Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 09/19/18 at 07:53:58




NEWARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-01-01-06
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lincoln School:
16-1048   Reconstruction               0-001-011  09/07/17     DONE    DONE       DONE      12/22/16   12/22/16   07/15/16   05/17/16   2,4,7,8,9,10,155,15,   1,223,366             0  BMJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-001-012                                              /  /       /  /     09/14/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Perkin School:
16-1049   Reconstruction               0-002-017  09/07/17     DONE    DONE       DONE      12/22/16   12/22/16   07/15/16   05/17/16   2,4,7,8,9,10,155,15,   3,876,276             0  BMJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-002-018                                              /  /       /  /     09/14/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          High School:
16-1050   Reconstruction               0-003-016  09/07/17     DONE    DONE       DONE      12/22/16   12/22/16   07/15/16   05/17/16   2,7,9,155,15,16        4,978,120             0  BMJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-003-017                                              /  /       /  /     09/14/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-018                                              /  /       /  /     09/14/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Newark Middle School:
16-1051   Reconstruction               0-006-015  09/07/17     DONE    DONE       DONE      12/22/16   12/22/16   07/15/16   05/17/16   2,4,7,8,9,10,155,15,   1,259,046     1,259,046  BMJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-006-016                                              /  /       /  /     09/14/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Kelly Intermediate School:
16-1052   Reconstruction               0-008-012  09/07/17     DONE    DONE       DONE      12/22/16   12/22/16   07/15/16   05/17/16   2,4,7,8,9,10,155,15,  10,025,634    10,025,634  BMJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             
  -       Reconstruction               0-008-013                                              /  /       /  /     09/14/18     /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-008-014                                              /  /       /  /     09/14/18     /  /     7                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Concession/Toilet Building:
16-1053   New Construction             7-031-001  09/07/17     DONE    DONE       DONE      12/22/16   12/22/16   07/15/16   05/17/16   02 - 16                  937,558             0  BMJ             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CLYDE-SAVANNAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-03-01-04
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
16-0110   Reconstruction               0-001-011  02/14/17     DONE    DONE       DONE      07/15/16   07/15/16   03/21/16   12/09/09   2,4,8,9,155,15,16      1,053,725     1,053,725  JMB             0           0           0 Hunt Engineers,Architects & l           0      10/27/17                       01/29/18           
16-0114   Reconstruction               0-001-012  09/07/16     DONE    DONE       DONE      07/15/16   07/15/16   06/14/16   06/17/16   16                       100,000       100,000  MTM             0           0           0 Hunt Engineers,Architects & l           0      05/08/17                       06/30/17           
17-1714   Reconstruction               0-001-013                       ADDENDUM REQ'D       04/17/18   04/17/18   11/23/16   05/16/17   2,4,7,8,9,155,15,16            0    14,446,764  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Clyde Elementary School:
  -    PR Additions and Alterations    0-015-008                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
15-1286SB Additions and Alterations    0-015-008               DONE                           /  /       /  /     02/24/16     /  /     02 - 16                        0             0  JMB             0           0           0                                         0        /  /                           /  /             
17-1715   Additions and Alterations    0-015-008                       ADDENDUM REQ'D       04/17/18   04/17/18     /  /     05/16/16   02 - 16                        0             0  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
16-0111   Reconstruction               0-015-009  02/14/17     DONE    DONE       DONE      07/15/16   07/15/16   03/21/16   12/08/09   2,4,8,9,155,15,16        162,580       162,580  JMB             0           0           0 Hunt Engineers,Architects & l           0      10/27/17                       01/29/18           
17-1716   Reconstruction               0-015-010                       ADDENDUM REQ'D       04/17/18   04/17/18   11/23/16   05/16/17   2,4,7,8,9,155,15,16            0     9,118,980  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          xxStorage Bldgxx Demo'd 2018:
  -       Reconstruction               2-004-001                                              /  /       /  /     03/23/18     /  /     2                              0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Clyde Bus Garage:
16-0112   Reconstruction               4-002-007  02/14/17     DONE    DONE       DONE      07/15/16   07/15/16   03/21/16   12/08/09   16                        94,840        94,840  JMB             0           0           0 Hunt Engineers,Architects & l           0      10/27/17                       01/29/18           
17-1164   Reconstruction               4-002-008  06/05/18     DONE    DONE       DONE      01/16/18   12/15/17   06/01/17   05/16/17   2,4,7,8,9,10,14,155,   2,858,000     2,858,000  MTM             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Field House:
16-0113   Reconstruction               7-005-004  02/14/17     DONE    DONE       DONE      07/15/16   07/15/16   03/21/16   12/09/09   16                        43,700             0  JMB             0           0           0 Hunt Engineers,Architects & l           0      10/27/17                       01/29/18           

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LYONS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-05-01-04
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle/High School:
14-1183   Reconstruction               0-001-010  03/25/15     DONE    DONE       DONE      02/23/15   02/23/15   12/16/14   12/09/13   2,7                    2,709,136     2,709,136  JMB             0           0      54,182 SEI Design Group                        0      05/18/16                       09/16/16           
15-0424   Reconstruction               0-001-011  06/17/16     DONE    DONE       DONE      09/09/15   09/08/15   05/27/15   12/09/14   2,4,7,8,9,10,155,15,   4,126,019     4,126,019  JMB             0           0      75,913 SEI Design Group                        0      12/29/17                       03/29/18           
  -    PR Additions and Alterations    0-001-012                                              /  /       /  /     06/02/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
17-1755   Reconstruction               0-001-013               DONE    DONE       ADD. REQ'D04/26/18   04/26/18   08/15/17   12/09/14   2,4,7,8,9,10,155,15,           0    19,631,360  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Elementary School:
  -       Reconstruction               0-002-011                                              /  /       /  /     12/16/14     /  /     2,7                            0    10,348,125  JMB             0           0           0                                         0        /  /                           /  /             
15-0425   Reconstruction               0-002-012  06/17/16     DONE    DONE       DONE      09/09/15   09/08/15   05/27/15   12/09/14   2,4,7,8,9,155,15,16    3,033,000     3,033,000  JMB             0           0           0 SEI Design Group                        0      12/29/17                       03/29/18           

          Bus Garage/Fuel Facility:
15-0426   Reconstruction               5-014-003  06/17/16     DONE    DONE       DONE      09/09/15   09/08/15   05/27/15   12/09/14   15,16                     92,680        92,680  JMB             0           0           0 SEI Design Group                        0      12/29/17                       03/29/18           
  -       Reconstruction               5-014-004                                              /  /       /  /     08/15/17     /  /     2,15,16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARION CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-07-01-04
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Marion Elementary:
  -       Reconstruction               0-001-012                                              /  /       /  /     07/22/14     /  /     2,7,16                         0    11,449,746  DDJ             0           0           0                                         0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0201   Reconstruction               0-001-013  12/11/17     DONE    DONE       DONE      08/10/17   08/10/17   05/24/17   12/06/16   2,155,15,16              250,000             0  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0901   Reconstruction               0-001-014                       ADDENDUM REQ'D       12/05/17   12/04/17   09/06/17   12/06/16   2,4,7,8,155,15,16              0    11,514,118  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Jr/Sr High School:
13-0643   Reconstruction               0-005-015  05/21/14     DONE    DONE       DONE      10/28/13   10/28/13   03/01/13   12/11/12   2,4,8,10,16            1,196,256     1,196,256  DDJ             0           0     109,491 SEI Design Group                        0      10/19/15                       12/14/15         YES
                                                                                                                                                                                                                                                                                                                                   
14-0580   Reconstruction               0-005-016  06/30/16     DONE    DONE       DONE      11/05/14   11/04/14   07/22/14   07/07/14   2,7,16                 1,100,000     1,100,000  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-0322   Reconstruction               0-005-017  11/04/14     DONE    DONE       DONE      09/22/14   09/19/14   07/22/14   05/20/14   10                       100,000       100,000  DDJ             0           0           0 SEI Design Group                        0      03/24/15                       02/16/16         YES
                                                                                                                                                                                                                                                                                                                                   
15-0600   Reconstruction               0-005-018  10/29/15     DONE    DONE       DONE      10/16/15   10/15/15   09/17/15   05/19/15   2,9                      100,000       100,000  DDJ             0           0           0 SEI Design Group                        0      06/22/16                       09/16/16         YES
                                                                                                                                                                                                                                                                                                                                   
16-0215   Reconstruction               0-005-019  10/05/16     DONE    DONE       DONE      08/05/16   08/05/16   05/11/16   12/11/12   9,155,16                 250,353       250,353  BMJ             0           0      21,805 SEI Design Group                        0      11/13/17                       12/21/17         YES
                                                                                                                                                                                                                                                                                                                                   
16-0213   Reconstruction               0-005-020  08/11/16     DONE    DONE       DONE      08/05/16   08/05/16   05/11/16   12/11/12   2,8,9                    271,183       271,183  BMJ             0           0      20,000 SEI Design Group                        0      11/13/17                       12/21/17         YES
                                                                                                                                                                                                                                                                                                                                   
16-0214   Reconstruction               0-005-021  08/12/16     DONE    DONE       DONE      08/05/16   08/05/16   05/24/16   05/17/16   2,8,9                    100,000       100,000  DDJ             0           0           0 SEI Design Group                        0      06/16/17                       07/17/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-0202   Reconstruction               0-005-022  12/11/17     DONE    DONE       DONE      08/10/17   08/10/17   05/24/17   12/06/16   2,155,15,16              250,000             0  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0907   Reconstruction               0-005-023  03/07/18     DONE    DONE       DONE      12/05/17   12/04/17   09/06/17   04/17/17   2,8,9,16                 100,000             0  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0902   Reconstruction               0-005-024                       ADDENDUM REQ'D       12/05/17   12/04/17   09/06/17   12/06/16   2,4,7,8,9,10,155,15,           0    20,051,504  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Marion Bus Garage/bus storage facili:
14-0581   Reconstruction               5-002-005  06/30/16     DONE    DONE       DONE      11/05/14   11/04/14   09/17/14   07/07/14   2,7,16                   300,000       300,000  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New Bus Garage & Fueling Station:
  -       Reconstruction               5-006-002                                              /  /       /  /     09/24/14     /  /     2,7,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /       /  /       /  /     10,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
16-0891SB Reconstruction               7-999-001               DONE                           /  /       /  /     11/29/16     /  /     10,16                          0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               7-999-BA2                                              /  /       /  /       /  /       /  /     10                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    SB Visual Structural Inspection 7-999-SB1               DONE                           /  /       /  /       /  /       /  /     10                             0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WAYNE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-08-01-06
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          James A Beneway High School:
  -       Reconstruction               0-001-011                                              /  /       /  /     05/11/18     /  /     2,4,7,8,9,10,14,155,           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Wayne Elem School (fmly Ontario ES):
  -       Reconstruction               0-002-013                                              /  /       /  /     05/11/18     /  /     2,4,7,8,9,10,155,15,           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Wayne Primary Schl (fmly Ontario PS):
  -       Reconstruction               0-004-014                                              /  /       /  /     05/11/18     /  /     2,4,7,8,9,10,155,15,           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Armstrong Middle School:
  -       Reconstruction               0-006-012                                              /  /       /  /     05/11/18     /  /     2,4,7,8,9,10,155,15,           0             0  MTM             0           0           0                                         0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  MTM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PALMYRA-MACEDON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-09-01-06
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
14-0037   Reconstruction               0-001-014  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/13/13   4,7,9,155,15,16        5,467,100     5,467,100  JMB             0           0           0 King & King Architects                  0      12/01/15                       04/17/17           
16-1983   Reconstruction               0-001-015  04/19/18     DONE    DONE       DONE      06/05/17   06/05/17   01/25/17   12/09/13   155                      473,000             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             
  -    XX Additions and Alterations    0-001-016                         CANCELLED            /  /       /  /     08/23/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-017                                              /  /       /  /     10/05/17     /  /     2,4,7,8,9,10,14,155,           0             0  BMJ             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-001-018                                              /  /       /  /       /  /       /  /     2,4,7,8,9,10,14,155,           0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Primary School:
14-0038   Reconstruction               0-002-005  11/03/14     DONE    DONE       DONE      07/23/14   07/07/04   01/07/14   12/13/13   2,15,16                  192,200       192,200  JMB             0           0           0 King & King Architects                  0      12/01/15                       04/17/17           
16-1984   Reconstruction               0-002-006  04/19/18     DONE    DONE       DONE      06/05/17   06/05/17   01/25/17   02/09/13   155                    1,162,000             0  BMJ             0           0           0 King & King Architects                  0        /  /                           /  /             
  -       Reconstruction               0-002-007                                              /  /       /  /     08/23/17     /  /     2,4,7,8,9,10,155,15,           0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Intermediate School:
14-0039   Reconstruction               0-003-012  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/13/13   9,15                      89,500        89,500  JMB             0           0           0 King & King Architects                  0      12/01/15                       06/14/16           
  -       Reconstruction               0-003-013                                              /  /       /  /     08/23/17     /  /     2,4,7,8,9,10,155,15,           0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Middle School:
14-0040   Reconstruction               0-008-007  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/13/13   15,16                     39,900        26,200  JMB             0           0           0 King & King Architects                  0      12/01/15                       04/17/17           
16-1252   Reconstruction               0-008-008  02/27/17     DONE    DONE       DONE      01/24/17   01/24/17   09/09/16   01/10/17   7                        600,000       600,000  BMJ             0           0           0 King & King Architects                  0      01/26/18                       07/30/18           
17-0188   Reconstruction               0-008-009  11/17/17     DONE    DONE       DONE      08/09/17   08/09/17   07/12/17   05/16/17   16                       100,000       100,000  BMJ             0           0           0 King & King Architects                  0      06/01/18                       06/28/18           
  -       Reconstruction               0-008-010                                              /  /       /  /     08/23/17     /  /     2,4,7,8,9,10,155,15,           0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Storage Building - High School:
  -       New Construction             2-017-001                                              /  /       /  /     08/23/17     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             

          Transportation Facility:
14-0041   Reconstruction               5-014-002  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/19/13   2,4,8,155,15,16          511,400       511,400  JMB             0           0           0 King & King Architects                  0      12/01/15                       04/17/17           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GANANDA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-09-02-04
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School Bldg:
16-1808   Reconstruction               0-001-016  01/23/18     DONE    DONE       DONE      05/11/17   05/11/17   03/07/17   12/01/16   2,4,7,8,9,10,155,15,   2,565,500             0  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Richard Mann Elem (fmly New Primary):
13-1602   Reconstruction               0-002-011  06/30/14     DONE    DONE       DONE      06/10/14   06/09/14   05/20/14   05/20/14   4,7,8,9,16               100,000       100,000  DDJ             0           0           0 SEI Design Group                        0      01/20/15                       03/05/15           
14-0911   Reconstruction               0-002-012  01/28/15     DONE    DONE       DONE      12/31/14   12/26/14   12/01/14   12/09/14   4,7                    1,426,500     1,426,500  DDJ             0           0           0 SEI Design Group                        0      11/24/15                       12/15/15           
14-1491   Reconstruction               0-002-013  07/31/15     DONE    DONE       DONE      05/11/15   05/11/15   01/12/15   12/09/14   2,4,7,8,9,155,15,16    1,079,113     1,079,113  DDJ             0           0           0 SEI Design Group                        0      11/30/16                       12/22/16           
15-1711   Reconstruction               0-002-014  06/16/16     DONE    DONE       DONE      05/11/16   05/11/16   04/19/16   12/09/14   2,7,155,15,16            284,000       284,000  DDJ             0           0           0 SEI Design Group                        0      12/06/16                       12/22/16           
16-1809   Reconstruction               0-002-015  01/22/18     DONE    DONE       DONE      05/11/17   05/11/17   04/20/17   12/01/16   2,4,8,9,10,155,15,16   9,020,228     9,020,228  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
16-2006   Reconstruction               0-002-016  09/21/17     DONE    DONE       DONE      06/08/17   06/08/17   05/19/17   05/16/17   155,15,16                100,000       100,000  MTM             0           0           0 SEI Design Group                        0      05/01/18                       06/20/18           
17-1901   Reconstruction               0-002-017  07/31/18     DONE    DONE       DONE      05/29/18   05/25/18   03/27/18   05/15/18   155,15,16                100,000             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Ruben A. Cirillo High School:
14-1667   Reconstruction               0-004-005  08/04/15     DONE    DONE       DONE      06/16/15   06/15/15   05/15/15   05/19/15   155,15,16                100,000       100,000  DDJ             0           0           0 SEI Design Group                        0      06/28/16                       07/05/16           
15-1811   Reconstruction               0-004-006  06/21/16     DONE    DONE       DONE      05/27/16   05/27/16   04/19/16   05/17/16   155,15,16                100,000       100,000  DDJ             0           0           0 SEI Design Group                        0      03/03/17                       03/31/17           
16-1810   Reconstruction               0-004-007  01/23/18     DONE    DONE       DONE      05/11/17   05/11/17   04/20/17   12/01/16   4,7,8,9,10,155,15,16   3,514,272             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          District-Wide:
16-1811XX Reconstruction               7-999-002                         CANCELLED          05/11/17   05/11/17   03/07/17   12/01/16   10                             0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0    18,205,542  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SODUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-12-01-06
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sodus Middle/High School:
14-0176   Reconstruction               0-001-013  07/10/14     DONE    DONE       DONE      08/14/14   08/13/14   06/26/14   06/10/14   4,8,9,10                  48,488        48,488  MFS             0           0           0 SEI Design Group                        0      11/12/14                       12/22/14           
14-0146   Reconstruction               0-001-014  05/11/15     DONE    DONE       DONE      08/13/14   08/13/14   06/26/14   04/29/14   2,4,8,9,10,155,15,16   4,153,911     4,153,911  MFS             0           0           0 SEI Design Group                        0      05/31/16                       06/02/17           
14-1593   Reconstruction               0-001-015  04/21/16     DONE    DONE       DONE      06/08/15   06/04/15   06/26/14   04/29/14   2,4,8,9,10,155,15,16   9,089,625     8,886,435  MFS             0           0     518,819 SEI Design Group                        0        /  /                           /  /             
14-0939   Reconstruction               0-001-016  02/11/15     DONE    DONE       DONE      01/12/15   01/12/15   12/23/14   04/29/14   7                      2,688,530     2,688,530  MFS             0           0           0 SEI Design Group                        0      09/16/15                       12/14/16           

          Sodus Primary:
14-1594   Reconstruction               0-004-012  04/21/16     DONE    DONE       DONE      06/08/15   06/04/15   06/26/14   04/29/15   2,4,8,9,10,155,15,16     509,600       509,600  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0150   Reconstruction               0-004-013  05/09/18     DONE    DONE       DONE      08/02/17   08/02/17   05/24/17   11/08/16   155,15,16                 38,000             0  BMJ             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Ath. Storage HS(Comm.Bldg.):
14-0147   Reconstruction               7-010-002  05/11/15     DONE    DONE       DONE      08/13/14   08/13/14   06/26/14   04/29/14   8,9,13,155,15,16         119,025             0  MFS             0           0           0 SEI Design Group                        0      05/31/16                       06/02/17           

          Press Box:
14-0148   New Construction             7-012-001  05/11/15     DONE    DONE       DONE      08/13/14   08/13/14   06/26/14   04/29/14   02 - 16                   75,000             0  MFS             0           0           0 SEI Design Group                        0      05/31/16                       06/02/17           

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     13                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WILLIAMSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-14-02-04
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Williamson Elementary School:
17-1955   Reconstruction               0-001-011               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   07/18/17   05/16/17   2,4,7,8,9,155,15,16            0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0740   Reconstruction               0-001-012  03/22/18     DONE    DONE       DONE      11/08/17   10/20/17   07/18/17   05/16/17   2,8                      674,000             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Williamson Middle School:
16-0216   Reconstruction               0-002-010  11/02/16     DONE    DONE       DONE      08/05/16   08/05/16   07/10/15   05/17/16   2,7                      100,000       100,000  MFS             0           0           0 SEI Design Group                        0      12/30/16                       05/26/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-1956   Reconstruction               0-002-011               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   07/18/17   05/16/17   2,4,8,9,13,155,15,16           0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0741   Reconstruction               0-002-012  03/22/18     DONE    DONE       DONE      11/08/17   10/20/17   07/18/17   05/16/17   2,8                      760,000             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-1914   Reconstruction               0-002-013  07/30/18     DONE    DONE       DONE      06/01/18   05/31/18   04/16/18   05/15/18   2,4,8,9,155,15,16        100,000             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Williamson Senior High School:
15-1665   Reconstruction               0-006-009  05/09/16     DONE    DONE       DONE      05/03/16   05/02/16   07/10/15   03/20/12   2,16                      93,388        93,388  MFS             0           0           0 SEI Design Group                        0      03/20/17                       05/26/17         YES
                                                                                                                                                                                                                                                                                                                                   
17-1957   Reconstruction               0-006-010               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   07/18/17   05/16/17   2,4,8,9,13,155,15,16           0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
17-0742   Reconstruction               0-006-011  03/22/18     DONE    DONE       DONE      11/08/17   10/20/17   07/18/17   05/16/17   2,8                    1,050,000             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
17-0754   Reconstruction               0-006-012  02/16/18     DONE    DONE       DONE      11/13/17   11/13/17   07/18/17   05/16/17   2,9,10                   100,000       100,000  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-006-013                                              /  /       /  /     09/28/17     /  /     2,9,10                         0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Administration Building:
17-1958   Reconstruction               1-003-003               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   07/18/17   05/16/17   2,7                            0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Bus Garage:
17-1959   Reconstruction               5-004-005               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   07/18/17   05/16/17   2,7,13,155,15,16               0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               5-004-006                                              /  /       /  /     02/09/18     /  /     2,4,13,15,16                   0             0  MTM             0           0           0                                         0        /  /                           /  /             

          Press Box/Storage:
17-1960   New Construction             7-012-001               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   07/18/17   05/16/17   02 - 16                        0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Storage/Dugout:
17-1961   New Construction             7-060-001               UNREVIEWED
                                                                       STARTED    UNREVIEWED06/08/18   06/08/18   04/21/18   05/16/17   02 - 16                        0             0  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     14                             0             0  MFS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH ROSE-WOLCOTT CENTRAL SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-15-01-06
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
16-0653PR Reconstruction               0-001-016               DONE                         10/20/16     /  /     10/17/16     /  /     2,4,7,8,9,10,14,155,           0    14,991,100  SLC             0           0           0                                         0        /  /                           /  /             
16-1531SB Reconstruction               0-001-016               DONE                           /  /       /  /     03/22/17     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             
17-0541   Reconstruction               0-001-016  04/18/18     DONE    DONE       DONE      10/05/17   10/04/17   03/22/17   02/28/17   16                    19,705,133             0  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                           /  /             

          Florentine-Hendrick Elem.:
  -       Reconstruction               0-002-012                                              /  /       /  /     09/19/17     /  /     8,9,155,15,16                  0             0  SLC             0           0           0                                         0        /  /                           /  /             

          North Rose Elementary School:
15-0053   Reconstruction               0-007-014  04/03/15     DONE    DONE       DONE      07/13/15   07/09/15   05/18/15   10/14/14   2,15,16                  270,000       270,000  JMB             0           0           0 SEI Design Group                        0      06/30/15                       11/09/15           
  -    XX Additions and Alterations    0-007-015                         CANCELLED            /  /       /  /     03/23/17     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
17-0542   Additions and Alterations    0-007-015  04/18/18     DONE    DONE       DONE      10/05/17   10/04/17   03/23/17   02/28/17   02 - 16                7,680,538     7,530,812  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                           /  /             
  -       Reconstruction               0-007-016                                              /  /       /  /     04/11/18     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-007-017                                              /  /       /  /     05/16/18     /  /     2,4,7,8,9                      0             0  SLC             0           0           0                                         0        /  /                           /  /             

          High School:
15-1609   Reconstruction               0-010-014  04/26/16     DONE    DONE       DONE      04/20/16   04/19/16   03/30/16   03/05/07   7                      1,390,000     1,390,000  JMB             0           0           0 SWBR Architects P.C.                    0      09/01/16                       02/14/17           
15-1971   Reconstruction               0-010-015  07/06/16     DONE    DONE       DONE      06/23/16   06/23/16   05/16/16   05/17/16   2,4                      100,000       100,000  JMB             0           0           0 SWBR ARCHITECTS                         0      09/02/16                       02/14/17           
16-1622   Reconstruction               0-010-016  04/24/17     DONE    DONE       DONE      04/04/17   04/04/17   01/06/17   12/13/16   7,155,15,16              500,000       500,000  SLC             0           0           0 SWBR Architects P.C.                    0      09/08/17                       02/15/18           
17-0543   Reconstruction               0-010-017  04/18/18     DONE    DONE       DONE      10/05/17   10/04/17   03/23/17   02/28/17   2,4,7,8,9,10,155,15,   4,468,683             0  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                           /  /             
16-1980   Reconstruction               0-010-018  07/06/17     DONE    DONE       DONE      06/05/17   06/05/17   05/02/17   04/11/17   15,16                    100,000       100,000  SLC             0           0           0 SWBR Architects P.C.                    0      09/08/17                       02/15/18           
16-1981   Reconstruction               0-010-019  07/06/17     DONE    DONE       DONE      06/05/17   06/05/17   05/04/17   03/05/07   15,16                     50,000        50,000  SLC             0           0           0 SWBR Architects P.C.                    0      11/06/17                       02/15/18           
  -       Reconstruction               0-010-020                                              /  /       /  /     05/04/17     /  /     8,15,16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXDistrict Office (demo'd 2017):
17-1516   Reconstruction               1-003-005  04/18/18     DONE    DONE       DONE      03/08/18   03/08/18   03/23/17   02/28/17   2                         89,258             0  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                           /  /             

          Bus Garage Storage (Mdl Sch):
  -    XX Reconstruction               4-008-010                         CANCELLED            /  /       /  /     03/23/17     /  /     2,15,16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          North Rose Bus Garage (Maint):
17-0544   Reconstruction               5-009-010  04/18/18     DONE    DONE       DONE      10/05/17   10/04/17   05/04/17   02/28/17   2,15,16                  130,407             0  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                           /  /             
  -       Reconstruction               5-009-011                                              /  /       /  /     05/24/18     /  /     2,4,13,15,16                   0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Concession Stand:
16-2142   Reconstruction               7-014-003  07/06/17     DONE    DONE       DONE      06/27/17   06/27/17   06/22/17   03/05/07   155,16                    25,000             0  SLC             0           0           0 SWBR ARCHITECTS                         0      11/06/17                       02/15/18           

          Huron Environmental LLC:
17-1507TQ Temporary Quarters           8-023-001  05/04/18     DONE    DONE       DONE      03/07/18     /  /     02/07/18     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Temp Clrms @ Elem School:
17-1517XX Reconstruction               8-024-001                         CANCELLED          03/29/18   03/29/18   02/23/18     /  /                                    0             0  SLC             0           0           0 SWBR Architects P.C.                    0        /  /                           /  /             

          District Storage Building:
  -    TQ Temporary Quarters           8-025-001                                              /  /       /  /     06/19/18     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RED CREEK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-15-03-04
last updated on 09/19/18
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Building:
12-0835   Reconstruction               0-006-007  05/15/14     DONE    DONE       DONE      02/14/13   02/13/13   08/14/12   09/06/12   2,4,7,8,9,155,15,16      100,000       100,000  JMB             0           0           0 C&S Companies                           0      06/27/14                       03/26/15           
14-1574   Reconstruction               0-006-008  08/28/15     DONE    DONE       DONE      06/01/15   05/26/15   03/16/15   05/19/15   16                       100,000       100,000  JMB             0           0           0 C&S Companies                           0      03/01/16                       02/27/17           
16-1717   Reconstruction               0-006-009  12/21/17     DONE    DONE       DONE      04/21/17   04/21/17   10/30/15   02/09/16   2,4,7,8,9,10,155,15,  18,500,000    17,459,763  JMB             0           0     352,776 King & King Architects                  0        /  /                           /  /             
16-1937   Reconstruction               0-006-010  09/06/16     DONE    DONE       DONE      06/02/17   06/02/17   06/09/16   06/13/16   7,155,15,16              396,750       396,750  JMB             0           0           0 King & King Architects                  0      12/31/16                       12/05/17           
17-0894   Reconstruction               0-006-011  02/13/18     DONE    DONE       DONE      12/01/17   11/28/17   07/20/17   05/16/17   16                       100,000       100,000  MTM             0           0           0 King & King Architects                  0      06/21/18                       06/25/18           
18-0215   Reconstruction               0-006-012                         UNREVIEWED         08/09/18   08/08/18   05/02/18   05/09/18   2,155,16                       0             0  MTM             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED