Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 08/21/17 at 09:22:35




KINGSTON CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-06-00-01
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          John F. Kennedy Elem School:
12-0619   Reconstruction               0-003-009  03/06/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,7                    1,102,000     1,102,000  DDJ             0           0           0 KSQ ARCHITECTS PC                       0      08/16/13                       02/21/14           
12-0641   Reconstruction               0-003-010  03/26/13     DONE    DONE       DONE      01/07/13   01/03/13   12/28/12   12/15/12   155,15,16                348,000       348,000  DDJ             0           0           0 KSQ ARCHITECTS PC                       0      09/05/13                       02/21/14           

          George Washington School:
13-1224   Reconstruction               0-004-011  11/14/14     DONE    DONE       DONE      02/12/14   02/12/14   01/24/14   05/21/13   2,4,8,9,10,155,15,16   2,908,289     2,908,289  JMB             0           0           0 Kaeyer, Garment & Davidson              0      09/04/15                       09/15/15           

          Kingston High School:
13-0974   Additions and Alterations    0-006-019  04/08/14     DONE    DONE       DONE      12/31/13   12/24/13   10/12/11   05/21/13   02 - 16                  950,000       950,000  JOD             0           0           0 KSQ ARCHITECTS PC                       0      09/22/14                       06/15/15           
14-1060   Additions and Alterations    0-006-020  06/01/16     DONE    DONE       DONE      02/03/15   02/03/15   10/18/11   12/10/13   02 - 16               79,375,000    79,375,000  JOD             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
14-1580SR Additions and Alterations    0-006-020  06/24/15     DONE    DONE       DONE      06/05/15   05/26/15   10/18/11   12/10/13   02 - 16                        0             0  JOD             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
14-1524   Reconstruction               0-006-022  06/12/15     DONE    DONE       DONE      05/14/15   05/13/15   03/24/15   12/10/13   2,9,155,15,16            326,931       326,931  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/27/15                       03/07/16           
15-0368   Reconstruction               0-006-023  07/11/16     DONE    DONE       DONE      08/28/15   08/28/15   03/24/15   12/10/13   2,155                  2,770,240     2,770,240  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
15-1410   Reconstruction               0-006-024  03/11/16     DONE    DONE       DONE      03/10/16   03/10/16   01/15/16   12/10/13   2                        399,756       399,756  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
  -       Reconstruction               0-006-025                                              /  /       /  /     06/20/17     /  /     2,4,8,9,10,14,155,15           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Kate Walton Field House:
14-0214   Additions and Alterations    0-008-013  05/06/15     DONE    DONE       DONE      08/22/14   08/19/14   10/12/11   12/10/13   02 - 16               14,100,000    14,100,000  JOD             0           0           0 KSQ ARCHITECTS PC                       0      08/26/16           YES           /  /             

          Chambers Elementary School:
13-1117SR Reconstruction               0-009-012  04/25/14     DONE    DONE       DONE      01/28/14   01/27/14   01/07/14   05/21/13   2,4,9,10,155,15,16             0     8,623,490  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             
13-1225   Reconstruction               0-009-012  11/14/14     DONE    DONE       DONE      02/12/14   02/12/14   01/07/14   05/21/13   2,4,9,10,155,15,16       702,000       702,000  JMB             0           0           0 Kaeyer, Garment & Davidson              0      09/04/15                       09/15/15           

          Ernest C. Myer Elementary:
13-0975   Reconstruction               0-013-009  04/09/14     DONE    DONE       DONE      12/31/13   12/24/13   12/12/13   05/21/13   7                        200,000       200,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      09/22/15                       06/15/15           
13-1226   Reconstruction               0-013-010  11/14/14     DONE    DONE       DONE      02/12/14   02/12/14   01/07/14   05/21/13   2,9,10,155,15,16         738,000       738,000  JMB             0           0           0 Kaeyer, Garment & Davidson              0      09/04/15                       09/15/15           
13-1118   Reconstruction               0-013-011  04/25/14     DONE    DONE       DONE      01/28/14   01/27/14   01/27/14   05/21/13   2,9                       45,000        45,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      09/09/14                       06/15/15           
  -       Reconstruction               0-013-012                                              /  /       /  /     07/03/14     /  /     15                             0     5,806,530  JMB             0           0           0                                         0        /  /                           /  /             

          Robert Graves Elem. School:
15-0989   Reconstruction               0-016-008  12/11/16     DONE    DONE       DONE      12/30/15   12/23/15   02/06/15   05/21/13   2,4,8,9,155,15,16        100,000       100,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0        /  /                           /  /             

          J. Watson Bailey Middle School:
12-0615   Reconstruction               0-026-012  03/21/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,16                     250,000       250,000  DDJ             0           0           0 KSQ ARCHITECTS PC                       0      08/30/13                       02/21/14           
13-1119   Reconstruction               0-026-013  04/25/14     DONE    DONE       DONE      01/28/14   01/27/14   11/27/13   05/21/13   2,9                       65,000        65,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/22/14                       06/15/15           
15-0934   Reconstruction               0-026-014  02/24/16     DONE    DONE       DONE      12/22/15   12/22/15   02/18/15   05/21/13   9,10                     100,000       100,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      06/29/16                       08/30/16           

          Harry L. Edson Elem. School:
12-0620   Reconstruction               0-027-007  03/06/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,7                    1,143,760     1,143,760  DDJ             0           0           0 KSQ ARCHITECTS PC                       0      08/30/13                       02/21/14           
13-1120   Reconstruction               0-027-008  04/25/14     DONE    DONE       DONE      01/28/14   01/27/14   01/27/14   05/21/13   2,4                       60,000        60,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/04/14                       04/01/15           

          M. Clifford Miller Middle School:
12-0621   Reconstruction               0-028-011  03/06/13     DONE    DONE       DONE      12/26/12   12/19/12   09/19/12   05/15/12   2,7                    4,234,000     4,234,000  DDJ             0           0           0 KSQ ARCHITECTS PC                       0      08/30/13                       02/21/14           
13-1227   Reconstruction               0-028-012  11/14/14     DONE    DONE       DONE      02/12/14   02/12/12   01/07/14   05/21/13   2,155,15,16              570,000       570,000  JMB             0           0           0 Kaeyer, Garment & Davidson              0      09/04/15                       09/15/15           
13-1121   Reconstruction               0-028-013  04/25/14     DONE    DONE       DONE      01/23/14   01/22/14   01/27/14   05/21/13   2,9                      950,000       950,000  JMB             0           0           0 KSQ ARCHITECTS PC                       0      08/25/14                       04/01/15           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HIGHLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-08-03-04
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
12-1051   Reconstruction               0-001-005  03/06/14     DONE    DONE       DONE      04/02/13   03/26/13   01/08/13   12/18/12   2,155,15,16              454,811       454,811  DDJ             0           0           0 ECG Engineering, LLC              454,811      04/30/15                       06/01/15           
15-0148   Reconstruction               0-001-006  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   2,4,8,9,10,13,14,155   2,563,532     2,563,532  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
15-0149   Reconstruction               0-001-007  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   7                        301,423       301,423  DDJ             0           0           0 Ashley McGraw                           0        /  /                           /  /             
15-0165   Reconstruction               0-001-008  12/31/15     DONE    DONE       DONE      07/27/15   07/20/15   06/08/15   10/28/14   2,4,8,9                2,886,235     2,886,235  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Junior/Senior High School:
12-1052   Reconstruction               0-009-009  03/06/14     DONE    DONE       DONE      04/02/13   03/26/13   01/08/13   12/18/12   2,155,15,16              598,838       598,838  DDJ             0           0           0 ECG Engineering, LLC              598,838      04/30/15                       06/01/15           
15-0150   Reconstruction               0-009-010  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   2,4,8,9,10,13,14,155   4,124,744     4,124,744  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
15-0151   Reconstruction               0-009-011  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   7                        803,155       803,155  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
15-0166   Reconstruction               0-009-012  12/31/15     DONE    DONE       DONE      07/27/15   07/20/15   06/08/15   10/28/14   2,4,8,9                1,357,886     1,357,886  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Elementary School:
12-1053   Reconstruction               0-010-009  03/06/14     DONE    DONE       DONE      04/02/13   03/26/13   01/08/13   12/18/12   2,155,15,16              566,953       566,953  DDJ             0           0           0 ECG Engineering, LLC              566,953      04/30/15                       06/01/15           
15-0152   Reconstruction               0-010-010  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   2,4,8,9,10,13,14,155   2,656,914     2,656,914  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
15-0153   Reconstruction               0-010-011  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   7                        542,689       542,689  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
15-0167   Reconstruction               0-010-012  12/31/15     DONE    DONE       DONE      07/27/15   07/20/15   06/05/15   10/28/14   2,4,8,9                  823,807       823,807  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Athletic Storage Building @ HS:
15-1500DB Discovered Building          2-016-001  01/17/17     DONE    DONE       DONE      03/28/16   03/24/16   06/23/15     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Additions and Alterations    2-016-002                                              /  /       /  /     10/02/15     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
12-1054   Reconstruction               5-002-006  03/06/14     DONE    DONE       DONE      04/02/13   03/26/13   01/09/13   12/18/12   155,16                    18,969        18,969  DDJ             0           0           0 ECG Engineering, LLC               18,969      04/30/15                       06/01/15           
15-0154   Reconstruction               5-002-007  06/29/16     DONE    DONE       DONE      07/24/15   07/22/15   12/12/14   10/28/14   2,4,8,9,10,13,14,155     404,038       404,038  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             
  -       Reconstruction               5-002-008                                              /  /       /  /     12/12/14     /  /     7                              0             0  DDJ             0           0           0                                         0        /  /                           /  /             
15-0168   Reconstruction               5-002-009  12/31/15     DONE    DONE       DONE      07/27/15   07/20/15   06/08/15   10/28/14   2,7,9                    983,216       983,216  DDJ             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Highland Public Library:
15-0503   New Construction             6-015-001  06/16/16     DONE    DONE       DONE      09/25/15   09/25/15   06/09/15   03/17/15   02 - 16                4,855,433             0  DDJ             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RONDOUT VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-09-01-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Rondout Valley High:
  -       Reconstruction               0-002-009                                              /  /       /  /     11/13/13     /  /     13,16                          0    26,257,936  JMB             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-010                                              /  /       /  /       /  /       /  /     10,16                          0    26,257,936  MTM             0           0           0                                         0        /  /                           /  /             
16-1186SB Reconstruction               0-002-010               DONE                           /  /       /  /     01/14/17     /  /     10,16                          0    26,257,936  MTM             0           0           0                                         0        /  /                           /  /             

          Kerhonkson Elementary:
  -       Reconstruction               0-006-007                                              /  /       /  /     07/18/17     /  /     8,9,16                         0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Middle School:
15-1494   Reconstruction               0-007-012  01/03/17     DONE    DONE       DONE      03/28/16   03/25/16   07/29/14   05/10/16   155,15,16                279,589       279,589  JMB             0           0           0 AlFandre Architecture                   0        /  /                           /  /             

          NEW ADMINISTRATION BLDG.:
14-0534   Reconstruction               1-017-003  07/03/15     DONE    DONE       DONE      10/23/14   10/23/14   11/13/13   03/31/14   16                        60,000             0  JMB             0           0           0 AlFandre Architecture                   0        /  /                           /  /             
16-0532   Reconstruction               1-017-003                         UNREVIEWED         10/23/14   10/23/14   11/13/13   03/31/14   16                        60,000             0  MTM             0           0           0 AlFandre Architecture                   0        /  /                           /  /             

          Greenhouse:
14-0716   New Construction             7-020-001  03/09/15     DONE    DONE       DONE      12/04/14   12/04/14   07/30/14   07/11/14   02 - 16                  297,810             0  JMB             0           0           0 AlFandre Architecture                   0      01/28/16                       02/16/16           

          District-Wide:
  -       Reconstruction               7-999-004                                              /  /       /  /       /  /       /  /     13,16                          0             0  AAA             0           0           0                                         0        /  /                           /  /             
16-0016SB Reconstruction               7-999-004                                              /  /       /  /     07/05/16     /  /     13,16                          0             0  AAA             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  AAA             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARLBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-10-01-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
12-0595   Reconstruction               0-001-008  11/22/13     DONE    DONE       DONE      12/24/12   12/13/12   08/07/12   05/15/12   2,10                   3,385,000     3,385,000  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
  -       Reconstruction               0-001-009                                              /  /       /  /     11/19/12     /  /     2,10                           0    11,063,798  JMB             0           0           0                                         0        /  /                           /  /             
15-1558SB Reconstruction               0-001-010               DONE                           /  /       /  /     04/12/16     /  /     13,16                          0    11,063,798  JMB             0           0           0                                         0        /  /                           /  /             
17-0189   Reconstruction               0-001-010                         UNREVIEWED         08/09/17   08/09/17     /  /     05/17/16   13,16                          0    11,063,798  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             

          Middle Hope ES:
  -       Reconstruction               0-003-004                                              /  /       /  /     12/23/16     /  /     13,16                          0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEW PALTZ CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-11-01-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
13-0136   Reconstruction               0-001-014  10/31/13     DONE    DONE       DONE      08/06/13   08/02/13   07/17/13   05/21/13   2,15,16                  176,290       176,290  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
13-0720   Reconstruction               0-001-015  06/01/15     DONE    DONE       DONE      11/19/13   11/15/13   07/17/13   05/21/13   4,7,8                    238,825       238,825  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
15-0857   Reconstruction               0-001-016  01/04/16     DONE    DONE       DONE      12/08/15   12/07/15   01/22/15   03/24/15   2,4,7                  1,397,160     1,397,160  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
15-1035   Reconstruction               0-001-017  01/17/17     DONE    DONE       DONE      01/11/16   01/07/16   04/15/15   01/27/15   2,7                   34,997,560    13,593,650  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
  -    PR Additions and Alterations    0-001-018                                              /  /       /  /     12/11/15     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Duzine Elementary School:
13-0721   Reconstruction               0-004-013  06/01/15     DONE    DONE       DONE      11/19/13   11/15/13   07/17/13   05/21/13   16                        15,930        15,930  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
14-1561   Reconstruction               0-004-014  08/06/15     DONE    DONE       DONE      05/27/15   05/18/15   01/22/15   03/24/15   2,4,7                    918,600       918,600  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
15-0851   Reconstruction               0-004-015  08/01/16     DONE    DONE       DONE      12/09/15   12/07/15   04/15/15   03/24/15   4,8,9,155,15,16        1,128,770     1,128,770  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             

          High School:
13-0722   Reconstruction               0-005-019  06/01/15     DONE    DONE       DONE      11/19/13   11/15/13   07/17/13   05/21/13   16                        39,805        39,805  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
14-1522   Reconstruction               0-005-020  06/02/15     DONE    DONE       DONE      05/14/15   05/13/15   01/22/15   03/24/15   10                       157,000       157,000  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
15-1062   Reconstruction               0-005-021  02/09/16     DONE    DONE       DONE      01/20/16   01/16/16   04/15/15   03/24/15   2,7                    3,735,000     3,735,000  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
  -    PR Additions and Alterations    0-005-022                                              /  /       /  /     12/02/15     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1026   Additions and Alterations    0-005-022  10/31/16     DONE    DONE       DONE      01/06/15   01/05/15   12/02/15   03/24/15   02 - 16                4,924,590             0  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
  -    KS Reconstruction               0-005-023                                              /  /       /  /     04/20/16     /  /     2,13,16                        0    16,744,305  JMB             0           0           0                                         0        /  /                           /  /             

          Lenape Elementary School:
13-0137   Reconstruction               0-008-013  10/31/13     DONE    DONE       DONE      08/06/13   08/02/13   07/17/13   05/21/13   8                         21,560        21,560  JMB             0           0           0 Kaeyer, Garment & Davidson              0        /  /                           /  /             
14-1523   Reconstruction               0-008-014  06/02/15     DONE    DONE       DONE      05/14/15   05/13/15   01/22/15   03/24/15   10                       100,000       100,000  JMB             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
15-0852   Reconstruction               0-008-015  08/01/16     DONE    DONE       DONE      12/09/15   12/07/15   04/15/15   03/24/15   4,8,9,155,15,16          714,270       714,270  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
  -    KS Reconstruction               0-008-016                                              /  /       /  /     04/20/16     /  /     2,13,16                        0    15,743,790  JMB             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
15-0542   Reconstruction               5-006-009  10/28/15     DONE    DONE       DONE      10/07/15   10/05/15   09/03/15   03/24/15   2,15                     200,000       200,000  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             
16-0327   Additions and Alterations    5-006-010                       ADDENDUM REQ'D       08/30/16   08/29/16   01/20/16   03/24/15   02 - 16                        0             0  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             

          District-Wide:
15-1027   Reconstruction               7-999-003  06/22/16     DONE    DONE       DONE      01/06/16   01/05/16   11/20/15   06/24/15   16                     2,019,355             0  JMB             0           0           0 Tetra Tech Architects & Engin           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ONTEORA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-12-01-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
12-0496   Reconstruction               0-001-023  08/19/12     DONE    DONE       DONE      11/29/12   11/28/12   08/29/12   08/07/12   16                       450,000       450,000  DDJ             0           0           0 Mosaic Associates                       0      07/05/13                       07/17/13           
13-0491   Reconstruction               0-001-024  03/14/14     DONE    DONE       DONE      10/09/13   09/27/13   06/18/13   05/21/13   2                        115,000       115,000  JMB             0           0           0 Mosaic Associates                       0      09/03/15                       02/10/16           
13-1347   Reconstruction               0-001-025  05/21/14     DONE    DONE       DONE      03/18/14   03/12/14   01/21/14   05/20/08   4                        508,000       508,000  JMB             0           0           0 Mosaic Associates                       0      08/28/15                       01/28/16           
14-0349   Reconstruction               0-001-026  06/30/15     DONE    DONE       DONE      09/25/14   09/22/14   06/19/14   05/20/14   2,8,9,155,15           6,035,534     6,035,534  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
14-0914   Reconstruction               0-001-027  06/08/16     DONE    DONE       DONE      12/31/14   12/23/14   10/27/14   08/19/14   8,155,15,16              998,572       998,572  JMB             0           0           0 Mosaic Associates                 998,572        /  /                           /  /             
  -       Reconstruction               0-001-028                                              /  /       /  /     03/15/17     /  /     2                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             
16-1608SR Reconstruction               0-001-028  07/03/17     DONE    DONE       DONE      04/03/17   04/03/17   03/15/17   05/16/17                             40,000             0  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          Reginald R Bennett School:
12-0494   Additions and Alterations    0-002-010  04/03/13     DONE    DONE       DONE      11/28/12   11/28/12   05/02/12   06/12/12   02 - 16                   17,318        17,318  DDJ             0           0           0 Mosaic Associates                       0      08/15/13                       06/16/16           
13-1348   Reconstruction               0-002-012  05/21/14     DONE    DONE       DONE      03/18/14   03/12/14   01/21/14   05/20/08   4                         69,440        69,440  JMB             0           0           0 Mosaic Associates                       0      08/28/15                       01/28/16           
14-0915   Reconstruction               0-002-013  06/08/16     DONE    DONE       DONE      12/31/14   12/23/14   10/27/14   08/19/14   155,15,16                226,913       226,913  JMB             0           0           0 Mosaic Associates                 226,913        /  /                           /  /             
16-1064   Reconstruction               0-002-014  03/13/17     DONE    DONE       DONE      12/27/16   12/23/16   06/16/16   05/17/16   2                        550,000             0  BMJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             

          Woodstock Elementary:
13-0492   Reconstruction               0-009-013  03/14/14     DONE    DONE       DONE      10/09/13   09/27/13   06/18/13   05/21/13   2,4,9,16                 875,000       875,000  JMB             0           0           0 Mosaic Associates                       0      09/03/15                       02/10/16           
13-1349   Reconstruction               0-009-014  05/21/14     DONE    DONE       DONE      03/18/14   03/12/14   01/21/14   05/20/08   4                        165,000       165,000  JMB             0           0           0 Mosaic Associates                       0      08/28/15                       01/28/16           
14-0916   Reconstruction               0-009-015  06/08/16     DONE    DONE       DONE      12/31/14   12/23/14   10/27/14   08/19/14   8,155,15,16            1,150,900     1,150,900  JMB             0           0           0 Mosaic Associates               1,150,900        /  /                           /  /             

          Phoenicia Elementary:
13-0493   Reconstruction               0-011-012  03/14/14     DONE    DONE       DONE      10/09/13   09/27/13   06/18/13   05/21/13   2,4,9,16                 190,000       190,000  JMB             0           0           0 Mosaic Associates                       0      09/03/15                       02/10/16           
13-1350   Reconstruction               0-011-013  05/21/14     DONE    DONE       DONE      03/18/14   03/12/14   01/21/14   05/20/08   4                        224,000       224,000  JMB             0           0           0 Mosaic Associates                       0      08/28/15                       01/28/16           
14-0350   Reconstruction               0-011-014  06/30/15     DONE    DONE       DONE      09/25/14   09/22/14   06/19/14   05/20/14   155                      701,933       701,933  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
14-0917   Reconstruction               0-011-015  06/08/16     DONE    DONE       DONE      12/31/14   12/23/14   10/27/14   08/19/14   8,155,15,16              372,578       372,578  JMB             0           0           0 Mosaic Associates                 372,578        /  /                           /  /             
  -       Reconstruction               0-011-016                                              /  /       /  /     07/25/17     /  /     2,7,8,9,155,15,16              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
14-0351   Reconstruction               5-004-010  06/30/15     DONE    DONE       DONE      09/25/14   09/22/14   06/19/14   05/20/14   7                        262,533       262,533  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             
14-0918   Reconstruction               5-004-011  06/08/16     DONE    DONE       DONE      12/31/14   12/23/14   10/27/14   08/19/14   8,155,15,16               57,004        57,004  JMB             0           0           0 Mosaic Associates                  57,004        /  /                           /  /             

          Biomass Boiler Container:
15-0406   New Construction             7-020-001  09/03/15     DONE    DONE       DONE      09/03/15   09/01/15   07/17/15   05/20/14   02 - 16                   28,000             0  JMB             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /     01/12/16     /  /     16                             0             0  JMB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SAUGERTIES CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-16-01-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Riccardi School (F'mlyGlasco):
15-0064   Reconstruction               0-004-006  07/23/15     DONE    DONE       DONE      07/15/15   07/09/15   06/29/15   06/09/15   2,7                      656,037       656,037  MFS             0           0           0 Mosaic Associates                       0      12/02/15                       12/14/15           
  -       Reconstruction               0-004-007                                              /  /       /  /     03/22/17     /  /     2,9                            0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Cahill Elementary School:
12-0329   Reconstruction               0-005-016  12/13/11     DONE    DONE       DONE      10/25/12   10/25/12   11/18/11   12/13/11   7                        300,000       300,000  DDJ             0           0           0 Mosaic Associates                       0      03/12/13                       03/18/13           
13-1690   Reconstruction               0-005-017  07/25/14     DONE    DONE       DONE      07/02/14   06/30/14   07/08/13   06/24/14   155                      494,000       494,000  MFS             0           0           0 Mosaic Associates                       0      12/12/14                       12/12/14           

          Mt Marion Elementary:
  -       Reconstruction               0-008-013                                              /  /       /  /     09/21/15     /  /     2,9,15                         0     8,768,250  MFS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-014                                              /  /       /  /     03/22/17     /  /     155,16                         0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Jr/Sr High School:
13-1490   Reconstruction               0-009-015  06/12/14     DONE    DONE       DONE      04/28/14   04/25/14   04/09/14   05/20/14   2,9                      100,000       100,000  MFS             0           0           0 Mosaic Associates                       0      08/21/14                       09/18/14           
15-1568   Reconstruction               0-009-017  04/25/16     DONE    DONE       DONE      04/15/16   04/14/16   01/27/16   03/08/16   2,9                      100,000       100,000  MFS             0           0           0 Mosaic Associates                       0      08/12/16                       11/04/16           
16-0794   Reconstruction               0-009-018  02/18/17     DONE    DONE       DONE      11/15/16   11/15/16   11/01/16   11/08/16   2,9                      100,000       100,000  BMJ             0           0           0 Mosaic Associates                       0        /  /                           /  /             

          Greenhouse:
  -       New Construction             7-013-001                                              /  /       /  /     05/24/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1                                              /  /       /  /       /  /       /  /     8,155,16                       0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               7-999-BA2                                              /  /       /  /       /  /       /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WALLKILL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-18-01-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Leptondale Elementary:
13-0237   Reconstruction               0-001-016  03/27/14     DONE    DONE       DONE      08/19/13   08/15/13   07/03/13   07/24/13   2,155,15,16              628,653       628,653  MFS             0           0           0 ECG Engineering, LLC              628,653      04/14/15                       05/18/15           
14-1658   Reconstruction               0-001-017  10/26/15     DONE    DONE       DONE      06/12/15   06/11/15   02/20/15   02/03/15   2,8,15,16                457,557       457,557  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1536   Reconstruction               0-001-018  07/26/17     DONE    DONE       DONE      03/22/17   03/22/17   01/31/17   02/03/15   8                         39,110             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          John G. Borden Middle(fmly Wallkill):
13-0238   Reconstruction               0-002-011  03/27/14     DONE    DONE       DONE      08/19/13   08/15/13   07/03/13   07/24/13   2,155,15,16              610,391       610,391  MFS             0           0           0 ECG Engineering, LLC              610,391      04/14/15                       05/18/15           
14-1659   Reconstruction               0-002-012  10/26/15     DONE    DONE       DONE      06/12/15   06/11/15   02/23/15   02/03/15   2,8,13,15,16             476,581       476,581  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1537   Reconstruction               0-002-013  07/26/17     DONE    DONE       DONE      03/22/17   03/22/17   01/31/17   02/03/15   8                         69,537             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Ostrander Elementary:
13-0239   Reconstruction               0-003-011  03/27/14     DONE    DONE       DONE      08/19/13   08/15/13   07/03/13   07/24/13   2,155,15,16              702,567       702,567  MFS             0           0           0 ECG Engineering, LLC              702,567      04/14/15                       05/18/15           
14-1660   Reconstruction               0-003-012  10/26/15     DONE    DONE       DONE      06/12/15   06/11/15   02/23/15   02/03/15   2,8,15,16                470,982       470,982  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1538   Reconstruction               0-003-013  07/26/17     DONE    DONE       DONE      03/22/17   03/22/17   01/31/17   02/03/15   8                         39,110             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Plattekill Elementary:
13-0240   Reconstruction               0-005-012  03/27/14     DONE    DONE       DONE      08/19/13   08/15/13   07/03/13   07/24/13   2,15,16                1,135,367     1,135,367  MFS             0           0           0 ECG Engineering, LLC            1,135,367      04/14/15                       05/18/15           
14-1661   Reconstruction               0-005-013  10/26/15     DONE    DONE       DONE      06/12/15   06/11/15   02/23/15   02/03/15   2,8,15,16                467,591       467,591  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1539   Reconstruction               0-005-014  07/26/17     DONE    DONE       DONE      03/22/17   03/22/17   01/31/17   02/03/15   8                         39,110             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Wallkill High School:
13-0241   Reconstruction               0-007-015  03/27/14     DONE    DONE       DONE      08/19/13   08/15/13   07/03/13   07/24/13   2,155,15,16            3,116,994     3,116,994  MFS             0           0           0 ECG Engineering, LLC            3,116,994      04/14/15                       05/18/15           
14-1662   Reconstruction               0-007-016  10/26/15     DONE    DONE       DONE      06/12/15   06/11/15   02/23/15   02/03/15   2,8,13,15,16           6,325,805     6,325,805  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             
16-1540   Reconstruction               0-007-017  07/26/17     DONE    DONE       DONE      03/22/17   03/22/17   01/31/17   02/03/15   2,8,13,16                637,364             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Administration Bldg.:
13-0242   Reconstruction               1-004-002  03/27/14     DONE    DONE       DONE      08/19/13   08/19/13   07/03/13   07/24/13   2,155,16                   9,978             0  MFS             0           0           0 ECG Engineering, LLC                9,978      04/14/15                       05/18/15           
14-1663   Reconstruction               1-004-003  10/26/15     DONE    DONE       DONE      06/12/15   06/11/15   02/24/15   02/03/15   16                        10,824             0  MFS             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          Maintenance Storage Building:
  -    DB Discovered Building          2-027-001                                              /  /       /  /     01/22/16     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Technology Storage Building:
  -    DB Discovered Building          2-028-001                                              /  /       /  /     01/22/16     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Concession Bldg. @ Soccer Field:
  -       Reconstruction               7-026-002                                              /  /       /  /     07/03/13     /  /     16                             0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Press Box @ High School 2:
16-1442   New Construction             7-029-001               DONE    DONE       ADD. REQ'D02/27/17   02/27/17   01/30/17   05/18/16   02 - 16                        0             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          HS Bathroom Building:
17-0057   New Construction             7-030-001                         UNREVIEWED         07/13/17   07/13/17   05/15/17   02/03/15                                  0             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-003                                              /  /       /  /       /  /       /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             
15-1101SB Reconstruction               7-999-003                         UNREVIEWED         01/21/16   01/21/16   01/21/16     /  /     13,16                          0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELLENVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-20-02-06
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 5-12:
15-0302   Reconstruction               0-001-022  04/25/16     DONE    DONE       DONE      08/18/15   08/18/15   12/12/13   12/16/14   2,10,15                7,862,452     7,862,452  DDJ             0           0     746,040 Mosaic Associates                       0        /  /                           /  /             
  -       Reconstruction               0-001-023                                              /  /       /  /     05/25/17     /  /     2,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-024                                              /  /       /  /     05/31/17     /  /     2,16                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          ES K-4:
15-0303   Reconstruction               0-008-008  04/25/16     DONE    DONE       DONE      08/18/15   08/18/15   12/12/13   12/16/14   2,7,9,15               6,562,548     6,562,548  DDJ             0           0     610,397 Mosaic Associates                       0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ULSTER STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-90-00-00
last updated on 08/21/17
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Port Ewen Ed Center (Votec):
12-1079   Reconstruction               0-014-018  10/25/13     DONE    DONE       DONE      04/05/13   04/05/13   11/02/12   05/15/12   10,15,16                 204,243       204,243  MFS             0           0           0 Mosaic Associates                       0      08/22/14                       09/04/14           
14-0851   Reconstruction               0-014-019  01/23/15     DONE    DONE       DONE      12/29/14   12/19/14   05/14/14   05/08/14   2,4,7,8,155,15,16      1,354,001     1,354,001  MFS             0           0           0 Mosaic Associates                       0      08/28/15                       02/25/16           
16-1443   Reconstruction               0-014-020  04/03/17     DONE    DONE       DONE      02/27/17   02/27/17   06/15/15   02/22/17   7,9,155,15,16          1,700,000             0  MFS             0           0           0 LAN Associates                          0        /  /                           /  /             
  -       Reconstruction               0-014-021                                              /  /       /  /     05/30/17     /  /     155,15,16                      0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Instructional Center:
12-0894   Reconstruction               1-002-003  05/23/13     DONE    DONE       DONE      02/21/13   02/20/13   04/02/12   05/17/12   10,16                     13,258             0  MFS             0           0           0 Mosaic Associates                       0      04/01/14                       07/16/14           

          Administration Building:
12-0895   Reconstruction               1-003-013  05/23/13     DONE    DONE       DONE      02/21/13   02/20/13   04/02/12   05/17/12   10,16                    119,318             0  MFS             0           0           0 Mosaic Associates                       0      04/01/14                       07/16/14           

          1 DuBois Dr, New Paltz:
12-0592TQ Temporary Quarters           1-040-001                         UNREVIEWED         12/24/12   12/18/12   12/04/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Lenape Elem School (Leased Space):
12-0067   Reconstruction               8-039-001  11/21/12     DONE    DONE       DONE      07/31/12   07/12/12   05/29/12     /  /     4,8,9,155,15,16          599,840             0  JOD             0           0           0 Mosaic Associates                       0      06/01/13                       09/16/13           

          The Seven21 Media Center:
  -    TQ Temporary Quarters           8-041-001                                              /  /       /  /     12/04/12     /  /                                    0             0  JMB             0           0           0                                         0        /  /                           /  /             

          DiSanto Building @ Ellenville:
13-1390TQ Temporary Quarters           8-042-001  01/16/15     DONE    DONE       DONE      03/20/14   03/10/14   01/10/14     /  /                                    0             0  MFS             0           0           0                                         0        /  /                           /  /             

          SUNY Ulster Ext. Cntr. of Kingston:
16-0784TQ Temporary Quarters           8-043-001  02/14/17     DONE    DONE       DONE      11/15/16   11/15/16   11/15/16     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Richmor Aviation:
  -    TQ Temporary Quarters           8-044-001                                              /  /       /  /     05/30/17     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Anna Devine Elementary:
  -    TQ Temporary Quarters           8-045-001                                              /  /       /  /     06/22/17     /  /                                    0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED