Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 09/30/14 at 14:23:26




BURNT HILLS BALLSTON LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-01-01-06
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Burnt Hills Senior High:
12-0656   Reconstruction               0-003-017  03/28/13     DONE    DONE       DONE      01/10/13   01/08/13   01/04/13   12/09/09   2,7,8,9                1,687,500     1,687,500  JMB             0           0           0 Mosaic Associates                       0      08/30/13                       03/06/14           
09-0914   Reconstruction               0-003-028  04/26/10     DONE    DONE       DONE      02/19/10   02/16/10   02/01/10   12/09/09   2,8                      150,000       150,000  HCM             0           0           0 Mosaic Associates                       0      11/11/10                         /  /             
10-0029   Reconstruction               0-003-029  01/12/11     DONE    DONE       DONE      07/22/10   07/09/10   05/28/10   12/09/09   2,7,8,155,15,16        2,757,000     2,757,000  HCM             0           0           0 Mosaic Associates                       0      05/16/13                       07/29/13           
13-1102   Reconstruction               0-003-030  06/03/14     DONE    DONE       DONE      01/27/14   01/24/14   11/29/13   10/22/13   2,4,8,16               3,010,000             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
  -       Reconstruction               0-003-031                                              /  /       /  /     08/12/14     /  /     2,4,7,8,9,10,13,14,1           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Stevens Elementary:
09-0825   Reconstruction               0-004-019  03/09/10     DONE    DONE       DONE      01/27/10   01/26/10   10/16/09   03/01/07   8,9                      180,000       180,000  HCM             0           0      20,820 Mosaic Associates                       0      08/31/10                         /  /             
09-0915   Reconstruction               0-004-020  04/26/10     DONE    DONE       DONE      02/19/10   02/16/10   02/01/10   12/09/09   2,8                      330,000       330,000  HCM             0           0           0 Mosaic Associates                       0      11/03/10                         /  /             
10-0030   Reconstruction               0-004-021  01/12/11     DONE    DONE       DONE      07/22/10   07/09/10   05/28/10   12/09/09   2,7,155,15,16          2,305,026     2,305,026  HCM             0           0           0 Mosaic Associates                       0      08/30/13                       03/06/14           
13-1105   Reconstruction               0-004-022  08/13/14     DONE    DONE       DONE      01/27/14   01/24/14   11/29/13   10/22/13   2,8,9,155,15,16        1,107,000             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Pashley Elementary School:
12-0589XX Reconstruction               0-006-008  08/12/13               CANCELLED          12/24/12   12/19/12   12/07/12   12/09/09   2,8,16                    85,500        85,500  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
09-0916   Reconstruction               0-006-017  04/26/10     DONE    DONE       DONE      02/19/10   02/16/10   02/01/10   12/09/09   2,7,8,155,15,16          232,500       232,500  HCM             0           0           0 Mosaic Associates                       0      12/17/10                         /  /             
  -       Reconstruction               0-006-018                                              /  /       /  /     08/12/14     /  /     2,4,7,8,9,10,155,15,           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Charlton Hghts. Elementary:
09-0917   Reconstruction               0-008-016  04/26/10     DONE    DONE       DONE      02/19/10   02/16/10   02/01/10   12/09/09   2,8                       45,000        45,000  HCM             0           0           0 Mosaic Associates                       0      11/04/10                         /  /             
10-0031   Reconstruction               0-008-017  01/12/11     DONE    DONE       DONE      07/22/10   07/09/10   05/28/10   12/09/09   2,7,8,155,15,16        2,826,500     2,826,500  HCM             0           0           0 Mosaic Associates                       0      08/30/13                       03/06/14           
  -       Reconstruction               0-008-018                                              /  /       /  /     08/12/14     /  /     2,4,7,8,9,10,155,15,           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Middle/Jr High School:
12-0590XX Reconstruction               0-010-005  08/12/13               CANCELLED          12/24/12   12/19/12   12/07/12   12/09/09   2,8,16                   144,000       144,000  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
09-0918   Reconstruction               0-010-019  04/26/10     DONE    DONE       DONE      02/19/10   02/16/10   02/01/10   12/09/09   2,7,8,155,15,16        2,302,000     2,302,000  HCM             0           0           0 Mosaic Associates                       0      01/14/11                         /  /             
13-1103   Reconstruction               0-010-020  06/03/14     DONE    DONE       DONE      01/27/14   01/24/14   11/29/13   10/22/13   2,9                      628,000             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             
13-1106XX Additions and Alterations    0-010-021                         CANCELLED          01/27/14   01/24/14   11/29/13   10/22/13   02 - 16                        0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Storage Building:
13-1104   New Construction             2-016-001  06/03/14     DONE    DONE       DONE      01/27/14   01/24/14   12/02/13   10/22/13   02 - 16                  594,000             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Maintenance Storage:
  -    DB Discovered Building          2-017-001                                              /  /       /  /     08/12/14     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
12-0591XX Reconstruction               5-005-004  08/12/13               CANCELLED          12/24/12   12/19/12   12/07/12   12/09/09   2,7,155,16               556,250       556,250  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHENENDEHOWA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-03-02-06
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Arcadia-Gowana-Koda M.Schools:
09-1108   Reconstruction               0-001-026  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   8,9,155,15,16            239,426       239,426  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
12-0213   Reconstruction               0-001-027  03/27/13     DONE    DONE       DONE      09/27/12   09/27/12   05/18/12   05/15/12   8,9,16                   118,500             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
12-0530   Reconstruction               0-001-028  01/03/13     DONE    DONE       DONE      12/11/12   12/10/12   11/13/12   10/24/12   4,8,9,155,15,16          620,000       620,000  DDJ             0           0           0 Mosaic Associates                       0      08/30/13                       03/05/14           
12-0677   Reconstruction               0-001-029  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   2,4,7,13,155,15,16       844,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-001-030                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             
12-0030   Reconstruction               0-001-FP1  07/16/12     DONE    DONE       DONE      07/16/12   07/16/12     /  /       /  /     8                          4,648             0  JOD             0           0           0                                         0      03/31/10                         /  /             

          High School West(fmly Koda):
09-1109   Reconstruction               0-004-021  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   7,8,9,155,15,16          250,393       250,393  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
12-0678   Reconstruction               0-004-022  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   2,4,9,155,16             495,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-004-023                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Skano-Tesago E.S.:
09-1110   Reconstruction               0-006-018  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   8,9,155,15,16             23,770        23,770  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
12-0214   Reconstruction               0-006-019  03/27/13     DONE    DONE       DONE      09/27/12   09/27/12   05/18/12   05/15/12   9,16                      59,300        59,300  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
12-0679   Reconstruction               0-006-020  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   4,9,155,16               410,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-006-021                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Karigon Orenda Elementary:
09-1111   Reconstruction               0-007-015  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   8,9,155,15,16             25,884        25,884  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
12-0215   Reconstruction               0-007-016  03/27/13     DONE    DONE       DONE      09/27/12   09/27/12   05/18/12   05/15/12   9,16                      53,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
12-0680   Reconstruction               0-007-017  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   4,10,155,16              318,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-007-018                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          High School East:
09-1112   Reconstruction               0-008-018  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   8,9,155,15,16            254,463       254,463  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
09-1287   Reconstruction               0-008-019  06/08/10     DONE    DONE       DONE      04/13/10   04/06/10   01/07/10   05/19/09   7,10,16                  286,500             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             
12-0681   Reconstruction               0-008-020  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   2,4,7,8,9,10,14,155,   2,939,480             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
12-1241   Reconstruction               0-008-021  06/06/13     DONE    DONE       DONE      06/04/13   05/31/13   05/14/13   10/02/12   2                      1,037,520             0  JOB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-008-022                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             
12-0029   Reconstruction               0-008-FP1  07/16/12     DONE    DONE       DONE      07/16/12   07/16/12     /  /       /  /     8                         17,158        17,158  JOD             0           0           0                                         0      03/31/10                         /  /             

          Chango Elementary:
  -       Reconstruction               0-010-009                                              /  /       /  /     05/18/12     /  /     4,8,9,16                       0             0  JOD             0           0           0                                         0        /  /                           /  /             
12-0682   Reconstruction               0-010-010  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   7,9,155,16               243,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-010-011                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             
12-0031   Reconstruction               0-010-FP1  07/16/12     DONE    DONE       DONE      07/16/12   07/16/12     /  /       /  /     8                          4,510             0  JOD             0           0           0                                         0      03/31/10                         /  /             

          Okte Elementary:
12-0216   Reconstruction               0-011-010  03/27/13     DONE    DONE       DONE      09/27/12   09/27/12   05/18/12   05/15/12   4,7,9,15,16               39,700        39,700  JOD             0           0           0 Mosaic Associates                       0      08/30/13                       01/10/14           
12-0683   Reconstruction               0-011-011  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   7,155,16                 266,500             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-011-012                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Arongen E.S.(fmly ES #8):
09-1113   Reconstruction               0-031-006  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   7,8,9,155,15,16           47,530        47,530  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
  -       Reconstruction               0-031-007                                              /  /       /  /     05/18/12     /  /     9,16                           0             0  JOD             0           0           0                                         0        /  /                           /  /             
12-0684   Reconstruction               0-031-008  09/05/13     DONE    DONE       DONE      01/16/13   01/14/13   11/13/12   10/02/12   9,155,16                 535,625             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-031-009                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             
12-0032   Reconstruction               0-031-FP1  07/16/12     DONE    DONE       DONE      07/16/12   07/16/12     /  /       /  /     8                         10,640        10,640  JOD             0           0           0                                         0      03/31/10                         /  /             

          District Office:
  -       Reconstruction               1-052-003                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          CSEA Office:
11-0445DB Discovered Building          1-072-001  12/06/11     DONE    DONE       DONE      12/01/11   11/28/11   09/06/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Records Storage:
09-1164TQ Temporary Quarters           2-071-001  04/05/10     DONE    DONE       DONE      03/31/10   02/08/10   03/19/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Seed Storage:
11-0447DB Discovered Building          2-073-001  12/06/11     DONE    DONE       DONE      12/01/11   11/28/11   09/06/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Color Guard Storage:
11-0448DB Discovered Building          2-074-001  12/06/11     DONE    DONE       DONE      12/01/11   11/28/11   09/06/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Tennis Storage:
11-0449DB Discovered Building          2-075-001  12/06/11     DONE    DONE       DONE      12/01/11   11/28/11   09/06/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Baseball Storage:
11-0446DB Discovered Building          2-076-001  12/06/11     DONE    DONE       DONE      12/01/11   11/28/11   09/06/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Baseball Storage Shed #2:
13-0708DB Discovered Building          2-077-001  03/19/14     DONE    DONE       DONE      11/14/13   11/12/13   04/23/13     /  /                                    0             0  JOB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
09-1114   Reconstruction               5-003-010  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10   11/06/09   01/16/07   8,9,155,15,16            272,142       272,142  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
11-1456   Reconstruction               5-003-011  09/04/12     DONE    DONE       DONE      07/03/12   06/28/12   05/18/12   05/15/12   155,16                   191,000             0  JOD             0           0           0 Mosaic Associates                       0        /  /                           /  /             
12-0217   Reconstruction               5-003-012  03/27/13     DONE    DONE       DONE      09/27/12   09/27/12   07/30/12   05/15/12   4,9,155,16               236,000       236,000  DDJ             0           0           0 Mosaic Associates                       0      08/30/13                       01/10/14           
  -       Reconstruction               5-003-013                                              /  /       /  /     09/24/14     /  /     2,10,16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Bus Maintenance Center:
  -       Reconstruction               5-054-002                                              /  /       /  /     11/06/09     /  /     4,7,8,9,155,15,16              0             0  JOD             0           0           0                                         0        /  /                           /  /             

          District Wide Tech.:
09-1115   Reconstruction               7-999-002  09/16/10     DONE    DONE       DONE      03/18/10   03/12/10     /  /     01/16/07   10                       164,239       164,239  JOD             0           0           0 Mosaic Associates                       0      02/24/12                         /  /             
12-0607   Reconstruction               7-999-003  07/23/13     DONE    DONE       DONE      12/26/12   12/20/12   11/13/12   10/02/12   16                     2,608,250     2,608,250  DDJ             0           0           0 Mosaic Associates                       0      06/11/14                       07/09/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CORINTH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-04-01-04
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Oak Street Elem/High School:
  -       Reconstruction               0-001-025                                              /  /       /  /     12/02/10     /  /     2                              0    21,763,480  HCM             0           0           0                                         0        /  /                           /  /             
11-0006   Reconstruction               0-001-026                       ADDENDUM REQ'D       07/07/11   07/06/11   04/14/11     /  /     2                              0    21,763,480  HCM             0           0           0 Professional Service Indusrie           0        /  /                           /  /             
11-1118   Reconstruction               0-001-027  02/13/13     DONE    DONE       DONE      04/12/12   04/11/12   10/07/11   02/13/12   10,155,16              2,509,822     2,509,822  HCM             0           0           0 Guth DeConzo Consutlting, P.C   2,460,422        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-0658   Reconstruction               0-001-028  08/28/13     DONE    DONE       DONE      01/10/13   01/09/13   06/12/12   12/12/12   2,4,7,8,9,10,15,16     3,079,196     2,828,087  HCM             0           0      26,979 Clark Patterson Lee                     0      08/25/14                       09/03/14         YES
                                                                                                                                                                                                                                                                                                                                   
12-1133   Reconstruction               0-001-029  05/24/13     DONE    DONE       DONE      05/14/13   05/14/13   04/26/13   02/27/07   2                        334,500       334,500  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New K-4 Building:
11-1119   Reconstruction               0-015-006  02/13/13     DONE    DONE       DONE      04/12/12   04/11/12   10/07/11   03/13/12   10,155,16                378,503       378,503  HCM             0           0           0 Guth DeConzo Consutlting, P.C     354,098        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-0659   Reconstruction               0-015-007  08/28/13     DONE    DONE       DONE      01/10/13   01/09/13   06/12/12   12/12/12   2,4,7,9,10,15,16         648,000             0  HCM             0           0      20,000 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Center St. Restroom/Storage:
12-0660   New Construction             7-022-001  08/28/13     DONE    DONE       DONE      01/10/13   01/09/13   06/19/12   12/12/12   02 - 16                  164,528             0  HCM             0           0           0 Clark Patterson Lee                     0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EDINBURG COMMON SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-06-01-08
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Common School:
10-0533   Reconstruction               0-001-004  01/14/11     DONE    DONE       DONE      12/06/10   11/22/10   11/20/09   04/13/10   16                        99,000        99,000  HCM             0           0           0 Sacco & Mckinney Architects             0      06/22/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-0546   Reconstruction               0-001-005  07/11/13     DONE    DONE       DONE      12/12/12   12/12/12   06/28/12   09/18/12   7,155                    621,500             0  HCM             0           0           0 Sacco & Mckinney Architects             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New Bus Garage:
12-0547   Reconstruction               5-005-003  07/11/13     DONE    DONE       DONE      12/12/12   12/12/12   06/28/12   05/15/12   7                         78,500             0  HCM             0           0           0 Sacco & Mckinney Architects             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GALWAY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-07-01-04
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Galway K-12 Facility:
10-0184   Reconstruction               0-002-019  02/01/11     DONE    DONE       DONE      08/31/10   08/25/10   01/09/06   02/15/09   2,4,7,8,9,10,155,15,   5,159,500     5,159,500  DDJ             0           0     381,988 Collins & Scoville Architects           0      09/06/11           YES           /  /             

          Storage Trailer @ Bus Garage:
08-0143DB Discovered Building          2-009-001  08/17/10     DONE    DONE       DONE      08/12/08   07/17/08   02/01/08     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Concession Stand:
  -    PR New Construction             7-010-001                                              /  /       /  /     10/27/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MECHANICVILLE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-12-00-05
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School/High School:
09-0893XX Additions and Alterations    0-006-011  06/30/10               CANCELLED          02/12/10   02/09/10   06/09/09   05/20/08   02 - 16                  100,000       100,000  DDJ             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                           /  /             
  -    XX Reconstruction               0-006-012                         CANCELLED            /  /       /  /     08/13/10     /  /     4,8,9,155,16                   0    24,284,652  DDJ             0           0           0                                         0        /  /                           /  /             
10-0791   Additions and Alterations    0-006-013  02/24/11     DONE    DONE       DONE      02/04/11   01/02/11   09/27/10   08/13/09   02 - 16                  572,060       572,060  DDJ             0           0           0 Collins & Scoville Architects           0      11/04/10                         /  /             
  -       Reconstruction               0-006-014                                              /  /       /  /     07/18/12     /  /     2,7,8,10,13,155,15,1           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Shed @ Field:
  -    DB Discovered Building          2-013-001                                              /  /       /  /     09/02/14     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Public Library #2:
  -    PR Additions and Alterations    6-007-003                                              /  /       /  /     06/17/10     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             
11-0171   Additions and Alterations    6-007-003  12/05/11     DONE    DONE       DONE      09/13/11   09/09/11   06/17/10   02/15/11   02 - 16                1,625,000             0  DDJ             0           0           0 Mosaic Associates                       0      09/09/13                       10/28/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BALLSTON SPA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-13-01-06
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ballston Ave. Complex (HS/MS):
09-0997   Reconstruction               0-001-028  03/14/11     DONE    DONE       DONE      03/03/10   02/26/10   01/14/09   05/19/09   9,15,16                  291,800       291,800  HCM             0           0           0 Collins & Scoville Architects           0      10/28/11                       06/26/13           
11-0096   Reconstruction               0-001-029  10/06/11     DONE    DONE       DONE      08/15/11   08/10/11   06/15/11   10/19/10   2,4,7,8,9,155,15,16    5,000,000     5,000,000  HCM             0           0   1,210,000 Collins & Scoville Architects           0        /  /                           /  /             
12-0707   Reconstruction               0-001-030  08/15/13     DONE    DONE       DONE      01/22/13   01/22/13   11/16/11   10/19/10   155                      780,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Malta Avenue School:
09-0578   Reconstruction               0-002-021  05/26/10     DONE    DONE       DONE      12/15/09   12/11/09   01/14/09   05/20/08   9,10,16                  223,000       223,000  HCM             0           0           0 Collins & Scoville Architects           0      03/11/11                       06/26/13           
09-0998   Reconstruction               0-002-022  03/14/11     DONE    DONE       DONE      03/03/10   02/26/10   12/10/09   05/19/09   2,4,10,155,16            572,000       572,000  HCM             0           0           0 Collins & Scoville Architects           0      04/09/12                       06/26/13           
12-0237   Reconstruction               0-002-023  04/19/13     DONE    DONE       DONE      10/02/12   10/02/12   06/15/11   10/19/10   2,4,7,8,9,10,155,15,  11,800,000     9,674,468  HCM             0           0           0 Collins & Scoville Architects           0      08/04/14                       08/01/14           

          Wood Rd Complex (Prim. Middle):
09-0579   Reconstruction               0-006-018  05/26/10     DONE    DONE       DONE      12/15/09   12/11/09   01/14/09   05/20/08   9,10,16                  336,000       336,000  HCM             0           0           0 Collins & Scoville Architects           0      03/11/11                       06/26/13           
09-0999   Reconstruction               0-006-019  03/14/11     DONE    DONE       DONE      03/03/10   02/26/10   12/10/09   05/19/09   155,16                   352,100       352,100  HCM             0           0           0 Collins & Scoville Architects           0      10/06/11                       06/26/13           
12-0094   Reconstruction               0-006-020  01/15/13     DONE    DONE       DONE      08/09/12   07/31/12   06/15/11   10/19/10   2,4,7,8,9,10,155,15,   6,000,000     6,000,000  HCM             0           0     215,085 Collins & Scoville Architects           0        /  /                           /  /             
13-0355   Reconstruction               0-006-021  12/30/13     DONE    DONE       DONE      09/11/13   09/11/13   02/13/13   10/19/10   2,4,7,8,9,155,15,16    8,120,000     8,120,000  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0105   Reconstruction               0-006-022               STARTED STARTED    UNREVIEWED08/06/14   08/05/14   07/22/14   10/19/10   2,8,9,15,16                    0    20,243,828  JMB             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Milton Terrace Primary:
09-0580   Reconstruction               0-009-017  05/26/10     DONE    DONE       DONE      12/15/09   12/11/09   01/14/09   05/20/08   8,9,16                   150,000       150,000  HCM             0           0           0 Collins & Scoville Architects           0      03/11/11                       06/26/13           
09-1000   Reconstruction               0-009-018  03/14/11     DONE    DONE       DONE      03/03/10   02/26/10   12/10/09   05/19/09   155,16                   284,100       284,100  HCM             0           0           0 Collins & Scoville Architects           0      10/06/11                       06/26/13           

          New Elementary School:
11-0255   New Construction             0-024-001  11/30/11     DONE    DONE       DONE      10/12/11   10/11/11   06/15/11   10/19/10   02 - 16               23,957,000             0  HCM             0           0           0 Collins & Scoville Architects           0      07/22/13                       07/30/13           

          Wood Road Storage Building:
  -       New Construction             2-022-001                                              /  /       /  /     01/25/10     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Grounds Shop:
  -       New Construction             2-023-001                                              /  /       /  /     01/25/10     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Utility Building at New School:
11-0394   New Construction             3-025-001  11/30/11     DONE    DONE       DONE      11/16/11   11/16/11   11/03/11   10/19/10   02 - 16                  170,000             0  HCM             0           0           0 Collins & Scoville Architects           0      07/22/13                       07/30/13           

          Facilities & Maintenance Building:
12-0836   New Construction             3-026-001  10/30/13     DONE    DONE       DONE      02/14/13   02/13/13   02/24/12   10/19/10   02 - 16                  399,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          New Bus Garage-Site B:
09-0581   Reconstruction               5-015-004  05/26/10     DONE    DONE       DONE      12/15/09   12/11/09   01/14/09   05/20/09   9,16                     130,000       130,000  HCM             0           0           0 Collins & Scoville Architects           0      03/11/11                       06/26/13           

          Concession Stand:
02-1230DB Discovered Building          7-012-001  10/10/12     DONE    DONE       DONE      01/24/03     /  /     04/05/96     /  /                                    0             0  MAC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH GLENS FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-14-01-04
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
09-0314   Reconstruction               0-001-017  04/12/10     DONE    DONE       DONE      10/20/09   10/16/09   02/02/09   09/21/09   10,155,16                761,981       761,981  JOD             0           0           0 Einhorn Yaffee Prescott P.C.      761,981      08/20/12                       09/21/12           

          Harrison Ave Elementary:
09-0315   Reconstruction               0-002-009  04/12/10     DONE    DONE       DONE      10/20/09   10/16/09   02/02/09   09/21/09   10,155,16                453,977       453,977  JOD             0           0           0 Einhorn Yaffee Prescott P.C.      453,977      08/20/10                       09/21/12           

          Moreau Elementary School:
09-0316   Reconstruction               0-003-012  04/12/10     DONE    DONE       DONE      10/20/09   10/16/09   02/02/09   09/21/09   10,155,16                453,509       453,509  JOD             0           0           0 Einhorn Yaffee Prescott P.C.      453,509      12/14/11                       02/15/13           

          Oliver W. Winch Jr High:
09-0317   Reconstruction               0-007-009  04/12/10     DONE    DONE       DONE      10/20/09   10/16/09   02/02/09   09/21/09   10,155,16                395,941       395,941  JOD             0           0           0 Einhorn Yaffee Prescott P.C.      395,941      12/13/11                       02/15/13           

          Tanglewood School:
09-0318   Reconstruction               0-008-008  04/12/10     DONE    DONE       DONE      10/20/09   10/16/09   02/02/09   09/21/09   10,155                   618,910       618,910  JOD             0           0           0 Einhorn Yaffee Prescott P.C.      618,910      12/14/11                       02/15/13           
12-0868   Reconstruction               0-008-009  04/08/13     DONE    DONE       DONE      02/20/13   02/19/13   02/19/09   12/17/12   10,155                   104,000       104,000  MFS             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0      05/31/13                       11/18/13           

          Ballard Road Elementary:
09-0319   Reconstruction               0-009-007  04/12/10     DONE    DONE       DONE      10/20/09   10/16/09   02/19/09   09/21/09   10,155,16                577,504       577,504  JOD             0           0           0 Einhorn Yaffee Prescott P.C.      577,504      12/14/11                       02/15/13           

          Concession Stand:
12-0124   Additions and Alterations    7-013-002  03/25/13     DONE    DONE       DONE      08/24/12   08/24/12   05/19/11   01/10/11   02 - 16                   16,500             0  JOD             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHUYLERVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-17-01-04
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
09-0824XX Reconstruction               0-001-015                         CANCELLED          01/27/10   01/25/10   11/24/09     /  /     2,8                            0    19,467,228  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             
11-0358   Reconstruction               0-001-016  12/20/11     DONE    DONE       DONE      11/08/11   11/07/11   11/24/09   03/20/07   2,4,7,8,9,155,15,16    1,326,600             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0202   Reconstruction               0-001-017                         UNREVIEWED         08/21/14   08/20/14   02/27/14   06/24/14   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Elementary School K - 6:
11-0359   Reconstruction               0-002-013  12/20/11     DONE    DONE       DONE      11/08/11   11/07/11   11/24/09   03/20/07   2,4,7,8,9,155,15,16      468,600             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0203   Reconstruction               0-002-014                         UNREVIEWED         08/21/14   08/20/14   02/27/14   06/24/14   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Ag Bldg now Admin:
  -       Reconstruction               0-004-002                                              /  /       /  /     05/13/11     /  /     2,8,9,16                       0             0  HCM             0           0           0                                         0        /  /                           /  /             

          New Bus Garage:
11-1256   Reconstruction               5-011-003  07/17/13     DONE    DONE       DONE      05/01/12   04/27/11   09/29/11   05/19/09   13,15,16                  20,000             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0204   Reconstruction               5-011-004                         UNREVIEWED         08/21/14   08/20/14   02/27/14   06/24/14   16                             0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Press Box @ Jr. / Sr. High School:
10-0002   New Construction             7-015-001  07/13/10     DONE    DONE       DONE      07/01/10   07/01/10   04/02/10   03/20/07   02 - 16                  200,000             0  HCM             0           0           0 SEI Design Group                        0      10/08/10                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SARATOGA SPRINGS CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-18-00-01
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Caroline Street Elementary:
13-0518   Reconstruction               0-001-013  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   16                       153,000       153,000  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0121   Reconstruction               0-001-014               DONE    STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   2,4,7,8,9,155,15,16            0     8,425,783  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Maple Ave M.S.(formerly JHS):
13-0519   Reconstruction               0-003-010  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   16                       177,200       177,200  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0122   Reconstruction               0-003-011               DONE    STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   16                             0    46,864,086  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Division Street School:
13-0520   Reconstruction               0-004-012  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   8,9,16                   152,000       152,000  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0123   Reconstruction               0-004-013               DONE    STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   2,4,7,8,9,155,15,16            0     9,063,264  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Lake Avenue Elementary School:
11-0229   Reconstruction               0-005-008  05/26/11     DONE    DONE       DONE      10/03/11   10/03/11   07/14/11   05/26/11   2,4,7,9                  210,000       210,000  HCM             0           0           0 Tetra Tech Engineers, Archite           0      04/18/12                         /  /             
13-0521   Reconstruction               0-005-009  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   8,9,16                   194,200       194,200  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0124   Reconstruction               0-005-010               DONE    STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   2,7,15,16                      0    17,151,545  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Greenfield Center Elementary:
12-0180   Alterations                  0-014-015  03/07/13     DONE    DONE       DONE      09/18/12   09/14/12   08/15/12   08/14/12   02 - 16                  710,000       710,000  JMB             0           0           0 Bonacci Architects                      0      08/30/13                       09/15/14           
13-0522   Reconstruction               0-014-016  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   8,155,16                 262,300       262,300  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0125   Reconstruction               0-014-017               DONE    STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   2,16                           0     7,884,501  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Dorothy Nolan Elementary:
11-1401   Reconstruction               0-015-016  06/21/12     DONE    DONE       DONE      06/12/12   06/12/12   02/15/12   03/27/12   4,7                       96,000        96,000  HCM             0           0           0 Bonacci Architects pllc                 0      10/19/12                       02/06/13           
13-0523   Reconstruction               0-015-017  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   7,8,15,16                584,000       631,100  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0126   Reconstruction               0-015-018               STARTED STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   2,7,15,16                      0             0  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Saratoga Springs High School:
11-1402   Reconstruction               0-016-021  06/21/12     DONE    DONE       DONE      06/12/12   06/12/12   02/15/12   03/27/12   4,7                       77,000        77,000  HCM             0           0           0 Bonacci Architects pllc                 0      10/19/12                       02/06/13           
13-0524   Reconstruction               0-016-022  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   7,8,9,155,16           1,561,200     1,561,200  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0127   Reconstruction               0-016-023               STARTED STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   2,4,7,8,9,10,155,15,           0    56,371,080  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Geyser Road Elementary:
13-0525   Reconstruction               0-017-010  06/18/14     DONE    DONE       DONE      10/11/13   10/11/13   04/05/13   05/21/13   8,9,16                   156,100       156,100  JMB             0           0           0 Bonacci Architects                      0        /  /                           /  /             
14-0128   Reconstruction               0-017-011               UNREVIEWED
                                                                       STARTED    UNREVIEWED08/12/14   08/01/14   05/30/14   05/20/14   16                             0     8,502,420  JMB             0           0           0 Mosaic Associates Architects            0        /  /                           /  /             

          Former Field House:
11-0031DB Discovered Building          2-072-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   05/03/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Storage Shed:
11-0032DB Discovered Building          2-073-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   05/03/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             
11-0033DB Discovered Building          2-074-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   05/03/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Pole Barn:
11-0040DB Discovered Building          2-076-001  08/18/11     DONE    DONE       DONE      07/20/11   07/20/11   06/16/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Cold Storage:
11-0041DB Discovered Building          2-077-001  08/18/11     DONE    DONE       DONE      07/20/11   07/20/11   06/16/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          ONE STORY STORAGE:
11-0043DB Discovered Building          2-079-001  08/18/11     DONE    DONE       DONE      07/20/11   07/20/11   06/16/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0      02/16/12                         /  /             
12-0676   Additions and Alterations    2-079-002  08/05/13     DONE    DONE       DONE      01/16/13   01/11/13   10/26/11     /  /     02 - 16                   98,000             0  HCM             0           0           0                                         0        /  /                           /  /             

          Storage Shed - E Side Rec Area:
11-0035DB Discovered Building          2-082-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   07/12/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Saratoga Springs Public Library:
09-0656   Reconstruction               6-046-003  02/01/10     DONE    DONE       DONE      12/30/09   12/23/09   08/17/09   04/23/09   8,9,155,16               503,022             0  HCM             0           0           0 Butler Rowland Mays Architect           0      08/16/10                         /  /             
10-0161   Additions and Alterations    6-046-004  09/13/10     DONE    DONE       DONE      08/26/10   08/16/10   07/20/10   04/15/10   02 - 16                  258,497             0  HCM             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0      04/30/12                         /  /             
11-0164   Reconstruction               6-046-005  09/26/11     DONE    DONE       DONE      09/07/11   09/07/11   08/19/11   08/14/11   9,10                     380,230             0  HCM             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                           /  /             
12-0074   Reconstruction               6-046-006  09/05/12     DONE    DONE       DONE      08/02/12   07/23/12   06/28/12     /  /     9,10,16                  428,650             0  HCM             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0      02/06/13                       05/09/14           
13-0024   Reconstruction               6-046-007  08/28/13     DONE    DONE       DONE      07/10/13   07/09/13   05/21/13   03/12/13   2,9,10,155,15,16         400,206             0  JMB             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0      02/21/14                       04/17/14           
14-0026   Reconstruction               6-046-008  07/31/14     DONE    DONE       DONE      07/16/14   07/10/14   04/23/14   04/17/14   7                        200,000             0  JMB             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                           /  /             
14-0081   Reconstruction               6-046-009  07/31/14     DONE    DONE       DONE      07/29/14   07/29/14   06/05/14   07/17/14   155                      200,000             0  JMB             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                           /  /             

          East Side Concession Stand:
  -       New Construction             7-070-001                                              /  /       /  /     07/20/10     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Pump House:
11-0030DB Discovered Building          7-071-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   05/03/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             
11-0039DB Discovered Building          7-075-001  08/18/11     DONE    DONE       DONE      07/20/11   07/20/11   05/04/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          TWO STORY CONCESSION:
11-0042DB Discovered Building          7-078-001  08/18/11     DONE    DONE       DONE      07/20/11   07/20/11   06/16/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          CONCESSION STAND:
11-0038DB Discovered Building          7-080-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   06/16/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Concession:
11-0034DB Discovered Building          7-081-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   05/03/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Dugout #1 - E Side Rec Area:
11-0036DB Discovered Building          7-083-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   07/12/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Dugout #2 - E Side Rec Area:
11-0037DB Discovered Building          7-084-001  05/14/12     DONE    DONE       DONE      07/20/11   07/20/11   07/12/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             

          Grandstand - East Side Rec Area:
11-0165DB Discovered Building          7-085-001  02/15/12     DONE    DONE       DONE      09/09/11   09/06/11   08/16/11     /  /                                    0             0  HCM             0           0           0 Bonacci Architects                      0        /  /                           /  /             
  -    PR Additions and Alterations    7-085-002                                              /  /       /  /     05/04/12     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




STILLWATER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-20-01-04
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 6-12:
09-0835   Reconstruction               0-002-010  06/28/10     DONE    DONE       DONE      02/02/10   01/28/10   12/08/09   05/18/10   2,4,7,8,9,10,155,15,      99,938        99,938  DDJ             0           0           0 Griffith Dardanelli,Architect           0      05/03/11                         /  /             
11-0256   Reconstruction               0-002-011  11/14/11     DONE    DONE       DONE      10/12/11   10/11/11   06/29/11   05/17/11   2,9,10,15,16             100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0      04/20/12                       06/23/14           
13-0453   Reconstruction               0-002-012  03/28/14     DONE    DONE       DONE      10/04/13   09/30/13   07/28/11   06/19/12   2,4,7,8,9,10,155,15,     100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
12-1003   Reconstruction               0-002-013  10/10/13     DONE    DONE       DONE      03/21/13   03/18/13     /  /     03/05/13   16                        75,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Elementary School:
13-0460   Reconstruction               0-003-011  02/26/14     DONE    DONE       DONE      10/07/13   10/04/13   12/02/08   05/21/13   15                       100,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
12-1004   Reconstruction               0-003-012  10/10/13     DONE    DONE       DONE      03/21/13   03/18/13   02/14/13   03/05/13   16                        75,000             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             
14-0241   Reconstruction               0-003-013                         UNREVIEWED         09/04/14   09/02/14   08/07/14   08/02/14   4,8,9,10                       0             0  DDJ             0           0           0 Griffith Dardanelli,Architect           0        /  /                           /  /             

          Bus Garage:
12-1005   Reconstruction               5-007-004  10/10/13     DONE    DONE       DONE      03/21/13   03/18/13   02/14/13   03/05/13   16                        50,400             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             

          Press Box:
12-1006   Reconstruction               7-014-002  10/10/13     DONE    DONE       DONE      03/21/13   03/18/13   02/14/13   03/05/13   16                        50,400             0  DDJ             0           0           0 Collins & Scoville Architects           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERFORD - HALFMOON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 52-21-01-03
last updated on 09/30/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-1364   Reconstruction               0-004-021  04/06/10     DONE    DONE       DONE      04/30/10   04/27/10     /  /     04/15/10   2,10,15                  255,014       255,014  DDJ             0           0           0 Mosaic Associates                       0      06/28/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0142   Additions and Alterations    0-004-022  04/15/14     DONE    DONE       DONE      08/06/13   08/05/13   09/19/12   12/12/12   02 - 16                1,554,656             0  DDJ             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0537   Reconstruction               0-004-023  06/12/14     DONE    DONE       DONE      10/16/13   10/10/13   01/22/13   12/12/12   2,4,7,8,9,14,155,15,   8,125,246             0  DDJ             0           0           0 Bernier Carr Associates                 0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED