OISR

2014-2015 Performance Management Schedule

SIF Cohorts 2 and 3

Progress Reports Due to NYSED STO

Performance Review Calls with NYSED STO

   

August 1, 2014
Post Award Documents approved by NYSED STO
(SIF 3 only)

Week of August 11, 2014
Ready for September 2014:

  • SIF 2 begins Y2 Implementation Period     (includes MVPS results through June 30, 2014)
  • SIF 3 begins Y1 Implementation Period

October 16, 2014

Beginning October 27,  2014
(includes MVPS results from 7/1/14-9/30/14)

January 8, 2015

Beginning January 19, 2015
(includes MVPS results from 10/1/14-12/31/14)

April 16, 2015

Beginning April 27, 2015
(includes MVPS results from 1/1/15-3/31/15)

May 15, 2015
SIF 2 Only: No-Cost Extension documents due to STO

May 22, 2015
SIF 3 Only: Continuation Plans for 2015-2016 including updated MOUs

Beginning June 22, 2015
(SIF 2 to discuss extension; SIF 3 to discuss Continuation Plans)

SIF 2 ends 6/30/15; option to extend through 8/31/15

  • Final Report is due 7/31/15; 9/30/15 if extending.
  • FS-10F is due 9/30/15; 11/30/15 if extending.

Additional On-Site Monitoring and Performance Review:

In addition to the written progress reports and telephone conversations with district project leads and other district staff, NYSED STO may conduct on-site check-in visits to SIF Cohort 2 and 3 schools during the 2014-2015 school year.  Such visits may be conducted with or without advanced notification. NYSED STO may also work with district staff to arrange individual or group telephone or video conversations with school-level leaders, coordinators, and/or teachers as part of the STO Performance Management structure for the School Innovation Fund (SIF) Grant.


Performance Management Toolkit

SIF 3
SIF 2

SIF 1

Last Updated: March 5, 2015