Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 03/28/24 at 08:21:20




ALBANY CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-01-00-01
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Scotland Elementary (PS #19):
19-0637   Reconstruction               0-019-009  12/23/19     DONE    DONE       DONE      10/29/19   10/11/19   06/27/19   05/19/15   155,16                   613,000       613,000  BMJ             0           0           0 Collins & Scoville Architects           0      01/04/21                       10/11/19           
20-1404   Reconstruction               0-019-010  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,4,7,8,155,16           507,649             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          North Albany Academy (PS #20):
20-0683PR Additions and Alterations    0-020-007               DONE                         10/23/20     /  /     03/07/19     /  /     02 - 16                        0    20,571,816  JSS             0           0           0                                         0        /  /                           /  /             
20-0827   Additions and Alterations    0-020-007  03/11/21     DONE    DONE       DONE      11/16/20   11/06/20   03/07/19   05/21/19   02 - 16               28,460,000    22,414,704  JSS             0           0           0 Collins & Scoville Architects           0        /  /                         11/06/20           

          Albany Schl of Humanities (PS #23):
20-1405   Reconstruction               0-023-015  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   4,8,9,155,16             435,573             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           
22-2414   Reconstruction               0-023-016  02/02/24     DONE    DONE       DONE      06/20/23   06/20/23     /  /     05/17/22   2,8,9,155,16           2,382,591     2,382,591  JJH             0           0           0 Tetra Tech Engineers, Archite   2,382,591        /  /                         06/20/23           

          Thomas O'Brien Acad of Sci (PS #24):
20-1406   Reconstruction               0-024-010  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,8,9,10,155,15,16     1,269,782             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Eagle Point Elementary (PS #27):
20-1407   Reconstruction               0-027-008  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   8,155                     18,516             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Hackett Middle School:
20-1408   Reconstruction               0-044-014  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,7,8,9,10,155,15,16     144,615             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           
22-2415   Reconstruction               0-044-015  02/02/24     DONE    DONE       DONE      06/20/23   06/20/23   12/22/22   05/17/22   2,8,9,155,16           2,404,854     2,404,854  JJH             0           0           0 Tetra Tech Engineers, Archite   2,404,854        /  /                         06/20/23           

          James Hall Sunshine:
19-0494   Reconstruction               0-045-002  01/22/20     DONE    DONE       DONE      09/25/19   09/23/19   08/05/19   05/21/19   7                        256,199             0  BMJ             0           0           0 Collins & Scoville Architects           0      07/31/20                       09/23/19           

          Giffen Memorial Elementary School:
20-1409   Reconstruction               0-046-011  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,8,9,10,155,15,16     1,517,975             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Arbor Hill Elementary:
20-1410   Reconstruction               0-047-011  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,4,7,8,9,10,155,15,   6,046,946             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           
22-2416   Reconstruction               0-047-012  02/02/24     DONE    DONE       DONE      06/20/23   06/20/23   12/22/22   05/17/22   2,7,8,9,155,16         3,814,993     3,814,993  JJH             0           0           0 Tetra Tech Engineers, Archite   3,814,993        /  /                         06/20/23           

          Albany High School:
19-0790   Additions and Alterations    0-048-022  03/18/20     DONE    DONE       DONE      11/14/19   11/04/19   07/15/16   02/09/16   02 - 16               56,430,796    56,430,796  BMJ             0           0           0 Collins & Scoville Architects           0        /  /                         11/04/19           
22-0928   Additions and Alterations    0-048-023  05/10/23     DONE    DONE       DONE      11/07/22   11/04/22   07/15/16   02/09/16   02 - 16               43,600,000    43,600,000  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/04/22           

          Schuyler Achievmt Academy (PSES "A"):
19-0857   Reconstruction               0-056-005  01/15/20     DONE    DONE       DONE      11/21/19   11/12/19   08/05/19   11/07/19   8,9,155,16               436,339       436,339  BMJ             0           0           0 Collins & Scoville Architects           0        /  /                         11/12/19           
  -       Reconstruction               0-056-006                                              /  /       /  /     08/03/20     /  /     8,9,155,15,16                  0             0  JSS             0           0           0                                         0        /  /                           /  /             
20-1228   Reconstruction               0-056-007  03/11/21     DONE    DONE       DONE      02/01/21   01/13/21   10/29/20   11/05/20   2,8,9,155,16             262,120             0  JSS             0           0           0 Collins & Scoville Architects           0        /  /                         01/13/21           

          Sheridan Prep Academy (PSES "B"):
20-1411   Reconstruction               0-057-003  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   155,16                   260,041             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Delaware Community School:
20-1412   Reconstruction               0-059-002  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/06/19   05/21/19   2,9,155,16               989,396             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Pine Hills Elementary School:
20-1413   Reconstruction               0-060-002  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/06/19   05/21/19   155,16                   258,833             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Meyers Middle School:
20-1414   Reconstruction               0-061-004  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,8,155,16               424,155             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           
22-2417   Reconstruction               0-061-005  02/02/24     DONE    DONE       DONE      06/20/23   06/20/23   12/22/22   05/17/22   2,8,9,155,16           1,492,830     1,492,830  JJH             0           0           0 Tetra Tech Engineers, Archite   1,492,830        /  /                         06/20/23           

          Montessori Magnet School:
20-1415   Reconstruction               0-062-003  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   8,9,155,16               689,230             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Edmund J. O'Neal Middle School:
19-0495   Reconstruction               0-076-002  01/22/20     DONE    DONE       DONE      09/25/19   09/23/19   08/06/19   05/21/19   155,16                   301,869       301,869  BMJ             0           0           0 Collins & Scoville Architects           0      07/31/20                       09/23/19           
20-1416   Reconstruction               0-076-003  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/06/19   05/21/19   7                        205,664             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           
22-1979   Alterations                  0-076-004  07/19/23     DONE    DONE       DONE      04/03/23   03/30/23   12/12/22   05/17/22   02 - 16                  300,000       300,000  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         03/30/23           

          Tony Clement Centr for Ed (was8-078):
20-1417   Reconstruction               0-078-001  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/19/19   05/21/19   2,8                      137,169             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Administration @ Academy Park:
20-1418   Reconstruction               1-001-004  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2,4,7,8,9,155,15,16      315,046             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           

          Administration @ Harriet Gibbons:
20-1419   Reconstruction               1-064-003  06/02/21     DONE    DONE       DONE      03/10/21   02/23/21   08/05/19   05/21/19   2                         42,566             0  JSS             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/23/21           
19-0638   Reconstruction               1-064-004  12/23/19     DONE    DONE       DONE      10/29/19   10/11/19   09/30/19   05/19/15   155,16                   168,000             0  BMJ             0           0           0 Collins & Scoville Architects           0      11/04/20                       10/11/19           

          Storage @ HS Field:
  -    PR New Construction             2-085-001                                              /  /       /  /     04/06/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0929   New Construction             2-085-001  05/10/23     DONE    DONE       DONE      11/07/22   11/04/22   04/06/22   02/09/16   02 - 16                  145,000             0  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/04/22           

          Garden Shed @ HS:
  -    PR New Construction             2-086-001                                              /  /       /  /     09/29/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0952DB Discovered Building          2-086-001               UNREVIEWED
                                                                       DONE       DONE      11/09/22   11/09/22   09/29/22     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                         11/09/22           

          Shed #4 @ Myers MS:
23-1565DB Discovered Building          2-087-001                                            03/01/24     /  /     01/05/24     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Freight Farm @ Albany HS:
21-1233   New Construction             7-083-001  03/22/22     DONE    DONE       DONE      02/02/22   02/02/22   01/05/22   01/20/22   02 - 16                   97,153             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         02/02/22           

          Concession/Toilets @ HS Field:
  -    PR New Construction             7-084-001                                              /  /       /  /     04/06/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0930   New Construction             7-084-001  05/10/23     DONE    DONE       DONE      11/07/22   11/04/22   04/06/22   02/09/16   02 - 16                  518,000             0  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/04/22           

          The Salvation Army:
  -    TQ Temporary Quarters           8-083-001                                              /  /       /  /     05/03/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Hudson Valley Community College:
  -    TQ Temporary Quarters           8-084-001                                              /  /       /  /     05/03/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          NMCC HS "50 Beaver":
  -    TQ Temporary Quarters           8-001-001                                              /  /       /  /     04/20/23     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Doane Stuart School:
23-0124TQ Temporary Quarters           8-002-001  08/28/23     DONE    DONE       DONE      07/24/23   07/24/23   05/12/23     /  /                                    0             0  MSK             0           0           0                                         0        /  /                         07/24/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BERNE-KNOX-WESTERLO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-02-01-04
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Berne Elementary:
18-0575   Additions and Alterations    0-001-019  04/01/19     DONE    DONE       DONE      10/03/18   09/13/18   11/14/17   11/02/17   02 - 16               11,679,150    10,809,750  SLC             0           0           0 Synthesis Architects,L.L.P.             0      12/10/20                       09/13/18           

          Jr/Sr High School:
18-0576   Additions and Alterations    0-004-018  04/01/19     DONE    DONE       DONE      10/03/18   09/13/18   11/14/17   11/02/17   02 - 16                8,046,460     7,925,360  SLC             0           0           0 Synthesis Architects,L.L.P.             0      12/16/19                       09/13/18           

          Business Office:
23-0374DB Discovered Building          1-011-001               UNREVIEWED
                                                                       STARTED    UNREVIEWED09/05/23   09/01/23   03/01/23     /  /                                    0             0  JJH             0           0           0                                         0        /  /                         09/01/23           

          Storage Barn:
23-0375DB Discovered Building          2-012-001               UNREVIEWED
                                                                       DONE       DONE      09/05/23   09/01/23   03/01/23     /  /                                    0             0  JJH             0           0           0                                         0        /  /                         09/01/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BETHLEHEM CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-03-06-06
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Glenmont Elementary:
22-0465FC Reconstruction               0-002-016  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,4,7,8,9,10,155,15,   2,680,459     2,680,459  JLB             0           0           0                                         0        /  /                         09/13/22           

          Hamagrael Elementary:
22-0466FC Reconstruction               0-003-019  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,4,7,8,9,10,155,15,   4,477,578     4,477,578  JLB             0           0           0                                         0        /  /                         09/13/22           

          Middle School:
20-0297   Reconstruction               0-005-025  12/01/20     DONE    DONE       DONE      09/01/20   08/24/20   06/26/20   06/16/20   14                       100,000       100,000  JSS             0           0           0 Ashley McGraw                           0      06/15/21                       08/24/20           
22-0467   Reconstruction               0-005-026  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,4,7,8,9,14,155,16   10,381,393    10,381,393  JLB             0           0           0                                         0        /  /                         09/13/22           

          Senior High School:
21-1267XX Reconstruction               0-006-036  03/30/22               CANCELLED          02/11/22   02/09/22   10/15/21   05/18/21   155,16                   100,000       100,000  SLC             0           0           0 ning & King Architects                  0        /  /                         02/09/22           
22-0468   Reconstruction               0-006-037  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,4,7,8,9,10,155,15,  14,618,911    14,618,911  JLB             0           0           0                                         0        /  /                         09/13/22           
22-1141   Reconstruction               0-006-038  02/17/23     DONE    DONE       DONE      12/05/22   12/01/22   06/07/22   05/17/22   16                       100,000       100,000  JJH             0           0           0 Ashley McGraw                           0      05/02/23                       12/01/22           
  -       Reconstruction               0-006-039                                              /  /       /  /     11/09/23     /  /     8                              0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Elsmere Elementary:
22-0469   Reconstruction               0-008-020  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,7,8,16                 729,296       729,296  JLB             0           0           0                                         0        /  /                         09/13/22           

          Slingerlands Elementary:
22-0470FC Reconstruction               0-009-015  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,4,7,8,9,10,155,15,   2,434,236     2,434,236  JLB             0           0           0                                         0        /  /                         09/13/22           

          Eagle Elementary School:
22-0471   Reconstruction               0-026-006  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   2,4,9,16                 385,548       385,548  JLB             0           0           0                                         0        /  /                         09/13/22           

          Storage Bldg @ MS:
20-0626DB Discovered Building          2-052-001  07/15/21     DONE    DONE       DONE      10/19/20   02/25/20   10/19/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                         02/25/20           

          Storage Bldg @ Elsmere ES:
20-0627DB Discovered Building          2-053-001  07/15/21     DONE    DONE       DONE      10/19/20   02/25/20   10/19/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                         02/25/20           

          Football Storage Container #2:
20-0628DB Discovered Building          2-057-001  07/15/21     DONE    DONE       DONE      10/19/20   02/25/20   12/30/19     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                         02/25/20           

          Storage Shed #2 @ Glenmont ES:
20-0629DB Discovered Building          2-058-001  07/15/21     DONE    DONE       DONE      10/19/20   02/25/20   01/02/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                         02/25/20           

          HS X-Country Shed:
20-1573DB Discovered Building          2-059-001  07/15/21     DONE    DONE       DONE      04/09/21     /  /     02/06/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             

          MS Tennis Storage Shed:
20-1574DB Discovered Building          2-060-001  07/15/21     DONE    DONE       DONE      04/09/21     /  /     03/05/21     /  /                                    0             0  JSS             0           0           0                                         0        /  /                           /  /             

          XXTurf Field Bleacher Storage-Cancld:
  -    XX New Construction             2-062-001                         CANCELLED            /  /       /  /     06/14/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Maintenance & Storage Facility:
22-0472   Reconstruction               3-012-009  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   8,16                      96,611             0  JLB             0           0           0                                         0        /  /                         09/13/22           

          Bus Garage:
19-0037   Reconstruction               5-010-013  08/12/19     DONE    DONE       DONE      07/09/19   06/18/19   04/16/19   05/21/19   14                       100,000       100,000  SLC             0           0           0 Ashley McGraw                           0      06/05/20                       06/18/19           
22-0473   Additions and Alterations    5-010-014  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   02 - 16                2,897,074     2,897,074  JLB             0           0           0                                         0        /  /                         09/13/22           

          XXTransport: Electric Bus Charging:
22-0474XX New Construction             5-064-001                         CANCELLED          09/13/22   09/13/22   07/20/22   10/19/21   02 - 16                   59,280        59,280  JLB             0           0           0                                         0        /  /                         09/13/22           

          Concession Building:
22-0475   New Construction             7-061-001  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   05/16/22   10/19/21   02 - 16                  579,120             0  JLB             0           0           0                                         0        /  /                         09/13/22           

          Turf Field Pressbox:
22-0476   New Construction             7-063-001  04/11/23     DONE    DONE       DONE      09/13/22   09/13/22   06/14/22   10/19/21   02 - 16                  120,000             0  JLB             0           0           0                                         0        /  /                         09/13/22           

          HS Softball Dugout 2:
  -    PR New Construction             7-064-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1725   New Construction             7-064-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                   80,000             0  JJH             0           0           0 Ashley McGraw                           0        /  /                         02/22/23           

          HS Softball Dugout 1:
  -    PR New Construction             7-065-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1726   New Construction             7-065-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  120,000             0  JJH             0           0           0 Ashley McGraw                           0        /  /                         02/22/23           

          HS Stadium Pavilion:
  -    PR New Construction             7-066-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1727FC New Construction             7-066-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  200,000             0  JJH             0           0           0 Ashley McGraw                           0        /  /                         02/22/23           

          HS Cafe Pavilion:
  -    PR New Construction             7-067-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1728FC New Construction             7-067-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  164,800             0  JJH             0           0           0 Ashley McGraw                           0        /  /                         02/22/23           

          Slingerlands ES Pavilion:
  -    PR New Construction             7-068-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1729FC New Construction             7-068-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  133,760             0  JJH             0           0           0 Ashley McGraw                           0      09/29/23                       02/22/23           

          Hamagrael ES Pavilion:
  -    PR New Construction             7-069-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1730FC New Construction             7-069-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  133,760             0  JJH             0           0           0 Ashley McGraw                           0      09/29/23                       02/22/23           

          Glenmont ES Pavilion:
  -    PR New Construction             7-070-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1731FC New Construction             7-070-001  04/12/22     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  133,760             0  JJH             0           0           0 Ashley McGraw                           0      09/29/23                       02/22/23           

          Elsemere ES Pavilion:
  -    PR New Construction             7-071-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1732FC New Construction             7-071-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  133,760             0  JJH             0           0           0 Ashley McGraw                           0      09/29/23                       02/22/23           

          Eagle ES Pavilion:
  -    PR New Construction             7-072-001                                              /  /       /  /     02/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
22-1733FC New Construction             7-072-001  04/12/23     DONE    DONE       DONE      02/22/23   02/22/23   02/01/23   10/19/21   02 - 16                  133,760             0  JJH             0           0           0 Ashley McGraw                           0      09/29/23                       02/22/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAVENA COEYMANS SELKIRK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-04-02-06
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pieter B. Coeymans Elementary School:
20-1395   Reconstruction               0-005-012  04/05/21     DONE    DONE       DONE      03/09/21   02/23/21   05/19/17   01/13/15   2,8,9,10,155,15,16       747,500       747,500  SLC             0           0           0 Rhinebeck Architecture                  0      12/10/21                       02/23/21           
20-1875   Reconstruction               0-005-013  06/14/21     DONE    DONE       DONE      06/14/21   06/11/21   05/04/21   04/14/21   2,7                      109,000       109,000  SLC             0           0           0 Rhinebeck Architecture                  0      10/07/21                       06/11/21           
22-0902   Reconstruction               0-005-014  03/31/23     DONE    DONE       DONE      11/04/22   11/02/22   08/26/22   05/17/22   2,4,7,8,9,155,15,16      528,000       528,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/02/22           
23-0995   Reconstruction               0-005-015                         UNREVIEWED         11/14/23   11/08/23   10/11/23   01/09/23   2,4,7,8,9,155,15,16            0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/08/23           

          A.W. Becker Elementary School:
20-1396   Reconstruction               0-009-013  04/05/21     DONE    DONE       DONE      03/09/21   02/23/21   05/19/17   01/13/15   2,8,9,10,155,15,16       747,500       747,500  SLC             0           0           0 Rhinebeck Architecture                  0      12/10/21                       02/23/21           
22-0903   Reconstruction               0-009-014  03/31/23     DONE    DONE       DONE      11/04/22   11/02/22   08/26/22   05/17/22   2,4,7,8,9,155,15,16      324,000       324,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/02/22           
23-0996   Reconstruction               0-009-015                         UNREVIEWED         11/14/23   11/08/23   10/11/23   01/09/23   2,4,7,8,9,155,15,16            0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/08/23           

          High School:
20-1397   Reconstruction               0-013-023  04/05/21     DONE    DONE       DONE      03/09/21   02/23/21   01/11/21   01/13/15   2,4,7,8,9,10,155,15,     402,100       402,100  SLC             0           0           0 Rhinebeck Architecture                  0      12/10/21                       02/23/21           
21-1821   Reconstruction               0-013-024  05/18/22     DONE    DONE       DONE      05/16/22   05/16/22   03/02/22   03/02/22   9,13,15,16               700,000       700,000  FMJ             0           0           0 Rhinebeck Architecture                  0        /  /                         05/16/22           
22-0904   Reconstruction               0-013-025  03/31/23     DONE    DONE       DONE      11/04/22   11/02/22   08/26/22   05/17/22   2,4,7,8,9,155,15,16      528,000       528,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/02/22           
23-0997   Reconstruction               0-013-026                         UNREVIEWED         11/14/23   11/08/23   10/11/23   01/09/23   2,4,7,8,9,155,15,16            0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/08/23           

          Middle School:
20-1398   Reconstruction               0-014-012  04/05/21     DONE    DONE       DONE      03/09/21   02/23/21   05/19/17   01/13/15   2,8,9,10,155,15,16       412,900       412,900  SLC             0           0           0 Rhinebeck Architecture                  0      12/10/21                       02/23/21           
22-0905   Reconstruction               0-014-013  03/31/23     DONE    DONE       DONE      11/04/22   11/02/22   08/26/22   05/17/22   15,16                    712,000       712,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/02/22           
23-0161   Reconstruction               0-014-014  09/05/23     DONE    DONE       DONE      07/28/23   07/27/23   07/10/23   05/16/23   15,16                    100,000       100,000  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         07/27/23           
23-0998   Reconstruction               0-014-015                         UNREVIEWED         11/14/23   11/08/23   10/11/23   01/09/23   2,7,8,9,155,15,16              0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/08/23           

          Storage Tower:
  -    PR Additions and Alterations    2-015-002                                              /  /       /  /     08/26/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-0906   Additions and Alterations    2-015-002  03/31/23     DONE    DONE       DONE      11/04/22   11/02/22   08/26/22   05/17/22   02 - 16                  231,000             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/02/22           

          Warehouse Storage:
23-0999   Reconstruction               2-016-003                         UNREVIEWED         11/14/23   11/08/23   10/11/23   01/09/23   2,4,8,9,155,16                 0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/08/23           

          Bus Garage:
23-1000   Reconstruction               5-001-017                         UNREVIEWED         11/14/23   11/08/23   10/11/23   01/09/23   2,8,9,14,155,16                0             0  WLC             0           0           0 Rhinebeck Architecture                  0        /  /                         11/08/23           

          District-Wide:
  -    SB Reconstruction               7-999-BA3               DONE                           /  /       /  /       /  /       /  /     16                             0             0  WLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COHOES CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-05-00-01
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cohoes Middle School:
19-0061   Reconstruction               0-001-022  08/20/19     DONE    DONE       DONE      07/12/19   06/26/19   05/07/18   05/21/19   2,7                      547,053       547,053  SLC             0           0           0 Collins & Scoville Architects           0      09/01/20                       06/26/19           
22-2462   Reconstruction               0-001-023  12/11/23     DONE    DONE       DONE      06/28/23   06/27/23   11/10/22   05/17/22   2,4,7,8,9,10,14,155,   3,999,000     3,999,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         06/27/23           

          Abram Lansing School:
22-1492   Reconstruction               0-002-016  03/10/23     DONE    DONE       DONE      01/17/23   01/13/23   08/17/22   05/17/22   2,8                      100,000       100,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         01/13/23           
22-1592   Reconstruction               0-002-017  05/02/23     DONE    DONE       DONE      02/01/23   01/30/23   11/10/22   05/17/22   7                      1,055,981     1,055,981  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         01/30/23           
22-2463   Reconstruction               0-002-018  12/11/23     DONE    DONE       DONE      06/28/23   06/27/23   11/10/22   05/17/22   2,4,7,8,9,10,14,155,   1,704,000     1,704,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         06/27/23           

          Van Schaick Elementary:
22-2464   Reconstruction               0-005-018  12/11/23     DONE    DONE       DONE      06/28/23   06/27/23   11/10/22   05/17/22   2,4,7,8,9,10,14,16       526,500       526,500  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         06/27/23           
22-1593   Reconstruction               0-005-019  05/02/23     DONE    DONE       DONE      02/01/23   01/30/23   12/21/22   05/17/22   2,14                     469,689       469,689  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         01/30/23           

          High School:
  -       Reconstruction               0-006-022                                              /  /       /  /     07/12/19     /  /     9,14,16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
21-1336   Reconstruction               0-006-023  06/14/22     DONE    DONE       DONE      02/18/22   02/15/22   01/26/22   01/19/22   10,15,16                 111,259       111,259  SLC             0           0           0 Collins & Scoville Architects           0      06/06/23                       02/15/22           
22-2465   Reconstruction               0-006-024  12/11/23     DONE    DONE       DONE      06/28/23   06/27/23   11/10/22   05/17/22   2,4,7,8,9,10,14,155,  10,784,000    10,784,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         06/27/23           
23-1593   Reconstruction               0-006-025                         UNREVIEWED         03/06/24   03/05/24   02/20/24   05/16/23   9,10                     100,000             0  MSK             0           0           0 Collins & Scoville Architects           0        /  /                         03/05/24           

          Harmony Hill School:
19-0133   Reconstruction               0-010-010  09/06/19     DONE    DONE       DONE      07/23/19   07/15/19   05/07/18   05/21/19   155,16                   452,947       452,947  SLC             0           0           0 Collins & Scoville Architects           0      11/27/20                       07/15/19           
22-2466   Reconstruction               0-010-011  12/11/23     DONE    DONE       DONE      06/28/23   06/27/23   11/10/22   05/17/22   2,4,8,9,10,14,155,15   1,052,000     1,052,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         06/27/23           
22-1594   Reconstruction               0-010-012  05/02/23     DONE    DONE       DONE      02/01/23   01/30/23   12/21/22   05/17/22   2,14                     394,340       394,340  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         01/30/23           

          XXHolyTrinityChurch-StMarie-LseEnded:
19-0287TQ Temporary Quarters           8-021-001  09/05/19     DONE    DONE       DONE      08/23/19   08/23/19   05/03/19   07/31/19                                  0             0  SLC             0           0           0                                         0        /  /                         08/23/19           

          XXGraduation & EndOfYr Tent-dismantl:
20-1844TQ Temporary Quarters           8-022-001  06/14/21     DONE    DONE       DONE      06/04/21   06/04/21   05/07/21     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         06/04/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-01-06
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Colonie High School:
18-1623   Reconstruction               0-001-028  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/14/17   2,4,7,8,9,10,13,155,   3,025,000     3,025,000  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
19-0866   Reconstruction               0-001-029  02/20/20     DONE    DONE       DONE      11/27/19   11/08/19   07/18/19   05/21/19   16                        44,200        44,200  SLC             0           0           0 Mosaic Associates                       0      06/16/21                       11/08/19           
21-0350   Reconstruction               0-001-030  02/09/22     DONE    DONE       DONE      09/14/21   09/09/21   03/24/21   11/14/17   2,7,9,10,16            4,416,525     4,416,525  SLC             0           0           0 SEI Design Group                        0      12/15/23                       09/09/21           
22-1851   Reconstruction               0-001-031  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                     2,769,941     2,769,941  MSK             0           0           0 Energia Energy                  2,661,586        /  /                         03/10/23           
23-0742   Reconstruction               0-001-032                         UNREVIEWED         10/20/23   09/25/23   01/25/23   10/18/22   2,4,7,8,9,155,15,16   21,900,139             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           
23-1494   Reconstruction               0-001-033               DONE    STARTED    DONE      02/15/24   02/13/24   01/08/24   05/16/23   8,9,16                   100,000             0  MSK             0           0           0 SEI Design Group                        0        /  /                         02/13/24           

          Lisha Kill Jr High School:
18-1624   Reconstruction               0-002-016  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/14/17   2,4,7,8,9,10,13,155,   1,575,000     1,575,000  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
18-1625   Reconstruction               0-002-017  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/04/14   4,7,8,9,10,155,15,16     295,604       295,604  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
  -       Reconstruction               0-002-018                                              /  /       /  /     04/10/19     /  /     7                              0    24,100,968  SLC             0           0           0                                         0        /  /                           /  /             
19-1331   Reconstruction               0-002-019  02/19/20     DONE    DONE       DONE      02/03/20   01/31/20   01/21/20   01/21/20   2                        550,000       550,000  JSS             0           0           0 Mosaic Associates                       0      02/26/21                       01/31/20           
20-1906   Reconstruction               0-002-020  08/02/21     DONE    DONE       DONE      06/23/21   06/22/21   03/23/21   11/14/17   2,16                     472,000       472,000  SLC             0           0           0 SEI Design Group                        0      10/25/22                       06/22/21           
23-0744   Reconstruction               0-002-021                         UNREVIEWED         10/20/23   10/04/23   03/24/21   10/18/22   2,4,7,8,9,155,15,16    8,612,220             0  MSK             0           0           0 SEI Design Group                        0        /  /                         10/04/23           
22-1804   Reconstruction               0-002-022  05/10/23     DONE    DONE       DONE      03/08/23   03/07/23   11/29/22   05/17/22   16                       100,000       100,000  JLB             0           0           0 SEI Design Group                        0      06/29/23                       03/07/23           
22-1852   Reconstruction               0-002-023  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   01/25/23   01/03/23   2,4,7,8,9,155,15,16      639,163       639,163  MSK             0           0           0 Energia Energy                    614,160        /  /                         03/10/23           

          Veeder Elementary School:
18-1626   Reconstruction               0-003-016  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/04/14   4,7,8,9,10,155,15,16     390,928       390,928  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
19-0867   Reconstruction               0-003-017  02/20/20     DONE    DONE       DONE      11/27/19   11/08/19   07/18/19   05/21/19   16                       110,900       110,900  SLC             0           0           0 Mosaic Associates                       0      06/16/21                       11/08/19           
21-0351   Reconstruction               0-003-018  02/09/22     DONE    DONE       DONE      09/14/21   09/09/21   03/24/21   11/14/17   4                         57,169        57,169  SLC             0           0           0 SEI Design Group                        0      12/15/23                       09/09/21           
22-1853   Reconstruction               0-003-019  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                       717,765       717,765  MSK             0           0           0 Energia Energy                    689,687        /  /                         03/10/23           

          Saddlewood Elementary:
18-1627   Additions and Alterations    0-008-014  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/14/17   02 - 16                1,040,000     1,040,000  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
19-0868   Reconstruction               0-008-015  02/20/20     DONE    DONE       DONE      11/27/19   11/08/19   07/18/19   05/21/19   16                       105,400       105,400  SLC             0           0           0 Mosaic Associates                       0      06/16/21                       11/08/19           
22-1854   Reconstruction               0-008-016  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                       377,462       377,462  MSK             0           0           0 Energia Energy                    362,696        /  /                         03/10/23           
23-0743   Reconstruction               0-008-017                         UNREVIEWED         10/20/23   09/25/23   01/25/23   10/18/22   2,4,7,8,9,155,15,16    1,576,800     1,576,800  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Shaker Rd. Elementary:
18-1628   Reconstruction               0-009-015  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/04/14   4,7,8,9,10               524,927       524,927  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
19-0869   Reconstruction               0-009-016  02/20/20     DONE    DONE       DONE      11/27/19   11/08/19   07/18/19   05/21/19   16                       179,700       179,700  SLC             0           0           0 Mosaic Associates                       0      06/16/21                       11/08/19           
22-1855   Reconstruction               0-009-017  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                       499,025       499,025  MSK             0           0           0 Energia Energy                    479,504        /  /                         03/10/23           
23-0745   Reconstruction               0-009-018                         UNREVIEWED         10/20/23   09/25/23   01/25/23   10/18/22   2,4,7,8,9,155,15,16    6,275,616             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Forest Park Elementary School:
18-1629   Additions and Alterations    0-014-014  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/14/17   02 - 16                  250,000       250,000  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
19-0870   Reconstruction               0-014-015  02/20/20     DONE    DONE       DONE      11/27/19   11/08/19   07/18/19   05/21/19   16                       179,700       179,700  SLC             0           0           0 Mosaic Associates                       0      06/16/21                       11/08/19           
22-1856   Reconstruction               0-014-016  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                       514,957       514,957  MSK             0           0           0 Energia Energy                    494,813        /  /                         03/10/23           
23-0746   Reconstruction               0-014-017                         UNREVIEWED         10/20/23   09/25/23   01/25/23   10/18/22   2,7,8,9,155,15,16        845,470       845,470  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Sand Creek Middle School:
18-1630   Reconstruction               0-015-017  08/15/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/14/17   2,7,8,9,10,13,155,15     285,000       285,000  BMJ             0           0           0 Mosaic Associates                       0      04/07/21                       03/01/19           
  -       Reconstruction               0-015-018                                              /  /       /  /     04/10/19     /  /     7                              0             0  BMJ             0           0           0                                         0        /  /                           /  /             
21-0352   Reconstruction               0-015-019  02/09/22     DONE    DONE       DONE      09/14/21   09/09/21   03/24/21   11/14/17   2,9,155,15,16          1,556,770     1,556,770  SLC             0           0           0 SEI Design Group                        0      12/08/23                       09/09/21           
22-1857   Reconstruction               0-015-020  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                     1,020,423     1,020,423  MSK             0           0           0 Energia Energy                    980,506        /  /                         03/10/23           
23-0747   Reconstruction               0-015-021                         UNREVIEWED         10/20/23   09/25/23   01/25/23   10/18/22   2,4,7,8,9,155,15,16    4,165,644             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Roessleville Elementary:
18-1631   Additions and Alterations    0-017-013  07/29/19     DONE    DONE       DONE      03/13/19   03/01/19   02/15/19   11/14/17   02 - 16                  625,000       625,000  BMJ             0           0           0 Mosaic Associates                       0      06/29/21                       03/01/19           
19-0871   Reconstruction               0-017-014  02/20/20     DONE    DONE       DONE      11/27/19   11/08/19   07/18/19   05/21/19   16                       130,100       130,100  SLC             0           0           0 Mosaic Associates                       0      06/16/21                       11/08/19           
22-1858   Reconstruction               0-017-015  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                       315,451       315,451  MSK             0           0           0 Energia Energy                    303,111        /  /                         03/10/23           
23-0748   Reconstruction               0-017-016                         UNREVIEWED         10/20/23   09/25/23   01/25/23   10/18/22   2,7,8,9,155,15,16      1,779,000             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          District Offices:
22-1859   Reconstruction               1-005-004  08/29/23     DONE    DONE       DONE      03/15/23   03/10/23   11/29/22   01/03/23   16                       232,874             0  MSK             0           0           0 Energia Energy                    223,764        /  /                         03/10/23           

          Learning Annex (Storage):
23-0749   Reconstruction               2-040-001                         UNREVIEWED         10/20/23   09/25/23   09/18/23   10/18/22                            100,000             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Transportation Building:
23-0750   Reconstruction               5-036-001                         UNREVIEWED         10/20/23   09/25/23   08/17/23   10/18/22                            900,000             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Press Box @ HS:
  -    PR New Construction             7-038-001                                              /  /       /  /     09/18/23     /  /     02 - 16                        0             0  MSK             0           0           0                                         0        /  /                           /  /             
23-0751   New Construction             7-038-001                         UNREVIEWED         10/20/23   09/25/23   09/18/23   10/18/22   02 - 16                  175,000             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          Concession Bldg. @ HS:
  -    PR New Construction             7-039-001                                              /  /       /  /     09/18/23     /  /     02 - 16                        0             0  MSK             0           0           0                                         0        /  /                           /  /             
23-0752   New Construction             7-039-001                         UNREVIEWED         10/20/23   09/25/23   09/18/23   10/18/22   02 - 16                1,014,200             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           

          District Wide:
20-1958   Reconstruction               7-999-006  07/26/21     DONE    DONE       DONE      06/30/21   06/30/21   05/05/21   05/18/21   16                       100,000       100,000  SLC             0           0           0 SEI Design Group                        0      06/28/22                       06/30/21           

          (DEMO) Building BCD:
23-0753   Reconstruction               9-037-001                         UNREVIEWED         10/20/23   09/25/23   09/13/23   10/18/22                            454,000             0  MSK             0           0           0 SEI Design Group                        0        /  /                         09/25/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MENANDS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-15-02
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
22-2440   Reconstruction               0-001-011  10/10/23     DONE    DONE       DONE      06/23/23   06/22/23   01/18/23   05/16/23   2,7,155,16             2,360,000     2,360,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         06/22/23           

          Menands Public Library:
20-1327   Additions and Alterations    6-002-001  04/27/21     DONE    DONE       DONE      02/19/21   02/09/21   12/04/19   10/23/19   02 - 16                  135,600             0  JSS             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0      05/18/23                       02/09/21           
22-1494   Reconstruction               6-002-002  02/22/23     DONE    DONE       DONE      01/17/23   01/17/23   09/21/22   07/15/22   8,155,16                  57,472             0  SLC             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                         01/17/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH COLONIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-06-23-06
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Blue Creek Elementary:
18-1853   Reconstruction               0-003-009  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         40,200        40,200  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           

          Loudonville Elementary:
18-1081   Additions and Alterations    0-004-008  06/19/19     DONE    DONE       DONE      12/17/18   12/05/18   04/26/16   05/16/17   02 - 16                2,034,012     1,239,818  JLB             0           0           0 Collins & Scoville Architects           0      08/27/21                       12/05/18           
18-1854   Reconstruction               0-004-010  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   2,8,16                   439,605       439,605  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           

          Shaker High School:
18-2077   Additions and Alterations    0-005-011  10/10/19     DONE    DONE       DONE      06/10/19   06/04/19   04/26/16   05/16/17   02 - 16                6,890,817     6,414,652  JLB             0           0           0 Collins & Scoville Architects           0      08/27/21                       06/04/19           
18-1855   Reconstruction               0-005-016  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         84,848        84,848  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           
21-0964   Reconstruction               0-005-017  04/20/22     DONE    DONE       DONE      12/27/21   12/23/21   01/19/21   02/22/21   8,9,10,155,16            754,911       754,911  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/21           
22-1426   Reconstruction               0-005-018  05/17/23     DONE    DONE       DONE      01/06/23   01/05/23   09/27/22   05/16/17   2,7                    3,713,780     3,713,780  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         01/05/23           

          Southgate Elementary:
18-1856   Reconstruction               0-006-009  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         48,076        48,076  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           
22-1427   Reconstruction               0-006-010  05/17/23     DONE    DONE       DONE      01/06/23   01/05/23   11/21/22   05/16/17   2,4                      362,702       362,702  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         01/05/23           

          Boght Hill Elementary:
18-1857   Reconstruction               0-007-007  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         49,829        49,829  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           
  -       Reconstruction               0-007-008                                              /  /       /  /     11/16/21     /  /     2,4,7,8,9,10,155,16            0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Fort Ferry Elementary:
18-1082   Additions and Alterations    0-008-006  06/19/19     DONE    DONE       DONE      12/17/18   12/05/18   04/26/16   05/16/17   02 - 16                3,520,899     2,432,349  JLB             0           0           0 Collins & Scoville Architects           0      08/27/21                       12/05/18           
18-1858   Reconstruction               0-008-009  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   2,8,15                   234,843       234,843  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           

          Shaker Junior High:
18-1859   Reconstruction               0-009-011  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         74,619        74,619  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           
22-1428   Reconstruction               0-009-012  05/17/23     DONE    DONE       DONE      01/06/23   01/05/23   09/27/22   05/16/17   2,7                      692,810       692,810  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         01/05/23           

          Latham Ridge Elementary:
18-1083   Additions and Alterations    0-011-006  06/19/19     DONE    DONE       DONE      12/17/18   12/05/18   04/26/16   05/16/17   02 - 16                2,595,735     1,797,753  JLB             0           0           0 Collins & Scoville Architects           0      08/27/21                       12/05/18           
18-1860   Reconstruction               0-011-009  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         57,452        57,452  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           

          Maplewood Elem:
19-0744   Reconstruction               0-030-002  12/24/19     DONE    DONE       DONE      11/08/19   11/01/19   07/29/19   08/06/19   2,155                     80,000             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         11/01/19           

          Goodrich School:
18-1861   Reconstruction               1-002-004  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   8                         43,776             0  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           

          Bus Garage:
18-1862   Reconstruction               5-015-008  06/14/19     DONE    DONE       DONE      04/15/19   03/27/19   10/23/18   05/15/18   2,8,16                    96,752        96,752  MTM             0           0           0 Collins & Scoville Architects           0      07/28/22                       03/27/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREEN ISLAND UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-07-01-03
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Heatly School:
  -    PR Additions and Alterations    0-001-009                                              /  /       /  /     04/28/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-0359   Additions and Alterations    0-001-009  01/27/22     DONE    DONE       DONE      09/14/21   09/13/21   04/28/21   12/15/20   02 - 16                1,659,200     1,659,200  JLB             0           0           0 Collins & Scoville Architects           0      10/02/23                       09/13/21           
22-1452   Reconstruction               0-001-010  07/28/23     DONE    DONE       DONE      01/09/23   01/06/23   11/18/22   12/15/20   2                        150,000       150,000  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         01/06/23           
22-2269FC Reconstruction               0-001-011  08/18/23     DONE    DONE       DONE      05/24/23   04/19/23   02/22/23   12/15/20   155                      425,095       425,095  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         04/19/23           
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GUILDERLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-08-02-06
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Altamont Elementary School:
87-1220PR New Construction             0-001-001  03/25/88     DONE    DONE       DONE        /  /       /  /     04/17/22     /  /     02 - 16                  257,648       257,648  JLB             0           0           0                                         0        /  /                           /  /             
19-1091   Reconstruction               0-001-021  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                     543,046       543,046  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0201   Reconstruction               0-001-022  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,7,8,9,155,16           580,579       580,579  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-1001   Reconstruction               0-001-023  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                     377,706       377,706  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1344   Reconstruction               0-001-024  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   2,9,155,15,16            642,400       642,400  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Westmere Elementary:
19-1092   Reconstruction               0-003-012  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                     548,753       548,753  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0202   Reconstruction               0-003-013  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,8,9,155,15,16        1,264,463     1,264,463  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-0997   Reconstruction               0-003-014  04/06/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   05/21/19   155,15,16                288,352       288,352  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/29/21           
21-1002   Reconstruction               0-003-015  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                     457,006       457,006  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1345   Reconstruction               0-003-016  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   2,9,10,155,15,16         783,036             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Guilderland High School:
18-1726   Reconstruction               0-005-030  05/28/19     DONE    DONE       DONE      03/27/19   12/26/18   12/12/18   05/21/19   7,9,155,16               130,000       130,000  JLB             0           0           0 Collins & Scoville Architects           0      08/07/20                       12/26/18           
19-1093   Reconstruction               0-005-031  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                   2,055,252     2,055,252  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0203   Reconstruction               0-005-032  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,4,7,8,9,10,14,155,  11,936,611    11,936,611  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-1003   Reconstruction               0-005-033  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                   3,392,589     3,392,589  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1346   Reconstruction               0-005-034  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   2,7,8,9,10,155,15,16   6,130,922     6,130,922  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           
22-1399FC Reconstruction               0-005-035  01/11/23     DONE    DONE       DONE      01/04/23   12/27/22   04/18/22   12/20/22   7,16                     419,039       419,039  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/27/22           

          Lynwood Elementary:
19-1094   Reconstruction               0-007-010  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                     313,857       313,857  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0204   Reconstruction               0-007-011  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,8,9,10,155,15,16     1,093,726     1,093,726  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-0998   Reconstruction               0-007-012  04/06/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   05/21/19   155,15,16                262,841       262,841  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/29/21           
21-1004   Reconstruction               0-007-013  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                     527,006       527,006  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1347   Reconstruction               0-007-014  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   2,9,155,15,16            736,806       736,806  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Farnsworth Middle School:
19-1095   Reconstruction               0-009-022  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                   1,136,310     1,136,310  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0205   Reconstruction               0-009-023  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,4,7,8,9,14,155,15,   5,148,090     5,148,090  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-1005   Reconstruction               0-009-024  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                     610,507       610,507  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1348   Reconstruction               0-009-025  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   2,7,8,9,10,155,15,16   3,788,787     3,788,787  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Guilderland Elementary School:
19-1096   Reconstruction               0-012-017  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                     363,773       363,773  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0206   Reconstruction               0-012-018  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,9,155,16               974,701       974,701  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-0999   Reconstruction               0-012-019  04/06/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   05/21/19   155,15,16                288,352       288,352  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/29/21           
21-1006   Reconstruction               0-012-020  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                     442,006       442,006  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1349   Reconstruction               0-012-021  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   2,9,155,15,16            307,801       307,801  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Pine Bush Elementary School:
19-1097   Reconstruction               0-015-006  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   8,16                     349,776       349,776  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0207   Reconstruction               0-015-007  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,7,155,15,16          2,572,819     2,572,819  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           
21-1000   Reconstruction               0-015-008  04/06/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   05/21/19   155,15,16                262,841       262,841  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/29/21           
21-1007   Reconstruction               0-015-009  05/03/22     DONE    DONE       DONE      12/29/21   12/29/21   11/22/21   10/07/21   2,16                     557,006       557,006  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/29/21           
22-1350   Reconstruction               0-015-010  01/24/23     DONE    DONE       DONE      12/28/22   12/23/22   11/22/21   10/07/21   16                         7,999             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Maintenance Bldg #3 (frmrly 5-010):
19-1098   Reconstruction               3-010-006  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   16                        18,985             0  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0208   Reconstruction               3-010-007  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   7,15,16                  168,212             0  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           

          Transportation Facility:
19-1099   Reconstruction               5-016-004  05/15/20     DONE    DONE       DONE      01/02/20   12/18/19   06/21/19   05/21/19   10,16                  1,109,243     1,109,243  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       12/18/19           
20-0209   Reconstruction               5-016-005  10/13/20     DONE    DONE       DONE      08/13/20   07/17/20   06/21/19   05/21/19   2,9,14,155,15,16       1,313,995     1,313,995  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       07/17/20           

          Guilderland Public Library:
19-0313   Reconstruction               6-014-011  10/21/19     DONE    DONE       DONE      08/28/19   08/19/19   07/29/19   05/21/19   4,7,8,9,155,15         1,217,238             0  JLB             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                         08/19/19           
19-1842   Additions and Alterations    6-014-012  08/25/20     DONE    DONE       DONE      06/12/20   06/03/20   04/24/20   05/21/19   02 - 16                7,136,460             0  JLB             0           0           0 BUTLER ROWLAND MAYS ARCHITECT           0        /  /                         06/03/20           

          Farnsworth Middle School Pavilion:
  -    PR New Construction             7-023-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1402FA New Construction             7-023-001  01/11/23     DONE    DONE       DONE      01/04/23   12/27/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/27/22           

          Guilderland High School Pavilion:
  -    PR New Construction             7-024-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1403FA New Construction             7-024-001  01/11/23     DONE    DONE       DONE      01/04/23   12/27/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/27/22           

          Westmore Elementary School Pavilion:
  -    PR New Construction             7-025-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1400FC New Construction             7-025-001  01/11/23     DONE    DONE       DONE      01/04/23   12/27/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/27/22           

          Guilderland Elementary Sch Pavilion:
  -    PR New Construction             7-026-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1401FC New Construction             7-026-001  01/11/23     DONE    DONE       DONE      01/04/23   12/23/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Lynwood Elementary School Pavilion:
  -    PR New Construction             7-027-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1404FA New Construction             7-027-001  01/11/23     DONE    DONE       DONE      01/04/23   12/23/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Pine Bush Elementary School Pavilion:
  -    PR New Construction             7-028-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1405FA New Construction             7-028-001  01/11/23     DONE    DONE       DONE      01/04/23   12/23/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           

          Altamont Elementary School Pavilion:
  -    PR New Construction             7-029-001                                              /  /       /  /     04/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1406FA New Construction             7-029-001  01/11/23     DONE    DONE       DONE      01/04/23   12/23/22   04/17/22   12/20/22   02 - 16                  266,112             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         12/23/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VOORHEESVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-10-03-06
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Clayton A. Bouton Jr/Sr High School:
20-0199   Reconstruction               0-001-021  11/28/20     DONE    DONE       DONE      08/13/20   07/15/20   06/28/18   05/15/18   2,4,8,9,10,155,15,16   2,540,000     2,540,000  SLC             0           0           0 Mosaic Associates                       0      08/31/22                       07/15/20           
21-1583   Reconstruction               0-001-022  11/23/22     DONE    DONE       DONE      03/30/22   03/29/22   10/08/21   03/15/18   2,155,16                 180,000       180,000  WLC             0           0           0 Mosaic Associates                       0        /  /                         03/29/22           
  -       Reconstruction               0-001-023                                              /  /       /  /     08/19/22     /  /     8,9,155,16                     0    34,410,331  WLC             0           0           0                                         0        /  /                           /  /             
22-0295SB Reconstruction               0-001-023               DONE                           /  /       /  /     08/19/22     /  /     8,9,155,16                     0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-1393   Reconstruction               0-001-024  03/07/23     DONE    DONE       DONE      01/04/23   12/30/22   11/30/22   05/17/22   7,10                     100,000       100,000  WLC             0           0           0 Mosaic Associates                       0      06/28/23                       12/30/22           
23-0092   Reconstruction               0-001-025  02/06/24     DONE    DONE       DONE      07/17/23   07/14/23   03/10/23   03/15/18   2,8,9,155,16             205,000       205,000  WLC             0           0           0 Mosaic Associates                       0        /  /                         07/14/23           
23-0982   Reconstruction               0-001-026                         UNREVIEWED         11/14/23   11/07/23   06/14/23   12/06/22   155,16                         0             0  WLC             0           0           0 Mosaic Associates                       0        /  /                         11/07/23           
  -    SB Reconstruction               0-001-BA1                                              /  /       /  /       /  /       /  /     9,155,16                       0             0  WLC             0           0           0                                         0        /  /                           /  /             

          elementary School/Bus Garage:
20-0200   Reconstruction               0-002-018  11/28/20     DONE    DONE       DONE      08/13/20   07/15/20   06/28/18   05/15/18   2,8,9,16                 197,000       197,000  SLC             0           0           0 Mosaic Associates                       0      08/31/22                       07/15/20           
18-2209   Reconstruction               0-002-019  06/27/19     DONE    DONE       DONE      06/26/19   06/25/19   04/18/19   05/07/19   9                        125,000       125,000  SLC             0           0           0 Mosaic Associates                       0      09/13/19                       06/25/19           
21-1132   Reconstruction               0-002-020  03/02/22     DONE    DONE       DONE      01/14/22   01/13/22   10/13/21   05/20/21   2,155,16                 100,000       100,000  SLC             0           0           0 Mosaic Associates                       0      06/27/22                       01/13/22           
  -    PR Additions and Alterations    0-002-021                                              /  /       /  /     12/08/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
23-0291   Additions and Alterations    0-002-021               STARTED DONE       ADD. REQ'D08/18/23   08/18/23   12/08/22   12/06/22   02 - 16               14,910,638    14,047,250  WLC             0           0           0 Mosaic Associates                       0        /  /                         08/18/23           
23-0983   Reconstruction               0-002-022                         UNREVIEWED         11/14/23   11/07/23   06/14/23   12/06/22   155,16                         0             0  WLC             0           0           0 Mosaic Associates                       0        /  /                         11/07/23           
23-0619   Reconstruction               0-002-023  11/03/23     DONE    DONE       DONE      10/06/23   10/04/23   07/26/23   05/16/23   7                        100,000       100,000  WLC             0           0           0 Mosaic Associates                       0        /  /                         10/04/23           

          Storage Bldg:
22-1897PR New Construction             2-016-001                                            03/20/23     /  /     12/19/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
23-0292   New Construction             2-016-001               STARTED DONE       ADD. REQ'D08/18/23   08/18/23   12/19/22   12/06/22   02 - 16                  214,000             0  WLC             0           0           0 Mosaic Associates                       0        /  /                         08/18/23           

          Transportation Facility:
22-1630PR New Construction             5-015-001                         UNREVIEWED         02/06/23   02/03/23   12/08/22     /  /     02 - 16               10,075,362             0  WLC             0           0           0                                         0        /  /                         02/03/23           
22-2321   New Construction             5-015-001  01/09/24     DONE    DONE       DONE      06/05/23   06/02/23   12/08/22   12/06/22   02 - 16               10,075,362    10,075,362  WLC             0           0           0 Mosaic Associates                       0        /  /                         06/02/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERVLIET CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-12-00-01
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
20-0817   Reconstruction               0-001-015  02/19/21     DONE    DONE       DONE      11/13/20   11/02/20   08/24/20   02/04/20   2,4,7,9,14,155,15,16   5,105,797     5,105,797  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       11/02/20           
22-0754FA Reconstruction               0-001-016  01/11/23     DONE    DONE       DONE      10/19/22   09/28/22   03/29/22   05/17/22   2,4,7,8,9,10,155,15,     742,200       742,200  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         09/28/22           

          Watervliet Elementary:
20-0818   Reconstruction               0-006-013  02/19/21     DONE    DONE       DONE      11/13/20   11/02/20   08/24/20   02/04/20   2,4,7,8,9,14,155,15,   4,891,025     4,891,025  JLB             0           0           0 Collins & Scoville Architects           0      12/01/23                       11/02/20           
22-0755FA Reconstruction               0-006-014  01/11/23     DONE    DONE       DONE      10/19/22   09/28/22   03/29/22   05/17/22   2,4,7,8,9,10,155,15,     723,480       723,480  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         09/28/22           

          Storage Bldg @ Jr/Sr High:
22-0756FA Reconstruction               2-011-002  01/11/23     DONE    DONE       DONE      10/19/22   09/28/22   03/29/22   05/17/22   2,4,7,8,9,10,155,15,     659,280             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         09/28/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ALBANY-SCHOH-SCHEN STATUS REPORT ON CAPITAL PROJECTS
District No.: 01-90-00-00
last updated on 03/28/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Schoharie Center:
19-0064   Reconstruction               0-001-006  08/16/19     DONE    DONE       DONE      07/12/19   07/03/19   11/20/18   01/17/19   7,8,9,155,16             200,000       200,000  JLB             0           0           0 Griffith Dardanelli,Architect           0      10/13/20                       07/03/19           
22-2264   Reconstruction               0-001-007  09/21/23     DONE    DONE       DONE      05/22/23   05/22/23     /  /       /  /     2,9,155,15,16          4,034,798     1,165,640  WLC             0           0           0 WCGS Architects                         0        /  /                         05/22/23           
23-0420   Reconstruction               0-001-008  03/15/24     DONE    DONE       DONE      09/08/23   09/06/23   05/30/23   06/15/23   2                        328,500       328,500  WLC             0           0           0 WCGS Architects                         0        /  /                         09/06/23           

          Maywood School:
18-1409   Reconstruction               0-018-014  04/15/19     DONE    DONE       DONE      02/07/19   02/01/19   11/20/18   01/17/19   2,4,7                    550,000       550,000  MTM             0           0           0 Griffith Dardanelli,Architect           0      09/09/19                       02/01/19           

          Equipment Garage (@ Schoharie):
  -    PR New Construction             2-068-001                                              /  /       /  /     10/12/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1258   New Construction             2-068-001  07/13/23     DONE    DONE       DONE      12/15/22   12/15/22   10/12/22   07/11/23   02 - 16                2,525,249             0  WLC             0           0           0 WCGS Architects                         0      03/15/24           YES         12/15/22           

          10c Airline Drive:
18-1924TQ Temporary Quarters           8-065-001  08/03/20     DONE    DONE       DONE      05/06/19   05/01/19   05/06/19     /  /                                    0             0  JLB             0           0           0 HCP Architects                          0        /  /                         05/01/19           

          Capital Region Career & Tech Cntr:
19-1726TQ Temporary Quarters           8-066-001  11/03/20     DONE    DONE       DONE      05/13/20   05/08/20   01/31/20     /  /                                    0             0  JSS             0           0           0                                         0        /  /                         05/08/20           

          Special Education Center:
19-1727TQ Temporary Quarters           8-067-001  10/13/20     DONE    DONE       DONE      05/13/20   05/08/20   01/31/20     /  /                                    0             0  JSS             0           0           0                                         0        /  /                         05/08/20           

          Alb Career & Tech Education Ext Ctr.:
23-1639TQ Temporary Quarters           8-069-001                         UNREVIEWED         03/15/24   01/11/24   10/23/23     /  /                                    0             0  WLC             0           0           0                                         0        /  /                         01/11/24           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED