REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Argyle Central School:
- Reconstruction 0-001-009 / / / / 10/27/08 / / 2,7,9,10,155,15,16 0 0 HCM 0 0 0 0 / / / /
Bus Garage:
- Reconstruction 5-002-004 / / / / 10/27/08 / / 2,7,8,9,10,155,15,16 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
09-1251 Reconstruction 0-001-009 05/17/10 DONE DONE DONE 04/06/10 04/02/10 04/10/07 05/19/09 7,8,155,15 453,893 453,893 HCM 0 0 108,480 Mosaic Associates 0 / / / /
11-0189 Reconstruction 0-001-010 01/13/11 DONE DONE DONE 09/20/11 09/15/11 04/15/11 01/24/11 155 18,562 20,000 HCM 0 0 0 Mosaic Associates 0 / / 03/18/13
- Reconstruction 0-001-011 / / / / 06/09/11 / / 155 0 0 HCM 0 0 0 0 / / / /
12-0328 Reconstruction 0-001-012 ADDENDUM REQ'D 10/25/12 10/25/12 05/01/12 05/19/12 155 0 19,334,423 HCM 0 0 0 Mosaic Associates 0 / / / /
- Reconstruction 0-001-013 / / / / 04/25/13 / / 8 0 0 JMB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary School:
08-0970 Reconstruction 0-005-010 05/07/09 DONE DONE DONE 12/24/08 12/15/08 12/05/06 01/15/08 2,7,8,9,155,15,16 6,419,618 6,334,618 MGL 0 0 211,692 SEI Design Group 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
07-2066 Additions and Alterations 0-001-012 11/05/08 DONE DONE DONE 05/02/08 04/28/08 03/05/07 08/29/07 02 - 16 9,677,624 7,036,119 DDJ 0 0 648,400 SEI Design Group 0 / / / /
12-0462 Reconstruction 0-001-013 11/26/12 DONE DONE DONE 11/20/12 11/19/12 09/04/12 07/23/12 9 55,000 0 DDJ 0 0 0 SEI Design Group 0 / / 12/05/12
Granville Elem (fmrly Quaker):
07-2067 Additions and Alterations 0-013-007 11/05/08 DONE DONE DONE 05/02/08 04/28/08 03/05/07 08/29/07 02 - 16 6,131,809 6,131,809 DDJ 0 0 410,000 SEI Design Group 0 / / / /
Mary J. Tanner Elementary:
07-2068 Reconstruction 0-014-005 11/05/08 DONE DONE DONE 05/02/08 04/28/08 03/05/07 08/29/07 2,4,7,8,9,155,15,16 411,353 411,353 DDJ 0 0 27,500 SEI Design Group 0 / / / /
Temp Off Trailer(removed from site):
08-0047TQ Temporary Quarters 1-020-001 01/15/09 DONE DONE DONE 07/21/08 07/07/08 07/15/08 / / 0 0 DDJ 0 0 0 SEI Design Group 0 / / / /
Maintenance Storage Garage & Office:
07-2069 New Construction 2-018-001 11/05/08 DONE DONE DONE 05/02/08 04/28/08 11/23/07 08/29/07 02 - 16 299,602 0 DDJ 0 0 0 SEI Design Group 0 / / / /
Storage Container #2:
07-1651DB Discovered Building 2-019-001 09/18/08 DONE DONE DONE 02/21/08 02/14/08 12/05/07 / / 0 0 MGL 0 0 0 0 / / / /
Bus Garage:
07-2070 Reconstruction 5-002-005 11/05/08 DONE DONE DONE 05/02/08 04/28/08 11/23/07 08/29/07 8,13 107,212 107,212 DDJ 0 0 0 SEI Design Group 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Primary Bldg:
07-2023 Reconstruction 0-004-009 06/09/08 DONE DONE DONE 04/24/08 04/16/08 03/07/08 07/24/06 155 135,800 135,800 DDJ 0 0 21,728 St.John Architects 0 / / / /
11-0389 Reconstruction 0-004-010 12/29/11 DONE DONE DONE 11/15/11 11/15/11 09/10/10 12/14/10 8,10,155,16 235,620 0 DDJ 0 0 0 St. John Architects 0 / / / /
- Reconstruction 0-004-011 / / / / 04/13/12 / / 8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
12-1109 Reconstruction 0-004-012 04/16/13 DONE DONE DONE 04/16/13 04/16/13 04/13/12 11/11/12 7 750,000 750,000 MFS 0 0 0 WPS Consulting Engs. 0 / / / /
Middle Grade Building:
11-0390 Reconstruction 0-005-013 12/29/11 DONE DONE DONE 11/15/11 11/15/11 09/10/10 12/14/10 8,10,155,16 263,450 0 DDJ 0 0 0 St. John Architects 0 / / / /
- Reconstruction 0-005-014 / / / / 04/13/12 / / 7,8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
High School:
11-0391 Reconstruction 0-007-012 12/29/11 DONE DONE DONE 11/15/11 11/15/11 09/10/10 12/14/10 2,7,9,10,155 688,050 0 DDJ 0 0 0 St. John Architects 0 / / / /
10-1205 Reconstruction 0-007-013 04/21/11 DONE DONE DONE 04/19/11 04/14/11 02/15/11 12/14/10 7 800,000 800,000 DDJ 0 0 0 St. John Architects 0 / / / /
- Reconstruction 0-007-014 / / / / 04/13/12 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0 0 / / / /
12-1110 Reconstruction 0-007-015 04/16/13 DONE DONE DONE 04/16/13 04/16/13 01/03/13 12/14/10 7 200,000 200,000 MFS 0 0 0 WPS Consulting Engs. 0 / / / /
Bus Garage:
11-0392 Reconstruction 5-001-006 12/29/11 DONE DONE DONE 11/15/11 11/15/11 09/10/10 12/14/10 2,4,8 55,660 0 DDJ 0 0 0 St. John Architects 0 / / / /
- Reconstruction 5-001-007 / / / / 04/13/12 / / 2,4,8,9,10,155,15,16 0 0 DDJ 0 0 0 0 / / / /
12-1111 Reconstruction 5-001-008 04/16/13 DONE DONE DONE 04/16/13 04/16/13 04/13/12 11/11/12 8 255,000 255,000 DDJ 0 0 0 WPS Consulting Engs. 0 / / / /
District Wide:
08-0391 Reconstruction 7-999-002 11/03/08 DONE DONE DONE 09/24/08 09/23/08 02/27/08 07/24/06 10,13,16 182,000 182,000 DDJ 0 0 8,345 St.John Architects 0 / / / /
- Reconstruction 7-999-003 / / / / 04/17/12 / / 2,13 0 0 DDJ 0 0 0 0 / / / /
12-1127 Reconstruction 7-999-004 05/06/13 DONE DONE DONE 04/25/13 04/25/13 04/17/12 12/11/12 2,13,16 400,000 0 MFS 0 0 0 WPS Consulting Engs. 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Shop Building:
- Reconstruction 0-002-006 / / / / 07/07/10 / / 10 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School:
09-1415 Reconstruction 0-001-016 11/04/10 DONE DONE DONE 05/10/10 05/04/10 01/30/08 12/09/08 2,4,7,8,9,10,155,15, 3,893,295 3,893,295 HCM 0 0 346,503 James Jordan Associates 0 / / / /
09-0139 Reconstruction 0-001-017 08/20/09 DONE DONE DONE 08/20/09 08/20/09 05/14/09 12/09/08 155,16 27,200 27,200 HCM 0 0 2,421 James Jordan Associates 0 / / 03/25/13
- Reconstruction 0-001-018 / / / / 04/08/13 / / 8,9,13,155,16 0 0 JMB 0 0 0 0 / / / /
Margaret Murphy Kindergarten Ctr.:
09-1416 Reconstruction 0-003-012 11/04/10 DONE DONE DONE 05/10/10 05/03/10 01/30/08 12/09/08 2,4,7,8,9,155,15,16 1,030,809 1,030,809 HCM 0 0 91,742 James Jordan Associates 0 / / 03/25/13
Intermediate Sch. (was Maple St):
09-1417 Reconstruction 0-004-013 11/04/10 DONE DONE DONE 05/10/10 05/04/10 01/30/08 12/09/08 2,7,8,9,10,155,15,16 920,571 920,571 HCM 0 0 81,931 James Jordan Associates 0 / / 03/25/13
08-0375 Reconstruction 0-004-014 09/22/08 DONE DONE DONE 09/22/08 09/22/08 08/22/08 12/12/06 2,7,155,15,16 854,000 854,000 HCM 0 0 0 James Jordan Associates 0 / / / /
10-1105 Reconstruction 0-004-016 06/13/11 DONE DONE DONE 03/22/11 03/21/11 08/27/10 12/06/06 2,4,7,8,9,10,155,15, 1,688,941 1,688,941 HCM 0 0 30,482 James Jordan Associates 0 / / 03/25/13
Primary Sch.(Was Dix Avenue):
09-1418 Reconstruction 0-005-011 11/04/10 DONE DONE DONE 05/10/10 05/04/10 01/30/08 12/09/08 2,7,8,9,10,155,15,16 710,681 710,681 HCM 0 0 63,251 James Jordan Associates 0 / / 03/25/13
07-2220 Reconstruction 0-005-012 06/18/08 DONE DONE DONE 06/05/08 05/29/08 04/03/08 12/13/05 7 715,000 715,000 HCM 0 0 0 James Jordan Associates 0 / / / /
District Offices (Burgoyne Ave.Sch):
09-1419XX Reconstruction 0-006-003 CANCELLED 05/10/10 05/04/10 01/30/08 12/09/08 2,7,155,16 0 0 HCM 0 0 0 James Jordan Associates 0 / / / /
09-0876 Reconstruction 0-006-004 02/19/10 DONE DONE DONE 02/10/10 02/05/10 12/10/09 12/09/08 2,4,7,8,9,155,15,16 103,400 0 HCM 0 0 0 James Jordan Associates 0 / / / /
Middle School (Was Junior High):
09-1420 Reconstruction 0-007-011 11/04/10 DONE DONE DONE 05/10/10 05/04/10 01/30/08 12/09/08 2,7,8,9,10,155,15,16 3,390,244 3,390,244 HCM 0 0 301,732 James Jordan Associates 0 / / 03/25/13
09-0140 Reconstruction 0-007-012 08/20/09 DONE DONE DONE 08/20/09 08/20/09 05/14/09 12/09/08 155,16 27,200 27,200 HCM 0 0 2,421 James Jordan Associates 0 / / 03/25/13
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Primary School:
- PR Additions and Alterations 0-001-004 / / / / 10/07/08 / / 02 - 16 0 0 HCM 0 0 0 0 / / / /
Elementary/High School:
07-1809 Reconstruction 0-002-007 03/18/09 DONE DONE DONE 03/15/08 03/05/08 10/16/07 02/29/08 7,9,155,16 2,244,647 2,244,647 HCM 0 0 237,140 Einhorn, Yaffee, Prescott Arc 1,889,453 / / / /
10-0829 Reconstruction 0-002-008 04/12/11 DONE DONE DONE 02/08/11 02/04/11 10/26/10 10/06/10 2,8,9,13,16 824,500 824,500 HCM 0 0 0 Clark Patterson Lee 0 / / / /
08-1713SC Visual Structural Inspection 0-002-SC2 06/19/09 DONE DONE DONE 04/13/09 04/13/09 / / / / 16 13,762 0 JOD 0 0 0 0 / / / /
Athletic Storage Building:
- New Construction 2-008-001 / / / / 10/07/08 / / 02 - 16 0 0 HCM 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Cambridge Central:
08-1651 Reconstruction 0-002-012 06/12/09 DONE DONE DONE 06/01/09 05/18/09 08/29/07 05/20/08 2,4,7,8,9,155,15,16 100,000 100,000 MGL 0 0 0 Bernier Carr Associates 0 / / / /
09-0990 Reconstruction 0-002-013 05/24/10 DONE DONE DONE 03/02/10 02/24/10 01/06/10 06/17/08 2,4,8,9,155,16 2,283,000 2,283,000 HCM 0 0 349,950 Bernier Carr Associates 0 / / / /
10-1345 Reconstruction 0-002-014 06/15/11 DONE DONE DONE 05/27/11 05/26/11 02/18/11 05/18/10 8,9,10 100,000 100,000 HCM 0 0 0 Mosaic Associates 0 / / / /
- PR Additions and Alterations 0-002-015 / / / / 07/01/11 / / 02 - 16 0 0 HCM 0 0 0 0 / / / /
11-0710 Additions and Alterations 0-002-015 06/07/12 DONE DONE DONE 01/25/12 01/24/12 07/01/11 06/29/11 02 - 16 8,037,000 7,945,600 HCM 0 0 0 Mosaic Associates 0 / / 02/20/13
11-0414 Reconstruction 0-002-016 12/15/11 DONE DONE DONE 11/18/11 11/18/11 07/20/11 05/18/10 8,9 100,000 100,000 HCM 0 0 0 Mosaic Associates 0 / / 02/06/13
11-1237 Reconstruction 0-002-017 12/13/12 DONE DONE DONE 04/27/12 04/23/12 03/08/12 11/21/11 8,155,15,16 1,339,965 0 HCM 0 0 0 Mosaic Associates 1,309,358 / / / /
12-0493 Reconstruction 0-002-018 04/08/13 DONE DONE DONE 11/28/12 11/28/12 07/30/12 05/15/12 8,9 100,000 0 JMB 0 0 0 Mosaic Associates 0 / / / /
08-1370SC Visual Structural Inspection 0-002-SC1 03/17/09 DONE DONE DONE 10/27/08 10/27/08 / / / / 16 13,282 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior-Senior High School:
09-0564 Reconstruction 0-008-017 01/05/10 DONE DONE DONE 12/08/09 12/04/09 05/20/09 09/23/09 7,8,9,155,16 525,000 525,000 DDJ 0 0 0 WPS Consulting Engs. 0 / / 12/13/11
11-0026 Reconstruction 0-008-018 07/27/11 DONE DONE DONE 07/19/11 07/18/11 03/24/11 06/29/11 7 115,000 115,000 DDJ 0 0 0 WPS Consulting Engs. 0 / / 03/12/12
11-0523 Reconstruction 0-008-019 02/22/12 DONE DONE DONE 12/22/11 12/22/11 05/26/11 06/29/11 9,155,16 510,000 510,000 DDJ 0 0 0 WPS Consulting Engs. 0 / / / /
12-0938 Reconstruction 0-008-020 03/05/13 DONE DONE DONE 03/01/13 03/01/13 11/20/12 01/23/13 7 0 0 DDJ 0 0 0 WPS Consulting Engs. 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CERT. OCC. CSC REC'D
________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
F. Donald Myers Educ. Ctr.:
08-0241 Reconstruction 0-006-016 06/17/10 DONE DONE DONE 09/03/08 08/26/08 01/24/07 07/09/08 10,155,16 1,806,933 1,806,933 JOD 0 0 0 PB Power 1,642,910 / / / /
08-0995 Reconstruction 0-006-018 02/03/09 DONE DONE DONE 01/02/09 12/19/08 04/10/08 03/12/08 7,9,155,16 45,000 45,000 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
09-0371 Reconstruction 0-006-019 02/10/10 DONE DONE DONE 10/29/09 10/26/09 03/24/09 02/11/09 2,4,7,8,9,10,13,155, 615,938 615,938 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
10-0420 Reconstruction 0-006-020 02/08/11 DONE DONE DONE 11/04/10 10/22/10 03/10/10 02/10/10 2,4,9,155,16 412,000 412,000 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
11-0262 Reconstruction 0-006-021 12/05/11 DONE DONE DONE 10/17/11 10/14/11 03/31/11 02/09/11 4,7,9,10,13,155,15,1 237,000 237,000 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / 10/11/12
Education Svcs. Ctr. Complex:
08-0242 Reconstruction 0-014-019 06/17/10 DONE DONE DONE 09/03/08 08/26/08 01/24/07 07/09/08 10,155,16 1,804,276 0 JOD 0 0 0 PB Power 1,586,612 / / / /
08-0880 Reconstruction 0-014-020 04/20/09 DONE DONE DONE 12/08/08 12/01/08 03/23/07 03/12/08 9,155,15,16 740,650 740,650 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
07-1203 Reconstruction 0-014-021 06/04/08 DONE DONE DONE 12/24/07 12/21/07 03/23/07 02/21/07 9,155,15,16 114,940 114,940 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
- Reconstruction 0-014-022 ADDENDUM REQ'D 10/14/08 10/09/08 04/10/08 03/12/08 2,4,16 0 12,247,500 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
08-0994 Reconstruction 0-014-023 02/03/09 DONE DONE DONE 01/02/09 12/19/08 04/10/08 03/12/08 7,9,16 128,998 128,998 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
08-0881XX Reconstruction 0-014-024 04/20/09 CANCELLED 12/08/08 12/01/08 04/10/08 03/12/08 2,4,9,10,13,155,15,1 0 12,041,190 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
12-0482 Reconstruction 0-014-025 01/29/13 DONE DONE DONE 12/26/12 11/13/12 09/18/12 02/08/12 2,4,8,9 500,000 500,000 MFS 0 0 0 Griffith Dardanelli,Architect 0 / / / /
Special Education Modular:
08-0517 Reconstruction 0-020-002 03/31/09 DONE DONE DONE 10/14/08 10/09/08 02/24/09 03/12/08 4 144,500 144,500 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
Campus Bldg G:
10-0563 Reconstruction 0-048-002 12/28/10 DONE DONE DONE 12/08/10 11/30/10 03/10/10 02/10/10 2,7,9,155,16 190,000 190,000 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
Ed. Serv. Ctr. Cplx.(Bldg A,B,C,D,Eq:
- Reconstruction 0-056-002 / / / / 03/10/10 / / 2,7 0 0 JOD 0 0 0 0 / / / /
11-0263 Reconstruction 0-056-003 12/05/11 DONE DONE DONE 10/17/11 10/14/11 04/14/11 02/09/11 2,4,9,13,15,16 363,000 363,000 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / 10/11/12
Burgoyne Avenue - Building:
08-0732 Reconstruction 1-073-002 03/06/09 DONE DONE DONE 11/10/08 11/06/08 05/21/08 03/12/08 10,13,16 109,000 0 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
Dist.Wide Telephone-Phase II:
09-0618 Reconstruction 7-999-003 04/12/10 DONE DONE DONE 12/23/09 12/17/09 03/24/09 02/11/09 10,13,16 30,000 30,000 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
Gick Road Conference Center:
08-0243 Reconstruction 8-072-001 06/17/10 DONE DONE DONE 09/03/08 08/26/08 01/23/07 07/09/08 8,200 0 JOD 0 0 0 PB Power 4,032 / / / /
Longfellows Inn:
- TQ Temporary Quarters 8-074-001 / / / / 08/14/08 / / 0 0 JOD 0 0 0 0 / / / /
David Judkins, MD:
- TQ Temporary Quarters 8-075-001 / / / / 08/14/08 / / 0 0 JOD 0 0 0 0 / / / /
Lease @ 90 South Street:
- TQ Temporary Quarters 8-077-001 / / / / 12/04/08 / / 0 0 JOD 0 0 0 0 / / / /
St. Joseph's Elementary School:
09-0187TQ Temporary Quarters 8-078-001 09/15/09 DONE DONE DONE 09/02/09 09/02/09 04/09/09 / / 0 0 JOD 0 0 0 Griffith Dardanelli,Architect 0 / / / /
Empire Theatere Plaza, LLC:
- TQ Temporary Quarters 8-079-001 / / / / 05/14/09 / / 0 0 JOD 0 0 0 0 / / / /
Sanford St. Teaching & Learning Cntr:
12-0362 Reconstruction 8-080-001 02/06/13 DONE DONE DONE 10/30/12 10/30/12 / / 06/13/12 155,16 240,000 0 JMB 0 0 0 Griffith Dardanelli,Architect 0 / / / /
- Reconstruction 8-080-L01 / / / / 06/28/12 / / 0 0 JOD 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED