REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bolton Central:
12-0670 Additions and Alterations 0-001-007 04/15/13 DONE DONE DONE 01/15/13 01/15/13 06/01/06 09/27/12 02 - 16 1,260,000 0 MGL 0 0 91,331 Bernier Carr Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
New K-12 Building:
08-1706 Reconstruction 0-014-003 07/13/09 DONE DONE DONE 06/18/09 06/05/09 01/09/09 11/19/07 2,15,16 100,000 100,000 HCM 0 0 0 Griffith Dardanelli,Architect 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle/High School:
10-0513 Reconstruction 0-001-021 01/11/11 DONE DONE DONE 12/02/10 11/19/10 10/05/10 05/16/06 7 300,000 0 JOD 0 0 0 Mosaic Associates 0 / / / /
12-0526 Reconstruction 0-001-022 DONE DONE UNREVIEWED12/11/12 12/10/12 07/18/12 05/15/12 2,4,7,8,9,10,155,15, 0 41,076,027 DDJ 0 0 0 Mosaic Associates 0 / / / /
- Reconstruction 0-001-023 / / / / / / / / 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0 0 / / / /
- Reconstruction 0-001-023 / / / / 11/01/12 / / 2,4,7,8,14,155,15 0 0 DDJ 0 0 0 0 / / / /
12-1176 Reconstruction 0-001-024 STARTED STARTED DONE 05/10/13 05/08/13 04/17/13 05/15/12 2,7 0 0 JOB 0 0 0 Mosaic Associates 0 / / / /
Big Cross St. Elementary:
12-0527 Reconstruction 0-003-009 DONE DONE UNREVIEWED12/11/12 12/10/12 07/18/12 05/15/12 2,9,10,155,15,16 0 2,790,594 JOD 0 0 0 Mosaic Associates 0 / / / /
- Reconstruction 0-003-010 / / / / 11/01/12 / / 9,15,16 0 0 DDJ 0 0 0 0 / / / /
07-2200SC Visual Structural Inspection 0-003-SC1 09/30/08 DONE DONE DONE 05/16/08 05/16/08 / / / / 16 326 0 JOD 0 0 0 0 / / / /
Jackson Heights Elementary:
12-0528 Reconstruction 0-005-008 DONE DONE UNREVIEWED12/11/12 12/10/12 07/18/12 05/15/12 2,9,10,155,16 0 4,021,380 DDJ 0 0 0 Mosaic Associates 0 / / / /
- Reconstruction 0-005-009 / / / / 11/01/12 / / 7,8,155,15,16 0 0 DDJ 0 0 0 0 / / / /
Kensington Road Elementary:
- Reconstruction 0-007-009 / / / / 07/18/12 / / 16 0 0 JOD 0 0 0 0 / / / /
07-2199SC Visual Structural Inspection 0-007-SC1 09/30/08 DONE DONE DONE 05/16/08 05/16/08 / / / / 16 2,120 0 JOD 0 0 0 0 / / / /
Administration Bldg:
- Reconstruction 1-008-004 / / / / 07/18/12 / / 16 0 0 JOD 0 0 0 0 / / / /
- Reconstruction 1-008-005 / / / / 07/20/12 / / 16 0 0 JOD 0 0 0 0 / / / /
Morse Storage Building:
09-0289DB Discovered Building 2-019-001 10/23/09 DONE DONE DONE 10/06/09 09/30/09 08/07/09 / / 0 0 JOD 0 0 0 Mosaic Associates 0 / / / /
Bus Garage Warehouse:
- Reconstruction 5-009-003 / / / / 07/18/12 / / 16 0 0 JOD 0 0 0 0 / / / /
Morse Field House:
09-0290DB Discovered Building 7-018-001 10/23/09 DONE DONE DONE 10/06/09 09/30/09 08/07/09 / / 0 0 JOD 0 0 0 Mosaic Associates 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Bldg.Jr/Sr High School:
09-0659 Reconstruction 0-004-008 04/21/10 DONE DONE DONE 12/30/09 12/22/09 04/06/09 03/24/09 4,7,16 2,100,000 2,100,000 HCM 0 0 0 TEtra Tech Engineers, Archite 0 / / / /
11-0168 Reconstruction 0-004-009 01/04/12 DONE DONE DONE 09/13/11 09/09/11 04/19/11 01/13/09 2,4,7,8,9,10,13,14,1 668,523 668,523 HCM 0 0 0 Tetra Tech Architects And Eni 0 / / / /
Lake George Elementary School:
09-0660 Reconstruction 0-006-012 04/21/10 DONE DONE DONE 12/30/09 12/22/09 04/06/09 03/24/09 4,7,15,16 1,100,000 1,100,000 HCM 0 0 0 TEtra Tech Engineers, Archite 0 / / / /
11-0169 Reconstruction 0-006-013 01/04/12 DONE DONE DONE 09/13/11 09/09/11 04/19/11 01/13/09 2,4,7,8,9,10,13,155, 534,917 534,917 HCM 0 0 0 Tetra Tech Architects And Eni 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
09-1548 Reconstruction 0-001-017 03/22/11 DONE DONE DONE 06/21/10 06/11/10 11/05/09 07/06/10 155,16 792,469 792,469 HCM 0 0 0 M/E Engineering ,P.C 761,477 / / 04/03/13
11-0558 Reconstruction 0-001-018 03/26/12 DONE DONE DONE 12/28/11 12/27/11 09/28/11 09/20/11 2,4,7,16 1,560,000 0 HCM 0 0 0 RE4ORM ARCHITECTURE 0 / / 02/11/13
Middle School:
09-1549 Reconstruction 0-004-009 03/22/11 DONE DONE DONE 06/21/10 06/11/10 11/05/09 07/06/10 16 354,074 354,074 HCM 0 0 0 M/E Engineering ,P.C 337,230 / / 04/03/13
11-0559 Reconstruction 0-004-010 03/26/12 DONE DONE DONE 12/28/11 12/27/11 09/28/11 09/20/11 10,155,16 615,000 0 HCM 0 0 0 RE4ORM ARCHITECTURE 0 / / 02/11/13
Administration Bldg:
09-1550 Reconstruction 1-005-001 03/22/11 DONE DONE DONE 06/21/10 06/11/10 11/05/09 07/06/10 16 6,097 0 HCM 0 0 0 M/E Engineering ,P.C 4,837 / / 04/03/13
Bus Garage:
09-1551 Reconstruction 5-003-005 03/22/11 DONE DONE DONE 06/21/10 06/11/10 11/05/09 07/06/10 16 11,900 11,900 HCM 0 0 0 M/E Engineering ,P.C 10,293 / / 04/03/13
10-0698 Reconstruction 5-003-006 11/21/10 DONE DONE DONE 12/31/10 12/24/10 09/08/10 10/18/10 15 92,335 92,335 HCM 0 0 0 RE4ORM ARCHITECTURE 0 / / / /
11-0560 Reconstruction 5-003-007 03/26/12 DONE DONE DONE 12/28/11 12/27/11 09/28/11 09/20/11 7 225,000 0 HCM 0 0 0 RE4ORM ARCHITECTURE 0 / / 02/11/13
Recycling Shop @ Main School:
- Reconstruction 7-010-002 / / / / 08/31/10 / / 2,15 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
08-0142 Reconstruction 0-001-025 08/15/08 DONE DONE DONE 08/12/08 08/04/08 07/10/08 07/28/08 155,16 175,000 175,000 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
09-0541 Additions and Alterations 0-001-026 04/07/10 DONE DONE DONE 12/03/09 12/02/09 07/01/09 01/27/09 02 - 16 7,773,936 7,577,529 HCM 0 0 924,983 Collins & Scoville Architects 0 / / / /
10-1002 Additions and Alterations 0-001-027 03/14/11 DONE DONE DONE 03/08/11 03/07/11 / / 01/27/09 02 - 16 1,565,913 1,565,913 HCM 0 0 108,317 Collins & Scoville Architects 0 / / / /
High School:
09-0542 Reconstruction 0-002-018 04/07/10 DONE DONE DONE 12/03/09 12/02/09 07/01/09 01/27/09 2,4,7,8,9,10,155,15, 1,935,570 1,935,570 HCM 0 0 209,070 Collins & Scoville Architects 0 / / / /
10-1060 Reconstruction 0-002-019 06/07/11 DONE DONE DONE 03/17/11 03/14/11 03/16/11 06/14/10 9,10,16 300,000 300,000 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
11-1232 Reconstruction 0-002-020 07/27/12 DONE DONE DONE 04/26/12 04/25/12 / / 06/13/11 9,10,16 300,000 0 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
- Reconstruction 0-002-021 / / / / 03/14/12 / / 9,10,16 0 0 HCM 0 0 0 0 / / / /
K-3 Elementary School:
09-0543 Additions and Alterations 0-003-012 04/07/10 DONE DONE DONE 12/03/09 12/02/09 07/01/09 01/27/09 02 - 16 1,360,609 1,360,609 HCM 0 0 133,045 Collins & Scoville Architects 0 / / / /
10-0538 Reconstruction 0-003-013 05/13/11 DONE DONE DONE 12/06/10 11/22/10 06/18/10 05/19/09 2,7,9,16 350,000 350,000 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
- PR Alterations 0-003-014 / / / / 05/10/12 / / 0 0 HCM 0 0 0 0 / / / /
Relocatable Administration Bldg.:
11-0242 Reconstruction 0-016-004 10/18/11 DONE DONE DONE 10/07/11 10/07/11 09/08/11 06/13/11 7 50,000 0 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
William H.Barton Intermediate School:
09-0544 Additions and Alterations 0-019-004 04/07/10 DONE DONE DONE 12/03/09 12/02/09 07/01/09 01/27/09 02 - 16 769,392 768,190 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
12-0229 Reconstruction 0-019-005 11/06/12 DONE DONE DONE 10/01/12 09/18/12 06/19/12 06/11/12 2,15 250,000 0 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
Greenhouse:
09-1202 New Construction 0-024-001 04/07/10 DONE DONE DONE 04/01/10 03/29/10 03/12/10 01/27/09 02 - 16 65,000 0 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
Bus Garage B:
08-1185 Reconstruction 5-020-005 07/09/09 DONE DONE DONE 02/10/09 02/03/09 07/10/08 12/15/08 155,16 175,000 175,000 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
09-0545 Additions and Alterations 5-020-006 04/07/10 DONE DONE DONE 12/03/09 12/02/09 07/01/09 01/27/09 02 - 16 3,029,000 3,029,000 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
Bus Shelter:
09-0546XX Additions and Alterations 5-021-002 CANCELLED 12/03/09 12/02/09 07/01/09 01/27/09 02 - 16 0 0 HCM 0 0 0 Collins & Scoville Architects 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Abraham Wing School:
08-0481PR Additions and Alterations 0-001-005 UNREVIEWED 10/07/08 10/03/08 01/02/07 / / 02 - 16 0 0 JOD 0 0 0 Ronald Richard Rucinski Ethan 0 / / / /
08-0948 Additions and Alterations 0-001-005 04/22/09 DONE DONE DONE 12/17/08 12/15/08 01/02/07 09/12/07 02 - 16 600,000 544,397 JOD 0 0 113,620 Ronald Richard Rucinski Ethan 0 / / / /
- XX Reconstruction 0-001-006 CANCELLED / / / / 01/06/11 / / 13 0 3,862,962 JOD 0 0 0 0 / / / /
- Reconstruction 0-001-007 / / / / 10/10/12 / / 2,15 0 0 JMB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
09-1356 Reconstruction 0-001-006 09/08/10 DONE DONE DONE 04/22/10 04/20/10 03/03/10 03/06/07 9,10,16 376,879 376,879 DDJ 0 0 73,868 SEI Design Group 0 / / 09/18/12
11-1000 Reconstruction 0-001-007 05/13/12 DONE DONE DONE 03/21/12 03/21/12 12/16/11 12/12/11 155,15,16 320,600 320,600 DDJ 0 0 147,206 SEI Design Group 0 / / / /
Relocatables James St.(demo 2012):
11-1001 Reconstruction 0-006-002 06/29/12 DONE DONE DONE 03/21/12 03/21/12 12/14/11 01/09/12 155,15,16 43,000 0 DDJ 0 0 0 SEI Design Group 0 / / / /
New Jr./Sr. High School:
12-0536 Reconstruction 0-008-004 05/03/13 DONE DONE DONE 12/12/12 12/07/12 09/19/12 12/04/12 7,15,16 2,088,425 0 DDJ 0 0 83,064 SEI Design Group 0 / / / /
Maintenance Storage Bldg A:
09-0978 Reconstruction 2-011-001 05/14/10 DONE DONE DONE 03/02/10 02/24/10 10/22/08 / / 0 0 DDJ 0 0 0 0 / / / /
Softball Storage Bldg C:
09-0979 Reconstruction 2-012-001 05/14/10 DONE DONE DONE 03/02/10 02/24/10 10/22/08 / / 0 0 DDJ 0 0 0 0 / / / /
Storage Container:
09-0980DB Discovered Building 2-013-001 05/14/10 DONE DONE DONE 03/02/10 02/24/10 10/22/08 / / 0 0 DDJ 0 0 0 0 / / / /
Storage Bldg B:
09-0981DB Discovered Building 2-014-001 05/14/10 DONE DONE DONE 03/02/10 02/24/10 05/19/10 / / 02 - 16 0 0 DDJ 0 0 0 0 / / / /
Maintenance Storage (Garage):
12-0537 Reconstruction 3-004-001 05/03/13 DONE DONE DONE 12/12/12 12/07/12 04/26/07 12/04/12 7 132,000 0 DDJ 0 0 0 SEI Design Group 0 / / / /
New Bus Garage:
12-0538 Reconstruction 5-010-002 05/03/13 DONE DONE DONE 12/12/12 12/07/12 09/19/12 12/04/12 4,155 260,000 0 DDJ 0 0 0 SEI Design Group 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED