WAVERLY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-01-01-06
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elm Street School:
08-1229 Reconstruction 0-001-007 03/26/09 DONE DONE DONE 02/19/09 02/13/09 10/07/08 10/28/08 2,4,7,8,9,10,14,155, 361,854 361,854 HCM 0 0 361,854 0 / / / /
09-0183 Reconstruction 0-001-008 02/16/10 DONE DONE DONE 09/02/09 08/31/09 10/20/08 10/28/08 2,4,7,8,9,10,14,155, 3,969,001 3,641,984 HCM 0 0 0 0 / / / /
11-0873 Reconstruction 0-001-009 07/06/12 DONE DONE DONE 03/06/12 03/02/12 08/19/11 10/28/08 2,4,7,8,9,10,155,15, 1,703,000 1,703,000 HCM 0 0 0 0 / / / /
11-1234 Reconstruction 0-001-010 05/16/12 DONE DONE DONE 04/26/12 04/25/12 04/20/12 10/28/08 155,15,16 392,000 392,000 HCM 0 0 0 0 / / / /
- Reconstruction 0-001-011 / / / / 08/30/12 / / 2,4,8,9,10,13,155,15 0 7,177,366 JMB 0 0 0 0 / / / /
Chemung #3 Elementary:
08-1230 Reconstruction 0-009-006 03/26/09 DONE DONE DONE 02/19/09 02/13/09 10/20/08 10/28/08 2,4,7,8,9,10,155,15, 253,485 253,485 HCM 0 0 253,485 0 / / / /
09-0184 Reconstruction 0-009-007 02/16/10 DONE DONE DONE 09/02/09 08/31/09 02/12/09 10/28/08 2,4,7,8,9,10,155,15, 1,812,270 1,447,338 HCM 0 0 0 0 / / / /
11-0874 Reconstruction 0-009-008 07/06/12 DONE DONE DONE 03/06/12 03/02/12 08/19/11 10/28/08 2,4,7,8,9,10,155,15, 518,000 0 HCM 0 0 0 0 / / / /
Lincoln St School:
08-1231 Reconstruction 0-016-006 03/26/09 DONE DONE DONE 02/19/09 02/13/09 10/07/08 10/28/08 2,4,7,8,9,10,155,15, 585,951 585,951 HCM 0 0 585,951 0 / / / /
09-0185 Reconstruction 0-016-007 02/16/10 DONE DONE DONE 09/02/09 08/31/09 10/20/08 10/28/08 2,4,7,8,9,10,155,15, 2,913,458 2,351,330 HCM 0 0 0 0 / / / /
11-0875 Reconstruction 0-016-008 07/06/12 DONE DONE DONE 03/06/12 03/02/12 08/19/11 10/28/08 2,4,7,8,9,10,155,15, 1,300,000 0 HCM 0 0 0 0 / / / /
Waverly Jr/Sr High School:
09-0295 Reconstruction 0-018-011 02/12/10 DONE DONE DONE 10/06/09 10/06/09 10/07/08 10/28/08 2,4,7,8,9,10,155,15, 15,430,040 15,430,040 HCM 0 0 175,381 0 / / / /
11-0876 Reconstruction 0-018-012 07/06/12 DONE DONE DONE 03/06/12 03/02/12 10/20/08 10/28/08 2,4,7,8,9,10,155,15, 6,800,000 6,800,000 HCM 0 0 0 0 / / / /
12-0306 Reconstruction 0-018-013 05/08/13 DONE DONE DONE 10/24/12 10/23/12 10/18/12 03/28/08 2,9,13,16 4,008,000 0 JMB 0 0 0 0 / / / /
Metal Storage Building #1:
09-1096 Reconstruction 2-004-002 04/22/10 DONE DONE DONE 03/18/10 02/16/10 02/16/10 11/28/08 2,13 12,500 0 HCM 0 0 0 0 / / / /
Bus Garage:
08-1519 Reconstruction 5-002-004 12/02/09 DONE DONE DONE 04/16/09 04/16/09 10/20/08 10/28/08 2,7,8,9,10,155,15,16 1,502,755 1,502,755 HCM 0 0 0 0 / / 11/21/11
11-0877 Reconstruction 5-002-005 07/06/12 DONE DONE DONE 03/06/12 03/02/12 08/19/11 10/28/08 2,4,7,8,9,10,155,15, 855,000 855,000 HCM 0 0 0 0 / / / /
Concession Stand - Elm St Elem:
12-0415DB Discovered Building 7-022-001 11/27/12 DONE DONE DONE 11/14/12 10/19/12 08/29/12 / / 0 0 JMB 0 0 0 0 / / / /
12-0307 Reconstruction 7-022-002 04/22/13 DONE DONE DONE 10/24/12 10/23/12 10/24/12 10/28/08 4,7,8,9,10,155,15,16 30,000 0 JMB 0 0 0 0 / / / /
Press Box:
12-0308 New Construction 7-023-001 04/22/13 DONE DONE DONE 10/24/12 10/23/12 08/30/12 10/28/08 02 - 16 37,500 0 JMB 0 0 0 0 / / / /
Toilet Facility:
12-0309 New Construction 7-024-001 04/22/13 DONE DONE DONE 10/24/12 10/23/12 10/18/12 10/28/08 02 - 16 236,000 0 JMB 0 0 0 0 / / / /
Ticket Booth #1:
12-0310 New Construction 7-025-001 04/22/13 DONE DONE DONE 10/24/12 10/23/12 10/18/12 10/28/08 02 - 16 25,000 0 JMB 0 0 0 0 / / / /
Ticket Booth #2:
12-0311 New Construction 7-026-001 04/22/13 DONE DONE DONE 10/24/12 10/23/12 10/18/12 10/28/08 02 - 16 25,000 0 JMB 0 0 0 0 / / / /
Districtwide:
09-1410 Reconstruction 7-999-001 08/19/10 DONE DONE DONE 05/10/10 05/03/10 08/10/09 10/28/08 13,16 1,220,000 1,220,000 HCM 0 0 0 0 / / 11/02/12
11-1156 Reconstruction 7-999-002 06/20/12 DONE DONE DONE 04/19/12 04/18/12 01/31/12 12/08/08 16 450,000 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
NEWARK VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-04-02-04
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Nathan T. Hall Elementary:
09-0064 Reconstruction 0-002-010 12/11/09 DONE DONE DONE 07/22/09 07/16/09 09/27/07 03/18/08 2,7,8,9,15,16 933,676 933,676 DDJ 0 0 58,822 Clark Patterson Lee 0 / / 12/28/12
- XX Reconstruction 0-002-011 CANCELLED / / / / 07/10/08 / / 2,10 0 6,156,582 JOD 0 0 0 0 / / / /
09-0065 Reconstruction 0-002-012 12/11/09 DONE DONE DONE 07/22/09 07/16/09 06/23/09 03/18/08 2,4,9 1,146,049 1,146,049 DDJ 0 0 0 Clark Patterson Lee 0 / / 12/28/12
11-1353 Reconstruction 0-002-013 06/08/12 DONE DONE DONE 05/25/12 05/25/12 03/28/12 05/15/12 2,7,155,15,16 100,000 100,000 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / 11/02/12
Middle School:
09-0066 Reconstruction 0-003-015 12/11/09 DONE DONE DONE 07/22/09 07/16/09 09/27/07 03/18/08 2,4,7,8,9,10,13,155, 1,682,377 1,682,377 DDJ 0 0 105,991 Clark Patterson Lee 0 / / 12/28/12
09-0067 Reconstruction 0-003-016 12/11/09 DONE DONE DONE 07/22/09 07/16/09 06/23/09 03/18/08 2,4,9 1,155,298 1,155,298 DDJ 0 0 0 Clark Patterson Lee 0 / / 12/28/12
Newark Valley Senior High:
08-0218 Reconstruction 0-007-012 10/29/08 DONE DONE DONE 08/27/08 08/19/08 05/10/07 05/25/08 2,10 100,000 100,000 DDJ 0 0 0 Clark Patterson Lee 0 / / / /
09-0068 Reconstruction 0-007-013 12/11/09 DONE DONE DONE 07/22/09 07/16/09 09/27/07 03/18/08 2,4,7,8,9,10,13,155, 1,556,223 1,556,223 DDJ 0 0 98,042 Clark Patterson Lee 0 / / 12/28/12
09-0069 Reconstruction 0-007-014 12/11/09 DONE DONE DONE 07/22/09 07/16/09 06/23/09 03/18/08 2,4 1,888,378 1,888,378 DDJ 0 0 0 Clark Patterson Lee 0 / / 12/28/12
09-0404 Reconstruction 0-007-015 11/24/09 DONE DONE DONE 11/06/09 11/05/09 09/04/09 03/30/09 2,9,10 100,000 100,000 DDJ 0 0 0 Clark Patterson Lee 0 / / / /
10-0100 Reconstruction 0-007-016 10/19/10 DONE DONE DONE 08/10/10 07/29/10 03/24/10 05/24/10 2,4,8,9,155,16 100,000 100,000 DDJ 0 0 0 Clark Patterson Lee 0 / / / /
11-0014 Reconstruction 0-007-017 08/25/11 DONE DONE DONE 07/12/11 07/07/11 05/20/11 06/13/11 2,4,9,10,155,16 100,000 100,000 DDJ 0 0 0 Clark Patterson Lee 0 / / 11/19/12
- Reconstruction 0-007-018 / / / / 04/09/13 / / 16 0 0 DDJ 0 0 0 0 / / / /
Bus Garage:
12-0089 Reconstruction 5-004-007 08/14/12 DONE DONE DONE 08/08/12 08/06/12 07/30/12 08/12/12 2,15,16 85,500 85,500 DDJ 0 0 0 Keystone Assoc Architects, En 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
OWEGO APALACHIN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-06-01-06
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Owego Elementary School:
08-1110 Reconstruction 0-007-009 06/08/09 DONE DONE DONE 01/22/09 01/20/09 10/03/07 05/20/08 2,4,7,8,9,10,13,155, 4,095,000 4,603,696 HCM 0 0 642,915 Highland Associates 0 / / / /
- Reconstruction 0-007-010 / / / / 09/22/11 / / 2 0 0 HCM 0 0 0 0 / / / /
- Reconstruction 0-007-011 / / / / 09/22/11 / / 4,8,9,155,15,16 0 0 HCM 0 0 0 0 / / / /
12-0933 Reconstruction 0-007-012 03/19/13 DONE DONE DONE 02/28/13 02/22/13 08/30/12 08/29/12 2 1,542,031 0 JMB 0 0 0 Highland Associates 0 / / / /
Apalachin Elementary School:
08-1111 Reconstruction 0-008-011 06/08/09 DONE DONE DONE 01/22/09 01/20/09 10/03/07 05/20/08 2,4,7,8,9,10,13,155, 3,175,000 3,191,438 HCM 0 0 0 Highland Associates 0 / / / /
Owego Free Academy High:
08-1112 Reconstruction 0-009-014 06/08/09 DONE DONE DONE 01/22/09 01/20/09 10/03/07 05/20/08 2,4,7,8,9,10,13,14,1 6,361,250 5,329,616 HCM 0 0 79,722 Highland Associates 0 / / / /
- Reconstruction 0-009-015 / / / / 09/22/11 / / 2,4,8,9,155,15,16 0 0 HCM 0 0 0 0 / / / /
12-1108 Reconstruction 0-009-016 UNREVIEWED 04/15/13 04/15/13 03/13/12 09/06/12 4,8,9,10,155,15,16 0 9,579,546 JMB 0 0 0 Highland Associates 0 / / / /
Elementary School:
- PR New Construction 0-014-001 / / / / 12/26/12 / / 02 - 16 0 0 JMB 0 0 0 0 / / / /
Administration Bldg:
- Reconstruction 1-002-003 / / / / 09/22/11 / / 2,4,8,9,155,15,16 0 0 HCM 0 0 0 0 / / / /
Administration Building:
- New Construction 1-013-001 / / / / 12/26/12 / / 02 - 16 0 0 JMB 0 0 0 0 / / / /
Stadium Seating:
11-0817DB Discovered Building 2-012-001 03/02/12 DONE DONE DONE 02/14/12 02/13/12 06/14/11 / / 0 0 HCM 0 0 0 Highland Associates 0 / / / /
Maintenance Bldg:
- Reconstruction 3-004-003 / / / / 09/22/11 / / 2,4,8,155,15,16 0 0 HCM 0 0 0 0 / / / /
Maintenance Facility:
- New Construction 3-015-001 / / / / 12/26/12 / / 02 - 16 0 0 JMB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SPENCER VAN ETTEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-08-01-04
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Spencer Middle School:
08-1709 Reconstruction 0-001-012 10/14/09 DONE DONE DONE 06/18/09 06/09/09 02/03/09 03/18/08 2,4,7,8,9,10,14,155, 779,317 779,317 DDJ 0 0 31,998 SEI Design Group 0 / / / /
12-0521 Reconstruction 0-001-013 STARTED DONE UNREVIEWED12/11/12 12/10/12 05/17/12 / / 2,4,7,8,9,155,15,16 0 11,406,512 DDJ 0 0 0 SEI Design Group 0 / / / /
Van Etten Elementary:
08-1710 Reconstruction 0-006-011 10/14/09 DONE DONE DONE 06/18/09 06/09/09 02/03/09 03/18/08 2,8,9,155,15,16 2,106,336 2,106,336 DDJ 0 0 76,863 SEI Design Group 0 / / / /
12-0522 Reconstruction 0-006-012 STARTED STARTED UNREVIEWED12/11/12 12/10/12 05/17/12 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0 SEI Design Group 0 / / / /
Senior High School:
08-1711 Reconstruction 0-010-011 10/14/09 DONE DONE DONE 06/18/09 06/09/09 02/03/09 03/18/08 2,4,8,9,10,155,15,16 3,502,142 3,502,142 DDJ 0 0 120,119 SEI Design Group 0 / / / /
11-0275 Reconstruction 0-010-012 11/08/11 DONE DONE DONE 10/25/11 10/24/11 05/10/11 03/18/08 2,7,8,9 453,980 0 DDJ 0 0 0 SEI Design Group 0 / / / /
12-0523 Reconstruction 0-010-013 STARTED STARTED UNREVIEWED12/11/12 12/10/12 05/17/12 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0 SEI Design Group 0 / / / /
Bus Storage Maintenance:
08-1712 Reconstruction 5-002-005 10/14/09 DONE DONE DONE 06/18/09 06/09/09 02/03/09 03/18/08 2,7,155,15,16 349,055 349,055 DDJ 0 0 0 SEI Design Group 0 / / / /
12-0524 Reconstruction 5-002-006 STARTED STARTED UNREVIEWED12/11/12 12/10/12 05/17/12 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0 SEI Design Group 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
TIOGA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 60-09-03-04
last updated on 05/17/13
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Nichols Elementary:
07-1046 Reconstruction 0-003-008 06/30/08 DONE DONE DONE 12/05/07 12/04/07 11/29/05 05/15/07 2,7,8,9,155,15,16 1,536,735 1,536,735 JOD 0 0 30,735 DPC Engineering 0 / / / /
10-0909 Reconstruction 0-003-009 08/12/11 DONE DONE DONE 02/24/11 02/22/11 08/06/10 12/23/10 10,155,15,16 16,500 0 JOD 0 0 0 DPC Engineering 0 / / / /
K/12 Bldg.(Fmly SHS/MS/Elem):
07-1047 Reconstruction 0-007-008 06/30/08 DONE DONE DONE 12/04/07 12/04/07 11/29/05 05/15/07 2,7,155,15,16 7,814,452 7,029,454 JOD 0 0 868,887 DPC Engineering 0 / / / /
10-0910 Reconstruction 0-007-009 08/12/11 DONE DONE DONE 02/24/11 02/22/11 08/06/10 12/23/10 8,9,10,155,15,16 426,900 0 JOD 0 0 0 DPC Engineering 0 / / / /
- Reconstruction 0-007-010 / / / / 04/16/13 / / 8,10,16 0 0 JOB 0 0 0 0 / / / /
Old Garage Building:
07-1048 Reconstruction 5-005-004 06/30/08 DONE DONE DONE 12/05/07 12/04/07 12/04/07 05/15/07 4,8,9,15,16 266,420 266,420 JOD 0 0 0 DPC Engineering 0 / / / /
10-0922 Reconstruction 5-005-005 08/12/11 DONE DONE DONE 02/24/11 02/23/11 08/06/10 12/23/10 4,7,13 19,870 0 JOD 0 0 0 DPC Engineering 0 / / / /
- Reconstruction 5-005-006 UNREVIEWED 03/01/11 02/22/11 03/02/11 12/23/10 10 0 0 JOD 0 0 0 DPC Engineering 0 / / / /
New Bus Garage:
07-1049 New Construction 5-026-001 06/30/08 DONE DONE DONE 12/05/07 12/04/07 12/22/05 05/15/07 02 - 16 6,069,183 6,069,183 JOD 0 0 0 DPC Engineering 0 / / / /
10-0911 Reconstruction 5-026-002 08/12/11 DONE DONE DONE 02/24/11 02/23/11 08/06/10 12/23/10 2,9,14,15,16 86,730 0 JOD 0 0 0 DPC Engineering 0 / / / /
- Reconstruction 5-026-003 / / / / 04/16/13 / / 8,10,16 0 0 JOB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED