Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 06/17/13 at 15:21:19




FALLSBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-05-01-06
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior-Senior High School:
  -       Reconstruction               0-001-017                                              /  /       /  /     03/24/09     /  /     2,4,7,8,9,10,155,15,           0    18,441,681  DDJ             0           0           0                                         0        /  /             /  /        
10-0097   Reconstruction               0-001-018  03/25/11     DONE    DONE       DONE      08/10/10   07/28/10   08/14/09   07/15/09   2,8,155,15,16          1,430,515     1,394,185  DDJ             0           0      96,310 Tetra Tech Architects And Eni   1,334,205        /  /             /  /        
  -       Reconstruction               0-001-019                                              /  /       /  /     05/18/10     /  /     7,8                            0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Benjamin Cosor Elementary:
  -       Reconstruction               0-007-016                                              /  /       /  /     03/24/09     /  /     2,4,7,8,9,10,155,15,           0    14,252,542  DDJ             0           0           0                                         0        /  /             /  /        
10-0098   Reconstruction               0-007-017  03/25/11     DONE    DONE       DONE      08/10/10   07/28/10   08/14/09   07/15/09   2,8,155,15,16            589,905       578,674  DDJ             0           0      96,310 Tetra Tech Architects And Eni     493,595        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELDRED CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-08-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Eldred School:
  -       Reconstruction               0-001-009                                              /  /       /  /     11/19/12     /  /     2,4,8,9,13,155,15,16           0     3,876,642  JMB             0           0           0                                         0        /  /             /  /        
07-2039   Additions and Alterations    0-001-010  12/10/08     DONE    DONE       DONE      04/30/08   04/21/08   03/24/06   12/12/06   02 - 16               12,975,387    11,526,904  JOD             0           0     249,958 FOIT-ALBERT                             0        /  /             /  /        
07-1869XX Reconstruction               0-001-011  09/19/08               CANCELLED          03/25/08   03/25/08   06/04/07   12/12/06   2,16                      13,370             0  JOD             0           0           0 FOIT-ALBERT                             0        /  /             /  /        
07-2090   Reconstruction               0-001-012  12/09/08     DONE    DONE       DONE      05/07/08   05/06/08   12/17/07   10/08/07   8,155,16                 356,852       356,852  JOD             0           0           0 FOIT-ALBERT                       356,852        /  /           05/31/13      
10-1290   Reconstruction               0-001-013  06/07/11     DONE    DONE       DONE      05/12/11   05/02/11   03/25/10   03/15/11   2,9,15,16                650,000       650,000  JOD             0           0           0 Collins & Scoville Architects           0        /  /           03/15/13      

          Mackenzie Elementary School:
07-2091   Reconstruction               0-009-007  12/09/08     DONE    DONE       DONE      05/07/08   05/06/08   12/17/07   10/08/07   8,155,16                 243,148       243,148  JOD             0           0           0 FOIT-ALBERT                       243,148        /  /           02/28/13      

          Transportation Garage:
07-0855TQ Temporary Quarters           5-016-001  10/09/08     DONE    DONE       DONE      11/20/07   11/16/07   12/29/06     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Athletic Field Pump House:
  -    PR New Construction             7-017-001                                              /  /       /  /     12/10/10     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LIBERTY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-09-01-06
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
08-0189PR Additions and Alterations    0-002-014                         UNREVIEWED         08/19/08   08/11/08   07/23/07     /  /     02 - 16                        0             0  MGL             0           0           0 Ashley McGraw Architects                0        /  /             /  /        
08-0395   Additions and Alterations    0-002-014  06/01/09     DONE    DONE       DONE      09/26/08   09/24/08   07/23/07   11/28/07   02 - 16               19,278,387    13,743,044  MGL             0           0   1,049,067 Ashley McGraw Architects                0        /  /             /  /        

          Jr/Sr High School:
08-0190PR Additions and Alterations    0-009-010                         UNREVIEWED         08/19/08   08/11/08   07/24/07     /  /     02 - 16                        0             0  MGL             0           0           0 Ashley McGraw Architects                0        /  /             /  /        
08-0396   Additions and Alterations    0-009-010  06/01/09     DONE    DONE       DONE      09/26/08   09/24/08   07/24/07   11/28/07   02 - 16               16,578,957    16,578,957  MGL             0           0           0 Ashley McGraw Architects                0        /  /           06/06/13      

          Liberty Public Library:
10-0130   Reconstruction               6-012-001  09/01/10     DONE    DONE       DONE      08/20/10   08/17/10   07/08/10   04/13/10   8                        201,271             0  HCM             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TRI - VALLEY CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-12-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building (High School):
07-2032XX Reconstruction               0-001-022  06/25/08               CANCELLED          04/25/08   04/16/08   12/19/07   05/20/07   155                    2,146,000     2,146,000  MGL             0           0     392,000 Smith Miller Associates                 0        /  /             /  /        
09-0616   Reconstruction               0-001-023  04/19/10     DONE    DONE       DONE      12/23/09   12/23/09   12/19/07   05/20/09   2,7,8,9,155,15,16      2,146,000     2,146,000  MGL             0           0     391,281                                         0        /  /             /  /        
08-0104   Reconstruction               0-001-024  09/04/08     DONE    DONE       DONE      07/31/08   07/29/08   07/16/08   06/19/08   7                        205,500       205,500  JOD             0           0           0 Bertsche Engineering,Inc                0        /  /           12/26/12      
11-1060   Reconstruction               0-001-025  04/06/12     DONE    DONE       DONE      04/03/12   03/26/12   03/14/12   05/15/11   7                        350,000       350,000  JOD             0           0           0                                         0        /  /           01/28/13      

          Elementary School:
09-1018   Reconstruction               0-002-011  04/19/10     DONE    DONE       DONE      03/08/10   03/04/10   05/27/09   01/19/10   7                        700,000       700,000  JOD             0           0           0                                         0        /  /           12/26/12      

          Athletic Storage:
11-1409DB Discovered Building          2-016-001  09/24/12     DONE    DONE       DONE      06/15/12   06/07/12   04/19/12     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROSCOE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-13-01-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Roscoe School:
08-0949   Reconstruction               0-001-009  02/11/09     DONE    DONE       DONE      12/18/08   12/16/08   06/20/08   05/20/08   2,155,15,16            1,200,000     1,200,000  HCM             0           0      89,408 Ashley McGraw Architects                0        /  /             /  /        
09-0649   Reconstruction               0-001-010  02/12/10     DONE    DONE       DONE      12/30/09   12/22/09   06/23/09   05/19/09   4,7,8,10,13            1,150,000     1,150,000  HCM             0           0           0 Ashley McGraw Architects                0        /  /             /  /        
  -       Reconstruction               0-001-011                                              /  /       /  /     03/20/12     /  /     2,4,9,155,15,16                0    12,677,009  HCM             0           0           0                                         0        /  /             /  /        
12-0551   Reconstruction               0-001-012  05/17/13     DONE    DONE       DONE      12/13/12   12/03/12   10/16/12   09/27/12   2,4,7,8,9,10,155,15,   3,756,000     3,756,000  JMB             0           0           0 SEI Design Group                        0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LIVINGSTON MANOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-13-02-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Livingston Manor Central:
09-1431   Reconstruction               0-001-021  06/04/10     DONE    DONE       DONE      05/13/10   05/10/10   10/15/09   12/08/09   2,4,7,9,10,14            798,308       798,308  HCM             0           0           0                                         0        /  /             /  /        
09-1532   Reconstruction               0-001-022  10/14/10     DONE    DONE       DONE      06/15/10   06/07/10   05/21/10   12/08/09   2,4,7,8,9,13,14,155,   1,021,692     1,021,692  HCM             0           0           0                                         0        /  /           02/28/13      
12-1124   Reconstruction               0-001-023  06/06/13     DONE    DONE       DONE      04/23/13   04/22/13   01/22/13   12/08/09   2,7,8,9                  285,000             0  JMB             0           0           0 BCK-IBI Group, a New York Gen           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MONTICELLO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-14-01-06
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Emma C Chase School:
07-1887   Reconstruction               0-001-012  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   155,15,16                267,855       267,855  DDJ             0           0           0                                   267,855        /  /           09/17/12      

          Cornelius Duggan School:
07-1888   Reconstruction               0-004-013  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   9,155,16                 194,437       194,437  DDJ             0           0           0                                   194,437        /  /           09/17/12      

          George L Cooke School:
07-1889   Reconstruction               0-005-011  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   8,155,16                 925,698       925,698                  0           0           0                                   925,698        /  /           09/17/12      

          Kenneth Rutherford School:
07-1890   Reconstruction               0-006-010  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   8,155,15,16            1,044,360     1,044,360  DDJ             0           0           0                                 1,044,360        /  /           09/17/12      

          Middle/High School:
07-1891   Reconstruction               0-007-012  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   155,16                 1,578,861     1,578,861  MGL             0           0           0                                 1,578,861        /  /           09/17/12      
07-1405   Reconstruction               0-007-013  06/25/08     DONE    DONE       DONE      01/17/08   01/16/08   10/17/07   04/09/03   4,8,9,155,15,16          649,763       649,763  MGL             0           0           0                                         0        /  /           10/22/12      
12-1072   Reconstruction               0-007-014  06/06/13     DONE    DONE       DONE      04/05/13   04/02/13   01/15/13   01/10/13   2,4,13,16                440,922       440,922  MFS             0           0     115,922 Savin Engineers, P.C.                   0        /  /             /  /        

          Administration Bldg:
07-1892   Reconstruction               1-002-002  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   155,16                    76,679             0  MGL             0           0           0                                    76,679        /  /           09/17/12      

          Bus Garage:
07-1893   Reconstruction               5-010-008  04/16/10     DONE    DONE       DONE      03/31/08   03/21/08   07/16/07   09/07/07   155,16                    65,900        65,900  MGL             0           0           0                                    65,900        /  /           09/17/12      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SULLIVAN WEST CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-15-02-04
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sullivan West Elementary:
11-0819   Reconstruction               0-001-003  04/09/13     DONE    DONE       DONE      04/09/13   04/04/13   01/08/08   05/19/09   7                      1,547,169     1,600,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-001-010                                              /  /       /  /     02/02/10     /  /     7,155,16                       0             0  HCM             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-011                                              /  /       /  /     02/16/10     /  /     7,13,155,16                    0             0  HCM             0           0           0                                         0        /  /             /  /        

          New High School:
10-1059   Reconstruction               0-026-003  06/03/11     DONE    DONE       DONE      03/17/11   03/14/11   12/27/07   05/19/10   2,10,155,15            1,317,357     1,317,357  HCM             0           0           0 Bertsche Engineering                    0        /  /             /  /        
  -       Reconstruction               0-026-004                                              /  /       /  /     04/23/13     /  /     10,16                          0             0  JOB             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-026-005                                              /  /       /  /     03/25/11     /  /     2,16                           0             0  HCM             0           0           0                                         0        /  /             /  /        

          Mfd. Storage @ High School:
10-0410   New Construction             2-028-001  05/24/11     DONE    DONE       DONE      11/02/10   10/21/10   12/27/07   05/17/11   02 - 16                  190,000             0  HCM             0           0           0 Bertsche Engineering,Inc                0        /  /             /  /        

          Storage-Main Bldg.:
10-0403   New Construction             2-030-001  05/24/11     DONE    DONE       DONE      11/01/10   10/20/10   04/14/08   05/17/11   02 - 16                  190,000             0  HCM             0           0           0 Bertsche Engineering,Inc                0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES SULLIVAN COUNTY STATUS REPORT ON CAPITAL PROJECTS
District No.: 59-90-00-00
last updated on 06/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Rubin Pollack Ed. Ctr.:
10-1226   Reconstruction               0-013-014  06/23/11     DONE    DONE       DONE      04/27/11   04/25/11   04/15/11   04/19/11   7                         61,500        42,000  JOD             0           0           0                                         0        /  /             /  /        
11-0948   Reconstruction               0-013-015  04/06/12     DONE    DONE       DONE      03/14/12   03/12/12   02/17/12     /  /     7                        645,000             0  JOD             0           0           0                                         0        /  /             /  /        

          Boces Center Annex:
10-1227   Reconstruction               0-015-003  06/23/11     DONE    DONE       DONE      04/27/11   04/25/11   04/15/11   04/19/11   7                         65,700        48,000  JOD             0           0           0                                         0        /  /             /  /        

          Youngsville Elementary:
08-1028   Reconstruction               0-030-003  01/13/09     DONE    DONE       DONE      01/05/09   01/02/09   10/27/08   12/16/08   10                       105,876       105,876  JOD             0           0           0                                         0        /  /             /  /        
09-1438   Reconstruction               0-030-004  06/10/10     DONE    DONE       DONE      05/13/10   05/10/10   04/08/10   04/20/10   7                        148,000       148,000  JOD             0           0           0                                         0        /  /             /  /        
10-1398   Reconstruction               0-030-005  07/12/11     DONE    DONE       DONE      06/17/11   06/13/11   04/15/11   04/19/11   2,9,13                   210,000             0  JOD             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED