NASSAU COUNTY

NASSAU COUNTY

BALDWIN 280210
BELLMORE 280207
BELLMORE-MERRI 280253
BETHPAGE 280521
CARLE PLACE 280411
EAST MEADOW 280203
EAST ROCKAWAY 280219
EAST WILLISTON 280402
ELMONT 280216
FARMINGDALE 280522
FLORAL PARK 280222
FRANKLIN SQUAR 280217
FREEPORT 280209
GARDEN CITY 280218
GLEN COVE 280100
GREAT NECK 280407
HEMPSTEAD 280201
HERRICKS 280409
HEWLETT WOODME 280214
HICKSVILLE 280517
ISLAND PARK 280231
ISLAND TREES 280226
JERICHO 280515
LAWRENCE 280215
LEVITTOWN 280205
LOCUST VALLEY 280503
LONG BEACH 280300
LYNBROOK 280220
MANHASSET 280406
MALVERNE 280212
MASSAPEQUA 280523
MERRICK 280225
MINEOLA 280410
NASSAU BOCES 289000
NEW HYDE PARK 280405
NORTH BELLMORE 280204
NORTH MERRICK 280229
NORTH SHORE 280501
OCEANSIDE 280211
OYSTER BAY 280506
PLAINEDGE 280518
PLAINVIEW 280504
PORT WASHINGTO 280404
ROCKVILLE CENT 280221
ROOSEVELT 280208
ROSLYN 280403
SEAFORD 280206
SEWANHAKA 280252
SYOSSET 280502
UNIONDALE 280202
VALLEY STR CHS 280251
VALLEY STR UF 280230
V STR THIRTEEN 280213
V STR TWENTY-F 280224
WANTAGH 280223
WESTBURY 280401
WEST HEMPSTEAD 280227
















Overdue Final Cost Reports

Projects Missing Substantial Completion Dates

Without the Substantial Completion Date We Cannot Warn You When the FCR is Due

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 05/29/08 at 14:21:46




GLEN COVE CITY SCHOOLS SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-01-00-01
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Connolly Elementary School:
05-0275    Additions and Alterations    0-007-011  03/28/06   02 - 16                        0      863,548   01/31/06      /  /    RDR

           Landing Elementary School:
05-0276    Additions and Alterations    0-008-011  04/26/06   02 - 16                        0      685,420   01/01/06      /  /    RDR

           Eugene J. Gribbin Elementary:
04-1361    Reconstruction               0-013-007  06/15/06   10,155,16                      0      155,281   01/01/06      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HEMPSTEAD UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-01-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Middle School:
05-0042    Reconstruction               0-001-020  04/06/06   2,4,7,9,155,15,16              0    3,545,000     /  /        /  /    JOD
05-0041    Reconstruction               0-001-021  01/09/06   2,4,9,155,15,16                0    1,140,000     /  /        /  /    JOD

           Senior High School:
00-1456    Reconstruction               0-020-014  08/27/01   7                              0      170,000   06/30/01      /  /    BJB
03-0102    Reconstruction               0-020-016  10/06/03   13                             0      466,000   12/31/03      /  /    MGL
03-0103    Reconstruction               0-020-017  09/25/03   13                             0      275,000   12/31/03      /  /    MGL
06-0353    Reconstruction               0-020-020  10/23/06   4,13                           0      110,000     /  /        /  /    JOD
06-0354    Reconstruction               0-020-022  10/23/06   2,4,8,9,10,155,15,16           0   11,253,303     /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




UNIONDALE PUBLIC SCHOOLS SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-02-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Northern Parkway School:
04-0944    Reconstruction               0-002-025  05/04/05   2,4,10,16                      0       34,000   09/01/05      /  /    RDR
06-0025    Reconstruction               0-002-027  07/12/06   2,4,8,9                        0       16,550   09/01/06      /  /    RDR

           Smith Street School:
00-0940    Reconstruction               0-004-014  07/10/01   155                            0       16,897   09/01/01      /  /    RDR
05-1034    Reconstruction               0-004-022  07/12/06   2,9                            0       29,500   09/01/06      /  /    RDR

           Cornelius Court School:
05-1035    Reconstruction               0-005-011  07/12/06   2,4,8,9                        0      204,484   09/01/06      /  /    RDR

           Lawrence Road Junior High:
97-0670    Reconstruction               0-008-013  01/27/98   16                             0       30,000   12/01/98      /  /    RDR

           Uniondale High School:
97-1426    Reconstruction               0-009-018  05/19/98   2                              0       55,000   08/14/98      /  /    RDR
02-0301    Reconstruction               0-009-029  10/23/02   13,16                          0       50,000   09/01/03      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




EAST MEADOW UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-03-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Parkway Elementary:
00-0250    Reconstruction               0-001-015  01/09/01   8                              0       65,100   09/01/01      /  /    MGL
01-0319    Additions and Alterations    0-001-018  05/21/02   02 - 16                        0    3,506,477   12/15/02      /  /    MGL
00-0262    Reconstruction               0-001-019  11/14/00   8                              0      407,445   09/01/01      /  /    MGL
00-0163    Reconstruction               0-001-020  12/11/00   9                              0       47,424   09/30/01      /  /    MGL
00-0837    Reconstruction               0-001-021  05/30/01   2,13,14,15                     0      147,522   09/01/01      /  /    MGL
00-0317    Reconstruction               0-001-022  01/11/01   155,15,16                      0      457,826   09/01/01      /  /    MGL
00-1824    Reconstruction               0-001-023  07/30/01   14,16                          0      178,043   09/01/01      /  /    MGL
02-2138    Reconstruction               0-001-025  05/18/04   16                             0      151,356   12/31/03      /  /    DDJ
05-0576    Reconstruction               0-001-026  04/06/06   2,7,9                          0      141,356   09/01/06      /  /    DDJ

           Meadowbrook Elementary:
00-0251    Reconstruction               0-002-014  01/09/01   8                              0       49,219   09/01/01      /  /    MGL
01-0259    Additions and Alterations    0-002-017  05/29/02   02 - 16                        0    3,087,046   12/15/02      /  /    MGL
00-0263    Reconstruction               0-002-018  11/14/00   8                              0      221,006   09/01/01      /  /    MGL
00-0164    Reconstruction               0-002-019  12/11/00   9                              0       25,409   09/30/01      /  /    MGL
00-0838    Reconstruction               0-002-020  05/30/01   2,10,14                        0      147,522   09/01/01      /  /    MGL
00-0318    Reconstruction               0-002-021  01/11/01   155,15,16                      0      432,391   09/01/01      /  /    MGL
00-1825    Reconstruction               0-002-022  07/30/01   14,16                          0      178,043   09/01/01      /  /    MGL
02-2139    Reconstruction               0-002-023  05/18/04   16                             0      156,481   12/31/03      /  /    DDJ
05-0577    Reconstruction               0-002-024  04/06/06   2,9                            0       26,906   09/01/06      /  /    DDJ

           W T Clarke Middle/High School:
00-0252    Reconstruction               0-004-016  01/09/01   8                              0      129,864   09/01/01      /  /    MGL
98-0798    Reconstruction               0-004-018  05/07/99   2,7,8,9,155,15,16              0      609,500   09/01/98      /  /    MGL
99-1293    Reconstruction               0-004-020  05/16/00   2,7                            0    1,034,337   09/01/01      /  /    MGL
01-0005    Additions and Alterations    0-004-021  01/23/02   02 - 16                        0    5,466,700   09/01/02      /  /    MGL
00-0839    Reconstruction               0-004-022  05/30/01   2,10,13,14,155,15,16           0      748,413   09/01/01      /  /    MGL
00-0264    Reconstruction               0-004-023  11/14/00   8                              0    1,373,126   09/01/01      /  /    MGL
03-0969    Reconstruction               0-004-024  06/01/04   8,9                            0      697,635   10/15/04      /  /    DDJ
00-1128    Reconstruction               0-004-025  07/23/01   10                             0      600,000   09/01/01      /  /    MGL
00-0319    Reconstruction               0-004-026  01/11/01   155,15,16                      0      554,478   09/01/01      /  /    MGL
00-1826    Reconstruction               0-004-030  07/30/01   14,16                          0       50,869   09/01/01      /  /    MGL
02-2140    Reconstruction               0-004-032  05/18/04   16                             0      485,610   12/31/03      /  /    DDJ
05-0578    Reconstruction               0-004-035  04/06/06   2,10                           0       32,156   09/01/06      /  /    DDJ

           Barnum Woods Elementary:
00-0253    Reconstruction               0-006-015  01/09/01   8                              0       80,272   09/01/01      /  /    MGL
99-1294    Reconstruction               0-006-016  05/16/00   2,7                            0      371,174   09/01/01      /  /    MGL
00-0165    Reconstruction               0-006-017  12/11/00   8,9                            0       51,606   09/30/01      /  /    MGL
00-0265    Reconstruction               0-006-018  11/14/00   2,8,14,155,15,16               0      612,162   09/01/01      /  /    MGL
00-0320    Reconstruction               0-006-020  01/11/01   155,15,16                      0      432,391   09/01/01      /  /    MGL
00-0840    Reconstruction               0-006-022  05/30/01   2,13,14,15                     0      213,652   09/01/01      /  /    MGL
00-1827    Reconstruction               0-006-023  07/30/01   14,16                          0      178,043   09/01/01      /  /    MGL
02-2141    Reconstruction               0-006-024  05/18/04   16                             0      189,728   12/31/03      /  /    DDJ
05-0579    Reconstruction               0-006-025  04/06/06   2,9                            0       36,251   09/01/06      /  /    DDJ

           East Meadow High School:
00-1703    Additions and Alterations    0-007-023  12/10/01   02 - 16                        0    2,792,856   09/30/02      /  /    MGL
00-0254    Reconstruction               0-007-024  01/09/01   8                              0      133,928   09/01/01      /  /    MGL
00-0233    Reconstruction               0-007-027  11/08/00   2,14                           0       19,080   09/01/01      /  /    MGL
00-0266    Reconstruction               0-007-029  11/14/00   8                              0    1,688,310   09/01/01      /  /    MGL
00-1129    Reconstruction               0-007-030  07/23/01   2,9,155,16                     0      600,000   09/01/01      /  /    MGL
00-0841    Reconstruction               0-007-031  05/30/01   2,10,14,15                     0      724,891   09/01/01      /  /    MGL
00-1828    Reconstruction               0-007-032  07/30/01   10                             0      178,043   09/01/01      /  /    MGL
02-2142    Reconstruction               0-007-034  05/18/04   16                             0      438,109   12/31/03      /  /    DDJ
05-0580    Reconstruction               0-007-036  04/06/06   2,8,9,10                       0       77,006   09/01/06      /  /    DDJ

           Woodland Middle School:
00-0255    Reconstruction               0-009-012  01/09/01   2,7,8,9,15,16                  0       73,920   09/01/01      /  /    MGL
97-1733    Additions and Alterations    0-009-016  07/29/98   02 - 16                        0      140,400   09/01/98      /  /    MGL
01-0340    Additions and Alterations    0-009-018  02/14/02   02 - 16                        0    7,204,716   12/31/02      /  /    MGL
00-0267    Reconstruction               0-009-019  11/14/00   8                              0      663,646   09/01/01      /  /    MGL
00-1356    Reconstruction               0-009-020  04/09/01   7                              0    1,188,720   09/01/01      /  /    MGL
00-0842    Reconstruction               0-009-021  05/30/01   7                              0      586,957   09/01/01      /  /    MGL
03-1011    Reconstruction               0-009-022  06/01/04   8,9                            0      621,330   10/15/04      /  /    DDJ
02-1050    Reconstruction               0-009-026  01/31/03   4,7                            0       44,600   09/01/03      /  /    DDJ
02-2143    Reconstruction               0-009-027  05/18/04   16                             0      284,460   12/31/03      /  /    DDJ
05-0581    Reconstruction               0-009-029  04/06/06   2,9,16                         0       51,581   09/01/06      /  /    DDJ

           George McVey Elementary:
00-0256    Reconstruction               0-011-013  01/09/01   8                              0       96,904   09/01/01      /  /    MGL
00-0268    Reconstruction               0-011-015  11/14/00   8                              0      642,299   09/01/01      /  /    MGL
00-1358    Reconstruction               0-011-017  04/09/01   7                              0      932,256   09/01/01      /  /    MGL
00-0843    Reconstruction               0-011-018  05/30/01   2,14,15                        0      203,478   09/01/01      /  /    MGL
02-2144    Reconstruction               0-011-020  05/18/04   16                             0      214,045   12/31/03      /  /    DDJ
05-0582    Reconstruction               0-011-021  04/06/06   2,9                            0       35,831   09/01/06      /  /    DDJ

           Bowling Green #1:
00-0257    Reconstruction               0-012-014  01/09/01   8                              0      105,525   09/01/01      /  /    MGL
00-0269    Reconstruction               0-012-017  11/14/00   8                              0      692,528   09/01/01      /  /    MGL
00-0167    Reconstruction               0-012-018  12/11/00   9                              0       83,229   09/30/01      /  /    MGL
00-1357    Reconstruction               0-012-019  04/09/01                                  0      873,288   09/01/01      /  /    MGL
00-0844    Reconstruction               0-012-020  05/30/01   2,14,15                        0      254,348   09/01/01      /  /    MGL
00-0321    Reconstruction               0-012-021  01/11/01   155,15,16                      0      864,783   09/01/01      /  /    MGL
02-2145    Reconstruction               0-012-022  05/18/04   16                             0      243,324   12/31/03      /  /    DDJ
05-0583    Reconstruction               0-012-023  04/06/06   2,9,10                         0       51,058   09/01/06      /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




NORTH BELLMORE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-04-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Jacob Gunther Elementary:
05-0141    Reconstruction               0-001-017  10/11/05   2,13                           0       90,326   09/30/05      /  /    HCM

           Newbridge Road School:
05-0133    Reconstruction               0-003-020  10/26/05   8,9,155,15,16                  0       48,174   09/30/05      /  /    HCM

           Saw Mill Road School:
97-1845    Reconstruction               0-005-012  08/03/98   2,4,8,9                        0       42,000   09/01/98      /  /    MGL

           J.G. Dinkelmeyer Elementary:
01-1120    Reconstruction               0-006-015  08/26/02   9,13,16                        0      202,895   08/31/02      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




LEVITTOWN UNION FREE SCHOOL DISTRICT SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-05-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Jonas E. Salk Middle School & HighSc:
05-0982    Reconstruction               0-002-018  06/16/06   2,9,155,15,16                  0    1,035,551   11/30/06      /  /    RDR

           Division Avenue High School:
05-0983    Reconstruction               0-003-016  06/16/06   2,16                           0      226,000   11/30/06      /  /    RDR

           Northside School:
05-1303    Reconstruction               0-008-011  09/21/06   13                             0      595,669   11/30/06      /  /    MGL

           Abbey Lane School:
05-0987    Reconstruction               0-015-013  06/16/06   2,155,15,16                    0    1,003,515   11/30/06      /  /    RDR

           Storage/Maintenance Vehicles Equipme:
00-0293    New Construction             5-053-001  01/05/01   02 - 16                        0       71,500   09/01/01      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SEAFORD UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-06-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Seaford High School:
06-0338    Reconstruction               0-001-017  01/25/07   2,8,9,10,16                    0      203,000     /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BELLMORE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-07-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Charles A Reinhard Early Chldhd Ctr:
06-1276    Reconstruction               0-003-017  05/14/07   16                             0      141,000     /  /        /  /    HCM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ROOSEVELT UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-08-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           High School Renovation:
03-0411    Reconstruction               0-005-010  10/14/03   155                            0       73,000   12/31/03      /  /    RDR

           NEW MIDDLE SCHOOL:
05-0144    New Construction             0-029-001  08/22/05   02 - 16                        0   55,500,000     /  /        /  /    RDR

           New Ulysses Byas Elementary:
06-0233    New Construction             0-033-001  09/25/06   02 - 16                        0   31,500,000     /  /        /  /    MGL

           Districtwide:
04-0093    Reconstruction               7-999-002  08/11/02   2,4,8,9,155,15,16              0      987,202     /  /        /  /    RDR
04-0738    Reconstruction               7-999-003  08/11/02   4,9                            0      723,662   09/11/02      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




FREEPORT UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-09-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BALDWIN UNION FREE SD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-10-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Brookside Elementary:
06-0126    Reconstruction               0-001-010  10/16/06   16                             0       95,875   08/31/06      /  /    DDJ

           Lenox School:
06-0127    Reconstruction               0-005-012  10/16/06   16                             0       51,725   08/31/06      /  /    DDJ

           Milburn School:
06-0128    Reconstruction               0-006-012  10/16/06   16                             0      107,825   08/31/06      /  /    DDJ

           Plaza Elementary:
05-1064    Reconstruction               0-007-013  06/02/06   10                             0       30,000   08/31/06      /  /    DDJ
06-0129    Reconstruction               0-007-015  10/16/06   16                             0       83,325   08/31/06      /  /    DDJ

           Baldwin Senior High School:
06-0130    Reconstruction               0-009-023  10/16/06   13,16                          0      133,050   08/31/06      /  /    DDJ
05-0111    Reconstruction               0-009-026  11/02/05   16                             0      396,303     /  /        /  /    DDJ
05-1290    Reconstruction               0-009-029  09/06/06   16                             0      327,185   08/31/06      /  /    DDJ

           Shubert Elementary:
05-1180    Reconstruction               0-010-016  05/10/06   9                              0       65,350   08/31/06      /  /    DDJ

           Steele Elementary:
06-0131    Reconstruction               0-011-016  10/16/06   16                             0       84,225   08/31/06      /  /    DDJ
05-0689    Reconstruction               0-011-017  06/07/06   16                             0      161,170   08/31/06      /  /    DDJ

           Baldwin Middle School:
05-0874    Reconstruction               0-012-016  06/01/06   10                             0       55,000   08/31/06      /  /    DDJ
06-0132    Reconstruction               0-012-019  10/16/06   16                             0       80,875   08/31/06      /  /    DDJ
05-1206    Reconstruction               0-012-021  05/26/06   8                              0    1,630,000   08/31/06      /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




OCEANSIDE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-11-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Senior High School #7:
00-0645    Reconstruction               0-008-017  03/23/01   155,15,16                      0       40,250   09/01/01      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MALVERNE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-12-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Malverne Senior High:
05-0149    Reconstruction               0-001-010  12/07/05   10,15,16                       0       50,000     /  /        /  /    DDJ
04-1308    Reconstruction               0-001-011  12/23/05   155,15,16                      0      404,560   09/01/05      /  /    DDJ

           H.T. Herber Middle School:
04-1309    Reconstruction               0-002-012  12/23/05   155,15,16                      0    1,053,935   09/01/05      /  /    DDJ

           M W Downing School:
04-1310    Reconstruction               0-003-008  12/22/05   155,15,16                      0      637,060   09/01/05      /  /    DDJ

           Davison Ave School:
04-1311    Reconstruction               0-004-007  12/23/05   155,15,16                      0      355,975   09/01/05      /  /    DDJ

           Districtwide:
04-1418    Reconstruction               7-999-003  08/12/05   16                             0      100,000     /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




VALLEY STREAM 13 UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-13-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HEWLETT-WOODMERE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-14-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Franklin Early Childhood Center:
00-1888    Reconstruction               0-001-012  04/12/02   10,155,15,16                   0      687,980   09/30/01      /  /    RDR

           Hewlett Elementary School:
00-1299    Additions and Alterations    0-002-009  06/28/01   02 - 16                        0      225,970   09/30/01      /  /    RDR

           Ogden Elementary School:
00-1886    Additions and Alterations    0-003-010  04/12/02   02 - 16                        0      183,530   09/30/01      /  /    RDR

           George W. Hewlett High School:
00-0157    Reconstruction               0-006-017  11/01/00   2,15                           0    2,470,000   09/30/01      /  /    RDR
04-1032    Reconstruction               0-006-018  05/23/05   15,16                          0      735,000     /  /        /  /    RDR

           Recreation Building:
00-1890    Reconstruction               0-007-004  04/12/02   8,155,15,16                    0      143,130   09/30/01      /  /    RDR

           Modular #1 @ Woodmere MS:
00-1984    New Construction             0-020-001  12/14/01   02 - 16                        0      260,000   11/01/01      /  /    RDR

           Modular #2 @ Woodmere MS:
00-1985    New Construction             0-021-001  12/14/01   02 - 16                        0      260,000   11/01/01      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




LAWRENCE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-15-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Lawrence Jr. High School:
05-1361    Reconstruction               0-007-034  07/26/06   9,14,16                        0      184,080   11/01/06      /  /    HCM

           Districtwide:
99-0599    Reconstruction               7-999-003  12/23/99   16                             0    1,220,700   09/01/01      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ELMONT UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-16-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




FRANKLIN SQUARE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-17-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           John Street School:
06-1324    Reconstruction               0-003-014  05/10/07   2,7                            0      405,000     /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GARDEN CITY UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-18-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Homestead School:
05-1185    Reconstruction               0-001-004  06/23/06   7                              0       50,000   08/21/06      /  /    MGL

           Stratford Ave. School:
03-0210    Reconstruction               0-005-008  02/19/04   2,15                           0      200,000   05/01/04      /  /    RDR

           Garden City Jr. High:
05-0487    Reconstruction               0-006-012  05/18/06   8,9,13,15,16                   0      250,000     /  /        /  /    RDR
05-1186    Reconstruction               0-006-013  06/23/06   7                              0      523,000   08/21/06      /  /    MGL

           Garden City Sr. High:
05-0488    Reconstruction               0-007-012  05/18/06   8,9,13,15,16                   0      250,000     /  /        /  /    RDR

           Hemlock School:
05-1187    Reconstruction               0-018-005  06/23/06   7                              0      860,000   08/21/06      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




EAST ROCKAWAY UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-19-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Junior Senior High School:
02-0127    Reconstruction               0-001-018  12/02/02   7,9                            0      157,500   09/01/03      /  /    MAC
02-2130    Reconstruction               0-001-020  09/08/03   2,155                          0      116,487   09/01/03      /  /    RDR
06-1414    Reconstruction               0-001-026  05/08/07   2                              0      100,000     /  /        /  /    DDJ

           Centre Ave School:
02-2131    Reconstruction               0-003-011  06/04/03   7                              0       95,001   09/01/03      /  /    RDR

           Districtwide:
00-0516    Reconstruction               7-999-001  03/02/01   16                             0    2,639,326   09/01/01      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




LYNBROOK UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-20-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Marion Elementary School:
04-1031    Reconstruction               0-004-015  04/26/05   2,4,8                          0    1,501,953   08/31/05      /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ROCKVILLE CENTRE UDSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-21-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Riverside School:
00-1816    Reconstruction               0-001-013  06/04/01   7                              0      138,183   09/04/01      /  /    MGL
02-1115    Reconstruction               0-001-014  01/31/03   4                              0       50,000   09/01/03      /  /    MGL
04-1163    Reconstruction               0-001-015  07/05/05   2,4,7,8,9,155,15,16            0      683,317   09/30/05      /  /    JOD
05-0590    Reconstruction               0-001-016  02/21/07   9,155,15,16                    0      644,553   09/01/06      /  /    JOD

           Southside Middle:
97-0703    Additions and Alterations    0-002-010  12/31/97   02 - 16                        0      496,500   09/01/98      /  /    MGL
98-0136    Reconstruction               0-002-011  09/02/98   2,9                            0      102,600   09/01/98      /  /    MEM
98-0081    Reconstruction               0-002-012  09/02/98   2,15                           0       52,908   09/01/98      /  /    MGL
02-1116    Reconstruction               0-002-014  01/31/03   4,8                            0       30,000   09/01/03      /  /    MGL
04-0864    Reconstruction               0-002-015  06/13/05   2,4,7,8,9,155,15,16            0    3,538,214   09/01/05      /  /    JOD
04-1164    Reconstruction               0-002-016  07/05/05   2,7                            0      268,151   09/30/05      /  /    JOD
05-0249    Reconstruction               0-002-017  12/12/05   4                              0      615,989   09/01/06      /  /    JOD
05-0234    Reconstruction               0-002-018  12/29/05   8                              0      777,357   09/01/06      /  /    JOD
05-0591    Reconstruction               0-002-019  02/21/07   2,9,10,15                      0      504,446   09/01/06      /  /    JOD

           Floyd B Watson Elementary:
96-0571    Reconstruction               0-003-006  02/24/97   2,4,10,155,16                  0      400,679   09/01/97      /  /    MGL
95-1650    Alterations                  0-003-008  07/22/96   02 - 16                        0       35,893   11/01/96      /  /    MGL
04-1165    Reconstruction               0-003-012  07/05/05   2,4,7,8,9,155,15,16            0      176,095   09/30/05      /  /    JOD
05-0592    Reconstruction               0-003-013  02/21/07   9,10,155,15,16                 0      179,995   09/01/06      /  /    JOD

           Wilson Elementary:
96-0572    Reconstruction               0-004-006  02/24/97   2,4,7,155,16                   0      290,927   09/01/97      /  /    MGL
98-0137    Reconstruction               0-004-012  09/02/98   4,9                            0       44,280   09/01/98      /  /    MEM
01-0287    Reconstruction               0-004-015  09/26/01   155,15,16                      0       90,000   10/30/01      /  /    MGL
04-1166    Reconstruction               0-004-016  07/05/05   4,7,8,9,155,15,16              0      151,097   09/30/05      /  /    JOD
05-0235    Reconstruction               0-004-017  12/29/05   8                              0      395,094   09/01/06      /  /    JOD
05-0250    Reconstruction               0-004-018  12/12/05   4                              0      454,382   09/01/06      /  /    JOD
05-0593    Reconstruction               0-004-019  02/21/07   2,9,10,155,15,16               0      610,747   09/01/06      /  /    JOD

           031208Side Senior High:
94-1466    Reconstruction               0-005-006  06/09/95   7                              0       60,000   08/30/95      /  /    MEM
95-1088    Reconstruction               0-005-008  05/21/96   2                              0       18,000   09/30/96      /  /    MGL
96-0573    Reconstruction               0-005-009  02/24/97   2,7,9,155,16                   0      493,830   09/01/97      /  /    MGL
98-0082    Reconstruction               0-005-012  09/02/98   15,16                          0       59,257   09/01/98      /  /    MGL
99-1754    Reconstruction               0-005-013  08/17/00   8,9,155,16                     0       81,000   09/01/00      /  /    MGL
99-1311    Reconstruction               0-005-015  05/09/00   9,10                           0       14,825   09/01/00      /  /    MGL
00-0187    Reconstruction               0-005-016  10/04/00   9,10                           0       66,850   10/01/00      /  /    MGL
01-1377    Reconstruction               0-005-017  10/16/02   9,16                           0      109,522   07/30/02      /  /    MGL
04-0862    Reconstruction               0-005-019  06/10/05   4,8,9,155,15,16                0    1,031,291   09/01/05      /  /    JOD
04-1167    Reconstruction               0-005-020  07/05/05   2,7,8                          0    1,148,645   09/30/05      /  /    JOD
05-0251    Reconstruction               0-005-021  12/12/05   4                              0      138,840   09/01/06      /  /    JOD
05-0236    Reconstruction               0-005-022  12/29/05   8                              0    1,097,038   09/01/06      /  /    JOD

           Hewitt School:
96-0953    Additions and Alterations    0-007-007  03/20/97   02 - 16                        0      401,500   12/01/97      /  /    MGL
97-0704    Additions and Alterations    0-007-010  12/31/97   02 - 16                        0      420,000   09/01/98      /  /    MGL
04-0863    Reconstruction               0-007-011  06/10/05   2,4,7,8,9,155,15,16            0      230,867   09/01/05      /  /    JOD
04-1168    Reconstruction               0-007-012  07/05/05   2,4,7                          0      539,907   09/30/05      /  /    JOD
05-0252    Reconstruction               0-007-013  12/12/05   4                              0      439,318   09/01/06      /  /    JOD
05-0237    Reconstruction               0-007-014  12/27/05   8                              0      503,170   09/01/06      /  /    JOD
05-0594    Reconstruction               0-007-015  02/21/07   2,9,10,155,15,16               0      466,461   09/01/06      /  /    JOD

           William Covert:
01-1400    Reconstruction               0-008-010  01/08/03   155,15,16                      0    1,661,280   09/01/02      /  /    MGL
02-0716    Additions and Alterations    0-008-011  01/31/03   02 - 16                        0      926,367   09/01/03      /  /    JOD
04-1169    Reconstruction               0-008-013  07/05/05   2,9,155,15,16                  0       74,699   09/30/05      /  /    JOD
05-0595    Reconstruction               0-008-014  02/21/07   9,10,155,15,16                 0      303,944   09/01/06      /  /    JOD

           New Bldg. @ South Side HS:
02-0046    New Construction             0-026-001  08/28/03   02 - 16                        0      150,000   12/01/02      /  /    MGL

           District Wide:
97-1585    Reconstruction               7-999-003  06/26/98   16                             0    1,444,533   01/01/99      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




FLORAL PARK-BELLEROSE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-22-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           John Lewis Childs School:
00-1728    Reconstruction               0-001-017  05/12/01   155,16                         0       70,000   12/31/01      /  /    MGL
04-1175    Reconstruction               0-001-020  06/15/05   2,9                            0       13,400   09/01/05      /  /    HCM
05-1215    Reconstruction               0-001-022  11/16/06   16                             0      130,699   09/01/06      /  /    HCM

           Floral Pk-Bellerose School:
02-2319    Reconstruction               0-002-019  11/25/03   155,15,16                      0      138,800   12/31/03      /  /    MGL
04-1438    Reconstruction               0-002-021  06/15/05   2,9,10,16                      0      106,600   09/01/05      /  /    HCM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WANTAGH UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-23-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Forest Lake School:
98-0477    Reconstruction               0-005-007  01/27/99   4                              0       10,800   04/01/99      /  /    MEM

           Middle School:
97-0759    Reconstruction               0-006-009  03/06/98   7,8,9,13,16                    0       32,330   09/01/98      /  /    MEM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




VALLEY STREAM UFSD SCHOOL DIST. #24 SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-24-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MERRICK UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-25-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ISLAND TREES UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-26-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WEST HEMPSTEAD UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-27-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           George Washington Elementary School:
06-0743    Reconstruction               0-001-014  04/10/07   2,4                            0       52,900     /  /        /  /    DDJ
06-0742    Reconstruction               0-001-015  04/10/07   2,4                            0      365,000     /  /        /  /    DDJ

           Junior/Senior High:
98-1365    Reconstruction               0-005-016  05/13/99   4                              0      241,905   08/16/99      /  /    MEM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




NORTH MERRICK UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-29-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




VALLEY STREAM 30 UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-30-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ISLAND PARK UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-31-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Francis X Hegarty:
03-1540    Reconstruction               0-001-007  05/28/04   2                              0      278,500     /  /        /  /    MAC


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




VALLEY STREAM CENTRAL H.S. DISTRICT SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-51-07
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SEWANHAKA CENTRAL DISTRICT SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-52-07
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Sewanhaka High School:
02-2135    Additions and Alterations    0-002-026  10/31/03   02 - 16                        0      500,000   09/01/03      /  /    RDR
04-1048    Reconstruction               0-002-030  06/06/05   2,4                            0      600,000   09/30/05      /  /    RDR
05-1204    Reconstruction               0-002-032  09/20/06   4,14,15,16                     0      754,435   09/30/06      /  /    RDR
05-0800    Reconstruction               0-002-033  03/15/06   14,16                          0      354,750   09/30/06      /  /    RDR

           Floral Park Memorial High:
95-1578    Reconstruction               0-003-019  06/21/96   9,15,16                        0       21,650   11/30/96      /  /    RDR
02-2132    Additions and Alterations    0-003-028  10/31/03   02 - 16                        0      175,000   09/01/03      /  /    RDR
05-1203    Reconstruction               0-003-032  06/28/06   8                              0      266,062   09/30/06      /  /    MGL

           Hyde Park Memorial High:
02-2134    Additions and Alterations    0-004-025  10/31/03   02 - 16                        0      125,000   09/01/03      /  /    RDR
03-0251    Reconstruction               0-004-027  12/16/03   2,8,9,10,15,16                 0      759,530   09/01/04      /  /    RDR
04-0451    Reconstruction               0-004-028  12/07/04   7,8,9                          0      215,000   09/30/05      /  /    RDR

           H. Frank Carey HS:
02-2136    Additions and Alterations    0-005-026  10/31/03   02 - 16                        0      125,000   09/01/03      /  /    RDR
06-0290    Reconstruction               0-005-030  10/25/06   2,7,8,155,15,16                0      141,094   09/30/06      /  /    MGL

           Elmont Memorial High School:
02-2133    Additions and Alterations    0-006-029  10/31/03   02 - 16                        0      300,000   09/01/03      /  /    RDR
02-1714    Reconstruction               0-006-031  07/31/02   8,9,16                         0      226,275   09/01/03      /  /    RDR
05-1205    Reconstruction               0-006-035  09/20/06   2,7,16                         0      638,550   09/30/06      /  /    RDR
06-0140    Reconstruction               0-006-036  08/28/06   7                              0      186,244   09/30/06      /  /    MGL

           New Press Box @ NHP Memorial HS:
03-1555    New Construction             7-038-001  07/01/04   02 - 16                        0       33,000   09/01/04      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BELLMORE - MERRICK CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-02-53-07
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Mepham High School:
98-1255    Reconstruction               0-005-029  06/09/99   2,14                           0      450,000   05/30/00      /  /    RDR

           Brookside Jr. High School:
90-1133    Reconstruction               0-006-010  04/11/91   10                             0       20,000     /  /        /  /    CAE

           District Wide:
93-1737    Reconstruction               7-999-004  08/08/94   16                             0      324,223   11/30/94      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




LONG BEACH CITY SCHOOL DISTRICT SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-03-00-01
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Lido School:
01-0560    Reconstruction               0-001-024  04/08/02   8                              0       30,000   08/31/02      /  /    RDR

           West School:
01-0561    Reconstruction               0-003-016  04/08/02   8                              0       13,000   08/31/02      /  /    RDR

           East School:
01-0562    Reconstruction               0-004-015  04/08/02   8                              0       32,000   08/31/02      /  /    RDR

           Lindell School:
99-1470    Reconstruction               0-005-020  06/19/00   10                             0       28,000   08/30/00      /  /    RDR
01-0563    Reconstruction               0-005-021  04/08/02   8                              0       12,000   08/31/02      /  /    RDR

           High School:
97-1310    Reconstruction               0-011-026  05/22/98   14                             0      325,000   08/31/98      /  /    RDR
01-0564    Reconstruction               0-011-028  04/08/02   8                              0      120,000   08/31/02      /  /    RDR
06-0941    Reconstruction               0-011-034  05/16/07   16                             0      355,000     /  /        /  /    MGL

           Bus Maint. Garage (Transp. Facility:
03-0166    Reconstruction               5-013-002  08/20/03   2                              0      690,990   12/31/03      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WESTBURY UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-01-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Drexel Elementary:
97-0481    Reconstruction               0-001-008  11/19/97   4,8                            0       53,000   12/31/97      /  /    MGL
03-1083    Reconstruction               0-001-011  04/23/04   2,4,7,8,9,10,155,15,           0      351,513   09/30/04      /  /    RDR

           Westbury Middle/Jr High 6-8:
98-0239    Reconstruction               0-002-012  11/02/98   9                              0       39,000   09/30/98      /  /    MGL
03-1084    Reconstruction               0-002-016  04/23/04   8,9,155,16                     0    1,209,189   09/30/04      /  /    RDR

           Powell's Lane Elementary:
04-0673    Reconstruction               0-005-013  05/12/05   2,4,8,10,13,155,15,1           0    1,264,984   09/30/05      /  /    RDR

           Westbury High School:
03-1086    Reconstruction               0-007-014  04/23/04   2,4,7,8,9,10,155,15,           0    5,214,241   09/30/04      /  /    RDR
04-0674    Reconstruction               0-007-018  05/12/05   2,4,8,10,13,155,15,1           0    7,540,613   09/30/05      /  /    RDR

           Park Avenue School:
03-1087    Reconstruction               0-010-011  04/23/04   2,4,7,8,9,10,155,15,           0      185,016   09/30/04      /  /    RDR

           Dryden St ES(K/Pre Sch):
03-1088    Reconstruction               0-012-010  04/23/04   2,4,7,8,9,10,155,15,           0      397,513   09/30/04      /  /    RDR

           Portable #1 @ Senior High School:
05-1102    New Construction             0-020-001  11/02/06   02 - 16                        0      500,000     /  /        /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




EAST WILLISTON UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-02-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ROSLYN UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-03-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           East Hills School:
04-1374    Reconstruction               0-001-017  06/07/05   2,4,7                          0    1,104,000     /  /        /  /    DDJ

           Roslyn High School:
04-0562    Reconstruction               0-002-020  12/17/04   16                             0       81,200   01/31/05      /  /    DDJ
04-1372    Reconstruction               0-002-024  06/07/05   2,4,7                          0    2,289,646     /  /        /  /    DDJ

           Roslyn Middle School:
03-1090    Reconstruction               0-006-017  03/24/04   7                              0      298,820   01/31/04      /  /    MAC
04-1369    Reconstruction               0-006-018  06/07/05   2,4                            0      434,000     /  /        /  /    DDJ
05-0033    Reconstruction               0-006-019  09/02/05   2,15                           0       40,000     /  /        /  /    DDJ

           Roslyn Heights Elementary:
04-1375    Reconstruction               0-007-015  06/07/05   2,4,7                          0      415,204     /  /        /  /    DDJ

           Harbor Hill Elementary:
04-1371    Reconstruction               0-009-014  06/07/05   2,4,7                          0      750,555     /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PORT WASHINGTON UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-04-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Paul D Schreiber High School:
94-1606    Reconstruction               0-001-014  06/21/95   2                              0      161,768   07/19/95      /  /    RDR
06-1108    Reconstruction               0-001-024  04/03/07   7                              0      692,800     /  /        /  /    HCM

           Flower Hill Elementary:
93-0512    Additions and Alterations    0-002-006  03/21/94   02 - 16                        0      319,100   09/30/95      /  /    RDR
94-0030    Reconstruction               0-002-007  08/11/94   9,16                           0      104,000   01/30/96      /  /    RDR
95-0595    Reconstruction               0-002-009  02/22/96   2,8,9,15,16                    0      250,000   09/01/96      /  /    RDR

           John Philip Sousa Elementary:
95-1526    Reconstruction               0-003-012  06/06/96   16                             0      147,035   09/01/96      /  /    RDR
95-1530    Reconstruction               0-003-013  06/25/96   2,9,10,16                      0      147,000   09/01/96      /  /    RDR

           Manorhaven Elementary School:
91-1293    Reconstruction               0-005-012  06/23/92   2                              0       66,000   07/10/92      /  /    RDR
94-1605    Reconstruction               0-005-014  06/21/95   2,155,15,16                    0       12,000   07/19/95      /  /    RDR
95-1527    Reconstruction               0-005-016  06/06/96   16                             0      159,669   09/01/96      /  /    RDR
99-1216    Reconstruction               0-005-019  04/29/00   7                              0       46,000   09/01/00      /  /    MGL

           Carrie P. Weber Junior High:
93-0514    Additions and Alterations    0-006-014  03/21/94   02 - 16                        0      849,000   09/30/95      /  /    RDR
94-0031    Reconstruction               0-006-017  08/11/94   16                             0       70,000   01/30/96      /  /    RDR
95-0596    Reconstruction               0-006-018  02/22/96   2,4,7,8,9,10,13,14             0      433,278   09/01/96      /  /    RDR
98-0457    Reconstruction               0-006-021  01/26/99   16                             0      247,310   05/21/99      /  /    RDR
99-1641    Reconstruction               0-006-024  06/12/00   2,8,9                          0       23,000   09/30/00      /  /    MGL
00-0002    Reconstruction               0-006-025  07/27/00   8,9,15,16                      0       68,400   10/30/00      /  /    MAC

           John J. Daly Elementary:
91-1295    Reconstruction               0-007-007  06/23/92   2                              0       38,000   07/06/92      /  /    RDR
93-0515    Additions and Alterations    0-007-009  03/21/94   02 - 16                        0      655,000   09/15/95      /  /    RDR
93-1204    Reconstruction               0-007-010  05/12/94   2                              0      218,000   07/14/94      /  /    RDR
94-1604    Reconstruction               0-007-011  06/21/95   2                              0      163,625   07/19/95      /  /    RDR
95-1528    Reconstruction               0-007-013  06/06/96   16                             0      105,628   09/01/96      /  /    RDR
95-1531    Reconstruction               0-007-014  06/25/96   2,9,10                         0       59,000   09/01/96      /  /    RDR
97-1226    Reconstruction               0-007-017  04/28/98   8,9,16                         0       96,000   08/30/98      /  /    RDR

           South Salem Elementary:
96-0287    Reconstruction               0-008-003  10/24/96   7                              0      295,000   11/30/96      /  /    RDR

           F.E. Guggenheim Elementary:
95-1529    Reconstruction               0-010-015  06/06/96   16                             0      146,448   09/01/96      /  /    RDR
97-1314    Reconstruction               0-010-016  12/30/98   2,155                          0      102,000   05/30/99      /  /    RDR
99-1219    Reconstruction               0-010-020  04/29/00   9                              0       72,300   09/01/00      /  /    MGL

           Districtwide:
99-1180    Reconstruction               7-999-002  04/27/00   16                             0      132,000   10/30/00      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




NEW HYDE PARK-GARDEN CITY PARK UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-05-02
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Garden City Park School:
05-1025    Reconstruction               0-001-016  05/12/06   4                              0      250,000   09/01/06      /  /    DDJ

           Hillside Grade School:
06-1304    Reconstruction               0-002-021  05/10/07   10,15                          0       50,000     /  /        /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MANHASSET PUBLIC SCHOOLS SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-06-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Manhasset Jr/Sr High School:
04-1270    Reconstruction               0-004-027  09/02/05   2,16                           0      300,000     /  /        /  /    RDR
06-1032    Reconstruction               0-004-029  05/10/07   2,4,7,8,9,155,15,16            0    7,237,025     /  /        /  /    MGL

           Shelter Rock Elementary:
98-1719    Reconstruction               0-005-013  03/13/00   8                              0      121,926   09/30/99      /  /    LSS


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GREAT NECK UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-07-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           North Senior High:
01-0293    Reconstruction               0-012-010  03/09/04   16                             0      275,000   08/30/01      /  /    MGL

           Parkville School:
00-1376    Reconstruction               0-014-010  06/22/01   2                              0       15,000   08/31/01      /  /    MGL

           Saddle Rock School:
03-1327    Reconstruction               0-015-015  08/09/04   8,9,10,13,155,15,16            0      175,000   09/30/04      /  /    HCM

           South Middle School:
01-0294    Reconstruction               0-019-016  03/09/04   16                             0      410,000   08/30/01      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HERRICKS UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-09-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Herricks Senior High School:
94-1184    Reconstruction               0-008-020  05/12/95   2,4,7,8,9,10,155,15,           0       39,960   08/30/95      /  /    MGL
00-1307    Reconstruction               0-008-025  06/06/01   4,8,9,155,15,16                0      147,960   09/01/01      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MINEOLA UNION FREE SCHOOL DISTRICT SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-10-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CARLE PLACE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-04-11-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Rushmore Ave. School:
98-1539    Reconstruction               0-002-018  11/04/99   2,8,155,15,16                  0       66,880   06/30/00      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




NORTH SHORE CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-01-06
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Glen Head School:
06-0820    Reconstruction               0-002-014  02/01/07   2                              0      500,000     /  /        /  /    MGL

           North Shore High School:
05-0677    Reconstruction               0-004-020  04/06/06   4,7                            0    2,743,540     /  /        /  /    RDR

           Districtwide:
05-0229    Reconstruction               7-999-002  12/23/05   16                             0      803,301   12/30/05      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SYOSSET CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-02-06
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           South Grove Elem. Annex:
04-1143    Reconstruction               0-002-006  07/15/05   10,155                         0       60,382   09/01/05      /  /    MGL

           Syosset High School:
02-1126    Additions and Alterations    0-010-026  09/11/03   02 - 16                        0    5,616,265   09/01/03      /  /    MGL

           Walt Whitman Elementary:
03-1410    Additions and Alterations    0-013-014  07/01/04   02 - 16                        0      767,782   12/01/04      /  /    HCM


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




LOCUST VALLEY CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-03-06
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Locust Valley High:
99-0655    Reconstruction               0-012-019  03/14/00   8                              0      720,000   12/31/00      /  /    RDR

           Concession Stand @ High School:
00-1289    New Construction             7-018-001  05/10/01   02 - 16                        0       50,000   12/31/02      /  /    RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PLAINVIEW-OLD BETHPAGE SCHOOL SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-04-06
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Old Bethpage Elementary:
92-0181    Reconstruction               0-002-012  08/31/92   2,16                           0       67,600     /  /        /  /    PNL

           Jamaica Avenue Elementary:
90-1002    Reconstruction               0-004-011  03/28/91   2,16                           0      102,500     /  /        /  /    MGL
92-0182    Reconstruction               0-004-012  08/31/92   2,16                           0       74,900     /  /        /  /    PNL

           Parkway Elementary:
92-0183    Reconstruction               0-008-011  08/31/92   2,16                           0       74,900     /  /        /  /    PNL

           Stratford Road School:
92-0184    Reconstruction               0-011-011  08/31/92   2,16                           0      121,700     /  /        /  /    PNL

           Plainview Old Bethpage Middle Sch.:
92-0185    Reconstruction               0-012-016  08/31/92   16                             0      138,400     /  /        /  /    MGL

           Mattlin Middle School:
92-0186    Reconstruction               0-014-014  08/31/92   2,16                           0      176,900     /  /        /  /    PNL

           John F. Kennedy High School:
92-0187    Reconstruction               0-015-016  08/31/92   16                             0      176,900     /  /        /  /    MGL

           Fern Place School Boces:
99-1291    Additions and Alterations    0-020-005  05/05/00   02 - 16                        0      470,339   09/01/00      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




OYSTER BAY-EAST NORWICH CSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-06-06
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Oyster Bay High School:
00-1324    Reconstruction               0-001-022  06/01/01   9,16                           0      350,000   09/01/01      /  /    BJB
04-0262    Reconstruction               0-001-025  01/19/05   8,9,16                         0    1,900,000   08/31/05      /  /    DDJ
03-1496    Reconstruction               0-001-026  05/04/04   4                              0      200,000   08/31/04      /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




JERICHO UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-15-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Jericho MS/HS:
00-1167    Reconstruction               0-003-030  04/05/01   2                              0       70,000   07/30/01      /  /    MGL
04-0995    Reconstruction               0-003-031  04/04/05   8,9,10,155,16                  0       50,000   08/31/05      /  /    JOD
05-0162    Reconstruction               0-003-032  12/01/05   2,7                            0      300,000     /  /        /  /    JOD
06-1104    Reconstruction               0-003-033  03/26/07   2,7                            0      375,000     /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HICKSVILLE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-17-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Burns Avenue Elementary:
05-0613    Reconstruction               0-001-017  05/16/06   2,4,9,10,16                    0      180,000   10/27/06      /  /    DDJ

           Dutch Lane School:
04-0456    Reconstruction               0-002-014  01/19/05   4                              0      137,400   10/15/04      /  /    DDJ
05-0614    Reconstruction               0-002-016  05/16/06   16                             0       30,000   10/27/06      /  /    DDJ

           East Street Elementary:
05-0615    Reconstruction               0-003-016  05/16/06   16                             0       30,000   10/27/06      /  /    DDJ

           Fork Lane School:
05-0616    Reconstruction               0-004-017  05/16/06   16                             0       30,000   10/27/06      /  /    DDJ

           Lee Avenue School:
05-0617    Reconstruction               0-005-017  05/16/06   2,4,8,9,10,16                  0      174,275   10/27/06      /  /    DDJ

           Old Country Rd. School:
05-0618    Reconstruction               0-007-015  05/16/06   16                             0       90,000   10/27/06      /  /    DDJ

           Woodland Avenue School:
05-0619    Reconstruction               0-008-016  05/16/06   16                             0      111,675   10/27/06      /  /    DDJ

           Hicksville Middle School:
05-0620    Reconstruction               0-009-024  05/16/06   2,4,8,9,10,155,15,16           0      156,995   10/27/06      /  /    DDJ
05-0307    Reconstruction               0-009-025  12/30/05   16                             0       80,000   10/31/05      /  /    DDJ
05-1304    Reconstruction               0-009-026  06/19/06   4                              0      365,000   09/01/06      /  /    DDJ
06-0552    Reconstruction               0-009-027  12/01/06   13                             0       27,500   09/01/06      /  /    DDJ

           Hicksville High School:
04-0459    Reconstruction               0-010-026  01/19/05   16                             0      125,000   10/15/04      /  /    DDJ
05-0621    Reconstruction               0-010-029  05/16/06   2,4,8,9,16                     0       97,000   10/27/06      /  /    DDJ
06-0480    Reconstruction               0-010-030  01/09/07   4                              0       30,000   09/01/02      /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PLAINEDGE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-18-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           NO MISSING SUBS. COMPLETION DATES:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BETHPAGE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-21-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           John F. Kennedy Middle School:
99-0070    Reconstruction               0-002-015  04/22/00   2,9,14,16                      0      375,000   08/30/00      /  /    MGL

           Kramer Lane Elementary:
01-0014    Additions and Alterations    0-004-010  02/12/02   02 - 16                        0    3,530,252   12/31/02      /  /    MGL

           Charles Campagne Elementary:
01-0237    Additions and Alterations    0-007-013  04/01/02   02 - 16                        0    2,088,681   12/31/02      /  /    MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




FARMINGDALE UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-22-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Weldon E.Howitt Jr.High-East:
97-1741    Reconstruction               0-001-013  07/30/98   2,16                           0       31,000   08/15/98      /  /    MGL
99-0155    Reconstruction               0-001-015  11/05/99   2,9,155,16                     0       32,400   09/01/00      /  /    MGL
05-0664    Reconstruction               0-001-022  05/12/06   2,8,9,155,15,16                0      750,500     /  /        /  /    DDJ

           Albany Ave. Elementary School:
97-1742    Reconstruction               0-003-012  07/30/98   2,16                           0       27,000   08/15/98      /  /    MGL
02-0251    Reconstruction               0-003-017  01/07/03   2,155,16                       0      887,570   09/30/05      /  /    MGL
03-1568    Reconstruction               0-003-019  07/08/04   9,16                           0      100,000   12/15/04      /  /    DDJ
06-0709    Reconstruction               0-003-023  03/07/07   155                            0      972,300     /  /        /  /    DDJ

           Woodward Parkway Elementary:
97-1743    Reconstruction               0-006-011  07/30/98   2,16                           0       51,900   08/15/98      /  /    MGL
02-0088    Reconstruction               0-006-013  01/31/03   155,16                         0      432,370   09/01/03      /  /    MGL
03-1569    Reconstruction               0-006-018  07/08/04   9,16                           0      100,000   12/15/04      /  /    DDJ

           Farmingdale High School:
97-1744    Reconstruction               0-007-016  07/30/98   2,16                           0       48,800   08/15/98      /  /    MGL
98-0672    Reconstruction               0-007-019  03/05/99   2,7,155                        0    1,025,000   09/01/99      /  /    MGL
05-0665    Reconstruction               0-007-037  05/12/06   2,9,155,16                     0      433,982     /  /        /  /    DDJ

           Northside Elementary School:
97-1745    Reconstruction               0-008-011  07/30/98   2,16                           0       11,300   08/15/98      /  /    MGL

           East Memorial at Mill Lane:
97-1746    Reconstruction               0-009-011  07/30/98   2,16                           0       20,730   08/15/98      /  /    MGL
98-0673    Reconstruction               0-009-015  03/05/99   2,8,155,16                     0      300,000   09/01/99      /  /    MGL
03-1570    Reconstruction               0-009-021  07/08/04   155                            0      125,000   12/15/04      /  /    DDJ

           Districtwide:
03-1571    Reconstruction               7-999-009  07/08/04   16                             0      150,000   12/15/04      /  /    DDJ


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




MASSAPEQUA UFSD SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-05-23-03
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           Birch Lane School:
98-1058    Reconstruction               0-001-014  04/08/99   16                             0       68,200   08/31/99      /  /    BJB

           Fairfield Elementary:
96-1209    Reconstruction               0-004-017  05/20/97   2                              0      300,000   08/31/97      /  /    BJB

           Hawthorn School:
06-1218    Reconstruction               0-005-011  05/09/07   2,4,7,8,155                    0    1,229,000     /  /        /  /    JOD

           R. Lockhart Elementary School:
98-1059    Reconstruction               0-006-011  04/08/99   16                             0       53,500   08/31/99      /  /    BJB

           Unqua Elementary School:
98-1060    Reconstruction               0-007-018  04/08/99   16                             0       81,150   08/31/99      /  /    BJB

           Ames Campus:
06-1219    Reconstruction               0-009-016  05/09/07   2,7                            0    1,300,000     /  /        /  /    JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BOCES NASSAU SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 28-90-00-00
last updated on 05/29/08
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    ANTICIP   SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         COMPLETE  COMPLETE  MGR.
_______________________________________________________________________________________________________________________________________

           P.A.C.E. Modular:
03-0241    New Construction             0-139-001  02/24/04   02 - 16                        0    1,062,700   08/15/03      /  /    MAC


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition