Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/19/24 at 06:55:14




WAVERLY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-01-01-06
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elm Street Elementary School:
18-1756   Reconstruction               0-001-016  04/30/19     DONE    DONE       DONE      03/29/19   03/18/19   05/30/18   05/15/18   2,4,7,8,9,155,15,16      640,000       640,000  BMJ             0           0           0 IBI GROUP                               0        /  /                         03/18/19           
  -    PR Additions and Alterations    0-001-017                                              /  /       /  /     12/16/19     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
23-0331   Reconstruction               0-001-018  04/17/24     DONE    DONE       DONE      08/28/23   08/25/23   05/24/23   05/17/22   2,7,9,155,16           1,426,193     1,426,193  JLB             0           0           0 Tetra Tech Architects and Eng   1,426,193        /  /                         08/25/23           

          Lincoln St School:
18-1757   Reconstruction               0-016-012  04/30/19     DONE    DONE       DONE      03/29/19   03/18/19   05/25/18   05/15/18   2,4,8,9,155,16           168,734       168,734  BMJ             0           0           0 IBI GROUP                               0      12/31/20                       03/18/19           
22-1184   Reconstruction               0-016-013  05/01/23     DONE    DONE       DONE      12/07/22   12/07/22   06/29/22   05/17/22   2,4,7,8,9,10,155,15,   3,421,660     3,421,660  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         12/07/22           
23-0332   Reconstruction               0-016-014  04/17/24     DONE    DONE       DONE      08/28/23   08/25/23   05/24/23   05/17/22   2,7,9,155,15,16          419,539       419,539  JLB             0           0           0 Tetra Tech Architects and Eng     419,539        /  /                         08/25/23           

          Waverly Jr/Sr High School:
18-1758   Reconstruction               0-018-020  04/30/19     DONE    DONE       DONE      03/29/19   03/18/19   05/30/18   05/15/18   2,4,7,8,9,10,155,15,     794,117       794,117  BMJ             0           0           0 IBI GROUP                               0      12/31/20                       03/18/19           
21-1905   Reconstruction               0-018-021  07/21/22     DONE    DONE       DONE      06/01/22   05/27/22   05/10/22   05/17/22   155,15                   100,000       100,000  JLB             0           0           0 Tetra Tech Architects and Eng           0      05/11/23                       05/27/22           
22-0976   Reconstruction               0-018-022  03/23/23     DONE    DONE       DONE      11/14/22   11/14/22   06/29/22   05/17/22   2,4,9,16               6,474,089     6,474,089  JJH             0           0           0 Tetra Tech Architects & Engin           0        /  /                         11/14/22           
  -    PR Additions and Alterations    0-018-023                                              /  /       /  /     06/29/22     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-2266   Reconstruction               0-018-023  10/19/23     DONE    DONE       DONE      05/22/23   05/22/23   06/29/22   05/17/22   2,4,7,8,9,155,15,16   30,232,808    30,232,808  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/22/23           
22-1876   Reconstruction               0-018-024  07/31/23     DONE    DONE       DONE      03/20/23   03/15/23   12/22/22   05/16/23   13,15,16                 100,000       100,000  JJH             0           0           0 Tetra Tech Architects and Eng           0        /  /                         03/15/23           
23-0333   Reconstruction               0-018-025  04/17/24     DONE    DONE       DONE      08/28/23   08/25/23   05/24/23   05/17/22   2,7,9,155,16           1,106,203     1,106,203  JLB             0           0           0 Tetra Tech Architects and Eng   1,106,203        /  /                         08/25/23           

          Bus Garage:
23-0334   Reconstruction               5-002-008  04/17/24     DONE    DONE       DONE      08/28/23   08/25/23   05/24/23   05/17/22   7,9,155,16               154,424       154,424  JLB             0           0           0 Tetra Tech Architects and Eng     154,424        /  /                         08/25/23           

          Districtwide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CANDOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-03-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School Academy:
19-1174   Reconstruction               0-001-012  01/24/20     DONE    DONE       DONE      01/07/20   12/17/19   12/20/19   05/21/19   8                        100,000       100,000  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/05/22                       12/17/19           
22-0403   Reconstruction               0-001-013  10/17/22     DONE    DONE       DONE      09/02/22   09/02/22   05/24/22   05/17/22   2,10                     100,000       100,000  JLB             0           0           0 King & King Architects                  0      06/30/23                       09/02/22           
23-0659   Reconstruction               0-001-014               UNREVIEWED
                                                                       ADD. REQ'D DONE      10/10/23   10/05/23   05/24/23   03/21/23   2,7,8,9,155,15,16              0             0  JJH             0           0           0 King & King Architects                  0        /  /                         10/05/23           

          Elementary Academy:
23-0660   Reconstruction               0-003-009               UNREVIEWED
                                                                       ADD. REQ'D DONE      10/10/23   10/05/23   05/24/23   03/21/23   7,9,15,16                      0             0  JJH             0           0           0 King & King Architects                  0        /  /                         10/05/23           
23-1331   Reconstruction               0-003-010  03/12/24     DONE    DONE       DONE      01/11/24   01/08/23   06/23/23   05/16/23   2,155,15                 100,000       100,000  JJH             0           0           0 King & King Architects                  0        /  /                         01/08/23           

          Bus Garage:
23-0661   Reconstruction               5-013-003               UNREVIEWED
                                                                       ADD. REQ'D DONE      10/10/23   10/05/23   05/24/23   03/21/23   2,16                           0             0  JJH             0           0           0 King & King Architects                  0        /  /                         10/05/23           

          District Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JJH             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWARK VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-04-02-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nathan T. Hall Elementary:
  -    XX Reconstruction               0-002-016                         CANCELLED            /  /       /  /     11/03/20     /  /     16                             0             0  JSS             0           0           0                                         0        /  /                           /  /             
21-1648FA Reconstruction               0-002-017  04/26/22     DONE    DONE       DONE      04/11/22   04/07/22   02/14/22   10/12/21   4,8,9,10                 100,000       100,000  WLC             0           0           0 Keystone Assoc Architects, En           0      01/10/23                       04/07/22           
22-1693   Reconstruction               0-002-018  06/06/23     DONE    DONE       DONE      02/15/23   02/15/23   02/03/23   12/14/22   2,4,7,9,155,15,16      2,137,000     2,137,000  WLC             0           0           0 Keystone Assoc Architects, En           0        /  /                         02/15/23           
23-0760   Reconstruction               0-002-019               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/20/23   10/13/23   04/28/23   12/14/22   2,4,7,8,9,14,155,15,           0             0  WLC             0           0           0 Keystone Assoc Architects, En           0        /  /                         10/13/23           

          Middle School:
19-1082   Reconstruction               0-003-019  01/21/20     DONE    DONE       DONE      12/30/19   12/19/19   11/08/19   05/21/19   8,9,10                   100,000       100,000  BMJ             0           0           0 Keystone Assoc Architects, En           0      06/18/20                       12/19/19           
20-1077   Reconstruction               0-003-020  02/02/21     DONE    DONE       DONE      12/31/20   12/22/20   11/03/20   06/09/20   16                       100,000       100,000  JSS             0           0           0 Keystone Assoc Architects, En           0      05/28/21                       12/22/20           
23-0761   Reconstruction               0-003-021               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/20/23   10/13/23   04/28/23   12/14/22   2,4,7,8,9,14,155,15,           0             0  WLC             0           0           0 Keystone Assoc Architects, En           0        /  /                         10/13/23           

          High School:
21-0955FA Reconstruction               0-007-021  01/18/22     DONE    DONE       DONE      12/27/21   11/03/21   08/12/21   10/12/21   4,8,9                    100,000       100,000  JLB             0           0           0 Keystone Assoc Architects, En           0      08/22/22                       11/03/21           
23-0762   Reconstruction               0-007-022               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/20/23   10/13/23   04/10/23   12/14/22   2,4,7,8,9,10,14,155,           0             0  WLC             0           0           0 Keystone Assoc Architects, En           0        /  /                         10/13/23           

          Bus Garage:
23-0763   Reconstruction               5-004-010               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/20/23   10/13/23   04/10/23   12/14/22   2,4,7,155,15,16                0             0  WLC             0           0           0 Keystone Assoc Architects, En           0        /  /                         10/13/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OWEGO APALACHIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-06-01-06
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Apalachin Elementary School:
19-1104   Reconstruction               0-008-013  06/11/20     DONE    DONE       DONE      01/02/20   12/20/19   04/01/19   01/22/19   2,4,7,8,9,10,155,15,  12,131,968    10,244,637  SLC             0           0           0 Highland Associates                     0      09/30/22                       12/20/19           
  -    XX Reconstruction               0-008-014                         CANCELLED            /  /       /  /     09/04/19     /  /     8,16                           0    13,769,352  SLC             0           0           0                                         0        /  /                           /  /             
19-1613   Reconstruction               0-008-015  06/22/20     DONE    DONE       DONE      03/20/20   03/20/20   01/09/20   06/18/19   7                        100,000       100,000  SLC             0           0           0 Highland Associates                     0      08/06/21                       03/20/20           
19-1612   Reconstruction               0-008-016  06/22/20     DONE    DONE       DONE      03/20/20   03/20/20   01/09/20   06/09/20   7                        100,000       100,000  SLC             0           0           0 Highland Associates                     0      08/06/21                       03/20/20           
21-1532FA Reconstruction               0-008-017  04/04/22     DONE    DONE       DONE      03/18/22   03/16/22   12/06/21   12/20/21   7,155,16               1,974,991             0  SLC             0           0           0 Highland Associates                     0        /  /                         03/16/22           
  -       Reconstruction               0-008-BA1               DONE                           /  /       /  /     09/04/19     /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Owego Free Academy (incl Middle Sch):
18-1211XX Additions and Alterations    0-009-024  05/21/19               CANCELLED          01/10/19   11/30/18   08/09/18   10/18/18   02 - 16                  350,000             0  SLC             0           0           0 Ashley McGraw                           0        /  /                         11/30/18           
19-1105   Reconstruction               0-009-025  06/11/20     DONE    DONE       DONE      01/02/20   12/20/19   04/01/19   01/22/19   2,4,8,9,10,155,15,16   1,231,062     1,131,062  SLC             0           0           0 Highland Associates                     0      12/10/20                       12/20/19           
19-1106   Reconstruction               0-009-026  06/11/20     DONE    DONE       DONE      01/02/20   12/20/19   04/01/19   01/22/19   2,4,7,8,9,10,155,15,  11,112,754    11,112,754  SLC             0           0           0 Highland Associates                     0      10/01/21                       12/20/19           
  -    XX Reconstruction               0-009-027                         CANCELLED            /  /       /  /     09/04/19     /  /     8,16                           0    56,476,880  SLC             0           0           0                                         0        /  /                           /  /             
21-1577   Reconstruction               0-009-028  05/13/22     DONE    DONE       DONE      03/30/22   03/28/22   12/15/21   05/18/21   9,10,16                  100,000       100,000  SLC             0           0           0 Highland Associates                     0      08/24/23                       03/28/22           
22-0234   Reconstruction               0-009-029  12/16/22     DONE    DONE       DONE      08/05/22   08/03/22   03/28/22   05/17/22   2,9,16                 1,233,400     1,233,400  SLC             0           0           0 Highland Associates                     0      09/12/23                       08/03/22           
23-1643   Reconstruction               0-009-030                         UNREVIEWED         03/18/24   03/18/24   03/28/22   05/17/22   2,4,7,8,9,10,155,15,           0             0  MSK             0           0           0 Highland Associates                     0        /  /                         03/18/24           
22-2018   Reconstruction               0-009-031  06/29/23     DONE    DONE       DONE      04/12/23   04/07/23   03/22/23   05/17/22   9                        100,000       100,000  MSK             0           0           0 Highland Associates                     0        /  /                         04/07/23           
  -    SB Reconstruction               0-009-BA1               DONE                           /  /       /  /     09/04/19     /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          New Owego Elementary (2015):
  -    XX Reconstruction               0-014-002                         CANCELLED            /  /       /  /     09/04/19     /  /     8,16                           0    20,108,637  SLC             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               0-014-BA1               DONE                           /  /       /  /     09/04/19     /  /     8,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Existing Pavilion @Apalachin Elem.:
  -    DB Discovered Building          0-017-001                                              /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          2004 Bus Maintenance Bldg.:
22-0235   Reconstruction               5-011-003  12/16/22     DONE    DONE       DONE      08/05/22   08/03/22   05/02/22   05/17/22   2,9,155,16             1,539,800     1,539,800  SLC             0           0           0 Highland Associates                     0      06/15/23           YES         08/03/22           

          Agriculture Building:
  -    PR New Construction             7-024-001                                              /  /       /  /     12/08/23     /  /     02 - 16                        0             0  MSK             0           0           0                                         0        /  /                           /  /             
23-1590   New Construction             7-024-001                         UNREVIEWED         03/05/24   03/05/24   12/08/23   10/18/18   02 - 16                        0             0  MSK             0           0           0 Highland Associates                     0        /  /                         03/05/24           

          XXTemp.Tent#1 @ Owego ES -Canceled:
  -    XX Reconstruction               8-018-001                         CANCELLED            /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTemp Tent#2 @ Owego ES - canceled:
  -    XX Reconstruction               8-019-001                         CANCELLED            /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTemp Tent#1 @ Owego Free Acad-Canc:
  -    XX Reconstruction               8-020-001                         CANCELLED            /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTemp Tent#2 @ Owego Free Acad-Canc:
  -    XX Reconstruction               8-021-001                         CANCELLED            /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTemp.Tent#1 @Apalachin ES -Cancell:
  -    XX Reconstruction               8-022-001                         CANCELLED            /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXTemp.Tent#2 @ Apalachin ES - Cance:
  -    XX Reconstruction               8-023-001                         CANCELLED            /  /       /  /     08/25/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SPENCER VAN ETTEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-08-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Spencer Middle School:
  -    SB Reconstruction               0-001-016                         UNREVIEWED         09/22/21   09/22/21   11/06/20   03/16/21   2,4,8,9,10,155,15,16   4,305,873     4,305,873  SLC             0           0           0 LaBella Associates P.C.                 0        /  /                         09/22/21           
21-0399   Reconstruction               0-001-016  01/19/22     DONE    DONE       DONE      09/22/21   09/22/21   11/06/20   03/16/21   2,4,8,9,10,155,15,16   2,944,444     2,944,444  SLC             0           0           0 LaBella Associates P.C.                 0      01/02/23                       09/22/21           
  -    SB Reconstruction               0-001-017                         UNREVIEWED         02/17/23   02/17/23   01/18/23   11/04/14   8,16                     203,146       203,146  JLB             0           0           0 LaBella Associates, P.C.                0        /  /                         02/17/23           
22-1712SB Reconstruction               0-001-017  05/03/23     DONE    DONE       DONE      02/21/23   02/17/23   01/18/23   11/04/14   8,16                     203,146       203,146  JLB             0           0           0 LaBella Associates, P.C.                0        /  /                         02/17/23           
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /     8                              0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Van Etten Elementary:
  -    SB Reconstruction               0-006-014                         UNREVIEWED         09/22/21   09/22/21   11/06/20   03/16/21   2,4,7,8,9,10,155,15,   3,559,775     3,559,775  SLC             0           0           0 LaBella Associates P.C.                 0        /  /                         09/22/21           
21-0400   Reconstruction               0-006-014  01/19/22     DONE    DONE       DONE      09/22/21   09/22/21   11/06/20   03/16/21   2,4,7,8,9,10,155,15,   3,029,574     3,029,574  SLC             0           0           0 LaBella Associates P.C.                 0      01/02/23                       09/22/21           
  -    SB Reconstruction               0-006-015                         UNREVIEWED         02/17/23   02/17/23   01/18/23   11/04/14   8,16                     159,443       159,443  JLB             0           0           0 LaBella Associates, P.C.                0        /  /                         02/17/23           
22-1713SB Reconstruction               0-006-015  05/03/23     DONE    DONE       DONE      02/21/23   02/17/23   01/18/23   11/04/14   8,16                     159,443       159,443  JLB             0           0           0 LaBella Associates, P.C.                0        /  /                         02/17/23           
  -    SB Reconstruction               0-006-BA1               DONE                           /  /       /  /       /  /       /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Senior High School:
  -    SB Reconstruction               0-010-016                         UNREVIEWED         09/22/21   09/22/21   11/06/20   03/16/21   2,4,7,8,9,10,155,15,   6,649,668     6,649,668  SLC             0           0           0 LaBella Associates P.C.                 0        /  /                         09/22/21           
21-0401   Reconstruction               0-010-016  01/19/22     DONE    DONE       DONE      09/22/21   09/22/21   11/06/20   03/16/21   2,4,7,8,9,10,155,15,   7,408,788     7,408,788  SLC             0           0           0 LaBella Associates P.C.                 0      01/02/23                       09/22/21           
  -    SB Reconstruction               0-010-017                         UNREVIEWED         02/17/23   02/17/23   01/18/23   11/04/14   8,16                     309,158       309,158  JLB             0           0           0 LaBella Associates, P.C.                0        /  /                         02/17/23           
22-1714SB Reconstruction               0-010-017  05/03/23     DONE    DONE       DONE      02/21/23   02/17/23   01/18/23   11/04/14   8,16                     309,158       309,158  JLB             0           0           0 LaBella Associates, P.C.                0        /  /                         02/17/23           
  -    SB Reconstruction               0-010-BA1               DONE                           /  /       /  /       /  /       /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Bus Storage Maintenance:
  -    SB Reconstruction               5-002-009                         UNREVIEWED         09/22/21   09/22/21   11/06/20   03/16/21   2,4,7,8,9,10,155,15,   1,254,683     1,254,683  SLC             0           0           0 LaBella Associates P.C.                 0        /  /                         09/22/21           
21-0402   Reconstruction               5-002-009  01/19/22     DONE    DONE       DONE      09/22/21   09/22/21   11/06/20   03/16/21   2,4,7,8,9,10,155,15,   1,057,305     1,057,305  SLC             0           0           0 LaBella Associates P.C.                 0      01/02/23                       09/22/21           

          District-Wide:
  -       Reconstruction               7-999-002                                              /  /       /  /     09/02/21     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             
21-0270SB Reconstruction               7-999-002               DONE                           /  /       /  /     09/02/21     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TIOGA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-09-03-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Bldg.(Fmly SHS/MS/Elem):
19-1439   Reconstruction               0-007-018  04/01/20     DONE    DONE       DONE      02/20/20   02/14/20   12/23/19   02/28/17   2,4,7,9,155,15,16      1,348,708     1,348,708  JSS             0           0           0 King & King Architects                  0      09/15/21                       02/14/20           
20-0460   Reconstruction               0-007-019  01/15/21     DONE    DONE       DONE      09/28/20   09/22/20   08/28/20   06/09/20   16                       100,000       100,000  JSS             0           0           0 King & King Architects                  0      06/01/21                       09/22/20           
20-1866   Reconstruction               0-007-020  07/13/21     DONE    DONE       DONE      06/11/21   06/10/21   04/28/21   05/18/21   16                       100,000       100,000  JLB             0           0           0 King & King Architects                  0      02/24/22                       06/10/21           
21-0984FC Reconstruction               0-007-021  01/05/22     DONE    DONE       DONE      12/28/21   12/23/21   08/02/21   10/06/21   155                      600,000       600,000  JLB             0           0           0 King & King Architects                  0      08/20/22                       12/23/21           
21-0842   Reconstruction               0-007-022  02/24/22     DONE    DONE       DONE      12/06/21   12/02/21   11/03/21   11/02/21   2,7,155,15,16          1,560,000     1,560,000  JLB             0           0           0 King & King Architects                  0      09/13/22                       12/02/21           
21-1735FA Reconstruction               0-007-023  05/31/22     DONE    DONE       DONE      05/02/22   04/27/22   02/22/22   10/06/21   155,16                   964,559       964,559  JLB             0           0           0 King & King Architects                  0      04/14/23                       04/27/22           
22-0603   Reconstruction               0-007-024  03/30/22     DONE    DONE       DONE      09/28/22   09/28/22   03/02/22   03/02/22   7                        460,000       460,000  JLB             0           0           0 King & King Architects                  0      08/12/22                       09/28/22           
21-1963   Reconstruction               0-007-025  07/22/22     DONE    DONE       DONE      06/10/22   06/10/22   05/25/22   05/17/22   16                       100,000       100,000  JLB             0           0           0 King & King Architects                  0      12/30/22                       06/10/22           
22-1487   Reconstruction               0-007-026  04/26/23     DONE    DONE       DONE      01/13/23   01/12/23   06/14/22   11/02/21   2,4,7,8,9,10,155,15,  15,264,000    15,264,000  JJH             0           0           0 King & King Architects                  0        /  /                         01/12/23           
22-1521   Reconstruction               0-007-027  06/01/23     DONE    DONE       DONE      01/20/23   01/19/23   12/15/22   12/14/22   2,155,16               4,500,000     4,500,000  JJH             0           0           0 King & King Architects                  0      09/25/23                       01/19/23           
23-0538   Reconstruction               0-007-028  11/27/23     DONE    DONE       DONE      09/22/23   09/20/23   05/26/23   05/16/23   16                       100,000       100,000  JJH             0           0           0 King & King Architects                  0        /  /                         09/20/23           
23-1700   Reconstruction               0-007-029                         UNREVIEWED         03/28/24   03/28/24   03/15/24   12/14/22   16                             0             0  JJH             0           0           0 King & King Architects                  0        /  /                         03/28/24           

          Sewage Treatment Plant (prev 7-022):
22-1488   Reconstruction               0-022-001  04/26/23     DONE    DONE       DONE      01/13/23   01/12/23   06/14/22   11/02/21   15,16                    768,575             0  JJH             0           0           0 King & King Architects                  0        /  /                         01/12/23           

          New Bus Garage:
22-1489   Reconstruction               5-026-004  04/26/23     DONE    DONE       DONE      01/13/23   01/12/23   06/14/22   11/02/21   2,16                   1,015,000     1,015,000  JJH             0           0           0 King & King Architects                  0        /  /                         01/12/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED