BOCES GREATER SOUTHERN TIER SUBSTANTIAL COMPLETION DATE MISSING FOR APPROVED CAPITAL PROJECTS
District No.: 55-90-00-00
last updated on 05/29/08
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED ANTICIP SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST COMPLETE COMPLETE MGR.
_______________________________________________________________________________________________________________________________________
P.C. Bush Center--Bldg. 1:
06-0691 Alterations 0-001-018 04/11/07 02 - 16 0 679,166 / / / / JOD
Bldg 4 (was 1-004) Bush Campus:
06-0692 Additions and Alterations 0-004-009 04/11/07 02 - 16 0 230,000 / / / / JOD
Bldg 5:
05-0213 Reconstruction 0-005-012 01/06/06 7 0 105,000 / / / / JOD
Bldg 6:
05-0214 Reconstruction 0-006-012 01/06/06 7 0 119,000 / / / / JOD
Bldg 7:
05-0215 Reconstruction 0-007-008 01/06/06 7 0 152,000 / / / / JOD
Bldg 8:
05-0216 Reconstruction 0-008-005 01/06/05 2,4,7,8 0 180,450 / / / / JOD
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition