Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 12/17/14 at 12:21:29




ATTICA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 67-02-01-06
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
09-0791   Reconstruction               0-001-017  02/18/10     DONE    DONE       DONE      01/25/10   01/22/10   06/10/09   12/05/06   2,9                      127,531       127,531  JOD             0           0      16,069 Habiterra Associates                    0      12/27/10                         /  /           YES
                                                                                                                                                                                                                                                                                                                                   
  -       Reconstruction               0-001-018                                              /  /       /  /     01/31/14     /  /     155,16                         0             0  DDJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LETCHWORTH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 67-04-01-04
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Lockwood El/Letch HS:
13-1050   Reconstruction               0-001-007  04/10/14     DONE    DONE       DONE      01/16/14   01/16/14   06/05/13   10/29/13   2,4,8,9,10,14,155,15     752,035       752,035  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
13-1696   Reconstruction               0-001-008  12/05/14     DONE    DONE       DONE      07/03/14   06/27/14   06/17/13   10/29/13   2,9,10,155,15,16       3,205,765             0  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             
13-1697   Reconstruction               0-001-009  12/05/14     DONE    DONE       DONE      07/03/14   06/27/14   11/04/13   10/29/13   2,4,9,10               1,097,000             0  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             

          Bus Garage:
  -    XX Reconstruction               5-004-008                         CANCELLED            /  /       /  /     06/05/13     /  /     2,8,9,10,155,16                0             0  JMB             0           0           0                                         0        /  /                           /  /             
13-1698   Reconstruction               5-004-009  12/05/14     DONE    DONE       DONE      07/03/14   06/27/14   07/15/13   10/29/13   2,4,8,9,155,15,16        585,200             0  JMB             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PERRY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 67-12-01-06
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Perry High School:
  -       Reconstruction               0-001-014                                              /  /       /  /     02/29/12     /  /     7                              0             0  HCM             0           0           0                                         0        /  /                           /  /             
13-0473   Reconstruction               0-001-015  04/11/14     DONE    DONE       DONE      10/08/13   10/04/13   09/14/12   12/04/12   2,4,8,9,155,15,16      1,052,000             0  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             
12-0957   Reconstruction               0-001-016  03/25/13     DONE    DONE       DONE      03/11/13   03/11/13     /  /     12/04/12   7                      1,851,000     1,851,000  JMB             0           0      16,481 Clark Patterson Lee                     0      04/03/14                       05/12/14           

          New Elementary School:
13-0474   Reconstruction               0-005-004  04/11/14     DONE    DONE       DONE      10/08/13   10/04/13   09/14/12   12/04/12   4,8,9,155,15,16          528,000             0  JMB             0           0           0 Clark Patterson Lee                     0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WARSAW CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 67-15-01-04
last updated on 12/17/14
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE             CERT. OCC.    CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Warsaw Elem.(frmly HS):
12-1065   Reconstruction               0-001-009  06/06/13     DONE    DONE       DONE      04/02/13   04/01/13   12/26/12   05/21/13   4,8,9,10,16              100,000       100,000  DDJ             0           0           0 Hunt Engineers & Architects &           0      04/27/14                       06/26/14         YES
                                                                                                                                                                                                                                                                                                                                   

          Court Street Middle/HS (frmr ES):
13-1694   Reconstruction               0-007-009  10/03/14     DONE    DONE       DONE      07/02/14   06/30/14   05/29/14   06/03/14   4,7,8,9,10,155,15,16     100,000             0  DDJ             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /           YES
                                                                                                                                                                                                                                                                                                                                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED