Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/24/17 at 06:49:38




GILBOA CONESVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-08-01-04
last updated on 07/24/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
15-0317   Reconstruction               0-001-010  08/28/14     DONE    DONE       DONE      08/19/15   08/17/15   06/26/14   06/14/14   4,8                       41,398        41,398  JMB             0           0           0 BCK-IBI Group, a New York Gen           0      07/15/15                       10/16/15           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-09-01-04
last updated on 07/24/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jefferson Central School:
  -       Reconstruction               0-001-010                                              /  /       /  /       /  /       /  /     13,16                          0    10,653,942  DDJ             0           0           0                                         0        /  /                           /  /             
15-1875SB Reconstruction               0-001-010               DONE                           /  /       /  /     06/07/16     /  /     13,16                          0    10,653,942  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-011                                              /  /       /  /     07/19/16     /  /     4                              0    10,653,942  DDJ             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               0-001-BA1                                              /  /       /  /       /  /       /  /     13                             0    10,653,942  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MIDDLEBURGH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-10-01-04
last updated on 07/24/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
14-0071   Reconstruction               0-001-012  08/26/14     DONE    DONE       DONE      07/28/14   07/28/14   03/21/14   05/21/14   4                         73,330        73,330  DDJ             0           0           0 Mosaic Associates                       0      07/07/15                       04/08/16         YES
                                                                                                                                                                                                                                                                                                                                   
16-1743   Reconstruction               0-001-013                         UNREVIEWED         04/28/17   04/27/17   02/23/17   12/14/16   16                             0    11,078,263  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
16-1692   Reconstruction               0-001-014  05/06/17     DONE    DONE       DONE      04/18/17   04/18/17   03/07/17   05/17/16   16                       100,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Elementary School:
15-1584   Reconstruction               0-007-009  06/10/16     DONE    DONE       DONE      04/19/16   04/18/16   02/01/16   05/19/15   8,9                      100,000       100,000  DDJ             0           0           0 Mosaic Associates                       0      04/04/17                       06/05/17         YES
                                                                                                                                                                                                                                                                                                                                   

          Storage Building (fmly Dist Office):
  -    DB Discovered Building          2-011-001                                              /  /       /  /     06/19/17     /  /                                    0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage - Storage Barn:
  -    DB Discovered Building          2-012-001                                              /  /       /  /     06/19/17     /  /                                    0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Concession Stand #2:
  -    DB Discovered Building          7-010-001                                              /  /       /  /     06/19/17     /  /                                    0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COBLESKILL-RICHMONDVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-11-02-06
last updated on 07/24/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building - Radez Elem.:
12-0172   Reconstruction               0-015-013  04/02/12     DONE    DONE       DONE      09/13/12   09/13/12   09/21/11   09/20/11   13,16                     73,000        73,000  HCM             0           0           0 Collins & Scoville Architects           0      10/30/14                       03/24/15           

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             
16-1274   Reconstruction               7-999-001               DONE                           /  /       /  /     01/28/17     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHOHARIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-12-01-04
last updated on 07/24/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
13-1299   Reconstruction               0-001-015  04/18/14     DONE    DONE       DONE      03/05/14   02/28/14   10/23/13   11/20/13   7                         76,095        76,095  MFS             0           0           0 Mosaic Associates                       0      10/31/14                       11/17/14         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-016                                              /  /       /  /     11/14/13     /  /     10,16                          0    25,816,512  MFS             0           0           0                                         0        /  /                           /  /             
14-0923   Reconstruction               0-001-017  03/20/15     DONE    DONE       DONE      01/07/15   12/08/14   04/16/14   05/20/14   2,7,9,10,13,155,16       858,000       858,000  MFS             0           0           0 Mosaic Associates                       0      11/17/15                       12/29/16         YES
                                                                                                                                                                                                                                                                                                                                   
14-0845   Reconstruction               0-001-018  10/26/15     DONE    DONE       DONE      12/29/14   12/19/14   11/24/14   05/20/14   155,16                   187,000       187,000  MFS             0           0           0 Mosaic Associates                       0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-019                                              /  /       /  /     10/20/16     /  /     2,4,7,8,9,14,155,15,           0    25,816,512  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-020                                              /  /       /  /     06/19/17     /  /     2,10,155                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Elementary School:
  -       Reconstruction               0-002-012                                              /  /       /  /     11/14/13     /  /     10,16                          0     7,845,960  MFS             0           0           0                                         0        /  /                           /  /             
14-0924   Reconstruction               0-002-013  03/20/15     DONE    DONE       DONE      01/07/15   12/08/14   06/25/14   05/20/14   2,4,8,9,10,155,15,16      87,831        87,831  MFS             0           0           0 Mosaic Associates                       0      11/17/15                       12/24/15         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-002-014                                              /  /       /  /     10/20/16     /  /     2,4,8,9,14,155,15,16           0     7,845,960  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
12-1295   Reconstruction               5-005-007  11/08/13     DONE    DONE       DONE      06/18/13   06/14/13   07/17/12   05/21/13   10                       376,000       376,000  HCM             0           0           0 Mosaic Associates                       0      03/02/14                       08/12/15         YES
                                                                                                                                                                                                                                                                                                                                   
13-0530   Reconstruction               5-005-008  04/07/14     DONE    DONE       DONE      10/15/13   10/11/13   02/26/13   05/21/13   2,8,9,10,15,16           437,000       437,000  JOB             0           0           0 Mosaic Associates                       0      07/23/14                       08/12/15         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               5-005-009                                              /  /       /  /     11/14/13     /  /     10,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHARON SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-14-01-04
last updated on 07/24/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
15-0565   Reconstruction               0-001-015  08/27/14     DONE    DONE       DONE      10/14/15   10/07/15   09/17/14   08/21/14   4,8,9,10                  73,154        73,154  DDJ             0           0           0                                         0      03/08/16                       06/05/17         YES
                                                                                                                                                                                                                                                                                                                                   
15-0287   Reconstruction               0-001-016  02/05/16     DONE    DONE       DONE      08/18/15   08/18/15   06/23/15   05/19/15   2,4,9,13,16              100,000       100,000  DDJ             0           0           0 Teitsch-Kent                            0      06/20/16                       06/27/16         YES
                                                                                                                                                                                                                                                                                                                                   
15-0729SB Reconstruction               0-001-017                         UNREVIEWED         11/17/15   11/17/15   11/17/15     /  /     10,16                          0    17,117,091  DDJ             0           0           0                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
16-0514   Reconstruction               0-001-017  03/07/17     DONE    DONE       DONE      09/28/16   09/28/16     /  /     11/04/14   10,16                     46,000        46,000  DDJ             0           0           0 Teitsch-Kent                            0        /  /                           /  /             
16-0493   Reconstruction               0-001-018  03/13/17     DONE    DONE       DONE      09/23/16   09/23/16   06/24/16   05/17/16   2,4,7,8,9,10,155,15,     100,000       100,000  DDJ             0           0           0 Teitsch-Kent                            0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-019                                              /  /       /  /     05/19/17     /  /     2,4,7,8,9,10,155,15,           0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED