Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/31/14 at 17:15:52




BABYLON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-01-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior-Senior High School:
12-0078   Reconstruction               0-001-017  08/28/12     DONE    DONE       DONE      08/02/12   07/27/12   05/10/12   06/11/12   9,10,155,15,16           269,014       269,014  HCM             0           0           0 James M. Campbell Architects            0      02/01/13                       02/22/13           
  -       Reconstruction               0-001-018                                              /  /       /  /     06/11/14     /  /     2,4,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Memorial Grade School:
13-0872   Reconstruction               0-002-010                       ADDENDUM REQ'D       12/10/13   12/10/13   07/17/06   08/28/13   2,4,9,155,16                   0    11,763,252  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-002-012                                              /  /       /  /     01/08/14     /  /     2                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-013                                              /  /       /  /     06/11/14     /  /     2,155,16                       0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-014                                              /  /       /  /     06/11/14     /  /     8,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Elementary School:
13-0873   Reconstruction               0-003-012                       ADDENDUM REQ'D       12/12/13   12/10/13   09/10/13   08/28/13   2                              0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1293   Reconstruction               0-003-013  04/30/14     DONE    DONE       DONE      02/26/14   02/25/14   01/08/14   12/10/13   2,7                    1,100,490             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1457   Reconstruction               0-003-014  06/02/14     DONE    DONE       DONE      04/16/14   04/07/14   01/08/14   12/10/13   155                       58,798             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-003-015                                              /  /       /  /     06/11/14     /  /     8,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Container @ Babylon Library:
08-1663DB Discovered Building          2-015-001  07/30/09     DONE    DONE       DONE      06/08/09   05/27/09   05/10/07     /  /                                    0             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Press Box @ Babylon HS Football Stad:
09-0270DB Discovered Building          7-010-001  10/09/09     DONE    DONE       DONE      09/28/09   09/28/09   03/18/04     /  /                                    0             0  MAC             0           0           0 James M. Campbell Architects            0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WEST BABYLON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-02-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
10-0304   Reconstruction               0-001-024  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/23/10   04/27/10   2,155,15,16            1,774,024     1,774,024  JOD             0           0           0 ECG Engineering, LLC            1,774,024        /  /                           /  /             
11-1120   Reconstruction               0-001-025  05/08/12     DONE    DONE       DONE      04/12/12   04/11/12   02/02/12   02/15/07   2,4,7,9,155,16           137,853       137,853  JOD             0           0     137,853 Burton Behrendt Smith                   0      06/07/13                       04/03/14           
  -       Reconstruction               0-001-026                                              /  /       /  /     01/22/14     /  /     2,155,15,16                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Junior High School:
09-1162XX Reconstruction               0-002-021  09/17/10               CANCELLED          03/26/10   03/23/10   03/07/08   04/12/99   2,9,10,16                119,462       119,462  MGL             0           0     119,462 Burton Behrendt Smith                   0        /  /                           /  /             
10-0305   Reconstruction               0-002-022  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/23/10   04/27/10   2,155,15,16            1,089,620     1,089,620  JOD             0           0           0 ECG Engineering, LLC            1,089,620        /  /                           /  /             
14-0018   Reconstruction               0-002-023               DONE    STARTED    STARTED   07/15/14   07/08/14   06/17/14     /  /     2,155,15,16                    0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Forest Avenue School:
10-0306   Reconstruction               0-003-018  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/23/10   04/27/10   2,155,16                 303,308       303,308  JOD             0           0           0 ECG Engineering, LLC              303,308        /  /                           /  /             
11-1098   Reconstruction               0-003-019  04/12/12     DONE    DONE       DONE      04/10/12   04/10/12   02/02/12   02/15/07   4,9,16                   297,000       297,000  JOD             0           0     297,000 Burton Behrendt Smith                   0      01/31/13                       07/29/13           

          Santapogue Elementary School:
09-1163XX Reconstruction               0-005-018  09/17/10               CANCELLED          03/26/10   03/23/10   03/07/08   04/12/99   2,9,15,16                345,465             0  MGL             0           0     345,465 Burton Behrendt Smith                   0        /  /                           /  /             
10-0307   Reconstruction               0-005-019  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/22/10   04/27/10   2,155,16                 456,712       456,712  JOD             0           0           0 ECG Engineering, LLC              456,712        /  /                           /  /             

          South Bay School:
10-0160   Reconstruction               0-006-023  09/08/10     DONE    DONE       DONE      08/26/10   08/23/10   07/22/10   03/02/10   2,4,7,8,9,10,155,15,  16,772,027    13,028,856  JOD             0           0           0 Burton Behrendt Smith                   0      08/05/11                         /  /             

          Tooker Avenue Elementary:
10-0308   Reconstruction               0-007-017  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/22/10   04/27/10   2,155,16                 200,659       200,659  JOD             0           0           0 ECG Engineering, LLC              200,659        /  /                           /  /             

          John F Kennedy Elementary School:
10-0309   Reconstruction               0-008-021  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/22/10   04/27/10   2,155,16                 362,353       362,353  JOD             0           0           0 ECG Engineering, LLC              362,353        /  /                           /  /             

          Bus Garage:
  -       Reconstruction               5-004-011                                              /  /       /  /     07/22/10     /  /     2,155,16                       0             0  JOD             0           0           0                                         0        /  /                           /  /             
10-0310   Reconstruction               5-004-011  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10     /  /     04/27/10                            177,034       177,034                  0           0           0 ECG Engineering, LLC              177,034        /  /                           /  /             

          Drivers Building:
10-0311   Reconstruction               7-009-002  03/28/11     DONE    DONE       DONE      10/04/10   09/24/10   07/22/10     /  /     2,155,16                  41,095             0  JOD             0           0           0 ECG Engineering, LLC               41,095        /  /                           /  /             

          Our Lady of Grace School:
09-0971TQ Temporary Quarters           8-013-001  08/26/10     DONE    DONE       DONE      02/26/10   02/25/10   02/22/10     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH BABYLON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-03-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Transportation Trailer - Bus Lot:
  -    DB Discovered Building          1-028-001                                              /  /       /  /     02/07/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Container - Robert Moses MS:
  -    DB Discovered Building          2-024-001                                              /  /       /  /     02/07/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Container - Marion G. Vedder Elem:
  -    DB Discovered Building          2-025-001                                              /  /       /  /     02/07/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Shed 1 - High School:
  -    DB Discovered Building          2-026-001                                              /  /       /  /     02/07/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Shed 2 - High School:
  -    DB Discovered Building          2-027-001                                              /  /       /  /     02/07/12     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          North Babylon Public Library:
09-1518   Reconstruction               6-005-017  06/29/10     DONE    DONE       DONE      06/14/10   06/11/10   11/06/09   04/17/09   8                        500,000             0  DDJ             0           0           0 William F. Collins                      0        /  /                           /  /             
13-1692   Reconstruction               6-005-018                       ADDENDUM REQ'D       07/02/14   06/26/14   03/14/14   02/18/14   10,16                          0             0  DDJ             0           0           0 Paul Cataldo Architecture & P           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LINDENHURST UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-04-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Kellum School:
10-1021   Reconstruction               0-001-007  09/13/11     DONE    DONE       DONE      03/10/11   03/09/11   10/15/10   10/20/10   2,155,15,16              235,576       235,576  JOD             0           0           0 ECG Engineering, LLC              235,576      02/07/13                       02/13/13           
13-0026   Reconstruction               0-001-008  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                   94,940             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Middle School:
10-1022   Reconstruction               0-002-024  09/12/11     DONE    DONE       DONE      03/10/11   03/09/11   10/15/10   10/20/10   2,155,15,16              645,270       645,270  JOD             0           0           0 ECG Engineering, LLC              645,270      02/07/13                       02/13/13           
11-0156   Reconstruction               0-002-025  09/21/11     DONE    DONE       DONE      09/02/11   09/02/11   06/29/11   05/17/11   4,7,9                    214,710       214,710  JOD             0           0      56,035 John A Grillo-ARCHITECTS PC             0      08/15/12                       03/14/13           
  -       Reconstruction               0-002-026                                              /  /       /  /     03/07/12     /  /     4,7                            0    31,460,594  JOD             0           0           0                                         0        /  /                           /  /             
12-1195   Reconstruction               0-002-027  06/11/13     DONE    DONE       DONE      05/15/13   05/15/13   03/29/13   05/17/11   155                       70,000        70,000  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0027   Reconstruction               0-002-028  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                  158,540             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0792   Reconstruction               0-002-029  12/16/13     DONE    DONE       DONE      11/29/13   11/29/13   10/21/13   11/06/13   4,7                      181,000             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Alleghany Ave. Elementary:
10-1023   Reconstruction               0-004-017  09/13/11     DONE    DONE       DONE      03/10/11   03/09/11   10/15/10   10/20/10   2,155,15,16              222,931       222,931  JOD             0           0           0 ECG Engineering, LLC              222,931      02/07/13                       02/13/13           
13-0028   Reconstruction               0-004-018  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                  222,140             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Edward Bower Elementary:
10-1024   Reconstruction               0-005-018  09/13/11     DONE    DONE       DONE      03/10/11   03/09/11   10/15/10   10/20/10   2,155,15,16              287,589             0  JOD             0           0           0 ECG Engineering, LLC              287,589      02/07/13                       02/13/13           

          Daniel Street Elementary:
10-1025   Reconstruction               0-006-020  09/13/11     DONE    DONE       DONE      03/10/11   03/09/11   10/14/10   10/20/10   2,155,15,16              374,535       374,535  JOD             0           0           0 ECG Engineering, LLC              374,535      02/07/13                       02/13/13           
12-0771   Reconstruction               0-006-021  04/17/13     DONE    DONE       DONE      02/05/13   02/05/13   11/28/12   11/20/12   9                         40,000        40,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      08/15/13                       08/29/13           
13-0029   Reconstruction               0-006-022  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                   94,940             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1326   Reconstruction               0-006-023                         UNREVIEWED         03/11/14   03/11/14   01/28/14     /  /     155                            0    10,853,379  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          William Rall Elementary:
10-1026   Reconstruction               0-007-017  09/13/11     DONE    DONE       DONE      03/11/11   03/09/11   10/15/10   10/20/10   2,155,15,16              231,942       231,942  JOD             0           0           0 ECG Engineering, LLC              231,942      02/07/13                       02/13/13           
13-0030   Reconstruction               0-007-018  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                  158,540             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Senior High School:
09-0266   Reconstruction               0-009-026  10/07/09     DONE    DONE       DONE      09/28/09   09/25/09   05/20/09   05/19/09   2,15                     100,000       100,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      02/04/11                         /  /             
10-1027   Reconstruction               0-009-027  09/13/11     DONE    DONE       DONE      03/11/11   03/09/11   10/15/10   10/20/10   2,155,15,16              959,595       959,595  JOD             0           0           0 ECG Engineering, LLC              959,595      02/07/13                       02/13/13           
10-0601   Reconstruction               0-009-028  04/12/11     DONE    DONE       DONE      12/22/10   12/13/10   10/15/10   11/15/06   4,13,15                   64,900        64,900  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      03/11/11                       08/30/12           
10-1052   Reconstruction               0-009-029  06/04/11     DONE    DONE       DONE      03/15/11   03/10/11   02/10/11   01/15/11   2,4,8,9,155,15,16        485,000       485,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      09/01/12                       08/30/12           
12-1083XX Additions and Alterations    0-009-030                         CANCELLED          04/10/13   04/08/13   11/28/12   05/15/12   02 - 16                        0    53,240,880  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0031   Reconstruction               0-009-031  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                  282,380             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1060   Reconstruction               0-009-032  07/11/14     DONE    DONE       DONE      01/21/14   01/17/14   12/12/13   05/17/13   155                       75,000             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1266   Reconstruction               0-009-033  04/29/14     DONE    DONE       DONE      02/24/14   02/18/14     /  /     02/05/14   13,16                    100,000       100,000  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
14-0050   Reconstruction               0-009-034                         UNREVIEWED         07/25/14   07/16/14   01/28/14   05/20/14   16                             0             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          West Gates Elementary:
09-1428   Reconstruction               0-010-012  06/16/10     DONE    DONE       DONE      05/11/10   05/07/10   05/20/09   11/15/06   2,4,15                    49,560        49,560  JOD             0           0      49,560 John A Grillo-ARCHITECTS PC             0      02/11/11                         /  /             
10-1028   Reconstruction               0-010-013  09/13/11     DONE    DONE       DONE      03/11/11   03/09/11   10/15/10   10/20/10   2,155,15,16              263,544       263,544  JOD             0           0           0 ECG Engineering, LLC              263,544      02/07/13                       02/13/13           

          Harding Elementary School:
10-1029   Reconstruction               0-011-016  09/13/11     DONE    DONE       DONE      03/11/11   03/09/11   10/15/10   10/20/10   2,155,15,16              283,081       283,081  JOD             0           0           0 ECG Engineering, LLC              283,081      02/07/13                       02/13/13           
13-1325   Reconstruction               0-011-017  05/06/14     DONE    DONE       DONE      03/11/14   03/11/14   01/28/14   05/21/13   4,8                      260,000             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Albany Avenue Elementary School:
10-1030   Reconstruction               0-012-016  09/13/11     DONE    DONE       DONE      03/11/11   03/09/11   10/15/10   10/20/10   2,155,15,16              985,427       985,427  JOD             0           0           0 ECG Engineering, LLC              985,427      02/07/13                       02/13/13           
13-0032   Reconstruction               0-012-017  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   05/24/13   05/21/13   2,15,16                   94,940             0  JOB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1061   Reconstruction               0-012-018  07/11/14     DONE    DONE       DONE      01/21/14   01/17/14   12/12/13   05/15/12   155                       65,000             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Niagara Ave. School & Admin.:
10-1031   Reconstruction               0-013-008  09/13/11     DONE    DONE       DONE      03/11/11   03/09/11   10/15/10   10/20/10   2,14,155,15,16           961,736       961,736  JOD             0           0           0 ECG Engineering, LLC              961,736      02/07/13                       02/13/13           
12-0264   Reconstruction               0-013-009  03/15/13     DONE    DONE       DONE      10/11/12   10/09/12   06/08/12   05/15/12   2,16                     302,080             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      03/12/14                       05/19/14           

          MA McKenna (formerly Niagara Admin):
13-0033   Reconstruction               1-013-002  08/22/13     DONE    DONE       DONE      07/16/13   07/10/13   07/17/13   05/21/13                             94,940             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Containter #1:
09-0034DB Discovered Building          2-021-001  02/13/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Masonry Storage Shed (Memorial Shed):
09-0035DB Discovered Building          2-022-001  07/18/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Containter #1:
09-0036DB Discovered Building          2-023-001  02/13/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Container #2:
09-0037DB Discovered Building          2-024-001  02/13/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Container:
09-0038DB Discovered Building          2-025-001  02/13/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Athletic Field Storage Building:
09-0039DB Discovered Building          2-026-001  07/18/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Courtyard Storage Shed #1:
09-0040DB Discovered Building          2-027-001  02/13/13     DONE    DONE       DONE      07/16/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Courtyard Storage Shed #2:
09-0042DB Discovered Building          2-028-001  02/13/13     DONE    DONE       DONE      07/17/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Grounds Department Shop (Storage Bl):
09-0041DB Discovered Building          2-029-001  07/18/13     DONE    DONE       DONE      07/17/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Container #2:
09-0043DB Discovered Building          2-030-001  02/13/13     DONE    DONE       DONE      07/17/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Container #3:
09-0044DB Discovered Building          2-031-001  02/13/13     DONE    DONE       DONE      07/17/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Inter-Modal Shipping Container #4:
09-0045DB Discovered Building          2-032-001  02/13/13     DONE    DONE       DONE      07/17/09   07/09/09   08/14/08     /  /                                    0             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Lindenhurst Memorial Library:
12-0469   Reconstruction               6-003-003  01/10/13     DONE    DONE       DONE      11/20/12   11/20/12   06/29/12   09/22/12   155,16                 1,261,000             0  DDJ             0           0           0 EMTEC Consultants, P.C.                 0        /  /                           /  /             
13-1622   Reconstruction               6-003-004                       ADDENDUM REQ'D       06/18/14   06/16/14   11/21/13   02/19/14   7,8                            0             0  JMB             0           0           0 The Facilities Management Gro           0        /  /                           /  /             
  -       Additions and Alterations    6-003-005                                              /  /       /  /     07/24/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COPIAGUE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-05-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Deauville Gardens Elementary:
  -       Additions and Alterations    0-001-020                                              /  /       /  /     04/04/14     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Great Neck Rd. Elementary:
09-1366   Reconstruction               0-002-018  05/26/10     DONE    DONE       DONE      05/03/10   04/26/10   04/08/10   01/25/07   8                        668,606       668,606  DDJ             0           0     136,663 John A Grillo-ARCHITECTS PC             0      09/20/11                         /  /             
  -       Reconstruction               0-002-019                                              /  /       /  /     04/08/14     /  /     2,4,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Copiague Middle School:
07-2000   Reconstruction               0-004-019  07/13/11     DONE    DONE       DONE      04/21/08   04/11/08     /  /     01/25/07   10,13                    162,875       162,875  DDJ             0           0      52,934 John A Grillo-ARCHITECTS PC             0      09/20/11                         /  /             
  -       Reconstruction               0-004-021                                              /  /       /  /     04/08/10     /  /     9,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-022                                              /  /       /  /     04/04/14     /  /     2,4,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Susan E. Wiley Elementary:
09-1367   Reconstruction               0-005-020  05/26/10     DONE    DONE       DONE      05/03/10   04/26/10   04/08/10   01/25/10   7,8,9,16                 209,981       209,981  DDJ             0           0      68,244 John A Grillo-ARCHITECTS PC             0      03/31/11                         /  /             
  -       Reconstruction               0-005-021                                              /  /       /  /     04/08/14     /  /     2,4,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Walter G. O'Connell High School:
09-1368   Reconstruction               0-006-022  05/26/10     DONE    DONE       DONE      05/03/10   04/26/10   04/08/10   01/25/10   4,8,9,16                 209,306       209,306  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/20/11                         /  /             
  -       Reconstruction               0-006-023                                              /  /       /  /     04/04/14     /  /     2,4,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Public Library:
09-0857   Additions and Alterations    6-007-005  07/16/10     DONE    DONE       DONE      02/04/10   02/01/10   04/23/09   10/27/09   02 - 16                1,865,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
11-0069   Reconstruction               6-007-006  08/05/11     DONE    DONE       DONE      07/26/11   07/26/11   05/19/11   04/26/11   155,15                   100,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      08/15/12                       08/29/12           
12-0005   Reconstruction               6-007-007  08/29/12     DONE    DONE       DONE      07/09/12   07/05/12   05/29/12   04/25/12   9,10,16                  150,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      01/03/13                       01/18/13           
13-1183   Reconstruction               6-007-008  05/13/14     DONE    DONE       DONE      02/06/14   02/03/14   02/06/14   11/20/13   155                      325,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




AMITYVILLE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-06-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Amityville Memorial High School:
13-1177   Reconstruction               0-001-011               DONE    DONE       STARTED   02/06/14   02/03/14   11/27/13   09/04/13   155,15,16                      0             0  MFS             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Northeast Elementary School:
09-1200   Reconstruction               0-003-011  05/11/10     DONE    DONE       DONE      04/01/10   03/29/10   05/03/07   03/16/10   2,4,7,15                 988,000       988,000  MGL             0           0           0 Thornton-Tomasetti,Inc                  0      04/11/12                         /  /             
  -    PR Additions and Alterations    0-003-012                                              /  /       /  /     03/24/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-1178   Reconstruction               0-003-013               DONE    DONE       STARTED   02/06/14   02/03/14   11/27/13   09/04/13   2,155,15,16                    0             0  MFS             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Northwest Elementary School:
09-1201   Reconstruction               0-004-010  04/27/10     DONE    DONE       DONE      04/01/10   03/29/10   05/03/07   03/16/10   2,4,7,15               1,202,000     1,202,000  MGL             0           0           0 Thornton-Tomasetti,Inc                  0      04/11/12                         /  /             
  -    PR Additions and Alterations    0-004-011                                              /  /       /  /     03/25/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-1179   Reconstruction               0-004-012               DONE    DONE       STARTED   02/06/14   02/03/14   11/27/13   09/04/13   2,155,15,16                    0             0  MFS             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Park Avenue Elementary:
  -       Reconstruction               0-005-011                                              /  /       /  /     10/22/13     /  /     2                              0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-1180   Reconstruction               0-005-012               DONE    DONE       STARTED   02/06/14   02/03/14   11/27/13   09/04/13   155,15,16                      0             0  MFS             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Edmund Miles Middle School:
13-1181   Reconstruction               0-008-014               DONE    DONE       STARTED   02/06/14   02/03/14   11/27/13   09/04/13   155,16                         0             0  MFS             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Amityville Public Library:
10-1332   Reconstruction               6-015-005  08/12/11     DONE    DONE       DONE      05/24/11   05/23/11   04/15/11   04/05/11   7,155,15,16              700,000             0  JOD             0           0           0 EMTEC Consultants, P.C.                 0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DEER PARK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-07-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Abraham Lincoln Elementary:
09-1189   Reconstruction               0-001-008  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   11/20/06   11/25/09   8,9                    2,069,195     2,069,195  JOD             0           0           0 John A Grillo-ARCHITECTS PC     2,069,195      05/09/12                         /  /             
13-0260   Reconstruction               0-001-009  12/02/13     DONE    DONE       DONE      08/23/13   08/22/13   06/28/13   05/21/13   2,16                      19,167             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          JF Kennedy Junior High:
09-1190   Reconstruction               0-002-031  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   12/17/09   11/25/09   2,4,7,9,10,155,15,16   3,298,698     3,298,698  JOD             0           0           0 John A Grillo-ARCHITECTS PC     3,298,698      05/09/12                         /  /             
13-0261   Reconstruction               0-002-032  12/02/13     DONE    DONE       DONE      08/23/13   08/22/13   06/28/13   05/21/13   2,16                      19,167             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-002-033                                              /  /       /  /     06/06/14     /  /     2,9                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Memorial Elementary:
09-1191   Reconstruction               0-003-007  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   12/17/09   11/25/09   15,16                    113,443       113,443  JOD             0           0           0 John A Grillo-ARCHITECTS PC       113,443      05/09/12                         /  /             

          May Moore Elementary School:
09-1192   Reconstruction               0-004-031  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   12/17/09   11/25/09   2,8,155,15,16          1,681,055     1,681,055  JOD             0           0           0 John A Grillo-ARCHITECTS PC     1,681,055      05/09/12                         /  /             
13-0262   Reconstruction               0-004-032  12/02/13     DONE    DONE       DONE      08/23/13   08/22/13   06/28/13   05/21/13   2,16                      88,167             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          G. Washington School:
09-1193   Reconstruction               0-005-009  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   12/17/09   11/25/09   2,155,15,16              404,273       404,273  JOD             0           0           0 John A Grillo-ARCHITECTS PC       404,273      05/09/12                         /  /             

          Senior High School:
09-1194   Reconstruction               0-006-046  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10     /  /     11/25/09                          1,412,009     1,412,009  JOD             0           0           0 John A Grillo-ARCHITECTS PC     1,412,009      05/09/12                         /  /             
10-0589   Reconstruction               0-006-047  06/16/11     DONE    DONE       DONE      12/21/10   12/10/10   11/22/10   05/17/11   2,15                     118,000       118,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      09/19/11                         /  /             
10-1396   Reconstruction               0-006-048  07/28/11     DONE    DONE       DONE      06/15/11   06/10/11   05/26/11   05/11/11   2,4,13                   500,000       500,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/27/13                       02/03/14           
11-1446   Reconstruction               0-006-049  07/12/12     DONE    DONE       DONE      06/29/12   06/21/12   05/29/12   05/12/12   7                        279,400             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/27/13                       09/19/13           
12-1230   Reconstruction               0-006-050  07/25/13     DONE    DONE       DONE      05/23/13   05/23/13   03/08/13   05/21/13   2,4                      200,000       200,000  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0      08/27/13                       11/14/13           
13-0263   Reconstruction               0-006-051  12/02/13     DONE    DONE       DONE      08/23/13   08/22/13   06/28/13   05/21/13   2,16                     242,686             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-006-052                                              /  /       /  /     06/06/14     /  /     15                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          John Q. Adams Elementary:
09-1195   Reconstruction               0-007-023  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   12/17/09   11/25/09   2,8,14,155,15            521,244       521,244  JOD             0           0           0 John A Grillo-ARCHITECTS PC       521,244      05/09/12                         /  /             
13-0264   Reconstruction               0-007-024  12/02/13     DONE    DONE       DONE      08/23/13   08/22/13   06/28/13   05/21/13   2,16                      88,167             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-007-025                                              /  /       /  /     06/06/14     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Robert Frost Junior High:
09-1196   Reconstruction               0-008-029  12/22/10     DONE    DONE       DONE      04/01/10   03/25/10   12/17/09   11/25/09   2,155,15,16              802,629       802,629  JOD             0           0           0 John A Grillo-ARCHITECTS PC       802,629      05/09/12                         /  /             
13-0265   Reconstruction               0-008-030  12/02/13     DONE    DONE       DONE      08/23/13   08/22/13   06/28/13   05/21/13   2,16                      19,167        19,167  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-008-031                                              /  /       /  /     06/06/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Annex Office Buildin:
12-0093   Reconstruction               1-009-003  10/31/12     DONE    DONE       DONE      08/09/12   07/26/12   10/05/12   05/15/12                             53,100             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Trans Annex(Fuel-Buses only):
09-1228   Reconstruction               5-017-002  05/28/10     DONE    DONE       DONE      04/05/10   03/31/10   03/26/10   05/20/08   2,13,15                  135,000       135,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      09/19/11                         /  /             
  -    XX Reconstruction               5-017-003                         CANCELLED          08/09/12   07/26/12   08/07/12     /  /     7                              0             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Deer Park Public Library:
10-0088   Reconstruction               6-010-004  08/24/10     DONE    DONE       DONE      08/05/10   07/30/10   03/25/10     /  /     2,8                      500,000             0  JOD             0           0           0 William F. Collins                      0        /  /                           /  /             

          Press Box:
10-1397   New Construction             7-014-001  07/28/11     DONE    DONE       DONE      06/15/11   06/10/11   05/30/96   05/11/11   02 - 16                  137,349             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      09/13/11                       05/18/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WYANDANCH UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-01-09-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          ML King ES/LaFrancis Hardiman/Admin.:
10-1182   Reconstruction               0-002-024  04/13/11     DONE    DONE       DONE      04/12/11   04/08/11   11/18/10   08/25/10   7                        225,000       225,000  DDJ             0           0           0 Tetra  Tech Architects & Engi           0      12/06/12                       01/17/13           
  -    PR Additions and Alterations    0-002-025                                              /  /       /  /     02/08/11     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             
11-0827   Reconstruction               0-002-026  05/11/12     DONE    DONE       DONE      02/22/12   02/21/12   01/25/12   01/12/12   7                      1,061,572     1,789,165  DDJ             0           0           0 Tetra  Tech Architects & Engi           0      12/21/12                       01/17/13           
12-0070   Reconstruction               0-002-027  10/19/12     DONE    DONE       DONE      08/01/12   07/26/12   03/15/12   01/10/12   2,4,155,15,16          1,516,330             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0164   Reconstruction               0-002-028  10/11/12     DONE    DONE       DONE      09/13/12   09/04/12   06/29/12   01/10/12   8                      3,145,000             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
13-0833   Reconstruction               0-002-029  06/12/14     DONE    DONE       DONE      12/04/13   12/04/13   11/21/13   01/10/12   8,9                       45,210             0  MFS             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Wyandanch Memorial High School:
09-0582   Reconstruction               0-004-018  12/23/09     DONE    DONE       DONE      12/17/09   12/14/09   11/09/09   12/17/09   7                        725,000       725,000  DDJ             0           0       9,555 Tetra  Tech Architects & Engi           0      12/06/12                       01/17/12           
  -       Additions and Alterations    0-004-019                                              /  /       /  /     11/18/10     /  /     02 - 16                        0    16,451,700  DDJ             0           0           0                                         0        /  /                           /  /             
11-0829   Reconstruction               0-004-020  05/11/12     DONE    DONE       DONE      02/22/12   02/21/12   01/25/12   01/10/12   7,9,10                   645,895     1,127,925  DDJ             0           0           0 Tetra  Tech Architects & Engi           0      12/21/12                       01/17/13           
12-0071   Reconstruction               0-004-021  10/19/12     DONE    DONE       DONE      08/01/12   07/26/12   06/29/12   01/10/12   8,10                   4,812,626             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0165   Reconstruction               0-004-022  10/11/12     DONE    DONE       DONE      09/14/12   09/14/12     /  /     01/10/12   8                      2,096,150             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
13-0834   Reconstruction               0-004-023  06/12/14     DONE    DONE       DONE      12/04/13   12/04/13   09/04/13   01/10/12   2,4,7,8,9,155,15,16    1,637,440             0  MFS             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Olive Middle School:
11-0828   Reconstruction               0-005-019  05/11/12     DONE    DONE       DONE      02/22/12   02/21/12   01/25/12   01/10/12   7,9                      398,938       799,475  DDJ             0           0           0 Tetra  Tech Architects & Engi           0      12/21/12                       01/17/13           
12-0072   Reconstruction               0-005-020  10/19/12     DONE    DONE       DONE      08/01/12   07/26/12   03/15/12   01/10/12   2,4,9,155,15,16        2,567,169             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0166   Reconstruction               0-005-021  10/11/12     DONE    DONE       DONE      09/13/12   09/04/12   06/29/12   01/10/12   8                      2,068,000             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
13-0835   Reconstruction               0-005-022  06/12/14     DONE    DONE       DONE      12/04/13   12/04/13   09/04/13   01/10/12   2,4,7,8,9,155,15,16      307,350             0  MFS             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Wyandanch Hoigh School:
  -    PR New Construction             0-010-001                                              /  /       /  /     11/16/10     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
11-0830   Reconstruction               5-007-007  05/11/12     DONE    DONE       DONE      02/22/12   02/21/12   01/25/12   01/10/12   7                        161,520       133,435  DDJ             0           0           0 Tetra  Tech Architects & Engi           0      12/21/12                       01/17/13           
12-0073   Reconstruction               5-007-008  10/19/12     DONE    DONE       DONE      08/01/12   07/26/12   06/06/12   01/10/12   2,9,155,15,16            221,000             0  DDJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
12-0167   Reconstruction               5-007-009  10/11/12     DONE    DONE       DONE      09/13/12   09/04/12   06/29/12   01/10/12   8                         90,850             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Wyandanch Public Library:
12-0163   Additions and Alterations    6-008-004  08/09/13     DONE    DONE       DONE      09/10/12   09/04/12   12/08/11   07/15/09   02 - 16                  965,000             0  DDJ             0           0           0 ACGA ARCHITECTS                         0        /  /                           /  /             

          District Wide:
13-0877   Reconstruction               7-999-003  04/09/14     DONE    DONE       DONE      12/12/13   12/09/13   09/04/13   01/10/12   13,16                  1,390,000             0  MFS             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




THREE VILLAGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-01-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Setauket Elementary School:
10-0757   Reconstruction               0-001-031  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     160,000       160,000  DDJ             0           0      28,800 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
11-1418   Reconstruction               0-001-032  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                       90,000        90,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
12-1024   Reconstruction               0-001-033  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   03/23/12   11/10/09   16                       185,450       185,450  DDJ             0           0      32,453 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0739   Reconstruction               0-001-034               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-001-035                                              /  /       /  /     06/18/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Nassakeag Elementary School:
10-0758   Reconstruction               0-002-024  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     160,000       160,000  DDJ             0           0      28,800 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
11-1419   Reconstruction               0-002-025  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                       70,000        70,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
12-1025   Reconstruction               0-002-026  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   03/23/12   11/10/09   16                       185,850       185,850  DDJ             0           0      32,524 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0740   Reconstruction               0-002-027               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1379   Reconstruction               0-002-028  05/06/14     DONE    DONE       DONE      03/19/14   03/18/14   02/07/14   02/04/14   2,4,8,9,10               324,900             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-002-029                                              /  /       /  /     06/18/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Mount Elementary School:
10-0759   Reconstruction               0-006-023  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     160,000       160,000  DDJ             0           0      28,800 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
  -       Reconstruction               0-006-024                                              /  /       /  /     03/08/12     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
11-1420   Reconstruction               0-006-025  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                       70,000        70,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
12-1026   Reconstruction               0-006-026  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   03/23/12   11/10/09   16                       154,250       154,250  DDJ             0           0      26,993 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0741   Reconstruction               0-006-027               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-006-028                                              /  /       /  /     06/18/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Arrowhead Lane Elementary:
10-0760   Reconstruction               0-007-023  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     160,000       160,000  DDJ             0           0      28,800 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
11-1421   Reconstruction               0-007-024  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                      140,000       140,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
12-1027   Reconstruction               0-007-025  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   03/23/12   11/10/09   16                       202,550       202,550  DDJ             0           0      35,446 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0742   Reconstruction               0-007-026               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1013   Reconstruction               0-007-027  04/04/14     DONE    DONE       DONE      01/13/14   01/13/14   12/12/13   05/17/05   4                         21,128             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
14-0051   Reconstruction               0-007-028                         UNREVIEWED         07/25/14   07/16/14   04/18/14   02/04/14   2,4,8,9,10,155,15,16           0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Paul J Gelinas Junior High:
09-0653   Reconstruction               0-008-028  01/15/10     DONE    DONE       DONE      12/30/09   12/23/09   07/22/09   11/10/09   7                      2,265,120     2,265,120  DDJ             0           0     407,722 John A Grillo-ARCHITECTS PC             0      05/09/11                         /  /             
10-0761   Reconstruction               0-008-029  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     350,000       350,000  DDJ             0           0      63,000 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
12-1028   Reconstruction               0-008-030  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   01/12/12   11/10/09   16                       190,850       190,850  DDJ             0           0      33,397 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
11-1422   Reconstruction               0-008-031  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                       85,000        85,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
13-0743   Reconstruction               0-008-032               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0    28,514,836  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1009   Reconstruction               0-008-033  06/04/14     DONE    DONE       DONE      01/13/14   01/13/14   12/12/13   10/18/94   9,15                      47,027             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1008   Reconstruction               0-008-034  04/29/14     DONE    DONE       DONE      01/13/14   01/13/14   12/12/13   02/03/99   16                        61,278             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1301   Reconstruction               0-008-035  04/22/14     DONE    DONE       DONE      03/05/14   03/03/14   02/07/14   02/04/14   2,4,9,10               1,201,348             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
14-0052   Reconstruction               0-008-036                         UNREVIEWED         07/25/14   07/16/14   05/02/14   02/04/14   2,4,8,9,10,155,15,16           0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-008-037                                              /  /       /  /     07/31/14     /  /     14                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Ward Melville Senior High:
09-0654   Reconstruction               0-009-033  01/15/10     DONE    DONE       DONE      12/30/09   12/23/09   07/28/09   11/10/09   7                      3,346,200     3,346,200  DDJ             0           0     602,316 John A Grillo-ARCHITECTS PC             0      05/09/11                         /  /             
10-0762   Reconstruction               0-009-034  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     700,000       700,000  DDJ             0           0     126,000 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
12-1029   Reconstruction               0-009-035  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   01/11/12   11/10/09   16                       295,050       295,050  DDJ             0           0      36,384 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0744   Reconstruction               0-009-036               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1010   Reconstruction               0-009-037  06/04/14     DONE    DONE       DONE      01/13/14   01/13/14   12/12/13   02/03/99   16                        47,027             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1302   Reconstruction               0-009-038  04/22/14     DONE    DONE       DONE      03/05/14   03/03/14   02/07/14   02/04/14   2,4,10                 1,031,220             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
14-0053   Reconstruction               0-009-039                         UNREVIEWED         07/25/14   07/16/14   02/25/14   02/04/14   2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Minnesauke Elementary:
10-0763   Reconstruction               0-014-022  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     160,000       160,000  DDJ             0           0      28,800 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
11-1423   Reconstruction               0-014-023  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                      100,000       100,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
12-1030   Reconstruction               0-014-024  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   03/23/12   11/10/09   16                       133,050       133,050  DDJ             0           0      23,283 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0745   Reconstruction               0-014-025               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1014   Reconstruction               0-014-026  04/04/14     DONE    DONE       DONE      01/13/14   01/13/14   12/12/13   05/18/99   2,4,7                    149,854             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1380   Reconstruction               0-014-027  05/06/14     DONE    DONE       DONE      03/19/14   03/18/14   02/07/14   02/04/14   2,8,9,10                 255,100             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-014-028                                              /  /       /  /     06/18/14     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Murphy Jr. High School:
09-0655   Reconstruction               0-015-026  01/15/10     DONE    DONE       DONE      12/30/09   12/23/09   07/22/09   11/10/09   7                      2,265,120     2,265,120  DDJ             0           0     407,722 John A Grillo-ARCHITECTS PC             0      05/09/11                         /  /             
10-0764   Reconstruction               0-015-027  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     350,000       350,000  DDJ             0           0      63,000 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
12-1031   Reconstruction               0-015-028  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   01/12/12   11/10/09   16                       204,650       204,650  DDJ             0           0      35,813 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
11-1424   Reconstruction               0-015-029  08/03/12     DONE    DONE       DONE      06/21/12   06/18/12   03/20/12   05/15/12   155                       85,000        85,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
13-0746   Reconstruction               0-015-030               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0    28,256,484  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1011   Reconstruction               0-015-031  06/04/14     DONE    DONE       DONE      01/13/14   01/13/14   12/12/13   02/03/99   16                        47,027             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1303   Reconstruction               0-015-032  04/22/14     DONE    DONE       DONE      03/05/14   03/03/14   02/07/14   02/04/14   2,4,9,10                 867,620             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1522   Reconstruction               0-015-033  06/11/14     DONE    DONE       DONE      05/14/14   05/06/14   04/02/14   04/09/14   14                        55,750             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
14-0054   Reconstruction               0-015-034                         UNREVIEWED         07/25/14   07/16/14   05/02/14   02/04/14   2,4,7,8,9,10,155,15,           0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          North Country Learning Ctr.:
10-0765   Reconstruction               0-018-015  05/19/11     DONE    DONE       DONE      01/28/11   01/14/11   05/19/10   11/10/09   8,16                     159,685       159,685  DDJ             0           0      28,743 John A Grillo-ARCHITECTS PC             0      05/14/12                         /  /             
12-1032   Reconstruction               0-018-016  07/01/13     DONE    DONE       DONE      03/27/13   03/27/13   12/05/11   11/10/09   2,16                     111,250       111,250  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
11-1425   Reconstruction               0-018-017  08/03/12     DONE    DONE       DONE      07/05/12   06/18/12   03/20/12   05/15/12   155                      140,000       140,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/12/14                       05/30/14           
12-1130   Reconstruction               0-018-018  05/22/13     DONE    DONE       DONE      04/25/13   04/19/13   02/26/13   02/28/13   7                        283,376       283,376  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      08/30/13                       09/13/13           
13-0747   Reconstruction               0-018-019               DONE    DONE       ADD. REQ'D11/22/13   11/20/13   04/16/13   06/25/13   155,15,16                      0     1,201,260  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container @ Arrowhead ES:
09-1049   Reconstruction               2-033-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/22/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container @ Minnesauke ES:
09-1050   Reconstruction               2-034-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/22/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container @ Minnesauke ES:
09-1051   Reconstruction               2-035-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #1 @ PJ Gelinas:
09-1052   Reconstruction               2-036-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #2 @ PJ Gelinas:
09-1053   Reconstruction               2-037-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #3 @ PJ Gelinas:
09-1054   Reconstruction               2-038-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #4 @ PJ Gelinas:
09-1055   Reconstruction               2-039-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #1 @ Murphy Jr HS:
09-1056   Reconstruction               2-040-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #2 @ Murphy Jr HS:
09-1057   Reconstruction               2-041-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #1 @ Murphy Jr HS:
09-1058   Reconstruction               2-042-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #2 @ Murphy Jr HS:
09-1059   Reconstruction               2-043-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #1 @ Ward Melville HS:
09-1060   Reconstruction               2-044-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #2 @ Ward Melville HS:
09-1061   Reconstruction               2-045-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #1 @ Ward Melville HS:
09-1062   Reconstruction               2-046-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #2 @ Ward Melville HS:
09-1063   Reconstruction               2-047-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #3 @ Ward Melville HS:
09-1064   Reconstruction               2-048-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #3 @ Ward Melville HS:
09-1065   Reconstruction               2-049-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #4 @ Ward Melville HS:
09-1066   Reconstruction               2-050-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #5 @ Ward Melville HS:
09-1067   Reconstruction               2-051-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          40' Container #6 @ Ward Melville HS:
09-1068   Reconstruction               2-052-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #4 @ Ward Melville HS:
09-1069   Reconstruction               2-053-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #5 @ Ward Melville HS:
09-1070   Reconstruction               2-054-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #6 @ Ward Melville HS:
09-1071   Reconstruction               2-055-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/23/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #7 @ Ward Melville HS:
09-1072   Reconstruction               2-056-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/24/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #8 @ Ward Melville HS:
09-1073   Reconstruction               2-057-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/24/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #9 @ Ward Melville HS:
09-1074   Reconstruction               2-058-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/24/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          20' Container #10 @ Ward Melville HS:
09-1075   Reconstruction               2-059-001  05/11/10     DONE    DONE       DONE      03/10/10   03/09/10   02/24/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Container #1 @ NC Admin Cntr:
09-1520   Reconstruction               2-060-001  06/20/11     DONE    DONE       DONE      06/14/10   06/01/10   04/30/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Container #2 @ NC Admin Cntr:
09-1521   Reconstruction               2-061-001  06/20/11     DONE    DONE       DONE      06/14/10   06/01/10   04/30/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Container #3 @ NC Admin Cntr:
09-1522   Reconstruction               2-062-001               UNREVIEWED
                                                                       DONE       DONE      06/14/10   06/01/10   04/30/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Container #4 @ NC Admin Cntr:
09-1523   Reconstruction               2-063-001               UNREVIEWED
                                                                       DONE       DONE      06/14/10   06/01/10   05/26/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Baseball Concession Stand (Storage):
09-1563DB Discovered Building          2-064-001                       ADDENDUM REQ'D       06/21/10   06/14/10   05/18/10     /  /                                    0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Container #1 @ North Country:
  -       Reconstruction               2-065-001                                              /  /       /  /     06/23/11     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          20' Container #11 @ Ward Melville HS:
13-1318DB Discovered Building          2-069-001                       ADDENDUM REQ'D       03/10/14   03/07/14   01/23/14     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          20' Container #12 @ Ward Melville HS:
13-1319DB Discovered Building          2-070-001                       ADDENDUM REQ'D       03/10/14   03/07/14   01/23/14     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Maintenance Building:
14-0025   New Construction             3-071-001                         UNREVIEWED         07/16/14   07/10/14   03/12/14   02/04/14   02 - 16                        0             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BROOKHAVEN-COMSEWOGUE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-03-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Terryville Elementary:
09-0614   Reconstruction               0-002-015  01/06/10     DONE    DONE       DONE      12/23/09   12/18/09   10/08/09   05/19/09   7                        117,405       117,405  DDJ             0           0           0 Burton Behrendt Smith                   0      05/16/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0902   Reconstruction               0-002-016  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,8,155,15,16          441,814             0  JOD             0           0           0 Burton Behrendt Smith             441,814        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -    PR Additions and Alterations    0-002-017                                              /  /       /  /     03/21/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          John F Kennedy Jr. Middle:
12-1194   Reconstruction               0-003-007  07/16/13     DONE    DONE       DONE      05/15/13   05/15/13   12/11/12   06/19/12   2,9,16                   275,000       275,000  DDJ             0           0           0 Burton Behrendt Smith                   0      03/27/14                       04/18/14         YES
                                                                                                                                                                                                                                                                                                                                   
11-0903   Reconstruction               0-003-013  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,8,15,16              599,505             0  JOD             0           0           0 Burton Behrendt Smith             599,505        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Norwood Avenue Elem. School:
11-0904   Reconstruction               0-004-010  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,8,155,15,16          529,530             0  JOD             0           0           0 Burton Behrendt Smith             529,530        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-1208   Reconstruction               0-004-011  05/17/12     DONE    DONE       DONE      04/25/12   04/20/12   03/01/12   05/17/11   155,16                   100,000       100,000  JOD             0           0           0 Burton Behrendt Smith                   0      07/22/13                       04/24/14         YES
                                                                                                                                                                                                                                                                                                                                   
13-1182   Reconstruction               0-004-012  04/14/14     DONE    DONE       DONE      02/06/14   02/03/14   08/27/13   05/21/13   2,4,8,9,15               365,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Boyle Road Elementary:
11-0905   Reconstruction               0-005-011  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,7,8,155,15,16        334,796             0  JOD             0           0           0 Burton Behrendt Smith             334,796        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-1143   Reconstruction               0-005-012  07/10/13     DONE    DONE       DONE      05/01/13   04/29/13   02/01/13   05/17/11   2,4,8,155,15,16           81,500        81,500  MFS             0           0           0 Burton Behrendt Smith                   0      06/25/14                       07/03/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Comsewogue Senior High School:
10-1011   Reconstruction               0-010-016  05/31/11     DONE    DONE       DONE      03/09/11   03/07/11   12/28/10   05/18/10   2,10,16                  125,000       125,000  JOD             0           0           0 Burton Behrendt Smith                   0      04/05/12                       01/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0906   Reconstruction               0-010-017  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,8,155,15,16        1,163,179             0  JOD             0           0           0 Burton Behrendt Smith           1,163,179        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-010-018                                              /  /       /  /     08/27/13     /  /     2,4,155,15,16                  0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-010-019                                              /  /       /  /     07/22/14     /  /     2,8,9,155,15,16                0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Clinton Avenue ES:
11-0907   Reconstruction               0-011-009  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,8,155,15,16          274,580             0  JOD             0           0           0 Burton Behrendt Smith             274,580        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Administration Bldg.:
11-0908   Reconstruction               1-001-001  03/01/13     DONE    DONE       DONE      03/06/12   03/06/12   03/25/11   02/07/11   2,4,7,8,155,15,16        241,523             0  JOD             0           0           0 Burton Behrendt Smith             241,523        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Comsewogue Public Library:
11-0072   Reconstruction               6-009-001  08/08/11     DONE    DONE       DONE      07/28/11   07/28/11   04/13/11   06/21/11   4                         68,000             0  JOD             0           0           0 BEATTY HARVEY COCO                      0      06/11/14                       07/02/14           
  -       Reconstruction               6-009-002                                              /  /       /  /     04/10/12     /  /     4                              0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SACHEM CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-05-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sachem HS Union Campus(frmnly admin:
08-1552   Reconstruction               0-001-005  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16               97,527             0  DDJ             0           0           0 ECG Engineering, LLC               97,527      06/12/13                       07/25/13           

          Lynwood Avenue School:
09-0773   Reconstruction               0-002-015  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,8,155,15,16          1,123,660     1,123,660  DDJ             0           0     258,724 John A Grillo-ARCHITECTS PC             0      03/22/12                       05/04/12           
08-1553   Reconstruction               0-002-016  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              499,691       499,691  DDJ             0           0           0 ECG Engineering, LLC              499,691      06/12/13                       07/25/13           
11-0681XX Reconstruction               0-002-017  05/16/12               CANCELLED          01/18/12   01/18/12   06/28/11   05/17/11   155,16                    42,857        42,857  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Waverly Ave. Elementary:
09-0774   Reconstruction               0-003-016  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 178,480       178,480  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       11/14/11           
08-1554   Reconstruction               0-003-017  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/13/09   12/03/08   2,155,15,16              515,408       515,408  DDJ             0           0           0 ECG Engineering, LLC              515,408      06/12/13                       07/25/13           
  -       Reconstruction               0-003-018                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Nokomis School:
09-0775   Reconstruction               0-004-013  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                  99,732        99,732  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       12/12/11           
08-1555   Reconstruction               0-004-014  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              393,731       393,731  DDJ             0           0           0 ECG Engineering, LLC              393,731      06/12/13                       07/25/13           
11-0682   Reconstruction               0-004-015  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   2,9,155,16               155,607       155,607  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      01/07/13                       10/04/13           

          Grundy Avenue Elementary:
09-0776   Reconstruction               0-006-012  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10     /  /     03/18/08   2,9,155,16               341,760       341,760  DDJ             0           0      77,866 John A Grillo-ARCHITECTS PC             0      11/30/11                       01/30/12           
08-1556   Reconstruction               0-006-013  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              954,816       954,816  DDJ             0           0           0 ECG Engineering, LLC              954,816      06/12/13                       07/25/13           
  -       Reconstruction               0-006-014                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Gatelot Ave. School:
09-0777   Reconstruction               0-007-014  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,8,9,155,16           1,367,004     1,367,004  DDJ             0           0     317,136 John A Grillo-ARCHITECTS PC             0      03/22/12                       05/04/12           
08-1557   Reconstruction               0-007-015  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16            1,654,535     1,654,535  DDJ             0           0           0 ECG Engineering, LLC            1,654,535      06/12/13                       07/25/13           
11-0683   Reconstruction               0-007-016  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   2,9,155,16               127,249       127,249  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/13/13                       10/28/13           

          Samoset M.S.(fmly  HS South):
09-0778   Reconstruction               0-008-023  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,8,9,155,15,16        3,625,947     3,625,947  DDJ             0           0     726,640 John A Grillo-ARCHITECTS PC             0      03/22/12                       10/17/12           
08-1558   Reconstruction               0-008-024  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,16               1,305,742     1,305,742  DDJ             0           0           0 ECG Engineering, LLC            1,305,742      06/12/13                       07/25/13           
10-0470   Reconstruction               0-008-025  01/06/11     DONE    DONE       DONE      11/15/10   11/12/10   07/07/10   05/18/10   13,16                    877,000       877,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      03/22/12                       05/04/12           
11-0684   Reconstruction               0-008-026  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   2,9,155,16               354,333       354,333  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/13/13                       10/28/13           

          Sagamore Jr. High:
09-0779   Reconstruction               0-010-018  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 119,950       119,950  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      10/31/11                       10/17/12           
08-1559   Reconstruction               0-010-019  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              868,426       868,426  DDJ             0           0           0 ECG Engineering, LLC              868,426      06/12/13                       07/25/13           
11-0685   Reconstruction               0-010-020  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   155,16                    75,857        75,857  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Hiawatha Elementary:
09-0780   Reconstruction               0-011-014  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 111,026       111,026  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       12/12/11           
08-1560   Reconstruction               0-011-015  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              444,358       444,358  DDJ             0           0           0 ECG Engineering, LLC              444,358      06/12/13                       07/25/13           
  -       Reconstruction               0-011-016                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Chippewa School:
09-0781   Reconstruction               0-012-011  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                  77,246        77,246  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       11/14/11           
08-1561   Reconstruction               0-012-012  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              421,815       421,815  DDJ             0           0           0 ECG Engineering, LLC              421,815      06/12/13                       07/25/13           
  -       Reconstruction               0-012-013                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Wenonah Elementary:
09-0782   Reconstruction               0-013-016  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 109,267       109,267  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       11/14/11           
08-1562   Reconstruction               0-013-017  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/13/09   12/03/08   2,155,15,16              457,539       457,539  DDJ             0           0           0 ECG Engineering, LLC              457,539      06/12/13                       07/25/13           
  -       Reconstruction               0-013-018                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Merrimac School:
09-0783   Reconstruction               0-014-014  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 127,121       127,121  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       11/14/11           
08-1563   Reconstruction               0-014-015  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              397,406       397,406  HCM             0           0           0 ECG Engineering, LLC              397,406      06/12/13                       07/25/13           
  -       Reconstruction               0-014-016                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Cayuga School:
09-0784   Reconstruction               0-015-013  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                  74,640        74,640  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      12/21/10                         /  /             
08-1564   Reconstruction               0-015-014  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              396,630       396,630  DDJ             0           0           0 ECG Engineering, LLC              396,630      06/12/13                       07/25/13           
  -       Reconstruction               0-015-015                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          North High School:
09-0785   Reconstruction               0-016-023  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 644,260       644,260  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      03/22/12                       05/04/12           
08-1565   Reconstruction               0-016-024  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16            2,040,975     2,040,975  DDJ             0           0           0 ECG Engineering, LLC            2,040,975      06/12/13                       07/25/13           
11-0686   Reconstruction               0-016-025  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   15                        22,000        22,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      07/09/13                       10/04/13           
13-1310   Reconstruction               0-016-026  06/02/14     DONE    DONE       DONE      03/07/14   03/06/14   02/04/14   05/20/14   4,7,9,15,16              750,000       750,000  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Seneca Jr. High:
09-0786   Reconstruction               0-017-013  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,9,155,15,16          1,009,200     1,009,200  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       11/14/11           
08-1566   Reconstruction               0-017-014  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16            1,126,655     1,126,655  DDJ             0           0           0 ECG Engineering, LLC            1,126,655      06/12/13                       07/25/13           
11-0687   Reconstruction               0-017-015  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   155,16                   119,858             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Tecumseh Elementary:
09-0787   Reconstruction               0-018-011  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                 176,975       176,975  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      01/14/11                       11/14/11           
08-1567   Reconstruction               0-018-012  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              424,316       424,316  DDJ             0           0           0 ECG Engineering, LLC              424,316      06/12/13                       07/25/13           
11-0688XX Reconstruction               0-018-013  05/16/12               CANCELLED          01/18/12   01/18/12   06/28/11   05/17/11   155,16                    42,857        42,857  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Tamarac Elementary:
09-0788   Reconstruction               0-019-014  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   09/24/08   03/18/08   2,155,16                  88,935        88,935  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      06/23/11                       11/14/11           
08-1568   Reconstruction               0-019-015  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              928,489       928,489  DDJ             0           0           0 ECG Engineering, LLC              928,489      06/12/13                       07/25/13           
  -       Reconstruction               0-019-016                                              /  /       /  /     06/28/11     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Sachem East High School:
08-1569   Reconstruction               0-050-003  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16            1,724,587     1,724,587  DDJ             0           0           0 ECG Engineering, LLC            1,724,587      06/12/13                       07/25/13           
09-1082   Reconstruction               0-050-004  03/15/10     DONE    DONE       DONE      03/16/10   03/15/10   03/11/10   09/16/09   7                      2,530,000     2,530,000  DDJ             0           0           0 McClave Engineering,P.C                 0        /  /                           /  /             
10-1108   Reconstruction               0-050-005  04/07/11     DONE    DONE       DONE      03/24/11   03/24/11   10/15/10   10/06/10   4,7,10,16              3,200,000     3,200,000  DDJ             0           0           0 McClave Engineering,P.C                 0        /  /                           /  /             
11-0689   Reconstruction               0-050-006  05/16/12     DONE    DONE       DONE      01/18/12   01/18/12   06/28/11   05/17/11   15                        60,500        60,500  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      07/09/13                       10/04/13           

          Sequoya Middle School:
08-1570   Reconstruction               0-051-004  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,15,16              949,212       949,212  DDJ             0           0           0 ECG Engineering, LLC              949,212      06/12/13                       07/25/13           

          Walter C. Dunham Admin Bldg:
09-0789   Reconstruction               1-001-007  05/25/10     DONE    DONE       DONE      01/25/10   01/21/10   01/22/10   03/18/08   2,16                     759,400             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      11/30/11                       10/17/12           
  -       Reconstruction               1-001-008                                              /  /       /  /       /  /       /  /     2,9,155,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Administrative Annex:
08-1571   Reconstruction               1-005-004  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,8,155,15,16            256,183             0  DDJ             0           0           0 ECG Engineering, LLC              256,183      06/12/13                       07/25/13           

          Transportation Office Bus Garage:
08-1572   Reconstruction               5-021-007  03/18/10     DONE    DONE       DONE      04/29/09   04/24/09   02/11/09   12/03/08   2,155,16                 168,479       168,479  DDJ             0           0           0 ECG Engineering, LLC              168,479      06/12/13                       07/25/13           
11-0416   Reconstruction               5-021-008  12/15/11     DONE    DONE       DONE      11/18/11   11/18/11   09/09/11   03/11/08   7,155,16                 190,000       190,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      01/08/13                       02/04/13           

          Public Library:
09-0180   Reconstruction               6-022-007  09/02/09     DONE    DONE       DONE      08/31/09   08/27/09   08/31/09   08/06/09   16                        60,000             0  DDJ             0           0           0 McClave Engineering,P.C                 0      05/30/08                       12/13/12           
11-0055   Reconstruction               6-022-008  08/03/11     DONE    DONE       DONE      07/21/11   07/15/11   06/29/11   06/20/11   4,8,9,16                 199,500             0  DDJ             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             
13-0143   Reconstruction               6-022-009  08/28/13     DONE    DONE       DONE      08/06/13   08/06/13   07/29/13   04/15/13   16                        86,000             0  MFS             0           0           0 JOHN TANZI ARCHITECTS                   0        /  /                           /  /             
  -       Reconstruction               6-022-010                                              /  /       /  /     04/29/14     /  /     2                              0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               6-022-011                                              /  /       /  /     07/16/14     /  /     7,16                           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          District Wide:
08-1746   Reconstruction               7-999-007  12/22/09     DONE    DONE       DONE      06/26/09   06/18/09   04/23/09   03/18/08   10,13,16               1,200,111     1,200,111  DDJ             0           0     515,070 John A Grillo-ARCHITECTS PC             0      10/14/10                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PORT JEFFERSON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-06-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Earl Vandermeulen High School:
09-1578   Reconstruction               0-001-013  08/12/10     DONE    DONE       DONE      07/06/10   06/30/10   04/21/10   04/28/10   16                       211,213             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-001-014                                              /  /       /  /     07/09/10     /  /     2,8,9,155,16                   0             0  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     07/16/14     /  /     2,4,7,8,9,10,155,15,           0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Edna Louise Spear ES (Pt.Jeff ES):
09-1579   Reconstruction               0-002-014  08/12/10     DONE    DONE       DONE      07/06/10   06/30/10   04/21/10   04/28/10   16                        64,582             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
10-0402   Additions and Alterations    0-002-015  12/10/10     DONE    DONE       DONE      11/01/10   10/19/10   07/09/10   08/30/10   02 - 16                  402,930             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Industrial Arts:
09-1580   Reconstruction               0-004-001  08/12/10     DONE    DONE       DONE      07/06/10   06/30/10   04/21/10   04/28/10   16                        20,827             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
12-0609   Reconstruction               0-004-002  03/07/13     DONE    DONE       DONE      12/26/12   12/20/12   03/08/12   05/15/12   2,7,155,16               640,000             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Relocatable:
09-1581   Reconstruction               0-005-001  08/12/10     DONE    DONE       DONE      07/06/10   06/30/10   04/21/10   04/28/10   16                        10,000             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Elem S Field House:
  -       Reconstruction               0-015-002                                              /  /       /  /     04/21/10     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-015-003                                              /  /       /  /     05/02/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Admin Bldg (was Pupil Personal Srv):
  -       Reconstruction               1-009-002                                              /  /       /  /     04/08/10     /  /     16                             0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MOUNT SINAI UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-07-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
11-0285   Reconstruction               0-001-013  12/27/11     DONE    DONE       DONE      10/25/11   10/24/11   11/30/10   11/17/10   16                       321,127       321,127  DDJ             0           0           0 H2M Group                         321,127      08/08/13                       09/16/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Mt. Sinai Middle School:
10-0956   Reconstruction               0-002-009  06/01/11     DONE    DONE       DONE      03/08/11   03/03/11   07/07/10   02/11/09   2,7                      491,655       491,655  DDJ             0           0           0 H2M Group                               0      11/23/11                       09/13/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-0286   Reconstruction               0-002-010  12/27/11     DONE    DONE       DONE      10/25/11   10/24/11   11/30/10   11/17/10   16                       464,784       464,784  DDJ             0           0           0 H2M Group                         464,784      08/08/13                       09/16/13         YES
                                                                                                                                                                                                                                                                                                                                   
13-0280   Reconstruction               0-002-011  11/14/13     DONE    DONE       DONE      08/26/13   08/23/13   04/24/13   05/21/13   7                        327,099       327,099  DDJ             0           0           0 H2M Group                               0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-002-012                                              /  /       /  /     03/25/14     /  /     2,4,7,9                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Senior High School:
11-0287   Reconstruction               0-006-011  12/27/11     DONE    DONE       DONE      10/25/11   10/24/11   11/30/10   11/17/10   16                     2,884,089     2,884,089  DDJ             0           0           0 H2M Group                       2,884,089      08/08/13                       09/16/13         YES
                                                                                                                                                                                                                                                                                                                                   

          HS Storage Shed:
13-0839DB Discovered Building          2-007-001  04/17/14     DONE    DONE       DONE      12/09/13   12/05/13   10/22/13     /  /                                    0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          HS Concession Stand:
13-0840DB Discovered Building          7-008-001  04/09/14     DONE    DONE       DONE      12/09/13   12/05/13   10/22/13     /  /                                    0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          HS Press Box:
13-0841DB Discovered Building          7-009-001  04/17/14     DONE    DONE       DONE      12/09/13   12/05/13   10/22/13     /  /                                    0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MILLER PLACE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-08-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          No.Country Road MS(former ES):
09-0303PR Reconstruction               0-001-013                         UNREVIEWED         10/14/09   10/09/09   01/28/05     /  /     8,9,155,15,16          2,421,900     1,786,410  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
09-0525   Reconstruction               0-001-013  05/14/10     DONE    DONE       DONE      11/30/09   11/18/09   01/28/05   11/12/08   8,9,155,15,16          2,424,900     2,424,900  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/01/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0743   Reconstruction               0-001-014  06/12/12     DONE    DONE       DONE      02/01/12   01/30/12   03/18/09   05/20/08   2,4,8,9,16               687,500             0  DDJ             0           0     189,750 Michael J. Guido Jr.                    0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0172   Reconstruction               0-001-017  04/19/12     DONE    DONE       DONE      09/13/11   09/09/11   05/19/11   11/17/10   8,155,15,16              733,890       733,890  DDJ             0           0           0 Michael J. Guido Jr.              733,890      05/29/13                       11/08/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-018                                              /  /       /  /     05/06/14     /  /     2,7,8,16                       0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          A. Muller Primary School:
09-0304PR Additions and Alterations    0-002-012                         UNREVIEWED         10/14/09   10/09/09   11/21/07     /  /     02 - 16                2,829,904     1,548,212  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-0526   Additions and Alterations    0-002-012  05/14/10     DONE    DONE       DONE      11/30/09   11/18/09   11/21/07   11/12/08   02 - 16                2,829,904     2,309,318  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/01/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0744   Reconstruction               0-002-013  06/12/12     DONE    DONE       DONE      02/02/12   01/30/12   03/18/09   06/12/12   2,4,9,16                  62,500        62,500  DDJ             0           0      17,250                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0173   Reconstruction               0-002-015  04/19/12     DONE    DONE       DONE      09/13/11   09/09/11   05/19/11   11/17/10   8,155,15,16              387,347       387,347  DDJ             0           0           0 Michael J. Guido Jr.              387,347      05/29/13                       11/08/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-002-016                                              /  /       /  /     05/06/14     /  /     2,4,7,8,9,155,16               0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Sound Beach School:
09-0305PR Reconstruction               0-003-011                         UNREVIEWED         10/14/09   10/09/09   02/25/05     /  /     8,9,155,15,16          4,702,300     3,050,722  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-0527   Reconstruction               0-003-011  05/14/10     DONE    DONE       DONE      11/30/09   11/18/09   02/25/05   11/12/08   16                     4,702,300     4,572,935  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/01/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0745   Reconstruction               0-003-012  06/12/12     DONE    DONE       DONE      02/01/12   01/30/12   03/18/09   05/20/08   16                        12,500             0  DDJ             0           0       3,450 Michael J. Guido Jr.                    0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0174   Reconstruction               0-003-014  04/19/12     DONE    DONE       DONE      09/13/11   09/09/11   05/19/11   11/17/10   8,155,15,16              532,401       532,401  DDJ             0           0           0 Michael J. Guido Jr.              532,401      05/29/13                       11/08/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-003-015                                              /  /       /  /     05/06/14     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-016                                              /  /       /  /     06/03/14     /  /     2,4,9,14,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Miller Place High School:
09-0306PR Additions and Alterations    0-006-022                         UNREVIEWED         10/14/09   10/09/09   11/21/07     /  /     02 - 16               15,442,896     9,727,084  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-0528   Additions and Alterations    0-006-022  05/14/10     DONE    DONE       DONE      11/30/09   11/18/09   11/21/07   11/12/08   02 - 16               15,442,896     9,624,164  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/06/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
10-0590   Additions and Alterations    0-006-023  06/13/11     DONE    DONE       DONE      12/21/10   12/10/10   03/18/09   03/02/10   02 - 16                  100,000       100,000  DDJ             0           0           0 Michael J Guido Jr                      0      03/21/12                       06/13/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0746   Reconstruction               0-006-024  06/12/12     DONE    DONE       DONE      02/01/12   01/30/12   03/18/09   05/20/08   2,4,9,16                 187,500             0  DDJ             0           0      51,750 Michael J. Guido Jr.                    0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-006-025                                              /  /       /  /     09/20/10     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0                                         0        /  /                           /  /             
11-0175   Reconstruction               0-006-026  04/19/12     DONE    DONE       DONE      09/13/11   09/09/11   05/19/11   11/17/10   8,155,15,16            1,321,618     1,321,618  DDJ             0           0           0 Michael J. Guido Jr.            1,321,618      05/29/13                       11/08/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-006-027                                              /  /       /  /     05/06/14     /  /     2,7,8,9,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-006-028                                              /  /       /  /     06/03/14     /  /     2,4,9,14,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Administration Building:
10-0591   New Construction             1-028-001  06/13/11     DONE    DONE       DONE      12/21/10   12/10/10   10/06/10   03/02/10   02 - 16                3,300,000             0  DDJ             0           0           0 Michael J Guido Jr                      0      03/21/12                       06/13/13           
  -       Reconstruction               1-028-002                                              /  /       /  /     05/06/14     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROCKY POINT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-09-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Joseph A Edgar School:
11-1024   Reconstruction               0-001-012  04/03/12     DONE    DONE       DONE      03/27/12   03/27/12   03/13/12   05/17/11   2,9                       94,400        94,400  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      08/15/12                       03/22/13         YES
                                                                                                                                                                                                                                                                                                                                   

          Rocky Point High:
09-1016   Reconstruction               0-005-024  03/04/10     DONE    DONE       DONE      03/04/10   03/03/10   05/20/09   05/15/07   4,7                      766,809       766,809  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/21/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
10-1225   Reconstruction               0-005-025  05/26/11     DONE    DONE       DONE      04/26/11   04/22/11   11/24/10   05/17/10   2,7,9,16               2,757,660     2,757,660  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      08/15/12                       03/22/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-005-026                                              /  /       /  /     05/10/11     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-005-027                                              /  /       /  /     05/10/11     /  /     2,7,9                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0492   Reconstruction               0-005-028  01/23/13     DONE    DONE       DONE      11/28/12   11/28/12   11/27/12   05/17/11   2,7,8,9,10,155,15,16      64,900        64,900  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/16/13                       06/23/14         YES
                                                                                                                                                                                                                                                                                                                                   
12-0673   Reconstruction               0-005-029  03/15/13     DONE    DONE       DONE      01/16/13   12/18/12   01/16/13   11/19/12   2,7,8,9,10,155,15,16   1,990,000     1,990,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/16/13                       06/23/14         YES
                                                                                                                                                                                                                                                                                                                                   
12-0862   Reconstruction               0-005-030  05/15/13     DONE    DONE       DONE      02/15/13   02/12/13   02/14/13   05/17/11   2,4,9,10,155,15,16       136,500       136,500  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/16/13                       06/23/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Frank J. Carasiti Elementary School:
12-0281   Reconstruction               0-006-015  10/30/12     DONE    DONE       DONE      10/16/12   10/15/12     /  /     05/15/07   2,10                      58,800             0  DDJ             0           0      42,000 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-1231   Reconstruction               0-006-016  06/17/13     DONE    DONE       DONE      05/28/13   05/28/13   04/12/13   05/15/07   7                        100,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MIDDLE COUNTRY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-11-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Oxhead Road Elementary:
09-1257   Reconstruction               0-001-017  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,15,16              326,731       326,731  JOD             0           0           0 ECG Engineering, LLC              323,171      07/22/13                       11/04/13           

          Holbrook Road Elementary:
  -       Reconstruction               0-002-013                                              /  /       /  /     10/08/09     /  /     2,155,15,16                    0             0  JOD             0           0           0                                         0        /  /                           /  /             
09-1258   Reconstruction               0-002-014  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,8,155,15,16            262,412       262,412  JOD             0           0           0 ECG Engineering, LLC              259,842      07/22/13                       11/04/13           

          Unity Dr. Pre-K Kdgtn. Ctr.:
09-1259   Reconstruction               0-003-012  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,15,16              371,314       371,314  JOD             0           0           0 ECG Engineering, LLC              365,304      07/22/13                       11/04/13           

          Bicycle Path Pre-K Kdgtn. Ctr.:
09-1260   Reconstruction               0-005-011  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              323,793       323,793  JOD             0           0           0 ECG Engineering, LLC              321,293      07/22/13                       11/04/13           

          Newfield High School:
09-1261   Reconstruction               0-006-019  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,8,155,15,16          2,699,296     2,699,296  JOD             0           0     450,000 ECG Engineering, LLC            2,245,051      07/22/13                       11/04/13           
13-0437   Reconstruction               0-006-020                       ADDENDUM REQ'D       09/26/13   09/26/13   02/14/13     /  /     155,15,16                      0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Dawnwood Middle School:
  -       Reconstruction               0-008-007                         UNREVIEWED         04/09/10   04/02/10   04/20/92   09/23/09   155,15,16                      0    23,606,010  MGL             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             
09-1262   Reconstruction               0-008-017  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,8,155,15,16          1,478,580     1,478,580  JOD             0           0     230,000 ECG Engineering, LLC            1,241,730      07/22/13                       11/04/13           

          Hawkins Path Elementary:
09-1263   Reconstruction               0-009-009  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              340,946       340,946  JOD             0           0           0 ECG Engineering, LLC              336,846      07/22/13                       11/04/13           

          Selden Middle School:
09-1264   Reconstruction               0-010-016  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,8,155,15,16          1,504,250     1,504,250  JOD             0           0     236,731 ECG Engineering, LLC            1,260,619      07/22/13                       11/04/13           

          North Coleman Elementary:
09-1265   Reconstruction               0-011-013  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              387,884       387,884  JOD             0           0      38,708 ECG Engineering, LLC              341,458      07/22/13                       11/04/13           

          Stagecoach Rd. Elementary:
09-1266   Reconstruction               0-012-010  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              317,484       317,484  JOD             0           0           0 ECG Engineering, LLC              312,444      07/22/13                       11/04/13           

          Auer Elementary:
09-1267   Reconstruction               0-013-012  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              301,678       301,678  JOD             0           0           0 ECG Engineering, LLC              299,748      07/22/13                       11/04/13           

          Jericho Elementary:
09-1268   Reconstruction               0-014-010  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              484,077       484,077  JOD             0           0      50,000 ECG Engineering, LLC              429,552      07/22/13                       11/04/13           

          Centereach High School:
09-1269   Reconstruction               0-015-017  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,8,155,15,16          3,793,407     3,793,407  JOD             0           0     600,000 ECG Engineering, LLC            3,185,207      07/22/13                       11/04/13           
13-0438   Reconstruction               0-015-018               STARTED DONE       DONE      09/26/13   09/26/13   10/16/12     /  /     13,155,15,16                   0             0  JMB             0           0           0 H2M Group                               0        /  /                           /  /             

          New Lane Memorial Elementary:
09-1270   Reconstruction               0-016-013  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16              806,922       806,922  JOD             0           0     120,000 ECG Engineering, LLC              679,532      07/22/13                       11/04/13           

          Trans Admin Bldg:
09-1271   Reconstruction               1-004-005  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,15,16               17,193             0  JOD             0           0           0 ECG Engineering, LLC               16,733      07/22/13                       11/04/13           

          Administration Building:
09-1272   Reconstruction               1-022-004  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/08/09   09/23/09   2,155,15,16               44,026             0  JOD             0           0           0 ECG Engineering, LLC               43,906      07/22/13                       11/04/13           

          Double Modular #1 @ Transp. Bldg.:
09-1273   Reconstruction               1-024-002  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,16                   7,950             0  JOD             0           0           0 ECG Engineering, LLC                7,950      07/22/13                       11/04/13           

          Double Modular #2 @ Transp. Bldg.:
09-1274   Reconstruction               1-025-002  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,16                  12,255             0  JOD             0           0           0 ECG Engineering, LLC               12,255      07/22/13                       11/04/13           

          Trans./Student Services:
09-1275   Reconstruction               1-028-002  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,16                  10,440             0  JOD             0           0           0 ECG Engineering, LLC               10,440      07/22/13                       11/04/13           

          Transportation Garage:
09-1276   Reconstruction               3-007-004  04/15/11     DONE    DONE       DONE      04/09/10   04/02/10   10/09/09   09/23/09   2,155,15,16               59,362             0  JOD             0           0           0 ECG Engineering, LLC               56,332      07/22/13                       11/04/13           

          Transporation Garage(was 3-007):
09-0617   Reconstruction               5-007-003  02/12/10     DONE    DONE       DONE      12/23/09   12/18/09   10/09/09   05/20/08   15                        44,000             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Bus Garage / Transportation Garage:
10-0404   New Construction             5-032-001  04/11/11     DONE    DONE       DONE      11/01/10   10/20/10   05/19/10   05/18/10   02 - 16                1,185,000             0  JOD             0           0           0 McClave Engineering,P.C                 0        /  /                           /  /             

          Middle Country Public Library:
10-1346   Additions and Alterations    6-020-005  08/16/11     DONE    DONE       DONE      06/02/11   05/27/11   03/25/11   05/18/11   02 - 16                1,958,555             0  JOD             0           0           0 BERMELLO AJAMIL & PARTNERS AR           0      11/15/12                       01/24/13           

          Mid Country Cultural Center:
  -    PR Additions and Alterations    6-021-002                                              /  /       /  /     03/25/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LONGWOOD CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-12-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Chas. E. Walters Elementary:
12-0776   Reconstruction               0-002-012  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   262,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0790   Reconstruction               0-002-013  04/23/13     DONE    DONE       DONE      02/07/13   02/07/13   11/20/12   03/06/12   2,9,16                    80,000             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          West Middle Island Primary School:
12-0777   Reconstruction               0-004-015  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   358,050             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-0758   Reconstruction               0-004-016  04/16/14     DONE    DONE       DONE      11/25/13   11/21/13   10/23/13   05/21/13   155                      262,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Coram Elementary:
12-0778   Reconstruction               0-007-013  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   262,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-007-014                                              /  /       /  /     11/19/13     /  /     155                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Ridge Elementary:
12-0779   Reconstruction               0-008-013  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   298,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Longwood Junior High School:
12-0780   Reconstruction               0-009-012  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   2,4,8,16                 871,720             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-0157XX Reconstruction               0-009-013                         CANCELLED          09/02/11   09/01/11   08/16/11   05/10/10   2,4                            0             0  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0791   Reconstruction               0-009-014  04/23/13     DONE    DONE       DONE      02/07/13   02/07/13   11/20/12   03/06/12   2,4,8,16                 657,700       657,700  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-0759   Reconstruction               0-009-015                       ADDENDUM REQ'D       11/25/13   11/21/13   10/23/13   05/21/13   155                            0             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Longwood Middle School:
12-0781   Reconstruction               0-010-011  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                 2,800,100             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-0879   Reconstruction               0-010-012  05/18/12     DONE    DONE       DONE      03/06/12   02/24/12   11/17/11   05/18/10   155,16                   450,000       450,000  DDJ             0           0           0 Wiedersum Associates Architec           0      11/19/13                       03/03/14           
  -       Reconstruction               0-010-013                                              /  /       /  /     03/15/12     /  /     2,4,7                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
11-1076   Reconstruction               0-010-014  04/10/12     DONE    DONE       DONE      04/05/12   04/02/12   03/20/12   03/06/12   2,4,7                  3,415,000     3,415,000  DDJ             0           0           0 Wiedersum Associates Architec           0      06/28/13                       09/13/13           
12-0792   Reconstruction               0-010-015  04/23/13     DONE    DONE       DONE      02/07/13   02/07/13   11/20/12   03/06/12   2,8,9                  1,740,000             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Ridge Elem.Annex 1:
12-0782   Reconstruction               0-011-009  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   02/06/12   155,16                   265,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-1077   Reconstruction               0-011-010  04/10/12     DONE    DONE       DONE      04/05/12   04/02/12   03/20/12   03/06/12   2,7                      766,500       766,500  DDJ             0           0           0 Wiedersum Associates Architec           0      06/28/13                       09/13/13           

          Coram Primary School:
12-0783   Reconstruction               0-012-006  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   249,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-1078   Reconstruction               0-012-007  04/10/12     DONE    DONE       DONE      04/05/12   04/02/12   03/20/12   03/06/12   2,7                      816,500       816,500  DDJ             0           0           0 Wiedersum Associates Architec           0      06/28/13                       09/13/13           
  -       Reconstruction               0-012-008                                              /  /       /  /     10/23/13     /  /     155                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Charles E. Walters Annex 1:
12-0784   Reconstruction               0-014-008  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   620,600             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-1079   Reconstruction               0-014-009  04/10/12     DONE    DONE       DONE      04/05/12   04/02/12   03/20/12   03/06/12   2,7                      797,500       797,500  DDJ             0           0           0 Wiedersum Associates Architec           0      06/28/13                       09/13/13           

          Longwood Sr High School:
09-0296   Reconstruction               0-015-012  11/23/09     DONE    DONE       DONE      10/09/09   10/09/09   07/14/09   05/19/09   155,16                   450,000       450,000  DDJ             0           0           0 Wiedersum Associates Architec           0      09/17/10                         /  /             
11-1443   Reconstruction               0-015-013  10/25/12     DONE    DONE       DONE      06/29/12   06/20/12   05/07/12   03/06/12   2,14,16                2,796,303     2,207,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0785   Reconstruction               0-015-014  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   06/20/12   03/06/12   155,16                 1,906,430             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-0760   Reconstruction               0-015-015                       ADDENDUM REQ'D       11/25/13   11/21/13   08/27/13   05/21/13   155                            0             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          W. Middle Island Annex:
12-0786   Reconstruction               0-018-005  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   07/14/09   03/06/12   155,16                   258,100             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-1080   Reconstruction               0-018-006  04/10/12     DONE    DONE       DONE      04/05/12   04/02/12   03/20/12   03/06/12   2,7                      865,800       865,800  DDJ             0           0           0 Wiedersum Associates Architec           0      06/28/13                       09/13/13           

          Public Library:
12-1229   Additions and Alterations    6-016-005  11/26/13     DONE    DONE       DONE      05/28/13   05/28/13   11/02/12   10/09/12   02 - 16               17,896,347             0  DDJ             0           0           0 Peter Gisolfi Associates                0        /  /                           /  /             
09-0072   Reconstruction               6-016-006  08/11/09     DONE    DONE       DONE      07/22/09   07/20/09   06/19/09   06/17/09   7,16                     180,000             0  DDJ             0           0           0 Beatty, Harvey & Associates             0        /  /                           /  /             
13-0116   Reconstruction               6-016-007  08/16/13     DONE    DONE       DONE      08/01/13   07/26/13   05/31/13   10/09/12   2                        319,859             0  MFS             0           0           0 Peter Gisolfi Associates                0        /  /                           /  /             

          New Co-Gen Building:
12-0787   New Construction             7-020-001  04/16/14     DONE    DONE       DONE      02/07/13   02/06/13   06/21/12   03/06/12   02 - 16                4,600,000             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PATCHOGUE-MEDFORD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-24-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bay Avenue School:
13-0195   Reconstruction               0-001-011               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,8,155,16               112,000             0  DDJ             0           0      29,904 Burton Behrendt Smith                   0        /  /                           /  /             
12-0372   Reconstruction               0-001-017  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              324,610       324,610  DDJ             0           0           0 Burton Behrendt Smith             305,640        /  /                           /  /             

          Medford Avenue School:
13-0196   Reconstruction               0-002-008               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   8,155,16                  89,300             0  DDJ             0           0      23,843 Burton Behrendt Smith                   0        /  /                           /  /             
12-0373   Reconstruction               0-002-011  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              346,628       346,628  DDJ             0           0           0 Burton Behrendt Smith             318,113        /  /                           /  /             

          River Avenue Elem. School:
13-0197   Reconstruction               0-003-004               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,8                       70,000             0  DDJ             0           0      18,690 Burton Behrendt Smith                   0        /  /                           /  /             
12-0374   Reconstruction               0-003-009  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              286,291       286,291  DDJ             0           0           0 Burton Behrendt Smith             265,926        /  /                           /  /             

          South Ocean Middle School:
13-0198   Reconstruction               0-004-011               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,8,9,155                437,000             0  DDJ             0           0     116,679 Burton Behrendt Smith                   0        /  /                           /  /             
12-0375   Reconstruction               0-004-017  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              454,706       454,706  DDJ             0           0           0 Burton Behrendt Smith             399,416        /  /                           /  /             

          Saxton Middle School:
10-1250   Reconstruction               0-005-016  08/03/11     DONE    DONE       DONE      05/02/11   05/02/11   02/27/08   12/11/10   10                       160,777       160,777  JOD             0           0      42,999 Burton Behrendt Smith                   0      06/29/12                       01/04/13           
09-0313   Reconstruction               0-005-018  11/24/09     DONE    DONE       DONE      10/19/09   10/14/09   02/27/08   12/11/07   4,155,16                 266,759       266,759  JOD             0           0      72,357 Burton Behrendt Smith                   0      11/30/11                       12/28/11           
12-0376   Reconstruction               0-005-019  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16            1,688,939     1,688,939  DDJ             0           0           0 Burton Behrendt Smith           1,621,529        /  /                           /  /             
13-0199   Reconstruction               0-005-020               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,155                    134,000             0  DDJ             0           0      35,778 Burton Behrendt Smith                   0        /  /                           /  /             

          Barton Ave. Elementary:
13-0200   Reconstruction               0-008-008               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,8,9,15                  41,500             0  DDJ             0           0      11,080 Burton Behrendt Smith                   0        /  /                           /  /             
12-0377   Reconstruction               0-008-010  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              520,751       520,751  DDJ             0           0           0 Burton Behrendt Smith             478,706        /  /                           /  /             

          Oregon Avenue Junior High:
13-0201   Reconstruction               0-009-009               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   8                        416,795             0  DDJ             0           0     111,284 Burton Behrendt Smith                   0        /  /                           /  /             
12-0378   Reconstruction               0-009-011  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16            1,141,382     1,141,382  DDJ             0           0           0 Burton Behrendt Smith           1,102,777        /  /                           /  /             

          Tremont Ave School:
13-0202   Reconstruction               0-010-005               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4                          4,500             0  DDJ             0           0       1,201 Burton Behrendt Smith                   0        /  /                           /  /             
12-0379   Reconstruction               0-010-011  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              400,718       400,718  JOD             0           0           0 Burton Behrendt Smith             360,848        /  /                           /  /             

          Eagle Drive Elementary:
13-0204   Reconstruction               0-011-005               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4                          2,500             0  DDJ             0           0         667 Burton Behrendt Smith                   0        /  /                           /  /             
08-0606   Reconstruction               0-011-011  03/18/10     DONE    DONE       DONE      10/29/08   10/28/08   02/27/08   12/11/07   16                        28,625        28,625  JOD             0           0       7,706 Burton Behrendt Smith                   0      07/30/10                         /  /             
12-0380   Reconstruction               0-011-012  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              478,884       478,884  DDJ             0           0           0 Burton Behrendt Smith             441,109        /  /                           /  /             

          Canaan Elementary School:
13-0205   Reconstruction               0-013-007               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,155                     85,000             0  DDJ             0           0      22,695 Burton Behrendt Smith                   0        /  /                           /  /             
12-0381   Reconstruction               0-013-011  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16              401,384       401,384  DDJ             0           0           0 Burton Behrendt Smith             374,529        /  /                           /  /             

          Patchogue-Medford High School:
  -       Reconstruction               0-015-017                                              /  /       /  /     03/22/10     /  /     2,4,7,9,15                     0    75,384,578  JOD             0           0           0                                         0        /  /                           /  /             
12-0382   Reconstruction               0-015-018  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16            4,466,193     4,466,193  DDJ             0           0           0 Burton Behrendt Smith           4,348,013        /  /                           /  /             
13-0203   Reconstruction               0-015-019               DONE    DONE       ADD. REQ'D08/14/13   08/12/13   12/18/12   12/11/07   4,7,8,155,16             293,000             0  DDJ             0           0      78,231 Burton Behrendt Smith                   0        /  /                           /  /             

          Administration Bldg.:
12-0383   Reconstruction               1-006-002  12/30/13     DONE    DONE       DONE      11/02/12   10/30/12   06/21/12   05/03/12   8,155,15,16               92,045             0  DDJ             0           0           0 Burton Behrendt Smith              86,615        /  /                           /  /             

          Public Library:
09-1207   Reconstruction               6-021-010  08/19/10     DONE    DONE       DONE      04/02/10   03/29/10   01/06/10   02/16/10   2,9,10,155,15,16       1,064,238             0  JOD             0           0           0 H2M Group                               0      03/29/11                         /  /             
11-0012   Reconstruction               6-021-011  07/11/11     DONE    DONE       DONE      07/11/11   07/07/11   04/14/11   02/15/11   14                       250,000             0  JOD             0           0           0 RICHARD SEARLES ARCHITECTS              0        /  /                           /  /             

          St. Paul Episcopal Church:
10-0179TQ Temporary Quarters           6-032-001  08/30/10     DONE    DONE       DONE      08/30/10   08/30/10   08/10/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Carnegie Library:
13-1305   Reconstruction               6-033-001               DONE    DONE       STARTED   03/05/14   03/03/14   11/22/13   01/15/14   2,4,7,8,9,10,13,14,1           0             0  MFS             0           0           0 RICHARD SEARLES ARCHITECTS              0        /  /                           /  /             

          Press Box @ High School:
12-0939DB Discovered Building          7-026-001  03/06/13     DONE    DONE       DONE      03/01/13   03/01/13   04/10/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          District Wide:
10-0916   Reconstruction               7-999-008  05/24/11     DONE    DONE       DONE      02/28/11   02/22/11   02/27/08   12/11/07   10,13,16               1,723,136     1,723,136  JOD             0           0     460,077 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WILLIAM FLOYD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-32-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nathaniel Woodhull Elementary:
12-1287   Reconstruction               0-003-011  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/08/13   12/12/07   2,8                       27,450        27,450  JOB             0           0       5,764 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          William Floyd Elementary:
12-1288   Reconstruction               0-004-015  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/14/13   12/12/07   2,8                       27,450        27,450  JOB             0           0       5,764 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          William Floyd Jr/Sr High:
08-1622   Additions and Alterations    0-005-020  11/05/09     DONE    DONE       DONE      05/12/09   05/11/09   07/05/05   12/12/07   02 - 16               48,735,000    48,735,000  HCM             0           0   5,653,260 Tetra  Tech Architects & Engi           0      05/30/14                       06/30/14           
11-0826   Additions and Alterations    0-005-021  06/12/12     DONE    DONE       DONE      02/22/12   02/21/12   10/05/11   12/12/07   02 - 16                  211,000       211,000  HCM             0           0     211,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             
11-0914   Reconstruction               0-005-022  06/26/12     DONE    DONE       DONE      03/08/12   02/23/12   02/17/12   12/12/07   4,8,9,155,15,16        1,120,000     1,120,000  HCM             0           0     235,200 Tetra  Tech Architects & Engi           0        /  /                           /  /             
  -    PR Additions and Alterations    0-005-023                                              /  /       /  /     09/19/12     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
12-0390   Additions and Alterations    0-005-023  03/19/13     DONE    DONE       DONE      11/06/12   11/05/12   09/19/12   12/12/07   02 - 16                2,440,000             0  JMB             0           0   1,722,200 Tetra  Tech Architects & Engi           0        /  /                           /  /             
  -       Reconstruction               0-005-024                                              /  /       /  /     05/08/13     /  /     2,8                            0             0  JOB             0           0           0                                         0        /  /                           /  /             

          Moriches Elementary School:
12-1289   Reconstruction               0-009-011  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/08/13   12/12/07   2,8                       27,450        27,450  JOB             0           0       5,764 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Tangier Smith Elementary:
12-1290   Reconstruction               0-010-013  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/08/13   12/12/07   2,8                       27,450        27,450  JOB             0           0       5,764 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Wm. Paca Jr. HS/7-9:
12-1291   Reconstruction               0-011-014  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/08/13   12/12/07   2,4,8                    103,000       103,000  JOB             0           0      21,630 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Hobart Elementary School:
12-1292   Reconstruction               0-012-011  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/08/13   12/12/07   2,8                       27,450        27,450  JOB             0           0       5,764 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          New Middle School:
12-1293   Reconstruction               0-053-003  09/24/13     DONE    DONE       DONE      06/14/13   06/12/13   05/14/13   12/12/07   2,8                       42,250        42,250  JOB             0           0       8,872 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Mastics Moriches Shirley Comu. Libr.:
12-0170   Reconstruction               6-007-006  09/17/12     DONE    DONE       DONE      09/13/12   09/12/12   03/24/11   08/27/12   7,9,10,155,15,16         223,000             0  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               6-007-007                                              /  /       /  /     03/25/11     /  /     7,9,10,155,15,16               0             0  HCM             0           0           0                                         0        /  /                           /  /             
13-1442   Reconstruction               6-007-008  06/02/14     DONE    DONE       DONE      04/10/14   04/08/14   10/03/13   10/28/13   4,10                     362,000             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-1441   Reconstruction               6-007-009               DONE    DONE       ADD. REQ'D04/10/14   04/08/14   01/17/14     /  /     7,9,16                         0             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CENTER MORICHES UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-33-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Street School:
08-1496   Reconstruction               0-001-013  08/28/09     DONE    DONE       DONE      04/14/09   04/09/09   01/15/09   05/20/08   2,4,7,8,9,155,15,16    1,197,980     1,197,980  JOD             0           0     352,980 James M. Campbell Architects            0      06/30/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
09-0751   Reconstruction               0-001-014  10/15/10     DONE    DONE       DONE      01/22/10   01/21/10   09/09/09   09/02/09   2,8,155,15,16            973,904       973,904  JOD             0           0           0 ECG Engineering, LLC              973,904      02/01/12                       09/24/12         YES
                                                                                                                                                                                                                                                                                                                                   

          High School:
09-0752   Reconstruction               0-006-009  10/15/10     DONE    DONE       DONE      01/22/10   01/21/10   09/09/09   09/02/09   2,8,155,15,16          1,815,335     1,815,335  JOD             0           0           0 ECG Engineering, LLC            1,815,335      02/01/12                       09/24/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-1246   Reconstruction               0-006-010  07/13/12     DONE    DONE       DONE      05/01/12   04/26/12   03/23/12   06/19/12   4,7,8,9,10,155,16        100,000       100,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      12/05/12                       12/19/12         YES
                                                                                                                                                                                                                                                                                                                                   

          Administration Building:
09-0753   Reconstruction               1-003-002  10/15/10     DONE    DONE       DONE      01/22/10   01/21/10   09/09/09   09/02/09   2,155,16                  70,051             0  JOD             0           0           0 ECG Engineering, LLC               70,051      02/01/12                       09/24/12         YES
                                                                                                                                                                                                                                                                                                                                   

          High School Field storage:
09-1091XX Reconstruction               2-024-001                         CANCELLED          03/17/10   03/04/10   10/26/09     /  /                                    0             0  JOD             0           0           0 James M. Campbell Architects            0        /  /                           /  /             

          Maintenance Building:
09-0754   Reconstruction               3-016-002  10/15/10     DONE    DONE       DONE      01/22/10   01/21/10   09/09/09   09/02/09   2,155,16                  24,503             0  JOD             0           0           0 ECG Engineering, LLC               24,503      02/01/12                       09/24/12           

          Public Library:
  -    XX Reconstruction               6-003-006                         CANCELLED            /  /       /  /     08/10/09     /  /     2,4,8,10,155,15,16             0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-0045   Additions and Alterations    6-003-007  08/17/11     DONE    DONE       DONE      07/20/11   07/20/11   01/04/11   02/28/11   02 - 16                2,750,000             0  JOD             0           0           0 Wiedersum Associates Architec           0      12/27/12                       02/20/13           

          CONCESSION TRAILER:
09-1091DB Discovered Building          7-019-001                       ADDENDUM REQ'D       03/04/10   03/04/10   10/26/09     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          High School Field Press Box:
09-1089DB Discovered Building          7-022-001                       ADDENDUM REQ'D       03/17/10   03/04/10   10/26/09     /  /                                    0             0  JOD             0           0           0 James M. Campbell Architects            0        /  /                           /  /             

          High School Small Concession Stand:
09-1090DB Discovered Building          7-023-001                       ADDENDUM REQ'D       03/17/10   03/04/10   10/26/09     /  /                                    0             0  JOD             0           0           0 James M. Campbell Architects            0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST MORICHES UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-34-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          East Moriches School:
11-0704   Reconstruction               0-001-016  03/19/12     DONE    DONE       DONE      01/24/12   01/19/12   01/10/12   05/17/11   4,7,9                     28,320             0  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-1258   Reconstruction               0-001-017  07/02/12     DONE    DONE       DONE      05/03/12   05/01/12   01/10/12   05/15/12   7,9                      450,000       450,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0430   Reconstruction               0-001-018  04/04/14     DONE    DONE       DONE      09/25/13   09/24/13   05/23/13   05/21/13   2,4,7,8,9,15,16          977,040       977,040  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-019                                              /  /       /  /     06/26/13     /  /     2                              0    10,115,679  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH COUNTRY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-02-35-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          South Haven Primary School:
  -       Reconstruction               0-001-006                                              /  /       /  /     02/05/10     /  /     2,9,155,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-007                                              /  /       /  /     03/12/10     /  /     2,9,155,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Kreamer Street Elementary:
09-0638   Reconstruction               0-002-009  05/06/10     DONE    DONE       DONE      12/29/09   12/18/09   08/05/09   06/19/06   9,155,16                 968,480       968,480  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           
09-1143   Reconstruction               0-002-010  05/27/10     DONE    DONE       DONE      03/25/10   03/18/10   02/05/10   06/16/09   2,9,155,16             1,280,410     1,280,410  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           

          Brookhaven Elementary:
09-0639   Reconstruction               0-003-009  05/06/10     DONE    DONE       DONE      12/29/09   12/18/09   08/05/09   06/19/06   9,155,16                 851,500       851,500  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           
09-1144   Reconstruction               0-003-010  05/27/10     DONE    DONE       DONE      03/25/10   03/18/10   02/05/10   06/16/09   2,155,16                 630,000       630,000  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           

          Bellport Middle School:
09-0640   Reconstruction               0-004-011  05/06/10     DONE    DONE       DONE      12/29/09   12/18/09   08/05/09   06/19/06   2,9,155,16             1,574,470     1,574,470  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           
09-1145   Reconstruction               0-004-012  05/27/10     DONE    DONE       DONE      03/25/10   03/18/10   02/05/10   06/16/09   2,8,9,155,15,16        1,006,066     1,006,066  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           

          Frank P Long Inter.(frmr Hampton):
09-0641   Reconstruction               0-005-009  05/06/10     DONE    DONE       DONE      12/29/09   12/18/09   12/29/09   06/19/06   7,16                     993,950       993,950  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           
09-1146   Reconstruction               0-005-010  05/27/10     DONE    DONE       DONE      03/25/10   03/18/10     /  /     06/16/09                          1,807,800     1,807,800  JOD             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           

          Senior High School:
09-0642   Reconstruction               0-006-009  05/06/10     DONE    DONE       DONE      12/29/09   12/18/09   08/05/09   06/19/06   4,9,155,15,16          1,712,020     1,712,020  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           
09-1147   Reconstruction               0-006-010  05/27/10     DONE    DONE       DONE      03/25/10   03/18/10   02/05/10   06/16/09   2,4,8,9,155,15,16      2,835,454     2,835,454  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           

          Verne W. Critz Elementary:
09-0643   Reconstruction               0-007-009  05/06/10     DONE    DONE       DONE      12/29/09   12/18/09   08/05/09   06/19/06   9,155,16               1,024,850     1,024,850  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           
09-1148   Reconstruction               0-007-010  05/27/10     DONE    DONE       DONE      03/25/10   03/18/10   02/05/10   06/16/09   2,9,155,16               315,000       315,000  DDJ             0           0           0 Wiedersum Associates Architec           0      10/15/12                       12/23/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST HAMPTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-03-01-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
09-1576   Reconstruction               0-003-017  07/19/10     DONE    DONE       DONE      07/02/10   06/23/10   07/15/08   05/18/10   4                        650,000       650,000  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0      06/17/11                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0693   Reconstruction               0-003-018  08/18/11     DONE    DONE       DONE      01/19/12   01/18/12   03/23/10   07/26/11   2,15,16                  150,000       150,000  HCM             0           0           0 Michael J. Guido Jr.                    0      08/06/12                       09/27/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-0979   Reconstruction               0-003-019  06/15/12     DONE    DONE       DONE      03/16/12   03/15/12   05/19/11   05/18/10   4                        734,870             0  HCM             0           0           0 Michael J. Guido Jr.                    0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-1047   Reconstruction               0-003-020  05/06/13     DONE    DONE       DONE      03/29/13   03/29/13   02/01/13   03/05/13   16                       133,000             0  MFS             0           0           0 MICHAEL J. GUIDO JR. ARCHITEC           0        /  /                           /  /             
  -    PR Additions and Alterations    0-003-021                                              /  /       /  /     04/01/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          John Marshall Elementary:
11-0980   Reconstruction               0-004-016  06/15/12     DONE    DONE       DONE      03/16/12   03/15/12   01/25/12   05/18/10   2                        114,000       114,000  HCM             0           0           0 Michael J. Guido Jr.                    0      03/25/13                       04/29/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-1057   Reconstruction               0-004-017  05/14/13     DONE    DONE       DONE      04/02/13   03/29/13   02/01/13   05/15/12   7                        650,000             0  MFS             0           0           0 Michael J. Guido Jr.                    0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -    PR Additions and Alterations    0-004-018                                              /  /       /  /     04/01/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          High School/Modular @ HS:
  -       Reconstruction               0-006-027                                              /  /       /  /     04/01/14     /  /     8,9,16                         0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Football Storage Shed @ High School:
09-1030DB Discovered Building          2-021-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Soccer Shed @ High School:
09-1031DB Discovered Building          2-022-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Softball Storage @ High School:
09-1033DB Discovered Building          2-024-001               UNREVIEWED
                                                                       DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Technology Shop Storage Shed:
09-1024DB Discovered Building          2-025-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/12/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Large Pole Barn - High School:
09-1026DB Discovered Building          2-027-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Softball Dugout / Storage (3rd Base):
09-1027DB Discovered Building          2-028-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Baseball Dugout / Storage (3rd Base):
09-1029DB Discovered Building          2-030-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Press Box @ High School:
09-1032DB Discovered Building          7-023-001  08/09/10     DONE    DONE       DONE      03/09/10   03/08/10   03/12/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Softball Dugout (1st base) @ High:
09-1025DB Discovered Building          7-026-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Baseball Dugout (1st Base):
09-1028DB Discovered Building          7-029-001  06/22/10     DONE    DONE       DONE      03/09/10   03/08/10   03/11/08     /  /                                    0             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




AMAGANSETT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-03-03-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
10-0825   Reconstruction               0-001-014  05/17/11     DONE    DONE       DONE      02/08/11   02/04/11   08/19/10   05/18/10   4                        135,000             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
10-0790   Reconstruction               0-001-015  05/23/11     DONE    DONE       DONE      02/03/11   02/03/11   09/08/10   05/18/10   155                       45,000        45,000  DDJ             0           0           0 Burton Behrendt Smith                   0      12/03/12                       01/24/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-1288   Reconstruction               0-001-016  05/17/12     DONE    DONE       DONE      05/10/12   05/07/12   03/29/12   05/17/11   2,9                       40,000        40,000  DDJ             0           0           0 Burton Behrendt Smith                   0      08/31/12                       08/25/12         YES
                                                                                                                                                                                                                                                                                                                                   

          Superintendent's Residence:
09-0257   Reconstruction               7-005-003  01/11/10     DONE    DONE       DONE      09/22/09   09/22/09   08/28/09   05/19/09   2,155                     25,000             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SPRINGS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-03-04-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Springs School:
09-0171   Reconstruction               0-001-011  10/22/09     DONE    DONE       DONE      08/27/09   08/25/09   03/26/09   02/13/07   2,16                     159,427       159,427  JOD             0           0      80,462 ECG Engineering, LLC                    0      07/08/10                       12/26/12         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-012                                              /  /       /  /     10/06/10     /  /     7                              0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-0081   Reconstruction               0-001-013  08/16/11     DONE    DONE       DONE      08/04/11   08/04/11   06/29/11   07/05/11   7                        211,000             0  JOD             0           0      98,675 Chaleff & Rogers Architects,P           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0441   Reconstruction               0-001-014  05/01/14     DONE    DONE       DONE      10/03/13   10/01/13   03/22/13   05/08/13   2,4,7,8,9,10,155,16      168,000             0  MFS             0           0           0 Chaleff & Rogers Architects             0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-015                                              /  /       /  /     04/04/13     /  /     8,9,10,155,16                  0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Greenhouse:
08-1530TQ Temporary Quarters           0-011-001  07/03/14     DONE    DONE       DONE      04/22/09   03/17/09   12/04/08     /  /     02 - 16                        0             0  JOD             0           0           0 D.B. Bennett Consulting engin           0        /  /                           /  /             

          Storage Shed:
10-0514DB Discovered Building          2-012-001                         UNREVIEWED         12/02/10   12/02/10   11/05/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Springs Youth Center:
13-1465TQ Temporary Quarters           8-013-001  07/03/14     DONE    DONE       DONE      04/17/14   04/16/14   03/20/14     /  /                                    0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SAG HARBOR UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-03-05-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pierson High School:
09-0242   Reconstruction               0-001-023  03/03/10     DONE    DONE       DONE      09/17/09   09/16/09     /  /     05/19/09   10                       150,000       150,000  DDJ             0           0           0 Burton Behrendt Smith                   0      11/23/11                       07/15/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-0915   Reconstruction               0-001-024  07/27/12     DONE    DONE       DONE      03/08/12   02/23/12   06/29/11   05/18/10   16                       274,320             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-1369   Reconstruction               0-001-025  10/22/12     DONE    DONE       DONE      05/31/12   05/25/12   12/06/11   05/15/10   10,155,16                 77,682             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0034   Reconstruction               0-001-026  09/17/13     DONE    DONE       DONE      07/11/13   07/11/13   08/09/12   05/22/12   155,16                   315,476             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0709   Reconstruction               0-001-027  05/01/14     DONE    DONE       DONE      11/14/13   11/12/13   05/31/13   05/21/13   10                       703,600             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-028                                              /  /       /  /     05/31/13     /  /     7                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    PR Additions and Alterations    0-001-029                                              /  /       /  /     11/26/13     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Sag Harbor Elementary:
11-0916   Reconstruction               0-003-018  07/27/12     DONE    DONE       DONE      03/08/12   02/23/12   06/29/11   05/18/10   16                       106,680       106,680  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-1370   Reconstruction               0-003-019  10/22/12     DONE    DONE       DONE      05/31/12   05/25/12   12/06/11   05/18/10   8,10,155,16               40,446             0                  0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0035   Reconstruction               0-003-020  09/17/13     DONE    DONE       DONE      07/11/13   07/11/13   08/09/12   05/22/12   155,16                   166,000             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0710   Reconstruction               0-003-021  05/01/14     DONE    DONE       DONE      11/14/13   11/12/13   05/31/13   05/21/13   7                        410,000             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -    PR Additions and Alterations    0-003-022                                              /  /       /  /     11/26/13     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Container - Elem School:
  -    DB Discovered Building          2-013-001                                              /  /       /  /     06/23/11     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MONTAUK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-03-06-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Montauk School K-8:
  -       Reconstruction               0-001-009                                              /  /       /  /     04/29/14     /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Storage Shed 3:
13-0471DB Discovered Building          2-011-001                       ADDENDUM REQ'D       10/08/13   10/08/13   10/08/13     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Public Library:
13-0341   Reconstruction               6-002-008  09/26/13     DONE    DONE       DONE      09/09/13   09/09/13   08/21/13   08/27/13   15,16                    119,280             0  MFS             0           0           0 JOHN TANZI ARCHITECTS                   0        /  /                           /  /             

          Modular Classroom Building:
  -    TQ Temporary Quarters           8-012-001                                              /  /       /  /     04/03/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELWOOD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-01-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          John H. Glen High School:
08-1510   Reconstruction               0-004-020  04/07/10     DONE    DONE       DONE      04/16/09   04/15/09   10/06/08   05/20/08   8,9,155,16                40,322        40,322  JOD             0           0      14,717 Burton Behrendt Smith                   0      01/07/11                       04/22/14           
11-0318   Reconstruction               0-004-021  02/02/12     DONE    DONE       DONE      11/01/11   11/01/11   01/19/11   12/09/10   2,4,8,9,10,155,16        737,700       737,700  JOD             0           0     292,609 Burton Behrendt Smith                   0      08/30/12                       10/23/12           

          Harley Avenue Elementary:
10-1391   Reconstruction               0-005-013  07/08/11     DONE    DONE       DONE      06/09/11   06/08/11   01/19/11   12/10/10   2,4,8,9,155,15,16        211,860       211,860  JOD             0           0      67,801 Burton Behrendt Smith                   0      08/30/12                       10/23/12           

          Elwood Middle School:
11-0319   Reconstruction               0-006-015  02/02/12     DONE    DONE       DONE      11/01/11   11/01/11   01/19/11   12/09/10   2,10,16                   96,300        96,300  JOD             0           0      30,819 Burton Behrendt Smith                   0      08/30/12                       10/23/12           

          James Boyd Intermediate:
11-0320   Reconstruction               0-007-007  02/02/12     DONE    DONE       DONE      11/01/11   11/01/11   01/19/11   12/09/10   2,155,16                 353,742             0  JOD             0           0     113,207 Burton Behrendt Smith                   0        /  /                           /  /             

          Districtwide:
11-0274   Reconstruction               7-999-002  12/06/11     DONE    DONE       DONE      10/25/11   10/21/11   08/19/11   12/09/10   16                        50,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COLD SPRING HARBOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-02-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lloyd Harbor School:
09-1106   Reconstruction               0-002-022  04/29/10     DONE    DONE       DONE      03/18/10   03/12/10   11/19/09   12/08/09   2,8,9,155,15,16          479,243       479,243  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/08/11                         /  /             
  -       Reconstruction               0-002-023                                              /  /       /  /     03/15/10     /  /     2,15,16                        0     8,202,765  DDJ             0           0           0                                         0        /  /                           /  /             
10-0826   Reconstruction               0-002-024  06/07/11     DONE    DONE       DONE      02/08/11   02/04/11   11/02/10   12/08/09   2,4,7,8,9,10,155,15,     613,458       613,458  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/20/11                       10/05/11           
11-0466   Reconstruction               0-002-025  03/19/12     DONE    DONE       DONE      12/08/11   12/05/11   12/01/11   05/17/11   2,155                    370,000       370,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/04/12                       09/04/12           
11-1395   Reconstruction               0-002-026  01/30/13     DONE    DONE       DONE      06/12/12   06/06/12   12/21/11   12/13/11   155,15,16                730,692       730,692  DDJ             0           0           0 John A Grillo-ARCHITECTS PC       730,692        /  /                           /  /             
12-0898   Reconstruction               0-002-027  09/12/13     DONE    DONE       DONE      02/21/13   02/21/13   05/17/12   05/15/12   2,4,7,9,10,155,16        577,110             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0549   Reconstruction               0-002-028  06/04/14     DONE    DONE       DONE      10/16/13   10/10/13   05/23/13   05/21/13   2,4,7,8,9,10,155,15,     670,133             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-002-029                                              /  /       /  /     06/17/14     /  /     2,155,16                       0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Goosehill Primary School:
  -    XX Reconstruction               0-003-026                         CANCELLED            /  /       /  /     11/18/09     /  /     7,9,155,16                     0     3,746,358  DDJ             0           0           0                                         0        /  /                           /  /             
10-0827   Reconstruction               0-003-027  06/07/11     DONE    DONE       DONE      02/08/11   02/04/11   11/02/10   12/08/09   4,7,155,16               188,800       188,800  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/20/11                         /  /             
11-1394   Reconstruction               0-003-028  01/30/13     DONE    DONE       DONE      06/12/12   06/06/12   12/21/11   12/13/11   155,15,16                359,375             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC       359,375        /  /                           /  /             
12-0899   Reconstruction               0-003-029  09/12/13     DONE    DONE       DONE      02/21/13   02/21/13   05/17/12   05/15/12   2,4,7,155                291,640             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0550   Reconstruction               0-003-030  06/04/14     DONE    DONE       DONE      10/16/13   10/10/13   05/23/13   05/21/13   10,155,15,16             187,450             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-1403   Reconstruction               0-003-031  05/30/14     DONE    DONE       DONE      03/25/14   03/21/14   12/17/13   05/20/13   2,9                      223,206             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Westside Elementary:
  -    XX Reconstruction               0-006-022                         CANCELLED            /  /       /  /     11/18/09     /  /     2,4,15,16                      0     5,058,214  DDJ             0           0           0                                         0        /  /                           /  /             
11-0467   Reconstruction               0-006-023  03/19/12     DONE    DONE       DONE      12/08/11   12/05/11   12/01/11   05/17/11   2,4,7,9,155,16           980,000       980,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/04/12                       11/04/13           
11-1393   Reconstruction               0-006-024  01/30/13     DONE    DONE       DONE      06/12/12   06/06/12   12/21/11   12/13/11   155,15,16                503,652             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC       503,652        /  /                           /  /             
12-0900   Reconstruction               0-006-025  09/12/13     DONE    DONE       DONE      02/21/13   02/21/13   05/17/12   05/15/12   2,4,7,9,10,155,16        275,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0551   Reconstruction               0-006-026  06/04/14     DONE    DONE       DONE      10/16/13   10/10/13   05/23/13   05/21/13   10,155,15,16             263,965             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-006-027                                              /  /       /  /     06/17/14     /  /     9,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Junior/Senior High:
09-0199   Reconstruction               0-007-036  10/26/09     DONE    DONE       DONE      09/14/09   09/08/09   07/30/09   09/25/07   16                       130,000       130,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      05/11/10                         /  /             
09-1107   Reconstruction               0-007-037  04/29/10     DONE    DONE       DONE      03/18/10   03/12/10   11/18/09   12/08/09   2,8,9,13,155,15,16       814,952       814,952  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/08/11                         /  /             
  -       Reconstruction               0-007-038                                              /  /       /  /     03/15/10     /  /     2,7                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             
10-0828   Reconstruction               0-007-039  06/07/11     DONE    DONE       DONE      02/08/11   02/04/11   11/02/10   12/08/09   8,16                     265,500       265,500  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/20/11                       10/05/11           
11-0468   Reconstruction               0-007-040  03/19/12     DONE    DONE       DONE      12/08/11   12/05/11   12/01/11   05/17/11   2,4,7,8,9,10,155,15,     450,000       450,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/04/12                       11/04/13           
11-0818   Reconstruction               0-007-041  04/30/12     DONE    DONE       DONE      02/15/12   02/14/12   12/01/11   09/25/07   2,7                      270,000       270,000  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      02/01/13                       04/11/13           
11-1392   Reconstruction               0-007-042  01/30/13     DONE    DONE       DONE      06/12/12   06/06/12   12/21/11   12/13/11   9,155,15,16            2,345,681     2,345,681  DDJ             0           0           0 John A Grillo-ARCHITECTS PC     2,345,681        /  /                           /  /             
12-0901   Reconstruction               0-007-043  09/12/13     DONE    DONE       DONE      02/21/13   02/21/13   05/17/12   05/15/12   2,4,7,9,155,15,16        636,250             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0552   Reconstruction               0-007-044  06/04/14     DONE    DONE       DONE      10/16/13   10/10/13   05/23/13   05/21/13   2,155,15,16              428,452             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-007-045                                              /  /       /  /     06/17/14     /  /     2,4,7,8,9,10,14,155,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Storage Building:
13-0553   New Construction             2-016-001  06/04/14     DONE    DONE       DONE      10/16/13   10/10/13   05/23/13   05/21/13   02 - 16                   50,000             0  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Districtwide:
11-1065   Reconstruction               7-999-006  04/23/12     DONE    DONE       DONE      04/04/12   03/28/12   12/01/11   05/17/11   16                       148,900       148,900  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      10/01/12                       02/04/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HUNTINGTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-03-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Huntington High School:
12-0923   Reconstruction               0-001-027  12/13/13     DONE    DONE       DONE      02/28/13   02/22/13   11/21/12   05/15/12   2,8,9,155,15,16          480,000       480,000  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
09-0633   Reconstruction               0-001-039  04/23/10     DONE    DONE       DONE      12/29/09   12/21/09   08/14/08   05/19/09   8,9                       46,810        46,810  JOD             0           0           0 Burton Behrendt Smith                   0      06/29/11                         /  /             
10-0534   Reconstruction               0-001-040  01/13/11     DONE    DONE       DONE      12/06/10   11/22/10   04/30/10   05/15/07   8,16                      25,900        25,900  JOD             0           0      25,900 Burton Behrendt Smith                   0      09/09/11                         /  /             
12-0844   Reconstruction               0-001-041  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   4,8,9,155,15,16          335,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1232   Reconstruction               0-001-042               DONE    STARTED    UNREVIEWED02/14/14   02/13/14   07/29/13   05/20/13   2,4,7,9,10,15,16               0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-001-043                                              /  /       /  /     05/22/14     /  /     2                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Flower Hill Elementary:
09-0634   Reconstruction               0-002-017  04/23/10     DONE    DONE       DONE      12/29/09   12/21/09   08/12/08   05/19/09   8,9                       29,000        29,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/08/11                         /  /             
11-0520   Reconstruction               0-002-018  02/22/12     DONE    DONE       DONE      12/22/11   12/19/11   06/08/11   06/06/11   15                       215,000       215,000  JOD             0           0           0 Burton Behrendt Smith                   0      09/25/12                       01/04/13           
12-0845   Reconstruction               0-002-019  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   9,16                      25,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Southdown Primary School:
09-0635   Reconstruction               0-003-017  04/23/10     DONE    DONE       DONE      12/29/09   12/21/09   08/12/08   05/19/09   8,9                       29,000        29,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/29/11                         /  /             
12-0846   Reconstruction               0-003-018  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   2,9,16                   630,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Woodhull Intermediate:
10-0535   Reconstruction               0-004-014  01/13/11     DONE    DONE       DONE      12/06/10   11/22/10   04/30/10   05/15/07   8,16                      17,934        17,934  JOD             0           0      17,934 Burton Behrendt Smith                   0        /  /                           /  /             
11-0521   Reconstruction               0-004-015  02/22/12     DONE    DONE       DONE      12/22/11   12/19/11   06/07/11   06/06/11   15                       215,000       215,000  JOD             0           0           0 Burton Behrendt Smith                   0      12/31/12                       01/24/13           
12-0847   Reconstruction               0-004-016  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   2,9,16                   185,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1233   Reconstruction               0-004-017               DONE    STARTED    UNREVIEWED02/14/14   02/13/14   08/05/13   05/21/13   16                             0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-004-018                                              /  /       /  /     10/21/13     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-019                                              /  /       /  /     05/22/14     /  /     8                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Washington Elementary:
09-0636   Reconstruction               0-009-017  04/23/10     DONE    DONE       DONE      12/29/09   12/21/09   08/12/08   05/19/09   8,9                       29,000        29,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/08/11                         /  /             
12-0848   Reconstruction               0-009-018  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   2,9,16                   350,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Jefferson Elementary:
09-0637   Reconstruction               0-013-012  04/23/10     DONE    DONE       DONE      12/29/09   12/21/09   08/12/08   05/19/09   8,9,10,14,15,16          235,000       235,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/08/11                         /  /             
11-0522   Reconstruction               0-013-013  02/22/12     DONE    DONE       DONE      12/22/11   12/19/11   06/08/11   06/06/11   15                       215,000       215,000  JOD             0           0           0 Burton Behrendt Smith                   0      11/06/12                       01/04/13           
12-0849   Reconstruction               0-013-014  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   9,16                      25,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1234   Reconstruction               0-013-015               DONE    STARTED    UNREVIEWED02/14/14   02/13/14   07/29/13   05/21/13   2,16                           0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          J. Taylor Finley:
10-0536   Reconstruction               0-014-021  01/13/11     DONE    DONE       DONE      12/06/10   11/22/10   04/30/10   05/15/10   8,16                      17,934        17,934  JOD             0           0      17,934 Burton Behrendt Smith                   0        /  /                           /  /             
12-0850   Reconstruction               0-014-022  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   9,16                     242,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1235   Reconstruction               0-014-023               DONE    STARTED    UNREVIEWED02/14/14   02/13/14   07/29/13   05/21/13   2,4,8,9,10,15,16               0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Jack Abrams Interm.(fka Huntington I:
10-0537   Reconstruction               0-017-014  01/13/11     DONE    DONE       DONE      12/06/10   11/22/10   04/30/10   05/15/07   8,16                      17,934        17,934  JOD             0           0      17,934 Burton Behrendt Smith                   0      09/09/11                         /  /             
12-0851   Reconstruction               0-017-015  09/24/13     DONE    DONE       DONE      02/15/13   02/14/13   05/21/12   05/15/12   16                        27,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1236   Reconstruction               0-017-016               DONE    STARTED    UNREVIEWED02/14/14   02/13/14   07/29/13   05/21/13   15,16                          0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Woodhull - Leased Modular:
10-0042   Reconstruction               0-021-001  07/28/10     DONE    DONE       DONE      07/26/10   07/15/10   04/30/10   05/18/10                            255,000             0  JOD             0           0           0 Burton Behrendt Smith                   0      01/18/11                         /  /             

          Container #1 @ Woodhull:
12-1011DB Discovered Building          2-022-001  04/10/13     DONE    DONE       DONE      03/25/13   03/25/13   03/16/12     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Container #2 @ Woodhull:
12-1012DB Discovered Building          2-023-001  04/10/13     DONE    DONE       DONE      03/25/13   03/25/13   03/16/12     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Container #3 @ Woodhull:
12-1013DB Discovered Building          2-024-001  04/10/13     DONE    DONE       DONE      03/25/13   03/25/13   03/16/12     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          District-Wide:
14-0080   Reconstruction               7-999-001                         UNREVIEWED         07/29/14   07/29/14   05/22/14   05/20/14   16                             0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHPORT-EAST NORTHPORT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-04-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Dickenson Ave. Elementary:
12-0837   Reconstruction               0-002-014  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   09/25/12   09/19/12   2,10,155,15,16           750,000             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1202   Reconstruction               0-002-016               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          East Northport Middle School:
10-0158   Reconstruction               0-003-017  11/04/10     DONE    DONE       DONE      08/26/10   08/12/10   07/10/08   05/18/10   8                        838,000       838,000  HCM             0           0           0 Burton Behrendt Smith                   0      04/04/12                       12/31/12           
  -       Reconstruction               0-003-018                                              /  /       /  /     09/25/12     /  /     2,9,10                         0    12,736,234  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-019                                              /  /       /  /     06/22/11     /  /     155,16                         0    12,736,234  HCM             0           0           0                                         0        /  /                           /  /             
11-1111   Reconstruction               0-003-020  05/16/12     DONE    DONE       DONE      04/11/12   04/06/12   07/05/11   05/17/11   2,16                     987,500       987,500  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
12-0838   Reconstruction               0-003-021  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   05/18/12   05/15/12   155                      342,500             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-003-022                                              /  /       /  /     07/30/13     /  /     2,9,10,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1203   Reconstruction               0-003-023               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Fifth Ave. Elementary:
10-1066   Reconstruction               0-004-019  03/29/11     DONE    DONE       DONE      03/18/11   03/16/11   05/21/10   05/18/10   155                      428,283       428,283  HCM             0           0           0 Burton Behrendt Smith                   0      01/06/12                       06/13/13           
13-1204   Reconstruction               0-004-020               DONE    DONE       UNREVIEWED02/11/14   02/10/14     /  /     12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Norwood Ave. Elementary:
13-1205   Reconstruction               0-005-018               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Laurel Ave-Admin office:
  -       Reconstruction               0-006-020                                              /  /       /  /     06/22/11     /  /     4                              0             0  HCM             0           0           0                                         0        /  /                           /  /             
12-0661   Reconstruction               0-006-021  03/01/13     DONE    DONE       DONE      01/10/13   01/10/13   02/24/12   05/18/10   16                       162,000             0  HCM             0           0     117,125 Burton Behrendt Smith                   0        /  /                           /  /             
12-0839   Reconstruction               0-006-022  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   05/18/12   05/15/12   15,16                    125,000             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1206   Reconstruction               0-006-023               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Ocean Avenue Elementary:
10-0159   Reconstruction               0-007-015  11/04/10     DONE    DONE       DONE      08/26/10   08/12/10   07/10/08   05/18/10   8                        189,191       189,191  HCM             0           0           0 Burton Behrendt Smith                   0      04/04/12                       12/31/12           
12-0840   Reconstruction               0-007-016  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   05/18/12   05/15/12   9,13,15                  200,000             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-007-017                                              /  /       /  /     07/30/13     /  /     2,4,16                         0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1207   Reconstruction               0-007-018               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Northport Middle School:
  -       Reconstruction               0-008-016                                              /  /       /  /     09/25/12     /  /     9,155,15,16                    0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-017                                              /  /       /  /     09/25/12     /  /     2,9,10,16                      0             0  JMB             0           0           0                                         0        /  /                           /  /             
12-0042   Reconstruction               0-008-019  12/06/12     DONE    DONE       DONE      07/19/12   07/11/12   07/05/11   05/17/11   2,16                     362,500             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
12-0841   Reconstruction               0-008-020  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   05/18/12   05/15/12   155                      747,500             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-008-021                                              /  /       /  /     07/30/13     /  /     2,9,16                         0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1208   Reconstruction               0-008-022               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Pulaski Rd. Elementary:
13-1209   Reconstruction               0-009-016               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Northport High School:
09-0604   Alterations                  0-010-024  04/07/10     DONE    DONE       DONE      12/23/09   12/17/09   03/04/09   06/16/08   02 - 16                   40,000        40,000  HCM             0           0           0 Burton Behrendt Smith                   0      09/14/10                         /  /             
10-0662   Reconstruction               0-010-025  01/25/11     DONE    DONE       DONE      12/30/10   12/23/10   05/21/10   05/18/10   4                        100,000       100,000  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-010-026                                              /  /       /  /     12/16/11     /  /     16                             0    59,448,376  HCM             0           0           0                                         0        /  /                           /  /             
12-0842   Reconstruction               0-010-027  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   05/18/12   05/15/12   2,9,10,155             1,275,000             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-010-028                                              /  /       /  /     07/30/13     /  /     2,8,16                         0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1210   Reconstruction               0-010-029               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Bellerose Elementary:
12-0843   Reconstruction               0-019-014  12/12/13     DONE    DONE       DONE      02/14/13   02/14/13   05/18/12   05/15/12   2,155                    600,000             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1211   Reconstruction               0-019-015               DONE    DONE       UNREVIEWED02/11/14   02/10/14   11/08/13   12/09/13   155,15,16                      0             0  JMB             0           0           0 ECG Engineering, LLC                    0        /  /                           /  /             

          Container @ Ocean Ave Elem:
11-0214DB Discovered Building          2-049-001  10/05/11     DONE    DONE       DONE      10/05/11   09/28/11   06/10/11     /  /                                    0             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage Container:
12-0788   New Construction             2-050-001  01/13/13     DONE    DONE       DONE      02/07/13   02/04/13     /  /       /  /     02 - 16                        0             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Northport Public Library:
10-1453   Reconstruction               6-001-004  08/17/11     DONE    DONE       DONE      07/01/11   06/28/11   06/28/11   06/15/11   2,4                       45,000             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             
11-0976   Reconstruction               6-001-005  06/15/12     DONE    DONE       DONE      03/16/12   03/15/12   10/05/11   06/15/11   8,9,155,15,16             34,000             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HALF HOLLOW HILLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-05-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sunquam School:
09-0434   Reconstruction               0-001-013  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16              465,529       465,529  HCM             0           0           0 ECG Engineering, LLC              465,529      02/22/13                       06/28/13           
10-0350   Reconstruction               0-001-014  02/14/11     DONE    DONE       DONE      10/12/10   10/04/10   05/12/10   05/18/10   4,7,155,15,16            782,000       782,000  HCM             0           0           0 Wiedersum Associates Architec           0      10/01/12                       06/04/12           
10-1253   Reconstruction               0-001-015  06/27/11     DONE    DONE       DONE      05/10/11   05/03/11   04/13/11   05/17/11   4,7,155,15,16            890,477       890,477  HCM             0           0           0 James M. Campbell Architects            0      11/30/12                       07/10/13           

          Forest Park ES(closed 6/2014):
12-1089   Reconstruction               0-002-014  07/25/13     DONE    DONE       DONE      04/11/13   04/08/13   12/04/12   05/15/12   2,7,155                  400,000             0  DDJ             0           0           0 James M. Campbell Architects            0        /  /                           /  /             
09-0435   Reconstruction               0-002-019  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16              493,651       493,651  HCM             0           0           0 ECG Engineering, LLC              493,651      02/22/13                       06/28/13           

          High School East:
12-1091   Reconstruction               0-006-018  07/25/13     DONE    DONE       DONE      04/11/13   04/08/13   12/04/12   05/15/12   2,4,8,9,15               109,000       109,000  DDJ             0           0           0 James M. Campbell Architects            0        /  /                           /  /             
09-0436   Reconstruction               0-006-032  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,8,155,15,16          2,164,575     2,164,575  HCM             0           0           0 ECG Engineering, LLC            2,164,575      02/22/13                       06/28/13           
  -       Reconstruction               0-006-033                                              /  /       /  /     06/19/14     /  /     2,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Manasquan School (see 1-007):
09-0437   Reconstruction               0-007-012  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16              559,110       559,110  HCM             0           0           0 ECG Engineering, LLC              559,110      02/22/13                       06/28/13           
09-1323   Reconstruction               0-007-013  09/03/10     DONE    DONE       DONE      04/16/10   04/13/10   08/19/09   05/19/09   2,8,9,155,15,16          212,000       212,000  HCM             0           0           0 Wiedersum Associates Architec           0      09/01/11                       05/25/12           

          Candlewood Junior High:
09-0438   Reconstruction               0-008-019  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16              786,972       786,972  HCM             0           0           0 ECG Engineering, LLC              786,972      02/22/13                       06/28/13           
09-1324   Reconstruction               0-008-020  09/03/10     DONE    DONE       DONE      04/16/10   04/13/10   08/18/09   05/19/09   2,8,9,10,155,15,16       300,000       300,000  HCM             0           0           0 Wiedersum Associates Architec           0      09/01/11                       05/25/12           

          Otsego Avenue Elementary:
09-0439   Reconstruction               0-011-016  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16            1,167,814     1,167,814  HCM             0           0           0 ECG Engineering, LLC            1,167,814      02/22/13                       06/28/13           

          Paumanok School:
09-0440   Reconstruction               0-014-018  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16            1,163,886     1,163,886  HCM             0           0           0 ECG Engineering, LLC            1,163,886      02/22/13                       06/28/13           

          Signal Hill School:
09-0441   Reconstruction               0-015-018  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16              545,269       545,269  HCM             0           0           0 ECG Engineering, LLC              545,269      02/20/13                       06/28/13           
09-1325   Reconstruction               0-015-019  09/03/10     DONE    DONE       DONE      04/16/10   04/13/10   08/19/09   05/19/09   2,8,9,13,155,15,16       450,500       450,500  HCM             0           0           0 Wiedersum Associates Architec           0      09/01/11                       05/25/12           

          Vanderbilt Elementary School:
09-0442   Reconstruction               0-016-017  10/01/10     DONE    DONE       DONE      11/18/09   11/16/09   07/20/09   07/01/09   2,155,15,16            1,225,302     1,225,302  HCM             0           0           0 ECG Engineering, LLC            1,225,302      02/22/13                       06/28/13           

          West Hollow Middle School:
09-0443   Reconstruction               0-017-016  10/01/10     DONE    DONE       DONE      11/19/09   11/16/09   07/20/09   07/01/09   2,155,15,16            3,178,349     3,178,349  HCM             0           0           0 ECG Engineering, LLC            3,178,349      02/22/13                       06/28/13           
13-0644   Reconstruction               0-017-017  02/10/14     DONE    DONE       DONE      10/28/13   10/28/13   06/13/13   05/21/13   2,9,16                 1,000,000             0  DDJ             0           0           0 James M. Campbell Architects            0        /  /                           /  /             
  -       Reconstruction               0-017-018                                              /  /       /  /     06/19/14     /  /     7,8,9,16                       0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Chestnut Hill(bldg closed 6/2014):
09-0444   Reconstruction               0-018-016  10/01/10     DONE    DONE       DONE      11/19/09   11/16/09   07/20/09   07/01/09   2,155,15,16            1,243,171     1,243,171  HCM             0           0           0 ECG Engineering, LLC            1,243,171      02/22/13                       06/28/13           
  -    XX Reconstruction               0-018-017                         CANCELLED            /  /       /  /     02/03/10     /  /     2                              0    10,737,873  HCM             0           0           0                                         0        /  /                           /  /             

          Natatorium:
09-0445   Reconstruction               0-020-008  10/01/10     DONE    DONE       DONE      11/19/09   11/16/09   07/20/09   07/01/09   2,155,15,16              639,968       639,968  HCM             0           0           0 ECG Engineering, LLC              639,968      02/22/13                       06/28/13           
12-1090   Reconstruction               0-020-009  07/25/13     DONE    DONE       DONE      04/11/13   04/08/13   12/04/12   05/15/12   7,9                      175,000             0  DDJ             0           0           0 James M. Campbell Architects            0        /  /                           /  /             

          High School West:
09-0446   Reconstruction               0-021-015  10/01/10     DONE    DONE       DONE      11/19/09   11/16/09   07/20/09   07/01/09   2,155,15,16            2,406,820     2,406,820  HCM             0           0           0 ECG Engineering, LLC            2,406,820      02/22/13                       04/10/13           

          Administration Bldg (fmly 0-007):
  -       Reconstruction               1-007-001                                              /  /       /  /     06/19/14     /  /     2,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Transportation Building:
09-0447   Reconstruction               5-003-004  10/01/10     DONE    DONE       DONE      11/19/09   11/16/09   07/20/09   07/01/09   2,155,15,16              359,584       359,584  HCM             0           0           0 ECG Engineering, LLC              359,584      02/22/13                       06/28/13           
09-0177   Reconstruction               5-003-005  09/17/09     DONE    DONE       DONE      08/31/09   08/28/09   07/31/09   05/18/04   15                       250,000       250,000  HCM             0           0           0 Wiedersum Associates Architec           0      09/08/10                         /  /             

          Half Hollow Hills Community Library:
09-1250   Reconstruction               6-009-007  08/18/10     DONE    DONE       DONE      04/06/10   04/02/10   12/21/09     /  /     7,16                     600,000             0  HCM             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             
12-0181   Reconstruction               6-009-008  01/30/13     DONE    DONE       DONE      09/18/12   09/14/12   07/17/12   09/24/12   155,16                   195,000             0  DDJ             0           0           0 DESIGN & CONSTRUCTION SERVICE           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HARBORFIELDS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-06-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
10-0539   Reconstruction               0-001-023  07/13/11     DONE    DONE       DONE      12/06/10   11/22/10   06/01/10   06/04/09   8,155,15,16            1,296,859     1,296,859  HCM             0           0           0 Burton Behrendt Smith           1,296,859      09/11/12                       10/23/12           
  -       Reconstruction               0-001-024                                              /  /       /  /     09/23/13     /  /     2,9                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Washington Drive School:
10-0540   Reconstruction               0-005-003  07/13/11     DONE    DONE       DONE      12/06/10   11/22/10   06/01/10   06/04/09   8,155,15,16              532,438       532,438  HCM             0           0           0 Burton Behrendt Smith             532,438      09/11/12                       10/12/12           

          Oldfield Middle School:
10-0541   Reconstruction               0-007-020  07/13/11     DONE    DONE       DONE      12/06/10   11/22/10   06/01/10   06/04/09   8,155,15,16              892,980       892,980  HCM             0           0           0 Burton Behrendt Smith             892,980      09/11/12                       10/23/12           

          T. J. Lahey Elementary:
10-0542   Reconstruction               0-011-012  07/13/11     DONE    DONE       DONE      12/06/10   11/22/10   06/01/10   06/04/09   8,155,15,16            1,680,373     1,680,373  HCM             0           0           0 Burton Behrendt Smith           1,680,373      09/11/12                       10/23/12           

          District-wide:
09-1156   Reconstruction               7-999-002  10/15/10     DONE    DONE       DONE      03/26/10   03/22/10   09/28/09   10/27/09   10                       479,850       479,850  HCM             0           0     216,150 Burton Behrendt Smith                   0      02/01/12                       01/06/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COMMACK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-10-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cedar Rd School:
11-0625   Reconstruction               0-004-008  06/21/12     DONE    DONE       DONE      01/10/12   01/06/12   09/28/11   09/01/11   2,155,15,16              855,912       855,912  JOD             0           0           0 ECG Engineering, LLC              855,912        /  /                           /  /             

          Old Farms School:
11-0074   Reconstruction               0-006-008  08/12/11     DONE    DONE       DONE      07/28/11   07/28/11   05/19/11   06/19/01   2,10                      97,125             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
11-0626   Reconstruction               0-006-009  06/21/12     DONE    DONE       DONE      01/10/12   01/06/12   09/28/11   09/01/11   2,155,15,16              251,508       251,508  JOD             0           0           0 ECG Engineering, LLC              251,508        /  /                           /  /             

          North Ridge School:
09-0147   Reconstruction               0-007-009  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                      45,052        45,052  JOD             0           0      16,354 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0148   Reconstruction               0-007-010  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    113,589       113,589  JOD             0           0      41,233 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0627   Reconstruction               0-007-011  06/21/12     DONE    DONE       DONE      01/09/12   01/06/12   09/28/11   09/01/11   2,7,155,15,16          1,951,047     1,951,047  JOD             0           0           0 ECG Engineering, LLC            1,951,047        /  /                           /  /             
13-1414   Reconstruction               0-007-012  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                        39,000             0  DDJ             0           0      14,160 Burton Behrendt Smith                   0        /  /                           /  /             

          North Senior High School:
09-0116   Reconstruction               0-008-017  03/31/10     DONE    DONE       DONE      08/12/09   08/11/09   01/26/09   10/16/08   16                       722,283       722,283  JOD             0           0     262,189 Burton Behrendt Smith                   0      01/27/11                       06/28/13           
09-0149   Reconstruction               0-008-018  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                     206,610       206,610  JOD             0           0      75,000 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0150   Reconstruction               0-008-019  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    574,662       574,662  JOD             0           0     208,602 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0628   Reconstruction               0-008-020  06/21/12     DONE    DONE       DONE      01/09/12   01/06/12   09/28/11   09/01/11   2,8,155,15,16          3,218,357     3,218,357  JOD             0           0           0 ECG Engineering, LLC            3,218,357        /  /                           /  /             
12-0969   Reconstruction               0-008-021  07/11/13     DONE    DONE       DONE      03/14/13   03/14/13   01/15/13   06/19/01   2,4,9                    436,400       436,400  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1415   Reconstruction               0-008-022  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                       226,000             0  DDJ             0           0      82,052 Burton Behrendt Smith                   0        /  /                           /  /             

          Wood Park School:
09-0151   Reconstruction               0-009-009  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                      50,707        50,707  JOD             0           0      18,407 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0152   Reconstruction               0-009-010  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    120,402       120,402  JOD             0           0      43,706 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0629   Reconstruction               0-009-011  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16            1,141,455     1,141,455  JOD             0           0           0 ECG Engineering, LLC            1,141,455        /  /                           /  /             
13-1416   Reconstruction               0-009-012  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                        30,000        30,000  DDJ             0           0      10,900 Burton Behrendt Smith                   0        /  /                           /  /             
13-0869   Reconstruction               0-009-013  06/05/14     DONE    DONE       DONE      12/09/13   12/06/13   08/20/13   06/19/01   2,15,16                        0             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          SMITH'S Lane Elementary:
11-0630   Reconstruction               0-011-006  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16              247,964       247,964  JOD             0           0           0 ECG Engineering, LLC              247,964        /  /                           /  /             

          Long Acres School:
11-0631   Reconstruction               0-012-009  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/11/11   2,155,15,16              413,479       413,479  JOD             0           0           0 ECG Engineering, LLC              413,479        /  /                           /  /             

          Indian Hollow School:
09-0153   Reconstruction               0-014-008  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                      39,160        39,160  JOD             0           0      14,216 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0154   Reconstruction               0-014-009  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    167,291       167,291  JOD             0           0      60,726 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0632   Reconstruction               0-014-010  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16            1,228,730     1,228,730  JOD             0           0           0 ECG Engineering, LLC            1,228,730        /  /                           /  /             
13-1417   Reconstruction               0-014-011  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                        18,000             0  DDJ             0           0       6,530 Burton Behrendt Smith                   0        /  /                           /  /             

          Sagtikos School:
11-0633   Reconstruction               0-017-006  06/21/12     DONE    DONE       DONE      01/06/12   01/06/12   09/28/11   09/01/11   2,8,155,15,16          1,998,047     1,998,047  JOD             0           0           0 ECG Engineering, LLC            1,998,047        /  /                           /  /             

          Rolling Hills School:
09-0155   Reconstruction               0-023-010  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                      41,711        41,711  JOD             0           0      15,142 Burton Behrendt Smith                   0      07/31/12                       10/04/13           
09-0156   Reconstruction               0-023-011  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    100,207       100,207  JOD             0           0      36,375 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0634   Reconstruction               0-023-012  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16              474,300       474,300  JOD             0           0           0 ECG Engineering, LLC              474,300        /  /                           /  /             
13-1418   Reconstruction               0-023-013  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                        23,780             0  DDJ             0           0       8,630 Burton Behrendt Smith                   0        /  /                           /  /             

          eommack M.S. ( fmly HS South):
09-0117   Reconstruction               0-027-012  03/31/10     DONE    DONE       DONE      08/12/09   08/11/09   01/26/09   10/16/08   16                       722,283       722,283  JOD             0           0     262,189 Burton Behrendt Smith                   0      01/27/11                       06/28/13           
09-0157   Reconstruction               0-027-013  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                     218,871       218,871  JOD             0           0      79,451 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0158   Reconstruction               0-027-014  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    502,551       502,551  JOD             0           0     182,427 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0635   Reconstruction               0-027-015  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16            2,404,238     2,404,238  JOD             0           0           0 ECG Engineering, LLC            2,404,238        /  /                           /  /             
12-0127   Reconstruction               0-027-016  02/13/13     DONE    DONE       DONE      08/28/12   08/21/12   10/14/11   06/19/01   4,9,10                   358,335       358,335  JOD             0           0           0 Burton Behrendt Smith                   0      06/26/13                       08/27/13           
12-0970   Reconstruction               0-027-017  07/11/13     DONE    DONE       DONE      03/14/13   03/14/13   01/15/13   06/19/01   2,4,9                    258,685       258,685  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1419   Reconstruction               0-027-018  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                       139,000             0  DDJ             0           0      50,470 Burton Behrendt Smith                   0        /  /                           /  /             

          Burr Rd. Intermediate (fmly JH):
09-0292   Reconstruction               0-035-010  11/23/09     DONE    DONE       DONE      10/06/09   10/05/09   09/27/07   06/19/01   9,10                     663,079       663,079  MGL             0           0           0 Burton Behrendt Smith                   0      08/08/11                       06/28/13           
09-0159   Reconstruction               0-035-012  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                      99,621        99,621  JOD             0           0      36,163 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0118   Reconstruction               0-035-013  03/31/10     DONE    DONE       DONE      08/12/09   08/11/09   01/26/09   10/16/08   16                       722,283       722,283  JOD             0           0     262,189 Burton Behrendt Smith                   0      01/27/11                       06/28/13           
09-0160   Reconstruction               0-035-014  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    253,242       253,242  JOD             0           0      91,927 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0636   Reconstruction               0-035-015  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16            1,411,448     1,411,448  JOD             0           0           0 ECG Engineering, LLC            1,411,448        /  /                           /  /             
12-0971   Reconstruction               0-035-016  07/11/13     DONE    DONE       DONE      03/14/13   03/14/13   01/15/13   06/19/01   4,9                      118,100       118,100  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1420   Reconstruction               0-035-017  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                        45,000             0  DDJ             0           0      16,340 Burton Behrendt Smith                   0        /  /                           /  /             

          Sawmill Int.(fmly Jr.HS):
09-0293   Reconstruction               0-036-009  11/23/09     DONE    DONE       DONE      10/06/09   10/05/09   10/11/07   06/19/01   155,15,16                688,200       688,200  MGL             0           0           0 Burton Behrendt Smith                   0      08/08/11                       06/28/13           
09-0070   Reconstruction               0-036-010  02/04/10     DONE    DONE       DONE      07/22/09   07/16/09   01/26/09   10/16/08   16                       722,283       722,283  JOD             0           0     262,189 Burton Behrendt Smith                   0      04/18/11                       06/28/13           
09-0027   Reconstruction               0-036-011  02/22/10     DONE    DONE       DONE      07/03/09   07/03/09   01/26/09   10/16/08   2,7                    2,921,968     2,921,968  JOD             0           0   1,060,674 Burton Behrendt Smith                   0      04/11/11                       06/28/13           
09-0161   Reconstruction               0-036-012  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   8,16                      73,425        73,425  JOD             0           0      26,654 Burton Behrendt Smith                   0      07/31/12                       12/04/13           
09-0162   Reconstruction               0-036-013  03/10/10     DONE    DONE       DONE      08/25/09   08/20/09   01/26/09   10/16/08   10,16                    236,617       236,617  JOD             0           0      85,892 Burton Behrendt Smith                   0      02/08/11                       06/28/13           
11-0637   Reconstruction               0-036-014  06/21/12     DONE    DONE       DONE      01/11/12   01/06/11   09/28/11   09/01/11   2,155,15,16            1,168,330     1,168,330  JOD             0           0           0 ECG Engineering, LLC            1,168,330        /  /                           /  /             
12-0972   Reconstruction               0-036-015  07/11/13     DONE    DONE       DONE      03/14/13   03/14/13   01/15/13   06/19/01   4,9                      119,100       119,100  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1421   Reconstruction               0-036-016  05/29/14     DONE    DONE       DONE      04/01/14   03/27/14   07/18/13   10/16/08   16                        45,000             0  DDJ             0           0      16,340 Burton Behrendt Smith                   0        /  /                           /  /             

          Maintenance Office:
11-0638   Reconstruction               1-002-003  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16               61,458             0  JOD             0           0           0 ECG Engineering, LLC               61,458        /  /                           /  /             

          Hubbs Administration:
09-0028   Additions and Alterations    1-015-004  05/11/10     DONE    DONE       DONE      07/08/09   07/07/09   05/30/07   06/19/01   02 - 16                1,506,432             0  MGL             0           0           0 Burton Behrendt Smith                   0      08/02/11                       06/28/13           
11-0639   Reconstruction               1-015-008  06/21/12     DONE    DONE       DONE      01/11/12   01/06/12   09/28/11   09/01/11   2,155,15,16              341,880             0  JOD             0           0           0 ECG Engineering, LLC              341,880        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH HUNTINGTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-04-13-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Birchwood Intermediate:
09-1235   Reconstruction               0-001-021  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16              971,601       971,601  DDJ             0           0           0 ECG Engineering, LLC              971,601      09/10/12                       09/26/12           
10-0561   Additions and Alterations    0-001-022  06/08/11     DONE    DONE       DONE      12/08/10   11/26/10   10/25/10   03/03/07   02 - 16                  568,946       568,946  DDJ             0           0           0 H2M Group                               0      04/12/12                       08/20/12           
10-0517   Reconstruction               0-001-023  01/27/11     DONE    DONE       DONE      12/03/10   11/19/10     /  /     03/03/07                            400,635       400,635  DDJ             0           0           0 H2M Group                               0      11/16/12                       01/25/13           
12-0815   Reconstruction               0-001-024  08/16/13     DONE    DONE       DONE      02/12/13   02/08/13     /  /     03/03/07   16                       107,000             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             
12-1058   Reconstruction               0-001-025                       ADDENDUM REQ'D       04/02/13   04/01/13   01/09/13   03/03/07   16                             0    10,557,918  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Maplewood Intermediate School:
11-0493   Reconstruction               0-005-020  04/27/12     DONE    DONE       DONE      12/13/11   12/08/11   03/24/09   03/03/07   2,8,9,15,16            1,710,685     1,710,685  DDJ             0           0           0 H2M Group                               0      11/14/13                       12/05/13           
09-0951   Reconstruction               0-005-021  05/27/10     DONE    DONE       DONE      02/22/10   02/18/10   11/10/09   12/04/02   2,15                     279,682       279,682  DDJ             0           0           0 H2M Group                               0      08/20/10                         /  /             
09-1236   Reconstruction               0-005-022  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16              917,641       917,641  DDJ             0           0           0 ECG Engineering, LLC              917,641      09/10/12                       09/26/12           
11-0525   Additions and Alterations    0-005-023  04/06/12     DONE    DONE       DONE      12/22/11   12/16/11   10/19/11   02/28/03   02 - 16                  461,794       316,836  DDJ             0           0           0 H2M Group                               0      04/12/13                       09/27/13           
12-1059   Reconstruction               0-005-024                       ADDENDUM REQ'D       04/02/13   04/01/13   01/09/13   03/03/07   16                             0    10,557,918  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Oakwood Elementary:
11-0524   Reconstruction               0-006-020  07/03/12     DONE    DONE       DONE      12/22/11   12/19/11   03/30/09   02/28/03   2,8,9,15,16            2,019,626     2,019,626  DDJ             0           0           0 H2M Group                               0      08/31/12                       10/09/12           
09-0948   Reconstruction               0-006-021  11/12/10     DONE    DONE       DONE      02/22/10   02/17/10   01/07/10   12/04/02   2,16                     425,425       425,425  DDJ             0           0           0 H2M Group                               0      11/16/12                       01/25/13           
09-1237   Reconstruction               0-006-022  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16              982,587       982,587  DDJ             0           0           0 ECG Engineering, LLC              982,587      09/10/12                       09/26/12           
11-0526   Additions and Alterations    0-006-023  04/06/12     DONE    DONE       DONE      12/22/11   12/16/11   10/19/11   02/28/03   02 - 16                  556,000       316,836  DDJ             0           0           0 H2M Group                               0      07/19/13                       08/08/13           
12-1060   Reconstruction               0-006-024                       ADDENDUM REQ'D       04/02/13   04/01/13   01/09/13   03/03/07   16                             0    12,260,808  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          SILAS WOOD 6TH GRADE CENTER:
07-1903   Reconstruction               0-008-027  03/28/13     DONE    DONE       DONE      04/01/08   03/25/08   10/29/07   03/03/07   2,8,9                  1,025,157     1,025,157  DDJ             0           0           0 H2M Group                               0      09/03/13                       09/27/13           
09-0952   Reconstruction               0-008-029  05/27/10     DONE    DONE       DONE      02/22/10   02/18/10   11/10/09   12/04/02   2,15                     103,007       103,007  DDJ             0           0           0 H2M Group                               0      08/29/10                         /  /             
09-0947   Reconstruction               0-008-030  11/12/10     DONE    DONE       DONE      02/22/10   02/17/10   01/07/10   03/03/07   2,16                     425,425       425,425  DDJ             0           0           0 H2M Group                               0      06/27/13                       09/27/13           
09-1238   Reconstruction               0-008-031  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16            1,093,220     1,093,220  DDJ             0           0           0 ECG Engineering, LLC            1,093,220      09/10/12                       09/26/12           

          Walt Whitman Senior High:
08-0054   Reconstruction               0-010-043  03/30/10     DONE    DONE       DONE      07/21/08   07/08/08   10/03/07   02/29/08   2,4,8,9,10,16            337,752       337,752  DDJ             0           0           0 H2M Group                               0      09/18/10                         /  /             
09-0961   Reconstruction               0-010-046  05/28/10     DONE    DONE       DONE      02/25/10   02/18/10   11/10/09   12/04/02   2,15                   1,042,012     1,042,012  DDJ             0           0           0 H2M Group                               0      06/02/11                         /  /             
09-1239   Reconstruction               0-010-047  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16            1,420,938     1,420,938  DDJ             0           0           0 ECG Engineering, LLC            1,420,938      09/10/12                       09/26/12           
09-1452   Reconstruction               0-010-048  07/29/10     DONE    DONE       DONE      05/20/10   05/18/10   04/02/10   03/07/07   2                         63,303        63,303  DDJ             0           0           0 H2M Group                               0      04/12/11                         /  /             
10-0518   Reconstruction               0-010-049  04/11/11     DONE    DONE       DONE      12/03/10   11/19/10   04/02/10   03/03/07   2,16                     228,438       228,438  DDJ             0           0           0 H2M Group                               0      09/07/11                         /  /             
12-1061   Reconstruction               0-010-050                       ADDENDUM REQ'D       04/02/13   04/01/13   01/09/13   03/03/07                                  0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Countrywood Elementary:
10-0519   Reconstruction               0-011-021  04/19/11     DONE    DONE       DONE      12/03/10   11/19/10   03/30/09   03/03/07   2,8,9,15,16            1,796,966     1,796,966  DDJ             0           0           0 H2M Group                               0      03/26/12                       06/30/13           
09-0950   Reconstruction               0-011-022  05/27/10     DONE    DONE       DONE      02/22/10   02/18/10   11/10/09   12/04/02   2,15                      78,462        78,462  DDJ             0           0           0 H2M Group                               0      08/29/10                         /  /             
09-1240   Reconstruction               0-011-023  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16              660,652       660,652  DDJ             0           0           0 ECG Engineering, LLC              660,652      09/10/12                       09/26/12           
10-0520   Reconstruction               0-011-024  04/11/11     DONE    DONE       DONE      12/03/10   11/19/10   04/02/10   03/03/07   2,13,15,16               189,376       189,376  DDJ             0           0           0 H2M Group                               0      08/10/11                         /  /             
  -       Reconstruction               0-011-025                                              /  /       /  /     10/26/10     /  /     2                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-1062   Reconstruction               0-011-026                       ADDENDUM REQ'D       04/02/13   04/01/13   01/09/13   03/03/07   16                             0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             
13-0754   Reconstruction               0-011-027  08/26/13     DONE    DONE       DONE      11/22/13   11/18/13   09/13/13   08/14/13   2,9                       62,740        62,740  DDJ             0           0           0 H2M Group                               0      08/27/13                       06/24/14           

          Stimson Middle School:
09-0953   Reconstruction               0-012-025  05/27/10     DONE    DONE       DONE      02/22/10   02/18/10   11/18/09   12/04/02   2,15                     251,173       251,173  DDJ             0           0           0 H2M Group                               0      08/29/10                         /  /             
09-0954   Reconstruction               0-012-026  11/12/10     DONE    DONE       DONE      02/22/10   02/17/10   11/18/09   03/03/07   2,16                     594,354       594,354  DDJ             0           0           0 H2M Group                               0      11/16/12                       09/18/13           
09-1208   Reconstruction               0-012-027  06/24/10     DONE    DONE       DONE      04/02/10   03/30/10   11/18/09   03/03/07   2,8,9,15,16            1,353,575     1,353,575  DDJ             0           0           0 H2M Group                               0      03/31/11                         /  /             
09-1241   Reconstruction               0-012-028  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,16                 899,223       899,223  DDJ             0           0           0 ECG Engineering, LLC              899,223      09/10/12                       09/26/12           
12-1063   Reconstruction               0-012-029                       ADDENDUM REQ'D       04/02/13   04/01/13   01/09/13   03/03/07   16                             0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             
13-1591   Reconstruction               0-012-030                       ADDENDUM REQ'D       05/30/14   05/29/14   04/23/14   02/28/03   2,8,9,10,15                    0    23,002,100  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Birchwood Portable:
09-1242   Reconstruction               0-020-002  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,7,155,15,16            611,930       611,930  DDJ             0           0           0 ECG Engineering, LLC              611,930      09/10/12                       09/26/12           

          Maplewood Portable:
09-1243   Reconstruction               0-021-002  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,7,155,15,16            634,680       634,680  DDJ             0           0           0 ECG Engineering, LLC              634,680      09/10/12                       09/26/12           

          Countrywood Portable:
09-1244   Reconstruction               0-022-002  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,7,8,155,15,16          778,609       778,609  DDJ             0           0           0 ECG Engineering, LLC              778,609      09/10/12                       09/26/12           

          Oakwood Portable:
09-1245   Reconstruction               0-023-002  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,7,155,15,16            787,421       787,421  DDJ             0           0           0 ECG Engineering, LLC              787,421      09/10/12                       09/26/12           

          Administration Bldg:
09-1246   Reconstruction               1-002-011  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16              505,989             0  DDJ             0           0           0 ECG Engineering, LLC              505,989      09/10/12                       09/26/12           
10-0521   Reconstruction               1-002-012  02/01/11     DONE    DONE       DONE      12/03/10   11/19/10   10/26/10   03/03/07   9,15                     149,800             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             
11-0546   Reconstruction               1-002-013  03/08/12     DONE    DONE       DONE      12/22/11   12/22/11   10/19/11   02/28/03   2,16                     308,500             0  DDJ             0           0           0 H2M Group                               0      06/27/13                       09/27/13           

          Public Library:
10-1435   Reconstruction               6-024-004  08/08/11     DONE    DONE       DONE      06/29/11   06/23/11   04/15/11   04/25/11   4,8,9,155,15,16          661,847             0  DDJ             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             
13-0112   Reconstruction               6-024-005  09/06/13     DONE    DONE       DONE      07/31/13   07/30/13   06/05/13   05/17/13   2,15,16                  450,000             0  DDJ             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             

          Teen Center:
09-1247   Reconstruction               7-004-004  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,16                  96,122        96,122  DDJ             0           0           0 ECG Engineering, LLC               96,122      09/10/12                       09/26/12           
11-0568XX Reconstruction               7-004-005                         CANCELLED          12/29/11   12/29/11   10/19/11   03/03/07   4                              0       591,330  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Memorial Junior High School:
09-1248   Reconstruction               7-009-015  02/15/11     DONE    DONE       DONE      04/06/10   04/01/10   01/20/10   12/09/09   2,155,15,16              677,052             0  DDJ             0           0           0 ECG Engineering, LLC              677,052      09/10/12                       09/26/12           
10-0522   Reconstruction               7-009-016  04/12/11     DONE    DONE       DONE      12/03/10   11/19/10   10/26/10   03/03/07   8,9                      508,230             0  DDJ             0           0           0 H2M Group                               0      01/12/12                         /  /             
11-0666   Reconstruction               7-009-017  04/27/12     DONE    DONE       DONE      01/17/12   01/12/12   10/19/11   03/03/07   2,16                     267,500             0  DDJ             0           0           0 H2M Group                               0      08/07/13                       09/27/13           
12-1064   Reconstruction               7-009-018                       ADDENDUM REQ'D       04/02/13   04/01/13   11/16/12   03/03/07   16                             0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             
12-0816   Reconstruction               7-009-019  08/16/13     DONE    DONE       DONE      02/12/13   02/08/13   01/09/13   03/03/07   16                       133,750             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BAY SHORE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-01-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Armory Pre-K:
12-0501   Reconstruction               0-019-001  12/13/12     DONE    DONE       DONE      11/30/12   11/30/12   11/13/12   11/20/12   2,4,7,8,9,155,15,16    1,350,000             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage Field House:
10-1097   Additions and Alterations    2-008-001  06/08/11     DONE    DONE       DONE      03/23/11   03/18/11   03/21/11     /  /     02 - 16                  181,600             0  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Bay Shore-Brightwaters Publ. Library:
13-1664   Reconstruction               6-010-005  07/22/14     DONE    DONE       DONE      06/25/14   06/24/14   05/28/14   05/27/14   8,9                       50,000             0  DDJ             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ISLIP UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-02-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sherwood Elementary:
09-0244   Reconstruction               0-002-009  02/10/10     DONE    DONE       DONE      09/22/09   09/18/09   06/11/09   02/10/09   2,8,10,155,15,16         170,510       170,510  JOD             0           0      54,734 Burton Behrendt Smith                   0      02/01/12                       06/16/14           
09-1173   Reconstruction               0-002-010  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   10/02/09   02/10/09   155,15,16                 54,125        54,125  JOD             0           0      17,374 Burton Behrendt Smith                   0      04/05/12                       01/04/13           
  -       Reconstruction               0-002-011                                              /  /       /  /     10/08/09     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             
10-1001   Reconstruction               0-002-012  07/14/11     DONE    DONE       DONE      03/08/11   03/03/11   03/26/10   05/17/11   2,4,8,9,10,155,15,16     185,500       185,500  JOD             0           0           0 Burton Behrendt Smith                   0      01/04/12                       01/04/13           
13-0091   Reconstruction               0-002-013  11/13/13     DONE    DONE       DONE      07/24/13   07/23/13   02/05/13   12/13/12   2,4,8,9                  566,073             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-002-014                                              /  /       /  /     02/05/13     /  /     2                              0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0584   Reconstruction               0-002-015                       ADDENDUM REQ'D       10/18/13   10/16/13   08/13/13   12/13/12   16                             0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1699   Reconstruction               0-002-016               DONE    STARTED    STARTED   07/03/14   06/27/14   11/19/13   12/13/12   2,4,8,9                        0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1700   Reconstruction               0-002-017               DONE    STARTED    STARTED   07/03/14   06/27/14   11/19/13   12/13/12   2,7,9                          0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-002-018                                              /  /       /  /     03/13/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-019                                              /  /       /  /     04/18/14     /  /     2,155,16                       0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Winganhauppauge Elementary:
09-0245   Reconstruction               0-003-015  02/10/10     DONE    DONE       DONE      09/22/09   09/18/09   06/11/09   02/10/09   2,4,8,10,155,15,16       114,166       114,166  JOD             0           0      36,647 Burton Behrendt Smith                   0      02/06/12                       06/16/14           
09-0553   Reconstruction               0-003-016  02/12/10     DONE    DONE       DONE      12/07/09   12/03/09   08/25/09   02/10/09   7                        562,972       562,972  JOD             0           0     180,714 Burton Behrendt Smith                   0      09/07/10                         /  /             
09-1174   Reconstruction               0-003-017  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   10/02/09   02/10/09   155,15,16                 54,125        54,125  JOD             0           0      17,374 Burton Behrendt Smith                   0      04/05/12                       08/06/12           
  -       Reconstruction               0-003-018                                              /  /       /  /     10/08/09     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0092   Reconstruction               0-003-019  11/13/13     DONE    DONE       DONE      07/24/13   07/23/13   02/05/13   12/13/12   2,4,8,9                  530,140             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-003-020                                              /  /       /  /     02/05/13     /  /     2                              0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0585   Reconstruction               0-003-021                       ADDENDUM REQ'D       10/18/13   10/16/13   08/09/13   12/13/12   16                             0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-003-022                                              /  /       /  /     01/22/14     /  /     2,4,7,8,9                      0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-023                                              /  /       /  /     03/13/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Senior High School:
09-0246   Reconstruction               0-007-013  02/10/10     DONE    DONE       DONE      09/22/09   09/18/09   06/11/09   02/10/09   8,155,15,16              119,362       119,362  JOD             0           0      38,315 Burton Behrendt Smith                   0      09/01/12                       06/16/14           
09-1175   Reconstruction               0-007-014  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   10/02/09   02/10/09   155,15,16                240,233       240,233  JOD             0           0      77,115 Burton Behrendt Smith                   0      04/05/12                       08/06/12           
  -       Reconstruction               0-007-015                                              /  /       /  /     10/08/09     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0093   Reconstruction               0-007-016  11/13/13     DONE    DONE       DONE      07/24/13   07/23/13   02/05/13   12/13/12   2,4,8,9                  419,500             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-007-017                                              /  /       /  /     02/05/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0126   Reconstruction               0-007-018  10/08/13     DONE    DONE       DONE      08/05/13   08/02/13   03/08/13   12/13/12   10                       172,000       172,000  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0586   Reconstruction               0-007-019                       ADDENDUM REQ'D       10/18/13   10/16/13   08/13/13   12/13/12   16                             0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0686   Reconstruction               0-007-020               DONE    DONE       ADD. REQ'D11/07/13   11/07/13   09/18/13   12/13/12   2,4,7,8,13,155,15,16           0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-007-021                                              /  /       /  /     09/23/13     /  /     2,4,7,8,13,155,15,16           0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-1191   Reconstruction               0-007-022                         UNREVIEWED         02/06/14   02/06/14   11/26/13   12/13/12   155,16                         0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-007-023                                              /  /       /  /     03/13/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Commack Road Elementary:
09-0247   Reconstruction               0-008-011  02/10/10     DONE    DONE       DONE      09/22/09   09/18/09   06/11/09   02/10/09   2,8,10,155,15,16         517,291       517,291  JOD             0           0     166,051 Burton Behrendt Smith                   0      09/15/10                         /  /             
09-1176   Reconstruction               0-008-012  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   10/02/09   02/10/09   155,15,16                 54,125        54,125  JOD             0           0      17,374 Burton Behrendt Smith                   0      04/05/12                       08/06/12           
  -       Reconstruction               0-008-013                                              /  /       /  /     10/08/09     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0094   Reconstruction               0-008-014  11/13/13     DONE    DONE       DONE      07/24/13   07/23/13   02/05/13   12/13/12   2,4,8,9                  687,503             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-008-015                                              /  /       /  /     02/05/13     /  /     2                              0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-0587   Reconstruction               0-008-016                       ADDENDUM REQ'D       10/18/13   10/16/13   08/13/13   12/13/12   16                             0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1620   Reconstruction               0-008-017               DONE    DONE       UNREVIEWED06/18/14   06/17/14   11/04/13   12/13/12   2,4,8,9,10,155,15,16           0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1674   Reconstruction               0-008-018               DONE    STARTED    STARTED   06/27/14   06/19/14   11/04/13   12/13/12   2,4,8,9                        0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1675   Reconstruction               0-008-019               DONE    STARTED    STARTED   06/27/14   06/19/14   01/22/14   12/13/12   2,4,7,8,9                      0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-008-020                                              /  /       /  /     03/13/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-021                                              /  /       /  /     04/18/14     /  /     2,155,16                       0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Junior High School:
09-0248   Reconstruction               0-011-011  02/10/10     DONE    DONE       DONE      09/22/09   09/18/09   06/11/09   02/10/09   8,155,15,16              146,237       146,237  JOD             0           0      46,943 Burton Behrendt Smith                   0      01/24/12                       06/16/14           
09-1177   Reconstruction               0-011-012  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   10/02/09   02/10/09   155,15,16                 54,295        54,295  JOD             0           0      17,429 Burton Behrendt Smith                   0      04/05/12                       08/06/12           
  -       Reconstruction               0-011-013                                              /  /       /  /     10/08/09     /  /     155,15,16                      0             0  JOD             0           0           0                                         0        /  /                           /  /             
12-1163   Reconstruction               0-011-014  06/28/13     DONE    DONE       DONE      05/07/13   05/06/13   02/05/13   12/13/12   2,4,7                    673,300       673,300  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0095   Reconstruction               0-011-015  11/13/13     DONE    DONE       DONE      07/24/13   07/23/13   02/05/13   12/13/12   2,4,8,9                  356,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0127   Reconstruction               0-011-016  10/08/13     DONE    DONE       DONE      08/05/13   08/02/13   03/08/13   12/13/12   10                       247,500       247,500  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0588   Reconstruction               0-011-017                       ADDENDUM REQ'D       10/18/13   10/16/13   08/09/13   12/13/12   9,16                           0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0687   Reconstruction               0-011-018               DONE    DONE       ADD. REQ'D11/07/13   11/07/13   09/18/13   12/13/12   2,4,8,13,155,15,16             0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-011-019                                              /  /       /  /     09/23/13     /  /     2,4,8,13,155,15,16             0             0  MFS             0           0           0                                         0        /  /                           /  /             
13-1192   Reconstruction               0-011-020                         UNREVIEWED         02/06/14   02/06/14   11/26/13   12/13/12   155,16                         0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-011-021                                              /  /       /  /     03/13/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Administration Building:
09-1178   Reconstruction               1-001-006  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   06/11/09   02/10/09   8,155,15,16               49,925             0  JOD             0           0           0 Burton Behrendt Smith                   0      04/05/12                       01/04/13           

          Storage @ Maintenance Building:
10-0283DB Discovered Building          2-012-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage @ Commack Elementary School:
10-0284DB Discovered Building          2-013-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage @ Elementary School Wing:
10-0285DB Discovered Building          2-014-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #1 @ Sherwood ES:
10-0286DB Discovered Building          2-015-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #2 @ Sherwood ES:
10-0287DB Discovered Building          2-016-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #1 @ HS:
10-0288DB Discovered Building          2-017-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #2 @ HS:
10-0289DB Discovered Building          2-018-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #3 @ HS:
10-0290DB Discovered Building          2-019-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #4 @ HS:
10-0291   Reconstruction               2-020-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   10/17/07     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Storage #5 @ HS:
10-0292   Reconstruction               2-021-001  04/11/11     DONE    DONE       DONE      09/29/10   09/20/10   05/14/09     /  /                                    0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Maintenance Bldg:
09-1179   Reconstruction               3-004-003  05/13/11     DONE    DONE       DONE      03/31/10   03/25/10   06/11/09   02/10/09   8,155,15,16               49,925             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Islip Public Library:
10-0028   Reconstruction               6-010-007  08/19/10     DONE    DONE       DONE      07/22/10   07/09/10   06/17/09   06/10/10   7,9,13,155,16          1,069,642             0  JOD             0           0           0 Beatty, Harvey & Associates             0        /  /                           /  /             
09-0222   Reconstruction               6-010-008  09/29/09     DONE    DONE       DONE      09/16/09   09/15/09   08/14/09   09/10/09   7                        215,868             0  JOD             0           0           0 Beatty, Harvey & Associates             0        /  /                           /  /             

          Islip HS Comfort & Concession Bldg:
13-0688   New Construction             7-022-001               DONE    DONE       ADD. REQ'D11/07/13   11/07/13   10/22/13   12/13/12   02 - 16                        0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Press Box @ HS:
13-1340   New Construction             7-023-001               DONE    DONE       UNREVIEWED03/14/14   03/14/14   03/13/14     /  /     02 - 16                        0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Districtwide:
09-0258   Reconstruction               7-999-003  10/30/09     DONE    DONE       DONE      09/22/09   09/22/09   06/11/09   02/10/09   10,16                    584,403       584,403  JOD             0           0     187,593 Burton Behrendt Smith                   0      09/02/11                       01/04/13           
09-0259   Reconstruction               7-999-004  10/30/09     DONE    DONE       DONE      09/22/09   09/22/09   06/11/09   02/10/09   10,16                    385,625       385,625  JOD             0           0     123,785 Burton Behrendt Smith                   0      02/04/11                       01/04/13           
09-0260   Reconstruction               7-999-005  10/30/09     DONE    DONE       DONE      09/22/09   09/22/09   06/11/09   02/10/09   10,16                    523,225       523,225  JOD             0           0     167,955 Burton Behrendt Smith                   0      02/06/12                       01/04/13           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST ISLIP UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-03-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Terrace Junior High:
11-0711   Reconstruction               0-002-017  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   8,9,155,15,16            722,120       775,665  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Timber Point Elementary:
11-0712   Reconstruction               0-003-009  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   4,8,9,155,15,16          457,262       635,330  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Connetquot Elementary:
11-0713   Reconstruction               0-005-009  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   4,8,9,155,15,16          286,333       286,333  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          JF Kennedy Elementary:
11-0714   Reconstruction               0-007-011  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   2,4,8,9,155,15,16        340,239       503,285  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Ruth Kinney Elementary:
11-0715   Reconstruction               0-008-011  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   4,8,9,155,15,16          516,794       483,975  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Early Childhood Center:
11-0716   Reconstruction               0-009-010  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   4,8,155,15,16            567,069       446,400  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          East Islip Senior High:
11-0656   Reconstruction               0-010-019  04/06/12     DONE    DONE       DONE      01/12/12   01/10/12   06/30/11   11/17/11   10,16                          0             0  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
11-0717   Reconstruction               0-010-020  07/05/12     DONE    DONE       DONE      01/25/12   01/19/12   09/28/11   06/20/00   2,9,155,15,16          1,312,427     1,284,930  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SAYVILLE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-04-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Old Sayville Jr. High School:
09-1582   Reconstruction               0-001-007  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/01/10   02/23/10   2,155,15,16              240,109             0  JOD             0           0           0 ECG Engineering, LLC              240,109      11/07/12                       11/19/12           

          Greene Elementary School:
12-0943   Reconstruction               0-002-009  10/22/13     DONE    DONE       DONE      03/06/13   03/04/13   12/17/12   11/29/07   4,7,8,9,155,15,16        517,000             0  MFS             0           0           0 James M. Campbell Architects            0        /  /                           /  /             

          Sunrise Drive Elementary:
09-1583   Reconstruction               0-003-015  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/01/10   02/23/10   2,7,155,15,16          1,353,635     1,353,635  JOD             0           0           0 ECG Engineering, LLC            1,353,635      11/07/12                       11/19/12           

          Sayville High School:
08-1488   Reconstruction               0-004-021  09/18/09     DONE    DONE       DONE      04/13/09   04/08/09   02/28/08   11/29/07   2,4,7,8,9,155,15,16    1,402,878     1,402,878  MGL             0           0           0 James M. Campbell Architects            0      10/21/10                       03/21/13           
09-1584   Reconstruction               0-004-023  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/01/10   02/23/10   2,8,155,15,16          1,506,828     1,506,828  JOD             0           0           0 ECG Engineering, LLC            1,506,828      11/07/12                       11/19/12           

          Cherry Ave. Elementary:
08-1377   Additions and Alterations    0-005-010  04/15/10     DONE    DONE       DONE      03/16/09   03/10/09   09/27/07   11/29/07   02 - 16                2,312,000     1,775,708  MGL             0           0           0 James M. Campbell Architects            0      09/03/11                       09/04/12           
09-1585   Reconstruction               0-005-011  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/01/10   02/23/10   2,8,155,15,16            621,721       621,721  JOD             0           0           0 ECG Engineering, LLC              621,721      11/07/12                       11/19/12           

          Lincoln Ave. Elementary:
09-1586   Reconstruction               0-006-011  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/02/10   02/23/10   2,155,15,16              642,916       642,916  JOD             0           0           0 ECG Engineering, LLC              642,916      11/07/12                       11/19/12           

          Sayville Junior High School:
09-1587   Reconstruction               0-008-017  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/01/10   02/23/10   2,155,15,16            1,833,970     1,833,970  JOD             0           0           0 ECG Engineering, LLC            1,833,970      11/07/12                       11/19/12           

          Administration Bldg:
09-1588   Reconstruction               1-011-005  03/28/11     DONE    DONE       DONE      07/06/10   06/30/10   04/01/10   02/23/10   2,8,155,15,16            967,625             0  JOD             0           0           0 ECG Engineering, LLC              967,625      11/07/12                       11/19/12           

          HS Sports Stor #1:
12-0948DB Discovered Building          2-019-001  03/08/13     DONE    DONE       DONE      03/08/13   02/27/13   10/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          HS Sports Stor #2:
12-0949DB Discovered Building          2-020-001  03/08/13     DONE    DONE       DONE      03/08/13   02/27/13   10/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          MS Drama Stor:
11-1309DB Discovered Building          2-021-001  05/22/12     DONE    DONE       DONE      05/22/12   05/04/12   10/07/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Cherry Avenue Storage Shed:
12-0947DB Discovered Building          2-022-001  03/08/13     DONE    DONE       DONE      03/08/13   02/27/13   10/14/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Garfield Avenue Maintenance Facility:
09-1530   New Construction             3-018-001  08/17/11     DONE    DONE       DONE      06/15/10   06/07/10   07/16/08   05/19/09   02 - 16                1,108,000             0  JOD             0           0           0 James M. Campbell Architects            0      05/14/13                       07/10/13           

          District Wide:
13-0167   Reconstruction               7-999-005  12/24/13     DONE    DONE       DONE      08/07/13   08/05/13   07/29/13   05/21/13   16                       500,000             0  MFS             0           0           0 James M. Campbell Architects            0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BAYPORT BLUE POINT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-05-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bayport Blue Point Elementary:
09-0897   Reconstruction               0-001-015  02/22/10     DONE    DONE       DONE      02/18/10   02/10/10   01/29/09   10/15/03   7                        126,000       126,000  DDJ             0           0           0 Wiedersum Associates Architec           0      11/26/12                       12/23/12           
11-1268   Reconstruction               0-001-016  11/21/12     DONE    DONE       DONE      05/07/12   05/04/12   03/08/12   02/07/12   2,155,15,16              778,743       778,743  DDJ             0           0           0 ECG Engineering, LLC              778,743        /  /                           /  /             

          Academy Street Elementary:
11-1269   Reconstruction               0-002-015  11/21/12     DONE    DONE       DONE      05/07/12   05/04/12   03/08/12   02/07/12   2,155,15,16              367,367       367,367  DDJ             0           0           0 ECG Engineering, LLC              367,367        /  /                           /  /             

          Bayport High School:
09-0898   Reconstruction               0-004-019  02/22/10     DONE    DONE       DONE      02/18/10   02/10/10   01/29/09   10/15/03   7                        585,000       585,000  DDJ             0           0           0 Wiedersum Associates Architec           0      11/26/12                       12/23/12           
11-1270   Reconstruction               0-004-020  11/21/12     DONE    DONE       DONE      05/07/12   05/04/12   03/08/12   02/07/12   2,8,155,15,16          1,298,166     1,298,166  DDJ             0           0           0 ECG Engineering, LLC            1,298,166        /  /                           /  /             

          Sylvan Avenue Elementary:
11-1271   Reconstruction               0-006-011  11/21/12     DONE    DONE       DONE      05/07/12   05/04/12   03/08/12   02/07/12   2,8,155,15,16            983,113       983,113  DDJ             0           0           0 ECG Engineering, LLC              983,113        /  /                           /  /             

          J. W. Young Jr. High School:
11-1272   Reconstruction               0-011-012  11/21/12     DONE    DONE       DONE      05/07/12   05/04/12   03/08/12   02/07/12   2,4,8,155,15             889,412       889,412  DDJ             0           0           0 ECG Engineering, LLC              889,412        /  /                           /  /             

          Barn:
11-1273   Reconstruction               2-012-003  11/21/12     DONE    DONE       DONE      05/07/12   05/04/12   03/08/12   02/07/12   8,15,16                   86,459             0  DDJ             0           0           0 ECG Engineering, LLC               86,459        /  /                           /  /             

          Container @ HS:
13-1588DB Discovered Building          2-017-001               UNREVIEWED
                                                                       DONE       DONE      05/29/14   05/29/14   05/29/14     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Container @ Academy St Elem School:
13-1589DB Discovered Building          2-018-001               UNREVIEWED
                                                                       DONE       DONE      05/29/14   05/29/14   05/29/14     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Container @ JW Young Jr HS:
13-1590DB Discovered Building          2-019-001               UNREVIEWED
                                                                       DONE       DONE      05/29/14   05/29/14   05/29/14     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bayport Blue Point Public Library:
10-0089   Reconstruction               6-009-005  08/10/10     DONE    DONE       DONE      08/09/10   08/05/10   07/06/10   07/14/10   7                         52,360             0  DDJ             0           0           0 Beatty, Harvey & Associates             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HAUPPAUGE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-06-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
09-0003   Additions and Alterations    0-002-024  11/02/09     DONE    DONE       DONE      07/01/09   07/01/09   01/17/08   10/15/08   02 - 16               16,481,897    14,121,526  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      01/28/11                         /  /             
11-0751   Reconstruction               0-002-027  06/25/12     DONE    DONE       DONE      02/02/12   02/01/12   01/19/11   10/15/08   2,9,155,16               647,460       647,460  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      03/01/13                       03/05/14           
  -       Reconstruction               0-002-028                                              /  /       /  /     07/01/14     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Pines Elementary School:
09-0840   Reconstruction               0-006-020  05/24/10     DONE    DONE       DONE      02/02/10   01/28/10   05/27/09   05/19/09   2,8,9,10,15,16           255,103       255,103  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      01/10/12                         /  /             
12-0739   Reconstruction               0-006-021  08/09/13     DONE    DONE       DONE      01/31/13   01/30/13   10/18/12   05/15/12   2,4,9,155,15,16          971,765             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0813   Reconstruction               0-006-022  04/01/14     DONE    DONE       DONE      12/03/13   11/25/13   06/13/13   05/21/13   8,9,16                    21,000             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Bretton Woods Elementary:
09-0841   Reconstruction               0-007-016  05/24/10     DONE    DONE       DONE      02/02/10   01/28/10   05/27/09   05/19/09   2,8,16                   146,230       146,230  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      01/10/12                         /  /             
10-0614   Reconstruction               0-007-017  04/13/11     DONE    DONE       DONE      12/23/10   12/15/10   08/10/10   05/18/10   9,16                     100,000       100,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/16/11                         /  /             
10-0461   Reconstruction               0-007-018  02/18/11     DONE    DONE       DONE      11/12/10   11/08/10   08/10/10   05/18/10   155,15,16                635,700       635,700  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/25/11                         /  /             
11-0196   Reconstruction               0-007-019  09/28/11     DONE    DONE       DONE      09/23/11   09/20/11   09/07/10   05/17/11   9,16                     250,000       250,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/15/12                       09/12/12           
  -       Reconstruction               0-007-020                                              /  /       /  /     06/16/11     /  /     9,16                           0             0  JOD             0           0           0                                         0        /  /                           /  /             
13-0814   Reconstruction               0-007-021  04/01/14     DONE    DONE       DONE      12/03/13   11/25/13   06/13/13   05/21/13   2,8,9,16                 271,000             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0649   Reconstruction               0-007-022  04/21/14     DONE    DONE       DONE      10/30/13   10/28/13   10/30/13   05/17/11   9,155,16                 204,110             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Hauppauge High School:
09-0004   Reconstruction               0-008-040  11/02/09     DONE    DONE       DONE      07/01/09   07/01/09   01/08/09   10/15/08   2,4,7,8,9,155,15,16    7,458,418     7,458,418  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/31/11                       09/29/11           
11-0752   Reconstruction               0-008-041  06/25/12     DONE    DONE       DONE      02/02/12   02/01/12   12/01/11   10/15/08   7,9,155,16               468,460       468,460  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      03/01/13                       03/05/14           
12-0740   Reconstruction               0-008-042  08/09/13     DONE    DONE       DONE      01/31/13   01/30/13   10/18/12   05/15/12   2                        250,000             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0815   Reconstruction               0-008-043  04/01/14     DONE    DONE       DONE      12/03/13   11/25/13   06/13/13   05/21/13   2,8,9,10,155,15,16       607,494             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-008-044                                              /  /       /  /     05/28/14     /  /     2,4,7,8,9,10,155,15,           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Forest Brook Elementary:
09-0842   Reconstruction               0-010-015  05/24/10     DONE    DONE       DONE      02/02/10   01/28/10   05/27/09   05/19/09   2,8,16                    98,667        98,667  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      01/10/12                         /  /             
10-0739   Reconstruction               0-010-016  02/25/11     DONE    DONE       DONE      01/25/11   01/25/11   08/10/10   05/18/10   9,15,16                  150,000       150,000  JOD             0           0           0 John A Grillo-ARCHITECTS PC             0      08/25/11                         /  /             
12-0741   Reconstruction               0-010-017  08/09/13     DONE    DONE       DONE      01/31/13   01/30/13   10/18/12   05/15/12   2,4,9,155,15,16        1,042,720             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0816   Reconstruction               0-010-018  04/01/14     DONE    DONE       DONE      12/03/13   11/25/13   06/13/13   05/21/13   8,9,16                    21,000             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Whiporwil Dist.Office/Storage:
13-0357   Reconstruction               2-004-016  12/13/13     DONE    DONE       DONE      09/11/13   09/11/13   06/13/13   05/21/13   2,8                      665,000             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
13-0817   Reconstruction               2-004-017  04/01/14     DONE    DONE       DONE      12/03/13   11/25/13   12/02/13   05/21/13   8,9,16                    21,000             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               2-004-018                                              /  /       /  /     05/28/14     /  /     2,8                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          District-Wide:
13-1230   Reconstruction               7-999-005                         UNREVIEWED         02/13/14   02/13/14   02/13/14   11/15/08   16                             0             0  MFS             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CONNETQUOT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-07-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sycamore Avenue Elementary:
10-1260XX Reconstruction               0-001-014  11/08/11               CANCELLED          05/10/11   05/05/11   11/24/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0793   Reconstruction               0-001-015  06/26/13     DONE    DONE       DONE      02/08/13   01/29/13   11/24/10   02/01/11   2,4,8,9,14,155,15,16     728,350       728,350  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-001-016                                              /  /       /  /     05/08/14     /  /     2,4,155,16                     0             0  MFS             0           0           0                                         0        /  /                           /  /             

          John Pearl Elementary School:
09-0547   Reconstruction               0-002-016  12/21/09     DONE    DONE       DONE      12/04/09   12/02/09   09/22/09   12/12/07   7,155                  1,330,000     1,330,000  DDJ             0           0           0 Wiedersum Associates Architec           0      01/14/11                       04/03/13           
10-1261XX Reconstruction               0-002-017  11/08/11               CANCELLED          05/10/11   05/05/11   11/23/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0794   Reconstruction               0-002-018  03/04/14     DONE    DONE       DONE      02/08/13   01/29/13   11/24/10   02/01/11   2,4,8,9,14,155,15,16     154,750             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-002-019                                              /  /       /  /     05/08/14     /  /     2,8,9,155,16                   0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Edith L Slocum Elementary:
10-1262   Reconstruction               0-004-020  11/08/11     DONE    DONE       DONE      05/10/11   05/05/11   11/23/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0      10/02/12                       10/20/12           
12-0852   Reconstruction               0-004-021  10/11/13     DONE    DONE       DONE      02/15/13   02/14/13   11/24/10   02/01/11   2,4,8,9,14,155,15,16     541,150             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-0252   Reconstruction               0-004-022  11/29/13     DONE    DONE       DONE      08/20/13   08/13/13   05/09/13   05/20/08                            355,000             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-004-023                                              /  /       /  /     05/29/13     /  /     155                            0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-024                                              /  /       /  /     05/08/14     /  /     2,4,8,9,155,16                 0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Helen B Duffield Elementary:
09-0548   Reconstruction               0-005-017  12/21/09     DONE    DONE       DONE      12/04/09   12/02/09   09/22/09   12/12/07   7,155                  1,300,000     1,300,000  DDJ             0           0           0 Wiedersum Associates Architec           0      01/14/11                       04/03/13           
10-1263XX Reconstruction               0-005-018  11/08/11               CANCELLED          05/10/11   05/05/11   11/23/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0853   Reconstruction               0-005-019  10/11/13     DONE    DONE       DONE      02/15/13   02/14/13   11/24/10   02/01/11   2,4,8,9,14,155,15,16     745,150             0  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-005-020                                              /  /       /  /     05/08/14     /  /     2,4,9,155,16                   0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Arthur Premm Learning Center:
12-0854   Reconstruction               0-006-009  10/11/13     DONE    DONE       DONE      02/15/13   02/14/13   11/22/10   02/01/11   2,4,8,9,14,155,15,16     173,950             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-0994   Reconstruction               0-006-010  04/23/14     DONE    DONE       DONE      01/13/14   01/09/14   10/21/13   05/15/09   15                       250,000       250,000  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-006-011                                              /  /       /  /     05/08/14     /  /     4,9,16                         0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Connetquot High School:
  -       Reconstruction               0-007-033                                              /  /       /  /     10/01/09     /  /     7,16                           0             0  DDJ             0           0           0                                         0        /  /                           /  /             
10-0834   Reconstruction               0-007-034  06/17/11     DONE    DONE       DONE      02/08/11   02/08/11   10/14/10   12/12/07   155,16                   362,665       362,665  DDJ             0           0           0 Wiedersum Associates Architec           0      01/04/12                       04/03/13           
11-0261   Additions and Alterations    0-007-035  02/08/12     DONE    DONE       DONE      10/17/11   10/13/11   11/03/10   02/01/11   02 - 16               12,292,600    11,150,632  DDJ             0           0           0 Wiedersum Associates Architec           0      08/31/12                       09/10/12           
  -       Reconstruction               0-007-036                                              /  /       /  /     05/08/14     /  /     2,4,8,9,155,15,16              0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Idle Hour Elementary:
09-0549   Reconstruction               0-009-012  12/21/09     DONE    DONE       DONE      12/04/09   12/02/09   09/22/09   12/12/07   7,155                  1,400,000     1,400,000  DDJ             0           0           0 Wiedersum Associates Architec           0      01/04/11                       04/03/13           
10-1264XX Reconstruction               0-009-013  11/08/11               CANCELLED          05/10/11   05/05/11   11/23/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0855   Reconstruction               0-009-014  10/11/13     DONE    DONE       DONE      02/15/13   02/14/13   11/24/10   02/01/11   2,4,8,9,14,155,15,16     436,750             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-009-015                                              /  /       /  /     05/08/14     /  /     2,4,9,155,16                   0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Oakdale-Bohemia Jr. High:
  -    XX Reconstruction               0-010-020                         CANCELLED            /  /       /  /     11/19/10     /  /     155                            0    22,072,824  DDJ             0           0           0                                         0        /  /                           /  /             
12-0795   Reconstruction               0-010-021  03/04/14     DONE    DONE       DONE      02/08/13   01/29/13   11/22/10   02/01/11   2,4,7,8,9,14,155,15,   1,237,160             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0953   Reconstruction               0-010-022  06/17/13     DONE    DONE       DONE      03/11/13   03/08/13   01/31/13   05/15/12   8,16                      40,000        40,000  MFS             0           0           0 Wiedersum Associates Architec           0      09/03/13                       09/26/13           
  -       Reconstruction               0-010-023                                              /  /       /  /     08/09/13     /  /     155,15                         0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-010-024                                              /  /       /  /     05/08/14     /  /     2,4,8,9,155,16                 0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Ronkonkoma Junior High:
12-0796   Reconstruction               0-011-023  03/04/14     DONE    DONE       DONE      02/08/13   01/29/13   11/22/10   02/01/11   2,4,7,8,9,14,155,15,   1,254,440             0  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -    XX Reconstruction               0-011-024                         CANCELLED            /  /       /  /     11/23/10     /  /     155                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0954   Reconstruction               0-011-025  06/17/13     DONE    DONE       DONE      03/11/13   03/08/13   01/30/13   05/15/12   8,16                      40,000        40,000  MFS             0           0           0 Wiedersum Associates Architec           0      09/03/13                       09/26/13           
  -       Reconstruction               0-011-026                                              /  /       /  /     05/08/14     /  /     2,4,8,9,155,16                 0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Cherokee St Elementary:
10-1265XX Reconstruction               0-012-016  11/08/11               CANCELLED          05/10/11   05/05/11   11/23/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0797   Reconstruction               0-012-017  03/04/14     DONE    DONE       DONE      02/08/13   01/29/13   11/24/10   02/01/11   2,4,8,9,14,155,15,16     652,750             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0955   Reconstruction               0-012-018  06/17/13     DONE    DONE       DONE      03/11/13   03/08/13   01/31/13   05/15/12   8,16                      30,000        30,000  MFS             0           0           0 Wiedersum Associates Architec           0      09/03/13                       09/26/13           
  -       Reconstruction               0-012-019                                              /  /       /  /     05/29/13     /  /     155                            0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-012-020                                              /  /       /  /     05/08/14     /  /     2,4,9,155,16                   0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Edward J Bosti School:
12-0798   Reconstruction               0-013-014  03/04/14     DONE    DONE       DONE      02/08/13   01/29/13   11/23/10   02/01/11   2,4,8,9,14,155,15,16     136,750             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
10-1266XX Reconstruction               0-013-015  11/08/11               CANCELLED          05/10/11   05/05/11   11/23/10   12/12/07   155                       95,000        95,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0956   Reconstruction               0-013-016  06/17/13     DONE    DONE       DONE      03/11/13   03/08/13   01/31/13   05/15/12   8,16                      30,000        30,000  MFS             0           0           0 Wiedersum Associates Architec           0      09/03/13                       09/26/13           
  -       Reconstruction               0-013-017                                              /  /       /  /     05/08/14     /  /     2,4,9,155,16                   0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Administration Building:
  -    XX Reconstruction               1-015-012                         CANCELLED            /  /       /  /     11/22/10     /  /     2,4,7,8,9,14,155,15,           0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Field Storage Container:
12-0116DB Discovered Building          2-022-001  08/24/12     DONE    DONE       DONE      08/24/12   08/24/12   11/16/11     /  /                                    0             0  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Bus Garage/Adm(frmrly Admin_):
  -    PR Additions and Alterations    5-015-013                                              /  /       /  /     03/25/11     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0856   Additions and Alterations    5-015-013  10/11/13     DONE    DONE       DONE      02/15/13   02/14/13   03/25/11   02/01/11   02 - 16                1,276,800             0  MFS             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Connetquot Public Library:
09-1449   Reconstruction               6-016-003  06/04/10     DONE    DONE       DONE      05/20/10   05/14/10   11/05/09   11/12/09   2,9                      403,535             0  DDJ             0           0           0 Burton Behrendt Smith                   0      10/15/10                         /  /             
13-0141   Reconstruction               6-016-004  08/29/13     DONE    DONE       DONE      08/06/13   08/06/13   04/12/13   07/18/13   4,7,8,9,14,15,16         165,500             0  MFS             0           0           0 Burton Behrendt Smith                   0      01/31/14                       04/03/14           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WEST ISLIP UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-09-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Captree Elementary:
07-1550   Reconstruction               0-001-011  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                240,813       240,813  MGL             0           0           0 John A Grillo-ARCHITECTS PC       240,393      01/03/12                       06/19/14           

          Manetuck Elementary:
07-1551   Reconstruction               0-003-014  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                245,887       245,887  MGL             0           0           0 John A Grillo-ARCHITECTS PC       244,447      01/03/12                       06/19/14           

          Masera Elementary School:
12-1008   Reconstruction               0-004-010  04/09/13     DONE    DONE       DONE      03/21/13   03/18/13   02/15/13   12/13/12   2,16                     800,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Paul J. Bellew Elementary:
07-1552   Reconstruction               0-005-017  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                335,931       335,931  MGL             0           0           0 John A Grillo-ARCHITECTS PC       333,911      01/03/12                       06/19/14           

          Wdall Road Jr. High School:
07-1553   Reconstruction               0-007-013  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16              1,344,587     1,344,587  MGL             0           0           0 John A Grillo-ARCHITECTS PC     1,340,927      01/03/12                       06/19/14           

          West Islip Senior High School:
07-1554   Reconstruction               0-008-024  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16              4,951,826     4,951,826  MGL             0           0           0 John A Grillo-ARCHITECTS PC     4,789,946      01/03/12                       06/19/14           
10-1061   Reconstruction               0-008-027  06/29/11     DONE    DONE       DONE      03/17/11   03/15/11   12/29/10   10/02/07   2,4,8,9,10,155,15,16     692,121       692,121  JOD             0           0           0 Burton Behrendt Smith                   0      08/30/12                       10/23/12           
12-0999   Reconstruction               0-008-029  06/12/13     DONE    DONE       DONE      03/20/13   03/20/13   02/15/13   12/13/12   2                      1,220,000     1,220,000  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Westbrook Elementary:
07-1555   Reconstruction               0-009-014  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                247,911       247,911  MGL             0           0           0 John A Grillo-ARCHITECTS PC       245,731      01/03/12                       06/19/14           

          Beach Street Middle School:
07-1556   Reconstruction               0-010-018  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                376,508       376,508  MGL             0           0           0 John A Grillo-ARCHITECTS PC       371,978      01/03/12                       06/19/14           
10-1062   Reconstruction               0-010-020  06/29/11     DONE    DONE       DONE      03/17/11   03/15/11   02/15/11   10/02/07   2,4,8,9,155,15,16         76,320        76,320  JOD             0           0           0 Burton Behrendt Smith                   0      08/30/12                       10/23/12           

          Bayview School:
07-1557   Reconstruction               0-011-012  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                220,767       220,767  MGL             0           0           0 John A Grillo-ARCHITECTS PC       220,467      01/03/12                         /  /             
12-1000   Reconstruction               0-011-014  06/12/13     DONE    DONE       DONE      03/20/13   03/20/13   02/15/13   12/13/12   2                        500,000       500,000  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Oquenock School:
07-1558   Reconstruction               0-012-014  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                223,593       223,593  MGL             0           0           0 John A Grillo-ARCHITECTS PC       221,913      01/03/12                       06/19/14           

          West Islip High School:
10-1237   New Construction             2-030-001  02/22/12     DONE    DONE       DONE      04/29/11   04/28/11   02/15/11   10/02/07   02 - 16                   55,968             0  JOD             0           0           0 Burton Behrendt Smith                   0      02/15/13                       04/08/13           

          New Storage Building 2:
10-1238   New Construction             2-031-001  02/22/12     DONE    DONE       DONE      04/29/11   04/28/11   02/15/11   10/02/07   02 - 16                   42,612             0  JOD             0           0           0 Burton Behrendt Smith                   0      02/15/13                       04/08/13           

          New Storage Building:
10-1239   New Construction             2-032-001  02/22/12     DONE    DONE       DONE      04/29/11   04/28/11   02/15/11   10/02/07   02 - 16                   42,612             0  JOD             0           0           0 Burton Behrendt Smith                   0      02/15/13                       04/08/13           

          Bus Maintenance Garage:
07-1559   Reconstruction               5-002-004  06/28/10     DONE    DONE       DONE      02/06/08   02/04/08   09/06/06   08/17/06   155,15,16                 42,676        42,676  MGL             0           0           0 John A Grillo-ARCHITECTS PC        40,786      01/03/12                       06/19/14           

          District Wide:
  -       Reconstruction               7-999-006                                              /  /       /  /     02/15/11     /  /     16                             0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRENTWOOD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-12-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ross/Sonderling High School:
10-0032   Reconstruction               0-002-011  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   03/25/10   12/12/06   2,15,16                  423,647       423,647  HCM             0           0      71,596 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0321   Reconstruction               0-002-012  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   03/25/10   02/17/11   2,155,15,16            1,383,837             0  HCM             0           0           0 Tetra  Tech Architects & Engi   1,383,837        /  /                           /  /             
11-1213   Reconstruction               0-002-013  05/11/12     DONE    DONE       DONE      04/26/12   04/25/12   04/14/11   12/12/06   155,16                   672,979       672,979  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
  -       Reconstruction               0-002-014                                              /  /       /  /     03/13/12     /  /     7                              0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Southeast Elementary:
11-0322   Reconstruction               0-003-010  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16               661,318             0  HCM             0           0           0 Tetra  Tech Architects & Engi     661,318        /  /                           /  /             
11-1217   Reconstruction               0-003-011  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   2,9,155,16               135,000             0  HCM             0           0      20,250 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Southwest Elementary:
10-0033   Reconstruction               0-004-009  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   03/24/10   12/12/06   2,155,15,16              450,984       450,984  HCM             0           0      76,216 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0323   Reconstruction               0-004-010  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16             1,374,290             0  HCM             0           0           0 Tetra  Tech Architects & Engi   1,374,290        /  /                           /  /             
11-1218   Reconstruction               0-004-011  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   2,9,155,16               320,000             0  HCM             0           0      48,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          South Middle School:
10-0003   Reconstruction               0-005-012  08/18/10     DONE    DONE       DONE      07/06/10   07/01/10   03/25/10   12/12/06   7,16                     864,667       864,667  HCM             0           0     146,129 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0324   Reconstruction               0-005-013  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16             1,493,831             0  HCM             0           0           0 Tetra  Tech Architects & Engi   1,493,831        /  /                           /  /             
11-1219   Reconstruction               0-005-014  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   155,16                    55,000             0  HCM             0           0       8,250 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          FRESHMAN ANNEX (SEE 1-006-001):
08-1645   Reconstruction               0-006-001  12/23/10     DONE    DONE       DONE      05/20/09   05/07/09   05/21/09   12/12/06   2,4,8,9,155,15,16        732,324             0  HCM             0           0           0 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           

          Northeast Elementary:
10-0034   Reconstruction               0-007-008  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   03/25/10   12/12/06   2,155,15,16              422,894       422,894  HCM             0           0      71,469 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0325   Reconstruction               0-007-009  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16             1,168,892     1,168,892                  0           0           0 Tetra  Tech Architects & Engi   1,168,892        /  /                           /  /             
11-1220   Reconstruction               0-007-010  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   155,16                   260,000       260,000  HCM             0           0      39,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          North Elementary:
10-0035   Reconstruction               0-008-006  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   01/30/08   12/12/06   2,4,155,16               399,007       399,007  HCM             0           0      67,432 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0326   Reconstruction               0-008-008  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16             1,226,520     1,226,520  HCM             0           0           0 Tetra  Tech Architects & Engi   1,226,520        /  /                           /  /             
11-1221   Reconstruction               0-008-009  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   155,16                   790,000             0  HCM             0           0     118,500 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          East ES (K):
09-0085   Reconstruction               0-009-007  08/18/09     DONE    DONE       DONE      07/24/09   07/22/09   07/03/09   07/07/09   7                        788,960       845,000  HCM             0           0     131,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             
10-0036   Reconstruction               0-009-008  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   03/24/10   12/12/06   2,155,15,16              397,489       397,489  HCM             0           0      67,176 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0327   Reconstruction               0-009-009  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16               726,828             0  HCM             0           0           0 Tetra  Tech Architects & Engi     726,828        /  /                           /  /             
11-1222   Reconstruction               0-009-010  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   7,155,16                 502,000             0  HCM             0           0      75,300 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Freshman Center:
08-1646   Additions and Alterations    0-010-008  12/23/10     DONE    DONE       DONE      05/20/09   05/07/09   12/29/08   12/12/06   02 - 16                4,547,445     4,547,445  HCM             0           0     423,358 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
10-0004   Reconstruction               0-010-009  08/18/10     DONE    DONE       DONE      07/06/10   07/01/10   03/24/10   12/12/06   7                        101,934       101,934  HCM             0           0           0 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0328   Reconstruction               0-010-010  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/14/11   02/17/11   2,9,155,16               635,537             0  HCM             0           0           0 Tetra  Tech Architects & Engi     635,537        /  /                           /  /             
11-1214   Reconstruction               0-010-011  05/11/12     DONE    DONE       DONE      04/26/12   04/25/12   03/13/12   12/12/06   7                      1,943,565             0  HCM             0           0     291,535 Tetra  Tech Architects & Engi           0        /  /                           /  /             
11-1223   Reconstruction               0-010-012  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   2,155,15,16              500,000             0  HCM             0           0      75,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          North Middle School:
10-0800   Reconstruction               0-011-010  03/24/11     DONE    DONE       DONE      02/07/11   02/03/11   06/15/10   10/01/09   7,8,15                 1,086,333     1,086,333  HCM             0           0     183,590 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0329   Reconstruction               0-011-011  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               966,917       966,917  HCM             0           0           0 Tetra  Tech Architects & Engi     966,917        /  /                           /  /             

          Loretta Park Elementary:
09-1310   Reconstruction               0-012-006  05/20/10     DONE    DONE       DONE      04/15/10   04/09/10   03/03/10   12/12/06   2,7                    1,238,706     1,238,706  HCM             0           0     167,987 Tetra  Tech Architects & Engi           0      10/11/13                       05/30/14           
11-0330   Reconstruction               0-012-007  05/31/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               876,702             0  HCM             0           0           0 Tetra  Tech Architects & Engi     876,702        /  /                           /  /             
11-1224   Reconstruction               0-012-008  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12     /  /     12/12/06   7,155,16                 505,000             0  HCM             0           0      75,750 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Pine Park Elementary:
09-1311   Reconstruction               0-013-006  05/20/10     DONE    DONE       DONE      04/15/10   04/09/10   03/03/10   12/12/06   2,7                    1,132,638     1,132,638  HCM             0           0     174,108 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
10-0037   Reconstruction               0-013-007  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   03/25/10   12/12/06   2,16                     235,213       235,213  HCM             0           0      39,751 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0331   Reconstruction               0-013-008  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               721,144             0  HCM             0           0           0 Tetra  Tech Architects & Engi     721,144        /  /                           /  /             
11-1225   Reconstruction               0-013-009  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   7,155,16                 520,000             0  HCM             0           0      78,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Oak Park Elementary:
10-0038   Reconstruction               0-014-007  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   03/25/10   12/12/06   2,16                     137,574       137,574  HCM             0           0      23,250 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
10-0801   Reconstruction               0-014-008  03/24/11     DONE    DONE       DONE      02/07/11   02/03/11   06/15/10   10/01/09   2,7,15                 1,155,123     1,155,123  HCM             0           0     195,216 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0332   Reconstruction               0-014-009  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               914,430             0  HCM             0           0           0 Tetra  Tech Architects & Engi     914,430        /  /                           /  /             
11-1226   Reconstruction               0-014-010  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   7,155,16                 500,000             0  HCM             0           0      75,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          West Middle School:
10-0802   Reconstruction               0-015-009  03/24/11     DONE    DONE       DONE      02/07/11   02/03/07   06/15/10   10/01/09   7,15                   1,121,307     1,121,307  HCM             0           0     189,501 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0333   Reconstruction               0-015-010  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16             1,181,455             0  HCM             0           0           0 Tetra  Tech Architects & Engi   1,181,455        /  /                           /  /             
11-1227   Reconstruction               0-015-011  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   16                       383,768        85,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Sounderling Sr High:
10-0039   Reconstruction               0-016-007  12/20/10     DONE    DONE       DONE      07/22/10   07/09/10   06/15/10   12/12/06   2,155,15,16              663,102       663,102  HCM             0           0     112,065 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0334   Reconstruction               0-016-008  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   155,16                   998,850             0  HCM             0           0           0 Tetra  Tech Architects & Engi     998,850        /  /                           /  /             

          Hemlock Elem:
10-0803   Reconstruction               0-017-006  03/24/11     DONE    DONE       DONE      02/07/11   02/03/11   06/15/10   10/01/09   2,7                    1,265,564     1,265,564  HCM             0           0     213,880 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0338   Reconstruction               0-017-007  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               996,488             0  HCM             0           0           0 Tetra  Tech Architects & Engi     996,488        /  /                           /  /             
11-1228   Reconstruction               0-017-008  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   7,155,16                 500,000             0  HCM             0           0      75,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Laurel Park Elementary:
09-1312   Reconstruction               0-018-006  05/20/10     DONE    DONE       DONE      04/15/10   04/09/10   04/22/08   12/12/06   13                     1,914,000     1,914,000  HCM             0           0     287,100 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0335   Reconstruction               0-018-007  05/31/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               868,362             0  HCM             0           0           0 Tetra  Tech Architects & Engi     868,362        /  /                           /  /             
11-1229   Reconstruction               0-018-008  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   7,155,16                 500,000             0  HCM             0           0      75,000 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Twin Pines Elementary:
11-0336   Reconstruction               0-019-008  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16               912,019       912,019  HCM             0           0           0 Tetra  Tech Architects & Engi     912,019        /  /                           /  /             
11-1230   Reconstruction               0-019-009  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   7,155,16                 550,000             0  HCM             0           0      82,500 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          East Middle School:
09-1313   Reconstruction               0-020-011  05/20/10     DONE    DONE       DONE      04/15/10   04/09/10   03/03/10   12/12/06   7                      1,155,414     1,155,414  HCM             0           0     179,987 Tetra  Tech Architects & Engi           0      10/11/13                       11/04/13           
11-0337   Reconstruction               0-020-012  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   04/15/11   02/17/11   2,9,155,16             1,789,974             0  HCM             0           0           0 Tetra  Tech Architects & Engi   1,789,974        /  /                           /  /             
11-1231   Reconstruction               0-020-013  12/10/12     DONE    DONE       DONE      04/26/12   04/25/12   03/20/12   12/12/06   155,16                   135,000             0  HCM             0           0      20,250 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Headstart Center:
  -       Reconstruction               0-031-003                                              /  /       /  /     04/08/14     /  /     7                              0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Felicio Administration Bldg:
11-0339   Reconstruction               1-023-003  05/29/12     DONE    DONE       DONE      11/02/11   10/26/11   09/25/06   02/17/11   2,4,10,155,16             89,613             0  HCM             0           0           0 Tetra  Tech Architects & Engi      89,613        /  /                           /  /             
  -       Reconstruction               1-023-004                                              /  /       /  /     04/15/11     /  /     155                            0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Brentwood Public Library:
12-1120   Reconstruction               6-021-009  07/11/13     DONE    DONE       DONE      04/22/13   04/22/13   02/15/13   03/21/13   7,16                     385,000             0  JMB             0           0           0 Beatty, Harvey & Associates             0        /  /                           /  /             
13-1623   Reconstruction               6-021-010  07/17/14     DONE    DONE       DONE      06/18/14   06/16/14   03/04/14   05/29/14   8,9,155,15,16            525,000             0  JMB             0           0           0 BEATTY HARVEY COCO                      0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CENTRAL ISLIP UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-13-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ralph G. Reed Middle School:
09-1536   Reconstruction               0-001-011  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,15,16            1,999,162     1,999,162  JOD             0           0           0 ECG Engineering, LLC            1,999,162      03/13/13                       10/04/13           
  -       Reconstruction               0-001-012                                              /  /       /  /     04/05/12     /  /     2,9,10                         0             0  JOD             0           0           0                                         0        /  /                           /  /             
12-0726   Reconstruction               0-001-013  05/15/13     DONE    DONE       DONE      01/28/13   01/16/13   11/15/12   04/02/08   2,4,7,8,9,155,15,16      163,224       163,224  JMB             0           0      34,112 Tetra Tech Architects and Eng           0        /  /                           /  /             
13-1356   Reconstruction               0-001-014  04/18/14     DONE    DONE       DONE      03/17/14   03/14/14   02/05/14   01/28/14   2,9                      135,000             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     04/08/14     /  /     2,9,155,16                     0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-0062   Reconstruction               0-001-016                         UNREVIEWED         07/25/14   07/21/14   07/10/14   01/28/14   2,9,155,15,16                  0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Alfano Elementary:
09-0710PR Reconstruction               0-002-008                         UNREVIEWED         01/07/10   01/06/10   01/31/08     /  /     2,4,8,9,10,13,14,155           0             0  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
09-1097   Reconstruction               0-002-008  08/16/10     DONE    DONE       DONE      03/18/10   03/10/10   01/31/08   05/12/08   2,4,8,9,10,13,14,155   9,018,500     8,267,365  JOD             0           0   3,494,430 Tetra  Tech Architects & Engi           0      08/28/12           YES           /  /             
09-1537   Reconstruction               0-002-009  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,8,15,16                992,694       992,694  JOD             0           0           0 ECG Engineering, LLC              992,694      03/13/13                       10/04/13           
13-1357   Reconstruction               0-002-010  04/18/14     DONE    DONE       DONE      03/17/14   03/14/14   02/05/14   01/28/14   2,4,9                    610,000             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
14-0063   Reconstruction               0-002-011                         UNREVIEWED         07/25/14   07/21/14   04/08/14   01/28/14   155,16                         0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Marguerite L Mulvey Elem.:
09-1538   Reconstruction               0-003-012  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,15,16              974,529       974,529  JOD             0           0           0 ECG Engineering, LLC              974,529      03/13/13                       10/04/13           
13-1358   Reconstruction               0-003-013  04/18/14     DONE    DONE       DONE      03/17/14   03/14/14   02/05/14   01/28/14   2,9                      415,000             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
14-0064   Reconstruction               0-003-014                         UNREVIEWED         07/25/14   07/21/14   04/08/14   01/28/14   155,16                         0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Cordello Ave. School:
09-1539   Reconstruction               0-004-009  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,15,16              632,587       632,587  JOD             0           0           0 ECG Engineering, LLC              632,587      03/13/13                       10/04/13           
14-0065   Reconstruction               0-004-010                         UNREVIEWED         07/25/14   07/21/14   02/05/14   01/28/14   2,155,16                       0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Mulligan Middle School:
09-1540   Reconstruction               0-005-010  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,15,16            1,580,515     1,580,515  JOD             0           0           0 ECG Engineering, LLC            1,580,515      03/13/13                       10/04/13           
12-0727   Reconstruction               0-005-011  05/15/13     DONE    DONE       DONE      01/28/13   01/16/13   11/15/12   04/02/08   2,4,8,9,10,155,15,16   1,496,713     1,496,713  JMB             0           0     312,813 Tetra Tech Architects and Eng           0        /  /                           /  /             
13-1359XX Reconstruction               0-005-012                         CANCELLED          03/17/14   03/14/14   02/05/14   01/28/14   10                             0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
14-0066   Reconstruction               0-005-013                         UNREVIEWED         07/25/14   07/21/14   04/08/14   01/28/14   2,4,8,9,155,15,16              0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Francis O'Neil Elementary:
09-1541   Reconstruction               0-006-009  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,15,16              801,091       801,091  JOD             0           0           0 ECG Engineering, LLC              801,091      03/13/13                       10/04/13           
13-1360   Reconstruction               0-006-010  04/18/14     DONE    DONE       DONE      03/17/14   03/14/14   02/05/14   01/28/14   2,9                    1,113,000             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
14-0067   Reconstruction               0-006-011                         UNREVIEWED         07/25/14   07/21/14   04/08/14   01/28/14   2,155,16                       0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          A.T. Morrow Elementary:
09-1542   Reconstruction               0-007-009  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,15,16            1,229,095     1,229,095  JOD             0           0           0 ECG Engineering, LLC            1,229,095      03/13/13                       10/04/13           
14-0068   Reconstruction               0-007-010                         UNREVIEWED         07/25/14   07/21/14   02/05/14   01/28/14   2,155,16                       0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Senior High:
  -       Reconstruction               0-008-012                                              /  /       /  /     08/25/09     /  /     2,16                           0             0  JOD             0           0           0                                         0        /  /                           /  /             
09-1543   Reconstruction               0-008-013  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,8,155,15,16          3,376,148     3,376,148  JOD             0           0           0 ECG Engineering, LLC            3,376,148      03/13/13                       10/04/13           
14-0069   Reconstruction               0-008-014                         UNREVIEWED         07/25/14   07/21/14   02/05/14   01/28/14   155,16                         0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
  -       Reconstruction               0-008-015                                              /  /       /  /     04/08/14     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0                                         0        /  /                           /  /             
14-0079   Reconstruction               0-008-016                         UNREVIEWED         07/29/14   07/25/14   07/16/14   01/28/14   2,9                            0             0  DDJ             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             

          Early Childhood @ Alfeno:
09-1544   Reconstruction               0-014-005  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,16                  18,009             0  JOD             0           0           0 ECG Engineering, LLC               18,009      03/13/13                       10/04/13           

          Mulvey Annex:
09-1545   Reconstruction               2-010-002  03/17/11     DONE    DONE       DONE      06/15/10   06/08/10   02/26/10   02/08/10   2,155,16                  86,780             0  JOD             0           0           0 ECG Engineering, LLC               86,780      03/13/13                       10/04/13           

          Districtwide:
  -       Reconstruction               7-999-002                                              /  /       /  /     05/01/12     /  /     155                            0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FIRE ISLAND UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-05-14-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Woodhull School:
09-0585   Reconstruction               0-001-008  04/07/10     DONE    DONE       DONE      12/21/09   12/11/09   01/29/09   05/19/09   4,7,8,9                1,132,034     1,132,034  HCM             0           0           0 Burton Behrendt Smith                   0      03/09/11                         /  /             
09-0288   Reconstruction               0-001-009  11/03/09     DONE    DONE       DONE      10/06/09   10/05/09   06/17/09   05/19/09   2,4,8                    173,270       173,270  HCM             0           0           0 Burton Behrendt Smith                   0      08/04/10                         /  /             
  -       Reconstruction               0-001-010                                              /  /       /  /     01/06/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHOREHAM-WADING RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-06-01-04
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wading River School:
  -       Reconstruction               0-003-011                                              /  /       /  /     03/30/11     /  /     9,10,155,15                    0     5,011,250  HCM             0           0           0                                         0        /  /                           /  /             
11-0489   Reconstruction               0-003-012  02/17/12     DONE    DONE       DONE      12/13/11   12/08/11   08/19/11   05/17/11   13,15,16                 160,000       160,000  HCM             0           0           0 Burton Behrendt Smith                   0      04/08/13                       05/30/13           
12-0857   Reconstruction               0-003-013  05/09/13     DONE    DONE       DONE      02/15/13   02/14/13     /  /     10/02/12   16                       174,475       174,475  JMB             0           0           0 Burton Behrendt Smith                   0      01/23/14                       04/28/14           
13-1017   Reconstruction               0-003-014  05/15/14     DONE    DONE       DONE      01/14/14   01/13/14   09/23/13   05/21/13   8,9,16                    16,050             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-003-015                                              /  /       /  /     06/26/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Briarcliff ES (Closed 14/15 SY):
09-0679   Reconstruction               0-004-011  02/23/10     DONE    DONE       DONE      01/05/10   12/30/09   03/24/09   10/14/09   8,155                    404,437       404,437  HCM             0           0           0 Burton Behrendt Smith                   0      12/02/10                         /  /             
10-1246   Reconstruction               0-004-012  05/11/11     DONE    DONE       DONE      05/06/11   05/02/11   03/02/11   03/11/11   10                       795,000       795,000  HCM             0           0           0 Burton Behrendt Smith                   0      09/26/11                         /  /             
  -       Reconstruction               0-004-013                                              /  /       /  /     04/14/11     /  /     2,7,155,15,16                  0             0  HCM             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-014                                              /  /       /  /     06/07/11     /  /     10,15,16                       0     4,438,834  HCM             0           0           0                                         0        /  /                           /  /             
11-0490   Reconstruction               0-004-015  02/17/12     DONE    DONE       DONE      12/13/11   12/08/11   08/19/11   05/17/11   13,15,16                 191,144       191,144  HCM             0           0           0 Burton Behrendt Smith                   0      04/08/13                       05/30/13           
12-0858   Reconstruction               0-004-016  05/09/13     DONE    DONE       DONE      02/15/13   02/14/13   11/13/12   10/02/12   16                       124,975       124,975  JMB             0           0           0 Burton Behrendt Smith                   0      01/23/14                       04/28/14           
12-1097   Reconstruction               0-004-017  04/26/13     DONE    DONE       DONE      04/12/13   04/12/13   03/08/13   05/15/12   7                        228,487       228,487  JMB             0           0           0 Burton Behrendt Smith                   0      12/18/13                       02/25/14           
13-1018   Reconstruction               0-004-018  05/15/14     DONE    DONE       DONE      01/14/14   01/13/14   09/23/13   05/21/13   8,9,16                    20,425             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Albert Prodell Middle School:
09-0680   Reconstruction               0-005-011  02/23/10     DONE    DONE       DONE      01/05/10   12/30/09   03/24/09   10/14/09   8,9,155,15,16          2,667,213     2,667,213  HCM             0           0     371,651 Burton Behrendt Smith                   0      09/01/11                         /  /             
12-0859   Reconstruction               0-005-012  05/09/13     DONE    DONE       DONE      02/15/13   02/14/13   11/13/12   10/02/12   16                       296,250       296,250  JMB             0           0           0 Burton Behrendt Smith                   0      01/23/14           YES           /  /             
13-1019   Reconstruction               0-005-013  05/15/14     DONE    DONE       DONE      01/14/14   01/13/14   09/23/13   05/21/13   8,9,16                    31,642             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-005-014                                              /  /       /  /     06/26/14     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Miller Avenue School:
  -       Reconstruction               0-006-010                                              /  /       /  /     03/30/11     /  /     10,15,16                       0     7,076,160  HCM             0           0           0                                         0        /  /                           /  /             
11-0491   Reconstruction               0-006-011  02/17/12     DONE    DONE       DONE      12/13/11   12/08/11   08/19/11   05/17/11   13,15,16                 190,000       190,000  HCM             0           0           0 Burton Behrendt Smith                   0      04/08/13                       05/30/13           
12-0860   Reconstruction               0-006-012  05/09/13     DONE    DONE       DONE      02/15/13   02/14/13   11/13/12   10/02/12   16                       149,375       149,375  JMB             0           0           0 Burton Behrendt Smith                   0      01/23/14                       04/28/14           
13-1020   Reconstruction               0-006-013  05/15/14     DONE    DONE       DONE      01/14/14   01/13/14   09/23/13   05/21/13   8,9,16                    58,255             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-006-014                                              /  /       /  /     06/26/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          High School/Public Library:
  -       Reconstruction               0-007-018                                              /  /       /  /     03/30/11     /  /     10,15,16                       0       102,380  HCM             0           0           0                                         0        /  /                           /  /             
12-1098   Reconstruction               0-007-019  04/26/13     DONE    DONE       DONE      04/12/13   04/12/13   03/08/13   05/15/12   7                        451,502       451,502  JMB             0           0           0 Burton Behrendt Smith                   0      12/18/13                       02/25/14           
11-0492   Reconstruction               0-007-020  02/17/12     DONE    DONE       DONE      12/13/11   12/08/11   08/19/11   05/17/11   13,15,16                 350,000       350,000  HCM             0           0           0 Burton Behrendt Smith                   0      04/08/13                       05/30/13           
12-0861   Reconstruction               0-007-021  05/09/13     DONE    DONE       DONE      02/15/13   02/14/13   11/13/12   10/02/12   2,10,16                1,047,158       729,625  JMB             0           0      24,797 Burton Behrendt Smith                   0      01/23/14           YES           /  /             
13-1016   Reconstruction               0-007-022               DONE    DONE       UNREVIEWED01/14/14   01/13/14   09/23/13   05/21/13   2,4,8,9,14,155,15,16           0     2,723,308  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1021   Reconstruction               0-007-023  05/15/14     DONE    DONE       DONE      01/14/14   01/13/14   09/23/13   05/21/13   8,9,16                    35,875             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1338   Reconstruction               0-007-024  03/13/14     DONE    DONE       DONE      03/12/14   03/10/14   02/25/14   02/25/14   7,9                      401,923       401,923  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-007-025                                              /  /       /  /     06/26/14     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-007-026                                              /  /       /  /     06/26/14     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Container 1 @ Wading River ES:
12-0265DB Discovered Building          2-047-001  02/06/13     DONE    DONE       DONE        /  /       /  /     10/11/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Container 2 @ Wading River ES:
12-0266DB Discovered Building          2-048-001  02/05/13     DONE    DONE       DONE        /  /       /  /     10/11/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Press Box:
12-0075   New Construction             7-046-001  10/03/12     DONE    DONE       DONE      08/02/12   07/23/12   02/15/12   02/14/12   02 - 16                   60,000             0  HCM             0           0           0 Burton Behrendt Smith                   0      07/30/13                       08/01/13           

          Concession Stand:
12-0981   New Construction             7-049-001                       ADDENDUM REQ'D       03/18/13   03/15/13   11/16/12   06/19/12   02 - 16                        0             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RIVERHEAD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-06-02-04
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Phillips Avenue School:
09-1593   Reconstruction               0-001-013  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   11/20/09   07/08/09   10,155,15,16           1,555,576     1,555,576  HCM             0           0           0 Burton Behrendt Smith           1,555,576      03/04/14                       05/23/14           
10-0584   Reconstruction               0-001-014  03/31/11     DONE    DONE       DONE      12/15/10   12/13/10   11/04/10   02/06/07   10,155,15,16              64,735        64,735  HCM             0           0           0 Burton Behrendt Smith                   0      09/06/11                       06/14/13           
  -    PR Additions and Alterations    0-001-015                                              /  /       /  /     10/26/11     /  /     02 - 16                        0     6,415,200  HCM             0           0           0                                         0        /  /                           /  /             
11-0889   Additions and Alterations    0-001-015  07/03/12     DONE    DONE       DONE      03/06/12   03/05/12   10/26/11   10/11/11   02 - 16                4,025,891     4,025,891  HCM             0           0           0 Burton Behrendt Smith                   0      04/23/14                       05/23/14           

          Roanoke Avenue Elementary:
09-1594   Reconstruction               0-003-012  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   04/05/07   07/08/09   10,15,16                 271,437       271,437  HCM             0           0           0 Burton Behrendt Smith             271,437      03/04/14                       05/23/14           
10-0833   Reconstruction               0-003-013  07/20/11     DONE    DONE       DONE      02/08/11   02/08/11   06/10/10   02/07/08   4,7,14,16                565,000       565,000  HCM             0           0           0 Burton Behrendt Smith                   0      08/16/11                       08/16/11           
13-0187PR Additions and Alterations    0-003-014                         UNREVIEWED         08/12/13   08/12/13   10/26/11     /  /     02 - 16                        0             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0826   Additions and Alterations    0-003-014               STARTED DONE       ADD. REQ'D12/04/13   11/27/13   10/26/11   10/11/11   02 - 16                        0             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Pulaski Street Elementary:
09-1595   Reconstruction               0-004-015  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   03/17/08   07/08/09   7                        521,376       521,376  HCM             0           0           0 Burton Behrendt Smith             521,376      03/04/14                       05/23/14           
13-0188PR Additions and Alterations    0-004-017                         UNREVIEWED         08/12/13   08/12/13   10/26/11     /  /     02 - 16                        0             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0825   Additions and Alterations    0-004-017               STARTED DONE       ADD. REQ'D12/04/13   11/27/13   10/26/11   10/11/11   02 - 16                        0     2,122,848  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Aquebogue Elementary:
09-1596   Reconstruction               0-005-014  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   11/25/09   07/08/09   2,7,8,10,155,15,16       429,340       429,340  HCM             0           0           0 Burton Behrendt Smith             429,340      03/04/14                       06/09/14           
11-1067   Additions and Alterations    0-005-015  08/17/12     DONE    DONE       DONE      04/05/12   04/03/12   10/26/11   10/11/11   02 - 16                3,807,996     3,243,036  HCM             0           0           0 Burton Behrendt Smith                   0      03/04/14                       06/23/14           

          Relocatable Aquebog:
  -       Reconstruction               0-006-003                                              /  /       /  /     04/02/10     /  /     2,7,8,10,155,15,16             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Pulaski St. Music Annex:
09-1597   Reconstruction               0-008-002  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   03/31/10   07/08/09   2,7,8,10,155,15,16         4,001             0  HCM             0           0           0 Burton Behrendt Smith               4,001        /  /                           /  /             

          Riley Ave. Elementary:
09-1598   Reconstruction               0-009-011  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   06/08/05   07/08/09   8,9,16                 1,612,799     1,612,799  HCM             0           0           0 Burton Behrendt Smith           1,612,799      03/04/14                       05/23/14           
10-0355   Reconstruction               0-009-014  03/31/11     DONE    DONE       DONE      10/13/10   10/06/10   11/23/09   02/06/07   10,155,15,16             161,838       161,838  HCM             0           0           0 Burton Behrendt Smith                   0      09/06/11                       06/14/13           
  -    PR Additions and Alterations    0-009-015                                              /  /       /  /     10/26/11     /  /     02 - 16                        0             0  HCM             0           0           0                                         0        /  /                           /  /             
11-1252   Additions and Alterations    0-009-015  10/09/12     DONE    DONE       DONE      05/01/12   04/30/12   10/26/11   10/11/11   02 - 16                5,667,830     4,668,223  HCM             0           0           0 Burton Behrendt Smith                   0      05/27/14                       06/24/14           

          Middle School:
09-1599   Reconstruction               0-010-011  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   06/08/05   07/08/09   155                      887,583       887,583  HCM             0           0           0 Burton Behrendt Smith             887,583      03/04/14                       05/23/14           
10-0733   Reconstruction               0-010-015  12/09/11     DONE    DONE       DONE      01/25/11   01/12/11   11/20/09   02/06/07   4,8,13,155,16          2,200,770     2,200,770  HCM             0           0           0 Burton Behrendt Smith                   0      09/25/12                       10/03/12           
09-1038   Reconstruction               0-010-016  04/13/10     DONE    DONE       DONE      03/09/10   03/05/10   11/20/09   02/06/07   10                       173,347       173,347  HCM             0           0           0 Burton Behrendt Smith                   0      01/09/12                       09/20/13           
10-0356   Reconstruction               0-010-017  03/31/11     DONE    DONE       DONE      10/13/10   10/06/10   11/23/09   02/06/07   10,155,15,16             122,997       122,997  HCM             0           0           0 Burton Behrendt Smith                   0      09/06/11                       07/16/13           
12-1309PR Additions and Alterations    0-010-018                                              /  /       /  /     10/26/11     /  /     02 - 16                        0    20,651,374  HCM             0           0           0                                         0        /  /                           /  /             
13-0220   Additions and Alterations    0-010-018  04/16/14     DONE    DONE       DONE      08/15/13   08/08/13   10/26/11   10/11/11   02 - 16               15,965,944    12,616,905  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Riverhead Senior High:
09-1600   Reconstruction               0-012-016  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   06/08/05   07/08/09   10                     1,730,587     1,730,587  HCM             0           0           0 Burton Behrendt Smith           1,730,587      03/04/14                       05/23/14           
10-0357   Reconstruction               0-012-020  03/31/11     DONE    DONE       DONE      10/13/10   10/06/10   11/23/09   02/06/07   10,155,15,16             226,573       226,573  HCM             0           0           0 Burton Behrendt Smith                   0      09/03/11                       06/14/13           
12-0111   Additions and Alterations    0-012-021  06/05/13     DONE    DONE       DONE      08/15/12   08/03/12   10/26/11   10/11/11   02 - 16               32,572,521    23,333,754  HCM             0           0           0 Burton Behrendt Smith                   0      01/07/14                         /  /             

          Temp Classroom:
  -       Reconstruction               0-013-002                                              /  /       /  /     03/31/10     /  /     2,7,8,10,155,15,16             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Phillips Ave Portables (2):
09-1601   Reconstruction               0-035-003  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   03/31/10   07/08/09   2,7,8,10,155,15,16         7,575             0  HCM             0           0           0 Burton Behrendt Smith               7,575        /  /                           /  /             

          Phillips Avenue Portable:
  -       Reconstruction               0-036-002                                              /  /       /  /     04/01/10     /  /     2,7,8,10,155,15,16             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Roanoke School Portable:
09-1602   Reconstruction               0-038-002  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   04/01/10   07/08/09   2,8,10,155,15,16           5,170             0  HCM             0           0           0 Burton Behrendt Smith               5,170        /  /                           /  /             

          MS Portable:
09-1603   Reconstruction               0-039-002  07/02/12     DONE    DONE       DONE      07/06/10   07/08/09   04/01/10   07/08/09   2,7,8,10,155,15,16        16,385             0  HCM             0           0           0 Burton Behrendt Smith              16,385        /  /                           /  /             

          Portable A @ Riverhead High:
09-1604   Reconstruction               0-043-002  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   04/01/10   07/08/09   2,7,8,10,155,15,16        12,397             0  HCM             0           0           0 Burton Behrendt Smith              12,397        /  /                           /  /             

          Portable B @ Riverhead High:
09-1605   Reconstruction               0-044-002  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   04/01/10   07/08/09   2,7,8,10,155,15,16         6,485             0  HCM             0           0           0 Burton Behrendt Smith               6,485        /  /                           /  /             

          Portable C @ Riverhead High:
  -       Reconstruction               0-045-002                                              /  /       /  /     04/01/10     /  /     2,7,8,10,155,15,16             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          4 Double Units @ Riverhead HS:
  -       Reconstruction               0-047-002                                              /  /       /  /     04/01/10     /  /     2,7,8,10,155,15,16             0             0  HCM             0           0           0                                         0        /  /                           /  /             

          Administration Bldg:
09-1606   Additions and Alterations    1-002-002  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   05/03/07   07/08/09   02 - 16                   24,368             0  HCM             0           0           0 Burton Behrendt Smith              24,368      03/04/14                       05/23/14           

          Maintenance Shop/Bus Garage:
09-1607   Reconstruction               5-011-003  07/02/12     DONE    DONE       DONE      07/06/10   06/23/10   11/25/09   07/08/09   2,7,8,10,155,15,16        43,057        43,057  HCM             0           0           0 Burton Behrendt Smith              43,057      03/04/14                       05/23/14           

          XXRadio BoothXX (demo 2014):
  -    XX Additions and Alterations    7-022-001                         CANCELLED          08/15/13   08/08/13   10/26/11   10/11/11   02 - 16                        0             0  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Press Box @ MS:
13-0221   New Construction             7-050-001  04/16/14     DONE    DONE       DONE      03/07/14   03/07/14   03/07/14   10/11/11   02 - 16                  622,612             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LITTLE FLOWER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-06-03-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Respite Infirmory:
09-0724TQ Temporary Quarters           8-004-001  01/20/10     DONE    DONE       DONE      01/12/10   01/12/10   01/11/10     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHELTER ISLAND UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-07-01-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Shelter Island School:
09-0550   Reconstruction               0-001-022  12/31/09     DONE    DONE       DONE      12/07/09   12/03/09   07/22/09   05/01/09   2,4,7,15,16              925,000       925,000  DDJ             0           0           0 Mosaic Associates                       0      09/06/11                         /  /             
11-0671   Reconstruction               0-001-023  05/09/12     DONE    DONE       DONE      01/17/12   01/13/12   06/14/11   05/17/11   2,4,8,9,10,155,15,16   2,837,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-001-024                                              /  /       /  /     05/30/14     /  /     4,10,16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-025                                              /  /       /  /     05/30/14     /  /     2,9,13                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          St. Gabriel's Retreat:
09-1577XX New Construction             8-002-001                         CANCELLED          07/02/10   06/30/10     /  /       /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SMITHTOWN CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-08-01-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nesconset Elementary School:
12-0420   Reconstruction               0-001-021  06/27/13     DONE    DONE       DONE      11/14/12   11/08/12   05/31/12   09/28/12   7,8,9,155,15,16          104,500             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Smithtown Elementary:
  -       Reconstruction               0-006-023                                              /  /       /  /     06/18/14     /  /     2,155                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          St. James Elementary:
10-0224   Reconstruction               0-016-021  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   13,16                     15,825        15,825  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           
  -       Reconstruction               0-016-022                                              /  /       /  /     06/18/14     /  /     155                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Smithtown Middle School (H.S. East):
08-1321   Reconstruction               0-023-025  03/31/10     DONE    DONE       DONE      03/03/09   02/27/09   09/29/08   03/03/07   2,4,7,8,9,10,155,15,   2,578,500     2,578,500  DDJ             0           0           0 H2M Group                               0      08/01/11                         /  /             
12-0823   Reconstruction               0-023-027  02/22/13     DONE    DONE       DONE      02/12/13   02/12/13   12/19/12   04/17/08   2,7                    1,172,920     1,172,920  DDJ             0           0     444,071 John A Grillo-ARCHITECTS PC             0      09/06/13                       09/24/13           
10-0225   Reconstruction               0-023-028  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   13,16                     42,200        42,200  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           
10-1399XX Reconstruction               0-023-029  03/11/13               CANCELLED          06/17/11   06/13/11   05/19/11   03/03/07   2,4,7,8,9,10,13,155,   1,503,375             0  DDJ             0           0     626,907 H2M Group                               0        /  /                           /  /             
12-1096   Reconstruction               0-023-030  04/22/13     DONE    DONE       DONE      04/12/13   04/12/13   03/13/13   05/15/07   2                        580,525       580,525  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/06/13                       09/24/13           
13-0672   Reconstruction               0-023-031  12/16/13     DONE    DONE       DONE      11/04/13   11/04/13   11/04/13   05/20/08   2,4,7,8,9,10,155,15,   2,200,000             0  DDJ             0           0     848,401 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
  -       Reconstruction               0-023-032                                              /  /       /  /     06/19/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Dogwood Elementary School:
  -       Reconstruction               0-024-017                                              /  /       /  /     06/18/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Mt. Pleasant Elementary:
  -       Reconstruction               0-025-019                                              /  /       /  /     06/18/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Great Hollow Jr. High:
03-0391   Reconstruction               0-027-006  09/10/03     DONE    DONE       DONE      09/06/03   08/01/03   06/10/96   06/15/02   7                        260,030       260,030  MAC             0           0           0 Burton Behrendt Smith                   0      04/25/05                         /  /             
09-0906   Reconstruction               0-027-016  02/25/10     DONE    DONE       DONE      02/18/10   02/11/10   12/31/09   04/17/07   2,9                      132,944       132,944  DDJ             0           0           0 H2M Group                               0      09/06/10                         /  /             
10-0226   Reconstruction               0-027-017  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   15,16                    226,825       226,825  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           
12-0824   Reconstruction               0-027-018  02/22/13     DONE    DONE       DONE      02/12/13   02/12/13   12/19/12   05/15/00   7                      1,684,450     1,684,450  DDJ             0           0           0 John A Grillo-ARCHITECTS PC             0      09/06/13                       09/24/13           
  -       Reconstruction               0-027-019                                              /  /       /  /     06/18/14     /  /     155                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Mills Pond Elementary:
  -       Reconstruction               0-028-009                                              /  /       /  /     06/18/14     /  /     155                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Accompsett Elementary:
  -       Reconstruction               0-029-022                                              /  /       /  /     06/18/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Branch Brook Elementary:
  -       Reconstruction               0-030-020                                              /  /       /  /     06/18/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Tackan Elementary School:
09-0651   Reconstruction               0-031-017  04/06/10     DONE    DONE       DONE      12/30/09   12/23/09   01/09/09   05/15/08   2,4                      400,000       400,000  DDJ             0           0           0 H2M Group                               0      10/17/11                         /  /             
  -       Reconstruction               0-031-018                                              /  /       /  /     06/18/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Nesaquake Intermediate:
10-0227   Reconstruction               0-033-014  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   13,16                    226,825       226,825  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           
  -       Reconstruction               0-033-015                                              /  /       /  /     06/18/14     /  /     155                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Accompsett Middle School:
10-0228   Reconstruction               0-034-026  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   13,16                    211,000       211,000  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           
  -       Reconstruction               0-034-027                                              /  /       /  /     06/18/14     /  /     155                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Smithtown H.S. West:
08-1474   Reconstruction               0-038-020  08/31/09     DONE    DONE       DONE      04/09/09   04/07/09   03/17/08   05/15/07   2,4,9,155,15,16          208,271       208,271  DDJ             0           0           0 H2M Group                               0      09/02/11                         /  /             
08-1076   Reconstruction               0-038-021  08/07/09     DONE    DONE       DONE      01/09/09   01/09/09   07/16/08   05/15/07   2,7,9,155,15,16        2,240,250     2,240,250  DDJ             0           0           0 H2M Group                               0      09/06/10                         /  /             
10-0229   Reconstruction               0-038-022  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   13,16                    221,550       221,550  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           
09-1573   Reconstruction               0-038-023  07/28/10     DONE    DONE       DONE      07/02/10   06/21/10   06/18/10   05/25/10   15                       645,000             0  DDJ             0           0           0 H2M Group                               0      09/02/11                         /  /             
10-0106   Reconstruction               0-038-024  12/08/10     DONE    DONE       DONE      08/11/10   07/30/10   06/18/10   09/12/00   2,16                     149,800       149,800  DDJ             0           0           0 H2M Group                               0      11/23/11                         /  /             
  -       Reconstruction               0-038-025                                              /  /       /  /     06/19/14     /  /     2,155,15,16                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          J. Barton Admin./Ahern Annex:
10-0230   Reconstruction               1-008-014  01/24/11     DONE    DONE       DONE      09/17/10   09/15/10   04/16/10   06/15/00   13,16                     33,760             0  DDJ             0           0           0 H2M Group                               0      08/31/12                       09/26/12           

          District Storage:
08-1104DB Discovered Building          2-073-002  09/16/09     DONE    DONE       DONE      01/21/09   01/15/09   07/16/08     /  /     2,13                           0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Storage Container @ Branch Brook:
08-1190DB Discovered Building          2-077-001  09/16/09     DONE    DONE       DONE      02/10/09   02/04/09   01/29/09     /  /                                    0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Storage Building @ High School East:
10-1179DB Discovered Building          2-079-001  06/14/11     DONE    DONE       DONE      04/12/11   04/08/11   04/02/10     /  /                                    0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Storage Building @ DogwoodElementary:
10-1180DB Discovered Building          2-080-001  06/14/11     DONE    DONE       DONE      04/12/11   04/08/11   04/02/10     /  /                                    0             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             

          Storage FDR Kickers:
10-0045DB Discovered Building          2-081-001  08/12/10     DONE    DONE       DONE      07/27/10   07/27/10   07/23/10     /  /                                    0             0  DDJ             0           0           0 Petracca Design & Engineering           0        /  /                           /  /             

          New Maintenance Building:
12-0280   New Construction             3-082-001  09/03/13     DONE    DONE       DONE      10/15/12   10/15/12   12/13/11   09/28/12   02 - 16                  108,000             0  DDJ             0           0           0 H2M Group                               0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




KINGS PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-08-05-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          RJO Intermediate:
10-1291   Additions and Alterations    0-002-017  07/11/11     DONE    DONE       DONE      05/12/11   05/06/11   04/14/11   05/17/11   02 - 16                1,008,341     1,008,341  HCM             0           0           0 H2M Group                               0      09/02/11                       10/24/11           
12-0239   Reconstruction               0-002-018               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             

          Kings Park High:
  -       Reconstruction               0-004-025                                              /  /       /  /     07/07/10     /  /     2,13                           0             0  HCM             0           0           0                                         0        /  /                           /  /             
12-0240   Reconstruction               0-004-026               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             

          Parkview Elementary:
12-0241   Reconstruction               0-005-019               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             
13-1090   Reconstruction               0-005-020  07/22/14     DONE    DONE       DONE      01/24/14   01/24/14   02/21/13   11/13/12   4,7                            0             0  JMB             0           0           0 H2M Group                               0        /  /                           /  /             

          Fort Salonga Elementary:
12-0242   Reconstruction               0-006-021               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             

          W.T.Rogers Middle School:
12-0243   Reconstruction               0-008-021               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             

          San Remo School:
12-0244   Reconstruction               0-009-008               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             

          Press Box:
12-0060   New Construction             2-013-001  04/09/13     DONE    DONE       DONE      07/26/12   07/18/12   06/08/12   06/12/12   02 - 16                   75,000             0  HCM             0           0           0 H2M Group                               0      09/03/13                       09/10/13           

          Bus/Maintenance Garage:
12-0245   Reconstruction               5-003-010               DONE    DONE       ADD. REQ'D10/03/12   09/24/12   06/29/12   05/08/12   155,15,16                      0             0  HCM             0           0           0 H2M Group                               0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




REMSENBURG-SPEONK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-01-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Remsenburg Elementary:
09-0465   Additions and Alterations    0-002-011  02/24/10     DONE    DONE       DONE      11/25/09   11/19/09   07/13/09   03/04/08   02 - 16                   27,500        27,500  DDJ             0           0           0 James M. Campbell Architects            0      09/02/10                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WESTHAMPTON BEACH UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-02-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
10-0907   Additions and Alterations    0-002-013  03/25/11     DONE    DONE       DONE      02/24/11   02/22/11   12/28/10   06/09/10   02 - 16                  196,250       196,250  DDJ             0           0           0 Burton Behrendt Smith                   0      12/28/11                         /  /             

          Senior High School:
10-0446   Reconstruction               0-004-017  04/01/11     DONE    DONE       DONE      11/08/10   11/04/10   01/11/10   05/15/07   8,9,155,16               116,900       116,900  DDJ             0           0     116,900 Burton Behrendt Smith                   0      07/18/12                       08/06/12         YES
                                                                                                                                                                                                                                                                                                                                   
09-1380   Reconstruction               0-004-018  05/20/10     DONE    DONE       DONE      05/04/10   04/27/10   04/02/10   05/18/10   2                      1,600,000             0  DDJ             0           0           0 Burton Behrendt Smith                   0      09/10/10                         /  /             
10-0908   Additions and Alterations    0-004-019  03/25/11     DONE    DONE       DONE      02/23/11   02/22/11   12/28/10   06/09/10   02 - 16                  196,250       196,250  DDJ             0           0           0 Burton Behrendt Smith                   0      12/28/11                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




QUOGUE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-03-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Quogue Elementary:
10-0585   Reconstruction               0-001-011  03/30/11     DONE    DONE       DONE      12/20/10   12/08/10   09/09/10   04/14/09   2                         36,900        36,900  JOD             0           0           0 ECG Engineering, LLC                    0      04/26/12                       06/25/12           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HAMPTON BAYS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-05-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Hampton Bays Elementary:
09-1458   Alterations                  0-003-009  06/11/10     DONE    DONE       DONE      05/20/10   05/13/10   04/13/10   05/18/10   02 - 16                  250,000       250,000  HCM             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-0742   Reconstruction               0-003-010  04/25/13     DONE    DONE       DONE      01/31/13   01/30/13   12/07/12   11/27/12   2,4                    1,053,850     1,053,850  JMB             0           0           0 Burton Behrendt Smith                   0      09/07/13                       12/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-0977   Reconstruction               0-003-011  02/28/14     DONE    DONE       DONE      03/14/13   03/14/13   01/24/13   11/13/12   8,155,15,16              898,063       898,063  JMB             0           0           0 Burton Behrendt Smith             898,063        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0615   Reconstruction               0-003-012               DONE    DONE       ADD. REQ'D10/24/13   10/22/13   09/19/13   11/27/12   2,4,7,8,9,155,15,16      763,453       763,453  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-1000   Reconstruction               0-003-013  05/30/14     DONE    DONE       DONE      01/13/14   01/07/14   11/19/13   11/27/12   4,8,9,155,15,16        3,004,486     3,004,486  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          High School:
12-0743   Reconstruction               0-010-005  04/25/13     DONE    DONE       DONE      01/31/13   01/30/13   12/07/12   11/27/12   2,8,9,16               2,901,219     2,901,219  JMB             0           0           0 Burton Behrendt Smith                   0      09/07/13                       12/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
09-1552   Reconstruction               0-010-007  07/23/10     DONE    DONE       DONE      06/21/10   06/10/10   04/13/10   05/18/10   2,10,15,16                93,440        93,440  HCM             0           0           0 Burton Behrendt Smith                   0      08/31/10                       01/24/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-1300   Reconstruction               0-010-008  08/12/11     DONE    DONE       DONE      05/19/11   05/12/11   03/23/11   05/18/10   2,4,8,9,10,155,15,16     300,000       300,000  HCM             0           0           0 Burton Behrendt Smith                   0      09/27/11                       12/12/11         YES
                                                                                                                                                                                                                                                                                                                                   
11-1081   Reconstruction               0-010-009  09/07/12     DONE    DONE       DONE      04/05/12   04/02/12   01/05/12   05/22/12   2,4,8,9,155,15,16        548,282       548,282  HCM             0           0           0 Burton Behrendt Smith                   0      11/07/12                       01/24/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-0978   Reconstruction               0-010-010  02/28/14     DONE    DONE       DONE      03/14/13   03/14/13   01/09/13   11/13/12   8,155,15,16            1,460,502     1,460,502  JMB             0           0           0 Burton Behrendt Smith           1,460,502        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
12-1250   Reconstruction               0-010-011  06/18/13     DONE    DONE       DONE      06/05/13   05/31/13   02/05/13   11/27/12   155,16                   700,000       700,000  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0616   Reconstruction               0-010-012               DONE    DONE       ADD. REQ'D10/24/13   10/22/13   09/19/13   11/27/12   2,4,7,8,9,155,15,16      609,727       609,727  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-1001   Reconstruction               0-010-013  05/30/14     DONE    DONE       DONE      01/13/14   01/07/14   11/19/13   11/27/12   2,4,7,8,9,155,15,16    3,448,102     3,448,102  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New Middle School:
12-0979   Reconstruction               0-016-002  02/28/14     DONE    DONE       DONE      03/14/13   03/14/13   01/24/13   11/13/12   8,155,15,16              674,662       674,662  JMB             0           0           0 Burton Behrendt Smith             674,662        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0617   Reconstruction               0-016-003               DONE    DONE       ADD. REQ'D10/24/13   10/22/13   10/24/13     /  /     8,155,15,16              189,500       189,500  JMB             0           0           0 Burton Behrendt Smith                   0      11/27/12                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-1002   Reconstruction               0-016-004  05/30/14     DONE    DONE       DONE      01/13/14   01/07/14   11/19/13   11/27/12   8,155,15,16              415,000       415,000  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          District Office:
12-0980   Reconstruction               1-001-001  02/28/14     DONE    DONE       DONE      03/14/13   03/14/13   01/09/13   11/13/12   8,155,15,16               37,382             0  JMB             0           0           0 Burton Behrendt Smith              37,382        /  /                           /  /             
13-1003   Reconstruction               1-001-003  06/24/14     DONE    DONE       DONE      01/13/14   01/07/14   11/19/13   11/27/12   8,9,155,15,16             41,450             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          High School Press Box:
13-0185   New Construction             2-018-001  04/03/14     DONE    DONE       DONE      08/12/13   08/12/13   06/05/13   11/27/12   02 - 16                  698,095             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Storage Building:
13-0386   New Construction             2-020-001  03/21/14     DONE    DONE       DONE      09/19/13   09/18/13   08/02/13   11/27/12   02 - 16                  221,480             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          High School Concession Stand:
13-0186   New Construction             7-017-001  04/03/14     DONE    DONE       DONE      08/12/13   08/12/13   06/05/13   11/17/12   02 - 16                1,300,435             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Elem School Comfort Station:
13-0387   New Construction             7-019-001  03/21/14     DONE    DONE       DONE      09/19/13   09/18/13   06/05/13   11/27/12   02 - 16                  221,480             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Districtwide:
13-0189   Reconstruction               7-999-002  08/29/13     DONE    DONE       DONE      08/13/13   08/13/13   03/26/13   11/27/12   16                        76,000             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTHAMPTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-06-03
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Southampton Elementary:
09-0986   Reconstruction               0-001-023  04/19/10     DONE    DONE       DONE      03/02/10   02/25/10   09/23/08   05/19/09   4,7                    2,229,078     2,229,078  JOD             0           0           0 Burton Behrendt Smith                   0      03/12/12                       06/27/14         YES
                                                                                                                                                                                                                                                                                                                                   
11-0452   Reconstruction               0-001-025  03/23/12     DONE    DONE       DONE      12/02/11   12/01/11   02/15/11   05/17/11   2,4,8,9,155,16         1,030,571     1,030,571  JOD             0           0           0 Burton Behrendt Smith                   0      02/28/14                       04/03/14         YES
                                                                                                                                                                                                                                                                                                                                   
10-1119   Reconstruction               0-001-026  03/19/13     DONE    DONE       DONE      03/30/11   03/28/11   02/15/11   09/07/10   155,15,16                430,031       430,031  JOD             0           0           0 Burton Behrendt Smith             430,031        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-1223   Reconstruction               0-001-027  04/25/14     DONE    DONE       DONE      02/12/14   02/07/14   11/12/13   05/21/13   2,4,16                   201,708             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-028                                              /  /       /  /     12/03/13     /  /     2,16                           0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-029                                              /  /       /  /     06/10/14     /  /     7,9                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Intermediate School:
11-0453   Reconstruction               0-003-019  03/23/12     DONE    DONE       DONE      12/02/11   12/01/11   02/15/11   05/17/11   2,9,10,155,15,16       1,194,298     1,194,298  JOD             0           0           0 Burton Behrendt Smith                   0      11/22/13                       02/07/14         YES
                                                                                                                                                                                                                                                                                                                                   
10-1120   Reconstruction               0-003-020  03/19/13     DONE    DONE       DONE      03/30/11   03/28/11   02/15/11   09/07/10   155,15,16                207,654             0  JOD             0           0           0 Burton Behrendt Smith             207,654        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-0132   Reconstruction               0-003-021  10/08/13     DONE    DONE       DONE      08/05/13   08/02/13   05/24/13   05/21/13   4                        107,578             0  JOB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-003-022                                              /  /       /  /     06/10/14     /  /     2,7,10,155                     0             0  MFS             0           0           0                                         0        /  /                           /  /             

          High School:
09-0851   Additions and Alterations    0-007-010  04/26/10     DONE    DONE       DONE      02/03/10   02/01/10   07/21/05   02/06/07   02 - 16               17,984,221    12,701,435  JOD             0           0           0 Burton Behrendt Smith                   0      09/01/11           YES           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0836   Reconstruction               0-007-015  01/28/13     DONE    DONE       DONE      02/23/12   02/21/12   03/02/10   02/06/07   4,8,9,10,13,155,15,1     744,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
11-0605   Reconstruction               0-007-016  03/20/12     DONE    DONE       DONE      01/06/12   01/03/12   04/08/10   05/17/11   9,10,13,155,15,16      1,166,000     1,166,000  JOD             0           0           0 Burton Behrendt Smith                   0      09/06/13                       12/04/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-1121   Reconstruction               0-007-017  03/19/13     DONE    DONE       DONE      03/30/11   03/28/11   02/15/11   09/07/10   10,155,15,16           2,116,415             0  JOD             0           0           0 Burton Behrendt Smith           2,116,415        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
11-0454   Reconstruction               0-007-018  03/23/12     DONE    DONE       DONE      12/02/11   12/01/11   06/30/11   05/17/11   2,4,8,9,155,15,16        858,285       858,285  JOD             0           0           0 Burton Behrendt Smith                   0      05/01/14                       06/05/14         YES
                                                                                                                                                                                                                                                                                                                                   
13-0133   Reconstruction               0-007-019  10/08/13     DONE    DONE       DONE      08/05/13   08/02/13   05/24/13   05/21/13   4                        129,429             0  JOB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New District Office:
  -    PR New Construction             1-020-001                                              /  /       /  /     02/15/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
09-0345   Alterations                  5-005-005  01/07/10     DONE    DONE       DONE      10/27/09   10/22/09   11/03/06   05/19/09   02 - 16                  360,000       360,000  JOD             0           0           0 Burton Behrendt Smith                   0      11/05/13                       02/07/14           
11-0855   Reconstruction               5-005-007  06/11/12     DONE    DONE       DONE      02/28/12   02/27/12   01/04/11   05/17/11   2,7,8,9,155,15,16      1,100,000     1,100,000  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New Concession Stand @ High School:
10-0903   New Construction             7-018-001  06/29/11     DONE    DONE       DONE      02/24/11   02/22/11   12/28/09   02/06/07   02 - 16                  778,357             0  JOD             0           0           0 Burton Behrendt Smith                   0      04/26/13                       05/14/13           

          Athletic Support Facility:
  -    XX New Construction             7-019-001                         CANCELLED            /  /       /  /     01/10/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRIDGEHAMPTON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-09-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bridgehampton High:
11-0482   Reconstruction               0-001-014  06/04/12     DONE    DONE       DONE      12/12/11   12/12/11   04/12/05   11/30/11   10                       136,000       136,000  HCM             0           0           0 Chaleff & Rogers Architects,P           0      09/25/12                       01/14/14         YES
                                                                                                                                                                                                                                                                                                                                   
10-0616   Reconstruction               0-001-015  01/14/11     DONE    DONE       DONE      12/23/10   12/10/10   05/08/07   05/18/10   7,8,13                 1,395,505     1,395,505  HCM             0           0      45,505 Chaleff & Rogers Architects,P           0      01/13/14                       05/12/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Greenhouse:
10-0358   New Construction             0-008-001  11/04/10     DONE    DONE       DONE      10/14/10   10/07/10   07/09/10   03/24/10   02 - 16                        0             0  HCM             0           0           0 Chaleff & Rogers Architects,P           0        /  /                           /  /             

          Storage Building:
  -       New Construction             2-009-001                                              /  /       /  /     04/30/14     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EASTPORT - SOUTH MANOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-12-06
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Eastport Elementary:
09-0330PR Additions and Alterations    0-001-001                         UNREVIEWED         10/22/09   10/16/09   08/25/05     /  /     02 - 16                7,550,000     1,883,218  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
10-1394   Reconstruction               0-001-001  02/21/12     DONE    DONE       DONE      06/15/11   06/10/11     /  /     12/09/09                          4,267,324     4,201,783                  0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
10-0937   Reconstruction               0-001-003  05/20/11     DONE    DONE       DONE      03/04/11   02/18/11   02/13/07   12/08/09   2,8,9,155,15,16        3,140,000     3,140,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
09-0368   Reconstruction               0-001-005  08/26/13     DONE    DONE       DONE      10/29/09   10/26/09   05/14/09   10/21/09   10,155,16              3,880,150     3,880,150  DDJ             0           0           0 Wiedersum Associates Architec   3,880,150        /  /                           /  /             
13-1314   Reconstruction               0-001-006               STARTED DONE       ADD. REQ'D03/07/14   03/07/14   12/06/12   12/08/09   2,4,7,8,9,10,155,15,           0    10,328,198  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
12-0987   Reconstruction               0-001-007  05/21/13     DONE    DONE       DONE      03/19/13   03/19/13   02/14/13   12/08/09   2,4,7,8,9                543,000       543,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Relocatable I(demo):
11-0290   Reconstruction               0-002-001  11/03/11     DONE    DONE       DONE      10/26/11   10/25/11   10/07/11   12/08/09   2                         44,000        44,000  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Relocatable 2 (demo):
11-0291   Reconstruction               0-005-001  11/03/11     DONE    DONE       DONE      10/26/11   10/25/11   10/07/11   12/08/09   2                         55,000             0  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Eastport-South Manor Jr/Sr HS:
09-0369   Reconstruction               0-011-002  08/26/13     DONE    DONE       DONE      10/29/09   10/26/09   05/14/09   10/21/09   10,155,16              5,592,074             0  DDJ             0           0           0 Wiedersum Associates Architec   5,592,074        /  /                           /  /             
  -       Reconstruction               0-011-003                                              /  /       /  /     12/06/12     /  /     2,4,8,9,10,155,15,16           0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-1102PR Reconstruction               0-011-004                         UNREVIEWED         04/12/13   04/12/13   04/09/13     /  /     2,4,7,8,9,155,15,16            0    67,972,805  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          South Street ES (frmrly South Manor):
09-0331PR Additions and Alterations    0-012-002                         UNREVIEWED         10/22/09   10/16/09   12/01/05     /  /     02 - 16               12,300,000     7,233,510  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
10-0618   Additions and Alterations    0-012-002  05/12/11     DONE    DONE       DONE      12/24/10   12/16/10   12/01/05   12/08/09   02 - 16               12,300,000    11,705,440  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-1315   Reconstruction               0-012-003               STARTED DONE       ADD. REQ'D03/07/14   03/07/14   12/06/12   12/08/09   4,9,10,155,15,16               0     6,134,400  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
09-0370   Reconstruction               0-012-005  08/26/13     DONE    DONE       DONE      10/29/09   10/26/09   05/14/09   10/21/09   8,10,155,16            3,442,467             0  DDJ             0           0           0 Wiedersum Associates Architec   3,442,467        /  /                           /  /             

          South St. Portables:
10-1247   Reconstruction               0-013-001  05/12/11     DONE    DONE       DONE      05/03/11   04/29/11   04/29/11   12/08/09   2                         55,000             0  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Dayton Ave. School:
09-0332PR Additions and Alterations    0-014-002                         UNREVIEWED         10/22/09   10/16/09   12/01/05     /  /     02 - 16               16,200,000     9,745,110  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
09-1139   Additions and Alterations    0-014-002  09/01/10     DONE    DONE       DONE      03/25/10   03/16/10   12/01/05   12/08/09   02 - 16               16,200,000    15,981,416  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
13-1316   Reconstruction               0-014-004               STARTED DONE       ADD. REQ'D03/07/14   03/07/14   12/06/12   12/08/09   2,7,8,9,10,155,15,16           0    10,770,165  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
09-0601   Reconstruction               0-014-006  08/26/13     DONE    DONE       DONE      12/23/09   12/21/09   05/14/09   10/21/09   16                       283,394             0  DDJ             0           0           0 Wiedersum Associates Architec     283,394        /  /                           /  /             
  -       Reconstruction               0-014-007                                              /  /       /  /     02/21/12     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Tuttle Elementary:
09-0333PR New Construction             0-022-001                         UNREVIEWED         10/22/09   10/16/09   12/06/05     /  /     02 - 16               24,785,000     9,684,636  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
10-1395   Reconstruction               0-022-001  02/21/12     DONE    DONE       DONE      06/15/11   06/10/11     /  /     12/09/09   2,4,7,8,9,10,13,14,1  23,177,830    17,046,292  DDJ             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Maintenance Garage:
  -       Reconstruction               3-004-001                                              /  /       /  /     12/07/12     /  /     2,7,8,9,155,15,16              0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TUCKAHOE COMMON SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-13-08
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Tuckahoe Common School:
10-1213   Reconstruction               0-001-009  05/02/11     DONE    DONE       DONE      04/20/11   04/18/11   03/07/08   02/15/11   10,155,16                120,186       120,186  JOD             0           0     102,867 Chaleff & Rogers Architects,P           0      08/13/12                       01/30/13         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-010                                              /  /       /  /     12/07/11     /  /     15                             0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-1025   Reconstruction               0-001-011  03/21/12     DONE    DONE       DONE      03/28/12   03/22/12   03/07/12   02/27/12   2                        180,392       180,392  JOD             0           0           0 Chaleff & Rogers Architects,P           0      07/26/12                       09/20/12         YES
                                                                                                                                                                                                                                                                                                                                   
11-1249   Reconstruction               0-001-012  12/12/12     DONE    DONE       DONE      05/01/12   04/30/12   03/21/12   01/23/12   8,10,15,16               583,217       583,217  JOD             0           0           0 Savin Engineers, P.C.             583,217        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-013                                              /  /       /  /     04/17/12     /  /     8,10,15,16                     0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-014                                              /  /       /  /     11/09/12     /  /     7                              0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-0409   Reconstruction               0-001-015  11/22/13     DONE    DONE       DONE      09/24/13   09/23/13   05/03/13   06/19/12   15                       465,000             0  JMB             0           0           0 Chaleff & Rogers Architects,P           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Residence:
  -    PR New Construction             1-005-001                                              /  /       /  /     09/30/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST QUOGUE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-09-17-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          East Quogue Elementary School:
09-0083   Reconstruction               0-001-010  07/31/09     DONE    DONE       DONE      07/23/09   07/21/09   12/18/03   07/01/09   155                      499,995       499,995  HCM             0           0     149,975 Savin Engineers, P.C.                   0      10/31/09                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          House (demo):
12-0430   Reconstruction               7-005-001  01/25/13     DONE    DONE       DONE      11/16/12   11/02/12   09/20/12   02/28/12   2                         77,100             0  JMB             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OYSTERPONDS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-10-02-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Oysterponds Elementary:
09-0511   Reconstruction               0-001-006  01/29/14     DONE    DONE       DONE      11/27/09   11/24/09   06/29/06   05/15/08   8                        150,000       150,000  JOD             0           0           0 Beatty Harvey & Associates              0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FISHERS ISLAND UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-10-04-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bowling Alley:
  -       Reconstruction               7-007-001                                              /  /       /  /       /  /       /  /     8,9,155,15,16                  0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTHOLD UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-10-05-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Southold High & Middle:
09-0449   Reconstruction               0-001-011  02/22/10     DONE    DONE       DONE      11/19/09   11/16/09   08/25/09   11/15/07   2                         63,175        63,175  DDJ             0           0           0 Burton Behrendt Smith                   0      11/01/13                       12/12/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-0048   Reconstruction               0-001-012  04/12/11     DONE    DONE       DONE      07/28/10   07/14/10   03/02/10   09/10/08   2,155,15,16            1,303,527     1,303,527  DDJ             0           0           0 Burton Behrendt Smith           1,303,527      08/01/13                       10/01/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-0760   Reconstruction               0-001-013  02/14/13     DONE    DONE       DONE      02/01/13   01/22/13   12/07/12   10/16/12   2,4,7                  1,999,219     1,999,219  DDJ             0           0           0 Burton Behrendt Smith                   0      01/28/14                       02/25/14         YES
                                                                                                                                                                                                                                                                                                                                   
13-1213   Reconstruction               0-001-014  07/18/14     DONE    DONE       DONE      02/12/14   02/11/14   10/03/13   10/16/12   2,4,8,9,155,15,16              0    12,664,677  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
13-1214   Reconstruction               0-001-015  NEED AUTH    DONE    DONE       DONE      02/12/14   02/11/14   10/03/13     /  /     2,4,8,9,155,15,16              0    12,664,677  DDJ             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Elementary School:
10-0049   Reconstruction               0-014-004  04/12/11     DONE    DONE       DONE      07/28/10   07/14/10   03/02/10   09/10/08   2,155,16                 234,630       234,630  DDJ             0           0           0 Burton Behrendt Smith             234,630      08/01/13                       10/01/13         YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREENPORT UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-10-10-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
10-0709   Reconstruction               0-001-009  03/07/11     DONE    DONE       DONE      01/03/11   12/27/10   08/19/10   12/07/10   2,4,7,8,9,155,15,16    2,746,810     2,746,810  JOD             0           0           0 Tetra  Tech Architects & Engi           0      03/22/13                       11/21/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-0947   Reconstruction               0-001-010  05/17/11     DONE    DONE       DONE      03/04/11   02/23/11   02/22/11   12/07/10   155,15,16              2,325,000     2,325,000  JOD             0           0           0 Tetra  Tech Architects & Engi           0      11/12/13                       11/27/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-1068   Reconstruction               0-001-011  04/01/11     DONE    DONE       DONE      03/17/11   03/15/11   03/04/11   12/07/10   2,4,8,9,155,15,16        680,000       680,000  JOD             0           0           0 Tetra  Tech Architects & Engi           0      03/22/13                       06/13/13         YES
                                                                                                                                                                                                                                                                                                                                   
10-1177   Reconstruction               0-001-012  06/30/11     DONE    DONE       DONE      04/12/11   04/07/11   03/28/11   12/07/10   2,4,8,9,155,15,16      1,506,550     1,506,550                  0           0           0 Tetra  Tech Architects & Engi           0      03/22/13                       06/13/13         YES
                                                                                                                                                                                                                                                                                                                                   
11-0657   Reconstruction               0-001-013  10/15/12     DONE    DONE       DONE      01/12/12   01/10/12   12/20/11   12/07/10   2,16                   1,496,640             0  JOD             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             
12-1036   Reconstruction               0-001-014  06/03/13     DONE    DONE       DONE      03/27/13   03/27/13   01/30/13   12/07/10   2,4                      470,000       470,000  MFS             0           0           0 Tetra  Tech Architects & Engi           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MATTITUCK - CUTCHOGUE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-10-12-02
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Mattituck-Cutchogue Jr./Sr. HS:
13-0795   Reconstruction               0-001-005  03/26/14     DONE    DONE       DONE      11/29/13   11/29/13   07/19/13   10/29/13   2,9,13                   925,000             0  JMB             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             

          Cutchogue East School:
09-1371   Reconstruction               0-007-003  05/24/10     DONE    DONE       DONE      05/03/10   04/26/10   03/26/10   05/18/10   2,8                       90,000             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             
11-0557   Reconstruction               0-007-004               STARTED DONE       DONE      12/28/11   12/27/11   09/19/11     /  /     2,8                      100,000             0  HCM             0           0           0 John A Grillo-ARCHITECTS PC             0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES EASTERN SUFFOLK STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-91-00-00
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Carmine Antonelli (Central):
09-1553   Reconstruction               0-001-011  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   11/02/09   12/15/08   155,16                   194,800             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Shop Bldg - Riverhead Vocational:
09-1554   Reconstruction               0-002-010  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   02/09/10   12/15/08   155,16                   168,000             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
  -       Reconstruction               0-002-011                                              /  /       /  /     04/30/10     /  /     2                              0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Jefferson Academic Center:
09-1555   Reconstruction               0-003-008  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   02/09/10   12/15/08   155,16                    83,900             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-1070   Reconstruction               0-003-009  10/12/12     DONE    DONE       DONE      04/04/12   03/29/12   03/31/11   12/12/11   8,9                      175,000       175,000  JOD             0           0           0 Burton Behrendt Smith                   0      02/12/13                       04/08/13           

          Special Education Center:
11-0643   Reconstruction               0-013-010  03/12/12     DONE    DONE       DONE      01/12/12   01/10/12   03/31/11   01/27/10   8                        350,000       350,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/06/13                       08/27/13           

          BOCES I Learning Center:
11-0644   Reconstruction               0-022-009  03/12/12     DONE    DONE       DONE      01/12/12   01/10/12   03/31/11   01/27/10   8                         50,000        50,000  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          High School Ward Tech Cen.:
09-1556   Reconstruction               0-025-007  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   02/09/10   12/15/08   155,16                    51,400             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Gary D. Bixtorn Tech Ct(Brookheaven):
09-1142   Reconstruction               0-048-015  07/06/10     DONE    DONE       DONE      03/25/10   03/18/10   06/09/09   01/27/10   2,155,16                 168,500       168,500  JOD             0           0           0 Wiedersum Associates Architec           0      03/07/12                       12/12/12           
  -       Reconstruction               0-048-016                                              /  /       /  /     04/30/10     /  /     2                              0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Edward J. Milliken Technical Center:
  -       Reconstruction               0-049-018                                              /  /       /  /     07/22/14     /  /     2,7                            0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Islip Academic Center:
09-1557   Reconstruction               0-057-005  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   02/09/10   12/15/08   155,16                   376,800       376,800  JOD             0           0           0 Wiedersum Associates Architec           0      09/30/12                       12/12/12           
09-1507   Reconstruction               0-057-006  06/24/10     DONE    DONE       DONE      06/09/10   06/02/10   04/08/10   01/27/10   2,7                      540,000       540,000  JOD             0           0           0 Burton Behrendt Smith                   0      03/29/09                       12/12/12           

          Brookhaven Learning Center:
09-1558   Reconstruction               0-058-007  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   12/15/08   155,16                   229,600             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             
11-0645   Reconstruction               0-058-008  03/12/12     DONE    DONE       DONE      01/12/12   01/10/12   03/31/11   01/27/10   8                        230,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Brookhaven Career Center:
09-1559   Reconstruction               0-059-007  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   12/15/08   155,16                   264,300       264,300  JOD             0           0           0 Wiedersum Associates Architec           0      08/01/12                       01/17/13           
11-0646   Reconstruction               0-059-008  03/12/12     DONE    DONE       DONE      01/12/12   01/10/12   03/31/11   01/27/10   8                         25,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Islip Career Center:
09-1560   Reconstruction               0-061-008  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   12/15/08   155,16                   291,200       291,200  JOD             0           0           0 Wiedersum Associates Architec           0      08/01/12                       01/17/13           
11-0647   Reconstruction               0-061-009  03/12/12     DONE    DONE       DONE      01/10/12   01/10/12   03/31/11   01/27/10   8                        520,000       520,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/06/13                       08/27/13           

          Educ. Communic. Office:
09-1561   Reconstruction               1-029-003  04/11/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   12/15/08   155,16                    48,100             0  JOD             0           0           0 Wiedersum Associates Architec           0        /  /                           /  /             

          Grounds Building:
  -       New Construction             3-100-001                                              /  /       /  /     07/22/14     /  /     02 - 16                        0             0  MFS             0           0           0                                         0        /  /                           /  /             

          St Joseph's Academy:
12-1180TQ Temporary Quarters           8-099-001                       ADDENDUM REQ'D       05/10/13   05/08/13   04/08/13     /  /                                    0             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES WESTERN SUFFOLK STATUS REPORT ON CAPITAL PROJECTS
District No.: 58-93-00-00
last updated on 07/31/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          McGuire Hall #1:
09-0271   Reconstruction               0-001-013  10/27/09     DONE    DONE       DONE      09/28/09   09/28/09   05/01/07   05/08/07   155,16                   300,000       300,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      11/30/10                         /  /             
09-0672   Reconstruction               0-001-014  08/25/10     DONE    DONE       DONE      01/04/10   12/30/09   06/29/09   05/12/09   155,16                   200,000       200,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       04/18/13           
09-1484   Reconstruction               0-001-015  03/10/11     DONE    DONE       DONE      06/04/10   05/27/10   08/26/09   05/12/09   2,4                      140,000       140,000  JOD             0           0           0 James M. Campbell Architects            0      03/09/11                       02/08/12           
10-0923   Reconstruction               0-001-016  06/07/11     DONE    DONE       DONE      03/03/11   02/18/11   06/21/10   06/21/10   16                        75,000        75,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       02/07/13           
10-1167   Reconstruction               0-001-017  06/16/11     DONE    DONE       DONE      04/11/11   04/06/11   03/30/11   05/04/10   9                         15,360        15,360  JOD             0           0           0 Burton Behrendt Smith                   0      04/03/12                         /  /             
11-0206XX Reconstruction               0-001-018  04/17/12               CANCELLED          09/29/11   09/28/11   06/01/11   05/10/11   155                        7,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
11-1047   Reconstruction               0-001-019  04/27/12     DONE    DONE       DONE      03/28/12   03/23/12   01/31/12   05/11/11   8                        250,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
12-0807   Reconstruction               0-001-020  04/29/13     DONE    DONE       DONE      02/12/13   02/01/13   10/04/12   05/11/12   8,9,155,15,16             58,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
12-0880   Reconstruction               0-001-021  11/18/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   2,16                     100,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
12-0881   Reconstruction               0-001-022  05/22/13     DONE    DONE       DONE      02/20/13   02/11/13   02/20/13   05/08/12   2,10,16                   21,000        21,000  MFS             0           0           0 H2M Group                               0      12/03/13                       12/13/13           
13-0932   Reconstruction               0-001-023  04/16/14     DONE    DONE       DONE      12/24/13   12/20/13   11/29/13   05/07/13   8,9,10,155,15,16          75,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1328   Reconstruction               0-001-024                         UNREVIEWED         03/11/14   03/11/14   12/10/13   06/11/13   155                            0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
13-1269   Reconstruction               0-001-025                         UNREVIEWED         02/24/14   02/18/14   12/10/13   06/11/13   16                             0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Wilson Tech Career Center:
10-0217   Reconstruction               0-015-007  01/14/11     DONE    DONE       DONE      09/14/10   09/08/10   06/21/10   06/21/10   2,155,16                 257,000       257,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      02/20/12                       01/28/13           
11-0720   Reconstruction               0-015-008  04/17/12     DONE    DONE       DONE      01/25/12   01/24/12   06/01/11   05/10/11   2,15                     129,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/16/12                       01/29/13           
12-0882   Reconstruction               0-015-009  11/18/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   2,16                     100,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
  -    XX Reconstruction               0-015-010                         CANCELLED            /  /       /  /     11/02/12     /  /     2,10,16                        0     2,562,430  JMB             0           0           0                                         0        /  /                           /  /             
13-1270   Reconstruction               0-015-011                         UNREVIEWED         02/24/14   02/18/14   12/10/13   06/11/13   16                             0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
  -       Reconstruction               0-015-012                                              /  /       /  /     02/11/14     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          JE Allen Jr/Sr High School Mellville:
09-0823   Reconstruction               0-016-018  07/20/10     DONE    DONE       DONE      01/27/10   01/25/10   03/10/09   12/08/09   9,155,15,16              262,000       262,000  JOD             0           0           0 James M. Campbell Architects            0      07/27/11                         /  /             
09-0241   Reconstruction               0-016-019  10/05/09     DONE    DONE       DONE      09/17/09   09/16/09   07/14/09   05/12/09   2,7                    1,075,000     1,075,000  JOD             0           0           0 Burton Behrendt Smith                   0      12/15/10                         /  /             
09-0673   Reconstruction               0-016-020  08/10/10     DONE    DONE       DONE      01/05/10   12/30/09   08/25/09   12/08/09   155,15                   120,000       120,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      02/24/12                       11/19/12           
09-1226   Reconstruction               0-016-021  08/04/10     DONE    DONE       DONE      04/05/10   03/31/10   09/08/09   05/12/09   4,16                      90,500        90,500  JOD             0           0           0 Burton Behrendt Smith                   0      01/06/12                         /  /             
09-1482   Reconstruction               0-016-022  06/24/10     DONE    DONE       DONE      06/03/10   05/27/10   09/08/09   07/07/09   10                        32,000        32,000  JOD             0           0           0 James M. Campbell Architects            0      05/16/11                         /  /             
  -    XX Reconstruction               0-016-023                         CANCELLED            /  /       /  /     11/04/09     /  /     2,8                            0    11,960,256  JOD             0           0           0                                         0        /  /                           /  /             
09-0984   Additions and Alterations    0-016-024  05/25/10     DONE    DONE       DONE      03/02/10   02/25/10   11/20/09   10/28/09   02 - 16                2,858,800     2,858,800  JOD             0           0           0 Burton Behrendt Smith                   0      04/18/11                         /  /             
10-0924   Reconstruction               0-016-025  06/07/11     DONE    DONE       DONE      03/03/11   02/18/11   06/21/10   06/21/10   155,15,16                147,000       147,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       02/07/13           
11-0207   Reconstruction               0-016-026  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/01/11   05/10/11   16                        20,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
11-0386   Reconstruction               0-016-027  03/19/12     DONE    DONE       DONE      11/15/11   11/14/11   06/07/11   05/10/11   16                       170,000       170,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/04/12                       12/20/13           
11-0853   Reconstruction               0-016-028  06/26/12     DONE    DONE       DONE      02/28/12   02/27/12   07/21/11   04/07/11   16                       200,000       200,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/04/13                       11/29/13           
12-0806   Reconstruction               0-016-029  05/15/13     DONE    DONE       DONE      02/11/13   01/08/13   09/26/12   05/10/11   155,16                   700,000             0  MFS             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
12-0808   Reconstruction               0-016-030  04/29/13     DONE    DONE       DONE      02/12/13   02/01/13   10/04/12   05/10/12   8,16                      85,200        85,200  JMB             0           0           0 Burton Behrendt Smith                   0      05/09/14                       06/05/14           
12-0883   Reconstruction               0-016-031  06/25/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   155,15,16                 16,000        16,000  MFS             0           0           0 H2M Group                               0      12/03/13                       12/13/13           
  -       Reconstruction               0-016-032                                              /  /       /  /     12/10/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          JE Allen Elementary-Dix Hills:
09-1483   Reconstruction               0-017-023  06/24/10     DONE    DONE       DONE      06/03/10   05/27/10   08/26/09   07/07/09   10                        32,000        32,000  JOD             0           0           0 James M. Campbell Architects            0      05/16/11                         /  /             
09-0674   Reconstruction               0-017-024  08/10/10     DONE    DONE       DONE      01/05/10   12/30/09   08/25/09   12/08/09   155,15,16                244,847       244,847  JOD             0           0           0 Bladykas Engineering,P.C.               0      02/24/12                         /  /             
10-0925   Reconstruction               0-017-025  06/07/11     DONE    DONE       DONE      03/03/11   02/18/11   06/21/10   06/21/10   10,155,16                259,200       259,200  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       02/07/13           
11-0208   Reconstruction               0-017-026  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/01/11   05/10/11   155,16                    40,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
11-0215   Reconstruction               0-017-027  10/18/11     DONE    DONE       DONE      09/29/11   09/28/11   06/07/11   05/10/11   155,16                   885,000       885,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      07/03/13                       01/10/14           
11-0854   Reconstruction               0-017-028  06/26/12     DONE    DONE       DONE      02/28/11   02/27/11   07/21/11   04/07/11   16                       200,000       200,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/04/13                       11/29/13           
12-0884   Reconstruction               0-017-029  10/02/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   2,8,16                   148,000       148,000  MFS             0           0           0 H2M Group                               0      05/30/14                       06/30/14           
13-0667   Reconstruction               0-017-030  02/19/14     DONE    DONE       DONE      11/04/13   10/31/13   08/30/13     /  /     9,13,15,16                80,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
  -       Reconstruction               0-017-031                                              /  /       /  /     12/10/13     /  /     10,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-017-032                                              /  /       /  /     07/28/14     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Wilson Tech Northport:
12-0885   Reconstruction               0-018-017  08/22/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   16                       117,000       117,000  MFS             0           0           0 H2M Group                               0      02/28/14                       04/30/14           
09-1227   Reconstruction               0-018-018  08/04/10     DONE    DONE       DONE      04/05/10   03/31/10   08/26/09   05/12/09   8                         98,400        98,400  JOD             0           0           0 Burton Behrendt Smith                   0      01/06/12                         /  /             
09-0675   Reconstruction               0-018-019  08/10/10     DONE    DONE       DONE      01/05/10   12/30/09   09/01/09   12/08/09   4,15,16                  118,000       118,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      02/24/12                       11/19/12           
09-1564   Reconstruction               0-018-020  10/21/10     DONE    DONE       DONE      06/22/10   06/14/10   09/11/09   12/08/09   2,155,15,16              606,000       606,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      03/09/12                       12/10/12           
10-0666   Reconstruction               0-018-021  01/26/11     DONE    DONE       DONE      12/30/10   12/23/10   11/04/10   05/11/10   7                        855,000       855,000  JOD             0           0           0 Burton Behrendt Smith                   0      06/15/12                         /  /             
10-0667   Reconstruction               0-018-022  01/26/11     DONE    DONE       DONE      12/30/10   12/23/10   12/03/10   05/11/10   8                        780,000       780,000  JOD             0           0           0 Burton Behrendt Smith                   0      07/25/12                       01/22/13           
10-1168   Reconstruction               0-018-023  06/16/11     DONE    DONE       DONE      04/11/11   04/08/11   03/28/11   05/04/10   8,9,10                    70,000        70,000  JOD             0           0           0 Burton Behrendt Smith                   0      12/30/11                       06/17/13           
11-0288   Reconstruction               0-018-025  12/20/11     DONE    DONE       DONE      10/26/11   10/25/11   06/01/11   05/10/11   16                        85,000        85,000  JOD             0           0           0 Bladykas Engineering,P.C.               0      07/16/12                       01/28/13           
11-0209   Reconstruction               0-018-026  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/01/11   05/10/11   15                        11,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
12-0886   Reconstruction               0-018-027  03/31/14     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   16                       180,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Jones Hall #2:
10-1169   Reconstruction               0-019-006  06/16/11     DONE    DONE       DONE      04/11/11   04/08/11   03/30/11   05/04/10   8                         15,800        15,800  JOD             0           0           0 Burton Behrendt Smith                   0      04/03/12                         /  /             
12-0887   Reconstruction               0-019-007  11/18/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   2,16                     100,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
13-1271   Reconstruction               0-019-008                         UNREVIEWED         02/24/14   02/18/14   12/10/13   06/11/13   16                             0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          McGuire Hall #2:
  -    XX Reconstruction               0-021-007                         CANCELLED            /  /       /  /     11/02/12     /  /     2,16                           0     1,182,660  JMB             0           0           0                                         0        /  /                           /  /             
12-0888   Reconstruction               0-021-009  05/22/13     DONE    DONE       DONE      02/20/13   02/11/13   11/28/12   05/08/12   2,16                      21,000        18,350  MFS             0           0           0 H2M Group                               0      07/02/13                       07/24/13           
09-1485   Reconstruction               0-021-011  03/10/11     DONE    DONE       DONE      06/04/10   05/27/10   08/26/09   05/12/09   9,15,16                  196,000       196,000  JOD             0           0           0 James M. Campbell Architects            0      04/24/12                         /  /             
10-1170   Reconstruction               0-021-012  06/16/11     DONE    DONE       DONE      04/12/11   04/08/11   03/30/11   05/04/10   8                         15,000        15,000  JOD             0           0           0 Burton Behrendt Smith                   0      04/03/12                         /  /             
12-0889   Reconstruction               0-021-013  11/18/13     DONE    DONE       DONE      02/20/13   02/11/13   02/20/13   05/08/12   2,16                     100,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
13-1272   Reconstruction               0-021-014                         UNREVIEWED         02/24/14   02/18/14   12/10/13   06/11/13   16                             0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Jones Hall #1:
10-0926   Reconstruction               0-022-009  06/07/11     DONE    DONE       DONE      03/03/11   02/18/11   06/21/10   06/21/10   155                       10,500        10,500  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       02/07/13           
10-1171   Reconstruction               0-022-010  06/16/11     DONE    DONE       DONE      04/12/11   04/08/11   03/30/11   05/04/10   8                         16,000        16,000  JOD             0           0           0 Burton Behrendt Smith                   0      04/03/12                         /  /             
11-0210   Reconstruction               0-022-011  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/01/11   05/10/11   155,16                   190,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
12-0809   Reconstruction               0-022-012  04/29/13     DONE    DONE       DONE      02/12/13   02/01/13   10/04/12   05/10/12   8                         56,000        56,000  MFS             0           0           0 Burton Behrendt Smith                   0      05/09/14                       06/05/14           
12-0890   Reconstruction               0-022-013  11/18/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   2,16                     100,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
13-1273   Reconstruction               0-022-014                         UNREVIEWED         02/24/14   02/18/14   12/10/13   06/11/13   16                             0       398,760  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Taukomas School(Brennen Sch.):
12-0891   Reconstruction               0-025-015  06/05/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   16                       150,000       150,000  JMB             0           0           0 H2M Group                               0      01/08/14                       03/17/14           
10-0927   Reconstruction               0-025-016  06/07/11     DONE    DONE       DONE      03/03/11   02/18/11   06/21/10   06/21/10   16                        51,500        51,500  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       02/07/13           
10-0879   Reconstruction               0-025-017  05/26/11     DONE    DONE       DONE      02/18/11   02/14/11   11/10/10   10/01/10   4,8,9,155,16             869,950       869,950  JOD             0           0           0 Burton Behrendt Smith                   0      03/30/12                       01/22/13           
10-1172XX Reconstruction               0-025-018  06/16/11               CANCELLED          04/12/11   04/08/11   03/30/11   05/04/10   9,16                      25,000        25,000  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
11-0721   Reconstruction               0-025-019  04/17/12     DONE    DONE       DONE      01/25/12   01/24/12   06/01/11   05/10/11   2,15                     350,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/16/12                       01/29/13           
  -    XX Reconstruction               0-025-020                         CANCELLED            /  /       /  /     07/21/11     /  /     16                             0     7,573,704  JOD             0           0           0                                         0        /  /                           /  /             
13-0931   Reconstruction               0-025-021  04/08/14     DONE    DONE       DONE      12/24/13   12/20/13   08/30/13   05/07/13   2,8                    1,300,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1409   Reconstruction               0-025-022  04/28/14     DONE    DONE       DONE      04/01/14   03/27/14   12/10/13   06/11/13   16                        50,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Manor Plains School:
10-0928   Reconstruction               0-029-018  06/07/11     DONE    DONE       DONE      03/03/11   02/18/11   06/21/10   06/21/10   16                        10,500        10,500  JOD             0           0           0 Bladykas Engineering,P.C.               0      10/15/12                       02/07/13           
10-1173   Reconstruction               0-029-019  06/16/11     DONE    DONE       DONE      04/12/11   04/08/11   03/30/11   05/04/10   9,16                     126,878       126,878  JOD             0           0           0 Burton Behrendt Smith                   0      12/30/11                         /  /             
11-0211   Reconstruction               0-029-020  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/01/11   05/10/11   15                        80,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
11-1048   Reconstruction               0-029-021  04/27/12     DONE    DONE       DONE      03/28/12   03/23/12   01/31/12   05/11/11   8                        500,000       500,000  JOD             0           0           0 Burton Behrendt Smith                   0      05/09/14                       06/05/14           
12-0810   Reconstruction               0-029-022  04/29/13     DONE    DONE       DONE      02/12/13   02/01/13   10/04/12   05/10/12   8                        520,000       520,000  MFS             0           0           0 Burton Behrendt Smith                   0      05/09/14                       06/05/14           
12-0892   Reconstruction               0-029-023  07/23/13     DONE    DONE       DONE      02/20/13   02/11/13   11/02/12   05/08/12   155,15,16                500,000             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             
13-0666   Reconstruction               0-029-024  02/19/14     DONE    DONE       DONE      11/04/13   10/31/13   08/30/13   05/11/11   4,8,9,15,16               89,300             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-0930   Reconstruction               0-029-025  04/08/14     DONE    DONE       DONE      12/24/13   12/20/13   11/29/13   05/07/13   2,9                       85,000             0  MFS             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
13-1517   Reconstruction               0-029-026                         UNREVIEWED         05/14/14   04/30/14   02/11/14   06/11/13   16                             0             0  MFS             0           0           0 H2M Group                               0        /  /                           /  /             

          Aviation Center:
  -    XX Reconstruction               0-052-002                         CANCELLED            /  /       /  /     07/21/11     /  /     16                             0     5,346,432  JOD             0           0           0                                         0        /  /                           /  /             

          Central Office:
09-0275   Reconstruction               1-035-009  11/13/09     DONE    DONE       DONE      10/01/09   09/30/09   06/29/09   06/10/09   2,8,9,155,16             395,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
09-1451   Reconstruction               1-035-010  06/10/10     DONE    DONE       DONE      05/20/10   05/17/10   01/06/10   06/10/08   2,8,9,155,16             237,000             0  JOD             0           0           0 Burton Behrendt Smith                   0      03/07/11                         /  /             
11-0212   Reconstruction               1-035-011  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/01/11   05/10/11   155                       15,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
  -    XX Reconstruction               1-035-012                         CANCELLED            /  /       /  /     07/21/11     /  /     16                             0             0  JOD             0           0           0                                         0        /  /                           /  /             
11-0675   Reconstruction               1-035-013  05/01/12     DONE    DONE       DONE      01/18/12   01/17/12   10/05/11   04/07/10   2,8,9,10,155,15,16       543,000             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             

          Manor Plains Md#3:
09-0983   Reconstruction               2-032-001  06/10/10     DONE    DONE       DONE      03/02/10   02/25/10   10/22/08   07/08/08   2,16                      99,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0      11/08/10                         /  /             

          Storage @ Wilson Tech:
10-0435   New Construction             2-056-001  11/30/10     DONE    DONE       DONE      11/05/10   10/28/10   06/02/10   10/28/09   02 - 16                1,385,500             0  JOD             0           0           0 Burton Behrendt Smith                   0      05/25/11                         /  /             

          Maintenace / Grounds Facilty:
10-0107   New Construction             3-055-001  08/16/10     DONE    DONE       DONE      08/11/10   08/02/10   06/18/10   10/28/09   02 - 16                  146,500             0  JOD             0           0           0 Burton Behrendt Smith                   0      04/18/11                         /  /             
11-0216   Reconstruction               3-055-002  10/18/11     DONE    DONE       DONE      09/29/11   09/28/11   05/27/11   05/10/11   155                       15,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0      07/03/13                       01/10/14           
  -    XX Reconstruction               3-055-003                         CANCELLED            /  /       /  /     07/21/11     /  /     16                             0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Dix Hills:
10-1439PR New Construction             7-060-001                         UNREVIEWED         06/30/11   06/23/11   05/23/11     /  /     02 - 16                        0             0  JOD             0           0           0 Burton Behrendt Smith                   0        /  /                           /  /             
11-0276   New Construction             7-060-001  11/08/11     DONE    DONE       DONE      10/25/11   10/21/11   05/23/11   06/09/09   02 - 16                  950,000             0  JOD             0           0           0 Burton Behrendt Smith                   0      07/25/12                       07/27/12           

          P.J. Brennan - North Babylon:
11-0213   Reconstruction               8-048-009  04/17/12     DONE    DONE       DONE      09/29/11   09/28/11   06/07/11   05/10/11   155,16                    75,000             0  JOD             0           0           0 Bladykas Engineering,P.C.               0        /  /                           /  /             
  -    XX Reconstruction               8-048-010                         CANCELLED            /  /       /  /     07/21/11     /  /     16                             0             0  JOD             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               8-048-011                                              /  /       /  /     12/10/13     /  /     155,16                         0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED