Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 12/19/14 at 16:05:33




NEWARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-01-01-06
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lincoln School:
10-0322   Reconstruction               0-001-009  03/02/11     DONE    DONE       DONE      10/06/10   10/01/10   12/21/09   02/23/10   2,4,7,8,9,10,155,15,   2,199,183     2,199,183  JOD             0           0      43,984 Gordon W. Jones Associates              0      03/03/14                       03/12/14           
12-0366   Reconstruction               0-001-010  05/08/13     DONE    DONE       DONE      10/31/12   10/30/12   08/28/12   02/23/10   8,16                      31,551        31,551  DDJ             0           0           0 Gordon W. Jones Associates              0      10/01/14                       10/23/14           

          Perkin School:
10-0323   Reconstruction               0-002-013  03/02/11     DONE    DONE       DONE      10/06/10   10/01/10   12/21/09   02/23/10   2,4,8,9,155,15,16        839,161       817,824  JOD             0           0      37,693 Gordon W. Jones Associates              0      03/03/14                       03/12/14           
12-0367   Reconstruction               0-002-014  05/08/13     DONE    DONE       DONE      10/31/12   10/30/12   08/28/12   02/23/10   2,155,15,16            1,114,532     1,114,532  DDJ             0           0      10,000 Gordon W. Jones Associates              0      10/01/14                       10/23/14           
  -       Reconstruction               0-002-015                                              /  /       /  /     09/21/12     /  /     2,7                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             
  -    XX Reconstruction               0-002-016                         CANCELLED            /  /       /  /     09/21/12     /  /     2,155,15,16                    0    16,122,456  DDJ             0           0           0                                         0        /  /                           /  /             

          High School:
10-0324   Additions and Alterations    0-003-014  03/02/11     DONE    DONE       DONE      10/06/10   10/01/10   12/21/09   02/23/10   02 - 16               14,351,530    14,351,530  JOD             0           0     287,031 Gordon W. Jones Associates              0      03/03/14                       03/12/14           
12-0368   Reconstruction               0-003-015  05/08/13     DONE    DONE       DONE      10/31/12   10/30/12   08/28/12   02/23/10   2,4,8,9,10,155,15,16   4,577,049     4,577,049  DDJ             0           0      69,918 Gordon W. Jones Associates              0      10/01/14                       10/23/14           

          Newark Middle School:
10-0325   Reconstruction               0-006-013  03/02/11     DONE    DONE       DONE      10/06/10   10/01/10   12/21/09   02/23/10   2,4,7,8,9,10,155,15,   2,968,212     2,968,212  JOD             0           0      59,364 Gordon W. Jones Associates              0      03/03/14                       03/12/14           
12-0369   Reconstruction               0-006-014  05/08/13     DONE    DONE       DONE      10/31/12   10/30/12   08/28/12   02/23/10   2,8,155,15,16            737,523       737,523  DDJ             0           0     737,523 Gordon W. Jones Associates              0      10/01/14                       10/23/14           

          Kelly Intermediate School:
10-0326   Reconstruction               0-008-010  03/02/11     DONE    DONE       DONE      10/06/10   10/01/10   12/21/09   02/23/10   2,4,7,8,9,10,155,15,   2,646,183     2,646,183  JOD             0           0      52,924 Gordon W. Jones Associates              0      03/03/14                       03/12/14           
12-0370   Reconstruction               0-008-011  05/08/13     DONE    DONE       DONE      10/31/12   10/30/12   08/28/12   02/23/10   2,4,8,10,155,15,16       650,103       650,103  DDJ             0           0     650,103 Gordon W. Jones Associates              0      10/01/14                       10/23/14           

          Storage Bldg #1 - HS Main Campus:
  -    DB Discovered Building          2-019-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Storage Bldg #3 - HS Main Campus:
  -    DB Discovered Building          2-021-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Storage Bldg #5 - HS Main Campus:
  -    DB Discovered Building          2-023-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Storage Bldg #6 - HS Main Campus:
  -    DB Discovered Building          2-024-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Dug Out Stg Bldg #7 - HS Main Campus:
  -    DB Discovered Building          2-025-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Storage Bldg #8 - HS Main Campus:
  -    DB Discovered Building          2-026-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Dug Out/Storage Bldg #9-HS Main Camp:
  -    DB Discovered Building          2-027-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Storage Bldg #10 - HS Main Campus:
  -    DB Discovered Building          2-028-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Storage Garage:
  -    DB Discovered Building          4-029-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
10-0327   Reconstruction               5-009-005  03/02/11     DONE    DONE       DONE      10/06/10   10/01/10   12/21/09   02/23/10   2,4,9,13,155,15,16     1,125,179     1,125,179  JOD             0           0           0 Gordon W. Jones Associates              0      03/03/14                       03/12/14           
12-0371   Reconstruction               5-009-006  05/08/13     DONE    DONE       DONE      10/31/12   10/30/12   08/28/12   02/23/10   2,4,7,8,9,10,155,15,   1,282,836     1,282,836  DDJ             0           0           0 Gordon W. Jones Associates              0      10/01/14                       10/23/14           

          Press Box:
10-0376   New Construction             7-018-001  03/02/11     DONE    DONE       DONE      10/25/10   10/25/10   10/14/10   02/23/10   02 - 16                   75,466             0  JOD             0           0           0 Gordon W. Jones Associates              0        /  /                           /  /             

          Concession Bldg #2 - HS Main Campus:
  -    DB Discovered Building          7-020-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Concession Bldg #4 - HS Main Campus:
  -    DB Discovered Building          7-022-001                                              /  /       /  /     06/22/11     /  /                                    0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Newark Municipal Bldg, 4th Floor:
14-0194XX Reconstruction               8-030-001                         CANCELLED          08/19/14   08/14/14   07/02/14     /  /                                    0             0                  0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CLYDE-SAVANNAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-03-01-04
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
10-0507   Additions and Alterations    0-001-009  03/16/11     DONE    DONE       DONE      12/02/10   11/19/10   11/09/07   12/08/09   02 - 16               11,021,548    11,021,548  HCM             0           0     319,276 Ashley McGraw Architects                0      08/30/12                       09/04/12           
11-1322   Additions and Alterations    0-001-010  10/09/12     DONE    DONE       DONE      05/21/12   05/18/12   03/28/12   12/08/09   02 - 16                1,697,974     1,697,974  HCM             0           0      74,817 Ashley McGraw Architects                0      09/01/13                       09/03/13           

          Savannah Elementary:
10-0508   Reconstruction               0-014-007  03/16/11     DONE    DONE       DONE      12/02/10   11/19/10   11/09/07   12/08/09   8,9,155,15,16             17,655        17,655  HCM             0           0      17,655 Ashley McGraw Architects                0      08/30/12                       09/04/12           
11-1323   Reconstruction               0-014-008  10/09/12     DONE    DONE       DONE      05/21/12   05/18/12   03/28/12   12/06/09   2,8,9,15                 101,250       101,250  HCM             0           0           0 Ashley McGraw Architects                0      09/01/13                       09/03/13           

          Clyde Elementary:
10-0509   Additions and Alterations    0-015-006  03/16/11     DONE    DONE       DONE      12/02/10   11/19/10   11/09/07   12/08/09   02 - 16                1,408,920     1,408,920  HCM             0           0           0 Ashley McGraw Architects                0      08/30/12                       09/04/12           
11-1324   Reconstruction               0-015-007  10/09/12     DONE    DONE       DONE      05/21/12   05/18/12   03/28/12   12/06/09   2,7,8,9,155,15,16      1,176,595     1,176,595  HCM             0           0      24,708 Ashley McGraw Architects                0      09/01/13                       09/03/13           

          Track Storage Building:
12-0828   New Construction             2-020-001  04/26/13     DONE    DONE       DONE      02/14/13   02/11/13   01/17/13   12/08/09   02 - 16                   81,500             0  JMB             0           0           0 Ashley McGraw Architects                0        /  /                           /  /             

          Clyde Bus Garage:
10-0510   Additions and Alterations    4-002-006  03/16/11     DONE    DONE       DONE      12/02/10   11/19/10   11/09/07   12/08/09   02 - 16                  592,103       592,103  HCM             0           0           0 Ashley McGraw Architects                0      08/30/12                       09/04/12           

          Savannah Bus Garage:
10-0511   Additions and Alterations    4-003-003  03/16/11     DONE    DONE       DONE      12/19/10   12/19/10   11/09/07   12/08/09   02 - 16                   49,538        49,538  HCM             0           0           0 Ashley McGraw Architects                0      08/30/12                       09/04/12           

          Field House:
10-0512   Reconstruction               7-005-002  03/16/11     DONE    DONE       DONE      12/02/10   11/19/10   11/16/10   12/08/09   8,16                      83,619             0  HCM             0           0           0 Ashley McGraw Architects                0      08/30/12                       09/04/12           
11-1325   Reconstruction               7-005-003  10/09/12     DONE    DONE       DONE      05/21/12   05/18/12   03/28/12   12/06/11   2,4,8,9,10,155,15,16     236,000             0  HCM             0           0           0 Ashley McGraw Architects                0      09/01/13                       09/03/13           

          Press Box - High School:
01-1081DB Discovered Building          7-018-001  03/01/10     DONE    DONE       DONE      03/28/02     /  /     10/23/98     /  /     02 - 16                        0             0  MAC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LYONS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-05-01-04
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle / High School:
09-1085   Reconstruction               0-001-009  08/20/10     DONE    DONE       DONE      03/16/10   03/09/10   08/26/08   12/15/09   10,16                    731,360       731,360  HCM             0           0      28,579 MOSSIEN ASSOCIATES                      0      05/11/12                         /  /             
  -       Reconstruction               0-001-010                                              /  /       /  /     12/16/14     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          Elementary School:
09-1086   Reconstruction               0-002-009  08/20/10     DONE    DONE       DONE      03/16/10   03/09/10   08/26/08   12/15/09   10,16                    800,260       800,260  HCM             0           0      32,179 MOSSIEN ASSOCIATES                      0      05/11/12                         /  /             
  -       Reconstruction               0-002-011                                              /  /       /  /     12/16/14     /  /     2,7                            0             0  JMB             0           0           0                                         0        /  /                           /  /             

          New Bus Garage/Fuel Facility:
09-1087   Reconstruction               5-014-002  08/20/10     DONE    DONE       DONE      03/16/10   03/09/10   08/26/08   12/15/09   10,16                     68,380        68,380  HCM             0           0           0 MOSSIEN ASSOCIATES                      0      05/11/12                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARION CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-07-01-04
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Marion Elementary:
11-0815   Reconstruction               0-001-011  04/16/12     DONE    DONE       DONE      02/14/12   02/13/12   10/20/08   03/16/05   2,4,8,9,15,16            680,500       680,500  DDJ             0           0           0 SEI Design Group                        0      10/18/12                       11/29/12         YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-012                                              /  /       /  /     07/22/14     /  /     2,7,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             

          Jr/Sr High School:
11-0816   Reconstruction               0-005-013  04/16/12     DONE    DONE       DONE      02/14/12   02/13/12   10/12/10   03/16/05   8,9,155,15,16             18,300        18,300  DDJ             0           0           0 SEI Design Group                        0      10/18/12                       11/20/12         YES
                                                                                                                                                                                                                                                                                                                                   
12-0636   Reconstruction               0-005-014  02/01/13     DONE    DONE       DONE      01/07/13   01/03/13   11/02/12   12/11/12   7,15                   1,602,470     1,602,470  DDJ             0           0     141,017 SEI Design Group                        0      10/03/14                       12/16/14         YES
                                                                                                                                                                                                                                                                                                                                   
13-0643   Reconstruction               0-005-015  05/21/14     DONE    DONE       DONE      10/28/13   10/28/13   03/01/13   12/11/12   2,4,8,10,16            1,196,256             0  DDJ             0           0     109,491 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-0580   Reconstruction               0-005-016                         UNREVIEWED         11/05/14   11/04/14   07/22/14   07/07/14   2,7,16                         0    19,352,000  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   
14-0322   Reconstruction               0-005-017  11/04/14     DONE    DONE       DONE      09/22/14   09/19/14   07/22/14   05/20/14   10                       100,000             0  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          Marion Bus Garage/bus storage facili:
14-0581   Reconstruction               5-002-005                         UNREVIEWED         11/05/14   11/04/14   09/17/14   07/07/14   2,7,16                         0             0  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   

          New Bus Garage & Fueling Station:
  -       Reconstruction               5-006-002                                              /  /       /  /     09/24/14     /  /     2,7,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WAYNE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-08-01-06
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          James A Beneway High School:
12-0247   Additions and Alterations    0-001-009  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   01/25/12   12/14/11   02 - 16                4,629,024     4,629,024  DDJ             0           0     300,000 Clark Patterson Lee                     0        /  /                           /  /             
12-0218   Reconstruction               0-001-010  05/31/13     DONE    DONE       DONE      09/27/12   09/27/12   08/09/12   07/12/12   2,155,15,16            1,472,199             0  DDJ             0           0           0 Clark Patterson Lee             1,472,199        /  /                           /  /             

          Ontario Elementary School:
12-0248   Additions and Alterations    0-002-011  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   01/25/12   12/14/11   02 - 16                1,185,287             0  DDJ             0           0      75,000 Clark Patterson Lee                     0        /  /                           /  /             
12-0219   Reconstruction               0-002-012  05/31/13     DONE    DONE       DONE      09/27/12   09/27/12   08/09/12   07/12/12   2,155,15,16              395,801             0  DDJ             0           0           0 Clark Patterson Lee               395,801        /  /                           /  /             

          Ontario Primary School:
12-0249   Additions and Alterations    0-004-012  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   01/25/12   12/14/11   02 - 16                1,627,228             0  DDJ             0           0     100,000 Clark Patterson Lee                     0        /  /                           /  /             
12-0220   Reconstruction               0-004-013  05/31/13     DONE    DONE       DONE      09/27/12   09/27/12   08/09/12   07/12/12   2,155,15,16              199,624             0  DDJ             0           0           0 Clark Patterson Lee               199,624        /  /                           /  /             

          Armstrong Middle School:
12-0250   Additions and Alterations    0-006-010  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   01/25/12   12/14/11   02 - 16                4,704,731             0  DDJ             0           0     289,921 Clark Patterson Lee                     0        /  /                           /  /             
12-0221   Reconstruction               0-006-011  05/31/13     DONE    DONE       DONE      09/27/12   09/27/12   08/09/12   07/12/12   2,155,15,16            1,208,933             0  DDJ             0           0           0 Clark Patterson Lee             1,208,933        /  /                           /  /             

          Freewill Elementary:
12-0251   Additions and Alterations    0-007-009  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   01/25/12   12/14/11   02 - 16                2,269,073             0  DDJ             0           0     100,000 Clark Patterson Lee                     0        /  /                           /  /             
12-0222   Reconstruction               0-007-010  05/29/13     DONE    DONE       DONE      09/27/12   09/27/12   08/09/12   07/12/12   2,155,15,16              377,294             0  DDJ             0           0           0 Clark Patterson Lee               377,294        /  /                           /  /             

          Maintenance Building:
12-0223   Reconstruction               3-003-008  05/29/13     DONE    DONE       DONE      09/27/12   09/27/12   09/11/12   07/12/12   15,16                      5,701             0  DDJ             0           0           0 Clark Patterson Lee                 5,701        /  /                           /  /             

          Bus Garage:
12-0252   Additions and Alterations    5-005-011  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   01/25/12   12/14/11   02 - 16                  144,082             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
12-0224   Reconstruction               5-005-012  05/29/13     DONE    DONE       DONE      09/27/12   09/27/12   08/09/12   07/12/12   2,15,16                   76,685             0  DDJ             0           0           0 Clark Patterson Lee                76,685        /  /                           /  /             

          Concession Stand:
  -       New Construction             7-011-001                                              /  /       /  /     08/08/12     /  /     02 - 16                        0             0  DDJ             0           0           0                                         0        /  /                           /  /             
12-0253   New Construction             7-017-001  05/03/13     DONE    DONE       DONE      10/03/12   09/24/12   09/21/09   12/14/11   02 - 16                  312,471             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PALMYRA-MACEDON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-09-01-06
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
09-0855   Additions and Alterations    0-001-013  06/07/10     DONE    DONE       DONE      02/04/10   02/01/10   09/24/09   05/15/07   02 - 16                1,738,301       839,915  JOD             0           0           0 SWBR Architects P.C.                    0      11/30/11                       06/27/13           
14-0037   Reconstruction               0-001-014  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/13/13   4,7,9,155,15,16        5,467,100             0  JMB             0           0           0 King & King Architects                  0        /  /                           /  /             

          Primary School:
09-0856   Reconstruction               0-002-004  06/07/10     DONE    DONE       DONE      02/04/10   02/01/10   09/24/09   05/15/07   8,9,155                  252,501       252,501  JOD             0           0           0 SWBR Architects P.C.                    0      11/30/11                       06/27/13           
14-0038   Reconstruction               0-002-005  11/03/14     DONE    DONE       DONE      07/23/14   07/07/04   01/07/14   12/13/13   2,15,16                  192,200             0  JMB             0           0           0 King & King Architects                  0        /  /                           /  /             

          Intermediate School:
14-0039   Reconstruction               0-003-012  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/13/13   9,15                      89,500             0  JMB             0           0           0 King & King Architects                  0        /  /                           /  /             

          Middle School:
14-0040   Reconstruction               0-008-007  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/13/13   15,16                     39,900             0  JMB             0           0           0 King & King Architects                  0        /  /                           /  /             

          Transportation Facility:
14-0041   Reconstruction               5-014-002  11/03/14     DONE    DONE       DONE      07/23/14   07/07/14   01/07/14   12/19/13   2,4,8,155,15,16          511,400             0  JMB             0           0           0 King & King Architects                  0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GANANDA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-09-02-04
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School Bldg:
10-0056   Reconstruction               0-001-015  02/18/11     DONE    DONE       DONE      07/29/10   07/15/10   04/06/10   03/20/07   7,155,15,16               42,343        42,343  DDJ             0           0           0 Clark Patterson Lee                     0      09/30/11                       03/11/13           

          Richard Mann Elem (fmly New Primary):
10-0057   Reconstruction               0-002-010  02/18/11     DONE    DONE       DONE      07/29/10   07/15/10   04/06/10   03/20/07   2,7,8,9,10,16                  0    15,893,760  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
13-1602   Reconstruction               0-002-011  06/30/14     DONE    DONE       DONE      06/10/14   06/09/14   05/20/14   05/20/14   4,7,8,9,16               100,000             0  DDJ             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               0-002-012                                              /  /       /  /     12/01/14     /  /     4,7                            0             0  DDJ             0           0           0                                         0        /  /                           /  /             

           9-12 High School:
10-0058   Reconstruction               0-004-004  02/18/11     DONE    DONE       DONE      07/29/10   07/15/10   04/06/10   03/20/07   2,4,7,9,10,16            273,787       273,787  DDJ             0           0           0 Clark Patterson Lee                     0      09/30/11                       03/11/13           

          Maintance Building:
10-0445DB Discovered Building          2-007-001                       ADDENDUM REQ'D       11/08/10   11/03/10   09/01/10     /  /                                    0             0  DDJ             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SODUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-12-01-06
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sodus Middle/High School:
14-0176   Reconstruction               0-001-013  11/12/14     DONE    DONE       DONE      08/14/14   08/13/14   06/26/14   06/10/14   4,8,9,10                  48,488             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             
14-0146   Reconstruction               0-001-014               STARTED DONE       UNREVIEWED08/13/14   08/13/14   06/26/14   04/29/14   2,4,8,9,10,155,15,16           0             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             
  -       Reconstruction               0-001-015                                              /  /       /  /     06/26/14     /  /     2,4,8,9,10,155,15,16           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Sodus Primary:
  -       Reconstruction               0-004-012                                              /  /       /  /     06/26/14     /  /     2,4,8,9,10,155,15,16           0             0  MFS             0           0           0                                         0        /  /                           /  /             

          Ath. Storage HS(Comm.Bldg.):
14-0147   Reconstruction               7-010-002               STARTED DONE       UNREVIEWED08/13/14   08/13/14   06/26/14   04/29/14   8,9,13,155,15,16               0             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Press Box:
14-0148   New Construction             7-012-001               STARTED DONE       UNREVIEWED08/13/14   08/13/14   06/26/14   04/29/14   02 - 16                        0             0  MFS             0           0           0 SEI Design Group                        0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WILLIAMSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-14-02-04
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Williamson Elementary School:
11-1012   Reconstruction               0-001-009  08/08/12     DONE    DONE       DONE      03/26/12   03/22/12   03/25/11   12/14/11   155,16                   574,891       574,891  JOD             0           0           0 IBC Engineering,P.C.              574,891      08/23/13                       11/19/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-0471   Reconstruction               0-001-010  06/20/13     DONE    DONE       DONE      11/21/12   11/13/12   12/01/11   03/20/12   7,10,155,15,16           812,442       812,442  DDJ             0           0           0 SEI Design Group                        0      11/05/14                       12/17/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Williamson Middle School:
11-1013   Reconstruction               0-002-008  08/08/12     DONE    DONE       DONE      03/26/12   03/22/12   03/25/11   12/14/11   155,16                   847,517       847,517  JOD             0           0           0 IBC Engineering,P.C.              847,517      08/23/13                       11/19/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-0472   Reconstruction               0-002-009  06/20/13     DONE    DONE       DONE      11/21/12   11/13/12   12/01/11   03/20/12   7,10,13,155,15,16        412,920       412,920  DDJ             0           0           0 SEI Design Group                        0      11/05/14                       12/17/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Williamson Senior High School:
11-1014   Reconstruction               0-006-007  08/08/12     DONE    DONE       DONE      03/26/12   03/22/12   03/25/11   12/14/11   155,16                   365,111       365,111  JOD             0           0           0 IBC Engineering,P.C.              365,111      08/23/13                       11/19/13         YES
                                                                                                                                                                                                                                                                                                                                   
12-0473   Reconstruction               0-006-008  06/20/13     DONE    DONE       DONE      11/21/12   11/13/12   12/01/11   03/20/12   2,7,10,155,15,16       1,339,368     1,339,368  DDJ             0           0           0 SEI Design Group                        0      11/05/14                       12/17/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Administration Building:
  -       Reconstruction               1-003-002                                              /  /       /  /     03/25/11     /  /     155,16                         0             0  JOD             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
11-1015   Reconstruction               5-004-004  08/08/12     DONE    DONE       DONE      03/26/12   03/22/12   03/25/11   12/14/11   155,16                    24,587        24,587  JOD             0           0           0 IBC Engineering,P.C.               24,587      08/23/13                       11/19/13         YES
                                                                                                                                                                                                                                                                                                                                   

          First United Methodist Church:
10-0173TQ Temporary Quarters           8-011-001  10/13/10     DONE    DONE       DONE      08/27/10   08/23/10   07/27/10     /  /                                    0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH ROSE - WOLCOTT CENTRAL SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-15-01-06
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
11-1030   Reconstruction               0-001-015                       ADDENDUM REQ'D       03/28/12   03/16/12   02/03/12     /  /     2,4,8,9,10,155,15,16           0             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          North Rose Elementary School:
10-0293   Reconstruction               0-007-012  01/27/11     DONE    DONE       DONE      09/29/10   09/22/10   09/08/10   03/05/07   2,4,7,8,9,155,15,16    2,130,000     2,130,000  HCM             0           0     202,350 SEI Design Group                        0      08/31/11                       06/21/13           
11-1031   Reconstruction               0-007-013                       ADDENDUM REQ'D       03/28/12   03/16/12   02/03/12     /  /     2,4,8,9,10,155,15,16           0             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          High School:
11-1032   Reconstruction               0-010-013                       ADDENDUM REQ'D       03/28/12   03/16/12   02/03/12     /  /     2,8,9,155,15,16                0             0  HCM             0           0           0 SEI Design Group                        0        /  /                           /  /             

          Baseball Storage Shed:
  -    DB Discovered Building          2-022-001                                              /  /       /  /     05/17/12     /  /                                    0             0  HCM             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RED CREEK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 65-15-03-04
last updated on 12/19/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Building:
11-0823   Reconstruction               0-006-006  06/26/12     DONE    DONE       DONE      02/21/12   02/21/12   09/20/10   03/27/09   2,4,7,8,9,14,155,15,   1,000,000     1,000,000  HCM             0           0           0 GLYNN SPILLANE GRIFFING ARCHI           0      12/12/12                       03/15/13           
12-0835   Reconstruction               0-006-007  05/15/14     DONE    DONE       DONE      02/14/13   02/13/13   08/14/12   09/06/12   2,4,7,8,9,155,15,16      100,000       100,000  JMB             0           0           0 C&S Companies                           0        /  /                           /  /             

          Bus Garage:
09-1140   Additions and Alterations    5-004-005  09/07/10     DONE    DONE       DONE      03/25/10   03/17/10   08/21/06   03/29/07   02 - 16                  675,000       675,000  HCM             0           0           0 Glynn Spillane Griffing Archi           0      02/01/12                         /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED