CHEMUNG COUNTY

CHEMUNG COUNTY

ELMIRA 070600
ELMIRA HEIGHTS 070902
HORSEHEADS 070901

















Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/25/24 at 06:56:33




ELMIRA CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-06-00-01
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Coburn Elementary:
20-1148   Reconstruction               0-002-017  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 524,980       524,980  JLB             0           0           0 Hunt Engineers,Architects & l     524,980        /  /                         01/15/21           
21-0763FA Reconstruction               0-002-018  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   02/16/22   8,155,16               2,000,000     2,000,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
22-1648   Reconstruction               0-002-019               DONE    DONE       ADD. REQ'D02/10/23   10/21/22   10/20/22   06/09/20   2,7,8,9,155,15,16      3,473,500     3,473,500  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/21/22           

          Beecher Elementary:
20-1149   Reconstruction               0-005-014  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 410,413       410,413  JLB             0           0           0 Hunt Engineers,Architects & l     410,413        /  /                         01/15/21           
21-0764FC Reconstruction               0-005-015  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   02/16/22   8,155,16                 250,000       250,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
22-1944FA Reconstruction               0-005-016  05/25/23     DONE    DONE       DONE      03/29/23   10/31/22   10/20/22   06/09/20   2,8,9,155,15,16        2,198,000     2,198,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/31/22           

          Diven Elementary:
19-1436   Reconstruction               0-006-016  04/02/20     DONE    DONE       DONE      02/19/20   02/12/20   12/12/19   05/21/19   8                        100,000       100,000  JLB             0           0           0 Hunt Engineers,Architects & l           0      11/23/20                       02/12/20           
20-1150   Reconstruction               0-006-017  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 276,398       276,398  JLB             0           0           0 Hunt Engineers,Architects & l     276,398        /  /                         01/15/21           
21-0765   Reconstruction               0-006-018  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   06/09/20   8,9,16                   450,000       450,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
22-1945FA Reconstruction               0-006-019  05/25/23     DONE    DONE       DONE      03/29/23   10/31/22   10/20/22   06/09/20   2,4,8,9,155,15,16      6,360,000     6,360,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/31/22           

          Fassett Elementary School:
20-1151   Reconstruction               0-008-011  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 338,517       338,517  JLB             0           0           0 Hunt Engineers,Architects & l     338,517        /  /                         01/15/21           
21-0766FC Reconstruction               0-008-012  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   02/16/22   155,16                   350,000       350,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
21-0767   Reconstruction               0-008-013  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   06/09/20   2,4,7,8,9,10,155,15,   4,747,819     4,747,819  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
22-1946FA Reconstruction               0-008-014  05/25/23     DONE    DONE       DONE      03/29/23   10/31/22   10/20/22   02/16/22   2                        221,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/31/22           

          Thomas Natatorium Elmira Free Acad.:
20-1152   Reconstruction               0-009-007  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 301,690       301,690  JLB             0           0           0 Hunt Engineers,Architects & l     301,690        /  /                         01/15/21           
20-1266   Reconstruction               0-009-008  05/12/21     DONE    DONE       DONE      02/09/21   02/01/21   12/08/20   06/09/20   2,4,7,8,9,10,155,15,   4,807,356     4,807,356  JLB             0           0           0 Hunt Engineers,Architects & l           0      07/20/22                       02/01/21           

          Riverside Elementary:
20-1153   Reconstruction               0-012-015  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 376,963       376,963  JLB             0           0           0 Hunt Engineers,Architects & l     376,963        /  /                         01/15/21           
21-0768   Reconstruction               0-012-016  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   06/09/20   2,7,8,9,10,155,15,16   1,603,489     1,603,489  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
21-0769FC Reconstruction               0-012-017  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   02/16/22   8,155,16                 390,000       390,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           

          Hendy Avenue Elementary:
20-1154   Reconstruction               0-014-018  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 419,678       419,678  JLB             0           0           0 Hunt Engineers,Architects & l     419,678        /  /                         01/15/21           
21-0770   Reconstruction               0-014-019  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   06/09/20   7,8,9,10,155,15,16     2,542,693     2,542,693  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
21-0771FC Reconstruction               0-014-020  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   02/16/22   155,16                   400,000       400,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
22-1649   Reconstruction               0-014-021               DONE    DONE       ADD. REQ'D02/10/23   10/31/22   10/20/22   06/09/20   9,16                     220,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/31/22           

          Southside HS (see files DEC issue):
20-0081   Reconstruction               0-016-023  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/24/18   06/09/20   2,4,8,9,10,155,15,16   7,951,796     7,951,796  JLB             0           0           0 Hunt Engineers,Architects & l           0      09/09/22                       07/02/20           
20-1155   Reconstruction               0-016-024  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 909,093       909,093  JLB             0           0           0 Hunt Engineers,Architects & l     909,093        /  /                         01/15/21           
21-0128   Reconstruction               0-016-025  12/21/21     DONE    DONE       DONE      08/02/21   08/02/21   04/28/21     /  /     2,4,7,9                        0             0  JLB             0           0           0 SWBR Architects P.C.                    0        /  /                         08/02/21           
21-1609   Reconstruction               0-016-026  02/07/23     DONE    DONE       DONE      04/06/22   04/06/22   03/17/22   06/09/20   2,155,16               2,149,337     2,149,337  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         04/06/22           

          Pine City Elementary:
20-1156   Reconstruction               0-033-020  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 407,629       407,629  JLB             0           0           0 Hunt Engineers,Architects & l     407,629        /  /                         01/15/21           
21-0772   Reconstruction               0-033-021  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   06/09/20   2,4,8,9,10,155,15,16   2,254,066     2,254,066  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
21-0773FC Reconstruction               0-033-022  03/02/22     DONE    DONE       DONE      11/19/21   11/19/21   10/29/21   02/16/22   155,16                   950,000       950,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/19/21           
22-1947FA Reconstruction               0-033-023  05/25/23     DONE    DONE       DONE      03/29/23   10/31/22   10/03/22   02/16/22   2                        229,000             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/31/22           

          Broadway ES(K-6)/MS(7-8):
20-1157   Reconstruction               0-034-021  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16               1,158,899     1,158,899  JLB             0           0           0 Hunt Engineers,Architects & l   1,158,899        /  /                         01/15/21           
22-1948FA Reconstruction               0-034-022  05/25/23     DONE    DONE       DONE      03/29/23   10/31/22   10/20/22   06/09/20   2,9,16                 1,195,000     1,195,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/31/22           
22-2295   Reconstruction               0-034-023  10/05/23     DONE    DONE       DONE      05/30/23   05/26/23   05/18/23   05/17/22   155                      100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         05/26/23           

          ErnieDavisfmr Elm Free(1-007 comb.):
20-1158   Reconstruction               0-038-029  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                 391,989       391,989  JLB             0           0           0 Hunt Engineers,Architects & l     391,989        /  /                         01/15/21           
20-1267   Reconstruction               0-038-030  05/21/21     DONE    DONE       DONE      02/09/21   02/01/21   12/08/20   06/09/20   155                      100,000       100,000  JLB             0           0           0 Hunt Engineers,Architects & l           0      02/25/22                       02/01/21           
22-1638FA Reconstruction               0-038-031  06/22/23     DONE    DONE       DONE      02/08/23   01/27/23   11/16/22   06/09/20   2,4,155,15,16          1,951,706     1,951,706  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/27/23           
23-1146   Reconstruction               0-038-032                         UNREVIEWED         12/07/23   11/30/23   10/11/23   06/09/20   2,8,9,10,155,15,16             0             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/30/23           

          Admin Building (previously 0-013):
20-1159   Reconstruction               1-013-001  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16               1,555,513             0  JLB             0           0           0 Hunt Engineers,Architects & l   1,555,513        /  /                         01/15/21           
21-0327   Reconstruction               1-013-002  11/22/21     DONE    DONE       DONE      09/13/21   09/10/21   05/17/21   06/09/20   2,4,7,8,9,10,155,15,   8,969,929             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/10/21           

          Field House South Side:
20-0082   Reconstruction               2-044-002  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/24/18   06/09/20   2,4,8,9,10,155,15,16   1,013,965             0  JLB             0           0           0 Hunt Engineers,Architects & l           0      09/09/22                       07/02/20           
21-1610   Reconstruction               2-044-003  02/07/23     DONE    DONE       DONE      04/06/22   04/06/22   03/17/22   06/09/20   2,15,16                   28,500             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         04/06/22           

          Storage Bldg #4@ Bus Garage:
19-0163   Reconstruction               2-075-002  12/04/19     DONE    DONE       DONE      07/25/19   07/16/19   07/02/19   05/17/16   16                        67,164             0  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/20                       07/16/19           

          Benjamin Building:
  -    PR Additions and Alterations    2-076-003                                              /  /       /  /     10/20/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-2240FA Additions and Alterations    2-076-003  07/13/23     DONE    DONE       DONE      05/19/23   11/14/22   10/20/22   06/09/20   02 - 16                2,346,888             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/14/22           

          Maintenance Building:
20-1160   Reconstruction               3-028-006  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                  59,223             0  JLB             0           0           0 Hunt Engineers,Architects & l      59,223        /  /                         01/15/21           

          Bus Garage:
19-0164   Reconstruction               5-017-015  12/04/19     DONE    DONE       DONE      07/25/19   07/16/19   07/02/19   05/17/16   2,4,8,16               1,385,027     1,385,027  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/20                       07/16/19           
20-1161   Reconstruction               5-017-016  01/28/22     DONE    DONE       DONE      01/19/21   01/15/21   11/24/20   06/09/20   8,155,16                  64,239        64,239  JLB             0           0           0 Hunt Engineers,Architects & l      64,239        /  /                         01/15/21           

          Southside Press Box Demolition:
20-0083   Reconstruction               7-051-002  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/26/18   06/09/20   2                              0             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/02/20           

          Restrooms/Athl Stad. Southside HS:
20-0084   Reconstruction               7-070-002  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/24/18   06/09/20   2,4,7,8,9,10,155,15,           0             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/02/20           

          Fieldhouse 2:
20-0085   New Construction             7-078-001  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/26/18   06/09/20   02 - 16                1,430,370             0  JLB             0           0           0 Hunt Engineers,Architects & l           0      09/01/22                       07/02/20           

          Press Box (repl Southside Press Box):
20-0086   New Construction             7-079-001  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/26/18   06/09/20   02 - 16                  247,970             0  JLB             0           0           0 Hunt Engineers,Architects & l           0      09/01/22                       07/02/20           

          Ticket Booth - South:
20-0087   New Construction             7-081-001  09/16/20     DONE    DONE       DONE      07/21/20   07/02/20   10/26/18   06/09/20   02 - 16                   86,620             0  JLB             0           0           0 Hunt Engineers,Architects & l           0      09/09/22                       07/02/20           

          Press Box @ Baseball Field:
  -    PR New Construction             7-082-001                                              /  /       /  /     03/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-1611   New Construction             7-082-001  02/07/23     DONE    DONE       DONE      04/06/22   04/06/22   03/17/22   05/17/22   02 - 16                   56,705             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         04/06/22           

          Press Box @ Softball Field:
  -    PR New Construction             7-083-001                                              /  /       /  /     03/17/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-1612   New Construction             7-083-001  02/07/23     DONE    DONE       DONE      04/06/22   04/06/22   03/17/22   05/17/22   02 - 16                   56,705             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         04/06/22           

          District-Wide:
  -    SB Reconstruction               7-999-BA2               DONE                           /  /       /  /       /  /       /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Lease @ frmr Elmira Ernie Davis MS:
18-2140XX Reconstruction               8-003-003                         CANCELLED          06/18/19   06/17/19   04/08/19     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         06/17/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HORSEHEADS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-01-06
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Center Street Elementary:
20-0329   Reconstruction               0-003-021  12/23/20     DONE    DONE       DONE      09/03/20   08/26/20   07/14/20   10/17/17   2,8,9                    390,260       390,260  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/26/20           
21-0197FC Reconstruction               0-003-022  02/07/22     DONE    DONE       DONE      08/20/21   08/17/21   07/23/21   05/18/21   2,4,7,8,9,155,15,16    1,400,000     1,400,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      09/28/23                       08/17/21           
21-0198   Reconstruction               0-003-023  02/07/22     DONE    DONE       DONE      08/20/21   08/17/21   07/23/21   05/18/21   2,4,7,8,9,155,15,16    2,000,000     2,000,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      09/28/23                       08/17/21           

          Big Flats Elementary:
20-0330   Reconstruction               0-006-017  12/23/20     DONE    DONE       DONE      09/03/20   08/26/20   07/14/20   10/17/17   2,9,155,15,16          1,703,946     1,703,946  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/26/20           
22-0604PR Additions and Alterations    0-006-018               DONE                         09/28/22     /  /     10/04/21     /  /     02 - 16                        0    17,285,646  JJH             0           0           0                                         0        /  /                           /  /             
22-0638   Additions and Alterations    0-006-018  03/13/23     DONE    DONE       DONE      10/05/22   10/04/22   10/04/21   12/07/21   02 - 16               18,581,722     8,948,645  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/04/22           
  -    PR Additions and Alterations    0-006-019                                              /  /       /  /     09/15/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0639FA Additions and Alterations    0-006-019  03/13/23     DONE    DONE       DONE      10/05/22   10/04/22   09/15/22   09/15/22   02 - 16                1,000,000             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/04/22           
23-0890   Reconstruction               0-006-020                         UNREVIEWED         11/06/23   10/25/23   10/05/23   05/16/23   2,16                           0             0  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/25/23           

          Ridge Road Elementary:
20-0331   Reconstruction               0-008-018  12/23/20     DONE    DONE       DONE      09/03/20   08/26/20   07/14/20   10/10/17   2,7,155,15,16          1,928,874     1,928,874  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/26/20           
22-0605PR Additions and Alterations    0-008-019               DONE                         09/28/22     /  /     10/04/21     /  /     02 - 16                        0    15,900,021  JJH             0           0           0                                         0        /  /                           /  /             

          Senior High School (fmly North Wing):
19-1596   Reconstruction               0-009-028  05/29/20     DONE    DONE       DONE      03/16/20   02/28/20   11/15/19   05/21/19   155                    1,000,000     1,000,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/30/21                       02/28/20           
22-1509   Reconstruction               0-009-029  06/20/23     DONE    DONE       DONE      01/18/23   01/18/23   10/25/22   05/17/22   16                       214,631       214,631  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/18/23           
23-0723   Reconstruction               0-009-030               UNREVIEWED
                                                                       DONE       DONE      10/16/23   10/07/23   10/05/23   12/07/21   2,4,8,9,155,16                 0             0  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/07/23           
  -    PR Additions and Alterations    0-009-031                                              /  /       /  /     12/01/23     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Gardner Road Elementary:
20-0332   Reconstruction               0-012-019  12/23/20     DONE    DONE       DONE      09/03/20   08/26/20   07/14/20   10/10/17   2,7,8,155,15,16        1,132,990     1,132,990  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/26/20           
21-0199   Reconstruction               0-012-020  02/07/22     DONE    DONE       DONE      08/20/21   08/17/21   07/23/21   05/18/21   2,8                      400,000       400,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      09/28/23                       08/17/21           
22-0606PR Additions and Alterations    0-012-021               DONE                         09/28/22     /  /     10/04/21     /  /     02 - 16                        0    17,158,828  JJH             0           0           0                                         0        /  /                           /  /             
22-0841   Additions and Alterations    0-012-021  03/28/23     DONE    DONE       DONE      10/28/22   10/24/22   10/04/21   12/07/21   02 - 16               16,556,974    10,106,841  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/24/22           
23-0891   Reconstruction               0-012-022                         UNREVIEWED         11/06/23   10/25/23   10/05/23   05/16/23   2,16                           0             0  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/25/23           

          Middle School:
  -    PR Additions and Alterations    0-013-028                                              /  /       /  /     04/29/19     /  /     02 - 16                        0    29,436,590  SLC             0           0           0                                         0        /  /                           /  /             
19-0289   Additions and Alterations    0-013-028  01/03/20     DONE    DONE       DONE      08/26/19   08/08/19   04/29/19   10/17/17   02 - 16               14,548,439    14,548,439  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/08/19           
22-0256   Reconstruction               0-013-029  11/01/22     DONE    DONE       DONE      08/15/22   08/09/22   07/18/22   12/07/21   2,7,155,15,16          4,948,676     4,948,676  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/09/22           
22-1510   Reconstruction               0-013-030  06/20/23     DONE    DONE       DONE      01/18/23   01/18/23   10/25/22   05/17/22   7,155,16                 327,156       327,156  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/18/23           
22-1001SB Reconstruction               0-013-031               DONE                           /  /       /  /     11/17/22     /  /     7,10,14,16                     0    39,845,023  JLB             0           0           0                                         0        /  /                           /  /             
22-1240   Reconstruction               0-013-031  05/08/23     DONE    DONE       DONE      12/14/22   12/13/22     /  /     11/04/14   7,10,14,16               238,037       238,037  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         12/13/22           

          Storage Building:
  -    PR New Construction             2-050-001                                              /  /       /  /     10/25/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1511   New Construction             2-050-001  06/20/23     DONE    DONE       DONE      01/18/23   01/18/23   10/25/22   05/17/22   02 - 16                  612,191             0  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/18/23           

          Bus Garage:
20-0333   Reconstruction               5-005-015  12/23/20     DONE    DONE       DONE      09/03/20   08/26/20   07/14/20   10/10/17   2,8,9,155,15,16        1,988,802     1,988,802  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/26/20           
22-1512   Reconstruction               5-005-016  06/20/23     DONE    DONE       DONE      01/18/23   01/18/23   11/16/22   05/17/22   16                        96,022        96,022  JJH             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/18/23           

          Stadium Entry Building:
21-2002   Reconstruction               7-044-002  10/04/22     DONE    DONE       DONE      06/17/22   06/17/22   05/31/22   12/07/21   2,4,7,8,9,155,15,16    1,795,855             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         06/17/22           

          Stadium Locker Room and Storage:
  -    PR New Construction             7-049-001                                              /  /       /  /     06/09/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
21-2003   New Construction             7-049-001  10/04/22     DONE    DONE       DONE      06/17/22   06/17/22   06/09/22   12/07/21   02 - 16                3,199,365             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         06/17/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELMIRA HEIGHTS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 07-09-02-06
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Edison High School:
19-0337   Reconstruction               0-001-016  01/16/20     DONE    DONE       DONE      08/30/19   08/14/19   05/15/19   05/21/19   2,4,8,9,155,16           100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      05/29/20                       08/14/19           
20-0267   Reconstruction               0-001-017  12/01/20     DONE    DONE       DONE      08/25/20   07/16/20   05/08/20   06/16/20   2,4,8,9,155,16           100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      06/04/21                       07/16/20           
20-0268   Reconstruction               0-001-018  12/01/20     DONE    DONE       DONE      08/25/20   07/16/20   05/19/20   06/16/20   2,4,8,9,155,16           125,000             0  SLC             0           0           0 Hunt Engineers,Architects & l           0      10/01/21                       07/16/20           
21-0138   Reconstruction               0-001-019  01/10/22     DONE    DONE       DONE      08/04/21   08/03/21   06/11/21   05/18/21   8,9,13                   100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      05/31/22                       08/03/21           
21-0139   Reconstruction               0-001-020  01/10/22     DONE    DONE       DONE      08/04/21   08/03/21   06/11/21   05/18/21   8,9,13,16                195,000       195,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      03/22/23                       08/03/21           
21-1467   Reconstruction               0-001-021  11/22/22     DONE    DONE       DONE      03/09/22   03/08/22   01/25/22   12/14/21   8,155,16                 499,917       499,917  SLC             0           0           0 Hunt Engineers,Architects & l     499,917        /  /                         03/08/22           
22-0478   Reconstruction               0-001-022  01/20/23     DONE    DONE       DONE      09/14/22   08/24/22   04/11/22   12/14/21   2,4,7,8,9,13,155,15,   4,367,090     4,367,090  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/24/22           
22-2096   Reconstruction               0-001-023  05/31/23     DONE    DONE       DONE      04/26/23   04/24/23   03/31/23   05/16/23   2,8,16                   100,000       100,000  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         04/24/23           

          Cohen Elementary/Middle School:
21-1468   Reconstruction               0-007-018  11/22/22     DONE    DONE       DONE      03/09/22   03/08/22   01/25/22   12/14/21   8,9,14,16                400,172       400,172  SLC             0           0           0 Hunt Engineers,Architects & l     400,172        /  /                         03/08/22           
21-1614   Reconstruction               0-007-019  05/19/22     DONE    DONE       DONE      04/08/22   04/08/22   02/23/22   05/17/22   8,9,14,16                100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      05/31/23                       04/08/22           
22-0477FA Reconstruction               0-007-020  01/20/23     DONE    DONE       DONE      09/14/22   08/24/22   04/11/22   11/03/21   9,155,16               1,066,513             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/24/22           
22-0479   Reconstruction               0-007-021  01/20/23     DONE    DONE       DONE      09/14/22   08/24/22   04/11/22   12/14/21   2,4,8,9,155,15,16      5,060,401     5,060,401  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         08/24/22           

          Transportation Facility:
  -       New Construction             5-015-001                                              /  /       /  /     04/24/24     /  /     02 - 16                        0             0  MSK             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED