Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/23/13 at 14:42:32




WEST PARK UFSD(DISTRICT CLOSED) STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-02-02-02
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Maintenance Storage Building:
00-0188DB Discovered Building          2-010-001  09/21/09     DONE    DONE       DONE      08/22/00     /  /     07/24/00     /  /                                    0             0  BJB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




KINGSTON CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-06-00-01
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Frank T. Meagher Elementary:
08-0845   Reconstruction               0-001-009  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/30/07   03/20/07   2,8,16                   253,025       253,025  JOD             0           0      71,859 Collins & Scoville Architects           0        /  /             /  /        
10-0061   Reconstruction               0-001-010  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           939,318             0  JOD             0           0           0 Cannon Design                     939,318        /  /             /  /        

          Sophie Finn Elementary School:
07-0931   Reconstruction               0-002-010  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/17/06   03/20/07   8                        752,583       721,070  JOD             0           0     213,733 Collins & Scoville Architects           0        /  /             /  /        
10-0062   Reconstruction               0-002-012  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           131,646             0  JOD             0           0           0 Cannon Design                     131,646        /  /             /  /        

          John F. Kennedy Elem School:
07-0932   Reconstruction               0-003-006  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   2,15                     146,342       146,342  JOD             0           0      41,561 Collins & Scoville Architects           0        /  /             /  /        
08-0846   Reconstruction               0-003-007  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/09/08   03/20/07   2,7,8,155,15,16          413,074       413,074  JOD             0           0     117,313 Collins & Scoville Architects           0        /  /             /  /        
10-0063   Reconstruction               0-003-008  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   13,155,15,16             314,977             0  JOD             0           0           0 Cannon Design                     314,977        /  /             /  /        
12-0619   Reconstruction               0-003-009  03/06/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,7                    1,102,000             0  DDJ             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        
12-0641   Reconstruction               0-003-010  03/26/13     DONE    DONE       DONE      01/07/13   01/03/13   12/28/12   12/15/12   155,15,16                348,000             0  DDJ             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        

          George Washington School:
07-0933   Reconstruction               0-004-008  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   2,8,9,13,14,15,16        775,925       775,925  JOD             0           0     235,570 Collins & Scoville Architects           0        /  /             /  /        
10-0064   Reconstruction               0-004-010  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           220,861             0  JOD             0           0           0 Cannon Design                     220,861        /  /             /  /        

          Myron J. Michael Building:
07-0934   Reconstruction               0-005-011  07/24/08     DONE    DONE       DONE      11/23/07   11/21/07     /  /     03/20/07                             35,220        35,220  JOD             0           0      10,002 Collins & Scoville Architects           0        /  /             /  /        
10-0065   Reconstruction               0-005-013  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   06/01/10   09/16/09   2,13,155,15,16           222,768             0  JOD             0           0           0 Cannon Design                     222,768        /  /             /  /        
  -    PR Additions and Alterations    0-005-014                                              /  /       /  /     10/12/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-005-015                                              /  /       /  /     10/18/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-005-016                                              /  /       /  /     11/03/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          Kingston High School:
07-0935   Reconstruction               0-006-014  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   2,4,7,8,9,15,16          925,934       925,934  JOD             0           0     281,114 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-006-016                                              /  /       /  /     02/06/09     /  /     10                             0             0  JOD             0           0           0                                         0        /  /             /  /        
09-0970   Reconstruction               0-006-017  05/20/10     DONE    DONE       DONE      02/26/10   02/19/10   01/07/10   05/18/10   9,10,16                  148,700       148,700  JOD             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        
10-0066   Reconstruction               0-006-018  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           412,062       412,062  JOD             0           0           0 Cannon Design                     412,062        /  /             /  /        
  -    PR Additions and Alterations    0-006-019                                              /  /       /  /     10/12/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-006-020                                              /  /       /  /     10/18/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-006-021                                              /  /       /  /     11/03/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          Vocational Bldg(Whiston Bldg.):
07-0936   Reconstruction               0-007-006  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   155,16                    57,330        57,330  JOD             0           0      16,282 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-007-007                                              /  /       /  /     06/01/10     /  /     2,13,155,15,16                 0             0  JOD             0           0           0                                         0        /  /             /  /        
10-0067   Reconstruction               0-007-007  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10     /  /     09/16/09                             64,278             0                  0           0           0 Cannon Design                      64,278        /  /             /  /        
  -    PR Additions and Alterations    0-007-008                                              /  /       /  /     10/12/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -       Additions and Alterations    0-007-009                                              /  /       /  /     10/18/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-007-010                                              /  /       /  /     11/03/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          Kate Walton Field House:
07-0937   Reconstruction               0-008-010  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   2,14,15,16               326,937       326,937  JOD             0           0      99,258 Collins & Scoville Architects           0        /  /             /  /        
10-0068   Reconstruction               0-008-012  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   06/01/10   09/16/09   2,13,155,15,16           521,952             0  JOD             0           0           0 Cannon Design                     521,953        /  /             /  /        
  -    PR Additions and Alterations    0-008-013                                              /  /       /  /     10/12/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-008-014                                              /  /       /  /     10/18/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-008-015                                              /  /       /  /     11/03/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          Chambers Elementary:
08-0847   Reconstruction               0-009-010  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   02/16/06   03/20/08   7,8,155,16             1,975,947     1,975,947  JOD             0           0     599,897 Collins & Scoville Architects           0        /  /             /  /        
10-0069   Reconstruction               0-009-011  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           174,858             0  JOD             0           0           0 Cannon Design                     174,858        /  /             /  /        

          Anna Devine School:
07-0938   Reconstruction               0-010-005  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   2,8                      702,895       702,895  JOD             0           0     199,622 Collins & Scoville Architects           0        /  /             /  /        
09-0946   Reconstruction               0-010-007  05/24/10     DONE    DONE       DONE      02/22/10   02/17/10   01/07/10   05/18/10   155,15,16                450,950       450,950  JOD             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        
10-0070   Reconstruction               0-010-008  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,14,155,15,16        222,756             0  JOD             0           0           0 Cannon Design                     222,756        /  /             /  /        

          Louis A Salzmann Bldg.:
07-0939   Reconstruction               0-011-006  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   9,16                     106,967       106,967  JOD             0           0      32,475 Collins & Scoville Architects           0        /  /             /  /        
10-0071   Reconstruction               0-011-007  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   06/01/10   09/16/09   2,13,155,15,16           179,766             0  JOD             0           0           0 Cannon Design                     179,767        /  /             /  /        
  -    PR Additions and Alterations    0-011-008                                              /  /       /  /     10/12/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-011-009                                              /  /       /  /     10/18/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-011-010                                              /  /       /  /     11/03/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          Ernest C. Myer Elementary:
08-0848   Reconstruction               0-013-007  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   02/16/06   03/20/08   2,7,8,15,16            1,394,843     1,394,843  JOD             0           0     396,135 Collins & Scoville Architects           0        /  /             /  /        
10-0072   Reconstruction               0-013-008  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   155,15,16                266,547             0  JOD             0           0           0 Cannon Design                     266,547        /  /             /  /        

          Edward R.Crosby Elementary:
08-0849   Reconstruction               0-014-007  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/30/07   03/20/07   2,7,8,16               1,425,906     1,425,906  JOD             0           0     404,957 Collins & Scoville Architects           0        /  /             /  /        
10-0073   Reconstruction               0-014-008  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           177,937             0  JOD             0           0           0 Cannon Design                     177,937        /  /             /  /        

          Robert Graves Elem. School:
07-0940   Reconstruction               0-016-005  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   2,4,7,9,15,16            557,510       557,510  JOD             0           0     169,260 Collins & Scoville Architects           0        /  /             /  /        
10-0074   Reconstruction               0-016-007  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/19/10   09/16/09   2,13,155,15,16           164,628             0  JOD             0           0           0 Cannon Design                     164,628        /  /             /  /        

          Tobin Learning Center:
07-0941   Reconstruction               0-017-004  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   155,16                    34,295        34,295  JOD             0           0       9,740 Collins & Scoville Architects           0        /  /             /  /        
10-0075   Reconstruction               0-017-005  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   06/01/10   09/16/09   2,13,155,15,16            64,112             0  JOD             0           0           0 Cannon Design                      64,112        /  /             /  /        
  -    PR Additions and Alterations    0-017-006                                              /  /       /  /     10/12/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-017-007                                              /  /       /  /     10/18/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        
  -    PR Additions and Alterations    0-017-008                                              /  /       /  /     11/03/11     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          J. Watson Bailey Jr High proj.advent:
07-0942   Reconstruction               0-026-008  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   2,4,7,8,9,10,155,15,     611,053       611,053  JOD             0           0     185,516 Collins & Scoville Architects           0        /  /             /  /        
08-0850   Reconstruction               0-026-010  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/09/08   03/20/07   2,8,155,16             2,000,000             0  JOD             0           0     568,000 Collins & Scoville Architects           0        /  /             /  /        
10-0076   Reconstruction               0-026-011  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/22/10   09/16/09   2,13,155,15,16           441,684             0  JOD             0           0           0 Cannon Design                     441,684        /  /             /  /        
12-0615   Reconstruction               0-026-012  03/21/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,16                     250,000             0  DDJ             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        

          Harry L. Edson Elem. School:
07-0943   Reconstruction               0-027-005  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   8                      1,127,772     1,127,772  JOD             0           0     320,287 Collins & Scoville Architects           0        /  /             /  /        
10-0077   Reconstruction               0-027-006  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/22/10   09/16/09   2,13,155,15,16           206,296             0  JOD             0           0           0 Cannon Design                     206,296        /  /             /  /        
12-0620   Reconstruction               0-027-007  03/06/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,7                    1,143,760     1,143,760  DDJ             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        

          M. Clifford Miller Middle:
08-0851   Reconstruction               0-028-008  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   02/16/06   03/20/07   2,8,10,15,16           2,001,057     2,001,057  JOD             0           0     612,082 Collins & Scoville Architects           0        /  /             /  /        
10-0078   Reconstruction               0-028-010  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/22/10   09/16/09   2,13,155,15,16           384,604             0  JOD             0           0           0 Cannon Design                     384,605        /  /             /  /        
12-0621   Reconstruction               0-028-011  03/06/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,7                    4,234,000             0  DDJ             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        

          Zena Elementary:
08-0852   Reconstruction               0-031-005  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/30/07   03/20/07   2,7,8,15,16              613,840       613,840  JOD             0           0     174,331 Collins & Scoville Architects           0        /  /             /  /        
10-0079   Reconstruction               0-031-006  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/22/10   09/16/09   2,13,155,15,16           186,586             0  JOD             0           0           0 Cannon Design                     186,586        /  /             /  /        

          Carnegie Learning Center:
09-0380   Reconstruction               0-041-001  02/03/10     DONE    DONE       DONE      11/02/09   11/02/09     /  /     11/19/08   2,4,7,8,9,10,14,155,   3,430,000     3,430,000  JOD             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        

          Central Administration:
10-0080   Reconstruction               1-029-006  01/09/12     DONE    DONE       DONE      08/03/10   07/16/10   02/22/10   09/16/09   2,13,155,15,16           363,431             0  JOD             0           0           0 Cannon Design                     363,431        /  /             /  /        

          Carnegie Library Annex:
  -       Additions and Alterations    6-041-002                         UNREVIEWED         11/03/09   11/02/09   05/14/09   11/19/08   02 - 16                        0             0  JOD             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        
09-0119PR Additions and Alterations    6-041-002  09/22/09     DONE    DONE       DONE      08/12/09   08/11/09   05/14/09   11/19/08   02 - 16                        0             0  JOD             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        

          Gray Building:
09-0750XX Reconstruction               8-049-001                         CANCELLED          01/21/10   01/19/10   11/10/09     /  /                                    0             0  JOD             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HIGHLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-08-03-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
07-2019   Reconstruction               0-001-004  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   02/04/08   10/30/07   2,4,8,10,16              299,635       299,635  JOD             0           0      66,010 Dodge Chamberlin Luzine Weber           0        /  /           10/19/12      
12-1051   Reconstruction               0-001-005                         UNREVIEWED         04/02/13   03/26/13   01/08/13   12/18/12   2,155,15,16                    0             0  DDJ             0           0           0 ECG Eninering, LLC                      0        /  /             /  /        

          Junior/Senior High School:
07-2020   Reconstruction               0-009-008  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   02/04/08   10/30/07   2,8,10,155,16            797,317       797,317  JOD             0           0     178,227 Dodge Chamberlin Luzine Weber           0        /  /           10/19/12      
12-1052   Reconstruction               0-009-009                         UNREVIEWED         04/02/13   03/26/13   01/08/13   12/18/12   2,155,15,16                    0             0  DDJ             0           0           0 ECG Eninering, LLC                      0        /  /             /  /        

          Elementary School:
07-2021   Reconstruction               0-010-008  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   02/04/08   10/30/07   2,4,8,10,155,16          444,168       444,168  JOD             0           0      85,813 Dodge Chamberlin Luzine Weber           0        /  /           10/19/12      
12-1053   Reconstruction               0-010-009                         UNREVIEWED         04/02/13   03/26/13   01/08/13   12/18/12   2,155,15,16                    0             0  DDJ             0           0           0 ECG Eninering, LLC                      0        /  /             /  /        

          Bus Garage:
07-2022   Reconstruction               5-002-004  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   06/19/07   10/30/07   2,7,15                         0       100,000  JOD             0           0           0 Dodge Chamberlin Luzine Weber           0        /  /           10/19/12      
12-1054   Reconstruction               5-002-006                         UNREVIEWED         04/02/13   03/26/13   01/09/13   12/18/12   155,16                         0             0  DDJ             0           0           0 ECG Eninering, LLC                      0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RONDOUT VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-09-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Rondout Valley High:
08-0285PR Additions and Alterations    0-002-007                         UNREVIEWED         09/09/08   09/04/08   01/10/06     /  /     02 - 16                        0             0  MGL             0           0           0 Einhorn Yaffee Prescott P.C.            0        /  /             /  /        
08-0593   Additions and Alterations    0-002-007  05/14/09     DONE    DONE       DONE      10/24/08   10/22/08   01/10/06   10/21/07   02 - 16               25,736,500    23,368,940  JOD             0           0     871,330 Einhorn Yaffee Prescott P.C.            0        /  /             /  /        
  -    PR Additions and Alterations    0-002-008                                              /  /       /  /     08/27/08     /  /     02 - 16                        0             0  JOD             0           0           0                                         0        /  /             /  /        

          Middle School:
08-0594   Reconstruction               0-007-010  05/14/09     DONE    DONE       DONE      10/24/08   10/22/08   11/06/06   10/21/07   2,8,9,10,15,16         2,181,205     1,688,500  MGL             0           0           0 Einhorn Yaffee Prescott P.C.            0        /  /             /  /        
10-0084   Reconstruction               0-007-011  01/27/11     DONE    DONE       DONE      08/03/10   07/20/10   03/24/09   03/24/09   10,15                     54,000             0  JOD             0           0           0 AlFandre Architecture                   0        /  /             /  /        

          Rosendale Elementary:
09-0908   Reconstruction               0-012-007  04/19/10     DONE    DONE       DONE      02/19/10   02/12/10   03/24/09   05/19/09   2,7                      271,919       271,919  JOD             0           0           0 AlFandre Architecture                   0        /  /           10/15/12      

          Bus Garage:
09-0909   Reconstruction               5-008-003  06/02/10     DONE    DONE       DONE      02/19/10   02/12/10   03/24/09   05/19/09   2,7                       98,210        98,210  JOD             0           0           0 AlFandre Architecture                   0        /  /           10/15/12      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARLBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-10-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
08-1730   Reconstruction               0-001-007  07/15/09     DONE    DONE       DONE      06/22/09   06/12/09   03/24/09   05/11/09   15                       325,000       325,000  HCM             0           0           0 Fellenzer Engineering                   0        /  /             /  /        
12-0595   Reconstruction               0-001-008               DONE    STARTED    UNREVIEWED12/24/12   12/13/12   08/07/12   05/15/12   2,10                           0             0  JMB             0           0           0 Tetra  Tech Architects & Engi           0        /  /             /  /        
  -       Reconstruction               0-001-009                                              /  /       /  /     11/19/12     /  /     2,10                           0             0  JMB             0           0           0                                         0        /  /             /  /        

          Milton Elementary:
10-0018   Reconstruction               0-006-005  07/13/10     DONE    DONE       DONE      07/08/10   07/06/10   06/02/10   06/17/10   2,9,16                   435,000       435,000  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /             /  /        

          Marlboro High School:
07-1263   Additions and Alterations    0-007-005  09/26/08     DONE    DONE       DONE      12/31/07   12/26/07   09/07/04   03/20/07   02 - 16               20,878,500             0  HCM             0           0     870,000 ThomasAssociates, PC                    0        /  /             /  /        
09-0311   Reconstruction               0-007-006  01/21/10     DONE    DONE       DONE      10/19/09   10/15/09   04/26/07   03/20/07   2,4,7,8,155,15,16      3,500,000             0  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /             /  /        
09-1472   Reconstruction               0-007-007  09/13/10     DONE    DONE       DONE      05/28/10   05/21/10   04/30/10   03/20/07   15,16                    360,000             0  HCM             0           0           0 Tetra Tech Architects And Eni           0        /  /             /  /        

          Marlboro CSD - Central Offices:
08-0675TQ Temporary Quarters           1-020-001  11/03/08     DONE    DONE       DONE      11/04/08   10/31/08   04/03/08     /  /                                    0             0  HCM             0           0           0 Thomas Associates                       0        /  /             /  /        
  -       Reconstruction               1-020-002                                              /  /       /  /     03/01/12     /  /     2,4,7,8,9,155,15,16            0             0  HCM             0           0           0                                         0        /  /             /  /        

          :
07-2292   Reconstruction               2-005-001  07/07/08     DONE    DONE       DONE      07/01/08   06/16/08   04/03/08   04/17/08   2                         90,000             0  HCM             0           0           0 ThomasAssociates, PC                    0        /  /             /  /        

          Residential Building #4 (1 Fam Rent):
08-1303DB Discovered Building          7-019-001  04/30/09     DONE    DONE       DONE      03/02/09   02/26/09   04/23/07     /  /                                    0             0  HCM             0           0           0                                         0        /  /             /  /        

          Concession Stand at Middle High:
09-0400   New Construction             7-021-001  04/26/10     DONE    DONE       DONE      11/06/09   11/05/09   03/26/09   09/30/09   02 - 16                        0             0  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /             /  /        

          Press Box at Middle High School:
09-0709   New Construction             7-022-001               STARTED DONE       DONE      ***SHPO RESPONSE***                                                                      0  HCM             0           0           0 Tetra  Tech Architects & Engi           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEW PALTZ CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-11-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
  -    PR Additions and Alterations    0-001-011                                              /  /       /  /     11/06/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        
10-0059   Reconstruction               0-001-012  08/30/10     DONE    DONE       DONE      08/03/10   08/02/10   07/22/10   07/21/10   2,4,7,9,155,15,16        100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
10-0704   Reconstruction               0-001-013  09/28/11     DONE    DONE       DONE      01/03/11   12/24/10   10/05/10   10/06/10   2,155,15,16            1,100,000             0  DDJ             0           0           0 ECG Eninering, LLC              1,100,000        /  /             /  /        

          Duzine Elementary School:
07-1282   Reconstruction               0-004-010  04/15/09     DONE    DONE       DONE      01/02/08   12/28/07   09/27/07   05/15/07   2,4,7,155,15,16          803,555       803,555  DDJ             0           0     315,418 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-004-011                                              /  /       /  /     08/12/08     /  /     2,4,10,13,14,15,16             0             0  DDJ             0           0           0                                         0        /  /             /  /        
10-0705   Reconstruction               0-004-012  09/28/11     DONE    DONE       DONE      01/03/11   12/24/10   10/05/10   10/06/10   2,155,15,16              660,000             0  DDJ             0           0           0 ECG Eninering, LLC                660,000        /  /             /  /        

          High School:
07-1283   Reconstruction               0-005-014  04/15/09     DONE    DONE       DONE      01/02/08   12/28/07   09/27/07   05/15/07   2,4,7,8,9,10,155,15,     927,257       927,257  DDJ             0           0     364,566 Collins & Scoville Architects           0        /  /             /  /        
09-0985   Reconstruction               0-005-015  03/03/10     DONE    DONE       DONE      03/02/10   02/25/10   01/20/09   01/20/09   2,4,8,9,10,155,15,16      12,700             0  DDJ             0           0           0 AlFandre Architecture                   0        /  /             /  /        
  -    PR Additions and Alterations    0-005-016                                              /  /       /  /     11/06/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        
10-0706   Reconstruction               0-005-017  09/28/11     DONE    DONE       DONE      01/03/11   12/24/10   10/05/10   10/06/10   2,155,15,16              880,000             0  DDJ             0           0           0 ECG Eninering, LLC                880,000        /  /             /  /        
10-1276   Reconstruction               0-005-018  05/11/11     DONE    DONE       DONE      05/11/11   05/09/11   03/25/11   04/06/11   2,15,16                  200,000       200,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Lenape Elementary School:
07-1284   Reconstruction               0-008-008  04/15/09     DONE    DONE       DONE      01/02/08   12/28/07   09/27/07   05/15/07   2,4,7,8,9,10,13,14,1     135,688       135,688  DDJ             0           0      53,548 Collins & Scoville Architects           0        /  /             /  /        
08-1610   Reconstruction               0-008-009  05/12/09     DONE    DONE       DONE      05/11/09   05/05/09   01/20/09   01/20/09   2,4,8,9,10,155,15,16      20,000             0  DDJ             0           0           0 AlFandre Architecture                   0        /  /             /  /        
10-0060   Reconstruction               0-008-010  08/30/10     DONE    DONE       DONE      08/03/10   08/02/10   07/22/10   07/21/10   2,4,7,9,155,15,16        100,000       100,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
10-0234   Reconstruction               0-008-011  09/27/10     DONE    DONE       DONE      09/20/10   09/17/10   08/27/10   09/01/10   2,10,14,155,15,16        250,000       250,000  DDJ             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
10-0707   Reconstruction               0-008-012  09/28/11     DONE    DONE       DONE      01/03/11   12/24/10   10/05/10   10/06/10   2,155,15,16            1,040,000             0  DDJ             0           0           0 ECG Eninering, LLC              1,040,000        /  /             /  /        

          561 Bus Garage:
10-0708   Additions and Alterations    5-006-007  09/28/11     DONE    DONE       DONE      01/03/11   12/24/10   12/15/10   10/06/10   02 - 16                  320,000             0  DDJ             0           0           0 ECG Eninering, LLC                320,000        /  /             /  /        
  -    PR Additions and Alterations    5-006-008                                              /  /       /  /     12/28/10     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Transportation Facility:
  -    PR Additions and Alterations    5-015-002                                              /  /       /  /     11/06/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ONTEORA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-12-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
07-1199   Reconstruction               0-001-016  08/04/08     DONE    DONE       DONE      12/24/07   12/21/07   04/18/07   03/29/07   4,8,9,10,13,14,155,1   1,587,060     1,587,060  DDJ             0           0     321,010 KSQ Architects,P.Corp                   0        /  /           11/08/12      
08-1391   Reconstruction               0-001-017  03/18/09     DONE    DONE       DONE      03/18/09   03/18/09   01/09/09   12/02/08   2,15,16                  181,329       181,329  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        
08-1546   Reconstruction               0-001-018  07/06/09     DONE    DONE       DONE      04/27/09   04/21/09   01/12/09   05/20/08   2,7                    1,079,100     1,079,100  DDJ             0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        
  -    PR Additions and Alterations    0-001-019                                              /  /       /  /     06/04/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        
08-1707   Reconstruction               0-001-019  09/03/09     DONE    DONE       DONE      06/18/09   06/18/09   01/14/09   05/20/08   2,15,16                  171,000       171,000                  0           0           0 KSQ Architects,P.Corp                   0        /  /             /  /        
10-1174   Reconstruction               0-001-020  04/13/11     DONE    DONE       DONE      04/11/11   04/06/11   09/27/10   04/23/08   2,15,16                  150,000       150,000  DDJ             0           0           0 Clark Patterson Lee                     0        /  /             /  /        
10-1369   Reconstruction               0-001-021  08/03/11     DONE    DONE       DONE      06/06/11   06/02/11   04/14/11   05/17/11   16                       350,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
11-1449   Reconstruction               0-001-022  07/03/12     DONE    DONE       DONE      06/29/12   06/25/12   06/11/12   05/17/11   2                        247,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
12-0496   Reconstruction               0-001-023  02/13/13     DONE    DONE       DONE      11/29/12   11/28/12   08/29/12   08/07/12   16                       450,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Reginald R Bennett School:
  -       Additions and Alterations    0-002-010                                              /  /       /  /     05/02/12     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        
12-0494   Additions and Alterations    0-002-010  04/03/13     DONE    DONE       DONE      11/28/12   11/28/12   05/02/12   06/12/12   02 - 16                   17,318             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
11-1450   Reconstruction               0-002-011  07/03/12     DONE    DONE       DONE      06/29/12   06/25/12   06/11/12   05/17/11   2                         14,300             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Woodstock Elementary:
  -    XX Additions and Alterations    0-009-011                         CANCELLED            /  /       /  /     12/08/09     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        
11-1451   Reconstruction               0-009-012  07/03/12     DONE    DONE       DONE      06/29/12   06/25/12   06/12/12   05/17/11   2                         14,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        

          West Hurley #2:
11-1452   Reconstruction               0-010-009  07/03/12     DONE    DONE       DONE      06/29/12   06/25/12   06/12/12   05/17/11   2                         14,300             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Phoenicia Elementary:
11-1453   Reconstruction               0-011-011  07/03/12     DONE    DONE       DONE      06/29/12   06/25/12   06/12/12   05/17/11   2                         14,300             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Bus Garage:
10-1370   Reconstruction               5-004-007  08/03/11     DONE    DONE       DONE      06/06/11   06/02/11   04/14/11   05/17/11   16                        50,000             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
10-1443   Reconstruction               5-004-008  07/21/11     DONE    DONE       DONE      06/30/11   06/29/11   05/20/11   05/17/11   155,16                   150,000       150,000  DDJ             0           0           0 Mosaic Associates                       0        /  /           12/13/12      
11-1454   Reconstruction               5-004-009  07/03/12     DONE    DONE       DONE      06/29/12   06/25/12   06/12/12   05/17/11   2                         14,300             0  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SAUGERTIES CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-16-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cahill Elementary School:
12-0329   Reconstruction               0-005-016  03/04/13     DONE    DONE       DONE      10/25/12   10/25/12   11/18/11   12/13/11   7                        300,000       300,000  DDJ             0           0           0 Mosaic Associates                       0        /  /           03/18/13      

          Mt Marion Elementary:
11-0244   Reconstruction               0-008-012  11/07/11     DONE    DONE       DONE      10/07/11   10/07/11   02/03/10   01/28/10   2,15                      65,000        65,000  DDJ             0           0           0 Praetorius and Conrad PC                0        /  /             /  /        

          Grant D Morse Elem. School:
11-0228   Reconstruction               0-010-009  01/28/10     DONE    DONE       DONE      09/30/11   09/30/11   02/03/10   01/28/10   2,15                      65,000        65,000  DDJ             0           0           0 Praetorius & Conrad, P.C.               0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WALLKILL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-18-01-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Leptondale Elementary:
09-0414   Reconstruction               0-001-015  02/19/10     DONE    DONE       DONE      11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16      880,285       880,285  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /             /  /        

          John G. Borden Middle(fmly Wallkill):
09-0415   Reconstruction               0-002-009  02/19/10     DONE    DONE       DONE      11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16      524,883       524,883  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /             /  /        
11-0754   Reconstruction               0-002-010  03/30/12     DONE    DONE       DONE      02/03/12   02/02/12   10/26/11   02/27/07   2                        235,550       235,550  DDJ             0           0           0 Gardiner Engineering                    0        /  /             /  /        

          Ostrander Elementary:
09-0416   Reconstruction               0-003-010  02/19/10     DONE    DONE       DONE      11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16      884,969       884,969  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /             /  /        

          Plattekill Elementary:
09-0417   Reconstruction               0-005-011  02/19/10     DONE    DONE       DONE      11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16      899,990       899,990  DDJ             0           0           0 TEtra Tech Engineers, Archite           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELLENVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-20-02-06
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 5-12:
08-0002   Reconstruction               0-001-020  07/14/08     DONE    DONE       DONE      07/11/08   07/07/08   05/14/08   05/22/08   155,16                   341,376       341,376  DDJ             0           0           0 Dodge Chamberlin Luzine Weber           0        /  /             /  /        
09-1461   Reconstruction               0-001-021  02/08/11     DONE    DONE       DONE      05/20/10   05/18/10   02/05/10   05/19/09   2,8,10,15                520,757       520,757  DDJ             0           0           0 Mosaic Associates                       0        /  /           08/17/12      

          ES K-4:
08-1654   Reconstruction               0-008-005  06/26/09     DONE    DONE       DONE      06/01/09   05/20/09   03/26/09   05/13/08   2,9                       56,599        56,599  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
09-1462   Reconstruction               0-008-006  02/08/11     DONE    DONE       DONE      05/20/10   05/18/10   02/05/10   05/19/09   2,8                      232,788       232,788  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
11-1267   Reconstruction               0-008-007  05/23/12     DONE    DONE       DONE      05/07/12   04/27/12   03/21/12   05/27/11   2,9                      350,000       350,000  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Sports Equipment Storage Building:
09-1463   New Construction             2-013-001  02/08/11     DONE    DONE       DONE      05/20/10   05/18/10   02/05/10   05/19/09   02 - 16                  169,080             0  DDJ             0           0           0 Mosaic Associates                       0        /  /           08/17/12      

          Buildings and Grounds Storage Build:
09-1464   New Construction             2-014-001  02/08/11     DONE    DONE       DONE      05/20/10   05/18/10   02/05/10   05/19/09   02 - 16                  177,376             0  DDJ             0           0           0 Mosaic Associates                       0        /  /           08/17/12      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ULSTER STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-90-00-00
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Port Ewen Ed Center (Votec):
08-1422   Reconstruction               0-014-014  04/13/09     DONE    DONE       DONE      03/24/09   03/20/09   01/21/09   05/11/08   7                        241,188       241,188  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        
08-1421   Reconstruction               0-014-015  04/21/09     DONE    DONE       DONE      03/24/09   03/20/09   01/26/09   05/11/08   4,8,9                    172,216       172,216  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        
10-0434   Reconstruction               0-014-016  02/28/11     DONE    DONE       DONE      11/05/10   11/02/10   06/04/09   05/18/10   4,8,9,10,155,15,16     1,619,905     1,619,905  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        
09-0390   Reconstruction               0-014-017  12/16/09     DONE    DONE       DONE      11/05/09   11/04/09   09/04/09   05/19/08   4,9,155                  221,609       221,609  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        
12-1079   Reconstruction               0-014-018                         UNREVIEWED         04/05/13   04/05/13   11/02/12   05/15/12   10,15,16                       0     7,884,400  MFS             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Instructional Center:
12-0894   Reconstruction               1-002-003  05/23/13     DONE    DONE       DONE      02/21/13   02/20/13   04/02/12   05/17/12   10,16                          0             0  MFS             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Administration Building:
11-1131   Reconstruction               1-003-012  04/20/12     DONE    DONE       DONE      04/12/12   04/12/12   10/27/11   05/17/11   7                        220,969             0  MFS             0           0           0 Mosaic Associates                       0        /  /             /  /        
12-0895   Reconstruction               1-003-013  05/23/13     DONE    DONE       DONE      02/21/13   02/20/13   04/02/12   05/17/12   10,16                          0             0  MFS             0           0           0 Mosaic Associates                       0        /  /             /  /        

          1 DuBois Dr, New Paltz:
12-0592TQ Temporary Quarters           1-040-001                         UNREVIEWED         12/24/12   12/18/12   12/04/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /             /  /        

          District-Wide Project:
08-1131   Reconstruction               7-999-002  03/16/09     DONE    DONE       DONE      01/27/09   01/23/09   12/04/08   05/20/08   16                       356,904             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Edgewater Additional Square footage:
11-0070TQ Temporary Quarters           8-028-002  08/09/11     DONE    DONE       DONE      07/27/11   07/27/11   12/10/10     /  /                                    0             0  JOD             0           0           0                                         0        /  /             /  /        

          Ulster Technology Learning Center:
10-1019   Reconstruction               8-038-001  01/30/12     DONE    DONE       DONE      03/09/11   03/08/11   10/25/10     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Lenape Elem School (Leased Space):
12-0067   Reconstruction               8-039-001  11/21/12     DONE    DONE       DONE      07/31/12   07/12/12   05/29/12     /  /     4,8,9,155,15,16          600,000             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        

          The Seven21 Media Center:
  -    TQ Temporary Quarters           8-041-001                                              /  /       /  /     12/04/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED