BRASHER FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-01-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle/High School:
18-1584 Additions and Alterations 0-001-013 07/17/19 DONE DONE DONE 03/05/19 02/26/19 05/14/18 12/12/17 02 - 16 6,700,000 6,700,000 JLB 0 0 126,708 King & King Architects 0 12/31/20 02/26/19
- XX Reconstruction 0-001-014 CANCELLED 08/12/20 08/07/20 03/18/20 06/16/20 15 100,000 100,000 JLB 0 0 0 King & King Architects 0 / / 08/07/20
23-0295 Reconstruction 0-001-015 10/24/23 DONE DONE DONE 08/21/23 08/21/23 05/09/23 05/16/23 8,10,16 100,000 100,000 WLC 0 0 0 King & King Architects 0 / / 08/21/23
- Reconstruction 0-001-016 / / / / 01/18/24 / / 2,4,7,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-001-017 / / / / 03/27/24 / / 9,15 0 0 WLC 0 0 0 0 / / / /
Elementary School:
18-1585 Reconstruction 0-005-011 07/17/19 DONE DONE DONE 03/05/19 02/26/19 05/14/18 12/12/17 2,4,8,9,10,155,15,16 5,300,000 5,300,000 JLB 0 0 100,000 King & King Architects 0 09/04/20 02/26/19
21-0062 Reconstruction 0-005-012 08/11/21 DONE DONE DONE 07/16/21 07/16/21 04/30/21 05/18/21 2,8,13 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/01/22 07/16/21
22-0310 Reconstruction 0-005-013 10/14/22 DONE DONE DONE 08/22/22 08/22/22 05/10/22 05/17/22 8,155,15 100,000 100,000 WLC 0 0 0 King & King Architects 0 06/14/23 08/22/22
22-0061 Reconstruction 0-005-014 06/14/22 DONE DONE DONE 07/11/22 07/08/22 / / 06/14/22 2 90,000 90,000 WLC 0 0 0 King & King Architects 0 / / 07/08/22
- Reconstruction 0-005-015 / / / / 01/18/24 / / 2,7,8,9,10,155,15,16 0 0 WLC 0 0 0 0 / / / /
Storage #2:
- PR New Construction 2-005-001 / / / / / / / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
Bus Garage:
18-1586 Reconstruction 5-002-009 07/17/19 DONE DONE DONE 03/05/19 02/26/19 05/14/18 12/12/17 2,4,8,9,10,155,15,16 1,808,500 1,808,500 JLB 0 0 0 King & King Architects 0 09/04/20 02/26/19
20-0192 Reconstruction 5-002-010 10/21/20 DONE DONE DONE 08/12/20 08/07/20 06/11/19 06/09/20 15 100,000 100,000 JLB 0 0 0 0 06/25/21 08/07/20
- Reconstruction 5-002-011 / / / / 01/18/24 / / 2,8,9,14,16 0 0 WLC 0 0 0 0 / / / /
District-Wide:
- XX Reconstruction 7-999-002 CANCELLED / / / / 10/17/22 / / 4,8 0 0 WLC 0 0 0 0 / / / /
22-0738XX Reconstruction 7-999-002 CANCELLED / / / / 10/17/22 / / 4,8 0 0 WLC 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA3 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
- SB Reconstruction 7-999-BA4 DONE / / / / / / / / 4,8 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CANTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-02-01-06
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Canton Cent. Sch(PK-12)was 002&009:
- XX Reconstruction 0-010-016 CANCELLED 07/30/19 07/16/19 10/03/17 04/04/19 16 0 62,109,806 BMJ 0 0 0 Tisdel Associates consulting 0 / / 07/16/19
18-2005 Reconstruction 0-010-019 06/17/19 DONE DONE DONE 05/23/19 05/08/19 04/25/19 05/19/15 15,16 243,900 243,900 BMJ 0 0 0 IBC Engineering,P.C. 0 06/10/20 05/08/19
19-0189 Reconstruction 0-010-020 09/19/19 DONE DONE DONE / / / / 06/26/19 05/21/19 2,8 98,500 98,500 BMJ 0 0 0 Tisdel Associates consulting 0 04/24/20 / /
20-1800 Reconstruction 0-010-021 07/19/21 DONE DONE DONE 05/28/21 05/28/21 03/10/20 05/18/21 2,9 50,000 50,000 SLC 0 0 0 King & King Architects 0 01/03/22 05/28/21
20-1056 Reconstruction 0-010-022 09/01/20 DONE DONE DONE 12/28/20 12/21/20 12/02/20 11/19/20 2,15 35,000 0 JSS 0 0 0 King & King Architects 0 01/07/21 12/21/20
20-1173 Reconstruction 0-010-023 01/19/21 DONE DONE DONE 01/21/21 01/21/21 01/08/21 01/07/21 15 15,000 0 JSS 0 0 0 King & King Architects 0 02/04/21 01/21/21
21-1812 Reconstruction 0-010-024 11/09/22 DONE DONE DONE 05/13/22 05/10/22 07/09/21 05/18/21 2,4,7,8,9,10,155,15, 36,181,760 24,781,400 SLC 0 0 0 King & King Architects 0 / / 05/10/22
22-1046 Reconstruction 0-010-025 12/23/22 DONE DONE DONE 11/18/22 11/17/22 05/09/22 05/17/22 2,16 100,000 100,000 SLC 0 0 0 King & King Architects 0 04/21/23 11/17/22
23-0194 Reconstruction 0-010-026 10/23/23 DONE DONE DONE 08/04/23 08/04/23 05/11/23 05/16/23 9,10 100,000 100,000 MSK 0 0 0 King & King Architects 0 / / 08/04/23
23-0590 Reconstruction 0-010-027 09/07/23 DONE DONE DONE 10/02/23 09/29/23 09/25/23 09/07/23 14 40,000 40,000 MSK 0 0 0 King & King Architects 0 10/31/23 09/29/23
- Reconstruction 0-010-028 / / / / 04/03/24 / / 9,10,15 0 0 MSK 0 0 0 0 / / / /
1998 Small Bus Garage:
21-1813 Reconstruction 5-012-003 11/09/22 DONE DONE DONE 05/13/22 05/10/22 08/25/21 05/18/21 2,4,9,155,15,16 2,718,600 2,718,600 SLC 0 0 0 King & King Architects 0 / / 05/10/22
District-Wide:
- XX Reconstruction 7-999-002 CANCELLED / / / / 11/20/20 / / 15 0 0 JSS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CLIFTON FINE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-04-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Clifton-Fine School Main Bldg.:
19-0595 Reconstruction 0-002-022 01/10/20 DONE DONE DONE 10/21/19 10/08/19 09/06/19 05/21/19 2,9,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 05/15/20 10/08/19
20-1491 Reconstruction 0-002-023 07/31/21 DONE DONE DONE 03/26/21 03/09/21 09/13/19 12/20/17 2,8,9,155,16 1,168,000 1,168,000 SLC 0 0 0 Bernier Carr Associates 0 05/23/23 03/09/21
20-0345 Reconstruction 0-002-024 11/12/20 DONE DONE DONE 09/04/20 08/27/20 08/11/20 06/16/20 2,8,9,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 06/09/21 08/27/20
20-1567 Reconstruction 0-002-025 06/15/21 DONE DONE DONE 04/07/21 04/05/21 02/18/21 05/18/21 9 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 08/30/21 04/05/21
21-1950 Reconstruction 0-002-026 06/28/22 DONE DONE DONE 06/08/22 06/08/22 04/25/22 05/17/22 2,16 100,000 100,000 WLC 0 0 0 Bernier Carr Associates 0 04/12/23 06/08/22
23-0542 Reconstruction 0-002-027 STARTED DONE ADD. REQ'D09/25/23 09/21/23 02/15/23 11/17/22 2,4,8,9,10,155,15,16 5,274,000 0 WLC 0 0 0 Bernier Carr Associates 0 / / 09/21/23
22-2044FC Reconstruction 0-002-028 05/31/23 DONE DONE DONE 04/17/23 03/01/23 02/16/23 05/30/23 9 44,000 0 WLC 0 0 0 Bernier Carr Associates 0 / / 03/01/23
22-2342 Reconstruction 0-002-029 07/05/23 DONE DONE DONE 06/09/23 06/08/23 03/27/23 05/16/23 2,8,9,16 100,000 100,000 WLC 0 0 0 Bernier Carr Associates 0 02/23/24 06/08/23
- Reconstruction 0-002-030 / / / / 02/15/24 / / 2,4,9,155,16 0 0 WLC 0 0 0 0 / / / /
Bus Garage:
23-0543 Reconstruction 5-001-007 STARTED DONE ADD. REQ'D09/25/23 09/21/23 02/15/23 11/17/22 2,4 326,000 0 WLC 0 0 0 Bernier Carr Associates 0 / / 09/21/23
- Reconstruction 5-001-008 / / / / 01/23/24 / / 16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
COLTON-PIERREPONT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-05-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
20-1879 Reconstruction 0-001-015 06/15/21 DONE DONE DONE 06/14/21 06/14/21 05/14/21 05/18/21 2,9 140,000 140,000 SLC 0 0 0 Bernier Carr Associates 0 08/31/21 06/14/21
21-1832 Reconstruction 0-001-016 07/26/22 DONE DONE DONE 05/18/22 05/18/22 02/14/22 05/17/22 2,4,7,8,9,10,155,15, 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 05/03/23 05/18/22
22-1969 Reconstruction 0-001-017 06/21/23 DONE DONE DONE 03/31/23 03/28/23 01/20/23 05/16/23 4,8,9,10 100,000 100,000 MSK 0 0 0 Bernier Carr Associates 0 11/28/23 03/28/23
23-0954 Reconstruction 0-001-018 UNREVIEWED 11/10/23 11/08/23 02/10/23 05/16/23 2,4,7,8,9,10,14,155, 0 0 MSK 0 0 0 Bernier Carr Associates 0 / / 11/08/23
23-1826 Reconstruction 0-001-019 UNREVIEWED 04/16/24 04/16/24 01/09/24 / / 4,8,9,10 0 0 MSK 0 0 0 Bernier Carr Associates 0 / / 04/16/24
- SB Reconstruction 0-001-BA1 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
GOUVERNEUR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-11-01-06
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Gouverneur ES (fmly East Side ES):
- Reconstruction 0-003-013 / / / / 02/20/24 / / 2,4,7,8,9,16 0 0 MSK 0 0 0 0 / / / /
West Side Middle School:
23-0827 Reconstruction 0-006-012 UNREVIEWED
STARTED STARTED 10/30/23 10/26/23 04/24/23 05/16/23 2,4,8,9,10,155,15,16 0 23,705,897 MSK 0 0 0 Bernier Carr Associates 0 / / 10/26/23
- Reconstruction 0-006-013 / / / / 02/15/24 / / 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
Senior High School:
21-0538 Reconstruction 0-007-015 01/11/22 DONE DONE DONE 10/15/21 10/15/21 03/29/21 05/21/19 7,8,9 1,555,000 1,555,000 SLC 0 0 0 March Associates 0 / / 10/15/21
- Reconstruction 0-007-016 / / / / 02/15/24 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
XX West Side Access - DEMO XX:
- Reconstruction 1-016-002 / / / / 02/16/24 / / 2 0 0 MSK 0 0 0 0 / / / /
Bus Garage:
- Reconstruction 5-011-007 / / / / 02/15/24 / / 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HAMMOND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-12-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central School Main Bldg.:
19-1363 Reconstruction 0-001-013 03/04/20 DONE DONE DONE 02/05/20 02/04/20 01/15/20 05/21/19 16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 06/17/20 02/04/20
20-0760 Reconstruction 0-001-014 01/04/21 DONE DONE DONE 10/30/20 10/29/20 09/17/20 06/09/20 9,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 05/28/21 10/29/20
20-1765 Reconstruction 0-001-015 07/16/21 DONE DONE DONE 05/21/21 05/18/21 04/28/21 05/18/21 9,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 02/24/22 05/18/21
22-0242 Reconstruction 0-001-016 11/22/22 DONE DONE DONE 08/05/22 08/05/22 04/04/22 05/17/22 9 100,000 100,000 WLC 0 0 0 Bernier Carr Associates 0 05/25/23 08/05/22
22-1685 Reconstruction 0-001-017 07/21/23 DONE DONE DONE 02/15/23 02/14/23 09/21/22 06/14/22 8,155,16 640,061 640,061 WLC 0 0 0 Bernier Carr Associates 640,061 / / 02/14/23
23-0018 Reconstruction 0-001-018 08/17/23 DONE DONE DONE 07/07/23 07/05/23 05/08/23 05/16/23 9,16 100,000 100,000 WLC 0 0 0 Bernier Carr Associates 0 / / 07/05/23
23-0925 Reconstruction 0-001-019 UNREVIEWED 11/08/23 11/06/23 06/27/23 03/14/23 2,4,8,9,10,155,15,16 0 0 WLC 0 0 0 Bernier Carr Associates 0 / / 11/06/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LISBON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-16-02-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
School Building:
20-0836 Reconstruction 0-001-018 03/01/21 DONE DONE DONE 11/17/20 11/05/20 07/08/20 06/16/20 2,4,7,8,9,10,14,155, 4,300,000 4,300,000 JSS 0 0 0 SEI Design Group 0 04/16/23 11/05/20
20-1460 Reconstruction 0-001-019 06/14/21 DONE DONE DONE 03/23/21 03/18/21 11/20/20 02/23/21 2,155,16 1,200,000 1,200,000 JSS 0 0 0 SEI Design Group 1,200,000 04/17/23 03/18/21
22-2083SB Reconstruction 0-001-020 DONE / / / / 04/24/23 / / 8,16 0 0 JJH 0 0 0 0 / / / /
23-0871 Reconstruction 0-001-020 UNREVIEWED 11/03/23 10/31/23 / / 08/19/23 8,16 0 17,211,278 JJH 0 0 0 SEI Design Group 0 / / 10/31/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MADRID WADDINGTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-19-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
18-1929 Reconstruction 0-003-015 06/06/19 DONE DONE DONE 05/07/19 05/03/19 03/25/19 05/21/19 2,8,9 100,000 100,000 JLB 0 0 0 SEI Design Group 0 05/21/20 05/03/19
19-1692 Reconstruction 0-003-016 07/13/20 DONE DONE DONE 04/13/20 04/08/20 12/20/19 12/17/19 2,4,7,8,9,10,155,15, 5,024,883 5,024,883 JLB 0 0 0 SEI Design Group 0 05/10/22 04/08/20
19-1827 Reconstruction 0-003-017 08/06/20 DONE DONE DONE 06/09/20 05/29/20 03/05/20 06/09/20 8,10,16 100,000 100,000 JLB 0 0 0 SEI Design Group 0 05/19/21 05/29/20
21-0951 Reconstruction 0-003-018 04/07/22 DONE DONE DONE 12/22/21 12/22/21 11/17/21 12/17/19 2,4,8,9,16 850,000 850,000 JLB 0 0 0 SEI Design Group 0 10/12/22 12/22/21
21-1968 Reconstruction 0-003-019 07/26/22 DONE DONE DONE 06/13/22 06/13/22 03/10/22 05/17/22 8 100,000 100,000 JLB 0 0 0 SEI Design Group 0 05/16/23 06/13/22
22-2140 Reconstruction 0-003-020 07/07/23 DONE DONE DONE 05/03/23 05/03/23 03/29/23 05/17/23 8 100,000 100,000 JJH 0 0 0 SEI Design Group 0 / / 05/03/23
- Reconstruction 0-003-021 / / / / 10/25/23 / / 2,4,7,8,9,10,14,155, 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-003-022 / / / / 02/13/24 / / 8 0 0 JJH 0 0 0 0 / / / /
Metal Field Storage:
- Reconstruction 2-008-002 / / / / 10/25/23 / / 2,7,8,9 0 0 JJH 0 0 0 0 / / / /
Bus Garage:
20-1642 Reconstruction 5-006-007 08/05/21 DONE DONE DONE 04/27/21 04/22/21 03/09/21 05/18/21 8,16 100,000 100,000 JLB 0 0 0 SEI Design Group 0 05/11/22 04/22/21
23-1597 Additions and Alterations 5-006-008 UNREVIEWED 03/07/24 03/05/24 10/25/23 10/18/23 02 - 16 0 0 JJH 0 0 0 SEI Design Group 0 / / 03/05/24
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MASSENA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-20-01-06
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jefferson Elementary:
19-1306 Reconstruction 0-001-011 04/29/20 DONE DONE DONE 01/30/20 01/21/20 01/08/20 12/12/19 2,4,7,9,16 4,042,000 3,969,540 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-1012 Reconstruction 0-001-012 03/19/21 DONE DONE DONE 12/22/20 12/17/20 12/01/20 12/12/19 2,4,8,9,10,155,15,16 4,250,000 4,250,000 JSS 0 0 0 IBI GROUP 0 09/19/22 12/17/20
Madison Elementary:
19-1307 Reconstruction 0-004-009 04/29/20 DONE DONE DONE 01/30/20 01/21/20 01/08/20 12/12/19 2,4,7,9,16 4,262,000 4,262,000 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-1013 Reconstruction 0-004-010 03/19/21 DONE DONE DONE 12/22/20 12/17/20 12/01/20 12/12/19 2,4,8,9,10,155,15,16 4,660,000 4,660,000 JSS 0 0 0 IBI GROUP 0 09/19/22 12/17/20
Nightengale Elementary:
19-1308 Reconstruction 0-005-011 04/29/20 DONE DONE DONE 01/30/20 01/21/20 01/08/20 12/12/19 2,4,7,9,16 4,255,000 4,255,000 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-1014 Reconstruction 0-005-012 03/19/21 DONE DONE DONE 12/22/20 12/17/20 12/01/20 12/12/19 2,4,8,9,10,155,15,16 4,720,000 4,720,000 JSS 0 0 0 IBI GROUP 0 09/19/22 12/17/20
Massena Senior High:
19-1309 Reconstruction 0-008-019 04/29/20 DONE DONE DONE 01/30/20 01/21/20 01/08/20 12/12/19 2,4,7,9,16 9,075,000 9,075,000 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-1015 Reconstruction 0-008-020 03/19/21 DONE DONE DONE 12/22/20 12/17/20 12/01/20 12/12/19 2,4,9,155,15,16 1,716,600 1,716,600 JSS 0 0 0 IBI GROUP 0 09/19/22 12/17/20
20-1951 Reconstruction 0-008-021 11/23/21 DONE DONE DONE 06/30/21 06/25/21 06/02/21 12/12/19 2,4,7,8,9,10,155,15, 9,590,000 9,590,000 JLB 0 0 0 IBI GROUP 0 / / 06/25/21
22-1813 Reconstruction 0-008-022 04/25/23 DONE DONE DONE 03/10/23 03/08/23 12/19/22 05/17/22 155 100,000 100,000 WLC 0 0 0 IBI GROUP 0 06/20/23 03/08/23
23-1302 Reconstruction 0-008-023 02/15/24 DONE DONE DONE 12/28/23 12/26/23 07/10/23 05/16/23 155 100,000 100,000 WLC 0 0 0 Arcadis Architects, Engineers 0 / / 12/26/23
- Reconstruction 0-008-024 / / / / 12/21/23 / / 2,155 0 0 WLC 0 0 0 0 / / / /
J.W. Leary Junior High School:
19-1310 Reconstruction 0-012-011 04/29/20 DONE DONE DONE 01/30/20 01/21/20 / / 12/12/19 2,4,7,9,16 6,120,000 6,120,000 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-1952 Reconstruction 0-012-012 11/23/21 DONE DONE DONE 07/13/21 06/25/21 06/02/21 12/12/19 2,4,7,8,9,10,155,15, 4,100,000 4,100,000 JLB 0 0 0 IBI GROUP 0 / / 06/25/21
Cent Admin Bldg (fmly Bus Gar/Maint):
19-1311 Reconstruction 5-006-013 04/29/20 DONE DONE DONE 01/30/20 01/21/20 01/08/20 12/12/19 2,9,16 452,000 452,000 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-1953 Reconstruction 5-006-014 11/23/21 DONE DONE DONE 07/13/21 06/25/21 06/02/21 12/12/19 155,16 290,000 290,000 JLB 0 0 0 IBI GROUP 0 / / 06/25/21
Trans. Fac./Fuel Depot:
18-2093 Reconstruction 5-019-003 07/01/19 DONE DONE DONE 06/10/19 05/31/19 05/08/19 05/21/19 15 100,000 100,000 JLB 0 0 0 IBI GROUP 0 04/28/20 05/31/19
19-1312 Reconstruction 5-019-004 04/29/20 DONE DONE DONE 01/30/20 01/21/20 01/08/20 12/12/19 2,4,7,9,16 700,000 700,000 JSS 0 0 0 IBI GROUP 0 09/28/21 01/21/20
20-0300 Reconstruction 5-019-005 11/13/20 DONE DONE DONE 09/01/20 08/27/20 06/22/20 06/16/20 16 100,000 100,000 JSS 0 0 0 IBI GROUP 0 04/30/21 08/27/20
20-1016 Reconstruction 5-019-006 03/19/21 DONE DONE DONE 12/22/20 12/17/20 12/01/20 12/12/19 2,4,8,9,16 375,000 375,000 JSS 0 0 0 IBI GROUP 0 09/19/22 12/17/20
20-1954 Reconstruction 5-019-007 11/23/21 DONE DONE DONE 06/30/21 06/25/21 06/02/21 12/12/19 155,16 350,000 350,000 JLB 0 0 0 IBI GROUP 0 / / 06/25/21
TRANSPORTATION FACILITY cANOPY:
- PR New Construction 5-021-001 / / / / 12/14/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
20-1017XX New Construction 5-021-001 CANCELLED 12/22/20 12/17/20 12/14/20 12/12/19 02 - 16 0 0 JSS 0 0 0 IBI GROUP 0 / / 12/17/20
District-Wide:
21-1110 Reconstruction 7-999-001 03/09/22 DONE DONE DONE 01/12/22 01/11/22 09/24/21 05/18/21 16 100,000 100,000 JLB 0 0 0 IBI GROUP 0 06/01/22 01/11/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
OGDENSBURG CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-23-00-01
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
John F. Kennedy Elem. School:
22-0056FA Reconstruction 0-006-013 07/13/22 DONE DONE DONE 07/07/22 06/06/22 02/23/22 05/17/22 2,4,7,8,9,155,15,16 3,173,000 3,173,000 WLC 0 0 0 Bernier Carr Associates 0 05/25/23 06/06/22
- Reconstruction 0-006-014 / / / / 10/24/23 / / 2,4,7,8,9,10,155,15, 0 0 WLC 0 0 0 0 / / / /
Free Academy:
19-0132 Reconstruction 0-007-022 08/19/19 DONE DONE DONE 07/23/19 07/16/19 / / 05/21/19 2,4,7,9,155,15,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 02/10/20 07/16/19
19-1862 Reconstruction 0-007-023 07/24/20 DONE DONE DONE 06/22/20 05/21/20 02/21/20 06/09/20 4,7,9,155,15,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 02/17/21 05/21/20
21-0106 Reconstruction 0-007-024 08/28/21 DONE DONE DONE 07/28/21 07/27/21 03/17/21 05/18/21 2,4,7,8,9,155,15,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 05/10/22 07/27/21
22-1970 Reconstruction 0-007-025 06/05/23 DONE DONE DONE 03/31/23 03/29/23 02/23/23 05/16/23 2,4,7,8,9,155,15,16 2,980,000 2,980,000 WLC 0 0 0 Bernier Carr Associates 0 / / 03/29/23
- Reconstruction 0-007-026 / / / / 10/24/23 / / 2,4,7,8,9,10,13,14,1 0 0 WLC 0 0 0 0 / / / /
23-1822 Reconstruction 0-007-027 UNREVIEWED 04/16/24 04/15/24 03/05/24 / / 2,4,7,8,9,13,155,15, 0 0 WLC 0 0 0 Bernier Carr Associates 0 / / 04/15/24
Madill Elementary School:
- PR Additions and Alterations 0-014-013 / / / / 10/24/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
Transport Facility:
22-2143PR New Construction 5-022-001 DONE 05/05/23 / / 04/24/23 / / 02 - 16 10,500,000 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HEUVELTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-24-04-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
19-1825 Reconstruction 0-001-012 08/10/20 DONE DONE DONE 06/09/20 05/27/20 04/21/20 03/26/15 2,8,9,15,16 398,000 398,000 SLC 0 0 0 SEI Design Group 0 09/30/21 05/27/20
22-0046 Reconstruction 0-001-013 10/11/22 DONE DONE DONE 07/06/22 07/05/22 03/28/22 05/17/22 9,10 100,000 100,000 WLC 0 0 0 SEI Design Group 0 / / 07/05/22
22-2332 Reconstruction 0-001-014 07/05/23 DONE DONE DONE 06/07/23 06/07/23 05/19/22 05/16/23 9 100,000 100,000 WLC 0 0 0 SEI Design Group 0 / / 06/07/23
23-1598PR Reconstruction 0-001-015 03/08/24 / / / / / / 2,4,7,8,9,10,13,155, 0 0 WLC 0 0 0 0 / / / /
- SB Reconstruction 0-001-BA1 DONE / / / / / / / / 16 0 0 WLC 0 0 0 0 / / / /
Storage Barn:
- Reconstruction 2-003-001 / / / / 12/18/23 / / 2,9 0 0 WLC 0 0 0 0 / / / /
Bus Garage:
- Reconstruction 5-002-009 / / / / 12/18/23 / / 4,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PARISHVILLE-HOPKINTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-25-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
19-0248 Reconstruction 0-003-022 10/03/19 DONE DONE DONE 08/12/19 08/05/19 06/11/19 05/21/19 8 50,000 50,000 SLC 0 0 0 King & King Architects 0 06/30/20 08/05/19
19-1059 Reconstruction 0-003-023 09/19/19 DONE DONE DONE 12/26/19 12/20/19 09/12/19 09/16/19 15 40,000 40,000 SLC 0 0 0 King & King Architects 0 01/21/20 12/20/19
19-1034SB Reconstruction 0-003-024 DONE / / / / 12/23/19 / / 16 0 0 SLC 0 0 0 0 / / / /
20-0566 Reconstruction 0-003-024 01/09/21 DONE DONE DONE 10/09/20 09/25/20 12/23/19 08/15/16 16 17,000 0 SLC 0 0 0 King & King Architects 0 / / 09/25/20
20-0064 Reconstruction 0-003-025 08/26/20 DONE DONE DONE 07/17/20 07/16/20 03/10/20 06/09/20 8 75,000 75,000 SLC 0 0 0 King & King Architects 0 05/31/22 07/16/20
21-1158 Reconstruction 0-003-026 02/22/22 DONE DONE DONE 01/18/22 01/18/22 12/17/21 05/18/21 8 100,000 100,000 SLC 0 0 0 King & King Architects 0 04/21/23 01/18/22
22-1606 Reconstruction 0-003-027 04/25/23 DONE DONE DONE 02/01/23 02/01/23 11/07/22 05/17/22 4,8,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 / / 02/01/23
23-0249 Reconstruction 0-003-028 01/23/24 DONE DONE DONE 08/14/23 08/14/23 07/17/23 07/19/23 2 165,000 0 MSK 0 0 0 King & King Architects 0 / / 08/14/23
- Reconstruction 0-003-029 / / / / 01/16/24 / / 2,4,8,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-003-030 / / / / 03/29/24 / / 8,9,155,16 0 0 MSK 0 0 0 0 / / / /
District-Wide:
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
POTSDAM CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-29-02-06
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Potsdam High School:
21-1500 Reconstruction 0-001-016 11/09/22 DONE DONE DONE 03/14/22 03/14/22 03/02/21 02/10/21 2,4,7,8,9,14,155,15, 8,219,200 8,219,200 JLB 0 0 0 SEI Design Group 0 / / 03/14/22
20-1676 Reconstruction 0-001-017 12/14/21 DONE DONE DONE 05/05/21 05/05/21 03/03/21 05/18/21 9,16 100,000 100,000 JLB 0 0 0 SEI Design Group 0 04/29/22 05/05/21
21-1913 Reconstruction 0-001-018 07/21/22 DONE DONE DONE 06/03/22 05/31/22 05/03/22 05/17/22 16 100,000 100,000 JLB 0 0 0 SEI Design Group 0 02/07/23 05/31/22
23-0714 Reconstruction 0-001-019 02/27/24 DONE DONE DONE 10/13/23 10/10/23 10/05/23 05/16/23 2,9,16 100,000 100,000 JJH 0 0 0 SEI Design Group 0 / / 10/10/23
Lawrence Ave. Elementary:
20-0137 Reconstruction 0-002-015 08/21/20 DONE DONE DONE 07/29/20 07/23/20 06/05/20 06/09/20 8 100,000 100,000 JLB 0 0 0 SEI Design Group 0 05/26/21 07/23/20
21-1501 Reconstruction 0-002-016 11/09/22 DONE DONE DONE 03/14/22 03/14/22 03/02/21 02/21/21 2,4,7,8,9,14,155,15, 5,925,000 5,925,000 JLB 0 0 0 SEI Design Group 0 / / 03/14/22
Middle School:
21-1502 Reconstruction 0-005-016 11/09/22 DONE DONE DONE 03/14/22 03/14/22 03/02/21 02/10/21 2,4,7,8,9,155,15,16 7,515,000 7,515,000 JLB 0 0 0 SEI Design Group 0 / / 03/14/22
Special Education Svcs Building:
21-1503 Reconstruction 0-011-005 11/09/22 DONE DONE DONE 03/14/22 03/14/22 03/02/21 02/10/21 8 67,800 67,800 JLB 0 0 0 SEI Design Group 0 / / 03/14/22
Bus Garage:
21-1504 Additions and Alterations 5-004-012 11/09/22 DONE DONE DONE 03/14/22 03/14/22 03/02/21 02/10/21 02 - 16 1,773,000 1,773,000 JLB 0 0 0 SEI Design Group 0 / / 03/14/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
EDWARDS-KNOX CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-31-02-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central Building:
19-0211 Reconstruction 0-004-016 10/11/19 DONE DONE DONE 08/06/19 07/30/19 11/07/18 10/30/18 2,4,8,9,10,13,155,15 4,300,000 4,300,000 JLB 0 0 0 King & King Architects 0 09/04/20 07/30/19
19-0339 Reconstruction 0-004-017 11/27/19 DONE DONE DONE 08/30/19 08/27/19 06/11/19 05/21/19 9,15 100,000 100,000 JLB 0 0 0 King & King Architects 0 05/29/20 08/27/19
20-0380 Reconstruction 0-004-018 12/07/20 DONE DONE DONE 09/16/20 09/11/20 03/10/20 06/09/20 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/25/21 09/11/20
20-1714 Reconstruction 0-004-019 08/10/21 DONE DONE DONE 05/14/21 05/10/21 03/23/21 10/30/18 9,10,155,15,16 1,128,000 1,128,000 JLB 0 0 0 King & King Architects 0 09/01/22 05/10/21
22-0446 Reconstruction 0-004-020 11/14/22 DONE DONE DONE 09/09/22 09/09/22 05/10/22 05/17/22 8,9,10 100,000 100,000 JJH 0 0 0 King & King Architects 0 06/12/23 09/09/22
23-0065 Reconstruction 0-004-021 12/01/23 DONE DONE DONE 07/12/23 07/12/23 01/10/23 12/13/22 2,7,8,9,10,155,15,16 6,102,000 6,102,000 JJH 0 0 0 King & King Architects 0 / / 07/12/23
- Reconstruction 0-004-022 / / / / 04/24/23 / / 4,8,9,10,155,16 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-004-023 / / / / 03/28/24 / / 4 0 0 JJH 0 0 0 0 / / / /
Boiler House - Biomass Renvovations:
23-0159 Reconstruction 0-011-002 09/19/23 DONE DONE DONE 07/28/23 07/28/23 04/24/23 05/16/23 155 100,000 100,000 JJH 0 0 0 King & King Architects 0 01/05/24 07/28/23
Bus Garage:
20-1903 Reconstruction 5-005-005 07/07/21 DONE DONE DONE 06/18/21 06/18/21 04/14/21 05/18/21 9,10,15 100,000 100,000 JLB 0 0 0 King & King Architects 0 04/22/22 06/18/21
23-0066 Reconstruction 5-005-006 12/01/23 DONE DONE DONE 07/12/23 07/12/23 01/10/23 12/13/22 2,15 698,000 698,000 JJH 0 0 0 King & King Architects 0 / / 07/12/23
Fabric Storage Structure:
- PR New Construction 7-012-001 / / / / 09/24/19 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
19-0621 New Construction 7-012-001 11/07/19 DONE DONE DONE 10/28/19 10/03/19 09/24/19 10/30/18 02 - 16 11,000 0 JLB 0 0 0 King & King Architects 0 09/04/20 10/03/19
Concessions&Restroom:
- PR New Construction 7-013-001 / / / / 01/10/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
23-0067 New Construction 7-013-001 12/01/23 DONE DONE DONE 07/12/23 07/12/23 01/10/23 12/13/22 02 - 16 750,000 0 JJH 0 0 0 King & King Architects 0 / / 07/12/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES ST. LAWRENCE-LEWIS STATUS REPORT ON CAPITAL PROJECTS
District No.: 51-90-00-00
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Seaway Tech Center- Main Building:
19-0577 Reconstruction 0-012-011 02/28/20 DONE DONE DONE 10/21/19 10/02/19 / / 10/09/18 2,4,7,8,9,10,155,15, 18,000,932 11,255,295 JSS 0 0 0 March Associates 0 08/31/20 YES 10/02/19
20-0860 Reconstruction 0-012-012 03/02/21 DONE DONE DONE 11/20/20 11/17/20 09/08/20 05/14/20 155,16 540,849 0 JSS 0 0 0 March Associates 540,849 / / 11/17/20
Southwest Technical Ctr.- Main Bldg.:
19-0578 Reconstruction 0-013-011 02/28/20 DONE DONE DONE 10/21/19 10/02/19 11/02/18 10/09/18 2,4,7,8,9,10,155,15, 9,758,709 9,758,709 JSS 0 0 0 March Associates 0 08/31/20 YES 10/02/19
20-0861 Reconstruction 0-013-012 03/02/21 DONE DONE DONE 11/20/20 11/17/20 09/08/20 05/14/20 155,16 368,487 0 JSS 0 0 0 March Associates 368,487 / / 11/17/20
Northwest Technical Ctr.- Main Bldg.:
19-0579 Reconstruction 0-014-008 02/28/20 DONE DONE DONE 10/21/19 10/02/19 11/02/18 10/02/19 2,4,7,8,9,10,155,15, 15,374,285 11,179,521 JSS 0 0 0 March Associates 0 08/31/20 YES 10/02/19
20-0862 Reconstruction 0-014-009 03/02/21 DONE DONE DONE 11/20/20 11/17/20 09/08/20 05/14/20 155,16 491,931 0 JSS 0 0 0 March Associates 491,931 / / 11/17/20
Northwest Tech Child Care Demolition:
19-0580 Reconstruction 0-018-004 02/28/20 DONE DONE DONE 10/21/19 10/02/19 11/02/18 10/09/18 2 53,000 0 JSS 0 0 0 March Associates 0 / / 10/02/19
Seaway Adult Education Demolition:
19-0581 Reconstruction 0-019-004 02/28/20 DONE DONE DONE 10/21/19 10/02/19 11/02/18 10/09/18 2 150,500 0 JSS 0 0 0 March Associates 0 / / 10/02/19
Learning Resource Ctr Demolition:
19-0582 Reconstruction 7-008-003 02/28/20 DONE DONE DONE 10/21/19 10/02/19 11/02/18 10/09/18 2 155,500 0 JSS 0 0 0 March Associates 0 / / 10/02/19
St. Lawrence County IDA (Adult Edu):
23-1562TQ Temporary Quarters 8-048-001 UNREVIEWED 03/01/24 02/16/24 11/17/23 / / 0 0 WLC 0 0 0 0 / / 02/16/24
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED