Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/17/13 at 12:35:09




WAVERLY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-01-01-06
last updated on 05/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elm Street School:
08-1229   Reconstruction               0-001-007  03/26/09     DONE    DONE       DONE      02/19/09   02/13/09   10/07/08   10/28/08   2,4,7,8,9,10,14,155,     361,854       361,854  HCM             0           0     361,854                                         0        /  /             /  /        
09-0183   Reconstruction               0-001-008  02/16/10     DONE    DONE       DONE      09/02/09   08/31/09   10/20/08   10/28/08   2,4,7,8,9,10,14,155,   3,969,001     3,641,984  HCM             0           0           0                                         0        /  /             /  /        
11-0873   Reconstruction               0-001-009  07/06/12     DONE    DONE       DONE      03/06/12   03/02/12   08/19/11   10/28/08   2,4,7,8,9,10,155,15,   1,703,000     1,703,000  HCM             0           0           0                                         0        /  /             /  /        
11-1234   Reconstruction               0-001-010  05/16/12     DONE    DONE       DONE      04/26/12   04/25/12   04/20/12   10/28/08   155,15,16                392,000       392,000  HCM             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-011                                              /  /       /  /     08/30/12     /  /     2,4,8,9,10,13,155,15           0     7,177,366  JMB             0           0           0                                         0        /  /             /  /        

          Chemung #3 Elementary:
08-1230   Reconstruction               0-009-006  03/26/09     DONE    DONE       DONE      02/19/09   02/13/09   10/20/08   10/28/08   2,4,7,8,9,10,155,15,     253,485       253,485  HCM             0           0     253,485                                         0        /  /             /  /        
09-0184   Reconstruction               0-009-007  02/16/10     DONE    DONE       DONE      09/02/09   08/31/09   02/12/09   10/28/08   2,4,7,8,9,10,155,15,   1,812,270     1,447,338  HCM             0           0           0                                         0        /  /             /  /        
11-0874   Reconstruction               0-009-008  07/06/12     DONE    DONE       DONE      03/06/12   03/02/12   08/19/11   10/28/08   2,4,7,8,9,10,155,15,     518,000             0  HCM             0           0           0                                         0        /  /             /  /        

          Lincoln St School:
08-1231   Reconstruction               0-016-006  03/26/09     DONE    DONE       DONE      02/19/09   02/13/09   10/07/08   10/28/08   2,4,7,8,9,10,155,15,     585,951       585,951  HCM             0           0     585,951                                         0        /  /             /  /        
09-0185   Reconstruction               0-016-007  02/16/10     DONE    DONE       DONE      09/02/09   08/31/09   10/20/08   10/28/08   2,4,7,8,9,10,155,15,   2,913,458     2,351,330  HCM             0           0           0                                         0        /  /             /  /        
11-0875   Reconstruction               0-016-008  07/06/12     DONE    DONE       DONE      03/06/12   03/02/12   08/19/11   10/28/08   2,4,7,8,9,10,155,15,   1,300,000             0  HCM             0           0           0                                         0        /  /             /  /        

          Waverly Jr/Sr High School:
09-0295   Reconstruction               0-018-011  02/12/10     DONE    DONE       DONE      10/06/09   10/06/09   10/07/08   10/28/08   2,4,7,8,9,10,155,15,  15,430,040    15,430,040  HCM             0           0     175,381                                         0        /  /             /  /        
11-0876   Reconstruction               0-018-012  07/06/12     DONE    DONE       DONE      03/06/12   03/02/12   10/20/08   10/28/08   2,4,7,8,9,10,155,15,   6,800,000     6,800,000  HCM             0           0           0                                         0        /  /             /  /        
12-0306   Reconstruction               0-018-013  05/08/13     DONE    DONE       DONE      10/24/12   10/23/12   10/18/12   03/28/08   2,9,13,16              4,008,000             0  JMB             0           0           0                                         0        /  /             /  /        

          Metal Storage Building #1:
09-1096   Reconstruction               2-004-002  04/22/10     DONE    DONE       DONE      03/18/10   02/16/10   02/16/10   11/28/08   2,13                      12,500             0  HCM             0           0           0                                         0        /  /             /  /        

          Bus Garage:
08-1519   Reconstruction               5-002-004  12/02/09     DONE    DONE       DONE      04/16/09   04/16/09   10/20/08   10/28/08   2,7,8,9,10,155,15,16   1,502,755     1,502,755  HCM             0           0           0                                         0        /  /           11/21/11      
11-0877   Reconstruction               5-002-005  07/06/12     DONE    DONE       DONE      03/06/12   03/02/12   08/19/11   10/28/08   2,4,7,8,9,10,155,15,     855,000       855,000  HCM             0           0           0                                         0        /  /             /  /        

          Concession Stand - Elm St Elem:
12-0415DB Discovered Building          7-022-001  11/27/12     DONE    DONE       DONE      11/14/12   10/19/12   08/29/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /             /  /        
12-0307   Reconstruction               7-022-002  04/22/13     DONE    DONE       DONE      10/24/12   10/23/12   10/24/12   10/28/08   4,7,8,9,10,155,15,16      30,000             0  JMB             0           0           0                                         0        /  /             /  /        

          Press Box:
12-0308   New Construction             7-023-001  04/22/13     DONE    DONE       DONE      10/24/12   10/23/12   08/30/12   10/28/08   02 - 16                   37,500             0  JMB             0           0           0                                         0        /  /             /  /        

          Toilet Facility:
12-0309   New Construction             7-024-001  04/22/13     DONE    DONE       DONE      10/24/12   10/23/12   10/18/12   10/28/08   02 - 16                  236,000             0  JMB             0           0           0                                         0        /  /             /  /        

          Ticket Booth #1:
12-0310   New Construction             7-025-001  04/22/13     DONE    DONE       DONE      10/24/12   10/23/12   10/18/12   10/28/08   02 - 16                   25,000             0  JMB             0           0           0                                         0        /  /             /  /        

          Ticket Booth #2:
12-0311   New Construction             7-026-001  04/22/13     DONE    DONE       DONE      10/24/12   10/23/12   10/18/12   10/28/08   02 - 16                   25,000             0  JMB             0           0           0                                         0        /  /             /  /        

          Districtwide:
09-1410   Reconstruction               7-999-001  08/19/10     DONE    DONE       DONE      05/10/10   05/03/10   08/10/09   10/28/08   13,16                  1,220,000     1,220,000  HCM             0           0           0                                         0        /  /           11/02/12      
11-1156   Reconstruction               7-999-002  06/20/12     DONE    DONE       DONE      04/19/12   04/18/12   01/31/12   12/08/08   16                       450,000             0  HCM             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CANDOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-03-01-04
last updated on 05/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School Academy:
08-0114   Reconstruction               0-001-007  04/03/09     DONE    DONE       DONE      08/04/08   07/30/08   01/16/07   04/05/07   2,4,7,8,9,10,13,155,   2,807,688     2,807,688  HCM             0           0     200,000 Highland Associates                     0        /  /             /  /        
12-0622   Reconstruction               0-001-008                         UNREVIEWED         12/26/12   12/23/12   11/15/12   11/15/12   10,155,16                      0    15,453,400  JMB             0           0           0 C&S Companies                           0        /  /             /  /        

          Elementary Academy:
08-0115   Reconstruction               0-003-005  04/03/09     DONE    DONE       DONE      08/04/08   07/30/08   01/16/07   04/05/07   2,4,8,9,10,13,155,15   1,160,934     1,160,934  HCM             0           0      83,927 Highland Associates                     0        /  /             /  /        
11-0079XX Reconstruction               0-003-006                         CANCELLED          08/03/11   08/03/11   04/13/11     /  /     8,10                           0     9,473,760  HCM             0           0           0 Highland Associates                     0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWARK VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-04-02-04
last updated on 05/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nathan T. Hall Elementary:
09-0064   Reconstruction               0-002-010  12/11/09     DONE    DONE       DONE      07/22/09   07/16/09   09/27/07   03/18/08   2,7,8,9,15,16            933,676       933,676  DDJ             0           0      58,822 Clark Patterson Lee                     0        /  /           12/28/12      
  -    XX Reconstruction               0-002-011                         CANCELLED            /  /       /  /     07/10/08     /  /     2,10                           0     6,156,582  JOD             0           0           0                                         0        /  /             /  /        
09-0065   Reconstruction               0-002-012  12/11/09     DONE    DONE       DONE      07/22/09   07/16/09   06/23/09   03/18/08   2,4,9                  1,146,049     1,146,049  DDJ             0           0           0 Clark Patterson Lee                     0        /  /           12/28/12      
11-1353   Reconstruction               0-002-013  06/08/12     DONE    DONE       DONE      05/25/12   05/25/12   03/28/12   05/15/12   2,7,155,15,16            100,000       100,000  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /           11/02/12      

          Middle School:
09-0066   Reconstruction               0-003-015  12/11/09     DONE    DONE       DONE      07/22/09   07/16/09   09/27/07   03/18/08   2,4,7,8,9,10,13,155,   1,682,377     1,682,377  DDJ             0           0     105,991 Clark Patterson Lee                     0        /  /           12/28/12      
09-0067   Reconstruction               0-003-016  12/11/09     DONE    DONE       DONE      07/22/09   07/16/09   06/23/09   03/18/08   2,4,9                  1,155,298     1,155,298  DDJ             0           0           0 Clark Patterson Lee                     0        /  /           12/28/12      

          Newark Valley Senior High:
08-0218   Reconstruction               0-007-012  10/29/08     DONE    DONE       DONE      08/27/08   08/19/08   05/10/07   05/25/08   2,10                     100,000       100,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        
09-0068   Reconstruction               0-007-013  12/11/09     DONE    DONE       DONE      07/22/09   07/16/09   09/27/07   03/18/08   2,4,7,8,9,10,13,155,   1,556,223     1,556,223  DDJ             0           0      98,042 Clark Patterson Lee                     0        /  /           12/28/12      
09-0069   Reconstruction               0-007-014  12/11/09     DONE    DONE       DONE      07/22/09   07/16/09   06/23/09   03/18/08   2,4                    1,888,378     1,888,378  DDJ             0           0           0 Clark Patterson Lee                     0        /  /           12/28/12      
09-0404   Reconstruction               0-007-015  11/24/09     DONE    DONE       DONE      11/06/09   11/05/09   09/04/09   03/30/09   2,9,10                   100,000       100,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        
10-0100   Reconstruction               0-007-016  10/19/10     DONE    DONE       DONE      08/10/10   07/29/10   03/24/10   05/24/10   2,4,8,9,155,16           100,000       100,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        
11-0014   Reconstruction               0-007-017  08/25/11     DONE    DONE       DONE      07/12/11   07/07/11   05/20/11   06/13/11   2,4,9,10,155,16          100,000       100,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /           11/19/12      
  -       Reconstruction               0-007-018                                              /  /       /  /     04/09/13     /  /     16                             0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Bus Garage:
12-0089   Reconstruction               5-004-007  08/14/12     DONE    DONE       DONE      08/08/12   08/06/12   07/30/12   08/12/12   2,15,16                   85,500        85,500  DDJ             0           0           0 Keystone Assoc Architects, En           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OWEGO APALACHIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-06-01-06
last updated on 05/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Owego Elementary School:
08-1110   Reconstruction               0-007-009  06/08/09     DONE    DONE       DONE      01/22/09   01/20/09   10/03/07   05/20/08   2,4,7,8,9,10,13,155,   4,095,000     4,603,696  HCM             0           0     642,915 Highland Associates                     0        /  /             /  /        
  -       Reconstruction               0-007-010                                              /  /       /  /     09/22/11     /  /     2                              0             0  HCM             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-007-011                                              /  /       /  /     09/22/11     /  /     4,8,9,155,15,16                0             0  HCM             0           0           0                                         0        /  /             /  /        
12-0933   Reconstruction               0-007-012  03/19/13     DONE    DONE       DONE      02/28/13   02/22/13   08/30/12   08/29/12   2                      1,542,031             0  JMB             0           0           0 Highland Associates                     0        /  /             /  /        

          Apalachin Elementary School:
08-1111   Reconstruction               0-008-011  06/08/09     DONE    DONE       DONE      01/22/09   01/20/09   10/03/07   05/20/08   2,4,7,8,9,10,13,155,   3,175,000     3,191,438  HCM             0           0           0 Highland Associates                     0        /  /             /  /        

          Owego Free Academy High:
08-1112   Reconstruction               0-009-014  06/08/09     DONE    DONE       DONE      01/22/09   01/20/09   10/03/07   05/20/08   2,4,7,8,9,10,13,14,1   6,361,250     5,329,616  HCM             0           0      79,722 Highland Associates                     0        /  /             /  /        
  -       Reconstruction               0-009-015                                              /  /       /  /     09/22/11     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0           0                                         0        /  /             /  /        
12-1108   Reconstruction               0-009-016                         UNREVIEWED         04/15/13   04/15/13   03/13/12   09/06/12   4,8,9,10,155,15,16             0     9,579,546  JMB             0           0           0 Highland Associates                     0        /  /             /  /        

          Elementary School:
  -    PR New Construction             0-014-001                                              /  /       /  /     12/26/12     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /             /  /        

          Administration Bldg:
  -       Reconstruction               1-002-003                                              /  /       /  /     09/22/11     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0           0                                         0        /  /             /  /        

          Administration Building:
  -       New Construction             1-013-001                                              /  /       /  /     12/26/12     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /             /  /        

          Stadium Seating:
11-0817DB Discovered Building          2-012-001  03/02/12     DONE    DONE       DONE      02/14/12   02/13/12   06/14/11     /  /                                    0             0  HCM             0           0           0 Highland Associates                     0        /  /             /  /        

          Maintenance Bldg:
  -       Reconstruction               3-004-003                                              /  /       /  /     09/22/11     /  /     2,4,8,155,15,16                0             0  HCM             0           0           0                                         0        /  /             /  /        

          Maintenance Facility:
  -       New Construction             3-015-001                                              /  /       /  /     12/26/12     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SPENCER VAN ETTEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-08-01-04
last updated on 05/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Spencer Middle School:
08-1709   Reconstruction               0-001-012  10/14/09     DONE    DONE       DONE      06/18/09   06/09/09   02/03/09   03/18/08   2,4,7,8,9,10,14,155,     779,317       779,317  DDJ             0           0      31,998 SEI Design Group                        0        /  /             /  /        
12-0521   Reconstruction               0-001-013               STARTED DONE       UNREVIEWED12/11/12   12/10/12   05/17/12     /  /     2,4,7,8,9,155,15,16            0    11,406,512  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        

          Van Etten Elementary:
08-1710   Reconstruction               0-006-011  10/14/09     DONE    DONE       DONE      06/18/09   06/09/09   02/03/09   03/18/08   2,8,9,155,15,16        2,106,336     2,106,336  DDJ             0           0      76,863 SEI Design Group                        0        /  /             /  /        
12-0522   Reconstruction               0-006-012               STARTED STARTED    UNREVIEWED12/11/12   12/10/12   05/17/12     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        

          Senior High School:
08-1711   Reconstruction               0-010-011  10/14/09     DONE    DONE       DONE      06/18/09   06/09/09   02/03/09   03/18/08   2,4,8,9,10,155,15,16   3,502,142     3,502,142  DDJ             0           0     120,119 SEI Design Group                        0        /  /             /  /        
11-0275   Reconstruction               0-010-012  11/08/11     DONE    DONE       DONE      10/25/11   10/24/11   05/10/11   03/18/08   2,7,8,9                  453,980             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        
12-0523   Reconstruction               0-010-013               STARTED STARTED    UNREVIEWED12/11/12   12/10/12   05/17/12     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        

          Bus Storage Maintenance:
08-1712   Reconstruction               5-002-005  10/14/09     DONE    DONE       DONE      06/18/09   06/09/09   02/03/09   03/18/08   2,7,155,15,16            349,055       349,055  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        
12-0524   Reconstruction               5-002-006               STARTED STARTED    UNREVIEWED12/11/12   12/10/12   05/17/12     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TIOGA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-09-03-04
last updated on 05/17/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Nichols Elementary:
07-1046   Reconstruction               0-003-008  06/30/08     DONE    DONE       DONE      12/05/07   12/04/07   11/29/05   05/15/07   2,7,8,9,155,15,16      1,536,735     1,536,735  JOD             0           0      30,735 DPC Engineering                         0        /  /             /  /        
10-0909   Reconstruction               0-003-009  08/12/11     DONE    DONE       DONE      02/24/11   02/22/11   08/06/10   12/23/10   10,155,15,16              16,500             0  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        

          K/12 Bldg.(Fmly SHS/MS/Elem):
07-1047   Reconstruction               0-007-008  06/30/08     DONE    DONE       DONE      12/04/07   12/04/07   11/29/05   05/15/07   2,7,155,15,16          7,814,452     7,029,454  JOD             0           0     868,887 DPC Engineering                         0        /  /             /  /        
10-0910   Reconstruction               0-007-009  08/12/11     DONE    DONE       DONE      02/24/11   02/22/11   08/06/10   12/23/10   8,9,10,155,15,16         426,900             0  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        
  -       Reconstruction               0-007-010                                              /  /       /  /     04/16/13     /  /     8,10,16                        0             0  JOB             0           0           0                                         0        /  /             /  /        

          Old Garage Building:
07-1048   Reconstruction               5-005-004  06/30/08     DONE    DONE       DONE      12/05/07   12/04/07   12/04/07   05/15/07   4,8,9,15,16              266,420       266,420  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        
10-0922   Reconstruction               5-005-005  08/12/11     DONE    DONE       DONE      02/24/11   02/23/11   08/06/10   12/23/10   4,7,13                    19,870             0  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        
  -       Reconstruction               5-005-006                         UNREVIEWED         03/01/11   02/22/11   03/02/11   12/23/10   10                             0             0  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        

          New Bus Garage:
07-1049   New Construction             5-026-001  06/30/08     DONE    DONE       DONE      12/05/07   12/04/07   12/22/05   05/15/07   02 - 16                6,069,183     6,069,183  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        
10-0911   Reconstruction               5-026-002  08/12/11     DONE    DONE       DONE      02/24/11   02/23/11   08/06/10   12/23/10   2,9,14,15,16              86,730             0  JOD             0           0           0 DPC Engineering                         0        /  /             /  /        
  -       Reconstruction               5-026-003                                              /  /       /  /     04/16/13     /  /     8,10,16                        0             0  JOB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED