Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 09/21/18 at 07:57:50




CLARKSTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-01-01-06
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Congers Elementary:
14-0120   Reconstruction               0-001-015  09/02/14     DONE    DONE       DONE      08/12/14   08/01/14   10/03/13   02/06/14   2,4,7,8,9              6,500,000             0  JMB             0           0           0 Collins & Scoville Architects           0      10/20/15                       07/14/16           

          Birchwood School:
15-1893   Reconstruction               0-002-011  11/07/16     DONE    DONE       DONE      06/09/16   06/08/16   01/19/16   12/10/15   2,155,16                 657,236             0  JMB             0           0           0 Collins & Scoville Architects           0      12/15/17                       02/23/18           
16-1220   Reconstruction               0-002-012  03/21/17     DONE    DONE       DONE      01/20/17   01/20/17   10/14/16   05/17/16   8                         22,971             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
17-1921   Reconstruction               0-002-013               UNREVIEWED
                                                                       DONE       DONE      06/04/18   06/04/18   12/15/17   12/10/15   2,4,7                          0             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          New City Elementary:
17-0175   Reconstruction               0-003-014  11/09/17     DONE    DONE       DONE      08/09/17   08/08/17   10/01/16   12/10/15   2,7                    1,711,831             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Little Tor Elementary School:
17-0176   Reconstruction               0-004-015  11/09/17     DONE    DONE       DONE      08/09/17   08/08/17   10/01/16   12/10/15   2,7,16                 2,146,476             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Chestnut Grove(Data Center):
17-1922   Reconstruction               0-005-012               UNREVIEWED
                                                                       DONE       DONE      06/04/18   06/04/18   02/16/18   12/10/15   2,4,7                          0             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          West Nyack Elementary School:
17-0177   Reconstruction               0-006-018  11/09/17     DONE    DONE       DONE      08/09/17   08/08/17   10/01/16   12/10/15   2,7,16                 1,788,882             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Bardonia Elementary School:
15-1894   Reconstruction               0-007-018  11/07/16     DONE    DONE       DONE      06/09/16   06/08/16   01/19/16   12/10/15   2,16                       8,573             0  JMB             0           0           0 Collins & Scoville Architects           0      10/15/17                       02/23/18           
16-1221   Reconstruction               0-007-019  03/21/17     DONE    DONE       DONE      01/20/17   01/20/17   10/14/16   05/19/15   16                        56,151             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
17-1923   Reconstruction               0-007-020               UNREVIEWED
                                                                       DONE       DONE      06/04/18   06/04/18   12/15/17   12/10/15   2,4,7                          0             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Senior High School North:
15-1895   Reconstruction               0-010-020  11/07/16     DONE    DONE       DONE      06/09/16   06/08/16   01/19/16   12/10/15   2,4,8,9,155,16         1,600,227     1,600,227  JMB             0           0           0 Collins & Scoville Architects           0      12/15/17                       02/23/18           
16-0519   Reconstruction               0-010-021  12/08/16     DONE    DONE       DONE      09/29/16   09/28/16   01/19/16   12/10/15   2,7                    4,603,293     4,603,293  JMB             0           0           0 Collins & Scoville Architects           0      09/01/17                       05/09/18           
16-0263   Reconstruction               0-010-022  09/20/16     DONE    DONE       DONE      08/16/16   08/15/16   06/16/16   05/17/16   4                         77,770        77,770  AAA             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-1222   Reconstruction               0-010-023  03/21/17     DONE    DONE       DONE      01/20/17   01/20/17   10/14/16   05/17/16   8                         50,249        50,249  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Laurel Plains Elementary:
15-1896   Reconstruction               0-011-012  11/07/16     DONE    DONE       DONE      06/09/16   06/08/16   01/19/16   12/10/15   2,16                     300,043       300,043  JMB             0           0           0 Collins & Scoville Architects           0      10/15/17                       02/23/18           
16-0520   Reconstruction               0-011-013  12/08/16     DONE    DONE       DONE      09/29/16   09/28/16   01/19/16   12/10/15   2,7                    2,105,590     2,105,590  JMB             0           0           0 Collins & Scoville Architects           0      09/01/17                       05/09/18           

          Felix Festa Junior High:
14-0579   Reconstruction               0-012-027  02/17/15     DONE    DONE       DONE      11/05/14   11/04/14   01/21/14   05/20/14   2,7                    2,000,000     2,000,000  JMB             0           0           0 Collins & Scoville Architects           0      02/19/16                       03/14/16           
15-1897   Reconstruction               0-012-028  11/07/16     DONE    DONE       DONE      06/09/16   06/08/16   01/19/16   10/12/15   2,155,16               1,300,185     1,300,185  JMB             0           0           0 Collins & Scoville Architects           0      12/15/17                       02/23/18           
16-0521   Reconstruction               0-012-029  12/08/16     DONE    DONE       DONE      09/29/16   09/28/16   01/19/16   12/10/15   2,7                    5,547,266     5,547,266  JMB             0           0           0 Collins & Scoville Architects           0      09/01/17                       05/09/18           
  -       Reconstruction               0-012-030                                              /  /       /  /     10/07/16     /  /     9,16                           0    53,365,248  SLC             0           0           0                                         0        /  /                           /  /             
16-1223   Reconstruction               0-012-031  03/21/17     DONE    DONE       DONE      01/20/17   01/20/17   10/17/16   05/17/16   2,8,9,10,14,155,16       168,454             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-0928   Reconstruction               0-012-032  01/20/17     DONE    DONE       DONE      12/07/16   12/05/16   12/06/16   05/17/16   2,9,10,14,16             249,453             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Dina Link Elementary:
17-0178   Reconstruction               0-013-014  11/09/17     DONE    DONE       DONE      08/09/17   08/08/17   10/01/16   12/10/15   2,7,16                 1,338,932             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Wood Glen Elementary:
17-1924   Reconstruction               0-016-013               UNREVIEWED
                                                                       DONE       DONE      06/04/18   06/04/18   12/15/17   12/10/15   2,4,7,16                       0    10,222,038  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
17-1646   Reconstruction               0-016-014                         UNREVIEWED         04/06/18   04/06/18   03/02/18   12/10/15   2,16                           0    10,222,038  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Lakewood Elementary School:
17-0179   Reconstruction               0-017-011  11/09/17     DONE    DONE       DONE      08/09/17   08/08/17   10/01/16   12/10/15   2,7,16                 1,387,826             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Senior High School South:
15-1898   Reconstruction               0-018-020  11/07/16     DONE    DONE       DONE      06/09/16   06/08/16   01/19/16   10/12/15   155,16                 2,328,902     2,328,902  JMB             0           0           0 Collins & Scoville Architects           0      12/15/17                       02/23/18           
16-0929   Reconstruction               0-018-021  01/20/17     DONE    DONE       DONE      12/07/16   12/05/16   11/25/16   05/19/15   2,9,10,14,16             380,426       380,426  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
  -       Alterations                  0-018-022                                              /  /       /  /       /  /       /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             
17-1925   Reconstruction               0-018-023               UNREVIEWED
                                                                       DONE       DONE      06/04/18   06/04/18   12/15/17   12/10/15   2,4,7,16                       0             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
17-1647   Reconstruction               0-018-024                         UNREVIEWED         04/06/18   04/06/18   03/02/18   12/10/15   2,16                           0    46,624,480  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Strawtown Road Elementary:
16-0647   Reconstruction               0-019-013  01/18/17     DONE    DONE       DONE      10/18/16   10/18/16   02/19/15   05/17/16   4                        175,473             0  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
17-0180   Reconstruction               0-019-014  11/09/17     DONE    DONE       DONE      08/09/17   08/08/17   10/01/16   12/10/15   2,7                    1,130,375             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
16-1224   Reconstruction               0-019-015  03/21/17     DONE    DONE       DONE      01/20/17   01/20/17   10/14/16   05/19/15   14                        32,303             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
17-1648   Reconstruction               0-019-016                         UNREVIEWED         04/06/18   04/06/18   12/15/17   12/10/15   2,16                           0     7,571,880  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Bus Garage:
17-1926   Reconstruction               5-005-004               UNREVIEWED
                                                                       DONE       DONE      06/04/18   06/04/18   02/16/18   12/10/15   2,4,7                          0             0  SLC             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          South High School Parking:
11-0017   New Construction             7-033-001  11/20/15     DONE    DONE       DONE      ***FINAL APPLICATION FORM INCOMPLETE/INCORRECT***                                        0  HCM             0           0           0 Fellenzer Engineering                   0      12/17/15                       03/14/16           

          NHS Guard Booth #2:
15-0582   New Construction             7-038-001  01/04/16     DONE    DONE       DONE      10/15/15   07/28/15   10/15/15   05/20/14   02 - 16                   37,400             0  JMB             0           0           0 H2M Architects + Engineers              0        /  /                           /  /             

          Athletic Stg Container @ South HS:
  -       New Construction             7-039-001                                              /  /       /  /     06/24/16     /  /     02 - 16                        0             0  AAA             0           0           0                                         0        /  /                           /  /             

          District-Wide:
13-1167   Reconstruction               7-999-007  08/12/14     DONE    DONE       DONE      02/03/14   01/31/14   11/12/13   05/21/13   4,8,10,16                599,450       599,450  JMB             0           0           0 H2M Group                               0      12/27/15                       06/21/16           
15-0180   Reconstruction               7-999-008  01/04/16     DONE    DONE       DONE      07/29/15   07/28/15   05/21/15   05/20/14   10,13,16                 524,350       524,350  JMB             0           0           0 H2M Architects + Engineers              0        /  /                           /  /             
15-1313SB Reconstruction               7-999-009                         UNREVIEWED         02/26/16   02/26/16   02/26/16     /  /     10,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
16-1499   Reconstruction               7-999-009  06/14/17     DONE    DONE       DONE      03/13/17   03/13/17     /  /     11/04/14   10,16                    250,481       250,481  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
15-2004   Reconstruction               7-999-010  08/08/16     DONE    DONE       DONE      06/29/16   06/28/16   06/15/16   05/17/16   2,9                    1,806,749     1,806,749  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          XXSt. Augustine Schl (2015 no lease):
13-0470   Reconstruction               8-037-L01  10/25/13     DONE    DONE       DONE      10/08/13   10/08/13   10/08/13     /  /                              195,000       195,000  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NANUET UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-01-08-03
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Miller Elementary:
13-1507   Reconstruction               0-001-018  05/07/15     DONE    DONE       DONE      05/07/14   04/30/14   01/08/14   11/19/13   7,16                           0    13,020,428  JMB             0           0           0                                         0        /  /                           /  /             
14-0831   Reconstruction               0-001-019  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   10/27/14   05/19/15   2,9,155,15,16             78,000        78,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
  -       Reconstruction               0-001-020                                              /  /       /  /     06/14/16     /  /     16                             0     9,469,710  AAA             0           0           0                                         0        /  /                           /  /             

          Highview Elementary:
13-1423   Reconstruction               0-002-016  06/04/14     DONE    DONE       DONE      04/01/14   03/31/14   02/28/14   05/20/14   2,9                      500,000       500,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/28/14                       03/20/15           
14-0832   Reconstruction               0-002-017  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   10/27/14   05/19/15   2,9,155,15,16             78,000        78,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          Nanuet Senior High:
12-0875   Reconstruction               0-003-023  09/20/13     DONE    DONE       DONE      02/20/13   02/19/13   05/23/12   05/15/12   2,4,16                   500,000       500,000  HCM             0           0           0 KSQ ARCHITECTS PC                       0      11/24/15                       08/04/17           
13-1508   Reconstruction               0-003-024  05/07/15     DONE    DONE       DONE      05/07/14   04/30/14   01/08/14   11/19/13   7,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-025                                              /  /       /  /     06/14/16     /  /     9,15,16                        0    12,702,118  AAA             0           0           0                                         0        /  /                           /  /             
16-1485   Reconstruction               0-003-026  05/19/17     DONE    DONE       DONE      03/09/17   03/09/17   01/06/17   05/17/16   2,9                      785,000       785,000  SLC             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
  -       Reconstruction               0-003-027                                              /  /       /  /     04/12/17     /  /     4,8,9,10,15,16                 0    12,702,118  SLC             0           0           0                                         0        /  /                           /  /             
17-0928   Reconstruction               0-003-028  04/24/18     DONE    DONE       DONE      12/08/17   10/10/17   07/13/17   12/12/16   8,9,10,155,15,16       6,250,000             0  SLC             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
17-1097XX Reconstruction               0-003-029                         CANCELLED          01/02/18   12/26/17   11/21/17   12/12/16   2                              0             0  SLC             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          Barr Middle School:
13-1509   Reconstruction               0-004-015  05/07/15     DONE    DONE       DONE      05/07/14   04/30/14   01/08/14   11/19/13   7,16                           0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-016                                              /  /       /  /     10/27/14     /  /     2,9,155,15,16                  0    16,149,882  JMB             0           0           0                                         0        /  /                           /  /             
14-0833   Reconstruction               0-004-017  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   10/27/14   05/19/15   2,4,9,155,15,16        1,083,000     1,083,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      09/29/16                       12/09/16           
15-1915   Reconstruction               0-004-018  07/06/16     DONE    DONE       DONE      06/14/16   06/14/16   03/10/16   05/17/16   2                        120,000       120,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/29/16                       08/04/17           

          Public Library:
  -       Reconstruction               6-005-004                                              /  /       /  /     09/11/17     /  /     10,14                          0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Nanuet Outdoor Recreation Center:
10-1319DB Discovered Building          7-012-001  03/19/14     DONE    DONE       DONE      05/19/11   05/19/11   08/24/07     /  /                                    0             0  HCM             0           0           0                                         0      08/21/14                       09/17/14           
14-0834   Reconstruction               7-012-002  11/04/15     DONE    DONE       DONE      12/24/14   12/19/14   09/08/14   09/09/14   8,9,10,155,15,16         100,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
17-1210   Reconstruction               7-012-003  05/07/18     DONE    DONE       DONE      01/19/18   01/18/18   11/21/17   04/28/14   8,9,10,155,15,16         240,000             0  SLC             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          Horse Stables:
10-1320DB Discovered Building          7-013-001  03/17/14     DONE    DONE       DONE      05/19/11   05/19/11   08/24/07     /  /                                    0             0  HCM             0           0           0                                         0      08/21/14                       09/17/14           

          NOEC Greenhouse:
13-1351   New Construction             7-019-001  09/16/14     DONE    DONE       DONE      03/17/14   03/12/14   11/13/13   09/10/13   02 - 16                   70,000             0  JMB             0           0           0 KSQ ARCHITECTS PC                       0      05/27/15                       06/27/16           

          District Wide:
13-0139   Reconstruction               7-999-003  10/10/13     DONE    DONE       DONE      08/06/13   08/06/13   05/15/13   05/21/13   10,16                    500,000       500,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      09/24/14                       08/04/17           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH ROCKLAND/HAVERSTRAW-STONY PT STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-02-01-06
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Farley Elementary:
13-1540   Reconstruction               0-003-009  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   155,16                   764,976       764,976  DDJ             0           0     258,562 Michael Shilale Architects,LL           0      09/23/15                       04/03/18           
17-2084   Reconstruction               0-003-010               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/11/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          North Rockland High School Ext.:
13-1541   Reconstruction               0-007-014  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,4,155,16               136,000       136,000  DDJ             0           0      45,968 Michael Shilale Architects,LL           0      08/12/15                       04/03/18           
17-2085   Reconstruction               0-007-015               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/11/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Haverstraw Elementary:
13-1542   Reconstruction               0-009-016  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,4,7,9                1,323,165     1,323,165  DDJ             0           0     447,230 Michael Shilale Architects,LL           0      10/22/15                       04/03/18           
17-2086   Reconstruction               0-009-017               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/11/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Gerald F. Neary Elementary:
17-2087   Reconstruction               0-011-007               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/12/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Stony Point Elementary:
13-1543   Reconstruction               0-014-008  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,7,16                 1,397,428     1,397,428  DDJ             0           0     472,331 Michael Shilale Architects,LL           0      10/07/15                       04/03/18           
17-2088   Reconstruction               0-014-009               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/16/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          North Rockland High School:
13-1544   Reconstruction               0-016-023  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,4,7,9,155,15,16      2,736,536     2,736,536  DDJ             0           0     926,261 Michael Shilale Architects,LL           0      10/22/15                       04/03/18           
17-2089   Reconstruction               0-016-024               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/11/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             
  -       Reconstruction               0-016-025                                              /  /       /  /     02/26/18     /  /     155,15,16                      0             0  MTM             0           0           0                                         0        /  /                           /  /             

          West Haverstraw Elementary:
13-1545   Reconstruction               0-024-011  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,7,15,16                293,366       293,366  DDJ             0           0      99,158 Michael Shilale Architects,LL           0      10/22/15                       04/03/18           
17-2090   Reconstruction               0-024-012               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/16/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Thiells Elementary School:
13-1546   Reconstruction               0-025-013  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   2,7,16                   529,142       529,142  DDJ             0           0     178,850 Michael Shilale Architects,LL           0      10/07/15                       04/03/18           
17-2091   Reconstruction               0-025-014               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/16/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Willow Grove MS (fmly 8-030):
13-1548   Reconstruction               0-030-012  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   4,9                      158,550       158,550  DDJ             0           0      53,590 Michael Shilale Architects,LL           0      10/29/15                       04/03/18           
17-2092   Reconstruction               0-030-013               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/11/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Fieldstone Middle School:
13-1547   Reconstruction               0-031-003  07/22/14     DONE    DONE       DONE      05/19/14   05/12/14   08/26/13   11/19/13   9                        350,837       350,837  DDJ             0           0     118,583 Michael Shilale Architects,LL           0      10/29/15                       04/03/18           
17-2093   Reconstruction               0-031-004               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/29/18   06/28/18   01/16/18   07/05/17   155,15,16                      0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Building K - Day Care:
  -    DB Discovered Building          7-058-001                                              /  /       /  /     03/12/18     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
15-1451SB Reconstruction               7-999-004               DONE                           /  /       /  /     03/18/16     /  /     13,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-1933   Reconstruction               7-999-004  10/05/16     DONE    DONE       DONE      06/21/16   06/21/16     /  /     05/17/16   13,16                  5,294,721             0  DDJ             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             
17-0587SB Reconstruction               7-999-005               DONE                           /  /       /  /     10/17/17     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             
18-0069   Reconstruction               7-999-005               UNREVIEWED
                                                                       DONE       UNREVIEWED07/16/18   06/27/18   10/17/17   05/17/16                                  0             0  MTM             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH ORANGETOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-01-06
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Tappan Zee High School:
12-0820   Reconstruction               0-006-022  10/08/13     DONE    DONE       DONE      02/12/13   02/12/13   07/18/12   05/17/12   14,16                    181,638       181,638  JOD             0           0           0 LAN Associates                          0      09/04/14                       01/20/15           
13-0676   Reconstruction               0-006-023  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/26/13   05/21/13   2,4,8,9,10,155,16        722,765       722,765  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
14-0266   Reconstruction               0-006-024  04/23/15     DONE    DONE       DONE      09/09/14   09/08/14   04/23/14   05/21/14   2,9,10,16              1,750,000     1,750,000  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
  -       Reconstruction               0-006-025                                              /  /       /  /     06/24/16     /  /     2,13                           0    39,252,464  AAA             0           0           0                                         0        /  /                           /  /             
16-1551   Reconstruction               0-006-026               UNREVIEWED
                                                                       STARTED    UNREVIEWED07/27/18   07/27/18   12/01/16     /  /     9,10,155,16              696,391             0  MTM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
  -       Reconstruction               0-006-027                                              /  /       /  /     01/18/18     /  /     2,8,9,155,15,16                0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Tappan Zee Elementary:
13-0677   Reconstruction               0-007-017  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   10/02/13   05/21/13   16                        68,968        68,968  MFS             0           0           0 LAN Associates                          0      04/06/16                       11/14/17           
  -       Reconstruction               0-007-018                                              /  /       /  /     01/18/18     /  /     2,4,8,9,155,15,16              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Palisades Elementary:
16-0678   Reconstruction               0-008-011  11/23/16     DONE    DONE       DONE      10/27/16   10/27/16   10/01/16   09/24/16   155                      217,800       217,800  MTM             0           0           0 D&B Engineers & Architects, P           0      07/17/17                       04/06/18           

          Cottage Lane Elementary:
13-0678   Additions and Alterations    0-010-017  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   02 - 16                  800,455       800,455  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
  -       Reconstruction               0-010-018                                              /  /       /  /     01/18/18     /  /     2,8,9,155,15,16                0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Greenbush Academy:
13-0679   Reconstruction               0-011-009  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   8,9                      157,275             0  MFS             0           0           0 LAN Associates                          0      09/18/15                       11/29/17           

          William Schaefer Elementary:
12-0822   Reconstruction               0-012-013  10/08/13     DONE    DONE       DONE      02/12/13   02/12/13   07/18/12   05/17/12   155,15,16                251,798       251,798  MFS             0           0           0 LAN Associates                          0      09/26/14                       01/20/15           
13-0680   Reconstruction               0-012-014  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   2,4,8,9,155,16           125,075       125,075  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
16-1550   Reconstruction               0-012-015               UNREVIEWED
                                                                       STARTED    UNREVIEWED07/27/18   07/27/18   12/01/16     /  /     2,7,9,155,15,16          526,093             0  MTM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
  -       Reconstruction               0-012-016                                              /  /       /  /     01/18/18     /  /     2,8,9,155,15,16                0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Middle School:
12-0821   Reconstruction               0-013-022  10/08/13     DONE    DONE       DONE      02/12/13   02/12/13   07/18/12   05/17/12   8,9,10,14,16           1,092,096     1,092,096  JOD             0           0           0 LAN Associates                          0      09/22/14                       01/20/15           
13-0681   Reconstruction               0-013-023  06/06/14     DONE    DONE       DONE      11/07/13   11/05/13   07/25/13   05/21/13   2,4,8,9,155,15,16        584,121       584,121  MFS             0           0           0 LAN Associates                          0      08/28/15                       12/18/15           
16-1552   Reconstruction               0-013-024               UNREVIEWED
                                                                       STARTED    UNREVIEWED07/27/18   07/27/18   12/01/16     /  /     2,4,8,9,10,155,15,16   1,516,477             0  MTM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
  -       Reconstruction               0-013-025                                              /  /       /  /     01/18/18     /  /     2,4,8,9,155,15,16              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Orangeburg Elementary:
  -       Reconstruction               7-004-009                                              /  /       /  /     01/25/18     /  /     2                              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Guard Booth @ MS:
13-1329XX New Construction             7-020-001  06/06/14               CANCELLED          03/11/14   03/11/14   03/11/14   05/21/13   02 - 16                   54,400             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Guard Booth-North @ Tappan Zee HS:
13-1330XX New Construction             7-021-001  06/06/14               CANCELLED          03/11/14   03/11/14   03/11/14   05/21/13   02 - 16                   34,400             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Guard Booth-South @ Tappan Zee HS:
13-1331XX New Construction             7-022-001  06/06/14               CANCELLED          03/11/14   03/11/14   03/11/14   05/21/13   02 - 16                   34,400             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             

          Cottage Lane Library:
  -    PR New Construction             8-023-001                       DONE                   /  /       /  /     05/23/17     /  /     02 - 16                        0             0  MTM             0           0           0                                         0        /  /                           /  /             
17-0371   New Construction             8-023-001  08/17/18     DONE    DONE       DONE      09/11/17   08/31/17   05/23/17   05/16/17   02 - 16                  267,901             0  MTM             0           0           0 D&B Engineers & Architects, P           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NYACK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-04-03
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Valley Cottage Elementary:
13-1199   Reconstruction               0-001-010  04/25/14     DONE    DONE       DONE      02/10/14   02/10/14   08/20/13   10/29/13   2,4,7,8,9,10,155,15,     144,619       144,619  DDJ             0           0           0 LAN Associates                          0      08/27/14                       02/09/15           
13-1684   Reconstruction               0-001-011  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   01/08/14   10/29/13   2,4,7,8,9,10,155,15,   1,472,851     1,472,851  DDJ             0           0           0 LAN Associates                          0      01/29/16                       12/23/16           

          Old Nyack HS Leased to BOCES:
13-1200   Reconstruction               0-003-012  04/28/14     DONE    DONE       DONE      02/10/14   02/10/14   08/20/13   10/29/13   2,4,7,8,9,10,155,15,     362,140       362,140  DDJ             0           0           0 LAN Associates                          0      08/27/14                       02/09/15           
16-0704   Reconstruction               0-003-013  02/18/17     DONE    DONE       DONE      11/02/16   11/02/16   01/08/14   10/29/13   2,4,7,8,10,15,16       4,830,831     4,830,831  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
14-0358   Reconstruction               0-003-014  06/09/14     DONE    DONE       DONE      09/25/14   09/25/14   07/29/14   08/19/14   2,9,10                   200,000       200,000  DDJ             0           0           0 LAN Associates                          0      10/09/14                       02/17/15           
15-1544   Reconstruction               0-003-015  04/25/16     DONE    DONE       DONE      04/11/16   04/08/16   07/24/15   10/29/13   7                        545,281       545,281  SLC             0           0           0 LAN Associates                          0      09/27/17                       06/29/18           
16-1055   Reconstruction               0-003-016  03/01/17     DONE    DONE       DONE      12/22/16   12/22/16   09/29/16   10/29/13   13,16                    260,787             0  SLC             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-003-017                                              /  /       /  /     04/19/18     /  /     13                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Nyack Middle School:
13-1685   Reconstruction               0-004-009  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   09/13/07   10/29/13   2,7,8,155,15,16          571,893       571,893  DDJ             0           0           0 LAN Associates                          0      01/29/16                       12/19/16           
16-0151   Reconstruction               0-004-011  04/25/17     DONE    DONE       DONE      07/25/16   07/25/16   08/21/13   10/29/13   2,4,7,8,9,10,155,15,   2,696,860             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
15-1545   Reconstruction               0-004-012  04/25/16     DONE    DONE       DONE      03/11/16   03/08/16   07/24/15   10/29/13   7                      1,570,646     1,570,646  SLC             0           0           0 LAN Associates                          0      09/27/17                       06/29/18           
  -       Reconstruction               0-004-013                                              /  /       /  /     01/15/16     /  /     2,8,9                          0    12,616,704  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-014                                              /  /       /  /     02/02/16     /  /     2,8,9                          0    12,616,704  DDJ             0           0           0                                         0        /  /                           /  /             

          Hilltop Admin (frmly IS)(see 1-005):
14-0926   Reconstruction               0-005-008  02/13/15     DONE    DONE       DONE      01/08/15   01/07/15   06/03/14   05/20/14   2,8,13                   383,054             0  DDJ             0           0           0 LAN Associates                          0      05/30/16                       12/19/16           
14-0927   Reconstruction               0-005-009  02/13/15     DONE    DONE       DONE      01/08/15   01/07/15   10/20/14   10/21/14   2,8,10                   693,379             0  DDJ             0           0           0 LAN Associates                          0      05/30/16                       12/23/16           

          Liberty Elementary School:
17-0439   Reconstruction               0-006-011  05/30/18     DONE    DONE       DONE      09/22/17   09/22/17   08/20/13   10/29/13   2,4,7,8,9,10,155,15,   1,384,534             0  SLC             0           0           0 LAN Associates                          0        /  /                           /  /             

          Upper Nyack Elementary School:
13-1201   Reconstruction               0-007-013  04/28/14     DONE    DONE       DONE      02/10/14   02/10/14   09/13/07   10/29/13   2,4,7,8,155,15,16         29,635        29,635  DDJ             0           0           0 LAN Associates                          0      08/27/14                       02/09/15           
13-1686   Reconstruction               0-007-014  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   08/21/13   10/29/13   2,4,7,8,9,10,155,15,     817,921       817,921  DDJ             0           0           0 LAN Associates                          0      01/18/16                       12/23/16           
16-0152   Reconstruction               0-007-015  04/25/17     DONE    DONE       DONE      07/25/16   07/25/16   01/08/14   10/29/13   2,4,7,8,9,10,155,15,     994,246             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
15-1546   Reconstruction               0-007-016  04/25/16     DONE    DONE       DONE      04/11/16   04/08/16   07/24/15   10/29/13   7                        681,601       681,601  DDJ             0           0           0 LAN Associates                          0      09/28/16                       06/19/17           
  -       Reconstruction               0-007-017                                              /  /       /  /     01/15/16     /  /     2,4,8,9                        0     7,774,488  DDJ             0           0           0                                         0        /  /                           /  /             

          High School:
13-1687   Reconstruction               0-021-007  12/19/14     DONE    DONE       DONE      07/01/14   06/23/14   08/20/13   10/29/13   2,4,7,8,9,10,155,15,   2,655,726     2,655,726  DDJ             0           0           0 LAN Associates                          0      01/18/16                       12/23/16           
15-0057   Reconstruction               0-021-008  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   12/05/13   10/29/13   2,4,7,8,9,10,155,15,   8,630,309     8,630,309  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-021-009                                              /  /       /  /     12/05/13     /  /     2,4,7,8,9,10,155,15,           0    22,630,088  DDJ             0           0           0                                         0        /  /                           /  /             
16-0116   Reconstruction               0-021-010  04/17/17     DONE    DONE       DONE      07/18/16   07/18/16   02/02/16   05/17/16   9,10,16                  541,000             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          Hilltop Administration:
  -       Reconstruction               1-005-001                                              /  /       /  /     07/24/15     /  /     7                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             
17-1519   Reconstruction               1-005-002  05/16/18     DONE    DONE       DONE      03/09/18   03/09/18   06/22/17   05/16/17   2,10                     400,000             0  SLC             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               1-005-003                                              /  /       /  /     11/29/17     /  /     2,9,10                         0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Wood Shop Annex-Old Nyack HS:
16-1038   Reconstruction               2-015-001  02/18/17     DONE    DONE       DONE      12/21/16   12/19/16   12/01/16   10/29/13   4,7,8                    264,000             0  SLC             0           0           0 LAN Associates                          0        /  /                           /  /             

          Field House Bus Garage:
15-0058   Reconstruction               5-019-001  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   01/08/14   10/29/13   155                       47,416        47,416  DDJ             0           0           0 LAN Associates                          0      09/28/16                       06/19/17           

          Exhibitn Field PressBox/Toil/Concess:
15-0059   New Construction             7-031-001  03/22/16     DONE    DONE       DONE      07/13/15   07/13/15   03/04/14   10/29/13   02 - 16                   92,400             0  DDJ             0           0           0 LAN Associates                          0      08/28/18                       08/29/18           

          Concession Stand:
15-0060XX New Construction             7-032-001  03/22/16               CANCELLED          07/13/15   07/13/15   03/04/14   10/29/13   02 - 16                  434,280             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             

          XXMemorial PressBx/Concession @ HS:
  -    XX New Construction             7-033-001                         CANCELLED            /  /       /  /     06/30/15     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
13-1212   Reconstruction               7-999-005  06/18/14     DONE    DONE       DONE      02/12/14   02/11/14   12/05/13   10/29/13   8,16                     643,940       643,940  DDJ             0           0     134,096 LAN Associates                          0      08/27/14                       02/09/15           
15-1970   Reconstruction               7-999-006  07/11/16     DONE    DONE       DONE      06/23/16   06/23/16   12/05/13   05/17/16   8,16                     100,000             0  DDJ             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               7-999-007                                              /  /       /  /     04/18/16     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-999-008                                              /  /       /  /     11/29/17     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PEARL RIVER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-08-03
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Evans Park School:
17-1034   Reconstruction               0-002-012  06/20/18     DONE    DONE       DONE      12/20/17   10/18/17   06/05/17   05/16/17   8,155,15                 963,099             0  BMJ             0           0           0 EI Associates                           0        /  /                           /  /             
  -       Reconstruction               0-002-013                                              /  /       /  /     06/05/17     /  /     8,9,155,15,16                  0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Lincoln Ave.Elementary School:
17-1051   Reconstruction               0-003-012  06/20/18     DONE    DONE       DONE      12/22/17   10/23/17   06/05/17   05/16/17   10,155,15                851,705             0  BMJ             0           0           0 EI Associates                           0        /  /                           /  /             
  -       Reconstruction               0-003-013                                              /  /       /  /     06/05/17     /  /     9,155,15,16                    0     5,839,776  BMJ             0           0           0                                         0        /  /                           /  /             

          Senior High School:
14-1711   Reconstruction               0-009-020  09/22/15     DONE    DONE       DONE      06/23/15   06/19/15   11/04/14   05/19/15   4,10,155               1,093,032     1,093,032  JMB             0           0           0 KEEL ARCHITECTURE                       0      09/04/16                       04/12/17           
  -       Reconstruction               0-009-021                                              /  /       /  /     02/25/15     /  /     155                            0    24,456,680  JMB             0           0           0                                         0        /  /                           /  /             
17-1271   Reconstruction               0-009-022  05/17/18     DONE    DONE       DONE      01/30/18   01/30/18   06/30/17   05/16/17   8,9,14,155,15,16       5,370,316             0  BMJ             0           0           0 EI Associates                           0        /  /                           /  /             
18-0183   Reconstruction               0-009-023                       ADDENDUM REQ'D       08/03/18   07/09/18   06/30/17   05/16/17   9,13                           0             0  BMJ             0           0           0 EI Associates                           0        /  /                           /  /             
  -       Reconstruction               0-009-024                                              /  /       /  /     07/31/17     /  /     7                              0    25,306,205  BMJ             0           0           0                                         0        /  /                           /  /             

          Franklin Ave. Elementary:
17-1035   Reconstruction               0-010-011  06/20/18     DONE    DONE       DONE      12/21/17   10/18/17   06/05/17   05/16/17   7,8,9,155              1,145,384             0  BMJ             0           0           0 EI Associates                           0        /  /                           /  /             
  -       Reconstruction               0-010-012                                              /  /       /  /     06/05/17     /  /     9,155,15,16                    0     6,150,662  BMJ             0           0           0                                         0        /  /                           /  /             

          Middle School:
  -       Reconstruction               0-011-016                                              /  /       /  /     06/27/17     /  /     2,7,8,9,155,15,16              0             0  BMJ             0           0           0                                         0        /  /                           /  /             
18-0184   Reconstruction               0-011-017                       ADDENDUM REQ'D       08/03/18   07/09/18   06/27/17   05/16/17   8,9,155,15                     0             0  BMJ             0           0           0 EI Associates                           0        /  /                           /  /             

          Storage Building - Field:
  -       New Construction             2-019-001                                              /  /       /  /     06/30/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Pearl River Public Library:
15-0475XX Reconstruction               6-005-002                         CANCELLED          09/18/15   09/14/15   08/11/15     /  /     155,16                         0             0  JMB             0           0           0 KEEL ARCHITECTURE                       0        /  /                           /  /             
  -       Reconstruction               6-005-003                                              /  /       /  /     06/19/18     /  /     7                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          High School Press Box:
  -       Reconstruction               7-015-002                                              /  /       /  /     12/21/17     /  /     8,9,15,16                      0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bathroom Building - Field:
  -       New Construction             7-020-001                                              /  /       /  /     07/13/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAMAPO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-01-06
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Suffern Middle School:
17-1395   Reconstruction               0-002-027                         UNREVIEWED         02/15/18   02/15/18   11/15/17   05/16/17   16                             0    25,453,080  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-002-028                                              /  /       /  /     04/06/18     /  /     2                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-029                                              /  /       /  /     07/05/18     /  /     4                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          RP Connor Elementary School:
  -    PR Additions and Alterations    0-005-018                                              /  /       /  /     04/06/18     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Suffern High School:
16-0836   Reconstruction               0-020-030  06/08/17     DONE    DONE       DONE      11/23/16   11/22/16   04/05/16   05/17/16   9,10,155,15,16           400,000       400,000  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
16-1061   Reconstruction               0-020-031  06/19/17     DONE    DONE       DONE      12/27/16   12/23/16   08/05/16   05/15/07   155,16                 1,073,000             0  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
16-2159   Reconstruction               0-020-032  04/04/17     DONE    DONE       DONE      06/29/17   06/29/17   01/17/17   01/20/17   7                        436,360       436,360  BMJ             0           0           0 Clark Patterson Lee                     0      06/29/18                       08/08/18         YES
                                                                                                                                                                                                                                                                                                                                   
16-2071   Reconstruction               0-020-033  08/21/17     DONE    DONE       DONE      06/19/17   06/19/17   03/02/17   05/16/17   7                        563,500             0  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-1396   Reconstruction               0-020-034                         UNREVIEWED         02/15/18   02/15/18   11/15/17   05/16/17   16                             0    67,511,430  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -    PR Additions and Alterations    0-020-035                                              /  /       /  /     04/06/18     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-020-036                                              /  /       /  /     08/09/18     /  /     7                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Viola Elementary:
15-0754   Reconstruction               0-026-016  04/13/16     DONE    DONE       DONE      11/23/15   11/16/15   06/30/11   05/17/11   2,16                     450,000       450,000  HCM             0           0           0 Clark Patterson Lee                     0      09/01/17                       12/18/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-1276   Reconstruction               0-026-017  06/08/18     DONE    DONE       DONE      01/31/18   01/30/18   10/23/17   05/16/17   16                       100,000       100,000  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -    PR Additions and Alterations    0-026-018                                              /  /       /  /     04/06/18     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Hillburn Administration Building:
17-1397   Reconstruction               1-006-010                         UNREVIEWED         02/15/18   02/15/18   11/15/17   05/16/17   16                             0             0  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST RAMAPO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-04-02-06
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Spring Valley Senior High:
15-1844   Reconstruction               0-003-019  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   06/21/12   04/19/16   2,9                       90,000        90,000  HCM             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
  -       Reconstruction               0-003-020                                              /  /       /  /     10/06/15     /  /     2,8,9,15                       0    39,414,832  JMB             0           0           0                                         0        /  /                           /  /             
16-1339   Reconstruction               0-003-021  03/08/17     DONE    DONE       DONE      02/07/17   02/07/17   01/17/17   12/06/16   2,7,13,155,16          6,388,890     6,388,890  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-1037   Reconstruction               0-003-022  04/05/18     DONE    DONE       DONE      12/21/17   12/12/17   08/02/17   12/06/16   2,8,155,16             1,250,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             
  -    XX Reconstruction               0-003-023                         CANCELLED            /  /       /  /     08/29/17     /  /     4                              0    41,016,982  SLC             0           0           0                                         0        /  /                           /  /             

          Hempstead School:
  -       Reconstruction               0-006-014                                              /  /       /  /     01/16/15     /  /     2,16                           0     9,820,440  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-006-015                                              /  /       /  /     10/06/15     /  /     2,8                            0     9,820,440  JMB             0           0           0                                         0        /  /                           /  /             
17-1067   Reconstruction               0-006-016  02/07/18     DONE    DONE       DONE      12/26/17   12/22/17   08/02/17   12/06/16   2,155,15,16              957,500             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             
17-0782   Reconstruction               0-006-017  02/13/18     DONE    DONE       DONE      11/16/17   11/15/17   08/02/17   12/06/16   2,7,155,16             1,034,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Pomona Middle(fmlyPomonaJR):
  -       Reconstruction               0-008-017                                              /  /       /  /     08/07/14     /  /     2,9,13,16                      0    31,579,648  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-018                                              /  /       /  /     10/06/15     /  /     2,8                            0    31,579,648  JMB             0           0           0                                         0        /  /                           /  /             
16-1336   Reconstruction               0-008-019  02/24/17     DONE    DONE       DONE      02/07/17   02/07/17   01/17/17   12/06/16   2,4,7                  3,125,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          KakiatElemSch(frmrlyRamapoFreshCtr):
14-0087   Reconstruction               0-013-018  08/01/14     DONE    DONE       DONE      07/31/14   07/30/14   05/23/13   07/24/14   15                       104,500       104,500  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0      06/04/15                       06/24/15           
  -       Reconstruction               0-013-019                                              /  /       /  /     10/06/15     /  /     2,8                            0    33,246,720  JMB             0           0           0                                         0        /  /                           /  /             
16-1891   Reconstruction               0-013-020  06/29/17     DONE    DONE       DONE      05/24/17   05/24/17   01/17/17   12/06/16   2,8,10,155             1,000,000             0  SLC             0           0   1,000,000 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
16-1714   Reconstruction               0-013-021  01/22/18     DONE    DONE       DONE      04/20/17   04/20/17   01/31/17   12/06/16   2,155,16                 312,500             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-0120   Reconstruction               0-013-022  08/31/17     DONE    DONE       DONE      07/25/17   07/21/17   07/25/17   12/08/16   2,8,9,155,15,16          700,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-1041   Reconstruction               0-013-023  02/06/18     DONE    DONE       DONE      12/21/17   12/07/17   08/02/17   12/06/16   2,7,8,155,15,16        8,000,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-1858   Reconstruction               0-013-024  05/24/18     DONE    DONE       DONE      05/17/18   05/17/18   12/21/17   12/06/16   2,4,8,9,155,15,16      1,190,000     1,190,000  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Fleetwood Elementary School:
15-1845   Reconstruction               0-014-016  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   05/23/13   04/19/16   15                       120,000       120,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
  -       Reconstruction               0-014-017                                              /  /       /  /     10/06/15     /  /     2,4,8                          0     9,820,440  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-014-018                                              /  /       /  /     12/21/16     /  /     2,9                            0             0  SLC             0           0           0                                         0        /  /                           /  /             
16-1337   Reconstruction               0-014-019  02/24/17     DONE    DONE       DONE      02/07/17   02/07/17   01/18/17   12/06/16   2,4,7                    125,000       125,000  SLC             0           0     125,000 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
16-1892   Reconstruction               0-014-020  06/29/17     DONE    DONE       DONE      05/24/17   05/24/17   01/18/17   12/06/16   2,4,8                    125,000             0  SLC             0           0     125,000 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-1068   Reconstruction               0-014-021  02/07/18     DONE    DONE       DONE      12/26/17   12/22/17   08/02/17   12/06/16   2,155,15,16              950,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Summit Park Elementary:
  -       Reconstruction               0-015-015                                              /  /       /  /     10/06/15     /  /     2,8                            0     9,820,440  JMB             0           0           0                                         0        /  /                           /  /             
17-0783   Reconstruction               0-015-016  02/09/18     DONE    DONE       DONE      11/16/17   11/15/17   08/02/17   12/06/16   2,7,155,16             1,500,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Grandview Elementary:
  -       Reconstruction               0-016-013                                              /  /       /  /     10/06/15     /  /     2,8                            0     9,820,440  JMB             0           0           0                                         0        /  /                           /  /             
17-1069   Reconstruction               0-016-014  02/07/18     DONE    DONE       DONE      12/26/17   12/22/17   08/02/17   12/06/16   2,155,15,16              957,500             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             
17-0771   Reconstruction               0-016-015  02/16/18     DONE    DONE       DONE      11/15/17   11/14/17   08/02/17   12/06/16   2,7,155,16               731,250       731,250  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Margetts Road Elementary:
15-1846   Reconstruction               0-020-012  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,8                       80,000        80,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-0772   Reconstruction               0-020-013  02/20/18     DONE    DONE       DONE      11/15/17   11/14/17   08/02/17   12/06/16   2,7,155,16               375,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Ramapo Senior High School:
15-1490   Reconstruction               0-022-019  04/26/16     DONE    DONE       DONE      03/28/16   03/25/16   10/06/15   04/20/16   2,8,9                  1,130,000     1,130,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
16-1340   Reconstruction               0-022-020  03/08/17     DONE    DONE       DONE      02/07/17   02/07/17   01/17/17   12/06/16   2,4,9,13,155,16        3,562,500     3,562,500  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Lime Kiln School:
  -       Reconstruction               0-027-014                                              /  /       /  /     10/06/15     /  /     2,8                            0     9,820,440  JMB             0           0           0                                         0        /  /                           /  /             
16-1517   Reconstruction               0-027-015  05/15/17     DONE    DONE       DONE      03/17/17   03/17/17   01/17/17   12/06/16   2,10,155,16              250,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-0773   Reconstruction               0-027-016  02/16/18     DONE    DONE       DONE      11/15/17   11/14/17   08/02/17   12/06/16   2,7,155,16               350,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Elmwood Elementary School:
15-0534   Reconstruction               0-030-013  11/18/15     DONE    DONE       DONE      10/06/15   10/06/15   08/28/15   05/19/15   2,8,9,15,16               50,000        50,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
15-1847   Reconstruction               0-030-014  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,8                       50,000        50,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
16-1523   Reconstruction               0-030-015  04/04/17     DONE    DONE       DONE      03/20/17   03/20/17   01/17/17   12/06/16   2,9,155,16               962,500       962,500  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Chestnut Ridge Middle(frmlySpring Va:
15-1848   Reconstruction               0-034-018  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,8,9                     65,000        65,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
  -       Reconstruction               0-034-019                                              /  /       /  /     10/25/16     /  /     2,9                            0    16,121,344  SLC             0           0           0                                         0        /  /                           /  /             
16-1893   Reconstruction               0-034-020  09/28/17     DONE    DONE       DONE      05/24/17   05/24/17   01/31/17   12/06/16   2,8                       44,445             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-1040   Reconstruction               0-034-021  02/09/18     DONE    DONE       DONE      12/21/17   12/15/17   08/02/17   12/06/16   2,7,155,15,16          8,356,000     8,356,000  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-1859   Reconstruction               0-034-022  05/24/18     DONE    DONE       DONE      05/17/18   05/17/18   12/21/17   12/06/16   2,4,7,9,155,15,16        875,000       875,000  SLC             0           0     150,000 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Eldorado Elementary:
15-1849   Reconstruction               0-037-015  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   10/06/15   04/19/16   2,4,8                     80,000        80,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
16-1518   Reconstruction               0-037-016  05/15/17     DONE    DONE       DONE      03/17/17   03/17/17   01/17/17   01/24/17   2,13,155,16              250,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
17-0774   Reconstruction               0-037-017  02/16/18     DONE    DONE       DONE      11/15/17   11/14/17   08/02/17   12/06/16   2,7,8,155,16             430,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Admin Bldg-frmly S.Madison Instr:
15-1850   Reconstruction               1-005-012  06/22/16     DONE    DONE       DONE      06/01/16   06/01/16   03/02/16   04/19/16   16                        15,000             0  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             
16-1338   Reconstruction               1-005-013  02/24/17     DONE    DONE       DONE      02/07/17   02/07/17   01/17/17   12/06/16   2,4,7                    125,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Central Warehouse Bldg.:
  -       Reconstruction               2-009-006                                              /  /       /  /     05/05/17     /  /     8,9,155,15,16                  0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Transportation Garage:
13-1164   Reconstruction               5-001-010  02/05/14     DONE    DONE       DONE      01/30/14   01/30/14   07/03/13   07/23/13   10                        65,000        65,000  JMB             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          xxPress Box @ Spr Valley Demolished:
17-1520   Reconstruction               7-055-002  05/14/18     DONE    DONE       DONE      03/09/18     /  /     01/31/17     /  /                                5,000             0  SLC             0           0           0 Eisenbach & Ruhnke Engineerin           0        /  /                           /  /             

          Press Box @ Spring Valley HS 2:
17-0784   New Construction             7-056-001  03/01/18     DONE    DONE       DONE      11/16/17   06/22/17   01/30/17   12/06/16   02 - 16                   75,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Press Box @ Ramapo High School:
17-0785   New Construction             7-057-001  03/01/18     DONE    DONE       DONE      11/16/17   06/22/17   01/30/17   12/06/16   02 - 16                   75,000             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Concession Stand @ Spring Valley HS:
17-0786DB Discovered Building          7-058-001  03/01/18     DONE    DONE       DONE      11/16/17   06/22/17   01/30/17   12/06/16                                  0             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          Concession Stand @ Ramapo HS:
17-0787DB Discovered Building          7-059-001  03/01/18     DONE    DONE       DONE      11/16/17   06/22/17   01/30/17   12/06/16                                  0             0  SLC             0           0           0 Eisenbach and Ruhnke Engineer           0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-002                                              /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1634SB Reconstruction               7-999-002               DONE                           /  /       /  /     04/27/16     /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-999-003                                              /  /       /  /     10/01/16     /  /     15                             0             0  SLC             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ROCKLAND STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-90-00-00
last updated on 09/21/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jessie J Kaplan #9:
14-1213PR Additions and Alterations    0-010-008                         UNREVIEWED         02/27/15   02/26/15   01/06/15     /  /     02 - 16                        0             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             
14-1550   Additions and Alterations    0-010-008  04/19/16     DONE    DONE       DONE      05/26/15   05/21/15   01/06/15   11/13/13   02 - 16                8,657,120             0  MFS             0           0           0 Michael Shilale Architects,LL           0      09/14/18           YES           /  /             

          Administration Bldg:
14-1214PR Additions and Alterations    1-007-007                         UNREVIEWED         02/27/15   02/26/15   01/06/15     /  /     02 - 16                        0             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             
14-1551   Additions and Alterations    1-007-007  04/19/16     DONE    DONE       DONE      05/26/15   05/21/15   01/06/15   11/11/13   02 - 16                  636,600             0  MFS             0           0           0 Michael Shilale Architects,LL           0        /  /                           /  /             

          Bldg #5 BUS GARAGE/WELDNG&MECH INSTR:
15-1076   Reconstruction               5-009-005  07/28/16     DONE    DONE       DONE      01/20/16   01/19/16   01/07/16   01/13/16   8,15                     254,458       254,458  MFS             0           0           0 Michael Shilale Architects,LL           0      11/15/16                       11/21/16           
  -       Reconstruction               5-009-006                                              /  /       /  /     08/30/18     /  /     155                            0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED