Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/23/13 at 14:42:32




BOLTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-01-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bolton Central:
12-0670   Additions and Alterations    0-001-007  04/15/13     DONE    DONE       DONE      01/15/13   01/15/13   06/01/06   09/27/12   02 - 16                1,260,000             0  MGL             0           0      91,331 Bernier Carr Associates                 0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH WARREN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-02-02-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New K-12 Building:
08-1706   Reconstruction               0-014-003  07/13/09     DONE    DONE       DONE      06/18/09   06/05/09   01/09/09   11/19/07   2,15,16                  100,000       100,000  HCM             0           0           0 Griffith Dardanelli,Architect           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GLENS FALLS CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-03-00-01
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle/High School:
10-0513   Reconstruction               0-001-021  01/11/11     DONE    DONE       DONE      12/02/10   11/19/10   10/05/10   05/16/06   7                        300,000             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        
12-0526   Reconstruction               0-001-022               DONE    DONE       UNREVIEWED12/11/12   12/10/12   07/18/12   05/15/12   2,4,7,8,9,10,155,15,           0    41,076,027  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
  -       Reconstruction               0-001-023                                              /  /       /  /       /  /       /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-023                                              /  /       /  /     11/01/12     /  /     2,4,7,8,14,155,15              0             0  DDJ             0           0           0                                         0        /  /             /  /        
12-1176   Reconstruction               0-001-024               STARTED STARTED    DONE      05/10/13   05/08/13   04/17/13   05/15/12   2,7                            0             0  JOB             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Big Cross St. Elementary:
12-0527   Reconstruction               0-003-009               DONE    DONE       UNREVIEWED12/11/12   12/10/12   07/18/12   05/15/12   2,9,10,155,15,16               0     2,790,594  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        
  -       Reconstruction               0-003-010                                              /  /       /  /     11/01/12     /  /     9,15,16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        
07-2200SC Visual Structural Inspection 0-003-SC1  09/30/08     DONE    DONE       DONE      05/16/08   05/16/08     /  /       /  /     16                           326             0  JOD             0           0           0                                         0        /  /             /  /        

          Jackson Heights Elementary:
12-0528   Reconstruction               0-005-008               DONE    DONE       UNREVIEWED12/11/12   12/10/12   07/18/12   05/15/12   2,9,10,155,16                  0     4,021,380  DDJ             0           0           0 Mosaic Associates                       0        /  /             /  /        
  -       Reconstruction               0-005-009                                              /  /       /  /     11/01/12     /  /     7,8,155,15,16                  0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Kensington Road Elementary:
  -       Reconstruction               0-007-009                                              /  /       /  /     07/18/12     /  /     16                             0             0  JOD             0           0           0                                         0        /  /             /  /        
07-2199SC Visual Structural Inspection 0-007-SC1  09/30/08     DONE    DONE       DONE      05/16/08   05/16/08     /  /       /  /     16                         2,120             0  JOD             0           0           0                                         0        /  /             /  /        

          Administration Bldg:
  -       Reconstruction               1-008-004                                              /  /       /  /     07/18/12     /  /     16                             0             0  JOD             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               1-008-005                                              /  /       /  /     07/20/12     /  /     16                             0             0  JOD             0           0           0                                         0        /  /             /  /        

          Morse Storage Building:
09-0289DB Discovered Building          2-019-001  10/23/09     DONE    DONE       DONE      10/06/09   09/30/09   08/07/09     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        

          Bus Garage Warehouse:
  -       Reconstruction               5-009-003                                              /  /       /  /     07/18/12     /  /     16                             0             0  JOD             0           0           0                                         0        /  /             /  /        

          Morse Field House:
09-0290DB Discovered Building          7-018-001  10/23/09     DONE    DONE       DONE      10/06/09   09/30/09   08/07/09     /  /                                    0             0  JOD             0           0           0 Mosaic Associates                       0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAKE GEORGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-07-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg.Jr/Sr High School:
09-0659   Reconstruction               0-004-008  04/21/10     DONE    DONE       DONE      12/30/09   12/22/09   04/06/09   03/24/09   4,7,16                 2,100,000     2,100,000  HCM             0           0           0 TEtra Tech Engineers, Archite           0        /  /             /  /        
11-0168   Reconstruction               0-004-009  01/04/12     DONE    DONE       DONE      09/13/11   09/09/11   04/19/11   01/13/09   2,4,7,8,9,10,13,14,1     668,523       668,523  HCM             0           0           0 Tetra Tech Architects And Eni           0        /  /             /  /        

          Lake George Elementary School:
09-0660   Reconstruction               0-006-012  04/21/10     DONE    DONE       DONE      12/30/09   12/22/09   04/06/09   03/24/09   4,7,15,16              1,100,000     1,100,000  HCM             0           0           0 TEtra Tech Engineers, Archite           0        /  /             /  /        
11-0169   Reconstruction               0-006-013  01/04/12     DONE    DONE       DONE      09/13/11   09/09/11   04/19/11   01/13/09   2,4,7,8,9,10,13,155,     534,917       534,917  HCM             0           0           0 Tetra Tech Architects And Eni           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HADLEY LUZERNE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-08-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-1548   Reconstruction               0-001-017  03/22/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   07/06/10   155,16                   792,469       792,469  HCM             0           0           0 M/E Engineering ,P.C              761,477        /  /           04/03/13      
11-0558   Reconstruction               0-001-018  03/26/12     DONE    DONE       DONE      12/28/11   12/27/11   09/28/11   09/20/11   2,4,7,16               1,560,000             0  HCM             0           0           0 RE4ORM ARCHITECTURE                     0        /  /           02/11/13      

          Middle School:
09-1549   Reconstruction               0-004-009  03/22/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   07/06/10   16                       354,074       354,074  HCM             0           0           0 M/E Engineering ,P.C              337,230        /  /           04/03/13      
11-0559   Reconstruction               0-004-010  03/26/12     DONE    DONE       DONE      12/28/11   12/27/11   09/28/11   09/20/11   10,155,16                615,000             0  HCM             0           0           0 RE4ORM ARCHITECTURE                     0        /  /           02/11/13      

          Administration Bldg:
09-1550   Reconstruction               1-005-001  03/22/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   07/06/10   16                         6,097             0  HCM             0           0           0 M/E Engineering ,P.C                4,837        /  /           04/03/13      

          Bus Garage:
09-1551   Reconstruction               5-003-005  03/22/11     DONE    DONE       DONE      06/21/10   06/11/10   11/05/09   07/06/10   16                        11,900        11,900  HCM             0           0           0 M/E Engineering ,P.C               10,293        /  /           04/03/13      
10-0698   Reconstruction               5-003-006  11/21/10     DONE    DONE       DONE      12/31/10   12/24/10   09/08/10   10/18/10   15                        92,335        92,335  HCM             0           0           0 RE4ORM ARCHITECTURE                     0        /  /             /  /        
11-0560   Reconstruction               5-003-007  03/26/12     DONE    DONE       DONE      12/28/11   12/27/11   09/28/11   09/20/11   7                        225,000             0  HCM             0           0           0 RE4ORM ARCHITECTURE                     0        /  /           02/11/13      

          Recycling Shop @ Main School:
  -       Reconstruction               7-010-002                                              /  /       /  /     08/31/10     /  /     2,15                           0             0  HCM             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




QUEENSBURY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-09-02-03
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
08-0142   Reconstruction               0-001-025  08/15/08     DONE    DONE       DONE      08/12/08   08/04/08   07/10/08   07/28/08   155,16                   175,000       175,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
09-0541   Additions and Alterations    0-001-026  04/07/10     DONE    DONE       DONE      12/03/09   12/02/09   07/01/09   01/27/09   02 - 16                7,773,936     7,577,529  HCM             0           0     924,983 Collins & Scoville Architects           0        /  /             /  /        
10-1002   Additions and Alterations    0-001-027  03/14/11     DONE    DONE       DONE      03/08/11   03/07/11     /  /     01/27/09   02 - 16                1,565,913     1,565,913  HCM             0           0     108,317 Collins & Scoville Architects           0        /  /             /  /        

          High School:
09-0542   Reconstruction               0-002-018  04/07/10     DONE    DONE       DONE      12/03/09   12/02/09   07/01/09   01/27/09   2,4,7,8,9,10,155,15,   1,935,570     1,935,570  HCM             0           0     209,070 Collins & Scoville Architects           0        /  /             /  /        
10-1060   Reconstruction               0-002-019  06/07/11     DONE    DONE       DONE      03/17/11   03/14/11   03/16/11   06/14/10   9,10,16                  300,000       300,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
11-1232   Reconstruction               0-002-020  07/27/12     DONE    DONE       DONE      04/26/12   04/25/12     /  /     06/13/11   9,10,16                  300,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -       Reconstruction               0-002-021                                              /  /       /  /     03/14/12     /  /     9,10,16                        0             0  HCM             0           0           0                                         0        /  /             /  /        

          K-3 Elementary School:
09-0543   Additions and Alterations    0-003-012  04/07/10     DONE    DONE       DONE      12/03/09   12/02/09   07/01/09   01/27/09   02 - 16                1,360,609     1,360,609  HCM             0           0     133,045 Collins & Scoville Architects           0        /  /             /  /        
10-0538   Reconstruction               0-003-013  05/13/11     DONE    DONE       DONE      12/06/10   11/22/10   06/18/10   05/19/09   2,7,9,16                 350,000       350,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
  -    PR Alterations                  0-003-014                                              /  /       /  /     05/10/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /             /  /        

          Relocatable Administration Bldg.:
11-0242   Reconstruction               0-016-004  10/18/11     DONE    DONE       DONE      10/07/11   10/07/11   09/08/11   06/13/11   7                         50,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          William H.Barton Intermediate School:
09-0544   Additions and Alterations    0-019-004  04/07/10     DONE    DONE       DONE      12/03/09   12/02/09   07/01/09   01/27/09   02 - 16                  769,392       768,190  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
12-0229   Reconstruction               0-019-005  11/06/12     DONE    DONE       DONE      10/01/12   09/18/12   06/19/12   06/11/12   2,15                     250,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Greenhouse:
09-1202   New Construction             0-024-001  04/07/10     DONE    DONE       DONE      04/01/10   03/29/10   03/12/10   01/27/09   02 - 16                   65,000             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Bus Garage B:
08-1185   Reconstruction               5-020-005  07/09/09     DONE    DONE       DONE      02/10/09   02/03/09   07/10/08   12/15/08   155,16                   175,000       175,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        
09-0545   Additions and Alterations    5-020-006  04/07/10     DONE    DONE       DONE      12/03/09   12/02/09   07/01/09   01/27/09   02 - 16                3,029,000     3,029,000  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        

          Bus Shelter:
09-0546XX Additions and Alterations    5-021-002                         CANCELLED          12/03/09   12/02/09   07/01/09   01/27/09   02 - 16                        0             0  HCM             0           0           0 Collins & Scoville Architects           0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GLENS FALLS COMMON SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-09-18-08
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Abraham Wing School:
08-0481PR Additions and Alterations    0-001-005                         UNREVIEWED         10/07/08   10/03/08   01/02/07     /  /     02 - 16                        0             0  JOD             0           0           0 Ronald Richard Rucinski Ethan           0        /  /             /  /        
08-0948   Additions and Alterations    0-001-005  04/22/09     DONE    DONE       DONE      12/17/08   12/15/08   01/02/07   09/12/07   02 - 16                  600,000       544,397  JOD             0           0     113,620 Ronald Richard Rucinski Ethan           0        /  /             /  /        
  -    XX Reconstruction               0-001-006                         CANCELLED            /  /       /  /     01/06/11     /  /     13                             0     3,862,962  JOD             0           0           0                                         0        /  /             /  /        
  -       Reconstruction               0-001-007                                              /  /       /  /     10/10/12     /  /     2,15                           0             0  JMB             0           0           0                                         0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WARRENSBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-12-01-04
last updated on 05/23/13
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
09-1356   Reconstruction               0-001-006  09/08/10     DONE    DONE       DONE      04/22/10   04/20/10   03/03/10   03/06/07   9,10,16                  376,879       376,879  DDJ             0           0      73,868 SEI Design Group                        0        /  /           09/18/12      
11-1000   Reconstruction               0-001-007  05/13/12     DONE    DONE       DONE      03/21/12   03/21/12   12/16/11   12/12/11   155,15,16                320,600       320,600  DDJ             0           0     147,206 SEI Design Group                        0        /  /             /  /        

          Relocatables James St.(demo 2012):
11-1001   Reconstruction               0-006-002  06/29/12     DONE    DONE       DONE      03/21/12   03/21/12   12/14/11   01/09/12   155,15,16                 43,000             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        

          New Jr./Sr. High School:
12-0536   Reconstruction               0-008-004  05/03/13     DONE    DONE       DONE      12/12/12   12/07/12   09/19/12   12/04/12   7,15,16                2,088,425             0  DDJ             0           0      83,064 SEI Design Group                        0        /  /             /  /        

          Maintenance Storage Bldg A:
09-0978   Reconstruction               2-011-001  05/14/10     DONE    DONE       DONE      03/02/10   02/24/10   10/22/08     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Softball Storage Bldg C:
09-0979   Reconstruction               2-012-001  05/14/10     DONE    DONE       DONE      03/02/10   02/24/10   10/22/08     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Storage Container:
09-0980DB Discovered Building          2-013-001  05/14/10     DONE    DONE       DONE      03/02/10   02/24/10   10/22/08     /  /                                    0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Storage Bldg B:
09-0981DB Discovered Building          2-014-001  05/14/10     DONE    DONE       DONE      03/02/10   02/24/10   05/19/10     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /             /  /        

          Maintenance Storage (Garage):
12-0537   Reconstruction               3-004-001  05/03/13     DONE    DONE       DONE      12/12/12   12/07/12   04/26/07   12/04/12   7                        132,000             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        

          New Bus Garage:
12-0538   Reconstruction               5-010-002  05/03/13     DONE    DONE       DONE      12/12/12   12/07/12   09/19/12   12/04/12   4,155                    260,000             0  DDJ             0           0           0 SEI Design Group                        0        /  /             /  /        


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED