Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/19/24 at 06:55:11




PISECO COMMON SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-01-01-08
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Piseco Elementary:
20-1515   Reconstruction               0-001-012  06/23/21     DONE    DONE       DONE      03/31/21   03/12/21   01/23/19   06/09/20   13                       199,675             0  JLB             0           0           0 Bernier Carr Associates                 0        /  /                         03/12/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




INDIAN LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-04-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Indian Lake Central:
19-1914   Reconstruction               0-001-020  08/31/20     DONE    DONE       DONE      06/30/20   06/22/20   02/10/20   12/10/19   2,7,8,9                2,021,250     2,021,250  JSS             0           0           0 Mosaic Associates                       0      11/01/22                       06/22/20           
22-0379   Reconstruction               0-001-021  02/07/23     DONE    DONE       DONE      08/31/22   08/30/22   06/16/22   05/17/22   2,9,155                1,195,000     1,195,000  WLC             0           0           0 Mosaic Associates                       0        /  /                         08/30/22           

          Storage Shed:
19-0557DB Discovered Building          2-007-001  06/29/20     DONE    DONE       DONE      10/15/19   10/15/19   09/19/19     /  /                                    0             0  JSS             0           0           0                                         0        /  /                         10/15/19           

          2021 Tent:
  -    TQ Temporary Quarters           8-008-001                                              /  /       /  /     05/20/21     /  /                                    0             0  JSS             0           0           0                                         0        /  /                           /  /             

          Bus Storage (Leased):
23-1128TQ Temporary Quarters           8-009-001                         UNREVIEWED         12/05/23   11/28/23   11/07/23     /  /                                    0             0  JJH             0           0           0                                         0        /  /                         11/28/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




INLET COMMON SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-05-01-08
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Inlet School:
  -       Reconstruction               0-002-003                                              /  /       /  /     10/11/23     /  /     2,8,9                          0             0  JJH             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAKE PLEASANT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-06-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lake Pleasant School Main Bldg:
21-1174   Reconstruction               0-007-003  04/14/22     DONE    DONE       DONE      01/19/22   01/19/22   05/20/21   05/18/21   2,4,7,10,14,155,15,1   3,333,546     3,333,546  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         01/19/22           
21-0360   Reconstruction               0-007-004  01/11/22     DONE    DONE       DONE      09/14/21   09/13/21   08/09/21   05/18/21   7                      1,255,710     1,255,710  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/13/21           
21-1175   Reconstruction               0-007-005  01/27/22     DONE    DONE       DONE      01/19/22   01/19/22   12/06/21   05/18/21   155,15,16                386,036       386,036  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         01/19/22           
22-2038FA Reconstruction               0-007-006  05/16/23     DONE    DONE       DONE      04/14/23   03/24/23   02/10/23   05/10/23   155                      168,731             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         03/24/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LONG LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-07-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building K-12:
19-0924   Reconstruction               0-001-023  03/26/20     DONE    DONE       DONE      12/05/19   11/20/19   06/18/19   05/21/19   2,8,9,155,15,16        3,500,000     3,500,000  JLB             0           0           0 Mosaic Associates                       0      07/15/23                       11/20/19           
21-1498   Reconstruction               0-001-024  06/16/22     DONE    DONE       DONE      03/11/22   03/11/22   12/14/21   05/21/19   8,9,16                   450,000       450,000  JLB             0           0           0 Mosaic Associates                       0      08/30/23                       03/11/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RAQUETTE LAKE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-07-02-02
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
20-1221   Reconstruction               0-001-003  02/17/21     DONE    DONE       DONE      01/29/21   01/06/21   04/23/20   04/01/20   16                       100,000             0  JLB             0           0           0 Bernier Carr Associates                 0      11/09/20                       01/06/21           
20-1425   Reconstruction               0-001-004  05/24/21     DONE    DONE       DONE      03/10/21   03/05/21   11/04/20   06/09/20   2,8,9,16                 205,390             0  JLB             0           0           0 Bernier Carr Associates                 0      04/25/23                       03/05/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WELLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 20-09-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
18-1406   Reconstruction               0-004-010  06/19/19     DONE    DONE       DONE      02/07/19   01/28/19   09/13/18   05/15/18   2,7,8,9,10,155,15,16   3,739,400     3,739,400  MTM             0           0           0 Mosaic Associates                       0      10/30/20                       01/28/19           
23-1094   Reconstruction               0-004-011                         UNREVIEWED         12/04/23   11/21/23   05/26/23   05/16/23   2,8,9,155,15,16                0             0  JJH             0           0           0 Mosaic Associates                       0        /  /                         11/21/23           

          Bus Barn:
18-1407   Reconstruction               4-002-001  06/19/19     DONE    DONE       DONE      02/07/19   01/28/19   09/13/18   05/15/18   16                        46,600        46,600  MTM             0           0           0 Mosaic Associates                       0      10/30/20                       01/28/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED