ROCKLAND COUNTY

ROCKLAND COUNTY

CLARKSTOWN 500101
EAST RAMAPO 500402
HAVERSTRAW-ST 500201
LAKESIDE-RAMAP 500414
NANUET 500108
NYACK 500304
PEARL RIVER 500308
RAMAPO 500401
ROCKLAND BOCES 509000
S. ORANGETOWN 500301

















Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/29/16 at 07:25:46




CLARKSTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-01-01-06
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Congers Elementary:
11-0801   Reconstruction               0-001-014  10/23/12     DONE    DONE       DONE      02/13/12   02/09/12   09/14/11   05/17/11   4,8,9,16                 179,000       179,000  HCM             0           0           0 Mosaic Associates                       0      11/10/15                       01/07/16           
14-0120   Reconstruction               0-001-015  09/02/14     DONE    DONE       DONE      08/12/14   08/01/14   10/03/13   02/06/14   2,4,7,8,9              6,500,000             0  JMB             0           0           0 Collins & Scoville Architects           0      08/06/15           YES         08/13/15           

          Birchwood School:
11-1074   Reconstruction               0-002-010  09/04/12     DONE    DONE       DONE      04/04/12   03/02/12   11/16/07   06/09/11   13                        97,912             0  HCM             0           0           0 Fellenzer Engineering                   0        /  /                           /  /             
15-1893   Reconstruction               0-002-011                         UNREVIEWED         06/09/16   06/08/16   01/19/16   12/10/15   2,155,16                       0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          New City Elementary:
11-1041   Reconstruction               0-003-013  08/08/12     DONE    DONE       DONE      03/28/12   03/23/12   11/16/07   06/09/11   13                        68,300        68,300  HCM             0           0           0 Collins & Scoville Architects           0      10/06/15                       10/15/15           

          Little Tor Elementary School:
11-1042   Reconstruction               0-004-014  08/08/12     DONE    DONE       DONE      03/28/12   03/23/12   11/16/07   06/09/11   13                        28,500        28,500  HCM             0           0           0 Collins & Scoville Architects           0      10/06/15                       10/15/15           

          Chestnut Grove(Data Center):
11-1043   Reconstruction               0-005-011  08/08/12     DONE    DONE       DONE      03/28/12   03/23/12   01/28/03   06/09/11   2,4,8,9,155,15,16         22,000             0  HCM             0           0           0 Collins & Scoville Architects           0      10/06/15                       10/15/15           

          West Nyack Elementary School:
11-0802   Reconstruction               0-006-017  10/23/12     DONE    DONE       DONE      02/13/12   02/09/12   09/14/11   05/17/11   8,155,16                  68,000        68,000  HCM             0           0           0 Mosaic Associates                       0      11/10/15                       01/07/16           

          Bardonia Elementary School:
11-1044   Reconstruction               0-007-017  08/08/12     DONE    DONE       DONE      03/28/12   03/23/12   11/16/07   06/09/11   155,16                    69,500        69,500  HCM             0           0           0 Collins & Scoville Architects           0      10/06/15                       10/15/15           
15-1894   Reconstruction               0-007-018                         UNREVIEWED         06/09/16   06/08/16   01/19/16   12/10/15   2,16                           0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Senior High School North:
11-1259   Reconstruction               0-010-014  12/11/12     DONE    DONE       DONE      05/03/12   05/03/12   05/24/01   06/09/11   10,16                    417,484       417,484  MGL             0           0           0 Fellenzer Engineering                   0      09/26/13                       10/02/13           
12-0065   Additions and Alterations    0-010-019  03/04/13     DONE    DONE       DONE      07/27/12   07/19/12   04/05/12   05/15/12   02 - 16                  500,000             0  HCM             0           0           0 Fellenzer Engineering                   0      10/23/15                       11/13/15           
15-1895   Reconstruction               0-010-020                         UNREVIEWED         06/09/16   06/08/16   01/19/16   12/10/15   2,4,8,9,155,16                 0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-010-021                                              /  /       /  /     01/19/16     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-010-022                                              /  /       /  /     06/16/16     /  /     4                              0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Laurel Plains Elementary:
11-0266   Reconstruction               0-011-010  09/27/10     DONE    DONE       DONE      10/18/11   10/14/11   10/15/10   10/28/10   10                       204,645       204,645  HCM             0           0           0 Fellenzer Engineering                   0      04/25/11                         /  /             
11-0803   Reconstruction               0-011-011  10/23/12     DONE    DONE       DONE      02/13/12   02/09/12   09/14/11   05/17/11   8                         31,000        31,000  HCM             0           0           0 Mosaic Associates                       0      11/10/15                       01/07/16           
15-1896   Reconstruction               0-011-012                         UNREVIEWED         06/09/16   06/08/16   01/19/16   12/10/15   2,16                           0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-011-013                                              /  /       /  /     01/19/16     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Felix Festa Junior High:
11-1045   Reconstruction               0-012-018  08/08/12     DONE    DONE       DONE      03/28/12   03/23/12   06/20/05   06/09/11   2,9                      279,500       279,500  HCM             0           0           0 Collins & Scoville Architects           0      10/06/15                       10/15/15           
14-0579   Reconstruction               0-012-027  02/17/15     DONE    DONE       DONE      11/05/14   11/04/14   01/21/14   05/20/14   2,7                    2,000,000     2,000,000  JMB             0           0           0 Collins & Scoville Architects           0      02/19/16                       03/14/16           
15-1897   Reconstruction               0-012-028                         UNREVIEWED         06/09/16   06/08/16   01/19/16   10/12/15   2,155,16                       0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Reconstruction               0-012-029                                              /  /       /  /     01/19/16     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Dina Link Elementary:
11-1046   Reconstruction               0-013-013  08/08/12     DONE    DONE       DONE      03/28/12   03/23/12   11/16/07   06/09/11   13                       125,000       125,000  HCM             0           0           0 Collins & Scoville Architects           0      10/06/15                       10/15/15           

          Wood Glen Elementary:
11-0804   Reconstruction               0-016-012  10/23/12     DONE    DONE       DONE      02/13/12   02/09/12   09/14/11   05/17/11   8,9,16                    47,000        47,000  HCM             0           0           0 Mosaic Associates                       0      11/10/15                       01/07/16           

          Lakewood Elementary School:
11-0805   Reconstruction               0-017-010  10/23/12     DONE    DONE       DONE      02/13/12   02/09/12   09/14/11   05/17/11   8,16                     118,000       118,000  HCM             0           0           0 Mosaic Associates                       0      11/10/15                       01/07/16           

          Senior High School South:
11-0806   Reconstruction               0-018-019  10/23/12     DONE    DONE       DONE      02/13/12   02/09/12   09/14/11   05/17/11   8,155,16                 175,500       175,500  HCM             0           0           0 Mosaic Associates                       0      11/10/15                       01/07/16           
15-1898   Reconstruction               0-018-020                         UNREVIEWED         06/09/16   06/08/16   01/19/16   10/12/15   155,16                         0             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Strawtown Road Elementary:
11-1075   Reconstruction               0-019-012  09/04/12     DONE    DONE       DONE      04/05/12   04/02/12   11/16/07   06/09/11   13                        88,712             0  HCM             0           0           0 Fellenzer Engineering                   0        /  /                           /  /             
  -       Reconstruction               0-019-013                                              /  /       /  /     02/19/15     /  /     4                              0             0  JMB             0           0           0                                         0        /  /                           /  /             

          South High School Parking:
11-0017   New Construction             7-033-001  11/20/15     DONE    DONE       DONE      ***FINAL APPLICATION FORM INCOMPLETE/INCORRECT***                                        0  HCM             0           0           0 Fellenzer Engineering                   0      12/17/15                       03/14/16           

          Press Box @ NHS:
11-1455   New Construction             7-034-001  11/08/12     DONE    DONE       DONE      06/29/12   06/25/12   05/23/12   06/09/11   02 - 16                   83,600             0  HCM             0           0           0 Fellenzer Engineering                   0      05/19/14                       06/17/14           

          North HS Concession Stand:
12-0456   New Construction             7-035-001  03/26/13     DONE    DONE       DONE      11/19/12   11/16/12   08/09/12   09/27/12   02 - 16                  153,450             0  JMB             0           0           0 Fellenzer Engineering                   0      05/19/14                       06/05/14           

          NHS Guard Booth:
12-0929   New Construction             7-036-001  05/02/13     DONE    DONE       DONE      02/28/13   02/27/13   01/17/13   05/15/12   02 - 16                   40,996             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          NHS Guard Booth #2:
15-0582   New Construction             7-038-001  01/04/16     DONE    DONE       DONE      10/15/15   07/28/15   10/15/15   05/20/14   02 - 16                   37,400             0  JMB             0           0           0 H2M Architects + Engineers              0        /  /                           /  /             

          Athletic Stg Container @ South HS:
  -       New Construction             7-039-001                                              /  /       /  /     06/24/16     /  /     02 - 16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             

          District-Wide:
13-1167   Reconstruction               7-999-007  08/12/14     DONE    DONE       DONE      02/03/14   01/31/14   11/12/13   05/21/13   4,8,10,16                599,450       599,450  JMB             0           0           0 H2M Group                               0      12/27/15                       06/21/16           
15-0180   Reconstruction               7-999-008  01/04/16     DONE    DONE       DONE      07/29/15   07/28/15   05/21/15   05/20/14   10,13,16                 524,350       561,750  JMB             0           0           0 H2M Architects + Engineers              0        /  /                           /  /             
  -       Reconstruction               7-999-009                                              /  /       /  /       /  /       /  /     10,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1313SB Reconstruction               7-999-009                         UNREVIEWED         02/26/16   02/26/16   02/26/16     /  /     10,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-2004   Reconstruction               7-999-010               STARTED DONE       DONE      06/29/16   06/28/16   06/15/16   05/17/16   2,9                            0   158,524,570  AAA             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          XXSt. Augustine Schl (2015 no lease):
13-0470   Reconstruction               8-037-L01  10/25/13     DONE    DONE       DONE      10/08/13   10/08/13   10/08/13     /  /                              195,000       195,000  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NANUET UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-01-08-03
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Miller Elementary:
10-1387   Reconstruction               0-001-017  08/01/11     DONE    DONE       DONE      06/09/11   06/06/11   06/09/11   05/18/10   4,8                      124,800       124,800  HCM             0           0           0 KSQ Architects, PC                      0      02/05/13                       10/27/14           
13-1507   Reconstruction               0-001-018  05/07/15     DONE    DONE       DONE      05/07/14   04/30/14   01/08/14   11/19/13   7,16                           0     9,469,710  JMB             0           0           0                                         0        /  /                           /  /             
14-0831   Reconstruction               0-001-019  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   10/27/14   05/19/15   2,9,155,15,16             78,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
  -       Reconstruction               0-001-020                                              /  /       /  /     06/14/16     /  /     16                             0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Highview Elementary:
10-1388   Reconstruction               0-002-014  08/01/11     DONE    DONE       DONE      06/09/11   06/06/11   06/08/11   05/20/11   4,8                       96,400        96,400  HCM             0           0           0 KSQ Architects, PC                      0      09/24/13                       09/30/13           
  -       Reconstruction               0-002-015                                              /  /       /  /     05/23/12     /  /     2,4                            0     7,374,742  HCM             0           0           0                                         0        /  /                           /  /             
13-1423   Reconstruction               0-002-016  06/04/14     DONE    DONE       DONE      04/01/14   03/31/14   02/28/14   05/20/14   2,9                      500,000       500,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/28/14                       03/20/15           
14-0832   Reconstruction               0-002-017  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   10/27/14   05/19/15   2,9,155,15,16             78,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          Nanuet Senior High:
10-1389   Reconstruction               0-003-022  08/01/11     DONE    DONE       DONE      06/09/11   06/06/11   06/08/11   05/20/11   4,8                      148,600       148,600  HCM             0           0           0 KSQ Architects, PC                      0      02/05/13                       10/27/14           
12-0875   Reconstruction               0-003-023  09/20/13     DONE    DONE       DONE      02/20/13   02/19/13   05/23/12   05/15/12   2,4,16                   500,000             0  HCM             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
13-1508   Reconstruction               0-003-024  05/07/15     DONE    DONE       DONE      05/07/14   04/30/14   01/08/14   11/19/13   7,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-025                                              /  /       /  /     06/14/16     /  /     9,15,16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Barr Middle School:
10-1390   Reconstruction               0-004-014  08/01/11     DONE    DONE       DONE      06/09/11   06/06/11   06/09/11   05/20/11   4,8                      130,200       130,200  HCM             0           0           0 KSQ Architects, PC                      0      09/24/13                       09/30/13           
13-1509   Reconstruction               0-004-015  05/07/15     DONE    DONE       DONE      05/07/14   04/30/14   01/08/14   11/19/13   7,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-016                                              /  /       /  /     10/27/14     /  /     2,9,155,15,16                  0    16,387,107  JMB             0           0           0                                         0        /  /                           /  /             
14-0833   Reconstruction               0-004-017  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   10/27/14   05/19/15   2,4,9,155,15,16        1,083,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
15-1915   Reconstruction               0-004-018  07/06/16     DONE    DONE       DONE      06/14/16   06/14/16   03/10/16   05/17/16   2                        120,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          Public Library:
12-1007   Reconstruction               6-005-003  06/18/13     DONE    DONE       DONE      03/21/13   03/18/13   01/24/13   03/05/13   155,16                   185,600             0  JMB             0           0           0 Savin Engineers, P.C.                   0        /  /                           /  /             

          Nanuet Outdoor Recreation Center:
10-1319DB Discovered Building          7-012-001  03/19/14     DONE    DONE       DONE      05/19/11   05/19/11   08/24/07     /  /                                    0             0  HCM             0           0           0                                         0      08/21/14                       09/17/14           
14-0834   Reconstruction               7-012-002  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   09/08/14   09/09/14   8,9,10,155,15,16         100,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          Horse Stables:
10-1320DB Discovered Building          7-013-001  03/17/14     DONE    DONE       DONE      05/19/11   05/19/11   08/24/07     /  /                                    0             0  HCM             0           0           0                                         0      08/21/14                       09/17/14           

          Children of Promise Equestrian Ring:
12-0535   New Construction             7-017-001  05/02/13     DONE    DONE       DONE      12/12/12   11/21/12   04/24/12   06/20/12   02 - 16                  238,418             0  HCM             0           0           0 John E. Collazuol and Associa           0      08/11/15                       08/21/15           

          NOEC Horse Stalls:
13-0025   New Construction             7-018-001  07/12/13     DONE    DONE       DONE      07/10/13   07/03/13   06/14/13   06/18/13   02 - 16                   11,300             0  JMB             0           0           0 NTA INC. ENGINEERS PLANNERS C           0        /  /                           /  /             

          NOEC Greenhouse:
13-1351   New Construction             7-019-001  09/16/14     DONE    DONE       DONE      03/17/14   03/12/14   11/13/13   09/10/13   02 - 16                   70,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0      05/27/15                       06/27/16           

          District Wide:
13-0139   Reconstruction               7-999-003  10/10/13     DONE    DONE       DONE      08/06/13   08/06/13   05/15/13   05/21/13   10,16                    500,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH ROCKLAND/HAVERSTRAW-STONY PT STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-02-01-06
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Farley Elementary:
10-1357   Reconstruction               0-003-008  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/15/10   01/06/09   155,15,16                201,769       201,769  HCM             0           0           0 Michael Shilale Architects,LL     201,769      12/13/12                       02/27/14           
13-1540   Reconstruction               0-003-009  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   155,16                   764,976       764,976  DDJ             0           0     258,562 Michael Shilale Architects,LL           0        /  /                           /  /             

          North Rockland High School Ext.:
10-1358   Reconstruction               0-007-013  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/15/10   01/06/09   155,15,16                183,624       183,624  HCM             0           0           0 Michael Shilale Architects,LL     183,624      09/18/13                       02/27/14           
13-1541   Reconstruction               0-007-014  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,4,155,16               136,000       136,000  DDJ             0           0      45,968 Michael Shilale Architects,LL           0        /  /                           /  /             

          Haverstraw Elementary:
10-1359   Reconstruction               0-009-014  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/15/10   01/06/09   155,15,16                191,315       191,315  HCM             0           0           0 Michael Shilale Architects,LL     191,315      09/18/13                       02/27/14           
13-1542   Reconstruction               0-009-016  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,4,7,9                1,323,165     1,323,165  DDJ             0           0     447,230 Michael Shilale Architects,LL           0        /  /                           /  /             

          Gerald F. Neary Elementary:
10-1360   Reconstruction               0-011-006  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/17/10   01/06/09   155,15,16                171,535       171,535  HCM             0           0           0 Michael Shilale Architects,LL     171,535      12/13/12                       02/27/14           

          Railroad Avenue School (Alt. Ed. Bld:
10-1361   Reconstruction               0-013-003  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/20/10   01/06/09   155,15,16                104,905             0  HCM             0           0           0 Michael Shilale Architects,LL     104,905      09/18/13                       02/27/14           

          Stony Point Elementary:
10-1362   Reconstruction               0-014-007  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/17/10   01/06/09   155,15,16                111,803       111,803  HCM             0           0           0 Michael Shilale Architects,LL     111,803      09/18/13                       02/27/14           
13-1543   Reconstruction               0-014-008  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,7,16                 1,397,428     2,087,235  DDJ             0           0     472,331 Michael Shilale Architects,LL           0        /  /                           /  /             

          North Rockland High School:
10-1363   Reconstruction               0-016-022  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/15/10   01/06/09   7,155,15,16            4,580,966     4,580,966  HCM             0           0           0 Michael Shilale Architects,LL   4,580,966      09/18/13                       02/27/14           
13-1544   Reconstruction               0-016-023  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,4,7,9,155,15,16      2,736,536     2,736,536  DDJ             0           0     926,261 Michael Shilale Architects,LL           0        /  /                           /  /             

          West Haverstraw Elementary:
10-1364   Reconstruction               0-024-010  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/20/10   01/06/09   155,15,16                110,015       110,015  HCM             0           0           0 Michael Shilale Architects,LL     110,015      12/05/12                       02/27/14           
13-1545   Reconstruction               0-024-011  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,7,15,16                293,366       293,366  DDJ             0           0      99,158 Michael Shilale Architects,LL           0        /  /                           /  /             

          Thiells Elementary School:
10-1365   Reconstruction               0-025-012  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/20/10   01/06/09   155,15,16                868,027       868,027  HCM             0           0           0 Michael Shilale Architects,LL     868,027      09/18/13                       02/27/14           
13-1546   Reconstruction               0-025-013  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,7,16                   529,142       529,142  DDJ             0           0     178,850 Michael Shilale Architects,LL           0        /  /                           /  /             

          Willow Grove MS (fmly 8-030):
13-1548   Reconstruction               0-030-012  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   4,9                      158,550       158,550  DDJ             0           0      53,590 Michael Shilale Architects,LL           0      01/08/15                       02/05/15           

          Fieldstone Middle School:
10-1366   Reconstruction               0-031-002  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/20/10   01/06/09   155,15,16                 99,027        99,027  HCM             0           0           0 Michael Shilale Architects,LL      99,027      10/17/12                       02/27/14           
13-1547   Reconstruction               0-031-003  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   9                        350,837       350,837  DDJ             0           0     118,583 Michael Shilale Architects,LL           0        /  /                           /  /             

          Buckberg Warehouse:
10-1367   Reconstruction               2-015-002  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11     /  /     01/06/09   155,15                    69,896             0  HCM             0           0           0 Michael Shilale Architects,LL      69,896      09/18/13                       02/27/14           

          Maintenance Garage:
  -    XX Reconstruction               3-002-004  03/15/12               CANCELLED          06/03/11   05/31/11   12/20/10   01/06/09   155,15,16                 71,561             0  HCM             0           0           0 Michael Shilale Architects,LL      71,561        /  /                           /  /             

          District-Wide:
15-1451SB Reconstruction               7-999-004                                              /  /       /  /     03/18/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1933   Reconstruction               7-999-004                         UNREVIEWED         06/21/16   06/21/16     /  /     05/17/16   13,16                          0             0  DDJ             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Willow Grove MS (purch-see 0-030):
10-1368   Reconstruction               8-030-011  03/15/12     DONE    DONE       DONE      06/03/11   05/31/11   12/15/10   01/06/09   155,15,16                243,812       243,812  HCM             0           0           0 Michael Shilale Architects,LL     243,812      10/17/13                       02/27/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH ORANGETOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-01-06
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Tappan Zee High School:
12-0820   Reconstruction               0-006-022  10/08/13     DONE    DONE       DONE      02/12/13   02/12/13   07/18/12   05/17/12   14,16                    181,638       425,000  JOD             0           0           0 LAN Associates                          0      09/04/14                       01/20/15           
13-0676   Reconstruction               0-006-023  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/26/13   05/21/13   2,4,8,9,10,155,16        722,765       722,765  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
14-0266   Reconstruction               0-006-024  04/23/15     DONE    DONE       DONE      09/09/14   09/08/14   04/23/14   05/21/14   2,9,10,16              1,750,000     1,750,000  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
  -       Reconstruction               0-006-025                                              /  /       /  /     06/24/16     /  /     2,13                           0             0  AAA             0           0           0                                         0        /  /                           /  /             

          Tappan Zee Elementary:
13-0677   Reconstruction               0-007-017  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   10/02/13   05/21/13   16                        68,968             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Cottage Lane Elementary:
13-0678   Additions and Alterations    0-010-017  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   02 - 16                  800,455       800,455  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           

          Greenbush Academy:
13-0679   Reconstruction               0-011-009  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   8,9                      157,275             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          William Schaefer Elementary:
12-0822   Reconstruction               0-012-013  10/08/13     DONE    DONE       DONE      02/12/13   02/12/13   07/18/12   05/17/12   155,15,16                251,798       243,500  MFS             0           0           0 LAN Associates                          0      09/26/14                       01/20/15           
13-0680   Reconstruction               0-012-014  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   2,4,8,9,155,16           125,075       125,075  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           

          Middle School:
12-0821   Reconstruction               0-013-022  10/08/13     DONE    DONE       DONE      02/12/13   02/12/13   07/18/12   05/17/12   8,9,10,14,16           1,092,096     1,129,000  JOD             0           0           0 LAN Associates                          0      09/22/14                       01/20/15           
13-0681   Reconstruction               0-013-023  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   2,4,8,9,155,15,16        584,121       584,121  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           

          Guard Booth @ MS:
13-1329   New Construction             7-020-001  06/06/14     DONE    DONE       DONE      03/11/14   03/11/14   03/11/14   05/21/13   02 - 16                   54,400             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Guard Booth-North @ Tappan Zee HS:
13-1330   New Construction             7-021-001  06/06/14     DONE    DONE       DONE      03/11/14   03/11/14   03/11/14   05/21/13   02 - 16                   34,400             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Guard Booth-South @ Tappan Zee HS:
13-1331   New Construction             7-022-001  06/06/14     DONE    DONE       DONE      03/11/14   03/11/14   03/11/14   05/21/13   02 - 16                   34,400             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Districtwide:
12-1235   Reconstruction               7-999-002  06/19/13     DONE    DONE       DONE      05/30/13   05/28/13   05/07/13   05/21/13                            186,716             0  MFS             0           0           0 LAN Associates                          0      03/31/14                       05/11/15           
  -       Reconstruction               7-999-003                                              /  /       /  /     07/25/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NYACK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-04-03
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Valley Cottage Elementary:
13-1199   Reconstruction               0-001-010  04/25/14     DONE    DONE       DONE      02/10/14   02/10/14   08/20/13   10/29/13   2,4,7,8,9,10,155,15,     144,619       144,619  DDJ             0           0           0 LAN Associates                          0      08/27/14                       02/09/15           
13-1684   Reconstruction               0-001-011  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   01/08/14   10/29/13   2,4,7,8,9,10,155,15,   1,472,851             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Old Nyack High School:
13-1200   Reconstruction               0-003-012  04/28/14     DONE    DONE       DONE      02/10/14   02/10/14   08/20/13   10/29/13   2,4,7,8,9,10,155,15,     362,140       362,140  DDJ             0           0           0 LAN Associates                          0      08/27/14                       02/09/15           
  -       Reconstruction               0-003-013                                              /  /       /  /     01/08/14     /  /     2,4,7,8,10,15,16               0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-0358   Reconstruction               0-003-014  06/09/14     DONE    DONE       DONE      09/25/14   09/25/14   07/29/14   08/19/14   2,9,10                   200,000       200,000  DDJ             0           0           0 LAN Associates                          0      10/09/14                       02/17/15           
15-1544   Reconstruction               0-003-015  04/25/16     DONE    DONE       DONE      04/11/16   04/08/16   07/24/15   10/29/13   7                        545,281             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Nyack Middle School:
13-1685   Reconstruction               0-004-009  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   09/13/07   10/29/13   2,7,8,155,15,16          571,893             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
12-1199   Reconstruction               0-004-010  05/23/13     DONE    DONE       DONE      05/16/13   05/14/13   04/22/13   04/23/13   2,9                      357,000       357,000  DDJ             0           0           0 LAN Associates                          0      10/30/13                       03/14/14           
16-0151   Reconstruction               0-004-011                         UNREVIEWED         07/25/16   07/25/16   08/21/13   10/29/13   2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
15-1545   Reconstruction               0-004-012  04/25/16     DONE    DONE       DONE      03/11/16   03/08/16   07/24/15   10/29/13   7                      1,570,646             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-004-013                                              /  /       /  /     01/15/16     /  /     2,8,9                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-014                                              /  /       /  /     02/02/16     /  /     2,8,9                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Hilltop Admin (frmly IS)(see 1-005):
12-0512   Reconstruction               0-005-006  12/20/12     DONE    DONE       DONE      12/06/12   12/06/12   09/13/07   06/12/12   7                        780,299             0  DDJ             0           0           0 DCAK-MSA Architecture                   0      07/30/13                       02/10/14           
  -       Reconstruction               0-005-007                                              /  /       /  /     08/20/13     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-0926   Reconstruction               0-005-008  02/13/15     DONE    DONE       DONE      01/08/15   01/07/15   06/03/14   05/20/14   2,8,13                   383,054       383,054  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
14-0927   Reconstruction               0-005-009  02/13/15     DONE    DONE       DONE      01/08/15   01/07/15   10/20/14   10/21/14   2,8,10                   693,379       693,379  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Liberty Elementary School:
11-1390   Reconstruction               0-006-010  06/14/12     DONE    DONE       DONE      06/08/12   06/05/12   04/02/12   04/17/12   4,7,8,9                  100,000       100,000  DDJ             0           0           0 DCAK-MSA Architecture                   0      03/11/13                       05/16/13           
  -       Reconstruction               0-006-011                                              /  /       /  /     08/20/13     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Upper Nyack Elementary School:
13-1201   Reconstruction               0-007-013  04/28/14     DONE    DONE       DONE      02/10/14   02/10/14   09/13/07   10/29/13   2,4,7,8,155,15,16         29,635        29,635  DDJ             0           0           0 LAN Associates                          0      08/27/14                       02/09/15           
13-1686   Reconstruction               0-007-014  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   08/21/13   10/29/13   2,4,7,8,9,10,155,15,     817,921             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
16-0152   Reconstruction               0-007-015                         UNREVIEWED         07/25/16   07/25/16   01/08/14   10/29/13   2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
15-1546   Reconstruction               0-007-016  04/25/16     DONE    DONE       DONE      04/11/16   04/08/16   07/24/15   10/29/13   7                        681,601             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-007-017                                              /  /       /  /     01/15/16     /  /     2,4,8,9                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          High School:
11-0927   Reconstruction               0-021-006  03/14/12     DONE    DONE       DONE      03/09/12   03/09/12   09/13/07   08/23/11   4                        500,000       500,000  DDJ             0           0           0 DCAK-MSA Architecture                   0      08/06/13                       02/10/14           
13-1687   Reconstruction               0-021-007  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   08/20/13   10/29/13   2,4,7,8,9,10,155,15,   2,655,726     2,655,726  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
15-0057   Reconstruction               0-021-008  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   12/05/13   10/29/13   2,4,7,8,9,10,155,15,   8,630,309             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-021-009                                              /  /       /  /     12/05/13     /  /     2,4,7,8,9,10,155,15,           0    22,630,088  DDJ             0           0           0                                         0        /  /                           /  /             
16-0116   Reconstruction               0-021-010                         UNREVIEWED         07/18/16   07/18/16   02/02/16   05/17/16   9,10,16                        0             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Hilltop Administration:
  -       Reconstruction               1-005-001                                              /  /       /  /     07/24/15     /  /     7                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Field House Bus Garage:
15-0058   Reconstruction               5-019-001  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   01/08/14   10/29/13   155                       47,416             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Exhibition Field Press Box:
15-0059   New Construction             7-031-001  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   03/04/14   10/29/13   02 - 16                   92,400             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Concession Stand:
15-0060   New Construction             7-032-001  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   03/04/14   10/29/13   02 - 16                  434,280             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Memorial Press Box/Concession @ HS:
  -       New Construction             7-033-001                                              /  /       /  /     06/30/15     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
12-1347   Reconstruction               7-999-004  07/18/13     DONE    DONE       DONE      07/01/13   06/28/13   04/22/13   04/23/13   10,16                    139,750       139,750  DDJ             0           0           0 LAN Associates                          0      04/29/14                       05/29/14           
13-1212   Reconstruction               7-999-005  06/18/14     DONE    DONE       DONE      02/12/14   02/11/14   12/05/13   10/29/13   8,16                     643,940       643,940  DDJ             0           0     134,096 LAN Associates                          0      08/27/14                       02/09/15           
15-1970   Reconstruction               7-999-006  07/11/16     DONE    DONE       DONE      06/23/16   06/23/16   12/05/13   05/17/16   8,16                     100,000             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               7-999-007                                              /  /       /  /     04/18/16     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PEARL RIVER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-08-03
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
11-0567   Reconstruction               0-009-019  04/09/12     DONE    DONE       DONE      12/29/11   12/29/11   12/01/11   11/10/10   8,9,10,155,15,16         585,000       585,000  HCM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
14-1711   Reconstruction               0-009-020  09/22/15     DONE    DONE       DONE      06/23/15   06/19/15   11/04/14   05/19/15   4,10,155                 783,000             0  JMB             0           0           0 KEEL ARCHITECTURE                       0        /  /                           /  /             
  -       Reconstruction               0-009-021                                              /  /       /  /     02/25/15     /  /     155                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Administration Building:
11-0393DB Discovered Building          1-017-001  11/30/11     DONE    DONE       DONE      11/15/11   11/15/11   11/01/11     /  /                                    0             0  HCM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          Facilities Storage:
  -    DB Discovered Building          2-018-001                                              /  /       /  /     11/01/11     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Pearl River Public Library:
15-0475XX Reconstruction               6-005-002                         CANCELLED          09/18/15   09/14/15   08/11/15     /  /     155,16                         0             0  JMB             0           0           0 KEEL ARCHITECTURE                       0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAMAPO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-01-06
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Suffern Middle School:
10-1150   Reconstruction               0-002-025  08/26/11     DONE    DONE       DONE      04/07/11   04/04/11   01/25/11   03/15/11   2,155,15,16            1,684,644     1,684,644  HCM             0           0           0 ECG Engineering, LLC            1,684,644      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0832   Additions and Alterations    0-002-026  06/26/12     DONE    DONE       DONE      02/22/12   02/21/12   06/30/11   05/17/11   02 - 16                1,050,000       100,000  HCM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          RP Connor Elementary School:
10-1151   Reconstruction               0-005-017  08/26/11     DONE    DONE       DONE      04/07/11   04/04/11   01/25/11   03/15/11   2,155,15,16              798,370       798,370  HCM             0           0           0 ECG Engineering, LLC              798,370      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Sloatsburg Elementary:
10-1152   Reconstruction               0-007-018  08/26/11     DONE    DONE       DONE      04/08/11   04/04/11   01/27/11   03/15/11   2,155,15,16              521,555       521,555  HCM             0           0           0 ECG Engineering, LLC              521,555      11/07/12                       10/09/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Cherry Lane Elementary:
10-1153   Reconstruction               0-011-018  08/26/11     DONE    DONE       DONE      04/08/11   04/04/11   01/25/11   03/15/11   2,155,15,16              376,741       376,741  HCM             0           0           0 ECG Engineering, LLC              376,741      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Montebello Elementary:
10-1154   Reconstruction               0-019-014  08/26/11     DONE    DONE       DONE      04/08/11   04/04/11   01/27/11   03/15/11   2,155,15,16              466,479       466,479  HCM             0           0           0 ECG Engineering, LLC              466,479      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Suffern High School:
10-1155   Reconstruction               0-020-028  08/26/11     DONE    DONE       DONE      04/04/11   04/04/11   01/25/11   03/15/11   2,155,15,16            4,503,958     4,503,958  HCM             0           0           0 ECG Engineering, LLC            4,503,958      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0833   Additions and Alterations    0-020-029  06/26/12     DONE    DONE       DONE      02/22/12   02/21/12   06/30/11   05/17/11   02 - 16                1,000,000        26,100  HCM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-020-030                                              /  /       /  /     04/05/16     /  /     9,10,155,15,16                 0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Viola Elementary:
10-1156   Reconstruction               0-026-015  08/26/11     DONE    DONE       DONE      04/08/11   04/04/11   01/27/11   03/15/11   2,155,15,16              422,446       422,446  HCM             0           0           0 ECG Engineering, LLC              422,446      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   
15-0754   Reconstruction               0-026-016  04/13/16     DONE    DONE       DONE      11/23/15   11/16/15   06/30/11   05/17/11   2,16                     450,000             0  HCM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Hillburn Administration Building:
10-1157   Reconstruction               1-006-009  08/26/11     DONE    DONE       DONE      04/08/11   04/04/11   01/25/11   03/15/11   2,155,15,16              650,806             0  HCM             0           0           0 ECG Engineering, LLC              650,806      11/07/12                       09/30/13         YES
                                                                                                                                                                                                                                                                                                                                   

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST RAMAPO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-02-06
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Spring Valley Senior High:
12-0623   Reconstruction               0-003-012  11/28/12     DONE    DONE       DONE      12/27/12   12/27/12   12/04/12   11/27/12   15                        16,000        16,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0      04/19/13                       05/09/13           
12-0434   Reconstruction               0-003-018  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   02/23/09   03/30/11   2,8                      364,298             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     364,298        /  /                           /  /             
15-1844   Reconstruction               0-003-019  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   06/21/12   04/19/16   2,9                       90,000             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
  -       Reconstruction               0-003-020                                              /  /       /  /     10/06/15     /  /     2,8,9,15                       0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Hempstead School:
12-0436   Reconstruction               0-006-013  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   05/23/12   03/30/11   10                       109,703             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     109,703        /  /                           /  /             
  -       Reconstruction               0-006-014                                              /  /       /  /     01/16/15     /  /     2,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-006-015                                              /  /       /  /     10/06/15     /  /     2,8                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Pomona Middle(fmlyPomonaJR):
12-0437   Reconstruction               0-008-015  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   02/23/09   03/30/11   2,8                      328,583             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     328,583        /  /                           /  /             
12-1286   Reconstruction               0-008-016  06/17/13     DONE    DONE       DONE      06/13/13   06/13/13   05/17/13   06/04/13   2,9                      135,700       135,700  JMB             0           0     135,700 Eisenbach & Ruhnke Engineerin           0      08/19/13                       02/13/14           
  -       Reconstruction               0-008-017                                              /  /       /  /     08/07/14     /  /     2,9,13,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-018                                              /  /       /  /     10/06/15     /  /     2,8                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Ramapo Fresh.Ctr.(frmlyKakiat):
12-0624   Reconstruction               0-013-010  10/16/12     DONE    DONE       DONE      12/27/12   12/27/12   12/04/12   11/27/12   13,15                     82,500        82,500  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0      04/19/13                       05/09/13           
12-0438   Reconstruction               0-013-015  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   10/22/08   03/30/11   4                      1,584,086     1,584,086  HCM             0           0           0 Eisenbach & Ruhnke Engineerin   1,584,086        /  /                           /  /             
  -       Reconstruction               0-013-016                                              /  /       /  /     06/21/12     /  /     9                              0    33,381,855  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-013-017                                              /  /       /  /     05/17/13     /  /     2,8                            0    33,381,855  JMB             0           0           0                                         0        /  /                           /  /             
14-0087   Reconstruction               0-013-018  08/01/14     DONE    DONE       DONE      07/31/14   07/30/14   05/23/13   07/24/14   15                       104,500       104,500  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0      06/04/15                       06/24/15           
  -       Reconstruction               0-013-019                                              /  /       /  /     10/06/15     /  /     2,8                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Fleetwood Elementary School:
12-0439   Reconstruction               0-014-014  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   02/23/09   03/30/11   2,8                      157,834             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     157,834        /  /                           /  /             
  -       Reconstruction               0-014-015                                              /  /       /  /     02/15/13     /  /     2,155                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1845   Reconstruction               0-014-016  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   05/23/13   04/19/16   15                       120,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
  -       Reconstruction               0-014-017                                              /  /       /  /     10/06/15     /  /     2,4,8                          0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Summit Park Elementary:
12-0440   Reconstruction               0-015-014  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   07/09/08   03/30/11   15                       146,522             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     146,522        /  /                           /  /             
  -       Reconstruction               0-015-015                                              /  /       /  /     10/06/15     /  /     2,8                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Grandview Elementary:
12-0441   Reconstruction               0-016-012  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   07/09/08   03/30/11   15                       183,562             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     183,562        /  /                           /  /             
  -       Reconstruction               0-016-013                                              /  /       /  /     10/06/15     /  /     2,8                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Margetts Road Elementary:
12-0442   Reconstruction               0-020-011  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   02/23/09   03/30/11   2,8                      116,420             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     116,420        /  /                           /  /             
15-1846   Reconstruction               0-020-012  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,8                       80,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Ramapo Senior High School:
12-0443   Reconstruction               0-022-016  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   02/23/09   03/30/11   2,8                      437,822       437,822  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     437,822        /  /                           /  /             
  -       Reconstruction               0-022-017                                              /  /       /  /     06/21/12     /  /     9                              0    37,567,896  HCM             0           0           0                                         0        /  /                           /  /             
12-1294   Reconstruction               0-022-018  07/23/13     DONE    DONE       DONE      06/17/13   06/12/13   02/15/13   06/04/13   8                         50,000        50,000  JMB             0           0      50,000 Eisenbach & Ruhnke Engineerin           0      06/03/14                       06/17/14           
15-1490   Reconstruction               0-022-019  04/26/16     DONE    DONE       DONE      03/28/16   03/25/16   10/06/15   04/20/16   2,8,9                  1,130,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Lime Kiln School:
12-0444   Reconstruction               0-027-013  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                       143,343             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     143,343        /  /                           /  /             
  -       Reconstruction               0-027-014                                              /  /       /  /     10/06/15     /  /     2,8                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Elmwood Elementary School:
12-0445   Reconstruction               0-030-011  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                       111,498       111,498  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     111,498        /  /                           /  /             
12-0171   Reconstruction               0-030-012  06/18/13     DONE    DONE       DONE      09/13/12   09/13/12   08/17/12   08/21/12   2,155                    285,000       285,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
15-0534   Reconstruction               0-030-013  11/18/15     DONE    DONE       DONE      10/06/15   10/06/15   08/28/15   05/19/15   2,8,9,15,16               50,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
15-1847   Reconstruction               0-030-014  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,8                       50,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Chestnut Ridge Middle(frmlySpring Va:
12-0446   Reconstruction               0-034-017  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                       451,415             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     451,415        /  /                           /  /             
15-1848   Reconstruction               0-034-018  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,8,9                     65,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Eldorado Elementary:
12-0447   Reconstruction               0-037-014  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                       143,642             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     143,642        /  /                           /  /             
15-1849   Reconstruction               0-037-015  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,4,8                     80,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Adminstration Building:
12-0435   Reconstruction               1-005-011  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   02/23/09   03/30/11   2,8                      245,382             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin     245,382        /  /                           /  /             
15-1850   Reconstruction               1-005-012  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   03/02/16   04/19/16   16                        15,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Transportation Office:
12-0448   Reconstruction               1-010-004  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                        46,429             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin      46,429        /  /                           /  /             

          Central Warehouse Bldg.:
12-0449   Reconstruction               2-009-005  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                       111,953             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin     111,953        /  /                           /  /             

          Bldgs Grounds Bldg 1:
12-0450   Reconstruction               3-002-008  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                        61,043             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin      61,043        /  /                           /  /             

          Transportation Garage:
12-0451   Reconstruction               5-001-009  07/03/13     DONE    DONE       DONE      11/16/12   11/13/12   01/26/12   03/30/11   10                        41,921             0  HCM             0           0           0 Eisenbach & Ruhnke Engineerin      41,921        /  /                           /  /             
13-1164   Reconstruction               5-001-010  02/05/14     DONE    DONE       DONE      01/30/14   01/30/14   07/03/13   07/23/13   10                        65,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Central Kitchen Bldg 1:
  -       Reconstruction               7-017-005                                              /  /       /  /     01/26/12     /  /     10                             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          New Central Kitchen:
  -       Reconstruction               7-053-002                                              /  /       /  /     01/26/12     /  /     10                             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-002                                              /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1634SB Reconstruction               7-999-002               DONE                           /  /       /  /     04/27/16     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ROCKLAND STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-90-00-00
last updated on 07/29/16
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jessie J Kaplan #9:
12-0748   Reconstruction               0-010-007  07/26/13     DONE    DONE       DONE      01/31/13   01/22/13   08/14/12   06/12/12   155                       65,000             0  JMB             0           0           0                                         0        /  /                           /  /             
14-1213PR Additions and Alterations    0-010-008                         UNREVIEWED         02/27/15   02/26/15   01/06/15     /  /     02 - 16                        0             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             
14-1550   Additions and Alterations    0-010-008  04/19/16     DONE    DONE       DONE      05/26/15   05/21/15   01/06/15   11/13/13   02 - 16                8,657,120             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Administration Bldg:
14-1214PR Additions and Alterations    1-007-007                         UNREVIEWED         02/27/15   02/26/15   01/06/15     /  /     02 - 16                        0             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             
14-1551   Additions and Alterations    1-007-007  04/19/16     DONE    DONE       DONE      05/26/15   05/21/15   01/06/15   11/11/13   02 - 16                  636,600             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Bus Garage Bldg #5:
15-1076   Reconstruction               5-009-005  07/28/16     DONE    DONE       DONE      01/20/16   01/19/16   01/07/16   01/13/16   8,15                           0             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Benchmark Edu:
  -    TQ Temporary Quarters           8-034-001                                              /  /       /  /     08/16/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Gerald F. Neary Elementary School:
  -    TQ Temporary Quarters           8-035-L01                                              /  /       /  /     08/28/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED