COLUMBIA COUNTY

COLUMBIA COUNTY

BERKSHIRE UFSD 100308
CHATHAM 101001
COPAKE-TACONIC 100501
GERMANTOWN 100902
HUDSON 101300
KINDERHOOK 101401
NEW LEBANON 101601

















Overdue Final Cost Reports

Projects Missing Substantial Completion Dates

Without the Substantial Completion Date We Cannot Warn You When the FCR is Due

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/29/08 at 14:21:45




BERKSHIRE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-03-08-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




TACONIC HILLS CSD AT CRARYVILLE SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-05-01-04
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           New K-12 School:
06-0226    Reconstruction               0-017-004  01/03/07   2,155                          0      395,000     /  /        /  /    HCM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GERMANTOWN CENTRAL SCHOOL DISTRICT SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-09-02-04
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CHATHAM CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-10-01-04
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Middle School:
04-1186    Reconstruction               0-002-013  06/29/05   2,4,7,9,13,155,15,16           0      600,000   10/01/05      /  /    DDJ

           Mary Dardess Elementary:
00-0285    Reconstruction               0-003-015  10/02/00   155,15,16                      0      120,000   12/30/00      /  /    MAC

           High School:
92-0902    Reconstruction               0-005-002  04/12/93   155,16                         0       45,000   08/01/93      /  /    MEM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HUDSON CITY SCHOOL SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-13-00-01
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           John Edwards Elementary:
95-1255    Reconstruction               0-010-005  06/06/96   2,7,8,9,10,14,155,16           0    1,000,000   08/31/97      /  /    MFK
96-1410    Reconstruction               0-010-006  05/23/97   14                             0      180,000   08/04/97      /  /    BJB

           New Elementary School:
95-0594    New Construction             0-013-001  04/10/96   02 - 16                        0   21,465,000   08/01/97      /  /    MFK


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ICHABOD CRANE (KINDERHOOK) CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-14-01-04
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Martin H. Glynn School:
04-1298    Reconstruction               0-003-009  07/28/05   2,13,15,16                     0      161,400   09/01/05      /  /    HCM
05-0465    Additions and Alterations    0-003-011  02/08/06   02 - 16                        0      561,960     /  /        /  /    HCM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




NEW LEBANON CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 10-16-01-04
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Bus Garage:
00-1319    Reconstruction               5-003-004  04/25/01   8                              0       34,341   12/01/01      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition