONE      03/17/11   03/11/11   02/03/10   02/10/10   2,4,7,8,9,10,13,14,1  51,420,000    51,420,000  JOD             0           0   3,422,611 Mosaic Associates                       0      04/21/14                       04/30/14           
13-1427   Reconstruction               0-012-015  08/20/13     DONE    DONE       DONE      04/02/14   03/28/14   03/05/14   08/07/13   2,155,15                  61,877        61,877  MFS             0           0           0 Mosaic Associates Architects            0      04/08/14                       04/21/14           

          Athlet Field Storage:
10-0583   Reconstruction               2-004-002  04/25/11     DONE    DONE       DONE      12/13/10   12/08/10   12/07/99   02/10/10   16                        10,000             0  BJB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Metal Storage Building @ School #14:
  -    DB Discovered Building          2-029-001                                              /  /       /  /     03/09/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Metal Atheletic Storage Building:
  -    DB Discovered Building          2-030-001                                              /  /       /  /     03/03/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Metal Maintenance Storage Buiolding:
  -    DB Discovered Building          2-068-001                                              /  /       /  /     03/05/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          District-Wide:
13-1404   Reconstruction               7-999-004                         UNREVIEWED         03/25/14   03/21/14   02/04/14   10/21/13   10,16                          0             0  MFS             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          YMCA:
11-0289TQ Temporary Quarters           8-031-001  12/01/11     DONE    DONE       DONE      10/26/11   10/25/11   09/07/11     /  /                                    0             0  JOD             0           0           0 Chazen Engineering & Land Sur           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES QUESTAR III STATUS REPORT ON CAPITAL PROJECTS
District No.: 49-90-00-00
last updated on 07/24/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          John E. Sackett Educ. Center:
  -       Reconstruction               0-001-002                                              /  /       /  /     07/24/13     /  /     155                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Columbia-Green VoTec Center:
10-1325   Reconstruction               0-021-004  08/05/11     DONE    DONE       DONE      05/20/11   05/18/11   05/26/11   05/12/11   4,7,8,9,155,16           400,000       400,000  JOD             0           0           0                                         0      01/11/13                       02/21/13           
12-1071   Reconstruction               0-021-005  06/26/13     DONE    DONE       DONE      04/05/13   04/02/13   02/13/13   02/13/13   2,8,9                  1,595,000             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
12-0926   Reconstruction               0-021-006  04/11/13     DONE    DONE       DONE      02/28/13   02/25/13   02/13/13   02/13/13   2,8,9,155,16             110,000             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             
  -       Reconstruction               0-021-007                                              /  /       /  /     07/24/13     /  /     2,7,8,9,155,16                 0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Rensselaer Educational Center:
12-0927   Reconstruction               0-030-002  04/11/13     DONE    DONE       DONE      02/28/13   02/25/13   09/15/11   02/13/13   2,4,7,8,9,10,155,15,      62,000             0  MFS             0           0           0 BCK-IBI Group, a New York Gen           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED